Upload
taylor-herron
View
564
Download
73
Embed Size (px)
DESCRIPTION
Operations Management
Citation preview
Class notes: Project Management
The objective of these notes is to provide you with a detailed description of the case study
discussed in class and a summary of the project management procedures and models used in
class to approach the case. These notes do not include all the details, or discussions or
explanations given in class and they are not intended to replace the class lecture. You should
read chapter 9 of the textbook for full coverage of the topic.
Milwaukee Paper Manufacturing Case
Milwaukee Paper Manufacturing, Inc., located near downtown Milwaukee, has long been
delaying the expense of installing air pollution control equipment in its facility. The
Environmental Protection Agency (EPA) has recently given the manufacturer 16 weeks to install
a complex air filter system. Milwaukee Paper has been warned that it may be forced to close
the facility unless the device is installed in the allotted time. Joni Steinberg, the plant manager,
wants to make sure that installation of the filtering system progresses smoothly and on time.
Given the following information, develop a table showing activity precedence relationships.
Approach: Milwaukee Paper has identified the eight activities that need to be performed in
order for the project to be completed. When the project begins, two activities can be
simultaneously started: building the internal components for the device ( activity A) and the
modifications necessary for the floor and roof (activity B). The construction of the collection
stack ( activity C) can begin when the internal components are completed. Pouring the concrete
floor and installation of the frame (activity D) can be started as soon as the internal
components are completed and the roof and floor have been modified. After the collection stack
has been constructed, two activities can begin: building the high- temperature burner ( activity
E) and installing the pollution control system ( activity F). The air pollution device can be
installed (activity G) after the concrete floor has been poured, the frame has been installed, and
the high-temperature burner has been built. Finally, after the control system and pollution
device have been installed, the system can be inspected and tested (activity H).
Solution: Activities and precedence relationships may seem rather confusing when they are
presented in this descriptive form. It is therefore convenient to list all the activity information
in a table, as shown in Table 1. We see in the table that activity A is listed as an immediate
predecessor of activity C. Likewise, both activities D and E must be performed prior to starting
activity G.
Table 1
Insight: To complete a network, all predecessors must be clearly defined.
Learning Exercise: What is the impact on the sequence of activities if EPA approval is required
after Inspect and Test?
Answer: The immediate predecessor for the new activity would be H, Inspect and Test, with
EPA approval as the last activity.
Note that in the Example, it is enough to list just the immediate predecessors for each activity.
For instance, in Table 1, since activity A precedes activity C, and activity C precedes activity E,
the fact that activity A precedes activity E is implicit. This relationship need not be explicitly
shown in the activity precedence relationships. When there are many activities in a project with
fairly complicated precedence relationships, it is difficult for an individual to comprehend the
complexity of the project from just the tabular information. In such cases a visual
representation of the project using a project network is convenient and useful. A project
network is a diagram of all the activities and the precedence relationships that exist between
these activities in a project. The project network for Milwaukee Paper Manufacturing is as
follows.
Activity DescriptionImmediate
Predecessors
A Build internal components —
B Modify roof and floor —
C Construct collection stack A
D Pour concrete and install frame A, B
E Build high-temperature burner C
F Install pollution control system C
G Install air pollution device D, E
H Inspect and test F, G
Determining the Project Schedule
Perform a Critical Path Analysis
The critical path is the longest path through the network
The critical path is the shortest time in which the project can be completed
Any delay in critical path activities delays the project
Critical path activities have no slack time
Activity Description Time (weeks)
A Build internal components 2
B Modify roof and floor 3
C Construct collection stack 2
D Pour concrete and install frame 4
E Build high-temperature burner 4
F Install pollution control system 3
G Install air pollution device 5
H Inspect and test 2
Total Time (weeks) 25
Earliest start (ES) = earliest time at which an activity can start, assuming all predecessors
have been completed
Earliest finish (EF) = earliest time at which an activity can be finished
Latest start (LS) = latest time at which an activity can start so as to not delay the completion
time of the entire project
Latest finish (LF) = latest time by which an activity has to be finished so as to not delay the
completion time of the entire project
Possible representation of an activity node (Note: your textbook shows another possible
representation)
Following this representation and after performing the forward and backward passes of the
critical path method (CPM) the network model becomes.
This shows the critical path linking all critical activities and gives the total project completion
time of 15 weeks.
The following table summarizes these results and shows the computation of the slack times for
each of the project activities. Note that critical activities have slack zero.
Also, from the information above the following Gantt Charts can be obtained, which are
particularly helpful in the monitoring (or controlling) phase.
ES → EF Gantt Chart for Milwaukee Paper
Earliest Earliest Latest Latest OnStart Finish Start Finish Slack Critical
Activity ES EF LS LF LS – ES Path
A 0 2 0 2 0 Yes
B 0 3 1 4 1 No
C 2 4 2 4 0 Yes
D 3 7 4 8 1 No
E 4 8 4 8 0 Yes
F 4 7 10 13 6 No
G 8 13 8 13 0 Yes
H 13 15 13 15 0 Yes
A Build internal components
B Modify roof and floor
C Construct collection stack
D Pour concrete and install frame
E Build high-temperature burner
F Install pollution control system
G Install air pollution device
H Inspect and test
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
LS → LF Gantt Chart for Milwaukee Paper
Variability in Activity Times
CPM assumes we know a fixed time estimate for each activity and there is no variability in
activity times.
PERT uses a probability distribution for activity times to allow for variability.
Three time estimates are required
Optimistic time (a) – if everything goes according to plan
Most likely time (m) – most realistic estimate
Pessimistic time (b) – assuming very unfavorable conditions
Estimate follows Beta distribution
Expected time:
4
6
a m bt
Variance of times:
22
6
b a
A Build internal components
B Modify roof and floor
C Construct collection stack
D Pour concrete and install frame
E Build high-temperature burner
F Install pollution control system
G Install air pollution device
H Inspect and test
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Beta Distribution
Given estimated times (a, m, and b) each activity the following table shows the computation of
the corresponding expected times and variance.
Probability of Project Completion
Project variance is computed by summing the variances of critical activities:
σ2 = Project variance = (variances of activities on critical path)
( , )N
Project variance is computed by
Project variance
2 .11 .11 1.00 1.78 .11 3.11p
Project standard deviation
project variance 3.11 1.76 weeksp
PERT makes two more assumptions:
Total project completion times follow a normal probability distribution –
Activity times are statistically independent
In the example, if x denotes a random variable representing a due date, we have
x ~ N (15, 1.76)
Determining the Probability of Project Completion
Question 1: What is the probability this project can be completed on or before the 16 week
deadline?
Probabilities are given in Normal distribution tables for a random variable z that follows a
standard Normal distribution with mean 0 and standard deviation 1.
More formally, z ~ N (0, 1).
The transformation of x into z is given by
p
xz
In our example
16 150.57
1.76z
As a result, μ = 15 and x = 16 in the original Normal distribution correspond to μ = 0 and z =
0.57 in the standard Normal distribution.
( 16) ( 0.57)P x P z
From Appendix A (Normal curve areas), we get
( 0.57) 0.5 0.2157 0.7157,P z hence, approximately 72%.
Question 2: What’s the due date that gives the company’s project a 99% chance of on-time
completion?
The answer to this question consists of determining the value of x for the z-value that
corresponds to a 99% of probability.
x z
Again, from Appendix A we see that for a 99% of probability given by 0.50 (area up to the
mean) + 0.4901 (area above the mean as given in Table A.1) = 0.99, the corresponding z value
is 2.33.
Hence,
15 2.33(1.76) 19.1 weeks.x
In sum: What Project Management has given so far?
The project’s expected completion time is 15 weeks
There is a 71.57% chance the equipment will be in place by the 16 week deadline
There is a 99% chance the equipment will be in place within about 19 weeks
Five activities (A, C, E, G, and H) are on the critical path
Three activities (B, D, F) are not on the critical path and have slack time
A detailed schedule is available