Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Local cryogenics for SIS100
Polish in kind contribution to the FAIR cryogenic system
Maciej Chorowski
on behalf of WrUT and Kriosystem team
18 November 2014 , FAIR
12th Machine Advisory Committee
Wrocław University of Technology
Faculty of Mechanical and Power Engineering
Content
1. Scope of Wroclaw University of Technology in-kind as stipulated in
FAIR Council Resolution from 12. December 2011
2. Scope of Wroclaw University of Technology contract with
Jagiellonian University signed on the 4. December 2013
3. Progress in design and construction of Test String elements, to be
reinstalled in Sector 5.
4. Conclusions.
Local cryogenic system of SIS100
Items in the tunnel in Sects. 1,3 and 5
Feed in line
Feed box
Connection Box Arc end upnstream
Connection Box Arc end downstream
Bypass line 9 m section
Bypass line 12 m sections
Connection boxes
PSP Code: 2.8.12.6.3
PSP Code: 2.8.12.1
PSP Code: 2.8.12.11
PSP Code: 2.8.12.5.2.1
PSP Code: 2.8.12.5.1
PSP Code: 2.8.12.6.2
PSP Code: 2.8.12.6.1
Bypass line 12 m section
to Feed-in-Box
PSP Code: 2.8.12.5.2.2
Local cryogenic system of SIS100
Items in the tunnel in Sects. 2,4 and 6
End box
Connection Box Arc end upnstream
Connection Box Arc end downstream
Bypass line 9 m section
Bypass line 12 m sections
Connection boxes
PSP Code: 2.8.12.3.1
PSP Code: 2.8.12.6.3
Bypass line 12 m section
to End-Box
PSP Code: 2.8.12.5.2.3
PSP Code: 2.8.12.6.1
PSP Code: 2.8.12.6.2
PSP Code: 2.8.12.5.2.1
PSP Code: 2.8.12.5.1
From resolution taken at the 5th Meeting
of the FAIR Council , 12. Dec. 2011
2.8.12.5 Cryogenic bypass line
2.8.12.6 Connecting Cryostat
2.8.12.6 Connecting Cryostat 2.8.12.3 Endboxes
2.8.12.12.1/2 Feed in cryostat
2.8.12.1/2 Feedbox 2.8.12.10 Current Lead boxes
2.4.12.2 Feedbox (without end-box integrated) for dipole stages 2.4.12.3 Feedboxes for Multiplet stages
2.4.12.4 Cryogenic transfer line in sections
2.4.12.1 Helium distribution box
Not shown:
WrUT – U. Jagiellonian contract - signed
4. December 2013
View – A Sectors 2, 4, 6
View – B Sectors 1, 3
View – C Sector 5
The elements of the test
string will be reinstalled in
sector 5.
WrUT – U. Jagiellonian contract - signed
4. December 2013, first elements in production
Connection Box Arc end upnstream PSP Code: 2.8.12.6.1
Bypass line 12 m section
to Feed-in-Box
PSP Code: 2.8.12.5.2.2
Magnet End Cap
Connection to Feed in
Line
SIS 100 Current Lead Box – in Resolution, not in WrUT - Jagiellonian contract
SIS 100 Feed Box - in Resolution, not in WrUT - Jagiellonian contract
Supersonducting link –neither in Resolution nor in WrUT - Jagiellonian contract
Feed-In Line - neither in Resolution nor in Jagiellonian contract
Bypass-line, Feed-In Cryostat, Connection Box – design ready, in production
WrUT – U. Jagiellonian contract - signed
4. December 2013, first elements in production
Bypass-line, Feed-In Cryostat, Connection Box –
design ready, in production
Vacuum external
envelope Radiation shield
Process pipes and busbars
Cross section of the BPL 9m Vacuum external envelope
Radiation shield
He supply VC
He supply
magnets
He return magnets
+ VC
He supply
shield
He return
shield
4 busbars pairs
Weak fixed support of the
process pipes
Sliding support of the
process pipes
Support of the thermal
shield
General view and cross section of the vacuum barrier and strong fixed support
Bypass-line, Feed-In Cryostat, Connection Box –
design ready, in production
Design verification – full 3D modelling
Geometrical model
Exemplary results
Design verification – thermal load
design
Exemplary results
Design verification – stress MPa
Exemplary results
Design verification – displacement of
process pipes - ready
Exemplary results
Heat transfer to process pipes -
BPL Cross section
Line B, He return
108x3, 4.3K
10 Layers of MLI
Line A2, He supply VC
32x2.0, 4.5K
10 Layers of MLI
Line A1, He supply mag.
54x2.0, 4.5K
10 Layers of MLI
Line C, He supply shield
42.4x2.0, 50K
10 Layers of MLI
Line D, He return shield,
42.4x2.0, 80K
No MLI !!!
Thermal shield, Al.
350x5, 80K
30 Layers of MLI
Thermal shield
supports (hangers)
Process pipes
sliding support
Bus bars
Vacuum vessel
427x5
Location of the process pipe supports
Fixed supports
Sliding supports +
thermal shield hangers
Fixed supports heat transfer
Fixed supports heat transfer
Heat conduction path to Line D 80K
Fixed supports heat transfer
Heat conduction path to Line D 80K
Heat conduction path to 4K Lines Heat conduction path to 4K Lines
Heat conduction path to Line D 80K Heat conduction path to Line D 80K
Fixed supports heat transfer – boundary
conditions
Fixed supports heat transfer –
temperature distribution
Fixed supports heat transfer – heat flux
distribution
Fixed supports heat transfer – summary
Line Heat flow, W
A1, 54x2mm – 4,5 K 0,637
A2, 32x2mm – 4,5 K 0,522
B, 108x3mm – 4,3 K 1,01
C, 42,4x2mm – 50 K 0,106
D, 42,4x2mm – 80 K 6,8
Lower right corner electrical feedthrough – 4,5K 4,31∙10-2
Lower right corner electrical feedthrough – 4,5K 4,51∙10-2
Upper right corner electrical feedthrough – 4,5K 8,98∙10-2
Upper right corner electrical feedthrough – 4,5K 7,73∙10-2
Upper left corner electrical feedthrough – 4,5K 6,09∙10-2
Upper left corner electrical feedthrough – 4,5K 3,72∙10-2
Lower left corner electrical feedthrough – 4,5K 3,62∙10-2
Lower left corner electrical feedthrough – 4,5K 2,06∙10-2
Sliding supports heat transfer –
temperature distribution
Sliding supports heat transfer – heat flux
distribution
Sliding supports heat transfer – summary
Line Heat flow, W
A1, 54x2mm – 4,5 K 0,54
A2, 32x2mm – 4,5 K 0,54
B, 108x3mm – 4,3 K 1,05
C, 42,4x2mm – 50 K - 0,17
D, 42,4x2mm – 80 K - 1,05
Summary of the heat transfer to the BPL
process lines
Comments:
For 4K lines, Q_MLI=0.1 W/m2
For 80K (Thermal Shield), Q_MLI= 1 W/m2
Pipe length: 7.05
For Line A1, A2, C, D: Q_tot=2*Q_slid_supp+2*Q_fix_supp + Q_MLI
Q_MLI for D Line is calculated as insulation heat transfer to the thermal shield
For Bus Bar: Q_tot = Q_fix_supp + Q_MLI
For Line B: Q_tot=2*Q_slid_supp+2*Q_fix_supp + Q_MLI+ 4* Q_tot(Bas Bar)
Line D A Q_MLI Q_slid_supp Q_fix_supp Q_tot qL Criteria
mm m2 W W W W W/m W/m
A1, 4.5K 54 1,20 0,12 0,54 0,64 2,48 0,35 0,5
A2, 4.5K 32 0,71 0,07 0,54 0,52 2,19 0,31 0,5
B, 4.3K 108 2,39 0,24 1,05 1,01 4.82 0,68 0,5
C, 50K 42,4 0,94 0,09 -0,17 0,11 -0,02 0,00 0,5
D, 80K 42,4 0,94 7,75 -0,14 6,8 21,07 2,99 2,5
Bus-bar 30 0,66 0,07 0,00 0,05 0,12 0,02 0,5
In case of the Line B and D, the heat
transfer to those pipes per their length
(qL) are higher than the specified value
(Criteria). Nevertheless, it should be
pointed out that the results presented
in the Table 1 are related to the
relatively short and complex BPL
modules. For the whole By-pass line
length, the qL to the corresponding
process line is expected to be lower
than criteria values.
28
G10, G11 high dielectric constants (ε~5)
Creates parasitic capacity
Other material possible? PEEK (ε~3),
Polyamide
Two SS half shells need to be electrically
insulated from each other
Welding ?, clamping ?
Bus bar – Eddy currents and cross talkin
analysis - ready
Eddy Current Loss in Outer Shell - results
Busbars support - prototyping
G 10 support
Superconducting cable External support
Internal structure of busbars support
Preliminary Design Review of BPL B50, BPL P50,
V B50 elements and their integration into test rig
From the: Minutes of the PDR meeting concerning design of the test rig
composed of BPL B50, BPL P50 and V B50 elements:
Date and place of PRD meeting
2014-10-13, time: 9:15 am - 3:00 pm, Wrocław University of Technology,
Participants: GSI (Peter Spiller, Thomas Eisel, Holger Kollmus, Jorge
Ceballos), WrUT (Maciej Chorowski, Marian Ciszek, Artur Iluk, Jarosław
Poliński, Kazimierz Malcher, Stanisław Trojanowski, Paweł Duda, Agnieszka
Pelc), Kriosystem Ltd (Piotr Grzegory).
Conclusions:
The meeting participants have unanimously approved the Preliminary Design
of the following elements BPL B50, BPL P50, V B50 elements and their
integration into test rig.
Extension of in-kind resolution as
proposed by GSI and WrUT
WrUT proposal
Local cryogenic system of SIS100
Items at the niches
Feed in line
Feed box
Feed in line box
Superconducting
Cold Links
Distrybution box
Current lead box
Transfer line
PSP Code: 2.8.12.1
PSP Code: 2.8.12.11
PSP Code: 2.8.12.5.2.2
PSP Code: 2.8.12.10
PSP Code: 2.8.12.9
No Local Cryogenics Item
No Local Cryogenics Item
Conclusions
1. The design process of SIS 100 local cryogenics elements is in progress.
2. The production of the elements foreseen to be first used in the Test String
has started. The elements will be ready for installation in April 2015
3. WrUt is ready to extent the in-kind contribution according to the proposal
from GSI
Thanks to: Eugeniusz Rusinski, Artur Iluk, Kazimierz Malcher, Jaroslaw
Polinski, Pawel Duda, Piotr Grzegory, Marian Ciszek, Stanislaw Trojanowski
and others