Upload
ankkit-bafna
View
67
Download
0
Embed Size (px)
DESCRIPTION
Project Management Network Techniques, Critical Path Method
Citation preview
Chapter 5Scheduling the Project
Copyright 2005 John Wiley & Sons, Inc.
PERT AND CPM NETWORKS
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
HistoryLate 1950sProgram Evaluation and Review Technique (PERT)U.S. Navy, Booz-Allen Hamilton, and Lockeheed AircraftProbabilistic activity durationsCritical Path Method (CPM)Dupont De Nemours Inc.Deterministic activity durations
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
The Language of PERT/CPMActivitytask or set of tasksuse resourcesEventstate resulting from completion of one or more activitiesconsume no resources or timepredecessor activities must be completed
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
The Language of PERT/CPM continuedMilestonesevents that mark significant progressNetworkdiagram of nodes and arcsused to illustrate technological relationshipsPathseries of connected activities between two events
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
The Language of PERT/CPM concludedCritical Pathset of activities on a path that if delayed will delay completion of projectCritical Timetime required to complete all activities on the critical path
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Building the NetworkAOA NetworkAON Network
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Table 5-1 A Sample Set of Project Activities and Precedences
Copyright 2005 John Wiley & Sons, Inc.
Task
Predecessor
a
--
b
--
c
a
d
b
e
b
f
c, d
g
e
MEM 612 Project Management
Figure 5-1 Stage 1 of a Sample AON Network
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-2 Stage 2 of a Sample AON Network
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-3 A Completed Sample AON Network
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-4 Stage 1 of a Sample AOA Network
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-5 Stage 2 of a Sample AOA Network
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-6a A Completed Sample AOA Network
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-6b A Completed Sample AOA Network Showing the Use of a Dummy Task
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Table 5-2 A Sample Problem for Finding the Critical Path and Critical Time
Copyright 2005 John Wiley & Sons, Inc.
Activity
Predecessor
Duration
a
--
5 days
b
--
4
c
a
3
d
a
4
e
a
6
f
b, c
4
g
d
5
h
d, e
6
i
f
6
j
g, h
4
MEM 612 Project Management
Figure 5-7 Stage 1 of a Sample Network
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-8 A Complete Network
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-9 Information Contents in an AON Node
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-10 The Critical Path and Time for Sample Project
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Calculating Activity SlackSlack or FloatLST - EST = LFT - EFT = Slack
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-11 An MSP Version of PERT/CPM Network
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-12 A Modified Version of MSP Network
Copyright 2005 John Wiley & Sons, Inc.
PROJECT UNCERTAINTY AND RISK MANAGEMENT
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Calculating Probabilistic Activity TimesThree Time Estimatespessimistic (a)most likely (m)optimistic (b)
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-13 The Statistical Distribution of all Possible Times for an Activity
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Activity Expected Time and Variance
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
95 Percent LevelTask will be a or lower 5 percent of the timeTask will be b or greater 5 percent of the time
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
90 Percent LevelTask will be a or lower 10 percent of the timeTask will be b or greater 10 percent of the time
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
95 Percent Level (Alternative Interpretation)Task will be between a and b 95 percent of the time
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
90 Percent Level (Alternative Interpretation)Task will be between a and b 90 percent of the time
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-14 An AON Network
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-15 An MSP Version of a Sample Problem Network
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-16 A Pert/CPM Network for the Day Care Project
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-17 An MSP Calendar for the Day Care Project, 4/16/00 to 5/27/00
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
The Probability of Completing the Project on Time=NORMDIST(D,,,TRUE)
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-18 The Statistical Distribution of Completion Times of the Path a-b-d-g-h
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Selecting Risk and Finding DNORMINV(probability,,,TRUE)
Copyright 2005 John Wiley & Sons, Inc.
SIMULATION
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Traditional Statistics Versus SimulationSimilaritiesmust enumerate alternate pathsDifferencessimulation does not require assumption of path independence
Copyright 2005 John Wiley & Sons, Inc.
THE GANNT CHART
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-23 A Gantt Chart of a Sample Project
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-24 A Gantt Chart of Sample Project Showing Critical Path, Path Connections, Slack, EST, LST, EFT, and LFT
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-25 A Gantt Chart of a Day Care Project Showing Expected Durations, Critical Path, Milestone, and Resource Requirements
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-26 A Progress Report on a Day Care Project Showing Actual Progress Versus Baseline
Copyright 2005 John Wiley & Sons, Inc.
EXTENSIONS TO PERT/CPM
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Precedence DiagrammingFinish-to-start linkageStart-to-start linkageFinish-to-finish linkageStart-to-finish linkage
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Figure 5-27 Precedence Diagramming Conventions
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
Other MethodsGraphical Evaluation and Review Technique (GERT)combines flowgraphs, probabilistic networks, and decision treesallows loops back to earlier events and probabilistic branching
Copyright 2005 John Wiley & Sons, Inc.
MEM 612 Project Management
CopyrightCopyright 2005John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that permitted in Section 117 of the 1976 United States Copyright Act without express permission of the copyright owner is unlawful. Request for further information should be addressed to the Permissions Department, John Wiley & Sons, Inc. The purchaser may make back-up copies for his/her own use only and not for distribution or resale. The Publisher assumes no responsibility for errors, omissions, or damages, caused by the use of these programs or from the use of the information herein.
Copyright 2005 John Wiley & Sons, Inc.