Madison Elementary School DistrictBond Project Update August 2013
Solar Update Madison #1
Solar Update Rose Lane Elementary
Solar Update Park Elementary
Solar - Schedule of Completion
• Structural and panel set- 8/22/13• Broken sidewalk replacement- 8/26/13• Installation of turf and DG- 9/16/13• Substantial completion- 9/23/13• First day of generation- 9/26/13• Final Completion- 10/14/13
The Next Step in Solar
Site evaluations later this weekPreliminary design by 8/29Submitting applications to APS for rebates by 8/30
Rose Lane Café Remodel
Madison Heights Café Remodel
Madison Meadows Site Work
Upcoming Projects
• Madison Heights kitchen remodel• Madison Meadows front office remodel• Non-skid surfacing on exterior stairs• Roof replacement at Heights• Daylighting in dining areas at Heights, Park and Rose Lane