15
US Army Corps of Engineers BUILDING STRONG ® EPA Lower Passaic River Community Advisory Group Tom Shea, PMP Project Manager 12 March 2015 Passaic River Flood Risk Management Projects

Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

US Army Corps of Engineers

BUILDING STRONG®

EPA Lower Passaic River

Community Advisory Group

Tom Shea, PMPProject Manager

12 March 2015

Passaic River Flood Risk Management Projects

Page 2: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Passaic River Main Stem Project

• Studies began in 1900

• USACE became involved in 1936, 1976 study authority

required a “comprehensive” solution

• Feasibility Study completed in 1987, recommended

the “Tunnel Plan”

• Congress authorized the project in WRDA 1990

• USACE initiated Pre-Construction Engineering and

Design (PED) in 1987 and stopped in 1995 when it

completed a draft General Design Memo

2

Page 3: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Passaic River Main Stem Project

• Effort was halted in 1995 at the request of the State

of New Jersey

• Project was further restricted by Section 327(i),

WRDA 2000, which forbids the obligation of funds for

the design or construction of the tunnel element

• The Main Stem portion of the project was never

constructed, other separable elements were (Minish,

Oakland, Molly Ann's Brook)

• The authorized plan includes tidal levees/floodwalls in

Newark, Kearny and Harrison

3

Page 4: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Passaic River Flood Risk Management Projects

Tidal Passaic

RiverPassaic Main

Stem

4

Page 5: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

• Apr 2010 – Governor Christie created Passaic River

Basin Flood Advisory Commission through Executive

Order 23

• Jan 2011 – Commission recommended reevaluation

of the Passaic River Basin for long-term flood damage

reduction at a cost of $15 million

• Mar 2011 – Letter from Governor Christie to Chief of

Engineers that requested support of

• Preservation of Natural Flood Storage Areas

• Reevaluation of the Passaic River Main Stem Study

Restart of the Passaic Main Stem

5

Page 6: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

1. Levees and Floodwalls� Alternative 14A from 1987

2. Levees, Floodwalls and Channel Modification� Alternative 16A from 1987

3. Tunnel� Duel Inlet – Newark Bay Outlet Tunnel Diversion (authorized plan)

4. Beatties Dam / Two Bridges Improvements � Plan requested by NJDEP in 2011

5. Nonstructural � 10 Year Flood, 1987 plan

6. No Action

Passaic Main Stem

Alternatives in Phase 1

6

Page 7: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Passaic Main Stem

Preliminary Alternative Analysis Report

7

• Submitted to NJDEP and HQUSACE in Sep 13.

� Reaffirmed that the Tunnel Diversion plan remains the

National Economic Development Plan and the non-structural

and levee/floodwall plans were marginally economically

justified.

• In Feb 2014, NJDEP requested that the District pursue the

following three alternatives:

1) Nonstructural alternative,

2) Alternative 14A (levee and floodwall), and

3) Tunnel Diversion Plan

• Public Information Sessions were held late March/early April

2014 to discuss the status of the study and describe the three

alternatives above

Page 8: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Passaic Main Stem Path Forward

Preliminary Benefit-to-Cost Ratios Feb 2016

Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016

Conduct Pre-TSP Briefing to HQUSACE Sep 2016

Phase 1 Complete Nov 2016

8

Page 9: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Passaic River Flood Risk Management Projects

Tidal Passaic

RiverPassaic Main Stem

9

Page 10: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Passaic River Tidal Protection Area

• An original component of the overall Passaic River Main Stem

• Broken out as a separate study in USACE Second Interim Report

to Congress, in accordance with PL 113-2 (Sandy Recovery)

• GRR fully funded by Sandy Recovery, although cost-shared

(non-Fed is financed by Fed)

• 3 year and $3M evaluation phase to update costs and

alignment and complete consideration of impacts to the

environment.

• Estimated construction cost is $300M, to be funded by Sandy

Recovery to the extend that funds remain, then go to annual

appropriations

10

Page 11: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Passaic River Tidal Protection Area

• Damages caused by the tidal surge flooding

• Severe flooding in all three communities – Harrison, Kearny

and Newark

• Storm surge affected highly developed industrial, commercial,

and residential areas.

• Passaic Valley Sewerage Commission Plant – overflow, flooded,

months to reopen

• PATH, AMTRAK, & NJ Transit – Flooded; FEMA dewatering

mission

• Numerous electrical substations flooded

• Damage to property was sustained; one death reported

11

Page 12: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®12

Page 13: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Light Shade Blue is FEMA 100 yr flood zone

Red lines are Authorized Project levees and

floodwalls

Passaic River Tidal Protection Area

Minish Waterfront Project

13

Page 14: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Milestone Dates

Draft GRR 20-Apr-16

Chief’s Report 05-Jul-17

Report to Congress 26-Sep-17

Schedule for Passaic Tidal Protection Area

General Reevaluation Report

14

Page 15: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Contacts

• USACE Project Manager:

Tom Shea, PMP

(917) 790-8304

[email protected]

or

[email protected]

Preliminary Alternatives Analysis Report can be found at:

www.nan.usace.army.mil/passaic

15