Agile Dino Wrangling Lessons learned on the game 65 million years in the making Montreal International Game Summit 2012 Thiéry Adam

Migs2012 Jurassic Park Builder

Embed Size (px)

DESCRIPTION

Montreal International Game Summit 2012 presentation. Post-mortem on the project management of Jurassic Park Builder from conception to launch on iOS.

Citation preview

Page 1: Migs2012 Jurassic Park Builder

Agile Dino WranglingLessons learned on the game 65 million

years in the making

Montreal International Game Summit 2012Thiéry Adam

Page 2: Migs2012 Jurassic Park Builder

PRESENTATION STRUCTURE• Introduction• Iterations to reduce risk• Stakeholder Iterations• Production Iterations• Team Format Iterations• Conclusion

Page 3: Migs2012 Jurassic Park Builder

INTRODUCTION

Who am I?• Producer• Design, art & technical backgrounds• Specialized in stakeholder management

Page 4: Migs2012 Jurassic Park Builder

INTRODUCTION

Past Projects

Page 5: Migs2012 Jurassic Park Builder

INTRODUCTION

Who is Ludia?• Facebook, iOS and Android• Publisher & developer• Specializes in mass market brands

Page 6: Migs2012 Jurassic Park Builder

PROJECT CONTEXT

Business Opportunity• City-building games

were the rage on FB• Ludia identifies brands

to apply to genres

Page 7: Migs2012 Jurassic Park Builder

PROJECT CONTEXT

License• First project with Universal• First movie license

Page 8: Migs2012 Jurassic Park Builder

INTRODUCTION

What is Jurassic Park Builder?• Resource management and park building• Free-to-play with in-app purchases• Now on iOS, soon on Android & Facebook

Page 9: Migs2012 Jurassic Park Builder

INTRODUCTION

Jurassic Park Builder Pre-Launch• 11 months of production• 35 direct internal team members at peak• 4 outsourcing partners

Page 10: Migs2012 Jurassic Park Builder

INTRODUCTION

Jurassic Park Builder Results• Has reached #1 game in 8 territories so far.• Consistently rated 4.5 stars.• Monetizes well thanks to continual new content.

Page 11: Migs2012 Jurassic Park Builder

ITERATIONS TO REDUCE RISK

Scrum Agile Framework

2-Week Sprint

Deliverables

Reviews

Improve

Game & methodologiesInternal, editorial, licensor

Page 12: Migs2012 Jurassic Park Builder

ITERATIONS TO REDUCE RISK

Assess the situation• Discuss with all the stakeholders• Identify where there are differences in

expectations or uncertainty

Page 13: Migs2012 Jurassic Park Builder

ITERATIONS TO REDUCE RISK

To Each Issue An Owner• For every issue, a single person must be

clearly labelled as responsible.• Responsibility must be assigned to team

members to remain empowered.

Page 14: Migs2012 Jurassic Park Builder

ITERATIONS TO REDUCE RISK

Prioritize Issues1. Reduce Uncertainty to Create Value2. Reduce Risks To Gain Velocity3. Seek Autonomy To Improve Growth

Page 15: Migs2012 Jurassic Park Builder

ITERATIONS TO REDUCE RISK

1. Reduce Uncertainty to Create Value• Agile is about delivering more and more

value per sprint• Reducing uncertainty initially generates the

most value

Page 16: Migs2012 Jurassic Park Builder

ITERATIONS TO REDUCE RISK

1. Reduce Uncertainty to Create ValueExample: Predictable Communication• Coming from an extended period of low-

communication & irregular effort while other projects were winding down, Universal was understandably anxious.

• Establishing clear expectancies of how and how often we would communicate, and committing to them, already started to deliver value in the form of trust.

Page 17: Migs2012 Jurassic Park Builder

ITERATIONS TO REDUCE RISK

2. Resolve Risks To Gain Velocity• Risks are bottlenecks that hold

back the talented team from full potential.

• Many risks can be resolved by provoking them as early as possible.

• Often maintaining potential risk is more costly than embracing the negative outcome.

Page 18: Migs2012 Jurassic Park Builder

ITERATIONS TO REDUCE RISK

2. Resolve Risks To Gain VelocityExample: 2D vs. 3D dinosaurs• Large commitment in terms of

style and technology• The team was paralyzed during

the investigation.• Instead of figuring out

completely if each could work, we cut off the investigation when at least one could work.

Page 19: Migs2012 Jurassic Park Builder

ITERATIONS TO REDUCE RISK

3. Seek Autonomy To Improve Growth• Invest in self-reliance to increase output.• Team composition and methodologies

should be continually revised to improve.• Include individual development in planning.

Page 20: Migs2012 Jurassic Park Builder

ITERATIONS TO REDUCE RISK

3. Seek Autonomy To Improve GrowthExample: Determine potential growth vs. needs• One important case to test out was

determining if future needs were within the potential evolution of the current team.

• We injected new team members to cover certain skill sets that were beyond a safe evolution timeframe.

Page 21: Migs2012 Jurassic Park Builder

ITERATIONS TO REDUCE RISK

Examples of Risk-Reducing Iteration1. Stakeholder Iterations2. Production Iterations3. Team Format Iterations

Page 22: Migs2012 Jurassic Park Builder

STAKEHOLDER ITERATIONS

Diverging Project Vision• Team members, Ludia editorial

& Universal all have a different game in mind.

• Player goals, brand goals and business goals are not necessarily initially aligned.

Page 23: Migs2012 Jurassic Park Builder

STAKEHOLDER ITERATIONS

The Project Core Lens• Identify a non-mechanical vision to

assemble common objectives.• From that solid foundation, build in layers.

Jurassic Park Builder

Ludia Editorial

Project Team

Licensor

BelievabilityLegibility

Page 24: Migs2012 Jurassic Park Builder

STAKEHOLDER ITERATIONS

The Project Core Lens Applied• Dinosaur’s perceived movement

limitations could have been a conflict between budget and brand image.

• By using the lens as an discussion tool, we were able to find a signature that made all stakeholders happy.

Page 25: Migs2012 Jurassic Park Builder

PRODUCTION ITERATIONS

The Good-Enough Cut-Off• Potential is endless, but resources aren’t.• Constantly consider if investing them

elsewhere would generate more value.

Page 26: Migs2012 Jurassic Park Builder

PRODUCTION ITERATIONS

Teach Good-Enough• Practice the thought process with the

team until they assimilate value/effort.• Example: going from over-engineering a

single feature to seeking ways to leverage.

Page 27: Migs2012 Jurassic Park Builder

TEAM FORMAT ITERATIONS

Initial Team Format• First team setup was by functionality…… but dependencies kept slipping through.

Jurassic Park Builder iOS Team

Game Programming

Online Programming

UIArt

3DArt

3DAnimation

Game Design

QualityAssurance

Page 28: Migs2012 Jurassic Park Builder

TEAM FORMAT ITERATIONS

Mega-Scrum• Merged into a group to share planning…… but the practices were unwieldy.

Jurassic Park Builder iOS Team

Scrum Team

Game DesignGame Programming

2D Art3D Art

Online Programming

3DAnimation

QualityAssurance

Page 29: Migs2012 Jurassic Park Builder

TEAM FORMAT ITERATIONS

Interactive vs. Content• Moving out of the scrum every iteration to

accelerate, based on features.

Jurassic Park Builder iOS Team

Scrum Interactive Team

New Features

Kanban Content Teams

DinosaursDecorations

Buildings

Outsourcing

Page 30: Migs2012 Jurassic Park Builder

TEAM FORMAT ITERATIONS

Example Kanban Board

Dinosaurs Kanban

Concept Model Skin Texture Animation

_ _

_

_ _

_

_ _ _ _

_

_ _

__ _

Page 31: Migs2012 Jurassic Park Builder

CONCLUSION

Recap: Risk Iteration• Your job is to help your

team by removing as many important impediments as possible every sprint.

• Invest in your team, and in the long run it they will be the biggest source of growth.

Page 32: Migs2012 Jurassic Park Builder