4
- 1 - MARINE ENGINEERING TEAM FLEET UPKEEP GROUP Category : Electricity DATE : 03/21/2012 REF.NO. : 2012 - 001 SEQ.NO. : 578 E SUBJECT: Blackout while passing through the Gulf of Aden A main switchboard blackout occurred on an LNG vessel under our operation while it was passing through the Gulf of Aden. The blackout happened during maintenance work on the main switchboard. After the blackout, electrical power was immediately restored, but the ship's crew took approx. 5.5 hours to restore all systems, including the main turbine. As a result, the ship was immobilized while it was in the piracy area. Diesel propulsion ships may encounter the occurrence of blackout similarly. To avoid a similar trouble, the following should be confirmed as soon as possible: the condition of each air circuit breaker (ACB), ACB operation, and emergency procedures. Needless to say, the risk of marine casualties in high-risk areas or during coastal navigation is higher than during oceangoing navigation. Therefore, a risk assessment prior to maintenance work should be carried out if the possibility of a blackout exists. 1. Summary of accident <Details of repair work> Replacement of the malfunctioned HIMAP for the No. 2 turbine generator fitted in the main switchboard (MSB). Function of HIMAP: Power management of MSB, monitoring, and safety device for 6600V <Accident sequence> 0800 Commenced replacement of the HIMAP for the No. 2 turbine generator fitted in the MSB. 0820 Transferred entire electric load from the No. 2 turbine generator to the No. 1 turbine generator and then disconnected the No.2 turbine generator. 0836 An alarm sounded for the No. 1 main bus-tie breaker earth fault. Immediately after the alarm, the alarm for the No. 2 main bus-tie breaker earth fault also sounded. 0837 The No. 1 turbine generator was automatically disconnected, causing

mei 2012001 Blackout while passing through the Gulf of Aden.pdf

Embed Size (px)

Citation preview

- 1 -MARINE ENGINEERING TEAMFLEET UPKEEP GROUPCategory : Electricity DATE : 03/21/2012REF.NO. : 2012 - 001SEQ.NO. : 578 ESUBJECT: Blackout while passing through the Gulf of AdenA main switchboard blackout occurred on an LNG vessel under our operation while it was passing through the Gulf of Aden. The blackout happened during maintenance work on the main switchboard. After the blackout, electrical power was immediately restored, but the ship's crew took approx. 5.5 hours to restore all systems, including the main turbine. As a result, the ship was immobilized while it was in the piracy area.Diesel propulsion ships may encounter the occurrence of blackout similarly. To avoid a similar trouble, the following should be confirmed as soon as possible: the condition of each air circuit breaker (ACB), ACB operation, and emergency procedures.Needless to say, the risk of marine casualties in high-risk areas or during coastal navigation is higher than during oceangoing navigation. Therefore, a risk assessment prior to maintenance work should be carried out if the possibility of a blackout exists.1. Summary of accident

Replacement of the malfunctioned HIMAP for the No. 2 turbine generator fitted in the main switchboard (MSB).Function of HIMAP: Power management of MSB, monitoring, and safety device for 6600V

0800 Commenced replacement of the HIMAP for the No. 2 turbine generator fitted in the MSB.0820Transferred entire electric load from the No. 2 turbine generator to the No. 1 turbine generator and then disconnected the No.2 turbine generator.0836An alarm sounded for the No. 1 main bus-tie breaker earth fault. Immediately after the alarm, the alarm for the No. 2 main bus-tie breaker earth fault also sounded. 0837 The No. 1 turbine generator was automatically disconnected, causing - 2 -a blackout. The standby diesel generator automatically started, and electric power was restored to both the 6600V high voltage (HV) switchboards. However, electric power was not restored to the No. 1 440V low voltage (LV) switchboard because the root ACB(TM1) of the switchboard was open. The cold start boiler feed pump was notable to start because there was no power from the No. 1 440 LVswitchboard. Worse, the main boiler was not able to recover due to amalfunction of the uninterruptible power supply (UPS) for the boiler.1022 The ACB (TM1) for the No. 1 440V LV switchboard was manually closed and electric power was restored.1345Both boilers were steamed up using emergency electric power insteadof the damaged UPS, and preparation work for the main turbine operation was completed.1359 Maneuvering operation resumed.2. Blackout sequence (see attached Fig. 2)(1) During replacement of the HIMAP, a live wire (terminal no. 18) accidentally made contact with an adjacent connection (terminal no. 15).(2) The above momentary event would have caused a short circuit and the circuit breaker (MCB-252) to trip. (3) There is a transducer that monitors the voltage and frequency downstream from MCB-252. It detected an abnormal condition.(4) The No. 1 turbine generator was disconnected because of the No. 2 HV MSB low voltage and frequency alarm, thus causing the blackout.3. Cause of extended unrestored condition for No. 1 440V LV switchboard (see attached Fig. 1)The latch relay for the ACB of the No. 1 440V LV switchboard was not set in the "latch" position. Therefore, the ACB would not close automatically. Moreover, much time was required to determine that the ACB was in an open position. Normal setting>>> Latch position Setting prior to the blackout incident>>> Unlatch positionThe "unlatch" position of the latch relay is a safety device used during maintenance work. If the latch relay is set to the "unlatch" position, the ACB will not close automatically. The latch relay might have been set to the "unlatch" position when the previous inspection was conducted by the service engineer.Latch relay for ACBBUS-TIEFig. 1GPT: Ground Potential TransformerBUS-TIEFig. 2