Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
TAB
MUGLA MUNICIPALITY
Seyh Mahallesi Belediye Sokak MUGLA
Phone : +90 (252) 214 1846
Fax : +90 (252) 212 0718
MUGLA MUNICIPALITY
WASTEWATER TREATMENT PLANT
PROJECT
ENVIRONMENTAL IMPACT ASSESSMENT
REPORT
DOKAY-ÇED Environmental Engineering Ltd. Co.
Öveçler Kabil Caddesi 140/A 06460 Çankaya-ANKARA
Phone: +90 312 475 7131 - Fax: +90 312 475 7130
www.dokay.info.tr
2013
ANKARA
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
i
Project’s Owner: MUGLA MUNICIPALITY
Address : Seyh Mahallesi Belediye Sokak / MUGLA
Phone : +90 (252) 214 1846
Fax : +90 (252) 212 0718
Name of the Project : Mugla Municipality Wastewater Treatment
Plant Project
Project Value: 10,000,000 €
Project Location: Mugla Province, Merkez District, Hamursuz
Hill
Station of the Project
within the Scope of EIA
Regulation (Sector,
subsector)
Project is within the scope of Annex-1 List of
EIA Regulation published on 16.12.2003 in
the Official Gazette No:25318. (Infrastructure,
Wastewater Treatment Plant)
Name of the
Organization/Working
Group Prepared the
PIF/EIA Report/Final EIA
Report
DOKAY-CED Environmental Engineering Ltd.
Co.
Address, Phone, Fax of
the
Organization/Working
Group Prepared the
PIF/EIA Report/Final EIA
Report
Ata Mah. Kabil Caddesi No:140/A 06460
Çankaya / ANKARA
Tel: +90 (312) 475 7131
Fax: +90 (312) 475 7130
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
ii
Presentation Date of
PIF/EIA Report/Final EIA
Report (Day, Month,
Year)
MARCH 2012
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
iii
TABLE OF CONTENTS
Page
Table of Contents iii
List of Tables v
List of Figures vi
Abbreviations vii
1. BRIEF NOTE 1
2. EXECUTIVE SUMMARY 3
3. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK 9
3.1. NATIONAL STANDARDS 9
3.2. INTERNATIONAL CRITERIA 10
4. PROJECT DESCRIPTION 12
4.1. PROJECT CHARACTERISTICS 12
4.1.1. CURRENT SITUATION 12
4.1.2. WORKFLOW DIAGRAM 12
4.1.3. POPULATION PROJECTIONS 16
4.1.4. AMOUNT OF WASTEWATER TO BE USED FOR THE DESIGN OF THE WWTP 18
4.1.5. TECHNOLOGY 19
4.1.6. PERSONNEL 33
4.1.7. SETTLEMENT OF TEMPORARY PERSONNEL 33
4.1.8. TYPE AND NUMBER OF CONSTRUCTION MACHINES TO BE USED 33
4.2. UTILIZATION OF NATURAL RESOURCES (LAND AND WATER UTILIZATION,
TYPE OF ENERGY UTILIZED ETC.) 34
4.2.1. LAND USE 34
4.2.2. WATER UTILIZATION 34
4.2.3. ENERGY UTILIZATION 34
4.3. PROJECT SITE 34
4.4. GEOLOGICAL CHARACTERISTICS 37
4.4.1. GENERAL GEOLOGY 37
4.4.2. LOCAL GEOLOGY 43
4.4.3. TECTONICS 45
4.4.4. HYDROGEOLOGY 45
4.4.5. SEISMICITY 46
4.4.6. NATURAL DISASTERS 47
4.5. CLIMATIC CHARACTERISTICS OF THE REGION 47
4.5.1. PRECIPITATION 48
4.5.2. TEMPERATURE 49
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
iv
4.5.3. WIND 49
4.6. GEOGROPHIC CONDITIONS 50
4.6.1. TOPOGRAPHICAL STRUCTURE 50
4.6.2. WATER RESOURCES 50
4.6.3. SOIL CONDITION 50
4.7. SOCIAL CHARACTERISTICS 51
4.7.1. POPULATION 51
4.7.2. POPULATION GROWTH RATE 51
4.7.3. EDUCATION 51
4.7.4. TRANSPORTATION 52
4.7.5. HEALTH SERVICES 52
4.8. ECONOMIC CHARACTERISTCIS 53
4.9. ECOLOGICAL CHARACTERISTICS 54
5. ENVIRONMENTAL IMPACTS 60
5.1. LIQUID WASTES 60
5.1.1. DOMESTIC WASTEWATER 60
5.1.2. RAIN WATER 61
5.1.3. FILTRATE WATER 61
5.2. SOLID WASTE 61
5.2.1. DOMESTIC SOLID WASTE 61
5.2.2. CONSTRUCTION WASTE 61
5.2.3. EXCAVATION EARTH 61
5.2.4. SLUDGE 62
5.3. HAZARDOUS WASTE 62
5.3.1. WASTE OIL 62
5.3.2. MEDICAL WASTE 62
5.3.3. WASTE BATTERIES AND ACCUMULATORS 62
5.4. AIR EMISSIONS 63
5.4.1. GASEOUS EMISSIONS 63
5.4.2. DUST EMISSIONS 63
5.5. ODOR 65
5.6. NOISE 65
5.7. ACCIDDENT RISK DUE TO TECHNOLOGY AND MATERIALS USED 69
6. MITIGATION MEASURES 71
6.1. LIQUID WASTES 71
6.1.1. DOMESTIC WASTEWATER 71
6.1.2. RAIN WATER 71
6.1.3. FILTRATE WATER 72
6.2. SOLID WASTE 72
6.2.1. DOMESTIC SOLID WASTE 72
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
v
6.2.2. EXCAVATION 72
6.2.3. WASTE SLUDGE 72
6.2.4. WASTE OIL 74
6.2.5. WASTE BATTERIES AND ACCUMULATORS 74
6.3. AIR EMISSIONS 74
6.4. ODOR 76
6.5. NOISE 76
7. ANALYSIS OF ALTERNATIVES 78
7.1. TECHNOLOGY ALTERNATIVES 78
7.2. OTHER ALTERNATIVES 79
8. ENVIRONMENTAL MANAGEMENT PLAN 81
8.1. INTRODUCTION 81
8.2. RESPONSIBLE PARTIES 82
8.3. MITIGATION MEASURES 83
8.3.1. CONSTRUCTION PHASE 83
8.3.2. OPERATIONAL PHASE 83
8.4. MONITORING PLAN 87
8.4.1. CONSTRUCTION PHASE 88
8.4.2. OPERATIONAL PHASE 88
8.5. INSTITUTIONAL STRENGTHENING 93
8.5.1. EQUIPMENT PURCHASE 93
8.5.2. TRAINING 93
8.5.3. CONSULTANCY SERVICES, 94
8.5.4. PUBLIC RELATIONS 94
8.5.5. SPECIAL STUDIES 95
8.6. INSTITUTIONAL ARRANGEMENTS 95
8.6.1. CONSTRUCTIONAL PHASE 95
8.6.2. OPERATIONAL PHASE 97
8.7. CONSULTATION WITH NGO’S AND PROJECT-AFFECTED GROUPS 97
8.7.1. CONSTRUCTION PHASE 97
8.7.2. OPERATIONAL PHASE 97
9. REFERENCES 99
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
vi
LIST OF APPENDICES
APPENDIX-A SUMMARY OF PROJECT RELATED TURKISH LEGISLATION
APPENDIX-B FLOWCHART OF SELECTED WWTP AND ALTERNATIVE PROCESS
APPENDIX -C GEOLOGICAL MAP OF THE PROJECT SITE
APPENDIX–D LONG TERM METEOROLOGICAL RECORDS OF MUGLA PROVINCE
APPENDIX -E FLORA INVENTORY
APPENDIX -F FAUNA INVENTORY
APPENDIX–G PUBLIC CONSULTATION MEETINGS
APPENDIX–H TECHNICAL, ECONOMIC AND ENVORONMENTAL STUDIES ON
DISCHARGE OF TREATED WASTEWATER OF MUGLA WWTP
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
vii
LIST OF TABLES
Table 1. Discharge Standards ..........................................................................................11
Table 2. Distribution of Population in the City Center .......................................................16
Table 3. Population Projections .......................................................................................17
Table 4. Population Projection for Adjacent Residential Areas based upon second-degree
regression method presented in Table 3 ...................................................................17
Table 5. Total Population of Muğla Province ....................................................................18
Table 6. Per Capita Wastewater Flow Data Used in Design.............................................19
Table 7. Characteristics of Project Units ..........................................................................21
Table 8. Flow Data and Pollutant Parameters Used in Design .........................................23
Table 9. Discharge Criteria ..............................................................................................24
Table 10. Number of Employees of the Operational Phase ..............................................33
Table 11. Machinery to be Used at Construction Phase ...................................................33
Table 12. Coordinates of the Project Site .........................................................................37
Table 13. Information on Foundation Drilling Wells ..........................................................43
Table 14. Mugla Meteorological Station ...........................................................................48
Table 15. Season-based Average Annual Precipitation Data ...........................................49
Table 16. Population Distribution of Muğla and the Central District ..................................51
Table 17. Population Densities of Muğla and the Central District .....................................51
Table 18. Distribution of Education Institutions with respect to Grade ..............................52
Table 19. Health Institutions in the City Center ................................................................53
Table 20. Specie of Mammals ..........................................................................................58
Table 21. Water Consumption Data .................................................................................60
Table 22. Emission Factors to be Used for Dust Calculations ..........................................64
Table 23. Construction Machinery and Equipment and Their Sound Power Levels (Lw) ...66
Table 24. Noise Distribution with respect to Distance.......................................................67
Table 25. Limit Values for Environmental Noise (Table 5 of annex VIII of the RAMEN) ...68
Table 26. Expenses Associated with Pumping of Effluent to the Outside of the Basin .....78
Table 27. Potential Environmental Impacts of the Project and Mitigation Measures. ........85
Table 28. Monitoring Plan ................................................................................................89
Table 29. Discharge Site Water Quality/Quantity Monitoring Plan ....................................92
Table 30. Task Distribution related to the construction phase EMP requirements ............96
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
viii
LIST OF FIGURES
Figure 1 View from Existing Disposal Site-I ....................................................................... 6
Figure 2 View from Existing Disposal Site-II ...................................................................... 6
Figure 3 View from Existing Disposal Site after the Site Arrangements-I........................... 7
Figure 4 View from Existing Disposal Site after the Site Arrangements-II .......................... 7
Figure 5. Workflow Diagram for the WWTP .....................................................................14
Figure 6. Implementation Plan .........................................................................................15
Figure 7. General View of Cogeneration System .............................................................28
Figure 8. A View from the Abandoned Sand and Gravel Quarry Area. .............................29
Figure 9. Excavations at the Abandoned Sand and Gravel Quarry Area ..........................30
Figure 10 Project Location ...............................................................................................35
Figure 11 Satellite View of the Project Site ......................................................................35
Figure 12. Borders of the Project Site ..............................................................................36
Figure 13. Geological Cross-Section ................................................................................39
Figure 14. Generalized Stratigraphic Cross-sectional View of Allochthon Deposit ...........42
Figure 15. Earthquake Map of Mugla Province ................................................................46
Figure 16. Active Fault Map .............................................................................................47
Figure 17. Monthly Precipitation .......................................................................................48
Figure 18. Monthly Temperature Data of Muğla Meteorological Station (1975-2005) .......49
Figure 19. Biodiversity Hotspot Map of Project Site .........................................................54
Figure 20. Global 200 Ecoregion Map of Project Site .......................................................55
Figure 21. Vegetation in Muğla and the Project Site ........................................................57
Figure 22. Map of Hunting Zones in Mugla Province ........................................................59
Figure 23. Noise Distribution with respect to Distance .....................................................67
Figure 24. Pumping the Effluent to the Outside of the Basin ............................................80
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
ix
ABBREVIATIONS
BOD Biological Oxygen Demand
COD Chemical Oxygen Demand
CHP Combined Heat and Power
dBA A-weighted decibels
DOKAY DOKAY Engineering and Consultancy Ltd.
E East
EIA Environmental Impact Assessment
EMP Environmental Management Plan
ERP Emergency Response Plan
h Hour
HWCR Hazardous Waste Control Regulation
IB Iller Bank
IFC International Finance Corporation
km2 Kilometer square
kWth Kilowatt Thermal
kWel Kilowatt Electric
L Liter
LW Sound Power Levels
m3 Metercube
MB Modified Bardenpho Process
mbar Millibar
mL Milliliter
MUNICIPALITY Project Owner
N North
NGO Non-Governmental Organizations
Nm3 Normal Metercube
PIF Project Introduction File
PROJECT Mugla Municipality Wastewater Treatment Plant Project
Q37 Minimum flowrate for the design of wastewater treatment plant
Q24 Average flowrate for the design of wastewater treatment plant
Q14 Design flowrate for the design of wastewater treatment plant
Q12 Maximum flowrate of wastewater treatment plant
Qinf Infiltration flowrate that leaks from groundwater into sewer pipes
RAMEN Regulation on Assessment and Management of Environmental Noise
RCAPOIE Regulation on Control of Air Pollution Originating from Industrial
Establishments
S South
SHW State Hydraulic Works
SPCR Soil Pollution Control Regulation
SS Suspended Solids
SSK Social Security Institution
SWCR Solid Waste Control Regulation
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
x
USEPA U.S. Environmental Protection Agency
W West
WB World Bank
WPCR Water Pollution Control Regulation
WWTP Wastewater Treatment Plant Project
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
1
1. BRIEF NOTE
Iller Bank (IB) has received credit from the World Bank (WB) to support environmental
investments within the scope of “Municipal Service Project” through the process of
Turkey’s accession to the European Union. The IB is supposed to use this credit on
drinking water, wastewater and solid waste investments of the municipalities.
The Project Owner (MUNICIPALITY) has signed a protocol with the IB and “Mugla
Municipality Wastewater Treatment Plant (WWTP) Project” (PROJECT) is developed by
Temelsu-Dornier Schneider Common Initiative in order to solve the wastewater handling
problem of Mugla Province.
As stated in Item 7 of Annex-II of old Turkish EIA Regulation (Official Gazette dated
December 16, 2003 and numbered 25318) a Project Introduction File1 (PIF) was prepared
by DOKAY Engineering and Consultancy Ltd. (DOKAY) for the PROJECT and submitted
to the Provincial Directorate of Environment and Forestry of Mugla2. After being reviewed
by the Provincial Directorate of Environment and Forestry of Mugla, DOKAY had reviesd
the PIF in accordance with their comments. After the revision the report was finalized and
Provincial Directorate gave the decision “EIA not required” on 28th of January, 2008, which
means that all the impact assessment done in the PIF phase was enough to evaluate the
PROJECT and any further impact assessment studies were not required.
The PIF was about the wastewater treatment plant of Mugla Municipality. In Mugla
Province wastewater had been collected in leaching septic tanks. However, the
wastewater amount has started to increase with increasing population, many overflowing
incidents in septic systems had been experienced especially in lowlands of city center.
This could be a potential danger for the environment and public health since wastewater
overflowing from the septic tanks pollutes soil and groundwater resources as well as it
causes odor problem. In the PIF Report, potential environmental impacts that can arise
from the construction and operation periods are also presented and submitted on
November, 2008. Report enclosed as well as the mitigation measures that should be
taken to remove or minimize these environmental impacts. These measures were
determined considering both the WB’s criteria and the national legislation. The socio-
economic status and the characteristics of Project Site are also considered in this report.
Moreover, a detailed EMP (including a mitigation plan and a monitoring plan) was
prepared within the EIA report as the project was “category A’ according to WB OP 4.01
(Environmental Assessment). Two public consultation meetings were held by
1 Turkish Environmental Impact Assessment (EIA) Regulation was revised in July 17, 2008. According Annex I of new EIA
regulation which presents a list of the project that requires the preparation of an EIA Report, the wastewater treatment
plants having a capacity more that 30,000 m3/day requires an EIA Report. It should be noted that, the EIA procedure of the
PROJECT was completed before the revision of the EIA Regulation.
2 T.C.Ministry of Environment and Urbanization (MoEU) has been established by the Decree Law published on repeated
Official Gazete No.27984 dated 04.07.2011. Duties and responsibilities of Ministry of Environment and Forestry and Provincial Directorates of Environment and Forestry on environmental management and planning have been transferred to MoEU and its related directorates.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
2
MUNICIPALITY at the city center of Mugla Province to introduce the PROJECT to the
local people and take opinions of representatives of the NGO’s.
After all the necessarry procedure has been followed and completed, according to request
of WB, discharge alternatives of treated wastewater of Muğla WWTP were re-evaluated
by the Consultant (Temelsu) and a short report was prepared named as “Technical,
Economical And Environmental Studies on Dıscharge Of Treated Wastewater of Mugla
WWTP” (see Appendix-H). On 26 and 28th of September 2011, a meeting was held in
Muğla with the participation of World Bank, İller Bank, Muğla Municipality, Consultant,
Ministry of Environment and Urbanization3 (MoEU), Provincial Directorate of Environment
and Urbanization4 and Regional and Provincial Directorates of State Hydraulic Works.
Based on the Report, discharge system of Muğla WWTP is discussed in the meetings and
discharging treated wastewater to the old quarry (which was approved from the Provincial
Environmental Directorate of Mugla in 2008 through the PIF prepared) was confirmed as
the solution for discharge.
This revised EIA report is prepared upon the request of World Bank in order to make
necessary amendments and designs of the discharge alternative, based on the proposed
and accepted solution.
3 Formerly known as Ministry of Environment and Forestry.
4 Formerly known as Provincial Directorate of Environment and Forestry.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
3
2. EXECUTIVE SUMMARY
As accepted in 2008 and re-accepted in 2011, an abandoned sand and gravel quarry will
be used as “Disposal Site” of the treated wastewater of Muğla WWTP. Disposal site exists
inside of Karabağlar Plain and it is in 2.0 km distance to Düğerek town and 5.0 km
distance to Muğla city. Treated wastewater, discharged to Disposal Site, will be infiltrated,
evaporated and used for other purposes like irrigation of forestry areas and green areas.
Treated wastewater will be monitored monthly as described in Table 29.
Upon the request of World Bank in order to make necessary amendments and designs,
based on the proposed and accepted solution, some investigations were made inside of
Disposal Site up to now. In 2009 Contractor of WWTP carried out drilling studies and
some permeability coefficients are found. In 2011, Prof. Serdar Bayarı, the Consultant of
World Bank carried out another hydro-geological investigation and new permeability
coefficients are found. According to the technical studies it was concluded that the quarry
will have adequate infiltration capacity (when a portion of the discharged wastewater is
also used for irrigation purposes in forest and parks/gardens). Detailed information on the
selection of quarry as the discharge site is provided below:
Different alternatives for discharging treated wastewater of Muğla WWTP were evaluated
for this project since 2005. In 2005, in Feasibility Study different alternatives which were
suggesting pumping the effluent outside of the catchment area were evaluated. However,
the results showed that due to the high operational costs these alternatives will not be
feasible.After that feasibility study, in 2008 during the preparation of the PIF, General
Directorate of State Hydraulic Works (DSİ) permitted for infiltration, evaporation and
storage of treated wastewater in proposed abandoned sand and gravel quarry on the
Yaraş Road. PIF was prepared in line with that discharge option and approved by
Provincial Directorate of Environment and Forestry (PDoEF).
In 2011, another study was carried out and new alternatives were evaluated upon the
request of World Bank to confirm if the selected discharge option, which is discharging to
the quarry is technically, environmentally and economically feasible as a long term
solution. These altenatives are:
Alternative 1: Pumping of treated wastewater from WWTP to downstream location
of Ula Irrigation Reservoir at Ula Creek in the neighbouring catchment area, which
connects to Gökova Bay.
Alternative 1a: A route following Muğla-Ula-Akyaka Road.
Alternative 1b: A route following Muğla Plain and hills at southern part of Yeniköy
settlement area.
Alternative 2: Pumping of treated wastewater from WWTP to Kızılağaç Branch of
Ula Creek.
Alternative 3: Lining of discharge site and pumping of treated wastewater to the
forestry areas.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
4
Alternative 4: Percolation of treated wastewater to underground at discharge site
and pumping the rest amount to the forestry areas.
After evaluating all alternatives, Alternative 4 was proposed to be most feasible solution
for Muğla Municipality from initial investment and yearly operational costs point of views.
Alternative 4 has also matched with the proposed solution in Approved Project
Introduction File. Details of the selection of Alternative 4 is provided in Appendix H.
One of the important decisions made during the meeting, held in Muğla on September
2011, was to divide Discharge Site into cells and operate it with short term and long term
operation approaches. Short term period operation shall also be used for monitoring
percolation capacity and slope stability of the site. The slopes of the side walls in the
disposal are thought as unstable after filling the disposal site with treated wastewater.
Within this scope, slope stability analysis was made slope stability analysis was also
performed by the Consultant and best option was recommended in order to minimize the
risks around the Disposal Site. Details of the slope stability analysis can be seen in
Annex-3 of Appendix H. It was advised that into each cell some fine and coarse material
would be spreaded in order to long- term use of the infiltration capacity of the site. When
the treated wastewater was directed to another cell, fine and coarse material in the used
cell would be collected and disposed. Before the new turn, new fine and coarse material
would be spreaded to the cell. Before starting discharge, stability of the slopes would be
formed.
Operation of disposal site was divided into two parts, which are:
Short-term operation period – Pilot cells (2012-2013): In this period, two cells
with minimum elevation, which are in the closest location to discharge structure,
will be used. Total volume of these cells is approximately 60,000 m3. Water will be
risen up to 618 m in the cells. Infiltration capacity of the treated wastewater will be
monitored during the pilot cells operation and necessary actions will be taken for
the final discharge system. Treated wastewater will be diverted to the cell, which
is under operation. During the short-term operation period, water level will be
measured periodically at the discharge location. If the water exceeds the desired
level, rock filling shall be necessary at the slope bottom of critical places such as
concrete plant location. This implementation is possible according to to civil works
and it shall not affect the capacity of the discharge area. Water level will be
monitored monthly at the disposal site (see Table 29). In November-December
2011 period Muğla Municipality performed excavation and site arrangement works
inside of discharge site in order to prepare short term operation cells, which are
designed by the Consultant.
Long-term operation period - (2014-2040): In this period, disposal site will be
divided into 2 big cells and all of the disposal site will be used according to
experiences obtained from the short-term operation period. Total volume of the
sites is approximately 370,000 m3. Water will be risen up to 627.50 m in the cells.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
5
Based on the slope stability analysis, the solutions for the long term slope stability
are as follows:.
- Alternative 1 Doing nothing except expropriation of risky areas around
the top of the slopes. In this alternative, approximately 50 m land from
each side will be expropriated and slopes will be formed naturally by
sliding of the earth from top to bottom. Expropriation distance was
determined by adding 20 m to natural slide distances from each side in
order to be at safe side. Rock filling at the slope bottom will prevent the
water level exceedance.
- Alternative 2 Making of buttress at the slope toe and excavation of
slopes to an angle of 1H:1V or 3H:2V, where required
- Alternative 3 Excavation of slopes of all discharge site to an angle of
3H:2V with one berm
For all alternatives rough cost estimations are prepared and presented below:
Alternative 1: The unit cost of rock fill with the required geometry and
including transportation is 20.71 Euro/m3 and total estimated amount is
90,750 Euro for approximately 4,382 m3 volume, required for short-term
operation period.
According to calculations, extra area to be expropriated is around
51,000 m2. Cost of land per m2 is 0.8 Euro as a rough estimation.
Therefore extra cost for expropriation is approximately 40,800 Euro.
Total amount for Alternative 1 is approximately 142,500 Euro including
fencing and replacement of village road.
Alternative 2: The unit cost of rock fill with the required geometry and
including transportation is 20.71 Euro/m3 and total estimated amount is
369,675 Euro for approximately 17,850 m3 volume, required for long-
term operation period.
The cost of excavation including transportation is 2.83 Euro/m3 and
total excavation amount is around 245,000 m3 and costs to 693,840
Euro.
Total amount for Alternative 2 is approximately 1,112,850 Euro
including expropriation, fencing and replacement of village road.
Alternative 3: The unit cost of rock fill with the required geometry and
including transportation is 20.71 Euro/m3 and total estimated amount is
90,750 Euro for approximately 4,382 m3 volume, required for short-term
operation period.
The cost of excavation including transportation is 2.83 Euro/m3 and
total excavation amount is around 325,000 m3 and costs to 919,750
Euro.
Total amount for Alternative 3 is approximately 1,065,250 Euro
including expropriation, fencing and replacement of village road.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
6
From the alternatives, Alternative 1 was selected by Muğla Municipality and applied.
After the completion of the short term period cells, Muğla Municipality has started trial
operation of the WWTP on 06.02.2012. Some views, of initial and final condition of the
Site, can be seen below (Figures 1-4). At the same time, Muğla Municipality shall be
tendered fencing of the discharge site in June 2012 in order to eliminate potential risks.
Figure 1 View from Existing Disposal Site-I
Figure 2 View from Existing Disposal Site-II
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
7
Figure 3 View from Existing Disposal Site after the Site Arrangements-I
Figure 4 View from Existing Disposal Site after the Site Arrangements-II
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
8
After that, wastewater service connections, on the other hand, were started by Muğla
Municipality on 01.12.2011.
Within the scope of monitoring and evaluation studies water samples would be taken by
Muğla Municipality in order to establish database for future evaluations. For this purpose,
5 wells were determined by the Consultant and Bank of Provinces. The places of the
monitoring wells can be seen in Annex 6.1. of Appendix H. First samples were taken from
these locations in October 2011 and it will continue quarterly (see Table 29). All samples
were taken by Muğla Municipality and analyzed by Public Health Laboratory in Muğla. All
samples were analysed according to “TS 266-Water Intended for Human Consumption
Standard” and “Regulation Concerning Water Intended for Human Consumption”.
Analysis results can be seen in Appendix-I Well Water Analysis. While considering the
analyses results, it has been seen that nearly all chemical and indicator parameter results
are under the limit values in the standard and regulation. Only nickel value in the well No:1
and turbidity value in the well No:2 are higher than limit values.
In the terms of microbiological parameters; enterococcus, escherichia coli, fecal coliform
and total coliform values in the well No:1 are higher than limit values. In the both of wells,
number of pseudomonas aeruginosa, total number of bacteria (at 22 C) and total number
of bacteria (at 37 C) are higher than 0 (zero). According to the analysis results it can be
said that water in the wells can not be drunk. That is why; necessary precautions and
implementations should be put in force by Muğla Municipality to ensure that people living
in the Muğla plain do not drink well water.
According to the monitoring plan, submitted in Chapter 8. Environmental Management
Plan, sampling shall be done by Muğla Municipality four times in a year and will be
continued during whole operation period and all results shall be submitted to İller Bank.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
9
3. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK
3.1. NATIONAL STANDARDS
Project specific environmental standards for the PROJECT are determined by
national legislation.
The national laws and regulations to be complied with during implementation of
the PROJECT is given below. In addition, Appendix-A presents the summary of these
regulations and national limit values to be complied with.
Environmental Law no. 2872
Labor Law no. 4857
Municipality Law no. 5215
Regulation on Assessment and Management of Environmental Noise
(Official Gazette dated March 7, 2008 and numbered 26809)
Solid Waste Control Regulation
(Official Gazette dated March 14, 1991 and numbered 20814)
Regulation on Environmental Audit
(Official Gazette dated November 2, 2008 and numbered 27061)
Regulation on the Septic Tanks that will be Constructed where Sewer System
Construction is not Applicable
(Official Gazette dated March 13, 1971 and numbered 13783)
Environmental Impact Assessment Regulation
(Official Gazette dated July 17, 2008 and numbered 26939)
Regulation on the Control of Air Pollution Originating from Industrial
Establishments
(Official Gazette dated July 22, 2006 and numbered 26236)
Regulation on Potable Waters
(Official Gazette dated February 17, 2005 and numbered 25730)
Regulation on Occupational Health and Safety
(Official Gazette dated December 9, 2003 and numbered 25311)
Guidelines on Worker Health and Safety on Constructive Works
(Official Gazette dated September 12, 1974 and numbered 15004.)
Regulation on Control of Waste Oil
(Official Gazette dated July 30, 2008 and numbered 26952)
Regulation on Control of Excavation Material, Construction and Demolition Wastes
(Official Gazette dated March 18, 2004 and numbered 25406)
Regulation on Control of Air Pollution Originating from Industrial Establishments
(Official Gazette dated July 3, 2009 and numbered 27277)
Water Pollution Control Regulation
(Official Gazette dated December 31, 2004 and numbered 25687)
Regulation on Control of Hazardous Wastes
(Official Gazette dated March 14, 2005 and numbered 25755)
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
10
Regulation on Soil Pollution Control
(Official Gazette dated May 31, 2005 and numbered 25831)
Regulation on Control of Packaging Materials
(Official Gazette dated August 24, 2011 and numbered 28035)
Regulation on Control of Waste Batteries and Accumulators
(Official Gazette dated August 31, 2004 and numbered 25569)
Regulation on Structures Constructed at Disaster Areas
(Official Gazette dated July 14, 2007 and numbered 26582)
Regulation on Protection of Buildings Against Fire
(Official Gazette dated July 26, 2002 and numbered 24822)
Vibration Regulation
(Official Gazette dated December 23, 2003 and numbered 25325)
Noise Regulation
(Official Gazette dated December 23, 2003 and numbered 235325)
Regulation on Urban Wastewater Treatment
(Official Gazette dated January 8, 2006 and numbered 26047)
Regulation on Occupational Health and Safety
(Official Gazette dated December 9, 2003 and numbered 25311)
Guidelines on Worker Health and Occupational Safety
(Official Gazette dated January 11, 1974 and numbered 14765)
3.2. INTERNATIONAL CRITERIA
Since the PROJECT is financed with the credit supplied by the WB to the IB,
environmental criteria of the WB5 shall be considered together with the Performance
Standards assigned by the International Finance Corporation (IFC) in April 2007.
However, since it is obligatory to conduct a project complying with Turkish Environmental
Legislation, PROJECT specific environmental standards will mostly be determined by the
national legislation. In this respect, as a first step of the PROJECT development, a Project
Introduction File that is required by the Turkish MoEF was prepared and approved by the
Provincial Directorate of Environment and Urbanization of Mugla.
Table 1 presents the national and international discharge standards to be applied
in this design of WWTP.
5 “Pollution Prevention and Abatement Handbook”, published by the WB in 1998, was considered in this
respect. Items in the Handbook encourages the protection human health, reduction of pollutant emissions, use
of cost-effective technologies, compliance to the national and international legislation updates and the
application of best engineering and environmental management practices.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
11
Table 1. Discharge Standards
Discharge Standards
Organization
Turkish Urban Wastewater Treatment
Regulation
EU Urban Wastewater Treatment
Directive
pH - -
COD 125 125
BOD5 25 25
Suspended Solids 35 35
P * 1 1
N * 10 10
*for sensitive areas
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
12
4. PROJECT DESCRIPTION
4.1. PROJECT CHARACTERISTICS
4.1.1. Current Situation
Since there is no present sewage network in the city center, wastewater disposal is
achieved by septic systems. Since soil permeability is high, leaking septic tanks are in
use. Even in some residences, wastewater is illegally discharged to streams.
Increasing urban population results in an increase in number of multi-storey
buildings, and thus overflow from septic tanks is frequently observed. This is an
unfavorablesituation for inhabitants. Leakage from septic tanks results in soil and
groundwater pollution besides odor problems at the city. Moreover, water leaking to
groundwater table has the potential to reach to drinking water resources and Gokova Bay.
Not only the collection but also the treatment of wastewater is a problematic issue.
Conditioning with lime has been applied to a flow of 400-500 m3/day in a simple WWTP
since middle of 2005.
4.1.2. Workflow Diagram
As stated in the feasibility report compiled by the Temelsu-Dornier Schneider
Common Initiative, Audit Services Contraction File for the WWTP will be prepared within
2007 together with the Conceptual Project will be completed. Construction and start-up of
the WWTP will be completed within two years, between 2008 and 2010. Discharge facility
which is the collection of treated wastewater in treated wastewater storage reservoir will
be carried out in 2010.
Construction of the WWTP has been planned to be completed in two stages. First
stage will handle population and pollution load by year 2022, and second stage will be
designed according to 2042 values.
These two stages will have a compact layout as the lines will be parallel to each
other. This will lead to;
enlargement of the WWTP in a more economical and practical way,
less land allocation by the PROJECT units,
less hydraulic losses,
flexible operational opportunities.
Workflow diagram of the PROJECT is given in Figure 5.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
13
Also, Muğla Municipality should perform some actions within short time for
securing the treated wastewater disposal system and operating it long-term period without
any problem. These actions and proposed implementation plan is explained below.
Expropriation of excess required lands near disposal site: In order to secure the
stability of slopes approximately 5.1 ha lands should be expropriated by
Municipality at latest in the first half of 2012.
Construction of green area irrigation pipes within the city centre: In order to
effective use of the capacity of the irrigation pumps in WWTP and decrease the
load of Disposal Site, additional pipes should be constructed by Municipality. It will
start with the beginning of 2012 with GEKA grant and constructions should be
completed at the end of 2014.
Construction of forestry area irrigation pipes up to the permitted location: In order
to long-term use of the Disposal Site, additional pipes should be constructed by
Municipality up to the forestry area, which will be permitted by Regional Directorate
of Forestry. Necessary steps are foreseen as follows:
- Getting permission from related authority: Up to March 2012
- Design and tender processes: April 2012-April 2013
- Construction period: April 2013- June 2014
Detailed implementation plan is submitted in Figure 6.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
14
MUGLA WASTEWATER TREATMENT PLANT - WORK PROGRAM
♦ Wastewater Treatment Plant
● Mobilization of the Contractor
● Control and Approval of Final Project
● Construction Works
-Site Preparation and Excavation Works
-Pumping Station, Screens, Sand
-Primary Sedimentation Tank
-Aeration Tank, Blower
-Secondary Sedimentation Tank
-Collection and Distribution Sytems, watch , flowmeter
-Digester
-Recycle and Excess Sludge Pumping Station and Outlet Pumping
Station
-Cogeneration Building, Gas Storage
-Sludge Treatment, Dewatering and Storage Yards
-Chlorination unit, other pumping station
-Administrative building, workshop and other auxillary units
-Roads, landscaping
● Mechanical Works
● Electrical Works
● Provisional Acceptance, Tests and Start-Up
● Defect Liability Period and Final Acceptance
1 2 3 4 5 6 7 8 9 10 11 12 14 15 16 17
Construction Phase (24 months)
21 22 23 2418 19 2013
Figure 5. Workflow Diagram for the WWTP
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
15
IMPLEMENTATION PLAN
No. Activity Responsible 2011 2012 2013 2014
10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12
1
Short-Term Operation of Disposal Site
Muğla Mun.
Arrangement of Disposal Site X
Short-term Operation Of Disposal Site X X X X X X X X X X X X X X X X X X X X X X X X
2 Connnection of Service Connections Muğla Mun. X X X X
3 Trial Operation Period of WWTP Contractor X X X X X X
4
Long-Term Operation oF Disposal Site
Muğla Mun.
Expropriation of Required Additional Lands X X X X X X X X X X X X
Arrangement of Disposal Site X X X X X X X X X X X X
Long-term Operation Of Disposal Site X X X X X X X X X X X X
5
Construction of Green Area Irrigation Pipes
Muğla Mun.
With GEKA Grants X X X X X X X X X X X X
With Municipality Budget X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X
6
Irrigation of Forestry Areas
Muğla Mun.
Getting Permission from Related Authority X X X
Design and Tender Stage X X X X X X X X X X X X
Constructions X X X X X X X X X X X X X X X X X X
Figure 6. Implementation Plan
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
16
4.1.3. Population Projections
Population of Mugla increased four times whereas population of Turkey increased
five times within last 73 between 1927 and 2000
Population in the city center is given with populations of sub and top governmental
units in Table 2.
Table 2. Distribution of Population in the City Center
Population
Settlement 1970 1975 1980 1985 1990 1995 2000
1
City center (Urban)
18.624 24.178 27.392 31.279 35.605 39.095 43.843
Increase (%) 23% 12% 12% 12% 9% 11%
2
City center (Rural)
35.769 32.520 33.076 34.580 35.550 37.781 39.666
Increase (%) 10% 2% 4% 3% 6% 5%
3
City center (Total)
54.393 56.698 60.468 65.859 71.155 76.876 83.511
Increase (%) 4% 6% 8% 7% 7% 8%
4
Mugla Province (Urban)
70.596 85.011 100.314 13.616 19.808 233.000 268.341
Increase (%) 17% 15% -637% 31% 91% 13%
5
Mugla Province (Rural)
298.180 315.785 337.831 350.130 364.729 396.800 446.987
Increase (%) 6% 7% 4% 4% 8% 11%
6
Mugla Province (Total)
368.776 400.796 438.145 486.290 562.809 629.800 715.328
Increase (%) 8% 9% 10% 14% 11% 12%
Turkey (Urban) 13.691.101 18.869.068 19.645.007 26.865.757 33.326.351 38.124.000 44.006.274
Increase (%) 27% 4% 27% 19% 13% 13%
Turkey (Rural) 21.914.075 23.478.651 25.091.950 23.798.701 23.146.684 23.408.000 23.797.653
Increase (%) 7% 6% -5% -3% 1% 2%
Turkey (Total) 35.605.176 40.347.719 44.736.957 50.664.458 56.473.035 61.532.000 67.803.297
Increase (%) 12% 10% 12% 10% 8% 9%
Source: Muğla Municipality Final Feasibility Report, September 2005
The city center, which covers the urban areas, is composed of 14 neighborhoods,
eight of which lie within urban protected area, in the core of the city, and they include few-
storey buildings that are located close to each other. In other neighborhoods, multi-storey
buildings dominate. Sections of the city outside the urban city center are developing. The
city is bounded by agricultural areas and natural protected areas in the south (Cukuryayla)
and mountainous and forest zones (Kızıldag) in the north.
City will enlarge in south (Akkaya, Kotekli, Yenikoy and Ortakoy), west (Akcaova)
and east (Dugerek and Karabaglar) directions. Mugla Structural Plan dated January 2004
shows that enlargement of urban city has started toward these directions.
Results of population projections based on population and demographic analyses
are given in Table 3. The base years for these projections are the years between 1970
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
17
and 2000 as seen from Table 3 and the populations of the years shown in Table 2 are
calculated by using the base years’ values.
Table 3. Population Projections
Projection Method 2005 2010 2015 2020 2025 2030 2030 2040
1 Iller Bank 49,365 55,580 62,578 70,456 79,327 89,314 100,588 113,219
2 Logarithmic Increase 49,361 55,571 62,562 70,433 79,294 89,270 100,500 113,144
3 First-Degree
Regression 45,956 49,054 52,151 55,249 58,347 61,444 64,542 67,639
4 Second-Degree
Regression 47,424 51,296 55,126 58,915 62,661 66,366 70,028 73,649
5 Least Squares 47,675 51,737 55,798 59,859 63,920 67,981 72,042 76,103
6 Compound Interest 1
(1970-2000) 50,570 58,327 67,273 77,591 89,493 103,219 119,051 137,312
7 Compound Interest 2
(1990-2000) 48,655 53,992 59,915 66,488 73,781 81,875 90,857 100,824
8 Exponential Increase 1
(1970-2000) 50,674 58,567 67,689 78,232 90,417 104,500 120,777 139,589
9 Exponential Increase 2
(1990-2000) 48,708 54,110 60,111 66,778 74,185 82,413 91,553 101,107
10 Average Projected
Populations 48,710 54,248 60,356 67,111 74,603 82,931 92,215 102,576
Source: Muğla Municipality Final Feasibility Report, September 2005
Since the Project Site was extended so as to include residential areas 5 km away
from border of the adjacent area, population of these residential areas were also
estimated by using second-degree regression method given in item 4 of Table 3 (see
Table 4). Wastewater generated in this area will also be collected for treatment in the
WWTP.
Table 4. Population Projection for Adjacent Residential Areas based upon second-degree regression method presented in Table 3
Year
Settlements
Toplam Kötekli Yeniköy Ortaköy
Akçaova 1*
Akçaova 2*
Yaraş** TOKİ Üni.
2000 3,328 884 970 5,182
2005 3,747 995 1,092 1,000 16,000 22,834
2010 4,219 1,121 1,230 2,000 4,500 16,000 29,070
2015 4,750 1,262 1,384 3,000 2,000 4,500 16,000 32,896
2020 5,348 1,421 1,559 4,000 2,800 1,194 4,500 20,000 40,822
2025 6,021 1,599 1,755 5,000 3,600 1,344 4,500 20,000 43,819
2030 6,779 1,801 1,976 6,000 4,400 1,514 4,500 20,000 46,970
2035 7,633 2,027 2,225 7,000 5,200 1,704 4,500 20,000 50,289
2040 8,594 2,283 2,505 8,000 6,000 1,919 4,500 20,000 53,801
* Population values determined for a “development area” named Akçaova. Construction of 500 houses is in
progress in “Akçaova 1”. “Akçaova 2” is expected to be connected to the sewage system by 2015.
** Expected to be connected to be the sewage system in 2020
Source: Muğla Municipality Final Feasibility Report, September 2005
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
18
Total population values of city center and adjacent residential areas were shifted to
2007 and subsequent 5 year increments up to 2042 by interpolating the values given in
Table 4 (see Table 5).
Table 5. Total Population of Muğla Province
Year Total Population
2007 74,600
2012 84,200
2017 92,900
2022 102,500
2027 109,300
2032 116,200
2037 123,200
2042 130,400
4.1.4. Amount of Wastewater to be Used for the Design of the WWTP
“Sewerage System Examination and Design Report” was compiled in July 2007
and submitted to the MUNICIPALITY and the IB for approval. The Conceptual Design
Report has been approved by IB in November of 2007. Design flows that are used for
calculating the capacity of the units of Wastewater Treatment Plant are computed by
using Bank of Province (Iller Bank) Drinking Water Specification as follows and they are
given for the years of 2022 and 2042 in Table 6.
The equations are utilized for the estimations of the flows for design of the WWTP.
Minimum flow is the amount of hourly wastewater that are expected during night
time when water use and thus wastewater generation is at minimum. It is calculated as
follows:
Minimum flow, Qmin = 2437
infQQ
Average flow is the hourly average of daily flow.
Average flow, Qave = 2424
infQQ
Maximum flow is the hourly flow that is assumed to be the twice of the average
flow.
Maximum flow, Qmax = 2412
infQQ
Design flow is assumed as the the hourly flowrate that is the maximum flow
observed between 8 am and 8 pm..
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
19
Design flow, Qdesign = 2414
infQQ
Infiltration flow (Qinf) is the flow that leaks into sewer pipes from groundwater.
Table 6. Per Capita Wastewater Flow Data Used in Design
Year Unit Wastewater
(L/cap-day)
Minimum Flow Rate (Q37)
(m3/h)
Average Flow Rate (Q24)
(m3/h)
Maximum Flow Rate (Q12)
(m3/h)
Design Flow Rate (Q14)
(m3/h)
2022 150 510 737 1,383 1,198
2042 166 679 998 1,905 1,646
It is the general rule that, some of the WWTP’s units (primary sedimentation tank,
aeration tank, final sedimentation tank) are designed for the design flowrate (see Table 6)
and the capacity of the units is checked for the maximum and minimum flowrates to meet
the criteria. In addition some units of the plant (pipes, channels, screens, grit and grease
chamber, chemical dosing units) are designed for the maximum flow and the capacity of
the units is checked for the minimum flowrate to meet the criteria. If the design criteria
(which of the standard will be selected by the Contractor and will be written by the
Contractor in its Proposal) of the units according to any selected standard are not
satisfied, the treatment efficiency cannot then meet the discharge criteria defined in the
Section 3.2.
4.1.5. Technology
WWTP shall be designed as two phases for the target years 2022 and 2042. the
units are phased as follows:
1. The following units shall be designed for the maximum flowrate of Stage 2.
Inlet pumping station
Coarse screen
Fine screen
Distribution and collection chambers
Discharge pipe
Chlorine contact tank
Outlet pumping station
Measurement units
2. The following units shall be designed and constructed for design flowrate of Stage 2.
Grit and grease chambers
Primary sedimentation tank
Aeration tank
Secondary sedimentation tank
Anareobic digester
Blowers station
Return and surplus sludge pumping station
Sludge dewatering unit
Filtrate pumping station
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
20
Pre-thickener
Post-thickener
Sludge storage tank
Sludge storage area
Technology to be utilized in the WWTP will be simultaneous denitrification and
nitrification in Carrousel – type ponds. Dimensions of PROJECT units are given in
Table 7.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
21
Table 7. Characteristics of Project Units
No Units Parameter Unit Amount
1 Inlet pumping station
Pumps - 3+1
Pump flow rate m³/h 500
Pump head m 6.8
2 Screens
Number of screens - 2
Bar spacing mm 6
Width m 1.2
Inlet water depth m 0.5
3 Aerated grit chambers
Retention time min 16
Number of divisions - 2
Width of one division m 1.6
Length of one division m 25
Cumulative volume m³ 160
Air demand m³/h 430
Blower
Number of blowers - 2
Pressure mbar 250
Air supplied by one blower Nm³/h 215
4 Flow measurement Type of measurement
5 Primary sedimentation tank
Retention time h 0.5
Width m 8
Length m 32
Volume m 294
Number of divisions - 2
6
Distributor Retention time min 15
Volume 300
Mixer Mixer
Specific heat input
Specific energy input W/m³ 5
Enerji input kW 1.5
Number of mixers - 1
7 Aeration tank
Design temperature °C 12
MLSS day/L 4.8
Sludge age day 13.2
Cumulative volume m³ 13,206
VDN/VBB-ratio 0.5
Excess sludge kg/day 4.478
Maximum supply of oxygen kgO2/h 742
Type of aeration Thin bubble
Water depth m 6
Blower
Number of blowers - 3+1
Pressure mbar 720
Air supplied by one blower at 30°C Nm³/min 57
Mixer
Specific energy input W/m³ 2.5
Energy input per tank kW 16.5
Number of mixers per tank - 4
Diameter mm 2,000
8 Distribution chamber Volume m³ 15
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
22
No Units Parameter Unit Amount
9 Secondary sedimentation tank
Surface loading rate m/h 0.8
Initial settling velocity mL/day 100
Tank depth m 4.3
Number of tanks - 2
Diameter m 30
Cumulative volume m³ 5,400
10
Pumping station for recycled
sludge
Number of pumps - 2+1
Pump flow rate m³/h 500
Pump head m 5
Excess sludge pumps
Number of pumps - 2
Pump flow rate l/s 20
Pump head m 6
11 Chlorination tank
Retention time min 5
Average amount of irrigation water m³/day 675
Duration of irrigation h 4
Maximum amount of irrigation water m³/h 169
Volume m³ 14
12 Contact tank Retention time min 30
Volume m³ 84
13 Primary sludge thickener
Retention time day 1
Suspended solids in thickened sludge % 4.5
Volume m³ 650
14 Anaerobic digester
Duration of digestion day 17
Number of digesters - 2
Volume per digester m³ 1,500
Circulation pump
Count - 2+1
Pump flow rate m³/h 150
Mixer
Specific energy input W/m³ 2.5
Energy input per digester kW 1.9
Number of mixers per digester - 1
Heat exchanger
Thermal power 288
Compound heat and power
Number of modules - 2
Capacity per unit kWel / kWth 90 / 150
Gas tank
Volume m³ 1,000
15 Secondary thickener
Retention time day 1
Suspended solids in thickened sludge % 4.5
Volume m³ 150
16 Sludge storage tank
Retention time day 2
Suspended solids in thickened sludge % 4.5
Volume m³ 260
Mixer
Specific energy input W/m³ 20
Energy input kW 5.2
Number of mixers - 1
17 Sludge dewatering Working period h/day 8
Working days day/week 5
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
23
No Units Parameter Unit Amount
Type of equipment belt press
Number of machines - 2
Capacity of one machine m³/h 24
Dry solids content % 20
Amount of sludge t/day 30
18 Dosage unit for P removal
Settling agent AlCl3
Number of storage tanks - 2
Volume of one tank m³ 35
Number of dosage pumps - 1+1
Dosage capacity of one pump l/h 0-228
19 Effluent pumping station
Pump type: centrifugal
Number of pumps - 3+1
Pump flow rate m³/h 500
Pump head m 50
Retention time min 10
Retention tank m³ 200
The flow data, which was made use of in design of the treatment process in both
stages of the WWTP, is given in Table 8.
Table 8. Flow Data and Pollutant Parameters Used in Design
Parameter Unit Year
2022 2042
Population Capita 102,500 130,400
Flow rate
Minimum m3/h 510 679
Average m3/h 737 998
Design m3/h 1,198 1,646
Maximum m3/h 1,383 1,905
Pollutant Load
Suspended solids (SS) g/cap-day 70 70
Biochemical oxygen
demand (BOD) g/cap-day 45 45
Chemical oxygen demand
(COD) g/cap-day 90 90
Nitrogen g/cap-day 10 10
Phosphorus g/cap-day 3 3
Pollutant Load
SS kg/day 7,215 9,168
BOD kg/day 4,638 5,894
COD kg/day 9,277 11,788
Nitrogen kg/day 1,030 1,310
Phosphorus kg/day 309 393
Source: Mugla Municipality Final Feasibility Report, September 2005
Mugla Basin, which is a closed basin, is not a sensitive area according to the
“Urban Wastewater Treatment Directive”, with code 91/271 EEC, of the European Union.
On the other hand, discharge sinkholes of the basin reach to the Aegean Sea. Since
Gokova Bay is a protected area, biochemical oxygen demand (BOD), chemical oxygen
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
24
demand (COD) and suspended solid (SS) values are taken considering the values for
sensitive areas stipulated in the directive (see Table 9).
Table 9. Discharge Criteria
Parameter Unit
Urban Wastewater Treatment Directive Discharge Values
Chosen Sensitive Area Less Sensitive Area
BOD mg/L 25 25
COD mg/L 125 125
SS mg/L 35 35
Total N mg/L 10-15 10
Total N mg/L 1-2 1
For the stage two of the WWTP, population estimation is 130,000, and thus, the
SS discharge criterion stipulated in the “Urban Wastewater Treatment Regulation”,
effective since publication in Official Gazette no. 26047 on 8 January 2006, for
settlements with population over 10,000 is considered. Discharge of nitrogen in sensitive
areas will be made in compliance with the discharge criterion stipulated in the same
regulation.
4.1.5.1 Units of the Selected Process
Inlet Structure, Coarse Screen and Pumping Station
The wastewater from the main collector line passes through coarse screen. Bar
spacing of coarse screen is 30 mm. A pumping station will be constructed at the outlet of
coarse screen.
Fine Screen
Fine screen retains matters that can pass through the coarse screen. The stage
one of the WWTP will be composed of two lines, and each of them will be designed to
handle the maximum flow of the stage two. Bar spacing of fine screen will be 6 mm.
Screens will be cleaned by an automated system that operates according to difference
between water levels at the inlet and outlet of the screen. Refuse from coarse and fine
screens will be transferred to press machines by belt conveyors. End products will be
collected in containers. Disintegrated and dewatered screen waste will be transferred to
storage sites by trucks.
Aerated Grit and Grease Chamber
The raw wastewater contains non-biodegradable inorganic compounds. Transfer
of these compounds to activated sludge tanks increases the amount of inorganic matters,
and affects the efficiency of the overall process. Therefore, inorganic compounds are
removed in the aerated grit and grease chamber. Aeration in the aerated grit chamber
makes organic compounds and light matters float. Aerated grit and grease retainer will be
composed of two lines, each of which will be constructed in stage one, and each of them
will be capable of handling the maximum flow in stage two.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
25
Primary Sedimentation Tank
Primary sedimentation tanks will be rectangular. In stage one, two primary
sedimentation tanks will be constructed, and one additional tank will be constructed in
stage two. Settling sludge will be scraped, and directed to sludge digestion unit.
Activated Sludge Tanks
Activated sludge tank is proposed to be rotary flow in order to achieve an effective
nitrification / denitrification process. Each tank will include a central wall which separates it
longitudinally. Rotation of flow will create serial aerobic, anoxic and anaerobic conditions.
Stage one will include two tanks, and one tank will be added for stage two.
Pressurized air is supplied to aerators by means of collection and distribution
pipes. Pressurized air is distributed in activated sludge section by thin bubble membrane
aerators. A separate mixing and aeration process ensures maximum oxygen input. Mixing
makes air bubbles stay longer as attached to wastewater rather than float to surface, and
this increases transfer of oxygen.
Secondary Sedimentation Tank
Flow will be directed to secondary sedimentation tank after it is processed in
aeration tanks. In stage one, two secondary sedimentation tanks will be constructed, and
one additional tank will be constructed for stage two. Wastewater will be fed to secondary
sedimentation tanks from bottom, and they will be equipped with a bridge scraper. In case
one of three tanks is out of operation in stage two, the remaining two will sustain the
process. Activated sludge will be separated from clear effluent, and activated sludge will
be recycled.
Primary Sludge Thickener
Primary sludge thickener is the first component of the sludge thickening process
and it will make the sludge to settle by gravitational force and directed to digester. Primary
sludge thickener functions as a storage tank besides thickening. Hydraulic retention time
in sludge thickener is one day. Effluent of sludge thickener is recycled back to the WWTP.
After the thickening the solid content of the sludge will be between 4 to 6 %.
Gravity Belt Thickener
Secondary sludge which is coming from the secondary settling tank and having
approximately 0.8 % of solid content is less dense than primary sludge which is coming
from the primary settling tank and having approximately 2 % of solid content.
Waste matters will be thickened before pumping to digester in order to prevent the
content of digester from being diluted with less dense solid matters. Sludge thickening
process will take place in dewatering unit, which is equipped with a gravity belt thickener.
Polymer will be added as the dewatering agent as secondary sludge is fed to gravity belt
thickeners. Solid matter will be pumped to digester for treatment. Anaerobic digester
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
26
functions very effectively with an input of 5-8% solid matter. Manufacturers state that
mechanical thickeners are capable of operating with a solid content between 5 – 10%
while it is 3 – 4% in gravity thickeners. Moreover, mechanical thickeners enable the
control of sludge density whereas it is considerably difficult in a gravity thickener. Sludge
content will be 5% after thickening. Sludge thickeners will be installed in the thickening
and dewatering building.
Anaerobic Sludge Digester
Primary and excess sludge will be pumped into the digester sludge recycle line,
and pass through the external heat exchanger, in which it is heated up to 35°C. Sludge
mixture in the digester will be obtained by mixing digested sludge with incoming sludge,
and the temperature will be kept constant everywhere in the digester to provide an
effective microbial activity.
Mixing will also disperse the foam formed on the surface of water in the digester.
Mixing in the digester will be achieved either by a mechanical way or by gas diffusion
systems. Digested sludge (with 50% solid matter) will be drawn from the bottom of the
digester, and directed to the secondary thickener.
The digester is a cylindrical structure with conical top and bottom. Water
Temperature inside tank should be 35°C, and retention time in the anaerobic tank will be
10 – 20 days. The design value is 17 days.
Secondary Gravity Sludge Thickener
After the anaerobic digester, the digested sludge will be taken into a tank equipped
with a special mechanism similar to the secondary sedimentation tank. Thickener will be
fence-type, and it will be installed in a building which will also house sludge dewatering
machines. Dry matter content will be at least 25% in these units.
Sludge will be thickened in mechanical thickeners, and then dewatered in sludge
dewatering units. Sludge cake is transferred to sludge storage site by belt conveyor.
Sludge Dewatering
Digested sludge will finally be dewatered in the belt filter press. A belt filter pres
has single or multiple moving belts to dewater sludge by means of both gravitational
drainage and compression. Solids are dewatered by a three-phase process: chemical
conditioning, gravitational drainage and compression with cutting.
Capacity of the belt filter press is determined by hydraulic and solid matter loading
rates. Hydraulic loading rate of the belt filter press is 0.08 – 0.20 m3/min-m, and its solid
loading rate is 180 – 320 kg/h-m. Filtrate from the belt filter press will be pumped into the
filtrate storage tank and directed to the inlet of the aeration tank of WWTP.
Amount of dewatered sludge at 15
Sludge density will be 800 kg/m3.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
27
Polymer conditioning units are composed of chemical measurement pumps,
polymer storage and mixing equipments, polymer and solid matter mixers and a control
unit. The polymer to be used at the WWTP will be selected by the contactor. According to
the information published by a polymer manufacturer
(http://www.snfturk.com/tr/teknik.asp), these polymers are not toxic for human. Moreover,
they are not corrosive and they are biologically degradable. Measurement pumps
generally include a positive displacement membrane, a rotary lobe or porous. Variable
frequency motor provides varying polymer feed. Dimensions of polymer storage shall be
suitable for transfer of unpacked material.
Sludge Storage Site
Sludge will be suitable for agricultural use provided that the requirements of Soil
Pollution Control Regulation is fulfilled. The requirements are that the stabilised sludge
shall not include heavy metal exceeding the limits of Appendix I-B in the regulation.
Details of this regulation is explained under the title of “Sludge Management”.
However, since sludge can only be used in 8-9 months of agricultural periods in a
year, a storage area shall provide three – month storage. Sludge storage area is concrete
– covered and outdoor. The sludge filtrate will drain into a filtrate pumping station. On the
other hand if the sludge does not meet the requirements of the regulation, then the sludge
will be deposited in the lanfill area.
As the amount of dewatered sludge at 15°C will be 25 ton/day in 2042, sludge
density will be 800 kg/m3 and the sludge height is selected as 2 m. Storage area shall be
designed according to storage periods of 90 days. Therefore, minimum land requirement
will be 1,500 m2 (30 x 50 m). In the Conceptual Report that has been approved by Iller
Bank, the height of the sludge deposited is deremined to be 2 m., it is not possible to be
changed. Then the required storage area is calculated as 1500 m.
Biogas and Cogeneration
Dry and low – pressure gas tank will be employed to store the digester gas that will
be utilized in the cogeneration system and the heater. The digester gas, being fed from
the low– pressure tank is combusted in two continuously operating combined heat and
power (CHP) units. The amount of gas to be produced in the WWTP is 2408 Nm3/d for
the year of 2022. This gas will be pumped to the cogenerator and used as fuel to produce
heat and electricity
Heat, as another energy source, will be generated during the entire combustion
process. Heat will be utilized in several ways. Heat dissipated from the exhaust is
benefited in gas – liquid exchanger, which is a part of the cooling cycle of the
cogeneration system. The cooling cycle achieves heat exchange directly from the engine,
and the cooling cycle keeps the temperature between 35 – 40 °C by means of a liquid –
liquid heat exchanger. Temperature in the digester should be within this range for the
digestion process to be sustained. Heat generated in cogeneration unit will also be utilized
for heating system in the facility Shematic view of the cogeneration system is given in
Figure 7.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
28
Figure 7. General View of Cogeneration System
The flow chart of WWTP process is presented in Appendix-B.
“Project Approval” for the PROJECT will be acquired by the MoEF in 2008.
Discharge of Treated Wastewater
Enhanced technology in wastewater treatment and disposal processes ease
production of effluent with desired discharge quality. Besides this, quality of effluent is
dependent on investment for the wastewater treatment plant.
Pollutants in the water treated according to public health criteria are mainly
biological and chemical matters. Reuse and discharge of wastewater requires improved
quality of the final effluent. Possible applications may be:
Irrigation water (inedible plants, plants that can be eaten when cooked, plants
that are eaten raw) and landscape works (direct contact and no direct contact)
Groundwater feedback
Industrial use
Reuse as drinking and service water
Reuse of the wastewater lessens the impacts on fresh water resources that arises
from demand. In addition to this, since the amount of untreated discharges will decrease,
there will be less impact on aquatic life. Investment costs should be considered to be low
to medium for most systems. Operation and maintenance is easier except direct reuse
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
29
systems that require more improved technology and quality control. Supply of wastewater
with mor nutrient content will increase agricultural yield.
Reuse of wastewater may be seasonal due to overload in treatment and disposal
within periods of heavy precipitation. Seasonal discharge of wastewater will be possible
provided that duration of precipitation is longer and/or precipitation is dense. Waterborne
diseases and skin diseases may be observed upon direct contact with reused wastewater.
Different alternatives were evaluated for discharge of treated wastewater in the WWTP.
As a result of assessments, Percolation of treated wastewater to underground at
discharge site and pumping the rest amount to the forestry areas, if needed, are made
turned out to be feasible (see Figures 8 and 9). Detailed information about the alternatives
and difference of this method from other alternatives are given at the end of report in
‘Addendum’ Section.
The wastewater stored in the abandoned sand and gravel quarries having
approximately 1.1 million m3 in volume may be utilized as irrigation water in forestry areas,
recreational areas and agricultural areas upon acquisition of necessary permits from the
Mugla Provincial Directorate of Environment and Urbanization. According to the Technical
Methods Comminique of the Water Pollution Control Regulation. This volume of the
quarries is almost sufficient for depositing treated wastewater about 8-9 months. In the
remaining time the treated wastewater is discharged to the receiving water bodies. If the
requirements of the regulation is not fulfilled then treated wastewater will only be utilised in
the irrigation of forestry areas and recreational areas.
Figure 8. A View from the Abandoned Sand and Gravel Quarry Area.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
30
Figure 9. Excavations at the Abandoned Sand and Gravel Quarry Area
Discharge permit will be acquired from Mugla Provincial Directorate of
Environment and Urbanization.
As it is declared above, different alternatives for discharging treated wastewater of
Mugla WWTP were evaluated.n 2008, Project Introduction File (PIF) was prepared
according to Turkish legislation and approved by Provincial Directorate of Environment
and Forestry (PDoEF). In PIF stage, General Directorate of State Hydraulic Works (DSİ)
permitted for infiltration, evaporation and storage of treated wastewater in proposed
abandoned sand and gravel quarry on the Yaraş Road.
In 2011, another study was carried out and new alternatives were evaluated upon
the request of World Bank, which is actually the reason for preparation of this revised
report. After the evaluation of the all alternatives, the alternative , which is “percolation of
treated wastewater to underground at discharge site and pumping the rest amount to the
forestry areas” was proposed to be most feasible solution for Mugla Municipality from
initial investment and yearly operational costs point of views. Yearly operational costs of
the considered alternatives are really very high for a small Municipality, like Mugla.
Therefore, in the comparisons, sustainability of the proposed solution from economical
point of view is also considered. From environmental point of view also, disposal site will
serve as a filtration unit and this will help improving water quality to be mixed with
Karabağlar aquifer.
Alternative 4 has also matched with the proposed solution in Approved Project
Introduction File.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
31
Arrangements in disposal site and slope stability investigations were done in order to
effective and long-term use according to selected solution. Within this scope, slope
stability analysis is made and results can be seen in Annex-3 of Appendix-H. Before
starting discharge stability of the slopes will be formed. For this reason, operation of
disposal site is divided into two parts, which are: short term operation period and long
term operation period.
When we take the long term operation period as a base for slope stability
analysiss some solutions were discussed and the solution which is “doing nothing
except expropriation of risky areas around the top of the slopes” has become the most
feasible and reasonable option with respect to rough cost estimations with approximately
142,500 Euro including fencing and replacement of village road. In this alternative
approximately 50 m land from each side will be expropriated and slopes will be formed
naturally. As the risky area is fenced, there will be no risk because of slide of the slopes
(Figure 1.8 in Annex 1, Appendix-H).
As explained above, treated wastewater will be discharged to Disposal Site. The
plan is to use the site for balancing the discharged water amount through infiltration,
evaporation and storage for the other purposes processes. To see and evaluate the
balancing capacity of the Disposal Site water balance calculations, prepared for 2012-
2015, 2020, 2025, 2030, 2035 and 2040 were done (see Table 4.1 in Annex 4.1,
Appendix-H).
According to Table, in 2020 water balance turns to positive, this means treated
wastewater starts to accumulate in Disposal Site and therefore after 2015 a system
should be put into operation for discharging stored wastewater in disposal site. In the
beginning, the capacity of the discharging system can be small but towards to 2040 the
capacity should be increased up to 14,500 m3/day.
Irrigation of green areas, irrigation of forestry areas, irrigation of agricultural areas
and risks under flooding conditions are reviewed in detail in Appendix-H.
In addition to this, as stated in Administrative Procedure Communique of
Regulation (Official Gazete dated March 12, 1989 and numbered 21106), since inflow to
the WWTP is greater than 10,000 m3, daily samples will be taken from the outlet of WWTP
and according to Table 21 of Water Pollution Control Regulation (Official Gazete dated
December 31, 2004 and numbered 25687), SS, BOD, COD and pH analysis will be
conducted.
Sludge Management
Final disposal of sludge generated in wastewater treatment plants is a major
problem. Therefore, a sludge management plan shall be prepared by the CONTRACTOR
at the beginning of the operation phase and reviewed and approved by the Environmental
Consultant. designed for final disposal of sludge. Several methods are under examination
for sludge disposal, and these are:
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
32
1. Agricultural use as fertilizer after composting and preliminary pasteurization
process,
2. Drying by solar energy and use as filling material in cement plants,
3. Laying on ground to enrich soil and forest areas, parks and green lands,
4. Combustion in a combustion plant after drying by solar energy and storage of ash,
5. Storage with lime stabilization.
Disposal of sludge according to methods 1, 3 and 5 may be preferred in terms of
sustainability. However, the “Soil Pollution Control Regulation” shall be complied with.
According to this regulation, the stabilized sludge to be generated in WWTP will be
analyzed in terms of the parameters stated in Annex I-A (b), Annex II-A and Annex II-B
These analyses must be carried out in laboratories that are accredited by considering the
principles given in Annex IV Summary of the Soil Pollution Control Regulation is also
presented in Appendix-A along with the relevant annexes.
The heavy metal content of the stabilized sludge must not exceed the
concentrations presented in Annex I-B.
The sludge generated from domestic wastewater treatment plant can be utilized for
agricultural purposes if it the content of the stabilized sludge does not exceed the limit
values presented in Annex I-B.
If the daily sludge generation of the treatment plant is less that 50 tone in dry
basis, the analyses of sludge must be repeted once every six months considering the
parameters given in Appendix II-B. If the daily sludge generation is more than 50 tones in
dry basis, these analyses must be repeated once every three months.
The owner of the sludge generating facility must apply to the Governorate of the
Province in order to take the permit to make the sludge used for agricultural purpose. The
application is evaluated by a commission including the members of Provincial Directorate
of Environment and Urbanization, Provincial Directorate of Agriculture and Rural Affairs,
General Directorate of State Hydraulic Works and Provincial Directorate of Health.
The commission evaluates the use of sludge on soil in terms of heavy metal load,
impacts on physical quality of soil and impacts on surface and groundwater resources. If
the commission decides that these impacts are negligiable, then the permit is for the use
of sludge for agricultural purpose is given.
The operator of the treatment plant is responsible with the analyses and the
records of the sludge.the records of the sludge must include the resultd of sludge
analyses, the method applied for stabilizing the sludge, the amount of sludge produced
and the amount of sludge utilized for agricultural purposes. These reports will be
presented to the Governorate of the Province.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
33
If the sludge will not be utilized for agricultural purposes and if it is not considered
to be a hazardous waste according to the analyses conducted as explained in the
previous paragraphs, then the sludge will be disposed to the landfills.
If the sludge is considered as hazardous wastes, they have to be sent to the
hazardous waste landfills or hazardous waste incinerators.
The Minisry of Environement and Foresty are responsible with the auditing the
compliance to this regulation.
4.1.6. Personnel
There will be 70 employees in the construction phase of the WWTP.
MUNICPALITY will decide on number and qualifications of employees that will be
hired during the operational phase of the WWTP. Currently estimated number of
employees is given in Table 10 along with qualifications of employees.
Table 10. Number of Employees of the Operational Phase
TASK Count
Engineer 3
Electrical-Mechanical Technician 2
Laboratory Technician 1
Qualified Employee 4
Security Guard 3
Secretary 1
Total 14
4.1.7. Settlement of Temporary Personnel
Temporary housing for the construction workers will be established near
construction site. This area will be restored after completion of WWTP construction
facilities. Main building in the construction site, settlement of employees, car park and
storage area will cover 2,000 m2 of area.
The waste handling issues related to the temporary housing for the constructional
worker such as sewage management, and garbage disposal services are explained in
Sections 6.1 and 6.2.
4.1.8. Type and Number of Construction Machines to be Used
Table 11 presents the type and number of construction machines that will be
employed in the scope of the PROJECT.
Table 11. Machinery to be Used at Construction Phase
Machine Count
Loader 2
Excavator 2
Compactor 1
Dump Truck 4
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
34
Machine Count
Concrete Pump Truck 1
Transmixer 3
Truck Crane 1
Water Truck 1
Car 1
Pick-up 2
4.2. UTILIZATION OF NATURAL RESOURCES (LAND AND WATER UTILIZATION,
TYPE OF ENERGY UTILIZED ETC.)
4.2.1. Land Use
The Project Site lies near Hamursuz Hill, Ortakoy and Dugerek, and covers 5.8 ha
of area, 2.5 km on the southeast of the city center. In addition to this area, there is 2,000
m2 of area to be used for establishment of construction and settlement facilities, car park
and storage site. Expropriation of the whole area has been completed.
4.2.2. Water Utilization
There is water utilization to meet employees’ needs in both construction and
operational phases of the PROJECT. Number of employees in the construction phase will
be 70. Assuming that water consumption will be 150 L/cap-day, daily water consumption
will be 10.5 m3 (70 people x 150 L/cap-day).
By same manner, there will be 14 employees to be working in the operational
phase, and daily water consumption will be 2.8 m3 (14 people x 200 L/cap-day).
Water demand for cleaning and bathing in the construction phase will be supplied
from water wells to be drilled nearby or from the water network of the city. The water
supply of the city is clean enough as the municipality must fullfill the drinking water
standards stipulated by Regulation on Potable Waters (see Section 3.1). Drinking water
will be provided from either water supply network or private drinking water supplier.
Selection of water source is the decision of the CONTRACTOR.
Necessary permits will be acquired from the General Directorate of State Hydraulic
Works (SHW) if water wells are decided to be drilled.
4.2.3. Energy Utilization
Energy demand of the WWTP will be supplied from the present electricity network.
4.3. PROJECT SITE
Project Site lies at the center of Mugla Province as shown in Figure 10. It is
located 2.5 km southeast of the city center at the eastern skirts of Hamursuz Hill, near
Ortakoy and Dugerek (see Figure 11).
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
35
Figure 10 Project Location
Figure 11 Satellite View of the Project Site
Map section and parcel numbers of the land where the PROJECT will be located is
56/903 and 117-118, respectively. Information about borders and coordinates of the
Project Site is given in Figure 12 and Table 12, respectively.
Hamursuz Tepe
Project
Site
N
PROJECT
SITE
Hamursuz Tepe
Project
Site
N
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
36
Figure 12. Borders of the Project Site
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
37
Table 12. Coordinates of the Project Site
Point Coordinates
Y X
P.1673 31870.950 28603.380
172001 31690.470 28631.670
172052 31672.260 28750.290
903034 32097.040 28811.770
903035 32052.760 28793.240
903036 32035.000 28787.630
903037 32001.200 28786.500
903038 31994.360 28836.580
903042 31891.060 28868.390
903043 31872.000 28809.330
903044 31930.940 28798.100
903045 31995.030 28687.850
903046 31962.560 28688.910
903047 32002.400 28663.460
903048 31897.080 28694.890
903049 31857.010 28710.190
903050 31834.910 28728.180
903051 31762.820 28728.540
903053 31702.780 28551.470
903054 31796.050 28528.650
903055 31869.750 28522.390
903056 31940.450 28518.120
903057 31997.780 28586.140
903058 32003.740 28533.630
903059 32003.170 28513.460
903083 32103.300 28691.440
903351 31712.220 28577.850
The Project Site covers 5.8 ha area. During the construction phase, 2,000 m2
areas will also be utilized temporarily for construction activities such as temporary
buildings, car park and storage facilities.
4.4. GEOLOGICAL CHARACTERISTICS
4.4.1. General Geology
The Mugla Plain, which is a closed basin, is drained by sinkholes present in it. Its
geological characteristics were defined in “Study for Mugla Plain Sinkholes Improvement”,
prepared by the Aydin Regional Directorate of the State Hydraulic Works (SHW) in 1996.
Mugla Plain lies in a region where shield sediments of the Menderes massive are
outcropped. Core rock of the Menderes massive is observable along the state road
connecting Aydin to Cine. Shield sediments are observed in Mugla Plain. Allochthon rocks
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
38
have been placed along a direction from South to northeast of Mugla Plain by dislodging
sediment activity. Hence, there is rock of allochthon and autochthon type accumulated in
Mugla Plain and its vicinity.
There are rock units, wide-spread in Mugla Plain and its vicinity, in the autochthon
deposit with a comprehensive lithologic composition, and they are given as follows. There
is Palezoic-aged metamorphic schist including thin calc schist layers, and above this,
there is Jura-Cretace-aged Milas Formation, represented by limestone and dolomitic
limestone. The Koprucay Formation, containing conglomerate and limestone, overlies
these rocks, which are outcropped in a wide area, by transgression. The Yatagan
Formation, which has lateral transition with the Koprucay Formation, is younger, has
relatively higher clast content. The top sedimentary units of the autochthon deposit are the
wide-spread alluvion and slope deposit.
Tectonic melange is the bottom most unit of the allochthon deposit which is
present as dislodged onto the autchthon deposit. This unit is observable as a chaotic rock
unit developed through dislodging, and is outcropped with various characteristics. Gulluk
Formation lies over this unit, and stratigraphically forms the bottom of allochthons. The
Gokova Formation, a metasedimentary deposit, overlies this formation with transitive
texture, and the Caydere Formation overlies both (see Figure 13).
These rock units are explained as follows. Furthermore, geological map of the
Project Site is shown in Appendix-C.
I. Autochthon Rock Units
Late Cretace-Paleocene Limestone Chert limestone
Mesozoic Limestone-Marble
Palezoic Schist-Gneiss
I.A. Schists (Pzs)
The schist group metamorphic rocks of the Menderes massive constitute the
impermeable bedrock in the area that the study was carried out. The unit, composed
mainly of phyllite, chloroschist, calc schist, quartz schist and quartzite, is observed on the
surface near Yesilyurt in the west of Mugla Plain. It forms the impermeable lower
boundary by underlying limestone at an angle of 10-20 degrees towards east. Considering
the structural position of the autochthon deposit in the vicinity of Mugla, schist is at a
higher elevation in the vicinity of Akcaova in the west of the plain.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
39
Figure 13. Geological Cross-Section
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
40
I.B. Milas Formation (Mzm)
Limestone units are the units that constitute the surrounding and underground
geological structures. The carbonate rocks overlying schist concordantly are mainly
composed of dark and fair grey, white rigid limestone and dolomitic limestone. The
sections surrounding the plain with higher altitudes are occupied by the limestone of the
Milas Formation. Hamursuz Hill is composed of this limestone. Position of Hamursuz Hill
in the plain denotes that an early paleotopographic threshold was present in this section.
Outcrops and geometry of the Milas Formation is controlled by faults. Alluvium
settled in sections of the plain with lower altitude, and the surrounding higher-elevated
sections were formed by strength of the Milas Formation.
The Yatagan Formation and the Koprucay Formation overlie the Milas Formation
belonging to the autochthon deposit. These two units of late deposit, presenting lateral
and vertical transitions, filled paleotopographic empty spaces.
I.C. Kopruçay Formation (Tk)
This unit, outcropped wide-spread between Mugla and Gokova Bay, is mostly
composed of conglomerate and conglomeratic limestone. It is wide-spread in northern
sections of Mugla Plain with altitudes higher than 1,000 m. There is an outcrop at an
elevation of 650-700 m in the northern part of the plain near Abdullahpinar. The vertical
difference in altitudes of the two outcrops is considered as net slip, and it is important as
far as the evolution of the plain is concerned.
I.D. Yatagan Formation (Ty)
Clastic Neogene sediments, observed near Yatagan, have developed in
paleotopographic ditches as facies. There is a narrow and long outcrop, which appears as
paleotopography-fill in the east of the plain. The Yatagan Formation’s being expanding
beneath the plain is an evidence for presence of a doline that has been developing since
the Neogene. Alluvium lies over the Yatagan Formation in the east of the plain.
I.E. Alluvium (Qal)
Ascension due to faulting around active tectonism in the plain resulted in a rapid
sedimentation of alluvium. Material transported from locations with higher altitude filled the
plain. It mostly includes coarse and clasty grit and gravel. Coarse clast-sediments appear
in the western sections of the plain, and thin clast-sediments appear in the east.
According to data in hand, there is thin clast-silt and clay in lower layers of alluvium, and a
coarse clastformation has developed in upper layers. Alluvial cones developed through
deposition of material that was transported from locations with higher altitudes, and they
are densely observed in the east and the northeast of the plain. Former and present slope
has considerably developed especially along the northern border of the plain.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
41
II. Allochthon Rock Units
Late Cretace-Paleocene Ophiolite
Eocene Gritstone, Mudstone, Conglomerate, Limestone
Mesozoic Limestone
Permian Conglomerate, Gritstone, Shale, Clay limestone
Late Cretace Tectonic Melange
There are allochthon units located in a dislodging zone along northeast-southwest
in the eastern part of the plain, and beneath these allochthon units there is tectonic
melange (see Figure 14).
II.A. Tectonic Mélange
This is chaotic unit that typically presents impacts of tectonism beneath dislodging
zone. Various lithologic structures are present in an ophiolitic matrix. The outcrop width of
tectonic melange varies depending on the relationship between allochthon and
autochthon and the characteristic of dislodging zone. For instance, although there is no
outcrop of tectonic melange in the eastern section of the plain, outcrops are considerably
dense in the north and south of the plain. Nature of tectonism accounts for its absence in
the outlet of the plain.
II.B. Gulluk Formation
Allochthon is the bottom unit in the stratigraphic deposit. Allochthon forms the
impermeable basement of the deposit. It is mainly composed of conglomerate, gritstone,
shale and limestone. It has undergone a significant cataclastic deformation. It is observed
in Gulluk near Milas, and is 1,000 m thick. This formation includes wide-spread outcrops
in the southeast of Mugla Plain. Due to its impermeable lithology, it is a barrier in front of
the plain and an important building block developing the plain. The faults of the Gulluk
Formation border the plain near Abdullahpinar and Kurtlar, and there is limestone
belonging to the Gulluk Formation lies in the North of the valley.
II.C. Gokova Formation
The unit that concordantly overlies the Gulluk Formation is composed of carbonate
rocks of allochthon deposit. It is represented by dolomitic limestone which is fair grey at
the bottom and relatively darker in upper levels.
It has developed next to the Gulluk Formation in the east of the plain. It is
widespread towards east.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
42
Figure 14. Generalized Stratigraphic Cross-sectional View of Allochthon Deposit
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
43
This unit, wide-spread from Kurtlar to Gokova Bay in the east of the plain,
constitutes the reservoir rock of the groundwater basin of Gokova. The limestone,
outcropped near Kurtlar, is the closest point in Gokova reservoir to the plain. allochthon
limestone and the limestone in Mugla territory are in contact.
4.4.2. Local Geology
The dolines present in the study area has formed through interactions with each of
the carstic pores of the Mesozoic limestone. The SHW has drilled four foundation drilling
wells around the Doline I and II in 1990 to examine development of carstic pores in
vertical direction.
Data obtained through this study is summarized in Table 13.
Table 13. Information on Foundation Drilling Wells
Drilling Well AR-1 (42681) Drilling Well AR-2 (42682)
Well Depth (m) 100 Well Depth (m) 100
Well Altitude (m) 625 Well Altitude (m) 628
Lithology 0-100 m Limestone Lithology 0-100 m Limestone
Depth 0-8 m
8-20 m 20-34 m
34-100 m
Permeability 4,3x10
-4
1.1x10-3
6.5x10
-5
10-6
Depth 0-8 m
8-20 m
Permeability 10
-5
10-5-10
-6
Core Length (m) 66 Core Length (m) 94
Core (%) 66 Core 94
Drilling Well AR-3 (42683) Drilling Well AR-4 (42684)
Well Depth (m) 71 Well Depth (m) 250
Well Altitude (m) 638 Well Altitude (m) 640
Lithology 0-49 m Slope Debris
49-71 m Chalky Limestone Lithology 0-250 m Kireçtaşı
Core Length (m) 42.5 Core Length (m) 184
Core (%) 59 Core (%) 73
According to data obtained from this study, there is a carstic region, which
developed 34 m along vertical direction, in the well AR-1, the limestone present along
vertical direction is impermeable, and there is not a well-developed carstic section in AR-
2. There is no adequate information obtained by examining the AR-3 and AR-4. However,
there were cave-like spaces in the AR-4, and this implies that there is not a major carstic
zone here (SHW, 1996).
There are three stratigraphic deposits in Mugla Plain, and these are the
authochthon deposit, the rocks constituting the Menderes Massive, the allochthon deposit,
rocks belonging to nappes of “likyen” that were dislodged sediment and late deposit called
the neotochthon deposit. Detailed geological information for the Project Site and its vicinity
and the geological map are presented in App- B.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
44
I. Autochthon Rock Units
Late Cretaceous Paleocene Limestone – Chert limestone
Mesozoic Limestone - Marble
Paleozoic Schist – Gneiss
Paleozoic (Gneiss-Schist): The unit constituting the core of the Menderes
Massive lies in the north of Mugla, and it is outside the Project Site.
Mesozoic (Limestone-Marble): It overlies schists of the Menderes Massive
gradationally. It has a solid, compact and dolomitic structure and dark grey, fair grey and
white color. It constitutes the northern slopes of the examination area. It is bounded by the
schist at the bottom and the overlap in the south and southeast. It forms topographic
heights in Kurdu Mountain, Kaleli Mountain and Marçal Mountain. It houses several carstic
formations due to its highly carstic structure. Limestone is orderly stratified. There were 36
slope-projected measurements between the Sinkhole- 1 and Sinkhole 2. According to this,
locations of plates are northwest / northeast and northeast / southeast.
Late Cretaceous – Paleocene (Limestone – Chert limestone): This forms the
upper unit of authochthon deposit. There is no detailed information since no samples of it
were observed in the examination area.
II. Allochthon Rock Units
Late Cretaceous - Paleocene Ophiolite
Eocene Gritstone, Mudstone, Conglomerate, Limestone
Mesozoic Limestone
Permian Conglomerate, Gritstone, Shale, Clay - limestone
Late Cretaceous Tectonic Melange
Tectonic Mélange (Serpentine, Limestone and Gritstone Blocks): They have
been present in the region since nappes were dislodged. They are typically observed in
the south of Mugla. It is composed of limestone and gritstone blocks in serpentine.
Permian (Conglomerate, Gritstone, Shale, Clay limestone): It forms the lower
units of allochthon deposit. It is mainly composed of conglomerate, gritstone, shale and
clay limestone of various sizes. The dominant color is reddish purple and brown. Shale
grades are grey, dark grey and greenish grey. Archosic gritstone and conglomerates have
distinctive purple color. Limestone has a fair grey and white color, and contains a great
amount of striped cherts. It is highly permeable due to its carstic structure.
Mesozoic (Limestone): Mesozoic limestone of white, grey and black color
overlies the Permian concordantly as massive, thick-layered, dolomitic with chert. It is
highly permeable due to its carstic structure.
Eocene and Cretaceous: It is Miocene and Pliocene sediments that cover
autochthon and allochthon units discordantly in the region.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
45
4.4.3. Tectonics
The structures in this region (Southwestern Anatolia, Lycia) were formed as a
result of two successive deformations. These are
Horizontal Movements: Resulted in curved and bended brick-like structures with
sizes varying from few meters to few kilometers and overlying each other.
Vertical Movements: As a result of these types of deformations, some land
sections ascended while some were descending. This resulted in formation of major
faults. There are subsidences and uplifts caused by these faults. Compression tectonics is
the most effective system from north to south.
4.4.4. Hydrogeology
Sinkholes were formed as a result of carstic structure in Mugla Plain. The plain
becomes a lake as there is precipitation over the drainage capacity of the plain, and it
starts to dry up as arid period begins. An area of 6,300 decares became lake in 1976, and
this was reduced to 3,200 decares by measures taken by the SHW. In order to reduce this
area to 800 decares, the measures given below are suggested to be taken in the “Study
for Mugla Plain Sinkholes Improvement” along with construction of a flood retarding dam
and a precipitation dam.
1. Preservation of the facilities constructed at the discharge points of Sinkhole 1 and
Sinkhole 2, and proper functioning of sinkholes should be ensured.
2. Debris on the limestone lying below the maximum water surface elevation of 617
m between sinkholes will be removed for formation of new sinkholes.
3. There should be two 50-m long drifts that will be opened considering layer
direction and slope of the limestone lying below altitude of 617 m between
sinkholes.
4. If there are no satisfactory results obtained through observations, broad drilling
wells with depth of 50 m should be opened.
There are two zones in the Project Site to hold groundwater:
Bahçeyaka Zone: this is the region, which lies by the road branching from the state
road between Yatagan and Mugla to Bahçeyaka Village, housing several drilling wells for
water supply. This zone is composed of quaternary alluvion, clay, soil and gravel blocks.
Thickness of the alluvion varies between 80 and 100 m, and the groundwater level is
between 35 and 40 m.
Orta Yaras Zone: Gokova Formation (limestone – dolmitic limestone) as aquifer
and conglomerate and clay limestone layers of Gulluk Formation was observed to be
present in this zone.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
46
According to literature survey, there are no geological structures of particular
importance and no underground assets in the Project Site.
4.4.5. Seismicity
The earthquake map of Mugla is given in Figure 15. According to this map
prepared by General Directorate of Disaster Affairs, the Central District and the Project
Site lie within the zone that has first degree earthquake risk which means the region is
seismically very active. Active faults around the Project Site are shown in Figure 16.
Figure 15. Earthquake Map of Mugla Province
Source: www.deprem.gov.tr
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
47
Figure 16. Active Fault Map
4.4.6. Natural Disasters
There is not a risk of natural disaster except risk of earthquake in Ortakoy and
Dugerek, flood risk in sinkholes. Moreover, ponding, the creation of a temporary lake on
the area, discharge of which is supplied by sinkholes, are another problem (Mugla Centre
Prospective Land Use Development Plan, 2004).
4.5. CLIMATIC CHARACTERISTICS OF THE REGION
The Mediterranean climate prevails in Mugla Province. In addition to the effect of
sea and altitude, topography also impacts on climatic characteristics of the region. Due to
Mediterranean climate and latitude effect, temperature is moderate in coastal areas and
low in mountainous parts in the winter.
The meteorological data recorded in the Mugla Meteorological Station, the closest
meteorological station to the Project Site, were assessed to determine the climatic
conditions of the region. General information about this station is given in Table 14
whereas detailed long-term meteorological data are presented in Appendix-D.
PROJECT
SITE
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
48
Table 14. Mugla Meteorological Station
Working Period 1975-2005
Latitude 37.13
Longitude 28.22
Altitude 646 m
Source:General Directorate of State Meteorological Works, Mugla Meteorological Station (1975-2004)
4.5.1. Precipitation
Amount of precipitation is high in summer, and low in winter due to Mediterranean
effect. Convective rain is observed in inland areas besides frontal rain
(www.mugla.gov.tr).
The long-term meteorological data recorded in the Mugla Meteorological Station
between 1975 and 2004 reveals that the amount of average annual precipitation is
1,161.5 mm. As seen from Table 16, most part of the precipitation is observed in winter
whereas in summer amount of precipitation decreases significantly. Amount of
precipitation is 637.3 mm in winter, and 40.9 mm in summer. Considering average
monthly precipitation, highest amount of precipitation is observed in December (251.6
mm) and lowest is observed in July (7.1 mm) (see Figure 17). Average number of days
with snow is 4.8, and number of days with snow cover is 2.2.
Figure 17. Monthly Precipitation
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
49
Table 15. Season-based Average Annual Precipitation Data
Season Average Total Precipitation Percentage
Spring 250.5 % 21.6
Summer 40.9 % 3.5
Fall 232.8 % 20.0
Winter 637.3 % 54.9
4.5.2. Temperature
As a characteristic of Mediterranean climate, air temperature is high throughout
the year. Average annual temperature is +14.9 oC. The minimum air temperature recorded
during the entire measurement period was -9.9 oC (February 9, 1976), and the maximum
recorded was +41.6 oC (July 6, 2000). Monthly variations in temperature are presented in
Figure 18. January is the coldest month with average temperature of +5.5 oC, and July is
the hottest with 26.2 oC. As seen from Figure 18, average monthly temperature curve for
Mugla is over +5 0C throughout the year. It is below +10 oC in only four months. Number
of months with temperature exceeding +20 oC is four. Temperature is in an increasing
trend from January to July, and it decreases from July to December.
Figure 18. Monthly Temperature Data of Muğla Meteorological Station (1975-2005)
4.5.3. Wind
Northerly winds dominate in Mugla due to topographic layout. The directions with
the prevailing winds are south, south west and east. Average annual wind speed is 2.2
m/s. Average counts of stormy days and days with powerful wind are 4.6 days and 50.7
days, respectively. North-northeast (NNE) is the direction of the fastest wind. The
prevailing wind direction is west-northwest with average speed of 3 m/s and its total
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
50
blowing number is 7060. The secondary prevailing wind direction is northwest (NW) with
2.5 m/s of average wind speed and its total blowing number is 3285.
4.6. GEOGROPHIC CONDITIONS
4.6.1. Topographical Structure
The mountains with perpendicular alignment to the Aegean Sea, plains lying
between them and peninsulas constitute the topographical structure of the region. The
major heights in the region are Sandıras Mountain (2,294 m), Goktepe (2,047 m) in the
north of Fethiye and Goktepe (1,892 m) in the north of the city center of Mugla.
There are valleys formed by Cine Creek and Akcay in southeast – northwest
direction. Plains with varying sizes lie in the southern part of the region due to lack of
streams since limestone prevails in geological structures, and is highly permeable. The
most important one among them is the Mugla Plain. It is a closed ditch in the southern
part of the region with 30 km of width, and 620 – 630 m elevated. The plain is surrounded
by elevated mountains, which are Kaleli Mountain (1,800 m) and Kurdu Mountain (1,600
m) in the north, Karadag (900 m) in the west and Derbent Mountain (900 m) in the south.
Hamursuz Hill lies in the middle of the plain, and its altitude is 780 m. The least altitudes
of topographical connections of the plain are 700 m. Late tectonism and vertical faults
have played an important role in the formation of the plain. The plain has connections with
its neighboring drainage basin at an altitude of 700 m in the east and west. The “Aydin –
Mugla Highway” in the west and the “Denizli–Mugla Highway” in the east are passing
through these connections points.
The Project Site lies in a flat and low altitude area. In order to get rid of the
accumulation of rain water, the Project Site will be elevated by 5 m through filling works.
4.6.2. Water Resources
There are streams called Degirmendere, Karamugla and Basmaci creeks flowing
through the city and their flow rates decreases significantly in the summer. The origin of
Degirmendere Creek is 4.5 km away from the city, and its flow rate is 50 L/s. The origin of
Basmaci Creek is 2.5 km away from the city, and its flow rate is 20 L/s. Flow rates of
these streams increase in flood periods.
Koycegiz Lake is the most important natural lake within the borders of Mugla
Province with a surface area of 65 km2 and depth between 1.5 – 5 m. It is 40 km away
from the city center. Besides this, there are some small lagoons at the coastal zone.
There are no major water resources at the Project Site and its vicinity.
4.6.3. Soil Condition
There are fields for agriculture with or without irrigation, forest zones, fruit gardens
and grasslands in the center of Mugla. Residential areas include soil with capability
classes of I, II, III, IV, V, VI, VII and VIII (Prospective Land Use Development Plan
Investigation Report, 2004).
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
51
4.7. SOCIAL CHARACTERISTICS
4.7.1. Population
The WWTP will serve for the settlements located at the city center of Mugla. The
population that will be served for in 2022 and 2042 was determined by utilizing census
results obtained by the Turkish Statistical Institute (TUIK) and data acquired from the
MUNICIPALITY.
The population of Mugla is 715,328 according to results of census in 2000 and
83,511 of this live in the city center, namely 12% of total (see Table 16). There are 11
districts6 in Mugla, and the city center is formally nominated as the “Central District”. The
Central District is the fourth largest district in terms of population.
Table 16. Population Distribution of Muğla and the Central District
Rural (%) Urban (%) Total (%)
Turkey 0.41 2.68 1.83
Muğla 2.03 3.04 2.40
Central District 1.10 2.08 1.60
4.7.2. Population Growth Rate
According to the data of TUIK for period between 1990 and 2000, population
growth rates of Turkey, Mugla and the Central District are 1.8%, 2.4% and 1.6%,
respectively. Distribution of population in Turkey, Mugla and the Central District is given in
Table 16. As seen from Table 17, population densities of Mugla and the Central District
are far below the average of Turkey.
4.7.3. Education
According to the data of 2000 for Mugla, literacy rate is 93%. It is 97% for male
population, and 89% for female population. There are 812 schools in Mugla, and their
distribution according to education levels is given in Table 18.
There is also a university in Mugla Province.
Table 17. Population Densities of Muğla and the Central District
Population (Year 2000) Surface Area
(km²) Population
Density Total Urban Rural
Turkey 67,803,927 44,006,274 23,797,653 769,604 88
Muğla 715,328 268,341 446,987 12851 56
Central District 83,511 43,845 39,666 1658 50
Source: TURKSTAT, 2000.
6 In Turkish administrative division, a district is the sub- governmental unit of a province governorship.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
52
Table 18. Distribution of Education Institutions with respect to Grade
Grade Number of Institutions
Early Childhood 314
Elementary Education 439
Vocational 59
Total 812
4.7.4. Transportation
The access road to the WWTP will be provided by a 2 km in length road, which will
be constructed by another Contractor If this road will be the stabilized type, the
CONTRACTOR of the PROJECT will then rehabilitate the access road by covering with
asphalt.
There is no railway transportation in Mugla Province. Airway transportation is
provided with the Milas–Bodrum Airport, 65 km to the northeast of the Project Site, and
with the Dalaman Airport, 65 km to the southwest of the Project Site. The 1,124 km long
coastal road created various natural bays and ports. The major ports in the province are in
Bodrum, Datca, Fethiye, Gulluk, Marmaris and Gocek.
4.7.5. Health Services
There is a public hospital with a capacity of 400 beds, a hospital of the
governmental social security institution, known as the SSK, with a capacity of 160 beds
and a private hospital with a capacity of 21 beds. The health institutions in the city are
listed in Table 19 below.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
53
Table 19. Health Institutions in the City Center
Name of Institution Bed Count
Mugla State Hospital 501
Bodrum State Hospital 77
Dalaman State Hospital 30
Datça State Hospital 26
Fethiye State Hospital 223
Köyceğiz State Hospital 42
Marmaris State Hospital 79
75.Yıl Milas State Hospital 173
Ortaca State Hospital 52
Yatağan State Hospital 51
Kavaklıdere District Hospital 10
Private Yucel Hospital 50
Private Ahu Hetman Hospital 36
Private Fethiye Letoon H. 50
Private Lokman Hekim Es. H. 35
Private Bodrum Hospital 38
Private Universal Hospital 94
Pirvate Güney Eye Hospital 11
Private Milas İzan Hospital 48
Private Ortaca Yucelen Hospital 31
Total 1657
There will be no infirmaries in the Project Site since it will be sufficiently close to
the city center, where the health institutions that may be utilized in an emergency case.
4.8. ECONOMIC CHARACTERISTCIS
Agriculture takes a major part in incomes of the province. The most important
agricultural products are wheat, barley, cotton, tobacco, olive, grape, vegetable, water
melone, feed crop and fruit along with animal products. Olive production is so important
that olive-processing industry is developed in Mugla. There are olive production fields and
olive oil plants in the province. Except these, there are marble processing plants and
various industrial activities within the borders of the province. However, these facilities are
out of the city center of Mugla and will not sent their wastewater to the new WWTP which
is the subject of this report.
Tourism is an important sector, which supplies a significant income to the
economy of the province, as well. Historical structures and natural beauties have
considerably developed the tourism sector in the province. The PROJECT will both
enhance public health by eliminating floods in septic tanks and reduce pollution in Gokova
Bay, and thus should improve tourism.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
54
4.9. ECOLOGICAL CHARACTERISTICS
Ecological studies are conducted within the context of this report in order to
identify flora and fauna specie of the Project Site and determine critically endangered
ones, if any, requiring special protection.
Desktop studies were conducted by reviewing the main literature sources in order
to obtain the ecological characteristics of Mugla and its vicinity as well as its floral and
faunal inventory. Furthermore, the IUCN Risk Categories were reviewed to identify the
category of the flora and fauna specie.
The following sources considered during the desktop studies are:
“Biodiversity Hotspots” identified by the Conservation International7
“Global 200” identified by the World Wide Fund for Nature (WWF)8
“Red List of Threatened Species” prepared by International Union for Conservation
of Nature and Natural Resources (IUCN)9
‘Biodiversity Hotspots’ are biologically rich areas that are under the greatest threat
of destruction and represent a variety of global ecosystems, identified on the basis of
three criteria: i) the number of species present, ii) the number of endemic species in an
ecosystem and iii) the degree of threat faced. The Project Site is located in Mediterranean
Basin, which surrounds the Mediterranean Sea. The basin's location at the intersection of
two major landmasses, Eurasia and Africa, has contributed to its high diversity
(see Figure 19).
Figure 19. Biodiversity Hotspot Map of Project Site
7 http://www.conservation.org/xp/CIWEB/ 8 http://www.panda.org/about_wwf/where_we_work/ecoregions/ecoregion_list/index.cfm
9 http://www.iucnredlist.org/
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
55
‘Global 200 ’ ecoregions are based on selection criteria such as species richness,
levels of endemism, taxonomic uniqueness, unusual evolutionary phenomena, and global
rarity of major habitat types. In terms of Global 200 ecoregions and habitat, the Project
Site is a typical Aegean and Western Turkey sclerophyllous and mixed forests which is
represented as PA1201 in Figure 20. This ecoregion is situated in parts of Turkey,
Greece, and the Aegean that enjoys a Mediterranean climate and encompasses islands,
coastal areas and some inland plains. As in all Mediterranean coastal areas, dense
human population, extensive settlements, and agricultural activities have largely
destroyed the natural habitat. Urbanization, conversion to agriculture, over-grazing and
illegal logging are the principal causes of destruction.
Figure 20. Global 200 Ecoregion Map of Project Site
Flora
The flora in Mugla includes variety of plant species. Mediterranean climate affects
a wide area in the province. Low temperature and precipitation is suitable for plants to
grow. Since drought is apparent, xerophytes formations were developed. These are called
“maquis formation”. There are needle-leaved forests in mountainous regions with higher
altitude.
There are pine forests with significant economic value, meadow mushroom, orchid
and orchids italica along with hygrophytes, specific to the Black Sea Region of Turkey,
and specie belonging to tropics in the shoreline.
Forest coverage is 15,119.5 ha in the Central District, and area without plant
coverage is 7,243 ha (www.ogm.gov.tr). Tree specie in the Project Site and its vicinity are
given below.
Project
Site
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
56
Juniperus excelsa
It is observed between altitudes of 300 and 2,300 m in arid and rocky habitats, and
they are usually 15-20 m tall. They can be observed in suitable habitats throughout
Turkey.
Quercus ithaburensis subsp. macrolepis
It is spread over Middle, Western and Southern Anatolia. Forest zone is
constituted by pine and oak, which is observed between altitudes of 50 and 1,700 m.
Pinus brutia
It is wide-spread in Turkey the most as compared to the rest of the world. It is
locally spread in Western and Middle Black Sea Region besides forming large forests in
Mediterranean and Aegean regions. There is an area of 3,729,866 ha covered by Turkish
Pine forest in Turkey. Turkish Pine can be observed between altitudes of 1,000 and 2,000
m. It is photophilic, and may grow as tall as 20 m. It was given this name because of its
young offshoots generally with dark red color.
Platanus orientalis
This species can naturally grow in alluvial soil, bottom of valleys and forests, and it
is observed at an altitude of 1,000 m. diameter of its body can be 10 m, and its height can
be 30 m. It has large palmate leafs and flowers forming spherical piles.
The majority of the taxa defined belong to the “Mediterranean Phytogeographic
Region” the Project Site lies in grid “C” according to the grid system invented by P. H.
Davis. The map showing the vegetation in Mugla and the Project Site is given in
Figure 21.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
57
Figure 21. Vegetation in Muğla and the Project Site
(Source: www.ogm.gov.tr)
As seen from Figure 21, the vegetation in the Project Site is mainly composed of
natural pine forest and Pinus brutia. Plant specie in the Project Site and its vicinity were
listed through site surveys and literature research. In addition to these, there may be
some missing specie in local flora researches considering floral richness of Turkey.
Therefore, all the identified flora specie presented in the “Flora of Turkey” was considered
in order to eliminate any missing species in the scope of surveys carried out. Besides
these, the “Turkish Plants Data Service”, prepared by “The Scientific and Technological
Research Council of Turkey”, was also made use of in compiling the flora list.
There is no specie, which are in danger, and need to be protected according to the
“IUCN Red List of Threatened Species 2007”, in the Project Site. Moreover, App.-I of the
Berne Convention, which Turkey also signed, does not cover any species in present in the
Project Site.
Latin names of the species along with relative abundance and endemism status of
each species are given in Table E.1 in Appendix- E.
Fauna
According to the decisions taken by the Central Hunting Commission for 2007 –
2008 Hunting Term, effective since publication in Official Gazette no. 26574 on 6 July
2007,
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
58
App.-I lists the specie that are protected by the Ministry of Forestry.
App.-II lists the specie that is protected by the Central Hunting Commission.
App.-III lists the specie that can only be hunted within periods determined by the Central
Hunting Commission.
According to the Decision of the Central Hunting Commission, hunting is restricted
in the areas described below. As seen from Figure 18, there are no areas defined as
“National Park”, “Natural Park”, “Nature Protection Area”, “Special Environmental
Protection Area”, “Wild Life Rearing Site” and “Wild Animal Settlement Site” within the
borders of the Project Site.
Ula District Mugla-Central District, Yaras, Kestanelik; eastern border: the line
connecting Damlacık Tepe, Yellibelen Tepe and Kestanelik, western border: the state
highway connecting Mugla to Marmaris, northern border: the line connecting Meseli Tepe,
Kuyugedigi and Dambası Tepe and the state highway connecting Mugla to Denizli,
southern border: the state highway connecting Mugla to Ula.
All the reptiles are listed in App. I of the Decision of the Central Hunting Commission, and
they are under protection (see Table F.1 in Appendix-F). Therefore, hunting and keeping
them is forbidden. Specie of mammals present in the Project Site and its vicinity are given
in Table 20.
Table 20. Specie of Mammals
LATIN NAME COMMON NAME CHC* 2007-2008 IUCN 2007** BERN
Sciurus vulgaris Chipmunk App.-I NT App.-III
Erinaceus europaeus Porcupine App.-I LR/lc App.-III
Hystrix cristata Crested Porcupines - LC -
Lepus europaeus Brown Hare App.-III LR/lc App.-III
Vulpes vulpes Fox App.-III LC -
* CHC stands for the Central Hunting Commission
** NT : Near Threatened
LR : Lower Risk
LC : Least Concern
Other specie of the local fauna (reptiles and birds) were assessed in terms of the
international conventions that Turkey signed, and are given Appendix–F. According to the
result of assessment of fauna species it can be stated that there are no rare or
endangered animals, reptiles, birds etc. that either are found at the Project Site or use the
site as a migratory route.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
59
Figure 22. Map of Hunting Zones in Mugla Province
Project
Site
REPUBLIC OF TURKEY
MINISTRY OF ENVIRONMENT AND
FORESTRY
MAP OF HUNTING ZONES
IN
MUĞLA
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
60
5. ENVIRONMENTAL IMPACTS
This section of the report provides a summary of PROJECT specific environmental
issues associated with constructional and operational phase of the wastewater treatment
plant. These issues are mainly associated with noise, air and dust emissions, wastewater
effluents, storage and disposal of hazardous materials and wastes. These may cause
impacts on the ambient air and water quality as well as ecology and sensitive receptors.
Hence, mitigation measures are assessed in this section, as well.
5.1. LIQUID WASTES
5.1.1. Domestic Wastewater
Domestic wastewater will be generated due to daily water utilization (for drinking,
bathing, washing, etc.) by employees. For the construction and operational phases of the
PROJECT, there will be 70 and 14 employees, respectively. Assuming that 90% of water
consumed transforms into wastewater and daily water consumption is 150 L/cap for
construction phase as water will be consumed for drinking, bathing and washing
purposes. However, in operational phase, water will be utilized for cleaning of the
administration, cogeneration, workshop buildings, irrigation of green areas and for
laboratory works in addition to drinking and bathing purposes for operational staff, so daily
water consumption is 200 L/cap for operational phase. The estimated amount of
wastewater for construction and operational phases of the PROJECT will be 9.45 m3/day
(70 people x 0.90 x 150 L/cap-day) and 2.5 m3/day (14 people x 0.90 x 200 L/cap-day),
respectively.
Assumptions made for the amount of water consumed are based on the water
consumption data was acquired from the MUNICIPALITY. A summary of these data is
given in Table 21.
Table 21. Water Consumption Data
Water Consumption Unit 2020 2040
Net Average Consumption L/cap-day 150 185
Net Unmeasured Legal Consumption and Net Illegal Consumption
L/cap-day 27 10
Net Total Water Consumption L/cap-day 177 195
Amount Returning to the Wastewater System (80 % of net consumption)
L/cap-day 142 156
Water Inlet from Gates L/cap-day 7 8
Total Amount of Wastewater L/cap-day 148 164
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
61
5.1.2. Rain Water
The Project Site lies at a lower elevation than its surroundings; hence, rain water is
accumulated at the Project Site. This problem inhibits the site arrangement as well as
construction facility of the treatment plant.
5.1.3. Filtrate Water
Filtrate water will result from sludge thickeners and sludge dewatering units. In
addition to this, there will be leakage water from pump stations, screens, wash water and
grit chamber.
Maximum amount of leakage water from the facility will be 132 m3/day. Utilization
of leakage water is explained in Section 6.1.3.
5.2. SOLID WASTE
Solid waste to be generated in the construction phase will be inorganic
construction waste, excavation waste and domestic solid waste generated by the
employees. In the operational phase, there will be sludge and domestic solid waste
generation in addition to the solid waste originating from maintenance of machinery and
equipment to be utilized in the operational phase.
5.2.1. Domestic Solid Waste
Assuming that there will be 3 kg/cap-day10 of solid waste generation, there will be
210 kg (70 people x 3 kg/cap-day) of solid waste in the construction phase. In the
operational phase, there will be 42 kg (14 people x 3 kg/cap-day) of solid waste.
5.2.2. Construction Waste
The solid waste arising from construction works is composed mainly of reusable
and recyclable materials (broken or unused metal or wooden concrete formwork
materials, broken or unusable metal or wooden parts construction cages, used clothes or
equipment).
5.2.3. Excavation Earth
Excavation works will be carried out prior to the construction activities for digging a
foundation, site preparation and road opening. Total amount of excavations are expected
to be 10,000 m3 at construction phase. No excavation works will be carried out at the
operational phase of the PROJECT.
10
Solid waste generation in Mugla is 3 kg/cap-day according to the regional statistics 2004 of TUIK.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
62
5.2.4. Sludge
There will be sludge generation due to biological wastewater treatment process.
Amount of dewatered sludge at 15C will be 15 ton/day in 2042. Details about storage and
disposal of the sludge are given in Section 6.2.3.
5.3. HAZARDOUS WASTE
5.3.1. Waste Oil
Waste oil to be generated in the construction phase will be limited to waste oil
resulting from the equipment used. Maintenance of the equipment shall be made in places
with appropriate infrastructure, where oil separator exist and the oils are collected and
disposed by the firms certified by the Ministry of Environment and Urbanization. Hence,
there will not be significant amount of waste oil generation.
A deal will be made with a catering firm to meet food demand of employees. Since
there will be no cooking in the Project Site, generation of waste cooking oil is out of
concern. In the operational phase, there will be waste lubrication oil. Besides, oil in the
wastewater will be scraped from the surface in grit and grease removal unit (aerated grit
chamber), and this will add to total generation of waste oil in the operational phase.
5.3.2. Medical Waste
Since the Project Site lies in the city center, no hospital or infirmary will be
established in the scope of the PROJECT. The health institutions in the city will be
benefited in case of an emergency. This ensures that there will be no generation of
medical waste in the scope of the PROJECT.
5.3.3. Waste Batteries and Accumulators
Waste accumulators will be resulting from equipment and cars utilized in the
construction and operational phases. Accumulators of cars will changed in places with
appropriate infrastructure in the workshop unit of the WWTP facility or the accumulator
supplier workshop. Mobile radios will be the waste battery sources.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
63
5.4. AIR EMISSIONS
5.4.1. Gaseous Emissions
Energy demand of the WWTP will be supplied from the present network. There will
be no emissions resulting from fossil fuels. Exhaust emissions from heavy machinery to
be used in construction and the cars that belong to the MUNICIPALITY and to be used
during the construction and operation phases will be controlled by regular maintenance.
Heating of buildings will be provided by utilization of biogas that will be generated
by the process. The H2S content of the biogas will be very low, nearly 0.0002-0.0005 % in
volume. Therefore, the use of biogas for heating purpose will both prevent the direct
emission of biogas to air and decrease the amount of the sulphur emission. This will both
prevent biogas from being emitted into air and decrease amount of pollutants that are
resulting from heat generation. To sum up, there will be no organic gas or vapor to be
emitted into air in the operational phase.
5.4.2. Dust Emissions
The activities that may result in dust generation are given below:
Transportation on unpaved roads,
Excavation works for roads and foundations,
Transport, utilization and storage of construction materials and
Transport of excavated material.
The dust emission factor of 9.9 gr/m2-day has been used in calculating the dust
emissions resulting from the construction activities. This factor has been calculated based
on a formula given by the U.S. Environmental Protection Agency (USEPA) considering
various construction sites. The formula below has been used to calculate dust emission
rates in construction sites:
Excavation works will be carried on 5,000 m2 of area. Working period will be nine
months, and there will be 12 hours of working a day.
Dust Emission = 9.9
month
dayxmonths
mx
hours
dayx
daym
g
1
309
000,5
12
2
2
Amount of dust = 15.3 g/hour ≈ 0.015 kg/hour
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
64
This value is below 1.5 kg/hour, the limit value stipulated in the Annex-2, Table 2.1
of the Regulation on the Control of Air Pollution Originating from Industrial Establishments
(Official Gazete dated July 22, 2006 and numbered 26236) and determines the
requirement of modelling study. Thus, modelling study is not required.
Vegetal top soil with a thickness of 0.3 m will be removed from surface before
excavation works begin. Excavation earth of 10,00 m3 will be used in filing works in the
Project Site, and thus, it will be transported to appropriate places with trucks. There will be
165,000 m3 of earth to be used in filling works. Therefore, 155,000 m3 of the filling earth
will be transported outside the Project Site. All these processes will result in dust
generation.
Since the distance covered for transportation of excavation materials is short,
there will be negligible amount of dust generation due to transport of vegetal soil.
Emission coefficients for calculation of dust generated during excavation and filling works
are given in Table 22.
Table 22. Emission Factors to be Used for Dust Calculations
Activity Unit Emission Coefficient
Excavation kg/ton 0.025
Loading kg/ton 0.01
Unloading kg/ton 0.01
Source : www.cedgm.gov.tr
Dust emission due to excavation:
Depth of vegetal soil = 0.30 m
Density of material = 1.6 ton/m3
Total amount of excavation = ((5,000 m2 x 0.30 m) + 10,000 m3) x 1.6 ton/m3 =
18,400 ton
Hourly amount of excavation = 18.400 ton / (9 ay x 30 gun x 12 hours) = 5.6
ton/hour
Dust emission = 5.6 ton/hour x 0.025 kg/ton = 0.142 kg/hour
Dust emission due to loading:
Amount of material extracted = 10,000 m3/(9 monthsx30 days x 12 hours) x 1.6
ton/m3 = 4.94 ton/hour
Dust emission = 4.94 ton/hour x 0.01 kg/ton = 0.05 kg/hour
Soil to be used in filling works will be transported to appropriate areas, and
hence, there will be no dust generation during unloading of this material.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
65
Dust emission due to unloading:
Amount of material = 165,000 m3 / (9 months x 30 days x 12 hours) x 1.6 ton/m3 =
81.5 ton/hours Dust emission = 81.5 ton/hour x 0.01 kg/ton = 0.815 kg/hour
Total amount of dust emission = 0.015 + 0.142 + 0.05 + 0.815 = 1.022
kg/hour
This value is below the limit value of 1.5 kg/hour, which is stipulated in the
“Regulation on Control of Air Pollution Originating from Industrial Establishments”
(RCAPOIE) to decide on whether a modeling study is necessary, and thus, conducting a
modeling study is not necessary. Mitigating measures for dust emissions is given in
Section 6.3 under the topic of “Air Emissions”.
5.5. ODOR
There will be odor formation in some units of the WWTP. These are;
Inlet pumping station
Screen house
Pump ditches
Grit and grease removal equipment
Sludge thickener
Sludge dewatering unit
Measures that shall be taken against odor formation are given in Section 6.4.
5.6. NOISE
There will be noise and vibration due to works carried out with construction
machines from the preparation of land for construction to start-up of the WWTP. Noise in
the construction phase will result from the machinery and vehicles that will be used for
excavation, loading and transportation.
The noise emission criteria that concern the WWTP are stipulated in the “List B” of
the “Regulation on Assessment and Management of Environmental Noise” (RAMEN),
effective since publication in Official Gazette no. 26809 on 7 March 2008 Equivalent
Sound Power Levels (LW) of equipment and machinery used in construction phase are
determined in accordance with the “Regulation on Environmental Noise Emission
Originating from the Equipment Used in Open Area” (Official Gazette dated January 22,
2003 and numbered 25001). Sound Power Levels (LW) of the equipment and machinery to
be used in the PROJECT is presented in Table 23.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
66
Table 23. Construction Machinery and Equipment and Their Sound Power Levels (Lw)
Machinery / Equipment Count Lw (dB)
Loader 2 115
Exkavator 2 103
Compactor 1 105
Dump truck 4 101
Concrete pump truck 1 101
Transmixer 3 115
Truck Crane 1 101
Water Tanker 1 90
Car 1 85
Pick-up 2 85
Total sound power level of all sources can be calculated by the formula (1)
presented below7. In the formula, it is assumed that all sound sources are on the same
plane.
n
i
L
WT
i
nL
1
10101
log10 ………………………………… (1)
In this formula;
n = Number of sources
Li = Sound power level of each source (dBA)
WTL = Total noise power level
10
11510
10510
12010
11010
100
102101101101101log10 xxxxxLWT
= 122 dB
Sound power level (Lp), caused by machinery or equipment, at a certain point can
be calculated using the Formula (2) below11.
2..4log10
r
QLL WTP
…………………………………....(2)
Lp : Sound power level (dBA)
Q : Constant selected with respect to the roughness of the ground (Q=2)
r : Distance (m)
11
Assessment and Management of Environmental Noise, Type A Certificate Program Seminar Notes- METU Continuing Education Center, Ankara, 2007
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
67
Atmospheric absorption may decrease the sound power level further since all the
activities will be at the outdoor. Nonetheless, atmospheric absorption is excluded from
calculations in order to consider the worst case scenario. Noise level with respect to
distance was calculated by using the formula given above, and calculations are
summarized in Figure 23.
0
20
40
60
80
100
120
140
0 500 1000 1500 2000 2500
Mesafe (m)
Gü
rült
ü S
ev
iye
si (
dB
A)…
.
Figure 23. Noise Distribution with respect to Distance
Variation of noise level with respect to distance is given in Table 24.
Table 24. Noise Distribution with respect to Distance
r (m) Lw (dB)
0 122
10 94,0
20 88,0
26 85,7
30 84,5
40 82,0
50 80,0
75 76,5
100 74,0
150 70,5
200 68,0
300 64,5
Noise level due to construction activities drops below the limit value of 70 dBA,
which is stipulated in the RAMEN for the closest sensitive receptor, at 150 m of distance
from the Project Site. Since the closest sensitive receptor is 1,100 m, the city center, there
will be no noise level exceeding the limit value at the sensitive receptor.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
68
Table 25 presents the criteria stipulated in, Table 5 of Annex VIII of the RAMEN for
the noise level that shall not be exceeded at the closest sensitive receptor to the place
where noise emitting activities take place. These criteria will be fulfilled in every phase of
the PROJECT.
Table 25. Limit Values for Environmental Noise (Table 5 of annex VIII of the RAMEN)
Activity (Construction, Demolition and Repair) Ldaytime (dBA)
Building 70
Road 75
Other Sources 70
During construction period precautions will be taken according to Occupational
Health and Safety Act (issued in the Official Gazette, dated 11.01.1974 and numbered
14765) Article 22; necessary equipment will be supplied to the workers, such as head
gears, earmuffs and ear-plugs. Furthermore during all the works rules specified by the
“Regulation on Occupational Health and Safety” (issued in the Official Gazette, dated
09.01.2003 and numbered 25311) will be obeyed.
In context of these legislation the followings are required:
The employee must prepare a health and safety plan and train the workers to
ensure that they have clearly understand this plan and their responsibilities. The training
session must be completed before the initiation of construction period and when a new
worker arrives, the training session must be repeated for the new comer.
At the facilities where heavy and dangerous works are not being carried out, the
noise level must not exceed 80 dBA. However, at the work places where more noisy
works are done, noise level can increase up to 95 dBA. In such situations, head gears,
earmuffs and ear-plugs must be provided to the workers.
Before being employed, their health will be checked and the ones having problem
with their ears and nervous system will not be employed.
According to assessment made according to the Article 23 of the RAMEN, there
will be no such sensitive receptors as schools, hospitals and houses in an area with 150
m of radius around the Project Site in order to fulfill the limit value of 70 dBA stipulated in
Table 5 of annex VIII of the RAMEN. Activities taking place near residential areas shall be
suspended except daytime period (07:00-19:00) in compliance with the criteria stipulated
in Table 1-2 of the RAMEN. The Project Site is 1,100 m away from residential areas, and
thus, necessary permits will be acquired from the municipality for continuation of activities
within excluded time period.
The Project Owner shall present the information on start and completion date,
working periods and permits acquired from the municipality on a table that can be easily
seen. This Table should be displayed at the building of the MUNICIPALITY in a place
where public can easily access. The limit values for sensitive areas will be complied with
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
69
during PROJECT activities. All the necessary measures will be taken in order to minimize
noise level (see Section 6.5).
The “Noise Regulation” and the “Vibration Regulation” published by the “Ministry of
Labor and Social Security” will be complied with for noise level that employees will be
subject to. Further mitigation measures for noise are given is Section 6.5.
5.7. ACCIDDENT RISK DUE TO TECHNOLOGY AND MATERIALS USED
Accidents during construction may be considered as risks for employees. Besides
this, increasing traffic load due to PROJECT activities may increase accident risk for local
people. However, these risks are not specific to the PROJECT but common to all similar
projects. It will be possible to minimize the potential accident risks by erection of warning
signs within and outside the construction site and by the use of personal protective
equipment.
Risk of accident to be resulted by the technology and materials used in the scope
of the PROJECT are negligibly low provided that the Occupational Health and Safety
legislation will be fully complied with. The policies and procedures related to Occupational
Health and Safety will be effective in every phase of the PROJECT, and all the activities
will be carried out in compliance with the regulations and standards implemented in
Turkey and safety certificates published by manufacturers.
According to the Labour Law (Official Gazette dated June 10, 2003 and numbered
25134) and related occupational health and safety legislation the followings will be
implemented:
The CONTRACTOR will be responsible with taking all the necessary measures
and maintaining all the needed means and tools in full in order to ensure occupational
health and safety in the establishment.
A health and safety plan and emergency response plan will be prepared by the
Conractor and they will train the workers to ensure that they have clearly understand this
plan and their responsibilities. The training session must be completed before the initiation
of construction period and when a new worker arrive, the training session must be
repeated for the new comer.
The construction works will mostly be carried out during daytime. However, in case
it needs to be continue at the night time, necessary illumination for ensuring safe working
conditions will be provided. The workers will wear helmets in the construction area to
protect their head from any falling object. Warning signals will be inserted around the
dangerous locations such as excavated ares. Moreover, the excavated areas will be
surrounded by wooden curtains. Safety harnesses and signal devices will be provided for
the staff working at the deeply excavated areas and excavation works will be stopped at
rainy weathers. Top boots will be provided for the staff working inside the water.
Guardrails will be constructed at the high buildings and stairs in order to prevent the
worker falling from high points.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
70
Emergency Response Plans (ERP) will be prepared by the Contarctor prior to the
construction phase and by the operator prior to the operation phase in the scope of the
PROJECT and these will be strictly obeyed. The requirements are monitored by the
Project Manager of the Consultant during construction and operation periods. The primary
objective of the ERPs is to describe the actions to be taken in an emergency case. Natural
disasters, accidents and sabotages are classified as “emergency case” in the scope of
this PROJECT. The measures to be taken to warn the endangered population prior to
hazardous situations are the major concerns of ERPs. Beside these, the following items
will be of concern in preparing ERPs:
The tools required for an immediate response in an emergency state (fire,
explosion etc.) will be identified and stored in a separate place. Mattocks and oars
face masks, protective eye-glasses, gloves, various pumps, electrical engines with
explosion protection, wireless and similar equipment shall be listed among these
tools.
It will be planned in advance how the heavy construction machinery like scoop and
bulldozer will respond to any emergency state and the parking locations of this
machinery will be chosen accordingly.
ERP’s will also comprise the list of emergency response teams, the locations of
safety equipment, emergency exists, emergency procedures as well as the
telephone numbers to be contacted.
ERP’s will be continuously reviewed by the CONTRACTOR and all the relevant
equipment will be periodically inspected and maintained. Key personnel will be trained on
this topic. The construction CONTRACTOR will be responsible for this during the
construction period whereas during the operational period operational CONTRACTOR will
be responsible.
The nearest security unit (police or gendarme) and fire department will be alarmed
in case of emergency.
According to the “Regulation on Structures Constructed at Disaster Areas” (Official
Gazette numbered 23098 and dated September 2, 1997) and the “Regulation on
Protection of Buildings Against Fire” (Official Gazette numbered 25865 and dated July 1
2005) the following precautions will be taken:
Any building will not be erected at the locations where snowslide, rock fall and
landslide is observed. If there is a flood risk, the height of the building and the locations of
the rooms in the building will be arranged accordingly. If there is a fire risk at the region,
the buildings will not be constructed from the materials like wood, etc that can burn easily.
There must be emergency exits and fire escape stairs at the buildings. Moreover, the
foundations and the bodies of the buildings shall be strong enough against any potential
earthquake.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
71
6. MITIGATION MEASURES
Related regulations and guidelines of Turkish environmental legislation will be
complied with in order to minimize the environmental impacts originating from the
construction and operation of the PROJECT. Environmental impacts and mititgation
measures in operation and decommissioning phases are given in detail in Chapter 8.3.
6.1. LIQUID WASTES
6.1.1. Domestic Wastewater
Amount of wastewater to be generated in the construction and operation phases of
the PROJECT is calculated as 9.45 and 2.7 m3/s, respectively (see Section 5.1.1).
Domestic wastewater to be generated in the construction phase of the PROJECT
will be collected in unleaking septic tanks that will be constructed by approval of the
Municipality in compliance with the “Regulation on the Tanks Constructed where Sewer
System Construction is Inapplicable”, effective since publication in Official Gazette no.
13783 on 13 March 1971. Provincial Directorate of Environment and Urbanization will
control the compliance to the this regulation. The septic tank will be checked regularly by
the constructional staff and when it is filled up sewage trucks will be employed to empty
and transport the sewage to the present and very simple wastewater treatment facility
which is located on the Marmaris road at the western part of the urban city.
Wastewater generated in the operational phase will be treated in the WWTP, and
the “Water Pollution Control Regulation”, effective since publication in Official Gazette no.
25687 on 31 December 2004, will be complied with in terms of discharge quality. Since
the flow rate of this wastewater is rather low, it will not affect the process in the WWTP
.Analysis of discharged wastewater shall be made daily in the operational phase
BOD, COD, suspended solids, pH, P and N are the parameters to be analzed as stated in
Section 3.2. Prior to the initiation of operational phase, discharge permit will be received
from Provincial Directorate of Environment and Urbanization. The water samples will be
taken from the discharge of the WWTP by the Provincial Directorate of Environment and
Urbanization and sent to the laboratories authorized by the MoEU to carry out
environmental analyses.
6.1.2. Rain Water
As stated in Section 5.1.2, in order to prevent the accumulation of rain waters, site
will be filled and it will be elevated prior to the construction activities. Moreover, a drainage
system will be established around the facility to collect rain water and conveyed the
collected stromwater to the river nearby the WWTP. Amount of wastewater to be collected
will be rather lower than the amount of wastewater that will be collected from the entire
city. Therefore, it is not expected to bring about an additional load to the WWTP.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
72
6.1.3. Filtrate Water
Effluent originated from sludge thickeners and leakage water from sludge
dewatering units will be directed to filtrate water storage tank along with wastewater from
pump stations, screens, wash water and grit chamber. Filtrate water collected within the
system will be directed to aeration tank of WWTP.
6.2. SOLID WASTE
6.2.1. Domestic Solid Waste
Solid waste generation in the construction and operational phase of the PROJECT
will be 210 kg/day and 45 kg/day. Solid waste generated will be collected by the
MUNICIPALITY, and disposed of in compliance with the “Solid Waste Control Regulation”
(SWCR), effective since publication in Official Gazette no. 20814 on 14 March 1991.
Recoverable waste, e.g. glass, plastic and metal packaging materials and paper,
will be separated and stored in containers, and given to licensed waste recovery
companies in compliance with the “Regulation on Control of Packaging Materials”,
effective since publication in Official Gazette no. 26562 on 24 June 2007.
6.2.2. Excavation
Amount of excavations will be 10,000 m3, all of which will be used in filling works in
the Project Site. Excavated material will be stored in an appropriate area at the Project
Site in compliance with the “Regulation on Control of Excavation Material, Construction
and Demolition Wastes”, effective since publication in Official Gazette no. 25406 on 18
March 2004. Appropriate area means a place in the construction site where the storage
for a certain period of time is possible for reuse of the excavated material when needed. It
does not require any permeability or similar ground conditions and will be determined by
the MUNICIPALITY.
Moreover, in compliance with the same regulation, vegetal top soil that will be
removed prior to excavation works will be stored in an appropriate area, and used in
landscape works. Appropriate area means a place in the construction site where the
storage for a certain period of time is possible for reuse of the excavated material when
needed. It does not require any permeability or similar ground conditions. In order to keep
the quality of the vegetal soil, the interval between its removal and the reuse will be as
short as possible. During storage, surface of vegetal soil will be grassed. Vegetal top soil
will be stored in a separate place than excavates and other solid wastes. Vegetal soil will
be laid back, and will be planted with local vegetation following the competition of
construction works.
6.2.3. Waste Sludge
Sludge will be analyzed in order to determine whether its content is considered as
a hazardous waste or not in compliance with the “Hazardous Waste Control Regulation”
(HWCR), effective since publication in Official Gazette no. 25755 on 14 March 2005, and
it will be utilized in agriculture, forest and landscape works provided that it is not within the
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
73
context of hazardous waste. If the sludge is determined to be hazardous, then it will be
sent to a licenced hazardous waste disposal facility that is the nearest disposal facilities
selected in order to reduce the transportation costs of hazardous wastes. Nearest
hazardous waste disposal facilities to the Mugla Province are located in Izmir or Manisa
provinces of Turkey. These facilities can be employed or other facilities can be selected
from other provinces. The licenced facilities are the facilities that have been approved by
MoEF for disposal of hazardous wastes. On the other hand, if the sludge is non-
hazardous, excess amount of sludge that is not utilized for agricultural purposes will be
stored in a concrete paved area. Decision on the way sludge will be utilized will be taken
in accordance with the preferences of farmers, the MUNICIPALITY and the Provincial
Directorate of Environment and Urbanization.
Sludge will be dewatered in compliance with the WPCR. Raw sludge cannot be
utilized in agriculture, in cultivated areas, forests and grasslands according to the “Soil
Pollution Control Regulation” (SPCR). Moreover, processed sludge cannot be used for
production of vegetables that are in contact with soil while growing.
Sludge may be utilized in agriculture according to the related tables given in the
SPCR depending on its composition.
Sludge cannot be used if amount of any of the heavy metals in it exceeds the limit
value. Besides, the terms given below also restricts utilization of sludge:
In case of yield in grassland and feed crop, before at least three weeks pass
In vegetable and fruit yielding fields,
10 months before the yield in fields that are planned to be used for yielding
vegetable and fruit.
To sum up, SPCR stipulates the restrictions on utilization of sludge and
procedures for acquisition of permits. According to this regulation, sludge shall be utilized
for agricultural products to be processed such as cotton, tobacco, etc. rather than for
products that are directly consumed by people.
In addition to these uses of sludge, it may also be made use of in soil
rehabilitation, in green lands and in landscape works. Moreover, it may also be stored.
Since the agricultural utilization of sludge will be seasonal, a storage area will be
arranged for three-month storage of sludge. This will be an outdoor facility with concrete –
covered bottom and concrete walls. The sludge filtrate will be drained from the bottom of
the storage area to filtrate pump station by means of drainage pipeline. The collected
wastewater will then elevated to inlet of the aeration tank by filtrate pumps.
As the amount of dewatered sludge at 15C will be 25 ton/day in 2042, sludge
height and density will be 2 m and 800 kg/m3, respectively. Storage area shall be
designed according to storage periods of 90 days. Therefore, minimum land requirement
will be 1,500 m2 (30 x 50 m).
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
74
6.2.4. Waste Oil
There will be no significant waste oil generation during construction activities. In
the operational phase, there will be generation of waste oil due to equipment used. Oil will
be supplied in barrels, and be transported to the Project Site by trucks. It will be stored in
an area, which has a connection to an oil trap not to let leaking oil mix with soil. Besides,
oil scraped in the aerated grit chamber will be stored in a separate tank, be prevented
from being mixed with pollutants. Unpolluted waste oil will be transferred to recycling
facilities whereas polluted oil will be properly disposed of.
Any kind of waste oil to be generated in the scope of the PROJECT will be
transported, stored and disposed of in compliance with the HWCR and the “Regulation on
Control of Waste Oil”, effective since publication in Official Gazette no. 25353 on 21
January 2004. The requirements of this regulation are explained in Appendix-A.
6.2.5. Waste Batteries and Accumulators
Waste batteries and accumulators will be collected and handled in compliance with
the “Regulation on Control of Waste Batteries and Accumulators”, effective since
publication in Official Gazette no. 25569 on 31 August 2004. The requirements of this
regulation are explained in Appendix-A.
6.3. AIR EMISSIONS
Gas emissions will result from vehicles, and will be controlled through regular
maintenance of them.
Dust emissions resulting from construction activities may vary according to the
type of activity, soil and wind. Dust particles are transported by air when wind speed
exceeds 3 m/s. Particles with diameter greater than 100 m settle at a distance between 6-
10 m when wind speed is 4 m/s. Particles with diameter between 30 and 100 m settle
after traveling 100 m from the source in the same wind condition.
Particles with diameter less than 10 m travel for a longer time, and they may be
transported out of the construction site by the effect of atmospheric turbulence. To sum
up, small particles may travel 500 m in the air whereas particles with diameter more than
or equal to 30 m only travel 100 m from the construction site.
Possible negative impacts due to dust emission are listed below:
Impacts on flora by inhibiting photosynthesis,
Disturbance in the terrestrial fauna,
Respiratory illnesses,
Increasing turbidity in surface water.
Impacts due to dust emission will be minimized through implementation of the
following measures:
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
75
The contractor will be required to use equipment that minimizes dust emission
In order to prevent or minimize dust formation at soil piles or similar spots, soil
piles shall be watered in dry weather for dampening.
30 km/hour speed limit shall be set on non-paved roads.
Both the site and access roads shall be mechanically cleaned or water-sprayed to
prevent dust formation.
Trucks carrying loose materials and rock wastes will be covered during the
transportation.
The workers will be trained in order to prevent unloading from high for example
from truck haulage during material transfer.
The mitigating measures that will be taken in compliance with the Appendix-1 of
the RCAPOIE for excavation to be made inside the Project Site are as follows:
Carriers will be covered
Transportation roads will be wetted when necessary
30 km/hour speed limit shall be set on non-paved roads.
Both the site and access roads shall be mechanically cleaned or water-sprayed to
prevent dust formation.
Trucks carrying loose materials and rock wastes will be covered and be watered
during the transportation.
The measures presented above will be taken in excavation areas. In addition to
these, the “Occupational Health and Safety Regulation”, effective since publication in
Official Gazette no. 25311 on 9 December 2003, will be complied with in order to minimize
the negative impacts of dust emission on employees.
In context of these legislation the followings are required:
The employee must prepare a health and safety plan and train the workers to
ensure that they have clearly understand this plan and their responsibilities. The
training session must be completed before the initiation of construction period and
when a new worker arrive, the training session must be repeated for the new
comer.
Dust generating activities will be realized by a closed system, if they are
technologically and economically viable
Aspiration system, water curtains and vacuums will be utilized to prevent the
spreading of the dust.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
76
Depending on the content of the dust, different personal protective equipments and
protective masks will be provided to the workers.
At the end of each shift, the workers employed in dust generating works will be
provided to have a bath and they will be prevented to sleep or eat before having
bath.
Each worker will have a medical control before employment and the ones having
respiratory and circulatory disorders and skin problems will not be employed for
dust generating works.
In conclusion, there will be no adverse impact either on the local air quality or on
the human health provided that particle matter emission is maintained at acceptable
levels.
Significant amount of dust is not expected to be generated in the operational
phase.
6.4. ODOR
The major odor sources in the facility are given in Section 5.5. The only measure
that can be taken against odor is to cover buildings where odor is generated. Proper
working conditions as stipulated in the “Labor Law” and related regulations will be
provided. In addition to these, the minimum hourly air exchange rate shall be 6 for these
buildings. Air exchange rate in PROJECT units that are operated infrequently may be low,
and these structures will be constructed using sulfate-proof concrete.
6.5. NOISE
Noise Emission in the Operational Phase
The major noise sources will be pumps, blowers, sludge trucks and loaders and
belt filter press. Another noise source will be generators.
All the measures including insulation will be taken generator building, blower
building and buildings housing belt filter press and pumps. Transmission of noise waves in
buildings will be in two ways, which are;
Transmission by the structure itself
Transmission by sound waves
Insulation will be made for three surfaces: ceiling, floor and side walls. Special
insulated doors will be used since sound is transmitted mostly through spaces at the
bottom of the door and key holes. A good insulation can decrease sound pressure level
down to 40 dBA. During the operational phase, there will be no noise reaching to sensitive
receptors.
Project Owner will take necessary precautions to keep noise level below the limit
value stipulated in the RAMEN for industrial establishments. Measures can be taken;
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
77
- At source
- Between source and receptor
- At receptor
Measures to be taken at source
Prevention of noise at source is the most effective way of noise control. The
primary objective is to select equipment emitting lower sound power level. High-
technology equipment to be used in the facility and closed cabins for noise emitting
equipment will minimize noise level. It is hard to indicate noise levels of equipments at this
stage of the Project. The noise levels of the equipments are determined by the supplier
and the contractor. Therefore, the noise levels of the equipments will be determined by
them. The main issue is complying with the limit values at the sensitive receptors
stipulated by Regulation on Assessment and Management of Environmental Noise. This is
also confirmed by the officials of Turkish Ministry of Environment and Urbanization.
Measures to be taken between source and receptor
Noise curtains, barriers and natural obstructions can be classified in this category.
Plant cover and bushes surrounding noise sources block noise transmission. A plant
cover with a width of 50 m will decrease sound level by approximately 3 dBA.
Measures to be taken at receptor
Primary measure to be taken at receptor is insulation in buildings made according
to the international standards. Employees will be supplied with earlaps and protective
clothes to wear within working periods.
Monitoring Studies
No noise measurement studies have been conducted in the scope of the
PROJECT. However, a background noise measurement study will be conducted for
proper assessment of noise in the scope of monitoring studies in the construction and
operational phases. Background noise measurements will be started just before the
initiation of construction activities and continue throughout the construction phase. These
measurements will be conducted by a company authorized to carry out noise
measurements.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
78
7. ANALYSIS OF ALTERNATIVES
7.1. TECHNOLOGY ALTERNATIVES
Handling of wastewater that is accomplished by leaching septic systems became
problematic issue since wastewater amount increases with the increasing population. As a
result of the rapid increase in urban population, overflow problem from the septic systems
have been experienced very commonly. Overflowing wastewater can reach to the
groundwater resources, cause odor problem and soil pollution. Moreover, wastewater
leaching down to groundwater table may reach drinking water supplies and also Gokova
Bay by means of sinkholes. These situations threaten both environment and public health.
In order to prevent all these problems, Modified Bardenpho Process (MB) with
extended aeration and nitrogen removal, which is the selected process in the waste water
treatment plant , was designed to overcome wastewater handling problem. This process is
commonly used for nitrogen and phosphorus removal. In addition, sludge thickening will
be achieved by sludge dewatering.
Carrousel type synchronous denitrification process was considered as an
“Alternative Project” of the PROJECT. Synchronous denitrification is flexible, and its
treatment efficiency is sufficient for organic loading of various wastewater types.
Moreover, methane generated as a by-product of the treatment sludge can be utilized as
fuel. Anaerobic digestion provides 70% of the facility’s energy requirement. Thus, it
possesses a considerable economic value. Process flow diagrams of the PROJECT and
the Alternative Project are presented in Appendix-B.
Mugla Province lies in the edge of a carstic plain. Water collected by the natural
drainage system infiltrates into the soil, and moves towards the sea through carstic pores.
Thus, there are two alternatives for the discharge of the effluent. The first one is pumping
the effluent into Kara Creek, which is a branch of Akarca Creek that flows into the sea at
Gokova Bay (see Figure 20). ”Effluent Discharge Line” is shown as “Aritilmis Atiksu Terfi
Hatti” and Wastewater Treatment (WWT) is shown as “AAT” at the figure. Energy
expenses to supply a head of 200 m to the effluent for pumping it to the outside of the
basin are given in Table 26.
Table 26. Expenses Associated with Pumping of Effluent to the Outside of the Basin
Year Average Flow
Rate (m
3/h)
Daily Energy Expense* Annual Expense*
(YTL) (€) (YTL) (€)
2012 595 1,296 741 473,000 270,000
2017 662 1,442 824 526,000 301,000
2022 737 1,606 918 586,000 335,000
2027 797 1,738 993 634,000 362,000
2032 861 1,877 1,072 685,000 391,000
2037 927 2,022 1,155 738,000 422,000
2042 998 2,175 1,243 794,000 454,000
* NTL stands for the New Turkish Lira
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
79
In stage one (at year 2022), the energy expense for pumping the effluent to the Kara
Creek is calculated as 586,000 YTL. The annual energy expense of the WWTP and its
annual cumulative expense are 62,000 and 700,000 YTL, respectively. Therefore, this
alternative has very high operational cost and seems to be infeasible considering budget of
the MUNICIPALITY.
On the other hand, second alternative involves reuse of water at the basin after
necessary arrangements. This alternative is feasible when the environmental issues and
operational costs are considered.
7.2. OTHER ALTERNATIVES
There are no alternatives for the Project Site. All the alternatives of the PROJECT
are different investment options developed for the realization of the PROJECT. Besides
these alternatives, there is also a “no action” alternative, in which the PROJECT will not be
realized. The aim of the no action alternative is to evaluate the benefits and cost in the
present situation. Making these quantitative evaluations are generally demanding, so,
instead, different scenarios are prepared regarding the PROJECT’s realization and
unrealization, and they are presented to the decision makers.
It is clear that absence of a wastewater treatment plant, namely “no action
“alternative contribute to soil and ground water pollution and pollution in Gokova Bay. On the
other hand, serious threat on environment and public health will be eliminated by
construction of a WWTP.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
80
Figure 24. Pumping the Effluent to the Outside of the Basin
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
81
8. ENVIRONMENTAL MANAGEMENT PLAN
8.1. INTRODUCTION
Purpose and Scope
This section of the report includes the Environmental Management Plan (EMP) in
which a series of mitigation measures to remove or minimize the environmental impacts
resulting from the activities performed during construction and operation periods of the
PROJECT and monitoring plans are presented. They are mostly determined considering
both the WB’s criteria and the national legislation.
The purpose of the EMP prepared for the PROJECT is as follows:
to address the environmental consequences resulting from the activities performed
during construction and operational phases of the PROJECT,
to specify related mitigation measures considering both the national legislation and
WB’s criteria,
to propose environmental monitoring program,
to set-up an institutional structure where environmental issues are followed up
during construction and operational phases of the PROJECT,
to inform local people, governmental and non-governmental organizations (NGOs)
about the PROJECT.
A World Bank Category A Project such as Mugla WWTP Project requires two
public consultations: In general, the first public consultation is held to discuss the draft
ToRs for the EIA study, and the second public consultation is to discuss the draft EIA
document. As stated above, two public consultation meetings were held by
MUNICIPALITY in Mugla city center. The details related to these meetings are presented
in Appendix G.
Both MUNICIPALITY and the CONTRACTOR will take their responsibilities for
monitoring environment to achieve and sustain a sound environmental performance
during implementation of the PROJECT. An environmental monitoring report will be
prepared by the CONTRACTOR during construction phase and be submitted to the
MUNICIPALITY every month. During operational phase, MUNICIPALITY will prepare an
environmental Monitoring report and submit it to the IB every four months.
DOKAY predicts that the environmental performance of the proposed PROJECT
will comply with both the national environmental legislation and WB’s criteria provided that
the items mentioned in the EMP will be ensured.
The mitigation measures and the monitoring plan proposed in the EMP require the
approval of the WB. In this regard, the scope of the EMP follows the typical EMP format of
the WB.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
82
8.2. RESPONSIBLE PARTIES
MUNICIPALITY has signed a protocol with the IB to develop a project, on which
the credit taken from the WB will be used for establishment of a wastewater treatment
plant, which has been developed within the scope of the above mentioned protocol and
prepared by Temelsu-Dornier Schneider Common Initiative for the MUNICIPALITY.
After the determination of the possible environmental impacts to be occurred
during construction and operational phase of the PROJECT, the EMP proposes mitigation
measures in order to minimize or, if possible, completely remove these impacts together
with the monitoring program. Principals of the public consultation meetings with the local
people, who may be affected from the PROJECT and the representatives of local NGO’s
have also been presented in this EMP.
Declarations related to the responsible parties of the PROJECT are presented
below:
WB: Reviews all the activities related to the PROJECT that it finance and states
“no objection” for the feasible ones or suggests points to be strengthened.
IB: Accomplishes quality assurance function to satisfy the WB requirements during
preparation of EMP, which is a credit requirement. IB evaluates whetheR the EMP
is feasible in terms of format and content and acquaints the WB.
Temelsu-Dornier Schneider Common Initiative: As being the Implementation
Consultant, takes the responsibility to execute the PROJECT according to the IB
and therefore WB requirements.
DOKAY: takes the responsibility to prepare the EMP document of the PROJECT
according to the format provided by the IB.
MUNICIPALITY: As being the beneficiary of the PROJECT, takes the responsibility
to both MoEF and IB for acquiring necessary permissions related to construction of
the PROJECT, implementation of the precautions defined in the EMP during
construction and operation period. In this context, every six months, the
MUNICIPALITY will prepare an Environmental Monitoring Report to affirm
compliance to the EMP and submit it to the IB and the MoEU.
CONTRACTOR: Takes the required precautions denoted in the EMP to minimize
environmental impacts that may occur during implementation of the PROJECT and
performs public consultation meetings suggested in the EMP. CONTRACTOR will
be responsible to the MUNICIPALITY.
MoEF: Enforces the items 18 and 19 of the Turkish EIA Regulation issued on the
Official Gazette dated 16.12.2003 and numbered 25318. These items are related
with “Monitoring and Control of Investment” in case MUNICIPALITY does not fulfill
the requirements of the EMP. According to Article 18, MoEF monitors and controls
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
83
whether the Project Owner complies with the commitments given in the final EIA
Report or Project Introduction File (PIF).
8.3. MITIGATION MEASURES
8.3.1. Construction Phase
Temelsu-Dornier Schneider Common Initiative, conducting engineering works of
the PROJECT, prepares documents required for construction tender. Therefore, this EMP
including the evaluation and minimizing precautions of environmental impacts that may
pose during construction will be presented to the requesting firms with tender documents
prior to the proposal period. The main responsibility of the CONTRACTOR to be
determined by tender is as presented below:
In order to contribute PROJECT’s environmental performance, educating the
construction staff to raise the environmental consciousness and assigning a
person responsible for “ Health, Safety and Environment”
Fulfilling the requirements of Turkish Environmental Legislation mentioned in
Chapter 3, and taking necessary mitigating precautions,
Acquiring licenses required in accordance with the national legislation presented in
Chapter 3 to conduct construction activities,
In addition to the present legal framework, fulfilling the new national or
international legislation that may come into force or be issued during construction
phase.
MUNICIPALITY will assign an engineer, in charge with implementing the EMP, as
the authority of “HSE” and follow the compliance by audits.
8.3.2. Operational Phase
MUNICIPALITY will be responsible for fulfilling the requirements in the EMP for the
facility that will have been constructed by the CONTRACTOR. CONTRACTOR has to
commit and prove that he/she will provide the facility approval conditions mentioned in the
tender document.
Below are the requirements that need to be fulfilled by the MUNICIPALITY:
Assigning an engineer to implement the EMP as the HSE authority and follo the
compliance with internal audits,
Educating operation and maintenance staff to raise the environmenta
consciousness to provide their contribution to the PROJECT’s environmental
performance,
Fulfilling the requirements of Turkish Environmental Legislation mentioned in
Chapter 3 and taking necessary mitigating precautions,
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
84
In addition to the present legal framework, fulfilling the new national o international
legislation that may come into force or be issued during operational phase.
Potential environmental impacts that may pose in water, air, soil and other
receiving media during construction and operational phase of the PROJECT and the
proposed mitigation measures are presented in Table 27.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
85
Table 27. Potential Environmental Impacts of the Project and Mitigation Measures.
Phase Issue Mitigating Measure Cost of
Mitigation Institutional
Responsibility
Construction Dust
Work sites shall be watered under warm, dry, and windy weather conditions. Materials
shall be loaded and unloaded without slueing; 30 km/hour speed limit shall be set on non-paved roads. Top of the trucks will be covered when carrying the excavations. Dust suppression system will be used in if
crusher is installed.
Included in the civil works
CONSTRUCTOR
Construction
Air Emission (exhaust gases
from heavy machinery)
Regular maintenance of heavy machinery. Exhaust emissions of the heavy machinery shall regularly be measured, controlled, and
recorded by the authorized institutions.
Included in the civil works
CONSTRUCTOR
Construction
Noise and vibration
(Excavation and drilling works)
Local people will be informed prior to such activities that may cause a temporary
disturbance; Regular maintenance of heavy machinery. Construction works should be
carried out during the day time period (07.00-19.00) stated in Regulation on
Assessment and Management of Environmental Noise.
No cost implementation
CONSTRUCTOR
Construction Excavated material
Excavated material will be stored at the Project Site and all of it will be used for
backfilling.
Included in the civil works
CONSTRUCTOR
Construction Vegetative top
soil
Vegetative top soil of the Project Site will be stripped prior to excavation works and will
be stored in the construction site away from the other excavations to be used in
landscaping.
Included in the civil works
CONSTRUCTOR
Construction Domestic solid
waste
Formed where construction sites are established. Wastes will be collected in the closed containers at the Project Site and
handled by the MUNICIPALITY at the waste disposal sites by trucks having necessary
license.
Included in the civil works
CONSTRUCTOR
Construction
Hazardous Waste (such as florescent lamp, water/temprerat
ure isolation marerial, waste
oil, waste batteries and accumulators
batteries)
Hazardous wastes will be handled in compliance with Regulation on Control of Hazardous Wastes, Regulation on Waste
Oil, Regulation on Control of Used Batteries and Accumulators (i.e., disposal of these
wastes to a proper landfill or collection by a company certified by the MoEF for collection
and disposal.
Included in the civil works
CONSTRUCTOR
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
86
Phase Issue Mitigating Measure Cost of
Mitigation Institutional
Responsibility
Construction Domestic
wastewater
Formed where construction sites are established. It will be collected in unleaking
septic tanks that will be constructed in compliance with the “Regulation on the
Tanks Constructed where Sewer System Construction is Inappliance” and sewage trucks will be employed for transport of
sewage from the septic tank to the present wastewater treatment facility.
Included in the civil works
CONSTRUCTOR
Construction Public health and safety
Drivers of the vehicles carrying materials to construction site should obey speed limit of
30 km/hour. Warning signals should be installed the sites where heavy construction
facilities are carried out.
Included in the civil works
CONSTRUCTOR
Construction Occupational
health and safety
Water will be sucked by a drainage system or pumps to prevent it accumulate it in pits
and muddy water sucked is discharged after allowing soil to settle down. Barriers should
be used to obstruct soil collapse in deep excavation areas. Compliance with the
relevant Occupational Health and Safety Regulation of Turkey (e.g., use of personal protective equipment and compliance with
excavation techniques detailed in Article 24 of the Regulation as within three days of the
start of construction works in terms of number of workers measures being taken,
etc.)
Included in the civil works
CONSTRUCTOR
Operation Noise and vibration
Noise will be minimized at the source with proper installation of noise barriers and
isolation. Employees will be supplied with earlaps to wear within working periods if
necessary.
Included in the operational costs
Contractor (In trial operation Period) and
Municipality
Operation Domestic solid
waste
Wastes will be collected in the closed containers at the Project Site and handled
by the MUNICIPALITY
Included in the operational costs
Contractor (In trial operation Period)
and Municipality
Operation Excess sludge
Excess sludge will be analyzed in accordance with Regulation on Control of
Hazardous Wastes, and used for agricultural purposes as fertilizer, if suitable.
If it is not used as fertilizer and it is not the hazardous waste, then it will be disposed to
the solid waste disposal area.
If it is not used as fertilizer and determined to be hazardous waste, then collection by a company certified by the MoEF for collection
and disposed at the certified hazardous waste storage site anywhere in Turkey or in
İZAYDAS which is the certified facility for disposal of hazardous materials. There is neither such a disposal area nor certified
collection company exist in Mugla Province. Certified collection and transportation
companies can be employed from Izmır or Manisa as they as they are the nearest provinces or other facilities from other
provinces can be selected. Similarly, the nearest hazardous waste storage area is
located in İzmir
Included in the operational costs
Contractor (In trial operation Period) and
Municipality
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
87
Phase Issue Mitigating Measure Cost of
Mitigation Institutional
Responsibility
Operation
Hazardous Waste (such as florescent lamp, water/temperatu
re isolation material, waste
oil, waste accumulator and
batteries)
Hazardous wastes will be handled in compliance with Regulation on Control of
Hazardous Wastes, Regulation on the Control of Waste Oil, Regulation on Control
of Used Batteries and Accumulators (i.e. collection by a company certified by the
MoEF for collection and and disposal to the certified hazardous waste storage site
anywhere in Turkey or in İZAYDAS which is the certified facility for disposal of hazardous materials.) there is neither such a disposal
area nor certified collection company exist in Mugla Province. Certified collection and
transportation companies will be employed from Izmir or Manisa as they as they are the
nearest provinces. Similarly, the nearest hazardous waste storage area is located in
Izmir.
Included in the operational costs
Contractor (In trial operation Period) and
Municipality
Operation Domestic
wastewater
Domestic wastewater will be directed to the WWTP and treated and discharged in
compliance with WPCR.
Included in the operational costs
Contractor (In trial operation Period) and
Municipality
Operation Odour
Top of the building where odor is generated will be covered. Minimum hourly air
circulation rate shall be 6 exchanges for these buildings. Buildings that have low air circulation rate with an odour problem shall be constructed from sulfate-proof concrete.
Included in the operational costs
Contractor (In trial operation Period) and
Municipality
Operation Occupational
health and safety
Compliance with the relevant Occupational Health and Safety Regulation of Turkey
(including use of personal protective equipment and preparation of an emergency
action plan, to be prepared by CONTRACTOR and approved by the
MUNICIPALITY prior to the start of the activities, for accidents during maintenance
of sewerage and water supply systems).
Included in the operational costs
Contractor (In trial operation Period) and
Municipality
Operation Hazardous
material
The chlorine will be stored in a building in the facility. This building will be aerated
properly. A shower will also be installed in the building.
Included in the operational costs
Contractor (In trial operation Period) and
Municipality
Operation Disposal of
treated wastewater
Wastewater will be treated according to Regulation and chlorination will be applied.
Included in the Contractor Contract.
Contractor (In trial operation Period) and
Municipality
Operation Aquifer water
quality
Wastewater will be treated according to Regulation and aquifer water quality will be
monitored periodically.
From Municipality Budget
Municipality
Operation Health and
Safety Disposal site will be fenced and necessary
precautions will be taken. From Municipality
Budget Municipality
Decommissioning
Abandon of disposal site
No mitigation measures are required since no construction works will arise.
- Municipality
* CONTRACTOR’s responsibilities will be stated in the tender document.
8.4. MONITORING PLAN
“Environmental Framework of Turkey’s Municipal Services” document, which was
prepared by the IB for infrastructural projects financed by the WB states that results
concerning environmental monitoring activities which are required during implementation
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
88
and operational period of the PROJECT within the context of EMP, should be declared to
IB with observation reports as well.
It is suggested that environmental monitoring studies should be conducted
separately because different activities during construction and operation period of the
PROJECT will result different possible environmental impacts. Data acquired during
monitoring studies will be compared with national legislation items which are mentioned in
Chapter 3.
8.4.1. Construction Phase
Monitoring every environmental parameter continuously is not practical and
necessary. Environmental monitoring functions according to the characteristics of existing
environmental conditions and identifies unacceptable changes during construction period.
In this context, monitoring plan is designed to commit that “project activities have no
permanent negative effect on environmental resources “.
For construction period, water and air quality, waste management applications and
noise levels will be monitored and the results will be compared to legal limiting values.
CONTRACTOR will prepare a report about monitoring studies according to the following
program and offers it to the MUNICIPALITY:
Daily environmental non-compliance report (if any)
Weekly environmental report (containing environmental problems occurred during
that week and precautions taken)
“Monthly Environmental Monitoring Reports” in which environmental performance
of the PROJECT is evaluated according to EMP requirements.
8.4.2. Operational Phase
In the operational phase of the PROJECT, fewer environmental effects are
expected than construction period. MUNICIPALITY will present environmental monitoring
studies to the IB within a report at least every six months in operational phase.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
89
Table 28. Monitoring Plan
Phase
What
parameter is to be
monitored?
Where
is the parameter to
be monitored?
How
is the parameter to be monitored/
type of monitoring equipment?
When
is the parameter to be monitored-
frequency of measurement or
continuous?
Monitoring Cost Responsibility
Construction Dust
Nearest
neighboring
sensible receptor
(ex. backyard of
the nearest house)
Site observation of dust Daily observation by the Project
staff for routine control No cost
implementation CONTRACTOR
Construction Air emissions from heavy
machineries
Heavy
machineries
Check to see that operatimng
permit is valid
Once, prior to allowing
equipment onto project site
Included in the civil
works CONTRACTOR
Construction
Noise and vibration
(Excavation, drilling and
blasting works)
Nearest
neighboring
sensible receptor
Noise measurement with a
calibrated sound level meter
Monthly and especially during the
activities that increase noise
levels (measurements should be
performed more frequently
depending on the complaint of
the public)
Measurements will be repeated if
a new facility will be performed
that cause an increase in noise
level or construction works will be
carried out during night time after
getting necessary permissions.
Included in the civil
works CONTRACTOR
Construction Excavated material disposal
method
Excavation and
storage sites
Site observation and document
review whether or not disposal
area and the method are
approved by the related
municipality.
Daily by the constructional staff No cost
implementation CONTRACTOR
Construction
Vegetative top soil conditions
(height of the storage-1.5 m
at max. and cover over piles)
Excavation and
storage sites
Site observation of disposal site
and storage technique Daily by the constructional staff
No cost
implementation CONTRACTOR
Construction Construction waste disposal
method
Construction and
storage sites
Site observation of disposal site
and storage technique Daily by the constructional staff
No cost
implementation CONTRACTOR
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
90
Phase
What
parameter is to be
monitored?
Where
is the parameter to
be monitored?
How
is the parameter to be monitored/
type of monitoring equipment?
When
is the parameter to be monitored-
frequency of measurement or
continuous?
Monitoring Cost Responsibility
Construction Domestic solid waste
disposal method
Construction and
storage sites
Site observation at collection site
whether collection and disposal
of the domestic solid wastes are
in compliance with Solid Waste
Control Regulation
Daily control whether the
domestic solid wastes are
collected and stored properly
Included in the civil
works CONTRACTOR
Construction Hazardous waste disposal
method
Construction and
storage sites
Site observation at collection site
whether collection and disposal
of the hazardous wastes are in
compliance with Hazardous
Waste Control Regulation.
Daily control whether the
domestic solid wastes are
collected and stored properly
Included in the civil
works CONTRACTOR
Construction Domestic wastewater
disposal method Septic tank
Measurement of wastewater
level in septic tanks Daily by the constructional staff
No cost
implementation CONTRACTOR
Construction Public health and safety
measures
Excavation and
construction site,
storage sites
Site observation Daily by the constructional staff No cost
implementation CONTRACTOR
Construction Occupational health and
safety measures Construction site
Site observation of
implementation of mitigation
measures
Daily by the constructional staff,
quarterly audits by environmental
consultant.
Included in the civil
works CONTRACTOR
Operation Noise and vibration
Nearest
neighboring
sensible receptor
Noise measurement with a
calibrated sound level meter
Monthly measurements
(measurements should be
performed more frequently
depending on the complaint of
the public)
Included in the
operational costs MUNICIPALITY
Operation Domestic solid wastes
disposal method
Operation and
maintenance sites
Site observation at collection site
whether collection and disposal
of the domestic solid wastes are
in compliance with Solid Waste
Control Regulation
Daily recordings and monthly
assessment of the solid wastes
generated.
Included in the
operational costs MUNICIPALITY
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
91
Phase
What
parameter is to be
monitored?
Where
is the parameter to
be monitored?
How
is the parameter to be monitored/
type of monitoring equipment?
When
is the parameter to be monitored-
frequency of measurement or
continuous?
Monitoring Cost Responsibility
Operation Excess sludge
Treatment plant
and excess sludge
storage site (if
sludge is not
hazardous it will
be sent to solid
waste storage, if
hazardous treated
in complience with
Regulation on the
Control of
Hazardous
Wastes
Site observation of sludge storage procedures and facility
(non-hazardous) If hazardous (as determined by elemental analysis of sludge in
compliance with the criteria stated in Soil Pollution Control Regulation) site observation of
sludge collection methods at the sludge collection site
Once everyyear (if non-
hazardous)
Twice a year (if hazardous)
Included in the
operational costs MUNICIPALITY
Operation Hazardous waste disposal
method
Construction and
storage sites
Site observation of hazardous
waste disposal method
Daily recordings and monthly
assessment of the solid wastes
generated. Annual audits of the
system
Included in the
operational costs MUNICIPALITY
Operation Domestic wastewater
disposal method
Connection pipes
to the WWTP
Site observation to insure pipe is
properly connected Once,
No cost
implementation MUNICIPALITY
Operation Odour
At the building
where odour
generation is
expected
Site observation Daily by the operational staff No cost
implementation MUNICIPALITY
Operation Occupational health and
safety measures Operation site
Site observation of personal
safety equipment use by staff
Daily by the operational staff,
quarterly audits by environmental
consultant
Included in the
operational costs
MUNICIPALITY and
Environmental
Consultant
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
92
Table 29. Discharge Site Water Quality/Quantity Monitoring Plan
MONITORING PLAN
No. Activity Responsible 2011 2012 2013 2014
10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12
1 Analysis of Effluent in WWTP Muğla Mun. X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X
2 Water Level Observation in Disposal Site Muğla Mun. X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X
3 Water Quality Analysis in 5 Monitoring Wells Muğla Mun. X X X X X X X X X X X X X
4 Water Level Observation in 5 Monitoring Wells Muğla Mun. X X X X X X X X X X X X
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
93
8.5. INSTITUTIONAL STRENGTHENING
In general, in this section of EMP’s, the recommendations related to the
institutional strengthening are provided in order to ensure that environmental measures
are applied for the environmentally sound and sustainable project development.
In this report, this section is mainly based on what proposed for construction phase
in terms of environmental monitoring. The recommendations on institutional strengthening
for the operational phase will be formed when the organizational structure for that phase is
finalized.
In this context, in the construction phase of the PROJECT, the MUNICIPALTY will
hire an Environmental Consultant to follow up and implement the requirements of the
EMP and hence commitments of the EIA Report. So, the following sub-sections were
structured based on this proposed methodology.
8.5.1. Equipment Purchase
The Environmental Consultant will utilize his own equipment for environmental
monitoring works since the Environmental Consultant will be a company authorized by the
Turkish MoEF for carrying out environmental measurements and analyses according to
the requirements of the Turkish environmental legislations.
8.5.2. Training
The Environmental Consultant will assign an Environmental Engineer for
performing the proposed environmental monitoring works at the Project Site. Prior to the
execution of the construction works, Environmental Engineer will carry out a training
campaign for the constructional staff of the staff of the Contractor in order to increase the
environmental awareness of the construction staff and to convey the requirements of the
EMP and EIA Report.
The scope of the training will include mainly the scope of the EMP, the relevant
environmental legislations of Turkey, requirements of the WB and Performance Standards
of the IFC and the following concepts should be included in the training program:
Understanding of the PROJECT’s environmental requirements and their
implementation at the site by the staff (i.e. what kind of environmental impacts are
expected and what kind of mitigation measures are proposed; where and how
take these measures);
Understanding of the procedures to be followed in improper situations;
Reporting principals and understanding rules;
The PROJECT’s environmental dimension and informing the related official
institutions about it;
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
94
Understanding how to treat the public and media visiting the site; and
Understanding how to act in case of unexpected environmental accidents.
The CONTRACTOR is in charge of keeping the records related to the
environmental training of the staff. Internal audits should test the effectiveness and the
adequacy of the training
8.5.3. Consultancy Services,
The Environmental Consultant to be hired by the MUNICIPALITY will do provide
environmental consultancy services to ensure the compliance with environmental rules
and regulations as well as guidelines and to meet the necessities that may occur during
audits by the WB or local authorities such as the provincial directorates of the MoEF in
Mugla.
On a monthly basis, the Environmental Consultant will do carry out monitoring
work outlined in Section 8.4 and will hold meetings with construction contractor to obtain
information about the progress in the works as well as environmental issues encountered.
The Environmental Consultant will report the findings of the audits every two months
during the construction period.
8.5.4. Public Relations
Relations with the Media
It is the MUNICIPALITY’s responsibility to communicate with the media as a
requirement of general implementations rules of public investments. For this reason, the
CONTRACTOR will not arrange a direct meeting with media without the permission and/or
presence of the MUNICIPALITY. A procedure, concerning the relations with the media,
should be prepared and applied when such authorization is given to the CONTRACTOR.
Handling Complaints
In the construction phase of the PROJECT, the CONTRACTOR will prepare a
procedure to direct complaints to the MUNICIPALITY. The MUNICIPALITY is responsible
to deliver the phone numbers, mail and e-mail addresses to interest groups (local people
and NGO’s) for receiving and recording any complaints. Hence, a public relations
mechanism should be constructed for the complaints from NGO’s and governmental
establishments of the province. Any complaints received will be recorded and directed by
the relevant units to the related technical personnel in the construction site to take
necessary measures and corrective actions. The complainant will be informed about the
progress after necessary measures are taken and the subject environmental problem is
resolved. All records of complaints and relative action taken will be recorded by the
relevant unit.
A public relation mechanism should be established by the MUNICIPALITY in the
operational phase of the PROJECT like the one developed in the construction phase and
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
95
the public relations process will be followed by this mechanism in order to evaluate
complaints and suggestions from people.
8.5.5. Special Studies
No additional special study is foreseen at the moment. On the other hand, based
on the findings during the implementation phase of the EMP, there might be a need for a
special study. Its methodology and cost could be determined when it is needed.
8.6. INSTITUTIONAL ARRANGEMENTS
This chapter gives information about how and by whom the environmental
Monitoring data which is conducted to achieve a balanced environmental performance of
the PROJECT, will be used.
8.6.1. Constructional Phase
MUNICIPALITY, the owner of the PROJECT, is the responsible party to minimize
or eliminate possible environmental impacts of the PROJECT. In this sense, for
construction period, the MUNICIPALITY will ensure that the EMP is added to the tender
documents before the CONTRACTOR is determined. Therefore, to guarantee the
environmental performance of the PROJECT, CONTRACTOR will be aware of his/her
responsibilities in the construction period before putting out to tender and prepare the bid
taking into consideration these points. In this way, CONTRACTOR can not claim that he is
uninformed about EMP after the tender and PROJECT’s environmental performance will
not be endangered.
CONTRACTOR will perform the following activities for a balanced environmental
performance:
Assigning his/her own HSE personnel to implement the EMP and synchronize with
the MUNICIPALITY HSE personnel;
Working in coordination with Environmental Consultant to ensure that the personel
working in the construction period are educated to raise the consciousness on
environmental issues and EMP requirements.
Minimization of the emissions and noise originating from the construction
equipments, protection of water resources, compliance with the requirements of
EMP concerning waste management.
MUNICIPALITY will inform the local public and NGO about public relations in the
construction period in the meeting of the presentation of this EMP (refer to Chapter 8).
This process will be carried out by the public relations department in the MUNICIPALITY.
In the construction period, a public relations mechanism will be constructed for the
complaints from NGO’s and governmental establishments in the city.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
96
This mechanism will handle the following subjects:
Informing the public about the progress of the PROJECT,
Taking the complaints and recording them,
Handling the complaints in a quick and effective manner and answering them.
In the construction period, CONTRACTOR, who will conduct the environmental
monitoring studies according to the issues stated in EMP under the control of
MUNICIPALITY Personnel, will present the results to the MUNICIPALITY with monthly
environmental monitoring reports.
CONTRACTOR, who will conduct the environmental monitoring studies according
to the issues stated in EMP under the control of MUNICIPALITY and Environmental
Consultant, will present the results to the MUNICIPALITY with monthly environmental
monitoring reports.
MUNICIPALITY will evaluate the monitoring reports which are presented by the
CONTRACTOR in terms of related environmental regulation and declare to the. Moreover,
MUNICIPALITY will provide each copy of the environmental Monitoring reports to be kept
in the MUNICIPALITY and in the field office of CONTRACTOR to present it to authorities
in the controls that are made by Mugla Province Director of Environment and
Urbanization.
When non-compliance is detected by the Province Directorate of Environment and
Urbanization or the IB, CONTRACTOR will fix the situation and declare it to the
MUNICIPALITY.
Within the context of this EMP, the task distribution concerning anticipated
activities in the construction phase is presented in Table 30.
Table 30. Task Distribution related to the construction phase EMP requirements
Task Item CONTRACTOR MUNICIPALITY
Environmental Quality Monitoring (water, air, soil, noise, etc.) R1 S
Training of Key Personnel2
R S
Training of Staff R S
Corrective Actions R S
Internal Audit R S
Reporting R S
Relations with the Media A R3
Handling complaints R S
(R: responsible, S: supervisor, A: assistant) 1 Measures should be conducted by the qualified institutions and establishments according to the national legislation
2 Training activities will be carried out in coordination with Environmental Consultant
3 Relations with the media is the responsibility of MUNICIPALITY as a requirement of general implementation rules of public investments. This forbids the CONTRACTOR from arranging a direct meeting with the media.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
97
8.6.2. Operational Phase
As the proposed environmental monitoring works for the operation phase are very
limited and the organizational structure of the operational staff is not certain yet, there is
no detailed proposal for institutional arrangements at the moment. In short, there should
be one HSE officer in the organizational structure of the MUNICIPALITY who will be
responsible for following up the EMP requirements, related to the operational phase, and
coordination with Environmental Consultant to be hired by MUNICIPALITY.
8.7. CONSULTATION WITH NGO’S AND PROJECT-AFFECTED GROUPS
A public relation mechanism should be set up and applied throughout the
construction and operational phases of the PROJECT. In this respect, local people and
NGO’s as well as local authorities will be informed about the project progress. Hence, any
public objection that might be raised by local people due to lack of information could be
prevented and good relations between the local people and project owner as well as
contractors can be formed and maintained.
Any complaint raised by local people or NGO’s will be recorded and followed up
whether or not corrective actions, if necessary, are taken. Therefore, a log book for such
complaints will be available at the site office (during the construction phase) or at the
wastewater treatment plant administrative building (during the operational phase).
8.7.1. Construction Phase
At the beginning and at the end of each construction season during the
construction phase, public consultation meetings will be held in the nearest settlement or
at the MUNICIPALITY building. In these meetings, the relevant stakeholders (villagers,
village head, representatives of local NGO’s as well as local authorities) will be informed
about the progress of the PROJECT development.
During public consultation meetings, minutes of meeting will be taken together with
a list of participants by signing an attendance sheet. In the monitoring reports, there will
be an annex including these minutes and the participant list as well as a copy of the
presentations and brochures, if available.
The firstand second public consultation meetings of the construction period took
place in Nail Cakirhan Meeting Hall at Konakalti Iskender Alper Cultural Center. Final lists
related to the interest groups was determined by the MUNICIPALITY before the meetings,
and invitations were sent to these groups. Detailed information about the meetings and
the participant records are given in Appendix-G.
8.7.2. Operational Phase
During the operational phase of the PROJECT, these public consultation meetings
should be held twice a year since the operational works will be routine and limited with
the locale of the treatment plant.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
98
During public consultation meetings, minutes of meeting will be taken together with
a list of participants who will sign an attendance sheet. These records should be kept by
the MUNICIPALITY.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
99
9. REFERENCES
1. World Bank “Pollution Prevention and Abatement Handbook”, July 1998.
2. Mugla Environmental Situation Report, 2003
3. Mugla Municipality Final Feasibility Report, 2005
4. Mugla Structural Plan, 2004
5. Ozturk, I., Timur H., Koskan U., (2005): Atiksu Aritiminin Esaslari: Evsel, Endustriyel
Atiksu Aritimi ve Aritma Camurlarinin Kontrolu, Ministry of Environment and Forestry,
Ankara.
6. Toprak, H., (2000) (Extended 3. Publication): Atiksu Aritma Sistemlerinin Tasarim
Esaslari, Volume-1 and Volume-2, Dokuz Eylul University, Engineering Faculty
Publication, No.240-241, ISBN : 975-441-148-4 ve 975-441-149-2, Izmir.
7. Toprak, H., 2005. Aktif Camur Surecinin Đsletilmesi. Dokuz Eylul University, Faculty
of Engineering, Environmental Engineering Department, Izmir.
8. Toprak, H., 2005. Aktif Camur Surecinin Tasarimi. Dokuz Eylul University, Faculty of
Engineering, Environmental Engineering Department, Izmir.
9. Study for Mugla Plain Sinkholes Improvement, SHW, 1996
10. http://www.mugla.gov.tr
11. www.dmi.gov.tr
12. www.tuik.gov.tr
13. www.deprem.gov.tr
14. www.ogm.gov.tr
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
i
APPENDICES
APPENDIX-A SUMMARY OF PROJECT RELATED TURKISH
LEGISLATION
APPENDIX-B FLOWCHART OF WWTP AND ALTERNATIVE
PROJECT
APPENDIX-C GEOLOGICAL MAPS OF THE PROJECT SITE
APPENDIX-D METEOROLOGICAL DATA OF MUGLA
PROVINCE
APPENDIX-E FLORA INVENTORY
APPENDIX-F FAUNA INVENTORY
APPENDIX-G PUBLIC CONSULTATION MEETINGS
APPENDIX-H TECHNICAL, ECONOMIC AND
ENVIRONMENTAL STUDIES ON DISCHARGE
OF TREATED WASTEWATER OF MUGLA
WWTP
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
1 / 35
Appendix-A SUMMARY OF PROJECT RELATED TURKISH
LEGISLATION
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
2 / 35
Municipality Law (Law Numbered 5393)
This law is published on the Official Gazette dated July 13, 2005 and numbered
25874. the aim of this law is is to regulate the establishment, responsibilities and scope of
authorities of municipalities.
According to Article 15 of this law, municipalies are responsible with the construction
of infrastructures such as sewer system and wastewater treatment plants.
Environment Law (Law Numbered 2872)
This law is published in the Official Gazette dated August 11, 1983 and numbered
18132. Purpose of this law is to protect the destruction, deterioration, and extinction of the
environmental values and the ecological balance, to remedy current degradation, to improve,
and develop and to prevent pollution of the biological, physiological, social, economic and
cultural environment in which is the common asset of all the living beings, all through their
life conduct their relationships and mutually interact, in line with the principles of sustainable
environment and sustainable development. With the amendment of the law, A Supreme
Environment Board, chaired by the Prime Minister, shall be established, and its main tasks
include: the formulation of the targets, policies and strategies; the definition of legal and
administrative measures to include environment aspects to economical decisions; the
resolution of environment-related disputes among the ministries and agencies, etc.
Municipalities are also obliged to set up or organize household solid waste disposal facilities.
The law as umbrella legislation to ensure above mention objectives outlines the rules and
principles on organization, procedures, encouragement and penal provisions.
According to Article 8 of this regulation, directly disposing the wastes to the
environment or transporting, storing and handling those by the methods in contravention of
the rules of related regulations are strickly forbidden.
According to Article 11, if the establishment of a project poses potential
environmental impacts, then this project requires preparation of an Environmental Impact
Assessment Report of Project Introduction File. Before the approval of any of these reports
by Ministry of Environment and Urbanization, the establishment of the project can not be
initiated.
According to Article 11, municipalities are responsible with construction of sewer
ayatem and wastewater treatment plant for the collection of wastewater at the locations
which are under the responsibility of municipalities. The user of these infrastructures has to
contribute to the payment of investment, operational, maintenance and cleaning costs.
According to Article 12, the Ministry of Environment and Urbanization is responsible
with controlling the complience to that law.
According to Article 14, the noise and vibration limits are determined by the related
regulations. Emitting noise and vibration above these limits are strickly forbidden. In order to
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
3 / 35
decrease noise levels, the owner of the residences of facilities have to take necessary
precautions.
According to Article 28, the polluters are responsible with paying for any destruction
or deterioration they create on environment.
Regulation on Assessment and Management of Environmental Noise
This regulation is published on the Official Gazette dated March 7, 2008 and
numbered 26809. It has been prepared to develop an environment, which does not disturb
physical and psychological health of people with noise. The regulation determines basis and
criteria on environmental noise, the levels of noise and the measures for decreasing
environmental noise.
According to Article 22, noise level of the facilities can not exceed the limit values
presented in Table 4 of Annex-VIII of this regulation. These limit values are given in Table
A.1.
Table A.1. Standard Noise Level Values at Receptors for Industrial Facilities
Areas Lday
(dBA)
Levening
(dBA)
Lnight
(dBA)
Areas including noise sensitive areas, place of education, cultural activities, health and
summer resort and camping sites 60 55 50
Areas with both noise sensitive areas and industrial activities (predominantly residential) 65 60 55
Areas with both noise sensitive areas and industrial activities (predominantly industrial) 68 63 58
For each facilities in which industrial zone and industrial region 70 65 60
Source: Regulation on Assessment and Management of Environmental Noise, Annex VIII, Table 4
According to Article 23, the environmental noise generated by construction activities
can not exceed the limit values stipulated by Table 5 of Annex-VIII of this regulation. These
limit values are given in Table A.2. If the construction activities of public utilities are needed
to be carried out at evening and night time, the noise limit of evening is determined by
subtracting 5 dBA from daytime noise levels, and the noise level of night time is determined
by subtracting 10 dBA from day time noise level.
Table A.2. Limit Values of Environmental Noise at the Construction Area
Operation type (construction, destruction and
maintenance) Lday (dBA)
Building 70
Road 75
Other Sources 70
Source: Regulation on Assessment and Management of Environmental Noise, Annex VIII, Table 5
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
4 / 35
According to Article 25, vibration generated by the use of heavy machinery during the
construction activities can not exceed the limit values stipulated by Table 7 of Annex-VIII of
this regulation. These limit values are presented in Table A.3.
Table A.3. Maximum Allowable Limit Values Generated by Heavy Machinery during Construction Activities
Maximum Allowable Vibration
(Peak Value-mm/s)
Continuous Vibration Intermittent Vibration
Nearest Settlement 5 10
Industrial and Trade Areas 15 30
Source: Regulation on Assessment and Management of Environmental Noise, Annex VIII, Table 7
Soil Pollution Control Regulation
This regulation is published on the Official Gazette dated May 31, 2005 and
numbered 25831. The purpose of this regulation is prevention of pollution of soil as a
receiving environment. This regulation defines the scope of the activities causing soil
pollution; discharge of hazadous substances, waste, cleaning sludge and compost of
domestic and urban waste water discharged to soil; the techniques to control the soil
pollution and administrative principles and penal law sanction.
According to Article 7 of this regulation, the stabilized sludge to be generated at the
WWTP will be analzed in terms of the parameters stated in Annex I-A (b), Annex II-A and
Annex II-B. These analyses must be carried out in accredited laboratories by considering the
principles given in Annex IV.
According to Article 9, the heavy metal content of the sludge must not exceed the
concentrations presented in Annex I-B.
According to Article 10, the sludge generated at domestic wastewater treatment plant
can be utilized for agricultural purposes if it the content of the sludge does not exceed the
limit values presented in Annex I-B.
If the daily sludge generation of the treatment plant is less that 50 tone in dry basis,
the analyses of sludge must be repeted once every six months considering the parameters
given in Appendix II-B. If the daily sludge generation is more than 50 tones in dry basis,
these analyses must be repeated once every three months.
The owner of the sludge generating facility must apply to the Governorate of the
Province in order to take the permit to make the sludge used for agricultural purpose. The
application is evaluated by a commission including the members of Provincial Directorate of
Environment and Urbanization, Provincial Directorate of Agriculture and Rural Affairs,
General Directorate of State Hydraulic Works and Provincial Directorate of Health.
The commission evaluates the use of sludge on soil in terms of heavy metal load,
impacts on physical quality of soil and impacts on surface and groundwater resources. If the
commission decides that these impacts are negligiable, then the permit is for the use of
sludge for agricultural purpose is given.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
5 / 35
According to Article 11, the operator of the treatment plant is responsible with the
analyses and the records of the sludge.the records of the sludge must include the resultd of
sludge analyses, the method applied for stabilizing the sludge, the amount of sludge
produced and the amount of sludge utilized for agricultural purposes. These reports will be
presented to the Governorate of the Province.
According to the Article 13, stabilized sludge can not be utilized for agricultural
purposes if the content of the sludge exceeds the limit values stipulated by Annex I-B and
Annex I-A (a) of this regulation . Moreover, raw sludge can not be utilized for agricultural
purposes.
Stabilized sludge cannot be used for production of vegetables that are in contact with
soil while growing. It shall be utilized for agricultural products to be processed rather than for
products that are directly consumed by people. Besides, the terms given below also restricts
utilization of sludge:
• In case of yield in grassland and feed crop, before a certain period of time passes (at
least three weeks)
• In vegetable and fruit yielding fields,
• 10 months before the yield in fields that are planned to be used for yielding vegetable
and fruit.
If the sludge will not be utilized for agricultural purposes and if it is not considered to
be a hazardous waste according to the analyses conducted as explained in the previous
paragraphs, than the sludge will be disposed to the municipal landfills.
If the sludge is considered as hazardous wastes, they have to be sent to the
hazardous waste landfills or hazardous waste incinerators.
According to Article 16, the Minisry of Environement and Foresty are responsible with
controlling the compliance to this regulation.
Annex I.A (a) presents the heavy metal limit values on soil. These values are
presented in Table A.4.
Table A.4. Heavy Metal Limit Values on Soil
Heavy Metal (Total) pH 5- 6 mg/kg Soil Dried in Furnace
pH6 mg/kg Soil Dried in Furnace
Lead 50 300
Cadmium 1 3
Chromium 100 100
Cupper * 50 140
Nickel* 30 75
Zinc * 150 300
Mercury 1 1.5
Ministry of Environment and Urbanization can increase the limit value by 50 % ensuring that pH value is higher than 7 and it is
determined that this does not have significant adverse impact on environment, public health and groungwater resources.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
6 / 35
These limit values can be exceeded at the areas where feed crop is harvested considering that it is scientificly prooved that
this situation does not have significant impact on environment and human health.
Annex I.A (b) presents the limit values on that must be achieved after treatment of
contaminated soil treatment. These values are presented in Table A.5.
Table A.5. Limit Values that must be Achieved after Treatment of Cotaminated Soil
Parameter Limit Values
Chlorur Ion (mg Cl - /l) (Total) 25
Sodium (mg Na/l) (Total) 125
Cobalt (mg/kg Soil Dried in Furnace) 20
Arsenic (mg/kg Soil Dried in Furnace) 20
Molibdenum (mg/kg Soil Dried in Furnace) 10
Stannum (mg/kg Soil Dried in Furnace) 20
Barium (mg/kg Soil Dried in Furnace) 200
Floride (mg/kg Soil Dried in Furnace) 200
Free Cyanide (mg/kg Soil Dried in Furnace) 1
Complex Cyanide (mg/kg Soil Dried in Furnace) 5
Sulphur (mg/kg Soil Dried in Furnace) 2
Bromine (mg/kg Soil Dried in Furnace) 20
Benzene (mg/kg Soil Dried in Furnace) 0.05
Buthyl benzene (mg/kg Soil Dried in Furnace) 0.05
Toluole (mg/kg Soil Dried in Furnace) 0.05
Xylole (mg/kg Soil Dried in Furnace) 0.05
Phenol (mg/kg Soil Dried in Furnace) 0.05
Selenium (mg/kg Soil Dried in Furnace) 5
Talium (mg/kg Soil Dried in Furnace) 1
Uranium (mg/kg Soil Dried in Furnace) 5
Polycyclic Aromatic Hydrocarbons (mg/kg Soil Dried in Furnace) 5
Organo-chloride compounds (mg/kg Soil Dried in Furnace) 0.5
Pesticides –Personal (mg/kg Soil Dried in Furnace)
Pesticides –Total (mg/kg Soil Dried in Furnace)
0.5
2
PCB Polychlorinated biphenols (mg/kg Soil Dried in Furnace) 0.5
Hexachlore benzol (mg/kg Soil Dried in Furnace) 0.1
Pentachlore benzol (mg/kg Soil Dried in Furnace) 0.1
- HCH (lindan) (mg/kg Soil Dried in Furnace) 0.1
Annex I-B of this regulaton presents the maximum allowable heavy metal content of
stabilized sludge to be utilized for agricultural purposes (see Table A.6).
Table A.6. Maximum Allowable Heavy Metal Content of Stabilized Sludge to be Utilized for Agricultural Purposes
Heavy Metal (Total) Limit Value (mg/kg Material Dried in Furnace)
Lead 1200
Cadmium 40
Chromium 1200
Cupper 1750
Nickel 400
Zinc 4000
Mercury 25
Annex II-A lists the parameters to be analzed in soil samples. These parameters are;
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
7 / 35
Lead (mg/kg Soil Dried in Furnace)
Cadmium (mg/kg Soil Dried in Furnace)
Chromium (mg/kg Soil Dried in Furnace)
Cupper (mg/kg Soil Dried in Furnace)
Nickel (mg/kg Soil Dried in Furnace)
Zinc (mg/kg Soil Dried in Furnace)
Mercury (mg/kg Soil Dried in Furnace)
Nitrogen (mg/kg Soil Dried in Furnace)
Phosphorus (mg/kg Soil Dried in Furnace)
pH
Organic Material
Annex II-B lists the parameters to be analzed in stabilized sludge samples. These
parameters are;
Lead (mg/kg Material Dried in Furnace)
Cadmium (mg/kg Material Dried in Furnace)
Chromium (mg/kg Material Dried in Furnace)
Cupper (mg/kg Material Dried in Furnace)
Nickel (mg/kg Material Dried in Furnace)
Zinc (mg/kg Material Dried in Furnace)
Mercury (mg/kg Material Dried in Furnace)
Nitrogen (mg/kg Material Dried in Furnace)
Phosphorus (mg/kg Material Dried in Furnace)
pH
Organic Material
Dry Material
Loss of Combution
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
8 / 35
Annex IV of this regulation defines the sampling and analyses methods. Soil samples
will be generated by mixing 25 soil samples taken from the agricultural areas that do not
exceed 50 decare. However, by the permit of Governorate of the province same sampling
method can be applied to an area that does not exceed 200 decare. Soil samples shall be
taken from 25 cm depth. If the soil depth is less than 25 cm, then sampling depth can be at
least 10 cm.
Stabilized sludge sample will be formed by mixing at least 25 different representative
sludge sample.
Heavy metal analyses shall be started after strong acid fragmentation. Reference
analyses method shall be atomic absorption spectrophotometry.
Regulation on the Control of Air Pollution Originating from Industrial
Establishments
This regulation is published on the Official Gazette dated July 22, 2006 and
numbered 26236. This regulation sets the principles for controlling emissions of soot, smoke,
dust, gas, steam, and aerosols due to industrial and energy production. Production facilities
listed in regulation must obtain a preliminary Emission Licence (at planning phase) and
Emission Permit (at operation phase) (Mugla WWTP is not included in this list therefore
emission licenece is not required for this facility.). Procedures for the issuance of preliminary
and assorted permits are detailed in the Regulation. Emission threshold values are indicated
in the Regulation.
This regulation is utilized for evaluation of dust emissions expected from the
construction of the facility. According to Table 2.1 of Annex 2 of this regulation, air pollution
modeling study in order to determine the distribution and background dust concentration is
required if the calculated dust concentration is above 1.5 kg/hour.
Solid Waste Control Regulation
This regulation is published on the Official Gazette dated March 14, 1991 and
numbered 20814. This regulation defines the bases on collection, transportation, recycle,
evaluation, disposal and sanitization of the domestic wastes in residential areas, yard wastes
from park lands, gardens and grounds, huge solid wastes, non-hazardous domestic waste
from industrial and commercial sector, sludge produced in domestic waste water treatment
plants and the sludge produced in non-hazardous industrial treatment plants.
According to Article 4 of this regulation, the households or facilities that are
generating the solid wastes are responsible with minimizing the waste generation, providing
separate collection and recycling the wastes.
According to Article 5, municipalities are responsible with proper collection and
disposal of solid wastes and taking the necessary measures to minimize the impact on
environment.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
9 / 35
According to Article 8, hazardous wastes, packing materials and domestic solid
wastes shall be collected and store separately.
According to Article 18, disposal of solid wastes to river, lake, sea and similar
receiving environments, streets and forests are strickly forbidden. Waste containers where
solid wastes are collected shall be kept close and shall be located on the streets at the time
of collection by the municipality.
Acording to Article 28, water content of stabilized sludge shall be 65 % to be stored
with municipal solid wastes. It can be increased to 75 % ensuring that this situation will not
disturb the stability of storage and will not create odour problem.
Regulation on the Control of Hazardous Wastes
This regulation is published by the Turkish Ministry of Environment and Urbanization
and in the Official Gazette dated March 14, 2005 and numbered 25755. The purpose of this
regulation is by taking the hazardous chemicals under control, to arrange the administrative
as well as technical principles and procedures to protect the human beings and the
environment from the negative effects of these chemicals. This regulation defines the
provisions on production, collection, labeling and packaging, temporary storage, interim
storage, transportation, recovery, disposal, prohibition on import and export, limitations and
authorization, market surveillance and control, the preparation and distribution of the security
information forms legal and technical responsibility matters related to the wastes which are
classified as hazardous.
Article 9 of this regulation, the consignor of hazardous wastes are responsible with
taking the necessary measures for the minimization of waste generation, taking permission
from the Governor’s Office for the temporary storage of wastes inside the plant in
accordance with the decisions stated under this regulation, funding the expenses made for
the qualification of wastes,
According to Article 11 of this regulation, the transportation of the wastes is made by
people or companies with appropriate licenses and with appropriate vehicles for this job. The
code number of the waste in the same container and in the same car should be the same.
According to Article 22, hazardous wastes are disposed to the licenced hazardous
wastes disposal areas separate from municipal solid wastes.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
10 / 35
ANNEX- 3
CATEGORIES OR GENERIC TYPES OF HAZARDOUS WASTE LISTED
ACCORDING TO THEIR NATURE OR THE ACTIVITY WHICH GENERATED THEM
(WASTE MAY BE LIQUID, SLUDGE OR SOLID IN FORM)
A) Wastes displaying any of the properties listed in Annex -5 and which consist
of:
1) Anatomical substances; hospital and other clinical wastes
2) Pharmaceuticals, medicines and veterinary compounds
3) Wood preservatives
4)Biocides and phyto-pharmaceutical substances
5) Residue from substances employed as solvents
6) Halogenated organic substances not employed as solvents excluding inert
polymerized materials
7) Tempering salts containing cyanides
8) Mineral oils and oily substances (e.g. cutting sludges, etc.);
9) Oil/water, hydrocarbon/water mixtures, emulsions
10) Substances containing PCBs and/or PCTs (e.g. dielectrics etc.);
11) Tarry materials arising from refining, distillation and any pyrolytic treatment (e.g.
still bottoms, etc.);
12) Inks, dyes, pigments, paints, lacquers, varnishes
13) Resins, latex, plasticizers, glues/adhesives
14) Chemical substances arising from research and development or teaching
activities which are not identified and/or are new and whose effects on man and/or the
environment are not known (e.g. laboratory residues, etc.);
15) Pyrotechnics and other explosive materials
16) photographic chemicals and processing materials
17) Any material contaminated with any congener of polychlorinated dibenzo-furan
18) Any material contaminated with any congener of polychlorinated dibenzo-p-dioxin
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
11 / 35
B) Wastes which contain any of the constituents listed in Annex-4 and having
any of the properties listed in Annex -5 and consisting of:
19) Animal or vegetable soaps, fats, waxes;
20) Non-halogenated organic substances not employed as solvents;
21) Inorganic substances without metals or metal compounds;
22) Ashes and/or cinders;
23) Soil, sand, clay including dredging spoils;
24) Non-cyanidic tempering salts;
25) Metallic dust, powder;
26) Spent catalyst materials;
27) Liquids or sludges containing metals or metal compounds;
28) Residue from pollution control operations (e.g. baghouse dusts, etc.) except (29),
(30) and (33);
29) Scrubber sludges;
30) Sludges from water purification plants;
31) Decarbonization residue;
32) Ion-exchange column residue;
33) Sewage sludges, untreated or unsuitable for use in agriculture;
34) Residue from cleaning of tanks and/or equipment;
35) Contaminated equipment;
36) Contaminated containers (e.g. packaging, gas cylinders, etc.) whose contents
included one or more of the constituents listed in Annex-4;
37) Batteries and other electrical cells;
38) Vegetable oils;
39) Materials resulting from selective waste collections from households and which
exhibit any of the characteristics listed in Annex-5;
40) Any other wastes which contain any of the constituents listed in Annex-4 and any
of the properties listed in Annex-5.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
12 / 35
ANNEX- 4
CONSTITUENTS OF THE WASTES IN ANNEX-4 WHICH RENDER THEM
HAZARDOUS WHEN THEY HAVE THE PROPERTIES DESCRIBED IN ANNEX-5
Wastes having as constituents:
C1 Beryllium; beryllium compounds;
C2 vanadium compounds;
C3 chromium (VI) compounds;
C4 cobalt compounds;
C5 nickel compounds;
C6 copper compounds;
C7 zinc compounds;
C8 arsenic; arsenic compounds;
C9 selenium; selenium compounds;
C10 silver compounds;
C11 cadmium; cadmium compounds;
C12 tin compounds;
C13 antimony; antimony compounds;
C14 tellurium; tellurium compounds;
C15 barium compounds; excluding barium sulfate;
C16 mercury; mercury compounds;
C17 thallium; thallium compounds;
C18 lead; lead compounds;
C19 inorganic sulphides;
C20 inorganic fluorine compounds, excluding calcium fluoride;
C21 inorganic cyanides;
C22 the following alkaline or alkaline earth metals: lithium, sodium, potassium,
calcium, magnesium in uncombined form;
C23 acidic solutions or acids in solid form;
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
13 / 35
C24 basic solutions or bases in solid form;
C25 asbestos (dust and fibres);
C26 phosphorus: phosphorus compounds, excluding mineral phosphates;
C27 metal carbonyls;
C28 peroxides;
C29 chlorates;
C30 perchlorates;
C31 azides;
C32 PCBs and/or PCTs;
C33 pharmaceutical or veterinary coumpounds;
C34 biocides and phyto-pharmaceutical substances (e.g. pesticides, etc.);
C35 infectious substances;
C36 creosotes;
C37 isocyanates; thiocyanates;
C38 organic cyanides (e.g. nitriles, etc.);
C39 phenols; phenol compounds;
C40 halogenated solvents;
C41 organic solvents, excluding halogenated solvents;
C42 organohalogen compounds, excluding inert polymerized materials and other
substances referred to in this Annex;
C43 aromatic compounds; polycyclic and heterocyclic organic compounds;
C44 aliphatic amines;
C45 aromatic amines C46 ethers;
C47 substances of an explosive character, excluding those listed elsewhere in this
Annex;
C48 sulphur organic compounds;
C49 any congener of polychlorinated dibenzo-furan;
C50 any congener of polychlorinated dibenzo-p-dioxin;
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
14 / 35
C51 hydrocarbons and their oxygen; nitrogen and/or sulphur compounds not
otherwise taken into account in this Annex.
ANNEX- 5
PROPERTIES OF WASTES WHICH RENDER THEM HAZARDOUS
H1 Explosive
Substances and preparations which may explode under the effect of flame or which
are more sensitive to shocks or friction than dinitrobenzene
H2 Oxidizing
Substances and preparations which exhibit highly exothermic reactions when in
contact with other substances, particularly flammable substances
H3-A Highly flammable
a) Liquid substances and preparations having a flash point below 21 °C (including
extremely flammable liquids),
b) Substances and preparations which may become hot and finally catch fire in
contact with air at ambient temperature without any application of energy
c) Solid substances and preparations which may readily catch fire after brief contact
with a source of ignition and which continue to burn or to be consumed after removal of the
source of ignition
d) Gaseous substances and preparations which are flammable in air at normal
pressure
e) Substances and preparations which, in contact with water or damp air, evolve
highly flammable gases in dangerous quantities
H3-B Flammable
Liquid substances and preparations having a flash point equal to or greater than 21
°C and less than or equal to 55 °C.
H4 Irritant
Non-corrosive substances and preparations which, through immediate, prolonged or
repeated contact with the skin or mucous membrane, can cause inflammation.
H5 Harmful
Substances and preparations which, if they are inhaled or ingested or if they
penetrate the skin, may involve limited health risks.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
15 / 35
H6 Toxic
Substances and preparations (including very toxic substances and preparations)
which, if they are inhaled or ingested or if they penetrate the skin, may involve serious, acute
or chronic health risks and even death.
H7 Cancerogen
Substances and preparations which, if they are inhaled or ingested or if they
penetrate the skin, may induce cancer or increase its incidence.
H8 Corrosive
Substances and preparations which may destroy living tissue on contacts.
H9 Infectious
Substances containing viable micro-organisms or their toxins which are known or
reliably believed to cause disease in man or other living organisms.
H10 Teratogenic
Substances and preparations which, if they are inhaled or ingested or if they
penetrate the skin, may induce non-hereditary congenital malformations or increase their
incidence.
H11 Mutagenic
Substances and preparations which, if they are inhaled or ingested or if they
penetrate the skin, may induce hereditary genetic defects or increase their incidence.
H12
Substances and preparations which release toxic or very toxic gases in contact with
water, air or an acid.
H13
Substances and preparations capable by any means, after disposal, of yielding
another substance, e.g. leachates, which possesses any of the characteristics listed above.
H14 Ecotoxic
Substances and preparations which present or may present immediate or delayed
risks for one or more sectors of the environment.
Notes
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
16 / 35
1) About the signs for labeling hazardous specifications, the Different Hazardous
Chemicals Regulation published on 11/07/1993 dated and 21634 numbered Official
Newspaper is valid.
2) Test Methods:
The methods to be used for gaining a definite meaning to the hazardous
specifications to this attachment, are explained at (Attachment 5) of 67/548/EEC numbered
order of European Union Instructions. The actual versions of this order are valid which
contain 84/449/EEC numbered additional orders and additional Commission Directions
version. These methods are based on international institutions and especially Organization
of Economical Cooperation Directorate studies and recommendations.
The manuals determining hazardous specifications will be published by The Ministry.
ANNEX- 6
Threshold concentrations for the wastes marked with (M) in Annex-7
The waste considered as hazardous must contain one or more of the specifications
listed on (Attachment 5) or carry one or more characteristics of H3, H4, H5, H6, H7,
H8, H10
a) Flash point<=55 ºC,
b) One or more substances classified as very toxic at a total concentration of ≥0.1 %
c) One or more substances classified as toxic at a total concentration of ≥3 %
d) One or more substances classified as harmful at a total concentration of ≥25 %
e) One or more corrosive substances classified as R35 at a total concentration of ≥ 1 %
f) One or more corrosive substances classified as R34 at a total concentration of ≥ 5 %
g) One or more irritant substances classified as R41 at a total concentration of ≥ 10 %
h) One or more irritant substances classified as R36, R37 and R38 at a total
concentration of ≥ 20 %
a) One or more substances known to be carcinogenic of category 1 or 2 at a total
concentration of ≥ 0.1 %
i) One or more substances toxic for reproduction of category 1 or 2 classified as R60,
R61 at a total concentration of ≥ 0.5 %
j) One or more substances toxic for reproduction of category 3 classified as R62, R63
at a total concentration of ≥ 5 %
k) One or more mutagenic substances of category 1 or 2 classified as R46 at a total
concentration of ≥ 0.1 %
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
17 / 35
l) One or more mutagenic substances of category 3 classified as R40 at a total
concentration of ≥ 1 %
Note
The R codes (risk possibility) are shown at the Different Hazardous Chemicals
Regulation at (Attachment 7), which is published on Official Gazette dated 20/04/2001 and
numbered 24379.
ANNEX- 7
HAZARDOUS WASTE LIST
Chapters of the List:
(01) Wastes resulting from exploration, mining, dressing and further physico-chemical
treatment of minerals and quarry
(02) Wastes from agricultural, horticultural, hunting, fishing and aquaculture production, food
preparation and processing
(03) Wastes from wood processing and the production of paper, cardboard, pulp, panels and
furniture
(04) Wastes from the leather, fur and textile industries
(05) Wastes from petroleum refining, natural gas purification and pyrolytic treatment of coal
(06) Wastes from inorganic chemical processes
(07) Wastes from organic chemical processes
(08) Wastes from the manufacture, formulation, supply and use (MFSU) of coatings (paints,
varnishes and vitreous enamels), adhesives, sealants and printing inks
(09) Wastes from the photographic industry
(10) Inorganic wastes from thermal processes
(11) Inorganic metal-containing wastes from metal treatment and the coating of metals, and
non-ferrous hydrometallurgy
(12) Wastes from shaping and surface treatment of metals and plastics
(13) Oil wastes (except edible oils, 05 and 12)
(14) Wastes from organic substances used as solvents, coolants and wastes from pushing
gases
(15) Wastes packaging; absorbents, wiping cloths, filter materials and protective clothing not
otherwise specified
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
18 / 35
(16) Wastes not otherwise specified in the list
(17) Construction and demolition wastes (including excavation of polluted soil)
(18) Wastes from human or animal health care and/or related research (except kitchen and
restaurant wastes not arising from immediate health care)
(19) Wastes from waste treatment facilities, off-site wastewater treatment plants and the
water industry
(20) Municipal wastes and similar commercial, industrial and institutional wastes including
separately collected wastes
Regulation on the Control of Waste Oil
This regulation is published by the Turkish Ministry of Environment and Forestry and
in the Official Gazette dated July 30, 2008 and numbered 26952. The objective of this
Regulation is to ensure that waste oils are not dispersed into absorbing environment either
directly or indirectly in a harmful way; are stored, transported and disposed of without giving
any harm to the environment or human health; to define technical and administrative
standards of waste oils, installing temporary storage and recycling facilities and organizing
legal and technical basis towards determining the principles, policies and programs.
According to Article 5 of this regulation, the direct disposal of waste oil to the any
receiving environment is strickly forbidden.
According to Article 9, the waste oil generating facilities are responsible with
minimizing their waste oil generation, collecting the waste oils originating from different
sources separately and providing the transportation of these wastes by the certified by the
Ministry of Environment and Urbanization for the transportation firms to the certified waste oil
disposal facilities by the Ministry of Environment and Urbanization.
Regulation on Control of Used Batteries and Accumulators
This regulation is published by the Turkish Ministry of Environment and Forestry and
in the Official Gazette dated August 31, 2004 and numbered 25569 (amended in March 03,
2005). This Regulation arranges prohibitions, limitations, responsibilities, precautions,
inspections about labeling and marking of batteries and accumulators, decreasing the
dangerous materials in production, collecting, transferring the waste batteries and
accumulators separately from household and other wastes, dispose and import, transit pass
and export.
Article 13 of this regulation defines the duty of consumer on handling and control of
the waste batteries and accumulators. Article 13 of this regulation is given below:
Consumers of batteries and accumulators are obliged to;
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
19 / 35
a) collect used batteries apart from residential (household) wastes, and deliver used
batteries to the collection points to be established by enterprises engaged in the
distribution and sales of battery products, or by municipalities;
b) deliver the old accumulator when replacing their vehicles’ accumulators to the
temporary storage places established by the enterprises engaged in the distribution
and sale of accumulator products and enterprises operating vehicle
maintenance/repair sites free of charge; and pay a deposit if a new accumulator is to
be purchased when delivering the old one;
According to Article 15, transportation of these wastes is achieved by the firms that
are certified by the governorate of the province.
According to this regulation, the waste batteries and accumulators have to return to
the battery and accumulator producers to provide recycling and disposal of these wastes.
Regulation on Control of Excavation Material, Construction and Demolition
Wastes
This regulation is published in Official Gazette dated March 18, 2004 and numbered
25406. The aim of the Regulations is to organize the technical and administrative issues as
well as the general conditions to be adapted primarily in reduction of excavation earth,
constructional and destruction wastes at source, collection, temporary deposition,
transportation, recovery, utilization and removal of excavation earth, construction and
destruction wastes in a way not causing any damage to the environment.
According to Article 13, excavation, demolition and construction wastes must not be
disposed to receiving environments such as lakes, rivers, etc. they must be stored at the
recycling or storage areas determined by the municipalities.
According to Article 14, the consignors of excavation wastes are responsible with the
implementation of measures necessary for minimizing dust and noise levels. They are also
responsible with covering surrounding of the excavation site.
The excavated material will be used as backfilling material at the site as much as
possible. The excavated material that will be used as backfilling can be temporarily stored at
the site ensuring that 2000 m2 area out of the constrcuction area is available.
During excavation works, natural drainage systems will be protected and necessary
precautions will be taken against erosion and agains any potential damage on cables of
telecommunication and energy systems.
During the excavation, vegetative top soil is separately stripped and strored from
other excavation materials. The quality of quantity of vegetative top soil is protected as much
as possible. This soil is reused on parks, gardens, green fields and agricultural areas.
According to Article 17, the consignor is responsible with paying the costs of
collection, transportation and disposal of excavation wastes.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
20 / 35
According to Article 24, the excavation materials are transported by the vehicles
authorized by the municipalities.
Article 25 of this regulation defines the precautions to be taken during the
transportation of excavated materials. According to this article, the precautions must be
taken by the consignor or the firm transporting these materials in order to prevent
environmental pollution and any potential damage on public health and public goods. For this
purpose, the top of the material shall be covered in order to prevent spillages. Moreover, the
mud on the wheels of the truck shall be cleared of. The municipality can regulate the time of
transportation in order to decrease the impact of this activity on traffic load of the region.
According to article 41, the following issues will be considered during the storage of
excavated materials:
The stored materials will be daily compacted by a compactor.
Necessary warning signals shall be inserted around the storage sites.
The storing activities will not prevent natural surface flow or natural drainage.
The vegetative top soil of the storage are will be stripped prior to the storage
activities.
Accession to the storage site will be available.
Dust generation will be minimized within the storage site by water spraying and other
possible precautions.
The wheels of the vehicles will be cleaned at the exit of storage area.
According to Article 45, Ministry of Environment and Urbanization is responsible with
controlling the compliance to this regulation.
Regulation on Control of Packaging Materials
This regulation is published on the Official Gazette dated June 24, 2007 and
numbered 26562. The purpose of this regulation is; to determine the principles, policies and
programs on packing material and its wastes, to produce packaging materials that have
particular criteria in terms of environment, and have basic conditions/provisions and
characteristics, to prevent the packaging wastes from direct and indirect disposal to the
receiving environment in such a way that they cannot cause any harm on the environment,
to prevent the packaging wastes from being formation, reducing the amount of the packaging
wastes that shall be removed by means of reusing, recycling and recovering of the
packaging wastes that cannot be prevented from being formation, to generate the necessary
technical and administrative standards related with the packaging waste management.
According to Article 26 of this regulation, the consignors of packing materials are
responsible with collecting the packing materials separate from the other solid wastes.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
21 / 35
According to Article 27, the municipalies shall prepare packing wastes management
plant. This plan includes the way of collection and separation of packing wastes by the
municipality. The municipalities can transfer this job to the firms that are certified for
collection and separation of packing wastes. These firms will carry out this job in accordance
with the management plans prepared by the municipalities.
Collection and separation of packing wastes are except the municipalities of the by
the certified firms awarded by the municipalities are banned.
Collection of these wastes by the municipal solid waste collection truck and disposal
to the municipal solid waste landfills are banned.
ANNEX-1. Definition of Packing Wastes
The Ministry of Environment and Urbanzation decide whether a material is packing or
not according to the definitions given in Annex-1.
If a material is not the part of a product, if it is not necessary for protecting and
supporting the product, then this material is considered as packing material.
The coverages that are designed to be filled in the stores or disposable materials
designed for the same purpose are considered as packing materials.
The supporting parts of packings or the pieces attached to the packings are
considered as packing materials.
The following examples are considered to be packing materials:
Stretch film covering CD boxes
Disposable plates and cups
Stretch films, soft packs and sandwich bags used in shops
Packings of fast-foods
The covers of water, fruit juice, mineral waters, shampoo, detergent, etc.
Supporting materials such as papperboard, expanded plastics, etc.
Viols of eggs
The following examples are not considered as packing materials:
Flowerpots
Storage boxes of maintenance metrials
Teabags
Wax covering the cheese
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
22 / 35
The boxes that are used to protect CD
Disposable fork, spoon and knife
The brush of mascara
The stickers on the packing materials
Plastic, metal or other ridges sued for packing
Measuring cups of detergents
Shopping bags
Plastic bags, envelopes and boxes used by couriers
Regulation on Urban Wastewater Treatment
This regulation is published on the Official Gazette dated January 8, 2006 and
numbered 26047. The purpose of this regulation is to protect the environment against the
adverse effects of urban waste water collection, treatment, and discharge as well as the
waste water discharge from certain sectors. This regulation covers the technical and
administrative principles pertaining to the collection of the urban and specific industrial waste
water that is discharged into the sewage system, their treatment and discharge as well as its
monitoring, reporting and controlling.
According to Article 6 of ths regulation the related authority is responsible with
construction, operation and maintenance of urban wastewater treatment plant that can work
effectively under the existing locak meteorological conditions.
According to Article 8, the discharge limits presented in Table 1 and Table 2 of Annex
IV of this regulation has to be achieved by the treatment plants. These limits are presented in
Table A.6 and Table A.7, respectively.
Table A.6. Discharge Limits for Urban Wastewater Treatment*
Parameters Concentrations ( mg/l) Minimum treatment
efficiency (%)
Reference measurement
method
Without Nitrification1
Biochemical oxygen
demand (BOD5 at
20ºC)
25
70-90
40 Article 8 (c)
Homogen, unfiltered, not
precipitated raw sample. Five
days before and after incubation
measurements in the totally
darkened room at the 20ºC
(±1ºC) temperature. Adding a
nitrification inhibitor.
Chemical Oxygen
Demand (COD) 125 75
Homogen, unfiltered, not
precipitated raw sample.
Potassium dichromate method.
Total Suspended
Solids (TSS)
35
35 Article 8 (c)
(More than 10,000 E.P.)
60 Article 8 (c)
902
90 Article 8 (c)
(More than 10000 E.P.)
70 Article 8 (c)
- Filtration of the representative
sample with 0.45 μm
membrane. To dry and weigh at
105 ºC temperature.
- Centrifuge of the representative
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
23 / 35
Parameters Concentrations ( mg/l) Minimum treatment
efficiency (%)
Reference measurement
method
(Between 2,000-10,000 E.P.)
(Between 2000-10000 E.P.)
sample (five mins. with average
2,800 – 3,200 g acceleration). To
dry and weigh at 105 ºC
temperature.
* Concentration values or treatment efficiencies will be applied. 1 If it is possible to make correlation between BOD5 and parameter that is used instead, this parameter can be
exchanged with another parameter: such as Total Organic Carbon (TOC) or Total Oxygen Demand (TOD). 2 This condition depends on the size of the settlement.
Analyses of the lagoon water discharges are prepared with filtered samples; total suspended solid concentrations
must not exceed 150 mg/l in unfiltered samples.
Table A.7. Discharge Limits for Secondary Urban Wastewater Treatment*
Parameters Concentrations ( mg/l) Minimum treatment
efficiency (%)
Reference measurement
method
Total Phosphorus
2 mg/l P
(Between 10,000-100,000 E.P.)
1 mg/l P
(More than 100,000 E.P.)
80 Molecular Absorption
Spectrophotometer
Total Nitrogen1
15 mg/l N
(Between 10,000-100,000 E.P.)
10 mg/l N
(More than 100,000 E.P.)2
70-80 Molecular Absorption
Spectrophotometer
*One or both two parameters can be applied according to the local conditions. Concentration values or treatment
efficiencies will be applied.
Regulation on Environmental Audits
This regulation is published on the Official Gazette dated January 5, 2002 and
numbered 24631. The aim of this regulation is to determine the procedures and basis of
environmental inspections for environmental protection at all phases from the establishment
of facility, the process, production and to final disposal of waste.
According to Artcile 6 of this regulation, the establishments have to prepare a Facility
and Operation Information Form and sent to Ministry of Environment and Urbanization.
Moreover, they have to provide necessary documents during the audits of Ministry of
Environment and Urbanization and other institutions. They have to provide the necessary
analyses to be carried out by the certified laboratories.
Water Pollution Control Regulation
This regulation is published in the Official Gazette dated December 31, 2004 and
numbered 25687. The aim of this Regulation is to protect surface and ground water sources
potential and determine necessary juridical and technical basis for prevention of water
pollution in accordance with the development targets for the best usage of water sources.
This Regulation includes the quality classifications of water, their usage aims, planning basis
and limits on water quality protection, discharge criterion of waste water and basis of
discharge permission, the basis and principleson waste water substructure facilities and
monitoring and control methods, prevention of water pollution.
According to Article 4, water resources must be protected. For this purpose, amont of
wastewater and waste load in the wastewater shall be minimized. The optimum treatment
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
24 / 35
techniques shall be selected in terms of technical and economic aspects. One common
treatment plant shall be established for different wastewater sources having same
characteristics.
According to Article 43, the municipalities are responsible with collection and handling
of wastewaters. Inhabitants of the region under the directorship of the municipalities has to
be connected to the collection and handling systems.
According to Article 54, the operators of the WWTPA are responsible with monitoring
the efficiency of the treatment plant and keeping the related records and reports. The
characteristics and the amount of wastewater shall be recorded and kept. The period of
sampling from the outlet of the wastewater treatment plant will be determined in the
discharge licence. The operators of the WWTP are responsible with these sampling and
measurements.
Regulation on Potable Waters
This regulation is published by Ministry of Health and on the Official Gazette dated
February 17, 2005 and numbered 25730. The aim of this regulation is to provide limit values
and quality criteria for the potable waters to be used by public.
According to Article 6, water can be regarded as clean if it complys with parameters
given in Annex 1 (see Tables A.8, A.9, A.10 and A.11).
According to Article 8, these limit values have to be complied with for the tap water.
According to Artile 10, potable waters will be controlled and monitored by the Ministry
of Health in compliance with the period stated in Annex 2 (see Table A.12).
Annex 1. Limit Values
Table A.8. Microbiologic Parameters
Parameter Parametric Limit (number/100 ml)
Escherichia Coli ( E. Coli ) 0/100 ml
Enterococci 0/100 ml
Coliform bakteria 0/100 ml
Table A.9. Chemical Parameters
Parameter Limit Value Unit
Acrylamide 0.1 μg/L
Antimony 5.0 μg/L
Arsenic 10 μg/L
Benzene 1.0 μg/L
Benzo (a) pyrene 0.010 μg/L
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
25 / 35
Parameter Limit Value Unit
Boron 1 mg/L
Bromate 10 μg/L
Cadmium 5.0 μg/L
Chromium 50 μg/L
Copper 2 mg/L
Cyanide 50 μg/L
1,2-dichlorethane 3.0 μg/L
Epichlorite 0.10 μg/L
Floride 1.5 mg/L
Lead 10 μg/L
Mercury 1.0 μg/L
Nickel 20 μg/L
Nitrate 50 mg/L
Nitrite 0.50 mg/L
Pesticides 0.10 μg/L
Total pesticides 0.50 μg/L
Polycyclic aromatic hydrocarbons 0.10 μg/L
Selenium 10 μg/L
Tetrachloroethane and trichlorethane 10 μg/L
Trihalomethanes 100 μg/L
Vinyl Chloride 0.50 μg/L
Table A.10. Indicator Parameters
Parameter Limit Value Unit
Aluminum 200 μg/L
Ammonium 0.50 mg/L
Chloride 250 mg/L
C. perfringens 0 number/100 ml
Color Acceptable by the consumers and no abnormal change
Conductivity 2500 (at 20 °C) μS / cm
pH 6.5 and 9.5
Iron 200 μg/L
Mangan 50 μg/L
Odour Acceptable by the consumers and no abnormal change
Oxidizability 5.0 mg/L O2
Sulphate 250 mg/L
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
26 / 35
Sodium 200 mg/L
Taste Acceptable by the consumers and no abnormal change
Number of Colonies at 22 °C No abnormal change
Coliforms 0 Number /100 ml
Total Organic Carbon No abnormal change
Turbidity Acceptable by the consumers and no abnormal change
Table A.11. Radioactivity
Parameter Limit Value Unit
Tritium 100 Bq/L
Total Indicative Dose 0.10 mSv/yıl
Alpha Emitters 0.1 Bq/L
Beta Emitters 1 Bq/L
Annex 2. Monitoring
Table A.12. Sampling and Monitoring Periods
Amount of Water Distributed or
Produced Daily
m3
Number of Sampling per Year Number of Auditing per Year
100 2 1
100 and 1000 4 1
1000 and 10000
4
After 1000 m3/day flowrate, 3 monitoring
will be added to this number for every
1000 m3/day flowrate increase.
1
After 1000 m3/day flowrate, 3 audits will
be added to this number for every 3300
m3/day flowrate inxcrease
10000 and 100 000
31
After 10000 m3/day flowrate, 3
monitoring will be added to this number
for every 1000 m3/day flowrate increase.
3
After 10000 m3/day flowrate, 1 audits will
be added to this number for every 10000
m3/day flowrate increase.
100000
301
After 100000 m3/day flowrate, 3
monitoring will be added to this number
for every 1000 m3/day flowrate increase
10
After 100000 m3/day flowrate, 3 audits
will be added to this number for every
25000 m3/day flowrate increase
Regulation on Protection of Buildings Against Fire
This regulation is published in the Official Gazette dated July 26, 2002 and numbered
24822. The aim of this regulation is to define the necessary precautions to minimize loss of
life and property in case of fire.
Article 30 defines the design, construction, protection and maintenance of safety
exits.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
27 / 35
Every building used by the people will include an emergency exit to be used in case
of fire and other emergency cases. Emergency exits shall be constructed in a way to protect
people from smog, heat and other dangers in case of fire.
Emergency exits shall have appropriate dimentions and shall be in appropriate
number to serve for the whole population.
Locations of emergency exits shall be clearly indicated by warning signs.
If required, emergency exits shall be illuminated adequately.
Article 31, emerbency exits start from a location of building and end at a street at the
ground level. The basic components of emergency exits are as follows:
Exits from rooms and other independent locations,
Corridors and passages in in each floor,
Exits of each floors,
Stairways leading to ground floor,
Ways leading from end of stairs to final exit,
Final exit to the streets.
Elevators are not considered as the part of emergency exits.
According to Article 35, emergency exits shall be easily accessed as long as the
building is used by people. Doors of emergency exits shall be opened easily.
According to Article 38, fire escape will be used for evacuating people from the
building in a short time and secure way in case of fire. Construction material of fire exits shall
be fire proof. The directors of the buildings are responsible with the construction of fire
excapes.
Regulation on Structures Constructed at Disaster Areas
This regulation is published by Ministry of Public Works and Settlement and on the
Official Gazette dated July 14, 2007 and numbered 26582. This regulation aims to determine
the technical requirements of the buildings to be constructed in disaster areas.
According to Article 4, any construction activities shall not be constructed at the areas
if one of the landslide, rockfall and snowlide are observed at this area.
According to Article 5, foundations of the buildings have to be strengthened if there is
the risk of flood in order to make the building resistant to floods.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
28 / 35
Article 6 is related with the protection against fire. According to this article, if there is a
fire risk at the site of a building, then this building shall be constructed In compliance with the
articles of Regulation on Protection of Buildings against Fire.
According to Article 7, which mention the precautions to be taken against the
earthquake, the buildings shall construct in compliance with regulation on Buildings
Constructed in Earthquake Areas.
Labour Law (Law Numbered 4857)
This law is published in the Official Gazette dated June 10, 2003 and numbered
25134. The purpose of this law is to regulate the working conditions and work-related rights
and obligations of employers and employees working under an employment contract.
Artcile 5 defines the principle of equal treatment. According to this principle, no
discrimination based on language, race, sex, political opinion, philosophical belief, religion
and sex or similar reasons is permissible in the employment relationship.
Unless there are essential reasons for differential treatment, the employer must not
make any discrimination between a full-time and a part-time employee or an employee
working under a fixed-term employment contract (contract made for a definite period) and
one working under an open-ended employment contract (contract made for an indefinite
period).
Accrding to Article 77, with a view to ensure occupational health and safety in their
establishments, employers shall take all the necessary measures and maintain all the
needed means and tools in full; and employees are under the obligation to obey and observe
all the measures taken in the field of occupational health and safety.
In order to ensure compliance with and supervision of the measures taken for
occupational health and work safety at the establishment, the employer must inform the
employees of the occupational risks and measures that must be taken against them as well
as employees’ legal rights and obligations and, in this connection, he must provide the
employees with the necessary training on occupational health and safety.
According to Article 91, the State shall follow up, supervise and inspect the
implementation of labour legislation governing working conditions. This duty shall be
performed by officials of the Ministry of Labour and Social Security in sufficient numbers and
with the necessary qualifications, specially empowered to exercise supervision and to make
visits of inspection.
According to Article 92, for the purpose of implementing Article 91, the administrative
authorities and the competent officials responsible for following up, supervising and
inspecting working conditions shall be entitled.
During an inspection it shall be the duty of the employer, his representatives, the
employees and any other person concerned to attend whenever summoned by the
authorities or officials responsible for inspection, to give them any information requested, to
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
29 / 35
present for their inspection and, if necessary, to hand over all relevant documents and
records, to provide them with every assistance in the exercise of their functions as indicated
in the first paragraph, and to comply, without any attempt at evasion, with all relevant orders
and requests received in this connection.
The reports prepared by the authorities and officials empowered to follow up,
supervise and inspect working conditions shall be held as valid until they are disproven.
According to Article 93, the authorities and officials responsible for following up,
supervising and inspecting working conditions shall not, in the performance of their duties,
cause any derangement of or hindrance to the normal progress of operations and the work
of the establishment, except in so far as may be deemed necessary by the nature of their
responsibilities; and they shall observe strict secrecy with respect to all they have seen and
learned concerning the technical secrets of the employer and the establishment and his
financial and commercial circumstances, unless it is necessary to disclose these matters in
order to institute official proceedings, and they shall not reveal the names and identities of
employees and other persons from whom they have received information or who have made
reports to them.
According to Article 95, the municipalities and other authorities competent to issue
permissions for the setting up and opening of establishments shall, before giving the said
permisions, investigate the existence of the opening and operating certificate which must
have been granted by the Ministry of Labour and Social Security in accordance with
pertinent labour legislation.
Municipalities and other authorities may not give opening and operating licences to
establishments which have not yet been granted opening and operating certificates by the
Ministry of Labour and Social Security.
Public institutions and organisations shall communicate to the competent regional
directorate of labour the results of their occupational health and safety inspections and
supervisions at establishments as well as the actions they will take regarding these
establishments.
Municipalities and other authorities competent to give permits for setting up and
opening establishments shall communicate every month to the relevant regional directorates
of labour lists of names and addresses of employers and establishments for which they have
issued permits as well as the nature of the work to be performed until the fifteenth day of the
following month.
Regulation on Occupational Health and Safety
This regulation is published by the Ministry of Labour and Social Security and on the
Official Gazette dated December 9, 2003 and numbered 25311. This regulation includes the
precautions that shall be taken on the workplaces in order to minimize health and safety
risks.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
30 / 35
According to Article 5, employers are responsible with protecting the health and
safety of the workers.
According to Article 6, employers are responsible with the following issues:
They have to prevent occupational risks, train the workers, take all the necessary
precautions, make necessary arrangements and provide equipments in order to protect
health and safety of the workers.
The employer shall take the following principals into consideration to provide
occupational health and safety:
Preventing risks
Assessing the risks that can not be prevented
Coping with the risks at the source
While determining the duty of a worker, health and safety of the worker shall be
considered.
Necessary warning signals shall be inserted in the locations that are very dangerous.
Acoording to Article 7, employer shall hire one or more responsible person for the
prevention of health and safety risks and implementation of protective activities.
According to Article 8, the employers shall take the measures for first aid, fire fighting
and evacuation of workers considering the number of the employees and necessary number
of responsible persons. They shall make the necessary arrangement to provide the contact
with the necessary institutions in case of emergency.
According to Article 9, employers are also responsible with assessing the risks by
considering the group of workers that are under special risks. According to the results of this
assessment, they shall determine the protective measures and equipments. The
occupational accidents that shall also be recorded and the records shall be kept by the
employer.
According to Article 12, the workers have to be trained that includes special health
and safety precautions depending on the content of the job. This training session shall be
conducted;
Before the initiation of work,
When the workplace or the work changed,
When the equipments change,
When a new technology is applied.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
31 / 35
Training sessions shall be repeated when required. The employer shall adequately
emphasize the health and safety risks that can be faced and the related precautions that
must be taken agains these risks.
Guidelines on Worker Health and Occupational Safety
This guideline was published on the Official Gazete dated January 11, 1974 and
numbered 14765. It defines the health conditions that must be accomplished at the
residential areas of the workers. Moreover, necessary precautions that must be taken to
prevent potential occupational accidents and diseases are als defined in this guideline.
According to Article 2, every employer and worker has to comply with the issues
stated in this guideline.
According to Article 3, the employer has to train and inform the workers about the
health and safety rules that they are obliged to comply with.
According to Article 16, the workplaces shall be illuminated adequately by the day
light or by lamps.
According to Article 21, closed workplaces have to be aerated at least once for one
hour. Sharp temperature decreases during the aeration will be prevented during winter time.
At the workplaces where heavy and dangerous works are being carried out, the noise
level shall be below 95 dB. In such conditions, earmuffs and ear-plugs have to be provided
for the workers. If heavy and dangerous works ae not being conducted, then noise level
must be below 80 dB.
According to Article 32, drinking water must be free from patogens.
According to Article 36, if lunch time is not long enough to go home, then the
employer have to provide a safe place where workers can have their lunch.
According to article 39, cleaning places shall be provided for the workers to wash
their hands and bodies. Flowing water and necessary cleaning equipments shall be
provided.
According to Article 76, if dust generatin activities such as construction will be
conducted, then the following precautions have to be taken;
Dust generating activities will be realized by a closed system, if they are
technologically and economically viable
Aspiration system, water curtains and vacuums will be utilized to prevent the
spreading of the dust.
Depending on the content of the dust, different personal protective
equipments and protective masks will be provided to the workers.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
32 / 35
At the end of each shift, the workers employed in dust generating works will
be provided to have a bath and they will be prevented to sleep or eat before
having bath.
Each worker will have a medical control before employment and the ones
having respiratory and circulatory disorders and skin problems will not be
employed for dust generating works.
According to Article 78, in order to protect workers from the adverse impacts of noise,
the following precautions shall be taken:
Before the installation of noise generating equipment and machinery, floor of
workplace shall be covered with isolation material against noise and vibration.
Before being employed, workers shall have health checks and the ones
having problem with their ears and nervous system will not be employed to be
worked for noise generating activities.
According to Article 79, in order to protect workers from the adverse impacts of
vibration, the following precautions shall be taken:
Before being employed, workers shall have health checks and the ones having
problem with their bones, arthrosises and vascular system will not be employed to be worked
for vibration generating activities.
According to Article 116, adequate fire extinction equipment and personnel who can
use these equipments shall be present at the workplaces.
According to Article 128, mobile fire extinguishers shall be controlled and checked
once every 6 months.
According to Article 134, recently employed workers shall be informed about the
emergency exits and equipments to be used in case of fire. Employer shall be responsible
with that.
Guidelines on Worker Health and Safety on Constructive Works
This guideline are published on the Official Gazette dated September 12, 1974 and
numbered 15004. This guideline sets the health and safety precautions that must be taken in
construction works.
According to Article 6, the construction works shall be carried out during daytime.
However, in case it needs to be continue at the night time, necessary illumination for
ensuring safe working conditions will be provided.
According to Article 7, helmets shall be used by the workers to protect their heads
from falling objects. Guardrails will be constructed at the high buildings and stairs in order to
prevent the worker falling from high locations.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
33 / 35
According to Article 8, dangerous locations will be surrounded by the barriers and
warning signals and lightes will be inserted.
According to Article 17, entrance and exit of vehicles and car parks shall be specified.
According to Article 18, the excavation areas will be surrounded by wooden curtains
prior to the initiation of xcavation activities.
According to Article 20, necessary precautions will be taken in excavation sites in
order to protect electricity cables, gas pipes, water ways and sewer system, if any.
According to Article 23, if the excavations are deeper than 150 cm, the walls of the
excavated area will be supported in order to prevent collapsing.
According to Article 25, for the excavations deeper than 150 cm, ladder will be
provided for the workers.
According to Article 26, safety harnesses and signal devices will be provided for the
staff working at the deeply excavated areas such as sewer system excavations.
According to Article 27, excavation works shall be stopped at rainy weathers. After
the rain is ceased, necessary precautions will be taken before the excavation activities
initiate.
According to Article 28, shelters shall be provided to the workers in order to protect
from rain.
According to Article 29, top boots will be provided for the staff working inside the
water.
According to Article 30, heavy machineries will be controlled by competent operators
and any worker aill not be present at their working areas.
According to Article 43, if there is flood risk, emergency exits will be determined at the
excavation areas.
Noise Regulation
This regulation is published by Ministry of Labor and Social Security and published on
the Official Gazette dated December 23, 2003 and numbered 25325. This regulation
includes the necessary measures to protect the workers from the potential adverse impacts
of noise.
According to Article 5, weekly average noise exposure levels and sound pressure
levels are as follows:
Exposure limit values: weekly average exposure level= 87 dB (A) and sound
pressure level= 200 Pai
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
34 / 35
Highest effective exposure values: weekly average exposure level= 85 dB (A)
and sound pressure level= 140 Pai
Lowest effective exposure values: weekly average exposure level= 80 dB (A)
and sound pressure level= 112 Pai
Weekly average noise exposure levels shall not exceed 87 dB (A).
According to Article 7, in order to decrease exposure, noise will be destroyed or
minimized at source, as much as possible. If possible, noise shall be minimized by using
different technologies. If technology alteration is not possible, noise isolators shall be used
and personel protective equipments shall be distributed.
According to Article 8, personal protective equipments are earmuffs and ear-plugs.
Employer shall be responsible wih use of these equipments.
According to Article 9, exposure levels stated in Article 5 shall not be exceeded.
Vibration Regulation
This regulation is published by Ministry of Labour and Social Security and on the
Official Gazette dated December 23, 2003 and numbered 25325. This regulation includes
the necessary measures to protect the workers from the potential adverse impacts of
vibration.
Article 5 explains the exposure limits to the vibration. According to this article, for the
exposure to vibration on hand and arm,
1. Limit value for daily exposure is 5 m/s2 for 8 hour working period.
2. Effective value for daily exposure is 2.5 m/s2 for 8 hour working period.
For the exposure to vibration on the whole body,
1. Limit value for daily exposure is 1.15 m/s2 for 8 hour working period.
2. Effective value for daily exposure is 0.5 m/s2 for 8 hour working period.
Law on Natural and Cultural Heritages (Law Numbered 2863)
This law is published on the Official Gazette dated July 23, 1983 and numbered
18113. The aim of this law is is to define the issues related with the natural and cultural
assets, regulate the related activities and facilities, and determine the responsibilities of
authorized institutions.
According to Article 4 of this law, if any natural and cultural asset is founded, then the
nearest museum or the headmen of the village or the other civil administrations has to be
informed at most in three days.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-A
35 / 35
According to Article 9 of this regulation, cultural or natural assets can not be used,
disturbed, relocated without the permission of Ministry of Culture and Tourism.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-B
1 / 3
Appendix-B FLOWCHART OF WWTP AND ALTERNATIVE
PROJECT
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-B
2 / 3
MUGLA WASTEWATER TREATMENT PLANT MODIFIED BARDENPHO PROCESS
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-B
3 / 3
ALTERNATIVE NO.1 – MUGLA MUNICIPALITY WASTEWATER TREATMENT PLANT
ACTIVATED SLUDGE PROCESS WITH DENITRFICATION
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-C
1 / 3
Appendix-C GEOLOGICAL MAPS OF THE ROJECT SITE
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-C
2 / 3
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-C
3 / 3
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-D
1 / 5
Appendix-D METEOROLOGICAL DATA FOR MUGLA
PROVINCE
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-D
2 / 5
Enlem : 37.13
Boylam : 28.22
Yukseklik : 646 m ( MUGLA ) MUGLA
METEOROLOJIK Rasat S. A Y L A R
ELEMANLAR (YIL) I II III IV V VI VII VIII IX X XI XII YILLIK
Ortalama Yerel Basinc (hPa) 30 941.5 940.6 939.6 938.7 939.1 938.0 936.0 936.8 940.0 942.2 942.7 941.8 939.8
En Yuksek Yerel Basinc (hPa) 30 957.1 955.4 953.2 950.3 947.3 945.6 943.2 943.0 947.8 950.5 953.2 953.5 957.0
En Dusuk Yerel Basinc (hPa) 30 910.0 918.4 918.0 924.8 927.8 927.8 929.1 930.4 931.1 931.0 927.6 920.4 910.0
Saat 07 deki Ortalama Sicaklik (C) 30 2.6 2.5 4.5 8.5 13.8 18.8 21.8 21.1 16.5 11.2 6.3 4.0 11.0
Saat 14 deki Ortalama Sicaklik (C) 30 9.1 9.8 13.2 17.3 23.1 28.6 32.4 32.3 28.5 22.6 15.3 10.2 20.2
Saat 21 deki Ortalama Sicaklik (C) 30 5.1 5.6 8.1 11.8 16.8 22.0 25.4 24.8 20.7 15.4 9.7 6.4 14.3
Ortalama Sicaklik (C) 30 5.5 5.9 8.5 12.3 17.6 22.9 26.2 25.7 21.6 16.1 10.2 6.8 14.9
Ort. Sicaklik >= 5 C Old. Gunler Sayisi 30 19.0 18.6 26.6 29.7 31.0 30.0 31.0 31.0 30.0 31.0 28.0 23.1 329.0
Ort. Sicaklik >= 10 C Old. Gunler Sayisi 30 1.4 2.6 10.8 22.9 30.6 30.0 31.0 31.0 30.0 30.0 18.0 4.6 242.9
Ortalama Yuksek Sicaklik 30 10.0 10.8 14.2 18.4 24.3 29.7 33.3 33.2 29.2 23.4 16.2 11.1 21.2
Ortalama Dusuk Sicaklik 30 1.5 1.6 3.4 6.9 11.4 16.2 19.7 19.5 15.1 10.3 5.4 3.0 9.5
En Yuksek Sicaklik Gunu 30 18 7 27 24 26 13 6 12 1 1 1 4 6
En Yuksek Sicaklik Yili 30 1987 2004 2001 1989 1990 2001 2000 2002 2003 1991 2004 2004 2000
En Yuksek Sicaklik (C) 30 18.8 21.2 26.8 29.8 35.7 38.8 41.6 40.8 38.8 34.5 27.6 20.4 41.6
Yuk. Sicaklik >=30 C Old. Ort. Gunler Sayisi 30 3.2 15.1 26.9 26.3 13.0 2.2 86.7
Yuk. Sicaklik >=25 C Old. Ort. Gunler Sayisi 30 0.3 2.7 14.4 26.7 30.8 31.0 27.0 12.4 0.7 146.0
Yuk. Sicaklik >=20 C Old. Ort. Gunler Sayisi 30 0.2 2.9 11.1 25.7 29.5 31.0 31.0 29.9 24.1 5.9 0.1 191.4
Yuk. Sicaklik <=-0.1 C Old. Ort. Gunler Sayisi 30 0.1 0.1 0.2
Gunluk En Yuksek Sicaklik Farki
En Dusuk sicaklik Gunu 30 8 9 1 10 4 1 1 24 28 28 25 22 9
En Dusuk sicaklik Yili 30 2004 1976 1985 1997 1990 1991 1983 1977 1992 1985 1995 2002 1976
En Dusuk Sicaklik (C) 30 - 7.8 - 9.9 - 8.5 - 3.6 1.0 6.7 11.3 13.2 5.6 0.20 - 4.0 - 6.8 - 9.9
Dus. Sicaklik <=-0.1 C Old. Ort. Gunler Sayisi 30 11.7 9.6 4.6 0.3 2.6 7.4 36.2
Dus. Sicaklik <=-3 C Old. Ort. Gunler Sayisi 30 3.8 3.8 1.2 0.0 0.3 2.0 11.1
Dus. Sicaklik <=-5 C Old. Ort. Gunler Sayisi 30 1.0 1.4 0.4 0.3 3.1
Dus. Sicaklik <=-10 C Old. Ort. Gunler Sayisi 30 0.0
Dus. Sicaklik <=-15 C Old. Ort. Gunler Sayisi 30 0.0
Dus. Sicaklik <=-20 C Old. Ort. Gunler Sayisi 30 0.0
Dus. Sicaklik >=20 C Old. Ort. Gunler Sayisi 30 0.1 3.4 14.7 13.2 1.6 0.0 33.0
Dus. Sicaklik >=15 C Old. Ort. Gunler Sayisi 30 0.1 3.9 19.7 29.7 29.6 15.7 2.5 0.1 101.3
Dus. Sicaklik >=10 C Old. Ort. Gunler Sayisi 30 0.1 0.2 0.7 4.5 21.3 29.4 31.0 31.0 29.2 16.1 3.6 0.8 167.9
Dus. Sicaklik >=5 C Old. Ort. Gunler Sayisi 30 6.9 5.7 10.4 22.4 30.5 30.0 31.0 31.0 30.0 29.3 16.3 10.4 253.9
Ortalama Toprakustu Minimum Sicaklik 30 0.3 0.3 1.9 5.0 9.3 14.0 17.8 17.6 13.0 8.3 3.9 1.8 7.8
En dusuk Toprakustu Minimum Sicaklik 30 - 8.9 -12.0 -10.3 - 4.8 - 0.4 1.0 2.0 10.2 3.4 - 2.7 - 6.9 - 8.6 -12.0
Top. us. min. sic. <=-0.1 C Old. Gunler Sayisi 30 15.0 13.1 9.0 1.4 0.0 0.2 5.4 11.0 55.1
Top. us. min. sic. <=-3 C Old. Gunler Sayisi 30 8.0 6.3 2.6 0.0 1.6 4.2 22.7
Top. us. min. sic. <=-5 C Old. Gunler Sayisi 30 3.1 2.7 0.9 0.3 1.5 8.5
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-D
3 / 5
Istasyonun Calisma Suresi : 1975 - 2004 ARASTIRMA ve BILGI ISLEM DAIRE BASKANLIGI
Enlem : 37.13
Boylam : 28.22
Yukseklik : 646 m ( MUGLA ) MUGLA
METEOROLOJIK Rasat S. A Y L A R
ELEMANLAR (YIL) I II III IV V VI VII VIII IX X XI XII
YILLIK
Top. us. min. sic. <=-10 C Old. Gunler Sayisi 30 0.2 0.0 0.2
Ortalama Buhar Basinci (hPa) 30 7.1 6.9 7.6 9.4 12.0 13.9 15.5 15.6 13.2 11.2 9.3 8.0 10.8
Saat 07 deki Ortalama Bagil Nem (%) 30 86 84 85 84 77 67 61 64 71 81 87 87 77
Saat 14 deki Ortalama Bagil Nem (%) 30 63 58 52 48 42 34 31 31 33 42 56 66 46
Saat 21 deki Ortalama Bagil Nem (%) 30 78 75 73 70 64 54 48 51 55 66 77 82 66
Ortalama Bagil Nem (%) 30 76 72 70 67 61 52 47 49 53 64 73 78 64
En dusuk Bagil Nem (%) 30 16 12 6 5 6 4 5 5 3 5 10 18 3
Saat 07 deki Ortalama Bulutluluk (0-10) 30 5.0 4.9 4.3 4.1 2.6 0.8 0.3 0.3 0.7 2.6 4.1 5.4 2.9
Saat 14 deki Ortalama Bulutluluk (0-10) 30 5.4 5.5 5.4 5.6 4.8 2.9 1.8 2.0 2.2 3.5 4.7 5.8 4.1
Saat 21 deki Ortalama Bulutluluk (0-10) 30 4.2 4.0 3.5 3.3 2.2 0.8 0.3 0.2 0.6 1.7 3.3 4.4 2.4
Ortalama Bulutluluk (0-10) 30 4.9 4.8 4.4 4.3 3.2 1.5 0.8 0.8 1.2 2.6 4.1 5.2 3.2
Ort. Acik Gunler Sayisi (bult. 0.0-1.9) 30 8.7 7.8 8.5 7.8 11.6 21.3 26.5 26.8 23.4 16.3 10.9 7.6 177.2
Ort. Bulutlu Gunler Sayisi (bult. 2.0-8.0) 30 13.9 13.8 16.8 18.2 17.6 8.6 4.5 4.1 6.5 12.9 13.5 14.3 144.7
Ort. Kapali Gunler Sayisi (bult. 8.1-10.0) 30 8.4 6.7 5.7 4.1 1.8 0.1 0.0 0.0 0.1 1.8 5.6 9.1 43.4
Saat 07 deki Ort. Toplam Yagis Miktari (mm) 30 98.5 67.5 41.4 27.9 10.9 2.1 0.6 0.3 4.1 19.9 65.0 110.7 448.9
Saat 14 deki Ort. Toplam Yagis Miktari (mm) 30 62.8 46.6 42.0 19.9 21.6 6.8 1.4 5.5 4.4 18.2 51.3 73.8 354.3
Saat 21 deki Ort. Toplam Yagis Miktari (mm) 30 59.7 41.2 39.4 22.8 21.8 13.4 4.8 2.7 5.8 15.9 47.0 59.7 334.2
Ortalama Toplam Yagis Miktari (mm) 30 226.0 159.7 122.3 74.7 53.5 24.7 7.1 9.1 14.3 54.8 163.7 251.6 1161.5
Gunluk En Cok Yagis Miktari (mm) 30 138.9 96.0 103.5 90.9 78.5 45.6 30.8 68.2 47.7 107.2 119.5 155.6 155.6
Yagis >= 0.1 mm Oldugu Gunler Sayisi 30 13.5 12.1 10.3 10.3 7.8 3.5 1.6 1.6 2.5 5.8 9.9 14.5 93.4
Yagis >= 10 mm Oldugu Gunler Sayisi 30 6.1 4.7 3.6 2.2 1.6 0.8 0.2 0.2 0.4 1.7 4.4 6.9 32.8
Yagis >= 50 mm Oldugu Gunler Sayisi 30 1.1 0.6 0.4 0.1 0.1 0.0 0.1 0.8 1.1 4.3
Ortalama Kar Yagisli Gunler Sayisi 30 1.6 1.2 1.1 0.1 0.1 0.6 4.8
Ortalama Kar Ortulu Gunler Sayisi 30 0.8 0.6 0.6 0.2 2.2
En Yuksek Kar Ortusu Kalinligi (cm) 10 17.0 25.0 12.0 0.0 5.0 25.0
Ortalama Sisli Gunler Sayisi 30 2.9 1.6 1.5 1.1 0.6 0.2 0.2 1.0 3.3 5.1 17.1
Ortalama Dolulu Gunler Sayisi 30 0.9 0.7 0.8 0.6 0.4 0.3 0.2 0.1 0.1 0.1 0.3 0.5 5.0
Ortalama Kiragili Gunler Sayisi 30 7.9 6.3 3.7 0.5 0.1 3.2 5.7 27.1
Ortalama Orajli Gunler Sayisi 30 3.6 2.4 2.8 3.5 4.8 3.2 2.1 2.0 1.7 2.3 3.2 4.6 36.2
Saat 07 deki Ortalama Ruzgar hizi (m/s) 30 1.8 1.9 1.7 1.5 1.8 2.2 2.8 2.6 1.9 1.3 1.4 1.7 1.9
Saat 14 deki Ortalama Ruzgar hizi (m/s) 30 2.8 3.0 3.0 3.1 3.1 3.3 3.3 3.2 3.1 2.7 2.7 2.7 3.0
Saat 21 deki Ortalama Ruzgar hizi (m/s) 30 1.8 2.0 1.8 1.5 1.4 1.8 2.1 1.9 1.7 1.5 1.6 1.8 1.8
Ortalama Ruzgar Hizi (m/s) 30 2.1 2.3 2.2 2.0 2.1 2.4 2.7 2.6 2.2 1.8 1.9 2.1 2.2
En Hizli Esen Ruzgarin Yonu 30 NE NNE SE NNE ESE NNE NNE NNE NW WNW ENE SSW NNE
En Hizli Esen Ruzgarin Hizi (m/s) 30 25.6 30.0 28.7 20.9 17.2 17.9 20.6 17.6 19.2 27.6 27.8 26.1 30.0
Ort. Firtinali Gun Say. (ruz.hiz>=17.2 m/s) 29 1.0 0.9 0.5 0.2 0.1 0.0 0.2 0.0 0.1 0.3 0.4 0.9 4.6
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-D
4 / 5
Istasyonun Calisma Suresi : 1975 - 2004 ARASTIRMA ve BILGI ISLEM DAIRE BASKANLIGI
Enlem : 37.13
Boylam : 28.22
Yukseklik : 646 m ( MUGLA ) MUGLA
METEOROLOJIK Rasat S. A Y L A R
ELEMANLAR (YIL) I II III IV V VI VII VIII IX X XI XII
YILLIK
Ort. Kuv.Ruz. Gun Say. (ruz.hiz 10.8-17.1 m/s) 29 5.1 5.4 4.3 3.9 3.4 4.2 5.3 4.7 2.9 3.0 4.2 4.3 50.7
N Ruzgarin Esme Sayilari Toplami 30 78 65 72 75 69 84 97 62 69 65 73 74 883
N Ruzgarin Ortalama Hizi (m/s) 30 2.2 2.4 2.2 1.5 1.7 2.0 2.5 2.4 1.9 2.2 2.0 1.8 2.1
NNE Ruzgarin Esme Sayilari Toplami 30 88 100 96 64 81 86 133 101 91 107 96 95 1138
NNE Ruzgarin Ortalama Hizi (m/s) 30 2.3 3.0 2.4 2.3 1.9 2.9 3.3 3.1 2.8 2.6 2.2 2.5 2.7
NE Ruzgarin Esme Sayilari Toplami 30 114 120 108 78 93 93 106 78 104 120 91 97 1202
NE Ruzgarin Ortalama Hizi (m/s) 30 2.3 2.4 1.7 1.4 1.7 2.5 2.9 2.7 2.2 1.8 1.9 2.3 2.2
ENE Ruzgarin Esme Sayilari Toplami 30 190 151 198 204 181 166 139 147 168 201 168 186 2099
ENE Ruzgarin Ortalama Hizi (m/s) 30 1.3 1.4 1.4 1.2 1.2 1.3 1.9 1.5 1.4 1.2 1.4 1.2 1.4
E Ruzgarin Esme Sayilari Toplami 30 204 172 153 187 125 95 63 87 90 120 165 221 1682
E Ruzgarin Ortalama Hizi (m/s) 30 2.2 2.2 2.2 1.6 1.4 1.3 1.2 1.4 1.2 1.4 1.7 2.0 1.8
ESE Ruzgarin Esme Sayilari Toplami 30 256 239 240 241 172 96 72 67 97 146 245 322 2193
ESE Ruzgarin Ortalama Hizi (m/s) 30 2.7 2.6 2.7 2.2 2.0 1.7 1.6 2.2 1.8 1.7 2.4 2.7 2.3
SE Ruzgarin Esme Sayilari Toplami 30 170 151 138 162 123 69 87 58 99 111 166 171 1505
SE Ruzgarin Ortalama Hizi (m/s) 30 2.7 3.0 2.8 2.6 2.3 2.2 2.7 2.6 2.0 2.1 2.4 2.6 2.5
SSE Ruzgarin Esme Sayilari Toplami 30 145 133 185 171 151 86 81 107 133 136 172 151 1651
SSE Ruzgarin Ortalama Hizi (m/s) 30 2.3 2.7 2.5 2.6 2.6 2.5 2.7 2.6 2.6 2.1 2.2 2.3 2.5
S Ruzgarin Esme Sayilari Toplami 30 90 86 125 154 155 105 99 120 136 143 119 115 1447
S Ruzgarin Ortalama Hizi (m/s) 30 2.1 2.2 2.4 2.6 2.8 2.8 2.8 2.7 2.5 2.4 2.2 2.0 2.5
SSW Ruzgarin Esme Sayilari Toplami 30 71 55 77 93 93 76 54 57 82 83 80 54 875
SSW Ruzgarin Ortalama Hizi (m/s) 30 1.7 1.8 2.1 2.3 2.3 2.6 2.6 2.6 2.5 2.0 1.7 1.7 2.2
SW Ruzgarin Esme Sayilari Toplami 30 28 24 28 36 37 35 29 34 27 31 25 35 369
SW Ruzgarin Ortalama Hizi (m/s) 30 1.7 1.4 1.8 1.9 2.3 2.2 2.3 2.3 2.6 1.7 1.9 1.1 1.9
WSW Ruzgarin Esme Sayilari Toplami 30 47 55 65 76 66 74 83 61 75 62 51 54 769
WSW Ruzgarin Ortalama Hizi (m/s) 30 2.0 2.3 2.3 2.4 2.3 2.3 3.0 2.6 2.1 2.0 1.8 1.5 2.3
W Ruzgarin Esme Sayilari Toplami 30 122 124 141 147 144 149 178 160 150 137 107 100 1659
W Ruzgarin Ortalama Hizi (m/s) 30 2.6 2.8 2.8 2.8 3.0 2.8 3.3 3.2 2.9 2.7 2.6 2.4 2.9
WNW Ruzgarin Esme Sayilari Toplami 30 509 451 507 464 667 712 795 882 723 477 406 467 7060
WNW Ruzgarin Ortalama Hizi (m/s) 30 2.9 3.0 2.9 2.9 2.9 3.2 3.3 3.2 3.0 2.8 2.8 2.9 3.0
NW Ruzgarin Esme Sayilari Toplami 30 248 237 241 170 250 383 403 400 269 276 201 207 3285
NW Ruzgarin Ortalama Hizi (m/s) 30 2.3 2.4 2.5 2.4 2.2 2.6 2.8 2.7 2.4 2.2 2.4 2.4 2.5
NNW Ruzgarin Esme Sayilari Toplami 30 129 157 140 110 132 257 278 222 163 179 118 128 2013
NNW Ruzgarin Ortalama Hizi (m/s) 30 2.3 2.1 2.1 1.9 2.0 2.5 2.6 2.4 2.1 1.8 2.2 2.4 2.2
Ortalama 5 cm Toprak Sicakligi (C) 30 4.6 5.8 9.1 14.1 21.0 27.6 32.0 31.1 25.6 17.7 10.0 6.0 17.1
En dusuk 5 cm Toprak sicakligi (C) 30 - 1.8 - 4.5 - 0.7 5.0 9.4 14.3 20.7 21.1 14.5 7.7 1.0 - 1.7 - 4.5
Ortalama 10 cm Toprak Sicakligi (C) 30 5.1 6.3 9.5 14.4 21.0 27.2 31.4 30.9 26.0 18.5 10.7 6.6 17.3
En dusuk 10 cm Toprak sicakligi (C) 30 - 0.6 - 1.1 0.5 5.7 10.9 15.0 22.4 23.6 16.2 9.1 2.4 - 0.3 - 1.1
Ortalama 20 cm Toprak Sicakligi (C) 30 5.1 6.0 8.9 13.5 19.8 25.6 29.7 29.5 25.4 18.6 11.1 6.8 16.7
En dusuk 20 cm Toprak sicakligi (C) 30 0.5 0.0 1.8 5.8 10.9 16.1 21.8 23.9 17.9 10.9 4.2 0.7 0.0
Ortalama 50 cm Toprak Sicakligi (C) 30 6.8 7.0 9.1 13.0 18.3 23.6 27.8 28.5 25.7 20.3 13.6 8.9 16.9
En dusuk 50 cm Toprak sicakligi (C) 30 3.6 3.2 3.6 7.0 11.6 15.2 22.3 25.2 20.6 13.3 8.0 4.1 3.2
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impact Assessment Report
Appendix-D
5 / 5
Istasyonun Calisma Suresi : 1975 - 2004 ARASTIRMA ve BILGI ISLEM DAIRE BASKANLIGI
Enlem : 37.13
Boylam : 28.22
Yukseklik : 646 m ( MUGLA ) MUGLA
METEOROLOJIK Rasat S. A Y L A R
ELEMANLAR (YIL) I II III IV V VI VII VIII IX X XI XII
YILLIK
Ortalama 100 cm Toprak Sicakligi (C) 30 8.5 8.0 9.2 12.1 16.1 20.7 24.8 26.3 25.1 21.5 15.9 11.1 16.6
En dusuk 100 cm Toprak sicakligi (C) 30 5.9 5.6 5.9 6.8 11.3 15.6 21.0 23.2 21.6 16.3 11.3 7.4 5.6
Ortalama Buharlasma (mm) 30 94.2 152.8 225.1 292.4 271.0 193.0 114.1 45.1
Gunluk En Cok Buharlasma (mm) 30 0.0 0.0 0.0 10.0 13.0 14.8 17.0 15.6 15.5 10.7 7.0 0.0 17.0
Gunluk Ort. Guneslenme Suresi (saat,dakika) 30 04:05 05:03 06:06 07:03 08:27 10:13 10:45 10:45 09:40 07:26 05:08 03:37 07:22
Gunluk Ort. Guneslenme Sidt.(cal/cm^2.dak) 30 166.30 231.01 313.35 385.88 456.59 512.92 508.39 462.76 392.07 285.50 191.37 138.44 337.05
Aylik En Yuk. Guneslenme Sidt.(cal/cm^2.dak) 30 1.08 1.40 1.50 1.56 1.84 1.53 1.45 1.34 1.95 1.25 1.11 0.99 1.95
Ortalama Deniz Suyu Sicakligi (C) 0.0
En Yuksek Deniz Suyu Sicakligi (C)
En dusuk Deniz Suyu Sicakligi (C)
Istasyonun Calisma Suresi : 1975 - 2004 ARASTIRMA ve BILGI ISLEM DAIRE BASKANLIGI
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-E
1 / 13
Appendix-E FLORA INVENTORY
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-E
2 / 13
FLORA INVENTORY
The flora inventory is prepared in the light of the site surveys and literature studies.
The reference named “Flora of Turkey and the East Aegean Islands, Volume 1-10, 1965-
1988” of P. H. Davis is utilized in the determination of species. This book is also the
reference for the authors of the taxa stated in the list. The regional flora list is prepared in
alphabetic order. The habitat, flora zone, endemism and relative abundance of species as
well as risk classes existing in Red Data Book of Turkey are mentioned in the list. The scale
and abbreviations stated in the list are defined below. The Dictionary of Plant Names was
utilized for the names of specie in Turkish and for its locally used names as well. Besides,
the Turkish Plant Data Service of the Scientific and Technological Research Council of
Turkey was made use of in preparing this inventory.
PHYTOGEOGRAPHICAL REGIONS OF TURKEY
[Davis P.H., Harper P.C. and Hege I.C. (eds.), 1971. Plant Life of South-West Asia.
The Botanical Society of Edinburg]
EUR.-SIB.(EUX): European-Siberian Region( sub-region); Col.: Kolsik secture of Oksin sub-
region
MED.: Mediterranaen Region (Eastern Mediterranaen sub-region); W.A: Western Anatolian
Region; T.: Taurus Region; A.:Amanus Region
IR.-TUR.: Iran-Turanien Region; C.A.: Central Anatolia Region; E.A.: Eastern Anatolian
Region (Mes: Mezsopotamia)
X: Most probably Central European/Balkan sub-region of European-Siberian Region
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-E
3 / 13
(mt): Mountain
Relative Abundancy Classes:
1 Very Rare
2 Rare
3 Moderately Abundant
4 Abundant
5 Very Abundant
Risk Classes according to IUCN (2007)
Red Data Book of Turkey has been classified the endemic and rare species
according to Red List Categories published by IUCN in 2007. Explanation of these caterories
are given below:
EW : “Extinct in the wild” A taxon is Extinct in the wild when it is known only to survive in
cultivation, in captivity or as a naturalised population (or populations) well outside the
past range.
CR : “Critically Endangered” A taxon is Critically Endangered when it is facing an
extremely high risk of extinction in the wild in the immediate future.
EN : “Endangered” A taxon is Endangered when it is not Critically Endangered but is
facing a very high risk of extinction in the wild in the near future.
VU : “Vulnerable” A taxon is vulnerable when it is critically endangered in middle term.
LR : “Lower risk” A taxon is Lower Risk when it has been evaluated, does not satisfy the
criteria for any of the categories Critically Endangered, Endangered or Vulnerable.
Taxa included in the Lower Risk category can be separated into three subcategories:
(cd) :”Conservation Dependent” Taxa which are the focus of a continuing taxon- or
habitat-specific conservation program targeted towards the taxon in question,
the cessation of which would result in the taxon qualifying for one of the
threatened categories above within a period of five years.
(nt) :“Near Threatened” Taxa which do not qualify for Conservation Dependent, but
which are close to qualifying for Vulnerable.
(lc) :“Least Concern” A taxon is Least Concern when it has been evaluated against
the criteria and does not qualify for Critically Endangered, Endangered,
Vulnerable or Near Threatened.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-E
4 / 13
THE BERNE CONVENTION
[Convention on the Conservation of European Wildlife and Natural Habitats]
Appendix1 : Conserved flora specie
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-E
5 / 13
Table E.1. Regional Flora Inventory
LATIN NAME ENDEMISM PHYTOGEOGRAPHICAL
REGION IUCN 2007 BERN
RELATIVE
ABUNDANCE
Aceraceae
Acer sempervirens - E. Mediterranean - - 2
Amaryllidaceae
Galanthus gracilis - E. Mediterranean - - 3
Narcissus tazetta
subsp. aureus - - - - 2
Sternbergia candida + E. Mediterranean - - 2
Sternbergia clusiana - Irano-Turanian - - 2
Sternbergia
fischeriana - - - - 3
Sternbergia sicula - E. Mediterranean - - 3
Anacardiaceae
Cotinus coggyria - - - - 2
Apiaceae
Ainsworthia
trachycarpa - E. Mediterranean - - 3
Ammi visnaga - Mediterranean - - 3
Bupleurum gracile - E. Mediterranean - - 3
Eryngium glomeratum - - - - 2
Ferulago humilis + E. Mediterranean - - 1
Ferulago mughlae + E. Mediterranean - - 2
Lagoecia cuminoides - Mediterranean - - 2
Microsciadium
minutum - E. Mediterranean - - 3
Scandix australis
subsp. grandiflora - - - - 2
Scandix pecten-
veneris - - - - 3
Torilis arvensis subsp.
arvensis - - - - 3
Araceae
Arisarum vulgare
subsp. vulgare - Mediterranean - - 2
Arum byzantinum - Black Sea - - 2
Arum maculatum - - - - 3
Biarum bovei - Irano-Turanian - - 2
Aristolochiaceae
Aristolochia hirta - E. Mediterranean - - 2
Aristolochia parvifolia - E. Mediterranean - - 2
Asclepiadaceae
Vincetoxicum
canescens subsp.
canescens
- - - - 3
Ceterah officinarum - - - - 2
Asteraceae
Anthemis cretica
subsp. pontica - - - - 2
Anthemis rosea
subsp. carnea + E. Mediterranean - - 3
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-E
6 / 13
LATIN NAME ENDEMISM PHYTOGEOGRAPHICAL
REGION IUCN 2007 BERN
RELATIVE
ABUNDANCE
Carduus acicularis - Mediterranean - - 3
Carduus argentatus - E. Mediterranean - - 2
Carlina corymbosa - Mediterranean - - 3
Centaurea cyanus - - - - 3
Centaurea urvillei
subsp. urvillei - E. Mediterranean - - 2
Chrysanthemum
segetum - Mediterranean - - 2
Crepis micrantha - - - - 3
Crepis sancta - - - - 3
Geropogon hybridus + Mediterranean - - 2
Hedypnois cretica - Mediterranean - - 2
Inula anatolica + - - - 3
Inula heterolepis - E. Mediterranean - - 1
Jurinea consanguinea - - - - 2
Ptilostemon
chamaepeuce - E. Mediterranean - - 1
Pulicaria arabica - - - - 2
Rhagadiolus stellatus
var. stellatus - Mediterranean - - 2
Scorzonera eriophora + - - - 1
Taraxacum serotinum - - - - 2
Tragopogon
longirostis var.
longirostis
- - - - 2
Urospermum
picroides - Mediterranean - - 3
Athyriaceae
Cystopteris fragilis - - - - 2
Boraginaceae
Alkanna areolata var.
areolata - E. Mediterranean - - 2
Alkanna tinctoria
subsp. tinctoria - Mediterranean - - 2
Alkanna tubulosa - E. Mediterranean - - 1
Anchusa azurea var.
azurea - - - - 2
Buglossoides
incrassata - - - - 2
Echium plantagineum - Mediterranean - - 3
Lithodora hispidula
subsp. hispidula - E. Mediterranean - - 2
Myosotis cadmaea - E. Mediterranean - - 2
Myosotis ramosissima
subsp. ramosissima - - - - 3
Onosma frutescens - E. Mediterranean - - 2
Onosma nanum + E. Mediterranean - - 2
Onosma roussaei - Irano-Turanian - - 3
Brassicaceae
Alyssum corsicum - - - - 3
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-E
7 / 13
LATIN NAME ENDEMISM PHYTOGEOGRAPHICAL
REGION IUCN 2007 BERN
RELATIVE
ABUNDANCE
Alyssum fulvescens
var. fulvescens - E. Mediterranean - - 2
Alyssum giosnanum + - - - 3
Alyssum smyrnaeum - E. Mediterranean - - 3
Alyssum strigosum
subsp. strigosum - - - - 2
Cardamine hirsuta - - - - 3
Erophila verna subsp.
praecox - - - - 2
Hirschfeldia incana - - - - 3
Iberis attica - E. Mediterranean - - 2
Isatis lusitanica - - - - 3
Malcolmia chia - E. Mediterranean - - 3
Ricotia carnosula + E. Mediterranean - - 2
Thlaspi perfoliatum - - - - 3
Campanulaceae
Asyneuma
limonifolium subsp.
limonifolium
- - - - 2
Asyneuma linifolium
subsp. linifolium + E. Mediterranean (mt) - - 3
Campanula delicatula - E. Mediterranean - - 3
Campanula drabifolia - E. Mediterranean - - 3
Campanula erinus - Mediterranean - - 2
Legousia pentagonia - E. Mediterranean - - 2
Legousia speculum-
veneris - Mediterranean - - 3
Capparaceae
Cleome iberica - E. Mediterranean - - 2
Caryophyllaceae
Arenaria deflexa
subsp. deflexa - E. Mediterranean - - 2
Minuartia hybrida
subsp. hybrida - Mediterranean - - 3
Polycarpon
tetraphyilum - - - - 3
Silene behen - - - - 2
Silene delicatula
subsp. delicatula + E. Mediterranean - - 2
Silene
echinospermoides + E. Mediterranean - - 2
Silene rigidula - E. Mediterranean - - 3
Silene vulgaris var.
vulgaris - - - - 2
Stellaria media subsp.
postii - - - - 2
Vaccaria pyramidata
var. pyramidata - - - - 3
Velezia rigida - - - - 2
Cistaceae
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-E
8 / 13
LATIN NAME ENDEMISM PHYTOGEOGRAPHICAL
REGION IUCN 2007 BERN
RELATIVE
ABUNDANCE
Fumana arabica var.
arabica - - - - 3
Convolvulaceae
Convolvulus
betonicifolius subsp.
betonicifolius
- - - - 2
Convolvulus
compactus - - - - 3
Crassulaceae
Sedum caricum - E. Mediterranean - - 2
Sedum hispanicum
var. hispanicum - Irano-Turanian - - 2
Cupressaceae
Juniperus excelsa - - - - 2
Dipsacaceae
Knautia integrifolia
var. integrifolia - Mediterranean - - 3
Ericaceae
Erica arborea - - - - 2
Erica manipuliflora - E. Mediterranean - - 3
Euphorbiaceae
Euphorbia apios - E. Mediterranean - - 2
Euphorbia
austroanatolica + E. Mediterranean - - 3
Euphorbia characias
subsp. wulfenii - E. Mediterranean - - 3
Euphorbia falcata
subsp. falcata var.
falcata
- - - - 3
Euphorbia
herniariifolia var.
herniariifolia
- - - - 2
Euphorbia kotschyana - E. Mediterranean (mt) - - 3
Euphorbia peplus var.
peplus - - - - 2
Euphorbia rigida - - - - 3
Euphorbia stricta - Eur.-Sib. - - 3
Euphorbia taurinensis - - - - 2
Euphorbia
valerianifolia - E. Mediterranean - - 1
Fabaceae
Astragalus asterias - Irano-Turanian - - 3
Astragalus parnassi
subsp. parnassi - E. Mediterranean - - 2
Dorycnium hirsutum - Mediterranean - - 3
Genista anatolica - E. Mediterranean - - 4
Lathyrus cicera - - - - 2
Lathyrus setifolius - Mediterranean - - 3
Medicago constricta - E. Mediterranean - - 3
Medicago coronata - Mediterranean - - 3
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-E
9 / 13
LATIN NAME ENDEMISM PHYTOGEOGRAPHICAL
REGION IUCN 2007 BERN
RELATIVE
ABUNDANCE
Medicago lupulina - - - - 2
Medicago polymorpha
var. polymorpha - - - - 2
Medicago rigidula var.
rigidula - - - - 3
Melilotus neapolitana - - - - 3
Onobrychis
aequidentata - Mediterranean - - 2
Ononis pusilla - Mediterranean - - 2
Ononis spinosa
subsp. antiquorum - Mediterranean - - 3
Psoralea bituminosa - Mediterranean - - 3
Scorpiurus muricatus
var. subvillosus - Mediterranean - - 2
Trifolium campestre - - - - 2
Trifolium dasyurum - E. Mediterranean - - 3
Trifolium
glanduliferum var.
granduliferum
- E. Mediterranean - - 3
Trifolium globosum - - - - 2
Trifolium hirtum - Mediterranean - - 3
Trifolium lucanicum - Mediterranean - - 2
Trifolium physodes
var. physodes - Mediterranean - - 3
Trifolium scabrum - - - - 1
Trifolium speciosum - - - - 1
Trifolium stellatum
var. stellatum - - - - 2
Trifolium tomentosum - - - - 3
Trigonella carica + E. Mediterranean - - 2
Trigonella cariensis - E. Mediterranean - - 2
Trigonella
monspeliaca - Mediterranean - - 3
Vicia cuspidata - E. Mediterranean - - 2
Vicia ervilia - - - - 3
Vicia galilaea - - - - 2
Vicia hybrida - - - - 3
Vicia lathyroides - - - - 2
Fagaceae
Quercus cerris var.
cerris - Mediterranean - - 3
Quercus infectoria
subsp. infectoria - Eur.-Sib. - - 3
Quercus ithaburensis
subsp. macrolepis - E. Mediterranean - - 3
Quercus pubescens - - - - 3
Gentianaceae
Centaurium erythraea
subsp. erythraea - Eur.-Sib. - - 2
Erodium gruinum - E. Mediterranean - - 2
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-E
10 / 13
LATIN NAME ENDEMISM PHYTOGEOGRAPHICAL
REGION IUCN 2007 BERN
RELATIVE
ABUNDANCE
Geranium lucidum - - - - 2
Geranium purpureum - - - - 3
Illecebraceae
Herniaria hirsuta - - - - 2
Iridaceae
Crocus biflorus subsp.
biflorus - E. Mediterranean - - 3
Crocus cancellatus
subsp. cancellatus + E. Mediterranean - - 2
Crocus chrysanthus - - - - 2
Gladiolus anatolicus + E. Mediterranean - - 2
Gynandriris
sisyrinchium - - - - 3
Iris purpureobractea + E. Mediterranean - - 3
Iris suaveolens - E. Mediterranean - - 2
Iris unguicularis - Mediterranean - - 3
Juncaceae
Luzula forsteri - Eur.-Sib. - - 3
Lamiaceae
Ajuga bombycina + E. Mediterranean - - 2
Ajuga orientalis - - - - 3
Ballota acetabulosa - E. Mediterranean - - 2
Lamium cariense - E. Mediterranean - - 2
Lavandula stoechas
subsp. stoechas - Mediterranean - - 3
Melissa officinalis
subsp. officinalis - - - - 3
Phlomis grandiflora
var. grandiflora - E. Mediterranean - - 2
Phlomis lycia - E. Mediterranean - - 2
Phlomis pungens var.
pungens - - - - 3
Salvia cadmica + - - - 2
Salvia sclarea - - - - 3
Salvia viridis - Mediterranean - - 2
Scutellaria rubicunda
subsp. brevibracteata + E. Mediterranean - - 2
Sideritis curvidens - Mediterranean - - 3
Sideritis lanata - Mediterranean - - 2
Sideritis leptoclada + E. Mediterranean - - 3
Sideritis pisidica + E. Mediterranean - - 2
Stachys cretica
subsp. cassia - E. Mediterranean - - 3
Teucrium polium - - - - 3
Teucrium scordium
subsp. scordium - Eur.-Sib. - - 3
Thymus cilicicus - E. Mediterranean - - 2
Thymus longicaulis
subsp. longicaulis var.
longicaulis
- - - - 2
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-E
11 / 13
LATIN NAME ENDEMISM PHYTOGEOGRAPHICAL
REGION IUCN 2007 BERN
RELATIVE
ABUNDANCE
Liliaceae
Allium amethystinum - Mediterranean - - 2
Allium ampeloprasum - Mediterranean - - 3
Allium paniculatum
subsp. paniculatum - Mediterranean - - 3
Allium paniculatum
subsp. paniculatum - Mediterranean - - 2
Allium stamineum - E. Mediterranean - - 3
Asphodelus fistulous - Mediterranean - - 2
Colchicum balansae + E. Mediterranean - - 3
Colchicum burttii + E. Mediterranean - - 2
Colchicum variegatum - E. Mediterranean - - 2
Fritillaria acmopetala
subsp. acmopetala - E. Mediterranean - - 2
Fritillaria carica
subsp. carica + E. Mediterranean - - 3
Fritillaria elwesii + E. Mediterranean - - 2
Fritillaria forbesii + E. Mediterranean - - 3
Fritillaria sibthorpiana + E. Mediterranean - - 2
Ornithogalum
alpigenum + E. Mediterranean - - 2
Ornithogalum
montanum - E. Mediterranean - - 2
Ornithogalum nutans - - - - 3
Ornithogalum
orthophyllum - - - - 3
Tulipa orphanidea - E. Mediterranean - - 4
Tulipa saxatilis - E. Mediterranean - - 3
Oleaceae
Phillyrea latifolia - Mediterranean - - 3
Onagraceae
Epilobium lanceolatun - - - - 2
Orchidaceae
Anacamptis
pyramidalis - - - - 2
Cephalanthera
longifolia - Eur.-Sib. - - 3
Cephalanthera rubra - - - - 3
Comperia comperiana - Irano-Turanian - - 2
Limodorum abortivum - - - - 3
Neotinea maculata - Mediterranean - - 2
Ophrys apifera - - - - 3
Ophrys argolica
subsp. argolica - E. Mediterranean - - 2
Ophrys holoserica
subsp. holoserica - Mediterranean - - 2
Ophrys mammosa - E. Mediterranean - - 3
Ophrys oestrifera
subsp. oestrifera - - - - 2
Ophrys reinholdii - E. Mediterranean - - 2
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-E
12 / 13
LATIN NAME ENDEMISM PHYTOGEOGRAPHICAL
REGION IUCN 2007 BERN
RELATIVE
ABUNDANCE
subsp. reinholdii
Orchis anatolica - E. Mediterranean - - 2
Orchis morio - - - - 3
Orchis provincialis - Mediterranean - - 3
Platanthera bifolia - Eur.-Sib. - - 2
Serapias vomeracea
subsp. orientalis - E. Mediterranean - - 3
Oxalidaceae
Oxalis corniculata - - - - 1
Papaveraceae
Papaver argemone
subsp. argemone - - - - 2
Pinaceae
Pinus brutia - E. Mediterranean - - 3
Plantaginaceae
Plantago bellardii - E. Mediterranean - - 2
Plantago lagopus - Mediterranean - - 3
Platanaceae
Platanus orientalis - - - - 3
Poaceae
Aegilops biuncialis - - - - 2
Aegilops umbellulata
subsp. umbellulata - Irano-Turanian - - 2
Bromus scoparius - - - - 3
Bromus tectorum - - - - 3
Cynosurus echinatus - Mediterranean - - 2
Dactylis glomerata
subsp. glomerata - Eur.-Sib. - - 3
Poa annua - - - - 2
Rostraria cristata var.
cristata - - - - 3
Polygalaceae
Polygala supina - - - - 2
Primulaceae
Anagallis arvensis
var. arvensis - - - - 2
Cyclamen coum var.
coum - - - - 3
Cyclamen
hederifolium - Mediterranean - - 2
Lysimachia
atropurpurea - E. Mediterranean - - 2
Ranunculaceae
Adonis flammea - - - - 3
Anemone blanda - - - - 2
Anemone coronaria - Mediterranean - - 2
Clematis vitalba - - - - 3
Consolida orientalis - - - - 2
Nigella arvensis var.
glauca - - - - 3
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-E
13 / 13
LATIN NAME ENDEMISM PHYTOGEOGRAPHICAL
REGION IUCN 2007 BERN
RELATIVE
ABUNDANCE
Ranunculus ficaria
subsp. ficariiformis - - - - 2
Rosaceae
Crataegus aronia var.
aronia - - - - 3
Crataegus monogyna - - - - 2
Rubiaceae
Asperula brevifolia - E. Mediterranean - - 3
Galium canum subsp.
ovatum - E. Mediterranean - - 2
Galium floribundum
subsp. floribundum - - - - 2
Galium murale - Mediterranean - - 2
Rubia tenuifolia
subsp. tenuifolia - E. Mediterranean - - 3
Sherardia arvensis - Mediterranean - - 3
Valantia hispida - - 3
Scrophulariaceae
Digitalis cariensis - E. Mediterranean - - 3
Digitalis ferruginea
subsp. ferruginea - Eur.-Sib. - - 4
Verbascum cariense + E. Mediterranean - - 4
Verbascum
chrysochaete + E. Mediterranean - - 4
Verbascum lydium
var. lydium + E. Mediterranean - - 3
Sinopteridaceae
Cheilanthes fragrans - - - - 3
Solanaceae
Hyoscyamus niger - - - - 2
Styracaceae
Styrax officinalis - - - - 3
Thymelaeaceae
Daphne gnidioides - E. Mediterranean - - 3
Daphne sericea - E. Mediterranean - - 2
Urticaceae
Parietaria lusitanica - Mediterranean - - 3
Valerianaceae
Centranthus
calcitrapa - Mediterranean - - 3
Valeriana dioscoridis - E. Mediterranean - - 3
Valerianella costata - Mediterranean - - 4
Valerianella orientalis - E. Mediterranean - - 3
Valerianella vesicaria - - - - 2
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-F
1 / 6
Appendix-F FAUNA INVENTORY
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-F
2 / 6
FAUNA INVENTORY
The fauna inventory was compiled through site serveys and literature researches
besides the observations of the local people. An evaluation was made in terms of specie’s
biological (reproduction, nutrition and adaptation) and ecological characteristics (especially
habitat suitability). IUCN Risk Classes for faunal specie are given as follows.
EXTINCT (EX)
EXTINCT IN THE WILD (EW)
CRITICALLY ENDANGERED (CR)
ENDANGERED (EN)
VULNERABLE (VU)
NEAR THREATENED (NT)
LEAST CONCERN (LC)
DATA DEFICIENT (DD)
NOT EVALUATED (NE)
According to the “BERN Convention” (Convention on the Conservation of European
Wildlife and Natural Habitats);
Appendix II: has the list of species, protection of which are obligatory. Each
contracting party shall take the required legal and administrative measures. The following
actions will especially be forbidden regarding the species listed.
a. all forms of deliberate capture and keeping and deliberate killing;
b. the deliberate damage to or destruction of breeding or resting sites;
c. the deliberate disturbance of wild fauna, particularly during the period of breeding,
rearing and hibernation, insofar as disturbance would be significant in relation to the
objectives of this Convention;
d. the deliberate destruction or taking of eggs from the wild or keeping these eggs even
if empty;
e. the possession of and internal trade in these animals, alive or dead, including stuffed
animals and any readily recognizable part or derivative thereof, where this would
contribute to the effectiveness of the provisions of this article.
Appendix III: contains the list of the faunal species under protection. Each
contracting party is responsible with taking the required legal and administrative measures to
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-F
3 / 6
ensure the protection the faunal species mentioned in Appendix III. Abuse of the wild faunal
species in Appendix II will be arranged in order to keep populations away from danger
considering the conditions asserted in the Article 2. Measures regarding this will include the
following:
a) Closed seasons and / or other procedures related to abuse;
b) Temporary or local prohibition of abuse in a reasonable scale in order to protect
the population;
c) arrangement on the issues of selling alive or dead animals, keeping them to sell
later, transporting them to sell or giving proposal to sell them.
According to the decision of the Central Hunting Commission in Hunting Term, which
became effective upon publication in Official Gazette no. 26574 on 6 July 2007 by the
Ministry of Environment and Forestry;
Species listed in Appendix-I are protected by the Ministry of Environment and
Urbanization.
Species listed in Appendix-II are protected by the Central Hunting Commission.
Appendix-III includes the game animals whose hunting is allowed for certain terms
determined by the Central Hunting Commission.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-F
4 / 6
Table F.1. Reptilia
LATIN NAME BERN IUCN 2007 CHC 2007-2008* SOURCE**
TESTUDINIDAE
Testudo graeca App.-II VU App.-I L
GAPP.KONIDAE
Hemidactylus turcicus App.-III - App.-I L
Asaccus elisae App.-III - App.-I L
AGAMIDAE
Agama (Laudakia) stellio App.-II - App.-I O
SCINCIDAE
Ablepharus kitaibeili App.-II - App.-I L
Chalcides ocellatus App.-II - App.-I L
Mabuya aurata App.-III - App.-I L
LACERTIDAE
Lacerta danfordi App.-III - App.-I L
Lacerta trilineata App.-II LC App.-I L
Ophisops elegans App.-II - App.-I O
ANGUINIDAE
Ophisaurus apodus App.-II - App.-I L
AMPHISBAENIDAE
Blanus strauchi App.-III - App.-I O
TYPHLOPIDAE
Typhlops vermicularis App.-III - App.-I O
BOIDAE
Eryx jaculus App.-III - App.-I L
COLUBRIDAE
Coluber jugularis App.-II - App.-I Q
Coluber najadum App.-II - App.-I Q
Coluber nummifer App.-III - App.-I L
Coluber rubriceps App.-III - App.-I Q
Eirenis modestus App.-III - App.-I L
Elaphe quatuorlineata App.-II - App.-I L
Elaphe situla App.-II LC App.-I L
Malpolon monspessulanus App.-III - App.-I L
Telescopus fallax App.-II - App.-I L
VIPERIDAE
Vipera ammodytes App.-II - App.-I L
Vipera xanthina App.-II LC App.-I L
* CHC: Decision of the Central Hunting Commission
**SOURCE
Q Questionnairre
O Observation
L Literature
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-F
5 / 6
Table F.2. Aves
LATIN NAME IUCN 2007 BERN CHC 2007-2008* SOURCE**
STRIGIDAE
Aegolius fuenerus LC App...-II App.-I L
Asio otus LC App...-II App.-I L
Bubo bubo LC App...-II App.-I L
ALCEDINIDAE
Alcedo atthis LC App...-II App.-I L
PHASIANIDAE
Alectoris graeca LC App.-III L
Perdix perdix LC App.-II L
Coturnix coturnix LC App.-III O
MOTACILLIDAE
Anthus pratensis LC App...-II App.-I L
Anthus trivialis LC App...-II App.-I L
CAPRIMULGIDAE
Caprimulgus europaeus LC App...-II App.-I L
FRINGILLIDAE
Carduelis carduelis LC App...-II App.-I L
CICONIIDAE
Ciconia ciconia LC App...-II App.-I O
COLUMBIDAE
Columba livia LC App...-III App.-III O
Columba oenas LC App...-III App.-II O
Columba palumbus LC App...-III App.-III O
Streptopelia decaocto LC App...-III App.-II O
Streptopelia turtur LC App...-III App.-III O
CORVIDAE
Corvus corax LC App...-III App.-II O
Corvus corona LC App...-III App.-III O
Pica pica LC App...-III App.-III O
CUCULİDAE
Cuculus canorus LC App...-III App.-I L
PICIDAE
Dendrocopos major LC App...-II App.-I Q
Dendrocops syriacus LC App...-II App.-I Q
Dyrocopus martius LC App...-II App.-I Q
Picus canus LC App...-II App.-I Q
Picus viridis LC App...-II App.-I Q
FALCONIDAE
Falco peregrinus LC App...-II App.-I O
Falco tinnunculus LC App...-II App.-I O
RALLIDAE
Fulica atra LC App...-II App.-I L
Gallinula chloropus LC App...-III App.-I O
HIRUNDINIDAE
Hirundo rustica LC App...-II App.-I L
MEROPIDAE
Merops apiaster LC App...-II App.-I L
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-F
6 / 6
LATIN NAME IUCN 2007 BERN CHC 2007-2008* SOURCE**
ORIOLIDAE
Oriolus oriolus LC App...-II App.-I L
TIMALIIDAE
Panurus biarmicus LC App...-II App.-I L
PARIDAE
Parus ater LC App...-II App.-I L
PASSERIDAE
Passer domesticus LC App...-III App.-III O
Passer hispaniolensis LC App...-III App.-II O
PHALACROCORACIDAE
Phalacrocorax aricstotelis LC App...-II App.-I O
Phalacrocorax carbo LC App...-III App.-I L
SYLVIDAE
Prinia gracilis LC App...-II App.-I O
TURDIDAE
Saxicola torquata LC App...-II App.-I L
Turdus pilaris LC App...-II App.-I L
STURNIDAE
Sturnus vulgaris LC App...-III App.-III O
TYTONIDAE
Tyto alba LC App...-II App.-I L
UPUPIDAE
Upupa epops LC App...-II App.-I L
CHARADRIIDAE
Vanellus vanellus LC App...-II App.-I L
* CHC: Decision of the Central Hunting Commission
**SOURCE
Q Questionnairre
O Observation
L Literature
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-G
1 / 13
Appendix-G PUBLIC CONSULTATION MEETINGS
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-G
2 / 13
PUBLIC CONSULTATION MEETING
Local people, local NGO’s and MUNICIPALITY have been attended a “Public
Consultation Meeting” for the PROJECT that had been developed by the MUNICIPALITY.
The aim of this meeting is informing the above mentioned interest groups about the
PROJECT, explaining the possible environmental impacts that the PROJECT may result in,
and the proposed precautions, and take opinions and suggestions of the participators.
Date, time, place and subject of the meeting have been announced on a local
newspaper. The announcement is presented in Figure G.1.
Hamle Gazetesi (Hamle Newspaper) (September 3, 2007)
Figure G.1. Advertisement on newspaper to announce the Public Consultation Meeting
As to be seen from the announcement, the meeting took place in Nail Cakirhan
Meeting Hall at Konakalti Iskender Alper Cultural Center at 2 pm on September 10, 2007. A
final list related to the interest groups has been determined by the MUNICIPALITY before
the meeting, and invitations have been sent to these groups. The list of participators is
presented in Figure G.2 and some photos from the meeting are in Figure G.3.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-G
3 / 13
Figure G.2. Public Consultation Meeting Participation Records
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-G
4 / 13
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-G
5 / 13
Figure G.2. Public Consultation Meeting Participation Records (Cont’d)
Figure G.3. Photos from the Meeting.
In the meeting, the PROJECT has been introduced and it was noted that the target
was to serve people in the city center better through establishment of the sewerage network,
rehabilitation of the present water supply network as well as the wastewater treatment plant.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-G
6 / 13
Besides, the interest groups, who had attended the meeting, have been informed. At the
end of meeting, opinions of the participators about the PROJECT have been taken. It is
possible to say that the meeting had a positive ambience and the participators supported the
establishment of the PROJECT. Moreover, often repetition of the consultation meetings with
increased number of participators was demanded from the MUNICIPALITY by the interest
groups.
Second public consultation meeting of the construction phase was held in Nail
Cakirhan Meeting Hall at Konakalti Iskender Alper Cultural Center at 2 pm on June 17,
2008. The list of related interest groups was determined before for the first meting. This list
was reviewed by the MUNICIPALITY in order to sent the invitations. Moreover, date, time,
place and subject of the meeting have been announced on a local newspaper (see Figure
G.4).
Devrim Gazetesi (Devrim Newspaper) (June 13, 2008)
Figure G.4. Advertisement on newspaper to announce the Public Consultation Meeting
The list of participators of the second public participation meeting is presented in
Figure G.5. Minutes of both meetings are not recorded but instead video records are
available at the MUNICIPALITY. Therefore, only the participation list of people with their
signatures are provided in this Appendix.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-G
7 / 13
Figure G.5. Public Consultation Meeting Participation Records
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-G
8 / 13
Figure G.5. Public Consultation Meeting Participation Records (Cont’d)
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-G
9 / 13
At the beginning of the meeting, representative of Temelsu was informed the
participants anbout the PROJECT. Then, environmenatal impacts and assessment studies
related with the PROJECT was presented by the representative of DOKAY.
After informing the participants about the PROJECT, their questions was received.
The first question was about the cost of the PROJECT, which was answered by the
representative of DOKAY as 10 million Euro. The second question was the way of handling
the excess sludge discharged from anaerobic digestor. It is explained that the sludge will be
analzed and if it does not contain any hazardous materials, it will be used for agricultural
purposes but this subject will be considered at the operation phase of the PROJECT in
details. As the last question, the disposal methods and the uses of treated wastewater was
asked. Like the use of excess sludge, this subject will be considered during the operation
phase however, as it is written in the EIA Report, it is planned that wastewater will be reused
at the basin after necessary arrangements and permits.
In general, the first and second meetings reveal that the public support the
development and realization of the PROJECT.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-G
10 / 13
PUBLIC DISCLOSURE MEETING
Local people and MUNICIPALITY have been attended the “Public Disclosure
Meeting” for the PROJECT that had been developed by the MUNICIPALITY. The aim of this
meeting is to inform the above mentioned interest groups about the environmental and
social impacts of the PROJECT.
Date, time, place and subject of the meeting have been announced on a local
newspaper. The announcement is presented in Figure G.6.
Figure G.6. Advertisement on Newspaper to Announce the Public Disclosure Meeting
The list of participators of the public disclosure meeting is presented in Figure G.7.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-G
11 / 13
Figure G.7. Public Consultation Meeting Participation Records
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-G
12 / 13
At this meeting the importance of the PROJECT including environmenatal and social
impacts related with the PROJECT was presented by the representative of DOKAY.
The views from the meeting are given in Figure G.8, Figure G.9 and F.10 below.
Figure G.8. A View From Public Disclosure Meeting-I
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-G
13 / 13
Figure G.9. A View From Public Disclosure Meeting-II
Figure G.10. A View From Public Disclosure Meeting-III
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
1 / 73
Appendix-H TECHNICAL, ECONOMIC AND ENVIRONMENTAL STUDIES ON
DISCHARGE OF TREATED WASTEWATER OF MUGLA WWTP
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
2 / 73
1. DISCHARGE ALTERNATIVES AND PROPOSED OPTION
Different alternatives for discharging treated wastewater of Muğla WWTP were
evaluated for this project since 2005. In 2005, in Feasibility Study different alternatives
which were suggesting pumping the effluent outside of the catchment area were
evaluated. However, the results showed that due to the high operational costs these
alternatives will not be feasible regarding Muğla Municipality’s choice. After the feasibility
study, in 2008 during the preparation of the PIF (project introduction file), General
Directorate of State Hydraulic Works (DSİ) permitted for infiltration, evaporation, and
storage of treated wastewater in proposed abandoned sand and gravel quarry on the
Yaraş Road. Project Introduction File (PIF) was prepared in line with that discharge
option and approved by Provincial Directorate of Environment and Forestry (PDoEF).
In 2011, another study was carried out and new alternatives were evaluated upon
the request of World Bank to confirm if the selected discharge option, which is
discharging to the quarry is technically, environmentally, and economically feasible as a
long term solution. These alternatives and their brief explanations are below. Also all the
alternatives can be seen in Annex 1 (Figure 1.1-1.10 and Table 1.1).
Alternative 1: Pumping of treated wastewater from WWTP to downstream
location of Ula Irrigation Reservoir at Ula Creek in the neighboring catchment area,
which connects to Gökova Bay.
Ula Creek is closest creek to Muğla city within neighbouring catchments. But, in
order to reach this creek passing a hill is needed and at the same time in order to avoid
some nuisances treated wastewater shall be discharged at the downstream location of
Ula Irrigation Reservoir, which is under operation. This alternative has two sub-
alternatives:
Alternative 1a: A route following Muğla-Ula-Akyaka Road.
In this alternative, first there is 7.85 km pumping line (Ø 700 mm steel pipe) from
WWTP up to hills at Muğla-Ula-Akyaka Road. Elevation difference is 160 m (780-620 m).
Then wastewater will flow 5.35 km (Ø 700 mm steel pipe) with gravity up to downstream
of Ula Irrigation Reservoir.
Alternative 1b: A route following Muğla Plain and hills at southern part of
Yeniköy settlement area.
In this alternative, first there is 6.0 km pumping line (Ø 700 mm steel pipe) from
WWTP up to hills in southern part of Yeniköy settlement. Elevation difference is 230 m
(850-620m). Then wastewater will flow 6.2 km (Ø 700 mm steel pipe) with gravity up to
downstream of Ula Irrigation Reservoir.
Alternative 2: Pumping of treated wastewater from WWTP to Kızılağaç
Branch of Ula Creek.
This alternative has the same route with Alternative 1b up to downstream location
of Ula Irrigation Reservoir. From here, additional gravity pipeline (5.3 km Ø 700 mm steel
pipe) shall be laid up to discharge point at Kızılağaç creek. Kızılağaç Creek connects to
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
3 / 73
Ula Creek at downstream location of Ula town (Figure 1.2). This alternative was thought
in order to eliminate possible negative effects of treated wastewater in Ula town.
Alternative 3: Lining of discharge site and pumping of treated wastewater to
the forestry areas.
This alternative was created as a modification of proposed solution in Project
Introduction File. Abandoned quarry is planned to be lined with impermeable layer and to
be used as a storage area in order to prevent Karabağlar aquifer from possible negative
effects of treated wastewater disposal.
As lining material, PVC based membrane with 2 mm thickness shall be used.
Geotextile shall be laid at bottom to protect the membrane. After arrangements, total
utilizable area of the site is 61,000 m2 and total utilizable volume is 555,000 m3. Final
layout and cross-sections of the site can be seen in Figure 1.3,1. 4 and 1.5 in Annex 1.
A new pumping station shall be constructed near the discharge site and stored
wastewater shall be pumped to the forestry area for irrigation and infiltration purposes. By
calculating required area; worst case scenario permeability (2.34x10-6 m/s), founded by
drilling studies, was used. Runoff coefficient was selected as 0.20. In this case required
area is 95,000 m2. For collecting and infiltrating runoff volume total area is selected
120,000 m2. Pumping line and proposed forestry areas can be seen in Figure 2. Main
pumping line shall consist of 3,200 m Ø 600 mm steel pipe and 600 m Ø 400 mm steel
pipe. Secondary pipes are Ø 180 mm HDPE pipe and total length is 1,400 m. Distribution
pipes shall be Ø 65 mm drain flex perforated pipe and total length is approximately 9,000
m. Especially length of main pipes can change according to exact place of forestry areas.
In Figure, below, schematic drawing of irrigation system in forestry area can be seen. At
the same time, forestry area needs to be arranged for proper distribution and infiltration of
treated wastewater.
Figure: Schematic Drawing of Irrigation System in Forestry Area
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
4 / 73
Alternative 4: Percolation of treated wastewater to underground at
discharge site and pumping the rest amount to the forestry areas.
The difference of this alternative from Alternative 3 is that abandoned quarry will
not be lined with impermeable layer and to be used as a filtration area after arrangements
(Approved alternative in PIF Stage). Leakage capacity of the area was found by drilling
studies (realized by Arbiogaz Company in 2009 and by supplementary studies (realized
by Prof. Serdar Bayarı) in 2011. There are different permeability coefficients but under all
circumstances, abandoned quarry has an adequate infiltration capacity and shall be used
by arranging the site. In the calculations, minimum permeability coefficient 2.34x10-5 m/s,
which was calculated from the hydrogeological studies at the site, is used in order to stay
on the safe side. According to minimum permeability coefficient, filtration capacity of the
disposal site is 8,080 m3/day. To be at safe side, permeability coefficient decreased
gradually starting from 2020. It is taken 95% in 2020 while it is taken 75% in 2040.
As seen in Section 3.3, this alternative also needs a disposal system especially
after 2020. Therefore, pumping line to forestry area shall be constructed also in this
alternative. This is the excess amount of the treated wastewater. Pumping of irrigation
water to city recreational areas shall be supplied from WWTP between April-October
months. Despite required pumping capacity of this alternative is smaller than Alternative
3, a pumping station and pumping line was thought same as Alternative 3 in order to
eliminate worst scenario conditions in the future. In case the quarry was full for some
reasons (heavy rain conditions, an unexpected clogging in the quarry area or an
unexpected increase in coming treated wastewater) all wastewater in quarry area shall
be pumped to the forestry area. Hence, pumping to forestry area was designed same as
Alternative 3. In alternative 3, all of the treated water shall be pumped. However, in
Alternative 4 rest of the water after percolation shall be pumped.
In Table 1.1 (Annex 1), properties of the alternatives, initial investment costs,
yearly operational costs, advantages, and disadvantages of the above mentioned
alternatives can be seen.
As a result, Alternative 4 was proposed to be the most feasible solution for Muğla
Municipality from initial investment and yearly operational costs point of views. Yearly
operational costs of the other 3 alternatives are really very high for a small Municipality,
like Muğla. Therefore, in the comparisons, sustainability of the proposed solution from
economical point of views is also considered. It is assumed that disposal site will serve as
a filtration unit and this will help improving water quality to be mixed with Karabağlar
aquifer.
In 2011, PDoEF and DSİ declared that they are in consent with this alternative
and the official confirmation letter of PDoEF can be seen in Annex2.
2. EXPLANATION OF THE PROPOSED SOLUTION
2.1. General
Discharge site exists inside of Karabağlar Plain and it is in 2.0 km distance to
Düğerek town and 5.0 km distance to Muğla city. Infiltrated flow interferes and feeds
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
5 / 73
Karabağlar Plain underground water, which is used for small-scale irrigation purposes but not
for drinking purposes. Ground and underground water of Karabağlar Plain mix with Gökova
aquifer with several sinkholes.
Initially total capacity of the Disposal site was 1,100,000 m3 but since Muğla
Municipality did not expropriate the entire quarry, total area decreased approximately to
370,000 m3. But in order to obtain slope stabilities at the disposal site, as will be described
later, municipality needs to expropriate some more plots.
Treated wastewater, discharged to Disposal Site will be infiltrated, evaporated, and
used for other purposes like irrigation of forestry areas.
2.2. Arrangement in Disposal Site and Slope Stability
In order to effective and long-term use, some arrangements will be made inside of the
disposal site. As present situation, slopes of the side walls in the disposal site are almost
vertical and they are thought as unstable after filling the disposal site with treated
wastewater. Within this scope, slope stability analysis is made and results can be seen in
Annex 3. On the other hand there are some disposed materials, big stones, tyres, trees and
other things inside of the disposal site. These materials will be thrown out of the site by the
Municipality.
At the same time it is advised to do some extra clearing works (like distribution of fine
material evenly, forming of slopes towards to minimum elevations), except big ones
explained above, before using cells. This will decrease the clogging risk and cause long-term
effective use of the site.
After cleaning the bottom, disposal site will be divided into cells and used in turn
(Refer Figures 1.6, 1.8, and 1.9). Before starting discharge, slopes will be stabilized.
Operation of disposal site is divided into two parts, which are:
Short-term operation period – Pilot cells (2012-2013): In this period, two cells with
minimum elevation, which are in the closest location to discharge structure, will be
used. Total volume of these cells is approximately 60,000 m3. Water will be risen up
to 618.00 m in the cells. Water height will be app. 8.0 m in Cell 1 and 5.0 m in Cell 2 if
no infiltration occurs. Infiltration capacity of the treated wastewater will be monitored
during the pilot cells operation and necessary actions will be taken for the final
discharge system, which is explained in Section 5. Treated wastewater will be
diverted to the cell, which is under operation. Plan and cross-sections of the disposal
site, which will be used for short-term can be seen in Annex 1 (Figure 1.6-1.7).
In short-term operation period some precautions should be taken. In some
parts of the cells, especially in close parts to Concrete Plant, rock fill is needed in
critical slope sections. It is advised that in sensitive slope parts rock fill shall be made
and height of the fill shall be increased parallel to water height during short-term
operation period.
Long-term operation period - (2014-2040): In this period, disposal site will be divided
into 2 big cells and all of the disposal site will be used according to experiences
obtained from the short-term operation period. Total volume of the site is
approximately 370,000 m3. Water will be risen up to 627.50 m in the cells. Water
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
6 / 73
height will be app. 14.0 m in Cell 1 and 7.5 m in Cell 2 if no infiltration occurs. Plan
and cross-sections of the disposal site, which will be used for long-term can be seen
in Annex 1 (From Figure 1.8 to 1.14).
Based on the slope stability analysis, the solutions for the long term slope stability
and their potential risks are as follows:
- Alternative 1 Doing nothing except expropriation of risky areas around the
top of the slopes. In this alternative approximately 50 m land from each
side will be expropriated and slopes will be formed naturally by sliding of
the earth from top to bottom. Expropriation distance was determined by
adding 20 m to natural slide distances from each side in order to be at safe
side. Natural slide distances of the critical cross-sections can be seen in
Section 2.2 in Annex 3. As the risky area is fenced, there will be no risk
foreseen at outside of the fences because of slide of the slopes (Figure 1.8
in Annex 1).
- Alternative 2 Making of buttress at the slope toe and excavation of slopes
to an angle of 1H:1V or 3H:2V, where required (Figure 1.9-1.11 in Annex
1).
- Alternative 3 Excavation of slopes of the discharge site to an angle of
3H:2V with one berm (Figure 1.12-1.14 in Annex 1).
For all alternatives rough cost estimations are prepared and presented
below:
Alternative 1: The unit cost of rock fill with the required geometry and
including transportation is 20.71 Euro/m3 and total estimated amount is
90,750 Euro for approximately 4,382 m3 volume, required for short-term
operation period.
According to calculations, extra area to be expropriated is around 51,000
m2. Cost of land per m2 is 0.8 Euro as a rough estimation. Therefore extra
cost for expropriation is approximately 40,800 Euro.
Total amount for Alternative 1 is approximately 142,500 Euro including
fencing and replacement of village road (Figure 1.8).
Alternative 2: The unit cost of rock fill with the required geometry and
including transportation is 20.71 Euro/m3 and total estimated amount is
369,675 Euro for approximately 17,850 m3 volume, required for long-term
operation period.
The cost of excavation including transportation is 2.83 Euro/m3 and total
excavation amount is around 245,000 m3 and costs to 693,840 Euro.
Total amount for Alternative 2 is approximately 1,112,850 Euro including
expropriation, fencing and replacement of village road.
Alternative 3: The unit cost of rock fill with the required geometry and
including transportation is 20.71 Euro/m3 and total estimated amount is
90,750 Euro for approximately 4,382 m3 volume, required for short-term
operation period.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
7 / 73
The cost of excavation including transportation is 2.83 Euro/m3 and total
excavation amount is around 325,000 m3 and costs to 919,750 Euro.
Total amount for Alternative 3 is approximately 1,065,250 Euro including
expropriation, fencing and replacement of village road.
From the alternatives, Alternative 1 was selected by Muğla Municipality
and applied.
2.3. Water Balance Calculations
As explained above, treated wastewater will be discharged to Disposal Site. The plan
is to use the site for balancing the discharged water amount through infiltration, evaporation
and storage for the other purposes processes.
To see and evaluate the balancing capacity of the Disposal Site a water balance table
is prepared. Some assumptions are made during the calculations, which are:
During 2012 and 2013, short-term operation system, explained above, will be applied.
Surface area of Cell 1 and Cell 2 are app. 19,000 m2 and total volume is 90,000 m3.
After 2014, long-term operation system will be started. Surface area of Cell 1 and Cell
2 are app. 40,000 m2 and total volume is 370,000 m3.
Minimum value of the permeability coefficients, obtained from the drilling studies in
2009, is used for safety of the calculations. This minimum permeability coefficient is
2.34x10-6 m/s.
In order to be at safe side, permeability coefficient was decreased 5% starting from
2020. In 2040 water balance calculations, permeability coefficient was taken 25% of
the original.
It is assumed that 50% of the irrigation capacity of the city center green areas will be
developed in 2012, 75% in 2014 and full capacity will be used in 2015.
Water balance calculations, prepared for 2012-2015, 2020, 2025, 2030, 2035, and
2040 can be seen in Table 4.1 in Annex 4.1. According to Table, in Disposal Site and
therefore after 2015 a system should be put into operation for pumping stored
wastewater in disposal site. At the beginning, the capacity of the pumping system may be
small but towards to 2040 the pumping capacity should be increased up to 14,500
m3/day.
2.4. Irrigation of Green, Forestry, and Agricultural Areas
2.4.1. Irrigation of Green Areas
One of the aims of the project is to use treated wastewater for irrigation of green
areas in the city. The irrigation water of green areas will be pumped directly from WWTP and
this treated water will not reach to Disposal Site. Most of the cities in Turkey use this method
in order to minimize domestic or underground water usage for irrigation. Most important thing
for usage of treated wastewater as irrigation water is not to get in touch with people and to be
sure that this water is not drunk. Necessary precautions should be taken for satisfying these
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
8 / 73
criteria for sanitary application, such as disinfection of treated wastewater and putting
warning signs in the parks where treated water is used.
In Figure 4.1 (Annex 4.2), grass areas, flower gardens and areas with trees, which
are under responsibility of Muğla Municipality, are shown. On the other hand in Table 4.2
(Annex 4.2) areas of the irrigatable regions are given.
In below Table 1, total water requirement for irrigation of the Municipality areas are
calculated. Unit water requirements are calculated on the base of literature information. The
water demand for irrigation of green areas is around 4,000 m3/day.
Table 31: Green Areas of Muğla Municipality and Water Requirement
Type of Area
Total Area (m2)
Unit Water Requirement (L/m2-day)
Total Water Requirement (m3/day)
Grass Area 142,241 10 1,422.41
Flower Gardens
9,234 10 92.34
Areas with Trees
127,906 20 2,558.12
TOTAL 279,381 4,072.87
As it is known, within the scope of the WWTP construction contract, an irrigation
pumping line, starting from discharge building of WWTP, was laid down through the request
of Muğla Municipality. Total capacities of the irrigation pumps are 170 m3/h, which is 4,080
m3/day.
Since the capacities of irrigation pumps in WWTP are determined with the request of
Muğla Municipality from the beginning, the total water requirement, calculated in Table 35, is
same with the pump capacities. Municipality’s irrigation period will take 6 months starting at
the beginning of April and finishes at the beginning of October. Muğla Municipality tries to get
license from Provincial Directorate of Environment nowadays for using treated wastewater as
irrigation water.
The pumping line, explained above, is not connected to any reservoir of the
Municipality now. Muğla Municipality will continue this pumping line up to the small
reservoirs, existing inside of the Municipality parks, and use this water for the irrigation of the
green areas inside the parks.
As a first step, Muğla Municipality will use a GEKA (Southern Aegean Development
Agency) grant for irrigation of 41,000 m2 area in the city center. The construction tender will
be done on 21.11.2011. With this grant 410 m3/day treated wastewater will be used as a first
step. The irrigation process will be started after getting the license by the Municipality.
Parallel to GEKA grant, Municipality will construct this year another pipeline for
irrigation of 14,500 m2 green area with its own capital. With this constructions 145 m3/day
treated wastewater will be used as the second step.
Location of the green areas, to be irrigated in the first and second step can be seen in
Figure 4.1 (Annex 4.2).
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
9 / 73
Other irrigation lines is planned to be completed and put into operation between
2012 and 2014.
2.4.2. Irrigation of Forestry Areas
As it is mentioned in previous sections, except infiltration and evaporation
activities, Disposal Site will be used for balancing treated wastewater for the other
disposal methods. As it is also explained in “Water Balance” section, water balance turns
to positive after 2015. This means infiltration and evaporation capacity is not enough
starting this year for eliminating treated wastewater in Disposal Site and it starts to
accumulate. Therefore after 2015 spraying to forestry system, in addition to the irrigation
system for green areas should be put into operation for discharging stored wastewater
from the disposal site.
In this extent, spraying it to forestry areas seems as an applicable solution since:
Muğla has wide forestry areas approximately 3,500 ha close to city center of 3-5
km.
Muğla is located in a dry climate region especially in summer and this maximizes
forest fire risks.
Muğla uses this method since years for the treated wastewater of TOKİ Mass
Buildings. However, there is not any monitoring procedure for impacts
According to water balance calculations the amount of water to be sprayed to forestry
areas by the years are as follows. These amounts are approximate values and will be clear
with the operation of Disposal Site.
- 2020: 200,000 m3/month
- 2025: 250,000 m3/month
- 2030: 310,000 m3/month
- 2035: 365,000 m3/month
- 2040: 425,000 m3/month
A new pumping station will be constructed near the disposal site and excess water
will be pumped to forestry areas. Pumps can be selected in to stages:
2025: 220 m3/h (2+1)
2040: 220 m3/h (3+1)
Proposed location for forestry areas and pumping line can be seen in Figure 1.2 in
Annex1. Muğla Municipality will get official permission from Regional Directorate of Forestry.
As the proposed location is agreed by the parties, required area for spraying, length of the
main and secondary pipes are explained in Section 2. That is why it is not repeated here.
After determination of the exact place for spraying, detailed designs should be prepared and
constructions should be completed latest at the second half of 2014.
2.4.3. Irrigation of Agricultural Areas
As an alternative, excess wastewater can also be used for irrigation of agricultural
areas. The intension and demand of farmers will be clear after the start of the operation.
“Wastewater Treatment Plants Technical Procedures Bulletin”, published on
20.03.2010, is reference regulation in this sector in Turkey. This Bulletin organizes and
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
10 / 73
explains properties of treated wastewater to be used as irrigational purposes and shows
different agricultural treated wastewater usage and properties of treated wastewater for this
application. For using treated wastewater in this sector it should fit with the below criteria
according to Turkish legislations.
a-Agricultural Irrigation: Food products processed as commercially
b-Irrigation areas with limited entrance
c- Agricultural irrigation: Plants not to be used as food
Area of Application
Treatment Type Quality of treated wastewater
Monitoring Period
Application Distance
a) Orchards and vineyards
b)Grass production and reclamation agriculture areas
c) Pasture areas
-Secondary treatment
-Disinfection
-pH=6-9
-BOD5 < 30 mg/L
-TSS < 30 mg/L
-Fecal coliform
< 200/100 mL
-Residual Chlorine > 1 mg/L
-pH: Weekly
-BOD5: Weekly
-TSS: Daily
-Coliform: Daily
-Residual chlorine: continuous
-Minimum 90 m to the wells, used for drinking water.
-Minimum 30 m to the people if sprinkling system is used
This alternative is still considered by the Municipality and used by getting required
permissions. The olive trees near to the site seem a good solution, if agreed by the farmers.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
11 / 73
Annex-1
Altern
ativesProperties of the Alternative Properties of the Route
Reference
Drawings
Initial Investment Cost
(Euro)
Yearly Operational Cost
(Euro)
Advantages and
Opportunities
Disadvantages and
Treaths
Altern
ative
1a
- Discharge to outside of
catchment area
In this alternative treated WW shall
be pumped to Ula Creek at
downstream of Ula Irrigation
Reservoir.
This route follows Muğla-Ula-
Akyaka Road.
- Total length is app. 13.2 km.
The Route consist of 7.85 km
pumping line and 5.35 km gravity
line. Pump head is app. 160 m
(780m - 620m). Ø 700 mm steel
pipe is used.Figure 1.1
Figure 1.23.049.000
For the year 2015:
Maintenance: 31,511
Energy: 234,647
Total: 266,159
For the year 2040:
Maintenance: 31,511
Energy:362,426
Total: 393,937
Future Values of Main. & Energy Costs (2012-2040):
Total: 39,190,966
(calculations are based 8% discount rate)
- Treated WW will be discharged into a
riverbed outside of catchment area, that
flows to Aegean Sea.
- The route follows 9.7 km Muğla-Ula-Akyaka Highway. According to
2007/3 Circular of "General Directorate of Highways" (GDoH) (published
on 01.02.2007), parallel construction along the Highways are nearly
imposibble except some special conditions. That is why getting
permission from General Directorate of Highways seems very difficult.
- Expropriation and right of way values are not included to initial
investment cost as it will be defined by GDoH and it is not possible to
estimate this figure at this stage without an official application.
- Operation costs are very high.
Altern
ative
1b
- Discharge to outside of
catchment area
In this alternative treated WW shall
be pumped to Ula Creek at
downstream of Ula Irrigation
Reservoir.
This routes follows Muğla Plain and
hills at southern part of Yeniköy
Settlement Area.
- Total length is app 12.2 km .
The Route consist of 6.0 km
pumping line and 6.2 km gravity
line. Pump head is app. 210 m
(830m - 620m). Ø 700 mm steel
pipe is used.Figure 1.1
Figure 1.23.120.000
For the year 2015:
Maintenance: 33,104
Energy:321,096
Total: 354,200
For the year 2040:
Maintenance:33,094
Energy: 495,951
Total: 529,045
Future Values of Main. & Energy Costs (2012-2040):
Total:52,504,857
(calculations are based 8% discount rate)
- Treated WW will be discharged into a
riverbed outside of catchment area, that
flows to Aegean Sea.
- App. 3.5 km of the route follows very steepy areas in the southern part
of Yeniköy Settlement Area. Selected route can create a problem from
construction point of view.
- Expropriation and right of way values are not included to initial
investment cost as it will be defined by GDoH and it is not possible to
estimate this figure at this stage without an official application.
- Operation costs are very high.
Altern
ative
2
- Discharge to outside of
catchment area
In this alternative treated WW shall
be pumped to Kızılağaç Creek near
Kızılağaç Village. This branch
connects to Ula Creek at
downstream of Ula town.
This routes follows Muğla-Ula-
Akyaka Road.
- Total length is app. 17.5 km.
The Route consist of 6.0 km
pumping line and 11.5 km gravity
line. Pump head is app. 210 m
(830m - 620m).
Ø 700 mm steel pipe is used.Figure 1.1
Figure 1.24.215.000
For the year 2015:
Maintenance: 43,962
Energy: 321,096
Total: 365,058
For the year 2040:
Maintenance: 43,962
Energy: 495,951
Total: 539,913
Future Values of Main. & Energy Costs (2012-2040):
Total: 53,724,093
(calculations are based 8% discount rate)
- Treated WW will be discharged into a
riverbed outside of catchment area, that
flows to Aegean Sea.
- The route follows 3.6 km Muğla-Ula-Akyaka Highway. According to
2007/3 Circular of "General Directorate of Highways" (published on
01.02.2007), parallel construction along the Highways are nearly
imposibble except some special conditions. That is why getting
permission from General Directorate of Highways seems very difficult.
- Expropriation and right of way values are not included to initial
investment cost as it will be defined by GDoH and it is not possible to
estimate this figure at this stage without an official application.
- Operation costs are very high.
Altern
ative
3
- Discharge to inside of
catchment area
In this alternative treated WW shall
be pumped to abondoned quarry as
agreed. Quarry shall be covered and
used as storage area. Stored WW
shall be pumped to forestry areas
near Muğla-Denizli Highway.
- Total length is app. 3.8 km.
The Route consist of pumping
lines. Pump head is app. 80 m
(700m - 620m). Ø 600 mm (3.2
km) and Ø 400 mm (0.6 km) steel
pipes will be used as main pipes.
As distribution pipes Ø 180 mm
(1.4 km) HDPE pipe and Ø65 mm
drainflex perforated pipe (9.0 km)
will be used.
Figure 1.1
Figure 1.2
Figure 1.3
Figure 1.4
Figure 1.5
2.721.500
For the year 2015:
Maintenance: 16,931
Energy: 123,498
Total: 140,429
For the year 2040:
Maintenance: 16,931
Energy: 190,751
Total: 207,682
Future Values of Main. & Energy Costs (2012-2040):
Total: 25,169,200
(calculations are based 8% discount rate)
- Initial investment cost and yearly
operational costs are acceptable in
compared with alternatives 1 and 2.
- Pipeline up to abondoned quarry is
already constructed.
- Muğla-Denizli Highway shall be crossed
prependiculary at on location. This will not
create problem as parallel costruction.
- Expropriation and right of way values are not included to initial
investment cost as it will be defined by GDoH and it is not possible to
estimate this figure at this stage without an official application.
- Leakage capacity of the forestry areas may be decreased by time.
- Inconvenience can be created within the cose settlement areas.
Altern
ative
4
- Discharge to inside of
catchment area
In this alternative treated WW shall
be pumped to abondoned quarry as
agreed. Quarry shall be arranged
and used as infiltration area.
Excess WW shall be pumped to
forestry areas near Muğla-Denizli
Highway.
- Total length is app. 3.8 km.
The Route consist of pumping
lines. Pump head is app. 80 m
(700m - 620m). Ø 600 mm (3.2
km) and Ø 400 mm (0.6 km) steel
pipes will be used as main pipes.
As distribution pipes Ø 180 mm
(1.4 km) HDPE pipe and Ø65 mm
drainflex perforated pipe (9.0 km)
will be used.
Figure 1.1
Figure 1.2
From Figure 1.6
to
Figure 1.14
Sub-Alt. 1: 1,250,000
Sub Alt. 2: 2,220,300
Sub Alt. 3: 2,171,700
(Sub-Alternatives are
explanied in Chapter 3.2)
For the year 2015:
Maintenance: 12,202
Energy: 68,124
Total: 80,326
For the year 2040:
Maintenance: 12,202
Energy: 135,376
Total: 147,578
Future Values of Main. & Energy Costs (2012-2040):
Total: 18,420,589
(calculations are based 8% discount rate)
- Initial investment cost and yearly
operational costs are acceptable in
compared with all other alternatives.
- Pipeline up to abondoned quarry is
already constructed.
- Muğla-Denizli Highway shall be crossed
prependiculary at on location. This will not
create problem as parallel costruction.
- Expropriation and right of way values are not included to initial
investment cost as it will be defined by GDoH and it is not possible to
estimate this figure at this stage without an official application.
- Leakage capacity of the forestry areas may be decreased by time.
- Inconvenience can be created within the cose settlement areas.
TABLE 1.1: DISCHARGE ALTERNATIVES OF TREATED WASTEWATER OF MUĞLA WWTP
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
12 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
13 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
14 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
15 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
16 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
17 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
18 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
19 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
20 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
21 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
22 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
23 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
24 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
25 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
26 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
27 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
28 / 73
Annex-3
Stability of Discharge Site
1. Introduction
In the project of Waste Water Treatment Plant (WWTP) of Muğla city, the abandoned
gravel quarry will be used as discharge site of the treated water from the sanitary sewerage
system. At the discharge site treated water is supposed to percolate through the bottom of
the quarry. Water level at the discharge site will raise depending to the permeability of the
formation and reusing the stored water. The slopes of the quarry varies and their stability
should be checked for short and long term considering the operation of WWTP; discharge,
storage and reuse of the treated water.
2. Geotechnical Evaluations and Stability Analysis
The discharge site is located within the alluvial cone deposits and has an irregular
shape with longest and shortest length of 245 and 120 m. Maximum height of the slope
reaches to 27 m. According to the borehole S9 drilled in this formation was described as very
dense, slightly silty, sandy, coarse gravel with occasional boulders with SPT = Refü.
The discharge site will be operated within cells. Stability analyses have been
performed for the slopes of cell 1 and 2, which will be used first, considering present
condition and two operation stages. At the first operation stage an intermediate water level
was considered and at the second operation stage final water level. Measures to provide
slope stability were determined for these two stages. The case of taking no measure was
also considered for the assessment of failure extension. Slope stability analyses of the
discharge site are performed with software Slide. Seismic coefficient is taken as kh=0.2 g
considering the discharge site is located at earthquake zone 1. Analyzed cases are
mentioned below in details.
2.1 Present Condition (Section 1-1, 2-2, 3-3)
Present conditions of three cross sections (1-1, 2-2, and 3-3) from cell 1 and 2 are
analyzed. Locations of the cross sections are presented in Figure 3.1. Slope height and
slope angle are given for the cross sections below.
Section Slope height (m) Slope angle ()
1-1 23.16 m 44
2-2 20.05 m 70
3-3 22.00 m 38-72
Internal angle of friction () is taken as 40 for dense gravel. Pore pressure
coefficient (ru) is considered as 0.1. Cohesion (c) value of 32 kPa for the alluvium gives a
factor of safety for cross sections 1-1, 2-2 and 3-3 FS=1.62, 1.00, 1.16 respectively (Figure
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
29 / 73
3.2-3.4). Considering the present geometry of the slopes and same soil parameters (c=32
kPa =40) the critical section is evaluated as 2-2. Water levels for this section are also
higher than the others and measures will be determined considering the geometry of the
section 2-2.
2.2 Taking no measure at water level 2 for all sections
When the water level at the discharge site rises without taking any measure, slope
fails and extends of the failure widens especially for seismic case; factor of safety (FS)<1. To
simulate the influence of water on the soil behavior the parameters under the water is taken
as c=15kPA and =36. Analyses are performed for all cross sections (1-1, 2-2, 3-3, 4-4, 5-
5, and 6-6) to determine the extension of the failure (Figure 3.5-3.10). Location of cross
sections can be seen in Figure 3.1. Distance from the top of the slope in seismic case for all
cross sections is given.
Section Water level-
Stage 2
Distance from top of the
slope in failure
1-1 13.5 m 9.4 m
2-2 16.5 m 15 m
3-3 14.5 m 8.3 m
4-4 9.4 m
5-5 17.8
6-6 11.1 m
2.3 Stability Analysis at Section 2-2 for short term (Stage 1) and long term
(Stage2)
i) Buttress at the toe of the slopes for wl=7 m (Stage 1) at Section 2-2
A buttress at an intermediate level of operation (water level=7m) is considered to
stabilize the slope. 7 m high buttress with a top width of 3.0m and bottom width of 7.0 m
gives a FSstatic=1.24 (Figure 3.11).
ii) Buttress at the toe of the slope and excavation of slopes for final wl=16.5 m
(Stage2) at Section 2-2
Construction of a buttress at the toe of the slopes brings some increase of the stability
level for an intermediate stage. But, for the long term stability the slopes over buttress should
be excavated to a lower slope angle. This case is analyzed for the final water level of 16.5 m.
The decrease of the geotechnical parameters of the soil both over and under water are
considered in the analyses.
The parameters of the soil over and under treated water are given below.
Soil over water c=25kPa and =38 ru = 0.15
Soil under water c=15kPa and =36
Slope geometry established with an angle of 3H:2V (horizontal: vertical) gives
required factor of safety for a maximum water level of 16:5 m; FSstatic=1.97 FSseismic=1.16
(Figure 3.12, 3.13).
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
30 / 73
iii) Excavation of slopes without any other measure at an intermediate stage
for final wl=16.5 m (Stage 2) at Section 2-2
If a measure such as buttress at an intermediate stage is not taken, slopes of the
discharge site can be stabilized with excavation. Slope composition established with an
angle of 3H:2V (horizontal: vertical) gives required factor of safety for a maximum water level
of 16.5 m; FSstatic=2.20 FSseismic=1.19 (Figure 3.14,3.15).
2.4 Stability Analysis at Section 1-1 for short term (Stage 1) and long term
(Stage2)
The section 1-1 has a slope angle of 44 and height of 23.16 and gives a factor of
safety=1.62 for the present condition. At the first stage water level of 4 m gives FS=1.44 and
water level=13.5m FS=1.38 (figure 3.16 and 3.17). If the slope is excavated to the slope
angle of 3H/2V FS=1.65 and 1.05 are obtained for static and seismic case (Figure 3.18 and
3.19).
2.5 Stability Analysis at Section 3-3 for short term (Stage 1) and long term
(Stage2)
The section 3-3 has a slope angle of 66-72 and height of 22.00 and gives a factor of
safety=1.16 for the present condition. At the first stage water level of 5 m gives FS=0.9
(Figure 3.20). 5 m high buttress with a top width of 3.m and bottom width of 5.0 m gives a
FS=1.03 for static case (Figure 3.21). At the second stage water level of 14.5 m slope over
the buttress is excavated to a slope of 3H/2V and analysis gives FS =1.73 and 1.10 for static
and seismic cases (Figure 3.22,3.23).
2.6 Stability Evaluation at Section 4-4, 5-5, 6-6 for long term (Stage 2)
For the other cells, which will be operated in later period critical cross sections are
given as 4-4, 5-5 and 6-6
Section Slope height (m) Slope angle () Water level-Stage 2
4-4 21.54 m 37 7.5 m
5-5 27.00 m 50 7.5 m
6-6 23.55 m 57 7.5 m
Those cells will be operated in next stages and an urgent measure is not necessary.
Excavation of the slope to the slope angle 3H:2V will be adequate for the required stability.
3. Conclusion
Stability of the slopes at discharge site is analyzed considering the present and future
conditions. T present condition, which can be valuated as short term, slopes have a
limited stability. Stability of the slopes can be diminished in natural condition such as
heavy rain falls or with operation of the plant.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
31 / 73
When the Waste Water Treatment Plant is operated, the treated water will percolate
through the bottom of the discharge site. However as the water level at the discharge site
increases slopes will encounter failure.
For the stability of two cells discharge site three alternatives are applicable rather than
unrealistic expensive measures at deep vertical walls;
Alternative 1 Doing nothing except expropriation of risky areas around the top of the
slopes
Alternative 2 Excavation of slope an angle of 3H:2V (section 1-1)
Buttress at the slope toe and excavation of slopes an angle of 1H:1V (section 2-2)
Buttress at the slope toe and excavation of slopes an angle of 3H:2V (section 3-3)
Alternative 3 Excavation of slopes to an angle of 3H:2V with one berm (This alternative
is applicable through all discharge area). Slopes will be excavated from the beginning.
Alternative 2 enables to take measures in two levels. Buttress at the toe provide stability
for an intermediate level of operation. With excavation of the slopes required stability can
be obtained finally.
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
32 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
33 / 73
Figure 3.2: Stability analysis for present condition of slope at section 1-1
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
34 / 73
Figure 3.3: Stability analysis for present condition of slope at section 2-2
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
35 / 73
Figure 3.4: Stability analysis for present condition of slope at section 3-3
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
36 / 73
Figure 3.5: Stability analysis at section 1-1 for Stage 2 (wl=13.5 m) without taking any measure-seismic case
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
37 / 73
Figure 3.6: Stability analysis at section 2-2 for Stage 2 (wl=16.5 m) without taking any measure- seismic case
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
38 / 73
Figure 3.7: Stability analysis at section 3-3 for Stage 2 (wl=14.5 m) without taking any measure- seismic case
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
39 / 73
Figure 3.8: Stability analysis at section 4-4 for Stage 2 (wl=7.5 m) without taking any measure- seismic case
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
40 / 73
Figure 3.9: Stability analysis at section 5-5 for Stage 2 (wl=7.5 m) without taking any measure-seismic case
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
41 / 73
Figure 3.10: Stability analysis at section 6-6 for Stage 2 (wl=7.5 m) without taking any measure- seismic case
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
42 / 73
Figure 3.11: Stability analysis for Stage 1 (wl=7 m) with buttress at the toe at section 2-2-static case
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
43 / 73
Figure 3.12: Stability analysis for the final condition –Stage 2 (wl=16.5 m) with buttress and excavation at the slope of section 2-2 -static case
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
44 / 73
Figure 3.13: Stability analysis for the final condition–Stage 2(wl=16.5 m) with buttress and excavation at the slope of section 2-2 -seismic case
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
45 / 73
Figure 3.14: Stability analysis for the final condition –Stage 2 (wl=16.5 m) with excavation at the slope of section 2-2 –static case
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
46 / 73
Figure 3.15: Stability analysis for the final condition –Stage 2 (wl=16.5 m) with excavation at the slope of section 2-2 -seismic case
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
47 / 73
Figure 3.16: Stability analysis for wl=4 m- Stage 1 at section 1-1 without taking any measure-static case
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
48 / 73
Figure 3.17: Stability analysis for wl=13.5 m-Stage 2 at section 1-1 without taking any measure-static case
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
49 / 73
Figure 3.18: Stability analysis for wl=13.5 m-Stage 2 at section 1-1 with excavation at the slope -static case
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
50 / 73
Figure 3.19: Stability analysis for wl=13.5 m- Stage 2 at section 1-1 with excavation at the slope -seismic case
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
51 / 73
Figure 3.20: Stability analysis for slope at section 3-3 for Stage 1-wl=5 m without taking any measure-static case
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
52 / 73
Figure 3.21: Stability analysis for slope at section 3-3 for Stage 1 wl=5 m with buttress -static case
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
53 / 73
Figure 3.22: Stability analysis for slope at section 3-3 for Stage 2 wl=14.5 m with buttress -static case
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
54 / 73
Figure 3.23: Stability analysis for slope at section 3-3 for Stage 2 wl=14.5 m with buttress -seismic case
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H 55 / 73
Annex-4
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H 56 / 73
2012 Unit January February March April May June July August September October November December Total
Treated Wastewater m3/day 3.000 3.100 3.200 3.300 3.400 3.500 3.600 3.700 3.800 3.900 4.000 4.100
m3/month 90.000 93.000 96.000 99.000 102.000 105.000 108.000 111.000 114.000 117.000 120.000 123.000 1.278.000
Precipitation m3/month 11.869 9.125 6.732 4.015 2.706 1.320 385 446 913 3.284 9.026 13.178 62.997
Evaporation m3/month -401 -514 -847 -1.161 -1.861 -2.946 -4.017 -4.057 -2.777 -1.384 -646 -390 -21.001
Infiltration m3/month -116.841 -116.841 -116.841 -116.841 -116.841 -116.841 -116.841 -116.841 -116.841 -116.841 -116.841 -116.841 -1.402.091
Irrigation (Green Areas) m3/month - - - 0 0 0 0 0 0 - - - 0
Total m3/month -15.373 -15.230 -14.956 -14.987 -13.995 -13.467 -12.472 -9.453 -4.705 2.058 11.539 18.947 -82.094
Cumulative Total m3/month -15.373 -30.603 -45.559 -60.546 -74.541 -88.009 -100.481 -109.934 -114.638 -112.580 -101.042 -82.094
Total Volume m3 90.000 90.000 90.000 90.000 90.000 90.000 90.000 90.000 90.000 90.000 90.000 90.000
Ratio to Total Volume % -0,17 -0,34 -0,51 -0,67 -0,83 -0,98 -1,12 -1,22 -1,27 -1,25 -1,12 -0,91
2013 Unit January February March April May June July August September October November December Total
Treated Wastewater m3/day 4.200 4.300 4.400 4.500 4.600 4.700 4.800 4.900 5.000 5.100 5.200 5.300
m3/month 126.000 129.000 132.000 135.000 138.000 141.000 144.000 147.000 150.000 153.000 156.000 159.000 1.710.000
Precipitation m3/month 11.869 9.125 6.732 4.015 2.706 1.320 385 446 913 3.284 9.026 13.178 62.997
Evaporation m3/month -401 -514 -847 -1.161 -1.861 -2.946 -4.017 -4.057 -2.777 -1.384 -646 -390 -21.001
Infiltration m3/month -116.841 -116.841 -116.841 -116.841 -116.841 -116.841 -116.841 -116.841 -116.841 -116.841 -116.841 -116.841 -1.402.091
Irrigation (Green Areas) m3/month - - - -60.000 -60.000 -60.000 -60.000 -60.000 -60.000 - - - -360.000
Total m3/month 20.627 20.770 21.044 -38.987 -37.995 -37.467 -36.472 -33.453 -28.705 38.058 47.539 54.947 -10.094
Cumulative Total m3/month -61.467 -40.697 -19.653 -58.640 -96.635 -134.103 -170.575 -204.028 -232.733 -194.674 -147.136 -92.188
Total Volume m3 90.000 90.000 90.000 90.000 90.000 90.000 90.000 90.000 90.000 90.000 90.000 90.000
Ratio to Total Volume % -0,68 -0,45 -0,22 -0,65 -1,07 -1,49 -1,90 -2,27 -2,59 -2,16 -1,63 -1,02
2014 Unit January February March April May June July August September October November December Total
Treated Wastewater m3/day 5.500 5.700 5.900 6.100 6.300 6.500 6.700 6.900 7.100 7.300 7.500 7.700
m3/month 165.000 171.000 177.000 183.000 189.000 195.000 201.000 207.000 213.000 219.000 225.000 231.000 2.376.000
Precipitation m3/month 11.869 9.125 6.732 4.015 2.706 1.320 385 446 913 3.284 9.026 13.178 62.997
Evaporation m3/month -1.403 -1.799 -2.965 -4.065 -6.512 -10.313 -14.058 -14.201 -9.719 -4.846 -2.261 -1.364 -73.502
Infiltration m3/month -245.981 -245.981 -245.981 -245.981 -245.981 -245.981 -245.981 -245.981 -245.981 -245.981 -245.981 -245.981 -2.951.770
Irrigation (Green Areas) m3/month - - - -90.000 -90.000 -90.000 -90.000 -90.000 -90.000 - - - -540.000
Total m3/month -70.514 -67.655 -65.213 -153.030 -150.787 -149.973 -148.654 -142.736 -131.786 -28.543 -14.216 -3.167 -1.126.275
Cumulative Total m3/month -162.703 -230.357 -295.571 -448.601 -599.388 -749.361 -898.015 -1.040.751 -1.172.537 -1.201.080 -1.215.296 -1.218.463
Total Volume m3 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000
Ratio to Total Volume % -0,44 -0,62 -0,80 -1,21 -1,62 -2,03 -2,43 -2,81 -3,17 -3,25 -3,28 -3,29
2015 Unit January February March April May June July August September October November December Total
Treated Wastewater m3/day 7.900 8.100 8.300 8.500 8.700 8.900 9.000 9.200 9.400 9.600 9.800 10.000
m3/month 237.000 243.000 249.000 255.000 261.000 267.000 270.000 276.000 282.000 288.000 294.000 300.000 3.222.000
Precipitation m3/month 11.869 9.125 6.732 4.015 2.706 1.320 385 446 913 3.284 9.026 13.178 62.997
Evaporation m3/month -1.403 -1.799 -2.965 -4.065 -6.512 -10.313 -14.058 -14.201 -9.719 -4.846 -2.261 -1.364 -73.502
Infiltration m3/month -245.981 -245.981 -245.981 -245.981 -245.981 -245.981 -245.981 -245.981 -245.981 -245.981 -245.981 -245.981 -2.951.770
Irrigation (Green Areas) m3/month - - - -120.000 -120.000 -120.000 -120.000 -120.000 -120.000 - - - -720.000
Total m3/month 1.486 4.345 6.787 -111.030 -108.787 -107.973 -109.654 -103.736 -92.786 40.457 54.784 65.833 -460.275
Cumulative Total m3/month -1.216.977 -1.212.632 -1.205.845 -1.316.876 -1.425.662 -1.533.636 -1.643.289 -1.747.026 -1.839.812 -1.799.355 -1.744.571 -1.678.737
Total Volume m3 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000
Ratio to Total Volume % -3,29 -3,28 -3,26 -3,56 -3,85 -4,14 -4,44 -4,72 -4,97 -4,86 -4,72 -4,54
2020 Unit January February March April May June July August September October November December Total
Treated Wastewater m3/day 17.111 17.111 17.111 17.111 17.111 17.111 17.111 17.111 17.111 17.111 17.111 17.111
m3/month 513.335 513.335 513.335 513.335 513.335 513.335 513.335 513.335 513.335 513.335 513.335 513.335 6.160.016
Precipitation m3/month 11.869 9.125 6.732 4.015 2.706 1.320 385 446 913 3.284 9.026 13.178 62.997
Evaporation m3/month -1.403 -1.799 -2.965 -4.065 -6.512 -10.313 -14.058 -14.201 -9.719 -4.846 -2.261 -1.364 -73.502
Infiltration m3/month -233.682 -233.682 -233.682 -233.682 -233.682 -233.682 -233.682 -233.682 -233.682 -233.682 -233.682 -233.682 -2.804.181
Irrigation (Green Areas) m3/month - - - -120.000 -120.000 -120.000 -120.000 -120.000 -120.000 - - - -720.000
Irrigation (Forestry Areas) m3/month -200.000 -200.000 -200.000 -200.000 -200.000 -200.000 -200.000 -200.000 -200.000 -200.000 -200.000 -200.000 -2.400.000
Total m3/month 90.119 86.979 83.420 -40.397 -44.153 -49.340 -54.020 -54.103 -49.153 78.091 86.418 91.467 225.330
Cumulative Total m3/month 90.119 177.098 260.519 220.122 175.969 126.630 72.609 18.507 -30.646 47.445 133.863 225.330
Total Volume m3 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000
Ratio to Total Volume % 0,24 0,48 0,70 0,59 0,48 0,34 0,20 0,05 -0,08 0,13 0,36 0,61
2025 Unit January February March April May June July August September October November December Total
Treated Wastewater m3/day 18.535 18.535 18.535 18.535 18.535 18.535 18.535 18.535 18.535 18.535 18.535 18.535
m3/month 556.051 556.051 556.051 556.051 556.051 556.051 556.051 556.051 556.051 556.051 556.051 556.051 6.672.614
Precipitation m3/month 11.869 9.125 6.732 4.015 2.706 1.320 385 446 913 3.284 9.026 13.178 62.997
Evaporation m3/month -1.403 -1.799 -2.965 -4.065 -6.512 -10.313 -14.058 -14.201 -9.719 -4.846 -2.261 -1.364 -73.502
Infiltration m3/month -221.383 -221.383 -221.383 -221.383 -221.383 -221.383 -221.383 -221.383 -221.383 -221.383 -221.383 -221.383 -2.656.593
Irrigation (Green Areas) m3/month - - - -120.000 -120.000 -120.000 -120.000 -120.000 -120.000 - - - -720.000
Irrigation (Forestry Areas) m3/month -250.000 -250.000 -250.000 -250.000 -250.000 -250.000 -250.000 -250.000 -250.000 -250.000 -250.000 -250.000 -3.000.000
Total m3/month 95.135 91.994 88.436 -35.381 -39.138 -44.324 -49.005 -49.087 -44.137 83.106 91.433 96.482 285.517
Cumulative Total m3/month 95.135 187.129 275.565 240.184 201.047 156.723 107.718 58.631 14.494 97.601 189.034 285.517
Total Volume m3 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000
Ratio to Total Volume % 0,26 0,51 0,74 0,65 0,54 0,42 0,29 0,16 0,04 0,26 0,51 0,77
2030 Unit January February March April May June July August September October November December Total
Treated Wastewater m3/day 20.030 20.030 20.030 20.030 20.030 20.030 20.030 20.030 20.030 20.030 20.030 20.030
m3/month 600.915 600.915 600.915 600.915 600.915 600.915 600.915 600.915 600.915 600.915 600.915 600.915 7.210.979
Precipitation m3/month 11.869 9.125 6.732 4.015 2.706 1.320 385 446 913 3.284 9.026 13.178 62.997
Evaporation m3/month -1.403 -1.799 -2.965 -4.065 -6.512 -10.313 -14.058 -14.201 -9.719 -4.846 -2.261 -1.364 -73.502
Infiltration m3/month -209.084 -209.084 -209.084 -209.084 -209.084 -209.084 -209.084 -209.084 -209.084 -209.084 -209.084 -209.084 -2.509.004
Irrigation (Green Areas) m3/month - - - -120.000 -120.000 -120.000 -120.000 -120.000 -120.000 - - - -720.000
Irrigation (Forestry Areas) m3/month -310.000 -310.000 -310.000 -310.000 -310.000 -310.000 -310.000 -310.000 -310.000 -310.000 -310.000 -310.000 -3.720.000
Total m3/month 92.298 89.157 85.599 -38.218 -41.975 -47.161 -51.842 -51.924 -46.974 80.269 88.596 93.645 251.469
Cumulative Total m3/month 92.298 181.455 267.054 228.835 186.861 139.699 87.857 35.933 -11.041 69.228 157.824 251.469
Total Volume m3 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000
Ratio to Total Volume % 0,25 0,49 0,72 0,62 0,51 0,38 0,24 0,10 -0,03 0,19 0,43 0,68
2035 Unit January February March April May June July August September October November December Total
Treated Wastewater m3/day 21.601 21.601 21.601 21.601 21.601 21.601 21.601 21.601 21.601 21.601 21.601 21.601
m3/month 648.024 648.024 648.024 648.024 648.024 648.024 648.024 648.024 648.024 648.024 648.024 648.024 7.776.288
Precipitation m3/month 11.869 9.125 6.732 4.015 2.706 1.320 385 446 913 3.284 9.026 13.178 62.997
Evaporation m3/month -1.403 -1.799 -2.965 -4.065 -6.512 -10.313 -14.058 -14.201 -9.719 -4.846 -2.261 -1.364 -73.502
Infiltration m3/month -196.785 -196.785 -196.785 -196.785 -196.785 -196.785 -196.785 -196.785 -196.785 -196.785 -196.785 -196.785 -2.361.416
Irrigation (Green Areas) m3/month - - - -120.000 -120.000 -120.000 -120.000 -120.000 -120.000 - - - -720.000
Irrigation (Forestry Areas) m3/month -365.000 -365.000 -365.000 -365.000 -365.000 -365.000 -365.000 -365.000 -365.000 -365.000 -365.000 -365.000 -4.380.000
Total m3/month 96.706 93.565 90.007 -33.810 -37.567 -42.753 -47.434 -47.516 -42.566 84.677 93.004 98.053 304.367
Cumulative Total m3/month 96.706 190.271 280.278 246.468 208.901 166.148 118.715 71.198 28.632 113.310 206.314 304.367
Total Volume m3 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000
Ratio to Total Volume % 0,26 0,51 0,76 0,67 0,56 0,45 0,32 0,19 0,08 0,31 0,56 0,82
2040 Unit January February March April May June July August September October November December Total
Treated Wastewater m3/day 23.252 23.252 23.252 23.252 23.252 23.252 23.252 23.252 23.252 23.252 23.252 23.252
m3/month 697.556 697.556 697.556 697.556 697.556 697.556 697.556 697.556 697.556 697.556 697.556 697.556 8.370.677
Precipitation m3/month 11.869 9.125 6.732 4.015 2.706 1.320 385 446 913 3.284 9.026 13.178 62.997
Evaporation m3/month -1.403 -1.799 -2.965 -4.065 -6.512 -10.313 -14.058 -14.201 -9.719 -4.846 -2.261 -1.364 -73.502
Infiltration m3/month -184.486 -184.486 -184.486 -184.486 -184.486 -184.486 -184.486 -184.486 -184.486 -184.486 -184.486 -184.486 -2.213.827
Irrigation (Green Areas) m3/month - - - -120.000 -120.000 -120.000 -120.000 -120.000 -120.000 - - - -720.000
Irrigation (Forestry Areas) m3/month -425.000 -425.000 -425.000 -425.000 -425.000 -425.000 -425.000 -425.000 -425.000 -425.000 -425.000 -425.000 -5.100.000
Total m3/month 98.537 95.397 91.838 -31.979 -35.735 -40.922 -45.602 -45.685 -40.735 86.509 94.836 99.885 326.345
Cumulative Total m3/month 98.537 193.934 285.772 253.794 218.059 177.137 131.535 85.850 45.115 131.624 226.460 326.345
Total Volume m3 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000 370.000
Ratio to Total Volume % 0,27 0,52 0,77 0,69 0,59 0,48 0,36 0,23 0,12 0,36 0,61 0,88
Assumptions: In 2012 and 2013 short-term operation system will be applied.
Starting with 2014 whole area will be used.
Minimum permeability coefficient, obtained from drilling studies, is applied.
It is suggested that disposal site will loose 5% of its permeability in 2020 and 25% in 2040.
50% of the irrigation pumps in WWTP will be in operation in 2015, 75% in 2014 and 100% in 2015.
2012 ve 2013'de deşarj sahasının ilk bölümlerinin kullanılacağı düşünülmüştür.
2013'den itibaren deşarj sahasının tamamının kullanılacağı düşünülmüştür.
Hesaplamalarda, sondaj çalışmalarından elde edilen geçirimlilik katsayılarının minimum değeri kullanılmıştır.
2020 Yılında deşarj sahasının geçirimliliğinin %5'ini, 2040 yılında ise %25'ini kaybedeceği öngörülmüştür.
Atıksu Arıtma Tesisinde bulunan sulama suyu pompalarının 2013 yılında yarısının 2015 yılında ise tamamının devreye gireceği düşünülmüştür.
Table 4.1: Water Balance of Discharge Site (Abandoned Sand and Gravel Quarry)
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H 57 / 73
No Name of the Park and Green Areas Green Area Flower
Gardens
Groumd Number of
Tree
Area with
Trees m2
Total Area
1 İnsan Hakları Parkı 370 70 914 1354
2 Muğlaspor Parkı 920 920
3 2.nolu Sağlık Ocağı Altı Üçgen Alan 400 400
4 Düğerek Düğün Salonu 500 500
5 Otogar Adliye Arası Refüj 250 250 500
6 Salık Meslek Yüksek Okulu Karşısı 80 20 100
7 Düğerek Meydanı ve Adnan Menderes Bulvarı Refüj 20 150 170
8 İsmail Hakkı Tonguç Parkı(Sınırsızlık Meydanı) 800 1460 2260
9 Kışla Parkı 11720 100 adet 800 24400
10 Uğur Mumcu Bulvarı 2880 1684 3846 8410
12 Bölge Trafik Kavşağı 620 780 1400
13 Düğerek 41 Evler Kav.+Otopark Düz.+Tedaş Önü 250 230 480
14 Kocamustafendi İlköğretim Okulu Önü 30 adet 250 250
15 Çınar Caddesi 100 100
16 Titiz Benz. Altı 200 200
17 Milli Piyango Önü 250 250
18 İsmet Çatak Cad.+Devlet Hastanesi Karşısı 250 250
19 Tekel Kavşağı 80 80
20 Bankalar Cad.+Özer Türk Cad. 200 200
21 Sanayi Uğur Mumcu Kavşağı Ağaçlık Alan 730 adet 16000 16000
22 Düğerek Cezaevi Kavşağı 165 165
23 Düğerek Giriş Kavşağı 190 190
24 Açık Pazar Yerindeki Yeşil Alanlar 100 100
25 Belediye Çevresi 80 30 110
26 Yeni Belediye Binası Çevresi 200 50 250
27 Milli Egemenlik Meydanı 830 150 980
28 Belediye Parkı 2080 1958 4038
29 Akyol Parkı 1657 30 1824 3511
30 Nazım Hikmet Parkı 3812 40 3733 7585
31 Ersan Gümüşalan Parkı 2200 1908 4108
32 DSİ Önü Parkı 1500 257 1757
33 Eski Cezaevi Arkası 250 250
34 Cumhuriyet Meydanı (300 m2 dıs alan fıskıye.) 700 100 800
35 Eski Tansa Yerindeki park 500 500
36 Kurşunlu Camii Yanı 100 100
37 Akyol Memurlar Sitesi Parkı 1000 1000
38 Ticaret Lisesi Önü ve Büfeli Parkı 25 adet 50 50
39 Düğerek İlkokulu Karşısı Kavşak 527 527
40 Otogar İçi Minibüs Garajı ve Çevresi 200 250 adet 200
41 Aylin Karaca Kavşağı 150 150
42 Cumhuriyet Caddesi Yol Kenarı 50 50
43 Düğerek Pazar Yeri 300 300
44 Ziraat Bankası Karşısı 50 50
45 Emniyet Kademe Karşısı Kavşak 150 30 180
46 Akyol Pazar Yeri Girişi 100 50 150
47 Serpil Park 100 185 285
48 Konakaltı Kültür Merkezi 240 10 250
49 Yekap 1 Parkı 378 adet 740 740
50 Avcılar Sokak Üçgen Alan 400 400
51 Doktorlar Sitesi Parkı 900 2296 3196
52 Atatürk Bulvarı Yürüyüş Yolu Kenarı 1. Kısım 822 adet 2200 2200
53 Atatürk Bulvarı Refüj 1. Kısım 340 adet 3000 3000
54 İtfaiye Altı Mezbaha Yolu- Köpek Evi 250 adet 1470 1470
55 Özbekler Evi ve Kültür Evi 30 30
56 Düğerek Hayvan Pazarı ve Pazaryeri Kenarı 55 adet 0
57 Bölge Trafik Yücelen Arası 215 adet 800 800
58 Akkaya Yol Kavşağı 115 adet 1000 1000
59 Osman Günsan Parkı 1100 1367 2467
60 Atatürk Cad.Evler-Yürüyüş Yolu Arası (Türkcell Pehlivanoğlu) 315 adet 12900 12900
61 Bellona Önü Ağaçlık Alan 94 adet 4000 4000
62 Atatürk Cad.Evler-Yürüyüş Yolu Arası (Bellona Karamuğla D.) 300 adet 14000 14000
63 Orhaniye Dere Kenarı Zakkumlar ve Huzurevi Kar. 360 adet 1500 1500
64 Turan Şahin Parkı 2582 18 869 3469
65 Yalçın İnan Parkı 2000 1208 3208
66 Stadyum Karşısı Dere Kenarı 123adet 0
67 Parke Atl.+Hamursuz İskender Alper Cad.+Rektörlük Ç. 250adet 0
68 Kuranoğlu Üstü 3350 2180 6adet 5530
69 Emek Sitesi içindeki Parklar 6060 6910 12970
70 Akyol Muğlaspor Tesisleri Çevresi ve Anaokulu Çevresi 55adet 0
Table 4.2: Green Areas Of Muğla Municipality
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H 58 / 73
70 Akyol Muğlaspor Tesisleri Çevresi ve Anaokulu Çevresi 55adet 0
71 32 Evler Parkı 1300 700 37adet 2000
72 Orta Sanayi ve Döşemeciler Karşısı 110adet 1000 1000
73 Şehit Özden Aşınmaz Caddesi 151adet 0
74 Şehitler Anı Ormanı (2.El oto Pazarı Üstü) 1500adet 31000 31000
75 Fen Lisesi Önü 75adet 0
76 Atatürk Cad. 3. Kısım Çamlar 11adet 0
77 Emniyet Kademe Karşısı (Çamlar ve Çınarlar) 30adet 0
78 Ayşegül Parkı 295 283 578
79 Muğla 2000 Derneği Parkı 3938 40 987 4965
80 Toptancı Hali İç ve Dış Kısım-Nakliyeciler 470 88adet 470
81 ADLİYE ÖNÜ 50
82 Uğur Mumcu Kavşağı 11412 100 11512
83 Ahmet Taner Kışlalı Parkı 6950 250 6128 13328
84 Yeni Mezarlık 460adet 164493
85 Munise Hamdi Doğruel Parkı 640 400 1040
86 Eğer Gediği 2300 100 2400
87 Org.Mustafa Muğlalı İşhanı Etrafı 120 120
88 Akyol Girişi Zakkumlar 370adet 250 250
89 Eski Mezarlık 30 67424
90 Emin Arslan Parkı 513 17 567 1097
91 M.Eren Parkı 770 30 1000 1800
92 Köfteciler Önü ve Dere Kenarı 1000 1000
93 Spor İl Müd. Karşısı 515 55 570
94 Pehlivanoğlu Karşısı Kavşak 240 60 300
95 Sekibaşı Kadın Dayanışma Evi 145 20 165
96 Yekap 2 Parkı 580 820 1400
97 Atatürk Cad. Refüj 2. Kısım 1430 580 2010
98 Atatürk Cad.Yürüyüş Yolu Kenarı 2930 600 3530
99 Spor Kompleksi 1500 3698 5198
100 Yücelen Hast.- Ermaş Önü 1000 1000
101 Saburhane Meydanı 20 20
102 112 Evler Semt P.(Şehit Kom.Er Osman Kara Parkı) 450 250 902 1602
103 Düğerek Yürüyüş Yolu Kenarı 710 710
104 Anadolu Lisesi Çevresi 80adet 0
105 Latif Sepil Parkı 1720 60 1228 3008
106 Kandere Kenarı Ağaçlık Alan 1115adet 1000 1000
107 Düğerek İlkokulu Arkasındaki Park 1900 1523 3423
108 Sağlık Müdürlüğü Karşısı 65 109adet 65
109 Düğerek Çayır Yolu Kaldırımı Ağaçlar 366adet 0
110 İtfaiye Altı Yeşil Alan 150 150
111 Kötekli Gençlik Parkı 1000 800 1800
112 Tarım İl Müdürlüğü 20 30 50
113 Mevhibe İnönü Parkı 9850 100 10350 20300
114 Kireç Sanayi Kavşağı 260 260
115 Düğerek Çayır Yolu Kavşağı 370 370
116 Recai Güreli Okul Karşısı Yeşil Alan 290 290
117 Öğretmen Evi Karşısı Yeşil Alan 600 30 290 920
118 Muğla Şehitliği Karşısı Kavşak 3100 100 3200
119 İzciler Parkı 1000 1000
120 Saburhane Ecza Odası Karşısı 10adet 50 50
121 Karşıyaka Semt Parkı 450 187adet 300 750
122 Orhaniye Semt Parkı 50 50
123 Orhaniye Camii Karşısı 50 50
124 Asar Su Deposu Altı 200 400 600
126 Celali Bahçesi 86adet 100 100
127 Fen Lisesi Karşısı Refüj 2600 2600
128 Türk Telekom Karşısı park 380 220 600
129 Düğerek Soda Kavşağı 350 350
130 Yeni Mezbaha Karşısı 540 540
131 Basmacı Deresi Mutluluk Ormanı 1100adet 17000 17000
132 G. Mustafa Kemal Kong.Merk.Çevresi 2700 200 2160 5060
133 Mehmet Ağa Koca Havuz Parkı 6300 100 3800 10200
134 Huzurevi Karşısı Park 250 180 430
135 Kışla Parkı Yamaç Alan 7000 250 7250
136 Kötekli Semt Parkı 1000 500 1500
137 Üçerenler Yeşil Alan 180 180
138 telekom Altı Parklar (4 adet) 1530 1020 2550
139 Kötekli Mezarlığı 5000
140 TOKİ 3666adet 0
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H 59 / 73
141 Karabağlar Yayla Yolu Kenarları 4000
142 Genç Yapı Parkları 1000 460 144adet 3400 5024
143 Sanayi Parkı 1000 1000
144 Söğütlü Önü Yeşil Alan 500 500
145 Sertaç Market Karşısı Yeşil Alan 30 105adet 30
147 Atatürk Cad. 3 Kısım Refüj 660adet 5000 5000
148 EGEHAN ÖNÜ REFÜJ 1500
149 Düğerek Girişi Semt Parkı 1400 845 2245
153 Düverek Futbol Sahası Kenarı Ağaç. 300adet 1500 1500
154 Düverek Mezarlığı 39745
155 YUCELEN KARSISI 1600 1600
156 Arıcılar birliği önü yeşil alan 3200 3200
157 sertaç market yanı yeşil alan 365 528 893
158 şehitlik eger gedığı arası kaldırımlar 1604adet
160 EMNİYET KADEME YANI YEŞİL ALAN 1600
167 ÇINAR SITESI KARSISI KAVSAK 2500
172 zahire pazarı 50 10 60
Toplam 142241 9234 0 127906 636865
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H 60 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H 61 / 73
Annex-5
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H 62 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
63 / 73
Annex-6
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
64 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
65 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
66 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
67 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
68 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
69 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
70 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
71 / 73
Mugla Municipality Mugla Municipality Wastewater Treatment Plant Project
Environmental Impcat Assessment Report
Appendix-H
72 / 73