MEETING NOTICE AND AGENDA TransNet INDEPENDENT TAXPAYER OVERSIGHT COMMITTEE (ITOC) The ITOC may take action on any item appearing on this agenda. Wednesday, September 19, 2007 9:30 a.m. to 3:30 p.m. SANDAG 7th Floor Conference Room 401 B Street, 7th Floor San Diego, CA 92101 Staff Contact: Kim Kawada (619) 699-6994 [email protected] AGENDA HIGHLIGHTS UPDATE ON THE SPRINTER RAIL PROJECT QUARTERLY REPORT ON THE TransNet EARLY ACTION PROGRAM 2007 ITOC ANNUAL REPORT SANDAG offices are accessible by public transit. Phone 1-800-COMMUTE or see www.sdcommute.com for route information. In compliance with the Americans with Disabilities Act (ADA), SANDAG will accommodate persons who require assistance in order to participate in SANDAG meetings. If such assistance is required, please contact SANDAG at (619) 699-1900 at least 72 hours in advance of the meeting. To request this document or related reports in an alternative format, please call (619) 699-1900, (619) 699-1904 (TTY), or fax (619) 699-1905.

MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

MEETING NOTICE AND AGENDA

TransNet INDEPENDENT TAXPAYER OVERSIGHT COMMITTEE (ITOC) The ITOC may take action on any item appearing on this agenda. Wednesday, September 19, 2007 9:30 a.m. to 3:30 p.m. SANDAG 7th Floor Conference Room 401 B Street, 7th Floor San Diego, CA 92101 Staff Contact: Kim Kawada (619) 699-6994 [email protected]

AGENDA HIGHLIGHTS

• UPDATE ON THE SPRINTER RAIL PROJECT

• QUARTERLY REPORT ON THE TransNet EARLY ACTION PROGRAM

• 2007 ITOC ANNUAL REPORT

SANDAG offices are accessible by public transit. Phone 1-800-COMMUTE or see www.sdcommute.com for route information. In compliance with the Americans with Disabilities Act (ADA), SANDAG will accommodate persons who require assistance in order to participate in SANDAG meetings. If such assistance is required, please contact SANDAG at (619) 699-1900 at least 72 hours in advance of the meeting. To request this document or related reports in an alternative format, please call (619) 699-1900, (619) 699-1904 (TTY), or fax (619) 699-1905.

Page 2: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

2

Welcome to SANDAG. Members of the public may speak to the TransNet Independent Taxpayer Oversight Committee (ITOC) members on any item at the time the ITOC is considering the item. Also, members of the public are invited to address the ITOC on any issue under the agenda item entitled Public Comments/Communications/Member Comments. Speakers are limited to three minutes. The ITOC may take action on any item appearing on the agenda. This agenda and related staff reports can be accessed at www.sandag.org under Meetings on SANDAG’s Web site. Public comments regarding the agenda can be forwarded to SANDAG via the e-mail comment form also available on the Web site. E-mail comments should be received no later than noon, two working days prior to the ITOC meeting. In compliance with the Americans with Disabilities Act (ADA), SANDAG will accommodate persons who require assistance in order to participate in SANDAG meetings. If such assistance is required, please contact SANDAG at (619) 699-1900 at least 72 hours in advance of the meeting. To request this document or related reports in an alternative format, please call (619) 699-1900, (619) 699-1904 (TTY), or fax (619) 699-1905.

SANDAG offices are accessible by public transit. Phone 1-800-COMMUTE or see www.sdcommute.com for route information.

Page 3: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

TransNet INDEPENDENT TAXPAYER OVERSIGHT COMMITTEE (ITOC)

Wednesday, September 19, 2007

3

ITEM # RECOMMENDATION

+1. MEETING SUMMARY FOR THE JULY 18, 2007, ITOC MEETING APPROVE A summary of the July 18, 2007, ITOC meeting has been prepared for the

Committee’s review and approval. Estimated Start Time: 9:30 a.m.

2. PUBLIC COMMENTS/COMMUNICATIONS/MEMBER COMMENTS INFORMATION Members of the public will have the opportunity to address the ITOC on

any issue within the jurisdiction of the ITOC. Speakers will be limited to three minutes each. Committee members also may provide information and announcements under this agenda item.

Estimated Start Time: 9:35 a.m.

3. ITOC MEETING SCHEDULE: ALTERNATIVE DATES AND TIMES DISCUSSION/

POSSIBLE ACTION The ITOC has been meeting on the third Wednesday of the month starting

at 9:30 a.m. A request has been made for consideration of revision to the schedule. The committee should discuss potential options and decide if a change is to be made to the meeting schedule.

Estimated Start Time 9:40 a.m.

+4. SPRINTER PROJECT STATUS REPORT AND SANDAG INDEPENDENT

ASSESSMENT (Jim Linthicum) INFORMATION

This item provides a monthly status report on the SPRINTER rail project,

including discussion of implementation and effectiveness of project cost control measures and the SANDAG independent assessment of the project.

Estimated Start Time: 9:55 a.m.

+5. QUARTERLY REPORT ON TransNet EARLY ACTION PROGRAM

(Richard Chavez) INFORMATION

Staff will provide an overview of the TransNet major corridor projects in

terms of cost control and schedule adherence based on data provided through the Dashboard reporting system. Updates and refinements to the Dashboard also will be discussed. This item relates to the required quarterly reporting process specified under Paragraph 10 of the Ordinance. The ITOC is to review the information provided by staff and accept the quarterly report or make additional comments and recommendations.

Estimated Start Time: 10:30 a.m.

+6. FINAL DRAFT 2007 ITOC ANNUAL REPORT (Joy De Korte) REVIEW AND COMMENT/

APPROVE Staff distributed an initial draft of an annual report for FY 2007 at the last

meeting. Based on comments received since that meeting, a final draft annual report has been developed. If approved, a presentation of the annual report will be scheduled for the SANDAG Board of Directors.

Estimated Start Time: 11:30 a.m.

Page 4: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

4

ITEM # RECOMMENDATION

7. FUTURE MEETING SCHEDULE APPROVE The dates shown below have been suggested as potential meeting dates.

The meetings are proposed to be scheduled from 9:30 a.m. to 3:30 p.m. The next meeting date and time will be confirmed at the end of each meeting. The ITOC may wish to suggest specific agenda topics for the next meeting(s). Potential topics for the next meeting include: ongoing discussions of major corridor projects, continued discussion of the TransNet Plan of Finance update process, and a briefing on the Committee’s responsibilities related to the new $2,000 per dwelling unit private funding requirement. Staff will provide a schedule of potential agenda items for upcoming meetings for the Committee’s review.

Scheduled Future Meeting Dates:

Estimated Start Time: 12:00 p.m.

October 17, 2007

November 21, 2007

December 19, 2007 (if needed)

8. ADJOURNMENT

+ next to an agenda item indicates an attachment

Page 5: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

San Diego Association of Governments – TransNet Program

INDEPENDENT TAXPAYER OVERSIGHT COMMITTEE

September 19, 2007 AGENDA ITEM NO.: 1Action Requested: ACCEPT

MEETING SUMMARY FOR THE JULY 18, 2007 File Number 1110200 INDEPENDENT TAXPAYER OVERSIGHT COMMITTEE (ITOC) MEETING Attendance–

Committee Members: Kevin Cummins Ron Gerow Valerie Harrison

John Meyer Jim Ryan

Ex-Officio Members: Gary Gallegos Others: Susan Carter, San Dieguito River Park

Zachary Lopez, citizen Jack Boda, SANDAG Susan Brown, SANDAG Richard Chavez, SANDAG Joy De Korte, SANDAG Mike Hix, SANDAG Miriam Kirshner, SANDAG Danielle Kochman, SANDAG

Dan Levy, SANDAG Jim Linthicum, SANDAG Jose Nuncio, SANDAG Bill Prey, SANDAG Dave Schumacher, SANDAG Craig Scott, SANDAG Anne Steinberger, SANDAG Stephan Vance, SANDAG Renee Wasmund, SANDAG

The following summarizes the major actions and key discussion points under each agenda item from the July 18, 2007, meeting.

Item 1 – Meeting Summary for the June 20, 2007, ITOC Meeting

The summary of the June 20, 2007, regular ITOC meeting was approved as written. John Meyer mentioned that, as requested at the last meeting, the draft meeting summary had been distributed to members via e-mail in advance of the agenda mailout. Valerie Harrison requested that a running list of future commitments be added as an attachment to the minutes to help the members track when future discussion items will be coming back to the committee. Craig Scott indicated he would put such a list together for the next meeting summary (Attachment 1).

Item 2 – Public Comments/Communications/Member Comments

No public comments were received.

Page 6: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

2

Item 3 – Annual Election of Chair and Vice-Chair

Craig Scott reviewed the ITOC bylaws related to the election of Chair and Vice-Chair each year.

ACTION: The ITOC unanimously selected John Meyer to serve as Chair and Hamid Bahadori to serve as Vice-Chair for FY 2008.

John Meyer asked for assistance from other members for potential presentations to the SANDAG Board of Directors and Transportation Committee as may be needed due to his occasional out-of-town commitments. He also outlined potential areas for ITOC involvement in the upcoming year, including further discussion of the performance measurement issue, a detailed briefing on ITOC responsibilities under the new impact fee program, and reports from the Metropolitan Transit System (MTS) and North County Transit District (NCTD) on future service plans and rehabilitation and capital replacement needs. Jim Ryan commented that, as we get closer to the actual start of the TransNet Extension, additional requirements will kick in, and the ITOC needs to start developing a timeline for implementation of these new requirements.

Item 4 – Mid-City Rapid Bus Project: Pursuit of Federal Very Small Starts Funding

Miriam Kirshner, SANDAG project manager for the Mid-City project, reviewed the materials included in the staff report and provided a PowerPoint presentation (Attachment 2) covering the characteristics of the project, the requirements of the new Federal Transit Administration (FTA) Very Small Starts funding program, and how the Mid-City project would fit the criteria for this new program. Valerie Harrison asked a number of questions regarding the cost estimate for the project, how it would be operated, and how it would be different from the current express services on I-15. Miriam provided additional detail on the cost estimate and the new features of the proposed Rapid Bus concept. Kevin Cummins asked about the specifics of this project as identified in the ballot measure in terms of budget and project features. He also asked what action was before the ITOC. Staff explained that the action today would be to support staff moving forward with the FTA application process in order to meet deadlines required to obtain the federal matching funds. If SANDAG is successful in obtaining the FTA Very Small Starts funding, future actions would include the inclusion of the project in the TransNet Early Action Program (EAP) and in the Plan of Finance work to be undertaken through the fall. John Meyer indicated that the ITOC should support the effort to obtain federal matching funds for one of the projects called out in the ballot measure expenditure plan.

ACTION: The ITOC voted unanimously to support staff efforts in moving ahead with the application process to seek FTA Very Small Starts program funding for the Mid-City Rapid Bus project.

Item 5 – Draft 2007 Regional Transportation Plan (RTP)

Mike Hix, SANDAG project manager for the RTP update, provided a PowerPoint presentation (Attachment 3) summarizing the key components of the RTP, which also were highlighted in the agenda materials. He focused on the differences in the three major scenarios included in the RTP – the Revenue Constrained, Reasonably Expected Revenue, and Unconstrained Revenue scenarios. Mr. Hix explained how the RTP includes the projects in the TransNet EAP, as well as other projects and programs. He highlighted the potential use of toll funding to implement improvements to I-5 and I-15 connecting with Orange and Riverside Counties, respectively, and to SR 11 serving a new third border crossing. He reviewed the major transit improvements included in the RTP and summarized

Page 7: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

3

the results of a travel time by mode comparison by major travel corridor, showing the improvements in travel time as a result of the investments planned in the RTP. Mike also described the public workshops to be held to obtain input on the draft RTP and the schedule for adoption of the final RTP by in SANDAG Board of Directors in November.

Kevin Cummins reported that he had attended the first of the scheduled public workshops in Encinitas and reviewed some of the feedback from the public received at that meeting. Valerie Harrison asked about the percentage split of funds by mode in the RTP. Gary Gallegos explained that the percentage splits were not the goal of the RTP, but rather the outcome of applying the project evaluation criteria, developing regional priorities for improvements to the transportation network, and reflecting restrictions on the use of available state and federal funds.

John Meyer expressed concern over the reliance on state and federal funds since projections are that the gas tax revenues are declining due to better fuel efficiency, use of hybrids, and other factors. Gary Gallegos commented that this will be a major issue in the next federal surface transportation reauthorization bill. He said that federal funding makes up a smaller proportion of the total RTP funding than in prior plans, as local (TransNet), and state (Propositions 1B and 42) revenues have increased in importance. John Meyer felt that proposed toll-funded improvements on I-15 north to Riverside County were a good idea given the rapid growth in southwestern Riverside County.

Item 6 – Lake Hodges Bicycle and Pedestrian Bridge Quarterly Status Report

Stephan Vance provided an overview of the Lake Hodges bicycle and pedestrian bridge project, which the ITOC first discussed at the March meeting. At that time, quarterly progress reports were requested. This report is the first of that series of progress reports. Susan Carter from the San Dieguito River Park reviewed the bidding process for construction of the bridge. A total of five bids were received, with the low bid being $600,000 more than the funds available. An additional $347,000 in grant funds was received from the State Resources Agency, leaving the project $253,000 short. The River Park has accepted the bid and is moving forward with the project. Susan reviewed the options being considered for obtaining the additional funding.

Bill Prey of SANDAG engineering staff described the agency’s oversight efforts for the project, which are similar to the role SANDAG staff has played in the development of the SPRINTER rail project over the past year. He reviewed SANDAG efforts in reviewing the bids, meeting with the selected construction firm, and analyzing the budget and schedule for the overall project. He raised concerns over the lack of contingency funds for the project and outlined potential construction risks on the project that could result in higher costs. Jim Ryan and Valerie Harrison raised questions about the total cost of the project and the range of bids. Mr. Prey responded that the low bid for construction is $6.67 million, and the high bid was $10 million. The concern was raised that adding contingency funds might lead to the likelihood that the funds would be spent. John Meyer suggested that, even though the ITOC had requested quarterly progress reports on the project, the progress reports be waived until December unless there are significant new issues to be addressed.

Item 7 – TransNet Extension Senior Transportation Mini-Grant Program

Danielle Kochman, SANDAG Assistant Planner, reviewed the materials provided in the agenda package regarding the proposed approach to implementing the new Senior Mini-Grant program that was included as part of the TransNet Extension. She also reviewed three FTA funding programs that are related to senior transportation. The proposed approach is based on the concept of

Page 8: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

4

merging these federal programs with the new TransNet funds to leverage the available funding and provide as much senior transportation service as possible. She summarized the proposed criteria to be used to select the projects to be funded. The criteria emphasize improved coordination and cost-effectiveness in order to stretch the dollars further. The merging of the TransNet program with the federal programs would result in a slight delay in the start up of the TransNet program from July 2008 to fall 2008.

John Meyer supported the focus on improved coordination as a way of getting the most out of the available dollars. Kevin Cummins suggested consideration of a set of pass/fail criteria or minimum scores to eliminate less competitive applications from the evaluation process. Valerie Harrison raised a concern about how data is verified. Dan Levy, SANDAG Senior Planner, described the process in more detail. He mentioned the difficulty of evaluating brand new proposals without any history to use to verify the projections of cost, usage, etc. The review process is designed to check for reasonableness in the data provided and to identify the best projects for consideration.

The members expressed an interest in discussing the criteria in more detail at a future meeting. Staff indicated that the key action being sought from the ITOC at this meeting was conceptual support for integrating the TransNet program with the federal programs. That would allow work underway this year in relation to required Coordinated Plan and other activities for the federal programs to continue. This work would set the stage for phasing in the TransNet Senior Mini-Grant Program in 2008. Work on the details of the application process and the evaluation criteria can continue to be discussed in the meantime.

ACTION: The ITOC unanimously supported the concept of merging the TransNet Senior Mini-Grant Program with the FTA senior transportation-related programs and requested further review of the evaluation criteria and imple-mentation procedures for the TransNet funds.

Item 8 – Draft ITOC Annual Report for Fiscal Year 2006-07

Craig Scott distributed the initial draft of the second annual report of ITOC activities. He introduced Joy De Korte, Public Information Officer, who had prepared the draft report and asked the members to provide comments on the draft report to Ms. De Korte. The schedule is to have a draft final report for the committee to review in September and, if approved, to make a presentation of the final annual report to the SANDAG Board of Directors in September or October.

John Meyer suggested that the roster of ITOC members be expanded to reflect all ITOC members, not just the current members. All members were encouraged to provide their input on the draft report.

Item 9 – Update on the TransNet Plan of Finance Process

Richard Chavez updated the ITOC on work underway on the Plan of Finance using a PowerPoint presentation (Attachment 4). As discussed at the May meeting, the plan update process is intended to review the financial status of the EAP, including detailed cost and schedule estimates for each of the EAP projects, as well as to analyze on a programwide basis, the financial status of the entire TransNet expenditure plan through 2048. Richard reviewed the latest trends in the Caltrans construction cost index and several of the key factors driving the increasing costs. As a result of these trends in cost escalation, Richard reported that the total cost of the EAP projects has increased from $9.4 billion in 2002 dollars to $17.5 billion in 2006 dollars. These updated project costs are

Page 9: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

5

being incorporated into the financial model. A new methodology for estimating future cost escalation factors also is being worked on by the staff and will be used in the update process. All revenue estimates will be updated as well, and staff will be conducting model runs over the summer. Preliminary results should be available for discussion at the September meeting.

Kevin Cummins asked if the funding provided through the Environmental Mitigation Program (EMP) would be sufficient to cover the estimated mitigation needs for the program. Gary Gallegos reviewed the background of the EMP and explained that the EMP was sized to cover the estimated mitigation needs of all the projects in the RTP, not just the TransNet program. Gary said if we are successful in acquiring mitigation land early and establishing mitigation ratios, then the funding should be sufficient to mitigate the program. Richard provided some examples of mitigation properties being acquired for SR 76 where actual costs are coming in below the initial estimates for the project.

Item 10 – SPRINTER Project Status Report and SANDAG Independent Assessment

Jim Linthicum reviewed the latest information on the status of the SPRINTER project. He reported that progress continues on the project with the mainline track work being 85 percent complete, all grade crossings complete, and testing of the vehicles and the grade crossing equipment continuing. He mentioned a quality control problem on the anchors used on the bridge for the San Marcos loop section of the line that is currently being addressed. The critical work item continues to be the ongoing work on the communications systems. Jim also mentioned that Operation Lifesaver is conducting outreach and safety training in the community.

In response to questions from members, Mr. Linthicum provided additional detail on the $12.2 million dollar settlement agreement that was discussed at last month’s meeting. He reviewed the process and the milestones used to determine the amount and timing of the release of funds under the terms of the agreement. He mentioned that work is still underway on the update to the cost to complete estimate, but the project is still on track for opening by the end of the year.

Item 11 – Future Meeting Schedule

The next regular meeting of the ITOC was scheduled for September 19, 2007, from 9:30 a.m. to 3:30 p.m. at SANDAG. Potential agenda items for the meeting included ongoing discussions of the status of the major corridor projects, review of the final draft ITOC annual report, and preliminary results from the Plan of Finance update process.

Item 12 – Adjournment

John Meyer expressed appreciation for the news clipping “read file” that Craig Scott assembles for the members each month and encouraged the members to read the articles. The meeting was adjourned at 1:50 p.m.

Page 10: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

6

Attachment 1

Future ITOC Agenda Items

Regular/Recurring Items

Chair and Vice-Chair Elections Annual [Jul]

ITOC Annual Report Annual [Jul-Sep]

Reports on status of all major corridor projects Quarterly [Nov/Feb/May/Aug]

Review of Lake Hodges Bicycle & Pedestrian Bridge Status Quarterly [Jul/Oct/Jan/Apr]

SPRINTER Project Status Report Monthly

Regular periodic reports on major project status by Corridor Directors/Project Managers

Prior Updates: I-15 3/06, 6/06, 11/06, 5/07 I-15 BRT 9/06 I-5 5/06 SR 52 5/06, 4/07 SR 76 9/06, 6/07 I-805 10/06 Mid-Coast 4/07 Super Loop 4/07

RTIP Amendments (if TransNet projects included)

Review “State of Commute”/ongoing SANDAG Annual [at a minimum] system performance evaluations

Specific Follow-up Discussion Items*

Briefing on ITOC responsibilities regarding the TransNet Impact Fee Requirement

TransNet Extension Senior Transportation Mini-Grant Program Process/Criteria

Update on TransNet Plan of Finance Process

EMP Program Update – Status of Agreement Process/Fund Allocations

* Items that either SANDAG staff has indicated they would be bringing back at a future meeting or that ITOC members have requested for a future agenda.

Page 11: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

1

11

Mid-City Rapid BusApplication for Federal Very Small Starts Funds

22

MidMid--City Rapid Bus City Rapid Bus PhasingPhasing

Phase I Very Small Starts

Attachment 2

7

Page 12: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

2

33

Faster Travel TimesFaster Travel TimesEnhanced Customer Enhanced Customer ExperienceExperienceFrequent ServiceFrequent Service

Project GoalsProject Goals

44

Queue Jumper Lanes & StationsQueue Jumper Lanes & Stations

8

Page 13: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

3

55

Communication between vehicle and traffic signal allows green light to be extended for several seconds

Transit Signal PriorityTransit Signal Priority

66

Cars allowed, but transit vehicles stop in-lane to serve stations

El Cajon Blvd.

Transit RouteTransit Route

9

Page 14: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

4

77

Cars kept out of transit lane by barriers, striping, curbs, and signage

Park Boulevard between University Ave. and El Cajon Blvd.

Dedicated Dedicated TransitwayTransitway

88

Station DevelopmentStation DevelopmentElements:• Bulb-outs• Shelter• Level Boarding

Platforms• Improved

Sidewalk Crossings

• Benches• Bike Rack• Street trees• Next Bus signs

EXPRESSM E T R O

10

Page 15: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

5

99

Level BoardingLevel Boarding

Raised PlatformsLow-Floor Buses

1010

Branding of ServiceBranding of Service

Branded Shelters

New, branded vehicles

Signage

11

Page 16: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

6

1111

Demand for All Day/Demand for All Day/Every Day TravelEvery Day Travel

Mid-City BRT

Service Service FrequenciesFrequencies

Existing Frequency is 15-minutes all day for Route 15 + 30-minutes for Route 1

Increase to 10-minute peak frequency for Mid-City Rapid + 30-minute for local (net 7.5 minute peak frequency)

1212

Federal Very Small Starts Program CriteriaFederal Very Small Starts Program CriteriaSubstantial transit stationsSubstantial transit stations

Traffic Signal PriorityTraffic Signal Priority

Low floor vehicle or level boardingLow floor vehicle or level boarding

Branding of serviceBranding of service

Frequency Frequency –– 1010--minute peak, 15minute peak, 15--minute offminute off--peak peak

Existing Existing ridershipridership of 3,000+ daily ridersof 3,000+ daily ridersCapital cost less than $50 million total and Capital cost less than $50 million total and $3 million per mile$3 million per mile

FTA staff has expressed strong interest in Mid-City Rapid Bus project

12

Page 17: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

7

1313

Capital CostCapital CostRequest Federal Funding for the El Cajon Request Federal Funding for the El Cajon Blvd/northern Park Blvd segmentBlvd/northern Park Blvd segmentTotal Capital Cost is approx. $40 millionTotal Capital Cost is approx. $40 millionRequest a 50% Federal Match ($20 million)Request a 50% Federal Match ($20 million)

1414

ActionsActionsActions TodayActions Today

Recommend to Board to authorize application to FTA Recommend to Board to authorize application to FTA for Very Small Starts fundingfor Very Small Starts fundingRecommend selection of MidRecommend selection of Mid--City Rapid Bus route as City Rapid Bus route as the the ““Locally Preferred AlternativeLocally Preferred Alternative”” for this corridorfor this corridor

Next StepsNext StepsSubmittal of applicationSubmittal of applicationBring project forward for inclusion in updated Plan of Bring project forward for inclusion in updated Plan of FinanceFinance

13

Page 18: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

8

1515

Mid-City Rapid BusA Great Very Small StartEXPRESS

M E T R OEXPRESSM E T R O

1616

Existing Existing RidershipRidershipSmall Starts Requires 3,000+ Daily RidersSmall Starts Requires 3,000+ Daily RidersRoute 15 Currently has 4,000+ daily ridersRoute 15 Currently has 4,000+ daily ridersRoute 1 (local service on same corridor) currently has Route 1 (local service on same corridor) currently has 5,000 daily riders5,000 daily ridersCombined Combined ridershipridership on corridor is 9,000 daily riderson corridor is 9,000 daily riders

El Cajon Blvd. Corridor Routes

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

09/05

/2006

09/07

/2006

09/09

/2006

09/11

/2006

09/13

/2006

09/15

/2006

09/17

/2006

09/19

/2006

09/21

/2006

09/23

/2006

09/25

/2006

09/27

/2006

09/29

/2006

10/01

/2006

10/03

/2006

10/05

/2006

Wee

kday

Rid

ersh

ip

Route 1Route 15

Date Route 1 Route 15 Total

09/05/06 4,701 4,249 8,95009/06/06 5,461 4,538 9,99909/07/06 4,659 5,320 9,97909/08/06 5,105 4,332 9,43709/11/06 4,757 4,443 9,20009/12/06 5,111 4,456 9,56709/13/06 5,833 3,059 8,89209/14/06 4,802 4,414 9,21609/15/06 4,952 3,985 8,93709/18/06 4,302 4,687 8,98909/19/06 4,571 4,711 9,28209/20/06 4,859 3,901 8,76009/21/06 4,698 4,374 9,07209/22/06 4,757 4,253 9,01009/25/06 5,364 4,551 9,91509/26/06 4,722 4,756 9,47809/27/06 4,587 4,298 8,88509/28/06 4,930 3,794 8,72409/29/06 4,851 4,089 8,940

14

Page 19: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

9

1717

1818

Focus Study Area

Balboa

NavalHospital

Downtown

SR 1

6310

thAve

11th

Ave

C St

Park

Blvd

SDSU

Cajon Blvd

University Ave

Park

I-805 SR-15Montezuma Rd

Ave

College

NormalHeights

NorthPark

54th

43rd

35th

30th

TransitPlaza

El

49/E

u clid

Santa Fe

Depot

CityCollege

Gaslamp

I-5

CityHeights

Broadway

LegendTransit Route (mixed-flow)

Dedicated Transitway

Transit Lane

Downtown alignment(to be determined)

Station

Texa

s

SDSU to Downtown Route

SDSU to Downtown Route

15

Page 20: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

1

Draft 2007 RegionalDraft 2007 RegionalTransportation PlanTransportation Plan

ITOCITOCJuly 18, 2007July 18, 2007

22

A million new residents by 2030A million new residents by 2030

A half million new jobsA half million new jobs

Attachment 3

16

Page 21: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

2

33

2007 RTP Scenarios2007 RTP Scenarios

•• Unconstrained NeedsUnconstrained Needs–– $89 billion $89 billion

•• Revenue ConstrainedRevenue Constrained–– $41 billion$41 billion

•• The Plan: Reasonably Expected RevenuesThe Plan: Reasonably Expected Revenues–– $58 billion$58 billion

44

Reasonably Expected RevenueReasonably Expected RevenueScenarioScenario

($Billions)($Billions)

4141

RCRCBaseBase

58582222331010

TotalTotalLocal Local ShareShare

GoodsGoodsMovementMovement

Toll Toll LanesLanesII--5/I5/I--1515

RERELevel ofLevel of

InvestmentInvestment

17

Page 22: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

3

55

Board DirectionBoard Direction

•• Support previous goals andSupport previous goals andcomponents of MOBILITY 2030components of MOBILITY 2030

•• Commitment to Commitment to TransNetTransNet EarlyEarlyAction Program and HOV/ML systemAction Program and HOV/ML system

•• Transportation project evaluation criteriaTransportation project evaluation criteriato prioritize improvementsto prioritize improvements

66

2007 RTP Goals2007 RTP Goals2007 RTP Goals

MobilityMobility

LivabilityLivability EfficiencyEfficiency

SustainabilitySustainability ReliabilityReliability

EquityEquity AccessibilityAccessibility

2007RTP

18

Page 23: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

4

77

Land UseLand Use

SystemsSystemsDevelopmentDevelopment2007

RTPDemandDemand

ManagementManagement

SystemsSystemsManagementManagement

Four ComponentsFour Componentsof the 2007 RTPof the 2007 RTP

88

Four ComponentsFour Componentsof the 2007 RTPof the 2007 RTP

Land UseLand Use

SystemsSystemsDevelopmentDevelopment

2007RTP

DemandDemandManagementManagement

SystemsSystemsManagementManagement

19

Page 24: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

5

99

Land Use Land Use –– Transportation Transportation Connection (Growing Smarter)Connection (Growing Smarter)

•• Regional Comprehensive Plan Regional Comprehensive Plan •• Smart Growth Concept MapSmart Growth Concept Map•• Independent Transit Plan ReviewIndependent Transit Plan Review•• Tribal CollaborationTribal Collaboration•• TransNetTransNet Environmental Mitigation Program Environmental Mitigation Program •• Energy/Green House Gas EmissionsEnergy/Green House Gas Emissions

1010

Four ComponentsFour Componentsof the 2007 RTPof the 2007 RTP

Land UseLand Use

SystemsSystemsDevelopmentDevelopment2007

RTPDemandDemand

ManagementManagement

SystemsSystemsManagementManagement

20

Page 25: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

6

1111

Demand ManagementDemand Management

1212

Four ComponentsFour Componentsof the 2007 RTPof the 2007 RTP

Land UseLand Use

SystemsSystemsDevelopmentDevelopment2007

RTPDemandDemand

ManagementManagement

SystemsSystemsManagementManagement

21

Page 26: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

7

1313

Systems ManagementSystems Management

1414

Four ComponentsFour Componentsof the 2007 RTPof the 2007 RTP

Land UseLand Use

SystemsSystemsDevelopmentDevelopment2007

RTPDemandDemand

ManagementManagement

SystemsSystemsManagementManagement

22

Page 27: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

8

1515

Systems DevelopmentSystems Development(Capacity and Choices)(Capacity and Choices)

•• Commitment to Commitment to TransNetTransNet EarlyEarlyAction Program and Action Program and HOV/ML systemHOV/ML system

•• Revised Transit PlanRevised Transit Plan•• Goods Movement Action PlanGoods Movement Action Plan•• Toll RoadsToll Roads•• Updated Regional Arterial SystemUpdated Regional Arterial System

1616

20302030HighwayHighwayNetworkNetwork

N/S FreewaysN/S Freeways

E/W FreewaysE/W Freeways

HighwaysHighways

Toll FacilitiesToll Facilities

23

Page 28: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

9

1717

20302030TransitTransit

NetworkNetwork

BRT and Commuter BRT and Commuter RailRail

Local ServicesLocal Services

Light RailLight Rail

Arterial RapidArterial Rapid

1818

Oceanside to Downtown San DiegoOceanside to Downtown San DiegoOceanside to Downtown San Diego

SOV HOV

Existing(2006)

O 30 60 90 120Minutes

Transit (Park & Ride)

69

Transit (Walk)

10593

76

24

Page 29: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

10

1919

Oceanside to Downtown San DiegoOceanside to Downtown San DiegoOceanside to Downtown San Diego

Existing(2006)

No Build(2030)

O 30 60 90 120MinutesO

10081

10593

7669

10593

SOV HOV Transit (Park & Ride)Transit (Walk)

2020

10081

10593

Oceanside to Downtown San DiegoOceanside to Downtown San DiegoOceanside to Downtown San Diego

Existing(2006)

ReasonablyExpected

(2030)

O 30 60 90 120MinutesO

7048

8677

7669

10593

SOV HOV Transit (Park & Ride)Transit (Walk)

25

Page 30: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

11

2121

Chula Vista to Sorrento ValleyChula Vista to Sorrento ValleyChula Vista to Sorrento Valley

Existing(2006)

O 30 60 90 120Minutes

5555

120104

SOV HOV Transit (Park & Ride)Transit (Walk)

2222

Chula Vista to Sorrento ValleyChula Vista to Sorrento ValleyChula Vista to Sorrento Valley

Existing(2006)

O 30 60 90 120Minutes

9590

122106

5555

120

No Build(2030)

104

SOV HOV Transit (Park & Ride)Transit (Walk)

26

Page 31: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

12

2323

9590

122106

Chula Vista to Sorrento ValleyChula Vista to Sorrento ValleyChula Vista to Sorrento Valley

Existing(2006)

ReasonablyExpected

(2030)

O 30 60 90 120Minutes

6630

5843

5555

120104

SOV HOV Transit (Park & Ride)Transit (Walk)

2424

RTP EIRRTP EIR

•• Tentative Distribution: MidTentative Distribution: Mid--August August

•• Alternatives include:Alternatives include:

–– Project: Reasonably Expected RevenuesProject: Reasonably Expected Revenues

–– No Project No Project

–– Revenue ConstrainedRevenue Constrained

–– Transit EmphasisTransit Emphasis

–– Transit Emphasis (Urban Core)Transit Emphasis (Urban Core)

27

Page 32: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

13

2525

Next StepsNext Steps•• July 17July 17--2626 –– Public WorkshopsPublic Workshops•• MidMid--AugustAugust –– Release Draft EIRRelease Draft EIR•• Sept 14Sept 14 –– Public HearingPublic Hearing•• Sept 17 Sept 17 –– Public Comment Period ClosesPublic Comment Period Closes•• October 9October 9 –– Response to Comments at Response to Comments at

Transportation CommitteeTransportation Committee•• NovemberNovember –– Certify EIR, adopt RTP, Certify EIR, adopt RTP,

approve AQ Conformity approve AQ Conformity findingfinding

2626

Public WorkshopsPublic Workshops

•• July 17 July 17 –– EncinitasEncinitas

•• July 19 July 19 –– Balboa ParkBalboa Park

•• July 23 July 23 –– Chula VistaChula Vista

•• July 25 July 25 –– San MarcosSan Marcos

•• July 26 July 26 –– El CajonEl Cajon

28

Page 33: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

14

Draft 2007 RegionalDraft 2007 RegionalTransportation PlanTransportation Plan

ITOCITOCJuly 18, 2007July 18, 2007

29

Page 34: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

1

Plan of Finance UpdatePlan of Finance Update

July 18, 2007July 18, 2007

Plan of Finance UpdatePlan of Finance Update

First comprehensive update since First comprehensive update since TransNetTransNet extended in November 2004extended in November 2004Will include all Will include all TransNet ExtensionTransNet ExtensionprojectsprojectsWill determine bonding capacity and state Will determine bonding capacity and state and federal match requirementsand federal match requirements

Attachment 4

30

Page 35: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

2

2015

2020

2030

2040

2050

2007

EAP TransNet Projects

Other TransNet Projects

RTP Reasonably ExpectedTransNet Projects

RTP Revenue Constrained TransNet Projects

Project Implementation TimelineProject Implementation Timeline

$

Caltrans Construction IndexCaltrans Construction Index

0

50

100

150

200

250

300

350

1972

1974

1976

1978

1980

1982

1984

1986

1988

1990

1992

1994

1996

1998

2000

2002

2004

2006

Doubling every5 years

Doubling every20 years

Doubling every4 years

TransNet OrdinanceCost Estimates Established

31

Page 36: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

3

Factors Affecting CostFactors Affecting Cost

Oil PricesOil PricesMaterial Prices Material Prices –– rock, steel, cement, etc.rock, steel, cement, etc.Labor PricesLabor PricesRight of WayRight of WayRegional Cost of LivingRegional Cost of LivingWorking ConditionsWorking Conditions

Updated Cost EstimatesUpdated Cost Estimates

Totaled $9.4 billion in 2002 dollarsTotaled $9.4 billion in 2002 dollarsNew total $17.5 billion in 2006 dollarsNew total $17.5 billion in 2006 dollarsCosts increased 86%Costs increased 86%Compares to 89% increase in Caltrans Compares to 89% increase in Caltrans construction price index over same period, construction price index over same period, 2002 to 20062002 to 2006

32

Page 37: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

4

Next StepsNext Steps

Define cost escalation factorsDefine cost escalation factorsComplete initial financial model runsComplete initial financial model runs

Plan of Finance UpdatePlan of Finance Update

July 18, 2007July 18, 2007

33

Page 38: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

San Diego Association of Governments – TransNet Program

INDEPENDENT TAXPAYER OVERSIGHT COMMITTEE

September 19, 2007 AGENDA ITEM NO.: 4Action Requested: INFORMATION

SPRINTER PROJECT STATUS REPORT AND File Number 1110200 SANDAG INDEPENDENT ASSESSMENT

At several meetings last year, the ITOC reviewed the status of the SPRINTER project and the related financial plan for fully funding the project. During those meetings, it was requested that the ITOC and the SANDAG Transportation Committee receive regular updates on the ongoing implementa-tion of the SPRINTER and SANDAG’s independent assessment of the final cost estimates and the schedule for completion of the project. This is the next in that series of status reports. Attachment for this report:

Attachment 1 – Transportation Committee report for the September 21, 2007, meeting summa-rizing the progress on the implementation of the SPRINTER rail project.

Page 39: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

San Diego Association of Governments

TRANSPORTATION COMMITTEE

2

September 21, 2007 AGENDA ITEM NO.: 9

Action Requested: INFORMATION

SPRINTER PROJECT STATUS REPORT AND SANDAG INDEPENDENT ASSESSMENT File Number 1115200

Introduction

The North County Transit District (NCTD) SPRINTER Rail Project converts an existing 22-mile freight rail corridor into a Diesel Multiple Unit (DMU) transit system connecting Oceanside, Vista, unincorporated County areas, San Marcos, and Escondido. The SPRINTER is a TransNet-funded project. In response to requests from NCTD and the Federal Transit Administration (FTA), SANDAG staff is currently providing support and oversight services for the project and has been asked by the SANDAG Board of Directors to report on its progress monthly to the Transportation Committee.

Discussion

Current Progress

The Mainline contractor continues to place most effort on the communication and signaling work which has been the critical path for completion since last winter. They are currently working on train signal optimization, signal pre-emption timing, crossing protection, and installation of communication components at each station. Communications equipment is operable at five of the 15 stations. They are also working with the Cities of Vista and Oceanside on traffic signal programming.

All work at the Vehicle Maintenance Facility, now called the SPRINTER Operations Facility (SOF), is expected to be complete by the end of September. The elevator at the California State University San Marcos station is installed, and the San Marcos Loop contract is expected to be complete in the next few weeks. All DMU vehicles have been granted preliminary acceptance by NCTD and only require additional running time on the tracks before final acceptance. Test trains are running from the SOF to Las Posas Road in San Marcos.

The Mainline contract is approximately 87 percent complete. All grade crossings are done; testing of the warning devices is ongoing. Track construction is complete. Three of the 13 stations with parking lots are paved.

A problem with the anchors that attach the rail to the bridges over State Route 78 has been resolved with the contractor removing and replacing all 5,000 concrete inserts.

Attachment 1

Page 40: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

3

Schedule

The settlement agreement with the Mainline contractor provides for new internal schedule milestones to track progress. If the contractor delivers the work required of a particular milestone, the contractor is compensated for “constructive acceleration.” The maximum payment the contractor could earn by meeting all milestones is $3.3 million. Five of the seven milestones also provide for a liquidated damage penalty if the contractor fails to meet the milestone.

The first new milestone, 5.5, occurred on August 2. It required the contractor to have all trackwork complete and enough of the communications network in place to permit transferring of train dispatching from the Metrolink Operations Center to the SPRINTER Central Control Facility in Escondido. The dispatching was complete but the track work was not. All track work is now complete. There are no liquidated damages associated with this milestone, and the contractor still has the opportunity to achieve the acceleration payment if this work is complete by Milestone 7 on October 1.

Milestone 6 required six stations to be complete and operational by September 3. The contractor did not achieve this either but like Milestone 5.5, is eligible to receive the acceleration payment if work is complete by Milestone 7.

Milestone 7 requires the contractor to be substantially complete with all work except landscaping. If achieved on October 1, NCTD may begin pre-revenue testing and training by its contract operator. Two months of pre-revenue operations are planned. The contractor is three weeks behind the Milestone 7 schedule. A Milestone 7 recovery schedule has been submitted by the contractor. It should be noted that the contractor will receive an extension of time should NCTD make any changes that delay the critical items of work. This also would extend the internal milestone delivery dates. There continues to be a great emphasis on minimizing changes to the work but some have been made and the contractor may be due additional time.

Various safety documents must be approved by the CPUC prior to commencing revenue operations. Both the System Safety Program Plan and the System Safety Security Plan have been submitted and are being reviewed by CPUC staff. NCTD and the Mainline contractor are working on the System Safety Certification which documents the implementation of thousands of safety critical items of work. More than 30 percent of this effort is complete.

Estimate at Completion

The settlement agreement with the Mainline contractor provides for payments not to exceed $12.2 million for damages the contractor incurred due to the design changes. Before receiving any payment, the contractor is required to submit documentation verifying any loss. The contractor is focusing all efforts on completing the work and has not yet submitted follow-up documentation.

NCTD staff is focusing its construction management effort on calculating the final construction quantities and adjusting each item of work for quantity overruns and underruns. Then they will begin negotiations with the Mainline contractor on the final costs of outstanding change order work.

Page 41: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

4

NCTD elected not to calculate a new estimate at completion (EAC) last month as the adjustments described above were just beginning. Therefore the latest EAC continues to be the $470 million figure reported in July. A new EAC is expected by the end of September. The not-to-exceed project budget set by the NCTD Board and included in the Amended Recovery Plan for the FTA is $484.1 million.

Summary

As reported previously, only the communication and signaling work on the Mainline contract remains a concern. All other facilities either are complete or will soon be complete. NCTD continues to work closely with the California Public Utilities Commission and Federal Railroad Administration to ensure timely inspection of the work and approval of all documentation required for operations. Likewise, these agencies are very proactive and responsive to NCTD and its goal of opening by year end.

The contractor’s adherence to the recovery schedule for Milestone 7 and NCTD ability to mitigate any delay to pre-revenue operations will affect when revenue service may start. The schedule continues to be very tight but achievable.

NCTD and its construction manager continue to work on finalizing costs to develop a more accurate EAC. They have a plan to accelerate this effort and resources are being devoted to this task.

JACK BODA Director of Mobility Management and Project Implementation

Key Staff Contact: Jim Linthicum, (619) 699-1970, [email protected]

Page 42: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

San Diego Association of Governments – TransNet Program

INDEPENDENT TAXPAYER OVERSIGHT COMMITTEE

September 19, 2007 AGENDA ITEM NO.:5

Action Requested: INFORMATION

QUARTERLY REPORT ON THE TransNet EARLY ACTION PROGRAM File Number 1200100 Introduction This report provides an overview of the TransNet Early Action Program (EAP), including cost control and schedule adherence and the general trends that affect both cost and schedule. This overview fulfills the ITOC requirement defined in the TransNet Ordinance to review the major congestion relief projects for performance in terms of cost control and schedule adherence on a quarterly basis.

Discussion The TransNet EAP includes improvements to nine transportation corridors: Interstates (I-) 5, 15, and 805, State Routes (SR) 52 and 76, Mid-Coast transit, Blue Line Trolley, Orange Line Trolley, and the SPRINTER transit corridor. The TransNet Dashboard reporting system is used to track cost control and schedule adherence for TransNet EAP projects. The Dashboard can be accessed at www.KeepSanDiegoMoving.com. The Blue Line Trolley, Orange Line Trolley, and SPRINTER are recent additions to the EAP and have not yet been added to the Dashboard.

Schedule Adherence Constructed improvements on the I-5, I-15, and I-805, SR 52 and SR 76, SPRINTER, and Mid-Coast corridors remain on schedule. More detailed schedule information can be found in Attachment 1.

Cost Control Cash flowcharts from the Dashboard can be found in Attachment 2. These charts indicate that the actual expenditures are tracking closely against budgeted amounts for the majority of the projects. Projects where expenditures are accruing more slowly than anticipated include the I-15 FasTrak® project and the I-15 bus rapid transit (BRT) stations (downtown to SR 163) projects. The procure-ment process for hiring a system integrator for the I-15 FasTrak® project has taken much longer than anticipated. However, this is not expected to delay the opening of the I-15 Managed Lanes. The I-15 BRT Stations (downtown to SR 163) project is experiencing delay. The California Department of Transportation (Caltrans) has raised safety and operational concerns over the design concept for the Mid-City center platform stations. SANDAG is working with Caltrans, Metropolitan Transit System (MTS), and the community on alternatives to the center platform design concept.

Page 43: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

2

Trends Construction costs continue to rise. The Caltrans construction cost index is up 37.5 points to 401.4 for the second quarter of 2007 compared to the first quarter of 2007 when the index was at 363.9. The average number of bidders on Caltrans’ construction projects more than $5 million is down 1.3 points to 4.3 for the second quarter of 2007 compared to the second quarter of 2007 when the average number of bidders was 5.6. The resale price of single-family homes is a good indicator of right-of-way costs for transportation projects. The median resale price for San Diego County in 2006 was $575,000. This is the same median resale price as in 2005. See Attachments 3 through 5 for more information.

Dashboard Enhancements During the last quarterly report, the ITOC requested the ability to review support costs and capital costs separately. Support costs include project development costs like planning and engineering, and capital costs include land acquisition costs and construction costs. Efforts are underway to separate these costs in the TransNet Dashboard. This added functionality will be available shortly under the “Cash Flow & Info” tab in the Dashboard. Attachments: 1. Schedule for TransNet Early Action Program 2. Cash Flow Charts 3. Caltrans Quarterly Construction Price Index 4. Average Number of Bidders, Caltrans Projects Over $5 Million 5. Median Prices, Single Family Homes – San Diego County Key Staff Contact: Richard Chavez, (619) 699-6989; [email protected]

Page 44: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

Attachment 1

3

-

Page 45: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

4

Mid-Coast Super Loop

I-5 North Coast I-5 HOV/Lomas

Attach

men

t 2

Page 46: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

5

I-5 South I-15 Middle

I-15 North I-15 FasTrak®

Page 47: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

6

I-15 BRT Stations (SR 163 to SR 78) I-15 BRT Stations (Downtown to SR 163)

I-15 BRT Planning SR 52 ML

Page 48: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

7

I-805 South SR 52 Extension

SR 76 Middle SR 76 East

Page 49: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

8

I-805 South I-805 North

South Bay BRT

Page 50: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

9

Caltans Quarterly Construction Price Index

0

50

100

150

200

250

300

350

400

450

2002Q1

2002Q2

2002Q3

2002Q4

2003Q1

2003Q2

2003Q3

2003Q4

2004Q1

2004Q2

2004Q3

2004Q4

2005Q1

2005Q2

2005Q3

2005Q4

2006Q1

2006Q2

2006Q3

2006Q4

2007Q1

2007Q2

Attach

men

t 3

Page 51: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

10

Average Number of BiddersCaltrans Projects Over $5 million

2

3

4

5

6

7

8

Mar

-02

Jun-0

2Se

p-02

Dec-0

2M

ar-0

3Ju

n-03

Sep-0

3Dec

-03

Mar

-04

Jun-0

4Se

p-04

Dec-0

4M

ar-0

5Ju

n-05

Sep-0

5Dec

-05

Mar

-06

Jun-0

6Se

p-06

Dec-0

6M

ar-0

7Ju

n-07

Attach

men

t 4

Page 52: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

11

Median PricesSingle Family Home - San Diego County

$0

$100,000

$200,000

$300,000

$400,000

$500,000

$600,000

$700,000

2002 2003 2004 2005 2006

Attach

men

t 5

Page 53: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

San Diego Association of Governments – TransNet Program

INDEPENDENT TAXPAYER OVERSIGHT COMMITTEE

September 19, 2007 AGENDA ITEM NO.: 6Action Requested: REVIEW AND COMMENT/APPROVE

FINAL DRAFT 2007 ITOC ANNUAL REPORT File Number 1110200

Staff distributed an initial draft of an annual report for FY 2007 at the last meeting. Based on comments received since that meeting, a final draft annual report has been developed. If approved, a presentation of the annual report will be scheduled for the SANDAG Board of Directors. Attachment related to this item:

Final Draft 2007 ITOC Annual Report

Page 54: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

ITOC

Safeguarding your TransNet dollars

2007 Annual Report

The Independent Taxpayer Oversight Committee

A message from the Chair…

ITOC is now in its third year, having gone from

formative status to a very proactive position in reviewing

TransNet expenditures for the Early Action Program.

We have a great deal of appreciation for our previous

chairpersons, Michael Boyle and Maryam Babaki, for

providing steady leadership during this period.

This second annual report shows in detail our

involvement in carrying out the voters’ mandate

on the TransNet Extension. We are charged with

“oversight” of TransNet, while the planning and

setting of priorities are the responsibility of the

SANDAG Board of Directors. We were pleased to

see that the Board followed our recommendations

to impose strict accountability measures on projects

like the SPRINTER and the Lake Hodges bicycle

and pedestrian bridge before TransNet funds

were authorized.

Another challenging year is ahead. We need to

refine the performance measurement methods,

get ready for the mandated fiscal audits, and provide

oversight tasks for pending implementation of the new

impact fee requirements. Add to that the challenge of

having to deal with increasing costs and the impact

that could have on our TransNet program. We know

we have our work cut out for us!

With so much of our attention having been focused

on the highway side during the early years, it also is

imperative that we examine the funding plans and

objectives of the transit operators who will receive a

substantial percentage of the TransNet funds.

Finally, a word of thanks is in order to SANDAG

and Caltrans staff who participated in the many

presentations and preparation of monthly reports,

and to the representatives of the San Diego County

Taxpayers Association and other groups that have

contributed to our discussions.

Maryam Babaki (2006) and John Meyer (2007)

d to onsojects ycle

ide new of

Attachment 1

2

Page 55: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

ITOC

Milestones & Accomplishments — FY 2007

The following summarizes the major ITOC

initiatives and key accomplishments from

July 1, 2006 to June 30, 2007:

Elected Maryam Babaki and Jim

Callaghan to serve as Chair and

Vice-Chair, respectively, for FY 2007.

When Jim Callaghan’s term expired in

May 2007, John Meyer was elected to

serve as Vice Chair for the remainder

of the term. ITOC also welcomed two

new members, Valerie Harrison and

Kevin Cummins, who were appointed

to serve in the private sector employer

and biologist/environmental scientist

categories, respectively. In addition,

Hamid Bahadori was reappointed for

a second term.

Developed the fi rst ITOC Annual Report

summarizing key accomplishments

during its fi rst year of work. The report

was presented to the SANDAG Board

of Directors and made available to the

public through the SANDAG Web site.

Played a key role in working with

SANDAG staff and consultants on

the development of a “Dashboard”

reporting system to provide Web access

to information on the status of project

costs and schedules for use in the

required quarterly reporting process

specifi ed in the TransNet Ordinance,

as well as other project and program

management efforts. ITOC continues to

make suggestions for refi nements to the

Dashboard reporting system.

Reviewed ongoing status of major

corridor projects included in the TransNet

EAP through the quarterly reporting

process, including updates on the status

of costs and schedules for each project.

In addition to the quarterly reports, ITOC

received detailed presentations from

Caltrans and SANDAG Corridor Directors

and Project Managers on the status of

the following TransNet Major Corridor

projects: I-15 Managed Lanes including

the bus rapid transit (BRT) operating

plans, I-805, SR 52, SR 76, the Mid-Coast

Corridor, and the Super Loop project.

Conducted a series of discussions related

to the cost increases on the SPRINTER rail

project and the development

of a new fi nancial plan for the

project. ITOC reviewed the

initial fi nancial plan proposed

to cover SPRINTER cost

increases and did not support

this proposal due to a number

of concerns. Over several

months, ITOC worked with

SANDAG and North County

Transit District (NCTD) staff

on a revised fi nancial plan

for the SPRINTER. Ultimately, ITOC

recommended support of a revised

fi nancial plan to the SANDAG Board of

Directors that involved an amendment

to the TransNet Ordinance and the EAP.

Consistent with this recommendation,

in December 2006, the SANDAG Board

amended the TransNet Ordinance and

revised the EAP and the related Plan of

Finance to include the completion of

the SPRINTER project. This same action

amended the EAP to include additional

funding for the Environmental Mitigation

Program (EMP) and Trolley Blue and

Orange Line capital improvements, which

An Independent Perspective

The Independent Taxpayer Oversight

Committee (ITOC) is a key component

of TransNet, the local half-cent sales tax

for regional transportation improvements

extended by San Diego County voters in

2004 for 40 years. SANDAG administers

the TransNet program and is responsible for

implementing the projects outlined in the

TransNet Ordinance and Expenditure Plan.

As mandated by the ordinance, ITOC

provides an increased level of accountability

for the allocation of TransNet revenues. ITOC

also provides guidance and oversight on the

development of the TransNet Early Action

Program (EAP) and the implementation of

other key components of the new measure.

Beginning with Fiscal Year (FY) 2009, ITOC

will assume responsibility for the annual

independent fi scal audits. Future annual

reports will include results, fi ndings, and

recommendations coming out of the annual

audit process.

ITOC includes individuals from a variety of

professional fi elds who collectively offer

SANDAG the benefi t of their experience in

order to advance the timely and effi cient

implementation of TransNet projects, and

ensure that all TransNet funds are expended

in compliance with the 2004 ordinance. ITOC

positions on key TransNet issues are regularly

presented at SANDAG Board of Directors and

Policy Advisory Committee meetings, and

meetings are held in an open, public forum.

The seven ITOC members play a key role in

shaping San Diego’s transportation future

as they work to ensure that the TransNet

program is a success.

2I-15 Managed Lanes north of Bernardo Center Dr.

SPRINTER at Cal State San Marcos Station

3

Page 56: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

The Independent Taxpayer Oversight Committee

of SR 52 to SR 67 as

originally proposed,

with additional funding

required to cover a

cost increase coming

from the future SR

52 managed lanes

project. ITOC members

also raised a major

concern about the trend

toward signifi cant cost

increases on all major

projects and urged

staff to initiate the Plan

of Finance update process as soon as

possible so that the impacts to the overall

program could be assessed.

Supported the approach proposed by

staff for updating the Plan of Finance for

the EAP. The concept was to update the

plan to refl ect the current cost estimates

for the projects, update cash fl ow sched-

ules for each of the EAP projects, identify

the availability of new matching funds

for the TransNet projects, and assess the

overall impact on the deliverability of the

EAP projects as well as the rest of the

TransNet Expenditure Plan through 2048.

Approved additional implementation

guidelines for inclusion in the ITOC

manual related to how ITOC would

handle responsibilities for reviewing

projects for the Regional Transportation

Improvement Program (RTIP) and project

evaluation criteria for use in the Regional

Transportation Plan (RTP) development

process, as well as general guidelines for

how ITOC would work with SANDAG

staff and consultants in carrying out its

roles and responsibilities over time.

Supported draft implementation guide-

lines related to the TransNet Ordinance

requirement that all new construction

and major reconstruction projects funded

under the Ordinance provide accommo-

dations for bicycle and pedestrian traffi c

where such traffi c is legal and the cost of

doing so is not unreasonable given the

expected use.

Recommended that $1.8 million in

funding from the FY 2009 new

TransNet Extension Bicycle, Pedestrian,

and Neighborhood Safety Program be

used to fully fund the Lake Hodges bicycle

and pedestrian bridge. SANDAG staff

will provide oversight for the project and

deliver quarterly progress reports on the

project to ITOC.

Endorsed the SANDAG proposal for

funding under the Urban Partnership

Program. This new federal initiative

provides a unique opportunity to attract

additional federal dollars to implement

innovative, new programs in the region.

As a result of this process, the region

was awarded $18 million to pilot the $22

million “swoop” project, an innovative

new transit service that uses advanced

vehicle guidance technologies to assist

drivers operating vehicles in a narrow

right of way.

Received updates on the status of

TransNet audits for FY 2006, reviewed

proposed procedures for establishing

the new “Maintenance of Effort” levels

to be required of local jurisdictions per

the TransNet Extension Ordinance, and

considered a proposed change to the

approved SANDAG audit policy for

TransNet funds. ITOC will be taking over

the annual fi scal audit process effective

with the audits for FY 2009.

also was supported by ITOC. As a result

of this process, SANDAG assumed a

higher level of oversight for the SPRINTER

project and began a series of monthly

briefi ngs for ITOC on the status of the

SPRINTER project implementation.

Reviewed the implementation of

Proposition 1B, which was approved by

California voters in November 2006, in

terms of the potential state matching

funds available to contribute to the

delivery of the TransNet EAP. A series of

presentations focused on actions by the

California Transportation Commission

relating to the allocation of funding

under the Corridor Mobility Improve-

ment Account (CMIA) and the State

Transportation Improvement Program

Augmentation, two of the fi rst Proposi-

tion 1B programs to be implemented. The

additional $600 million in state funding

from these two programs contributes

positively toward the overall goal of

achieving a 50 percent TransNet – 50

percent State/Federal/Other matching

ratio for the major corridor projects.

Supported a $37.7 million increase to

the I-15 Managed Lanes corridor project

budget. The total estimated cost of

this TransNet EAP project is $1.29 billion.

Because of the addition of $350 million

in CMIA funding from Proposition 1B

for this project, this cost increase

was manageable.

Received a detailed report on the status

of the SR 52 project and the increased

cost estimate for completion of the

project. ITOC supported the completion (continued on page 4) 3

Lake Hodges bicycle and pedestrian bridge

ITOC Chair Maryam Babaki at SR 52 groundbreaking ceremony

4

Page 57: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

Biology/Environmental Science:

Kevin Cummins(May 2007 through April 2011)

Doug Gibson (May 2005 through April 2007)

Municipal/Public Finance:

John Meyer (May 2005 through April 2009 - ITOC Vice-Chair May 2007 through June 2007)

Construction Project Management:

Jim Ryan (May 2005 through April 2009)

Ex-Offi cio Members:

San Diego County Auditor: Tracy Sandoval (May 2005 through present)

SANDAG Executive Director: Gary Gallegos (May 2005 through present)

ITOC

contained new procedures for tracking

progress on the implementation of RCP

goals, including transportation, using a

wide range of measurements. This would

provide another tool, along with other

more transportation-specifi c methods, to

monitor progress on a regional basis.

Received numerous briefi ngs from

SANDAG and Caltrans staff on a range

of topics related to the implementation

of the overall TransNet program, with

an emphasis on new programs to be

implemented with TransNet Extension

funding, including the new Environmental

Mitigation Program, the senior trans-

portation mini-grant program, and other

components of the TransNet Extension.

ITOC also made several presentations

Reviewed several amendments to

the current Regional Transportation

Improvement Program, with a focus on

compliance with the new provisions

of the TransNet Ordinance for projects

proposed for funding in FY 2009 and

beyond, such as consistency with the

“70/30” guidelines for local street

and road projects and tracking of fund

availability by program.

Received several presentations on the

development of the long-range RTP.

This effort focused on the refi nement

of the project evaluation criteria and

performance measures to be used in

the RTP process, which is one of the

ITOC roles as specifi ed in the TransNet

Ordinance. ITOC encouraged SANDAG

staff to continue to work on cross-mode

cost-effectiveness criteria to be used as

part of the evaluation process in future

RTPs. ITOC also reviewed preliminary

scenarios developed for the draft RTP

based on the application of new project

evaluation criteria and proposed changes

to the Regional Arterial System.

Continued discussions related to

transportation performance measure-

ment. As part of this process, ITOC

received a report on the Regional

Comprehensive Plan (RCP) Performance

Monitoring Baseline Report, which

The Independent Taxpayer Oversight CommitteePast and current (in bold) ITOC members and the area of professional expertise they represent:

Information about each member is available at www.sandag.org/ITOC

to the SANDAG Board of Directors and

Transportation Committee to provide its

input on TransNet-related issues.

ITOC Works For YouITOC was created to objectively represent

the taxpayers of the San Diego region —

to ensure that promises made regarding

the implementation of the TransNet

half-cent sales tax for transportation

improvements are fulfi lled in accordance

with the program’s Ordinance and

Expenditure Plan. The success of ITOC

relies on continuous feedback from the

public. To share your thoughts and opinions

with ITOC, go to www.sandag.org/ITOC

and complete the feedback form. Meeting

schedules, agendas, and minutes also are

available on this Web page.

(continued from page 3)

4

Transportation Project Design/Construction:

Maryam Babaki (ITOC Chair) (May 2005 through June 2007 - ITOC Chair February 2006 through June 2007)

Traffi c/Civil Engineering:

Hamid Bahadori (May 2005 through April 2011)

Private Sector Senior Decision Maker:

Valerie Harrison(May 2007 through April 2011)

James C. Callaghan, Jr. (ITOC Vice Chair May 2005 through April 2007)

Real Estate/Right-of-Way Acquisition:

Ron Gerow (April 2006 through April 2009)

Michael Boyle(ITOC Chair May 2005 through January 2006)

P A C I F I C

O C

E A

N

P A C I F I C

O C

E A

N

San Diego Region

MAP AREA

0 3 6

0 4.83 9.6

MILES

KILOMETERS

Highway Projects

Transit Projects

All Dashed Lines IndicateProjects Under Construction

March 2007

1

4

3

2

6

4

4

7

7

9

7

4

8

5

9

9

74

4

SanDiego

Oceanside

Carlsbad

Encinitas

Del Mar

Solana Beach

Poway

Coronado

ImperialBeach

LemonGrove

La Mesa

Santee

El Cajon

Escondido

Countyof

San Diego

Vista

SanMarcos

ChulaVista

Tijuana, B.C.

UNITED STATES

MEXICO

NationalCity

SR 76 - Widening

SR 52 - New Freeway

Mid-Coast and Super Loop Transit

I-15 Managed Lanes and Bus Rapid Transit (BRT)

SR 52 - HOV/Managed Lanes and Widening

I-5 North Coast Corridor - Environmental Effort and HOV Lanes

I-805 Corridor - Environmental Effort & BRT

SPRINTER - Oceanside to Escondido

Trolley - Vehicle and Station Upgrades (Blue and Orange Lines)

Early ActionProjects

1

4

3

2

5

6

7

8

9

www.KeepSanDiegoMoving.com

ITOC c/o SANDAG401 B Street, Suite 800San Diego, CA 92101-4231(619) 699-1900

5

Page 58: MEETING NOTICE AND AGENDAThis agenda and related staff reports can be accessed at under Meetings on ... (Joy De Korte) REVIEW AND COMMENT/ APPROVE Staff distributed an initial draft

This item relates to Agenda Item No. 7

Potential ITOC Agenda Items 2007

Item October November December

I-805 Corridor Status Report (Joel Haven) X

RTCIP: Nexus Study findings and ITOC responsibilities (Marney Cox)

X

TransNet Plan of Finance Update (Jose Nuncio) X X?

EMP Program Update – Master Agreement (Keith Greer) X

Quarterly Report on Major Corridor Project Status X

Quarterly Lake Hodges Bridge Status Report (Stephan Vance)

X

SPRINTER Project Status Report (Jim Linthicum) X X X

Other EAP Corridor Status Reports (Corridor Directors) • I-15 , I-5, SR 53, SR 76, Mid-Coast, Super Loop

Update to TransNet Board Policy on Fiscal Audits and MOE Audits (Renee Wasmund)

X X?

TransNet Smart Growth Incentive Program (Stephan Vance) X

TransNet Senior Transportation Mini-Grant Program (Dan Levy)

RTIP Amendments (Sookyung Kim) X X?

Annual Performance Measurement Reporting/ “State of the Commute” (Jack Boda/ Alex Estrella)