Upload
corey-reeves
View
219
Download
0
Tags:
Embed Size (px)
Citation preview
1
OPERATIONS MANAGEMENTfor MBAs Second Edition
Prepared by
Scott M. Shafer
Wake Forest University
Meredith and Shafer
John Wiley and Sons, Inc.
Chapter 10: Materials Requirements Planning
4
Courtaulds Films Produces plastic films used to package food Plants operated 24 hours/day 7 days/week Uses 60 types of raw materials to produce 40
types of film and offers 12,5000 make-to-order products
At end of 1980s, 25% of deliveries were shipped late because production planning and scheduling system unable to handle the complexity
Chapter 10: Materials Requirements Planning
5
Courtaulds Films continued
Visited the Formica Company to learn about MRP II
By 1990s Courtaulds implemented its own MRP II system
Became class A user Employees now take pride in their excellent
on-time performance
6
Recording for the Blind & Dyslexic (RFB&D) Loans textbooks in recorded or computerized
format When RFB&D moved to new facility, took
opportunity to design and implement a new integrated production system
With limited resources needed to satisfy increasing demand
Fast response was also critical Space limited amount of inventory
Chapter 10: Materials Requirements Planning
7
Recording for the Blind & Dyslexic (RFB&D) continued Goal: achieve lead time of no more than 2
working days for at least 95% of all requests
To achieve this, would need to increase performance from 333 books per day by 28%
To help achieve goal, RFB&D implemented a resource requirements planning system
Chapter 10: Materials Requirements Planning
9
Background Independent Demand
– automobiles, televisions, cartons of ice cream
– demand often occurs at constant rate
Dependent Demand– most raw materials, components, and subassemblies
– demand often occurs in lumps
Materials Requirements Planning (MRP)– designed when lumps in demand are known about
before hand
Chapter 10: Materials Requirements Planning
11
Relationship Between Finished Item Inventory and Raw Material/Subassembly Item Inventory (ROP)
Chapter 10: Materials Requirements Planning
13
The Boardsports Company
Component Lead TimeSidewalk Special 1 weekFiberglass board 3 weeksWheel assembly 1 weekWheel mount stand 4 weeksWheel 1 weekLocknut 1 weekSpindle 2 weeks
Chapter 10: Materials Requirements Planning
15
Material Requirements of Sidewalk SpecialFiberglass boards: 1 number of specials
Wheel assemblies: 2 number of specials
Wheels: 2 number of wheel assemblies
Spindles: 1 number of wheel assemblies
Locknut: 2 number of wheel assemblies
Wheel mount stand: 1 number of wheel assemblies
Chapter 10: Materials Requirements Planning
16
Material Required to Produce 50 Sidewalk SpecialsFiberglass boards: 1 number of specials = 1 50 = 50
Wheel assemblies: 2 number of specials = 2 50 = 100
Wheels: 2 number of wheel assemblies = 2 100 = 200
Spindles: 1 number of wheel assemblies = 1 100 = 100
Locknut: 2 number of wheel assemblies = 2 100 = 200
Wheel mount stand:
1 number of wheel assemblies = 1 100 = 100
Chapter 10: Materials Requirements Planning
17
Delivery 50 Sidewalk Specials in Week 10
1 2 3 4 5 6 7 8 9 10Sidewalk Specials 50
Date needed 50Boards Order date 50
Date needed 100Wheel assembly Order date 100
Date needed 200Wheels Order date 200
Date needed 100Spindles Order date 100
Date needed 100Mounting stands Order date 100
Date needed 200Locknuts Order date 200
Week
3 week lead time
Chapter 10: Materials Requirements Planning
20
Primary Inputs to MRP System
Master Production Schedule Bill of Materials File Inventory Master File
Chapter 10: Materials Requirements Planning
22
Master Production Schedule
Based on actual customer orders and predicted demand
Indicates when each ordered item will be produced
Chapter 10: Materials Requirements Planning
23
Bill of Materials (BOM)
Indicates all the raw materials, components, subassemblies, and assemblies required to produce an item
Shows way a finished product or parent item is put together from individual components
Parent item shown at highest level or level zero
Chapter 10: Materials Requirements Planning
24
Bill of Materials continued
Parts that go into parent item are called level 1 components and so on
Production planners explode BOM for level zero item to determine the number, due dates, and order dates of subcomponents
Chapter 10: Materials Requirements Planning
26
Inventory Master File Detailed information regarding the quantity of
each item, on hand, on order committed to use in various time periods
MRP system using inventory master file to determine the quantity available for use in a given period
If sufficient items not available, the system includes the item on the planned order release report
Chapter 10: Materials Requirements Planning
27
Low-Level Coding
Original product tree structure
Low-level-coded product tree structure
Chapter 10: Materials Requirements Planning
28
MRP System Outputs
Order Action Report– which orders are to be released and canceled
during the current time period
Open Orders Report– which orders to expedite or deexpedite
Planned Order Release Report– time-phased plan for orders to be released in
future time periods
Chapter 10: Materials Requirements Planning
29
MRP Computations
Process all items in BOM level-by-level– For each item at a level
• determine time phased gross requirements
• subtract on-hand and on-order amounts from gross requirements to determine net requirements
• apply lot-sizing rule to determine lot size
• offset the order release for lead time yielding time-phased planned order releases
Chapter 10: Materials Requirements Planning
30
MRP Computations continued
Net requirements for planning period = gross requirements
for planning period - planned on hand at planning period
Planned on hand at planning period = current on hand +
scheduled receipts prior to planning period - scheduled
requirements prior to planning period
Chapter 10: Materials Requirements Planning
31
MRP Computations continued
Zero-LevelWeek 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 50 150 50 100 100On hand 400 400 400 350 350 350 200 200 200 150 50 50 50Net requirements -- -- -- -- -- -- -- -- -- -- -- 50Planned order receipts 50Planned order releases 50Lead time = 3 weeks
Level 1Week 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 50 200On hand 50 50 50 100 100 100 100 100 100 100 50 100Net requirements 150Planned order receipts 50Planned order releases 250Lead time = 4 weeks
Chapter 10: Materials Requirements Planning
33
Capacity Requirements Planning
Capacity Using Overall Factors– production standards used to convert MPS into
loads on each work center– loads assumed to fall in same period as finished
goods in MPS
Bills of Capacity– same as capacity using overall factors but instead
of using historical ratios, uses the BOM and routing sheets
Chapter 10: Materials Requirements Planning
34
Capacity Requirements Planning continued Resource Profiles
– same as bills of capacity except lead times included so workloads fall in the correct period
Capacity Requirements Planning– uses all preceding information plus MRP outputs to
take existing inventories and lot sizing into consideration
– also considers partially completed work, demands for service parts, and scrap adjustments
Chapter 10: Materials Requirements Planning
37
Enterprise Resource Planning (ERP) MRP II extends MRP systems to share
information with other functional areas Key component of MRP II is storing operational
information centrally ERP systems seek to integrate all business
activities and processes throughout the organization
Goal is to provide real-time information to all employees that need it
39
CopyrightCopyright John Wiley & Sons, Inc. All rights reserved.
Reproduction or translation of this work beyond that named in Section 117 of the United States Copyright Act without the express written consent of the copyright owner is unlawful. Requests for further information should be addressed to the Permissions Department, John Wiley & Sons, Inc. Adopters of the textbook are granted permission to make back-up copies for their own use only, to make copies for distribution to students of the course the textbook is used in, and to modify this material to best suit their instructional needs. Under no circumstances can copies be made for resale. The Publisher assumes no responsibility for errors, omissions, or damages, caused by the use of these programs or from the use of the information contained herein.