MRP & ERP - I

Embed Size (px)

Citation preview

  • 8/7/2019 MRP & ERP - I

    1/26

    The McGraw-Hill Companies, Inc., 2004

    1

    Materials Requirements

    Planning

  • 8/7/2019 MRP & ERP - I

    2/26

    The McGraw-Hill Companies, Inc., 2004

    2

    Material Requirements Planning (MRP)

    MRP Logic and Product Structure Trees

    Time Fences

    MRP Example

    MRP II and Lot Sizing

    OBJECTIVES

  • 8/7/2019 MRP & ERP - I

    3/26

    The McGraw-Hill Companies, Inc., 2004

    3

    Material Requirements Planning

    Defined

    Materials requirements planning (MRP) is ameans for determining the number of parts,components, and materials needed to produce

    a product MRP provides time scheduling information

    specifying when each of the materials, parts,and components should be ordered orproduced

    Dependent demand drives MRP

    MRP is a software system

  • 8/7/2019 MRP & ERP - I

    4/26

    The McGraw-Hill Companies, Inc., 2004

    4

    Example of MRP Logic and Product

    Structure Tree

    B(4)

    E(1)D(2)

    C(2)

    F(2)D(3)

    A

    Product Structure Tree for Assembly A Lead Times

    A 1 day

    B 2 days

    C 1 day

    D 3 days

    E 4 days

    F 1 day

    Total Unit Demand

    Day 10 50 A

    Day 8 20 B (Spares)

    Day 6 15 D (Spares)

    Given the product structure tree for A and the lead time anddemand information below, provide a materials requirements

    plan that defines the number of units of each component and

    when they will be needed

  • 8/7/2019 MRP & ERP - I

    5/26

    The McGraw-Hill Companies, Inc., 2004

    5

    LT = 1 day

    Day: 1 2 3 4 5 6 7 8 9 10

    A Required

    Order Placement 50

    First, the number of units of A are scheduled

    backwards to allow for their lead time. So, in thematerials requirement plan below, we have to place

    an order for 50 units of A on the 9th day to receive

    them on day 10.

  • 8/7/2019 MRP & ERP - I

    6/26

    The McGraw-Hill Companies, Inc., 2004

    6

    Next, we need to start scheduling the components that make up

    A. In the case of component B we need 4 Bs for each A.

    Since we need 50 As, that means 200 Bs. And again, we back

    the schedule up for the necessary 2 days of lead time.

    D a y : 1 2 3 4 5 6 7 8 9 1 0

    A R e q u i re d 5 0

    O rd e r P la c e m e n t 5 0

    B R e q u i re d 2 0 2 0 0

    O rd e r P la c e m e n t 2 0 2 0 0

    B(4)

    E(1)D(2)

    C(2)

    F(2)D(3)

    A

    SparesLT = 2

    4x50=200

  • 8/7/2019 MRP & ERP - I

    7/26

    Day: 1 2 3 4 5 6 7 8 9 10

    A Required LT=1 Order Placement 50

    B Required 20 200

    LT=2 Order Placement 20 200

    C Required 100

    LT=1 Order Placement 100

    D Required 55 400 300

    LT=3 Order Placement 55 400 300

    E Required 20 200

    LT=4 Order Placement 20 200

    F Required 200

    LT=1 Order Placement 200

    B(4)

    E(1)D(2)

    C(2)

    F(2)D(3)

    A

    40 + 15 spares

    Part D: Day 6

    Finally, repeating the process for all components, we have the

    final materials requirements plan:

    The McGraw-Hill Companies, Inc., 2001

    7

  • 8/7/2019 MRP & ERP - I

    8/26

    The McGraw-Hill Companies, Inc., 2004

    8

    Master Production Schedule (MPS)

    Time-phased plan specifying how many and

    when the firm plans to build each end item

    Aggregate Plan

    (Product Groups)

    MPS

    (Specific End Items)

  • 8/7/2019 MRP & ERP - I

    9/26

    The McGraw-Hill Companies, Inc., 2004

    9

    Types of Time Fences

    Frozen

    No schedule changes allowed within this window

    Moderately Firm

    Specific changes allowed within product groups aslong as parts are available

    Flexible

    Significant variation allowed as long as overall

    capacity requirements remain at the same levels

  • 8/7/2019 MRP & ERP - I

    10/26

    The McGraw-Hill Companies, Inc., 2004

    10

    Example of Time Fences

    8 15 26

    Weeks

    FrozenModerately

    Firm Flexible

    Firm Customer Orders

    Forecast and availablecapacity

    Capacity

    Exhibit 15.5

  • 8/7/2019 MRP & ERP - I

    11/26

  • 8/7/2019 MRP & ERP - I

    12/26

    From Exhibit 15.6

    12

    The McGraw-Hill Companies, Inc., 2004

    Firm orders

    from known

    customers

    Forecasts

    of demand

    from random

    customers

    Aggregate

    product

    plan

    Bill of

    material

    file

    Engineering

    design

    changes

    Inventory

    record file

    Inventory

    transactions

    Master production

    Schedule (MPS)

    Primary reportsSecondary reports

    Planned order schedule for

    inventory and production

    control

    Exception reports

    Planning reports

    Reports for performance

    control

    Material

    planning

    (MRP

    computer

    program)

  • 8/7/2019 MRP & ERP - I

    13/26

    The McGraw-Hill Companies, Inc., 2004

    13

    Bill of Materials (BOM) File

    A Complete Product Description

    Materials

    Parts

    Components Production sequence

    Modular BOM

    Subassemblies Super BOM

    Fractional options

  • 8/7/2019 MRP & ERP - I

    14/26

    The McGraw-Hill Companies, Inc., 2004

    14

    Inventory Records File

    Each inventory item carried as a separate file

    Status according to time buckets

    Pegging

    Identify each parent item that created demand

  • 8/7/2019 MRP & ERP - I

    15/26

    The McGraw-Hill Companies, Inc., 2004

    15

    Primary MRP Reports

    Plannedorders to be released at a future time Orderrelease notices to execute the planned

    orders

    Changes in due dates of open orders due to

    rescheduling

    Cancellations orsuspensions of open orders due

    to cancellation or suspension of orders on the

    master production schedule Inventory status data

  • 8/7/2019 MRP & ERP - I

    16/26

    The McGraw-Hill Companies, Inc., 2004

    16

    Secondary MRP Reports

    Planningreports, for example, forecasting

    inventory requirements over a period of time

    Performance reports used to determine

    agreement between actual and programmed

    usage and costs

    Exception reports used to point out serious

    discrepancies, such as late or overdue orders

  • 8/7/2019 MRP & ERP - I

    17/26

    The McGraw-Hill Companies, Inc., 2004

    17

    Additional MRP Scheduling Terminology

    Gross Requirements

    Scheduled receipts

    Projected available balance

    Net requirements

    Planned order receipt

    Planned order release

  • 8/7/2019 MRP & ERP - I

    18/26

    The McGraw-Hill Companies, Inc., 2004

    18

    MRP Example

    A(2

    ) B(1

    )

    D(5)C(2)

    X

    C(3)

    Item On-Hand Lead Time (Weeks)

    X 50 2

    A 75 3

    B 25 1

    C 10 2

    D 20 2

    Requirements include 95 units (80 firm orders and 15 forecast) of X

    in week 10

  • 8/7/2019 MRP & ERP - I

    19/26

  • 8/7/2019 MRP & ERP - I

    20/26

  • 8/7/2019 MRP & ERP - I

    21/26

  • 8/7/2019 MRP & ERP - I

    22/26

  • 8/7/2019 MRP & ERP - I

    23/26

  • 8/7/2019 MRP & ERP - I

    24/26

    The McGraw-Hill Companies, Inc., 2004

    24

    Closed Loop MRP

    Production Planning

    Master Production Scheduling

    Material Requirements Planning

    Capacity Requirements Planning

    Realistic?No

    Feedback

    Execute:

    Capacity Plans

    Material Plans

    Yes

    Feedback

  • 8/7/2019 MRP & ERP - I

    25/26

    The McGraw-Hill Companies, Inc., 2004

    25

    Manufacturing Resource Planning

    (MRP II)

    Goal: Plan and monitor all resources of a

    manufacturing firm (closed loop):

    manufacturing

    marketing

    finance

    engineering

    Simulate the manufacturing system

  • 8/7/2019 MRP & ERP - I

    26/26

    The McGraw-Hill Companies, Inc., 2004

    26

    Lot Sizing in MRP Programs

    Lot-for-lot (L4L)

    Economic order quantity (EOQ)

    Least total cost (LTC)

    Least unit cost (LUC)

    Which one to use?

    The one that is least costly!