2019SPRING MAINTENANCE BOARD REPORT
MEDVEJIE HATCHERY
NEW PUMP CONTROL AND PLC ALARM SYSTEM UPGRADES
Worked with Dan at Cooper Marine Services
Remote access to alarm system
VFD level tracking
Programmable level set points
PROGRAMABLE SET POINTS SCREEN
ELECTRIC HYDRO’S FOR THE NET WASHER AREA
• Installed electric hydraulic pack to operate the
net washer and block
• Replaced gas hydraulic pack
• Installed by hatchery staff
NEW GREEN LAKE BOAT CONSTRUCTION
• Specmar 18’ Outback kit
• This replaces our old roughneck
Skiff
• Being built by hatchery staff
SAWMILL CREEK HATCHERY
CONSTRUCTED AN INSULATED SHED OVER THE FIRE LINE CROSSOVER TAP
BUILT BY HATCHERY STAFF
GUNNUK CREEK HATCHERY TEMPORARY HYDRO INSTALL
PLUMBING IS CURRENTLY BEING INSTALLED BY HATCHERY STAFF
HIDDEN FALLS DOMESTIC WATER SYSTEM / CHLORINATION PUMP RE PLUMB
FABRICATING NEW JUMP OUT SCREENS AND CROWDERS FOR ADULT RACEWAYS
NEW ELECTRICAL RUN INSTALLED TO SEPTIC TANK
SHOP ORGANIZATION AND CLEAN UP