Upload
calvin-cooper
View
224
Download
0
Tags:
Embed Size (px)
Citation preview
OPERATIONS MANAGEMENTOPERATIONS MANAGEMENTfor MBAs for MBAs Fourth EditionFourth Edition
Chapter 6: Managing Process Improvement Projects 1
Meredith and Shafer
John Wiley and Sons, Inc.
Prepared by: Al AnsariSeattle University
Chapter 6:Chapter 6:
Chapter 6: Managing Process Improvement Projects 2
Managing Process Improvement Projects
BackgroundBackground
Project management concerned with managing organizational activities.
Often used to integrate and coordinate diverse activities.
Projects are special types of processes.
Chapter 6: Managing Process Improvement Projects 4
Defining a ProjectDefining a Project
Projects are processes that are performed infrequently and ad hoc, with a clear specification of the desired objective.
Chapter 6: Managing Process Improvement Projects 5
Examples of ProjectsExamples of Projects
Constructing highways, bridges, tunnels and dams
Erecting skyscrapers, steel mills, and homes
Organizing conferences and conventions
Managing R&D projectsRunning political
campaigns, war operations, and advertising campaigns
Chapter 6: Managing Process Improvement Projects 6
Reasons for Growth in Reasons for Growth in Project OperationsProject OperationsMore Sophisticated
TechnologyBetter-Educated
CitizensMore Leisure Time Increased
AccountabilityHigher ProductivityFaster Response to
CustomersGreater customization
for customers
Chapter 6: Managing Process Improvement Projects 7
The Project PortfolioThe Project Portfolio
Chapter 6: Managing Process Improvement Projects 9
The project portfolio also known as the aggregate project plan is to achieve the organization’s goals
Four Categories of Four Categories of ProjectProject
Chapter 6: Managing Process Improvement Projects 10
1. Derivative projects. Seek to make incremental improvements in the output and/or process.
2. Breakthrough projects. Are at the opposite end of the continuum from derivative projects and seek the development of a new generation of outputs.
3. Platform projects. Fall between derivative and breakthrough projects.
4. R&D projects. Entail working with basic technology to develop new knowledge.
An Example of Aggregate An Example of Aggregate Project PlanProject Plan
Chapter 6: Managing Process Improvement Projects 12
Life Cycle of a Project Life Cycle of a Project (Stretched-S) (Stretched-S) & (Exponential)& (Exponential)
Chapter 6: Managing Process Improvement Projects 13
Organizing the Project Organizing the Project TeamTeam
Ad Hoc Project FormWeak Functional MatrixStrong Project Matrix
Chapter 6: Managing Process Improvement Projects 14
Types of Project Team Types of Project Team MembersMembers
Those having a long-term relationship with the project.
Those that the PM will need to communicate with closely.
Those with rare skills necessary to project success.
Chapter 6: Managing Process Improvement Projects 15
Elements of Project Elements of Project Charter Charter Overview A short summary of what the client expects from the project.
Goals, or Scope Contains a more detailed statement of the general goals
Business Case Describes the justification for the project
General Approach Describes both the managerial and the technical approaches
Chapter 6: Managing Process Improvement Projects 17
Elements of Project Elements of Project Charter Charter Cont.Cont.
Contractual Aspects This includes a complete list and description of allreporting requirements, customer-supplied resources, liaison arrangements, etc.,
Schedule and Milestones This outlines the schedule and lists milestone events.
Chapter 6: Managing Process Improvement Projects 18
Elements of Project Elements of Project Charter Charter Cont.Cont.
Resources -- The project budget and cost
PersonnelRisk Management Plan This covers
potential problems that could affect the project.
Evaluation Method Every project should be evaluated against standards
Chapter 6: Managing Process Improvement Projects 19
Three Project ObjectivesThree Project Objectives
Chapter 6: Managing Process Improvement Projects 20
Work Breakdown Work Breakdown StructureStructure
Chapter 6: Managing Process Improvement Projects 21
Complexity of Scheduling Complexity of Scheduling Project ActivitiesProject Activities
Large number of activities
Precedence relationships
Limited time of the project
Chapter 6: Managing Process Improvement Projects 23
Planning and Scheduling Planning and Scheduling ProjectsProjectsPlanning. Determining what must
be done and which tasks must precede others.
Scheduling. Determining when the tasks must be completed; when they can and when they must be started; which tasks are critical to the timely completion of the project; and which tasks have slack and how much.
Chapter 6: Managing Process Improvement Projects 24
TerminologyTerminologyActivityEventNetworkPathCritical PathCritical Activities
Chapter 6: Managing Process Improvement Projects 26
Project Scheduling with Certain Project Scheduling with Certain Activity Times: A Process Activity Times: A Process ImprovementImprovementInputs
◦list of the activities that must be completed
◦activity completion times◦activity precedence relationships
Chapter 6: Managing Process Improvement Projects 27
Project Scheduling with Certain Project Scheduling with Certain Activity Times: A Process Activity Times: A Process improvementimprovementOutputs
◦graphical representation of project◦time to complete project◦identification of critical path(s) and
activities◦activity and path slack◦earliest and latest time each
activity can be started ◦earliest and latest time each
activity can be completed
Chapter 6: Managing Process Improvement Projects 28
Activity Slack TimeActivity Slack TimeTES = earliest start time for activity
TLS = latest start time for activity
TEF = earliest finish time for activity
TLF = latest finish time for activity
Activity Slack = TLS - TES = TLF - TEF
Chapter 6: Managing Process Improvement Projects 31
Path SlackPath Slack
Path Slack = Duration of Critical Path - Path Duration
Chapter 6: Managing Process Improvement Projects 32
Project Scheduling with Project Scheduling with Uncertain Activity Times Uncertain Activity Times
Inputs◦Optimistic (to), most likely (tm), and
pessimistic (tp) time estimate for each activity
◦activity precedence relationshipsOutputs
◦graphical representation of project◦expected activity and path completion times◦variance of activity and path completion
times◦probability that project completed by
specified time
Chapter 6: Managing Process Improvement Projects 33
Expected Activity Time and Expected Activity Time and Variance of Activity TimeVariance of Activity Time
Chapter 6: Managing Process Improvement Projects 34
tt t t
t t
eo m p
p o
4
6
62
2
Probabilities of Probabilities of CompletionCompletion
Chapter 6: Managing Process Improvement Projects 36
V
timecompletion expected - timecompletion desiredz
Probability of Project Being Probability of Project Being Completed on or Before Time 23Completed on or Before Time 23
Chapter 6: Managing Process Improvement Projects 37
Only path A-D-J has reasonable chance of taking 21 or more:
From standard normal table in Appendix A, there is a 79 % chance of completing project on or before time 23.
Z = 23 -21/2.449 = 0.818
Probability of Path A-D-J being Probability of Path A-D-J being Completed on or Before Time 23Completed on or Before Time 23
Chapter 6: Managing Process Improvement Projects 38
Simulating Project Completion Simulating Project Completion TimesTimes
Chapter 6: Managing Process Improvement Projects 39
Simulating Project Completion Simulating Project Completion TimesTimes
Chapter 6: Managing Process Improvement Projects 40
Project Management Project Management Software CapabilitiesSoftware Capabilities
Chapter 6: Managing Process Improvement Projects 42
Microsoft Project’s Gantt Microsoft Project’s Gantt ChartChart
Chapter 6: Managing Process Improvement Projects 43
PERT Chart Generated by PERT Chart Generated by Microsoft ProjectMicrosoft Project
Chapter 6: Managing Process Improvement Projects
44
Calendar of Activities Calendar of Activities Created by Microsoft Created by Microsoft ProjectProject
Chapter 6: Managing Process Improvement Projects 45
Project and Feeder Project and Feeder BuffersBuffers
Chapter 6: Managing Process Improvement Projects 46
Controlling the Project: Controlling the Project: Earned ValueEarned Value
Chapter 6: Managing Process Improvement Projects 47
Variance ReportVariance ReportCost standard determined using
engineering estimates or analysis of past performance
Actual cost monitored and compared with cost standard
Project manager can exert control if difference between standard and actual (called a variance) is considered significant.
Chapter 6: Managing Process Improvement Projects 48
Cost-Schedule Reconciliation Cost-Schedule Reconciliation ChartsCharts
Chapter 6: Managing Process Improvement Projects 49
CopyrightCopyrightCopyright John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that named in Section 117 of the United States Copyright Act without the express written consent of the copyright owner is unlawful. Requests for further information should be addressed to the Permissions Department, John Wiley & Sons, Inc. Adopters of the textbook are granted permission to make back-up copies for their own use only, to make copies for distribution to students of the course the textbook is used in, and to modify this material to best suit their instructional needs. Under no circumstances can copies be made for resale. The Publisher assumes no responsibility for errors, omissions, or damages, caused by the use of these programs or from the use of the information contained herein.
Chapter 6: Managing Process Improvement Projects 51