Upload
domenico-beglan
View
21
Download
0
Embed Size (px)
DESCRIPTION
MRP and ERP. Chapter 12. Learning Objectives. Describe the inputs, outputs, and nature of MRP processing. Explain bill of materials Explain time-phased product structure Describe differences between MRP and ERP. MRP. Material requirements planning (MRP): - PowerPoint PPT Presentation
Citation preview
Learning Objectives
• Describe the inputs, outputs, and nature of MRP processing.
• Explain bill of materials• Explain time-phased product structure• Describe differences between MRP and ERP
MRP
• Material requirements planning (MRP):– A computer-based information system that translates
master schedule requirements for end items into time-phased requirements for subassemblies, components, and raw materials.
– The MRP is designed to answer three questions:1. What is needed?2. How much is needed?3. When is it needed?
Overview of MRP
Composition of a finished products
How much and when finished product is desired
How much inventory is on hand or on order
Weekly Quantity
Item X 11 12 13 14 15 16 17 18
Quantity 100 150
MRP Inputs:Master Schedule
• Master schedule: – States:
• Which end items are to be produced
• When these are needed
• In what quantities (customer orders, forecasts, order from warehouses to build up seasonal inventories).
Item X
at beginning of week 14 andat beginning of week 18
100 at beginning of week 14150 at beginning of week 18
Cumulative Lead Time
The master schedule should cover a period that is at least equivalent to the cumulative lead time
– Cumulative lead time » The sum of the lead times that sequential phases of a process
require, from ordering of parts or raw materials to completion of final assembly.
CLT = 9 weeks
Cumulative Lead Time
• Following the previous example, if CLT=9– When should we start work for the demand on the week
14?– When should we start work for the demand on the week
18?Weekly Quantity
Item X 11 12 13 14 15 16 17 18
Quantity 100 150
MRP Inputs:Bill of Materials
• Bill of Materials (BOM)– A hierarchical listing of all of the assemblies,
subassemblies, parts, and raw materials needed to produce one unit of a product
– Each finished product has its own BOM– Product structure tree
• A visual depiction of the requirements in a bill of materials, where all components are listed by levels
Assembly Diagram and Product Structure Tree
Level 0 = end itemparent
componentparent
component
Level 1
Level 2
Amount needed for assembly at the next higher level only
Low-Level Coding
• Low-level coding– Restructuring the bill of materials so that multiple
occurrences of a component all coincide with the lowest level at which the component occurs
• Example: 1 X requires: 2 B, 1 C, 6 D, 28 E, and 2 F
Level 3
Level 2
Level 1
Level 0 X
B(2)
D(3)
E(4)
E
C
E(2) F(2)
B: 2 x 1 = 2
D: 3 x 2 = 6E: 1 x 2 = 2
E: 4 x 6 = 24
C: 1 x 1 = 1
E: 2 x 1 = 2F: 2 x 1 = 2
X: 1
Low-Level Coding: 1 X
Level 3
Level 2
Level 1
Level 0 X
B(2)
D(3)
E(4)
E
C
E(2) F(2)
• 1 X requires:B: 2C: 1D: 6E: 2+24+2=28F: 2
B: 2 x 1 = 2
D: 3 x 2 = 6E: 1 x 2 = 2
E: 4 x 6 = 24
C: 1 x 1 = 1
E: 2 x 1 = 2F: 2 x 1 = 2
X: 1
Low-Level Coding: 10 Xwith on hand inventory
Level 3
Level 2
Level 1
Level 0 X
B(2)
D(3)
E(4)
E
C
E(2) F(2)
• 1 X requires:B: 2C: 1D: 6E: 28F: 2
10 X require:
B: 2x10-4=16
C: 1x10-10=0
D: 6x10-8=52
E: 28x10-60=220
F: 2x10-0=20
• On hand inventory
B: 4
C: 10
D: 8
E: 60
F: 0
Does not consider item hierarchy!
Low-Level Coding: 10 Xwith on hand inventory
Level 3
Level 2
Level 1
Level 0 X
B(2)
D(3)
E(4)
E
C
E(2) F(2)
B: 2 x 10 - 4 = 16
D: 3 x 16 – 8=40
E: 1 x 16 = 16
E: 4 x 40 – 60=100
C: 1 x 10 -10=0
E: 2 x 0 = 0
F: 2 x 0 = 0
• 10X require:
B: 16
C: 0
D: 40
E: 100+16+0=116
F: 0
X: 10
“Low-level coding”
• On hand inventory
B: 4
C: 10
D: 8
E: 60
F: 0
MRP Processing
• MRP processing takes the end item requirements specified by the master schedule and “explodes” them into time-phased requirements for assemblies, parts, and raw materials offset by lead times
Final assembly lead-time
Part E fabrication lead-time
Material F delivery
lead-time
Sub assembly lead-time
MRP Inputs:Inventory Records
• Inventory records– Includes information on the status of each item by time
period (called time buckets)• Information about
– Gross requirements– Scheduled receipts– Expected amount on hand
• Other details for each item such as– Supplier– Lead time– Lot size policy– Changes due to stock receipts and withdrawals– Canceled orders and similar events
MRP RecordGross requirements
• Total expected demand (during each period) without regard to the amount on hand.
Scheduled receipts• Open orders scheduled to arrive (at the
beginning of a period)Projected on hand
• Expected inventory on hand (at the beginning of each time period)
Week Number 1 2 3 4 5 6
Gross Requirements
Scheduled Receipts
Projected on hand
Net requirements
Planned-order-receipt
Planned-order release
12-16
Net requirements• Actual amount needed in each time period
Planned-order receipts• Quantity expected to received (at the
beginning of the period)• Under Lot-for-lot will equal net
requirementsPlanned-order releases
• Planned amount to order in each time period.
• Equal planned-order receipts offset by lead time.
MRP Processing • Gross requirements are generated by exploding the
bill of materials• The core of MRP processing is determining net
requirements (netting) -> materials that are actually needed to meet demand
Net requirements
Gross requirements
Available inventory
Available inventory
Projected on-hand
=
=
-
Net requirements
Gross requirements
Projected on hand inventory +
Scheduled receipts= -
Scheduled receipts
+
MRP: Development• The MRP is based on the product structure tree
diagram• Requirements are determined level by level, beginning
with the end item and working down the tree• The timing and quantity of each “parent” becomes the basis for
determining the timing and quantity of the “children” items directly below it.
• The “children” items then become the “parent” items for the next level, and so on
Example MRP
Shutter
Frames (2) Wood sections (4)
•Orders:• 100 units for delivery at (the start of) week
4• 150 units at (the start of) week 8.
• Assembly:• Wood sections made by the firm.
Fabrication takes 1 week.• Frames are ordered. Lead time is 2 weeks.• Shutter assembly requires 1 week.
• Schedule receipts:• 70 wood sections at (the beginning of) week
1.• • Determine the size and timing of planned-order releases (under Lot-for-Lot ordering)
MRPLot-For-Lot Ordering
Shutter[LT=1 week]
Frames (2)[LT=2 weeks]
Wood sections (4)[LT= 1 weeks]
Widget (1)[LT=1 weeks]
Widget (3)[LT=1 weeks]
200*1 300*1330*3 600*3
Updating the System• An MRP is not a static document
– As time passes• Some orders get completed• Other orders are nearing completion• New orders will have been entered• Existing orders will have been altered
– Quantity changes– Delays– Missed deliveries
– Rolling Horizon
MRP Outputs: Primary• Primary Outputs
– Planned orders• A schedule indicating the amount and timing of future
orders
– Order releases• Authorizing the execution of planned orders
– Changes• Revisions of the dates or quantities, or the cancellation of
orders
MRP Outputs: SecondarySecondary Outputs
Performance-control reportsEvaluation of system operation, including deviations from
plans and cost information– e.g., missed deliveries and stockouts
Planning reportsData useful for assessing future material requirements
– e.g., purchase commitmentsException reports
Data on any major discrepancies encountered– E.g., late and overdue orders, excessive scrap rates, requirements
for nonexistent parts
Enterprise Resource Planning (ERP)• Many organizations use a functional structure. Information tends
to flow freely within each function but less so between functions.
• Enterprise Resource Planning (ERP) – ERP was the next step in an evolution that began with MRP
– ERP typically has an MRP core
– ERP represents an expanded effort to integrate standardized record keeping that will permit information sharing among different areas of an organization in order to manage the system more effectively
– A system to capture and make data available in real-time to decision makers throughout the organization.
– ERP systems are composed of a collection of integrated modules
ERP Software ModulesModule Brief Description
Accounting/Finance A central component of most ERP systems. It provides a range of financial reports, including general ledger, accounts payable, accounts receivable, payroll, income statements, ad balance sheets
Marketing Supports lead generation, target marketing, direct mail, and salesHuman Resources Maintains a complete data base of employee information such as date of hire, salary,
contact information, performance evaluations, and other pertinent informationPurchasing Facilitates vendor selection, price negotiation, making purchasing decisions, and bill
paymentProduction Planning Integrates information on forecasts, orders, production capacity, on-hand inventory
quantities, bills of material, work in process, schedules, and production lead timesInventory Management Identifies inventory requirements, inventory availability, replenishment rules, and
inventory trackingDistribution Contains information on third-party shippers, shipping and delivery schedules, delivery
trackingSales Information on orders, invoices, order tracking, and shipping
Supply Chain Management
Facilitates supplier and customer management, supply chain visibility, and event management
Focused Reading (MIS Major Required)
1. Enterprise resource planning (ERP)—A brief history
2. 13 Common ERP Mistakes and How to Avoid Making Them
3. ERP and Business Process Re-engineering• ERP: The Business Process Re-engineering Dile
mma• To BPR, or not to BPR, that is the question
4. Cloud ERP• What Is Cloud ERP, and How Is It Different from T
raditional Solutions?• Benefits of Cloud ERP Software
ERP History• MRP: focus on cost reporting, materials, manufacturing
– tapes– IBM– 1960~1970
• MRPII: scheduling, procurement
– 1980s
• ERP
– SAP, Peoplesoft, – 1990– Client-server architecture
ERP Common Mistakes• Poor Planning• Not properly vetting ERP vendors• Not understanding or using key features• Understanding the time and resources required• Not having the right people on the team from the start• Not setting priorities• Not investing in training and change management• Underestimating the importance of accurate data• Taking the kitchen sink approach• Not decommissioning legacy applications• Not having an active load testing environment• Ignoring third-party support alternatives• Not having a maintenance strategy
ERP & Business Process Re-engineering
• Take place before ERP system selection• Output of BPR ERP• To be process vs. as is process
• Difference ways to do business globally• Process standardization after acquisition• Legacy systems• Make sure the process lead to higher values