Upload
norhalim-idrris
View
218
Download
0
Embed Size (px)
Citation preview
8/19/2019 Making of Bandra Bridge
1/41
Making of Bandra-Worli SeaLink
A triumph of precision engineering
Introduction The Bandra-Worli Sea Link (BWSL) is a civil
engineering marvel spanning an arc of the Mumbai coastline. With
its cable-staed to!ers soaring gracefull sk!ards" the sea link is a
reflection of the modern infrastructure that Mumbai is adding in its
progress to!ards becoming a !orld-class cit.
The BWSL pro#ect is a part of the Western $ree!a Sea %ro#ect"
!hich" in turn" is a part of a larger proposal to upgrade the road
transportation net!ork of greater Mumbai. &n the first phase it !illconnect Bandra to Worli !hereas in the subse'uent phases the plans
are to take it further to a#i li and then to *ariman %oint. &t is a
connecting bridge linking the cit of Mumbai !ith its !estern
suburbs and has the potential to bring about permanent and far
reaching changes in the travel patterns of the area. The Bandra-Worli
Sea Link is primaril meant to provide an alternative to the Mahim
+ause!a route that is presentl the onl connection bet!een South
Mumbai and the Western and +entral suburbs. The pro#ect startsfrom the interchange at Mahim intersection" i.e. intersection of
8/19/2019 Making of Bandra Bridge
2/41
Western ,press igh!a and S!ami ivekanand /oad at the
Bandra end" and connects it to 0han bdul 1affar 0han /oad at the
Worli end. The pro#ect has been commissioned to offer a 'uicker
alternative to the north-south traffic that presentl amounts toapproimatel 234"555 cars a da. The pro#ect has been
commissioned b the Maharashtra State /oad 6evelopment
+orporation Ltd (MS/6+) and the Maharashtra 1overnment and is
being built b ++ (industan +onstruction +ompan). s a
builder of landmark infrastructure pro#ects around the countr" ++
has handled numerous challenges both in terms of location and
technolog. The BWSL pro#ect offered ++ an opportunit to
accomplish one more feat7 to construct an eight-lane free!a over the open sea for the first time in &ndia. Highlights in brief 8 &ndia9s
first bridge to be constructed in open-sea conditions
,pansion #oints are provided at each end of the units. The
superstructure and substructure are designed in accordance !ith &/+
codes. Specifications conform to the &/+ standard !ith
supplementar specifications covering special items. The foundation
consists of 2.4 meters diameter drilled piles (: nos. for each pier)!ith pile caps. Bridge bearings are of 6isc Tpe.
The bridge has been built utilising the concept of %re-+ast" post-
tensioned" segmental concrete bo girder sections. n overhead
gantr crane !ith self-launching capabilit is custom built b the
compan to la the superstructure of the precast segments. The %re-
+ast segments are #oined together using high strength epo glue
!ith nominal pre-stressing initiall. The end segments ad#acent to
the pier are short segments ;cast-in-situ #oints
8/19/2019 Making of Bandra Bridge
3/41
Bandra channel is >55 meters in overall length bet!een epansion
#oints and consists of t!o 345-meter cables supported main spans
flanked b 45 meters conventional approach spans. centre to!er"
!ith an overall height of 23? meters above pile cap level" supportsthe superstructure b means of four planes of cable sta in a semi-
harp arrangement. +able spacing is >.5 meters along the bridge deck.
The cable-staed portion of the Worli channel is =45 meters in
overall length bet!een epansion #oints and consists of one 245
meters cable supported main span flanked b t!o 45 meters
conventional approach spans. centre to!er" !ith an overall height
of 44 meters" supports the superstructure above the pile cap level b
means of four planes of cable sta in a semi-harp arrangement.+able spacing here is also >.5 meters along the bridge deck. The
superstructure comprises t!in precast concrete bo girders !ith a
fish bell cross sectional shape" identical to the approaches. tpical
%re-+ast segment length is =.5 meters !ith the heaviest
superstructure segment approaching 2:5 tons. Balanced cantilever
construction is used for erecting the cable supported superstructure
as compared to span-b-span construction for the approaches. $or
ever second segment" cable anchorages are provided. total of 3>: cable stas are used at Bandra channel !ith cable
lengths varing from approimatel ?4 meters minimum to nearl
345 meters maimum. The to!er is cast in-situ reinforced concrete
using the climbing form method of construction. The overall to!er
configuration is an inverted ;@< shape !ith the inclined legs
oriented along the ais of the bridge. To!er cable anchorage
recesses are achieved b use of formed pockets and transverse and
longitudinal bar post-tensioning is provided in the to!er head toresist local cable forces.
total of 2>5 cable stas are used at Worli channel !ith cable
lengths varing from approimatel =5 meters minimum to nearl
?5 meters maimum. Like the Bandra channel" the to!er here is also
cast in-situ reinforced concrete using the climbing form method of
construction but the overall to!er configuration is ;&< shape !ith the
inclined legs. Similarl" to!er cable anchorage recesses are achieved
b use of formed pockets. The foundations for the main to!ercomprise 3 meter-drilled shafts of 34 meters length each. +offerdam
8/19/2019 Making of Bandra Bridge
4/41
and tremie seal construction have been used to construct the si-
meter deep foundation in the dr. Part – III South End approach
structure This portion of the bridge is similar to the *orth end
approach structure in construction methodolog !ith span b spanmatch cast concrete bo girder sections. Toll Plaa modern toll
plaAa !ith 2> lanes is provided at the Bandra end. The toll plaAa is
e'uipped !ith a state-of-the-art toll collection sstem. structure is
provided at this location to house the control sstem for the &TS.
Intelligent Bridge System The toll station (T%) and collection
sstem !ill provide for three different tpes of toll collection" as
follo!s7
- $ull automatic sstem7 ,lectronic pament through n boardCnits mounted on the vehicles !hich allo! passage !ithout
stopping.
- Semi-automatic sstem7 ,lectronic pament through a smart card"
!hich allo!s pament !ithout having to pa cash.
- Manual toll collection7 %ament of toll b cash" re'uiring vehicle
drivers to make cash pament to a toll attendant" and stopping for
cash echange. The intelligent bridge sstem !ill provide additional
traffic information" surveillance" monitoring and control sstems. &tcomprises ++Ts" traffic counting and vehicle classification
sstem" variable message signs" remote !eather information sstem
and emergenc telephones. The control centre located near the toll
plaAa is housed !ith the electronic tolling controls. The transmission
sstem comprises fibre-optic cable housed in %+ conduits running
parallel to the Bandra-Worli corridor. &n addition" facilities to assist
enforcement are provided in the form of pull-out locations" !hich
!ill allo! drivers and enforcement officers to safel pull-out oftraffic. Po!er Supply "istribution and #oad $ighting System
reliable and dependable po!er suppl has been arranged for the
entire pro#ect. &t !ill also house diesel generator sets and auto mains
failure panels to cater to critical load" e.g." monitoring" surveillance
and communication e'uipment emergenc services like aviation
obstruction lights. de'uate levels of lighting levels have been
maintained and energ saving luminaries has been installed. Special
emphasis has been given to incorporate lighting protection at bridgeto!er and control room building to protect those buildingD structures
8/19/2019 Making of Bandra Bridge
5/41
and the sophisticated monitoring and communication e'uipment
installed therein. +hallenges encountered during eecution of the
pro#ect ,ngineering challenges BWSL %ro#ect is a uni'ue and
pleasing structure" but before undertaking the construction"follo!ing !ere the ma#or challenges to be addressed7-
8 The foundations of the bridge included >5: large diameter shafts
drilled to lengths of >m to =:m in geotechnical conditions that
varied from highl !eathered volcanic material to massive high
strength rocks.
8 The superstructure of the approach bridges !ere the heaviest spans
in the countr to be built !ith span-b-span method using overhead
gantr through a series of vertical and horiAontal curves.8 one-of-its-kind" diamond shaped 23?m high concrete to!er !ith
flaring lo!er legs" converging upper legs" unified to!er head
housing the stas and a throughout varing cross section along the
height of to!er.
8 ,rection of 35555 MT Bandra cable-staed deck supported on sta
cables !ithin a ver close tolerance of deviations in plan and
elevation.
The challenges !ere varied and started right from the %re-+ast ard.1round stabilisation for %re-+ast @ard The %re-+ast ard is located
on reclaimed land. The ard caters to casting" storing and handling
of pre-cast segments for the pro#ect totalling 3=:3 in numbers. The
storage capacit re'uirement of ard is to be about :E5nos. s the
area available is limited" the segments are to be stored in stacks of
three laers. The bearing capacit of the ground is of paramount
importance to enable three-tier storage of segments. s the pre-cast
area is on reclaimed land" the bearing capacit of eisting ground!as ver poor and found to be less than 3 TDS'm.
ence detailed ground stabiliAation !as carried out" !hich involved
follo!ing7
8 ,cavation of the ground to a depth of F 3.4Mtrs.
8 Strengthening the ground using rubble soling and filling the voids
!ith sand. The soling thus done !as compacted laer b laer using
vibrator rollers.
8 Total area of the %re-cast @ard !as covered !ith a laer of %++.8 /++ $ooting done to facilitate storing of segments.
8/19/2019 Making of Bandra Bridge
6/41
These measures offered the re'uired strength to the casting ard.
%arine !or&s 'oundation and substructure The foundations for
the BWSL pro#ect consist of 3555-mm diameter piles numbering
235 for the cable-staed bridges and 2455-mm diameter pilesnumbering :?: for the approach bridges. The pro#ect9s site geolog
consists of basalts" volcanic tuffs and breccias !ith some
intertrappean deposits. These are overlain b completel !eathered
rocks and residual soil.
The strength of these rocks range from etremel !eak to etremel
strong and their conditions range from highl !eathered and
fractured" to fresh" massive and intact. The !eathered rock beds are
further overlain b transported soil" calcareous sandstone and thin bed of coarse grained conglomerate. The top of these strata are
overlain b marine soil laer up to Gm thick consisting of dark
bro!n clae silt !ith some fine sand overling !eathered" dark
bro!n basaltic boulders embedded in the silt. The ma#or engineering
problems that needed suitable solutions before proceeding !ith the
!ork !ere as follo!s7
2. ighl variable geotechnical conditions of the foundation bed as
eplained above.3. ighl uneven foundation bed even for plan area of one pile.
=. %resence of &ntertidal Hone ($oundation Bed eposed in lo! tide
and submerged in high
tide).
The ke to success !as a program of pier b pier in-situ testing. n
etensive subsurface eploration and drilling program (total 2G2
bores inside sea) !as undertaken to define the subsurface
stratigraph" determine the rock tpes and obtain material propertiesfor optimiAing the foundation design. !ing to a highl variable
geolog" the design calculations !ere performed on a pier-b-pier
basis and the unit side
shear values !ere checked that the did not eceed the load test
results under similar rock conditions.
The !orking load on the approach piles ranges from E55 tons to
2455 tons !hereas for the piles belo! the cable-staed bridge
!orking load
8/19/2019 Making of Bandra Bridge
7/41
is 3455 tons. $or conducting the
load test on the piles" the load to be applied varied from :455tons to
G>55tons.
rranging reactions for such loads either b normal kentledgemethod or b soil anchor re'uired massive scale arrangements in the
sea !aters. This !as completel avoided b a careful planning of
load
test using the sterberg load cell method (/efer sketch 2).
The a!ard !inning sterberg +ell" or ;-+ell9" gets its name from
the inventor" 6r. Ior# . sterberg. The -cell is a hdraulicall
driven" high capacit" sacrificial loading device installed !ithin the
foundation unit. Working in t!o directions" up!ard against side-
shear and do!n!ard against end-bearing" the -cell automaticall
separates the resistance parameters. B virtue of its installation
!ithin the foundation member" the sterberg +ell load test is not
restricted b overhead structural beams and tie-do!n piles. &nstead"
the -+ell derives all reaction from the soil andDor rock sstem. ,nd
bearing provides reaction for the skin friction portion of the -+ell
load test" and skin friction provides reaction for the end bearing
portion of the test. Load testing !ith the -+ell continues until one
8/19/2019 Making of Bandra Bridge
8/41
of three things occurs7 ultimate skin friction capacit is reached"
ultimate end bearing capacit is reached" or the maimum -cell
capacit is reached.
,ach sterberg +ell is speciall instrumented to allo! for directmeasurement of the end bearing and skin friction. -+ells range in
capacities from 5.E M* to 3E M*. B using multiple -+ells on a
single horiAontal plane" the available test capacit can be increased
to more than 355 M*. t BWSL" four test locations !ere selected
for the follo!ing criterion.
/everse +irculation 6rilling method is adopted for foundation
construction. The highl uneven foundation beds and the presence of
intertidal Aone brought in lots of difficult in terms of Liner pitching.This problem !as solved b constructing a gabion boundar at the
bed level around the casing" pouring concrete bet!een the casings to
make an artificial penetration of the casing. fter setting of the
concrete under the !ater" drilling !as commenced using /+6.
&t is interesting also to mention that loss of !ater head during
continuous drilling operation !as a ma#or problem !hile !orking in
the intertidal Aone. This !ater head loss leads to ver slo!
production rate and ver high consumption of drill bits. To overcomethis problem" pits
!ere made in the lo! tide at each foundation location using an
,cavator and the casing !as placed at the bottom of the pits. Then
the casing !as placed in the pits and !as concreted to make an
artificial penetration" maintaining the proper !ater head for
continuous drilling.
$or several locations" cofferdam construction using steel liner and
sheet piles !as not possible due to ver hard and uneven strata. erethe problem !as solved using circular steel caissons. These caissons
!ere fabricated outside and to!ed to location using -frame barge.
The caissons !ere sunk at the location using counter!eights. The
unevenness at the bottom !as sealed using the gabion method. The
benefit of this method !as that it completel eliminated deploment
of resources like Iack up %latform" +rane" ibrohammer"
+ompressor" etc. for liner pitching. &t also eliminated substantial
amount of field !orks and is pre-fabricated in principle.
8/19/2019 Making of Bandra Bridge
9/41
JFFFFFFFFFFFFJ
Superstructure The BWSL %ro#ect has (GK3) approach bridge
modules. These modules range from = continuous span units to ?continuous span units. The deck of the carriage!as consists of
triple cell precast bo girders supported on piers founded on
independent substructure. The +oncrete 1rade for the superstructure
is M>5. The average !eight of the span is 2?55 tons" !hereas the
heaviest span in the bridge (to be erected !ith the Launching
1antr) !eighs 3555 tons. &n addition" the trusses !ere to be
designed to receive the segment from the alread erected deck as
!ell as from barges parked directl under the truss.The Technical 6ata for the superstructure is as follo!s.
Ma Longitudinal 1radient 2.E3
Ma +rossfall >
Ma /adius in %lan >55m
Min /adius in %lan 3:>m
Tpical Span Length 45m and =5m in Link Bridge
Ma Span Weight 3555 tons
The erection gantr is 23>5MT truss designed to erect spans for theabove configuration. The uni'ue feature of the truss indeed is the
8/19/2019 Making of Bandra Bridge
10/41
maimum span !eight it can handle and that it can launch the pier
and ,I segment itself. The truss also has the capacit to align the
total span in hanging condition after the gluing is completed. The
truss is full mechaniAed for self-launching and aligning. n
individual segment can be aligned on the truss using a set of four
hdraulic #acks mounted on each suspension frame. &n order to
eliminate the casting or erection errors !ithin a span" t!o !et #oints
are provided on either end of the span. The !et #oints are cast after
finaliAation of the span alignment.
$or the fabrication of the truss" the entire structural steel (grade $e
4:5) !as sourced from !ithin &ndia. The accessories and
components ho!ever !ere procured from &ndia and abroad.
full scale load test !as conducted before putting the erection
gantr into actual operation.
The erection gantr comprises the follo!ing7
a. Main truss
b. $rontDrear plons
c. $rontDcentreDrear legs
d. $ront Drear trolle
e. +ross beamsf. Stressing gondola
g. Suspension frames
h. +onnection beams-Tpe DB
i. Spreader beams- Tpe DB
#. %ier bracket
k. +hain Support
Tpical 45m span of the approach bridges comprises 24 field
segments" a %ier segment and 355mm (nominal) in-situ !et #oints.6uring the span construction" all field segments are suspended from
the 1antr" glued and temporaril stressed together. nce the gluing
operation is completed" span alignment to the %iers is follo!ed.
fter alignment" the !et #oints are cast including grouting of
bearings top plinth. nce the !et #oints achieve the re'uired
strength" stressing of longitudinal %T is commenced follo!ed b
Load transfer of Span to %iers.
8/19/2019 Making of Bandra Bridge
11/41
.
/elocation of Launching Trusses using 2>55MT capacit Barge
Mounted +rane J sian ercules fter the successful erection of the
deck on Bandra side" the trusses !ere re'uired to be shifted across
the Bandra cable sta bridge b >55 meters to Worli side to take up
the spans
beond the Bandra +able Sta.
arious options like (i) dismantling of the trusses at present locations
and reassembling them at ne! locations" (ii) lo!ering the trusses on
a suitable floating craft and shifting and erecting them" and (iii)
shifting the total truss using a floating crane" etc. !ere analsed in
detail.
Taking into consideration various constraints like limited !orking
period available to eecute the !ork in sea" the effect of open sea on
dismantling and re-erection" etc." the best option available !as the
relocation of the trusses in one piece using a floating crane.
sian ercules is one of the biggest floating shear leg cranes in the
!orld. This crane is mounted on a barge !hich is over 3:5 feet long
and more than 2=5 feet !ide" !eighs 4"G55 tons and has enough
lifting capacit (2>55 MT) to lift a !eight e'ual to 3"555 small cars.
&t
started its voage from Singapore on ctober G" 355>" and arrived at
Mumbai9s shores on ctober 3E" 355>. fter obtaining the necessar
regulator clearances" it commenced operations from *ovember 5>"
355>" including trial runs and realignments in its settings.
Selection of e'uipment !as done considering various challenges"
8/19/2019 Making of Bandra Bridge
12/41
like the draft and space available at !orking locations" tide
limitations" and other !eather constraints. The process7 The biggest
hurdle on the sian ercules operation !as that the draft at the
re'uired locations !as not good enough to carr out the operation
smoothl !ithout disturbing the S*L cable ling underneath. This
problem !as overcome b using sophisticated global positioning
sstem and carring out the entire operation in a series of
smaller operations during the favourable high-tide. $irst the sian
ercules +rane !as positioned at the re'uired lifting position.
comple operation of balancing the vessel using ballasting !as
carried out as per the predetermined stages. %ositioning of the vessel
!as done considering the draft re'uirements. speciall fabricated
lifting spreader !as fied to the truss to facilitate the lifting.
The truss load !as taken b the crane in stages so that the lifting
operation !as smooth.
Through computeriAed central monitoring" the load in individual
lifting points !as monitored to ensure that no point !as overloaded.
fter taking the load" the sian ercules crane !as moved to a safe
location !here enough !ater depth (draft) !as available to park the
crane !ith the truss. Then the crane !ith the truss !as moved to a
ne! location during the net high tide. The truss !as then lo!eredon to the final location. The lo!ering of truss at the final location
!as achieved through 1uides" !hich helped to achieve a final
placement accurac of N45mm. The operation" !hich other!ise
!ould have taken one complete ear" !as completed in matters of a
fe! das. Cable Stay bridges &t is for the first time that cable sta
bridges have been attempted on open seas in &ndia.
8/19/2019 Making of Bandra Bridge
13/41
+oupled !ith the fact that the aestheticall designed plons have an
etremel comple geometr and one of the longest spans for
concrete deck" the challenges encountered !ere indeed formidable.
+onstruction of %lon To!er Legs
The salient characteristics of the plon to!er that make it comple
and challenging from the point of vie! of constructabilit are as
follo!s7
(a) The section decreases graduall !ith heightO
(b) There are horiAontal grooves at ever =m height and vertical
grooves for circular portion that re'uires special form liners as !ellas it re'uires attention for de-shutteringO
%&,/ TBL,
+BL, *+/ H*, 25
L&$TS
C%%,/ TW,/ L,1S 3:
L&$TS
LW,/ TW,/ L,1S ?
L&$TS
8/19/2019 Making of Bandra Bridge
14/41
S&6, &,W $ TW,/ %2G $/ B*6/ +BL,-ST@,6
B/&61,
(c) The to!er legs are inclined in t!o directions" !hich creates
compleities in alignment and climbing of soldiersO(d) +onstruction #oints permitted onl at =m level. &nserts !ere
permitted onl in horiAontal grooves provided at =m height.
n not being able to get immediate solution from reputed !orld!ide
form!ork manufacturers" the pro#ect design team designed an
automatic climbing shutter form!ork sstem" !hich !as fabricated
on site and emploed to eecute all to!er leg lifts belo! deck level.
To affect further reduction in time ccles" ++ approached 6oka"
ustria. 6oka then devised a customiAed solution based on theirS0,-255 automatic climbing shutter sstem.
+onstruction of to!er legs belo!
deck level 60 S0,-255 utomatic +limbing Scaffolding
Sstem erected on to!er legs
a. Surve of To!er Legs
The comple plon geometr !as another challenge for surveors.
+oupled !ith geometr" the construction stage analsis indicated
leaning and progressivel increasing in!ard inclination of plon legs
during construction. ++9s %rincipal Surveor devised a
sophisticated technolog to measure coordinates through a
combination of total station and prisms mounted on plon legs. The
temperature and construction stage analsis factors !ere applied to
derive the corrected coordinates. The plon legs !ere constructed
8/19/2019 Making of Bandra Bridge
15/41
!ithin an accurac of N4mm" !hich speaks volumes about the
techni'ue emploed.P
b. nchorage Bo
nchorage Bo for Bandra +able Sta Bridge placed on To!eread Iunction nchorage Bo for Worli +able Sta Bridge
nchorage Bo is used as inner shuttering for to!er head. Bearing
plates !ith guide pipes are fied to the anchorage bo. 1uide %ipe
and Bearing %lates actuall transfer the deck loads to to!er concrete
!hich are generated due to stressing of sta cables. The anchorage
bo is fabricated !ith 23mm thick high grade steel plates. &t is
fabricated in pieces and then bolted at to!er head portion. The
bearing plates and guide pipes of anchorage bo are galvaniAed andthe remaining portion !as painted !ith anticorrosive polurethane
based paint.
nchorage boes are fied !ith the help of co-ordinate sstem for
accuratel fiing the anchorage point and angle of sta cable.
c. +ompression struts
+ompression struts are provided at various levels of to!er legs.
These !ere basicall provided to keep the alignment of all to!er
legs in their re'uired position. 6uring construction" due to geometr
it !as possible that the to!er legs might lean in!ards due to !eight
and stresses involved in the base. &n order to avoid that" compression
struts !ere
8/19/2019 Making of Bandra Bridge
16/41
provided and #acking done to desired load to maintain the alignment.
d. ,rection of %ier Table segments The pier table segments
numbering :3 for both the carriage!as !ere another hurdle
encountered. The reasons being J (a) Launching Truss could not be deploedO
(b) Being generall over the plon pile cap" lifting segments from
the sea !as not possible. To overcome this hurdle" ++9s ,pat
devised a brilliant and ingenious solution in the form of J
-%ier Table Trusses (%TT)7 ne each !as erected for each
carriage!a. &t had rails on top to move segments !ith the help of
hdraulic #acks from one end to another.
-Lifting $rame7 This !as an ingenious little devise mounted at either end of %TT.
SLC (Strand Lifting Cnits) !ere mounted on top to lift the segment
from barges anchored in the sea. fter lifting the segment" the front
frame closed do!n" !here the segment !as lo!ered on the rails. The
rear frame lifted up to enable the segment to slide across the %TT
hdraulicall.
ST1,7 2
pen the Support Bracket and Lift the Segment. +lose the SupportBracket" Slide in the Trolle and Lo!er the Segment on Sliding
Trolle
ST1,7 3
pening of the Lifting Boom Q Strut" Slide out the Segment and
+lose the Lifting Boom and Q Strut. /epeat operations for the other
segment lifting.
e. ,rection of segments of +able Sta Bridge b 6errick The method
used for erection of segments at +able-Staed bridge !as balancecantilever construction method. 6uring construction" the length of
free cantilever for Bandra +able-
Staed bridge !as 324m and for Worli +able-Staed bridge it !as
E=m. The segments !ere lifted b the instrument named 6errick
!hich !as fied on both ends of the pier table segment and then
for!arded. Lifting operation !as done simultaneousl on both ends.
t a time" 6errick can lift one segment. 6eck is constructed of
alternate sta andnon sta segments #oined to pier table segments.
8/19/2019 Making of Bandra Bridge
17/41
Lifting of Segment !ith 6errick
f. 6r Matching" ,po and temporar stressing for gluing When
the segment is positioned" it is to be #oined !ith the eisting
segment. Therefore" the segment !as first dr-matched !ith thealread erected segment. n completion of dr-matching" the
segment !as moved back b sliding the lifting beam for a distance
of :55mm of the derrick and epo !as applied on the face of both
segments. fter application of the glue" the segments !ere #oined
together and !ere stressed b Temporar %T bars. %ost this step" the
segment lifting beam on derrick is moved for!ard to lift the net
segment i.e. sta segment.
g. ,rection of Sta segmentThese segments !ere also erected similarl as the non-sta segment
and !ere also #oined in the similar !a. fter this" guide pipes !ere
installed over the ducts left behind during segment casting.
h. Sta cable
Sta +ables used are R%arallel Wire Sta +ables9. The !ere
manufactured b ;Shanghai %u#iang +able +o. Ltd< +hina. ,ach
cable consists of a group of different number of steel !ires. ,ach
!ire is made up of high tensile steel. 6iameter of single !ire !asEmm !ith a
breaking limit of >.3? Tones. Si different siAes of cables !ere used
in the cable-staed portion. The difference bet!een them !as onl
on the basis of number of steel !ires in each cable. Si different
tpes used !ere of >2" E=" ?4" G2" 25G and 232 steel !ires. 1roup of
these !ires !as packed in t!o laers of 6%, (igh 6ensit %ol
,thlene) material to protect them from atmospheric effects. Typical
Cross Section of Stay Cable i. +losure pour &n Bandra +able-Staed Bridge" closure pour is provided bet!een
main cable-staed cantilevers and back span. &n Worli +able-Staed
bridge" closure pour is provided bet!een t!o cable-staed cantilever
decks
#. Longitudinal stressing and grouting
When all the segments and cables !ere erected" the segments !ere
post tensioned longitudinall. This post tensioning !as done b
stressing the steel tendons placed in the ducts provided inside the bod of segments. This helps the members to sta together and to
8/19/2019 Making of Bandra Bridge
18/41
increase their load carring capacit as a large number of segments
!ere #oined together to make single unit. nce the stressing !as
done as per re'uirement" these holes or ducts !ere filled !ith
cement grout and !ere plugged at both ends.k. $ine tuning
fter completion of closure pour and post-tensioning of the deck"
fine tuning of sta cables is done. $ine tuning is fine force
ad#ustments of the sta cables to achieve the re'uired stresses in the
deck and profile of the deck.
6uring fine tuning" forces in the sta cables are ad#usted to suit
further addition of superimposed dead loads such as !earing coat"
crash barriers" handrails and also vehicle loads.6uring fine tuning operation" longitudinal and transverse deck
profiles are also monitored to provide smooth curve.
l. Wearing +oat over south bound bridge deck Bridge deck surface
of south bound carriage!a is provided !ith :5mm thick %olmer
Modified Bituminous pavement in con#unction !ith !ater-proofing
sstem to seal the bridge deck. (or&ing during monsoon The
Maritime Board does not allo! marine traffic in monsoon season.
Thus" !ork !as halted mid-Ma onl to re-commence in ctober"effectivel reducing the !ork schedule to onl seven months in a
ear. To overcome this hurdle and to use this time to speed up the
construction activities at Bandra %lon" ++ put forth the solution
in the form of an innovativel designed temporar bridge. This
bridge had a total length of =34 metres. &t had the facilit of a
!alk!a" a concrete pipe line" an electricall-operated trolle
mounted on rail" !ater line and a pipe line. &t paved the !a for
successful continuation of !ork during the monsoon season !henthe sea !as rough and the !inds !ere strong. $ogistics nother
challenge !as ensuring effective suppl chain at all !orking
locations spread across the alignment in the sea and formulating
measures to ensure the same. diligentl !orked out logistic plan
!as put into action to ensure that commodities !ere handled at
dedicated
location and dispatches monitored meticulousl. State-of-the-art
electronic devices !ere placed on the barges to cut do!n on idletimings.
8/19/2019 Making of Bandra Bridge
19/41
6uring peak construction activities" innovative procedures and
specialiAed e'uipment9s !ere re'uired to enable high accurac.
,pert cre!s had to also eercise good #udgement in assessing sea
behaviour and priorities during foundationD substructureconstructions and final
placement of concrete in situ. *avigation and transporting 2G precast
segments in 3: hours at different open sea locations !as a challenge.
Secondl" concrete consumption at the peak had been at the rate of
45cumDhr. Cnder marine conditions" the consumption rate has been
in the order of E55cum per da. To add to this" maintaining ade'uate
food suppl for around 3455 people (in a shift) !orking in the sea at
over =5 locations !as a big challenge. These complete re'uirements!ere met !ith an effective utiliAation of a fleet of =5 marine vessels
including 2= barges for concrete" segments and material transport"
eight steel boats for material and !orkers transport" three tug boats
and si smaller passenger boats.
round four passenger boats !ere used for carring food to
approimatel =5 locations in the sea. ,ach emploee" !hile starting
his da" entered the log indicating the location at !hich the !ould
be !orking. Thereafter began the clock!ork of gathering tiffin boes" !ashing and cleaning" allocation and dispatch as per the log
entries along !ith the drinking !ater suppl including tea suppl at
t!o time intervals per shift. 6uring rough sea conditions in the
normal !orking season" etra tiffin9s !ere carried to take care of
possible spillage !hile
transferring the tiffin9s from boats to !orking locations. Thus
!orkers !ere also suitabl cared for" !hile meeting the engineering
challenges posed during construction of the Bandra- Worli Sea Link.Psychological conditioning With a long track record and
eperienced in building large infrastructure pro#ects" ++ follo!s
strict guidelines for occupational health and safet and environment
protection.
Safet is etremel important to ++ and the compan officials
!orked to!ards sensitising labour and creating greater a!areness of
safet standards !ith gentle persuasion" consistent motivation and
tool bo meetings. The kind of structured processes that !ereimplemented b ++ for ensuring safet is nothing short of
8/19/2019 Making of Bandra Bridge
20/41
phenomenal.
Lack of a!areness is the biggest haAard for safet. Since the primar
safet haAard are related to engineering control" e'uipment" #ob
methodolog" material handling" structural fabrication andemergenc preparedness" ++ made sure that ever !orker is taken
through the S, program. The orientation program made them
a!are of the various safet haAards associated !ith a pro#ect and
necessar precautions to be taken to prevent them. The are also
taught ho! to evacuate during an emergenc. $or its meticulous
planning and implementation of safet practices for the BWSL
pro#ect" ++ has !on the prestigious ;1olden %eacock !ard< for
safet" health and environment in Iune 355E. )ey people ver =555!orkers !ere emploed to !ork on the pro#ect. Several teams of
++ engineers and foreign engineers and technicians have been
involved in specialised tasks on the structure of the Sea Link. These
include professionals from +hina" ,gpt" +anada" S!itAerland"
Britain" Serbia" ustralia" Singapore" Thailand" ong 0ong"
&ndonesia and the %hilippines. &n terms of language" cultural
differences and methods of !ork these ke people !ere different" et
the engineering challenges kept the group creativel involved" andthe !orked enthusiasticall as a team.
JFFFFFFFFFFFFJ
*This pro+ect ga,e us an opportunity to sho!case our
euipment.
#a&esh )aul
says #a&esh )aul/ 0eneral %anager/ Elcome Technologies
P,t1 $td1/ !ith reference to the sur,ey euipment that they
supplied for the Bandra-(orli Sea $in&1
8/19/2019 Making of Bandra Bridge
21/41
(hen did Elcome Technologies first get associated !ith HCC on
the Bandra- (orli Sea $in& Pro+ect2 Leica e'uipment has been
used on most of the Sea Link pro#ects around the !orld and based on
this eperience !e approached industan +onstruction +ompan(++) sometime at the end of 3555 !ith our range of specialised
e'uipment9s for the Bandra-Worli Sea Link (BWSL). The first Leica
Total Station !as supplied b us to ++ in earl 3552. (hat !ere
the euipment supplied for this pro+ect2 To meet the demand for
high accurac coordinate measurements on the BWSL pro#ect !e
supplied high performance Leica Total Stations including the T+
355=" the T+ 2?55" the T+ 2352" the T+/M 2352 / =55 and the
T+ 2?55. We also supplied the S/ 425 1%S e'uipment. (hat &indof support did you pro,ide HCC ,is-3-,is the euipment that
you supplied to them2 We gave comprehensive application
trainings at their site to!ards effective and optimal usage of the
e'uipment. Moreover" these e'uipment9s in keeping the desired
accuracies that are re'uired for such a pro#ect" needed timel
calibration checks and corrections J for this" besides providing them
complete service support during the !arrant" !e also got into
annual maintenance contracts for these e'uipment post their!arrant period. We !ere thus able to provide timel service and
calibration of the e'uipment at our service centre. "o you thin&
being associated !ith the pro+ect gi,es Elcome Technologies any
le,erage for other similar pro+ects2 &t has been a privilege to be
associated !ith BWSL and the ++ team !e !orked !ith.
Moreover the challenges in geometric control on the pro#ect !ere
highl demanding and eacting. This gave us an opportunit to
sho!case our e'uipment and our epertise. ur eperience !ithBWSL pro#ect !ill be a basis for us to promote our technolog on
other such pro#ects too.
8/19/2019 Making of Bandra Bridge
22/41
8/19/2019 Making of Bandra Bridge
23/41
Partners in,ol,ed 2. SL Singapore %vt Ltd 7 Technical
+onsultants
3. Cltra Tech7 Supplier of cement
=. Metco group of companies7 Supplier of bearings
:. Tata Steel" /&* Ltd Q S&L7 Supplier of steel
4. ,L0,M &nternational Ltd.7 *or!a-based compan supplier of
micro silica
8/19/2019 Making of Bandra Bridge
24/41
>. S%++7 +hina-based compan supplier of sta cable
E. 60 ustralia7 supplier of %lon form!ork
,'uipment used
The ma#or e'uipment9s deploed for this pro#ect are78 Iack up platform" launching truss" reverse circulation drilling
machine floating barrages" boats" cra!ler crane" to!er crane" gantr
crane" derrick crane" placer boom" diesel generators" concrete pump"
transit miers Q R9 frame barrage.
8 The e'uipment !as brought together from various countries.
The construction of the mammoth bridge structure re'uired huge
cranes and other structures to lift material for off shore and on shore
structures. Some of these included72. Launching Truss7 Weighing 2345 tonnes and measuring 223 m in
length" it !as used for lifting segments each !eighing 2=5 tonnes.
This has been fabricated in &ndia.
3. Iack up platform7 SiAe 2?.==53.2m (Width Length 6epth)
having four legs of =5m. &t is a floating e'uipment used for marine
!ork.
=. $lat barge7 SiAe =5233m. Like motor boats" the are driven
inside the sea for material transportation.:. Self-propelled barge7 &t is a barge !ith a machine component and
is used for concrete transportation.
4. +ra!ler crane7 +apacit ranges from E4-245 tons. &t is used for
material and heav lifting activities.
>. /+6 drill bit7 6imension 2.4m 3m diameter. &mported from
0orea" the /+6 drill bit is used for pile drilling !ork.
E. ibro hammer (%T+)7 &mported from $rance and used for driving
of steel liners.?. $ushun cra!ler crane7 &mported from +hina" +apacit ?5 tons.
G. *+0 ,iger crane7 &mported from ,ngland" capacit >4 tons.
25. 0obelco cra!ler crane7 &mported from ong 0ong" capacit 245
tons. 'ascinating facts 8 The pro#ect has alread been acclaimed b
the vie!ers as an engineering marvel of modern &ndia.
8 $irst +able-Sta Bridge in &ndia in open sea.
8 The length of the bridge is >= times the height of the utub Minar
in 6elhi.8 &ts !eight is e'uivalent to 45"555 frican elephants.
8/19/2019 Making of Bandra Bridge
25/41
8 The length of the steel !ires used is e'uivalent to the
circumference of the earth.
8 The height of the cable-staed to!er is 23? m" !hich is e'ual to a
:=-store building.8 total of :3: cables !ere used for both Bandra cable sta as !ell
as Worli cable sta bridges.
8 The cables have been sourced from Shanghai %u#ang +able
+ompan" +hina. The cables !ere sub#ect to a series of 'ualit and
engineering tests to meet the special re'uirements including fatigue
tests of t!o million ccles.
8 The cables are made of high tensile steel and are designed to take
the maimum load of G55 tons.8 G3"555 tons of cement !as utiliAed to make BWSL.
8 ,nvironment friendliness !as top priorit during the construction J
fl ash" a !aste product etracted from thermal po!er plants" !as
mied !ith concrete" to make the construction durable as !ell as
eco-friendl" thus making good use of !aste material.
8 The construction team is like a mini Cnited *ations7 several teams
of foreign engineers and technicians have !orked on specialiAed
tasks on the structureO these include professionals from +hina",gpt" +anada" S!itAerland" Britain" Serbia" Singapore" Thailand"
ong 0ong" &ndonesia and the %hilippines" ustralia.
8 The Launching Trusses" each 223 meters long" !ere custom built to
precision b ++ for this pro#ect. The pre-cast concrete segments of
this four-lane road are fabricated at the Bandra site location. These
segments are then carried on a barge to the construction location and
are lifted b the Launching Truss to the designated height and
assembled bet!een t!o piers" each 45 meters apart. $ifteen suchsegments are fitted bet!een t!o piers and the Launching Truss can
lift all fifteen segments together" !eighing 2=5 tons each" bet!een
t!o piers. nce these segments are fied bet!een t!o piers" the
Launching
Truss cra!ls to the net piers on its mechanical legs.
8 1iven the gigantic siAe of the pro#ect" mega e'uipment9s !ere used
in constructionO bringing them to the pro#ect site and operating them
!as a feat in itself. sian ercules" one of the biggest floating shearleg cranes in the !orld" !as hired from Singapore to lift the massive
8/19/2019 Making of Bandra Bridge
26/41
2345 tonnes" custom-built Launching Trusses !ith its mechanical
arm and relocate them on the Worli side of the bridge.
industan +onstruction +ompan (++)
2. SL Singapore %vt Ltd7 Technical +onsultants3. Cltra Tech7 Supplier of cement
=. Metco group of companies7 Supplier of bearings
:. Tata Steel" /&* Ltd Q S&L7 Supplier of steel
4. ,L0,M &nternational Ltd.7 *or!a-based compan supplier of
micro silica
>. S%++7 +hina-based compan supplier of sta cable
E. 60 ustralia7 supplier of %lon form!ork Euipment used
The ma#or e'uipment9s deploed for this pro#ect are78 Iack up platform" launching truss" reverse circulation drilling
machine floating barrages" boats" cra!ler crane" to!er crane" gantr
crane" derrick crane" placer boom" diesel generators" concrete pump"
transit miers Q R9 frame barrage.
8 The e'uipment !as brought together from various countries.
The construction of the mammoth bridge structure re'uired huge
cranes and other structures to lift material for off shore and on shore
structures. Some of these included72. Launching Truss7 Weighing 2345 tonnes and measuring 223 m in
length" it !as used for lifting segments each !eighing 2=5 tonnes.
This has been fabricated in &ndia.
3. Iack up platform7 SiAe 2?.==53.2m (Width Length 6epth)
having four legs of =5m. &t is a floating e'uipment used for marine
!ork.
=. $lat barge7 SiAe =5233m. Like motor boats" the are driven
inside the sea for material transportation.:. Self-propelled barge7 &t is a barge !ith a machine component and
is used for concrete transportation.
4. +ra!ler crane7 +apacit ranges from E4-245 tons. &t is used for
material and heav lifting activities.
>. /+6 drill bit7 6imension 2.4m 3m diameter. &mported from
0orea" the /+6 drill bit is used for pile drilling !ork.
E. ibro hammer (%T+)7 &mported from $rance and used for driving
of steel liners.?. $ushun cra!ler crane7 &mported from +hina" +apacit ?5 tons.
8/19/2019 Making of Bandra Bridge
27/41
G. *+0 ,iger crane7 &mported from ,ngland" capacit >4 tons.
25. 0obelco cra!ler crane7 &mported from ong 0ong" capacit 245
tons. 'ascinating facts 8 The pro#ect has alread been acclaimed b
the vie!ers as an engineering marvel of modern &ndia.8 $irst +able-Sta Bridge in &ndia in open sea.
8 The length of the bridge is >= times the height of the utub Minar
in 6elhi.
8 &ts !eight is e'uivalent to 45"555 frican elephants.
8 The length of the steel !ires used is e'uivalent to the
circumference of the earth.
8 The height of the cable-staed to!er is 23? m" !hich is e'ual to a
:=-store building.8 total of :3: cables !ere used for both Bandra cable sta as !ell
as Worli cable sta bridges.
8 The cables have been sourced from Shanghai %u#ang +able
+ompan" +hina. The cables
!ere sub#ect to a series of 'ualit and engineering tests to meet the
special re'uirements including fatigue tests of t!o million ccles.
8 The cables are made of high tensile steel and are designed to take
the maimum load of G55 tons.8 G3"555 tons of cement !as utiliAed to make BWSL.
8 ,nvironment friendliness !as top priorit during the construction J
fl ash" a !aste product etracted from thermal po!er plants" !as
mied !ith concrete" to make the construction durable as !ell as
eco-friendl" thus making good use of !aste material.
8 The construction team is like a mini Cnited *ations7 several teams
of foreign engineers and technicians have !orked on specialiAed
tasks on the structureO these include professionals from +hina",gpt" +anada" S!itAerland" Britain" Serbia" Singapore" Thailand"
ong 0ong" &ndonesia and the %hilippines" ustralia.
8 The Launching Trusses" each 223 meters long" !ere custom built to
precision b ++ for this pro#ect. The pre-cast concrete segments of
this four-lane road are fabricated at the Bandra site location. These
segments are then carried on a barge to the construction location and
are lifted b the Launching Truss to the designated height and
assembled bet!een t!o piers" each 45 meters apart. $ifteen suchsegments are fitted bet!een t!o piers and the Launching Truss can
8/19/2019 Making of Bandra Bridge
28/41
lift all fifteen segments together" !eighing 2=5 tons each" bet!een
t!o piers. nce these segments are fied bet!een t!o piers" the
Launching
Truss cra!ls to the net piers on its mechanical legs.8 1iven the gigantic siAe of the pro#ect" mega e'uipment9s !ere used
in constructionO
bringing them to the pro#ect site and operating them !as a feat in
itself. sian ercules" one of the biggest floating shear leg cranes in
the !orld" !as hired from Singapore to lift the massive 2345 tonnes"
custom-built Launching Trusses !ith its mechanical arm and
relocate them on the Worli side of the bridge. industan
+onstruction +ompan (++).
JFFFFFFFFFFFFJ
%eeting challenges !ith inno,ation4
Col S "i!an+i
Pro+ect %anager/
Bandra-(orli Sea $in& Pro+ect/
Hindustan Construction Company
satish1di!an+i5hccindia1com
(hen did the !or& on the Bandra- (orli Sea $in& pro+ect
start2 industan +onstruction +ompan (++) !as a!arded
%ackage & of the %ro#ect and !ork started in September 3555" but
!as held up due to several reasons including environmental issues
and protests b fishermen. &n right earnest the !ork started in
6ecember 355:. 6n !hat basis !as the distance bet!een the
piers and the height of the bridge decided2 The span bet!een the
piers is 45m. This distance !as arrived at after considering various
8/19/2019 Making of Bandra Bridge
29/41
factors" !hich included optimiAation bet!een the foundation cost vs.
the superstructure cost. &f the piers are !ide apart then the
foundation cost comes do!n" but the superstructure becomes heavier
and its cost goes up.
lso the navigational re'uirements as in an emergenc the smaller
tra!lers and boats should be able to pass bet!een the piers.
Moreover" more number of piers provides better !ind resistance to
the bridge. (hy !as the cable-stayed bridge design chosen for
the Bandra-(orli Sea $in&2 cable staed design has some
inherent advantages compared to other conventional designs" the
main being that it allo!s for larger spans. There !ere three mainreasons !h a large span !as needed in case of the Bandra-Worli
Sea Link7
8 navigational channel for the fishermen and other sea faring
vessels had to be maintained.
8 There are plans to epand the present #ett.
8 There are overseas communication cables on the seafloor !hich
keep shifting and this had to be taken into consideration. At !hatstage of the bridge construction !as the need for precision
sur,ey instruments felt2 We kne! from the start of the pro#ect that
high precision e'uipment !ould be needed and one of the first
things !e did !as to mobilise the Total Stations J the first of !hich
!ere procured in earl 3552.
Sur,ey Challenges4 Bandra (orli Sea $in& Pro+ect
Len 1o!er" %rincipal Surveor on the Bandra-Worli Sea link
%ro#ect for industan +onstruction +ompan" shares his
eperiences on the pro#ect in an eclusive intervie! !ith
+oordinates.
$en 0o!er
len1go!er5gmail1com
8/19/2019 Making of Bandra Bridge
30/41
71 'or those of us !ho use them/ a bridge is a bridge8 but for
those !ho build them each bridge has its indi,iduality1 Pleasetell us about some of the bridges that you ha,e !or&ed on in the
last fe! years1 &n the past 25 ears" & have !orked on E long span
bridges. ,ach one posed uni'ue technical challenges that !ere
overcome b m teams.
The /ion ntirrion Bridge" bet!een the %eloponnese peninsula and
the 1reek mainland" is a four plon" 3355 metre span across a
seismic fault in the Strait of +orinth. The plon bases are not fied
to the seabed" but rather rest on an engineered bed of gravel and
inclusion pipe piles. Thus the are free to move during a seismic
event" !ithout sustaining damage. The deck is mounted to the plons
!ith telescopic Rshock absorber9 energ dampers" so minor plon
movement can be accommodated safel.
The %uente de las mericas cable staed bridge spans the %anama
+anal" about 24 km east of %anama +it. The siAe of the ships that
pass through the canal necessitated a ver high navigation envelope beneath the deck" and the commercial ramifications of interrupting
canal traffic meant that the entire bridge had to be constructed
!ithout the use of marine barges or floating cranes. The deck !as
cast in situ !ith movable shutters and one of the largest form!ork
travellers ever utiliAed in bridge construction. The other ma#or
technical challenge !as that the deck erection started before the
plon construction !as complete. This meant that if the deck !as
out of balance for some period of time" the plon lifts had to be castRout of plumb9 !ith the embedded cable anchors still set to tight
angular tolerances.
The +ooper /iver Bridge in +harleston" South +arolina !as (at the
time) the longest cable staed bridge in *orth merica. The
slenderness of the plon legs and the lack of a cross beam belo! the
cable anchorages made plon leg construction a challenge. The
selection of %,/& self-climbing form!ork made it impossible to place an instrument bracket on the form!ork support frame" so !e
8/19/2019 Making of Bandra Bridge
31/41
emploed a Trimble 61%S solution. ,arl in the morning"
immediatel after a section of the plon leg !as cast" !ith the
concrete in place for :-> hours" !e installed a special instrument
pedestal onto a Rcast in9 pipe flange. The to!er crane picked up a 24ton test block (to make the mast load neutral) and then s!ung to a
position that permitted the 1%S receiver to receive the maimum
number of Rclean9 satellite signals. We used a set of three Rone
minute9 static position averages" capturing one position ever
second" to determine our @ position and an approimate H. We
corrected the !eaker H position b taping a Uelevation up from the
previous lift. We then replaced the 1%S antenna !ith a Leica total
station and obtained an angular orientation from a back sight" setabout 3 km a!a. We set t!o auiliar instrument brackets on the
inside face of the eposed cable anchor bo" and then surveed their
positions for use in a =6imensional RBest $it9 solution.
The actual as-built of the most recentl cast lift took place =-: hours
later" long after sunup and !ith the to!er crane in full operation" but
!e could use a least s'uares solution to correct for temperature
gradients and eccentric load induced to!er deflections b turning off the internal compensators" observing the auiliar bracket positions
again" then taking measurements to our concrete lift as-built
positions last. 6uring post processing" !e applied a E parameter
similarit transformation to the observed data to perform the scale
factor" rotations and transformations necessar to get the instrument
position and the auiliar bracket positions to match the 5>755 M
positions" before sunup and !ith the to!er crane neutral. These
transformation parameters !ere of course applied to the as-builtmeasurements" to convert them to 5>755 M readings.
The Shaikh Haed Bridge !as not a cable staed bridge" but rather a
cast in place concrete deck supported b cable stas from a series of
asmmetrical steel arches. This pro#ect !as designed b Haha adid"
engineered b %/ and proved to be almost unbuildable and
absolutel unprofitable for the main contractor. &t is currentl 3 ears
behind schedule" !ith about 2? months to go until completion. &
staed on this pro#ect onl until & found an eit strateg J the Sutong
8/19/2019 Making of Bandra Bridge
32/41
Bridge" in *antong %/+.
The Sutong Bridge is currentl the !orld9s longest cable staed
bridge" !ith a clear span length of 25?? metresV B comparison" theBandra Worli9s main span is 455 metres. Cltra-long span bridges
bring a mriad of technical challenges" !hich directl impact the
pro#ect costs and construction schedule. Long decks re'uire tall
to!ers (to be able to accommodate the increased number of sta
anchors" and still maintain the necessar angular cable geometr).
Sutong9s plons !ere =5> Metres in height" as compared to Bandra
Worli9s tallest plon at %2G" at 23: Metres. The crossing of the
@angtAe /iver" bet!een *antong and SuAhou has strong !indsduring most of the ear so deck flutter and to!er deflection !ere
much more of a problem than thermal gradient induced deflections.
The plons !ere so tall" that after 355 metres" t!o auiliar
instrument positions had to be transferred onto the plon" to perform
set out and as-built surves" similar to the +ooper /iver Bridge"
ho!ever the +hinese chose a more traditional approach J a
reciprocal observation procedure !ith a Leica 355= total station. The
rebar for the lifts above !ere much too tall to permit a 1%S antennato receive satellite data free from multi-path errors.
The anchor boes for the plons !ere fabricated close to Bei#ing"
and then barged do!n to *antong. These boes !ere 'uite similar to
the Bandra Worli boes" and the surve control methodolog chosen
!as mine" a combination of metrolog and steel fabrication
Rdimensional9 'ualit control. The onl serious challenge in anchor
fabrication is to achieve angular accurac in the three planes (" Xand g)" $T,/ the !elding is completed. nticipating angular
errors due to !eld shrinkage" and mitigating unepected results is
almost an art J not a science. &f the acceptance criteria for angular
errors is K- 5.4 degrees (fabrication and installation errors combined)
that means that the post !eld fabrication error must be bet!een K-
5.34 degrees and the pre-!eld fit-up errors bet!een K- 5.234
degrees. &n an anchor plate of :55:55mm" that means making
repeatable surve measurements of sub-millimetre accurac. Thislevel of accurac demands the best 2st order instrumentation" on-
8/19/2019 Making of Bandra Bridge
33/41
board soft!are" customiAed targeting and methodolog available.
Both the *antong and the Bandra Worli anchor boes !ere
manufactured and installed !ithin the designer9s tolerances.
& also consulted to a bridge pro#ect in +anada" a long floating bridge
in the province of British +olumbia. The challenge the faced that
prompted m involvement !as completing the plon leg
construction once the pontoons !ere afloat. gain" & designed a
sstem based on a E parameter similarit transformation" utiliAing a
total station that could operate !ith the internal compensators
deactivated" and a series of control points originall established
!hen the pontoon !as still in the dr dock.
91 Could you please tell us briefly ho! a cable stayed bridge is
different from other bridges2 +able sta supported bridges are a
tpe of suspension bridge. tpical suspension bridge" like the
1olden 1ate Bridge in San $rancisco" consists of t!o large diameter
incrementall spun cables" hanging bet!een the t!o main to!ers" on
a catenar" !ith much smaller diameter vertical hangers spacedevenl along the deck" connected to the suspension cables.
+able staed bridges have man smaller diameter cables" connecting
the plon legs to the deck at evenl spaced intervals. The pattern of
plon connection can var. The parallel sta sstem is called a
Rharp9" the sstem that bunches the plon anchors close to the top of
the plon is called a Rfan9" but the most common stle is to space the
anchors from the plon top do!n!ards to!ards the deck. Thissstem is called a modified fan.
The longest spans still re'uire a suspension bridge" but for the
medium spans (255 J 2555 metres)" cable staed bridges ma offer
cost benefits and shorter construction schedules to the client.
The suspension bridge needs large" epensive abutments to Ranchor9
the suspension cables" and the time it takes to spin the suspension
cables is length. &f the span distance permits" a cable staed bridge
8/19/2019 Making of Bandra Bridge
34/41
alternative offers about 23 months gain in the schedule" as no
spinning delas are re'uired. possible compromise is a hbrid
design" !here a portion of the bridge deck is partiall suspended b
cable stas" !hile the suspension cable is being spun" and then uponcable spinning completion" the mid span portion of the deck is
suspended b hangers from the catenar cables. The cost benefit is
slight !ith this alternative" so is rarel chosen. Multiple span cable
staed bridges are also a cheaper alternative for long span bridge
designers" such as the /ion ntirrion Bridge in 1reece. The minor
dra!back to this solution is that the navigational channel is cut into
smaller portions b the etra plons.
:1 Please tell us about some of the sur,ey related challenges you
faced on the Bandra (orli Sea $in& Bridge2 The surve related
challenges for the Bandra Worli !ere similar to most cable staed
bridges. The accurac re'uirements are al!as demanding"
especiall in the fabrication of the cable anchor assemblies. The
angular misalignment permitted isK- 5.4 degrees in the completedstructure" so the fabrication and assembl tolerances are much
tighter. We fabricated the bearing plate D guide pipe assemblies to K-
5.5> degrees from perpendicular. We placed them in the deck slab
form!ork (prior to concrete placement) !ithin K- 5.234 degrees" to
ensure that the !ould still be !ithin K- 5.34 degrees after the
concrete had been placed and the concrete curing shrinkage !as
complete. This procedure re'uired custom design D manufacture of
ver accurate bearing plateDpipe sleeve assembl #igs" as !ell as
special dual turnbuckle pipe sleeve support okes and customiAed
targeting and tooling for surveing the anchor assemblies in the deck
sections.
The fabrication of the plon head anchor boes !as even more
comple" as !eld shrinkage had to be anticipated" and unforeseen
results dealt !ith during erection. The siAe of the base plate that the
bearing plate rests on is onl E55Y:55 mm in dimension" so that
means the fit-up surve measurements had to be accurate to sub-
8/19/2019 Making of Bandra Bridge
35/41
millimetre" to ensure the 5.234 degree angular misalignment
specification !as met.
The plon legs (belo! the to!er head) !ere ver slender" so !eresusceptible to thermal gradient deflections. +are had to be taken to
ensure that all important surves !ere performed in a thermall
neutral state. The legs also deflected to!ards the plon centre after
concrete placement" so the Ras-set9 positions !ere al!as different
from the Ras-built9 positions.
The reference geometr supplied b the designer is based on Time
Z" !hereas !e !ere constructing ever element at Time 5" soallo!ances had to be made for future creep" shrinkage and elastic
shortening. These allo!ances are referred to as pre-cambers and
over heightsDlengths. $or eample" the over height for the %2G
plon9s to!er head !as K=4 mm. s !e completed the south
carriage!a first" the deck load !as transferred into the plon legs"
causing the shared centre legs to shorten less than the single outer
leg. This caused the plon to temporaril incline a!a from bridge
centreline b nearl =5 mm at the top of the to!er head. This meantthat !e had to construct the north plon9s to!er head on a similar
inclination" !ith the epectation that the plon !ould come back to
plumb !hen the load of the north deck !as in place" bringing the
plon sub structure and common foundation back into e'uilibrium.
;1 Could you please elaborate on the role of the pylons in a cable
stayed bridge and the sur,ey methodology that !as used to put
them up in the Bandra (orli Sea $in& Bridge2 The plons of a
cable staed bridge are used primaril to anchor the upper cable stasockets. Man times the deck is firml attached to the plons (as in
the case of the Bandra and Worli spans) but other bridges onl have
sliding pot bearings at the plons (Ting 0au Bridge" in ong 0ong)"
or elastomeric bearings bet!een the to!er9s cross beam and the
underside of the deck (le $raser Bridge" +ooper /iver Bridge).
The plon must be tall enough to provide sufficient space for all the
cable anchors" and still ield a decent vertical angle at the uppermostcables. bviousl" as the alpha angle decreases !ith the height of the
8/19/2019 Making of Bandra Bridge
36/41
anchor above the deck" the amount of cable force in the vertical
direction decreases as the force in the horiAontal direction increases.
This is !h the diameter of the longest cables is greater than those
nearest the plon (!ith the steepest alpha angles). The have to bestrong enough to resist the etra cable force applied" to ield
sufficient up!ard lift to support the dead load and the live load
(traffic) in the !orst case scenario.
The surve method utiliAed to construct the Bandra Worli plons
!as based on the fact that the plon legs !ere inclined. &nclined
plon legs pose a significant challenge to the contractor" as the rebar
cage !ill have a natural tendenc to sag do!nhill duringconstruction. &f a rebar cage sags" it !ill be out of tolerance !hen
completed and clash !ith the form!ork ad#ustment procedure during
the final as-set surve. ur solution !as to implement a sacrificial
rebar template assembl" to guide the construction of the rebar cages
and to ensure that there !ould be no clashes of the steel embedment"
like crane tie-ins and 60 climbing cones.
ur surveors set the rebar templates in the earl morning hours"after the self-climbing form!ork !as fied for the net lift. These
templates had = or : ke points stamped onto them that the
surveors could shoot" and once the support frame!ork !as
completel interconnected" formed a local surve net!ork that
moved !ith the plon9s thermal deflections" et !as still based on a
thermall neutral plon. t an time" and !ith an amount of plon
leg deflections present" our surveors could set up their instrument
on the special brackets attached to the 60 frame!ork" disable
the internal compensators and then perform a Rresection9 or Rfree
station9 operation to determine instrument co-ordinates and
orientation" for set-out !ork. nce the concrete !as placed" the
plon !ould deflect do!n!ards to!ards the bridge centreline" so
ne! co-ordinates of the rebar template !ere measured (again in the
earl hours of the morning). The instrument !as again transferred up
to the top of the plon" installed on the same bracket" !here the as-
built surve could be completed 'uickl and accuratel.
8/19/2019 Making of Bandra Bridge
37/41
The main challenge to these surves !as in the form!ork
construction. n most bridge plons" there are 3 fied panels and
t!o ad#ustable panels" so fine ad#ustment at each corner is possible.
$or the Bandra Worli plons" the form!ork had no ad#ustabilit.,ach panel butted up to the ad#acent panels" so the entire shutter
assembl acted as a solid bod. To move the top into position" the
entire shutter had to be tipped" similar to the surve alignment
procedure of an elevator core shutter. &f an error in a panel length
cutting operation occurred" there !as no !a to eliminate this. Small
errors could be mitigated b setting the shutters so that half the error
!as on one corner and the other have !as on the opposite corner.
ur surve alignment criteria !as therefore based on the centroid ofthe entire shutter (> point average in the plon leg sections Q 23
point average in the to!er head sections)" and not on individual
corner positions.
8/19/2019 Making of Bandra Bridge
38/41
G. 6eck profile surves
25. Wet #oint alignment bet!een 2> deck segment Rblocks9
22. 6eck closure surves" pre cable length fine tuning
23. %ost fine tuning deck profile surves
2=. 0erb and asphalt grades
=1 (hat &inds of sur,ey instruments are best suited for thedifferent sur,ey !or&s in a typical cable stayed bridge
construction1 The best instruments for cable staed bridge
surveing are state of the art" high accurac" vibration tolerant
electronic total stations" !ith T/ (automatic target recognition) and
on-board soft!are for $ree Station and /esection.
1%S receivers can also pla a role" !hen the plons are etremel
tall (as in the Millau Bridge in $rance) or far out to sea. Their lack of accurac in H measurements is their onl !eakness" in m opinion.
With improvements in multi-path error mitigation and the
implementation of the 1lonass satellites" the availabilit issue and
%6% are much improved.
The eception to this high tech e'uipment is utiliAing a pair of old
fashioned tilting levels to perform accurate deck profiles. The
vibrations present in cable sta supported decks makes internallcompensated surve e'uipment susceptible to Rcompensator
ecitation9" producing a blurred image of the crosshairs in an auto
level or randoml inaccurate vertical differences in total stations.
split bubble tilting level ehibits the deck vibrations in the
movement of the tilting bubble J !hile the cross hair image remains
completel stable. B ad#usting the level so as to balance the bubble
movement evenl" a level observation is possible. The purpose of
having t!o instruments observing a single staff is that long circuits
can be run Rone !a9. ,ach set-up produces t!o back sights and t!o
8/19/2019 Making of Bandra Bridge
39/41
foresights" so constitutes a closed level loop. The net set-up again
produces 3 back sights and t!o foresights" !hich is again a closed
loop. &t is like building a chain" link b link. &t !as 'uite common to
be able to level from %2E to %32" a distance of >55 Metres" !ith amisclosure of onl 2-3 mm.
>1 Could you tell us about the &ind of accuracies that are needed
for ,arious aspects of a cable stayed bridge2 There are man
different accurac re'uirements" in the steel fabricationDconcrete
casting and their related surve control measurements" as some tpes
of errors can propagate or sstematicall multipl and others are
essentiall Rone off9 J !ith no knock-on effects.
6eck segment lengths are a tpical dimensional component that has
potential for sstematic error propagation. K2mm error on ever
=M long deck segment of a >55 metre span !ill produce K255 mm
errors at each epansion #oint at the end spans" or roughl 25 of
the thermal gradient epansion range. This is still an acceptable
range of error" but 355 or =55 mm !ouldn9t be" so deck lengths have
to be measured accurate to the millimetre" and significant errorsmust be tracked during deck segment installation" and compensated
for in the last in situ stitch #oints cast.
&nstallation of the first deck segment of a 2> segment block is
another eample of a potential sstematic error situation. $or ever
2mm rotational error (in either the horiAontal or vertical directions)
there !ill be a 2>mm error at the net !et #oint. When setting these
segments during !et #oint construction" !e measure the horiAontal
positions to the millimetre and the vertical differences to better than5.4 mm.
+able anchorage placement errors in either the deck or plon are
minor" as there is usuall a fairl generous range of cable length
ad#ustment at the live end socket J either b split shims or b
threaded sockets and lock nuts. shift of 2 or 3 centimetres in
longitudinal or transverse directions is insignificant" so normal
surve procedures are 'uite capable of controlling installation andidentifing absolute errors. The eception to this is angular
8/19/2019 Making of Bandra Bridge
40/41
misalignments. The principal of multi-strand stas" or parallel !ire
pre-formed stas is that each !ire or strand carries an e'ual
proportion of the cable force. &f the bearing plate isn9t perpendicular
to the cable force vector" then some !ires !ill carr much more oftheir respective share of the force" and other !ires !ill carr much
less of the force. The over-stressed !ires are therefore susceptible to
premature fatigue failures. Most manufactures !ill provide a
!arrant period for their stas" providing the final angular
alignments are !ithin K-5.52 /adians (K- 5.4E degrees). ,ven !ith
this Rless than generous9 installation tolerance" longer guide pipes
!ith a misalignment close to the limit !ill pose problems during
damper installation. This is the one phase of !orks that re'uires the best surve e'uipment and methodolog available" to produce
repeatable measurements at sub millimetre accurac.
The actual positions of the anchors need to be measured accuratel"
onl &$ the cables are to be installed to length" instead of force. s
absolute cable lengths at the installation forces are ver difficult to
determine" engineers rarel use length as an installation criteria" and
instead choose force (as measured at the hdraulic #ack pump). slong as the cable anchor socket has sufficient capacit for minor
length errors" the cable length" deck anchor and plon anchor
locations need onl to be !ithin 3 cm of design.
%ile driving and coffer dam positioning can be performed to K- 4mm
!ithout an detrimental effects" so is a perfect application for 61%S.
:: ?1 Ho! important is the use of 0PS for sur,ey purposes in a
cable stayed bridge pro+ect2 Ho! !as it used in the Bandra
(orli Sea $in& Bridge pro+ect2 The application of 1%S in cable
staed bridge construction is 'uickl gaining acceptance" for specific
tasks. While it can9t replace all traditional surve e'uipment J it
does have cost benefits in certain applications.
Bridges far from shore" ver tall plons" marine plant positioning" bathmetric vessel positioning" and construction site control
8/19/2019 Making of Bandra Bridge
41/41
net!orks are all perfect applications for 61%S. @ou can even use
static 1%S receivers for as-builts" provided the H co-ordinates are
not critical.
&n dnamic structures that re'uire periodic monitoring" a 61%S
sstem that logs reading once per second" over 3: hours is a much
more cost effective solution than a t!o man cre! !ith a total station
and prism pole.
s the Bandra Worli Bridge is fairl close to shore" 1%S plaed a
limited role in construction control.