Upload
harriet-lester
View
224
Download
4
Tags:
Embed Size (px)
Citation preview
Miscellaneous
CHEN 4470 – Process Design Practice
Dr. Mario Richard EdenDepartment of Chemical Engineering
Auburn University
Lecture No. 17 – Equipment Sizing, Economics and Pinch Analysis
March 7, 2013
• General Rule of Thumb– Based on discussions with industrial design
engineers
– Each major piece of equipment results in approximately $1,000,000 in capital investment (including installation, engineering time, instrumentation etc. etc.)
– Thus for a plant with a reactor and two distillation columns, the typical price will be around $3,000,000
– Remember, that this is “order of magnitude” estimation
Process Economics
• Distillation Columns– Required data is column diameter and height– Height is found from tray spacing specification
Equipment Sizing 1:4
Remember that the first and last stage are the condenser and
reboiler, respectively.
• Distillation Columns (Continued)– If identified diameter is beyond the curves found
in P&T, assume (for pricing purposes) that the separation is performed in NC columns in parallel all with the same specifications.
– The number of columns required should be based on equal distribution of the cross-sectional area NOT the diameter:
Equipment Sizing 2:4
maxAspen P&T
2 2 2Aspen
2 2 2P&T
2Aspen
2P&T
D 20ft , D 5ft Intuitive solution NC = 4 columns
A (20ft) 400ft 100ft4 4
A (5ft) 25ft 6.25ft4 4
A 100ftNC 16 columns
A 6.25ft
• Heat Exchangers– Required information is usually the heat transfer
area, apart from furnaces and fired heaters, which may be estimated based on the duty.
– Overall heat transfer coefficients can be found in P&T (p. 663 in 5th ed.). Assume an average value.
– Assume inlet and outlet temperatures for utility stream. Sample calculations given P&T p. 693.
Equipment Sizing 3:4
0 log meanQ U A T Q: Provided by Aspen
U: Found in P&T
ΔT: Calculated after assuming temps.
• Reactors and Vessels– Required information is usually the reactor
volume along with the amount of catalyst.– Both require detailed kinetic expressions
– Can also be determined from residence time
– When pricing in P&T remember the rule of thumb for major pieces of equipment, i.e. the reactor will not cost $50,000 if the distillation columns cost $1,000,000
Equipment Sizing 4:4
R flowV V Gas phase catalytic reactions = Fast
Order of magnitude would be: seconds range
ex
iR i0
i0
dXV F
( r )
• Units to Include– Heaters, coolers and reactors– Aspen will provide supply and target
temperatures as well as enthalpy change for each hot and cold stream
– Remember that a hot stream in pinch terminology will actually be TWO streams in Aspen
Pinch Analysis 1:5
Supply temp
Target temp
ΔH
Integration of streams should be
done using the HeatX model
B1
1
2
3
4
• Identifying the CP values (No phase change)– The heat capacity (CP) of a stream that does
NOT undergo any phase changes is readily calculated from the information provided by Aspen
Pinch Analysis 2:5
Ts Tt
Q
CP = Q/T
• Identifying the CP values (phase change)– Dashed line represents approximation if the duty
of the exchanger is averaged over the temperature range.
– Quality of approximation depends on the relative values of CPL, CPV and Hvap
Pinch Analysis 3:5
T
H
TT
TS
TB
HvapCPL * T CPV * T
• Approximation
Pinch Analysis 4:5
For mixtures with very different boiling points of the constituents the outlet temperatures in exchangers 1 and 2 will be quite different, but it will still give a better approximation than just an average over the entire temperature range.
Liquid @ Ts Vapor @ Tt
Q
Liquid @ Ts Liquid @ Tb
Q1Vapor @ Tb Vapor @ Tt
Q2 Q3
Can be specified in Aspen as
having an outlet vapor fraction of
0.001
Can be specified in Aspen as
having an outlet liquid fraction of
0.001
Specify outlet temperature at Tt
• Units NOT to Include– Distillation columns and flash drums
– Due to dynamic implications, distillation columns should not be directly integrated with the utility system
– Evaluate all columns together in tabular form with duties and temperature levels
– If there is a condenser with a temperature higher than a reboiler in another column, then those two are candidates for integration.
Pinch Analysis 5:5
• ASPEN Help File– References for equipment such as
scrubbers/absorbers
General Comment
• Next Lecture – March 19– Process risk assessment and inherently safe
design
Other Business