Upload
sahil-maini
View
126
Download
2
Tags:
Embed Size (px)
DESCRIPTION
construction
Citation preview
OFFSHORE CONSTRUCTION
INTRODUCTION
Offshore construction is the installation of structures
and pipelines in a marine environment for the production and
transmission of oil and gas. Construction in the offshore
environment is a dangerous activity and where possible the
construction is modular in nature with the individual modules being
assembled onshore and using a crane vessel to lift the modules into
place. Oil platforms are key fixed installations from which drilling and
production activity is carried out. Drilling rigs are either floating vessels
for deeper water or jack-up designs which is a barge with lift able legs.
Both of these types of vessel are constructed in marine yards but are
often involved during the construction phase to pre-drill some
production wells. Specialist floating hotel vessels known as floats are
used to accommodate workers during the construction and hook-up
phases.
Other key factors in offshore construction are the weather window
which defines periods of relatively light weather during which
continuous construction or other offshore activity can take place. Safety
is another key construction parameter, the main hazard obviously being
a fall into the sea from which speedy recovery in cold waters is
essential.
The Offshore Construction is a major field of operation in the Oil and
Gas industry, there are many people involved in accurate surface and
subsurface positioning aspects. It will provide people with the solid basic
knowledge of the associated terminology, equipment and techniques
used in the offshore construction industry. The course guides you
sequentially through all aspects of various example construction
projects whilst covering also project procedures, HSE, and reporting _______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE1
aspects. This course will beneficial to those co-operating with surveyors
and others involved in the daily operation of the Offshore Construction
industry.
OFFSHORE CONSTRUCTION INDUSTRY
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE2
INTRODUCTION:
The Offshore Construction industry done a major field of operation for
the Oil and Gas industry, there are many people involved in accurate
surface and subsurface positioning aspects. Construction industry
provides people with the solid basic knowledge of the associated
terminology, equipment and techniques used in the offshore
construction industry. They also provide sequentially through all aspects
of various example construction projects whilst covering also project
procedures, HSE, and reporting aspects.
Offshore construction industry worked on offshore as well as onshore.
offshore work depending upon the onshore work. In on shore work there
are two main things are; technical work & commercial work.
Construction industry giving the HSE & technical ,training because at
every time the employee have to handle anew things.
Some times offshore construction industry done a onshore
construction also they done a construction for to get some petroleum
goods . all the oil & gas industry are depend on the offshore
construction industry .
Offshore construction industry is known as contractors and
subcontractors. They may be companies, partnerships or self-employed
individuals.
NEED OF OFFSHORE CONSTRUCTION INDUSTRY
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE3
Man has found petroleum only in places where it seeped naturally
from the earth. Then in the 19th Century, man discovered ways to drill
water wells deep into the ground.
Sometimes these wells produced petroleum instead of water, and soon
the same techniques were being used to drill for oil. As the supply of
petroleum grew, ways of refining it into useful products were developed.
As the demand grew, this new technology for drilling holes could be
used to produce far more petroleum than ever before - if it could be
found.
On that time man needs to construct a structure or building on offshore
to store the natural products and research on the natural products.
All oil & gas are depend on the offshore construction industry because
of the construction industry they got a around 3000 bal. crude oil per
day . from one oil rig. for all this reason we need to be a offshore
construction industry in offshore business .
In the today’s world the new technology comes up because of this we
find out new source of natural resources for that we need a offshore
construction industry. offshore construction industry installing structure
and pipelines in marine environment for the production and
transmission of oil gas. And construction industry provide all the living
facility as well as protection facility to customer on oil platform.
Therefore offshore construction industry need of oil & gas industry.
.
CONSTRUCTION INDUSTRY ON ONSHORE & OFFSHORE
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE4
ONSHORE WORK
TENDER FLOATING BY OIL COMPANY
The Client or customer floats a tender in market which contains contract
and bid documents. These two further include commercial terms,
technical terms, scope of work and bid specification
The Contractor or the Sub Contractor who makes the lowest bid gets
the contract
SURVEY:
When the company got the contract they send a 3 to 4 member team
on a construction field to see what type of work will be carried out like
modification or revamping.
SCOPE OF WORK :
After the survey of construction field they find out the scope of work
with the help of piping and instrumental diagram which is given by the
client
DRAWINGS:
They prepare the isometrics & structural drawing of new modification
of construction with the help of existing general arrangement drawing,
existing piping plant, & existing framing plant.
CALCULATION:
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE5
After the drawing process is done then the project & operating
committee calculate the scope of work with the help of isometric
drawing & structural drawing which has been generated by construction
committee.
PROCUREMENT:
Is defined the structural & piping which is required during the
construction activity. Procurement is Depending on the scope of work
entrusted to , Purchase Order is released company or by the Clients.
Pursuant to this activity, regular Purchase Order specifications are
issued to facilitate vendor compliance, develop documents in
accordance with requirements and fulfill inspection requirements and
Third Party obligations.
INSPECTION:
Use of raw material during the construction activity will be inspected by
the respected quality control & quality assets department.
FABRICATION:
Fabrication will be carried out with the reference of approved drawing
which has been approved by the client & third party inspection.
Fabricated material will be inspected by the company’s quality control &
quality assets department then stage wise it offered to the third party &
client to inspected fabrication material.
After the final product comes OUT it will be transported on offshore
construction field to done the final construction activity by the way of
water transportation.
OFFSHORE WORK
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE6
ROUTE PREPARATION ,
PIPE LAYING (CONSTRUCTION)
ROUTE PREPARATION:
The offshore pipeline must be laid on terrain
that is clear of geohazards, debris and
boulders. The seabed must be sufficiently flat
and in water that is deep enough for
construction and construction vessels to
operate. If these conditions do not occur
naturally, then seabed preparation by methods such as presweeping or
dredging may be required.
Seabed preparation may involve localized presweeping in areas
where there are sand waves or natural depressions on the sea floor.
Presweeping, which creates a more even surface on which to lay the
pipe, is expected to be necessary in the more mobile bed form (sand-
wave) areas of Torres Strait. Presweeping is often performed
immediately prior to pipe claying, because sand-wave environments are
typically dynamic and the preswept seabed surface may quickly resume
its naturally uneven profile. Sand wave presweeping is typically
performed by plugging or jetting. Volumes of sand
mobilized when using these techniques are small and tend to settle
locally.
PIPING CLAYING (CONSTRUCTION):
Pipe claying vessels are expected to be employed to install the pipeline
in the offshore .Vessels of this type typically operate as follows:
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE7
• Sections of line pipe are stacked on the pipe claying vessel.
• Pipe ends are prepared for welding.
• Successive joints of line pipe are lined up and welded together.
• Welds are radio graphically inspected and repaired or replaced as
necessary.
• Anti-corrosion material (fusion-bonded epoxy) and a weight-coating
are applied to the welded joints.
• The pipeline is lowered to the seafloor.
A constant tension is applied to the pipeline as it is lowered from the
vessel to the seabed using a pipe claying arm (called a stinger). The
stinger extends from the stern of the pipe claying vessel and prevents
the pipeline from bending excessively between the vessel and the
seabed.
The laying of an offshore pipeline is generally a continuous process.
Barges (towed by tugs) or self-propelled vessels bring the line pipe and
other supplies to the pipe claying vessel. An offshore pipe claying
operation typically comprises:
• A pipe claying vessel.
• Up to three anchor-handling tugs (depending on pipe claying vessel
type )
• A general supply vessel.
• Line-pipe supply vessels in sufficient numbers to ensure a continuous
supply of line pipe to the pipe claying vessel.
• Bulk carriers to transport line pipe to a location from which the line
pipe supply vessels can supply line pipe to the pipe claying vessel.
• A dedicated survey vessel.
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE8
IMPORTANT’S OF R & D DEPARTMENT IN CONSTRUCTION
INDUSTRY
In the past half-century, spectacular advances have been made in the
design, construction, and installation of structures for offshore oil
and gas production. From the original simple fixed four-pile platform
in 20 ft of water offshore Louisiana, the industry has evolved to today’s
use of permanent floating structures with sophisticated Facilities
designed to support production in fields exceeding 1 million
bbl of oil equivalent and operating in water depths exceeding
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE9
7,000 ft.
Expansion into increasingly deeper waters in search of larger
reserves has presented operational challenges requiring ingenuity, risk
taking, and foresight. The ability to continually push the technological
envelope has historically been made possible by the joint R&D
efforts of operator companies, engineering and construction firms,
contractors, equipment manufacturers, and academia. This article will
highlight a few selected areas in which R&D has contributed to recent
operational successes or in which future R&D efforts undoubtedly
will be required to provide technological support for continued frontier
Pursuits and for meeting the associated challenges. Solutions from R&D
efforts can be broadly categorized according to their level of beneficial
impact on a project’s outcome and the immediacy of the need, whether
short-term or long-term. A breakthrough
Solution can be construed as one in which state-of-the-art
technology has been applied in a fashion that allows immediate and
significant gains. R&D also can improve current know-how by
advancing technology to newer generations that provide faster,
more economical or more viable alternatives to prior approaches.
Based on project involvement and knowledge of the offshore arena,
This article will attempt to categorize each of the areas accordingly
and discuss how this vital R&D activity should be protected.
GAS SOLUTION: (Example)
The increased demand for natural gas in the U.S. and globally,
supported by satisfactory market prices, makes the economic recovery,
processing, handling, and transportation of natural gas products an area
with immediate as well as long-term potential. Oil and gas
reserves have been, and continue to be, discovered in locations
remote to distribution infrastructure, such as deepwater Gulf of_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE10
Mexico, Newfoundland, West Africa, Malaysia, Trinidad, and Indonesia,
where the gas associated with oil production or gas reserves considered
small are disadvantaged economically. The industry has solved the
question of producing remote oil with floating production, storage, and
offloading (FPSO) vessels or with spars, tension leg platforms, subsea
completions, and other floating production systems that include subsea
oil pipelines, but we are still faced with the question, “What do we do
with smaller volumes of associated or produced gas?”
Technically feasible and economically viable gas solutions for
remote gas are emerging rapidly in the form of transportable,
marketable, and fungible gas products such as liquefied natural gas
(LNG), methanol, Fischer-Tropsch liquids, ammonia, urea,
diethyl ether (DME), and liquefied petroleum gases (propane,
butane). Organizing a commercial deal that connects a market for
the products with the gas source is the key. Bringing down capital
and operating costs is the facilitator, and the inventive process is
under way now.
Several innovations are now coming from research designed to
give clients the best options for commercializing their disadvantaged
gas. Immediate benefits are the elimination of gas flaring,
alternatives to costly gas reinjection, and the creation of marketable
gas products that, in themselves, can be a viable gas business. Some
of the most recently proposed gas solutions include:
• Barge-mounted gas-to-liquids process.
• FPSO-vessel-mounted methanol processing.
• Gasification of coal into Fischer-Tropsch liquids (methanol,
DME, diesel).
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE11
• Development of horizontal steel LNG storage tanks in a
Perliteinsulatedconcrete “cold box” for onshore or offshore applications.
• A “short haul” concept for small LNG quantities (150–300
MMscf/D) including a concrete barge with new tank design to liquefy,
store, and offload LNG near the gasfield end, transport it 1,000 to
1,500 miles, and then have a similar regas barge at the destination.
• New regas technology using air exchangers to greatly reduce
fuel costs and air emissions.
• A concept to produce and store compressed natural gas on specially
designed shuttle tankers.
• LNG FPSO vessels for liquefying gas at offshore field locations
in the open ocean.
• LNG floating storage and regasification units for importing
LNG and re gasifying it in the open ocean. In addition to these
technologies, R&D needs to continue its focus on developing economical
products and processes that can be used for stranded and associated
gas so the products can be readily marketed. In that regard, ongoing
efforts need to be continued in the transport, storage, and offloading of
LNG.
R & D PROVIDE SAFETY AND SECURITY SOLUTION
Offshore assets, remotely operated or manned, are vulnerable to
Potential terrorist attacks. There are both topside and sub sea
components that warrant a continued need for R&D to develop methods
to safeguard these investments after installation. Significant
advancements have been made in the reliability and safety aspects, but
minimal consideration has been given to the protection of the asset._______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE12
THE RELEVANT MARKETS OF OFFSHORE CONSTRUCTION
PRODUCT MARKET:
With regard to offshore construction, oil and gas installations are
considered to belong to the same product market, as many companies
tender for contracts for both types of installations and the orders derive
from the same set of customers. The same type of argument applies to
standing and floating installations where the choice from a demand
point of view depends on technical aspects such as the location of the
field and water depth. Offshore contracts may be awarded on piecemeal
basis with different contractors involved to perform different tasks.
Some customers award contracts on a turnkey basis, whereby one
contractor would be responsible for the entire project and, as the case
may be, would engage subcontractors. The abbreviation EPCI
(Engineering, Procurement, Construction and Installation) is used as an
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE13
industry specific term for the activities required in order to complete
turnkey offshore projects. Third parties have generally confirmed the
suggested product market definition even though some third parties
have pointed out that pipe laying on some occasions have formed part
of EPCI contracts
GEOGRAPHIC MARKET:
The parties have submitted that the geographic scope of the market for
offshore construction (EPCI) is world wide as such services are being
provided wherever oil and gas fields and contracts are awarded on the
basis of world-wide tenders. The off shore construction market has in
previous decisions by the Commission been considered to be either
global or regional (e.g. the North Sea or the Norwegian Shelf). The third
parties participating in the Commissions market investigation have
generally supported that this market is global.
KEY FACTORS IN ECONOMIC SUCSESS
Three key elements that contribute to economic success in the offshore
are cost management, reduction in project development time, and
improved well performance. The degree to which firms achieve gains in
any or all of these areas will contribute heavily to their potential for
success or failure.
COST MANAGEMENT
Cost management includes both efforts to alter operations to offset
increased costs and measures to reduce costs associated with given
aspects of a project. An example of the first type of effort occurred
when recent increased demand for offshore rigs drove drilling rates up.
Companies had no control over the market-determined price but could
search for ways to minimize drilling time and therefore drilling costs.
The other type of cost management effort refers to the continual search _______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE14
for cost-reduction techniques. Technology often is a major influence on
cost reduction.
Cost reductions are achieved in a number of other ways. day, and the
single Mystique well, which produces at Outsourcing of certain services
can allow for the sharing of 25 MMcf per day. resources to avoid the
cost of being on site 24 hours per
day. For example, inspection of operational equipment by qualified
contractor personnel and equipment on a part-time basis allows those
resources to be used for multiple projects. As costs are shared across a
larger volume of service, the costs associated with any one project
decline. Despite potential economic advantages, outsourcing is an area
of concern for the Minerals Management Service (MMS). The MMS has
issued a notice regarding possible
waivers from daily inspection requirements, which may prove essential
for marginally economic projects.23 Used equipment is becoming
another important factor even for deep-water operations. This approach
allows for both direct cost savings and reduction in delivery time to the
site. Another cost-saving option is sub sea well completions and
transportation tiebacks to nearby platforms for production processing.
This has been a promising approach to offshore development in deep
waters. This approach lowers overall
project cost by avoiding the cost of a production platform at the water’s
surface dedicated solely to a single project
REDUCTION IN PROJECT DEVELOPMENT TIME
The success of any construction project projects underscores the
importance of adequate planning to ensure both optimal resource
recovery and a strong economic return on investment. However, as
experience in offshore construction operations grows, companies’ need
for measured caution lessens and firms emphasize timely activity in
their approaches to project development. The goal is to
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE15
accelerate development, which increases the expected net
financial return by yielding an earlier economic return and
reducing the carrying costs of early expenditures on leases, geology
and geophysical work, and exploratory drilling.
Eg. Design improvements between the Auger (initial production in 1994)
and Mars (initial production in 1996) projects, both at water depths of
approximately 2,900 feet, allowed Shell to cut the construction period to
9 months with a saving of $120 million.26 Accelerated development
enhances economic attractiveness by reducing project uncertainty
because adverse changes in market price for the commodity or factor
costs become more of a possibility as development time lengthens.
One approach to achieve revenues as soon as reasonable is the use of
a subsea completion and transportation of production to an existing
platform. A key advantage to this approach is that it provides an early
contribution to project returns while additional engineering and design
work for the full project proceeds. Another approach being developed
especially for deep-water project development is in the overlapping of
design phases and construction. Improvements in technology and
project management allowed Shell Deepwater to develop the project in
about the same calendar time. Development for offshore construction
projects in general had ranged up to 5 years previously, with deep
projects requiring up to 10 years. Recent field development has been
accelerated with the period from discovery to first production in shallow
water ranging between 6 and 18 months. Variables.Experience with
deep-water construction and operations has enabled development to
proceed much faster, with time from discovery to production declining
from 10 years to just over 2 years by 2001
WELL PERFORMANCE
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE16
A third major factor behind favorable offshore economics for offshore
construction is the rather astonishing production
performance characteristics of large fields. This is seen clearly in deep-
water fields, which tend to have high permeability and pressure that
result in rapid flow to the well bore. Individual well flows of 100 million
cubic feet (MMcf) per day have been achieved at some fields,
Well performance is important of both ultimate product development &
speed of construction process Given that production performance
variables such as the initial flow rate dominate over drilling costs as a
major influence on profitability, a rational strategy is for the operator to
pursue well drilling and completion technology with an emphasis on
increased productivity despite increased costs. As long as the cost
increments are managed properly, the productivity gains may be well
justified.
Analysis of a representative deep-water gas project shows that possible
increases in drilling costs of 50 percent could be offset by flow rate
increases of only 19 percent (assuming all other project parameters
remain unchanged). These estimates show the economic incentive
behind research and development in drilling and completion
technologies that have resulted in very high flow rates.
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE17
CASE STUDY
ONGC: OFFSHORE CRISIS MANAGEMENT
Background
In the offshore Oil & Natural Gas Corp. of
India (ONGC) offshore platform BHN
located in Arabian Sea, 100 miles (160 km)
from Mumbai (Bombay).
BHN Complex consists of BHN + MNW +
NF + NA Platforms, all bridge connected.
Mumbai high - North & South put together is producing about 260,000
barrels of oil and 10.2 million cubic feet of gas per day. BHN Complex
production was 40,000 bbl & 4 million Cft of gas per day. Out of 4 m gas
being produced, 2.4 is used for gas lift, utilities etc and balance is
pumped to Onshore, Uran. Mumbai High North has another Complex –
NQ. Its production was going thru BHN & hence also affected now.
Presently, ONGC have resumed production from South Fields which is
150,000 bbl/day + 7.5 million Cft of gas per day.
Noble Charlie Yester (NCY) drill rig on-site at time of incident at NA
Platform. IRM DP Vessel of ONGC ‘MSV Samudra Suraksha’ also in area
to transfer person to platform. BHN Platform was built by J Ray
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE18
BHN COMPLEX
McDermott in Dubai and installed in working season 1980 - 81 under EIL
supervision. ONGC’s Insurance is covered by India’s United India
Insurance Company, re-insured with ACE, AIG and Zurich.
CRISIS ON OFFSHORE CONSTRUCTED LOCATION
The story starts with the bad weather, and a
cook cutting his finger in the galley of MSV
Samudra Suraksha. This is a DP-2 Multi Support
Vessel working for ONGC. The Master of the vessel
asked for an emergency chopper to send the
injured man to Bombay for treatment (Medivac).
Due to the rough seas The Chopper (helicopter) could not land on the
helideck of the said vessel. Therefore BHN being the nearest installation
(platform) to where the vessel was working decided to have the man
picked up and Airlifted from there to send to the Hospital.
While delivering the injured man to the Platform. (This is usually an
everyday operation of transferring personnel by way of a "Personnel
Basket" in the offshore oilfield), the vessel has to approach under the
crane of the Rig/ Platform and Persons will be lifted from the deck in a
conical shaped basket with the help of a crane.
Due to the High Seas at that time. Master of the vessel lost control; the
vessel was NOT on Dynamic Positioning system - This system keeps the
vessel at a fixed heading and holds position in high seas and strong
currents). The vessel’s Helideck hits the Platform’s Topsides, in the
process rupturing Aviation Turbine Fuel (ATF) lines; also, the vessel’s
hull-side hits gas pipeline (Riser). The Riser as well as ATF lines broke
and gas got mixed with the Air and due to metal-to-metal impact, spark
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE19
caused the gas to ignite. Explosions took place simultaneously igniting
the BHN platform and the MSV Suraksha.
People on board the platform and the drilling rig jumped into the water
in groups of 4 after wearing life jackets. Majority of the people from BHN
platform rushed to the bridge connected MNW platform. Some took
to life rafts that were available. There were about 7 or 8 Supply vessels
on the scene.
Total persons on board BHN Complex (BHN + NF + MNW + NA) were
227, on the MSV Suraksha 84 and the Rig Noble Charlie Yester 73 a
Total of 384 persons.
The MSV had 6 divers who were in the compression chamber at the time
of the accident; they went through decompression with the help of MSV
Samudra Prabha (another ONGC owned DP 2 vessel) and brought to
surface. ONGC’s OSV Sindhu-7 later on towed MSV Samudra Suraksha
but before reaching Mumbai, about 8 nautical miles from shore,
Samudra Suraksha also sank.
Final Outcome:
BHN platform destroyed.
NF Platform Topsides substantially damaged.
NA Platform only surface painting damage.
Noble Charlie Yester (NCY) rig minimal damage.
A Helicopter at BHN also destroyed in the fire.
MSV Suraksha sank.
22 persons died (11 confirmed + 11 missing
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE20
RECOVERY FROM CRISIS
A Committee has been formed by ONGC for investigation, comprising of
Mr. S.K. Manglik - Ex Chairman Of ONGC
Mr. H. S. Cheema - Ex Chairman Of Gas Authority of India
Mr. Ishwari Dutt - Ex Technical Director Of ONGC
ONGC’s immediate priority is to augment production from the Mumbai
High North Field. This to be initiated in several phases. Keeping this in
mind, ONGC have invited Expression Of Interest (EOI) as under:
- Wreck removal
- Charter Hire of FPSO
- Charter Hire of DP-2 MSV
This is part of ONGC’s Re-construction plan in phases broadly as under:
Short Term (1 to 2 months)
Revival of lift gas to MH South Well Platforms,
Resumption of production from NQ complex,
Diversion of well platforms of BHN to NQO / MH South.
Medium Term (6 to 12 months)
Laying of new pipelines to connect additional well platforms of
BHN,
Revival of well platforms connected to NA processing facilities,
Using FPSO for immediate revival,
Using an EPS near NA,
Commissioning of NA, BHF & MNW
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE21
Long Term (2 years+)
Construction of new surface facilities
CONCLUSION
After due to deliberations and exploring possibilities for resumption of
hydrocarbon production from Mumbai High North field, it emerged that
attention needs be given in phased revival based on use of existing
facilities, installation of new facilities and probable time required for
modification jobs. Committee came to a conclusion that around 70% of
the affected production can be revived in about 4 weeks time, additional
6-7% can be revived by the end of Sept. ’05. Committee also concluded
that all the affected wells can be put back on production in about 6
month time. However, these may not produce optimally because of
increased back-pressure which some of the wells would face on account
of improper well fluid and gas lift line size.
ONGC’S management take important decision on reconstruction of
platform after the one week they float the tender on market and they
divide work in two parts and they give the contract to two different
company therefore they reconstruct the plat form with in the one year.
this all possible because of active management and management
person.
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE22
CONCLUSION
ADVANSED TECHNOLOGY IN OFFSHORE CONSTRUCTION
In anticipation of increased activity by the
major oil companies in deep and ultra-deep
water, in particular in the South Atlantic, SBM
Has entered into a joint venture with the
Norwegian company Sol’s tad Shipping AS for a
new generation deepwater offshore construction and installation vessel,
placing a contract for the ship with the Ulstein Shipyard in Norway.
Boa Deep C ( worlds largest offshore construction vessel) -
Completed sea trials in mid-May and has since mobilized to begin work
on the Snohvit project in the North Sea. The ship's first project is being
undertaken in a joint venture with Acer Marine Contractors (AMC),
directly after which, the vessel will move on directly to the Kristin
project, where she will install moorings and manifolds .
In every respect a unique vessel, Boa Deep C is designed to carry
out subset construction work at great depths - up to 2000m - and makes
her owner, Boa Taubatkompaniet, a leading contractor in the offshore
construction marketplace, able to undertake sub sea installations,
mooring system and pipeline repairs, and template and anchor pattern
installations anywhere in the world, at depths
of up to 2000m.
Built in China at Jin Ling shipyard, and outfitted in Spain at
Factorias Vulcano shipyard, Boa Deep C is 120m overall and has a beam
of 27m, and was designed by Vik- Sandvik, the well-known Norwegian
naval architects. With a large deck area, a high deck
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE23
loading capacity, deepwater 250tonne and 300tonne heave-
compensated cranes, a deepwater winch with a 500tonne line pull and
extensive accommodation, Boa Deep C also boats twin built-in
deepwater ROVs, and a 7.2m x 7.2m moon pool, a stern roller designed
for a downward pull of 750tonnes, and has a bollard pull of in excess of
260tonnes.
A very interesting feature of Boa Deep C is propulsion machinery
designed to operate in three modes according to operational
requirements, these being diesel-mechanical, for steaming; diesel
electric for use in DP mode; or diesel mechanical with electric booster
for maximum power in 'bollard-pull mode.’
The machinery is based on six Caterpillar 3600 engines: a pair of V16-
cylinder units on the main shafts, and two eight cylinder and two six
cylinder models used as genset drives. Each of the two Caterpillar
3616TA engines is rated at 6000kW (8160hp) and drives a Scana Volda
four-bladed 4.4m-diameter CP propeller in a nozzle via a Scana Volda
ACG1080 gearbox, the direct-drive arrangement being used when
steaming. For maximum bollard pull, power on each shaft can be
boosted by 3000Kw from a Siemens combined PTI/PTO (electric
motor/shaft alternator).
A diesel-electric mode is used for DP operations, and positioning
requirements are met by four 1425kW Brunvoll FU-80-LTC tunnel
thrusters (two aft and two forward) and a 1200kW Brunvoll AR-80-LNC
retractable azimuth thruster located abaft the forward bow thrusters.
These thrusters are variable pitch and controllable speed, which allows
the optimization of power and fuel consumption and noise reduction
when operating in a DP 3 mode.
CASE STUDY
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE24
OFFSHORE HOOK-UP AND CONSTRUCTION SERVICES
OFFSHORE HOOK-UP AND CONSTRUCTION
SERVICES
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE25
INTRODUCTION:
Offshore Hook-Up And Construction Services ( India ) pvt. Ltd.,or
O.H.C.S.,as it is widely known, has been surviving the offshore oil & gas
industry, since its inspection, in the year 1981. it has since then been
providing design, engineering , fabrication , offshore installation , hook –
up , pre-commissioning , commissioning services to a cross – selection
of clients for a number of major offshore projects. OHCS clients include
all major world players in the offshore industry.
Offshore Hook-up and Construction Services (India) Pvt. Ltd.
(OHCS) is Engineering and Construction Company established in 1981.
Since inception, the Company has been involved with the Indian
Offshore Industry. The Company's main activities include Design, Detail
Engineering, Fabrication, Construction, Installation, Hook-up, Pre-
commissioning and Commissioning for new as well as existing facilities.
Areas of specialization include Offshore Projects involving new well
platforms, process platforms and extensive modification and hook-up
works on major existing offshore complexes
In addition to its participation in major offshore projects within
India, OHCS has crossed national boundaries and participated in
projects overseas. This continues to be one of out thrust areas.
Over the years, OHCS has evolved tested management systems and
has been successfully applying them to timely realize its tasks. We have
also been successful in developing a creative team of highly qualified
Project Managers and Discipline Engineers with a wealth of offshore
experience.
OHCS complies with specifications laid down by many of its well
known Clients / third party inspectors such as ONGCL, EIL, DNV to name
a few. Projects are normally carried out under OHCS's own Quality
Assurance System which, where necessary, can be further _______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE26
supplemented with specific project requirements or other specified
standards. OHCS Project
Managers constantly ensure compliance to Contract Specifications,
execute and monitor the projects using the latest application software
for Quality Control, Planning, Designing, Testing and Inspection, etc.
OHCS uses Computer Aided Design and Drafting techniques for its
projects. In-house facilities include adequately experienced personnel,
computing hardware and application software. Besides these facilities,
OHCS has a well equipped library providing necessary technical support.
In the light of its fulfillment of customer requirements with quality as the
prime objective, O.H.C.S. has earned the prestigious award of ISO
9001: 2000 Certificate. O.H.C.S. is serving a number of offshore clients.
Clients include reputed multinational companies from India and abroad.
OHCS, with its progressive outlook and tight schedule control is
recognized for prompt mobilization and swift execution. The Company
believes in elaborate planning, proper mobilization, optimum utilization
of manpower and effective schedule control maintaining strict
compliance to quality requirements.
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE27
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE28
ISO 9000: 2001_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE29
QUALITY POLICY
Offshore Hook-Up And Construction service (India)PVT . LTD.
IS Committed To Comply With The Customer ‘S Requirement By
Providing Timely And Efficient Service In Field Of Fabrication ,
Installation , Testing , Pre-Commencing , Commencing , And
Adopting Suitable Measures For Continual Improvement Of The
Effectiveness Of The Quality Management System
DESIGN & DETAIL ENGINEERING
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE30
OHCS's engineering team provides design, engineering and project
management services. It has in-house experience and expertise to
provide the aforesaid services for the disciplines of process,
instrumentation, piping, structural and electrical including inter-
disciplinary co-ordination for the Offshore Projects in particular and
other process industry in general. The design engineering team
specializes in providing detail engineering for major Re-design,
Revamping and Refurbishing works on the existing facilities at offshore.
With its participation in such projects, OHCS has systematically
compiled a library of 'As-Built' statistics and drawings and thus
commands a unique position as an engineering services agency.
Infrastructural support and facilities for Designing through drafting as
well as Computer Aided Designing are all available in-house.
It engineers support the client to liaise with the Client/Third Party
Inspectors/Vendors etc. during every facet of Detail Engineering also
assisting the client with various inputs required by them during the
Bidding/Proposal stage.
OHCS has a total commitment to engineering excellence, a knack
of finding the most creative design solutions to handle contingencies at
site and an uncompromising approach to quality. OHCS recognizes the
benefits of an effective Quality Assurance Programme in promoting and
achieving high Quality Standards of service and minimising costs &
delays to project schedules,
PLANNING
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE31
Planning is an on-going process for each project. Planning is project
based and commences at the time of Bidding when a schedule is
prepared for the entire Project.
OFFSHORE PLANNING
Prior to the commencement of offshore activities, OHCS undertakes
the planning of the offshore works in order to prepare itself for the work.
The following activities are planned :
Micro schedule of project with Primavera P3/MS Projects software.
Mobilization plan for Manpower / Construction Equipment.
Man hours estimation by trade.
Preparation of execution related procedures.
Preparation of S-curves for project progress planning / monitoring.
Preparation of Fabrication Drawings from Engineering Drawings.
Quantification of scope of work from AFC Drawings.
The work activity description cards or job cards are prepared one for
each scheduled activities. It defines the nature of required job,
materials required, description of tasks involved, estimated job duration
& manpower. The work activities defined at the planning stage include
not only the scheduled offshore works but also the onshore fabrication
works.
SUPPORT ACTIVITIES
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE32
While the planning exercise is in progress, OHCS will be developing its
land based support programme preparation for the offshore work. The
logistics of personnel and material form an important link between
office and offshore. Once the hook-up is in progress, the base will be the
focus of the project for technical, logistics and communication support.
PROCUREMENT
OHCS provides integrated procurement services commencing from
preparation of Request For Quotations (RFQ), to Technical specification,
identification of vendors, floating bids, evaluating bids, preparation of
purchase specification for procurement and release of Purchase Orders
to the technically acceptable vendors.
RFQ'S are generally developed as per Client's Bid Specifications duly
supplemented with engineering inputs. Enquiries are solicited from
approved vendors and technical evaluations of the proposals made and
Client's approval sought for the recommended vendors.
Depending on the scope of work entrusted to OHCS, Purchase Order is
released by OHCS or by the Clients. Pursuant to this activity, regular
Purchase Order specifications are issued to facilitate vendor compliance,
develop documents in accordance with requirements and fulfill
inspection requirements and Third Party obligations.
FABRICATION
OHCS has two fully equipped Workshops with Customs Bonded
Warehouse & In bond Manufacturing Facilities to undertake extensive
fabrication work both at Onshore in its workshop and at offshore while _______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE33
executing installation works. The workshop is equipped with the most
modern construction equipments, machines and fabrication facilities.
OHCS has independently developed various fabrication procedures and
welding procedures complying with bid specifications. These have been
duly approved by third party inspectors namely DNV, EIL, EICA, LRS, BV,
etc. for compliance with bid technical requirements. OHCS has an
experienced team of qualified welders duly vetted by various
consultants, like the ones mentioned above.
OHCS documentation work and qualification work in this respect cover
all materials from Carbon Steel to the most exotic materials known in
the process industry, viz. DSS, INCOLOY, INCOLOY CLAD,Cu-Ni, etc.
Fabrication is carried out as per AFC drawings and Client's Bid
Specifications with respect to tolerances and quality of work. All
consumables comply with technical specifications and compatibility with
the parent materials. An independent in-house QA / QC system ensures
fabrication standards of the highest quality. Third party inspection
requirements are duly adhered to. With prior Quality Management
effectively implemented, OHCS has seldom encountered any noticeable
rejection or re-work needs.
FABRICATION FACILITIES
Workshop I (W168 – 50000 Sq.ft.) : (Custom Bonded Warehousing
Facilities) : Well equipped workshop with 250 HP Power & two
Overhead Cranes of Capacity 25/5 tons each and span of 14 meters
each to provide upto 300T per month of Steel fabrication and 3000 inch
dia of Pipe Welding of various material such as Cu-Ni, Incoloy DSS and
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE34
Cladded pipes etc. Also fabrication of Pressure Vessels (medium range)
can be undertaken.
Workshop II (W175 – 7500 Sq.ft) : Well equipped workshop with
Power, Overhead Gantry, etc. to provide upto 100T per month of Steel
fabrication and 2000 inch dia of CS Piping.
INSTALLATION, HOOK-UP, TESTING, PRE-COMMISSIONING
AND COMMISSIONING
OHCS has the requisite expertise in installation of Equipments, Piping,
Instrumentation, Electrical & Structural works connected with Oil / Gas
Production Platforms.
OHCS has also undertaken major Hook-up / Testing and Pre-
commissioning works for various major International Contractors.
In this key area of work, OHCS's capabilities emanate from a very close
collaboration between Construction & Engineering personnel whose
backgrounds combine to provide the speedy solution to problems
frequently encountered in offshore projects Fine details such as general
equipment redundancy, installation aids, backup tooling, skilled floating
manpower, further enhance work capabilities. OHCS's successful track
record is the result of the interactive approach of its team to offshore
projects from planning stage to commissioning.
OHCS offers assistance during Installation to Client by Providing
support services and skilled manpower for the following :
Jacket Installation
Topside Modules Installation
Piles Installation
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE35
Riser Installation
Riser Clamp Installation
Removal of Temporary Decks
Stabbing new Decks
Installation of accessories like :
(1)Boat Landing
(2)Barge Bumpers
(3)Deck Cranes etc.
Stripping of Wells and Provision of Bullets during Installation
Pipe laying Mode
PRE-COMMISSIONING
OHCS offers complete spectrum of activities involving pre-
commissioning related works . OHCS engineers check :
Whether the works carried out are in line with P & ID’s
Assist in inert gas purging , drying etc. prior to flow of
hydrocarbons.
Some of the other activities include : pre – commissioning of
equipments :
Cranes
Fire water pumps
Diesel generator
Instrument air compressor
Pumps
Vessel
Pre – commissioning of electrical / instrumentation systems :
Switchgears
Panels
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE36
Simulation of interlocks
Relay settings
Loop checks
Set point check etc
Distribution
Motors
Rotation
Calibration
Continuity checks
Disciplines :
Multi disciplinary engineers drawn from OHCS ‘s commissioning team
assist client / owner & inspectors in these activities involving :
Process
Instrumentation
Piping
Mechanical
Electrical
COMMISSIONING
Commissioning of the facilities in general is carried out by the owner
and pertain to introduction of hydrocarbon after the whole system has
been simulated in pre commissioning checks
OHCS’s role in these activities is limited to assist the main contractor /
owner in these activities as follows :
Co-ordination / logistics with various vendors.
Keeping a check on all parameters during 72 hrs test run as per
consultant / owner checklist by providing professional personnel.
Preparation of as- built documents.
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE37
Preparation of list / replacement list for spare parts viz. chemicals,
lube charges, gaskets, fuses, etc.
MAINTENANCE
OHCS is well knit with experienced personnel to provide regular
maintenance required at offshore platforms. The team has invaluable
know-how and experience in the preventive maintenance of major
equipments on platforms.
OHCS has undertaken critical maintenance works for ONGCL at very
short mobilisation notice, at times when there has been a rupture/leak
in Oil / Gas lines or other platform facilities.
Various other services offered by OHCS are :
Supply of special Construction Equipment and Material.
Supply of skilled / semi-skilled manpower.
QUALITY CONTROL, INSPECTION,TESTING & CALIBRATION
OHCS has an independent Quality control Department with state of
the art equipments for carrying out activities like Welder Tests, all Non-
Destructive Tests, Physical & Chemical Tests, Equipment Calibration as
per latest International Standards, as a back-up to reinforce its
construction activities.
The main activities of the Quality Control Department include :
Maintaining Quality Standards for the Organisation as per ISO:9001-
2000.
Preparation of Quality Plans based on International codes and
Standards, in line with requirements of job specifications.
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE38
Quality Control at all stages, namely material receipt, in-process &
final inspection, including liaison with Third Party Inspectors like
DNV, EIL, LR, BV, etc.
OHCS has been providing Quality Assurance to it’s Clients/Customers
from the very beginning which has been highlighted by the fact that
OHCS is the first Offshore Company in India having ISO-9001:2000
Certificate.
OHCS is the only Company which through it’s Sister concern OFFSHORE
TESTING & INSPECTION SERVICES (full fledge Laboratory) holds ALL
essential equipment’s required for effective Quality Control at all stages
of the Project.
OHCS has an independent Quality Control Dept. with all important
Master Calibration Instruments [traceable to National / International
Standards], Welding Procedures for all important alloys duly approved
by 3rd Party Inspectors and NDT facilities available in-house. Services
offered by OHCS as a backup to reinforce it’s Construction activities also
includes:
Preparation of Welding Procedure Specification and conducting
Procedure Qualification Test under 3rd Party Inspection Agency.
Conducting Welder Performance Tests for Client / Customer under
reputed 3rd Party Inspection agencies viz. DNV, ABS, EIL etc.
Calibration of Instruments
Quality Control at all stages of Hook-up / Modification.
Inspection of Customer Supplied Products w.r.t. Purchase
Specifications, approved Drawings & Documents for Client /
Customer.
It’s QA/QC Engineers are totally familiar with the following
Codes, Standards & Specifications :
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE39
API (American Petroleum Institute) Standard
ASME (American Society of Mechanical Engineers) Codes
DNV (Det Norske Veritas) Offshore Rules & Recommended
Practices
ANSI (American National Standard Institution) Standards
ABS (American Bureau of Shipping) Rules
HEALTH SAFETY & ENVIRONMENTAL PLAN
OHCS recognizes the importance of protecting the Health, the Safety
and the Environment during its Operations. Therefore, it is OHCS’s
intention to pro-actively work with Employees, Clients, Subcontractors,
Public and Government Agencies in order to achieve the highest
possible standards of Health, Safety and Environmental protection,
sustaining individual awareness of safety issues.
The objectives to which OHCS assigns the greatest importance
are :-
The prevention of exposure to risk in all areas of its operations on
the basis that all accidents are preventable.
Compliance with relevant legislation and the application of more
stringent standards where OHCS considers it appropriate.
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE40
The protection of the Health of its employees and of those who
may be affected by its operations.
The prevention of damage to the environment that could be
caused by its operation.
OHCS seeks to achieve these objectives by :-
Ensuring an appropriate level of employee training in relation to
Health, Safety and Environmental Protection in all areas of its
operations.
The use of an effective two-ways communication system for all
Health, Safety and Environment issues.
Providing adequate human, technical and financial resources.
Clearly defining the duties and responsibilities of all employees
with regards to HSE.
Continually improving its Health, Safety and Environment
Management System by firm management principles in line with
current industry standards.
HEALTH, SAFETY & ENVIRONMENT POLICY
OFFSHORE HOOK-UP AND CONSTRUCTION SERVICES (INDIA)
PVT. LTD. SHALL FOLLOW APPLICABLE LAWS AND RELEVANT
INDUSTRY STANDARDS OF PRACTICE CONCERNING PROTECTION
OF HEALTH AND SAFETY OF ITS EMPLOYEES IN THE
WORK PLACE AND THE PROTECTION OF THE ENVIRONMENT
WHICH WILL BE THE COMPANY’S PRIMARY GOAL TO TAKE SUCH
ACTIONS AS REASONABLE AND NECESSARY TO ACHIEVE SUCH
GOAL AND CARRY OUT THIS POLICY
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE41
TURNOVER OF OHCS (I) PVT. LTD.
5.92
11.47
22.7121.84
18.10
0
5
10
15
20
25
20
01
-20
02
20
02
-20
03
20
03
-20
04
20
04
-20
05
20
05
-20
06
YEAR
TU
RN
OV
ER
T/O inCrs.
Growth rate of OHCS
TURNOVER TABEL OF O.H.C.S.
As per the above chart from 2001 to 2003-2004 the company
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE
Sr no Year Turn over in crs.
1 March-01 – March 02 5.92
2 March-02 – March 03 11.47
3 March-03 - March-04 22.71
4 March-04 - March-05 21.84
5 March-05 – March 06 18.1
42
may rapid progress with its turnover rising from 5.92 crs. In
2001-02 to 22.71 crs. In 2003-04 but later on turn over decline
18.10 crs. In 2005-2006 because of non availability or
unavailability of contract.
LIST OF MAJOR PROJECTS EXECUTED BY OHCS
Sr No
Period Client Project Nature Of Work
1 Aug 03-May 04
Hyundai Heavy Industries Co. Ltd – South Korea
MHB – PL PROJECT
Pre Fabrication Of Piping Spools / Structural DeckExtension For Top Side Modification At Seven Plat Forms Execution Of Works At Offshore & Riser Tie-Ins At 14 Location
2 Dec 03-Mar 04
Hyundai Heavy Industries Co. Ltd – South Korea
GA Hook- Up Hook – Up Of New 4 Legged Project Well Platform GA & Modification Of Existing Facilities At “ LA ” Platform For CEIL / Lamprell Energy Ltd.
3 Jul 03- Oct 03 Hyundai Heavy Industries Co. Ltd – South Korea
Block 5 Dev Project
Hook – Up And Modification Works On 4 Compressors Modules , 3 Quarters , 3 Wellhead Platforms , 3 Flare Decks , 1 Water Injection Platforms ( 14 Modules ) And Six Inter Connection Bridges At Al Shaheen Field Of Maersk Oil Qatar As
4 Jun02 – Dec03
Oil & Natural Gas Corporation Ltd. – INDIA
F.G. Skid Replacement
Design , Engineering , Supply , Installation , Demolition Of Existing F.G. Skid At SHP / SHQ Platform
5 Apr 02-Apr 03
J . Ray Mcdermott Eastern Hemisphere Ltd. - Dubai
N11- N12 Platform Project
Fabrication Of Spool Pipe , Support Deck Extension And Associated Modification
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE43
Of Existing Facilities On 18 Platform And Hook – Up Of 2 New Platforms.
6 Apr02-May02 Hyundai Heavy Industries Co. Ltd – South Korea
LA/LB Platform Project
Hook-Up Of Topside FacilitiesFor LA/LB Platform
Sr No Period Client Project Nature Of Work
7 Jan 02 – Apr 02 Larsen & toubro ltd - INDIA ACM-HRC
Installation Of Additional Compressor Module At HRC Platform And Its Integration With The Systems
8 Nov 00- may01 Hyundai Heavy Industries Co. Ltd – South Korea
WIPRP- 1 Project
Onshore fabrication of riser clamps / pipe spools and modification of 13 platforms at offshore
9 Dec 99 – may 00 Kvaemer energy ltd - U.K. TG revamp at
SLQ
3 x LM 2500 TG revamping at SLQ / BHS Bombay High
10 Sep 99 - oct 99 Brown & root energy services –SINGAPORE
NF riser replacement project
Replacement of 30 ( oil ) and 26( gas ) raiser at NF platform Bombay high
11 Oct 99-dce99 Mazagon docks ltd - INDIA BHN-RP project
Fabrication & welding of C.S. / SS/ pipe spools / piping for HHN revamping project of ONGCL under bonded warehouse of OHCS total fabrication was approx. 20000 dia .
12 Dec 98-Apr 99 Hyundai Heavy Industries Co. Ltd – South Korea BCP-B project
Modification of BPB / BLQ – II and hook-up of BCP-B platform
13 Feb 98- May 99 Larsen & toubro ltd - INDIAHRC AND modfns. Hook-up
Modification at HA,HRA, HRG & WIH platform and hook-up of HRC platform
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE44
14 Feb 98 – May 98 Subtect middle east – SHARJAH
Clamp on conductor project
Provision of additional conductors on seven existing platforms in Bombay high north field
LIST OF PROJECTS EXECUTED AS ON 30 TH JUNE 2005
Sr No
Period Client Project Nature Of Work
1 Jun04 – may05 Saipem S.P.A. – ITALY Sabrata Platform Project
Hook-up of one well cum process platform, living quarter , flare deck for saipem S.P.A. ( Italy ),
2 Aug04- Nov04Hyundai Heavy Industries Co. Ltd – South Korea
MUT-PL project
Modification & fabrication of existing facilities BCPA,SHP,SHG,ICP,NQP &MNW platform & fabrication of riser clamps
3 Dec 04 – may 05Hyundai Heavy Industries Co. Ltd – South Korea
MSP project Hook-up pre-commissioning ,commissioning of new MSP platform
4 Aug03-may04Hyundai Heavy Industries Co. Ltd – South Korea
MHB-PL project
Pre-fabrication of piping spool / structural deck extension for top side modification at seven platforms , execution works at offshore
5 Dec03-mar04 Hyundai Heavy Industries Co. Ltd – South Korea
GA Hook- Up
Hook – Up Of New 4 Legged Project Well Platform GA & Modification Of Existing Facilities At “ LA ” Platform For CEIL / Lamprell Energy Ltd.
6 Jul 03- Oct 03 Kvaemer energy ltd - U.K Block 5 Dev Project
Hook – Up And Modification Works On 4 Compressors Modules , 3 Quarters , 3 Wellhead Platforms , 3 Flare Decks , 1 Water Injection Platforms ( 14 Modules ) And Six Inter Connection Bridges At Al Shaheen Field Of Maersk Oil Qatar As
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE45
7 Jul 02 Bharat heavy electrical ltd –INDIA
Revamping of turbine ventilation system
Material procurement onshore duct fabrication of new ducting for BHN turbine ventilation system
8
Jun02 – Dec03 Oil & Natural Gas Corporation Ltd. – INDIA
F.G. Skid Replacement
Design , Engineering , Supply , Installation , Demolition Of Existing F.G. Skid At SHP / SHQ Platform
9
Apr 02-Apr 03 J . Ray Mcdermott Eastern Hemisphere Ltd. - Dubai
N11- N12 Platform Project
Fabrication Of Spool Pipe , Support Deck Extension And Associated ModificationOf Existing Facilities On 18 Platform And Hook – Up Of 2 New Platforms.
LIST OF MAJOR PROJECT EXECUTED BY OHCS
Sr No Client Project Nature Of Work
1Samsung heavy industries -
KOREA BE
Pre-engineering survey & detail engineering for
modification to platform under BE project
2Hyundai Heavy Industries Co.
Ltd – Korea SBHT
Pre-engineering survey & detail engineering for
electrical and instrumentation for
modification 2 platform under SBHT project
3National petroleum
construction company –ABU DHABI
SHG
Pre-engineering survey & detail engineering for
modification to existing facilities on 13 existing
platforms.
4 Oil & natural gas corporation ltd – INDIA
GLPM
Pre-engineering survey & detail engineering for
modification to existing facilities on NJ, N6, N3 , NH
platform
5 ETPM-FRANCE HUT
Pre-engineering survey & detail engineering for HRA
platform and URAN terminal modification to HUT project
6National petroleum
construction company –ABU HQRST-FPre-engineering survey &
detail engineering for
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE46
DHABI
modification to HA-HE platform under ONGC’S
HRQST-F platform
7 Snamprogretti – saipem – ITALY GLPN
Pre- engineering survey of 55 platforms at Bombay high
for incorporation of gas lift facility under ONGC’S GLPN
project
8 OTP / SOFRESID – FRANCE WIPPM
Pre-engineering survey & detail engineering for
modification to 11 platforms under ONGC’S WIPPM project
J. RAY Mc DERMOTT, INC.
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE47
J. RAY Mc DERMOTT, INC.
COMPANY PROFILE
J. Ray McDermott is a privately owned Oil & Gas Industry Construction
Company providing a range of products and services to the Industry,
Worldwide, ranging from General Fabrication, Engineering & Project
Management, Offshore Construction Services through to the supply of
Drilling Structures and Rebuilt Land Rigs, Rig Refurbishment etc
J. Ray McDermott is a leading worldwide marine solutions company with
fabrication facilities in the Americas, Middle East, Caspian and Asia
Pacific. Services include design, fabrication, transportation and
installation of offshore platforms, and installation of offshore pipelines.
JRM operates a diversified fleet of vessels for the marine construction
industry. Most of our primary vessels are combination derrick and lay
barges, making the fleet one of the most versatile in the world. Our
global fleet is located in the Gulf of Mexico, Asia Pacific, the Middle East,
and the Caspian
HISTORY
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE48
In the late 1940’s oil and gas companies began to realize the potential
of fields under the waters of the Gulf of Mexico. Technology made
offshore fields a primary source for the world’s petroleum. In the early
days of offshore production, facilities were placed in shallow water and
within sight of land. J. Ray McDermott had floating equipment for
marshland work, and as interest in the Gulf picked up, the company
formed joint ventures and made acquisitions that allowed it to pioneer
the construction and installation of platforms and pipelines to support
drilling and development near shore.
By the mid-1970’s, J. Ray McDermott was one of the world’s leading
marine contractors, providing services in every major offshore oil and
gas province. As offshore fields became a primary source for petroleum,
specialized equipment was developed to allow production in water
thousands of feet deep and many miles from land.
M I L E S T O N E S
1950 - Installed first all-concrete platform in Gulf of Mexico
1954 - Constructed first offshore platform in 100 m’ water depth
1956 - Established Morgan City yard, first fabrication facility dedicated
solely for offshore structures
1961 - First jacket installed by "Stacking" method - precursor of later
multi-piece jackets
1966 - Acquired diving company
1976 - Designed, provided fabrication technology for, and installed
Exxon’s record 850’, two-section Hondo platform off Santa Barbara, CA
1978 - Fabricated and installed first platform in water depth greater
than 1,000’. Shell Cognac (1040’ water depth) remains the world’s only
three-piece deep water structure and was recognized with an
achievement award by the American Society of Civil Engineers
1986 - Built Shear Leg Crane - lifting capacity of 5,000 short tons
1988 - Acquired dynamically positioned 4,400 short-ton capacity DB50,
world’s largest self-propelled monohull crane vessel
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE49
1989 - Installed deepest pipeline between Shell’s Bullwinkle and Boxer
platforms. The pipeline depth at Bullwinkle makes it deepest ever
installed in Gulf of Mexico - 1350’ water depth
1991 - Fabricated and installed world’s largest offshore sulfur extraction
complex for Freeport McMoran Resource Partners’ Main Pass mine
1993 - First use of J-Lay sets pipe-lay depth record in 2,860’ water
depth for Shell Auger project
1996 - Fabricated topsides and installed hull and deck for Oryx
Neptune, world’s first production spar
1997 - Completed modules for Shell’s Ursa, largest platform in the Gulf
of Mexico and the world’s deepest TLP in 4,000’ water depth
1998 - Installed the first Sea-Star "Mini-TLP, British-Borneo's Morpeth, in
1,200 ft. water depth
1999 - Completed British-Borneo's Allegheny Mini-TLP hull and deck
installation with associated design, procurement and installation of sub
sea pipelines and SCRs in 3,300 ft. water depth
2000 - Installed Shell Brutus pipelines, 16 miles of 20", which was the
deepest S-Lay pipeline in 3,010 ft. water depth
2000 - BP awards contract to construct the topsides for four of it's
deepwater projects in Gulf of Mexico
2001 - EPCI award of Murphy's Medusa Truss Spar - first Spar hull to be
built outside of Pori, Finland
2001 - EPCI award of Domion Resources Devil's Tower Spar
2002 - EPCI award of Murphy's Frontrunner Truss Spar
2002 - Wins sub sea development installation contract for BP Aspen
Project
2003 - 12,125 ton Amenam Kpono AMP1 production deck leaves Dubai
headed for the coast of Nigeria
2003 - P.T. McDermott Indonesia successfully completed fabrication of
the world's deepest dry-tree spar hull for the Devil's tower field in the
Gulf of Mexico
2003 - JRM completes deepwater Medusa Spar Project - the first spar
platform in the world delivered on a full scope engineer-procure-install-
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE50
construct ("EPIC") basis
2004 - JRM successfully completed Devils Tower and Front Runner EPCI
SparProjects
2004 - McDermott Caspian Contractors, Inc. (MCCI) completed
fabrication, load out and sail away of Central Azeri topsides, the largest
deck ever in the Caspian, consuming 10 million man-hours without a
single lost time accident and utilizing 80% local Azerbaijani workforce
2004 - P.T. McDermott Indonesia successfully completed fabrication,
integration and onshore mechanical completion of the Floating
Production, Storage and Offloading (FPSO) vessel - Belanak Natuna
2004 - JRM's Morgan City Yard completed three of four Deepwater
Development projects (Holstein, Mad Dog and Thunder Horse)
PLANNING
Planning is an on-going process for each project. Planning is project
based and commences at the time of Bidding when a schedule is
prepared for the entire Project.
OFFSHORE PLANNING
Prior to the commencement of offshore activities, JRM undertakes
the planning of the offshore works in order to prepare itself for the work.
The following activities are planned :
Micro schedule of project with Primavera P3/MS Projects software.
Mobilization plan for Manpower / Construction Equipment.
Man hours estimation by trade.
Preparation of execution related procedures.
Preparation of S-curves for project progress planning / monitoring.
Preparation of Fabrication Drawings from Engineering Drawings.
Quantification of scope of work from AFC Drawings.
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE51
The work activity description cards or job cards are prepared one for
each scheduled activities. It defines the nature of required job,
materials required, description of tasks involved, estimated job duration
& manpower. The work activities defined at the planning stage include
not only the scheduled offshore works but also the onshore fabrication
works.
FABRICATION
J. Ray McDermott (JRM) has fabrication locations in Batam, Dubai,
Harbor Island, and Morgan City.
JRM's fabrication yards are strategically positioned around the world to
service the oil and gas industry. Our fabrication yards are all qualified to
ISO 9000 standards, and each is capable of building to multiple industry
standards.
Although our fabrication bases are strategically placed to serve their
geographic regions, their cost-effective and high-quality products are
also exported to other regions of the world. We continue to provide
facilities to West Africa from both the United States and the Middle East,
and are poised to provide cost-effective fabrication services for Central
and South America from both locations
Working closely with our engineering groups as well as our marine
operations, JRM fabricators fully understand the project requirements of
both. That understanding helps knock down interface barriers, even
when another company performs the engineering or offshore installation
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE52
FACILITIES
JRM special area of work and interest has been the execution and
management of major modifications and refurbishments of existing
facilities on offshore well platforms and process complexes. With its
deep involvement in this work over the last decade and a half, JRM has
compiled well documented as-built data and drawings for almost all the
major Indian offshore platforms and projects with which it has been
associated along with other major International Contractors. This
provides the inherent strength and advantage to JRM in swiftly
executing all modification projects. Its capabilities and strengths in this
area have been fully recognised by all the major contractors who have
engaged and continue to engage its expertise for the total services of
modification and refurbishment work. This continues to be its major
forte.
Captive construction manpower employed by JRM acts as a nucleus on
which additional manpower is built, depending upon workload. The
Construction Division is headed by a Project Manager (Construction) and
assisted by a team of field engineers, workforce of various specialized
trades like welders, fitters, grinders, cutters, scaffolders, riggers,
mechanics, electricians, technicians, crane operators, logistic personnel
etc.
JRM has its offshore work team from senior, experienced marine
construction personnel up to supervisory level on a permanent basis.
The construction team is supported on the platform by project personnel
whose responsibilities are keyed to specific areas, systems and
disciplines. These personnel are linked to the craft supervisors and
establish priorities, interpret drawings, identify & rectify shortages, etc.
Within an area, various disciplines work simultaneously, however,
limited by safety considerations and reasonable access to the work.
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE53
JRM supervisory personnel and high level workers execute offshore
activities for platform topside works as per the planned schedules.
Services offered by JRM include Top side Hook-up / Modification of
Platform module with the following :
Piping Installation & Hook-up
Equipments Installation & Hook-up
Electrical / Instrumentation Installation & Hook-up
Internal revamping of Separators / Pressure Vessel
Structural Installation
Riser Tie-ins & associated modifications
Fire & Gas Detection System
MAINTENANCE
JRM is well knit with experienced personnel to provide regular
maintenance required at offshore platforms. The team has invaluable
know-how and experience in the preventive maintenance of major
equipments on platforms.
JRM has undertaken critical maintenance works for ONGCL at very short
mobilization notice, at times when there has been a rupture/leak in Oil /
Gas lines or other platform facilities.
Various other services offered by JRM are :
Supply of special Construction Equipment and Material.
Supply of skilled / semi-skilled manpower.
HEALTH & SAFETY ENVIRONMENT POLICY _______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE54
J. Ray McDermott, Inc. considers the protection of human Health, Safety,
and the Environment for all its employees, contractors, customers, and
the community to be of primary importance. As such the Company will
maintain a Health, Safety and Environmental (HSES) program
conforming to the best management practices of marine and
construction operations. The overall success of the HSES program is
based on the following:
Management commitment, planning, and accountability:
Management is responsible and accountable for protecting
employees, assets, and the environment in accordance with the
Company Charter and Philosophy. In addition, the prevention of
injuries, illnesses and pollution must be made a priority during
project planning, operations, maintenance and construction
activities.
Employee participation and accountability: Managers and
supervisors are accountable for the actions of their subordinates
and will always reinforce safe work behaviors. All employees are
responsible for stopping and reporting unsafe acts and conditions,
and for following Company HSES policies and procedures.
Compliance: The Company will comply with all applicable Health,
Safety & Environmental regulations, codes, and standards, and
will develop and enforce procedures that provide instruction to all
employees identifying their responsibilities for meeting or
exceeding these requirements.
Training : The Company will provide training to ensure
understanding of good HSES practices, Company procedures and
regulatory requirements.
Continuous Improvement : The Company will strive for
continuous improvement in its HSES performance through regular
measurement and review of its objectives, targets, programs,
procedures and processes. Managers, supervisors, employees,
contractors, customers, and vendors must work together to
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE55
develop proper attitudes, practice and promote proper work
habits, use good judgment, and comply with all applicable HSES
rules and regulations to ensure J. Ray McDermott, Inc. is a safe
and respectable environment in which to work.
QUALITY
JRM is an API approved company for the Design, Manufacture,
Repair, Upgrade, Installation and Decommissioning of Hoisting
Equipment and Drilling Structures; Provision of Rig Audits and
Inspection/Survey Services.
The company is dedicated to complete integrity of its operations and
services and this is reflected in the commitment to Quality .
The company has developed and implemented a Quality Management
System that complies with the requirements of both ISO 14001, OSHAS
18001 and ISM, provides a framework for all JRM Business Units
Project & operation committee
This committee deals with all matters relating to Projects and
Operations both onshore and offshore. The main aim is to establish
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE56
common objectives for the contracting community in project execution
and implementation. It works closely with the employment practices
committee and is responsible for the compilation of the projected
workload surveys that forecast resource requirements for the year
ahead. The predictions, coupled with those from the Employment
Practices Committee, give the association the facility to accurately
project future resource requirements.
The Committee also addresses new directives introduced by the
Dubai Union and legislation set out by the Government. The potential
impact of the recent Pressure Equipment Directive is typical of the items
tackled. A common contracting position is being established and there
will be discussions with other bodies to reach an industry-wide
consensus.
The committee will be focusing on working practices to see how
best to improve the methods in operation by members and others
in the industry.
HUMAN RESOURCE
J .Ray McDermott is a leading worldwide marine construction company.
Our services include design, fabrication, transportation, and installation
of new and refurbished offshore platforms, installation of offshore
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE57
pipelines, and design and installation of sub sea facilities for the
offshore oil and gas industry.
The diversity of our services reflects the company's commitment to
the world's energy future. The fulfillment of that commitment begins
with our employees. We offer not only the chance to play a key role in
solving the world's energy problems, but also a career opportunity with
a company that promotes from within and helps you grow to your fullest
potential.
P h i l o s o p h y
The success of J. Ray McDermott is dependent upon its employees. To
create and maintain a competitive advantage, J. Ray McDermott
requires a work force that is motivated, skilled, effectively led and
managed.
As such, we recognize the importance of quality employee programs for
recruiting, development, motivation and retention. With facilities
located around the world, we are committed to creating a challenging
and rewarding work environment for each facility whereby employees
are goal focused and motivated through these people oriented
programs.
Within J. Ray McDermott's Company Charter our values and guiding
principles describes how we conduct ourselves with colleagues, our
customers, vendors and communities as we go about accomplishing the
mission, vision and goals of our company.
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE58
J. Ray Mc Dermott Around The World
JRM located in many country also they got a construction contract from
many country. In India they got a contract from ONGC & Reliance. JRM is
one of biggest offshore construction company therefore they got a
contract from many country.
JRM located country are as follows :
Dubai
Batam
Jakarta
Morgan city
Harbor island
Singapore
Malaysia
India ( Mumbai only )
Perth
Houston
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE59
On Shore Job Execution Is Same Of Both Organizations Are As
Follows:
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE
FLOATING OF TENDER BY ONGCL & OTHER INTERNATIONAL COMPANIES
PROPOSAL
LETTER OF INTENT
DRAWING AND DOCUMENTS
PROJECT PLANNING
MATERIAL RECEPTION AND INSPECTION
QA / QC
MARKING & CUTTING
FIT UP
WELDING
NDT
GRIT BLASTING
60
PAINTING
PACKING
TRANSPORT TO OFFSHORE ETC.
ONSHORE JOB EXECUTION IN DETAIL (OHCS & J. Ray McDermott)
TENDER FLOATING BY OIL COMPANY
The Client or customer floats a tender in market which contains contract
and bid documents. These two further include commercial terms, technical
terms, scope of work and bid specification.
PROPOSAL
After studying the tender OHCS prepares a proposal. Proposal has two
aspects :
1. Technical : This includes :-
Scope of work
Terms and conditions
Background i.e. previous projects undertaken
Resources which include :
a. Manpower
b. Equipment
c. Organisation chart
d. Project Schedule
2. Commercial : All price related terms are included in this.
LETTER OF INTENT
The Contractor or the Sub Contractor who makes the lowest bid gets the
contract. The Client if directly gives the contract to a Company then, that
Company is a Contractor. The Contractor may grant parts of the project
further to some other Company. Then that Company becomes sub-
Contractor.
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE61
After contract has been given to the Contractor a letter of Intent or LOI is
given to it by the client. It includes a parameter called Liquidated
Damages (LD). If the Contractor fails to complete the job within the given
time the Client imposes LD on it. LD means that a certain percentage
(given in LOI) of money it is supposed to give to the Contractor would be
deducted per day after the allocated time period is over.
DRAWINGS AND DOCUMENTS
After contract copy is signed by Client and Contractor the Contractor is
given the drawings and documents for the project.
PROJECT PLANNING
Project planning is done by contract as to how to go by the project. It
includes parameters like :
Manpower mobilization i.e. when and how many workers should
be working on a particular aspect of the job.
Equipment
Project material
Project monitoring which is done to ensure whether the project is
being completed as per the given time. It is done using Daily
Progress Reports [DPR] and next day plans.
Job sequence
Micro schedules and activity breakup.
RECEPTION OF MATERIAL
Material received is of two kinds :
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE62
(a) Free issue material : It is the material that the Client gives to
Contractor.
(b) Self procured material : It is the material that the
Contractor itself has to arrange (is part
of lump sum cost).
INSPECTION OF MATERIAL
Inspection of material is done by the Third Party Agency. It checks
whether the grade and heat no. of the material matches with the Test
Certificate (TC). After the inspection is done material inspection report
(MIR) is prepared. This has to be signed by the Third Party Agency before
carrying out the project further. So if the material is as per code it is
approved by Third Party for fabrication.
QUALITY ASSURANCE / QUALITY CONTROL (QA / QC)
QA/QC means work procedure to be carried out to assure quality. This
includes :
a. Execution Procedure : Which includes micro schedules of
project. The whole activity is broken up into parts so that each
part can be completed within given time constraints with
expected quality.
b. Fabrication Procedure : Which includes methods to be used
for fabrication.
c. NDT Procedure : This includes methods of Non-destructive
Testing (NDT) to be used for evaluation of joints. The various
methods of NDT are Radiography, Ultrasonic Testing, Magnetic
Particle and Dye Penetrate Inspection.
The documents of the QA/QC are submitted to the Client for approval.
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE63
MARKING AND CUTTING
After material is approved for fabrication grinding of pipes and fittings is
done to make the surface smooth. Bevel preparation should as per degree.
FIT UP
The fit up of pipes before welding is witnessed by the Third Party Agency.
It checks where the orientation is as per drawing or not, ID of the material
and whether the gap between the fit up is accurate or not. A fit up report
is prepared which has to be signed by the Third Party Agency.
WELDING
Two types of welding are generally done for pipes.
(a) Gas Tungsten Arc Welding [GTAW] : It is a welding process that
uses a non-consumable tungsten electrode to produce the weld. The weld
area is protected from atmospheric contamination by a shielding gas
usually an inert gas such as argon and a filler metal is normally used,
though some welds, known as autogenous welds don’t require it. A
constant current welding power supply produces energy which is
conducted across the arc through a column of highly ionized gas and metal
vapours known as Plasma.
This process grants the operator greater control over the weld than SMAW
or Submerged Metal Arc Welding allowing for stronger, higher quality
welds. However, GTAW is more complex and difficult to master and further
more it is significantly slower than other welding techniques. This welding
has fewer defects then SMAW because of inert gas.
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE64
(b) Shielded Metal Arc Welding [SMAW] : It is also known as manual
metal arc (MMA) welding or informally as stick welding is a manual arc
welding process that uses a consumable electrode coated in flux to lay the
weld. A electric current in the form of either AC or DC from a welding
power supply is used to form an electric arc between the electrode and
metals to be joined. As the weld is laid, the flux coating of electrode
disintegrates, giving off vapours that serve as shielding gas and providing
a layer of slag, both of which protect the weld area from atmospheric
contamination.
Because of the versatility of the process and simplicity of its equipment
and operation, SMAW is a very popular welding process. It dominates
other welding processes in the maintenance and repair industry. SMAW
continues to be used extensively in construction of steel structures and
industrial fabrication. The process is primarily used to weld iron and steel
(including stainless steel) but aluminum, nickel and copper alloys can also
be welded with this method.
In piping a combination of GTAW and SMAW is used. GTAW is used for
making root and hot pass and SMAW is used for filling and capping.
PAINTING
Within 2 hours of Grit blasting a primer coat of Zinc silicate of thickness 40
– 50µ is applied. It is a preparatory coating put on materials before
painting. Primary insures better adhesion of paint to the surface, increases
paint durability and provides additional protection for the material being
painted.
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE65
After priming at least 8 hrs should be given to the material before applying
first coat of paint. Its thickness should be around 75µ. After yet another
12 hrs second coat of paint is applied. This also must have a thickness of
75µ.
After painting is done the coat is checked by the Third Party Agency using
a coat meter. The thickness should come around 300µ.
A painting report is prepared which is signed by Third Party Agency.
PACKING
After painting report is cleared the product is finished. The product is
packed in respective box, container, rack etc. depending upon size,
material and use . Packing list is prepared and product is put in respective
package. After this inspection of product is done as per packing list and
then packed items are stored in a safe area. Water contact is avoided.
TRANSPORTATION :
After the packaging the final product packages are transported at offshore
construction area by ship because these final products are very heavy
therefore the product packages are transfer by use of water transportation.
CONCLUSION:
Both the industry are well reputed in the world because of there
construction work. Some times J RAY McDermott given the contract to
OHCS so we see that they have a good business relation. Both
company’s are tack care of there employees. They play important role
in successes of country economic growth. Both the company have the
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE66
domestic as well as international client. They have a similar working
strategy.
BIBLIOGRAPHY:
Books:
Production Technology 1 & 2, By Mr. O.P. Khanna
Website:
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE67
www.google.com
www.altavista.com
www.jraymcdomott.com
www.ohcs.com
www.hook-upoffshore.com
_______________________________________________________________________________________________________
OFFSHORE CONSTRUCTION INDUSTRY, RAPCCE68