51
OPERATIONS MANAGEMENT OPERATIONS MANAGEMENT for MBAs for MBAs Fourth Edition Fourth Edition Chapter 6: Managing Process Improvement Projects 1 Meredith and Shafer John Wiley and Sons, Inc. Prepared by: Al Ansari Seattle University

OPERATIONS MANAGEMENT for MBAs Fourth Edition Chapter 6: Managing Process Improvement Projects 1 Meredith and Shafer John Wiley and Sons, Inc. Prepared

Embed Size (px)

Citation preview

OPERATIONS MANAGEMENTOPERATIONS MANAGEMENTfor MBAs for MBAs Fourth EditionFourth Edition

Chapter 6: Managing Process Improvement Projects 1

Meredith and Shafer

John Wiley and Sons, Inc.

Prepared by: Al AnsariSeattle University

Chapter 6:Chapter 6:

Chapter 6: Managing Process Improvement Projects 2

Managing Process Improvement Projects

IntroductionIntroduction

Chapter 6: Managing Process Improvement Projects 3

BackgroundBackground

Project management concerned with managing organizational activities.

Often used to integrate and coordinate diverse activities.

Projects are special types of processes.

Chapter 6: Managing Process Improvement Projects 4

Defining a ProjectDefining a Project

Projects are processes that are performed infrequently and ad hoc, with a clear specification of the desired objective.

Chapter 6: Managing Process Improvement Projects 5

Examples of ProjectsExamples of Projects

Constructing highways, bridges, tunnels and dams

Erecting skyscrapers, steel mills, and homes

Organizing conferences and conventions

Managing R&D projectsRunning political

campaigns, war operations, and advertising campaigns

Chapter 6: Managing Process Improvement Projects 6

Reasons for Growth in Reasons for Growth in Project OperationsProject OperationsMore Sophisticated

TechnologyBetter-Educated

CitizensMore Leisure Time Increased

AccountabilityHigher ProductivityFaster Response to

CustomersGreater customization

for customers

Chapter 6: Managing Process Improvement Projects 7

Planning the ProjectPlanning the Project

Chapter 6: Managing Process Improvement Projects 8

The Project PortfolioThe Project Portfolio

Chapter 6: Managing Process Improvement Projects 9

The project portfolio also known as the aggregate project plan is to achieve the organization’s goals

Four Categories of Four Categories of ProjectProject

Chapter 6: Managing Process Improvement Projects 10

1. Derivative projects. Seek to make incremental improvements in the output and/or process.

2. Breakthrough projects. Are at the opposite end of the continuum from derivative projects and seek the development of a new generation of outputs.

3. Platform projects. Fall between derivative and breakthrough projects.

4. R&D projects. Entail working with basic technology to develop new knowledge.

Aggregate Project PlanAggregate Project Plan

Chapter 6: Managing Process Improvement Projects 11

An Example of Aggregate An Example of Aggregate Project PlanProject Plan

Chapter 6: Managing Process Improvement Projects 12

Life Cycle of a Project Life Cycle of a Project (Stretched-S) (Stretched-S) & (Exponential)& (Exponential)

Chapter 6: Managing Process Improvement Projects 13

Organizing the Project Organizing the Project TeamTeam

Ad Hoc Project FormWeak Functional MatrixStrong Project Matrix

Chapter 6: Managing Process Improvement Projects 14

Types of Project Team Types of Project Team MembersMembers

Those having a long-term relationship with the project.

Those that the PM will need to communicate with closely.

Those with rare skills necessary to project success.

Chapter 6: Managing Process Improvement Projects 15

Project PlansProject Plans

Chapter 6: Managing Process Improvement Projects 16

Elements of Project Elements of Project Charter Charter Overview A short summary of what the client expects from the project.

Goals, or Scope Contains a more detailed statement of the general goals

Business Case Describes the justification for the project

General Approach Describes both the managerial and the technical approaches

Chapter 6: Managing Process Improvement Projects 17

Elements of Project Elements of Project Charter Charter Cont.Cont.

Contractual Aspects This includes a complete list and description of allreporting requirements, customer-supplied resources, liaison arrangements, etc.,

Schedule and Milestones This outlines the schedule and lists milestone events.

Chapter 6: Managing Process Improvement Projects 18

Elements of Project Elements of Project Charter Charter Cont.Cont.

Resources -- The project budget and cost

PersonnelRisk Management Plan This covers

potential problems that could affect the project.

Evaluation Method Every project should be evaluated against standards

Chapter 6: Managing Process Improvement Projects 19

Three Project ObjectivesThree Project Objectives

Chapter 6: Managing Process Improvement Projects 20

Work Breakdown Work Breakdown StructureStructure

Chapter 6: Managing Process Improvement Projects 21

Project Master ScheduleProject Master Schedule

Chapter 6: Managing Process Improvement Projects 22

Complexity of Scheduling Complexity of Scheduling Project ActivitiesProject Activities

Large number of activities

Precedence relationships

Limited time of the project

Chapter 6: Managing Process Improvement Projects 23

Planning and Scheduling Planning and Scheduling ProjectsProjectsPlanning. Determining what must

be done and which tasks must precede others.

Scheduling. Determining when the tasks must be completed; when they can and when they must be started; which tasks are critical to the timely completion of the project; and which tasks have slack and how much.

Chapter 6: Managing Process Improvement Projects 24

Scheduling the ProjectScheduling the Project

Chapter 6: Managing Process Improvement Projects 25

TerminologyTerminologyActivityEventNetworkPathCritical PathCritical Activities

Chapter 6: Managing Process Improvement Projects 26

Project Scheduling with Certain Project Scheduling with Certain Activity Times: A Process Activity Times: A Process ImprovementImprovementInputs

◦list of the activities that must be completed

◦activity completion times◦activity precedence relationships

Chapter 6: Managing Process Improvement Projects 27

Project Scheduling with Certain Project Scheduling with Certain Activity Times: A Process Activity Times: A Process improvementimprovementOutputs

◦graphical representation of project◦time to complete project◦identification of critical path(s) and

activities◦activity and path slack◦earliest and latest time each

activity can be started ◦earliest and latest time each

activity can be completed

Chapter 6: Managing Process Improvement Projects 28

ExampleExample

Chapter 6: Managing Process Improvement Projects 29

Network DiagramNetwork Diagram

Chapter 6: Managing Process Improvement Projects 30

Activity Slack TimeActivity Slack TimeTES = earliest start time for activity

TLS = latest start time for activity

TEF = earliest finish time for activity

TLF = latest finish time for activity

Activity Slack = TLS - TES = TLF - TEF

Chapter 6: Managing Process Improvement Projects 31

Path SlackPath Slack

Path Slack = Duration of Critical Path - Path Duration

Chapter 6: Managing Process Improvement Projects 32

Project Scheduling with Project Scheduling with Uncertain Activity Times Uncertain Activity Times

Inputs◦Optimistic (to), most likely (tm), and

pessimistic (tp) time estimate for each activity

◦activity precedence relationshipsOutputs

◦graphical representation of project◦expected activity and path completion times◦variance of activity and path completion

times◦probability that project completed by

specified time

Chapter 6: Managing Process Improvement Projects 33

Expected Activity Time and Expected Activity Time and Variance of Activity TimeVariance of Activity Time

Chapter 6: Managing Process Improvement Projects 34

tt t t

t t

eo m p

p o

4

6

62

2

ExampleExample

Chapter 6: Managing Process Improvement Projects 35

Probabilities of Probabilities of CompletionCompletion

Chapter 6: Managing Process Improvement Projects 36

V

timecompletion expected - timecompletion desiredz

Probability of Project Being Probability of Project Being Completed on or Before Time 23Completed on or Before Time 23

Chapter 6: Managing Process Improvement Projects 37

Only path A-D-J has reasonable chance of taking 21 or more:

From standard normal table in Appendix A, there is a 79 % chance of completing project on or before time 23.

Z = 23 -21/2.449 = 0.818

Probability of Path A-D-J being Probability of Path A-D-J being Completed on or Before Time 23Completed on or Before Time 23

Chapter 6: Managing Process Improvement Projects 38

Simulating Project Completion Simulating Project Completion TimesTimes

Chapter 6: Managing Process Improvement Projects 39

Simulating Project Completion Simulating Project Completion TimesTimes

Chapter 6: Managing Process Improvement Projects 40

Chapter 6: Managing Process Improvement Projects

41

Project Management Project Management Software CapabilitiesSoftware Capabilities

Chapter 6: Managing Process Improvement Projects 42

Microsoft Project’s Gantt Microsoft Project’s Gantt ChartChart

Chapter 6: Managing Process Improvement Projects 43

PERT Chart Generated by PERT Chart Generated by Microsoft ProjectMicrosoft Project

Chapter 6: Managing Process Improvement Projects

44

Calendar of Activities Calendar of Activities Created by Microsoft Created by Microsoft ProjectProject

Chapter 6: Managing Process Improvement Projects 45

Project and Feeder Project and Feeder BuffersBuffers

Chapter 6: Managing Process Improvement Projects 46

Controlling the Project: Controlling the Project: Earned ValueEarned Value

Chapter 6: Managing Process Improvement Projects 47

Variance ReportVariance ReportCost standard determined using

engineering estimates or analysis of past performance

Actual cost monitored and compared with cost standard

Project manager can exert control if difference between standard and actual (called a variance) is considered significant.

Chapter 6: Managing Process Improvement Projects 48

Cost-Schedule Reconciliation Cost-Schedule Reconciliation ChartsCharts

Chapter 6: Managing Process Improvement Projects 49

Earned Value ChartEarned Value Chart

Chapter 6: Managing Process Improvement Projects 50

CopyrightCopyrightCopyright John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that named in Section 117 of the United States Copyright Act without the express written consent of the copyright owner is unlawful. Requests for further information should be addressed to the Permissions Department, John Wiley & Sons, Inc. Adopters of the textbook are granted permission to make back-up copies for their own use only, to make copies for distribution to students of the course the textbook is used in, and to modify this material to best suit their instructional needs. Under no circumstances can copies be made for resale. The Publisher assumes no responsibility for errors, omissions, or damages, caused by the use of these programs or from the use of the information contained herein.

Chapter 6: Managing Process Improvement Projects 51