51
Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 30 June 2014 Consortium of INCDPM 1 MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175 PHASE II MONTHLY REPORT N0. 38 01 30 June 2014 FINAL VERSION

MONITORING THE ENVIRONMENTAL IMPACT OF THE · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

  • Upload
    voque

  • View
    222

  • Download
    2

Embed Size (px)

Citation preview

Page 1: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

1

MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING

THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER

BETWEEN CALARASI AND BRAILA, KM 375-175 – PHASE II

MONTHLY REPORT N0. 38

01 – 30 June 2014

FINAL VERSION

Page 2: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

2

CARRIED OUT BY:

1. PhD eng. DEÁK György – CS I – project manager

2. Math. Alexandru PETRESCU – CS II

3. Univ. Prof. PhD eng. Iulian Gabriel BÎRSAN

4. PhD eng. Mihai LESNIC – CS I

5. PhD eng. Dan COCIORVA – CS II

6. PhD eng. George POTERAŞ – CS I

7. PhD eng. Ioan BOSOANCĂ

8. biol. SZABO Jozsef

9. PhD eng. Gina GHIŢĂ – CS II

10. Phd chem. Adriana BORŞ – CS II

11. PhD eng. Victor CRISTEA

12. PhD biol. Florica MARINESCU – CS III

13. Maria FETECĂU

14. Cecilia ŞERBAN

15. Luiza FLOREA

16. FRINK Jozsef Pal

17. Marian TUDOR

18. PhD eng. Mihaela ILIE – CS III

19. prof. univ. eng. diplomate Helmut HABERSACK

20. PhD Falka Istvan

21. PhD ZAHARIA Tania

22. ecologist AMBRUS Laszlo

23. prof. PhD eng. Gh Viorel UNGUREANU

24. PhD math. Theodor GHINDĂ – CS I

25. biol. Magdalena CHIRIAC – CS I

26. eng. Marius RAISCHI – CS III

27. biol. Alina TRENTEA – CS III

28. PhD eng. Lucian LASLO – CS III

29. chem. Petra IONESCU – CS III

30. chem. Monica Violeta RADU – CS III

31. ecologist MIHOLCSA Tamas

32. eng. Bianca PETCULESCU – CS III

Page 3: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

3

33. eng. Ana Maria ANGHEL - CSIII

34. chem. Alexandru IVANOV - CS

35. Georgiana TĂNASE - ACS

36. geograph Bogdan URITESCU – ACS

37. eng. Larisa BODEA – ACS

38. PhD eng. Alin Marius BÂDILIŢĂ - CS

39. eng. Georgeta TUDOR, CS

40. fiz. Georgiana GRIGORAŞ, CS III

41. eng. Constantin CÎRSTINOIU, ACS

42. geogr. Alexandru Paul MANOLIU, ACS

43. chem. Carmen MUNTEANU, CS III

44. ecologist Mariana MINCU, CS III

45. PhD eng. Mihaela MÎŢIU, ACS

46. eng. Simona RAISCHI, ACS

47. biol. Ioana SAVIN – ACS

48. biol. Cristina CIMPOERU - ACS

49. ecologist Ecaterina MARCU – ACS

50. ecologist Cornelia LUNGU - ACS

51. eng. Marius OLTEANU, ACS

52. eng. Mădălin SILION, ACS

53. ecologist Tiberius DĂNĂLACHE, ACS

54. eng. Ştefan ZAMFIR, ACS

55. eng. Gabriel BADEA, ACS

56. eng. Alexandru CRISTEA, ACS

57. techn. Sergiu SĂNDICĂ

58. techn. Corneliu VASILE

59. techn. Emil NEAGU

60. techn. Traian PÂRVULESCU

61. techn. Angela GÎDEA

62. techn. Elena BARBU

63. techn. Paula CATANĂ

64. techn. Georgeta MĂNESCU

Page 4: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

4

CONTENT

1. INTRODUCTION ................................................................................................ 6

1.1. Brief presentation of the objectives monitored in the construction phase ................................. 6

1.2. Overview .................................................................................................................... 8

2. STATE OF THE PROGRESS ACTIVITIES ................................................................... 10

2.1. State and progress on each activity / critical point on specific monitoring objectives ................. 10 2.1.1 Critical Point 01 monitoring, Bala branch area and Caragheorghe sand strip ........................ 11

2.1.1.A. Air quality monitoring ........................................................................................ 11 2.1.1.B. Noise monitoring .............................................................................................. 11 2.1.1.C. Soil quality monitoring ....................................................................................... 12 2.1.1.D. Hydromorphological monitoring ............................................................................ 12 2.1.1.E. Water and sediments monitoring .......................................................................... 12 2.1.1.F. Aquatic flora and fauna monitoring ....................................................................... 13 2.1.1.G. Terrestrial flora and fauna monitoring ................................................................... 13 2.1.1.H. Natura 2000 sites monitoring ............................................................................... 14 2.1.1.I. Work site activities monitoring and intervention plan compliance in case of accidental pollution .............................................................................................................................. 14

2.1.2. Critical Point 02 monitoring, Epuraşu Island area (Lebăda) ............................................. 19 2.1.2.A. Air quality monitoring ........................................................................................ 19 2.1.2.B. Noise monitoring .............................................................................................. 19 2.1.2.C. Soil quality monitoring ....................................................................................... 20 2.1.2.D. Hydromorphological monitoring ............................................................................ 20 2.1.2.E. Water and sediments monitoring .......................................................................... 20 2.1.2.F. Aquatic flora and fauna monitoring ....................................................................... 20 2.1.2.G. Terrestrial flora and fauna monitoring ................................................................... 21 2.1.2.H. Natura 2000 sites monitoring ............................................................................... 21 2.1.2.I. Work site activities monitoring and intervention plan compliance in case of accidental pollution .............................................................................................................................. 21

2.1.3. Critical point 10 monitoring, Caleia Branch (Ostrovu Lupu) ............................................ 23 2.1.3.A. Air quality monitoring ........................................................................................ 23 2.1.3.B. Noise monitoring .............................................................................................. 24 2.1.3.C. Soil quality monitoring ....................................................................................... 24 2.1.3.D. Hydrophological monitoring ................................................................................. 24 2.1.3.E. Water and sediments quality monitoring ................................................................. 24 2.1.3.F. Aquatic flora and fauna monitoring ....................................................................... 25 2.1.3.G. Terrestrial flora and fauna monitoring ................................................................... 25 2.1.3.H. Natura 2000 sites monitoring ............................................................................... 25 2.1.3.I. Work site activities monitoring and intervention plan compliance in case of accidental pollution .............................................................................................................................. 26

2.1.4. Monitoring in the critical points 03÷07 ...................................................................... 27 2.1.4.1. Monitoring in the CP 03 (upstream and downstream Seica) ........................................... 27 2.1.4.2. Critical point 04 monitoring/Ceacâru/Fermecatu ...................................................... 28 2.1.4.3. Critical Point CP 07 / Fasolele monitoring ............................................................... 30

2.2. Stage of 3D numerical modeling ..................................................................................... 32 2.2.1. Numerical simulations for Delft3D model aplication improvement, in actual conditions in bottom sill area ............................................................................................................. 32 2.2.2. Simulation with Delft3D model for water flow parameters in critical point 10, in flow conditions from June .................................................................................................................... 36 2.2.3. Completing the data for modeling ............................................................................. 37

3. MEMBERS OF THE EXPERTS’ TEAM ....................................................................... 38

3.1. Members of the experts’ team ....................................................................................... 38

3.2. Experts’ tasks during the project .................................................................................... 38

3.3. Planning the activities for the next month on each phase/activity/critical point ........................ 39

Page 5: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

5

4. TIME SCHEDULE AND BUDGET PROJECT ................................................................ 40

4.1. Time schedule for project implementaion ........................................................................ 40

4.2. Budget and expenses incurred during the reporting period................................................... 46

4.3. Budget and expenses for the next period ......................................................................... 47

6. CONCLUSIONS, RECOMMENDATIONS, WARNINGS ................................................... 48

6. ANNEXES ...................................................................................................... 51

6.1 Relevant correspondence

6.2 Recording bulletins for samples measurement

6.2.1: AIR sampling sheets

6.2.2: NOISE sampling sheets

6.2.3: WATER sampling sheets

6.2.4: SEDIMENTS sampling sheets

6.3 Experts’ activity reports

6.4 Images of activities

6.5 Hydromorphological monitoring

6.6 Reports of analytical results for the period of 1 – 31 May 2014

6.6.1: Reports of analytical results- AIR

6.6.2: Reports of analytical results WATER

6.6.3: Reports of analytical results SEDIMENTS

6.7 Ichthyofauna monitoring

6.7.1: Bathimetric profiles in feeding habitats

6.7.2: Velocities on analized profiles

6.7.3: Sheets for benthos sampling in feeding habitats

Page 6: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

6

1. INTRODUCTION

1.1. Brief presentation of the objectives monitored in the construction phase

I. This report presents the monitoring activities for the period of 01 – 30 June 2014:

A – Air quality

B – Noise

C – Soil

D – Hydromorphology

E – Water quality

F – Aquatic flora and fauna

F. is.- Sturgeon and barbell monitoring

F.i. - Other fish species monitoring

G – Terrestrial flora and fauna

H - Natura 2000 sites monitoring

I – Building site activity and compliance with the intervention plan in case of accidental

pollution

Regarding the construction phase monitoring, the frequencies of the environmental

components are differentiated from the preconstruction period, a synthesis on this regard being

presented in Table 1.

II. 3D numerical modeling

It is noted that with a proper organization and development of the field campaign, a

permanent cooperation has been ensured, between the Coordinator and Partners with a support

from the National Agency for Fisheries and Aquaculture and Border Police.

Page 7: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

7

Table 1.1. Construction phase- monitoring objectives – frequencies with differences in the Critical Points

MONITORING OBJECTIVES

Critical points

Main Critical Points Secondary Critical Points

01 02 10 03A 03B 04A 04B 07

A. AIR M M M Q Q Q Q Q

B. NOISE M M M Q Q Q Q Q

C. SOIL S S S Q Q Q Q Q

D.

H

Y

D

R

O

M

O

R

P

H

O

L

O

G

Y

Water level C C C Q Q Q Q Q

Water velocity QC M M Q Q Q Q Q

Turbidity C C C Q Q Q Q Q

2D bathymetric elevation M M M Q Q Q Q Q

3D bathymetric elevation Q Q Q Not the case

E.

WATER QUALITY M M M S S S S S

SEDIMENTS M M M S S S S S

F.

AQUATIC FLORA July Q Q Q Q Q AQUATIC FAUNA S Q Q Q Q Q

F F. is STURGEONS

AND BARBELL

STURGEONS Two seasons / year

(February - May / August – December) Two seasons / year

(February - May / August – December)

BARBELL One season/year

April- May (breeding season) One season/year

April- May (breeding season)

F. i OTHER FISH SPECIES Anually

(Apr - May, Jul - Sept) Anually

(Apr - May, Jul - Sept)

G.

TERRESTRIAL FLORA Anualy in July Anualy in July

TERRESTRIAL FAUNA/ AVIFAUNĂ Anually

April – June, September- October, January)

Anually April – June, September- October, January)

H. NATURA

2000 SITES

SCI

ICHTYOFAUNA Anually

(Apr - May, Jul - Sept) Anually

(Apr - May, Jul - Sept)

AQUATIC FLORA

July Q Q Q Q Q

AQUATIC FAUNA

S Q Q Q Q Q

TERRESTRIAL FLORA

Annually in July Annually in July

TERRESTRIAL FAUNA

Anually (April – June, September- October,

January)

Anually (April – June, September- October, January)

SPA AVIFAUNĂ Anually

(April – June, September- October, January)

Anually (April – June, September- October, January)

I. BUILDING SITE ACTIVITY M M M Not the case

J. 3D numerical modeling M

NOTE: QC – quasi continuous M- monthly Q – quarterly S – semester C – continuous

Page 8: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

8

1.2. Overview

The elements related to the sampling periods for the objectives monitored are presented in

Table 1.2.

Table 1.2. Construction phase - objectives monitored during the period of 01.06-30.06.2014

Objectives monitored Sampling period /

ongoing activities Campaign

Critical Points

Main Critical Points Secondary Critical Points

01 02 10 03A 03B 04A 04B 07

A. AIR 12, 22,

29.06.2014 C35 YES YES YES YES YES YES YES YES

B. NOISE 12, 22,

29.06.2014 C38 YES YES YES YES YES YES YES YES

C. SOIL - - NO NO NO NO NO NO NO NO

D. HYDROMORPHOLOGY

02-04, 10-13, 18-

20, 23-

26.06.2014

C38 YES YES YES NO NO NO NO NO

E.

WATER QUALITY 26.06.2014

28.06.2014 C38 YES YES YES NO NO NO NO NO

SEDIMENTS 26.06.2014

28.06.2014 C38 YES YES YES NO NO NO NO NO

F.

AQUATIC FLORA - - NO NO NO NO NO NO NO NO

AQUATIC FAUNA - - NO NO NO NO NO NO NO NO

F.is. STURGEONS 01-30.06.2014 C7 YES YES YES YES YES YES YES YES

F.is. BARBELL 01-30.06.2014 C4 YES YES YES YES YES YES YES YES

F.i. OTHER FISH

SPECIES - - NO NO NO NO NO NO NO NO

G. TERRESTRIAL FLORA - - NO NO NO NO NO NO NO NO

TERRESTRIAL FAUNA/ AVIFAUNĂ

- - NO NO NO NO NO NO NO NO

H. NATURA 2000 SITES - - NO NO NO NO NO NO NO NO

I. BUILDING SITE 01-30.06.2014 C38 YES YES YES NO NO NO NO NO

NOTE: YES – samples were taken / activities were conducted in the field NO- no samples taken / no activities conducted in the field

Page 9: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

9

Within 01.06-30.06.2014 the following means of transport have been used, presented in

Table 1.3.

Table 1.3 Means of transportation used within 01.06 – 30.06.2014

Field Transportation means

WATER

trimaran type boat with 25 CP engine

Laguna type boat with 25 CP engine

Lotus type boat with 20 CP engine

RIB boat with 25 CP engine

ZODIAC boat with 25 CP engine in 4 stroke

LAND

vehicles

land vehicles

minibus

auto-laboratory

Page 10: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

10

2. STATE OF THE PROGRESS ACTIVITIES

2.1. State and progress on each activity / critical point on specific monitoring

objectives

The equipments used for sampling/ongoing activities and analysis of samples during 01.06-

30.06.2014 are presented in table 2.1.

Table 2.1 Main used devices

Objectives monitored Sampling equipment Laboratory equipments / ongoing

activities

A. AIR - LECKEL dust sampler - Auto-laboratory - Desaga pump

- Analytical balance KERN 770-14 - Atomic absorption spectrometer with graphite furnace AAS - UNICAM 939

B. NOISE - Sound Level Meter and Microphone, Brüel & Kjær Denmark

C. SOIL No monitoring activity during 01/30 June 2014

D. HYDROMORPHOLOGY

- EchoSounders STRATABOX - portable turbidimeter of VELP SCENTIFICA type - mini ADP SONTEK - monitoring system LB for turbidity and level - monitoring system for flow/velocities - portable turbidimeter HANNA Instruments - ADCP SONTEK River Surveyor R9 - Multiparameter YSI for turbidity and level measurements

- HACH RATIO/RX turbidimeter

E.

WATER QUALITY - Ruttner sampler

- Spectrometer with atomic absorption, with graphite oven, UNICAM 939 type - mercury analyser FIMS type - Spectrometer with atomic absorption VARIAN - Spectrometer CARY BIO 300 U.V.-VIS - GC-MS-VARIAN

SEDIMENTS - Petersen sampler

- drying stove - System of sieving sediment samples - Ethos - microwave digester for sediment - GC-MS-VARIAN - SOLAAR M5 Atomic absorption spectrometer

F.

AQUATIC FLORA No monitoring activity during 01/30 June 2014

AQUATIC FAUNA No monitoring activity during 01/30 June 2014

F.is. STURGEONS AND BARBELL

- Fixed monitoring system DKTB - Floating monitoring system type DKMR-01T - Complex monitoring, alarming and control system type DK-PRB-01U

- Reception station of WR2W - VR100 mobile receptor - Multiparameter YSI

F.i. OTHER FISH SPECIES

Nets and ichtyoplanktonic nets for Alosa species

G.

TERRESTRIAL FLORA No monitoring activity during 01/30 June 2014

TERRESTRIAL FAUNA/ AVIFAUNĂ

No monitoring activity during 01/30 June 2014

H. NATURA 2000 SITES No monitoring activity during 01/30 June 2014

I. BULDING SITE ACTIVITY

- DESAGA pump - Autolaboratory - Sound Level Meter and Microphone, Brüel & Kjær - dust sampler LECKEL

Page 11: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

11

2.1.1 Critical Point 01 monitoring, Bala branch area and Caragheorghe sand strip

2.1.1.A. Air quality monitoring

The activities carried out during the reporting period related to the monitoring of nitrogen

oxides, lead oxides, carbon monoxide, carbon dioxide and suspended particles, are summarized in

Table 2.1.1.A.1.

Table 2.1.1.A.1 Specific objective – air quality monitoring

No. Activities

1. Organizing the measurements campaign (Table 1.2)

2. Air sampling campaign (air samples bulletins - Annex 6.2.1)

3. Laboratory analysis for collected samples

4. Preliminary statistical processing of data measured in field

Table 2.1.1.A.2 presents the number of air samples taken/measurements "in situ" conducted

during 01-30 June 2014.

Table 2.1.1.A.2 Air samples distribution

Type of Critical Point

Critical Point (CP)

Samples for laboratory analysis

Number of “in situ” measurements

Main 01 9 9

Each sampling point has its geographic coordinates. The samples were coded and labelled

according to the encoding instructions. Also, for each sample /measurement a sampling bulletin

was completed, see Annex 6.2.1.

2.1.1.B. Noise monitoring

The activities carried out during this reporting period, related to noise level monitoring,

are summarized in Table 2.1.1.B.1.

Table 2.1.1.B.1 Specific objective – noise monitoring

No. Activities

1. The measurements campaign of noise level monitoring for zero naval traffic/ naval traffic (noise level measurement bulletin - Annex 6.2.2)

2. Primary processing of data obtained from measurements

In this noise level monitoring campaign the measurement results are presented in Table

2.1.1.B.2:

Table 2.1.1.B.2 Noise level monitoring

Type of Critical Point

Critical Point (CP)

No. of measurements

Zero naval traffic Naval traffic

Main 01 9 0

On Turcescu islet have been made 3 out of 9 measurements, another 3 measurements have

Page 12: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

12

been carried out on Danube left bank, where in this period were working to arrange stones for

guiding dam consolidation. In this area there were În zonă se aflau 2 excavators, 2 dredges and a

greifer on a barge. 3 measurements have been made on the Danube right bank, one of them at

construction site organization.

For each sampling point there have been established geographic coordinates which were

then transcalculated in the Stereo'70 projection system. The measurements were coded according

to the encoding instructions. Also, for each noise level measurement a bulletin has been

completed, see Annex 6.2.2.

2.1.1.C. Soil quality monitoring

No monitoring activities during this period.

2.1.1.D. Hydromorphological monitoring

The activities from this reporting period are synthetically presented in Table 2.1.1.D.1: Overall 4 main activities have been carried out:

Single-beam bathymetric measurements, including the monitoring sections from the Specifications

Flow and velocity measurements on monitoring sections

Weekly repeated measurements for flow and velocity on transversal sections near the 5 automatic stations for turbidity and level monitoring

Turbidity and level continuous measurements in the 5 automatic hydrometric stations

Table 2.1.1.D.1 Specific objective: hydromorphological monitoring

No. Activities

1. Single-beam bathymetry

2. Flow and velocity measurements on monitoring sections

3. Weekly repeated measurements for flow and velocity on transversal sections near the automatic stations for turbidity and level monitoring

4. Turbidity and level continuous measurements in the 5 automatic hydrometric stations

2.1.1.E. Water and sediments monitoring

The activities carried out during 01/30.06.2014 related to water and sediment quality, reported to

each critical point are summarized in Table 2.1.1.E.1:

Table 2.1.1.E.1 Specific objective: Water quality and sediments monitoring

No Activities

1. Organizing the 38th water and sediments sampling campaign (Table 1.2)

2. Performing water sampling campaign on cross sections at different depths (water sampling bulletins - Annex 6.2.3)

3. Sediments sampling campaign (sediments sampling bulletins - Annex 6.2.4)

4. Physical-chemical analysis in field for water samples

5. Further physical – chemical laboratory analysis for water samples

6. Further physical – chemical laboratory analysis for sediment samples.

Page 13: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

13

Within this sampling campaign, water and sediments samples were taken, according to table

2.1.1.E.2:

Table 2.1.1.E.2 Water and sediments samples

Type of Critical Points

Critical Point (CP)

Water samples Sediment samples

Main 01 20 8

Each sampling point has its geographical coordinates. The samples have been codified and

labelled according to the encoding instructions. For each sample a bulletin has been completed,

according to Annexes 6.2.3 and 6.2.4.

2.1.1.F. Aquatic flora and fauna monitoring

No monitoring activities during this period.

2.1.1.F.is. Sturgeons and barbell migration monitoring

În June at CP 01 have been performed bathimetrical measurements in order to determine

water velocities in sturgeons’ specific feeding habitats (Borcea branch km 62, Bala branch km 4

and Bala branch km 7), the monitoring systems have been downloaded, obtained data processed

and have been performed maintenance activities for the monitoring systems.

Activities during this reporting period regarding sturgeons’ migration monitoring are

summarized in Table 2.1.1.F.is.1.

Table. 2.1.1.F.is.1 Specific objective: sturgeons and barbell migration monitoring

No. Activities

1. Measurements for water velocities determination in feeding habitats

2. Maintenance for monitoring systems

3. Data downloading from the monitoring systems

4. Processing the data from monitoring activities

2.1.1.F.i. Other fish species monitoring

In June have not been performed any scientific fishing activities for other species. The

research team have been made processing for the data obtained in April – May for Alosa species.

2.1.1.G. Terrestrial flora and fauna monitoring

2.1.1.G.1 Terrestrial flora

No monitoring activities during this period.

2.1.1.G.2 Terrestrial fauna/ Avifauna

No monitoring activities during this period.

Page 14: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

14

2.1.1.H. Natura 2000 sites monitoring

No monitoring activities during this period.

2.1.1.I. Work site activities monitoring and intervention plan compliance in case of

accidental pollution

Monitoring campaign was carried out during 01 – 30 June 2014.

Between 01.06.2014 – 30.06.2014, in working point CP 01- Bala – Turcescu – Caragheorghe

area, have been executed following works:

Dredging in navigable channel from km 342 to km 345, in profiles area P170÷P260 (Figure

2.1.1) – dredged material volume was about 53312 m3;

Figure 2.1.1 – Channel dredging in working point CP 01- Bala – Turcescu - Caragheorghe

Detailed hydrographical mesurements from km 342 to km 345 on dredging works site, for

executed works verification and depths monitoring in working area.

During 01.06.2014 – 30.06.2014, in working point CP 01- Bala, have not been performed any

contruction works in guiding dam and bottom sill area. În figure 2.1.2 is presented the overall

picture of the guiding dam built in Bala branch area – left bank which requires finishing works for

the slope.

Page 15: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

15

Figure 2.1.2 – Guiding dam built in CP 01 area- Bala branch – left bank

Personnel observed on building site in this period (3 persons):

- auxiliary personnel (guardians) – 3.

Personnel usually working at navigable channel dredging in CP 01 area - 35 persons:

- engineer – 3

- naval engineer - 1

- RTE engineer – 1

- dredger chief/dredger – 4

- steerer/captain – 4

- chief mechanic/mechanic/motorist – 10

- Sailor – 8

- Electrician – 4

Equipments at working site in CP 01 Bala area have been:

- Dozers – 1

- Containers - 4

- Cranes 12 t - 1

- Excavator Hitachi – 1

- Excavator Akerman – 1

- Boats – 3

- Tug-boat / Pusher 800 CP - 1

- Crane 16 t – 1

- Floating platform 500 t - 1

- Excavator Graifer - 1

- Floating platform 100 t - 2

- Pontoon - 2

- Crane 10 t – 1

- Crane RDK 30 t - 1

- Barge 500 t - 3

Page 16: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

16

- Pusher 600 CP - 1

- Motor boat 65 CP -1

Equipments used for navigable channel dredging in this period at CP 01 area:

- Maritime barge with cups no. ANR 1756 – 1

- Barge 400 m3 Sendreni 15 – 1

- Station GPS/Sonar – 2 /2

- Duty boat – 2

- Pumping-drilling river dredge no. ANR 1764 - 1

- Barge 200 m3 Tiglina 5 – 1

- Tug-boat 800 CP- 1

During construction site monitoring (01.06.2014 – 30.06.2014) have not been observed any

cases of accidental pollution on site location and at working points.

There is no oil products leaks on soil in the area of fuel deposit (Fig. 2.1.3), the possible

leakages from fuels manipulation are retained in the metallic cuvette of the fuel storage tank.

The wastes are selectively collected in the construction site area, taken then by the

sanitation company and transported towards the nearest wastes deposit. The used oils are

collected in plastic bins, taken by specialised companies for recycling.

Figure 2.1.3 – Fuel storage in the construction organization site, CP 01

Page 17: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

17

Table no. 2.1.1.I.1. Comparative table upon the site monitoring activities in CP 01

No Parameter

36th campaign (01 – 30 April 2014)

37th campaign (01 – 31 May 2014)

38th campaign (01 – 30 June 2014)

Building site organization

Area of works execution

Building site organization

Area of works execution

Building site organization

Area of works execution

1. Executed works

- Launching and ballasting double layer geotextile mattresses Terrafix in profiles P91÷P94 area, in a quantity of: 3472 m2

;

- geotextile mattress ballasting with raw stone assortment 10-50 Kg/piece, in profiles P80÷P85 area, near the bottom sill, in a quantity of: 1196 m3;

- Launching and ballasting double layer geotextile mattresses Terrafix B813 in profiles P94÷P97 area, in a quantity of: 4627 m2;

- sorted raw stone filter, assortment 10-200 Kg/piece, in profiles P82÷P85 area, in a quantity of:1824 m3;

- geotextile mattress ballasting with raw stone assortment 10-50 Kg/piece, in profiles P91÷P107 area, in a quantity of: 4582 m3;

- Launching and ballasting double layer geotextile mattresses Terrafix B813 in profiles P97÷P101 area, in a quantity of: 3463 m2;

- Launching and ballasting double layer geotextile mattresses Terrafix B813 in profiles P104÷P107 area, in a quantity of: 3336 m2;

- geotextile mattress ballasting with raw stone assortment 10-50 Kg/piece, in profiles P51÷P73 area, upstream from the bottom sill, in a quantity of: 4191 m3;

- stone blocks covering, 200-600 Kg/piece pentru digul de dirijare, in profiles P93 ÷ P96 area, in a quantity of: 4877 m3;

- stone blocks covering 200-600 Kg/piece, in profiles P96÷P99 area, in a quantity of 6089 m3;

- stone blocks covering 200-600 Kg/piece, in profiles P99÷P103 area, in a quantity of: 3659 m3;

- detailed hydrographic measurements from km 342 la km 345 on the dredgings works site; -channel dredging in the area of P80 and P190 – 46 503m3 .

- detailed hydrographic measurements from km 342 la km 345 on the dredgings works site; -channel dredging in the area of P170÷P260–

53 312m3.

Page 18: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

18

- stone blocks covering 200-600 Kg/piece, in profiles P103÷P107 area, in a quantity of: 3637 m3;

- stone blocks covering, sortiment 0,5-2 t, in profiles P92 area, downstream from bottom sill, in a quantity of: 785 m3.

- Detailed hydrographic measurements from km 342 - 345 on the dredging works area, for executed works verification;

Dredging the navigable channel in the profiles for P51 ÷ P93, P111 ÷ P145, P155 ÷ P185: 79124m3.

2. Air quality Measurements activities of air quality indicators Sampling code: AER01MD01C33 AER01MD02C33 AER01MS01C33 AER01MS02C33 AER01OT01C33 AER01OT02C33

Measurements activities of air quality indicators Sampling code: AER01MD01C34 AER01MD02C34 AER01MS01C34 AER01MS02C34 AER01OT01C34 AER01OT02C34

Measurements activities of air quality indicators Sampling code: AER01MD01C35 AER01MD02C35 AER01MD03C35 AER01MS01C35 AER01MS02C35 AER01MS03C35 AER01OT01C35 AER01OT02C35 AER01OT03C35

3. Noise level Noise level determinations: samples code: ZGM01MD01C36 ZGM01MD02C36 ZGM01MS01C36 ZGM01MS02C36 ZGM01OT01C36 ZGM01OT02C36

Noise level determinations: samples code:

ZGM01MD01C37 ZGM01MD02C37 ZGM01MS01C37 ZGM01MS02C37 ZGM01OT01C37 ZGM01OT02C37

Noise level determinations: samples code: ZGM01MD01C38 ZGM01MD02C38 ZGM01MD03C38 ZGM01MS01C38 ZGM01MS02C38 ZGM01MS03C38 ZGM01OT01C38 ZGM01OT02C38 ZGM01OT03C38

4. Way of collecting, depositing and evacuation of wastes

220 l metallic barrel for collecting waste oil, placed on tugboats

220 l metallic barrel for collecting waste oil, placed on tugboats

220l metallic barrel for collecting waste oil, placed on tugboats

5 Way of depositing the oil products

There have not been observed leakages of petroleum products in the working areas

There have not been observed leakages of petroleum products in the working areas

There have not been observed leakages of petroleum products in the working areas

6 Way of depositing constructions materials

Stock of materials consist of degraded fascines- 4000 mst, are deposited Orbu Island.

The dragged material is transported with a barge and deposited in the area of km 347+500 Geotextile material type Terrafix 609 deposited on a stockade at building site area.

Stock of materials consist of degraded fascines- 4000 mst, are deposited Orbu Island.

The dragged material is transported with a barge and deposited in the area of km 347+500 Geotextile material deposited on a stockade at building site area.

Stock of materials consist of degraded fascines- 4000 mst, are deposited Orbu Island.

The dragged material is transported with a barge and deposited in the area of km 347+500 Geotextile material deposited on a stockade at building site area.

Page 19: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

19

2.1.2. Critical Point 02 monitoring, Epuraşu Island area (Lebăda)

2.1.2.A. Air quality monitoring

The activities carried out during this reporting period, related to air quality monitoring are

summarized in table 2.1.1.A.1.

Table 2.1.2.A.1 shows the number of air samples taken/“in situ” measurements during 01-30

June 2014.

Table 2.1.2.A.1 Air samplings repartition

Type of Critical Point

Critical Point (CP)

Laboratory analysis samples

Number of measurements “in situ”

Main 02 6 6

Each sampling point has its own geographic coordinates. The samples have been coded and

labelled according to the encoding instructions. Also, for each sample/ measurement a sampling

report has been completed, see Annex 6.2.1.

2.1.2.B. Noise monitoring

The activities carried out during this reporting period, related to noise level monitoring are

similar to those outlined for CP 01 – Table 2.1.1.B.1, the measurements being made according to

Table 2.1.2.B.1.

Table 2.1.2.B.1 Noise level monitoring

Type of critical point Critical Point

(CP)

No. of measurements

Zero naval traffic Intense naval traffic

Main 02 6 0

2 of the 6 measurements were made on Epuraşu island. On the right bank measurements

have been made near some devices of dredge type. Other 2 measurements were made on the left

bank of the Danube.

7 Conformation to the intervention plan in case of accidental pollution

Updating the existing absorbent material stockage on ships in the working points

Updating the existing absorbent material stockage on ships in the working points

Updating the existing absorbent material stockage on ships in the working points

8 Landscape Anthropic landscape Anthropic landscape Anthropic landscape

9 Personnel 60 - construction site personnel (25): engineer , foreman, topometrist,

driver, qualified workers, construction workers, mechanics, additional

personnel; - dredging personnel (35):

engineer, naval engineer, engineer RTE , dredging chief, river

steering/captain, chief mechanic/mechanic/motorist, sailor,

electrician.

38 - construction site personnel (3): auxiliary personnel (guardians); - dredging personnel (35):

engineer, naval engineer, engineer RTE , dredging chief, river

steering/captain, chief mechanic/mechanic/motorist, sailor,

electrician.

38 - construction site personnel (3): auxiliary personnel

(guardians); - dredging personnel (35):

engineer, naval engineer, engineer RTE , dredging chief, river steering/captain, chief

mechanic/mechanic/motorist, sailor, electrician.

10 Additional facilities used at works

No additonal devices No additonal devices No additonal devices

Page 20: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

20

Each sampling point has its own geographic coordinates, trans-calculated in Stereo'70

projection system. The measurements have been coded and labelled according to the encoding

instructions. Also, for each sample/measurement a report has been completed, see Annex 6.2.2.

2.1.2.C. Soil quality monitoring

No monitoring activities.

2.1.2.D. Hydromorphological monitoring

The activities from this reporting period are presented in table 2.1.1.D.2.

Overall 3 main activities have been carried out:

Single-beam bathymetric measurements, including on the monitoring sections from

Specifications

Flow and velocity measurements in different water sections, including the monitoring

sections from Specifications

Turbidity and level continuous measurements in the 2 automatic hydrometric stations

Table 2.1.2.D.2 Specific objective: hydromorphological monitoring

No. Activities

1. Single-beam bathymetry

2. Measurements for velocity and flow on monitoring sections

3. Turbidity and level continuous measurements in the 2 automatic hydrometric stations

2.1.2.E. Water and sediments monitoring

The activities carried out related to water quality, reported to each critical point are

summarized in Table 2.1.1.E.1.

In this sampling campaign the water and sediments samples have been taken according to

table 2.1.2.E.1.

Table 2.1.2.E.1 Water and sediments samples

Type of Critical Points

Critical Point (CP)

Water samples Sediments samples

Main 02 15 6

For each sample, a sampling bulletin was completed, according to Annexes no. 6.2.3 and

6.2.4.

2.1.2.F. Aquatic flora and fauna monitoring

No monitoring activities.

2.1.2.F.is. Sturgeons and barbell migration monitoring

In CP 02 have been downloaded the monitoring systems, data have been processed and

Page 21: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

21

performed maintenance activities for the monitoring systems.

Activities during this reporting period related to sturgeon migration monitoring are

summarized in Table 2.1.2.F.is.1.

Table 2.1.2.F.is.1 Specific objective: sturgeons and barbell migration monitoring

No. Activities

1. Monitoring systems maintenance

2. Data downloading from the monitoring systems

3. Monitoring data processing

2.1.2.F.i. Other fish species monitoring

In June have not been performed any scientific fishing activities for other species. The

research team have been made processing for the data obtained in April – May for Alosa species.

2.1.2.G. Terrestrial flora and fauna monitoring

2.1.2.G.1 Terrestrial flora

No monitoring activities.

2.1.2.G.2 Terrestrial fauna/ Avifauna

No monitoring activities.

2.1.2.H. Natura 2000 sites monitoring

No monitoring activities.

2.1.2.I. Work site activities monitoring and intervention plan compliance

in case of accidental pollution

The monitoring campaign for building site activities in CP02 Epuraşu has been carried out

during 01– 30 June 2014.

Between 01.06.2014 – 30.06.2014 have been made topo-hydrographic measurements in

guiding dam area to verify and follow-up the performed works. În June 2014 have not been

executed any works at submersible guiding dam.

Number of personnel on construction site was 4:

- RTE Engineer -1

- Workers (equipments security) -2

- Topometrist -1

Land and naval equipment on the working site, in June 2014:

- Terex/Fuchs handler- 1

- Floating platform 500 to no.ANR 1421 - 1

- Excavator 33 to Volvo - 1

- Various tools (generators, rewinder) - 3

Page 22: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

22

- Tug-boat150 CP Logic - 1

During the monitoring site activities (01.06.2014 – 30.06.2014) there have not been observed any

cases of accidental pollution on site location and working point.

Figure 2.1.2.I.1 – Preparation for geotextile placement in guiding dam area, CP 02

Table no. 2.1.2.I.1. Comparative table upon the site monitoring activities in CP02

No Parameter

36th campaign (01 – 30 April 2014)

37th campaign (01 – 31 May 2014)

38th campaign (01 – 30 June 2014)

Building site organization

Area of works execution

Building site organization

Area of works execution

Building site organization

Area of works execution

1. Executed works

-topohydrographic measurements in the guiding dam area, verification and follow-up for the executed works

topohydrographic measurements in the guidance dam area for verification and follow-up for the executed works

În May have not been executed works on riverbed at submersible guiding dam – interrupted due to Environment Permit

topohydrographic measurements in the guidance dam area for verification and follow-up for the executed works

În June have not been executed works on riverbed at submersible guiding dam

2. Air quality Determinations of air quality: (samples code: AER02MD01C33 AER02MD02C33 AER02MS01C33 AER02MS02C33 AER02IE01C33 AER02IE02C33

Determinations of air quality: (samples code: AER02MD01C34 AER02MD02C34 AER02MS01C34 AER02MS02C34 AER02IE01C34 AER02IE02C34

Determinations of air quality: (samples code: AER02MD01C35 AER02MD02C35 AER02MS01C35 AER02MS02C35 AER02IE01C35 AER02IE02C35

3. Noise level Noise level determinations: (samples code: ZGM02MS01C36 ZGM02MS02C36 ZGM02MD01C36 ZGM02MD02C36 ZGM02IE01C36 ZGM02IE02C36

Noise level determinations: (samples code: ZGM02MS01C37 ZGM02MS02C37 ZGM02MD01C37 ZGM02MD02C37 ZGM02IE01C37 ZGM02IE02C37

Noise level determinations: (samples code: ZGM02MS01C38 ZGM02MS02C38 ZGM02MD01C38 ZGM02MD02C38 ZGM02IE01C38 ZGM02IE02C38

Page 23: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

23

No Parameter

36th campaign (01 – 30 April 2014)

37th campaign (01 – 31 May 2014)

38th campaign (01 – 30 June 2014)

Building site organization

Area of works execution

Building site organization

Area of works execution

Building site organization

Area of works execution

4. Way of collecting, depositing and evacuation of wastes

The wastes are collected in metallic bins, placed on the floating crane

The wastes are collected in metallic bins, placed on the floating crane

The wastes are collected in metallic bins, placed on the floating crane

5. Way of depositing the oil products

No oil leakages in the working areas

No oil leakages in the working areas

No oil leakages in the working areas

6. Way of depositing constructions materials

Stone is downloaded from barges and placed directly into submersible dam

Stone is downloaded from barges and placed directly into submersible dam

Stone is downloaded from barges and placed directly into submersible dam

7. Conformation to the intervention plan in case of accidental pollution

Was created a stock of absorbent materials for potential oil leakages

Was created a stock of absorbent materials for potential oil leakages

Was created a stock of absorbent materials for potential oil leakages

8. Landscape Minor impact Minor impact Minor impact

9. Personnel 44

4 (RTE engineer, workers (equipments guarding), topometrist -1

4 (RTE engineer, workers (equipments guarding), topometrist -1

10. Additional facilities used at works

Retired: - river barges 1000/1500 to - 2 - floating crane 16 tf 1719/872 - 1

Retired: - Tug-boat 600CP/800 CP -1 - Duty boat - 1 - Floating platform 500 to no.ANR 132 - 1 - Tracked excavator JCB 260LR (LongReach) with 21m arm - 1 - Barge 100 to - 1 - Bedroom pontoon no.ANR 2477 – 1

No devices brought or withdrawn

2.1.3. Critical point 10 monitoring, Caleia Branch (Ostrovu Lupu)

2.1.3.A. Air quality monitoring

The activities carried out during this reporting period, related to air quality monitoring are

summarized in table 2.1.1.A.1.

Table 2.1.3.A.1 shows the number of air samples taken/measurements “in situ” made within

01-30 June 2014.

Table 2.1.3.A.1 Air samples repartition

Type of Critical Points

Critical Point (CP) Laboratory

analysis samples Number of measurements

“in situ”

Main 10 6 6

Each sampling point has its own geographic coordinates. The samples have been coded and

labelled according to the encoding instructions. Also, for each sample/ measurement a sampling

report has been completed, see Annex 6.2.1.

Page 24: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

24

2.1.3.B. Noise monitoring

The activities carried out during this reporting period, related to noise level monitoring are

similar to those presented for CP 01, the measurements being made according to Table 2.1.3.B.1.

Table 2.1.3.B.1 Noise level monitoring

Type of Critical Point

Critical Point (CP) No. of measurements

Zero naval traffic Naval traffic

Main 10 6 0

6 noise measurements at critical point CP10, 2 of these have been made on Ostrovul Lupu ,

other 2 measurements on Danube left bank and at building site. On the right bank of the Danube

have been made also 2 measurements, in this period.

Each sampling point has its own geographic coordinates, trans-calculated in STEREO'70

projection system. The measurements have been coded and labelled according to the encoding

instructions. Also, for each sample a measurement/sampling a report has been completed, see

Annex 6.2.2.

2.1.3.C. Soil quality monitoring

No monitoring activities in this period.

2.1.3.D. Hydrophological monitoring

The activities from this reporting period are presented in 2.1.3.D.1.

Overall 3 main activities have been carried out.

Single-beam bathymetric measurements on the monitoring sections from the

Specifications

Flow and velocity measurements in various water sections, including on the

monitoring sections from the Specifications

Turbidity and level continuous measurements in the 3 automatic hydrometric

stations.

Table 2.1.3.D.1 Specific objective: hydromorphological monitoring

No Activities

1. Single - beam bathymetry

2. Flow and velocity measurements on the transversal monitoring sections

3. Turbidity and level continuous measurements in the 3 automatic hydrometric stations

2.1.3.E. Water and sediments quality monitoring

The activities carried out in the reporting period, regarding water and sediments quality,

reported at this critical point are those presented in Table 2.1.1.E.1.

In this sampling campaign water and sediment samples have been collected as presented in

Table 2.1.3.E.1.

Page 25: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

25

Table 2.1.3.E.1 Water and sediment samples

Type of Critical point

Critical Point (CP) Water samples Sediment samples

Main 10 15 6

For each sample a sampling bulletin has been completed, according to Annexes 6.2.3 and 6.2.4.

2.1.3.F. Aquatic flora and fauna monitoring

No monitoring activities in this period.

2.1.3.F.is. Sturgeons and barbell migration monitoring

În June at CP 10 have been performed bathimetrical measurements in order to determine

water velocities in sturgeons’ specific feeding habitats and collected substrate samples in order to

determine the benthic fauna composition in the following points: Danube km 184, Danube km 186,

Danube km 195, Danube km 198, Caleia branch km 9, Caleia branch km 1, Cravia branch and Vâlciu

branch. There were also downloaded the monitoring systems, data processed and maintenance

activities have been performed for the monitoring systems.

Activities during this reporting period regarding the sturgeon migration monitoring are

summarized in Table 2.1.3.F.is.1.

Table 2.1.3.F.is.1 Specific objective: Sturgeons and barbell migration monitoring

No. Activities

1. Measurements for velocities determination in feeding habitats

2. Benthos sampling in feeding habitats

3. Maintenance of the monitoring systems

4. Data downloading from the monitoring systems

5. Processing of the monitoring data

2.1.3.F.i. Other fish species monitoring

In June have not been performed any scientific fishing activities for other species. The

research team have been made processing for the data obtained in April – May for Alosa species.

2.1.3.G. Terrestrial flora and fauna monitoring

2.1.3.G.1 Terrestrial flora

No monitoring activities in this period.

2.1.3.G.2 Terrestrial fauna/ Avifauna

No monitoring activities in this period.

2.1.3.H. Natura 2000 sites monitoring

No monitoring activities in this period.

Page 26: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

26

2.1.3.I. Work site activities monitoring and intervention plan compliance in case of

accidental pollution

Monitoring campaign for construction site activities in CP10 Ostrovu Lupu have been

conducted during 01.06.2014 – 30.06.2014.

Between 01.06.2014 – 30.06.2014.have not been executed any construction works.

Personnel and equipments existent in working point CP 10 area, in May were demobilized.

Table no. 2.1.3.I.1. Comparative table upon the site monitoring activities in CP10

No. Parameter

36th campaign (01 – 30 April 2014)

37th campaign (01 – 31 May 2014)

38th campaign (01 – 30 June 2014)

Building site organization

Area of works execution

Building site organization

Area of works execution

Building site organization

Area of works execution

1. Executed works

2. Air quality Determinations of air quality indicators (samples code AER10MS01C33 AER10MS02C33 AER10MD01C33 AER10MD02C33 AER10IL01C33 AER10IL02C33

Determinations of air quality indicators (samples code AER10MS01C34 AER10MS02C34 AER10MD01C34 AER10MD02C34 AER10IL01C34 AER10IL02C34)

Determinations of air quality indicators (samples code AER10MS01C35 AER10MS02C35 AER10MD01C35 AER10MD02C35 AER10IL01C35 AER10IL02C35)

3. Noise level Determinations of noise indicators (samples code: ZGM10MS01C36 ZGM10MS02C36 ZGM10MD01C36 ZGM10MD02C36 ZGM10IL01C36 ZGM10IL02C36

Determinations of noise indicators (samples code: ZGM10MS01C37 ZGM10MS02C37 ZGM10MD01C37 ZGM10MD02C37 ZGM10IL01C37 ZGM10IL02C37)

Determinations of noise indicators (samples code: ZGM10MS01C38 ZGM10MS02C38 ZGM10MD01C38 ZGM10MD02C38 ZGM10IL01C38 ZGM10IL02C38)

4. Way of collecting, depositing and evacuation of wastes

Waste collection bins

Waste collection bins

Waste collection bins

5. Way of depositing the oil products

There have not been observed any nonconformities

There have not been observed any nonconformities

There have not been observed any nonconformities

6. Way of depositing construction materials

7. Conformation to the intervention plan in case of accidental pollution

8. Landscape Anthropic landscape Anthropic landscape Anthropic landscape 9. Personnel Demobilized personnel Demobilized personnel Demobilized personnel

Page 27: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

27

2.1.4. Monitoring in the critical points 03÷07

2.1.4.1. Monitoring in the CP 03 (upstream and downstream Seica)

2.1.4.1.A. Air quality monitoring

Activities performed during this reporting period, regarding air quality, are presented in

Table 2.1.1.A.1.

În Table 2.1.4.1.A.1 is presented the air samples collected “in situ” between 01-30 June

2014.

Table 2.1.4.1.A.1. Air samples repartition

Critical point type Critical point

(CP) Samples for laboratory

analysis Number of “in situ”

measurements

Secondary 03A and 03B 4 4

For each sampling point has been established geographic coordinates. Samples have been

coded and labelled according to the encoding instructions. Also, for each sample/measurement a

report has been completed, see Annex 6.2.1.

2.1.4.1.B. Noise level monitoring

Activities performed during this reporting period, regarding noise level monitoring in this

secondary critical points are identical with those presented in Table 2.1.1.B.1.

In this noise monitoring campaign have been performed measurements as presented in Table

2.1.4.1.B.1:

Table 2.1.4.1.B.1.Noise level monitoring

Critical point type Critical point

(CP)

No. of measurements

zero naval traffic intense naval traffic

Secondary 03A 2 0

03B 2 0

Each sampling point has its own geographic coordinates, trans-calculated in STEREO'70

projection system. The measurements have been coded according to the encoding instructions.

Also, for each noise level measurement a report has been completed, see Annex 6.2.2.

2.1.4.1.C. Soil quality monitoring

No monitoring activities.

2.1.4.1.D. Hydromorphological monitoring

No monitoring activity.

2.1.4.1.E. Water and sediments quality monitoring

No monitoring activity.

Page 28: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

28

2.1.4.1.F. Aquatic flora and fauna monitoring

No monitoring activities.

2.1.4.1.F.is. Sturgeons and barbell migration monitoring

În June in critical point CP 03 have been monitored the sturgeons and barbell migration by

downloading, processing and correlating the data from monitoring systems fixed on Danube sector

between km 347 - km 240.

2.1.4.1.F.i. Other fish species monitoring

In June have not been performed any scientific fishing activities for other species. The

research team have been made processing for the data obtained in April – May for Alosa species.

2.1.4.1.G. Terrestrial flora and fauna monitoring

2.1.4.1.G.1 Terrestrial flora

No monitoring activities.

2.1.4.1.G.2 Terrestrial fauna / Avifauna

No monitoring activities.

2.1.4.1.H. Natura 2000 sites monitoring

No monitoring activities.

2.1.4.1.I. Work site activities monitoring and intervention plan

compliance in case of accidental pollution

Because the hydrotechnical works have not started, was not necessary construction site

activity monitoring.

2.1.4.2. Critical point 04 monitoring/Ceacâru/Fermecatu

2.1.4.2.A. Air quality monitoring

Activities performed during this reporting period, regarding air quality are summarized in

Table 2.1.1.A.1.

In Table 2.1.4.2.A.1. is presented the number of air samples collected “in situ” during 01-30

June 2014.

Table 2.1.4.2.A.1. Air samples repartition

Critical point type Critical point

(CP) Samples for laboratory

analysis Number of “in situ”

measurements

Secondary 04A and 04B 4 4

For each sampling point has been established geographic coordinates. Samples have been

coded and labelled according to the encoding instructions. Also, for each sample/measurement a

Page 29: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

29

report has been completed, see Annex 6.2.1.

2.1.4.2.B. Noise level monitoring

Activities performed during this reporting period, regarding noise level monitoring in this

secondary critical points are identical with those presented in Table 2.1.1.B.1.

In this noise monitoring campaign have been performed measurements as presented in Table

2.1.4.2.B.1, bellow:

Table 2.1.4.2.B.1. Noise level monitoring

Critical point type Critical point

(CP)

No. of measurements

zero naval traffic intense naval traffic

Secondary 04A 2 0

04B 2 0

Each sampling point has its own geographic coordinates, trans-calculated in STEREO’70

projection system. The measurements have been coded according to the encoding instructions.

Also, for each measurement a report has been completed, see Annex 6.2.2.

2.1.4.2.C. Soil quality monitoring

No monitoring activities.

2.1.4.2.D. Hydromorphological monitoring

No monitoring activities.

2.1.4.2.E. Water and sediments quality monitoring

No monitoring activities.

2.1.4.2.F. Aquatic flora and fauna monitoring

No monitoring activities.

2.1.4.2.F.is. Sturgeons and barbell migration monitoring

In June, in critical point CP 04 have been monitored the sturgeons and barbell migration by

downloading, processing and correlating the data from the monitoring systems fixed on Danube

sector between km 347 - km 240.

2.1.4.2.F.i. Other fish species monitoring

For June have not been performed any scientific fishing activities for other species. The

research team have been made processing for the data obtained in April – May for Alosa species.

Page 30: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

30

2.1.4.2.G. Terrestrial flora and fauna monitoring

2.1.4.2.G.1 Terrestrial flora

No monitoring activities.

2.1.4.2.G.2 Terrestrial fauna/Avifauna

No monitoring activities.

2.1.4.2.H. Natura 2000 monitoring sites

No monitoring activities.

2.1.4.2.I. Monitoring the building site activities and the compliance

with the intervention plan in case of accidental pollution

The monitoring of the building site was not necessary for this period of time because the

hydrotechnical works have not been started.

2.1.4.3. Critical Point CP 07 / Fasolele monitoring

2.1.4.3.A. Air quality monitoring

Activities performed during this reporting period, regarding air quality are summarized in

Table 2.1.1.A.1.

In Table 2.1.4.3.A.1. is presented the number of air samples collected “in situ” during 01-30

June 2014.

Table 2.1.4.3.A.1. Air samples repartition

Critical point type Critical point

(CP) Samples for laboratory

analysis Number of “in situ”

measurements

Secondary 07 2 2

Each sampling point has its own geographic coordinates, trans-calculated in STEREO’70

projection system. The measurements have been coded according to the encoding instructions.

Also, for each measurement a report has been completed, see Annex 6.2.1.

2.1.4.3.B. Noise level monitoring

Activities performed during this reporting period, regarding noise level monitoring in this

secondary critical point are identical with those presented in Table 2.1.1.B.1.

In this noise monitoring campaign have been performed measurements as presented in Table

2.1.4.3.B.1:

Tablel 2.1.4.3.B.1.Noise level monitoring

Critical point type Critical point

(CP)

No. of measurements

zero naval traffic intense naval traffic

Secondary 07 2 0

Page 31: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

31

Each sampling point has its own geographic coordinates, trans-calculated in STEREO’70

projection system. The measurements have been coded according to the encoding instructions.

Also, for each measurement a report has been completed, see Annex 6.2.2.

2.1.4.3.C. Soil quality monitoring

No monitoring activities.

2.1.4.3.D. Hydromorphological monitoring

No monitoring activities.

2.1.4.3.E. Water and sediments quality monitoring

No monitoring activities.

2.1.4.3.F. Aquatic flora and fauna monitoring

No monitoring activities.

2.1.4.3.F.is. Sturgeons and barbell migration monitoring

În June in CP07 have been monitored the sturgeons and barbell migration by downloading,

processing and correlating the data from the monitoring systems fixed on Old Danube sector

between km 347 - km 240.

2.1.4.3.F.i. Other fish species monitoring

In June have not been performed any scientific fishing activities for other species. The

research team have been made processing for the data obtained in April – May for Alosa species.

2.1.4.3.G. Terrestrial flora and fauna monitoring

2.1.4.3.G.1 Terrestrial flora

No monitoring activities.

2.1.4.3.G.2 Terrestrial fauna / Avifauna

No monitoring activities.

2.1.4.3.H. Natura 2000 sites monitoring

No monitoring activities.

2.1.4.3.I. Work site activities monitoring and intervention

compliance plan in case of accidental pollution

Because there have not been conducted any hydrotechnical works during this period, the

monitoring of the construction site activity was not necessary.

Page 32: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

32

2.2. Stage of 3D numerical modeling

Modeling activities have continued to establish ways to improve the application of Delft3D

model by local adjustments in the bottom sill area, given the measured data sets. The conducted

numerical simulations aimed to establish the necessary elements for the development and

recalibration of Delft3D model for current conditions, with a better substantiation based on

measurements from the period from autumn 2013 until the first half of 2014.

Calculations were performed with Delft3D model regarding the water flow parameters at

critical point 10, based on data from June. Completion of datasets for modeling continued by

processing the results of measurements carried out in June conditions.

2.2.1. Numerical simulations for Delft3D model aplication improvement, in actual

conditions in bottom sill area

An important part of the bottom sill effect on water flow parameters result using

calculation methods applied within Delft3D model and the additional structure option has a role of

completing the calculation of these effects.

Bottom sill effect on the water level was calculated with different Delft3D models and the

results were analyzed based on measured data sets. Simulations were conducted for local section

of the first part of Bala branch and used various vertical discretizations.

Measured datasets based on which the numerical simulations results were analyzed, refers

to situations with relatively low flows to an average, over 2500 m3/s Bala branch and below 4000

m3/s.

For data regarding the flows measured in March (situations marked with a and b) were used

recent data from May regarding riverbed configuration on local sector near the bottom sill. For

situations from previous months, with flow rates from the end of 2013 and beginning of 2014

(situations marked with 1, 2, 3, 4, 5) has been used bathymetric data from December 2013.

Simulations carried out with Delft3D models sigma type, without structures option, shows

that in order to achieve more accurate results on water level differences between the ends of the

sector, it would be useful a very fine discretization.

With the structures option at the bottom sill and in old section, a usual Delft3D model

sigma type can be locally adjusted so as to provide better results regarding water levels. This is

shown by the results of simulations for the situations in March (a and b), in addition to the results

presented above for other studied cases. It is found that with finer vertical discretization and at

riverbed level (which however requires larger memory resources and increase the duration of

calculation), the necessary adjustment of the model through structures option can be reduced.

This adjustment remains necessary to obtain calculated levels upstream and downstream near

those highlighted by measurements. Otherwise, there is a need for other local changes in the

model in order to obtain adequate levels.

Page 33: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

33

Figure 2.2.1 – Relative differences of water levels in the sector with bottom sill at Bala, results for relatively low flow with Delft3D models sigma type, with different vertical discretizations, without structures option

Figura 2.2.2 – Relative differences between the water levels at the ends of sector with bottom sill on

Bala branch, results at average flows with Delft3D model sigma type, with structures option at the sill and old section

Placing the structures in slightly different positions within the grid has a very little

influence on the results of water levels upstream and downstream from the bottom sill.

Considering that for the riverbed roughness representation may occur changes, in order to

make local adjustments of the model, have been taken into account also different roughness

values on the analyzed section. It is found that the effects of usual roughness modification are

Page 34: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

34

practically separate from those of structures option.

Numerical simulations performed with Delft3D models of z type, with horizontal layers,

without structures option, revealed that in order to get more accurate results regarding water

levels would be useful a finer discretization.

Figure 2.2.3 - Relative differences between the water levels at the ends of sector with bottom sill on Bala branch, results at a relatively low flow of Delft3D model of z type with different vertical disctretizations,

without structures option

Using additional option of structures at the bottom sill and at old section, the results show

that an usual Delft3D model of z type can be adjusted locally in order to provide more accurate

results on water levels in different situation.

Page 35: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

35

Figure 2.2.4 - Relative differences between the water levels at the ends of sector with bottom sill on Bala

branch, results at relatively low to medium flows, of Delft3D models of z type with different vertical discretizations, with structures option at bottom sill and in old section

The results of Z type non-hydrostatic models, with different vertical discretizations show,

for a relatively low water flow, differences in water levels at the ends of the sector that are

similar with those obtained with Z hydrostatic models.

Figura 2.2.5 - Relative differences between the water levels at the ends of sector with bottom sill on Bala

branch, results at relatively low to medium flows, of Delft3D models of z type non-hydrostatic with different vertical discretizations, without structures option

Page 36: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

36

2.2.2. Simulation with Delft3D model for water flow parameters in critical

point 10, in flow conditions from June

Simultation results with Delft3D model have indicated a flow percentage value on Danube

slightly lower than flow percentage on Caleia branch, the two values being relatively close.

This situation is similar to those previously observed, showing that the works performed at

the critical point 10 had significant effects in terms of flow distribution balancing on Danube

compared to Caleia branch.

Velocities distributions obtained by numerical simulation in critical point 10 area, upstream

from the entrance on Danube sector near Caleia branch, indicates values usually found on other

sectors of the Danube.

The distribution of calculated velocities in a section upstream from Caleia branch highlights

the effects due to water flow towards the two sides of the island and respectively the flow

influence on Valciu branch. The values distribution is similar to that obtained based on velocities

and flow measurement through a very close section. The measured values contain also fluctuations

due to water flow turbulence.

Figure 2.2.6 – Velocities distribution in a cross-section on Danube at critical point 10, upstream from Caleia branch

Figure 2.2.7 – Velocities distribution in a cross-section on Danube at critical point 10, upstream from Caleia

branch, representation based on measured data

Page 37: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

37

2.2.3. Completing the data for modeling

Processing activities for data measured on Danube and preparing the data sets and files in

a usable form for modeling have included the following:

Preparing the data for each section, regarding flow and velocity distributions

measured in main critical points areas.

Preparing the data sets for measured cross-sections representation and those

regarding bathimetric measurements on various trails for the riverbed.

Preparing the data sets for water flow and level in main critical points areas.

These activities have been performed based on analysis of the data measured by INCDPM, in

correlation with daily hydrological data.

Page 38: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

38

3. MEMBERS OF THE EXPERTS’ TEAM

3.1. Members of the experts’ team

Team’s members who carried out activities in the reporting period and the number of days

worked by each expert are schematically presented in Table 3.1.

Table 3.1. Members of the experts’ team

No. Experts Names of experts Number of working

days

1. Project manager Deák György 12

2. Chemist 1 Ghiţă Gina 6

3. Chemist 2 Borş Adriana 6

4. Ichthyologist 1 Cristea Victor 4

5. Ichthyologist 2 Falka Istvan 3

6. Hydrology Poteraş George 12

7. Hydraulic sedimentology Ungureanu Gh Viorel 15

8. Phytoplankton and aquatic macrophytes Marinescu Florica 0

9. Zooplankton Fetecău Maria 0

10. Terrestrial invertebrates Şerban Cecilia 0

11. Aquatic macroinvertebrates Florea Luiza 0

12. Terrestrial flora and vegetation Frink Jozsef Pal 0

13. Ornithologist 1 Jozsef Szabo 0

14. Ecologist 1 Ambrus Laszlo 6

15. Ecologist 2 Zaharia Tania 0

16. Assessor Tudor Marian 10

17. Modeling Helmut Habersack

3.2. Experts’ tasks during the project

The tasks accomplished by experts on each phase/activity/critical point are presented in

Experts’ Activity Reports (Annex 6.3).

Page 39: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

39

3.3. Planning the activities for the next month on each

phase/activity/critical point

The monitoring activities for the period of 01 – 31 July 2014 are synthetically presented in

the table 3.4.

Table 3.4. Activities for the period of 01.07-31.07.2014

No. ACTIVITIES

Critical points

Main critical points

Secondary critical points

01 02 10 03A 03B 04A 04B 07

1. Further campaign of measurements, field observations (where is necessary)

YES YES YES YES YES YES YES YES

2. Processing and interpretation of field and laboratory data (where is necessary)

YES YES YES YES YES YES YES YES

3. Monthly report preparation YES YES YES YES YES YES YES YES

Page 40: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

4. TIME SCHEDULE AND BUDGET PROJECT

4.1. Time schedule for project implementaion

Page 41: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

Page 42: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

Page 43: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

Page 44: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

Page 45: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

Page 46: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

46

4.2. Budget and expenses incurred during the reporting period

Justifying calculation for 01 – 31 June 2014

Page 47: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

47

4.3. Budget and expenses for the next period

Estimative calculation for 01 – 31 July 2014

Page 48: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

48

6. CONCLUSIONS, RECOMMENDATIONS, WARNINGS

5.1 This Monthly Report reflects the monitoring activities in June 2014.

5.2 For the specific monitoring objectives within this phase, the Provider respects the field and

laboratory activities, logistics and infrastructure be made according to the graphics and

stipulations mentioned in the Specifications.

5.3 Taking into consideration the importance of the construction works that take place on

Danube, on the section between Calarasi and Braila, the Consortium recommends further

actions on biodiversity monitoring, with the frequency related with the post-construction

stage, up to end of the project, in order to ensure an informational volume, with a high

confidence level, to allow if necessary, the development of preventive solutions.

5.4 ADCP measurements performed in June in Bala branch area confirmed the phenomenon of

erosion pit expansion, developed behind the bottom sill, to the right bank (phenomenon

shown by the bathymetric monitorings in previous months and especially by multi-beam

measurements made in May).

Irregular geometry of the riverbed and bottom sill leads to the occurrence of strong vortices

that cause problems to navigation in bottom sill area. At the same time, ADCP measurements

in the bottom sill area highlight the high water velocities.

5.5 Regarding sturgeons situation, we specify that during May were recorded three starry

sturgeon specimens that swim against the current over the new bottom sill built on Bala

branch. So far, our researches have not noticed problems regarding migration or for the

possibility to swim over the hydrotechnical construction.

5.6 Bala branch medium flows calculated at the time of passing of the three specimens of starry

sturgeon were:

- 5300 m3/s on 18.05.2014, for starry sturgeon with code 7S47;

- 5650 m3/s on 20.05.2014, for starry sturgeon with code 7S43;

- 5780 m3/s on 26.06.2014, for starry sturgeon with code 7S22bis.

Figures bellow presents migration maps for those 3 starry sturgeons:

Page 49: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

49

Page 50: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

50

Page 51: MONITORING THE ENVIRONMENTAL IMPACT OF THE  · PDF fileBETWEEN CALARASI AND BRAILA, ... Marian TUDOR 18. PhD eng. Mihaela ILIE – CS III ... Alexandru Paul MANOLIU, ACS

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, km 375-175 PHASE II MONTHLY REPORT No 38: 1 – 30 June 2014

Consortium of INCDPM

51

6. ANNEXES

6.1 Relevant correspondence

6.2 Recording bulletins for samples measurement

6.2.1: AIR sampling sheets

6.2.2: NOISE sampling sheets

6.2.3: WATER sampling sheets

6.2.4: SEDIMENTS sampling sheets

6.3 Experts’ activity reports

6.4 Images of activities

6.5 Hydromorphological monitoring

6.6 Reports of analytical results for the period of 1 – 30 May 2014

6.6.1: Reports of analytical results- AIR

6.6.2: Reports of analytical results WATER

6.6.3: Reports of analytical results SEDIMENTS

6.7 Ichthyofauna monitoring

6.7.1: Bathimetric profiles in feeding habitats

6.7.1: Velocities on analized profiles

6.7.2: Sheets for benthos sampling in feeding habitats