MINUTES OF ELEVENTH COORDINATION MEETING (06/01/2015)
Following issues of effective coordination for development of Mumbai were discussed and status of work clarified as follows:-
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
1 MMRDA CR / WR
CBE
A. Proposed construction of elevated connecter between Bandra-Kurla
complex and Eastern express
highway. 1. GAD for ROB between Kurla &
Sion. 2. GAD for ROB for Chunabhatti
Railway Station.
3. GAD for ROB near Chunabhatti Railway station. In lieu of L-xing
No. 1/T.
MMRDA suggested on 23.09.2014 that proposed elevated corridor (CSTM-Panvel) may
be raised at Chunabhatti to the same level as at
Kurla to enable ROB 2 & ROB 3 at Chunabhatti to remain underneath. MRVC agreed. MMRDA
was to give detailed proposal. Part proposal given by MMRDA on 14.10.14. PDC 30.10.14.
New PDC 17/11/14.
Drawings received from MMRDA on 18.11.14. Approved by DRM,COM,CEE,CSTE.
Approval of CAO/C & CBE will be done by 8/1/15.
Sion bridge GAD will be cleared by 23/12/14
(CBE) . In complete level of upto 21 M is
agreed for CSTM-Panvel Corridor. Three designers shall sit together & finalise this by
25/12/14. Chunabhatti level crossing shall be closed with this solution.
Chunabhatti GADs received and approved
by DRM, HQr approval by 20/1/15.
2 MMRDA
CR
CBE
Mumbai -Trans Harbour links (MTHL)
Approval of GAD’s of ROB’s over Central Railway land at Chirle Mainland Nhava
side Drg. No. 180581/142 sheets, and
2180581/ 1 to 7 sheets.
Observations regarding span arrangement over
running lines conveyed to MMRDA vide letter dated 17.07.2014.
MMRDA was to provide revised GAD of this by 07/10/14.
Now target shifted to 14/10/14. Target busted again. Again PDC fixed at 30.10.14.
PDC 17/11/14. Meeting held on 12/11/14.
Crossings will be with 3 spans. Instead of 5 sets of piers it was decided to submit GAD with
2 sets of piers. CBE: Final GAD from MMRDA is awaited.
PDC 01/01/2015.
Revised PDC 20/1/15
3 MMRDA
CR
Mumbai Monorail Project revised GAD for obligatory span crossing railway track at Currey Road railway station.
Revised GAD approved on 05.08.2014. GAD now under C.R.S. approval. During CRS inspection on 08.09.2014, modification to GAD has been suggested to Monorail Authorities (Mr. Murthy) regarding infringements. Revised GAD received in division sent to CRS on 24.09.2014. CRS sanction received and conveyed to MMRDA.
ITEM CLOSED.
4 MMRDA
CR
DRM/BB
Mumbai Monorail Project obligatory span
crossing railway track crossing Wadala railway yard.
Compliance to CRS observation dated
13.02,2014 submitted to CRS on 16/9/14. Still pending with CRS.
DRM/BB to give fresh application to CRS. Presentation in CRS office fixed today at 1600
Page 2 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
hrs.
DRM BB: Revised GAD approved by
HQ.(25.11.14) During presentation CRS, wanted revised launching scheme from
MMRDA. PDC 01/01/2015. Revised PDC 15/1/15 (MMRDA decided to
discus with CRS)
5 CIDCO CR
CBE
Proposal of crossing of Navi Mumbai Metro line at Taloja station on Diva-
Panvel railway line by DFCCIL.
It is necessary to accord approval by
Railways to the Metro Station No.10,
portion of Depot approach via duct and
the pier at the edge of the railway boundary (to facilitate the NHAI span
crossing) since all these work are away from the operational area of Diva-Panvel
line and it will expedite the execution of
the Metro works held up on the Railway land.
Meeting held between CIDCO & DRM, Central Railway along with other railway officials on
18.09.2014.
Central Railway & DFCC came to an Agreement
on the track layout of their respective track layout at Taloja Station.
Further item was discussed with DRM/BB, CE/CIDCO and PCE with GM/CR on 07.10.2014.
Revised drawing with relocation of RUB at
location of existing LC will be given by CIDCO by 10/10/14. This will permit some more space
for expansion to C.Rly. Meeting in GM’s Room held at 15.30 hours on
07.10.2014. CIDCO submitted revised GAD based on the
discussions by 14/10/14.
PDC for Railways and DFC 26/10/14. Rly gave feedback 22/10/14. GAD by CIDCO to
be given on 25/12/14. Central Railway agreed that the structure of
station No 10 and Depot Approach Viaduct of
Navi Mumbai Metro, located away from the operational area of Diva panel line are
permitted for construction. GM , Central Railway instructed the concerned Railway
officials to release letter by 27/11/14, to commence construction.
Central Railway confirmed that on formal
submission of GAD of superstructure of NM Metro crossing of operational Diva- Panvel line,
the construction of pier of NHA3 crossing stands approved for construction. Since this is
located away from the operational area of Diva-
Panvel line and at edge of Railway Boundary.
CIDCO is requested to expedite submission of GAD of through type girder. In view
ofdelay on part of CIDCO designer, it was
decided today that maintenance agreement will be submitted by Railway
to CIDCO 15/1/15. As soon as agreements is executed by CIDCO, the
construction of Depot, station no 10 and NH crossing can be started.
6 MCGM
CR
Carnac Road Over Bridge & Hancock
ROB: - Rebuilding of Carnac Road over bridge at KMs. 0/1-2 & Hancock Road
over bridge at KMs. 2/6-7.
MCGM has agreed for dismantling of existing
ROBs by Railways at their cost. Estimate for demolition of existing bridge submitted to
MCGM on 30.05.2014 but acceptance is still
Page 3 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
CBE
awaited.
Dismantling scheme of existing ROB has been
submitted on 08.08.2014. MCGM was to approve this by 5/10/14.
CAO (C) CSTM will execute the work of demolition. It was decided to process for CRS
sanction simultaneously for dismantling MCGM submitted the GAD & TAD to Railway for
approval on 14.08.2014 for the new bridges to
be constructed. GAD and TAD returned to MCGM with
observation vide letter no. W.294.Rehab.Genl. dated 20.08.2014 regarding launching.
Revised GAD and TAD was awaited from MCGM
by 15/10/14. Today MCGM clarified that they need approved plan of 5th and 6th line.
MCGM was requested by Railways to delink dismantling from the new bridge in view of
public safety.
Central Railway was to give approved plan of 5th and 6th line plan by 20/10/14. Plan given on
16.10.14. PDC for MCGM 15.11.14. Scrap will be removed by Rlys as cost of scrap
has been subtracted from estimate. Utilities planning in interim to be detailed by
MCGM by 5/12/14.
Rs.2.6 Cr received from MCGM on 27.11.14. Utility shifting – JJ hospital pipe of 300
mm dia and 9 cables of BEST , 3 cables of MTNL be taken along with 900 mm dia
pipe of MCGM pipe bridge 2M away.
Abandoned pipe of 600 mm dia to be thrown.
7 MCGM
CR
CBE
Currey Road ROB & Tilak ROB: -
Proposed strengthening work of Currey
road and Tilak ROB at kms. 6/2-3 and Tilak ROB at kms. 9/5-6.
Estimate amounting for Currey Road ROB
Rs.2,50,91,702/- and for Tilak ROB
Rs.2,35,70,677/- vide letter No. B.W. 3512. Estimate.ROB.Gen.DB. dated 30.06.2014
submitted to MCGM. Not received as per MCGM. To be given again.
Acceptance of estimate awaited from MCGM
TDC 22/10/14. Confirmed today, to be behind schedule. Revised target 7.11.14.
Target Revised again to 26/11/14. Rs 5 Crore will be deposited by 28/11/14.
Rs 2.5 Crs received for Currey Road on 15/12.
PDC for Tilak 22/12/14. Tilak Bridge money ( 2.5 Cr ) received on
25/12/14.
Page 4 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
8 CR
MCGM
GM
Issue of Occupation Certificate for “E”
building at Railway Officer’s Flats at
Nirmal Park, Byculla. Three Meetings already held on the issue with MCGM at
the level of GM and MCGM commissioner.
5% land for amenities was earmarked along
the station road and as BEST service station.
MCGM postponed the targets from 05/10/14 to
30/10/14. Now Railways will be forced to have a relook on rules.
Status: issue is taken up with BEST by MCGM. BEST remarks received. Case being
processed by BMC.
9 CR
MCGM
GM
Approval of layout for proposed
construction of Railway Staff Quarters on
replacement account at Gunpowder road railway colony near Dockyard station.
MCGM has submitted a comprehensive report
with Ch Eng (DP) / MC.
Under process with MCGM. TDC was 30/9/14. No progress by MCGM, will
be taken up after elections. Status: Approval of layout will be issued by
30/11/14.
Letter is yet to be issued.
10 CR
MCGM, GoM
GM
Permission for cutting / transplanting of
62 nos. trees for EMU Carshed at Kurla. Development of maintenance facility for
15 car rakes is held up.
Under process with Municipal secretary.
TDC 5/10/14 New TDC 15/10/14.
Next meeting of committee after election will
clear this. Work sanctioned. Letter likely to be issued in a week. Letter issued on last week of
November. CAO/C: Money has been deposited by Railways
for tree cutting.
Now trees can be cut under supervision of Superintendent of Gardens / Byculla.
ITEM CLOSED
11 CR TMC
CAO /C
For construction of ROB at level crossing no. 29-C at diva station, consent of TMC
for sharing 50 % of the cost of the ROB and approval of the GAD are held up.
Encroachments on the approach road are the main cause of delay. TMC decided to do a
survey and come up with revised plan of action by 15.11.14.
Board meeting of Dec ’14 is likely to clear this
project. None attended from TMC on 6/1/15.
12 CR
KDMC
CAO /C
ROB at level crossing no 47-B between
Shahad- Ambivali station has been
completed in Railway portion but work on the approaches by KDMC is at stand
still.
Contractor of KMDC is not progressing the
work. Due to problem of land acquisition. 12
out of 16 foundation works started, remaining 4 foundations, one will be started by Dec.14.
(One NRC pipeline to be shifted) work of three foundations also started. June 15 requested as
final date.
Land dispute of 2 piers will be solved by KDMC by 3/1/2015. KDMC is negotiating with a
builder (Mr Gadda) who is having one of the two POA of the land lady. Expected
PDC 31/1/15. Approved GAD of 38C (Thakurli
gate) submitted by KDMC on 16/12/14. Rly to clear landing permission in Rly land at Thakurli
by 10/1/15.
Page 5 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
13 CR
GoM/CIDCO
CAO /C
a) Releasing of funds for cost sharing
of railway projects Thane-Turbhe-
Nerul / Vashi and Nerul/Belapur-Seawood-Uran.
The fund utilization statement for Nerul-
Belapur-Uran corridor upto August 2014 was
asked for release of further funds. The fund utilization statement for Nerul-
Belapur-Uran corridor up to August 2014 was given on 15.09.2014 and the process for
release of funds is in progress.
C.Rly will give forecast of fund utilization up to
March 2015 also by 30.9.14 to enable CIDCO to release funds, regularly every month, as
discussed. CIDCO informed Railways that they will have to
submit the proper reconciliation of the funds
duly certified by their Accounts Department to enable Advance Payments made by CIDCO.
TDC for release of funds (24 crores) 10/10/14.
Cheque of 24 Crores received on 14/10/14.
Funds for Seawood – Uran have to be sanctioned by 31/12/14 to avoid break in
progress. Rs. 72 Crore deposited by CIDCO ON 25.11.14.
b) Land acquisition for Nerul/Belapur-
Seawoods – Uran Rly project. (Ch: 8000 to Ch.11000)
This matter is under process with the office of
Collector, Raigad and the Forest department.
The matter is under process with the office of Collector, Raigad and the Forest Dept.
TDC Dec 2014.
CIDCO is chasing actively. PDC of Dec. 14 will be honoured.
a) CIDCO is following up with concerned Land
Acquisition Authority of GoM for Navi Mumbai /
Raigad for expediting acquisition of the private land.
b) CIDCO is also following up for transfer of Forest Land. The matter involves multiple Govt
Departments.
Expected PDC will be given in next
meeting.
c) Approval for revised estimate for
Belapur-Panvel railway project.
Revised cost of Rs. 438 Crores
CIDCO will convey the terms and the approvals
in the week commencing 30/9/14.
Letter issued by CIDCO to Railways on 24.09.2014. Proposal sent to Railway Board on
10.10.14. Board sanction expected by 31/12/14.
CAO ( C) is pursuing with Board.
Page 6 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
14 CR
GoM/CIDCO
GM
Approval for sharing of 2/3rd cost of
project and making required land
available to railways for Panvel coaching complex.
Presentation was given to CIDCO on 04.07.14
as desired. A meeting with Chief Secretary &
CIDCO was also held in July. Draft minutes of the meetings received from CIDCO. GoM
signature still pending.
15 CR CIDCO
GM
Acquisition of land for DFCCIL alignment through Panvel.
The issuance of MoM of the meeting held on 04th July, 2014 in presence of C.S., GoM by PS
(UD-i) office GoM is expected anytime as discussed during Empowerment Committee
meeting on 26.09.14.
16
*
CR MbPT/
MMRDA
CAO/C
Construction of Wadala- Kurla dedicated Goods Line (on deposit terms) is pending
for want of removal of hutments and rehabilitation. Resettlement of the
project affected persons to be done by
MMRDA / MbPT.
237 allotments done out of 1680 encroachments. 150 shifted out of 237. SPARC
(NGO) coordinates. PDC Dec ’14 - given by MMRDA but progress on
ground is not commensurate.
Fresh allotments are held up due to MMRDA. New shifting held up for want of repairs to
tenement by MMRDA. (Civil Engineering Dept). Dy CE MbPT:
Demolition of the hutments vacated by the slum dwellers and construction of the
compound wall along the safety zone is in
progress. Demolition of the huts of the PAPs who have
been allotted the tenements but not shifted from the project site is scheduled on
10.11.2014.
Fresh allotment of tenements held up for want
of repairs to the tenements. CAO/C: Work is held up.
MbPT absent on 16/12/14.
445 allotments done. 220 shifted. 680
tenements repaired. 800 tenements scrutinized.
17
*
CR
GoM/CIDCO
CAO / C
ROB’s in lieu of 13 nos. of Level
Crossings have been sanctioned by Railway Board on cost sharing basis in
connection with DFCCIL alignment.
Sanction of State Government for sharing 50% of the cost is awaited.
6 GADs submitted to CIDCO
(One pertains to MMRDA ) (LC 9 does not pertain to CIDCO area)
(LC 6 near Bomali village needs to be
clarified whether the approach road pertains to PWD or CIDCO)
There are no guidelines regarding cost sharing.
It was decided to technically finalize the GAD drawings of these ROBs without waiting for
clarity on cost sharing.
DFCCIL to get the appropriate letter issued from Board, on cost sharing.
TDC for approval of GADs 30/10/14 (with 4 lane modification). Meeting fixed by CAO/C on
29.10.14. 3 Drawings will be approved by CIDCO by 14/11/14. Rest 3 by 31/12/14.
In the last meeting between CIDCO & C. Rly.
held on 13.11.2014, the nodal drawing of three locations LC 10, LC 20 & LC 23 were given to C.
Rly. to super impose the GAD of the ROB / RUB for checking the junction arrangement details.
Page 7 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
PDC 5/1/15. There is delay of 15 days on both
PDCs due to feedback from DFC.
Progress held up for want of revised Board circular on cost sharing.
18 CR
GoM
GM
` 5 crs out of ` 10.36 crs has been
released. The remaining funds shall also be transferred to Central Railway so that
developmental works for Kumbh Mela at Nasik can be completed without any
delay.
Release of funds expected by 15.10.14. Any
further delay beyond this will entail in discharge
of tenders.
ITEM CLOSED
19 CR
GoM
DRM
NAGOTHANE-ROHA (160KMPH)
LAND ENCROACHMENT & Land
acquisitions
GoM clarified on 23.09.14 that this
encroachment will have to be removed by
Railways only. GoM will, however, provide police bandobast. To be done after elections.
Planned in next 10 days. CAO ( C) to fence & put Cess material on the same day.
Meanwhile a copy of wrongly drawn
minutes was seen. These will be cancelled and as when encroachments are
removed, track will be slewed to increase the speed.
20 CR GoM
GM
Payment of MAHAGENCO: An outstanding of `84.34 Crs on net
demurrage and other charges is pending
with MAHAGENCO for payment to Central Railway.
GoM is requested to offset the electricity bills of Central Railway by the amount of agreed upon
demurrage. Issue is pending for last 18 months. GoM indicated that MAHAGENCO
officers visit CS every Thursday in 2nd half.
CCM/CR to ask for slot on 20/11/14. Meeting cancelled by CS. New date awaited.
To be fixed after new set of officers settle down.
21 CR
GoM
GM
a) Return of the land taken over by
Collector, Solapur without Railway’s consent near Solapur Station. (101
crore.)
GoM has advised CR to prefer an appeal with
Divl. Commissioner, Pune in the matter.
Previous Chief Secretary had agreed to a
proposal that transactions between CR and GoM
shall be debited and Credited as per the then value of land in a Register of Running accounts.
20/11/14 fixed for Meeting with CS. Meeting cancelled by CS. New meeting date awaited.
b) Allotment of Land at Pune in lieu of
land already handed over between Latur-Harangul in Latur District. (14
crore)
C) Relinquishment of land at Belapur-
Shevgaon in Ahmednagar district.
(18 crore)
D) Balance payment regarding Land
handed over to PMC, Pune for widening of road. (1.29 crore)
22 CR GoM
GM
Levy of Octroi /LT to m/s IOCL for HSD oil at Miraj.
Miraj Municipality is the only authority in Maharashtra levying the tax for last 3 years.
This money has to be refunded.
COS / C.Rly to press for arrears.
Page 8 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
23 CR
GoM
CAO / C
Approval for permission of mining the
moorum & stone at Daund-Gulbarga
doubling project.
ITEM CLOSED.
24 GoM
CR
CAO /C
SANCTION OF SIX PROJECTS:
i. WADSA–DESAIGANJ-GADCHIROLI
NEW LINE.
ii.GADCHANDUR-ADILABAD NEW LINE.
iii. PUNE-NASIK - NEW LINE.
iv. KARAD-CHIPLUN - NEW LINE.
v.MANMAD-DHULE-INDORE-NEW LINE
vi.NAGPUR-NAGBHID
GAUGE CONVERSION.
Hon’ble CM has written to Hon’ble MR
requesting to expedite sanction of pending
projects. i. Revised estimate of Rs 469 Cr has been
checked by PWD/Nagpur. Rs 10 Crs will be release shortly. Part estimate under sanction
with Railway Board. FLS and Geo- technical
exploration has been completed. Hon’ble CM requested Hon’ble MR to
expedite sanction of revised estimates for the project.
ii. Survey report submitted to Rly Board on 03.05.2013 at a cost of 48.4 crs. ROR
8.35% with 50% sharing with GoM. Status: Project not sanctioned yet.
iii. Survey report submitted to Rly Board on
12.03.2010 at projected cost of 1899.6 crs with
ROR less than (-) 2.84%. Revised ROR with 50% cost sharing by GoM is 4.11%, sent to
Rly Board on 28.02.12. Status: Project not sanctioned yet.
iv. Survey Report submitted to Rly. Board on 29.01.2010 at projected cost of 928.1 crs with
ROR (-) 4.37%. Revised project cost with 50% share of GoM with ROR (-) 3.17%. KRCL is
likely to do this project. Proposal for participating in the project is under
consideration of Maharashtra Maritime Board.
Hon’ble CM requested Hon’ble MR to sanction the project expeditiously.
v. Updated Report submitted to Rly Board in 2004 with revised cost of Rs. 2257 crs and ROR
9.52%.
Status: Project not sanctioned yet.
vi. Project sanctioned in 2013-14 at a cost of 401 crs. Final location survey and estimate
preparation has been started.
Board have stipulated that no expenditure is to be incurred by SECR
without Boards approval. Hon’ble MR has been requested by Hon’ble CM to
expedite pending approval.
Page 9 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
25 MbPT
CR
GM
Taking over of Port Railway by C.Rly and
Exchange of Haji Bunder land of
Railways with Wadala land of MbPT.
Agreement sent to MbPT on 08.09.2014.
MbPT is waiting for Rani Jadhav Committee
report. C.Rly cannot introduce 12 car services on
harbour line without this agreement of MbPT. Detailed meeting with MbPT office postponed to
10/10/14 at 17:00 hrs. ROB meeting was requested by MbPT on
14/10/14, which can be held today itself.
MbPT vide its letter dated 27.10.2014 has
forwarded its comments on the Central Railway’s letter dated 08.09.2014 wherein
certain terms and conditions have been
stipulated for taking over Port’s railway operations. MbPT Absent on 16/12/14.
This point added in the agenda of Port
Trust meeting planned for 7/1/15.
26 WR Land Acquisition at 4 locations (Total 1178 sqm) i.e. Vile Parle (South) &
(North), Malad (West) and Borivali (South) in connection with 6th line work
between Mumbai Central to Borivali. –
Application for Land acquisition submitted on 15.10.2012 and 25% of
Estimated cost of land has been deposited on 18.02.14 and 14.03.14.
OSD (Rlys) has been asked to coordinate with collector (suburban) to expedite land
acquisition cases. Action to be taken after elections.
Documents given to OSD (Rlys) on 17.10.14
Rs 48 lakhs deposited with GoM in March ’14. Sec IV notification for land acquisition by Dec
’14. Meeting held with DM (Suburban) on 25/11/14.
DM (Sub) advised that this acquisition will be
done under new rates with fresh social impacts study to be done after WR deposits charges for
the same. Collector requested to exempt social
impact study under section 9 of new act.
PS(FOREST)
GoM, COLLECTOR
MUMBAI /SUBURBAN
District
Collector /
suburban &
Commissioner
/ Konkan
27 WR MCGM
Land Acquisition 550 sq. m at Vile Parle (South) on BMC road in connection with
6th line work between Mumbai Central to Borivali. – Correspondences have been
made with MCGM authorities on
25.02.14, 04.04.14, 28.04.14 & 26.06.14.
Joint inspection by W.Rly and MCGM official held on 24/9/14.
Land required is not encroaching any road. It is not infringing with any future plans. Can be
acquired by W.Rly.
Detailed plan submitted on 6/10/14 to Ex. Eng / Tfc.
MCGM representative agreed to request Ex Engg (Tfc) to expedite. On 26/11/14. MCGM
has asked WR to submit details of owners. PDC
7/1/2015. Local society members objected to survey & a meeting fixed with MCGM
on 5/1/15 but postponed.
Page 10 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
28 WR
MCGM,
BEST, JT
COMMISSIONER POLICE (TRAFFIC)
Construction of Flyover to facilitate
smooth flow of traffic between Bandra
and Bandra Terminus. – MCGM has agreed to hand over 296 sqm of land
near water mains for widening of Existing Road on payment of easement
charges. However, there are
encroachments and license vendors on this land. MCGM is requested to hand
over Encumbrance free land early for widening of road.
BEST officials have inspected the site and
agreed with planning of Railways. Traffic police
have agreed to provide additional deployment during construction of ramp. MCGM was asked
to expedite early handing over of encumbrance free land for widening of road.
TDC for hand over of 296 sqm land – 17/10/14. Assistant commissioner (H ward) MCGM is to be
requested for handing over of land. A cheque
of Rs 90 lakhs ready with WR. MCGM to remove licensees presently occupying the land.
MCGM representative assured that this will be done after elections with the help of police.
MCGM: Action was proposed to be taken on
08.10.14 but due to elections, postponed to 10.11.2014.
According to the availability of police
protection, removal of encroachment at Gate
no.18 Bandra (east) is proposed on 10.11.14. Concerned officers of water department
(MCGM) and Railways informed. Work likely to be done today.
Encroachment removed on 11/11/14. 90.45 lakhs deposited on 1/12/14 .
Permission received from MCGM on
11/12/14. ITEM CLOSED
29 WR
MCGM
Completion of approaches of ROB’s at
Jogeshwari, so that Level crossings can be closed and Oshiwara station can be
commissioned. a) Construction of Road Over Bridge in
lieu of LC 26 & 27.
b) Construction of Road over Bridge in lieu of LC 24 & 25.
MCGM will complete ROB approaches by May
’15.
Interior progress on schedule as per WRly. Approach held up on east side for 80m . Out of
500 meter due to encroachment.
PDC by MCGM will be given in next meeting.
30 WR CR
DRM/BB
Handing over of 2731Sqm land at Curry Road depot from Central Railways to
Western Railways in connection 6th line
work between Mumbai Central to Borivali.
Joint inspection was carried out on 19/9/14 and there was agreement for transfer of land.
DRM / BB:
The revised drawings to be submitted by WR and transfer will be ensured after consulting
CAO (C) regarding requirements of 5th and 6th lines and Parel Terminus.
This issue will be decided by CRS on common drawing to be made by CAO (C) by 30/11/14.
WR has given an prima facie acceptable plan
on 4/12/14. PDC for CR 7/1/15. CR agreed that WR can take the narrow
strip of road as shown on drawing after reconstructing the CR structure at nearby
locations along with new boundary wall.
Page 11 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
31 CIDCO
CR
DRM
Taking over of maintenance of 14 nos. of
suburban railway stations by the railways
on or before 31st March 2015.
&
Finalizing the pending maintenance agreement between Central Railway and
CIDCO for the maintenance period
beyond 2008.
CR has not taken over maintenance from
CIDCO as yet. As such we cannot charge w.e.f.
2008. We will charge w.e.f 2015 after we take over.
We can take over after CIDCO does one time
clearance of arrears / deficiencies and clarifies the separation of utilities.
Agreement for 2008-2015 will also have to be
signed.
DRM / BB, Central Railway to be the single point for co-ordinating and decision in the
matter.
He will hold detailed meeting with CE ( Spl. Proj) / CIDCO in DRM office on 8/10/14 at
15:00 hrs. DRM / BB held meeting on 17.10.14. Next
meeting planned on 29.10.14 and site visits on
5.11.2014. CIDCO:
The maintenance agreement between CR & CIDCO has not been formalised w.e.f. 2008.
CIDCO has already communicated the draft of the maintenance agreement in 2011-12. Now
since it is decided that Railways shall take over
maintenance of the stations w.e.f. 01.04.2015, the maintenance agreement should be finalised
by Railways considering 2008-2015. CIDCO & Railways jointly should finalize the
issues pertaining to the outstanding dues, if
any, on either side, the cost of repairs to be shared & as also the utilities sharing /
separation.
32 MRVC CR,MbPT,
CIDCO, MMRDA
CAO / C & DRM
Fast elevated corridor between CST-Panvel:
Alignment through BPT
Navi Mumbai Area
Land Acquisition & Resettlement & Rehabilitation.
Meeting of CIDCO , MMRDA , MRVC , C.Rly as ordered by CM.
20% of land required (air space) is from MbPT. 70% will be air space of C.Rly.
Details with alignment particulars (between Reay Road & Wadala) to be given to
MbPT & MCGM again.
CIDCO has certain issues:
The alignment shown in the Navi Mumbai area needs to be resolved since it infringes on
existing structures. At Seawood station, the MRVC has proposed
Fast Track Corridor at grade passing through
the Seawood Station. The clearance from Central Railway is required since one platform
of Nerul-Uran corridor will be reduced to single discharge facility. This decision is required
urgently as phase –II construction of the new Seawood Railway Station will commence shortly
and accordingly the GAD and the design may
have to be revised for certain column and
Page 12 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
beams.
Land requirement put up by MRVC to the south
of Kharghar Railway Station is also to be decided.
The location of the platforms in Panvel Terminus for Fast Track Corridor is also to be
decided.
Detailed inspection was held by MRVC on
31/10/14 with CAO (C). Concept plan submitted on 07/11/14. DRM/BB to comment on this
along with CE / Plg. It was decided to merge the two lines of
the fast corridor & two line of harbor on
the same alignment from CSTM to Sandhrust road for the making of station
between CM & RM.
33 MRVC GoM/TMC
CE / G
Commercial Development of Railway Land at Thane, Mulund &
Bhandup Approval from the Govt. of
Maharashtra for Mulund
Additional survey by TMC as directed by
PS/UDD.
Under process with GoM. New meeting of committee made by CS on this
subject is expected to be held by last week of October.
Now last week of November ’14 TMC finished
their work of clearance.
Now pending with GoM.
34 MRVC
GoM
Redevelopment of 20 suburban Stations
alongwith station area development – Mumbai Central, Lower Parel, Dadar (W),
Bandra, Andheri, Goregaon, Borivali, Mira Road, Bhayander, Virar on Western
Line & Dadar (C), Kurla, Ghatkopar,
Mulund, Thane, Dombivali, Kalyan, Shahad on Central Line and Wadala
Road, Chembur on Harbour line.
This Project needs about Rs. 2000 cr. to
seamlessly transfer commuters between Railways, Metro and BEST. Most of the
Railways rooms will have to go to First floor air space. GoM has to foot the bill. Presentations
made by MRVC to
CR on 26.09.14. Details to be finalized and presented to the new Govt. by Nov. ’14.
PDC 7/1/15 by MRVC. Sent to Board by
MRVC for approval.
35 MRVC GoM,
MMRDA, MCGM,TMC, CR,WR,LOCA
L MUNICIPAL
BODIES.
Proposed mid-section trespass control
works at 20 locations on CR/WR/Harbour line – finalization of study by J. J. School
of Architecture.
44 Locations earmarked. We can do 20
immediately provided GoM shares the cost like they are sharing on existing 12 stations.
Presentation on sites on CR made on 26.09.14. Detailed proposal will be examined by CR and
thereafter by the new Govt.
PDC 7/1/15 by MRVC. Sent to Board by MRVC for approval.
36
& 57
MRVC
CR
CSTE & DRM
Running of 12 car on Harbour line
MRVC is executing the infrastructure works.
PDC: Dec.’14 – Wadala. Jan.’15 – CSTM.
CR will have to arrange for measurement of coupler forces (1 in 37) & for new stabling
yards for EMUs.
Page 13 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
CSTM block will be for 3 days to extend
platform no. 1 & 2.
(CR has to arrange rakes by AC-DC conversion) About 1100 crores required by CR for
rolling stock.
37 MRVC
CR
CAO /C
5th & 6th line between CSTM-Kurla.
1st phase Kurla-Parel.
Detailed estimate for 5th and 6th line
sanctioned. Tenders for works will be invited shortly.
Resettlement to be done expeditiously by MMRDA. For 642 hutments between (10/22 to
12/10) & 47 hutments at Parel.
(To be coordinated by MRVC) Partial list of
structure handed over to MMRDA on 30.09.14. Complete list will be made by SPARC by
October 2014.
Papers submitted to Distt Collector. Point to be discussed separately as decided by
CM on 3/12/14. Presentation (CSTM – Sandhrust )
submitted to CMD office. This may be be discussed on 8/1/15 between CM & RM
also.
38 MRVC
GoM,
MMRDA, CIDCO
MUTP III Proposal
Quadrupling of Virar-Dahanu Road, Doubling of Panvel-Karjat,
New suburban corridor between Airoli-Kalwa on Trans-Harbour Link,Virar-Vasai-
Panvel New Suburban Corridor, Extension of Harbour line from Goregaon
to Borivali, 5th & 6th line between
Borivali-Virar, 3rd & 4th line between Kalyan-Kasara, 3rd & 4th line between
Kalyan-Karjat, Capacity enhancement & augmentation work, Fast elevated
corridor between CST-Kurla-Panvel,
Elevated corridor between Oval Maidan-Virar.
With Ministry of Railways after approval of
GoM.
Part detail estimate costing 38.85cr sanctioned
vide letter NO.2013/W1/CR/Kalyan-Kasara dt. 16.01.2014. Full detail estimate under
preparation
Pending with Railway Board since 15/11/13.
C.Rly to clear these projects.
This can be included in the agenda of
meeting ordered by CM.
39 CR
MMRDA
DRM
Connecting the existing skywalk on west
side of Ghatkopar station to the Metro
building so as to ensure seamless
connectivity with railway’s 12 meters
wide FOB.
Under process.
Details given to MMRDA on
15/10/14.Consultants of MMRDA working on this.
PDC 15.11.14. Delayed to 05/12/14. DRM BB:
Proposal has to be submitted by MMRDA. The
same has not been submitted till date. Concerned officials not available on 16/12/14.
40 CR
GoM
DRM
Notices have been served on Igatpuri
Municipal Corporation and Manas Resort
to explain the permission granted for
construction and whether they have
Meanwhile GoM will check the authorized
existence of the rear building and the swimming pool
NOCs of Manas resort have been withdrawn by Igatpuri corporation OSD(services) to organize
Page 14 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
resulted in the hill slope being unstable.
The foundation of the Resort’s rear
building has been exposed during the
landslide on 30/7/14 The scheme
submitted by Manas Resort for repairs is
under scrutiny.
clear indication to all authorities that the
construction done in 2010 onwards is
dangerous and unsafe for travelling public.
DRM BB: Manas Resorts has submitted the proposal to carry all protection outside Railway
boundary to ensure safety of passengers. Protection plan has to be cleared by CRS.
41 CIDCO
CR
DRM
Whether there is a Railway requirement
for the triangular plot between Thane-
Turbhe & Mankhurd-Belapur Line near
Juinagar Station.
During meeting with CIDCO on 19.09.2014,
Railways have asked them to provide dimensions of the land plan.
Area plan was discussed on 23.09.14. Since the
length is about 350 meters, Stabling lines can be made. To be accepted by C.Rly formally.
CIDCO will communicate the terms and conditions.
The said piece of land has been marked for
25KV substation. CIDCO has been advised accordingly. C.Rly will try to accommodate few
stabling lines also. CIDCO:
The Railways informed that the said piece of land has been marked for 25 KV sub-station.
CIDCO stated that this triangular piece of land
belongs to CIDCO and the terms & conditions for use of this land for Railway purposes will be
conveyed to Railways. Railway to provide the exact net area of the
triangular plot after deducting the Railway
reservation of the three tracks corridors on the periphery of the plot. Thereafter, CIDCO will
communicate the terms & conditions for providing the CIDCO land of the triangular plot
to Railways. ITEM will be CLOSED after area of the plot is
decided by Railways.
Area calculated as 16000 sq.m. by Railways. Letter to be given to CIDCO PDC 2/1/2015.
42 CIDCO CR
DRM
For re-locating the Assistant Commissioner of Police, harbour
Division’s Office at the ground level unit of the Vashi Railway Station Building
(south side), the keys of these offices
have to be handed over to CIDCO for completing the handing over process.
Currently, the keys to these premises are kept in Station Master’s office.
The said premises are in possession of Central Railway since 1992 and are being used for
various purposes. Further all the station building in Navi Mumbai will be under control of
Central Railway from 01.04.2015, so it will be
appropriate that the railways take a view on this issue.
TDC: 15.10.14. CIDCO informed that these premises should
have lock up and even room for the Hon’ble Judge also. To be discussed in 08/10/14
meeting.
CIDCO informed that these premises have lock up and room for the Hon’ble Judge. This
premise has to function as mandated. Meeting rescheduled for 17.10.2014.
Railway has planned a safety training centre for
Page 15 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
Motormen & ASMs..
43 CIDCO
CR
There is demand for providing escalators
at Nerul-Uran Railway Stations Commuter Sub-ways. Necessary
provision need to be provided by Railways in the structures being
constructed by Railways.
Escalators are not to be provided in any
subway as per Railway policy.
(Usually subways are not provided with escalators since number of steps required to be
climbed is substantially less as compared to a
FOB). ITEM CLOSED.
44 CIDCO
CR
CAO /C
The details of the surcharges have not
been provided to CIDCO till date and it is
an Audit issue with CIDCO. CIDCO needs details of more micro
level. This is to be provided at the earliest.
Central Railway regularly makes payment by
third week of following month to CIDCO. The
information is also regularly conveyed to CIDCO. Copies of the latest acknowledged
communications and its confirmation are available on record.
Information of surcharges paid from the year
1992-93 onwards is also available on records. This is also a Court matter (PIL for stopping
surcharge) with CIDCO. Railways assured to provide the details in next meeting.
New PDC 14/10/14. To be coordinated by CAO
(C ). CIDCO conveyed that there is audit query in
regard to the absence of the details regarding collection of the surcharge. These details are to
be provided by the Railways urgently. Details given on 29/10/14 upto the minutest
level.
CCM & FA& CAO may be able to give further details.
A/c departments of CIDCO & Central Railway to sit together & decide.
45 CIDCO
CR
GM
The revenue from the rakes plying on
the Cost Sharing Projects of Mankhurd – Belapur - Panvel & Thane – Turbhe -
Vashi / Nerul -Panvel are not received from Railways.
C.Rly agrees to share ‘Revenue Expenses’ with
CIDCO as per the agreement between CIDCO and Railways.
This revenue to be passed to CIDCO shall be in
line with the agreed terms.
This will be Revenue minus the operating
expenses.
Page 16 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
46 CIDCO
CR
DRM
The Railways have not filled the form of
application for obtaining HT connection
at the New Seawood Railway station in the name of Railways which is to be
submitted to MSEDCL.
The issue was discussed during the meeting
held on 18.09.2013. MOU for taking up all the
buildings for maintenance by Railways in Seawood-Uran projects is to be formalized
between CIDCO and Central Railway. CIDCO advised to start with two temporary
electricity and water connections so that in due course, one set can be earmarked for railways
stations and hand over to railways
This item may be discussed with CIDCO
officials in next meeting scheduled on 17.10.2014.
The maintenance agreement between CIDCO &
Railways for Seawood-Uran project should be finalised now since the diversion to the new
Seawood station shall take place shortly. Draft agreement will be given to CIDCO
by 20/1/15.
47 MMRDA WR
Sparing of Railway Land:
a) At Mumbai Central Station: Metro station is proposed at Mumbai
Central Station, opposite to the long
distance terminal on Dr.Nair Marg. The station will be fully underground with
entry / exit structures and ancillary building being the only structure at
ground level. For the construction of the
proposed station entry / exit structures and ancillary facilities, some land is
required in Railway premises. i. Land for Entry / Exit point and
ancillary structure ii. Land for temporary use during
construction period
iii. Land below ground for proposed sub-ways for passenger connectivity.
b) At Grant Road Station:
1. Land for Entry / Exit points on
permanent basis. Approx. 400 sq. mtrs.
2. Interchange facilities at Mumbai Central, Churchgate, Mahalaxmi and
Grant Road stations.
3. Crossing of Metro alignment with WR tacks at Mahalaxmi & Mahim
stations. (Harbour and WR).
c) Space for Metro III.
PCE/WR
one reference was received vide MMRDA’s
letter dated 06.09.2013 which was examined and considering the adequate depth of the
proposed tunnels below the railway track and structures, prima facie the proposal appears to
be feasible. The permission will be subject to
drafting necessary agreement and submission of charges as per Railway Board’s extant
policy.
(Mahalaxmi opening may not be possible. A deck over BMC road with lift may be planned )
i. Approximately 400 sq. mtrs. Proposal submitted to Divisional Railway manager,
WR, Mumbai Central vide Letter No.MMRC/ML-3-CBS/WR/LA/2014 dated
15th September 2014.
ii. Proposal has been submitted to DRM, WR, Mumbai Central Dn. Vide letter No.
T&C/ML3 CBS/WR/LA/2014/99 dated 20th February 2014 for Mumbai Central,
Churchgate and Mahalaxmi stations.
Proposal has been submitted to DRM, WR vide letter No.MMRC/ML3-CBS/WR/LA/2014
dated 15th September 2014 for Grant Road Station.
iii. Proposal has been submitted to WR Rly. HQ, vide letter No. MRTS/ML3/WR Crossing
dated 04th February 2014.
MMRDA arranged a presentation on Metro III
by their consultants on 23/9/14 which was
Page 17 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
found very useful by all members. It was
assured by railway that whatever land will be
required for few years to lower TBMs will be made available at rates as applied for Chennai
Metro by S.Rly, without any delay. Google map of sites required for Metro 3 were handed over
to W.Rly on 14/10/14. Joint inspection at all four stations has been completed on 16.10.14
by BCT division along with MMRDA officials.
Based on joint inspection MMRDA has been given clearance to prepare final drawing duly
indicating exact dimensions vide letter no. W.220/2/737 dated 20.10.14. Copy again given
in the meeting to Advisor (Civil) MMRDA.
WR confirmed that Google Maps received on 19/10/14 and detailed inspection done on
20/10/14. Tech clearance given on 20/10/14.
Now MMRDA to submit details by 02/12/14. Fresh PDC 17/12/14.
Another PDC 15/1/15.
48 CIDCO
CR
DRM
Due to site constraint, CIDCO requires
1200 square meter railway land (CH 77 kms) along Panvel Uran railway line near
Bhangarpada falling under village Dapoli, Tal -Panvel for laying the storm
water drain in Pushpak Nagar which is
part and parcel of Navi Mumbai International Airport Project.
DEN (LM) CSTM through letter dtd 16/5/2014
informed CIDCO that land shall be leased to CIDCO for 35 years.
CIDCO to submit its proposal to Railways as explained in the meeting.
PDC for CIDCO 30/10/14.
Submitted on 8/10/14. Copy again given on 11/11/14.
DRM BB : Proposal is under divisional approval. XEN CIDCO to liaise with BB Division.
49 CIDCO CR
CAO / C
The final approval for two ROBs taken up for construction at MSEB Sub-station and
Uran Station on Nerul-Uran Railway Line are awaited from Railway.
Both ROBs are under scrutiny of Design office and for some clarifications, concerned designer
of that bridge is required at design office of headquarters office of CR.
Old PDC was 15/10/14. C.Rly requested for
priority. MSEB was indicated by CIDCO as priority 1
PDC for MSEB 31/10/14. PDC for URAN 07/11/14.
Both progresses are on schedule.
Designer required again in CAO(C)‘s office for
minor clarifications. One approval of MSEB done on 24/11/14. Second consultants to visit
CAO ( C ) for URAN. Meanwhile Board has reviewed the use of
PSC girders over lko/Railway tracks &
banned them six months ago in view of public safety. CIDCO & CAO(C) to sit
together on 12/1/15.
50 MCGM CR
Widening of Nanepada Nallah from Railway culvert to Jai Hind colony.
MCGM has already paid Rs.3,43,43,524/-
Item 50 to 56 given by Storm Water Department, who is not present in the meeting.
To be discussed in next meeting of 14/10/14.
Page 18 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
DRM
towards Way Leave Charges of railway
land vide Receipt No MR 063195 dated
24/12/2013 for grant of NOC to carry out the construction of nallah work in railway
premises. Matter pertains to Divisional Engineer (Land) C.Rly.
The drawing has been returned with remarks
on 13/10/14.
Meeting held on 20.10.14. Site inspection with MCGM planned for next week.
Site inspection done on 14/11/14 with Se DEN (South).
PDC for approval by DRM – 05/12/14. DRM BB: GAD for work under Railway Area
being finalized.
BOX is not feasible. Pipe crossing will be planned with 1.8 m dia as done in Kurla
upstream. NOC also requested by MCGM, after above is settled.
Drawing approval to be done by 8/1/15.
HQ PDC 25/1/15.
51 MCGM
CR
DRM
Work of widening of Somaiya Nallah
from Vidyavihar station (east) to Tansa pipeline is proposed to be undertaken in
the fair season starting from OCT 2014. NOC for the work is required from C.Rly
to carry out the work. Matter is being pursued with Sr Divn. Engg.(South) C.Rly
.
Photo copy of proposal given by MCGM again
on 11/11/14. Site inspection planned on 21/11/14 with Sr DEN (South). Joint inspection
done. DRM will communicate way lease charges by 10/12/14.
DRM BB: Existing Somaiya Nallah is 8m wide. During Joint Inspection, MCGM requested to
widen Nallah by 2m width and 6m wide service
road all along the Nallah. MCGM is requested to submit GAD incorporating this requirement.
GAD was awaited from MCGM five copies deposited again by MCGM on 16/12/14.
Revised PDC 15/1/15.
52 MCGM CR
DRM
Work of Kurla Carshed Nallah at Kurla (East) near Kranti Nagar was undertaken
by CR in last fair season, which was stopped during monsoon. Addl Municipal
Commissioner (Eastern Suburb) vide
letter dated 20.05.14 and 07.07.14 had requested GM/CR to give suitable
instructions to concerned staff for restarting the work immediately.
However, same is not still started on
site. The same may be instructed to be
started early.
Meeting between Sr.DEN/S and Director/Project/SWD is scheduled on
14.10.2014. Laying of three pipes (1800mm dia.) out of five
pipes under Yard/Main line completed. In order
to complete the widening project in all respect, four addititional works yet to be planned.
Therefore, MCGM has to deposit additional funds of Rs.9,53,58,685/- for completion of
balance work and same has been intimated to
MCGM Vide Mumbai division Sr DEN/S/BB letter no.BB/W/3512/BMC/CLA-nallah/DB dated
24.09.2014. Further, way leave charges of Rs. 3.0Cr has been deposited so far, balance Rs.
6.40 Cr. yet to be deposited by MCGM. Same
has been advised vide above letter. To complete balance work above funds may
deposited with Railway at earliest. Pending approval of AMC for RE . PDC – Feb 2015.
Leftover work of connectivity is being started and shall be completed by 28.02.15.
Page 19 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
53 MCGM
WR
Proposed work of widening and draining
of V.H.Desai Nallah parallel to W.Rly
Dahisar (west) from Dahisar Sub way to creek.
NOC for the work is required from WRly for which site visit and co-ordinations
between agencies is required so that Way Leave Charges can be paid to carry
out the work.
PDC 11/1/15.
Feasibility Okayed. On 28/10 Proposal to be
submitted by MCGM.
PDC 05/12/14. Letter given by WR again on 16/12. Further
PDC for money deposit for MCGM – 7/1/15.
Revised PDC 25/1/15.
54 MCGM
CR
DRM
MCGM has made payments for the work
of improvement and augmentation of
culvert capacity in Railway area for SWD system at 10 locations in city and
eastern suburbs in the following locations.
i. Dhobighat Nallah – Sion. ii. Swadeshi Mills Kms 14/2-3.
iii. LBS Marg Kurla kms 14/5-6 iv. LBS Marg Kurla kms 14/7-8
v. Chunabhatti Station kms 13/3-4.
vi. Wadala Harbour kms 9/61.
vii. Kurla Railway Colony Nallah
from Carshed culver to Tilak nagar Station.
viii. Culvert at Nanepada, kms 29/6-7.
ix. Currey Road kms 5/11-12.
x. Chinchpokli kms 5/1-2.
The works at above locations are yet to be carried out by CR.
MCGM:
Proposed augmentation:
i. Box Culvert 2 M x 1 M ii. Box Culvert 2 M x 1 M
iii. Box Culvert 2 M x 1 M iv. Box Culvert 2 M x 1 M
v. Box Culvert 2x2 M x 1 M
For items i. to v above, Rs. 6 Cr deposited on 26.03.2008.
vi. Box Culvert 1.80 M x 1.20 M
Rs. 27.11 lakh deposited on 20.03.2003.
vii. For Culvert and Nallah augmentation –
Rs. 12,62,72,125/- deposited on 18.03.2009.
viii. For Culvert augmentation - Rs. 1,75,
96, 987/- deposited on 28.03.2003.
ix. For Pipe culver 1.20 M dia. – Rs. 33,880/- deposited on 01.02.1996.
x. For Pipe 2 x 0.90 M.dia – Rs. 2,31,270/- deposited on 23.04.1996.
CBE: i) & ii) Contract awarded. Segmental box are
ready at Bhandup depot.
Iii) Work completed under Main lines. Work under HB lines balance.
Iv) Contract awarded. Segmental box are ready at Bhandup depot.
V) Details of connectivity of this culvert to
creek/ other Nallah system needs to be furnished by MCGM.
vi) Work partially completed. Segmental box are ready at site. For further work,
Downstream side to be augmented by MCGM.
vii)The work for widening of Nallah near Railway colony and LTT area has been
completed except encroachment location at Savale nagar.
viii), ix) & x) Feasibility of augmentation of culvert below Rly. tracks may be furnished
after joint inspection with Rly site Engineer.
DRM clarified that 2 or 3 out of 10 items ( Sr No ii, iii, iv ) will be completed in this
season.
Page 20 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
DRM BB: Work of the Dhobhighat and
LBS Marg at km 14/5-6 shall be planned.
55 MCGM
CR
DRM
Reconnection of SWD line at
Chunabhatti Railway Station by CR. (platform no. 1) since damaged and
blocked by CR while carrying out the work of foundation for FOB in 2013.
Several letters written to restore the
damaged SWD. Unfortunately as per CR, existing SWD to be diverted by MCGM
outside Railway land.
This pertains to Construction Organization,
Sr.DEN/S/BB Vide letter on 11.04.2014, construction org. has been advised to restore
the Pipe drain which has been damaged by Construction org. Dy CE (C) DR during the
work.
Storm water drainage was damaged during foundation work of FOB. MCGM has to divert
the drain in the BMC area. Railway will pay from deposit work of Wadala – Kurla. Drg will be ready by 10/12/14 by DRM. This drawing is not required as pipe is available under the platform. DRM BB: The Scheme is being developed.
56 MCGM CR
DRM
1. The work consists of laying 1.60 M.dia. pipe under steel casing of 2.50
M.dia. MCGM has made payment of Rs. 58,40,408/- on 13.01.2001 to CR. The
work was reported to have been
completed by CR in the year 2007. Now, MCGM has taken up work of
laying 1.60 M.dia pipe below the MbPT Railway track on downstream side of
the said work.
A Trial pit was for the said work when it is observed that the Railway
authorities have laid only the steel casing pipe below harbour Railway
track and the 1.60 M. dia pipe is not laid inside the casing pipes.
CR to expedite the work of laying 1.60
M.dia RCC pipe inside the casing pipe for the portion below Harbour Railway
track to enable MCGM to lay the downstream side pipe line with proper
connectivity.
2. Further, on upstream side the
newly laid drain has to be connected to the existing drain for which excavation
will be required in the Railway land at km 7/17-18 near Railway track. CR is
requested to grant permission for the
same.
DRM / BB: MCGM may give a firm proposal along with the
execution schedule. CBE:
1) The work of Casing pipe under Railway track
has already been completed in 2007. MCGM is to carry out the work of laying RCC pipe
through the Casing pipe. 2) No proposal received for extension of drain
on up stream side at km 7/17-18. On receipt of
proposal matter will be examined by Railway.
Casing pipe to be examined by MCGM and point recast if there is any problem.
ITEM CLOSED as casing work is over.
57 MRVC
CR/WR
GM
Running of 15 car on WR and CR:
MRVC has carried out study on the WR
and CR through RITES. The report has been submitted to WR and CR. The
same will be made to CR on the date to be mutually decided.
Presentation planned on 20/10/14.
Presentation made. RITES reports to be
modified as per discussion with of Railways.3 rakes of 12 car each requested every year
w.e.f 2015-16. For next year for this 360
coaches , 1080 crores for Rolling stock.
Page 21 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
58 MRVC
CR/WR
GM
Concept Plan: New Suburban link
between Wadala to Ballard Estate
through MbPT.
MRVC has prepared the concept plan for new suburban link between Wadala to
Ballard Estate through MbPT. This will enhance the capacity between South
Mumbai to Panvel and South Mumbai to
Andheri/Goregaon and thus enable direct connection with Central, Western & Navi
Mumbai area. The concept plan has been submitted to Mrs. Jadhav,
Chairperson of MbPT Land
Redevelopment Committee on 10.10.2014.
Joint meeting of MD/MRVC & GM/CR with Mrs
Jadhav to be organized on 16/10/14.
The meeting held on 14/11/14. & 19/11
ITEM CLOSED.
59 CR
TMC
CAO /C
Construction of ROB in lieu of LC No.
28/C between Thane-Kalwa on cost sharing basis (50:50) between CR &
TMC, sanctioned in the year 2012-13. Approach land is with Court receiver.
The work in Railway portion is in progress in full
swing but the work on approaches is yet to be started by TMC. This is likely to result into delay
in commissioning of the ROB and consequently in closing the LC gate.
Joint letter to be written to Court receiver. Draft by TMC given on 26/12/14. Rly will write to
collector as desired by TMC. TMC will now
request court with the help of collector. TMC absent on 6/1/15.
60 CR
MCGM
CAO / C
Kurla Subway:
New Subway for providing East to West connectivity on Kalyan end of Kurla
station has been constructed by Railways in Oct 2005. Subway could not be
commissioned so far due to non-completion of exit and entry works on
the approaches.
CE(Bridges),MCGM vide their letter No.
Ch.E/5060/Bridges dated 31.12.2013 has confirmed that MCGM will execute the part work
of approaches which is falling in MCGM limit. On confirmation of MCGM, CR has finalized
Railway portion (East approach) tender. West approach to be done by MCGM.
Tender floated by MCGM.
61 MRVC
MbPT
Chief Engg.
MRVC has requested MbPT to give the
permission to ply vehicles carrying P-way
and construction material on Reynold Road in Tejasnagar colony near Vadala
Road station. The same needs to be granted.
MbPT Absent on 16/12/14.
Permission given ITEM CLOSED.
62 MRVC TMC
Urgent permission is requested from TMC to cut gulmohar trees on platform 1
on Diva station which are coming in way of new FOB. Tree authority committed
has already inspected the site on 26-06-
2014.
TMC indicated PDC of 15/01/15.
TMC Absent
63 MBMC
WR
Construction 10M wide of subway for
pedestrians and light vehicles at Bhayandar station at Km 43/5A–6A
below platform and running tracks by trenchless technology.
MBMC deposited Rs.9 lakhs in June 2006 and
work started in May 2015 after CRS & other approvals.
75% work has been completed till June 2014 and further work stopped by WR for ‘Non-
payment of codal charges’ of Rs.16.83 Cr. MBMC requested WR in Sept.2014 for
Page 22 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
permission to resume work and assured
payments due after getting approval from
General Body meeting.
Mira Bhayandar Municipal official Absent. 3 Crore being paid today. Rest will be paid
in two installments on June ’15 & Dec ’15.
64 MCGM
CR
Construction of FOB across Harbour
Railway line at Govandi station near Ankur cinema in M/East ward.
Rs. 2,00,23,139/- paid on 28.03.2013.
65 MCGM
CR
Construction of FOB across Harbour
Railway line at Govandi station from
Kumud Vidyalaya to Tata Nagar in M/East ward.
Rs. 2,49,79,290/- paid on 28.03.2013.
PDC 30/6/15
66 MCGM
CR
Construction of FOB across Harbour
Railway line at Mankhurd station in M/East ward.
Rs. 3,11,72,881/- paid on 28.03.2013.
PDC 31/8/15
67 MCGM
CR
Construction of FOB across Harbour
Railway line at Kurla from Brahmanwadi Kurla (West) to Kurla (East) end of
platform No.9 in L ward. Rs. 1,60,000/- paid on 16.05.2000.
Rs. 1,10,00,000/- paid on 01.12.2006.
Rs. 30,00,000/- paid on 22.11.2007. Rs. 34,95,140/- paid on 25.03.2008.
Rs. 2,45,90,263/- paid on 28.03.2013. (Total .. Rs. 4.22 Crores)
PDC 30/11/15
68 KDMC
CR
Construction of 24.00 m. Wide Railway
parallel D.P. Road from Mhasoba Nagar Thakurli to Patripool,Kalyan
Benefits:-This road connects Kalyan - Dombivli parallel to railway line
reduces road length by 3.0 Km.
Useful for Railway passengers.
Railway Land required at a)
Mhasoba Nagar Thakurli East total
lenght 60.00 Mt and b) Kachora Gaon
total lenght 85.00 Mt .
Inform to KDMC by Rlys. Vide L.No. BB/W/6001/LM/KDMC-Road/THK-KYN/449/DB
dated 22/12/2014 to clarify the proposal.
Feasibility to be studied by OSD (services) for sparing ( 60 & 85 ) x 24 sq. meters.
69 KDMC
CR
15.00 Meter wide DP road near Mahila Samiti School at Thakurli East.
Railway has demanded Rs 14.07 Crs
towards lease charges of 3510 Sq.mt which comes out to be (Rs 40,095 per
Sq.mt) the rates are commercial rates. It is requested to correct the lease
charges as per the open land rate based
(Draft Agreement submitted to Commissioner KDMC on 5/3/2012 for signing is still awaited)
OSD / Services to study the ROB drawing of KDMC.
Page 23 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
on State ready reckoner.
70 KDMC
CR
Construction of Gutter Foothpath on Murbad Road opp. Breakmans Chawl
Kalyan (W) in Railway Land
During widening of Murbad road about 20 years back the gutter and foot path
was constructed opp. to old Breakmans Chawl. The gutter is about 3.00 mt
inside the Railway land for 10.00M
length. Now KDMC has taken up road concretization work. Recently Railway
provided barbed wire fencing, So work of gutter is pending and unhygienic
condition are created. Railway should
give NOC to construct gutter at its old alignment to avoid bottleneck in road.
(Proposal is not available in Division)
71 KDMC
CR
Proposal for Improvement of Traffic
Circulation area on Kalyan East.
Proposal submitted to Railway vide Letter No. KDMC/Commissioner/486
Dt.28/06/2013. It is requested to issue NOC to KDMC.
(Proposal is not available in Division)
72 KDMC
CR
Permission for crossing Railway Lines at 3 location in Dombivali for laying rising
Main DI Pipe, under JNNURM scheme.
KDMC has deposited Rs 2.52 Cr to
Railway for the Crossing of Tracks. As
KDMC doing work by HDD method, It is
requested to give permission at the
earliest.
(Pending with KDMC due to methodology details for CRS sanction, letter to KDMC)
73 KDMC
CR/
CAO/C
ROB at Level Crossing gate no 38-C
between Thakurli and Kalyan. Detail construction estimate is sanction by
Central Railway on 20/11/2013 for Rs. 1392.7 Lakhs Since work is on cost
sharing. To join this ROB to Railway parallel road the Elevated road is
proposed and GAD is approved.
It is requested to give required Railway land without any value charges. KDMC
has submitted the agreement for the
(The work executed by CAO/C agreement
signed & copy of same send to KDMC on 31.12.14)
Page 24 of 25
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
said work to Dy CE(Const) GC on
Dt 25.11.2014 for approval and sign.It is
requested to accept the agreement and execute it on Railways part so as to
deposit Rs. 242.63 lakhs to Railway as KDMC share.
74 KDMC
CR
ROB at Level crossing No 47-B between Shahad -Ambivali Station has been
completed in Railway portion but work on approaches by KDMC is delayed.
Due to problem of Land acquisition
KDMC could not complete the approaches. Substructures work
completed in available front and land acquisition is in process.
Railway has spend excess amount on
ROB on this level crossing
75 KDMC
CR/
CAO/C
ROB at Level Crossing Gate 1-A between Vitthalwadi and Kalyan.
Work is completed settlement of
accounts is requested. KDMC has submitted the completion cost of the
project to Dy-Chief Engineer [C]GC and requested to release balance amount of
Rs.383.50 lakhs by wide letter KDMC / CE/434, Dated 20/03/2014.
KDMC has spent excess amount on this
ROB. Therefore reconciliation of above item no 74 & 75 are under process
76 KDMC
CR
ROB at Level Crossing NO.51-A between
Ambivali and Titwala station. KDMC has submitted GAD by vide letter
No.KDMC/CE/18, 21/05/2014 to Sr. DEN [N/E] CSTM. GAD approval requested
(GAD approved and send to HQ on 31.12.14)
77 KDMC
CR
Construction of Skywalk under SATIS
Kalyan East Since Elevated booking office is included
in Phase II work and which is under
tendering process it is not possible to construct elevated booking structure
immediately. Due to this work of Phase I is prolonged. Hence it is requested to
dismantle the existing booking shed and
SBI ATM to carry further foundation at two location. KDMC is willing to construct
Temporary booking office on 5.00 wide span as done by railway on west side.
(Proposal not received)