14
Problem1: An assemble is to be made from „2‟ parts „x‟ a d ‟y‟. Botha parts must be turned a lathe. „y‟ must be polished whereas „x‟ need not be polished. The sequence of actives, to gather with their predecessor s given below. Activity Description Predecessor activity A Open work order - B Get Material for X A C Get material for Y A D Then X on lathe B E Then y on lathe B,C F Polish Y E G Assemble x and y D,F H Pack G Draw a net work diagram of activities for project. Solution: Problem-2: Listed in the table are the activities and sequencing necessary for a maintenance job on the heat exchanging. Activity Description Predecessor A Dismantle pipe connections - B Dismantle heater, closure, and floating front A C Remove Tube Bundle B D Clean bolts B E Clean heater and floating head B 1 6 5 3 4 2 8 7 F A C E B D G H Dummy

Cpm Pert Problem

Embed Size (px)

DESCRIPTION

MANAGEMENT

Citation preview

Page 1: Cpm Pert Problem

Problem1:

An assemble is to be made from „2‟ parts „x‟ a d ‟y‟. Botha parts must be turned a lathe. „y‟ must be polished

whereas „x‟ need not be polished. The sequence of actives, to gather with their predecessor s given below.

Activity Description Predecessor activity

A Open work order -

B Get Material for X A

C Get material for Y A

D Then X on lathe B

E Then y on lathe B,C

F Polish Y E

G Assemble x and y D,F

H Pack G

Draw a net work diagram of activities for project.

Solution:

Problem-2: Listed in the table are the activities and sequencing necessary for a maintenance job on the heat exchanging.

Activity Description Predecessor

A Dismantle pipe connections -

B Dismantle heater, closure, and

floating front

A

C Remove Tube Bundle B

D Clean bolts B

E Clean heater and floating head B

1 6

5 3

4

2 8 7

F

A

C

E

B D

G H

Dummy

Page 2: Cpm Pert Problem

front

F Clean tube bundle C

G Clean shell C

H Replace tube bundle F,G

I Prepare shell pressure test D,E,H

J Prepare tube pressure test

And reassemble

I

Draw a net work diagram of a activities for the projects.

Solution:

Problem-3: Listed in the table are activities and sequencing necessary for the completion of a recruitment

procedure for management trainees (µt) in a firm.

Solution:

Activity Description Predecessor Activity

A Asking units for recruitments -

B Ascertaining management

trains(MTs) requirement for

commercial function

A

C Asserting MTs requirement for

Account/finance functions

A

D Formulating advertisement for

MT(commercial)

C

E Calling applications from the B

5

10 9

6

8

7

3

4

2 1

C

A B

I

E

G

D

F

H

J

Page 3: Cpm Pert Problem

succedfull conditions passing

through the institute

F Calling application s from the

successful conditions passing

through the institute of chartered

Accounts (ICA)

C

G Releasing the advertisement D,E

H Completing applications

received

G

I Screening of applications against

advertisement

H

J Screening of applications

received from ICA

F

K Sending of personal forms I,J

L Issuing interview/regret letters K

M Preliminary interviews L

N Preliminary interviews of

outstanding candidates from ICA

J

O Final inter view M,N

Draw a network of activities for the project.

Solution: the net work diagram for the given project.

PROBLEMS ON CRITICAL PATH METHOD (CPM):

1

8 6 4

3 14 13 12 11 10 9 7 5

2

B

A

C

D R

O

M

L

K

H

G

E

N

F J

I

Page 4: Cpm Pert Problem

PROBLEM-1: A project has the following times schedule

Activity 1-2 1-3 2-4 3-4 3-5 4-9 5-6 5-7 6-8 7-8 8-9 8-10 9-10

Time in

weeks

4 1 1 1 6 5 4 8 1 2 1 8 7

Construct CPM Network and compute.

I. TE and TL for each event.

II. Float for each activity

III. Critical path and its duration.

SOLUTION:

The net work is constructed as given in diagram.

FORWARD PASS CALUCLATION: BACKWARD PASS CALUCLATION:

4

6

5

7

8

9

3

2

1

10

4

1

1

1

5

6

8

4 1

2

8

7

1

=18 =18

=17 =17

=15 =15

=1 =1

=7 =7

=4 12

=11 =16

=25 =25

=5 =13

{ } { ) )} , i=2, 3 = { ) )} =Max {5, 2} =5 { } { ) )} , i=6, 7 = { ) )} =Max {12, 17} =17 { } { ) )} , i=4, 8 = { ) )} =Max {10,18} =18 { } { )

{ } { )

)} , J=9, 10 = { ) )} =MIN {17, 17} =17

{ } { )

)} , J=6, 9 = { ) )} =Min {7, 12} =12

{ } { )

)} , J=2, 3

=1

=11

=15

=17

=0

Page 5: Cpm Pert Problem

I. The tail event ( )and head event ( ) computed on the network as follows

EVENT 1 2 3 4 5 6 7 8 9 10

0 4 1 5 7 11 15 17 18 25

0 12 1 13 7 16 15 17 18 25

CRITICAL PATH:

Activity

(i.j)

(1)

Duration

of time

( )

(2)

Earliest time

Starting

( )

Finishing time

( )

(3) (4)=(3)+(2)

Latest time

Starting

Finishing

)

(5)=(6)-(2) (6)

Total float

time

T-F= )

(7)=(5)-(3)

1-2 4 0 4 8

12

8

1-3 1 0 1 10 11 10

2-4 1 4 5 12 13 8

3-4 1 1 2 12 13 12

3-5 6 1 7 6 12 5

4-9 5 5 10 13 18 8

5-6 4 7 11 12 16 5

5-7 8 7 15 7 15 0

6-8 1 11 12 16 17 5

7-8 2 15 17 15 17 0

8-9 1 17 18 17 18 0

8-10 8 17 25 8 0 9

9-10 7 18 25 8 0 10

=25

=18

Page 6: Cpm Pert Problem

CRITICAL PATH ACTIVITIES:

From the above table we observe that the activities 5-7, 7-8 and 8-9 are critical activities

as their total float is zero. Hence we have the following critical path.

5-7, 7-8 and 8-9 8+8+7=25

Problem-2: The following table gives activities of duration of construction project work.

ACTIVITY 1-2 1-3 2-3 2-4 3-4 4-3

DURATION 20 25 10 12 6 10

a) Draw the network for the project.

b) Find the critical path.

Solution:

FORWARD PASS CALUCLATION: BACKWARD PASS CALUCLATION:

4 5

3

2

1

=30 =30

=46 =46

=20 20

=36 =36

25

20

6

12

10

10

{ } { ) )} , i=2, 3 = { ) )} =Max {32, 36} =36

{ } { )

)} , J= 3,4 = { ) )} =Min {20,14} =20

{ } { )

)} , J=2, 3 = { ) )} =Min {0,5} =0

=30

=0

Page 7: Cpm Pert Problem

Activity

(i.j)

(1)

Duration

of time

( )

(2)

Earliest time

Starting

( )

Finishing time

( )

(3) (4)=(3)+(2)

Latest time

Starting

Finishing

)

(5)=(6)-(2) (6)

Total float

time

T-F= )

(7)=(5)-(3)

1-2 20 0 20 0 20 0

1-3 25 0 25 5 30 5

2-3 10 20 30 20 30 0

2-4 12 20 32 24 36 4

3-4 6 30 36 30 36 0

4-5 10 36 46 36 46 0

From the above table we observe that the activities 1-2, 2-3, 3-4, and4-5 are critical activities as

their total float is „0‟. Hence we have the following critical path

1-2-3-4-5 with the total project duration is „46‟ days.

Problem-3:

Find the critical path and calculate the slack time for each event for the following PERT diagram.

Solution:

FORWARD PASS CALUCLATION: BACKWARD PASS CALUCLATION:

4

6

5

7 8 9 3

2

1

2

1

4

8

5

3

2

5

4

5

1

3

{ } { )

J= 1 = { ) ) =Min {12}

{ ) = { ))} = {10} =10

{ ) = { ))} = {11} =11

=0

Page 8: Cpm Pert Problem

These values can be represented in the following network diagram.

Activity

(i.j)

(1)

Duration

of time

( )

(2)

Earliest time

Starting

( )

Finishing time

( )

(3) (4)=(3)+(2)

Latest time

Starting

Finishing

)

(5)=(6)-(2) (6)

Total float

time

T-F= )

(7)=(5)-(3)

1-2 2 0 2 5 7 5

{ } { ) ) )} , J= 2, 3, 4 = { ) ) )} =Min {5, 0, 6} =0

4

6

5

7 8 9

2

1

2

1

4

8

5

3

2

5

4

5

1

3 3

=15 =15

=11 =12

=7 =8

=2 =2

=10 =10

=7

=11 =16

=1 =7

=1

=11

=11

=15

Page 9: Cpm Pert Problem

1-3 2 0 2 0 2 0

1-4 1 0 1 6 7 6

2-6 4 2 6 7 11 5

3-7 5 2 7 3 8 1

3-5 8 2 10 2 10 0

4-5 3 1 4 7 10 6

5-9 5 10 15 10 15 0

6-8 1 6 7 11 12 5

7-8 4 7 11 8 12 1

8-9 3 11 14 12 15 1

[PERT]

In the net work analysis it is implicitly assumed that the time values are deterministic or

variations in time are insignificant. This assumption is valid in regular jobs such as

i. Maintenance of machine.

ii. Construction of a building or a power

iii. Planning for production.

As these are done from time and various activities could be timed very well

However in reach projects or design of a gear box of a new machine various

Activities .are based on judgment. A reliable time estimate is difficult to get because the technologies is

changing the job? the pert approach taxes into account the uncertainties associated with in that activity.

DEFINATIONS:

1. OPTIMISTIC TIME: the optimistic time is the shortcut possible time in which the activity can be

finished. It assumes that everything goes very well. This is denoted by „ ”

2. MOST LIKELY TIME; the most likely time is the estimate of the activity would take. This assumes

normal delays. If a graph is plotted in the time of completion and the frequency of completion in that time

period than the „most likely time „will represent the highest frequency of a occurrence. This is denoted by

“ ”.

3. PESIMISTIC TIME; the „pessimistic time‟ represents the longest time the activity could take if

everything goes wrong. As in optimistic estimate. This value may be such that value. This is denoted by

„ ”

These 3 types‟ values are, shown in the following diagram in order to obtain these values; one could use time

values available similar jobs. But most of the time the estimator may not be so fortunate to have this data.

Secondary values are the functions of manpower, machines and supporting facility .A better approaches would

be to seek opinion of experts in the field keeping in views the resources available, this estimate does not take

into account such natural catastrophes as fire etc.

In pert calculation all values are used to attain the percent exportation value.

4.EXPECTED TIME; the „expected time‟ is average time an activity will take if it were to be reported on

large number of times and it is base on the assumption that the activity time follows „Bets distribution‟. This is

given by the formula

=(

)

5. VARIANCE: the variance for the activity is given by the formula

Page 10: Cpm Pert Problem

*( )

+

Where = the pessimistic time. =the expected time.

Frequency

O

Time

Problem-1: for the project represented by the network diagram, find the earliest time and latest times to reach

each node given the following data.

TASK A B C D E F G H I J K

LEAST TIME 4 5 8 2 4 6 8 5 3 5 6

GREATEST

TIME

8 10 12 7 10 15 16 9 7 11 13

MOST LIKELY

TIME

5 7 11 3 7 9 12 6 5 8 9

Optimistic time

Most likely time

Pessimistic Time

4 6

5 7

8

9

2

1

3

A B

D F

E

H

K C

Page 11: Cpm Pert Problem

SOLUTION;

First we calculate the expected time „ „by the formula “ = (

) as follows

Task Optimistic

time( ) Pessimistic

time( )

Most likely time

( ) Expected time

( )

A 4 8 5 = )

= 5.3

B 5 10 7 = )

7.2

C 8 12 11 = )

10.7

D 2 7 3 = )

3.5

E 4 10 7 = )

7

F 6 15 9 = )

9.5

G 8 16 12 = )

12

H 5 9 6 = )

6.3

I 3 7 5 = )

5

J 5 11 8 = )

8

K 6 13 9 = )

9.1

Now the earliest time expected time for each note are obtained by taking sum of the expected times for all

the activities leading to node i, when more than one activity leads to a node i, the maximum of is called.

FORWARD PASS CALUCLATION: BACKWARD PASS CALUCLATION:

G G J

{ } { ) =0+5.3=5.3 { } { ) ) { ) )} =max {12.5,10.4} =12.5 { } { ) ) { ) )} =max {13,19.5} =19.5 { } { ) ) { ) )} =max {15.5,24.5} =24.5

{ ) = { ))} = 24.5

{ ) = { ))} = 25.9

{ } { )

)} , J= 3,7 = { ) )} =Min {19.5,19.5} =2

{ ) = { ))} = 12.5

{ } { )

)} , J= 5,7 = { ) )} =Min {10,12.5} =10

{ ) = { ))} = 7

{ } { )

)} , J= 2,4

= 19.5

2.5

=25.8

=0

Page 12: Cpm Pert Problem

TASK A B C D E F G H I J K

LEAST TIME 4 5 8 2 4 6 8 5 3 5 6

GREATEST

TIME

8 10 12 7 10 15 16 9 7 11 13

MOST LIKELY

TIME

5 7 11 3 7 9 12 6 5 8 9

Estimation Time 5.3 7.2 10.7 3.5 7 9.5 12 6.3 5 8 9.2

These calculations are may be arranged in the following table.

NODE SLACK( )

1 5.3 5.3 5.3 0

2 3.5 3.5 10.0 6.5

3 7.2 12.5 12.5 0

4 7 19.5 19.5 0

5 6.3 25.8 25.8 0

6 5 24.5 24.5 0

7 9.1 34.9 34.9 0

8 8.0 32.5 32.5 0

=34.9

=32.5

4 6

5 7

8

9

2

1

3

A(5.3) B(7.2)

D(3.5)

G(12)

E(7)

H(6.3)

I (5) J(8)

K(9.1) C(10.4)

F=9.5

=32.5 =32.5

=34.9 =34.9

=24.5 =24.5

=3.5 =10.0

=19.5 =19.5

=5.3

=25.8 =25.8

=12.5 =12.5

Page 13: Cpm Pert Problem

PROBLEM-2: A project has the following characteristics

ACTIVITY 1-2 2-3 2-4 3-5 4-5 4-6 5-7 6-7 7-8 7-9 8-10 9-10

MOST

OPTEMESTI

TIME(a)

1 1 1 3 2 3 4 6 2 5 1 3

MOAST

PESSIMESTIC

TIME(b)

5 3 5 5 4 7 6 8 6 8 3 7

MOST LIKELY

TIME(m)

1.5 2 3 4 3 5 5 7 4 6 2 5

Construct a PERT network. Find critical path and variance for each event find the project duration as

95% probability.

SOLUTION: Activity expected times & their variances are computed by the following formula

Expected time ( ) = (

). V=

)

Activity a b 4m V

1-2 1 5 6 = )

=2 4/9

2-3 1 3 8 = )

2 1/9

2-4 1 5 12 = )

3 4/9

3-5 3 5 16 = )

4 1/9

4-5 2 4 12 = )

1/9

4-6 3 7 20 = )

5 4/9

5-7 4 6 20 = )

5 1/9

6-7 6 8 28 = )

7 1/9

7-8 2 6 16 = )

4 4/9

7-9 5 8 24 = )

6.16 1/9

8-10 1 3 8 = )

1 1/9

9-10 3 7 20 )

5 4/9

5

8

9

2

3

1

10

1

1

3

1 2

2

4

5

6

1

3

1

=139/6 =139/6

=17 =17

=4 =8

=8 =12

=169/9 =169/9

7

Page 14: Cpm Pert Problem

FORWARD PASS CALUCLATION: BACKWARD PASS CALUCLATION:

The longest path is 1-2-4-6-7-9-10 can be traced. This is known as critical path.

PROBLEM ON PROJECT CRASHING: The following table gives data on normal time, and cost crash time and cost for a project

Activity Normal

Time (weeks) Cost(Rs/-)

Crash

Time (weeks) Cost(Rs/-)

1-2 3 300 2 400

2-3 3 30 3 30

2-4 7 420 5 580

2-5 9 720 7 810

3-5 5 250 4 300

4-5 0 0 0 0

5-6 6 320 4 410

6-7 4 400 3 470

6-8 13 780 10 900

7-8 10 1000 9 1200

Indirect cost is 50/- per week.

Draw the network diagram for the

4

6

3

=17 =127/6

=10 =10

=5 =5

=2 =2

{ } { ) =0+2=2 { } { ) ) { ) )} ) { } { ) ) { ) )} =max {13,17} =17

{ } { )

) { )

)}

=max {21,

} =

-2=

{ } { )

)} , J= 8,9

= ,(

)

)} =Min {19.5,17} =17

{ ) = { ))} = 10

{ ) = { ))} = 12

{ ) = { ))} = 5

{ } { )

{ } { )

)} , J= 3,4 = { ) )} =Min {6,2} =2

{ } { )

=0

4 6 5 7 8 2 1 3

10

7

3 9 6

5 13 4 3 =32

=32

=22 =22

=6 =7

=12 =12

=3

=18 =18

=10 =12

=0

0