Page 1: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day 2008

Problems and worries

Pole Face Windings of the PS

Pierre Freyermuth

Page 2: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day - Pierre Freyermuth

TopicsI. Introduction

a. New PFW supplyingb. Operations mechanism

II. 2007 Objectives a. Initially start with 3 current mode but…b. Commissioningc. Write the adjustment softwared. Measuring matrix current/parameter

III. 2007 Worriesa. Power converters limitation discoveryb. Qmeter worries

IV. 2007 Performed Worka. Measurements and tests on PFW power convertersb. A first version of the adjustment softwarec. Some point of the matrix are done

V. 2008 Objectivesa. Start-up with calculated matrix from the 3 current modeb. Consolidation of PFW softwarec. Re-validate power converters with new improvements d. Measuring matrix

VI. Acknowledgements

march 18th 2008

Page 3: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day - Pierre Freyermuth

I. Introductiona. New PFW supplying : From

3 to 5 currents, new magnetic possibilities.

march 18th 2008

Page 4: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day - Pierre Freyermuth

I. Introduction

B8

DNi

PRW8L

PRWDNi

FWi

FWp

DWi

DWp

PRWFW

PRWDW

FNi

PRWFNi

FNp

PRWFNp

DNp

PRWDNp

a. New PFW supplying : new adjustment strategy.

We have the possibility to adjust 5 currents to control 4 parameters.A fifth parameter can be Q’’ or the less RMS current.

march 18th 2008

Page 5: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day - Pierre Freyermuth

b. Operation mechanism

I. Introduction

Initialization

Measurements

Adjustments

Validation

Q & Xi Functions

B referenceBasic PFW functionsOffsets (induced currents)

Basics Function + offsets + delay

Matrix Current/Parameters

Delta Q Xi and PFW

GFA Functions

F divided by 2 F divided by 2 D divided by 2 D divided by 2 8L

-69.62583902 -69.62583902 -69.34348382 -69.34348382 -140.9071886

4724.450193 4724.450193 4448.004963 4448.004963 15618.09203

-132097.6443 -132097.6443 -120847.1562 -120847.1562 -629118.599

2008207.907 2008207.907 1878489.268 1878489.268 12876124.13

-18441185.6 -18441185.6 -19064782.56 -19064782.56 -153801695.1

107310799.4 107310799.4 135356468.3 135356468.3 1156879365

-400722679.1 -400722679.1 -692359922.2 -692359922.2 -5752779781

926255245.5 926255245.5 2561901332 2561901332 19484885283

-1085404765 -1085404765 -6778874121 -6778874121 -45310391674

-311012453.2 -311012453.2 12412841053 12412841053 70431719737

3090360677 3090360677 -14337015336 -14337015336 -64975740067

-4010216606 -4010216606 6808948644 6808948644 15077847896

298791600.1 298791600.1 6952676039 6952676039 42452276462

4582049839 4582049839 -13544238105 -13544238105 -50622889472

-3978062740 -3978062740 4922539229 4922539229 4339840389

-2137567755 -2137567755 9776915079 9776915079 43423592268

6834200682 6834200682 -16099815280 -16099815280 -51959530208

-6190441427 -6190441427 11822739710 11822739710 31707962067

2976968966 2976968966 -4965473500 -4965473500 -11427875585

-771198535.1 -771198535.1 1158457836 1158457836 2322745119

85249649.04 85249649.04 -117296409.9 -117296409.9 -207001787.5

PR.P-MC-dQH-dFN 0.00178088 1.89E-07 -1.89E-11

PR.P-MC-dQH-dFW 0.0007982 -1.44E-07 6.89E-12

PR.P-MC-dQH-dDN -0.0046678 2.47E-06 -2.43E-10

PR.P-MC-dQH-dDW -0.00053476 9.65E-08 -4.62E-12

PR.P-MC-dQH-d8L -0.00048114 8.49E-08 -3.91E-12

PR.P-MC-dQV-dFN -0.00043632 7.85E-08 -3.74E-12

PR.P-MC-dQV-dFW -0.00049511 8.94E-08 -4.28E-12

PR.P-MC-dQV-dDN 0.00071702 -1.28E-07 6.08E-12

PR.P-MC-dQV-dDW 0.00084204 -1.52E-07 7.22E-12

PR.P-MC-dQV-d8L 0.00049109 -8.67E-08 4.00E-12

PR.P-MC-dXiH-dFN 0.05708207 6.15E-06 -6.15E-10

PR.P-MC-dXiH-dFW -0.01415477 -9.70E-07 9.69E-11

PR.P-MC-dXiH-dDN 0.03163256 3.58E-06 -3.58E-10

PR.P-MC-dXiH-dDW -0.00707463 -5.11E-07 5.10E-11

PR.P-MC-dXiH-d8L 0.00217581 -2.53E-07 2.53E-11

PR.P-MC-dXiV-dFN -0.03549138 -4.60E-06 4.59E-10

PR.P-MC-dXiV-dFW 0.01003489 1.33E-06 -1.33E-10

PR.P-MC-dXiV-dDN -0.0482633 -4.69E-06 4.69E-10

PR.P-MC-dXiV-dDW 0.01036297 4.94E-07 -4.93E-11

PR.P-MC-dXiV-d8L -0.00029342 -4.96E-08 4.95E-12

march 18th 2008

Page 6: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day - Pierre Freyermuth

b. Operation mechanism

The Matrix is:

Polynomials define the behavior of Qh, Qv, h, v as a function of current in DN, DW, FN, FW, 8L.

Fesa Class is used to store it.

I. IntroductionPR.P-MC-dQH-dFN 0.00178088 1.89E-07 -1.89E-11

PR.P-MC-dQH-dFW 0.0007982 -1.44E-07 6.89E-12

PR.P-MC-dQH-dDN -0.0046678 2.47E-06 -2.43E-10

PR.P-MC-dQH-dDW -0.00053476 9.65E-08 -4.62E-12

PR.P-MC-dQH-d8L -0.00048114 8.49E-08 -3.91E-12

PR.P-MC-dQV-dFN -0.00043632 7.85E-08 -3.74E-12

PR.P-MC-dQV-dFW -0.00049511 8.94E-08 -4.28E-12

PR.P-MC-dQV-dDN 0.00071702 -1.28E-07 6.08E-12

PR.P-MC-dQV-dDW 0.00084204 -1.52E-07 7.22E-12

PR.P-MC-dQV-d8L 0.00049109 -8.67E-08 4.00E-12

PR.P-MC-dXiH-dFN 0.05708207 6.15E-06 -6.15E-10

PR.P-MC-dXiH-dFW -0.01415477 -9.70E-07 9.69E-11

PR.P-MC-dXiH-dDN 0.03163256 3.58E-06 -3.58E-10

PR.P-MC-dXiH-dDW -0.00707463 -5.11E-07 5.10E-11

PR.P-MC-dXiH-d8L 0.00217581 -2.53E-07 2.53E-11

PR.P-MC-dXiV-dFN -0.03549138 -4.60E-06 4.59E-10

PR.P-MC-dXiV-dFW 0.01003489 1.33E-06 -1.33E-10

PR.P-MC-dXiV-dDN -0.0482633 -4.69E-06 4.69E-10

PR.P-MC-dXiV-dDW 0.01036297 4.94E-07 -4.93E-11

PR.P-MC-dXiV-d8L -0.00029342 -4.96E-08 4.95E-12

march 18th 2008

Page 7: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day - Pierre Freyermuth

a. Initially start with 3 current mode but…After the Cold check-out measurements, it was

decide to keep the 5 currents mode.

b. CommissioningTest, measure and validate to the 2008 start-up

c. Write the adjustment softwareA software to be able to control tune and

chromaticity. Imply to determine different new scenarios and re-write the previous application.

d. Measuring matrix current/parameterUse a special cycle for measurements, a multi flat-

top one or separated cycles.

II. 2007 Objectives

march 18th 2008

Page 8: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day - Pierre Freyermuth

a. Power converters limitations discovery:The 2007 run history.

III. Worries

April Mai June July August

5 5 5

Sta

rt-u

p

Sh

ut

Dow

n

3 3

Many changes between 3 to the new 5 currents mode occurred.

march 18th 2008

Page 9: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day - Pierre Freyermuth

a. Power converters limitation discovery:

III. Worries

April Mai June July August

55 53 3

At the beginning, induced currents from B field was not well compensate.

New samplers available, but with data worries.

We observed problems with the East Spills.

Adjustment of balance resistors between pair and odd windings.

Power converters started to be unstable.

We decided to return back in 3 currents mode the 15th of may.

march 18th 2008

Page 10: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day - Pierre Freyermuth

a. Power converters limitation discovery:

III. Worries

April Mai June July August

55 53 3

march 18th 2008

Page 11: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day - Pierre Freyermuth

a. Power converters limitation discovery:

III. Worries

April Mai June July August5

553 3

Back to 5CM, but still with induce currents.

Worries with GFA.

Many works done to improve the Dirac spill, not really successful.

Hybrid test, with new converters except the 8 loop.

The Multi-Turn Extraction was nearly impossible, whereas good in 3CM.

Back to 3CM to measure tune and East spill, in order to underline the difference of beam quality.

march 18th 2008

Page 12: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day - Pierre Freyermuth

a. Power converters limitation discovery:

III. Worries

April Mai June July August5

553 3

Dirac Spill 5CMDirac Spill 3CM

march 18th 2008

Page 13: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day - Pierre Freyermuth

a. Power converters limitation discovery:

III. Worries

April Mai June July August5 5 53 3

Back to 5CM, after lot of works from PO team. Among others, the synchronization of acquisitions and regulation loop was improve.

Dirac experiment observed a better spill than the 3CM.

MTE islands in 5CM.

But still a “transition” error around 40A.

march 18th 2008

Page 14: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day - Pierre Freyermuth

a. Power converters limitation discovery:

III. Worries

April Mai June July August5 5 53 3

3CM 5CMDirac Spill after averaging.

march 18th 2008

Page 15: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day - Pierre Freyermuth

a. Power converters limitation discovery:

III. Worries

April Mai June July August5 5 53 3

40A instabilities during 2007 run. Nowadays PO team found the solution.

march 18th 2008

Page 16: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day - Pierre Freyermuth

b. Q meter The BBQ front-end installed and connected to the

old acquisition system.

Measurements was impossible with an excursion more than 10mm.

III. Worries

march 18th 2008

Page 17: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day - Pierre Freyermuth

b. Q meter The most important impacts were

The impossibility to measure non-linear chromaticity.

Lot of points of the matrix is missing.

Q meter is an important tool for operation.

III. Worries

march 18th 2008

Page 18: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day - Pierre Freyermuth

a. Measurements and tests on PFW power converters Lots of tests were made, with impacts on the physic run. PO team brought PFW power converters to our

requirements.

b. A first version of the adjustment software Initialization, adjustments, measurements and validation

system work. Some adjusment scenarios was found.

c. Some point of the matrix are done 14 GeV/c 3,5 GeV/c 26 GeV/c (From 2004 measurement).

d. BBQ measurement was improved until the end of the run

IV. 2007 Performed Works

march 18th 2008

Page 19: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day - Pierre Freyermuth

a. Start-up with a calculated matrix and the virtual 3 current mode.

b. Consolidation of PFW software.

c. Re-validate power converters with new improvements.

A new DSP to avoid 40A ripple and reduce delays.

d. Validate tune measurementsBBQ and old system

e. Measuring matrix.

V. 2008 Objectives

march 18th 2008

Page 20: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day - Pierre Freyermuth

Bernard Vandorpe Simone Gilardoni Rende Steerenberg Jean-Paul Burnet, Olivier Michels And The PO team Marek Gasior and the BI team

All people imply in this project

VI. Acknowledgements

march 18th 2008

Page 21: OP day 2008  Problems   and  worries  P ole  F ace  W indings of the  PS

OP day 2008

Problems and worries

Pole Face Windings of the PS

Pierre Freyermuth

\\cern.ch\dfs\Users\p\pfreyerm\Public\Problems and worries PS.pptx