GENERAL DAILY REPORT
ENG 7 ENG 8Drain water out of radiator Removal of cylinder head coversDrain water out of water jacket Removal of injector pump linksClose air supply lines Removal of rocker arms and tappetsClose expansion tank inlet valves Removal of fuel high pressure pipes
01/08/11
02/08/11
ENG 7 ENG 8Removal of injector & injector pump links Removal of cylinder heads from A bank
(1-9)& B-bank (1-2)Removal of rocker arms, tappets and push rods
Removal of intake manifold
Removal of intake manifoldRemoval of injector valves
03/08/11
ENG 7 ENG 8Removal of cylinder heads from A bank (1-9) Removal of cylinder heads from B bank ( 1-2)Removal of cylinder heads from B bank (1-2) Removal of intake and exhaust valves (A1-A7)
Removal of injector valvesRemoval of rocker arms, tappets and push rodsremoval of injector pump links& high-pressure fuel pipes
04/08/11
ENG 7 ENG 8Removal of cylinder heads from B bank (3-9) Removal of cylinder heads from B bank ( 3-9)Cleaning of cylinder heads Cleaning of cylinder headsRemoval of intake & exhaust valves Removal of intake & exhaust valves
05/08/11
ENG 7 ENG 8Cleaning of cylinder heads continued Cleaning of cylinder heads continuedCleaning of intake & exhaust valves Cleaning of intake & exhaust valves
1
06/08/11
ENG 7 ENG 8Cleaning of cylinder heads continued Cleaning of cylinder heads continuedCleaning of intake & exhaust valves continued Cleaning of intake & exhaust valves completed
Grinding of valves
08/08/11
ENG 7 ENG 8Cleaning of cylinder heads continued Cleaning of cylinder heads continuedCleaning of intake & exhaust valves continued Cleaning of intake & exhaust valves completed
Grinding of intake & exhaust valves continuedGrinding of valve seats
Dismantling and cleaning of HFO separator bowls (1&2)Measurement of valve stem
09/08/11
ENG 7 ENG 8Cleaning of cylinder heads completed Cleaning of cylinder heads completedCleaning of valves completed Grinding of intake & exhaust valves continued
Grinding of intake & exhaust valve seats continued
Cleaning of HFO separator 1&2 completedMeasurement of valve stem continued
10/08/11
ENG 7 ENG 8Valve grinding continues Valve grinding continuesDismantling and cleaning of Lube Oil Separators Valve seats grinding continues
Inspection of turbo charger (OK)Testing of fuel injector nozzle pressure completed
Dismantling and cleaning of Lube Oil Separators
HFO separator 1 completely assembledMeasurement of valve stem continued
2
11/08/11
ENG 7 ENG 8Valve grinding continues Dismantling & cleaning of injector nozzles (A1-
A7)Lube Oil Separator dismantled and cleaning continued
Assembly of Lube Oil Separators
Valve seats grinding continuedTesting of fuel injector nozzle pressure completed – before servicingRemoval of firing rings (A1-A9)
HFO separator 2 completely assembledMeasurement of valve stem continued
12/08/11
ENG 7 ENG 8Dismantling& cleaning of injector valves Dismantling of injector nozzles (A8-A9)Lube Oil Separator dismantled and cleaning completely assembled
Grinding of exhaust valve seats continued
Piston crowns cleaned& liners continuedMeasurement of valve stem continued
Measurement of valve seatsmeasurement of valve thickness
Stand-by lube oil separator cleaned and assembled
13/08/11
ENG 7 ENG 8Dismantling& cleaning of injector valves Dismantling & cleaning of injector nozzles
completedNew O-rings & injector nozzles assembled Grinding of exhaust valve seats continuedPressure testing of injector nozzles after servicing completed
Grinding of exhaust valves continued
* Combustion ring cracked -A8*One injector valve spring was found broken when dismantling -B5
Dismantling and cleaning of primary and secondary filtersMeasurement of valve stem continuedMeasurement of valve seats continued
Measurement of valve thickness continues
3
15/08/11
ENG 7 ENG 8Lube Oil Strainer dismantled & Cleaned Lube Oil Strainer dismantled & cleaned1st filter Serviced Pressure testing of injector valves after serving
completed2nd Filter Serviced 1st filter serviced
2nd filter servicedValve seat grinding continued Valve seat grinding completed
Fuel oil drain tank filter servicedSludge tank filter servicedValve grinding completed
Measurement of valve stem continuedMeasurement of valve seats continued
Measurement of valve thickness continued
16/08/11
ENG 7 ENG 8Piston heads & liners cleaned Piston heads & liners cleaned
Installation of intake & exhaust valves (A1-A9)Grinding of valve seats completed Accumulators serviced
Measurement of valve stem continuedMeasurement of valve seats continued
Measurement of valve thickness continuesAll separator sludge tanks cleanedAll transfer pump filters serviced
17/08/11
ENG 7 ENG 8Installation of combustion firing rings completed Installation of combustion firing rings completedAccumulators servicedBack flush filter serviced Back flush filter servicedGrinding of valve seats continued Assembly of valves on B-bank completed
Measuring of valve guide completed Measuring of valve guide completedMeasuring of valve stems completed Measurement of valve stems completedMeasurement of valve thickness completed Measurement of valve thickness completed
Measurement of valve seats continued
18/08/11
ENG 7 ENG 8Grinding of valve seats completed Installation& tightening of cylinder heads A-bank
(1-7,9)Installation of intake & exhaust valve (B1-B3)
4
Measurement of valve seats completed
19/08/11
ENG 7 ENG 8Installation of intake & exhaust valves (A1-A3)& (B4-B9)
Installation & tightening of cylinder heads (B1-B9)
20/08/11
ENG 7 ENG 8Installation of intake & exhaust valves (A4-A9) Installation & tightening of cylinder heads ( A8
pending)Installation & tightening of cylinder heads (B1-B9)Installation of cylinder heads A1-A3
22/08/11
ENG 7 ENG 8Installation & tightening of cylinder heads complete
Installation of indicator corks A-bank completed
Installation indicator corks B-bank completed Installation of push rods & rocker arms A-bank completed
Installation of push rods & rocker arms B-bank completedInstallation of intake manifold completed Installation of intake manifold completeInstallation of thermo couples completed Installation of thermo couples A-bank completedNew injector valves O-rings assembly completed New injector valves O-rings assembly completedInstallation of injector valves completed Installation of injector valves B-bank completed
Installation of injector valve guides B-bank completedHigh- pressure fuel pipe assembly A1-A2
cylinder head water pipes fitted
23/08/11
ENG 7 ENG 8Installation of rocker arms A-bank complete Installation of rocker arms A&B-banks completeInstallation of Fuel high pressure pipes complete Installation of high-pressure fuel pipes (A3-A9)
& (B1-B9)Installation of cylinder heads A1-A3 Installation of new firing –A8Crankweb deflection measurement complete Installation of cylinder head-A8
5
24/08/11
ENG 7 ENG 8Valve lashing clearance completed Crankweb deflection measurement completedIndicator corks air-ran @ 15:20
10 gallons of Nalcool added on HT expansion tank5 gallons of Nalcool added on LT expansion tank
Lube oil priming pump started @ 14:00hrs & stopped @ 15:00hrsFuel circulating pump booster started @ 14:40 and stopped @ 15:40
All purifier sump oil changed
25/08/11
ENG 7 ENG 8Valve lashing clearance completedFiring order set (A-124689753)& (B-897531246)Installation of injector pumps (A4 & A5)Primed & confirmed for leaksLube oil priming pump started for leakage test
10 gallons of Nalcool added on LT expansion tank
ENG 7 TEST-RUN RUNDOWN
1. Start preparation @ 17: 11 hrsEngine started @ 17:30 hrs
Kwh- 341270 Kvarh-704460 F/meter-3006080
Engine shut down @ 17:32 hrs : exhaust gas leakage observed on two cylinder heads indicator corks A3 &B8. Amended immediately
2. Start preparation @ 17:34hrsEngine started @ 17:45hrs
Kwh-3412720 Kvarh-7044660 F/Meter-3006150
Engine shut down @ 17:55hrs : exhaust gas leakage observed on exhaust gas manifold. Amended immediately.
6
3. Start preparation @ 18:01hrsEngine started @ 18:17hrs
Kwh-3412720 Kvarh-7044660 F/Meter-3006150
Engine shut down @ 18:32hrs: exhaust gas leakage observed on fuel injection pumps-line A1, A2 and A5. They were amended immediately.
4. Start preparation @ 18:50Engine started @ 19:08Engine loaded @ 19:22hrs (1MW)
Kwh-3412720 Kvarh-7044660 F/Meter-3006200
@ 19:40 hrs Engine loaded to 2MW on diesel
@ 19:50 hrs Engine loaded to 3MW on diesel
@ 19:55 hrs Engine loaded to 4MW on diesel
F/S C/o to HFO @ 19:55 hrs
Kwh-3413490 Kvarh-7045050 F/Meter-3006550
F/S C/o to D/O @ 21:53 hrs
Kwh-3420040 Kvarh-7048280 F/Meter-3007750
C/B opened @ 21:53 hrs
Kwh-3420960 Kvarh-7048720 F/Meter-3008230
Engine shut down @ 18:32hrs: test run operations ended
F/Meter-3008230 D/O tank level-1900 H.F.O tank level-2000 Buffer tank level-1900
7
Sump level-27 mac
*Diesel oil tank level before test running
Before pumping – 1490l After pumping – 1900l
*Diesel oiltank level after test running
Before pumping-800l After pumping-1900l
*Maximum combustion pressure taken A1-A3 & A5-A8 (14) A4 &A9 (14.5) B-bank (14)
ENG 8 TEST-RUN RUNDOWN
Start preparation @ 20:25 hrs
Engine started @ 20:36 Kwh- 2230800 Kvarh-6305340 F/meter-1608490
Engine shut down @ 17:32 hrs
Kwh- 2230800 Kvarh-6305340 F/meter-1608650
Engine was shut down @ 20:40 hrs: fuel injection pump B5 temperature was very low. The pump was then removed under the supervision of the Philipino, Mr. Bautista. No further instruction was given to dismantle it.
*Diesel oil tank level before test running
Before pumping – 1650l After pumping – 2000l
*Diesel oil tank level After test running
Before pumping-1600l After pumping-2000l
8