13
8/6/2019 Multiple Component Moorings http://slidepdf.com/reader/full/multiple-component-moorings 1/13

Multiple Component Moorings

Embed Size (px)

Citation preview

Page 1: Multiple Component Moorings

8/6/2019 Multiple Component Moorings

http://slidepdf.com/reader/full/multiple-component-moorings 1/13

Page 2: Multiple Component Moorings

8/6/2019 Multiple Component Moorings

http://slidepdf.com/reader/full/multiple-component-moorings 2/13

  1

1.  INTRODUCTION

The problem addressed here is to determine the inclination of a mooring on the seaward side of 

the lower fairlead, given the tension recorded at the platform, water depth and immersed weights

of a multiple component line. The motivation for this work lies with the measurement of stabilityin service (MOSIS) of moored platforms (Bradley and MacFarlane 1986a - 1995, MacFarlane

1996). A previous report (Smith and MacFarlane 2000) considered a special case of a three-

component mooring. In particular, the mooring comprised two lines connected by a buoy or

sinker and made tangential contact with the seabed. This report considers an arbitrary number of 

components and non-tangential or acute contact with the seabed. The previously developed

method of analysis has so far failed to produce reliable numerical results. However, an

alternative and much simpler method is proposed and this readily extends to an arbitrary numberof components. Examples are provided for a three and nine component configurations.

A three component mooring is shown in Figure 1 – a typical taut deep water mooring made up of 

two lines joined at a submerged buoy or sinker. The lower line may connect with an anchor at an

acute angle, in which case, the segment is artificially extended so that the origin of the co-

ordinate axes is more conveniently placed at the point of horizontal inclination. The upper line

connects to a floating platform through a fairlead and winch. The two lines are connected at a

point buoy or sinker. Loads on the mooring are the immersed self weights of the components and

end-point tensions. The lines are considered inextensible. The effects of current flow and time

dependent motions are not considered being averaged and balanced over time.

The first part of the paper reviews the catenary equations in dimensional and dimensionless

forms. The method of solution for the configuration shown in Figure 1 is then developed and a

numerical example is also provided. The analysis is then extended to an arbitrary number of 

components without significant change to the methodology. An example is shown for a nine

component mooring, comprising five line segments and four buoys. It should be noted that the

method developed here is for input parameters relevant to the MOSIS assessment of stability and

these may not coincide with those necessary for the design of a mooring system (Niedzwecki and

Casarella 1976, Oppenheim and Wilson 1982).

Page 3: Multiple Component Moorings

8/6/2019 Multiple Component Moorings

http://slidepdf.com/reader/full/multiple-component-moorings 3/13

Page 4: Multiple Component Moorings

8/6/2019 Multiple Component Moorings

http://slidepdf.com/reader/full/multiple-component-moorings 4/13

T T w x T T T w x T  h i h i h i h= + − = +cosh( ) , sinh( )α α2 2 1 (8)

i ,

where the subscript i =1,2 for mooring lines on the intervals 0 = s−1 ≤ s < s1 , s1 < s ≤ s2 , and α i , β i ,

and γ i are integration constants to be determined from boundary conditions. The prescribed

parameters for the problem addressed here are  H ,  L1 ,  L2 , T 2 , w1 and w2 . The tension T h is themain unknown.

3.  DIMENSIONLESS EQUATIONS

The prescribed parameters H and T 2 provide for non-dimensionalisation through defining

w w T H W W T T T T F F T  i i= = =∗ ∗ ∗2 1 1 2 2, , , = ∗

2

  (9)

s s H x x H y y H H H  i i i i= = = = =∗ ∗ ∗ ∗, , , ,β β γ γ  

in which the superscript ∗ denotes a dimensionless quantity. Note that αi is dimensionless by

definition. Substitution of (9) in (3) to (8) shows that the catenary equations remain valid for the

dimensionless quantities; for example (6) becomes

3

d + βd sinh( ), cosh( ) y x w x T y T w w x T  i h i h i i h i i

∗ ∗ ∗ ∗ ∗ ∗ ∗ ∗ ∗ ∗ ∗ ∗= + = +α α . (10)

The main advantage of the dimensionless equations is that the unknown T  always lies on the

interval

h

0 1< <∗T h . (11)

The dimensionless lengths and tensions become simple proportions of  H  and T 2 , respectively.

Explicit distinction between the dimensional and dimensionless equations is not necessary as

long as the latter quantities for H ∗ and are understood to be unit values.T 2

4.  BOUNDARY CONDITIONS – 1

Origin of the axes

The boundary conditions at the origin of the axes are

s x y dy dx= = = =0 0 0 0, , , , (12)

and this gives for the integration constants

α β γ1 1 1 10 0= = − =, ,T wh .   (13)

The integration constants are not directly employed in establishing the equation that governs T h .

Placing the origin at the point of seabed contact introduces less simple relations for the

integration constants and these become employed in establishing the equation that governs T h .

The approach adopted here leads to a simpler derivation.

Page 5: Multiple Component Moorings

8/6/2019 Multiple Component Moorings

http://slidepdf.com/reader/full/multiple-component-moorings 5/13

Point of seabed contact 

The position of the seabed contact is not explicitly known with respect to the origin, however, the

length of the lower line above the seabed is incorporated in the boundary conditions through

s L s0 1 1+ =   (14)

which implies

T w w x T L T w w x T  h h h h1 1 0 1 1 1 1 1 1 1sinh( ) sinh( )+ 1+ + = + +α γ α γ . (15)

Denoting for brevity

S w x T C w x T  ij j i h j ij j i h j= + = +sinh( ) cosh( )α αand   (16)

in which i = −1, 0, 1, 2 and j = 1, 2, then (15) transforms to

S S w L T  h11 01 1 1= + . (17)

A second implicit condition that is employed below is the height of the seabed above the origin y T w w x T  

T w C 

h h

h

0 1 1 0 1

1 01 1

= 1+ +

= +

cosh( )

.

α β

β 

(18)

Connection point 

Immediately to the left of the connection point at s = s1 :

4

 y T w C dy dx S s T w Sh h1 1 11 1 1 11 1 1 11 1

− − −= + = = +β γ, ( ) , , (19)

where the superscript denotes a negative sided limit. Continuity of distance and displacement

requires

s s y y1 1 1 1

− + − += =, , (20)

where the superscripts denote negative and positive sided limits. The change in slope across

s = s1 is obtained from (3), (4) and noting dy/dx =tanθ :

( )( ) ( ) ( ) ( )dy dx dy dx F s F s T W T  h h1 1 1 1 1

+ − + −− = − = . (21)

Applying boundary conditions (20) and (21) gives implicit relations for the integration constants:

S S W T  h12 11 1= + , (22)

T w C T w C  h h1 11 1 2 12 2+ = +β β  

⇒ − = −β β2 1 1 11 2 12T w C T w C  h h   (23)

and

T w S T w Sh h1 11 1 2 12 2+ = +γ γ  

⇒ − = −γ γ2 1 1 11 2 12T w S T w Sh h . (24)

 Lower fairlead 

The boundary conditions on the seaward side of the lower fairlead are

Page 6: Multiple Component Moorings

8/6/2019 Multiple Component Moorings

http://slidepdf.com/reader/full/multiple-component-moorings 6/13

s s s L y y y H T T  = = + = = + =2 1 2 2 0 2, , , (25)

where L2 , H and T 2 have prescribed values. Substitutions for s, y and T from above give

T w S T w S Lh h2 22 2 2 12 2 2+ = + +γ γ  

⇒ = +S S w L T  h22 12 2 2   (26)

or

T w S T w S Lh h2 22 2 1 11 1 2+ = + +γ γ  

⇒ − = − +γ γ2 1 1 11 2 22 2T w S T w S Lh h , (27)

T w C T w C H  h h2 22 2 1 01 1+ = + +β β  

⇒ − = − +β β2 1 1 01 2 22T w C T w C H  h h   (28)

and

C T T h22 2= . (29)

 Elimination of the integration constants

Elimination of fromγ γ2 − 1

1

(24) and (27) simply gives (26). More importantly, elimination of 

fromβ β2 − (23) and (28) gives

T w C T w C T w C T w C H  h h h h1 11 2 12 1 01 2 22− = − + . (30)

5.  METHOD OF SOLUTION – 1

The boundary conditions are rearranged as nine coupled equations and ordered so that the error is

dependent on only T h. First it is helpful to define

a w w b T w H c w L d W e T t T  k k k h= = − = = = =2 1 2 2 1 2 1, , , , ,   (31)

and noting

2< <T T h .0 (32)

The conditions (17), (22), (26), (29) and (30), and the identity cosh2( )−sinh

2( ) =1, give

(33)C et S C  22 22 22

2 1= =, −  

S S c t S S dt S S c t  12 22 2 11 12 01 11 1= − = − = −, ,   (34)

(35)C S C S C S12 12

2

11 11

2

01 01

21 1 1= + = + = +, ,

a C C C bt  ( )01 11 12 0− + − =   (36)

where a non-zero result in the last equation denotes the error. A sufficiently small error is

determined from monotone iteration of T h across the interval (32) and a plot of the error against

T h indicates the sensitivity of the solution to small changes of tension. The computational effort

is small specially for the dimensionless formulation where 0 < T h < 1.

5

Page 7: Multiple Component Moorings

8/6/2019 Multiple Component Moorings

http://slidepdf.com/reader/full/multiple-component-moorings 7/13

Grounded Catenary

When the origin of the axes and the point of seabed contact coincide, the lower line is called a

grounded catenary. That is, the line makes tangential contact with the seabed. In this case the

length of the lower line is not usually prescribed. Moreover,  L1 cannot exceed the length of a

grounded line. The boundary conditions for the grounded line are slightly simplified where C 01 = 

1 and S01 = 0. The equations in the sequence (33) to (36) reduce in number and become

(37)C et S C  22 22 22

2 1= =, −  

S S c t S S dt  12 22 2 11 12= − = −, (38)

(39)C S C S12 12

2

11 11

21 1= + = +,

a C C bt  ( )1 011 12− + − = . (40)

After solving for T h and S11 , the length of the grounded line

s T w Sh1 1 11= . (41)

6.  EXAMPLE – 1

The above method of solution has been coded as a FORTRAN program. The bounding interval of 

T h is uniformly divided in 500 steps and the execution time on an Intel 486 33MHz processor is

less than one second. The following input parameters are partly based on data from

Uittenbogaard and Pijfers (1996):(42)w1=100kgf/m, L1=700 m, W 1=10 tef buoy, w2=20 kgf/m, L2=500 m,

 H =1000 m, T 2=100 tef 

where kgf and tef respectively denote kilogram-force (9.81N) and tonne-force (9810N). A plot

of the iteration is shown in Figure 2 where it is seen that only a single solution exists:

(43)T h / T 2 = 0.40, T 0 / T 2 = 0.45, θ0 = 29 deg, θ2 = 67deg,

s0 /  H  = 0.22,  x0 /  H  = 0.21,  y0 /  H  = 0.056,

s1 /  H  = 0.92, ( x1− x0)/  H  = 0.42, ( y1− y0)/  H  = 0.60,

( x2− x1)/  H  = 0.61.

Substitution of these values in the physical boundary conditions, (14) (20), (21) and (25), shows

the numerical error is negligible:

s s L

 H 

1 0 1 177 10− +

= × −( ) 

(44)

s s

 H 

 y y

 H 

dy

dx

dy

dx

T h

1 1 17 1 1 16

1 1

1 179 10 9 10 1 10+ −

−+ −

−+ −

−−= ×

−= × ⎛ 

⎝ 

⎜⎞

 ⎠

⎟ − ⎛ 

⎝ 

⎜⎞

 ⎠

⎟ − = ×, , ,(45)

(46)

  6

Page 8: Multiple Component Moorings

8/6/2019 Multiple Component Moorings

http://slidepdf.com/reader/full/multiple-component-moorings 8/13

s s L

 H 

 y y H  

 H 

T x T 

2 1 2 16 2 0 4 2 2

2

171 10 8 10 4 10− +

= ×− +

= ×−

= − ×− −( ),

( ),

( ) − .

A more sophisticated iteration method would reduce the largest error to within the machine

precision, this however, is not usually necessary given the uncertainty of the prescribed

parameters. The integration constants for the upper line are

(47)α 2 = 1.1, β2 /  H  = −3.9, γ2 /  H  = −3.2.

-0.4

-0.3

-0.2

-0.1

0

0.1

0.2

0.3

0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1

      e      r      r      o      r

Th/T2  

Figure 2. The error of the reduced boundary conditions versus the horizontal tension.

7.  BOUNDARY CONDITIONS – 2

This section extends the boundary conditions developed above to a mooring line comprising

multiple segments with interconnecting buoys or sinkers. The methodology is unchanged and theelimination of the integration constants becomes slightly modified.

Origin of the axes and the point of seabed contact 

The boundary conditions at these points remain unchanged and are summarised here. At the

origin of the axes

s x y dy dx= = = =0 0 0 0, , , , (48)

and this gives for the integration constants

7

α β γ1 1 1 10 0= = − =, ,T wh .   (49)

The line length from the origin to the point of seabed contact is defined through

Page 9: Multiple Component Moorings

8/6/2019 Multiple Component Moorings

http://slidepdf.com/reader/full/multiple-component-moorings 9/13

s s L1 0 1= +   (50)

which gives

S S w L T  h11 01 1 1= +   (51)

where terms of Sij (and C ij) have been defined in (16).

The height of the seabed above the origin has also been defined as (52)

 y T w C  h0 1 01 1= + β .  (53)

Connection points

The extended case allows for multiple connection points. The conditions at each such point are

similarly defined as above. Immediately to the left of the ith connection point at s = si :

8

 y T w C dy dx S s T w Si h i ii i i ii i h i ii i

− − −= + = = +β γ, ( ) , , (54)

where the superscript denotes a negative sided limit. Continuity of distance and displacement

requires

s s y yi i i i

− + − += =, , (55)

where the superscripts denote negative and positive sided limits. The change in slope across s = si 

is obtained from (3), (4) and noting dy/dx =tanθ :

( )( ) ( ) ( ) ( )dy dx dy dx F s F s T W T  i i i i h i

+ − + −− = − = (56)h .

Applying boundary conditions (55) and (56) gives implicit relations for the integration constants:S S W T  i i i i i h, ,+ = +1 , (57)

T w C T w C  h i i i i h i i i i, ,+ = ++ + +β β1 1 1  

⇒ − = −+ +β βi i h i i i h i i iT w C T w C  1 1, , +1   (58)

and

T w S T w Sh i i i i h i i i i, ,+ = ++ +γ γ1 1  

⇒ − = −+ +γ γi i h i i i h i i iT w S T w S1 1, , +1 . (59)

A further condition that generalises the relation for line length in (50), requires

s s Li i i= +−1 . (60)

Substitutions for s gives

T w S T w S Lh i i i h i i i, , i= +−1  

⇒ = +−S S w L T  i i i i i i h, ,1 . (61)

 Lower fairlead 

The lower fairlead becomes the I th connection point and the boundary conditions on the seaward

side become

Page 10: Multiple Component Moorings

8/6/2019 Multiple Component Moorings

http://slidepdf.com/reader/full/multiple-component-moorings 10/13

s s s L y y y H T T   I I I I I  = = + = = + =−1 0, , . (62)

Substitutions for s, y and T from above give

T w S T w S Lh I I I I h I I I I  , ,  I + = + +−γ γ1  

⇒ = +−S S w L T   I I I I I I h, ,1 , (63)

T w C T w C H  h I I I I h, ,+ = + +β β1 0 1 1  

⇒ − = − +β β I h h I I I  T w C T w C H  1 1 0 1, ,   (64)

and

C T T  I I I h, =   (65)

in which T  I  is the measured or prescribed tension. Note that (63) denotes a particular case of 

(61).

 Elimination of the integration constants

Elimination of βi follows from (58) and (64). First note that

β β β β β β β β β β

β β

 I I I I I  

i i

i

 I 

− = − + − + + − + −

= −

− − −

+=

1 1 1 2 3 2 2

1

1

1

L

.

(66)1

 

Equation (58), (64) and (66) give

T w C T w C H T w C T w C  h h I I I h i i i h i i

i

 I 

1 0 1 1 1

1

1

, , ,− + = − + +

=

∑ (67)i,

.

8.  METHOD OF SOLUTION – 2

The boundary conditions are rearranged as nine coupled equations and ordered so that the error is

dependent on only T h. First it is helpful to define

a w w b T w H c w L d W e T t T  i I i I I i i i i i I h= = − = = = =, , , , , 1

0

  (68)

and noting

< <T T h I  . (69)

The four conditions (57), (61), (65) and (67), and the identity cosh2( )−sinh

2( ) =1, give

(70)C et S C   I I I I I I  , , ,,= = 2 1−  

S S c t S S d t i I I  i i i i i i i i i i− − − − −= − = − = −1 1 1 1 1 1 1, , , ,, , , L, ,   (71)

(72)C S C Si i i i i i i i− − − − − −= + = +1 1

2

1 1 1 1

21 1, , ,, ,  

( )a C a C a C bt  i i i i i i

i

 I 

1 0 1 1 1

1

1

0, , ,− − − =+ +=

∑  (73)

  9

Page 11: Multiple Component Moorings

8/6/2019 Multiple Component Moorings

http://slidepdf.com/reader/full/multiple-component-moorings 11/13

where a non-zero result in the last equation denotes the error. A sufficiently small error is

determined from monotone iteration of T h across the interval (69) and a plot of the error against

T h indicates the sensitivity of the solution to small changes of tension. The computational effort

is small specially for the dimensionless formulation where 0 < T h < 1.

Grounded Catenary 

As discussed above, the prescribed length of the lowest line needs be checked against that of a

grounded catenary. The condition involving  L1 is replaced by C 01  = 1 and S01  = 0, which

modifies (71) and (73) so that

S S c t S S d t i I I  i i i i i i i i i i− − − − −= − = − = −1 1 1 1 1 1 2, , , ,, , , L, ,   (74)

and

( )a a C a C bt  i i i i i ii

 I 

1 1 11

1

0− − − =+ +=

∑, , .

(75)

9.  EXAMPLE – 2

The above method of solution has also been coded as a FORTRAN program. The following input

parameters are partly based the data of the previous example, which has been extended to five

line segments:

(76)w1  =  w2  = 100kgf/m, w3  =  w4  = 50 kgf/m, w5  = 20 kgf/m,

(77) L1  =   L2  = 500m,  L3  =   L3  =   L5  = 300m

(78)W 1  =  W 2  =  W 3  = 10 tef buoy, W 4  = 5tef buoy,

(79) H =1000 m, T 5=300 tef 

where kgf and tef respectively denote kilogram-force (9.81N) and tonne-force (9810N). The

execution time also remains less than one second A plot of the iteration is shown in Figure 3 

where it is seen that only a single solution exists. The main part of the solution follows.

(80)

  10

Page 12: Multiple Component Moorings

8/6/2019 Multiple Component Moorings

http://slidepdf.com/reader/full/multiple-component-moorings 12/13

T h / T 5 = 0.79, T 0 / T 5 = 0.84, θ0 = 19 deg, θ5 = 38deg.

-0.6

-0.5

-0.4

-0.3

-0.2

-0.1

0

0.1

0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1

      e      r      r      o      r

Th/T5  

Figure 3. The error of the reduced boundary conditions versus the horizontal tension for five line segments.

10.  CONCLUSION

The method of solution developed here is simpler than that presented in a previous report and

readily extends to mooring lines with an arbitrary number of components. The main unknown

parameter is bounded between zero and unit values and is determined by a simple iteration

scheme that uniformly samples the interval. Graphical depiction of the error readily shows if the

solution is non-unique, which is unlikely in most cases.

11.  REFERENCES

Bradley, M. S. and MacFarlane, C. J. (1986a) Inclining tests in service. In Stationing and 

Stability of Semi-submersibles, editor C. Kuo, Graham & Trotman (Kluwer), London, 83-109.

Bradley, M. S. and MacFarlane, C. J. (1986b) The in-service measurement of hydrostatic

stability. In Proceedings of the Eighteenth Annual Offshore Technology Conference, Houston,

Texas, 4, 491-508.

Bradley, M. S. and MacFarlane, C. J. (1995) Some lessons to be learned from the stability control

of semi-submersibles. In Offshore 95 – Design and Safety Assessment for Floating Installations

 – Conference Papers, Institute of Marine Engineers, London.

11

Page 13: Multiple Component Moorings

8/6/2019 Multiple Component Moorings

http://slidepdf.com/reader/full/multiple-component-moorings 13/13

  12

MacFarlane, C. J. (1996) Discussion of Brown, D. T. and Witz, J. A., Estimation of vessel

stability at sea using roll motion records. Transactions of the Royal Institution of Naval

 Architects, 138, 130-145.

Meriam, J. L. (1975) Statics, 2nd edition (SI-Version), John Wiley & Sons, New York.

Niedzwecki, J. W. and Casarella, M. J. (1976) On the design of mooring lines for deep water

applications. Transactions of the ASME – Journal of Engineering for Industry, 98, 514-522.

Oppenheim, B. W. and Wilson, P. A. (1982) Static 2-D solution of a mooring line of arbitrary

composition in the vertical and horizontal operating modes.   International Shipbuilding

Progress, 29, 142-153.

Smith, R. J. and MacFarlane, C. J. (2000) Static of a three component mooring line. Ocean

 Engineering (accepted).

Symon, K. R. (1971) Mechanics, 3rd edition, Addison-Wesley, Reading, Massachusetts.

Uittenbogaard, R. and Pijfers, J. (1996) Integrated asymmetric mooring and hybrid riser system

for turret moored vessels in deepwater. In Proceedings of the Twenty-eighth Annual Offshore

Technology Conference, Houston, Texas, 3, 67-78.

_____________