MOVING MODULAR PLATFORM DRILLING RIGS IN BASS STRAIT
PRESENTED BY BRYCE BAKER (RIG MANAGER)
DRILLWELL FORUM MELBOURNE 02 DECEMBER 2010
2
OBJECTIVE
DEVELOPING BEST PRACTICE FOR MOVING RIG 175 IN
BASS STRAIT
STRATERGIES
DESIGN AND SYSTEMS
TACTICS
PROCESS AND PEOPLE
RESULTS
?
3
> Box on Box
> Plug and Play
> Boot Strap Mast
> Appropriate Mechanization
> Integrated Modules
> Pinned Connections
> API Certification
RIG 175 DESIGN
4
RIG 175 DESIGN•Easy installation
•Services and access ways built in
•Weight limited to platform crane capacity (36 MT)
•Built in protection for work at height
•Built in spill prevention
•Third party verification of design and fabrication
•Trial rig up
5
SYSTEMS
> Platform Safety Case.
> Operations Integrity Management System (OIMS)
> Nabors Rig Management System (RMS)
> Site Safety Plan
6
CHALLENGES MOVING RIGS IN BASS STRAIT
•Weather
•Sea State
•Confined work site
•Crane activity
•Logistics
•Sim Ops
•Crew Focus change from drilling to rig move mode
13
PLANNING
> Rig Move on Paper> Rig Move Risk Assessment > Rig Move Plan> Certified Visual Inspections (CVI)> Platform preparation> Dropped Object Management System (DOMS)> Lifting Equipment Management System (LEMS)> Preventative Maintenance
14
TRAINING
Safety leadership
Observation & Intervention
Riggers
Dogman
Scaffolding
Tower Crane
Confined Space Entry
Work at Height
Emergency Response
15
SUPERVISION
> Training in effective leadership and supervision > Increased level of rig supervision
• Offshore rig move coordinator• Deck supervisor position• Onshore rig move coordinator
> Supervision of critical tasks is specified in Rig move plan: • Raising and Lowering the mast;• Removal and Installation of BOP;• Removal and Installation of Drawworks and Crown• Heavy Lifts over well head bay
16
COMMUNICATION
> Pre and Post Hitch Meetings> Daily operations meeting/conference call> Weekly Integrated Management Meeting> Onshore Rig Move Coordinator> Pre Tour Meetings> Weekly Safety Meeting> Stop Cards> Supportive leadership style encourages participation
17
TEAM WORK
> Rig Move Workshop > Job Safety Analysis (JSA) for all tasks> Step Back 5 x 5 during task> Hazard Hunt > Post Job Review – What Went Well/How Could We
Do Better – Documented on the PCAR.> Suggestions and Feedback> Short Service Employee “Red Hat” Program> Reward and Recognition> Offsite Team Building
18
RESULTS• Between Q2 2007 and Q3 2010 rig
175 drilled 34 wells including 4 complex ERD wells and the longest wells in Bass Strait A26a 6,456m MD, M33a – 6,200m MD with the highest rate of oil production in Bass Strait.
• First sub-volcanic completion.• Rig down time < 0.2% • 263 days Hurt Free Record• 3rd on EMDC Global Hurt Free
Leader board• 4 platform to platform rig moves. • 25% - 30% Improvement in rig move
time• Achieved Hurt Free Rig Move 2010
19
CONCLUSION
The continuous improvement model for best practice rig moves in Bass Strait is based on a team approach
that has been able to engage the hearts and minds of the entire team.