Upload
others
View
22
Download
3
Embed Size (px)
Citation preview
BACKGROUND OF THE KBRT PROJECT
• It was proposed in the National Transport Master plan that a BRT system be introduced to serve the Greater Kampala Metropolitan Area.
• The World Bank consequently funded prefeasibility studies for the development of a long term integrated Bus Rapid Transit System for Greater Kampala Metropolitan Area.
• Consultant was Integrated Transport Planning (ITP) in association with IBIS Transport Consultants.
• At the time, Kampala City Council (KCC) represented the Government of Uganda as the Client. Presently, this has transitioned in Kampala Capital City Authority (KCCA).
• The exercise (prefeasibility) was finalised in May 2010.
Recommendations of the Pre Feasibility Studies
Proposed corridors included;
1. Gayaza Road
2. Jinja Road
3. Old Port Bell Road
4. Gaba Road
5. Entebbe Road
6. Masaka Road
7. Hoima Road
8. Bombo Road
9. Kiira road
Initially Proposed core corridor = Bwaise to Kireka (14.7km), 2010
Kampala BRT Inception Report 6 11 September 2012
FEASIBILITY STUDY, DETAILED ENGINEERING DESIGN AND CONTRACT PREPARATION
• The Ministry of Works and Transport engaged (in August 2012) a Joint Venture of Consultants to carry out a feasibility study, detailed engineering design and contract preparation for the Pilot KBRT.
• Consortium included ROM Transport Engineers Ltd, ARUP and AH Consultants.
PROGRESS WITH THE JV CONSULTANTS
Reports submitted so far:
• Inception Report
• Feasibility, Preliminary Design and Operations
• Demand and Operations
• Interim Design Report
• Draft Detailed Designs
• Draft Tender Documents
Stage of Project Execution
• Detailed Designs
Pending Report
• Final report consisting of Detailed Deigns and Tender Documents
BRT Concept
• High capacity vehicles: 18m long articulated buses, capacity 150 passengers
• High frequencies: up to 30 vehicles per hour (each direction).
17 December 2012 Greater Kampala BRT - Report 2 11
• Design speed 29.5km/h. • Average stop distance of 800m. • Minimise delays at junctions to the extent possible. • Modern, standard low-floor vehicles with doors at the
left side. → vehicles can go beyond the BRT infrastructure
• Low-floor vehicles & low platforms → easy and quick boarding and alighting
• Side platforms • Platform length 40 m, suitable for two 18m long
vehicles. • BRT lanes in the middle of the road, with exceptions.
Ticketing
Recommendations
• No ticket sales on-board, pay before entering the platform.
• Closed and guarded platforms, enter via turnstiles.
• Ticket booth outside the closed platforms.
• Start with combination of single tickets or tokens and electronic ticketing.
17 December 2012 Greater Kampala BRT - Report 2 13
Junctions
• All key junctions along the BRT pilot corridor will be signalised.
• At all junctions, measures have been taken to avoid right-turning traffic which would affect BRT operation.
• KCCA has been recommended to consider an Urban Traffic Control System and centralised Traffic Control Centre (not part of the BRT project).
• All roundabouts are to be transformed into signalised junctions.
17 December 2012 Greater Kampala BRT - Report 2 14
Multiple Arm Signal Junction with BRT
central running way (ex-roundabout)
Previous
Roundabout
alignment
INVESTMENT COSTS
• USD 394M- Infrastructure Investment Cost
• USD 30M - Land acquisition costs
• USD 66M - Fleet Costs
NEXT STEPS
• Land acquisition
• Establishment of MATA
• Securing funding possibly with World Bank
• Publicising the Project
• Procurement of Infrastructure and ITS
• Procurement of Operator