70
Page 1 of 70 (236 th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 1 of 70 Minutes of the 236 th meeting of the State Level Expert Appraisal Committee held on 29/04/2015 at Committee Room, Gujarat Pollution Control Board, Gandhinagar. The 236 th meeting of the State Level Expert Appraisal Committee (SEAC) was held on 29 th April, 2015 at Committee Room, Gujarat Pollution Control Board, Gandhinagar. Following members attended the meeting: 1. Shri T. P. Singh, Chairman, SEAC. 2. Shri V. C. Soni, Member, SEAC. 3. Dr. Nikhil Desai, Member, SEAC. 4. Dr. V. K. Jain. Member, SEAC. 5. Dr. Mayuri Pandya, Member, SEAC. 6. Shri Natarajan Pratap, Member, SEAC. 7. Shri V.N.Patel, Member, SEAC. 8. Shri R. J. Shah, Member, SEAC. 9. Shri K. C. Mistry, Secretary, SEAC. The agenda of TOR/Scoping/Category 8 (a) cases, appraisal cases, EC amendment cases, Reconsideration case was taken up. Six (6) cases of TOR/Scoping/Category 8 (a), twelve (12) appraisal cases and five (5) Reconsideration cases were taken up. The applicants made presentations on the activities to be carried out along with other details furnished in the Form-1 / Form-1A, EIA report and other reports. 1. Causeway Pharma Plot no:331/1 GIDC Chitra, Dist,: Bhavnagar Appraisal Project / Activity No.: 5(f) Project status: Expansion Chronology of EC Process: This project proposed by M/s: Causeway Pharma (herein after Project Proponent – PP) has submitted Application vide their letter dated 14/08/2013. This project was considered in the meeting of the SEAC held on 24/06/2014. The project proponent requested for categorizing the project as B2 and to exempt them from carrying out detailed EIA study which was considered by the committee and the additional information was sought for appraisal of the project. The project proponent submitted the additional information vide their letter dated 12/12/2014.

Minutes of the 236th meeting of the State Level Expert Appraisal

Embed Size (px)

Citation preview

Page 1: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 1 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 1 of 70

Minutes of the 236th meeting of the State Level Expert Appraisal Committee held on 29/04/2015 at Committee Room, Gujarat Pollution Control Board, Gandhinagar.

The 236th meeting of the State Level Expert Appraisal Committee (SEAC) was held on 29th

April, 2015 at Committee Room, Gujarat Pollution Control Board, Gandhinagar. Following

members attended the meeting:

1. Shri T. P. Singh, Chairman, SEAC.

2. Shri V. C. Soni, Member, SEAC.

3. Dr. Nikhil Desai, Member, SEAC.

4. Dr. V. K. Jain. Member, SEAC.

5. Dr. Mayuri Pandya, Member, SEAC.

6. Shri Natarajan Pratap, Member, SEAC.

7. Shri V.N.Patel, Member, SEAC.

8. Shri R. J. Shah, Member, SEAC.

9. Shri K. C. Mistry, Secretary, SEAC.

The agenda of TOR/Scoping/Category 8 (a) cases, appraisal cases, EC amendment cases,

Reconsideration case was taken up. Six (6) cases of TOR/Scoping/Category 8 (a), twelve (12)

appraisal cases and five (5) Reconsideration cases were taken up. The applicants made

presentations on the activities to be carried out along with other details furnished in the Form-1 /

Form-1A, EIA report and other reports.

1. Causeway Pharma Plot no:331/1 GIDC Chitra, Dist,: Bhavnagar Appraisal

Project / Activity No.: 5(f)

Project status: Expansion

Chronology of EC Process: This project proposed by M/s: Causeway Pharma (herein after Project Proponent – PP)

has submitted Application vide their letter dated 14/08/2013.

This project was considered in the meeting of the SEAC held on 24/06/2014.

The project proponent requested for categorizing the project as B2 and to exempt them

from carrying out detailed EIA study which was considered by the committee and the

additional information was sought for appraisal of the project.

The project proponent submitted the additional information vide their letter dated

12/12/2014.

Page 2: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 2 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 2 of 70

Project / Activity Details:

This is an existing unit engaged in the formulation of various drugs with capacity of 18000 Lit/month. The unit now proposes to manufacture the following synthetic organic chemicals (bulk drugs):

Sr. no.

Name of Products Quantity

Existing 1. Formulation of

Various Drugs 18000 L/month

Proposed 1. Sucralfate 19,500 Kg/month 2. Febuxostat 480 Kg/month 3. Tenoxicam 1,125 Kg/month 4. Tolperisone HCl 700 Kg/month 5. Bosentan

Monohydrate 450 Kg/month

6. Balofloxacin Dihydrate

1400 Kg/month

The proposed production activity falls in the project activity 5(f) as per the Schedule of EIA Notificaiton, 2006 as amended from time to time.

Cost of the project is Rs.51 lakhs and total plot area of the proposed project is 833.0 m2. Water requirement of 1.6 KL/day will be met through GIDC water supply system. Industrial effluent generation will be 0.81 KL/day. Effluent will be evaporated after primary & tertiary treatment units. It was presented that there will not be any process gas emission from the proposed production and there will not be any flue gas emission source except the proposed D.G.set of 60 KVA using HSD-10 Lit/hr. ETP sludge (150 Kg/Month), used oil (12 Kg/Year), discarded containers/bags/ liners (2.7 MT/Year) and Evaporation salt (20 Kg/Month) are the hazardous waste to be generated from the proposed production. Waste solvents i.e. Ethyl acetate (68 ltr./Month), Toluene (10 ltr./Month) and Mixed Solvent-Xylene & Di Isopropyle ether (167.2 ltr./Month) generated will be sent to Authorised distillation units.

Observations & Discussions: Technical presentation made during the meeting also covered the point wise reply of additional information sought. On asking about membership of TSDF site, PP informed that they have applied for membership of TSDF site of SEPPL, Bhachau, Dist. Kutch. Committee noted that initially PP has proposed to utilise treated effluent on land for plantation & gardening, however they have now proposed evaporator to achieve zero liquid discharge. While discussing about solvent recovery, PP informed that in-house solvent recovery is not feasible and they will sent to GPCB Authorised distillation units. Unit has prepared Risk assessment considering four scenarios identified for consequence analysis viz. Release of Toluene, Triethylamine, Formic acid & Pyridine. After detailed discussion, it was decided to recommend the project to SEIAA, Gujarat for grant of Environmental Clearance.

2. Akshar City S.N.450/A,450/B,450/K,452/A452/B, VILL:Kelanpur, Vadodara

Appraisal

The project was taken up in the meeting of SEAC held on 20/09/2014 and during the meeting held on 20/09/2014, while asking by the committee the project proponent replied that till the

Page 3: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 3 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 3 of 70

time they get water supply & drainage connection from VUDA, they will have to rely upon ground water as a source of water supply during the operation phase and will have to dispose the domestic effluent into soak pit through septic tank. The project proponent was asked to carry out ground water recharge through rain water collected from roof top only. After detailed discussion, it was decided to further appraise the project only after submission of the following:

1. A letter from VUDA regarding availability of water supply, drainage connection and municipal solid waste collection also indicating the time limit within which all the above facilities will be available to the project.

2. Implementation schedule of the project along with the bar chart. 3. Details of sewage treatment plant with size of each unit, design capacity and its location on

the plan. Measures proposed to avoid odour nuisance due to the STP in operation phase. Details on operation and maintenance of STP during the operation phase of the project for the efficient and regular operation of STP. Design drawing of dual plumbing system to be provided for reuse of treated water.

4. Complete treated wastewater management plan along with the application wise break up of treated water utilization. Management plan of treated water during the monsoon season when utilization of treated water for irrigation is not possible.

5. Exact source of water supply during the operation phase of the project. In case of ground water utilization, the following should be submitted: i. Categorization of the area from the ground water resource point of view based on the

latest ground water resource estimation carried out by Central Ground Water Board. ii. Geo-hydrological study of the area. iii. Details of scheme for surface as well as roof top rain water harvesting and ground water

recharge revealing that quantity of ground water extraction would be compensated by equivalent or more quantity of rain water recharged, with proper scientific calculations considering rainfall in the region, catchment area, land / soil characteristics, ground water recharge rate, duration of rain water harvesting etc. Details of provisions of pre-treatment of the rainwater in the case of surface run off is to be harvested. Location of recharge percolation wells on the layout plan.

iv. Status of permission from the CGWA for ground water abstraction. Notarized undertaking stating that no borewell shall be drilled unless and until requisite permission is obtained from the CGWA.

The project proponent submitted the above mentioned details vide their letter dated 05/12/2014. They have submitted a letter from VUDA stating the process of providing water supply, drainage and municipal solid waste collection facilities in Kelanpur area will be carried out in the coming years. Bar chart of implementation schedule submitted by them shows that it will take at least 3 years to complete the construction phase of the project. Details of the proposed STP and revised water balance diagram has also been submitted. It was stated that they are not going to use ground water for the proposed project.

Details of the project are as under:

S.No Particulars Details 1. Proposal is for New Project 2. Type of Project Residential 3. Project /

Activity No. [8(a) or 8(b)]

8(a)

4. Name of the “Akshar City”

Page 4: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 4 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 4 of 70

project 5. Name of

Developer “Akshar Buildres”

6. Estimated Project Cost (Rs. In Crores)

95.0

7. Whether construction work has been initiated at site? If yes, details thereof

No.

8. Project Details Land / Plot Area (m2): 1,15,067.00

Permissible Proposed FSI Area (m2) 84,139.93 61,572.79 Ground Coverage (m2) 39,182.56 39,394.34 Common Plot Area (m2) 10,884.04 10,884.04 Max. building height (m) 30 9.88 m

Total BUA (m2):61,793.13

9. Building Details No. of Blocks/units:1070 + 02 Scope of buildings/blocks: 1070 Row Houses + 01 Club House +

01 Temple No. & size of Residential Units: 1070 Row Houses Details of amenities if any: 01 Club House & 01 Temple

10. No. of expected residents / users

Permanent – 4,815 and visitors - 482.

11. Water & waste water details during construction phase

Water requirement (KL/day): 12.0 Source of water: Existing bore well Waste water generation quantity (KL/day): 3.2 Mode of disposal: The sewage generated will be sent to

temporary Septic Tank and soak pits. Details of reuse of water, if any: Not applicable.

12. Water & waste water details during operation phase

Total water requirement (KL/day): 702.0 Fresh water requirement (KL/day): 437.0 Source of water: water supply from VUDA Waste water generation quantity (KL/day): 528.0 Mode of disposal: Treated sewage will be reused in flushing and

gardening purpose. In case of STP provision, capacity of STP: 600.0 KL /day Purposes for treated sewage utilization: -

1.Gardening (KL/day): 42.0 2. Flushing (KL/day): 223.0

Provision of dual plumbing system (Yes/No): Yes Quantity and type (treated/untreated)of sewage to be

discharged: 265 KL/day treated sewage will be reused for gardening & flushing purpose and remaining quantity of treated sewage will be discharged into drainage line of VUDA.

Mode of disposal: Remaining quantity of treated sewage will be discharged into drainage line of VUDA.

13. Status of water Water supply & drainage line will be available in the area as per

Page 5: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 5 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 5 of 70

supply and drainage line

the letter from VUDA.

14. Solid waste Management

Construction Phase: Generation

(m3) Quantity to be reused (m3)

Mode of Disposal / Reuse

Top Soil 1200 1200 Landscaping development.

Other excavated earth

2500 2500 Levelling of the site, internal roads, etc.

Construction debris

125 - Levelling of the site, internal roads, etc.

Steel scrap 25 - Will be Sold to scrap dealer

Discarded packing materials

15 - Will be Sold to scrap dealer

Operation Phase: Type of waste

Generation Quantity (Kg/day)

Mode of waste collection

Mode of Disposal / Reuse

Dry waste 735.0 Will be Collected in Bins

Solid Waste collection dispose off into nearby sanitary landfill site of VMC

Wet waste 1553.0 Will be Collected in Bins

-do-

Capacity and no. of community bins to be placed within premises: 50 Nos. 50 L Each.

15. Parking Details Total parking area requirement for the project as per GDCR: 8,787.59 sq. m.

Parking area requirement for residential units as per GDCR: 8,787.59 sq. m.

Total Parking area provided & No. of ECS: 13,596.25 sq.m. (Individual Parking provided for each tenement)

Parking area provided as open surface & No. of ECS: 12,840.00 sq.m. (Individual Parking provided for each tenement)

Parking area provided (at any other place-specify) & No. of ECS: 756.25 sq. m.

16. Traffic Management

Width of adjacent public roads: 20m. (75 m ring road is proposed adjacent to project site.)

Number of Entry & Exit provided on approach road/s: One for

Page 6: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 6 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 6 of 70

entry & one for exit. Width of Entry & Exit provided on approach road/s: 10.5 m Minimum width of open path all around the buildings for easy

access of fire tender (excluding the width for the plantation):4 m Width of all internal roads:7.5 m, 9.0 m and 10.5 m

17. Details of Green Building measures proposed.

Wall panel fabrics with recycled content. Low-VOC emitting and refurbished or bio-harvested renewable

material content for flooring. Will be installed dedicated exhaust systems in indentified area. On-site rainwater recharging systems for storm water control and

non-potable water uses. Light transmitting panels. Formaldehyde free Medium Density Fibreboard (MDF) Toilet partitions: Solid plastic model made with post consumer

HDPE plastic. Use of polyethylene plastic piping in lieu of PVC piping. Built-in entry way mats with drop pans and adequate drains to

catch dirt off shoes. Green belt development (13.65% of total plot area)

18. Energy Requirement, Source and Conservation

Power supply: Maximum demand: 1840 KVA Connected load: 2000 KVA

Source: MGVCL (Madhya Gujarat Vij Co. Limited) Energy saving measures: maximum use of T5/T8 and CFL

lighting fixtures % of saving with calculations: 35% saving on energy Compliance of the ECBC guidelines (Yes / No),if yes,

compliance in tabular form: Yes Section

No. Requirement Compliance

7.2 Lighting controls occupancy/ time switch

Parking area lighting will be controlled through switch with alternate switching.

7.2.1.4 Exterior lighting to be photo sensor or time switch

External lighting will be controlled through timer.

7.3 Interior lighting power to be within specified limits

All light in common open area will be ceiling mounted. It illuminates the required area only.

7.4 Exterior lighting power to be within specified limits

All lights will be with bracket or arm, so no extra light will be cross boundary limit.

8.2.1.1 Maximum allowable power lose from transformer

Shall be used energy efficient transformers as per ECBC Norms.

8.2.2 Energy efficient motors For the common area, all motor will be energy efficient as per ECBC.

8.2.3 Power factor be We will use capacitor

Page 7: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 7 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 7 of 70

maintained between 0.95 and unity

bank for common areas load to maintain power factor.

8.2.5 Power distribution system losses to be maintained less than 1%.

We will consider low watt loss type MCB in all distribution system.

19. Fire and Life Safety Measures

Nearest Fire station is at Haran Khana Road Fire Station which is 6.0 km away from the project site.

Details of Fire Fighting System during operation phase: Fire alarm system, Fire Extinguishers, Manually operated fire alarm system etc. will be provided.

Details of Safety measures for the construction workers: Provision of Personal Protective Equipments to all the workers and their usage shall be ensured, Full body harness to all the workers working at Height, Safety net to prevent the fall hazard etc.them during working hours.

20. Rain Water Harvesting (RWH)

Level of the Ground water table: 5.5 m No. and depth of percolations wells: 29 nos. & 40 m Details on Pre-treatment facilities: Sand Filter will be used to

remove suspended pollutants from the rainwater. After filtration, water will be recharged using percolation pit, filled with pebbles or brick and river sand and covered with perforated concrete slabs. Depth of recharge pit will be designed according to Water table of the area.

21. Green area details

Tree covered area (m2) : 2,908.98 Area covered by shrubs and bushes (m2): 0 Lawn covered area (m2): 10,884.04 Total Green Area (m2): 13,793.02 Green Area % of plot area: 11.98 No. of trees and species to be planted: 910 Trees & 15 Species.

Budget allocation for green belt development will be Rs. 5.3 lacs including capital & recurring cost.

22. Dust control measures.

Water sprinkling on loose top soil & construction material, covered shed for construction material storage etc.

23. Documents related to land possession

NA order for survey numbers 450/A, 450/B & 450/k shows the land in the name of land owners and development agreement between the land owners & M/s Akshar Builders is submitted.

24. Amenities to be provided to construction workers.

Wash rooms, rest rooms, drinking water, municipal solid waste collection facility etc.

25. Eco-friendly building materials

Fly ash bricks, lead free paints, aluminium windows, bagasses based particle boards in doors etc.

During the meeting, while asking by the committee, the project proponent replied that they have already planted 3 to 3.5 thousand trees within the premises and it proposed to plant 20000 trees. The project proponent was suggested to install drip irrigation system for development green belt. After detailed discussion, it was decided to consider the project only after submission of the following:

Land possession documents and a copy of permission obtained for non agricultural use of

Page 8: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 8 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 8 of 70

survey numbers 452/A & 452/B or a copy of documents showing the correspondences made in this regard. 3. Krishna House Block No : 71, Vill : Moje-Ghaludi, Ta : Kamrej,

Dist : Surat Appraisal

The project was taken up in the meeting of SEAC held on 23/06/2014 and during the meeting held on 23/06/2014, after deliberation on various aspects, it was decided to appraise the project after satisfactory submission of following additional information.

1. Explore the possibility of obtaining surface water supply during the operation phase. 2. Exact source of water supply during the operation phase and copy of permission obtained

from the concerned authority for water supply in operation phase of the project. 3. In case of ground water withdrawal during the operation phase, complete geo-hydrological

study of the area should be submitted.Permission letter from concerned authority for drainage connection and collection of Solid Waste.

4. Existing scenario of underground sewerage line of Ghaludi Gram Panchayat and its final disposal point. In case the sewage from the proposed project is to be finally sent to the Municipal Sewage Treatment plant for further treatment & disposal through the drainage line of Ghaludi Gram Panchayat, details of Sewage Treatment Plant like name, location, distance of it from the proposed project site etc should also be submitted.

5. Details on highest of the high flood level at the project site and elevation of the plinth level with respect to the same.

6. Details of Sewage Treatment Plant with its capacity, size of each unit, retention time and its location on the plan. Measures proposed to avoid odour nuisance due to the STP in operation phase.

7. Complete treated water management plan along with the application wise breakup of treated water utilization. Management plan of treated sewage during rainy season when utilization of treated water for gardening/plantation purpose is not possible.

8. Details of dual plumbing system to be provided for reuse of treated waste water. 9. STP Sludge management plan. 10. Revised water balance details considering the reuse of treated water after provision of STP

in operation phase. The project proponent submitted the above mentioned details vide their letter dated 03/10/2014. The project was appraised based on the additional details submitted as well as facts presented before the committee.

Sr. No.

Particulars Details

1 Proposal is for New Project 2 Type of Project Residential Flats 3 Project / Activity

No. [8(a) or 8(b)]

Project Activity - 8 (a) Category-B

4 Name of the project

“Krishna House”

5 Name of Developer

Krishna Corporation

6 Estimated Project Cost

Rs. 30 Crores.

Page 9: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 9 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 9 of 70

(Rs. In Crores) 7 Whether

construction work has been initiated at site? If yes, details thereof

No

8 Project Details Land / Plot Area (m2) : FSI area (m2): Non FSI area (m2): Total BUA (m2):

30,116.0 42,030.17 57,180.81

Permissible Proposed FSI Area (m2) 42,145.82 42,030.17 Ground Coverage (m2) 12,323.72 10,156.21 Common Plot Area (m2) 2,651.70 3,047.91 Max. building height (m) -- 14.75

9 Building Details No. of Buildings: 16

No. of Blocks: 51 Scope of buildings/blocks: Residential Flats. Hollow plinth + 5

floors. No. & size of Residential Units: 912 Flats No. & type of Commercial Units: - Details of amenities if any: No

10 No. of expected residents / users

4100 Nos. of expected residents/users

11 Water & waste water details during construction phase

Water requirement (KL/day): 14.45 Source of water: Borewell / local water tankers Waste water generation quantity (KL/day):

1.8

Mode of disposal:

Into septic tank/soak pit system.

Details of reuse of water, if any: Waste Water generated from the washing of construction equipment will be reused for curing purpose.

12 Water & waste water details during operation phase

Total water requirement (KL/day): 626.0 Fresh water requirement (KL/day): 348.0 Source of water: Ghaludi Gram Panchayat Waste water generation quantity (KL/day): 511.0 Mode of disposal: Treated sewage will be reused

in flushing and gardening purpose. In case of STP provision, capacity of STP: 280.0

KL /day Purposes for treated sewage utilization: -

1.Gardening (KL/day): 45.0 2. Flushing (KL/day): 223.0

Provision of dual plumbing system (Yes/No): Yes Quantity and type (treated/untreated)of sewage to

Page 10: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 10 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 10 of 70

be discharged: Treated grey sewage will be reused for gardening & flushing purpose. Remaining quantity of treated grey sewage and untreated black sewage will be disposed off into septic tank/soak pit system.

Mode of disposal: Remaining quantity of treated grey sewage and untreated black sewage will be disposed off into septic tank/soak pit system.

13 Status of water supply and drainage line

Fresh water will be supplied by Ghaludi gram Panchayat. Sewer line network is not available at site, so Sewage Treatment Plant for grey sewage will be provided

14 Solid waste Management

Construction Phase: Type of waste

Generation (m3)

Quantity to be reused

(m3) Mode of Disposal / Reuse

Top Soil 900 900 Excavated surplus earth will refilled at low lying areas in project premises adevelopment of road /greenbto raise plot area above existing level.

Other excavated earth

Construction debris Steel scrap 8.2 MT 7.2 MT sold to recyclers Discarded packing materials

1.5 MT 1.5 MT sold to recyclers

Operation Phase: Type of waste

Generation Quantity (Kg/day)

Mode of waste collection

Mode of Disposal / Reuse

Dry waste & Wet waste

1230 kg/day

Dry waste & wet waste will be segregated

at stage of generation.

Dry solid waste like paper, plastic, etc. will be sold to recycler. Wet solid waste will be decomposed and will be used as manure.

STP Sludge

10 MT/Year

Sludge slurry is removed

through sludge pump and dried in

sludge drying bed.

Dry sludge will be reused amanure in gardening and irrigation purpose.

Details of segregation if to be done: Segregate dry and wet solid waste at source

of generation Capacity and no. of community bins to be placed within premises:

140 litter each; 35 nos. of bins

Page 11: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 11 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 11 of 70

Landfill site where waste will be ultimately disposed by local authority:

Decomposed manures produced from waste will be used within the premises and provided to farmers.

15 Parking Details

Total parking area requirement for the project as per GDCR:

6,321.87 m2

Parking area requirement for residential units as per GDCR:

6,321.87 m2

Total number of CPS requirement for the project as per NBC :

456 Nos.

Number of CPS requirement for residential units as per NBC:

456 Nos.

Total Parking area provided (m2) & No. of ECS:

13,601.41 m2 & 515 Nos.

Parking area provided in hollow plinth (m2) & No. of ECS:

9,815.56 m2 & 350 Nos.

Parking area provided as open surface (m2) & No. of ECS:

3,785.85 m2 & 165 Nos.

16 Traffic Management Width of adjacent public roads: 60 meter wide Road Number of Entry & Exit provided on approach road/s:

One Entry & One Exit will provided

Width of Entry & Exit provided on approach road/s:

6.0 meter each wide Entry & Exit road will provide

Minimum width of open path all around the buildings for easy access of fire tender (excluding the width for the plantation):

3.0 m

Width of all internal roads: 12.0 m & 3.0 m 17 Details of Green Building measures

proposed. The project will be designed as energy efficient and environmental friendly building that will control formation of heat island effect. There will be also sufficient green cover at the site to reduce formation of heat island.

18 Energy Requirement, Source and Conservation

Power supply: 15 KW Maximum demand:

1500 KW

Connected load:

--

Source: D.G.V.C.L. Energy saving by Non-conventional Methods:

Yes (Use of solar energy in external lighting (Landscape lighting)).

Energy saving measures:

Maximum use of natural light through architectural design, use of energy efficient motor and pumps, maximum use of aerated blocks, use of CFL & low voltage lighting, solar lighting in open and landscape areas, rooftop thermal insulation etc.

Page 12: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 12 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 12 of 70

DG Sets No. and capacity of the DG sets:

--

Fuel & its quantity:

--

19 Fire and Life Safety Measures

Fire extinguisher, fire hydrant systems & hose reel will be proposed for fire safety. The nearest fire station at Kosad is approx. 14.40 Km away from the project site and a fire tender will take about 25 minutes to reach the project site in case of emergency.

20 Details on staircase

Type & no. of buildings

No. of floors

Floor area

No. of staircase

Width of the staircase

Travel distance (m)

A1 to A10 5 326.06 4 1.22 < 30 m B1 to B5 5 254.93 2 1.22 < 30 m

C 3 255.79 1 1.22 < 30 m

21 Rain Water Harvesting (RWH)

Level of the Ground water table:

80-100 ft

No. & dimensions of RWH tank(s) :

--

No. and depth of percolations wells :

8 Nos. and 40 meter each

Details on Pre-treatment facilities :

Gravity filter, MOC: PE

22 Green area details Tree covered area (m2) :

702.81

Area covered by shrubs and bushes (m2):

inclusive in lawn area

Lawn covered area (m2):

1,539.36

Total Green Area (m2):

2,242.17

Green Area % of plot area:

8.45 %

No. of trees and species to be planted:)

235 Nos. (Gulmohar, Galtoro, Ashopalav, Neem etc.)

23

Budgetary allocation for Environmental Management Plan (Rs. in lacs)

Sr. No.

Description Capital Cost (Rs.

In Lacs) 1 Landscaping 32 Lacs 2 Groundwater Recharge

Structure 23 Lacs

3 Solar Energy Utilization 11 lacs

Page 13: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 13 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 13 of 70

4 Energy Efficient Lighting 9 lacs 5 Solid Waste Management 3 lacs 6 Monitoring of Air, Water, Noise

& Soil 0.75 lacs

Total 78.75 Lacs

24 Proposed dust control measures during the construction phase

dust suppression by spraying of water, peripheral barricading the project site, covering the construction material during transportation and storage etc.

25 Eco friendly building material usage details.

Fly ash based bricks, Ready Mix Concrete and A.C.C Blocks will be used.

26 Facilities for construction workers

Provision of Personal Protective Equipments, safety related training, first aid facilities, along with the basic amenities like adequate sanitation facilities, drinking water facility etc.

During the meeting, it was presented that the project site was not affected by flood in the past. The project proponent submitted a letter from Ghaludi Gram Panchayat stating that water will be made available to the project if sufficient water will be available to the village. The committee was not convinced with the fact that the gram panchayat will be in position to avail water supply to the project. After discussing various aspects of the project in detail, it was decided to consider the project only after submission of the following:

1. Exact source of water supply during the operation phase. Copy of permission obtained from the concerned authority for water supply in operation phase of the project or documentary evidences showing the possibility of surface water availability to the project.

2. Management plan of treated sewage during rainy season when utilization of treated sewage for gardening/plantation purpose is not possible.

3. Land possession documents, list of partners & directors of the company and copy of permission obtained for non agricultural use of the project site or a copy of documents showing the correspondences made in this regard.

4. Alpha Chem Plot no:57, GIDC Estate, Mahuva, Dist.:Bhavnagar

Appraisal

Project / Activity No.: 5(f)

Project status: Expansion

Chronology of EC Process:

This project proposed by M/s: Alpha Chem (herein after Project Proponent – PP) has

submitted Application vide their letter dated 03/09/2014.

This project was considered in the meeting of the SEAC held on 05/12/2014.

The project proponent requested for categorizing the project as B2 and to exempt them

from carrying out detailed EIA study which was considered by the committee and the

additional information was sought for appraisal of the project.

The project proponent submitted the additional information vide their letter dated

21/02/2015.

Project / Activity Details:

Page 14: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 14 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 14 of 70

This is a new unit proposes manufacturing of S.O. Dyes:

Sr. no. Product Name Quantity 1. Direct Dyes

(Sky Blue FF, Orange TGLL, Red 12 B & Sun Yellow RCH) 5 MT/Month

2. Reactive Dyes (Black B & Red M5B)

3. Napthol Dyes (ASG/AS/ASBO/ASBS)

7 MT/Month

The project falls under Category B of project activity 5(f) as per the EIA Notification 2006.

A plot of 2456 sq.m area has been acquired for this project. Total cost of the project is Rs. 0.85 Crores. Total fresh water consumption for the proposed project will be 8 KLPD which will be sourced from GIDC water supply. Source of waste water generation is mainly from process & utilities. Total industrial waste water generation will be 5 KLPD, which will be evaporated after primary treatment to achieve zero discharge. Unit has proposed one Boiler and one HAG (Hot Air Generator). White coal (800 kg/day) and Diesel (7 ltr/hr) will be used as fuel. Hazardous waste generated from the manufacturing activity will be ETP sludge (5 MT/Month), Discarded containers (50 no.s/Month) and Discarded liners (50 no.s/Month).

Observations & Discussions:

Technical presentation made during the meeting also covered the point wise reply of additional information sought. Committee noted that PP has proposed Zero effluent discharge by primary treatment followed by Evaporation by forced evaporation. On asking about volatile organic compounds in the effluent and its impact on surrounding environment, pp informed that they have not considered VOC in the raw effluent. Committee noted that meteorological conditions may not be suitable all the times and forced natural evaporation may also result in atmospheric pollution. After deliberation, It was unanimously decided to consider the project for appraisal only after submission of the following:

1. Technical details of proposed evaporator including Control measures proposed for the evaporator in order to avoid/reduce gaseous emission/voc from evaporation of industrial effluent containing solvents & other chemicals.

2. Details of suppliers of the proposed technology and guarantee from the supplier.

3. Alternate treatment option with all technical details for treatment of the industrial effluent.

5. Shital Industries Plot no:1/11, GIDC-Kalo, Kalol, Dist.: Gandhinagar

Appraisal

Project / Activity No.: 5(f)

Project status: New

Chronology of EC Process:

This project proposed by M/s: Shital Industries (herein after Project Proponent – PP)

Page 15: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 15 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 15 of 70

has submitted Application vide their letter dated 02/01/2014.

The project was taken up in the SEAC meeting held on 27/08/2014. During the meeting

project was categorized as B1 and additional TOR were prescribed.

Project proponent submitted revised Form-1 along with revised PFR dated 07/11/2014.

Looking to the small scale of the project, technical aspects of the project, its location,

low pollution potential and the details presented during the meeting, after detailed

elaboration, the project was categorized as B2 category project.

Project / Activity Details:

This is new project and unit has proposed to manufacture following Synthetic Organic Chemicals:

Sr. no.

Name of Product

Quantity (MT/Month)

1 Epoxy Plasticizer (Epoxidised Soyabean Oil) 116 2 PVC Stabilizer (Methyl Base) 78

3 PVC Stabilizer (Antimony Base) 32

Project / Activity Details as per revised proposal:

The proposed activity falls in the Category 5(f) of the EIA Notification, 2006. Cost of the

proposed project will be Rs. 2.0 Crores. Total area acquired for the proposed project is 4406.88

sq. meter. Fresh Water Requirement for the proposed project will be 2.5 KL/day (Domestic: 1.5

KL/day, Ind. –0.7 KL/day, Gardening: 0.3 KL/day) which will be sourced from GIDC water

supply system. Domestic waste water generation will be 1.2 KL/day will be sent to soak pit and

Industrial waste water 3.3 KL/day will be treated in Primary, Secondary and Tertiary treatment

plant. Final treated effluent will be sent to CETP Kalol. One DG set is proposed as stand by

facility in case of power failure. Hazardous waste to be generated is ETP waste (500 Kg/Year),

Discarded Drums/Containers (4400 No.s/Month) & Bags with liners (1500 No.s/Month), Used

oil (40 Lit./Year) & Oil & Grease skimming residue (300 Lit./Year).

Observations and Discussions:

Technical presentation made during the meeting also covered the point wise reply of additional

information sought. Committee noted that PP has proposed to send their effluent to CETP of

Kalol after achieving CETP inlet Norms. On asking about CETP performance, PP informed that

they have submitted certificate from CETP Kalol regarding discharging the primary treated

effluent @ 5 KL/day. Committee asked strict compliance of the CETP inlet norms. After detailed

discussion, it was decided to recommend the project to SEIAA, Gujarat for grant of

Environmental Clearance.

6. Reliance Composites Polymers S.No.206 paiki 2, Village: Bidaj,

Ta.: & Dist.: Kheda Appraisal

Project / Activity No.: 5(f)

Page 16: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 16 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 16 of 70

Project status: New

Chronology of EC Process:

This project proposed by M/s: Reliance Composites Polymers (herein after Project

Proponent – PP) has submitted Application vide their letter dated 25/08/2014.

This project was considered in the meeting of the SEAC held on 05/12/2014.

Looking to the small scale of the project, technical aspects of the project, its location,

low pollution potential and the details presented during the meeting, after detailed

elaboration, request was considered & the project was categorized as B2 category

project and the additional information was sought for appraisal of the project.

The project proponent submitted the additional information vide their letter dated

02/03/2015.

Project / Activity Details: This is a new unit proposes manufacturing of Resins as tabulated below:

Sr. no. Product Name Quantity 1. Polyster Resin

180 MT/Month 2. Iso Phthalic Polyster Resin

3. PET Flakes Polyster Resin

The project falls under Category B of project activity 5(f) as per the EIA Notification 2006.

As per amendment to EIA Notification, 2006 vide SO 1599 (E) dated 25.06.2014, small units are categorized as Category “B” projects. Small units are defined as with water consumption less than 25 m3/day; Fuel consumption less than 25 TPD; and not covered in the category of MAH units as per the Management, Storage, Import of Hazardous Chemical Rules (MSIHC Rules), 1989. During presentation, PP informed that water requirement is 6 m3/day. Fuel requirement is 0.1 KL/day (LDO) and Chemicals to be used are not covered in MAH category. Hence, this project falls under Category B of project activity 5(f) as per the EIA Notification 2006.

A plot of 1672 sq.m area has been acquired for this new project. Unit has proposed 500 sq. m area for green belt development. Nearest residential area of village Bareja is @ 1.1 KM from the project site. Total cost of the project is Rs. 2 Crores. Total fresh water consumption for the proposed project will be 5 KLPD which will be sourced from Bore well. Source of waste water generation is mainly from process & utilities. Total industrial waste water generation will be 1 KLPD, which will be utilized for greenbelt development after primary & tertiary treatment. Unit has proposed TFH (cap.: 3 Lac Kcal/Hr) in which LDO 100 lit/day will be used. One DG set (cap. 50 KVA) is proposed as stand by arrangement in which HSD – 25 Lit./Hr will be used as fuel. Hazardous waste generated from the manufacturing activity will be ETP sludge (200 Kg/Month), Discarded containers (10 no.s/Month), Discarded liners (100 Kg/Month) and Used oil (20 ltr/Year).

Page 17: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 17 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 17 of 70

Observations / Discussion:

Technical presentation made during the meeting also covered the point wise reply of additional

information sought. Committee noted that this unit has proposed to utilize treated effluent for

gardening plantation within premises. PP has proposed 500 sq. meter land for green belt / tree

plantation. PP has also submitted Risk assessment report. After detailed deliberations the

Committee sought following additional information for further consideration of the proposal:

1. Ppercolation rate of the land available for gardening & plantation. Detail management plan for treated effluent in monsoon season.

7. Macson Color Chem Pvt. Ltd. Plot no: Z/12/2, SEZ Dahej, Part-II Ta.: Vagra, Dist.: Bharuch

Appraisal

Project / Activity No.: 5(f)

Project status: New

Chronology of EC Process:

This project proposed by M/s: Macson Color Chem Pvt. Ltd. (herein after Project

Proponent – PP) has submitted Application vide their letter dated 20/04/2013.

The project was considered for TOR finalization in the meeting of the SEAC held on

13/06/2014.

The project proponent submitted EIA report vide their letter dated 03/03/2015.

Project / Activity Details:

This is a new unit proposing the manufacturing of Dyes and Dyes intermediate products listed as below:

Sr. no.

Name of Product Production Capacity

MT/Month 1 Group 1 - Aryl Sulphonic Acid 192

i. Schaeffer's Acid

i. G - Salt

ii. R - Salt

iii. Para Cresidine Ortho Sulphonic Acid

iv. Sulpho Tobias Acid

v. Dhal’s Acid (2 napthylamine 5 sulphonic Acid )

vi. Ortho Nitro Chloro Benzene Sulphonic ACID

vii. Para Nitro Chloro Benzene Sulphonic ACID

viii. Para Nitro Chloro Toluene Ortho Sulphonic Acid

Page 18: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 18 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 18 of 70

ix. 5 Sulpho Salicylic Acid

x. Para Anisidine M Sulphonic Acid

xi. 5 Sulpho Antranilic Acid

2 Group 2 - Aryl Amination Product 30

i. Broner’s Acid

i. Amido G-Salt

ii. PNAOSA

iii. ONAPSA

3 Group 3 - Aryl Fusion Product 24

i. Di Oxy G Salt

i. Gama Acid

ii. Sulpho Gama Acid

4 Group 4 - Aryl Organic Fine Chemicals 153.9

i. Schaeffer’s Acid

i. G-Salt

ii. Para Cresidine Ortho Sulphonic Acid

iii. Sulphanilic Acid

iv. R-Salt

v. Dhal’s Acid

vi. Bronner’s Acid

vii. Fluroseine

viii. Urainine

5 Group 5 - Aryl Sulphonation Fine Product 102.6

i. Sulphanilic Acid

i. Ortho Toludine 5 Sulphonic Acid

ii. Alpha Naphthylamine Sulphonic Acid

6 Group 6 - Florocsecine 12 7 Group 7 - Aryl Sulphonic Acid - SO2 Gas 88.2

i. Schaeffer’s Acid

i. PCOSA

ii. Sulphanilic acid

Page 19: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 19 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 19 of 70

iii. G-salt

8 Group 8 - Aryl Sulphonamide 30

i. OPSAMIDE

i. Amino Phenyl Methyl Sulphone

ii. PT Sulphanilide

iii. PABSA

iv. NOXAMIDE

v. MABSA

9 Group 9 - Wet Grinding 63 10 Group 10 - BON Product 8.8 11 Group 11 - Synthetic Organic Dyes 36

i. Acid Orange 7

i. Food red 1

ii. Food red 17

iii. Acid yellow 23

iv. Acid orange 24

v. Acid red 33

vi. Acid red 18

vii. Acid red 27

viii. Acid yellow 36

12 Group 12 - Colour Former Product 21

i. RTRD Red

13 Group 13 - Para Cresidine 60

14 Group 14 - Sodium Naphthionate 40.8

15 Group 15 - N. W. Acid 41.7

Total - MT per Month 904

The proposed activity falls in the project activity 5(f) as per the schedule of the EIA Notification-

2006. Public Hearing is not required as proposed unit located within SEZ Dahej Ltd.

The proposed project is having land area of @ 12974.62 m2. Unit has proposed 3582 sq. m

land for green belt/ tree plantation. Cost of the proposed expansion will be Rs. 15.48 crores.

Water requirement will be 90 KL/day [84 KL/day for Industrial i.e. Process, boiler, cooling,

scrubber and washing + 3 KL/day for domestic + 3 KL/day for gardening] which will be sourced

from supply of Dahej SEZ Ltd. Industrial waste water generated from the proposed activity will

Page 20: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 20 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 20 of 70

be 69.4 KL/day (49 KL/day from Process + 8 KL/day from boiler and cooling blow down + 9

KL/day from washing + 3.4 KL/day from scrubber). Process effluent will be segregated into

different streams. Stream 1: 15 KL/day will be conveyed to process recovery plant, Stream 2:

10 KL/day will be sent to Spray Dryer, Stream 3: 11 KL/day will be used to make ferrous

sulphate/Copper sulphate or Gypsum and Stream 3: Remaining 13 KL/day will be sent to ETP.

Unit has proposed Effluent Treatment Plant consisting primary, secondary and tertiary

treatment. Total 34.7 KL/day of effluent (13 KL from process + 20.7 KL from Cooling & Boiler

blow down, Scrubber, washing + 1 KL from Ferrous sulphate recovery plant) will be treated in

Effluent Treatment Plant consisting primary, secondary and tertiary treatment. Treated effluent

will be discharges in Effluent Disposal Pipeline provided by Dahej SEZ Ltd. Domestic effluent

will be deposed of in septic tank/soak pit.

Bio fuel (9.5 MT/day) will be used as a fuel in one number of Boiler (2 MT) and one Thermic

Fluid Heater (8 Lac Kcal/Hour). Unit has proposed MDC followed by Bag filter as APCM for

Boiler and TFH. Diesel will be use in stand by D.G.set (250 KVA). Diesel – 400 liter/day will be

used as fuel. Ammonia scrubber is proposed for control of Ammonia gas to be emitted from

reaction vessels (2 no.s). Two stage alkali scrubbers are proposed for control of SO2 & HCL to

be emitted from Sulphonators (2 no.s). Alkali scrubber is proposed for control of PM, Sox &

NOx to be emitted from Spray Dryers.

ETP Sludge (25 MT/Month) & Spray dryer salt (17 MT/Month) will be sent to common TSDF

site, Distillation reside (20 MT/Month) & Spent Catalyst (0.40 MT/Month) will be sent to CHWIF,

Used Oil (400 lit./Month) will be disposed by selling to GPCB authorized recycler. Discarded

Drums & Discarded PP Bags/Liner (10500 no.s/Month) will be decontaminated; Detoxified &

Sold to GPCB authorized vendors. Iron Sludge (19.2 MT/Month) will be sold to Cement

Industries. Spent HCl (97 MT/Month), Spent Acetic Acid (59 MT/Month), Spent Nitric Acid (10

MT/Month), Ammonium Bisulphide (45.2 MT/Month) & Zinc Hydroxide (3.4 MT/Month) will be

reused in plant premises. Ferrous Sulphate/Copper Sulphate (300 MT/Month) will be sold to the

end users. Gypsum (If there will not manufacture FeSO4/CuSO4) (225 MT/Month) will be be

disposed at common TSDF.

Observations/Discussions:

Technical presentation during the meeting also included the details like general information

regarding the project, location of the project & lay out map, Point wise ToR compliance

including technical details, CSR, Public hearing action plan etc. The study period considered for

EIA was March to May 2014. Air quality monitoring was carried out at 7 stations. During the

study period the existing baselines levels of all the parameters were well within prescribed limit

at all locations. Ground level Estimation of emissions from the plant has been made by

Industrial Source Complex – Short Term (IST-ST3) model developed by USEPA. As per

dispersion modeling studies, concentrations calculated for proposed activities are

superimposed on existing ambient air quality monitoring results and combined values are found

within permissible National Ambient Air Quality Standards. Unit has also submitted Risk

assessment & Disaster management plan. While discussing about by-products, PP informed

that they will reuse most of the by-products within the premises as raw materials and remaining

Page 21: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 21 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 21 of 70

will be sold to the actual end users. Committee asked to submit details of products in which

these by-products are to be used and name of end users. Solvent recovery system and its

management were discussed. On asking about the huge quantum of production capacity, PP

clarified that they will manufacture only one product from each group at a time and they will

manage the production quantity in such a way that there will no increase in pollution potential

with respect to air, water and hazardous waste as proposed. Issues related to Worst case

scenarios, safety precautions, solvent recovery, online measurement of process gaseous

emissions etc were discussed in detail. After detailed deliberations the Committee sought

following additional information for further consideration of the proposal:

1. Compliance of ToR no. 11 i.e. Complete management plan of the by-products, Hazardous wastes & spent acids to be generated including break up of quantity to be recycled / reused within the premises and quantity to be sold outside along with Name and address of end consumers, Copies of agreement / MoU / letter of intent from them, showing their willingness to purchase said wastes / by-products from the proposed project. Give detailed justification and feasibility of reuse/recycle of the particular item.

2. Compliance of ToR no. 36 i.e. Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios should be carried out. The worst-case scenario should take into account the maximum inventory of storage at site at any point of time. The risk contours should be plotted on the map clearly showing which of the facilities and surrounding units would be affected in case of an accident taking place. Based on the same, proposed safeguard measures including On-Site / Off-Site Emergency Plan should be provided.

3. Compliance of ToR no. 19 Details of solvent recovery system including mass balance, solvent loss, recovery efficiency etc. for each type of solvent.

8. Ascent Pharma Survey no. 163/9 & 11, Shapar – Veraval Industrial Area, SIDC Road, Village: Veraval (Shapar) Taluka: Kotada Sangani, Dist: Rajkot

Appraisal

Project / Activity No.: 5(f)

Project status: Expansion

Chronology of EC Process:

M/s: Ascent Pharma (herein after Project Proponent – PP) has submitted their

application for this expansion project at MoEF vide letter dated 21/06/2013 as the

project site is located outside the notified area.

TOR issued by MoEF on 10/09/2013.

Public Hearing was conducted by GPCB on dated 15/10/2014.

PP has submitted final EIA/EMP report to SEAC, Gujarat on dated 10/11/2014.

MoEF&CC has transferred this case vide F.no. J-11011/108/2013-IA II (I) dated

23/02/2015 as per amendment to EIA Notification, 2006 vide SO 1599 (E) dated

Page 22: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 22 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 22 of 70

25.06.2014. As per amendment notification dated 25.06.2015, small units are

categorized as Category “B” projects. Small units are defined as with water consumption

less than 25 m3/day; Fuel consumption less than 25 TPD; and not covered in the

category of MAH units as per the Management, Storage, Import of Hazardous Chemical

Rules (MSIHC Rules), 1989.

Project / Activity Details:

This is an existing unit engaged in manufacturing of Synthetic Organic Chemicals proposes for expansion of the project as mentioned below:

Sr. No.

Name of Product Existing Quantity MT/Month

Proposed MT/Month

Total after expansion MT/Month

1. Potassium Nitrate 10 00 10 2. Potassium Sulphate 10 00 10 3. Magnesium Hydroxide 10 00 10 4. Potassium Chloride 10 00 10 5. Potassium Iodide 10 00 10 6 Oxyclozanide 00 25 25 7 Glibenclamide 00 20 20 8 1,2,4 Triazole

00

10

10

9 4-Amino -1,2,4 Triazole By-products Hydrochloric Acid (30%) 15.5 Sodium Bi-Sulphite 26.0 Phosphorous Acid Aq. 3.3

The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification

2006.

Plot area is approx.2292 sq.m. Unit has proposed 760 sq. m area for green belt development.

Estimated cost of proposed expansion is Rs. 36.5 Lacs. Fresh water requirement for proposed

expansion will be supplied by the Gram Panchayat, Veraval (Shapar) through Tankers.

Presently there unit maintains Zero Effluent Discharge and after proposed expansion the

industrial effluent will be treated in ETP, the treated water will be reused for gardening and

plantation within the premises. Domestic waste water will be disposed off into septic tank/soak

pit system. Consumption of fuel FO will be increased from 1.5 KL/Month to 3 KL/month for

existing steam Boiler (0.8 TPH). At present there is no process gaseous emission. Now unit has

proposed Water Scrubber followed by Alkali Scrubber for control of HCl & SO2 gas generated

from the manufacturing of Oxyclozanide. Hazardous waste to be generated are Inorganic salt

(52 MT/Annum), Distillation residue (14 MT/Annum), Spent Carbon (18 MT/Annum), Spent

solvent (7400 MT/Annum, ETP waste (2 MT/Annum), Discarded containers (1000 no.s/Annum)

& Used Oil (0.1 MT/Annum).

Discussions/Observations:

Page 23: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 23 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 23 of 70

Technical presentation during the meeting also included the details like general information

regarding the project, location of the project & lay out map, Point wise ToR compliance

including technical details, CSR, Public hearing action plan etc. Committee noted that existing

water consumption from the unit is already 20 KL/Day and as per the EIA report (pg. 2.42)

proposed quantity of fresh water will be 8.81 KL/day, which is more than 25 KL/day. As per

amendment of EIA dated 25.06.2014 if water consumption exceeds 25 KL/day, project should

not be considered as “B” category project. PP informed that there is a typographical error in

CC&A of the Board. Committee asked to submit the amended copy of CC&A and relevant

documents showing realistic data of water consumption. After deliberation, It was unanimously

decided to consider the project for appraisal only after submission of the following:

1. Copy of CC&A with corrected data and relevant documents showing realistic data for

existing water consumption.

9. Sika India Pvt LTd Plot No. 916, Jhagadia GIDC, Village: Vakhatpura, Taluka: Jhagadia, Dist: Bharuch

Appraisal

Project / Activity No.: 5(f)

Project status: New

Chronology of EC Process:

M/s: Sika India Pvt Ltd (herein after Project Proponent – PP) has submitted their

application for this expansion project at MoEF vide letter dated 18/03/2013 as the

project site is located within 10 KM from the critically polluted area as notified by the

CPCB.

TOR issued by MoEF on 10/09/2013.

PP has submitted final EIA/EMP report to MoEF&CC on 03/05/2014.

MoEF&CC has transferred this case vide F.no. J-11011/108/2013-IA II (I) dated

11/02/2015 as per amendment to EIA Notification, 2006 vide SO 1599 (E) dated

25.06.2014. As per amendment notification dated 25.06.2015, any project or activity

specified in category ‘B’ will be appraised at the central level as category ‘A’ located in

whole or in part within 5 km from the boundary of critically polluted areas as identified by

the CPCB. The proposed project is located at a distance of 9 km from Ankleshwar

Industrial Estate (Critically Polluted Area).

Project status: Expansion

Project / Activity Details:

This is an existing unit proposes for expansion of the project as mentioned below:

Sr. No.

Name of the Product Production Capacity,

MT/Annum Proposed

Page 24: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 24 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 24 of 70

1 Polymer MR (Medium Range Polymer) 1,250

2 Membrane (Liquid Applied Membrane Poly Urathrene, Poly Vinyl Chloride &Waterbar)

3,000

3 Sealant (Poly Sulphide) 1,500 Total 5,750

Existing (NOC Received) 1 Concrete Admixture Products 90,000 2 Cementitious Mortar (Powder) Products 60,000

3 Epoxy Resin based Industrial Flooring, Adhesives & Grouts Products

15,000

Total 1,65,000 Total Production 1,70,750

The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification

2006.

Plot area is approx.62798.80 sq.m. Unit has proposed 8728.43 sq. m area for green belt

development. Estimated cost of proposed expansion is Rs. 43.89 Crores. Total fresh water

requirement after proposed expansion will be increased from 102.7 KL/day to 104.7 KL/day

which will be supplied by the GIDC. Total water requirement after proposed expansion will be

111.5 KL/day (4.5 KL Domestic + 72 KL Process + 2 KL Boiler + 3 KL Washing + 30 KL

gardening) including 6.8 KL of recycled water.

Wastewater generation will be remain same as 6.8 KL/day (3 Kl washing + 0.2 KL Boiler Blow

down + 3.6 KL Domestic). There is no increase in effluent generation due to proposed

expansion. Unit has provided ETP comprises of Primary, Secondary & Tertiary treatment units.

After treatment, 6.8 KL/day will be recycled and reused for gardening. At present Natural gas

(35 SCM/Hr) or HSD (29 lit./hr) is used in one Boiler (TPH) and Natural gas (48 SCM/Hr) or

HSD (48 lit./hr) is used in stand by DG set. There will be no additional flue gas stack required

due to proposed expansion. At present Bag filter is provided with Mortar plant to control PM and

water scrubber is provided with Admixture plant to control PM. Now unit has proposed Water

scrubber and Bag filter with Polymer MR plant and Membrane Plant respectively to control PM.

Unit has also proposed Carbon active filter with Sealant Plant.

Hazardous waste to be generated are ETP waste (0.2 MT/Annum), Used Filter (0.004

MT/Annum), Flue gas cleaning residue (0.1 MT/Annum), Waste residue of resin (30

MT/Annum), Used Oil (0.1 MT/Annum), Discarded containers (25 MT/Annum), Process waste -

Contaminated aromatic, aliphatic or naphthenic solvents may or may not be fit for reuse (30

MT/Annum), Process waste Residue & Sludge (30 MT/Annum)

Flue gas cleaning residue, Chemical sludge from waste water treatment & Used Filter will be

disposed off at the nearby common TSDF. Contaminated aromatic, aliphatic or naphthenic

solvents may or may not be fit for reuse, Process Waste Residue & Sludge and Waste Residue

(Resin) will be sent to CHWIF. Discarded barrels / containers / bags / liners will be either

reused or returned back to suppliers or sold only to the authorized vendors after

decontamination. Used oil will be sold only to the registered recyclers. Unit is a member of

BEIL, Bharuch for TSDF site and CHWIF.

Page 25: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 25 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 25 of 70

Discussions/Observations:

Technical presentation during the meeting also included the details like general information

regarding the project, location of the project & lay out map, Point wise ToR compliance

including technical details, CSR, Public hearing action plan etc. The study period considered for

EIA was the months of October, November and December of year 2013, i.e. the post-monsoon

season of 2013. . Air quality monitoring was carried out at 6 stations. The parameters

monitored were Particulate Matter (PM2.5 & PM10), Sulphur Dioxide (SO2), Oxides of Nitrogen

(NOx), CO, HC and VOCs. The average concentrations of all the parameters are well within the

limits. The average concentrations of all the parameters are well within the limits. As per

dispersion modeling studies, concentrations calculated for proposed activities are

superimposed on existing ambient air quality monitoring results and combined values are found

within permissible National Ambient Air Quality Standards. Unit has also submitted Risk

assessment & Disaster management plan. While discussing about fugitive emissions, PP

informed that they have proposed water scrubber and bag filter to control dust emissions.

Issues related to green belt development, CSR activities, Occupational health etc were

discussed. After detailed discussion, it was decided to recommend the project to SEIAA,

Gujarat for grant of Environmental Clearance.

10 Rebecca Laminates Survey o. 132/P1, 8-A National High Way, Village: Bahudurgardh, Morbi, Dist: Rajkot

Appraisal

Project / Activity No.: 5(f) M/s: Rebecca Laminates (herein after Project Proponent – PP) had submitted their

application for this project at MoEF as the project site is located outside the notified

area.

TOR issued by MoEF on 22.02.2012.

Public Hearing was conducted by GPCB on dated 25.01.2013

MoEF asked to conduct fresh Public Hearing as Sub Divisional Magistrate, Morbi has

supervised and presided over the entire public hearing process, which was not as per

the provisions of EIA Notification, 2006 and amended in 2009.

Public Hearing was again conducted by GPCB on dated 27.11.2013

PP has submitted final EIA/EMP report to this office on 11.10.2014.

Project status: New

Project / Activity Details:

This is a new project proposes for manufacturing of Synthetic Resins as tabulated below:

Sr. no.

Name of Product Quantity/ Month

1 Laminated Sheets 69000 no.s 2 Phenol Formaldehyde Resin 87.5 MT 3 Melamine Formaldehyde Resin 37.5 MT

Page 26: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 26 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 26 of 70

The proposed production activity (Synthetic Resins) falls in the project/activity 5(f) as per the

schedule of the EIA Notificaiton-2006.

Total plot area is 14569 sq. m & unit has proposed 4955 sq mtr area for the green belt

development/Tree plantation. Expected project cost is Rs.6.19 Crores. Total water consumption

for proposed project will be 7.7 KL/D (2.5 :KL/day for Domestic & 5.3 KL/day for Industrial)

which will be sourced from Bore well. Industrial waste water generation will be 2.2 KL/day,

which will be evaporated after primary treatment. Domestic waste water (2 KL/day) will be

disposed off into soak pit system. Flue gas generation will be from one steam boiler (4 TPH),

one TFH (10 Lac Kcal/hr) and one D.G. set (250 KVA). Coal/Lignite 12 MT/day for boiler and

0.36 MT/day for TFH will be used as fuel. Unit has proposed MDC followed by Bag filter as

APCM for Boiler and MDC as APCM for TFH. No process gas emission is envisaged.

Hazardous waste generated from the manufacturing activity will be ETP sludge & evaporation

sludge (1 MT/Year), Discarded containers/Bags/Liners (0.8 MT/Year) and Used oil (0.04 MT

/Year).

Observations & Discussions:

Technical presentation during the meeting also included the details like general information

regarding the project, location of the project & lay out map, Point wise ToR compliance

including technical details, CSR, Public hearing action plan etc. The study period considered for

EIA was Summer 2012. Air quality monitoring was carried out at six stations. During the study

period Average concentration of all the parameters viz. PM2.5, PM10, SO2, NOx, & VOC were

well within prescribed limit at all locations except concentration of particular matter at project

site is higher due to movements of heavy vehicles on adjacent NH-8-A. EIA report reveals that

the impact due to this project is by the Boiler/TFH and evaluated impact will be Marginal. After

detailed discussion, it was decided to recommend the project to SEIAA, Gujarat for grant of

Environmental Clearance.

11. DCM Shriram Ltd. (Unit: Shriram Alkali & Chemicals Ltd.)

Plot No. 749, GIDC Estate, Jhagadiya, Dist: BHaruch

Appraisal

Project / Activity No.: 4(d) & 1(d) M/s: DCM Shriram Ltd. (herein after Project Proponent – PP) has submitted their

application for this expansion project at MoEF vide letter dated 03/04/2014 as the

project site is located within 10 KM from the critically polluted area as notified by the

CPCB.

TOR issued by MoEF on 10/10/2014.

PP has submitted final EIA/EMP report to MoEF&CC on 03/05/2014.

MoEF&CC has transferred this case vide F.no. J-11011/108/2013-IA II (I) dated

11/02/2015 as per amendment to EIA Notification, 2006 vide SO 1599 (E) dated

25.06.2014. As per amendment notification dated 25.06.2015, any project or activity

Page 27: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 27 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 27 of 70

specified in category ‘B’ will be appraised at the central level as category ‘A’ located in

whole or in part within 5 km from the boundary of critically polluted areas as identified by

the CPCB. The proposed project is located at a distance of 9 km from Ankleshwar

Industrial Estate (Critically Polluted Area).

The project proponent submitted EIA report vide their letter dated 23/02/2015.

Project status: Expansion

Project / Activity Details:

This is an existing unit proposes for expansion of the existing manufacturing capacity of the

Chlor-Alkali plant from 171000 MTPA to 342000 MTPA of caustic soda and captive Coal based

Co-generation Power plant (CPP) from 61 MW to 122 MW within existing premises. The

capacity of existing and proposed production tabulated below:

S. No.

Name of Product Unit Existing Capacity

Proposed Capacity

Total Capacity

Chlor-Alkali

1 Caustic Soda (Lye/Flakes) MTPA 1,71,000 1,71,000 3,42,000

2 Chlorine MTPA 1,48,900 1,48,900 2,97,800

3 Hydrochloric Acid MTPA 40,000 40,000 80,000

4 Hydrogen MTPA 4,558 4,558 9,116

5 Sodium Hypo Chloride MTPA 8,200 8,200 16,400

6 Dilute Sulphuric Acid MTPA 3,775 3,775 7,550

Power Generation

1 Coal Based CPP MW 61 61 122

2 DG Set (HFO Based) MW 24 Nil 24 The project falls under Category B of project activity 4(d) and 1(d) as per the schedule of EIA

Notification 2006.

Plot area is approx. 467300 sq.m. Unit has proposed 103600 sq. m area for green belt

development. Estimated cost of proposed expansion is Rs. 525 Crores. Fresh water

requirement after proposed expansion will be increased from 6300 KL/day to 12233 KL/day (13

KL Domestic & 12220 KL Industrial) which will be supplied by the GIDC. Industrial wastewater

generation after the expansion will be increased from 460 KL/day to 861 KL/day. Waste water

generated during the regeneration of ion exchange columns will be recycled /reused in process

plant, Alkaline effluent will be used for the preparation of sodium hypochlorite and Boiler blow

down will be used in cooling towers. Total 700 KL/day will be recycled / reused in plant

premises and 861 KL/day of treated effluent will be discharged into GIDC drain for final disposal

by the NCTL into the deep sea. Unit has provided Domestic waste water (13 KL/day) will be

disposed to soak pit and septic tank as per the existing practice.

Existing and proposed fuel consumption will be as below:

Page 28: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 28 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 28 of 70

Name of Fuel Existing (MTPA)

Proposed (MTPA)

Total (MTPA)

Blended Coal (for Boilers) 2,55,000 4,76,000 7,31,000 Lube Oil (for lubrication) 612 0 612 HFO (for DG set) 52,700 0 52,700 HSD (for Startup & support of Boilers) 100 100 200 Hydrogen (For Molten Salt heater) 34000

NM3/day 34000 NM3/day

68000 NM3/day

At present ESP is provided as APCM for 240 TPH P.F. Boiler (Coal Based Power Plant).

Adequate stack height is provided with Molten salt heater and auxiliary Boiler. Unit has now

proposed ESP as APCM and adequate stack height with CFBC steam boiler (300 TPH) of

CPP. Adequate stack height is proposed with Molten salt heater. Process gaseous emissions

and APCM for existing and proposed expansion will be as below:

Sr. no.

Source / Stack attached to APCM

Existing APCM

1 Chlorine Absorption Unit – Hypo Plant

Caustic Scrubber

2 HCl Units Water Scrubber

Proposed APCM

1 Chlorine Absorption Unit – Hypo Plant

Caustic Scrubber

2 HCl Units Water Scrubber

Hazardous waste/ solid waste generation and its disposal details is as below:

S. No

Waste Name Sourc

e

Quantity Disposal Method Existi

ng Propos

ed Total

Hazardous Waste

1

Discarded Barrels /

Containers of various

chemicals- Nos./year

Chlor Alkali and

Power Plant

2,200 2,200 4,400 GPCB approved authorized vendor/traders.

Bags-Nos./Year 66,30

0 66,300

1,32,600

GPCB approved authorized vendor/traders.

2 ETP Sludge-

MTPA ETP 3 -- 3

Own TSDF within premises.

3 Used Oil-MTPA

Chlor Alkali and

Power Plant

200 -- 200 Registered re-processors.

Page 29: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 29 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 29 of 70

Other Solid Waste

1 Brine Sludge –

MTPA

Chlor Alkali Plant

11,500

11,500 23,000 Own TSDF within factory

premises.

2 Fly ash – Lac

MTPA Power Plant

0.255 0.952 1.207 Brick / cement industries.

Observations/Discussions: Technical presentation during the meeting also included the details like general information

regarding the project, location of the project & lay out map, Point wise ToR compliance

including technical details, CSR, Public hearing action plan etc. The study period considered for

EIA was October to December 2014. Air quality monitoring was carried out at six stations.

During the study period average concentration of all the parameters viz. PM2.5, PM10 , SO2 ,

NOx, CL2 & HCl were well within prescribed limit at all locations. Estimation of emissions from

the plant has been made by AERMOD, developed by the AERMIC (American Meteorological

Society (AMS) / United States Environmental Protection Agency (USEPA). As per dispersion

modelling studies, the resultant ground level concentrations of PM10, NOx SO2, HCL & CL2

due to operation of all the proposed plants at various locations are well within the prescribed

limits. Proposed expansion will be within the existing industry which is located in notified

industrial area and thus public hearing is exempted as per MoEF&CC Office Memorandum no.

J – 11013/36/2014-IA-I dated 10/12/2014.

On asking by the committee, PP informed that they will provide adequate height of stack with

molten salt heater and they will add lime with fuel in proposed CFBC Boiler for control of SO2.

Committee suggested to provide CEMS (Continuous Emission Monitoring system) for flue gas

and process gas stacks/vents. On asking about control of gaseous emission of hydrogen &

chlorine, PP mentioned that the entire process is closed loop. The vent of chlorine is through

the scrubbers attached to the sodium hypochlorite plant and vent of HCl is through the

scrubbers attached to HCl plants. While discussing the capacity of NCTL pipeline for proposed

effluent quantity, PP informed that the work for new pipeline of NCTL is almost completed and

they have got the permission for effluent quantity to be generated after proposed expansion.

During the meeting, while discussing about the socio-economic upliftment activities to be

carried out by the company, the project proponent informed that the allocated fund for

community development for the financial Year 2015-17 is over INR 80.0 Lacs. SAC had

contributed INR 44.2 Lacs in the previous three financial years i.e. 2011-12, 2012-13 and 2013-

14 to improve the socio-economic status of people in the study area. Further PP explained

about various activities carried out in surrounding villages viz. Sanitation work by providing

toilets, renovation of Anganwadi and Kitchen used for midday meals, up gradation of library,

arrangement of health check up etc.

After detailed discussion, it was decided to recommend the project to SEIAA, Gujarat for grant

of Environmental Clearance.

Page 30: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 30 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 30 of 70

12. Jyoti Industries Shed No. C-1/B-3229, 3230, New Chemical Zone, GIDC Sarigam, District: Valsad

Appraisal

Project / Activity No.: 5(f) M/s: Jyoti Industries (herein after Project Proponent – PP) has submitted their

application for this expansion project at MoEF vide letter dated 16/12/2013 as the

project site is located within 10 KM from the critically polluted area as notified by the

CPCB.

TOR issued by MoEF on 11/08/2014.

PP has submitted final EIA/EMP report to SEAC, Gujarat on 19/01/2015.

MoEF&CC has transferred this case vide F.no. J-11011/29/2014-IA II(I) dated

11/08/2014 as per amendment to EIA Notification, 2006 vide SO 1599 (E) dated

25.06.2014. As per amendment notification dated 25.06.2015, any project or activity

specified in category ‘B’ will be appraised at the central level as category ‘A’ located in

whole or in part within 5 km from the interstate boundaries. The location of proposed

project is beyond 5 KM of interstate boundary of Gujarat & Daman & Diu.

Project status: Expansion

Project / Activity Details:

This is an existing unit proposes for expansion of the existing manufacturing capacity as tabulated below:

Sr. no.

Name of Product Existing Quantity (T/Month)

Expansion Quantity (T/Month)

Total Quantity After Expansion

(T/Month)

1. Red Pigment 6.0 44.0 50.0 2. Yellow Pigment -- 50.0 50.0 3. Orange Pigment -- 25.0 25.0

The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification

2006.

Plot area is approx. 1634 sq.m. Unit has proposed 540 sq. m area for green belt development.

Estimated cost of proposed expansion is Rs. 1.48 Crores. Fresh water requirement after

proposed expansion will be increased from 6.3 KL/day to 137.1 KL/day (1.5 KL Domestic and

135.6 KL Industrial) which will be supplied by the GIDC. Industrial wastewater generation after

the expansion will be 98.1 KL/day. At present Industrial effluent after treatment in ETP is

discharged into GIDC underground drainage system and is ultimately conveyed into deep

Arabian sea. After proposed expansion Industrial effluent will be treated in primary and

secondary treatment plant and sent to the CETP of Sarigam for further treatment and its

disposal Arabian Sea. Domestic waste water will be sent to septic tank/soak pit system. At

present Natural gas (160 SCM/Hr for each) is used in one Boiler (2 TPH) and one TFH (10 Lac

Kcal/Hr). One DG set (250 KVA) is installed for emergency purpose in which Natural gas (60

Page 31: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 31 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 31 of 70

SCM/Hr) is used. At present Natural gas (1200 SCM/Day) is used as fuel for 0.85 TPH Boiler.

Now unit has proposed 3 TPH steam boiler in which NG (3000 SCM/Day) will be used as fuel.

Unit has proposed one DG set (125 KVA) in which HSD 20 Lit./hr will be used as fuel. No

process gaseous emission from existing as well as proposed expansion. Hazardous waste to

be generated are ETP waste (61 MT/Month), Discarded containers (28 MT/Year), Used Oil

(0.026 KL/Year) & Filter cloth contaminated with waste sludge/residue (0.050 MT/Year). ETP

waste & contaminated filter cloth will be disposed off at the nearby common TSDF. Discarded

barrels / containers / bags / liners will be either reused or returned back to suppliers or sold only

to the authorized vendors after decontamination. Used oil will be sold only to the registered

recyclers.

Observations/Discussions:

Technical presentation during the meeting also included the details like general information

regarding the project, location of the project & lay out map, Point wise ToR compliance

including technical details, CSR, Public hearing action plan etc. The study period considered for

EIA was October to December 2014.

The study period considered for EIA was March to June 2014. Air quality monitoring was

carried out at 8 stations. The average concentration of PM10 varied from 42.08 μg/m3 to 79.29

μg/m3 , PM2.5 varied from 1.01 μg/m3 to 4.53 μg/m3, SO2 varied from 12.18 μg/m3 to 22.87

μg/m3, NOX varied from 9.50 to 11.05 μg/m3 at all monitoring locations during the study period.

Values of all parameters were well within the prescribed limits. Assessment of impacts on air

quality is done by using Gaussian Dispersion Formula by computer based dispersion models.

Lakes Environmental Software “AERMOD View 8.2.0” has been used to find out the maximum

ground level concentration of Pollutant. As per dispersion modelling studies, the resultant

ground level concentrations of PM10, PM2.5 , SO2 & NOx due to operation of all the proposed

plants at various locations are well within the prescribed limits. Proposed expansion will be

within the existing industry which is located in notified industrial area and thus public hearing is

exempted as per MoEF&CC Office Memorandum no. J – 11013/36/2014-IA-I dated 10/12/2014.

Committee noted that PP has proposed to send their effluent to CETP of Sarigam after

achieving CETP inlet Norms. On asking about CETP performance, PP informed that the CETP

is commissioned recently and performing well. Committee asked to comply CETP inlet norms

strictly. After detailed discussion, it was decided to recommend the project to SEIAA, Gujarat

for grant of Environmental Clearance.

13. Alex Industries Plot No CH – 11, GIDC Dahej, Taluka: Vagra Reconsideration

Project / Activity No.: 5(f)

Status of the Project: Expansion

Chronology of EC Process:

This is an It is an existing unit intending to include new products as shown in table

below :

Page 32: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 32 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 32 of 70

Sr. No.

Name of the Product

Production (MT/Month) As per NOC Proposed Ultimate

1. Ammonium Sulphate

100 -- 100

2. Pigment Beta Blue (Grinding Process)

600 -- 600

3. Magnesium Carbonate

100 -- 100

4 Ammonium Chloride 127 -- 127 5. Precipitated Silica 90 -- 90 6. Pigment Beta Blue -- 100 100

7. Pigment Red 122 or Pigment Violet 19

-- 10 10

8. Pigment Green-7 -- 50 50 9. Pigment Violet-23 -- 10 10

10. Calcium Chloride (90%)

-- 40 40

Total 1017 210 1227 The project proponent submitted the additional information sought by the committee;

vide their letter dated 05/01/2012.

The public hearing of the project based on the TOR issued was conducted by the

Gujarat Pollution Control Board on 18/12/2013.

The project proponent submitted the Environment Impact Assessment Report to this

office vide their letter dated 10/01/2014.

The project was appraised based on the additional information furnished and the details

presented before the committee in the SEAC meeting held on 20/08/2014 and sought

for certain details.

The project proponent submitted the additional information sought by the committee,

vide their letter dated 14/11/2014.

The committee recommended SEIAA, Gujarat for granting the environmental clearance

to the proposed project expansion vide letter no. EIA-10-2011-1142-E-3014 dated

27/11/2014.

Project was considered in the 7th meeting of SEIAA held on 23/01/2015. During the

meeting, it was decided by SEIAA to refer back the case to SEAC for reconsideration on

the following point:

1. Detail technical justification of boiler blow down quantity and cooling tower bleed

off quantity.

2. Quantity and concentration of VOC from condenser vent.

3. A Copy of the GIDC drainage line connection showing wastewater discharge

quantity.

Page 33: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 33 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 33 of 70

During the meeting, the project proponent gave following clarification for the above points :

Technical justification of boiler-blow down quantity and cooling tower bleed off quantity

is submitted. As per their submission total make-up water requirement : Boiler Water +

Boiler blowdown will be 39 KL/day (35 KL/Day Boiler water + 4 KL/Day Boiler blow

down) and total make-up Water is 43 KL/day (39 KL/Day Evaporation & Drift Losses +

4 KL/Day Bleed-off). Detailed calculations for Boiler blow down and cooling tower bleed

off are given.

Quantity and concentration of VOC from condenser vent is submitted in tabular form for

solvents namely Xylene/IBA. Methanol, IBA, MCB & ODCB. Considering the worst case

release concentration of the VOC i.e. 50.7 kg/hr, isopleths have been plotted. The result

shows maximum concentration of 515 μg/m3 at about 62 meters from the factory

boundary. This maximum VOC concentration of 515 μg/m3, is much lower than

documented time-weighted Average as well as Flammable Limits. Hence, there will not

be any adverse effect of the solvent losses on the human and the environment.

PP has submitted certificate from GIDC vide GIDC letter no.

GIDC/Bharuch/DEE/(Drg)/288 dated 15/04/2015. As per the letter, it is confirmed that

GIDC will take treated effluent load of additional 267.5 KL/day (beyond existing paid

quantity 210.5 KL/day).

Observations & Discussions: During the meeting, committee noted that PP has submitted reply of all the points raised by

SEIAA. After detailed deliberations the Committee was satisfied with the clarification given by

the project proponent and decided to forward the same to SEIAA for their consideration along

with the following additional condition in continuation of the same terms and conditions which

were prescribed earlier.

14. Ajitkumar J Desai S.N.49,55,56 ,VILL:MOTA

VARACHNA,SURAT

Reconsideration

Mr. Ajitkumar J. Desai had applied for getting environmental clearance and the SEAC recommended the project for grant of environmental clearance vide this office letter no. EIA-10-2014-6254-E-3195 dated 23/12/2014 for residential building construction project.

The case was referred back by the SEIAA vide letter no. SEIAA/GUJ/EC/8(a)/676/2015 dated 27/03/2015 for reconsideration by the SEAC based on the discussion in the SEIAA meeting held on 13/03/2015 for the following:

“Title clear clarification / development agreement for all the survey/block numbers.“

Hence the project proponent was called for the presentation and discussion in the meeting.

During the meeting, the project proponent has submitted a copy of N.A orders for residential

Page 34: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 34 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 34 of 70

use of all the three block numbers i.e 49, 55 & 56. A copy of development agreement made between the land owners & Mr. Ajitkumar J Desai has also been submitted. After discussing the matter it was decided to recommend the project again to SEIAA Gujarat for grant of Environmental Clearance.

15. Amul Cement Survey No. 47, Village: Patapar, Dist: Junagadh

Reconsideration

Project / Activity No.: 3(d)

Status of the Project: New

Chronology of EC Process:

The unit has applied to SEAC for obtaining Environmental Clearance on 17/10/2007 for Mini Cement Plant (37500 MTPA) at S.no.47, village:Patapar, Dist:Junagadh.

The project was considered for TOR finalization in the meeting of the SEAC held on 20/12/2007 and additional TORs were prescribed in addition to proposed Terms of Reference to include them in the EIA study.

Public hearing was carried out by Gujarat Pollution Control Board on 02/07/2008. EIA Report was submitted on 16/07/2008. During the meeting of SEAC held on 22/08/2008, considering that the reserved forest of

the Girnar is within 10 Km radial distance from the project site and as the general condition is applicable to the project, it was decided to forward the application to MoEF for the appraisal of the project.

Project Proponent has applied to MoEF, New Delhi on 04/09/2008. The project was considered by EAC in January-2009 and EIA report was appraised

based on the deliberations, the proposal was recommended for Environmental Clearance, with specific conditions, only after submission of latest meteorological data.

Meteorological data for January-2014 has been submitted to MoEF by the project proponent.

The project was transferred to SEAC Gujarat by MoEF&CC vide their letter dated 17/11/2014.

The project was appraised during the meeting of SEAC held on 29/11/2014.

The SEAC vide letter no. EIA-10-2007-150-P-3224 dated 30/12/2014 recommended the

proposal to SEIAA, Gujarat for granting the environmental clearance.

Salient features of the project are:

Unit has applied for manufacturing of Cement- 37500 MT/Annum (Dry Process-

Vertical Shaft Kiln technology based).

Total plot area is 7917.75 sq.m. Expected cost of the project is Rs 2.4 Crores.

Water requirement will be about 30 KL/day which will be sourced through Bore

well. No industrial effluent generation is envisaged.

Cyclone separators followed by Wet scrubbers are proposed for control of

emission from two no.s of VSK. Coal-13 MT/day will be used as fuel in two no.s

of VSK.

Page 35: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 35 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 35 of 70

Stacks will be provided with Crushing section (15 m), Raw Mills (30 m), VSK (30

m), Clinker crusher section (15 m) and Cement Mills (30 m).

Cyclone separator followed by Reverse pulse jet type bag filters are proposed for

Crushing and raw material silos, raw mill & blending silos, Clinker crusher and

cement mill feed hopper, cement mill and cement blending silo and packing

section. Reverse pulse jet type bag filters are proposed for Nodulisers.

Discarded bags will be either reused or sold to the registered recyclers only.

Used oil will be sold only to the registered recycler.

Cement dust collected from the different Air Pollution Control Measures and

other collection systems will be reutilized in the plant itself.

Project was considered in the 14th meeting (In continuation 94th) of SEIAA held on

23/01/2015. During the meeting, it was decided by SEIAA to refer back the case to

SEAC for reconsideration on the following point:

Distance certificate from competent authority from Girnar sanctuary to proposed project to be

submitted to State Level Expert Appraisal Committee for proper categorization as per EIA

Notifications 2006.

Observations & Discussions:

In view of the above, the matter was discussed in detail during the meeting and the

committee noted that as per the amendment dated 25/06/2014 of the EIA Notification-

2006, any project or activity specified in category “B” will be appraised at the central

level as category “A”, if located in whole or in part within 5 km from the boundary of Eco-

sensitive areas as notified under subsection (2) of section 3 of Environment Protection

Act-1986.

The committee also noted that inspite of the above mentioned amendment dated

25/06/2014 of EIA Notification-2006, the MoEF & CC, vide their letter dated 17/11/2014,

has transferred the proposal to SEAC Gujarat stating that:

“In response to MoEF’s clarification sought on the precise location of the project vis-à-

vis Girnar WL Sanctuary, PP vide letter dated 02.04.2014 submitted a letter no.

WLP/32/C/404 of 2013-14 dated 10.03.2014 which was received from the Office of the

Principal Chief Conservator of Forest, Government of Gujarat, Whereby it is stated that

the proposed Cement Plant is located at the shortest distance of 1.22 km from the

outermost boundary of Girnar Sanctuary, Gujarat and is outside the Eco-Sensitive

Zone of Girnar Sanctuary. In view of this, clearance is not required from the

NBWL as per MoEF letter no. 6-10/2011/WL dated 19/12/2012.

In view of para 2 above, the proposal is a category B project and should be appraised

for EC by the SEIAA/SEAC Gujarat.”

Considering the facts that

Though the proposal is of Category “A” project as per the amendment dated 25/06/2014

of the EIA Notification-2006, the MoEF&CC vide its letter dated 17/11/2014 transferred

Page 36: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 36 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 36 of 70

the proposal as Category B project for appraisal at SEAC/SEIAA Gujarat.

Further the project was considered by EAC at MoEF in January-2009 and EIA report

was appraised based on the deliberations, the proposal was recommended for

Environmental Clearance, with specific conditions, after submission of latest

meteorological data,

Further the project proponent has already submitted meteorological data of January-

2014 as well as other additional details to the MoEF&CC,

Further the project is pending & suffering since long.

Further the project site is outside the Eco Sensitive Zone of Girnar Sanctuary and does

not require NOC from standing committee of National Board for Wild Life as per the

letter no. WLP/32/C/404 of 2013-14 dated 10.03.2014 which was received from the

Office of the Principal Chief Conservator of Forest, Government of Gujarat,

To avoid any further inadvertent delay, which does not actually accrue any

specific advantage to the environment, the committee decided to recommend the

project again to SEIAA, Gujarat for appropriate decision with reference to SEAC

recommendation vide letter no. EIA-10-2007-150-P-3224 dated 30/12/2014 and MoEF

letter no. F.N.J-11011/721/2008-IA.II (I) dated 17/11/2014.

16. Glen mark Generics Ltd

Plot No. Z-103-01, Dahej SEZ, Phase-2, Dist. Bharuch

Reconsideration

Project / Activity No.: 5(f)

Status of the Project: Amendment

Chronology of EC Process:

This is an existing Pharmaceutical Bulk drugs manufacturing unit which was accorded Environmental Clearance vide letter no. SEIAA/GUJ/EC/5(f)/79/2012 dated 06/06/2012.

The project proponent vide their letter dated 03/03/2014, requested for amendment in the following condition no. 29 stipulated in the Environmental Clearance granted vide order no. SEIAA/GUJ/EC/5(f)/79/2012 dated 06/06/2012.

Proposal was taken up in the SEAC meeting held on 29/11/2014 and recommended to amend the EC order no. SEIAA/GUJ/EC/5(f)/79/ 2012 dated 06/06/2012 to replace condition no. 29 as proposed vide letter no. EIA-10-2011-876-E-122 dated 03/02/2015.

Project was considered in the 7th meeting of SEIAA held on 23/01/2015. During the

meeting, it was decided by SEIAA to refer back the case to SEAC for reconsideration on

the following point:

1. Details about generation and methods of disposal of spent solvent from date of

commencement of this unit to month of March 2015.

2. List of units/end users where spend solvent to be sold out as product after

solvent recovery.

Page 37: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 37 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 37 of 70

During the meeting, the project proponent gave following clarification for the above points :

Unit has submitted details of Sales of recovered solvent with disposal details since its

commissioning i.e. April-2014 to March-2015.

Observations & Discussions: During the meeting, it was observed that unit has submitted all the details related to solvent

recovery and its sales to different parties. PP presented that as per the mandate from USFDA

they can not use recovered solvent into Mfg. process of API drugs. PP also informed that the

recovered solvent has high degree of purity and generated in huge quantity which is also very

high valued product and used as raw material, in many industries such Paint Industries,

Pesticides, Plastics and Petro Chemicals and Thinners. PP requested to grant permission to

sale 6000 MT/Year of the Recovered Solvent as Product as it is sold in open market through

traders on regular basis. Committee noted that this unit has sold the recovered solvent to the

authorized end-users who have obtained CC&A of the GPCB. The committee was satisfied with

the clarification given by the project proponent and decided to forward the same to SEIAA for

the grant of environment clearance with the same conditions which were prescribed earlier.

17. Century Plyboard Plot no.:186, GIDC-Mithi Rohar, Vill:Mithi Rohar,Gandhidham, Kutch

Reconsideration

Project / Activity No.: 5(f)

Status of the Project: New

Chronology of EC Process:

This unit has applied for environmental clearance on 02/03/2013 for manufacturing of

Synthetic resins.

Proposal was taken up for screening / scoping in the SEAC meeting held on 15/05/2013

and looking to the low pollution potential, the unit was categorized as B2.

The project proponent submitted the additional information sought by the committee;

vide their letter dated 10/10/2013.

The project was appraised based on the additional information furnished and the details

presented before the committee in the SEAC meeting held on 12/06/2014 and sought

for certain details.

The project proponent submitted the additional information sought by the committee,

vide their letter dated 21/10/2014.

The committee recommended SEIAA, Gujarat for granting the environmental clearance

to the proposed project expansion vide letter no. EIA-10-2010-1718-E-2926 dated

Page 38: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 38 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 38 of 70

12/11/2014.

Project was considered in the 7th meeting of SEIAA held on 23/01/2015. During the

meeting, it was decided by SEIAA to refer back the case to SEAC for reconsideration on

the following point:

1. Details about technology to be used to justify about no generation of effluent

from manufacturing process.

During the meeting, the project proponent gave following clarification for the above points :

1. There is no discharge of waste water from the process. Amount of water that is evaporated in the process is again converted into water through process of condensation inside the condenser of the kettle. Water required for weekly washing of the resin kettle as general maintenance of the kettle will be recycled. Standard operating procedure will be followed for 100% reuse of washing water in next batches.

Observations & Discussions: During the meeting, it was observed that there is no generation of process water during

manufacturing process as the condensate water will not be taken out from the product. It was

also noted that washing water will be completely reused in next batches. Considering the

representation made by the project proponent and facts above the committee decided to

forward the same to SEIAA for their consideration for grant of environment clearance by

replacing the specific condition no. 2 as below and with rest of conditions same as prescribed

earlier in the recommendation letter dated 12/11/2014:

Specific Condition no.2: Separate Reaction Vessels shall be provided for manufacturing of each kind of resin to minimize the washing waste water and whatever quantity generated from the washing activity shall be utilized in next batch of the process. 18. RJD Buildcon Survey No. 57+58, FP No. 57+58/2, TPS No.

66, Village: Kali, Taluka: City, Dist: Ahmedabad

Screening & Scoping

The SEIAA, Gujarat has accorded environmental clearance to M/s RJD Buildcon Ltd. for the residential cum commercial building construction project at Survey No.57+58/P, F.P.No. 57+58/P, T.P.S.No.66, Vill:Kali, Dist:Ahmedabad vide order No. SEIAA/GUJ/EC/8(a)/339/ 2012 dated 21/11/2012 for built up area of 27,544.99 m2.

Now, M/s RJD Buildcon Ltd. vide their letter dated 13/06/2014 requested for amendment in Environmental Clearance order dated 21/11/2012 for the proposed changes in the project for which Environmental Clearance was granted by SEIAA, Gujarat.

The request for amendment in terms of proposed expansion was considered during the meeting. The project proponent presented the details of the previous and the revised project proposals which are tabulated below:

Page 39: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 39 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 39 of 70

Sr No.

Description Details as per environmental clearance

Revised details

1. Name of the project RJD Buildcon Sanidhya Flora 2. Plot / Land Area 10,610.0 m2 10,377.0 m2 3. Built-Up Area 27,544.99 m2 34,757.18 m2 4. Basement Area --- --- 5. Hollow Plinth Area 3,822.68 m2 3,978.84 m2 6. Parking Area requirement as

per NBC 216 252

7. Parking area provided and number of CPS

6,972.82 m2 and 229 CPS 7,056.02 m2 and 422 CPS

8. Common Plot Area 830.74 m2 830.74 m2 9. Tree Covered Area 300.0 m2 330.0 m2 10. Lawn Covered Area 700.0 m2 700.0 m2 11. Total no. of Blocks/Building 17 building blocks 17 building blocks

12. Scope and Height of Each Building

Hollow plinth + 5 floors, maximum building height 16.5 m.

Hollow plinth/ground floor + 7 floors, maximum building height 25.55 m.

13. Total number of units 396 residential units and 34 shops

483 residential units and 35 shops

14. Water requirement (KL/day) and source of water supply

287.38 & AMC 303.32 & AMC

15. Total waste water generation (KL/day)

225.0 KL/day & disposal through underground drainage line of AMC.

240.0 KL/day & disposal through underground drainage line of AMC.

16. Municipal solid waste generation (Kg/day)

942 1138.25

During the meeting, the project proponent presented that construction of almost 10-11 buildings has already been carried out. They were suggested to provide basement in the buildings yet to construct and in common open plots. The project proponent was agreed upon to provide basement. While asking by the committee, the project proponent replied that the project expansion in terms of two additional floors in all the buildings has been planned to commensurate with the additional FSI available to the project due to revised GDCR. Copy of NA permission obtained for the project site which is in the name of Director of RJD Buildcon Limited has been submitted. After detailed discussion on various aspects regarding the project, it was decided to consider the project only after submission of the following:

1. Copy of permission from concerned authority for proposed expansion due to availability of

additional FSI.

2. A certificate from structural engineer stating that the existing foundation is structurally sound

to bear the load of additional two floors.

3. Revised details on parking area provision in view of the basement area to be provided.

Revised details on the built up area of the project considering the additional basement. Lay

out plan of the project showing location of the basement with two separate approach ramps.

19. Blue’s Springfield (Developer:Blue

Block No:29,RS No.74, Pavlepur, Waghodiya, Vadodara

Screening & Scoping

Page 40: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 40 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 40 of 70

River Project)

Details of the proposed project as presented before the committee is tabulated below:

Sr. No. Particulars Details 1. Proposal is for New Project 2. Type of Project Residential 3. Project / Activity

No. [8(a) or 8(b)]

8(a)

4. Name of the project

Blues’s Spring Field

5. Name of Developer

Blue River Projects

6. Estimated ProjectCost (Rs. In crores)

115 Cr.

7. Whether construction work has been initiated at site? If yes, details thereof

No

8. Project Details

Permissible Proposed FSI Area (m2) 43,326.75 37,872.33 Ground Coverage (m2) 19,887.22 18,810.66 Common Plot Area (m2) 5,524.41 5,526.13 Max. building height (m) 40.00 6.90

Land / Plot Area (m2) : 57,769.0 FSI area (m2): 37,872.33 Non FSI area (m2): Nil Total BUA (m2): 37,872.33

9. Building Details No. of Buildings: 397 bungalows.

No. of Blocks: 397 bungalows Scope of buildings/blocks: ground floor + 1 floor. No. & size of Residential Units: 122.20 m2 /A1 type unit ,112.46

m2 /A type unit, 90.01m2/B type unit, 81.63 m2 /C type unit and 68.85 m2 /D type unit (All Residential)

No. & type of Commercial Units: NA Details of amenities if any: Home theatre & Gymnasium.

10. No. of expected residents / users

1628

11. Water & waste water details during construction phase

Water requirement (KL/day): 40 KL /Day Source of water: Tanker Waste water generation quantity (KL/day): 3 Mode of disposal: soak pit Details of reuse of water, if any: No

12. Water & waste water details during operation phase

Total water requirement (KL/day): 345.0 Fresh water requirement (KL/day): 137.0 Source of water: Tanker / Bore well

Page 41: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 41 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 41 of 70

Waste water generation quantity (KL/day): 208 Mode of disposal: Treated sewage will be reused in flushing

and gardening purpose. In case of STP provision, capacity of STP: 225 KL /day Purposes for treated sewage utilization: -

1.Gardening (KL/day): - 100 2. Flushing (KL/day): 108

Provision of dual plumbing system (Yes/No): Yes Quantity and type (treated/untreated)of sewage to be

discharged: Mode of disposal: Treated sewage will be completely used for

flushing and gardening purpose. 13. Status of water

supply and drainage line

Ground water will be used. Treated sewage will be completely reused within premises.

14. Solid waste Management

Construction Phase: Generation

(m3) Quantity to be reused (m3)

Mode of Disposal / Reuse

Top Soil 250 250 Will be reused for green belt development.

Other excavated earth

1200 900 Will be reused for backfilling, internal road, and other paved areas and remaining will be used for other projects in the vicinity.

Construction debris

200 120 Will be used for backfilling, internal roads development and remaining will be used at their other project site.

Steel scrap 5 0 Sold to vendors Discarded packing materials

2 0 Sold to vendors

Operation Phase: Type of waste

Generation Quantity (Kg/day)

Mode of waste collection

Mode of Disposal / Reuse

Dry waste & Wet waste

650 Kg /Day Collection in separate Bins

VUDA

STP Sludge 50 Kg /Day Collection in Sludge Drying Bed

Used in Gardening area.

Details of segregation if to be done: No

Page 42: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 42 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 42 of 70

Capacity and no. of community bins to be placed within premises: 200

Landfill site where waste will be ultimately disposed by local authority: at nearby MSW dumping site of VUDA.

15. Parking Details Parking area requirement for residential units as per GDCR: Per unit 1car

Total number of CPS requirement for the project as per NBC : 397

Number of CPS requirement for residential units as per NBC: 397

Parking will be provided in individual Bungalows : 397 ECS. 1 Car Parking Space will be provided in individual Bungalows.

16. Traffic Management

Width of adjacent public roads: 18.0 m Number of Entry & Exit provided on approach road/s: 1 (one) Width of Entry & Exit provided on approach road/s: 9 m Minimum width of open path all around the buildings for easy

access of fire tender (excluding the width for the plantation):1.8 m

Width of all internal roads: 7.50 m. 17. Details of Green

Building measures proposed.

Maximum use of natural lighting through architectural design.

18. Energy Requirement, Source and Conservation

Power supply: 3 - Phase with 2 lines of underground cabling Maximum demand: 2035 KW Connected load: 1221 KW

Source: MGVCL Energy saving by Non-conventional Methods: CFL tubes and

LED lighting Energy saving measures: each street light pole has its

individual MCB for switching off/on. Provision of ISI marked cables for better conductivity.

DG Sets: Not proposed. 19. Fire and Life

Safety Measures

3 nos. of underground fire water storage tanks each of 50 KL capacity.

20. Details on staircase: one staircase of 09 m width will be provided in each bungalow.

21. Rain Water Harvesting (RWH)

Level of the Ground water table: 30 m No. & dimensions of RWH tank(s) : No. and depth of percolations wells : 15 Nos. Details on Pre-treatment facilities :--

22. Green area details

Tree covered area (m2) : 3,000 Area covered by shrubs and bushes (m2): --- Lawn covered area (m2): 17,880.90 Total Green Area (m2): 18,330.78 Green Area % of plot area: 55.13 % No. of trees and species to be planted: 598.

23.

Budgetary allocation for Environmental Management

(Please specify the activities and break up of budget allocation) Site Development: 6.0 lacs Plants / seed : 3.0 lacs Plant care & Reg : 2.0 Lacs

Page 43: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 43 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 43 of 70

Plan (Rs. in lacs)

Total : 11.0 Lacs.

24. Proposed dust control measures during the construction phase

Spraying of water, peripheral barricading covered sheds for cements loading area, covering the excavated earth with tarpaulin sheets.

25. Eco friendly building material usage details.

Fly ash bricks, aerated blocks, fly ash paving blocks, maximum use of RMC, lead free paints etc.

26. Details of amenities to be provided to construction workers.

Education facilities to children like provision of books, school uniform, shoes, pens, bags, water bags etc. Doctor service once in a week, provision of residence with toilets & facility of drinking water, insurance for the company workers.

During the meeting, the project proponent was asked to explore the possibility of obtaining surface water supply from the concerned authority instead of using ground water for the proposed project. At this the project proponent replied that by the time the construction phase of the project is completed, the water supply and drainage line of VUDA will be available in the area. After discussing the various aspects of the project in detail, it was decided to consider the project only after submission of the following:

1. Copy of agreement made between land owners of the project site and the developers i.e Blue River Projects. Copy of partnership deed of the company.

2. Explore the possibility of obtaining surface water supply for the proposed project. A letter from concerned authority (VUDA) regarding availability of water supply, drainage connection and municipal solid waste collection facility.

20. Panoli Intermediates (India) Pvt. Ltd.

Plot No:41/1 & 41A, GIDC Nandesari, Dist.: Vadodara

Screening & Scoping

Project / Activity No.: 5(f)

M/s: Panoli Intermediates (India) Pvt. Ltd. (herein after Project Proponent – PP) has

submitted Application for Environmental Clearance vide their letter dated 30/09/2014.

Project Proponent did not remain present in the SEAC meeting dated 08/12/2014.

Project Status: New

Project / Activity Details:

This unit has applied for manufacturing of Synthetic organic Chemicals. List of Products and

By-products is as below:

Sr.

no.

Name of Products Capacity

MT/Month

1. Aniline 2000

2. Acetanilide 3000

Page 44: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 44 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 44 of 70

3. Acetic Acid (From Recovery Plant) 500

Total 5500

The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification

2006.

Total plot area is 18723 sq. m & unit has proposed 3745 sq mtr area for the green belt

development/Tree plantation. Expected project cost is Rs.10 Crores.Total water consumption

for proposed project will be 830 KL/D (10: KL/day for Domestic, 10 KL/day for Gardening & 810

KL/day for Industrial) which will be sourced from GIDC water supply. Industrial waste water

generation will be 74.8 KL/day ( Process & Washing 60 KL, Cooling 4 KL, Boier 10.8 KL), which

will be treated in proposed Primary treatment plant and treated waste water will be sent to

CETP of NIA-Nandesari. Domestic waste water (8 KL/day) will be disposed off into soak pit

system. Flue gas generation will be from Steam Boiler (15 TPH) and D.G. sets (750 KVA). Coal

(63 MT/day) will be used as fuel in Boiler. Diesel (30 lit./hr) will be used as fuel for DG set. Unit

has proposed MDC followed by Bag filter as APCM for Boiler. Unit has proposed MDC followed

by Bag filter as APCM. No process gas emission is envisaged. Hazardous waste generated

from the manufacturing activity will be ETP sludge (1.2 MT/Year), Discarded containers/Bags/

Liners (2400 no.s/Year) and Used oil (1200 lit. /Year).

Observations/Discussions:

Technical presentation by the PP included general information, details of products and raw

materials, Waste generation, hazards & control, analysis of pollution parameters before and

after treatment, resource consumption and conservation, Risk estimation etc. While discussing

about the reuse/recycle of waste water, Committee suggested to reduce fresh water

consumption by optimum reuse of treated waste water. Safety aspects of Hydrogen gas, Nitro

benzene, Aniline and other hazardous chemicals were discussed. Committee suggested to

provide ESP instead of Bag filter as APCM with Boiler. Committee also asked to take

necessary steps to control SO2 from the Boiler stack. After detailed discussion, the following

additional Terms of Reference were prescribed for the EIA study to be done covering 10 Km

radial distance from the project boundary.

1. Copy of plot holding certificate obtained from GIDC Nandesari.

2. Present land use pattern of the study area shall be given based on satellite imagery.

3. Layout plan of the factory premises. Provision of separate entry & exit and adequate margin all round the periphery for unobstructed easy movement of the emergency vehicle / fire tenders without reversing back. Mark the same in the plant layout.

4. Details of manufacturing process / operations of each product along with chemical reactions, mass balance, consumption of raw materials etc. Details on strategy for the implementation of cleaner production activities. (Give specific details about source of effluent generation).

5. Chemical name of each proposed product to be manufactured. Details on end use of each

Page 45: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 45 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 45 of 70

product.

6. Detailed mass balance and water balance (including reuse-recycle, if any) along with qualitative and quantitative analysis of the each waste stream from the processes.

7. Assessment of source of the water supply with adequacy of the same to meet with the requirements for the project. Permission obtained from the GIDC for supply of raw water. Undertaking stating that no bore well shall be dug within the premises.

8. Explore the possibility of reuse / recycle and other cleaner production options for reduction of wastes. Details of methods to be adopted for the water conservation.

9. Quality and quantity of waste water to be generated from the manufacturing process of each product to be manufactured along with mass balance.

10. Stream wise qualitative & quantitative analysis of each waste stream (including process water, cooling tower blow down, boiler blow down, washing effluent etc.) to be generated. Characteristics of untreated and treated wastewater. A detailed effluent treat ability study vis-à-vis the adequacy and efficacy of the treatment facilities proposed for the wastewater to be generated. The characteristic on which treatability is based shall also be stated.

11. Details of the ETP units including its capacity, size of each unit, retention time and other technical parameters. Details regarding provision of online continuous pH meter, TOC analyser and flow meter at the final outlet of the ETP.

12. Details of CETP- Nandesari including (1) Total capacity of the CETP (2) Actual load at present (Qualitative and Quantitative - per day) (3) CETP Up gradation scheme, if any (4) Last 6 analysis Reports of GPCB for Inlet and outlet of CETP (5) Spare capacity of CETP with treatability and feasibility report.

13. Plans for management, collection and disposal of waste streams to be generated from spillage, leakages, vessel washing, used container washing etc. Measures proposed for preventing effluent discharge during unforeseen circumstances.

14. One season Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be incorporated.

15. Anticipated environmental impacts due to the proposed project/production may be evaluated for significance and based on corresponding likely impacts VECs (Valued Environmental Components) may be identified. Baseline studies may be conducted within the study area of 10 km for all the concerned/identified VECs and likely impacts will have to be assessed for their magnitude in order to identify mitigation measures.

16. One complete season base line ambient air quality data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall be in accordance with the revised National Ambient Air Quality Standards as well as project specific parameters. Locations of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors. There should be at least one monitoring station in the upwind direction. There should be at least one monitoring station in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.

17. Modelling indicating the likely impact on ambient air quality due to proposed activities. The details of model used and input parameters used for modelling should be provided. The air

Page 46: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 46 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 46 of 70

quality contours may be shown on location map clearly indicating the location of sensitive receptors, if any, and the habitation. The wind rose showing pre-dominant wind direction should also be indicated on the map. Impact due to vehicular movement shall also be included into the prediction using suitable model. Results of Air dispersion modelling should be superimposed on satellite image / geographical area map.

18. Base line status of the noise environment, impact of noise on present environment due to the project and proposed measures for noise reduction including engineering controls.

19. Specific details of (i) Process gas emission from each unit process with its quantification, (ii) Air pollution Control Measures proposed for process gas emission, (iii) Adequacy of the air pollution control measures for process gas emission, measures to achieve the GPCB norms (iv) Details of the utilities required (v) Type and quantity of fuel to be used for each utility (vi) Flue gas emission rate from each utility (vii) Air Pollution Control Measures proposed to each of the utility along with its adequacy (viii) List the sources of fugitive emission along with its quantification and proposed measures to control it.

20. Technical details of APCM along with its adequacy, details of its operational controls with DCS, system for online monitoring of the pollutants from the stack etc. Details of provisions to be kept in APCM to ensure that in any case the air emission does not cross the GPCB norms, preventive maintenance, failure / tripping control system, guarantee from the APCM supplier, alternative arrangements in case of the failure of the APCM etc.

21. Fly ash management plan and copies of MOU / agreements done with actual consumers regarding utilization of fly ash & bottom ash etc. should also be incorporated.

22. Details on management of the hazardous wastes to be generated from the project stating detail of storage area for each type of waste, its handling, its utilization and disposal etc. How the manual handling of the hazardous wastes will be minimized. Methodology of de-contamination and disposal of discarded containers and its record keeping.

23. Membership of Common Environmental Infrastructure including CETP, TSDF, Common Hazardous Waste Incineration Facility (CHWIF). (Whichever is applicable)

24. Complete Management plan for By-products/Spent acids to be generated, (if any) from the project including their quantity, quality, characteristics, end use etc. along with the name and address of end consumers to whom the by-product will be sold. Copies of agreement / MoU / letter of intent from them, showing their willingness to purchase said by-product from the proposed project. Also give characteristics of the by products and feasibility of their actual use in respective products as a raw material.

25. Name and quantity of each type of solvents to be used for proposed production. Details of solvent recovery system including mass balance, solvent loss, recovery efficiency feasibility of reusing the recovered solvents etc. for each type of solvent.

26. A detailed EMP including the protection and mitigation measures for impact on human health and environment as well as detailed monitoring plan and environmental management cell proposed for implementation and monitoring of EMP. The EMP should also include the concept of waste-minimization, recycle/reuse/recover techniques, energy conservation, and natural resource conservation. Total capital cost and recurring cost/Year earmarked for environment pollution control measures.

Page 47: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 47 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 47 of 70

27. Permission from PESO, Nagpur for storage of solvents, other toxic chemicals, if any.

28. Occupational health impacts on the workers and mitigation measures proposed to avoid the human health hazards along with the personal protective equipment to be provided. Provision of industrial hygienist and monitoring of the occupational injury to workers as well as impact on the workers. Plan for periodic medical checkup of the workers exposed. Details of work place ambient air quality monitoring plan as per Gujarat Factories Rules.

29. Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios should be carried out. The worst-case scenario should take into account the maximum inventory of storage at site at any point of time. The risk contours should be plotted on the plant layout map clearly showing which of the facilities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures including On-Site / Off-Site Emergency Plan should be provided.

30. MSDS of all the products and raw materials.

31. Details of hazardous characteristics and toxicity of raw materials and products to be handled and the control measures proposed to ensure safety and avoid the human health impacts. This shall include the details of Antidotes also.

32. Details of quantity of each hazardous chemical (including solvents) to be stored, Material of Construction of major hazardous chemical storage tanks, dyke details, threshold storage quantity as per schedules of the Manufacture, Storage & Import of Hazardous Chemicals Rules of major hazardous chemicals, size of the biggest storage tank to be provided for each raw material & product etc. How the manual handling of the hazardous chemicals will be minimized?

33. Details of the separate isolated storage area for flammable chemicals. Details of flame proof electrical fittings, DCP extinguishers and other safety measures proposed. Detailed fire control plan for flammable substances and processes showing hydrant pipeline network, provision of DG Sets, fire pumps, jockey pump, toxic gas detectors etc.

34. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE, manufacturing utility staff for safety related measures.

35. Detailed five year greenbelt development program including annual budget, types & number of trees to be planted, area under green belt development [with map], budgetary outlay; along with commitment of the management to carry out the tree plantation activities outside the premises at appropriate places in the nearby areas and elsewhere.

36. Detailed socio-economic development measures including community welfare program most useful in the project area for the overall improvement of the environment. Submit a detailed plan for social corporate responsibilities, with appropriate budgetary provisions for the next five years and activities proposed to be carried out; specific to the current demographic status of the area.

37. (a) Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be detailed in the EIA report.(b). Does the Environment Policy prescribe for standard operating process / procedures to bring into focus any infringement / deviation / violation of the environmental or forest norms / conditions ? If so, it may be detailed in the EIA.

Page 48: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 48 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 48 of 70

38. What is the hierarchical system or administrative order of the company to deal with the environmental issues and for ensuring compliance with the EC conditions? Details of this system may be given.

39. Does the company have a system of reporting of non compliances / violations of environmental norms to the Board of Directors of the company and / or shareholders or stakeholders at large? This reporting mechanism should be detailed in the EIA Report.

40. Certificate of accreditation issued by the NABET, QCI to the environmental consultant should be incorporated in the EIA Report.

41. A tabular chart with index for point-wise compliance of above TORs.

The above mentioned project specific TORs/additional TORs and the model TORs available in

the MoEF’s sector specific EIA Manual for Synthetic Organic Chemical industry shall be

considered as generic TORs for preparation of the EIA report in addition to all the relevant

information as per the generic structure of EIA given in Appendix III in the EIA Notification,

2006. The project shall be appraised on receipt of the final EIA report.

21. Himalaya Chemicals

Plot no. 25, Shed No.C-1/B-4, GIDC Estate, Pandesara, Choryasi, Surat

Screening & Scoping

Project / Activity No.: 5(f)

M/s: Himalaya Chemicals (herein after Project Proponent – PP) has submitted application vide their letter dated 22/09/2014.

Project Proponent did not remain present in the SEAC meeting dated 08/12/2014.

Project status: Expansion

Project / Activity Details:

This is an existing unit engaged in Dyes intermediates and now proposes for expansion and addition of new products as below:

Sr. No.

Name of Product Existing Capacity

(MT/Month)

Additional Capacity

(MT/Month)

Total after Expansion (MT/Month)

1 Amido G – Salt 10 -- 10

2 Aniline 2 : 5 Disulphonic Acid 20 -- 20

3 Schaffer's Acid 1 -- 1

4 G – Salt -- 9 9

5 Anthranilic Acid -- 50 50

6 5 – Sulpho Antranilic Acid -- 20 20

Total 31 79 110

Total plot area is 2060 sq. m. The total cost of the proposed expansion is 0.5 Crores. Total

water consumption after proposed expansion will be 42.14 KL/day (Existing: 13.5 KL/day +

Proposed: 28.64 KL/day). Fresh water will be sourced from GIDC water supply. Total industrial

Page 49: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 49 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 49 of 70

effluent generation will be 56.04 KL/day (Existing: 8 KL/day + Proposed: 48.04 KL/day) which

will be treated in existing ETP. Dilute stream effluent ( 16.14 KL/day) generated from

manufacturing of Amido G – Salt, Schaeffer’s Acid and Aniline 2, 5 Disulphonic Acid, Boiler,

cooling, scrubber and washing will be treated in primary ETP and effluent will be sent to CETP

of M/s. Globe Enviro Care Limited for further treatment and final disposal. Concentrated effluent

stream (39.9 KL/day) generated from the manufacturing of G – Salt, Anthranilic Acid and 5 –

Sulfo Anthranilic Acid will be sent to their own MEE or Common MEE of MEPPL, Sachin.

Domestic waste water will be disposed off into septic tank/soak pit system. At present unit is a

member of CETP of Pandesara. At present Briquettes of Bio coal (200 Kg/day) is used as fuel

in one TFH (1 Lac Kcal/hr) and one HAG. Unit has provided one DG set. Now unit has

proposed one Boiler (0.6 TPH). Bio-coal (600 Kg/day) will be used as fuel in proposed Boiler.

Hazardous waste to be generated are ETP sludge (15 MT/Year), Process sludge (125

MT/Month), Used Oil (0.245 MT/Year), MEE salt (20 MT/Month) and Discarded

containers/Bags/Liners (4.84 MT/Year).

Observations/Discussions:

Technical presentation by the PP included general information, details of products and raw

materials, Waste generation, hazards & control, analysis of pollution parameters before and

after treatment, resource consumption and conservation, Risk estimation etc. On asking about

legal notices issued by GPCB, PP informed that they have been issued two notices by GPCB in

year 2011-12 and they have taken corrective action thereof. Issues related to safety aspects of

Oleum, Chlorine & other hazardous/toxic chemicals and segregation of effluent streams were

discussed in detail. After detailed discussion, the following additional Terms of Reference were

prescribed for the EIA study to be done covering 5 Km radial distance from the project

boundary.

1. Need for the proposed expansion should be justified in detail.

2. Demarcation of proposed expansion activities in lay out of the existing premises. Layout maps indicating existing unit as well as proposed unit indicating storage area, plant area, greenbelt area, utilities etc. Lay out of industrial area (GIDC) indicating location of unit within the Industrial area/Estate.

3. Exact details about additional infrastructural facilities, plant machineries etc. required for the proposed expansion

4. Detailed manufacturing process along with chemical reactions and mass balance (including reuse-recycle, if any).

5. Assessment of source of the water supply with adequacy of the same to meet with the requirements for the proposed expansion. Copy of permission obtained from GIDC/SMC for additional water supply.

6. Water consumption and consumption of each raw material per MT of each product.

7. Water balance diagram (including reuse-recycle, if any) along with qualitative and quantitative analysis of the each waste stream to be generated. A detailed treatability study

Page 50: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 50 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 50 of 70

vis-à-vis the adequacy and efficacy of the treatment facilities proposed for the wastewater to be generated.

8. Characteristics of the combined effluent and treated water to be sent to CETP of PIL.

9. Complete waste water management plan for existing as well as proposed production. Detailed effluent treatment scheme and disposal method.

10. Technical details of the ETP including size of each unit, retention time etc. including modifications / up gradation to be done in existing ETP to take care of increased effluent quantity along with its adequacy report. Provision of online continuous pH meter, TOC analyser and flow meter at the final outlet of the ETP with an arrangement to reflect the results on company's server, which can be accessed by the GPCB on real time basis along with the time bound program for installation of the same.

11. Details of CETP of PIL (1) Capacity of the CETP (2) Booked and spare capacity of CETP (3) Mode of transportation of waste water from industry to common facility (4) Manifest system for sending waste water to common facility and record keeping, (5) Acceptance criteria of common facility and copy of terms & conditions etc.

12. Technical details of the MEE including evaporation capacity, steam required for evaporation, adequacy of the boilers to supply steam for evaporation in addition to the steam required for the process etc.

13. Details of common MEE (Multiple Effect Evaporator) of NEPL like (1) Capacity of the MEE, (2) Booked and spare capacity of MEE, (3) Mode of transportation of waste water from industry to common facility (4) Manifest system for sending waste water to common facility and record keeping, (5) Acceptance criteria of common facility and copy of terms & conditions.

14. Plan for management and disposal of waste streams to be generated from spillage, leakages, occasional reactor washing and exhausted media from Scrubber etc.

15. Explore the possibility of reuse / recycle and other cleaner production options for reduction of wastes. Details of methods to be adopted for the water conservation.

16. One season site-specific meteorological data including temperature, relative humidity, hourly wind speed and direction and rainfall shall be provided.

17. Anticipated environmental impacts due to the proposed project/production may be evaluated for significance and based on corresponding likely impacts VECs (Valued Environmental Components) may be identified. Baseline studies may be conducted within the study area of 5 km for all the concerned/identified VECs and likely impacts will have to be assessed for their magnitude in order to identify mitigation measures.

18. One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall be in accordance with the revised National Ambient Air Quality Standards as well as project specific parameters. The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors. There should be at least one monitoring station in the upwind direction. There should be at least one monitoring station in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.

Page 51: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 51 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 51 of 70

19. Modelling indicating the likely impact on ambient air quality due to proposed activities. The details of model used and input parameters used for modelling should be provided. The air quality contours may be shown on location map clearly indicating the location of project site, habitation, sensitive receptors, if any. The wind rose showing pre-dominant wind direction should also be indicated on the map. Impact due to vehicular movement shall also be included into the prediction using suitable model. Results of Air dispersion modelling should be superimposed on satellite image / geographical area map.

20. Specific details of (i) Process gas emission from each unit process with its quantification, (ii) Air pollution Control Measures proposed for process gas emission, (iii) Adequacy of the air pollution control measures for process gas emission measures to achieve the GPCB norms (iv) Details of the utilities required (v) Type and quantity of fuel to be used for each utility (vi) Flue gas emission rate emission from each utility (vii) Air Pollution Control Measures proposed to each of the utility along with its adequacy (viii) List the sources of fugitive emission along with its quantification and proposed measures to control it.

21. Details on management of the hazardous wastes to be generated from the project stating detail of storage area for each type of waste, its handling, its utilization and disposal etc. How the manual handling of the hazardous wastes will be minimized.

22. Methodology of de-contamination and disposal of discarded containers and its record keeping.

23. Membership of Common Environmental Infrastructure including the CETP, TSDF / Common Hazardous Waste Incineration Facility (CHWIF), Common MEE along with an assessment to accommodate the additional quantity of wastes to be generated.

24. Complete Management plan for By-products/Spent acids to be generated from the project including their quantity, quality, characteristics, end use etc. along with the name and address of end consumers to whom the by-product will be sold. Copies of agreement / MoU / letter of intent from them, showing their willingness to purchase said by-product from the proposed project. Also give characteristics of the by products and feasibility of their actual use in respective products as a raw material.

25. Name and quantity of each type of solvents to be used for proposed production. Details of solvent recovery system including mass balance, solvent loss, recovery efficiency feasibility of reusing the recovered solvents etc. for each type of solvent.

26. Data on air emissions, wastewater generation and solid / hazardous waste generation and management for the existing plant should also be incorporated. (Comparative data in tabular format).

27. Details of measures proposed for the noise pollution abatement and its monitoring.

28. A detailed EMP including the protection and mitigation measures for impact on human health and environment as well as detailed monitoring plan and environmental management cell proposed for implementation and monitoring of EMP. The EMP should also include the concept of waste-minimization, recycle/reuse/recover techniques, energy conservation, and natural resource conservation. Total capital cost and recurring cost/annum earmarked for environment pollution control measures.

29. Permission from PESO, Nagpur for storage of solvents, other toxic chemicals, if any.

Page 52: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 52 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 52 of 70

30. Occupational health impacts on the workers and mitigation measures proposed to avoid the human health hazards along with the personal protective equipment (PPE) to be provided to the workers. Provision of industrial hygienist and monitoring of the occupational injury to workers as well as impact on the workers. Plan for periodic medical check up of the workers exposed. Details of work place ambient air quality monitoring plan as per Gujarat Factories Rules.

31. MSDS of all the raw materials and products.

32. Details of hazardous characteristics and toxicity of raw materials and products to be handled and the control measures proposed to ensure safety and avoid the human health impact.

33. Details of quantity of each hazardous chemical to be stored, material of construction of major hazardous chemical storage tanks, threshold storage quantity as per schedules of Manufacture, Storage & Import of Hazardous Chemicals (MSIHC) Rules of major hazardous chemicals.

34. Details of the separate isolated storage area for flammable chemicals. Details of flame proof electrical fittings, DCP extinguishers and other safety measures proposed. Detailed fire control plan for flammable substances and processes showing hydrant pipeline network, provision of DG Sets, fire pumps, jockey pump, toxic gas detectors etc.

35. Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios should be carried out. The worst-case scenario should take into account the maximum inventory of storage at site at any point of time. The risk contours should be plotted on the map clearly showing which of the facilities and surrounding units would be affected in case of an accident taking place. Based on the same, proposed safeguard measures including On-Site / Off-Site Emergency Plan should be provided.

36. Details of fire fighting system including provision for flame detectors, temperature actuated heat detectors with alarms, automatic sprinkler system, location of fire water tanks & capacity, separate power system for fire fighting, details of qualified and trained fire personnel & their job specifications, nearest fire station & time required to reach the proposed site. Submit line diagram of the fire hydrant network.

37. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE, manufacturing utility staff for safety related measures.

38. Detailed five year greenbelt development program including annual budget, types & number of trees to be planted, area under green belt development [with map], budgetary outlay; along with commitment of the management to carry out the tree plantation activities outside the premises at appropriate places in the nearby areas and elsewhere.

39. Copies of analysis report of the water samples of final outlet of ETP collected by GPCB (Last 3 years).

40. Consent to Establish, Consent to Operate orders obtained in past along with point wise compliance status of all the conditions stipulated therein.

41. Copy of Environmental Clearance obtained for the existing project and a certified report of the status of compliance of the conditions stipulated in the environmental clearance for the existing operation of the project by the Regional Office of the MoEF.

Page 53: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 53 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 53 of 70

42. Records of any legal breach of Environmental laws i.e. details of show- cause notices, closure notices etc. served by the GPCB to the existing unit in last five years and actions taken then after for prevention of pollution.

43. Details of fatal / non-fatal accidents, loss of life or man hours, if any, occurred in the existing unit in last three years and measures proposed to be taken for avoiding reoccurrence of such accidents in future.

44. (a) Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be detailed in the EIA report. (b). Does the Environment Policy prescribe for standard operating process / procedures to bring into focus any infringement / deviation / violation of the environmental or forest norms / conditions ? If so, it may be detailed in the EIA.

45. What is the hierarchical system or administrative order of the company to deal with the environmental issues and for ensuring compliance with the EC conditions. Details of this system may be given.

46. Does the company have a system of reporting of non compliances / violations of environmental norms to the Board of Directors of the company and / or shareholders or stakeholders at large? This reporting mechanism should be detailed in the EIA Report.

47. Certificate of accreditation issued by the NABET, QCI to the environmental consultant should be incorporated in the EIA Report.

48. A tabular chart with index for point-wise compliance of above TORs.

The above mentioned project specific TORs/additional TORs and the model TORs available in

the MoEF’s sector specific EIA Manual for Synthetic Organic Chemical industry shall be

considered as generic TORs for preparation of the EIA report in addition to all the relevant

information as per the generic structure of EIA given in Appendix III in the EIA Notification,

2006. The project shall be appraised on receipt of the final EIA report.

22. Ushanti Colour Chem Pvt. Ltd. C-18, Saykha GIDC,

Ta.: Vagra, Dist.: Bharuch Screening & Scoping

Project / Activity No.: 5(f)

M/s: Ushanti Colour Chem Pvt. Ltd. (herein after Project Proponent – PP) submitted Application vide their letter dated 20/10/2014.

This project was considered in the meeting of the SEAC held on 23/12/2014.

Looking to the product profile, while concerning about the problems of treatability of concentrated effluent & spent acid disposal issues being faced in present scenario as well as in absence of any common infrastructure facility in Saykha Industrial estate, the committee was of the view that manufacturing of such proposals should be considered with Zero Liquid Discharge (ZLD) only.

The project proponent submitted the additional information vide their letter dated 17/03/2015.

Project status: New

Page 54: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 54 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 54 of 70

Project / Activity Details: This is a new unit proposes manufacturing of Synthetic Organic Chemicals (Dyes & Dyes Intermediates) as tabulated below:

Sr. no.

Name of Products Quantity in MT/Month

01 Vinyl Sulphone 300 02 CPC 500 03 Alpha Blue 200 04 Beta Blue 200 05 CPC Green 7 200 06 Dyes 250 07 Direct Turquoise Blue 86 500 08 Direct Turquoise Blue FBL -199 09 Reactive Blue G 10 Reactive Turquoise Blue H5G 11 Reactive Blue 72 12 MPDSA 40 13 DASDA 50 14 MUA 50 15 H-Acid 200 16 Gamma Acid 40 17 Dasa 50 18 FC Acid 40 19 NMJ Acid 25 20 K Acid 50 21 Sulpho Tobias Acid 40

Total 2735 By-products

1 Hydrochloric Acid 75 2 Ammonium Sulphate 17.35 3 Spent Sulphuric Acid 469 4 Ammonium Carbamate 28.60 5 NaOCl 3.5

The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification

2006.

Total plot area is 39794.81 sq. m & unit has proposed 13132 sq mtr area for the green belt

development/Tree plantation. Expected project cost is Rs.15.79 Crores.Total water requirement

for proposed project will be 1023 KL/D (15 :KL/day for Domestic, 50 KL/day for Gardening &

956 KL/day for Industrial). Fresh water requirement will be 413 KL/day which will be sourced

from GIDC water supply. Total 608 KL/day (212 KL from MEE condensate + 368 KL from NF

permeate) of treated effluent will be reused. Ice (203 KL/day) will be used in process. Total

Industrial waste water generation will be 661 KL/day ( 585 KL process + 65 KL washing + 6 KL

Boiler + 5 KL cooling). Total spent acid generation will be 469 KL/day. 104 KL/day of spent acid

will be reused in process and remaining will be sent to authorised actual end-users. High

concentrated stream waste water will be sent to MEE after primary treatment and low

concentrated stream effluent will be sent to ETP (Primary +Secondary + Tertiary) followed by

Page 55: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 55 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 55 of 70

Nano Filter (NF). Reject stream of NF will be sent to MEE. NF treated will be reused in process,

whereas NF rejected will go to evaporator for zero discharge. Domestic waste water (10

KL/day) will be disposed off into soak pit system. Flue gas generation will be from Steam Boiler

(3 TPH), HAG (10 Lac Kcal/hr), TFH (20 Lac Kcal/hr), Incinerator and D.G. sets (250 KVA).

Total Coal/lignite consumption will be 2120 kg/hr for Boiler, HAG and TFH. Unit has proposed

MDC followed by Bag filter as APCM for Boiler, HAG & TFH. FO (40 lit./hr) will be used as fuel

for incinerator/Spray dryer. Unit has proposed Quenching followed by Ventury scrubber as

APCM for Incinerator. HSD (20 lit./hr) will be used as fuel in DG set. Sets of scrubbing systems

will be provided for control of HCL, NH3, SO2, NOx from the different reaction vessels. Wet

scrubber is proposed for control of SPM from spray dryer. Hazardous waste generated from the

manufacturing activity will be ETP sludge (1060 MT/Month), Spent catalyst (XX MT/Year),

Discarded containers/Bags/Liners (18000 no.s/Year) and Used oil (25 lit. /Year).

Observations / Discussion:

Technical presentation by the PP included general information, details of products and raw

materials, Waste generation, hazards & control, analysis of pollution parameters before and

after treatment, resource consumption and conservation, Risk estimation etc. Issues related to

spent acid management, segregation of effluent stream, safety and occupational health and

infrastructure by GIDC etc. were discussed. While discussing about the segregation of waste

streams and zero liquid discharge (ZLD), PP informed that they will segregate each waste

streams at source and will adopt state of the art technology to achieve ZLD. PP also requested

to permit them to discharge the low COD stream to CETP of Saykha whenever it comes in

existence. Committee also emphasized on complete management of by-products and

hazardous waste to be generated from the proposed activities. After deliberation on various

aspects, following additional TOR was prescribed for the EIA study covering 10 km radius of

the project boundary.

1. Copy of plot holding certificate obtained from GIDC Saykha.

2. Present land use pattern of the study area shall be given based on satellite imagery.

3. Layout plan of the factory premises. Provision of separate entry & exit and adequate margin all round the periphery for unobstructed easy movement of the emergency vehicle / fire tenders without reversing back. Mark the same in the plant layout.

4. Technical details of the plant/s along with details on best available technologies (BAT), proposed technology and reasons for selecting the same.

5. Details of manufacturing process / operations of each product along with chemical reactions, mass balance, consumption of raw materials etc. Details on strategy for the implementation of cleaner production activities.

6. Chemical name of each proposed product to be manufactured. Details on end use of each product.

7. Detailed mass balance and water balance (including reuse-recycle, if any) along with qualitative and quantitative analysis of the each waste stream from the processes.

Page 56: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 56 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 56 of 70

8. Assessment of source of the water supply with adequacy of the same to meet with the requirements for the project. Permission obtained from the GIDC for supply of raw water. Undertaking stating that no bore well shall be dug within the premises.

9. Explore the possibility of reuse / recycle and other cleaner production options for reduction of wastes. Details of methods to be adopted for the water conservation.

10. Qualitative and quantitative analysis of waste water to be generated from the manufacturing process of each product to be manufactured along with mass balance.

11. Segregation of waste streams and details on specific treatment and disposal of each stream.

12. Action plan for ‘Zero’ discharge of effluent shall be included.

13. Details of ETP including dimensions of each unit along with schematic flow diagram. Inlet, transitional and treated effluent qualities with specific efficiency of each treatment unit in reduction in respect of all concerned/regulated environmental parameters. Inlet effluent quality should be based on worst case scenario considering production of most polluting products that can be manufactured in the plant concurrently.

14. Technical details of MEE including evaporation capacity, steam required for evaporation, adequacy of the proposed boiler to supply steam for evaporation in addition to the steam required for the process etc. Techno-economical viability of the evaporation system. Control measures proposed for the evaporation system in order to avoid/reduce gaseous emission/VOC from evaporation of industrial effluent containing solvents & other chemicals.

15. Technical details of proposed Incinerator/Spray dryer including capacity, fuel to be used, adequacy etc. Techno-economical viability of the proposed Incinerator. Control measures proposed for the Incinerator in order to avoid/reduce gaseous emission/VOC from incineration of industrial effluent containing solvents & other chemicals.

16. Technical details of RO/NF system.

17. Undertaking stating that a separate electric meter will be provided for the ETP, RO, Incinerator/Spray Dryer & MEE.

18. Economical and technical viability of the effluent treatment system to achieve Zero Liquid Discharge (ZLD).

19. Proposal to provide and maintain separate electric meter, operational logbook for effluent treatment systems, online meters for monitoring of flow, pH, TOC/COD, etc.

20. Application wise break-up of effluent quantity to be recycled / reused in various applications like sprinkling for dust control and green belt development etc. In case of land application, details on availability of sufficient open land for utilizing effluent for plantation / gardening. How it will be ensured that treated effluent won't flow outside the premises linked with storm water during high rainy days.

21. Plans for management, collection and disposal of waste streams to be generated from spillage, leakages, vessel washing, used container washing etc. Measures proposed for preventing effluent discharge during unforeseen circumstances.

22. One season Site-specific micro-meteorological data using temperature, relative

Page 57: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 57 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 57 of 70

humidity, hourly wind speed and direction and rainfall should be incorporated.

23. Anticipated environmental impacts due to the proposed project/production may be evaluated for significance and based on corresponding likely impacts VECs (Valued Environmental Components) may be identified. Baseline studies may be conducted within the study area of 10 km for all the concerned/identified VECs and likely impacts will have to be assessed for their magnitude in order to identify mitigation measures.

24. One complete season base line ambient air quality data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall be in accordance with the revised National Ambient Air Quality Standards as well as project specific parameters. Locations of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors. There should be at least one monitoring station in the upwind direction. There should be at least one monitoring station in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.

25. Modeling indicating the likely impact on ambient air quality due to proposed activities. The details of model used and input parameters used for modeling should be provided. The air quality contours may be shown on location map clearly indicating the location of sensitive receptors, if any, and the habitation. The wind rose showing pre-dominant wind direction should also be indicated on the map. Impact due to vehicular movement shall also be included into the prediction using suitable model. Results of Air dispersion modeling should be superimposed on satellite Image / geographical area map.

26. Base line status of the noise environment, impact of noise on present environment due to the project and proposed measures for noise reduction including engineering controls.

27. Specific details of (i) Process gas emission from each unit process with its quantification, (ii) Air pollution Control Measures proposed for process gas emission, (iii) Adequacy of the air pollution control measures for process gas emission, measures to achieve the GPCB norms (iv) Details of the utilities required (v) Type and quantity of fuel to be used for each utility (vi) Flue gas emission rate from each utility (vii) Air Pollution Control Measures proposed to each of the utility along with its adequacy (viii) List the sources of fugitive emission along with its quantification and proposed measures to control it.

28. Details on management of the hazardous wastes to be generated from the project stating detail of storage area for each type of waste, its handling, its utilization and disposal etc. How the manual handling of the hazardous wastes will be minimized. Methodology of de-contamination and disposal of discarded containers and its record keeping.

29. Membership of Common Environmental Infrastructure including the TSDF / Common Incineration Facility, if any.

30. Complete management plan for By-products/Spent acids to be generated, along with the name and address of end consumers to whom the by-product/s will be sold. Copies of agreement / MoU / letter of intent from them, showing their willingness to purchase said by-products/Spent acids from the proposed project.

Page 58: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 58 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 58 of 70

31. Name and quantity of each type of solvents to be used for proposed production. Details of solvent recovery system including mass balance, solvent loss, recovery efficiency feasibility of reusing the recovered solvents etc. for each type of solvent.

32. A detailed EMP including the protection and mitigation measures for impact on human health and environment as well as detailed monitoring plan and environmental management cell proposed for implementation and monitoring of EMP. The EMP should also include the concept of waste-minimization, recycle/reuse/recover techniques, energy conservation, and natural resource conservation. Total capital cost and recurring cost/annum earmarked for environment pollution control measures.

33. Permission from PESO, Nagpur for storage of solvents, other toxic chemicals, if any.

34. Occupational health impacts on the workers and mitigation measures proposed to avoid the human health hazards along with the personal protective equipment to be provided. Provision of industrial hygienist and monitoring of the occupational injury to workers as well as impact on the workers. Plan for periodic medical checkup of the workers exposed. Details of work place ambient air quality monitoring plan as per Gujarat Factories Rules.

35. Details on volatile organic compounds (VOCs) from the plant operations and occupational safety and health protection measures.

36. Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios should be carried out. The worst-case scenario should take into account the maximum inventory of storage at site at any point of time. The risk contours should be plotted on the plant layout map clearly showing which of the facilities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures including On-Site / Off-Site Emergency Plan should be provided.

37. MSDS of all the products and raw materials.

38. Details of hazardous characteristics and toxicity of raw materials and products to be handled and the control measures proposed to ensure safety and avoid the human health impacts. This shall include the details of Antidotes also.

39. Details of quantity of each hazardous chemical (including solvents) to be stored, Material of Construction of major hazardous chemical storage tanks, dyke details, threshold storage quantity as per schedules of the Manufacture, Storage & Import of Hazardous Chemicals Rules of major hazardous chemicals, size of the biggest storage tank to be provided for each raw material & product etc. How the manual handling of the hazardous chemicals will be minimized?

40. Details of the separate isolated storage area for flammable chemicals. Details of flame proof electrical fittings, DCP extinguishers and other safety measures proposed. Detailed fire control plan for flammable substances and processes showing hydrant pipeline network, provision of DG Sets, fire pumps, jockey pump, toxic gas detectors etc.

41. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE, manufacturing utility staff for safety related measures.

42. Detailed five year greenbelt development program including annual budget, types &

Page 59: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 59 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 59 of 70

number of trees to be planted, area under green belt development [with map], budgetary outlay; along with commitment of the management to carry out the tree plantation activities outside the premises at appropriate places in the nearby areas and elsewhere.

43. Detailed socio-economic development measures including community welfare program most useful in the project area for the overall improvement of the environment. Submit a detailed plan for social corporate responsibilities, with appropriate budgetary provisions for the next five years and activities proposed to be carried out; specific to the current demographic status of the area.

44. A tabular chart for the issues raised and addressed during public hearing/consultation and commitment of the project proponent on the same should be provided. An action plan to address the issues raised during public hearing and the necessary allocation of funds for the same should be provided.

45. (a) Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be detailed in the EIA report. (b). Does the Environment Policy prescribe for standard operating process / procedures to bring into focus any infringement / deviation / violation of the environmental or forest norms / conditions ? If so, it may be detailed in the EIA.

46. What is the hierarchical system or administrative order of the company to deal with the environmental issues and for ensuring compliance with the EC conditions. Details of this system may be given.

47. Does the company have a system of reporting of non compliances / violations of environmental norms to the Board of Directors of the company and / or shareholders or stakeholders at large? This reporting mechanism should be detailed in the EIA Report.

48. Phase wise project implementation schedule with bar chart and time frame, in terms of site development, infrastructure provision, EMS implementation etc.

49. Certificate of accreditation issued by the NABET, QCI to the environmental consultant should be incorporated in the EIA Report.

50. A tabular chart with index for point-wise compliance of above TORs.

The above mentioned project specific TORs/additional TORs and the model TORs available in

the MoEF’s sector specific EIA Manual for synthetic organic chemical industry shall be

considered as generic TORs for preparation of the EIA report in addition to all the relevant

information as per the generic structure of EIA given in Appendix III in the EIA Notification,

2006. The draft EIA report shall be submitted to the Gujarat Pollution Control Board for

conducting the public consultation process as per the provisions of the EIA Notification, 2006.

The project shall be appraised on receipt of the final EIA report.

23. SKZ Properties F.P.No.10,Sub Plot No:10/A,T.P.S>No.10, Rakhiyal, Ahmedabad

Screening & Scoping

Details of the proposed project as presented before the committee is tabulated below:

Sr. No. Particulars Details 1. Proposal is for New Project

Page 60: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 60 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 60 of 70

2. Type of Project Residential cum Commercial 3. Project / Activity

No. [8(a) or 8(b)] 8(a)

4. Name of the project

Proposed Residential cum Commercial

5. Name of Developer

SKZ Properties

6. Estimated Project Cost (Rs. In Crores)

313.25 crore

7. Whether construction work has been initiated at site? If yes, details thereof

No construction activity started

8. Project Details

Permissible Proposed FSI Area(m2) 1,08,745.82 84,929.56 Ground Coverage(m2) 13,775.50 13,775.50 Common Plot Area(m2) 3,703.76 3,703.76 Max. building height(m) --- 39.5

Land / Plot Area (m2) : 37,037.63 FSI area (m2): 84,929.56 Non FSI area (m2):--- Total BUA (m2):1,38,082.04

9. Building Details No. of Buildings: 15 Scope of buildings/blocks:15 No.& size of Residential Units:968 No. & type of Commercial Units:500 Details of amenities if any: ---

10. No. of expected residents / users

5,856

11. Water & waste water details during construction phase

Water requirement (KL/day): 20.25 Source of water: Tanker/AMC Waste water generation quantity (KL/day): 10.53 Mode of disposal: AMC sewer line Details of reuse of water, if any: 4 KL/day for curing

12. Water & waste water details during operation phase

Total water requirement (KL/day):693.0 Fresh water requirement (KL/day):429.0 Source of water: AMC water supply system Waste water generation quantity (KL/day):542 Mode of disposal:STP and surplus Treated sewage into AMC

sewer line In case of STP provision, capacity of STP:600 KL/day STP Technology:Electrolysis Purposes for treated sewage utilization:Flushing & Gardening Quantity of treated sewage to be reused: 1.Gardening (KL/day):15 2. Flushing (KL/day):249 Provision of dual plumbing system (Yes/No): Yes

Page 61: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 61 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 61 of 70

Quantity and type (treated/untreated)of water to be discharged: 254 KL/day of treated sewage to be discharged into the drainage line of AMC

Mode of disposal: AMC sewer line. 13. Status of water

supply and drainage line

AMC drainage line and water supply line, both area available in the area.

14. Solid waste Management

Construction Phase: Generation

(m3) Quantity to be reused (m3)

Mode of Disposal / Reuse

Top Soil 4,650 4,650 Greenbelt development

Other excavated earth

88,350 39,060 Internal roads and other paved area, back filling

Construction debris

500 250 Back filling and internal road development

Steel scrap 22 --- Sold to vendors

Discarded packing materials

15 ---- Sold to vendors

Remaining quantity of excavated earth and construction debris will be used for back filling for the other projects in the vicinity as well as road development outside the premises. Operation Phase: Type of waste

Generation Quantity (Kg/day)

Mode of waste collection

Mode of Disposal / Reuse

Dry waste & Wet waste

3214 Bio degradable waste will be disposed into near by bins and non biodegradable waste will be sold to vendors

Details of segregation if to be done: Green bins for bio degradable waste& White bins for non‐biodegradable waste.

Capacity and no. of community bins to be placed within premises: Total 3200 bins provided with 5 litre to 25 litre capacity

Landfill site where waste will be ultimately disposed by local authority: nearby MSW landfill/dumping site of AMC.

15. Parking Details Total parking area requirement for the project as per GDCR:17,604.71 m2

Page 62: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 62 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 62 of 70

Parking area requirement for residential units as per GDCR:7,874.15

Parking area requirement for Commercial units as per GDCR:9,730.56 m2

Total number of CPS requirement for the project as per NBC: 1133 CPS

Number of CPS requirement for residential units as per NBC: 484

Number of CPS requirement for commercial units as per NBC:649 CPS

Total Parking area provided (m2) & No. of CPS: Area – 39,828.95 m2 , CPS - 1313

Parking area provided in basement (m2) & No. of CPS: 31,425.34 m2 , CPS - 982

Parking area provided in hollow plinth (m2) & No. of CPS: 4,401.61 m2 , CPS - 157

Parking area provided as open surface (m2) & No. of CPS: 4,002 m2, CPS – 174.

16. Traffic Management

Width of adjacent public roads:30 m on Southern and 30 m on Eastern side

Number of Entry & Exit provided on approach road/s: 5 gates will be provided

Width of Entry & Exit provided on approach road/s:6 m & 9 m Minimum width of open path all around the buildings for easy

access of fire tender(excluding the width forthe plantation): 6 m Width of all internal roads: 6.0 m, 7.5 m and 9.0 m.

17. Details of Green Building measures proposed.

----

18. Energy Requirement, Source and Conservation

Power supply: Maximum demand:7500 KVA Connected load:---- Source:Torrent Power

Energy saving measures: maximum use of natural light through architectural design, use of energy efficient motor and pumps, maximum use of aerated blocks, use of CFL & low voltage lighting, solarlighting in open and landscape areas, rooftop thermal insulation

DG Sets: No. and capacity of the DG sets:2 X 125 KVA Fuel & its quantity: HSD 50 litre/hr

19. Fire and Life Safety Measures

Fire extinguishers, hose reel, wet riser, automatic sprinkler system (basement), manually operated electric fire alarm system, automatic detection and fire alarm system, pump capacity near underground static water storage tank with minimum pressure of 3.5 kg/cm2.

Name of the nearest fire station: Odhav and Maninagar Distance from the project site: About 3.8 Km Time required by the fire tender to reach the project site: 20

minutes. 20. Details on staircase

Page 63: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 63 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 63 of 70

Block Max. Height (m)

No. of Floors

Floor Area (m2)

Number of stair case

Stair case width (m)

Travel distance m

AA 15 B+G+ 4 1766.02 2 1.5

27 m

AB 15 B+G+ 4 1766.02 2 1.5

AC 12 B+G+ 3 785.32 2 1.5

AD 12 B +G+3 705.96 2 1.5

AE 12 B+G+ 3 785.32 2 1.5

AF 12 B+G+ 3 705.96 2 1.5

BA 39.5 B+P+12 396.36 2 2.0

25 m

BB 39.5 B+P+12 396.36 2 2.0

BC 39.5 B+P+12 396.36 2 2.0

BD 39.5 B + P+12 396.36 2 2.0

CA 39.5 B+P+12 381.20 1 2.0

CB 39.5 B + P+12 381.20 1 2.0

CC 39.5 B+P+12 381.20 1 2.0

CD 39.5 B+P+12 381.20 1 2.0

CE 39.5 B+P+12 381.20 1 2.0

21. Rain Water Harvesting (RWH)

Level of the Ground water table: ---- No. & dimensions of RWH tank(s) : ---- No. and depth of percolations wells :10 Details on Pre-treatment facilities:Desilting cum filter chamber.

22. Green area details

Tree covered area (m2) :1,700 Area covered by shrubs, bushes and lawn (m2):2,003.76 Total Green Area (m2):3,703.76 Green Area % of plot area: 10 No. of trees and species to be planted:500

23.

Budgetary allocation for Environmental Management Plan (Rs. in lacs)

-----

24. Proposed dust control measures during the construction phase

Dust suppression by spraying of water,Peripheral barricading the project site, covering the construction material during transportation and storage, compaction of soil during various construction activities

25. Use of Eco-friendly building materials

Fly ash bricks, fly ash blended concrete blocks, fly ash paving blocks.

26. Documents Village form no 7/12 shows the land in the name of M/s SKZ

Page 64: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 64 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 64 of 70

Following projects were also discussed during the meeting: 1. Bhadbhut Barrage Project Latitude-220 39’ 47.36”, Longitude:720 47’ 54.89

Bhadbhut, Ta.: Vagra, Dist. Bharuch

The project was considered for screening /scoping in the meeting of the SEAC held on 05/01/2012. After detailed deliberation, certain additional TORs were prescribed for the EIA study. Subsequently, additional TOR were also prescribed in the meeting of the SEAC held on 06/02/2013. Public hearing for the project was organized by the GPCB on 19/07/2013 at Bhadbhut village. Final EIA and Risk Assessment report of the project prepared by CSIR-NEERI, Nagpur was submitted in February, 2014. The project proponent was called for appraisal of the project in the meeting of SEAC held on 31/07/2014 and during the meeting held on 31/07/2014 after deliberation on various aspects, it was decided to appraise the project further after satisfactory submission of certain additional information / documents. The project proponent submitted the details vide their letter dated 29/01/2015.

The project proponent along with their expert/consultants attended the meeting of SEAC held on 10/03/2015. During the meeting the project was further appraised based on the details submitted as well as facts presented before the committee.

It was presented that the barrage left bank approach is 7.29 km long for which 11.7494 ha Govt. land, 31.4 ha forest land and 1.8484 ha private land are required. Kalpsar department has proposed that an equal area of government land from the proposed Gir Lion Corridor in Bhavnagar district will be handed over to the Forest department. Project proponent has identified the land in village: Tol Saladi (survey no. 87/A/1), Ta.: Jesar as compensation land against the forest land required for the proposed Bhadbhut barrage. This land is acquired and handed over to Forest Dept for the purpose of extension of Gir Lion corridor. The Dy.

related to land possession.

properties Ltd.,

27. Basic amenities to be provided to construction workers

Sanitation facilities for workers and staff members, first aid & doctor facilities, drinking water, personal protective equipments, training to the workers related to construction safety & environmental aspects etc.

During the meeting, the project proponent was asked to operate and maintain the proposed STP regularly. Further they were suggested to increase the parking area provision for the proposed project and the project proponent was agreed upon the suggestion. After detailed discussion it was decided to consider the project only after submission of the following:

1. Revised details on increased parking area provision with complete back up calculation showing parking area to be provided in basement, hollow plinth and as open surface.

The following proponents did not remain present during the meeting 1. Hasmukh Dhaduk, Block No:208, O.P.No. 86,F.P.No.118, T.P.S.No.9(Palanpore- Bhesan),

Palanpore, Surat. 2. RNA Developers, TP-5(Athwa-Umara),C.S. No.248-251 & 253-260, O.P.No.84, F.P.No.

84/A/P +84/B/P,Parlr Point, Athwa-Umara, Choryasi, Surat It was decided to call them in one of the upcoming meetings of SEAC.

Page 65: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 65 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 65 of 70

Conservator of Forest, Bharuch will submit the proposal to the state Forest Department for their recommendation and onward submission to the committee of secretaries, Regional Office, Bhopal for final approval. During the meeting, after detailed discussion it was decided to consider the project only after obtaining status of forestry clearance of the forest land required for Barrage left bank flood protection embankment from Kalpsar department. Kalpsar department vide their letter dated 04/04/2015 submitted that total of 183.5521 ha forest land is involved in the proposed barrage project i.e for the construction of left bank approach road and forest land is going under submergence due to the proposed barrage project. As per original proposal, requirement of forest land for construction of approach road embankment was 31.40 ha and for construction of flood protection embankment was 15 ha. It was mentioned that the details submitted earlier was prepared based on the preliminary design and GIS maps/data available at that time.

The matter was discussed during the meeting & it was found that instead of involvement of total 46.4 ha (31.4 ha +15 ha) of forest land as proposed earlier, the total forest land involved in the proposed barrage project is 183.5521 ha. as per the submission of the Kalpsar Department dated 04/04/2015. Considering the fact the committee took note of the MoEF&CC’s O.M. dated 09/09/2011 which states that

“At the stage of consideration of proposals for EC in respect of projects involving forestland, the project proponent would inform the respective EACs about the status of their application for forestry clearance along with necessary supporting documents from the concerned Forest Authorities. It will clearly be informed to the EAC whether the application is at the State level or at the Central level. The EAC will take cognizance of the involvement of forestland and its status in terms of forestry clearance and make their recommendations on the project on its merits. After the EAC has recommended the project for environmental clearance, it would be processed on file for obtaining decision of the Competent Authority for grant of environmental clearance. In the cases where the Competent Authority has approved the grant of environmental clearance, the proponent will be informed of the same and a time limit of 12 months, which may be extended in exceptional circumstances to 18 months, a decision on which will be taken by the Competent Authority, will be given to the proponent to submit the requisite stage-I forestry clearance. The formal environmental clearance will be issued only after the stage-I forestry clearance has been submitted by the proponent.”

In view of the above the Committee felt that a credible proof in support of the fact that they have already submitted their application to the concerned Competent Authority for diversion of the total forestland involved in the project and information regarding the status of their application (i.e whether the application is at the State level or at the Central level) for forestry clearance along with necessary supporting documents from the concerned Forest Authorities should be sought from the Kalpsar Department for further processing of the application and to inform the Kalpsar Department accordingly.

After detailed discussion it was unanimously decided to consider the project only after submission of the following information from the Kalpsar Department.

1. Exact details on component wise total forest land involved in the project, a credible proof in support of the fact that they have already submitted their application to the concerned

Page 66: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 66 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 66 of 70

Competent Authority for diversion of the total forestland involved in the project and information regarding the status of their application (i.e whether the application is at the State level or at the Central level) for forestry clearance along with necessary supporting documents from the concerned Forest Authorities.

2. Jetpur Dyeing & Printing Association Jetpur Dyeing and Printing Association, Kanakia Plot, Jetpur, Dist: Rajkot.

Earlier this case was taken in the SEAC meeting dated 24/03/2015 for extension of validity of Environmental Clearance vide their letter dated 13/08/2014. SEIAA, Gujarat has accorded Environmental clearance to M/s: Jetpur Dyeing and Printing Association (JDPA) for setting up of Common Effluent Treatment Plant vide vide letter no. SEIAA/GUJ/EC/7(h)/246/2009, dated 01/09/2009.

During the meeting on 24/03/2015, Committee asked the reason for not starting the work at

village Derdi. PP informed that, they could not start the construction work at vill. Derdi due to

objection raised by the people of Vill. Derdi and matter is pending with Honorable High Court of

Gujarat. Committee referred the Honorable High Court order dated 03/02/2015. According to

the Honourable High Court order dated 03/02/2015, the Honourable court extended one

opportunity to the respondents i.e. JDPA to comply with the direction with regard to the Derdi or

to submit alternative plan. The committee was of the view that the issues have been raised as

far as the village Derdi was concern, before consideration of the case for extension of validity of

environmental clearance, Jetpur Dyeing and Printing Association (JDPA) should submit the

documents showing that there is no dispute in the vicinity especially by the farmers for the

CETP.

After detailed deliberations the Committee unanimously decided for further consideration of

their case for extension of validity of environmental clearance only after satisfactory submission

of the following:

An affidavit from the People of Derdi village regarding “No Objection” for this proposed

CETP at village Derdi.

Now Project proponent has submitted an affidavit from the People of Derdi village regarding “No

Objection” for this proposed CETP at village Derdi vide their letter no. NIL dated 20/04/2015.

The said submission by the project proponent was considered by the committee during the meeting and as it was found satisfactory, the committee decided to extend the validity of the environmental clearance. 3. Earlier in various meetings, following projects were issued ToR with Public Hearing as per the Ministry’s O.M. dated 16/05/2014 as provided under para7(i) III.Stage(3)(i)(b) of EIA Notification, 2006. Now as per the MoEF&CC’s O.M. dated 10/12/2014, the exemption from the public consultation, as provided under para 7(i) III. Stage (3) (i) (b) of EIA Notification, 2006 is available to the projects or activities or units located within the Industrial Estates or Parks, which were notified prior to 14.09.2006, i.e. the EIA Notification, 2006 coming in to force.

Committee also took notice of one of the ToR issued by MoEF&CC in case of M/s: Anvitha Life Care, plot no. 6, industrial park, Attivaram village, Ozili Mandal, SPSR Nellore district, Andhra Pradesh vide no. J-11011/177/2014-IA II (I) dated January, 2015 which states that “The project may be exempted from public hearing as per Ministry”s O.M. dated 10.12.2014 subject to submission of authenticated documents showing industrial estate has been established by the

Page 67: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 67 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 67 of 70

state prior to 2006 or has been obtained EC after 2006.”

In view of the above, It was decided to exempt the following projects from carrying out public consultation as per the said O.M. dated 10/12/2014.

Sr. no.

Name & Address of the Industry Date of ToR issued

1. Panoli Intermediates India Ltd Plot Number: 158, GIDC Nandesari, Dist: Vadodara.

13.06.2014

2. Lion Tapes Pvt. Ltd., P.No:293, GIDC Chitra Estate, Bhavnagar.

24.06.2014

3. Pharma Interchemie (Unit-II), Plot No. 139, 140, GIDC estate Nandesari, Dist: Vadodara.

24.06.2014

4. Aarti Industries Ltd., Unit-III, Plot No.756/6, GIDC Jhagadia, Dist:Bharuch.

31.07.2014

5. BMS Chemie, Plot no. 47/1/16 & 17, GIDC Nandesari, Vill.Nandesari, Ta. & Dist. Vadodara.

31.07.2014

6. Panchsheel Intermediates, Plot No:8101, Sachin, GIDC, Dist.:Surat.

31.07.2014

7. Sun Light Pigments, Plot No:48/1&48/2, GIDC-Kalol, Kalol, Dist.: Gandhinagar… Appraisal Case

31.07.2014

8. Gujara State Fertilizers & Chemicals Ltd. (GSFC) P.O.Fertilizernagar, Vadodara.

31.07.2014

9. KLJ Organic Limited (Unit II), Plot no.760 GIDC industrial Estate, Jhagadia, Dist.: Bharuch.

31.07.2014

10. Philoden Agrochem Pvt.Ltd, Plot no.145,GIDC-Nandesari, Dist.: Vadodara

11.09.2014

11. Amophil Chemicals Pvt.Ltd, Plot no. 124/33 A&B, GIDC-Nandesari, Dist.: Vadodara

11.09.2014

12. Nutan Dye Chem, Plot no. 2428,GIDC-Sachin, Ta: Choryasi, Dist.: Surat

11.09.2014

13. Shree Arihant Dye Chem, Plot no. 8107,GIDC-Sachin, Ta: Choryasi, Dist.: Surat

11.09.2014

14. Mascot Industries, Plot No:C-1/B/1306/ 3, Phase-IV, Naroda, GIDC, Ahmedabad.

18.10.2014

15. Aeidan Industries, Plot No. 769/6, Jhagadiya Industrial Estate, Taluka Jhagadia, Dist: Bharuch

18.10.2014

16. Jayvir Dyechem, 314/1/1/B & C,GIDC Estate, Phas-I, Naroda, Ahmedabad

05.12.2014

17. Aarti Drugs Limited, Plot No:2902,2904,2601, 2602,2603,2604,2605,2509, GIDC-Sarigam, Ta: Umbergam, Dist.:Valsad

05.12.2014

Page 68: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 68 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 68 of 70

18. Kosha Chem Tech Pvt. Ltd., 7119,7120,7121,7122, GIDC Sachin, Ta.: Choryasi, Dist.: Surat

05.12.2014

19. Shree Arihant Colours, A2-7113, Sachin GIDC, Ta.:Coryasi, Dist.: Surat-395230

05.12.2014

20. Anupam Rasayan India Ltd. (Unit-4) (Formerly known as:M/s.Krishna Solvechem, Plot No:907/3, GIDC-Jhagadia, Bharuch

23.12.2014

21. Anupam Rasayan India Ltd. (Unit-5) (Formerly known as: M/s. Dhruv Intermediates Pvt. Ltd.), Plot No:827, Jhagadia Industrial Estate, Jhagadia-393110, Bharuch

23.12.2014

22. Essar Power Limited, Survey no. 353-A-1-A-1, 354-A, 353-A-1-A-2, Sub Survey no. 174/A/1, 175/A, 104/A/1/A/2, Hazira Notified Area, Hazira, Choryasi, Dist.: Surat.

02.02.2015

23. Bhander Power Limited, Survey no. 353-A-1A-1/2, 354-2, Sub Survey no. 174/A1/A/1/2, 174/P2, Hazira Notified Area, Hazira, Ta: Choryasi, Dist. Surat

02.02.2015

4. Slum Rehabilitation Scheme by M/s

Safal Constructions Pvt. Ltd. F.P.No.190, T.P.S.No.3 (Shekpur-Khanpur), Lakhudi na Chhapra, Naranpura Ahmedabad

The project was taken up in the SEAC meeting held on 05/12/2014 and during the meeting considering the merits of the case, after detailed discussion, it was decided to recommend the project to SEIAA Gujarat for grant of Environmental Clearance. Meanwhile it was brought to the notice of the committee that the project proponent has already started construction activity at the proposed site and the same was also confirmed though the Regional Office-Ahmedabad of Gujarat Pollution Control Board. The matter was discussed during the meeting that though it was decided to recommend the project to SEIAA Gujarat for grant of Environmental Clearance during the meeting of SEAC held on 09/02/2015, as the project proponent violated the provisions of EIA Notification-2006 by initiating the construction activity at the proposed site, it was unanimously decided to consider the project only after submission of a formal resolution and after following the procedure depicted in the MoEF’s Office Memorandum No. J-11013/41/2006-IA.II (I) dtd. 12/12/2012. As the legal action has been initiated against the violation taken place and the project proponent submitted a copy of formal resolution, the committee, based on the merits of the case, decided to recommend the project to SEIAA, Gujarat for grant of Environmental Clearance. 5. The additional information received from the project proponents, which was sought

during various SEAC meetings for granting Environmental Clearance to the projects. The said submissions by the project proponents were considered by the committee during the meeting and as it was found satisfactory, the committee decided to recommend the following projects for grant of environmental clearance.

Sr.no Name & address of the project 1. Silver Business Point Cross Road (Silver Enterprise)

Block No:85,O.P.No 5,F.P.No.5+Block No.124/B,O.P.No.26/2,F.P.No.29,National plot No-2&1,At Preli,T.P.S.No.2 7,Utran-Kosad, Choryasi, Surat

Page 69: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 69 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 69 of 70

2. Hitendrabhai D.Patel, F.P.No.33, O.P.No.33, New R.S.No.234 (Old R.S.No.344), Moje-Vesu, Draft T.P.S.No. 75,(Vesu-Megdalla-Gavier-Abhava),Surat.

3. LIG & MIG Project (Residential cum Commercial), Jahangirabad, Block No: 40,41,43, Surat

4. Palak Classic, S.No.372, F.P.No.62, T.P.S.No.51(Bodakdev Makaraba-Vejalpur) Vejalpur-Jodhpur, Ahmedabad

5. Rushabhdev Infra Project Ltd.(Residentional cum Commercial Project, R.S.No.196/1,196/2+196/3,196/4, F.P.No.2+3+ 4,O.P.No.2+3+4, Draft T.P.S.No.74, Chandkheda,Ahmedabad.

6. Radhika Residency & Point, R.S.No.1218, Block No. 1161, O.P.No.36, F.P.No.47, P T..S.No.37, Variyav, Surat

7. LIG & MIG Project (Residential cum Commercial), Gorwa, S.No.258,259, Vadodara.

8. Proposed Group Housing & Commercial Projects (Tensile Steel Ltd.) Ansal F.P.No.150, T.P. No.19(Final), Manjalpur, Vadodara

9. Aswani Developers, Vesu, R.S.No.98/1, F.P.No.172,T.P.S.No.2 Surat

10. Amit Girishbhai Shah (Residential Project), Block No:114/p/10 to 114/p/11, O.P. No.120, 138, S.No.278/4,281, 305/1/B/p, Draft TPS No.35, Jambus,` Vadodara

11. Commercial Project (Nareshbhai Maneklal Patel), S.No.100/1/2,F.P.No.81,Draft T.P.S.No.31, Vastrapur, Ahmedabad

12. Prathna Elegance, S.No.230/2/2,F.P.No.56/1/2,O.P.No.56/1/2,Draft T.P.S.No.33, Gota, Ahmedabad

13. M/S khandwala & javeri Devlopers, S.N.02/1,jodhapur,Ahmedabad

14. Shree Narayan Exotica, F.P.No.78, Memnagar, Ahmedabad

15. Rushabhdev Infra Project Ltd., (Commercial Project), S.No.193,FP No.141,OP No.141, Draft TPS No.74 (Chandkheda-Zundal-Tragad),Zundal, Gandhinagar

16. Skyline Business Park (Radiance Infra Project) S.No.186/1,F.P.No.1/1,O.P.No.1/1,T.P.S.No.62, Narol, Ahmedabad

17. Ambika Pinnacle, Shakti Construction, T.P.S.No.18, F.P.No.48,49,50,51, O.P.No. 48/1,48/2,48/3,48/4, R.S.No.102/A,102/B,102/C,102/D, Mota Varacha, Choryasi, Surat

Meeting ended with thanks to the Chair and the Members.

--------------------------------

Page 70: Minutes of the 236th meeting of the State Level Expert Appraisal

Page 70 of 70

(236th meeting of SEAC-Gujarat, Dated 29.04.2015) Page 70 of 70

Minutes approved by:

1. Shri T. P. Singh, Chairman, SEAC.

2. Shri V. C. Soni, Member, SEAC.

3. Dr. Nikhil Desai, Member, SEAC.

4. Dr. V. K. Jain. Member, SEAC.

5. Dr. Mayuri Pandya, Member, SEAC.

6. Shri Natarajan Pratap, Member, SEAC.

7. Shri V.N.Patel, Member, SEAC.

8. Shri R. J. Shah, Member, SEAC.

9. Shri K. C. Mistry, Secretary, SEAC.