Operating Instructions

BA MC295 EN 07.97

MOTOX

Motors

FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 TübingenTel. 07071/707-0 ⋅ Telefax 07071/707-400 ⋅ www.flender.com

A company of A. Friedr. Flender AG

Page 2: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.972 / 23

Contents

1. General notes 4

2. Safety and startup notes for low-voltage machines 52.1 General 52.2 Use in accordance with regulations 52.3 Handling, storage 52.4 Installation 52.5 Electrical connection 62.6 Operation 62.7 Warranty 6

3. Description 73.1 Overall design of the motors 73.2 Storage 73.3 Surface cooling 73.4 Motor frame 73.5 Stator winding 73.6 Rotor 73.7 Terminal boxes 83.8 Moitoring devices 8

4. Incoming goods, handling and storage 94.1 Incoming goods 94.1.1 Check before installation 94.1.2 Storage safety 94.2 Handling 94.3 Storage instructions 104.3.1 Storage up to 2 years 104.3.2 Storage under special conditions 11

5. Installation and assembly 125.1 Installation 125.2 Assembly 12

6. Electrical connection 136.1 Connection, insulation resistance 136.2 Direction of rotation and terminal designation 136.2.1 Standard design 136.2.2 Reversal of the direction of rotation 136.3 Ancillary devices 146.3.1 Temperature monitoring 146.3.2 Electronic speed monitoring 146.3.3 Anticondensation heater 146.3.4 Forced ventilation system 14

Page 3: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.973 / 23

7. Startup 15

8. Operation 15

9. Disturbances, reasons and remedy 16

10. Maintenance and repair 1710.1 Bearings and greasing 1710.2 Usable life of grease with for-life lubrication and grease charge quantities 1710.3 Connection rooms, terminals, cooling-air paths 17

11. Spare parts stock, service addresses 1811.1 Stocking spare parts 1811.2 Spare parts and Customer Service addresses 18

FLENDER TÜBINGEN GMBH Germany 19FLENDER TÜBINGEN GMBH Europe 20FLENDER TÜBINGEN GMBH International 21

12. Declaration by the manufacturer 23

Page 4: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.974 / 23

1. General notes

These Operating Instructions (BA) constitute part of the motor shipment and should be kept in theimmediate vicinity of the motor.

Only a precise knowledge of the Operating Instructions will ensure trouble-free operation ofthe drive by avoiding operating errors and careless usage. It is therefore in the interest of theoperator that the Operating Instructions are read, understood and observed in all respects bythe persons responsible for installation and operation.

Note: We accept no liability for any damage or malfunction resulting from nonobservanceof the Operating Instructions.

The motors described here are in accordance with the state of the art at the time of going to print ofthese Operating Instructions.

In the interest of further development, we reserve the right to make changes to the individualsubassemblies and accessories which, while retaining the essential features, are considered desirablefor increasing their efficiency and safety.

The copyright of these Operating Instructions remains the property of FLENDER TÜBINGEN GMBH.

These Operating Instructions may not be duplicated in part or whole and may not be used forcompetitive purposes or made available to third parties without our express consent.

Alterations or additions of these Operating Instructions may be done exceptionally by us only; otherwisecomplete liability will be cancelled.

Note: For special designs of the motors and their ancillary devices, the special contractualstipulations and engineering documents, e.g. special circuit diagrams, specialdimensional diagrams etc., shall apply in addition to these Operating Instructions. Forgear units, couplings and ancillary equipment not described in these OperatingInstructions, please observe the additional Operating Instructions included in thesupply (e.g. BA G295, BA F295, BA K295, BA S295, BA H295, BA 3400 etc.).

Please contact our works listed below in respect of all technical queries

FLENDER TÜBINGEN GMBH

Postfach 1709 ⋅ D-72007 Tübingen

Bahnhofstr. 40-44 ⋅ D-72072 Tübingen

Tel. (+49) 07071/707-0

Fax (+49) 07071/707-400

Internet: http://www.flender.com

or one of our service branches which are listed in Section 11. “Spare parts stock, service addresses”.

Page 5: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.975 / 23

2. Safety and startup notes for low-voltage machinesaccording to Low-Voltage Directive 73/23/EEC

2.1 General

Low-voltage motors have dangerous, live and rotating parts, and probably hot surfaces. All work fortransport, connection, commissioning and maintenance is to be made by qualified, responsiblespecialists (EN50110-1/VDE 0105; IEC 364 must be observed). Negligent conduct can cause serious personal injury and property damage.

2.2 Use in accordance with regulations

These low-voltage machines are intented for industrial installations. They comply with the harmonizedstandards of Series EN 60034 (VDE 0530). The use in hazardous locations is prohibited.

IP 54 Types of enclosure should by no means be used in the open air. Air-cooled designs are rated forambient temperatures from –20°C to +40°C as well as installation altitudes of 1000 m above mean sealevel. Be absolutely sure to observe deviating data on the rating plate. The conditions prevailing atthe installation site must be in compliance with all rating plate data.

Note: Low-voltage machines are components for installation in machines in the intendmentof Machine Directive 98/37/ECC. Startup is not permitted until conformity of the endproduct with this Directive has been established (among others, observe EN 60204-1).

2.3 Handling, storage

Damage ascertained after delivery must be reported to the transport company immediately; ifnecessary, startup must be ruled out. Screwed lifting eyes must be tightened firmly. They aredesigned for the weight of the low-voltage machine; do not attach additional loads. If necessary, usesuitable and amply dimensioned material-handling equipment (e.g. rope guides).

Remove existing transport locks prior to startup. Reuse these for subsequent handling. Iflow-voltage machines are stored, make sure the environment is dry, dust-free and vibration-free(Veff 0,2 mm/s) (bearing damage with motor at standstill). Measure the insulation resistance priorto startup. In the case of values of 1,5 MΩ , dry the windings. Observe ”Storage Instructions”.

2.4 Installation

Ensure a uniform supporting surface, perfect foot and flange attachment and accurate alignment withdirect coupling. Avoid design-related resonances with the rotation frequency and the double mainsfrequency. Turn the rotor by hand and check for abnormal slipping noises. Check direction of rotationin uncoupled condition (observe Section ”Electric Connection”).

Mount and/or remove belt pulleys and couplings only with suitable devices (through heating!) and coverwith a guard against contact. Avoid inadmissible belt tensions (Technical List).The balancing condition of the low-voltage machine is indicated in the parallel keyway (H = half, F = whole keyway). In the case of a design with a half keyway (H), the coupling must likewisebe balanced with a half keyway. Remove any projecting, visible keyway portion by machining.

Establish any necessary pipe connections. Instruct the Owner to provide a covering for mounting typeswith shaft end towards the top to prevent foreign matter from falling into the fan. Aeration must not beobstructed, and the exhaust air - including that of adjacent units - must not be directly taken in again.

Figure 2.4: Ventilation

Page 6: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.976 / 23

2.5 Electrical connection

All work must only be carried out by qualified specialized staff with the low-voltage machine releasedand protected against restarting. This also applies to auxiliary circuits (e.g. anticondensation heater).Check for any residual voltages.

Exceeding the tolerances specified in EN 60034-1 (VDE 0530, Part 1)- voltage 5%, frequency 2%, curvature, symmetry - will increase through heating and affect the electromagnetic compatibility. Observe the rating plate dataas well as the connection diagram in the terminal box.

The connection must be made in such a manner that a permanently safe electric link is maintained(no projecting wire ends); use allocated cable end protection. Make a safe ground wire connection.

The smallest clearances between bare, live parts among themselves and against earth must not be lessthan the values given in DIN VDE 0110-1:8mm at UN 550V, 10mm at UN 725V, 14mm at UN 1000 V.

There must be no foreign matter, dirt or moisture in the terminal box. Close any unnecessary cableentry eyes and the box itself to make them dust and waterproof.

Secure the parallel key for trial operation without driven units.

2.6 Operation

Vibration levels Veff 3,5 mm/s (PN 15 kW) and/or 4,5 mm/s (PN > 15 kW) in coupled operation arequite safe. In case of changes as compared with normal operation - e.g. increased temperatures,noises, vibrations -, determine the cause and, if necessary, consult with the manufacturer. Do notdeactivate protective devices, i.e. not even during trial operation. In case of doubt, stop the low-voltagemachine.

In case of an excessive accumulation of dirt, clean the air paths at regular intervals.

Refill bearing arrangements fitted with regreasing device with grease, with the low-voltage machinerunning. Check out the type of saponification. If grease outlet holes are closed by plugs, remove plugsprior to startup and reclose the holes with grease. Bearing replacement with for-life lubrication (2Zbearings) after appr. 10000 hours (2-pole) and/or 20000 hours (higher-pole); however, not later thanafter 3-4 years or as instructed by the manufacturer.

2.7 Warranty

The warranty is given on condition that these safety and startup notes as well as the notes for ancillarydevices, if any, are observed. Further details are given in the following sections of the OperatingInstructions.

The Operating Instructions include that information which is necessary for specialized staff when usingthe electric machines in industrial installations. Additional information and notes for non-qualifiedpersons and for the use of the machines in non-industrial installations are not included in theseOperating Instructions.

Page 7: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.977 / 23

3. Description

3.1 Overall design of the motors

Mounting arrangement acc. to EN 60034-7

Mounting dimensions in the case of surface cooling up to frame size 200 according to FLENDERTÜBINGEN GMBH Manufacturing Standard to the modular system.

Connection designations acc. to DIN VDE 0530-8, IEC 60034-8.

Type of enclosure according to IEC 60034-5.

Type of cooling according to EN 60034-6 IC 411 surface cooling.

For details of the construction of the motors please refer to the valid catalogues.

3.2 Storage

The motors are fitted with grease-lubricated rolling bearings. The bearings of the surface-cooled motorsof standard design up to frame size 200 have for-life lubrication.

3.3 Surface cooling

Design for fin cooling, where an external fan takes in the cooling air through the openings in the fan coverand presses the air over the surface of the stator housing.

3.4 Motor frame

The stator frame and the bearing brackets are made of aluminium alloy or grey cast iron, dependingon the frame size. The cowl is made of sheet steel. Stator frame surface with cooling ribs and attachedterminal box.

3.5 Stator winding

The stator winding is designed in the thermal class (see rating plate) specified in EN 60034-1.High-quality varnished cambric wires, suitable surface insulants and the type of impregnationguarantee high mechanical and electric strength combined with high value in use and long service life.If required, the coil winding heads will be embedded in silicone rubber. Special advantages are offeredby the use of the embedding in combination with the thermal classes F and H if motors are used forparticularly arduous starting and braking conditions. In addition, embedding helps to achieve anincreased mechanical short-circuit resistance, and (in the case of surface cooling) the motor isprotected from condensed water.

3.6 Rotor

In the case of the smaller motors, the rotor has a short-circuited cage made of pressure die castaluminium, while a brazed cage is provided for the larger motors and for special startng and brakingconditions. The rotor is dynamically balanced.The balancing condition is shown in the parallel keyway; see Item 5.2, ”Assembly”. In their standard design, the motors comply with the vibration level N according to DIN VDE 0530-14/IEC 60034-14; in special cases, their vibration level is R (reduced) or S (special).

Page 8: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.978 / 23

3.7 Terminal boxes

If required, additional terminals for the monitoring devices are available inside the terminal box. Onspecial order an additional terminal box will be installed for larger motors (see dimension drawing).On special order, the larger motors will have an additional terminal box attached to them.For the number of the existing terminals please refer to the circuit diagrams to be found inside theterminal box.

3.8 Moitoring devices

Monitoring devices are only available on special request.For the technical information please refer to the circuit diagrams, the rating plates or the special orderdocuments.

Page 9: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.979 / 23

4. Incoming goods, handling and storage

4.1 Incoming goods

4.1.1 Check before installation

Check whether the motor has been damaged in transit. If the packaging is damaged to such an extentthat damage to the motor can be expected, the packaging should be removed in the presence of therepresentative of the transport company.

4.1.2 Storage safety

(Only for motors with cylindrical roller bearings)

The rotor of the motor is blocked in order to avoid bearing damage due tovibrations while at standstill:- by lock screws marked in red in the bearing end cover- or by the transport lock fixed to the shaft end.Prior to attaching the motor, the lock screws should be slackened back by 10mm und secured or the transport lock removed (see guide board on motor).Now it must be possible to turn the shaft manually.

It is recommended to release the blocking only after having fitted the drive unit.

The transport lock must be reused for subsequent transports.

Prevent trouble, thereby avoiding personal injury and property damage.The person responsible for the installation has to ensure that:- Safety Notes and Operating Instructions are available and observed;- operating conditions and technical information described in the order are observed,- protective devices are used, and- prescribed maintenance work is carried out.

4.2 Handling

Starting from frame size 132, lifting eyes for hanging up the lifting hooks areprovided on the stator construction of the motor.Check whether screwed lifting eyes are securely tightened.Lift motors only by using these lifting eyes. Several lifting eyes must alwaysbe used together.

Lifting of the motors on other parts (e.g. shaft ends) is not permitted, since thismight result in considerable damages.The motor lifting eyes are only suitable for the motor weight. Additional loadsattached to the motor, particularly gear units, must not be lifted with theselifting eyes.

Page 10: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.9710 / 23

4.3 Storage instructions

4.3.1 Storage up to 2 years

In the case of motors stored for a period of up to 2 years, the following should be observed:

Storage

The motors should be stored in a dry, dust-free room at the right temperature; this would avoid havingto use special packaging. In all other cases, the motors have to be packed in plastic sheet withhumidity-absorbing materials (e.g. Branogel) or in hermetically heat sealed film. Provide protectivecovering against sun and rain.

In order to avoid consequential damage to the bearings due to vibrations while at standstill, e.g. byadjacent running machines, the motors must only be stored in vibration-free rooms.

Motors with roller bearings are fitted with a storage lock for transport. This must be left in its blockedcondition until startup and/or refitted following an inspection or a trial run. An interlock is not requiredand does not exist if the bearing arrangement is axially preloaded.

Due to the long service life, the rolling bearings must be lubricated with special grease (e.g. StaburagsNBU 8 EP).

Startup

Prior to startup, the phase-to-phase and phase-to-chassis insulation resistance of the winding has tobe measured by specialized staff. Moist windings could cause leakage currents, flashovers anddisruptive discharges. In the case of values of < 1.5 MΩ measured at a winding temperature of 20°C,the winding should be dried. Drying can be effected by feeding the winding with single-phase alternatingcurrent. The voltage should be set such that the values of the heater current recommended in Figures4.3.1-1 and 4.3.1-2 are not exceeded. The temperature should reach appr. 80°C and act for several hours. Drying can also be effected in adrying oven.

Recommended heater circuits and maximum heater currents:

Figure 4.3.1-1: ∆-wiring diagram Figure 4.3.1-2: Y-wiring diagram

In the case of motors with bearing lock, this must be released prior to startup.

IMAX = 65 % IN IMAX = 75 % IN Y

Page 11: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.9711 / 23

Rolling bearings, lubrication

Provided proper storage for an extended period of time, one may assume that no deterioration of thegrease in the bearings will take place within 2 years. Motors with for-life lubrication can be put intooperation after having checked the insulation resistance of the winding and completed a short trial run.In the case of motors of thermal class F, a lithium saponified rolling bearing grease with a dropping pointof at least 180°C is used for a normal ambient temperature. In the case of motors of thermal class H and of certain special motors, a suitable special grease is used.

In the case of motors with relubrication system, relubrication of both bearings should be carried out asa precaution shortly after startup with motor running.The grease type, grease quantity and relubrication interval are stamped on an additional plate attachedto the motor.The values given for grease life with relubrication interval can definitely be expected for motors of IP55type of protection whose bearing arrangements are protected from the ingress of even fine dust andwater from any direction, e.g. for outdoor installation without additional protection. For motors of IP54 type of protection, these values apply with the reservation that the ecologicaldamage by dust and water will not go beyond the stipulation in DIN IEC 60034-5 with test accordingto DIN IEC 60034-5.

Note: In addition to the storage instructions, all particulars of these Operating Instructionsmust be observed. A warranty of the manufacturer can only be maintained if all of theabove-mentioned items are observed.

4.3.2 Storage under special conditions

If the motors are to be stored under the following conditions, i.e.storage for 2 years outdoor storage storage up to –50°C storage with driven machine storage under other special conditionsplease ask for the Special Storage Instructions (”ELV”) from our Service Departmentt, see Section 11.“Spare parts stock, service addresses”.

Page 12: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.9712 / 23

5. Installation and assembly

5.1 Installation

Note: Permissible coolant temperature (room temperature at the site) according to EN 60060034-1 / IEC 60034-1: max. 40°C and permissible installation altitude upto 1000 m above mean sea level (for other values please see rating plate).

Make sure that the cooling air can freely flow to the air inlet openings and flowout again through the air outlet openings and cannot be directly taken in again.Intake and blow-out orifices must be protected from blockagesand coarser-grained dust particles.

When installing the surface-heated motors starting from frame size 200, makeabsolutely sure that the condensed- water drain holes are located at the lowermost position.

Careful installation of the motors on a perfectly level support to avoid distortionswhen tightening screws. In the case of machines to be coupled, ensure perfectalignment. Flexible couplings should preferably be used. For larger motors werecommend double gear teeth couplings which, because to their large number ofteeth, bear uniformly and, because of their low weight, possess the smallestmoment of inertia.When using components such as belt pulleys, gears etc., makesure that the permissible radial and thrust loads of shafts are not exceeded.

5.2 Assembly

Fitting of belt pulleys or couplings.Start by cleaning (do not use emery cloth) and greasing the shaft end. Fit the belt pulley or couplingusing only the fitting device provided for this purpose. This can be done by using the centre hole withthread located in the shaft end. Screw corresponding threaded bolts into the thread. Now fit a steel diskof sufficient diameter to cover the hub bore of the belt pulley or coupling. Fit the belt pulley or couplingto the shaft end using a nut or a suitable hydraulic device.

Expanding the drive units by hammer blows is inadmissible because of therisk of bearing damage.When replacing the bearings, these should always be detached and fitted onlywith suitable devices and using the shaft centre hole. Use only original spareparts.

The rotor of the motor is dynamically balanced. The balancing condition is indicated in the parallel(H = half, F = whole keyway). Remove any projecting, visible keyway portion by machining. Whenmounting the drive unit, check for proper balancing condition!The balancing of the transmission parts to be fitted must be adapted to the rotor balancing. In the caseof half-keyway balancing, remove the projecting visible keyway portion by machining.

The motor and/or geared motor must only be mounted and operated in the designated mounting type(see rating plate).

Page 13: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.9713 / 23

6. Electrical connection

6.1 Connection, insulation resistance

The connection must be made by an expert in accordance with the current safety regulations. Therelevant mounting and operating instructions as well as the usual national and international regulationsmust also be observed.

Note: Observe rating plate data! Compare nature of current, mains voltage and frequency! Connect motor im compliance with the circuit diagram to be found

in the terminal box! Check wiring diagram! Observe calibration current for protective switch setting! The motor must be protected from undue heating, e.g. with a protective motor switch.

All motors are provided with a ground wire terminal inside the terminal box:

Unused cable entries in the terminal box are to be closed torsion-proof as a protection against dust andmoisture. All contact screws and nuts should be tightened firmly for avoidance of excessively hightransfer resistances.

In the case of terminal boards with U-shaped binding clips, the conductors to be connected must bebent into a U-shape and placed underneath the binding clips.

Figure 6.1: Cable connection

In the case of motors with terminal boxes having ground surfaces between cover and base, a thingrease layer should be applied for sealing and rust prevention purposes.After prolonged storage and standstill periods, the phase-to-phase and phase-to-chassis insulationresistance of the winding must be measured prior to startup.Moist windings could cause leakage currents, flashovers and disruptive discharges. In the case ofvalues of 1,5MΩ measured at a winding temperature of 20°C, the winding should be dried.

6.2 Direction of rotation and terminal designation

Direction of rotation and designation of the terminals in accordance with DIN VDE 0530-8/IEC 60034-8.

6.2.1 Standard design

In their standard design, the surface-cooled motors up to frame size 200 are suitable for both directionsof rotation.In the case of motors for only one direction of rotation, the sense of rotation is marked by an arrow onthe motor or gear unit. Terminals U1, V1, W1 to phases L1, L2, L3 (in alphabetical and/or natural order)will always result in clockwise rotation of the motor.

6.2.2 Reversal of the direction of rotation

The direction of rotation can be reversed in the case of on-line starting and pole-changeable motorswith separate windings by interchanging two mains conductors at the motor terminal board.In the case of motors with star/delta starting and pole-changeable motors with Dahlander winding, 2mains conductors at the feed-in to the motor switch must be interchanged. For a machine with only one shaft end or two shaft ends of different thicknesses, the sense of rotationwill be that direction of rotation of the rotor which an observer can establish when looking at the frontof the only or thicker shaft end.

Page 14: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.9714 / 23

6.3 Ancillary devices

6.3.1 Temperature monitoring *)

The temperature sensors for monitoring the temperature of, for instance, the stator winding, thebearings and the coolant should be connected via the additional terminals in the main terminal boxprovided for this purpose, or via one or several additional terminal boxes.The temperature sensors should be connected according to the applicable circuit diagram. Thespecifications and notes according to Item 6.1 ”Connection, Insulation Resistance” shall apply to theconnection.

6.3.2 Electronic speed monitoring *)

Basically, this consists of a slot proximity switch and the control segment. The electronic speed controlis maintenance-free.

6.3.3 Anticondensation heater *)

Heating power and connection voltage: See guide board on motor. The anticondensation heater shouldbe connected via the terminals provided in the main terminal box or via an additional terminal box inaccordance with the applicable circuit diagram.The specifications and notes according to Item 6.1 ”Connection, Insulation Resistance” shall apply tothe connection. The anticondensation heater should be switched on only after having stopped themotor. It must not be ON during motor operation.

6.3.4 Forced ventilation system *)

In the case of forced ventilation, the direction of rotation is identified separately by an arrow on the forcedventilation system. Observe direction of rotation! (See rotational direction arrow).Connect the forced ventilation system in accordance with the applicable circuit diagram included in theterminal box. The forced ventilation motor must be switched on during operation of the main motor! The forced ventilation system ensures dissipation of the heat loss while the motor is in operation. Whenthe main motor has been stopped, a temperature-dependent after-running of the forced ventilationsystem is required.

Check during startup of the main motor:

Check whether the forced ventilation is operative and activated during startup of the motor!

*) Only available on special order.

Page 15: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.9715 / 23

7. Startup

After having checked and verified the following items, the motor is ready for startup:

Check whether the bearing lock has been removed! See Item 4.1.2 ”Storage Safety”.

Observe rating plate data.

Check whether the voltage and frequency of the motor correspond to the mains data.

Check whether the direction of rotation is correct and whether, in case of converter operation, the limitspeed is not exceeded.

Check whether the motor is protected in accordance with regulations.

Check and ensure that in case of star/delta starting, because of the risk of undue operating loads,the changeover from star to delta takes place only after the starting current of the star stage has diedout.

Check whether the electrical connections are firmly tightened and whether the monitoring devices areconnected and adjusted according to regulations.

Check coolant temperature.

Check whether the ancillary devices, if any, are operative.

Check whether air intake openings and cooling surfaces are clean.

Check whether safety precautions have been taken: earthing.

Check whether the motor has been properly secured.

In case of a belt drive, check belt tension.

Check whether the terminal box cover has been closed and whether the lead entries have beenproperly sealed.

8. Operation

During operation, the motors should be checked for

excessive operating temperature and

any changes in gear unit noises.

If there are any irregularities during operation, the drive assembly must be shutdown immediately. The cause of the malfunction should be ascertained byreferring to the Troubleshooting Table (Section 9. “Disturbances, reasons andremedy”). The Troubleshooting Table includes possible malfunctions, their cause as wellas suggestions for remedy.If the cause cannot be ascertained and/or if there is no facility for repair usingown means, we recommend to call in one of our service fitters from one of ourService Departments (see Section 11. “Spare parts stock, service addresses”).

Attention!

Page 16: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.9716 / 23

9. Disturbances, reasons and remedy

Note: Malfunctions occuring during the warranty period which necessitate repair of the motorunit may only be repaired by FLENDER TÜBINGEN GMBH service personnel. Evenafter the warranty period has elapsed, we recommend our customers to consult ourService Division concerning malfunctions whose cause cannot be clearly ascertained.

DisturbancesBearing is too hot Bearing noise *) Motor runs unevenly

Reasons Remendy

Too much grease inbearing

Remove excess grease

Bearing dirty Replace bearing

Belt tension too high Reduce belt tension

Coupling forces are pul-ling or pushing

Realign motor, correctcoupling

Coolant temperatureabove 40 °C (104 °F)

Adjust temperature ofcooling air

Not enough grease in thebearing

Grease according tospecifications

Motor incorrectly mounted Check mounting type ofmotor

Bearing grease darkcoloured

Check bearing currents

Scoring at bearing innerrace, e.g. caused by

motor start with lockedbearing

Replace bearing, avoidvibrations at standstill

Unbalance caused bycoupling

Exact balancing

Motor fastening unstable Check fastening

Tabelle 9.: Disturbances, reasons and remedy

Disturbances

Motor doesnot start

Motor istoo hot

Highdecreasein speed

Protectivedevice triggers

Reasons Remendy

Countertorque too high Check motor and load torque

Mains voltage too low Check mains conditions

Phase interruption Check mains supply

Wrong winding connection Observe wiring diagram andrating plate

Overload Compare data on rating plate

Too many starts per hour Observe rated duty type

Insufficient ventilation Check ventilation passages,check direction of rotation

Ventilation passages dirty Clean

Short-circuit of winding orterminal board

Measure insulationresistance

Starting time exceeded Check starting conditions

Tabelle 9.: Disturbances, reasons and remedy

*) If remedies described are insufficient, we recommend to replace the bearings.

Page 17: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.9717 / 23

10. Maintenance and repair

10.1 Bearings and greasing

The bearings of the surface-cooled motors up to frame size 280 have for-life lubrication. In case ofdeviations therefrom, this will be shown on guide boards attached to the motor.For normal coolant temperatures, they will receive one charge of grease at the factory which will lastfor several years under normal operating conditions.

10.2 Usable life of grease with for-life lubrication and grease charge quantities

Horizontal mounting type (IM B.)

FramenN

Approximate greasequantity per bearing [g]Frame

size 3600[min–1]

3000[min–1]

1800[min–1]

1500[min–1]

1000[min–1] AS (DE) BS (NE)

C 80 43000 60000 9 9C 90

3000060000 15 11

C 100 3000043000

6000020 15

C 112 2200030000

4300045 25

C 13222000

75 50C 160 43000 90 70C 180 15000

22000 3000030000

43000110 80

C 20015000 30000

110 60

Tabel 10.2-1: Usable life of grease in operation hours

Vertical mounting type (IM V.)

FramenN

Approximate greasequantity per bearing [g]Frame

size 3600[min–1]

3000[min–1]

1800[min–1]

1500[min–1]

1000[min–1] AS (DE) BS (NE)

C 80 9 9C 90

2200022000 30000

4300015 11

C 10022000 30000

3000020 15

C 11215000

45 25C 132 15000 75 50C 160

1500022000

3000090 70

C 18011000

2200022000

110 80C 200

11000110 60

Tabel 10.2-2: Usable life of grease in operation hours

The usable life of grease indicated above applies to an ambient temperature of max. 40°C. The usablelife of grease should be reduced by the factor of 0,7 of the tabular value for every 10°C temperatureincrease (max. 20C = factor 0,5).

At an ambient temperature of 25C, twice the usable life of grease can be expected.

10.3 Connection rooms, terminals, cooling-air paths

Depending on operating conditions, the following work should be carried out:- the connection rooms and terminals should be checked for cleanliness;- the electrical connections should be checked for tight fit, and- the cooling-air paths should be cleaned.The intake orifices and the cooling surfaces must be protected from blockagesand contamination.Do not use sharp-edged tools for cleaning!

Page 18: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.9718 / 23

11. Spare parts stock, service addresses

11.1 Stocking spare parts

Maintaining a stock of the most essential replacement and wearing parts on site will ensure that the driveis serviceable at all times.

We assume warranty only for original spare parts supplied by us.

We would like to explicitly draw attention to the fact that spare parts andaccessories not supplied by us have not been tested and approved by useither. Fitting and/or use of such products can therefore under certaincircumstances adversely effect structurally specified properties of the driveand will thus impair active and/or passive safety. No form of reliability orwarranty will be assumed by FLENDER TÜBINGEN GMBH for damage causedby the use of non-original spare parts and accessories.

Please note that special production and supply specifications frequently exist for components and wewill always offer spare parts in accordance with the latest technology and the latest legal requirements.

When ordering spare parts, the following data should be stated:

- Order No. (see rating plate)

- Type designation (see rating plate)

- Part No. (3-digit pos. No. from the spare parts list, or 6-digit ident. No. or 7-digit part No.)

- Quantity

11.2 Spare parts and Customer Service addresses

FLENDER TÜBINGEN GMBH Germany

FLENDER TÜBINGEN GMBH Europe

FLENDER TÜBINGEN GMBH International

See following pages.

Attention!

Page 19: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.9719 / 23

FLENDER TÜBINGEN GMBH Germany

Sales Office BerlinEgellsstraße 21, D-13507 Berlin

Postfach, 13500 BerlinTel.: (030) 4301-0 - Fax: (030) 4301-2712E-mail: [email protected]

Your contact in Tübingen: Tel.: 07071 / 707-326 Fax: 07071 / 707-475

Sales Office HannoverMarktplatz 3, D-30853 Langenhagen

Postfach 1869, D-30839 LangenhagenTel.: (0511) 77189-0 - Fax: (0511) 77189-89

E-mail: [email protected]

Your contact in Tübingen: Tel.: 07071 / 707-470 Fax: 07071 / 707-324

Sales Office Herne

Westring 303, D-44629 HernePostfach 101240, D-44602 Herne

Tel.: (02323) 497-0 - Fax: (02323) 497-250E-mail: [email protected]

Your contact in Tübingen: Tel.: 07071 / 707-435 Fax: 07071 / 707-475

Babcock Centre Officec/o Deutsche Babcock AG H2 / 529

Duisburger Straße 375, D-46049 OberhausenTel.: (0208) 833-1430 - Fax: (0208) 833-2187

E-mail: [email protected]

Your contact in Tübingen: Tel.: 07071 / 707-435 Fax: 07071 / 707-475

Sales Office StuttgartFriolzheimer Straße 3, D-70499 Stuttgart

Postfach 311262, D-70472 StuttgartTel.: (0711) 78054-51 - Fax: (0711) 78054-50E-mail: [email protected]

Your contact in Tübingen: Tel.: 07071 / 707-310 Fax: 07071 / 707-391

Sales Office MünchenLiebigstraße 15, D-85757 KarlsfeldPostfach 1264, D-85750 Karlsfeld

Tel.: (08131) 9003-0 - Fax: (08131) 9003-33E-mail: [email protected]

Your contact in Tübingen: Tel.: 07071 / 707-467 Fax: 07071 / 707-211

FLENDER TÜBINGEN GMBH D-72007 Tübingen - Bahnhofstraße 40-44, D-72072 Tübingen Tel.: (07071) 707-0 - Fax: (07071) 707-400 http://www.flender.com

Further partners in the Flender Group: FLENDER ENGINEERING & SERVICE D-44607 Herne - Südstraße 111, D-44625 Herne ANTRIEBSTECHNIK GMBH Tel.: (02323) 940-0 - Tx.: 8229868 - Fax: (02323) 940-200

http://www.flender-service.com

A. FRIEDR. FLENDER AG D-46393 Bocholt - Alfred-Flender-Straße 77, D-46395 Bocholt Tel.: (02871) 92-0 - Tx.: 813841 - Fax: (02871) 922596 http://www.flender.com

LOHER AG D-94095 Ruhstorf - Hans-Loher-Straße 32, D-94099 Ruhstorf Tel.: (08531) 390 - Tx.: 8531806 - Fax: (08531) 39437 http://www.loher.de

A. FRIEDR. FLENDER AG Thierbacher Straße 24, D-09320 Penig GETRIEBEWERK PENIG Tel.: (037381) 60 - Tx.: 322661 - Fax: (037381) 80286

http://www.flender.com

FLENDER GUSS GMBH Obere Hauptstraße 228-230, D-09228 Wittgensdorf Tel.: (03722) 64-0 - Tx.: 322352 - Fax: (03722) 64-3112 http://www.flender-guss.de

Page 20: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.9720 / 23

FLENDER TÜBINGEN GMBH EuropeAUSTRIAFlender Ges.m.b.H. Industriezentrum Nö-SüdStrasse 4, Objekt 14, Postfach 132A-2355 Wiener NeudorfTel. 02236-645Fax 02236-64570-10E-mail: [email protected]

BELGIUM & LUXEMBOURGN.V. Flender Belge S.A. Cyriel Buyssestraat 130B-1800 VilvoordeTel. 02-2531030Fax 02-2530966E-mail: [email protected]

CZECH REPUBLICA. Friedr. Flender AG Branch Office Czech RepublicHotel DUO, Teplicka 17CZ-19000 Praha 9Tel. 00420-2-83882300Fax 00420-2-83882205E-mail: [email protected]

DENMARKFLENDER AS Sydmarken 46DK-2860 SoborgTel. 0045-7025-3000Fax 0045-7025-3001E-mail: [email protected]://www.flender.dk

EAST EUROPEAN COUNTRIESVertriebszentrum Berlin Egellsstrasse 21D-13507 BerlinTel. 0049-304301-0Fax 0049-304301-2712

FINLANDFlender Oy Korppaanmäentie 17 CL 6FIN-00300 HelsinkiTel. 09-4778410Fax 09-4361410E-mail: [email protected]://www.flender.fi

FRANCEFlender France S.A.R.L. 3, Rue Jean MonnetZone des CôtesF-78990 ElancourtB.P. 5F-78312 Maurepas CedexTel. 1-30663900Fax 1-30663513E-mail: [email protected]

BRANCH OFFICES:Flender S.A.R.L.25, Boulevard JoffreF-54000 NancyTel. 038-3308590Fax 038-3308599

Flender S.A.R.L.36, Rue Jean BroquinF-69006 LyonTel. 0472-839520 Fax 0472-839539

GREECEFlender Greece 14, Grevenon Str.GR-11855 AthensTel. 00301-3423827Fax 00301-3423827E-mail: [email protected]

Mangrinox S.A. 14, Grevenon Str.GR-11855 AthensTel. 00301-3423201-3 / 3412427Fax 00301-3459928 / 3459767E-mail: [email protected]

HUNGARYA. Friedr. Flender AG Branch OfficeBécsi Út 3-5H-1023 BudapestTel. 01-3450720Fax 01-3450729

ITALYFlender Cigala S.p.A. Via Privata da Strada Provinciale, 215I-20040 Caponago (Mi)Tel. 0039-02-95742371Fax 0039-02-95743887E-mail: [email protected]

THE NETHERLANDSFLENDER NEDERLAND BV Lage Brink 5-7NL-7317 BD ApeldoornTel. 055-5275000Fax 055-5218011E-mail:[email protected]://www.flender.nl

NORWAYATB Norge G. Bauknecht A.S.Frysjavn 40N-0884 OsloTel. 02-2021036Fax 02-2021050E-mail: [email protected]

POLANDA. Friedr. Flender AG Branch OfficeOddzial w Mikolowieul. Wyzwolenia 27PL-43-190 MikolowTel. 032-2264561Fax 032-2264562E-mail: [email protected]

PORTUGALROVEX Rol. e Vedantes, Lda.Rua Nelson de Barros, 11 r/c esq.P-1900 LisboaPortugalTel. 00351-1-8160240Fax 00351-1-8145022

SPAINFlender Ibérica S.A. Poligono Industrial San MarcosCalle Morse, 31 (Parcela D-15)E-28906 Getafe/MadridTel. 00349-1-6836186Fax 00349-1-6834650 E-mail: [email protected]://www.flender.es

SWEDENFlender Svenska AB Ellipsvägen 11S-141 75 HuddingeTel. 46-8-4495670Fax 46-8-4495690E-mail: [email protected]://www.flender.se

SWITZERLANDFlender ATB-Loher Zeughausstr. 48CH-5600 LenzburgTel. 062-8857600Fax 062-8857676E-mail: [email protected]://www.flender.ch

TURKEYFlender Güc Aktarma Sistemler San.

ve Tic. Ltd. STIImes Sanayi SitesiE Blok 502. sokak No.22TR-81360 Dudullu-IstanbulTel. 0216-3643413Fax 0216-3645913E-mail: [email protected]://www.flendertr.com

UNITED KINGDOM & EIREFlender-Himmelwerk Ltd. Thornbury Works, Leeds RoadGB-Bradford BD3 7EB West YorkshireTel. 01274-657700Fax 01274-669836E-mail: [email protected]://www.flender-power.co.uk

BOSNIA-HERZEGOVINA /BULGARIA / CROATIA / REPUBLICOF MACEDONIA / REPUBLIC OFYUGOSLAVIA / ROMANIA /SLOVAKIA / SLOVENIA / ALBANIAA. Friedr. Flender AG Branch OfficeIndustriezentrum Nö-Süd,Strasse 4, Objekt 14A-2355 Wiener NeudorfTel. 02236-6457020Fax 02236-6457023

Subsidiary, Manufacturing,Sales and Stock

Subsidiary, Sales and Stock

Distributor

Assembly Centre

Page 21: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.9721 / 23

FLENDER TÜBINGEN GMBH InternationalA F R I C A A M E R I C AALGERIA & TUNESIASimetra Flender S.A.R.L. 3, Rue Jean MonnetZone des CôtesF-78990 ElancourtB.P. 5, 78312 Maurepas CedexTel. 1-30663900Fax 1-30663513

EGYPTFarid Hassanen & Co. 81, Matbaa Ahleia StreetBoulac-Cairo, A.R.E.Tel. 5751489Fax 5751383

Workshop and Service:13, Selim Oma StreetBoulac-Cairo, A.R.E.Tel. 764656, 774897Fax 769741

MOROCCOS.M.E.M. 15, Boulevard du FouaratCasablancaTel. 2-240253, 2-240271

SAUDI ARABIA/U.A.E./KUWAITTicos-International General Trading Co.P.O. Box 2191AjmanTel. 428716Fax 428730

SOUTH AFRICAFlender Power Transmission (Pty.)Ltd.

No.8 Greenfield ParkCnr. Furnace Street & Quality RoadIsando, Kempton Park Tv1.P.O. Box 8358, Elandsfontein 1406Tel. 011-3922850/1/2/3/4/5Fax 011-3922434E-mail: [email protected]://www.flender.co.za

BRANCH OFFICE:P.O. Box 28283 Bothasig, Cape Town 7406Unit No.3 Marconi ParkNo.9 Marconi CresentMontague GardenTel. 021-5515003Fax 021-523824E-mail: [email protected]

BRAZILFlender Brasil Ltda. Rua Quartoze Nr. 60, Caixa Postal 29632211-970 Contagem-MGTel. 031-3692000Fax 031-3311893E-mail: [email protected]

BRANCH OFFICES:Rua Aratans, 1.455Planalto Paulista04081-005-São Paulo-SPTel. 011-5365211Fax 011-5301252E-mail: [email protected]

CANADAFlender Power Transmission Inc. 215 Shields Court, Units 4-6Markham, Ontario L3R8V2Tel. 905-3051021Fax 905-3051023E-mail: [email protected]://www.flenderpti.com

BRANCH OFFICES:Flender Power Transmission Inc.Bay # 3, 6565 40th Street S.E.Calgary, Alberta T2C - 2J9Tel. 403-543-7744Fax 403-543-7745E-mail: [email protected]

COLOMBIAFlender de ColombiaA.G.P. Representaciones Ltda.Carrera 68 Nr. 16-80 Piso 4.CIPRES TRADE CENTERBogota - ColombiaTel. 91-3460561Fax 91-3460415E-mail: [email protected]

CHILESargent S.A. Av. Pdte. Bulnes 205, Casilla 166 DSantiagoTel. 02-6991525Fax 02-6983989

MEXICOFlender de Mexico, S.A. de C.V. Vista Hermosa No.23 Col. Romero VargasAdpo. Postal 2-85Puebla, Pue.C.P. 72131Tel. 22310951, 22310844Fax 22310913E-mail: [email protected]://puebla.infosel.com.mx/flender

BRANCH OFFICE:Flender de Mexico, S.A. de C.V.Oficina MonterreyDiamante 112, Col. Pedregal del ValleSan Pedro de Garza Garcia, C.P. 66280Monterrey, Nuevo LeonTel. (08)3034806Fax (08)3034806

USAFlender Corporation 950 Tollgate Road, P.O. Box 1449Elgin, Illinois 60123Tel. 847-9311990Fax 847-9310711E-mail: [email protected]: [email protected]://www.flenderusa.com

VENEZUELAF. H. Transmissiones S.A. Urb. Buena VistaCalle Johan Schafer o Segunda CalleEdif. F.H.T. (frente a Lab. Boehringer)Municipio Sucre, Petare Edo. MirandaCaracas - VenezuelaTel. 0058-2-215261Fax 0058-2-211838 E-mail: [email protected]

Subsidiary, Manufacturing,Sales and Stock

Subsidiary, Sales and Stock

Distributor

Assembly Centre

Page 22: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.9722 / 23

FLENDER TÜBINGEN GMBH InternationalA U S T R A L I A A S I A

AUSTRALIA Flender (Australia) Pty. Ltd. 9 Nello PlaceWetherill ParkN.S.W. 2164SydneyTel. 02-97562322Fax 02-97564892E-mail: [email protected]://www.flenderaust.com

BRANCH OFFICES:20 Eskay Road, South OakleighMelbourneVictoria 3167Tel. 03-95790633Fax 03-95790417E-mail: [email protected]

20 Brookes Street, Bowen HillsBrisbaneQld. 4006Tel. 07-32522711Fax 07-32523150E-mail: [email protected]

1 Dampier RoadWelshpool, PerthW.A. 6106Tel. 09-4518355Fax 09-4583582E-mail: [email protected]

NEW ZEALANDR.R. Fisher & Co.Ltd. 13, Spring StreetPapatoetoeNew ZealandTel. 09-2784059

ASEANFlender Singapore Pte. Ltd. 13A, Tech Park CrescentSingapore 637843Tel. 0065-8979466Fax 0065-8979411E-mail: [email protected]://www.flender.com.sg

PEOPLE’S REPUBLIC OF CHINABeijing Flender No. C-411, Office Building,Beijing Lufthansa CenterNo. 50, Liangmaqiao RoadBeijing 100016 P.R.C.Tel. 0086-10-64622151-55Fax 0086-10-64622143E-mail: [email protected]

Shanghai Representative Office14C, Zhao Feng Universe Building1800 Zhongshan West RoadShanghai 200233, ChinaTel. 021-64282625Fax 021-64282615

INDIAFlender Limited. 2, St. Georges Gate Road, 5 th Floor Calcutta-700022 West Bengal - IndiaTel 33-223-0164/-0545/-0846 Fax 33-223-0830 E-mail: [email protected]

Flender Macneill Gears Ltd. Southern Region Office 41, Nelson Manickam Road Aminjikarai Chennai - 600029 Tel. 44-3741076/0677 Fax 44-3740473 E-mail: [email protected]

New DehliTel. 11-6250104/0221Fax 11-6256372

BombayTel. 22-7657227Fax 22-7657228

INDONESIA PT Flenindo Aditransimisi Jl. Ketintang Wiyata VI No. 22Surabaya 60231IndonesiaTel. 6231-8291082Fax 6231-8286363E-mail: [email protected]

JAPANFlender Ishibashi MFG. Co. Ltd. (Nogata Industrial Park)4636-15Oaza KamitonnoNogata-Shi, Fukuoka-ken822 JapanTel. 09492-6-3711 Fax 09492-6-3902E-mail: [email protected]

KOREA Flender LTD., KOREA 1128-4 Kuro-Dong, Kuro-Ku,Seoul, Korea. 152-050Tel. 02-859-1750-3Fax 02-859-1754E-mail: [email protected]

Sung Ji Trading Co. No.211, Ma YeolGochuk Ind. Market 103-4Gochuk DongKuro-Ku, Seoul/KoreaTel. 02-688-8367, 8368Fax 02-688-8368

MALAYSIAGerman Transmission Machinery SDN. BHD.Prime Subang Industrial ParkNo.3 Block C, Lot 757Jl Subang 6, off Persiaran Subang47500 Petaling JayaSelangor, MalaysiaTel. 03-7336023Fax 03-7336259

PAKISTANO.T.C. 114 Alama Iqbal RoadLahore-5Tel. 42-869398Fax 42-305291

PHILLIPPINEOTEC Pemex Philippines, Inc. Rm 209-210 Quinio Building64 Sen. Gil J. Puyat Avenue,Makati CityPhillippinesTel. 2-8448218, 8924636Fax 2-8437244, 8233602E-mail: [email protected]

TAIWANA. Fried. Flender AG Taiwan Branch No. 5, Alley 17, Lane 194, HuanHo St.,Hsichih, Taipei Hsien, Taiwan, R. O. C. Tel. 02-26932441-3Fax 02-26943611E-mail: [email protected]

THAILANDSmith Technology Co. Ltd. 128/75 Phyathai Plaza Building7th. Fl., Phyathai RoadRajtheveeBangkok 10400Tel. 02-2165831/3Fax 02-2165799

Subsidiary, Manufacturing,Sales and Stock

Subsidiary, Sales and Stock

Distributor

Assembly Centre

Page 23: Operating Instructions - HIMMEL-GEAR · Operating Instructions BA MC295 EN 07.97 MOTOX Motors FLENDER TÜBINGEN GMBH ⋅ Bahnhofstr. 40-44 ⋅ D-72072 Tübingen Tel. 07071/707-0 ⋅

BA MC295 EN 07.9723 / 23

12. Declaration by the manufacturer

Declaration by the manufacturer

as defined by EC machinery directive 98/37/EEC Annex II B

We hereby declare that the

three-phase asynchronous motors with squirrel-cage for low-voltage applications, types

C.80. C.132.

C.90. C.160.

C.100. C.180.

C.112. C.200.

described in these operating instructions are meant for being installed in a machine and thattheir putting into operation is prohibited until it has been ascertained that the machine, in whichthese components will be installed, corresponds to the regulations of the EC directive98/37/EEC (original version) incl. all further amendments.

All the harmonised standards published by the EC-Commission in the official journal of theEuropean Community applicable for our products are either totally or partly observed with thismanufacturers declarationThese are especially: - EN 292-1 - EN 292-2- EN 294- EN 349 - EN 50081-2- EN 50082-2- EN 60034- EN 60204-1

Tübingen, the 31.07.1998 (Manager of Standards Department)