Upload
paramjit-sharma
View
3.016
Download
12
Embed Size (px)
DESCRIPTION
ppt on OH Absorption questions
Citation preview
Overhead absorption
QUESTIONS-ANSWERS
Methods Of Overhead Absorption
Machine Hour Rate
Hourly Rates
OHAR=POHEs for the periodNo.Of Machine Hours
Most Popular Method
Can be fixed for a Machine or Group Of Machines
Computing Machine Hour RateComputing Machine Hour Rate
Cost of
PowerSteamOilRepairsMaintenanceDepreciation
Cost OfRent & RatesLighting &HeatingSupervisionInsuranceCotton WasteIndirect LabourConsumable StoresLubricants
Machine Running ExpensesOr
Variable Expenses
Standing ExpensesOr
Fixed Expenses
Methods Of Overhead Absorption
Machine Hour Rate
Hourly Rates
Common Costs to be apportioned
Both Fixed/variable costs be divided by Machine Hrs
Machine Hr represents Cost of Operating Machine for One Hour
Time spent on cleaning, warming may be excluded from Machine hours
Time spent on Normal Setting Up may be included
Cost of reserve machine ( Motor ) may be considered
Methods Of Overhead Absorption
Machine Hour Rate
Hourly Rates
Common Costs to be apportioned
Uniform Period Basis For Apportionment
Variable Cost Calculation
Depreciation
Maintenance
1. Calculate the machine hour rate from the following data:
Cost of machine Rs 19,200
Scrap value Rs 1,200
Repairs and maintenance per month Rs 150
Standing charges per month Rs 50
Effective working life 10,000 hours
Running time per month 200 hours
Power used 5 units at 18 paise per unit per hour.
1. Computation of Machine Hour Rate
Particulars Per Hour (Rs)
50 Standing charges -------- 200
Variable charges : 19,200 - 1,200Depreciation --------------------- 10,000
150Repairs and maintenance ------- 200
Power : 5 units per hour @ 18 paise
0.25
1.80
0.75
0.90
Machine Hour Rate 3.70
2) From the following particulars, calculate the machine hour rate for machine X:
Cost of the machine Rs 42,000
Estimate scrap value 2,000Estimated working life: 1O years of 2000 hours per yearRunning rime for a four week period: 150 hoursEstimated repairs for life Rs 10,000Standing charges allocated to this machine per week Rs 300Power consumed per hour: 5 units @ 10 paise per unit
Particulars Per Hour (Rs.)
300 x 4Standing charges ------------- 150
Variable charges : 42,000 – 2,0000Depreciation -------------------- 10 x 2,000
10,000Repairs -------------------- 10 x 2,000
Power consumed : 5 units per hour @ 10 paise
8.00
2.00
0.50
0.50
Machine Hour Rate 11.00
2. Computation of Machine Hour Rate
3. Work out the machine hour rate for the following machine:
Cost of machine Rs 90,000
Freight and installation charges Rs 10,000
Working life 10 years
Working hours 2,000 per year
Repair charges 50%of depreciation
Power 10 units per hour @ 10 paise per unit
Lubricating oil @ Rs 2 per day of 8 hours
Consumable stores @ Rs 10 per day of 8 hours
Wages of operator @ Rs 4 per day
Particulars Per hour (Rs.)
Standing charges :
Lubrication oil Rs.2 per day
Consumable stores Rs.10 per day
Wages of operator Rs. 4 per day
____________________Total Rs.16 per day of 8 hrs. ___________________
Standing charges per hour (16 ÷ 8)
90,000 + 10,000Depreciation ----------------------- 10 x 2,000
Repairs charges : 50% of depreciation
Power : 10 units @ 10 paise per unit
2.00
5.00
2.50
1.00
Machine Hour Rate 10.50
3. Computation of Machine Hour Rate
4. A machine costing Rs 10,000 is expected to run for 10 years at the end of which period its scrap value is likely to be Rs 900. Repairs, during the whole life of the machine are expected to be Rs 1,800 and the machine is expected to run 4,380 hours per year on the average. Its electricity consumption is 15 units per hour, the rate per unit being 5 paise. The machine occupies one fourth of the area of the department and has two points out of a total of ten for lighting. The foreman has to devote about one-third of his time to the machine. The monthly rent of the department is Rs 300 and the lighting charges amount to Rs 80 per month. The foreman is paid a monthly salary of Rs 480. Ascertain the machine hour rate
4. Computation of Machine Hour Rate
Particulars
Per annum (Rs.)
Per hour (Rs.)
Standing charges :
Rent (300 x 1 x 12) 4Lighting (80 x 2 x 12) 10Foreman’s salary (480 x 1 x 12) 3Total Standing charges
Standing charges per hour (3,012 ÷ 4,380)
Variable charges : 10,000 – 900Depreciation ------------------- 10 x 4,380 1,800Repairs ----------------- 10 x 4,380
Power : 15 units per hour @ 5 paise per unit
900
192
1920
__________
3012
--------------
0.69
0.21
0.04
0.75
Machine hour rate 1.69
5. Compute the machine hour rate from the following data:
Cost of the machine Rs 1,00,000
Installation charges Rs 10,000
Scrap value after its life (15 years) Rs 5,000
Rent and rates for the shop per month Rs 200
General lighting for the shop per month Rs 300
Insurance premium for the shop per annum Rs 960
Repairs and maintenance expenses per annum Rs 1,000
Power consumption 10 units per hour,
rate of power for 100 units Rs. 20
Estimated working hours per annum 2,200 hrs
(this includes setting up time of 200 hours)
Shop supervisor's salary per month Rs 600
The machine occupies 1/4th of the total area of the shop. The supervisor is expected to devote 1/5th of his time for supervising this machine.
Particulars Per annum (Rs.)
Per hour (Rs.)
Standing charges :Rent and rates for the shop 200 x 1 x 12 4General Lighting 300 x 1 x 12 4
InsuranceSupervisor’s salary 600 x 1 x 12 5
Total Standing charges
Standing charges per hour (3,900 ÷ 2,000)
Variable charges : 1,00,000 + 10,000 – 5,000Depreciation -------------------------------- 15 x 2,000 1,000Repairs and maintenance ---------- 2,000
Power consumption : 10 units per hour @ Rs.20 per 100 units
600
900
960
1,440
_________3,900--------------
1.95
3.50
0.50
2.00
Machine Hour Rate 7.95
5. Computation of Machine Hour Rate
6. Calculate the machine hour rate from the following particulars:
Rs
Cost of the machine 95,000
Installation charges 10,000
Estimated value of scrap at the end of the life (10 years) 5,000
Estimated working hours per annum 2,200 Hrs.
Rent and Rates for the shop per month 250
Supervisor's salary per month 700
General lighting for the shop per month 300
Rate of power per 100 units 50
Power consumption 10 units per hour. The machine occupies 1/4th of the total area of the shop. The supervisor is spending 1/5th of his time for this particular machine.
6. Computation of Machine Hour Rate
Particulars Per annum (Rs.)
Per Hour (Rs.)
Standing charges
Rent 250 x 12 x 1 4
Supervisor’s Salary 700 x 12 x 1 5
General lighting 300 x 12 x 1 4Total standing charges
Standing charges per hour (3,330 ÷ 2,200)Variable charges :
Depreciation 1,00,000 + 10,000 – 5,000 10 x 2,200
Power : 10 x 50 100
750
1,680
900---------3,300---------
1.51
4.77
5.00
Machine Hour Rate
11.28
7. A machine costs Rs 90,000 and deemed to have a scrap value of 5% of purchase price at the end of its life of 19 years. The machine works for 1,500 hours per annum. The other details of the machine are:
Rs
a) Wages of operator (the operator is in-charge
of two machines) 6,000 per year
b) Rent and rates of the shop (shop houses 4 machines 3,000 per year
c) Lighting of the shop 250 per month
d) Insurance on the machine 200 per quarter
e) Cost of repairs and maintenance 250 per month
f) Shop supervisor's salary 500 per month
g) Power consumption of machine: 20 units per hour at
the rate of Rs 10 per 100 units
h) Factory overhead for the shop Rs 4,000 per year
Compute the machine hour rate.
7. Computation of Machine Hour Rate
Particulars Per annum (Rs.)
Per Hour (Rs.)
Standing charges
Rent and Rates ( 3000 ÷ 4 )
Wages of operator ( Rs. 6,000 ÷ 2)Lighting ( 250 x 12 ) 4Insurance : ( 200 x 12 ) 3 x 4
Supervisor’s salary : ( Rs. 6,000 ÷ 4 )
Factory overhead : (Rs. 4,000 ÷ 4 )
Total Standing charges
Standing charges per hour (7,200 ÷ 1,500 )
Variable charges 90,000 - 4,500Depreciation -------------------------- 19 x 1,500
Repairs & maintenance Rs.250 x 12 1,500
Power consumption : 20 x 10 100
750
3,000
750
200
1,500
1,000-----------7,200-----------
4.80
3.00
2.00
2.00
Machine Hour Rate 11.80
8. Calculate the machine hour rate for the month of January to cover the overhead expenses, given below, relating to a machine.
Rs
1. Rent of the Department 780 p.a.
(1/5th area is occupied by the machine)
2. Lighting (out of 12 points, 2 are for this machine) 288 p.a.
3. Insurance 36 p.a.
4. Cotton, wastes etc. 60 p.a.
5. Foreman's salary (1/4th for the machine) 6,000 p.a.
6. Cost of machine 9,200
7. Scrap 200
It is assumed that machine will work for 1,800 hours p.a. and that will incur Rs 1,125 for repairs and maintenance for life. It is further assumed that 5 units of power would be used per hour available at 6 paise per unit, and that the life of machine will be of 10 years.
8. Computation of Machine Hour Rate
Particulars Per annum (Rs)
Per Hour (Rs.)
Standing charges :
Rent ( 780 x 1/5)
Lighting ( 288 x 2/12)
Foreman’s salary (6,000 x ¼)
Insurance
Cotton waste etc.
Total standing charges
Standing charges per hour (1,800 ÷ 1,800 )
Variable charges : 90,000 - 200Depreciation ---------------------- 10 x 1,900
Repairs ( 1,125 ÷ 1,800 x 10 )
Power 5 units @ 6 paise per unit
156.00
48.00
1,500.00
36.00
60.00
------------
1,800.00
1.00
0.50
0.06
0.30
Machine Hour Rate 1.86
9. The following information is given:
1. The original cost. of the machine used (purchased in June 1998) was Rs 10,000. Its estimated life is 10 years, the estimated scrap value at the end of its life is Rs 1,000 and the estimated working time per year (50 weeks of 44 hours) is 2,200 hours of which machine maintenance, etc. is estimated to take up 200 hours.
2. Setting up time of 100 hours is estimated
3. Electricity used by the machine during production is 16 units per hour at a cost of 20 paise per unit. No current is taken during maintenance or setting up.
4. The machine requires a chemical solution which is replaced at the end of each week at a cost of Rs 20 each time.
5. The estimated cost of maintenance per year is Rs 1,200
6. Two attendants control the operation of the machine together with five other identical machines. Their combined weekly wages, insurance, and the employer's contributions to holidays pay amount to Rs 120.
7. Departmental and general works overheads allocated to this machine for the year 1998 amount to Rs 2,000.
Calculate machine hour rate when
(a) Setting up time is unproductive
(b) Setting up-time is productive
9. Computation of Machine Hour
a) When setting up time is unproductive
Effective working hours are computed as shown below :
Annual working hours (50 x 44) 2200 hrs
Less - Maintenance time 200 hrs
---------------
2000 hrs
Less - set up time 100 hrs.
---------------
Effective working hours 1900 hrs
---------------
9.a Computation of Machine Hour
Particulars Per Hour (Rs.)
Standing charges 120 x 50(a) Wages of attendants ---------------------- 6 x 1,900
(b) Departmental and general works overheads (2,000 ÷ 1,900)
Standing charges per hour Total
Variable charges 10,000 - 1,000(a) Depreciation ----------------------- 10 x 1,900 20 x 50(b) Chemical Solution ---------------- 1,900
(c) Electricity ( 16 x 20 paise)(d) Maintenance ( 1,200 + 1,900)
0.53
1.05---------1.58--------
0.47
0.53
3.200.63
Machine Hour Rate 6.41
9. (b) When setting up time is productive
Annual working hours 2,200
Less : Maintenance time 200
---------------------
Effective working hours 2,000
--------------------
Particulars Per Hour (Rs.)
Standing charges : 120 x 50(a) Wages of attendants ------------------- 1,000.00 6
(b) Departmental and general work overheads 2,000.00
Standing charges per hour 3000 divided by 2000
Variable charges : 10,000 – 1,000(a) Depreciation ----------------------- 10 x 2,000
20 x 50(b) Chemical Solution -------------- 2,000
1,900 x 16 x 0.20(c) Electricity -------------------------- 2,000
(d) Maintenance (1,200 ÷ 2,000)
0.50
1.00
-----------
1.50
0.45
0.50
3.04
0.60
Machine Hour Rate 6.09
9.b Computation of Machine Hour Rate
10. The following particulars relate to a new machine
Rs.
Purchase price 4,00,000
Installation expenses 1,00,000
Rent per quarter 3,750
General lighting for the total area 1,000 per month
Foreman’s salary 30,000 per annum
Insurance premium for the machine 3,000 per annum
Estimated repairs for the machine 5,000 per annum
Consumable Stores 4,000 per annum
Power consumed 2 units per hour at Rs.50 per 100 units. The estimated life of the machine is 10 years and scrap value at the end of 10th year is Rs.1,00,000. The machine is expected to run 20,000 hours in its lifetime. The machine occupies 25% of total area. The foreman devotes 1/6th of his time for the machine. Calculate machine hour rate for the machine.
10. Calculation of Machine Hour Rate
Particulars Per annum (Rs.)
Per Hour (Rs.)
Standing Charges
3,750 x 4Rent ----------------- 4 1,000 x 12Lighting --------------------- 4 30,000Foreman’s Salary ------------- 6InsuranceStores
Total Standing Charges
Standing charges per hour (18,000 ÷ 2,000)
Variable charges : 4,00,000 + 1,00,000 - 1,00,000Depreciation -------------------------------------------- 10 x 2,000 5,000Repairs ---------- 2,000 2 x 50Power ------------------------ 100
3,750
3,000
5,000
3,000
4,000
--------
18,750
--------
9.375
20.000
2.500
1.000
Machine Hour Rate 32.875
11. From the following particulars, compute Machine Hour Rate :
Rs.
Cost of Machine 1,14,800
Installation charges 5,400
Anticipated life of machine 10 years
Residual value at the end of 10 years 5,000
Rent and rates per annum 12,000
Insurance of the machine p.a. 3,000
Repairs and maintenance p.a. 8,640
Consumable stores p.a. 1,200
Total production services p.a. 1,080
Power cost is 5 units per working hour @ 40 paise per unit
Setting up time
(non-productive) 400 hrs. p.a.
There are 300 working days of eight hours in a year.
11. Computation of Machine Hour Rate
Particulars Per annum (Rs.)
Per Hour (Rs.)
Standing charges
Rent and Rates
Insurance
Consumable Stores
Production Services
Total standing charges
Standing charges per hour (1`7,280 ÷ 2,000)
Variable charges :
1,14,800 + 5,400 - 5,000
Depreciation -----------------------------------
10
Power ( 300 x 8 x 5 x 0.40)
Repairs and maintenance
12,000
3,000
1,200
1,080
--------------
17,280
-------------
11,520
4,800
8,640
8.64
Total 24,960 12,48
Machine Hour Rate 21.12
12. From the following information, compute machine hour rate
Cost of the machine Rs. 3,00,000
Expenses on installation and freight charges Rs. 25,000
Estimated scrap value at the end Rs. 25,000
Insurance premium Rs. 480 p.a.
Standing charges allocated to the machine Rs. 480 p.m.
Effective working life of the machine 24,000 hours
Hours worked during the month 240 hours
Repairs during the effective life of the machine Rs. 24,000
Power consumed by the machine is 20 units per hour at a cost of 25 paise per unit. Additional charges at 5 paise per unit are payable on the total units consumed if the same exceeds the basic consumption of 2000 units per month.
12. Computation of Machine Hour Rate
Particulars Per annum (Rs.)
Per hour (Rs.)
Standing charges
Standing charges 480 x12
Insurance
Total standing charges
Standing charges per hour (6260 ÷ 2880)
Variable charges : 3,00000 + 25,000 - 25,000Depreciation ------------------------------------ 2,4000 hours
Repairs ( 24,000 ÷ 24.000 )
Power ( 0.30 x 20 )
5760
480
6260 2.17
12.50
1.00
6.00
Machine Hour Rate 21.67
13. Compute machine hour rate from the following data :
Cost of the machine Rs. 1,44,000
Installation charges Rs. 6,000
Estimated scrap value at the end Rs. 6,000
Effective working life of the machine 12,000 hours
Estimated repairs over the effective
working life of the machine Rs. 12,000
Standing charges allocated to the machine
per year Rs. 5,760
Power bill per year Rs. 7,200
Power consumed by the machine is 20 units per hour at a cost of 25 paise
per unit.
13. Computation of Machine Hour Rate No. of machine hours : 1440*
Particulars Per annum (Rs.)
Per Hour (Rs.)
Standing charges
(i) Standing charges allocated to the machine
Total standing charges
Standing charges per hour
Variable charges
1,44,000 + 6,000 - 6,000
(i) Depreciation -----------------------------------
12,000
12,000
(ii) Repairs -----------
12,000
(iii) Power (20 units x 25 P)
5,760
------------
5,760
-----------
4.00
12.00
1.00
5.00
Machine Hour Rate 22.00
Computation of Machine Hours :
•Power bill per year = Rs.7,200 Power bill per hour = 20 units x 25 p. = Rs.5
Therefore No.of machine hours per annum = 7,200/5 = 1,440 hours