Upload
others
View
11
Download
0
Embed Size (px)
Citation preview
OUTLOOK
Brief description of the RF power project & Summary
Building BAF3
Power systems
Transmission Lines
Cavities
FPC
Tunnel Integration
Conclusion
21 May 2109 [email protected] 2
DESCRIPTION OF THE PROJECT
First definition of the project (2011)
Four to become six Travelling Wave Cavities
Four existing amplifiers upgraded to 1.05 MW* feeding four cavities
Two New power amplifiers delivering 1.4 MW* to two cavities (became 1.6 MW* in 2015)
A new building
A new SPS-LSS3 layout
*All RF power levels being peak power operating with a duty cycle at 50% at 42 kHz or 172 kHz
21 May 2109 [email protected] 3
Available RF voltage as a function of Irf
Courtesy Elena Chapochnikova
DESCRIPTION OF THE PROJECT
Three main sub-tasks
New RF Building project
Cavities re-arrangement project
RF Power Amplifiers project
21 May 2109 [email protected] 4
RF amplifier
1 mW
Coaxial transmission line
150 meters
Accelerating cavity
1.7 MW
RF amplifier
1 mW
Accelerating cavity
1.7 MW
New RF Building
DESCRIPTION OF THE PROJECT
New RF Building project
Cavities re-arrangement project
LSS3
Coaxial lines
Cavities
Fundamental Power Couplers
RF Power Amplifiers project
Present amplifiers upgrade
New amplifiers
21 May 2109 [email protected] 5
New RF Building project
RF BE/RF Eric
BE Space Management BE/ASR Paula
Safety DGS/SEE Enrico
Ventilation and cooling EN/CV Mauro
Electrical Network EN/EL Joël
Transport EN/HE Keith
Integration EN/MEF Yvon
Alarms GS/ASE Christophe
Civil Engineering GS/SE Natasha
New RF Power Amplifiers project
Power BE/RF Eric
LLRF BE/RF Wolfgang, Philippe
Controls BE/RF Andy
HVPS TE/EPC David
Cooling (air/water) EN/CV Mauro
Diacrode
Los AlamosJohn
MICE Andy
SSA
SOLEIL Patrick
TTI (Spain) José
Tetrodes
Thales,E2V EU
CPI, L3comUSA
Thoshiba Japan
Cavities re-arrangement project
RF
Coaxial lines BE/RF Eric
New couplers BE/RF Eric
Spare sections BE/RF Eric
Dampers (LSS2-LSS3) BE/RF Wolfgang
Pickups BE/RF Thomas
Optics BE/ABP Gianluigi
Safety DGS/SEE Enrico
Cooling EN/CV Mauro
Transport EN/HE Catherina
Integration EN/MEF Yvon
Vacuum TE/VSC Miguel
OUTLOOK
Brief description of the RF power project & Summary
Manpower
Schedule
Budget
Building BAF3
Power systems
Transmission Lines
Cavities
FPC
Tunnel Integration
Conclusion
21 May 2109 [email protected] 6
MANPOWERA lot of people from many teams ! (more than 160 directly involved)
All teams involved know the requested manpower regarding their activities
21 May 2109 [email protected] 7
Dep-Group Persons
BE-RF
Eric Montesinos, Charles Julie, Frederic Killing, Sébastien Calvo, Gino Cipolla, Antoine Boucherie, Simon Rains, James Bibby, Christophe Renaud, Cedrick Grandbois, Pilar Parrado Caballero, Irene
Alonso Romero, Francisco Sauba Esteban, Morgan Wigham, Julien Novello, Sebastien Mutuel, Patrice Girod, Michel Ferrone, Jean-Marie Angonin, Romuald Terry, Sidi Chikhi, David Bastard, Lancelot
Brechignac-Denis, Thomas Henry, Elena Shaposhnikova, Thomas Bohl, Christine Vollinger, Nasrin Nasresfahani, Patrick Kramer, Rama Calaga, James Mitchell, Wolfgang Höfle, Philippe Baudrenghien,
Gregoire Hagmann, Luca Arnaudon, Carlos Oliveira, Diego Barrientos Turrion, Emile Grospelier, Thomas Kaltenbacher, Ester Sancho Cabrera, Débora Aguilera, Jose Enrique Varela Campelo, Paola
Mazzotta, Toon Roggen, Urs Wehrle, Philip Hofer
BE-ABP Benoit Salvan, Hannes Bartosik, Ghislain Roy, Yannis Papaphilipou
BE-ASR Marc Tavlet, Christelle Gaignant, Anne Funken, Lisa Kobzeva, Axelle Deleu, Paola Carvalho Correia
BE-BI Christian Boccard, Patrick Ogier
BE-ICS Denis Raffourt
BE-OP James Ridewood
DG-LS Florence Jacobs
HSE-SEE Olivier Tison, Cécile Pinto, Jonathan Gulley, Laurent Colly, Guillaume Fontana
IPT-PIThierry Lagrange, Anders Unnervik, Ivo Lobmaier, Bjorn Jenssen, Fatima Najeh, Dante Gregorio, Laszlo Abel, Sandrine Magnan, Nordine Azizi, Alexandre Tabary, Sandra Benoit-Godet, Boi-Lan
Nguyen-Lemoine
IT-CS Stephane Casenove
EN-ACE Katy Foraz, David McFarlane, Emmanuel Paulat, Patrick Bestmann, Julie Coupard, Sonia Bartolome Jimenez, Bertrand Nicquevert, Simon Cherault, Tobias Dobers, Yannick Beraud
EN-CV Mauro Nonis, Serge Deleval, Michele Battistin, Alexandre Broche, Mathieu Archambau, Bill Bannister, Glen Mason, Aurelio Berjillos Barranco, Michel Obrecht
EN-ELNicolas Bellegarde, Guillaume Gros, Nuno Dos Santos, Thierry Bourrel, Jean-Claude Guillaume, Stefano Bertolazi, Georgy Georgiev, Gerardo Velasquez Gutierrez, Joel Lahaye, Denis Ribiollet,
Simon Baird, Gérard Cumer, Davide Bozzini, Jérôme Pierlot, Juan Gomez, Thierry Octave, Christophe Crombez, François Duval, Jean-Pierre Sferruzza
EN-HECaterina Bertone, Jean-Baptiste Bonnamy, Pascal Brunero, Serge Pelletier, Yann Seraphin, Patrick Vallet, Gilles Roche, Helder Lorenco, Roberto Rinaldesi, Jean-Pierre Grandchelli, Jean-Louis
Grenard
EN-MEF Yvon Muttoni, Frédéric Galleazzi, Scharif Mehanneche, Antoine Kosmicki
EN-MME Gilles Favre, Stefano Sgoba, Alessandro Dallocchio, Jean-Marc Malzacker, Laurent Deparis, Alession D’Andrea, René Claret, Thierry Tardy, Pierre Moyret, Laurent Prever-Loiri, Jean-Marie Geiser
SMB-SE Luz-Anastasia Lopez-Hernandez, Christophe Biot, Laurent Faisandel, Mathieu Fontaine
TE-EPC Jean-Paul Burnet, Gilles LeGodec, Davide Aguglia, Karsten Kahle, Christophe Coupat, Clément Bovet
TE-MSC Jérémie Bauche
TE-VSC Paolo Chiggiato, Antonio Mongelluzzo, Sergio Calatroni, Wilhelmus Vollenberg, Ciara Pasquino, Jose Ferreira Somoza, Antonio Mongelluzzo
SCHEDULE
21 May 2109 [email protected] 8
OUTLOOK
Brief description of the RF power project & Summary
Building BAF3
Power systems
Transmission Lines
Cavities
FPC
Tunnel Integration
Conclusion
21 May 2109 [email protected] 9
BAF3
Design completed by end of October 2011 to allow Civil engineering studies and authorisation requests to be launched
Goal to have the bare building completed by end 2014 (taking advantage of LS1 to minimize accident impacting SPS operation during construction)
Even if we did not know what amplifier technology will be selected !
21 May 2109 [email protected] 10
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Bare building
BAF3
Point 3 is the best area even if we need a new building
New building between BA3 and BB3 in front of 929 RF workshop :
Ground floor
20m x 25m = 500 m2
Mezzanine:
10m x 25m = 250 m2
21 May 2109 [email protected] 11
RF workshop
Siemens
Philips
800 MHz
Faraday Cage
New RF building
BAF3
Amplifier tendering process opened to several technologies
2 x 16 tetrodes (well known)
2 x 2048 SSPA (Solid State Power Amplifiers)
4 x Diacrodes (new tube)
4 x IOT (Inductive Output Tube, almost new)
Answer of the selected technology (volume needed) after the building approval
Hybrid combiners and coaxial lines will be similar to the ones in use with present systems
21 May 2109 [email protected] 12
4.7 m4.7 m
2.3 m
4 tours (320 kW) = 33 m2
LVPS = 72 m2
total 64 towers = 600 m2
1 tube (160 kW) = 4 m2
HVPS = 192 m2
Total 32 tubes = 320 m2
Total combiners = 200 m2
Total combiners = 200 m2
Courtesy
Patrick Marchand
(SOLEIL)
BAF3
All main RF equipment around
Close to RF workshop
Take advantage of ‘nearly empty’ GT10 gallery to install 350 mm RF coaxial transmission lines Easiest path to the pit
Access through 929 RF workshop
Reserved area for BB3 transformers if needed in the future to replace oil transformers to
cast resin transformers
21 May 2109 [email protected] 13
Reserved area for
new BB3 transformers
28m x 4m
BAE3 Philips
BA3 Siemens
RF Faraday Cage
BB3
800 MHz
929 RF
workshop
BC3 New RF Amplifiers
GT10 Gallery
BAF3
Total surfaces:
Basement : 19.5 m x 36.5 m = 710 m2
Mezzanine : 475 m2
Total = 1185 m2
Total surfaces for RF:
Basement = 550 m2
Mezzanine = 475 m2
Total = 1025 m2
21 May 2109 [email protected] 14
36.5 m
19.5 m
BAF3
2011 Integration studies completed
2012 Enquiry ‘Etude Genie Civil’ sent out
2013 Construction
2014 Bare building delivered
2015 Ready for services integration
21 May 2109 [email protected] 16
OUTLOOK
Brief description of the RF power project & Summary
Building BAF3
Power systems
New amplifiers
Present amplifiers upgrade
Transmission Lines
Cavities
FPC
Tunnel Integration
Conclusion
21 May 2109 [email protected] 17
NEW SYSTEMS 2 x 2.0 MW @ 200 MHZ
21 May 2109 [email protected] 19
One line
(input cavity ~120 to 180 m away) From Beam Control
1.6 MW at cavity input
4 stages of 3 dB combiners = - 0.6 dB
120 to 180 m Coaxial lines = - 0.2 dB
Final Amplifier output = 1.6 MW + 0.8 dB = 2.0 MW / 16 = 125 kW
1/16 splitter
Three contracts
Drivers :
2 x 16 x SSPA
Finals :
Tetrode : 2 x 16 x 110 kW
IOT : 2 x 16 x 110 kW
SSPA : 2 x 16 x (110 x 1 kW)
Diacrode : 2 x 2 x 850 kW
No klystron at 200 MHz
Combiners + lines :
3 dB hybrids
850 kW power loads
PURCHASING STRATEGY
Two contracts
IT-3842 Drivers
IT-3841 Finals
A first contract for the Drivers (IT-3842)
SSPA only (best technology for a few kW amplifier)
Will be a first input for a predefined cost for the Finals
Combining systems
Done in house or subcontracted
Will be a second input for a predefined cost for the Finals
Once Drivers contract adjudicated, a second contract for the Finals
Drivers IT-3842 cost
+ Combiner cost (defined by CERN)
+ Finals IT-3841 offer
_______________________________________
IT-3841 adjudication to the lowest compliant
21 May 2109 [email protected] 20
IT-3842, DRIVERS
72 companies consulted
20 selected
10 offers
Defined a 1.25 kW unit Compatible with all Finals technologies
32 for SSPA & IOTS, 256 for Tetrodes, 192 for Diacrodes
12 pre-series for qualification (end of contract clause in case of any failure without any payment)
One to six batches of 50 (total 62 to 312) regarding result of future Finals IT-3841
TTI Norte, Spain, awarded the contract (3.7 €/W)
21 May 2109 [email protected] 21
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
November 2011 March 2014
Consulted
Selected
0
5
10
15
20
25
30
Sp
ain
Ita
ly
Sp
ain
Germ
any
Ita
ly
Franc
e
Ita
ly
Franc
e
Belg
ium
Isra
el
€ / W peak
IT-3842, DRIVERS
RF design is impressively robust
Double circulators !
Sustained the CERN Fast Short-Circuit test !
Successfully performed the 1000 hours test with five units (not a single failure)
Many broken transistors after 6 months of operation (first half 2017)
Very quick reaction of the company (TTi Norte, Spain) that repaired at no cost all the already produced units
64 units in operation since mid-2017 without very few failures !
300 units total delivered and successfully tested
21 May 2109 [email protected] 22
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
November 2011 March 2014
August 2015
IT-3842, DRIVERS
RF design is impressively robust
Double circulators !
Sustained the CERN Fast Short-Circuit test !
Successfully performed the 1000 hours test with five units (not a single failure)
Many broken transistors after 6 months of operation (first half 2017)
Very quick reaction of the company (TTi Norte, Spain) that repaired at no cost all the already produced units
64 units in operation since mid-2017 without very few failures !
300 units total delivered and successfully tested
21 May 2109 [email protected] 23
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
November 2011 March 2014
August 2015
IT-3842, DRIVERS
RF design is impressively robust
Double circulators !
Sustained the CERN Fast Short-Circuit test !
Successfully performed the 1000 hours test with five units (not a single failure)
Many broken transistors after 6 months of operation (first half 2017)
Very quick reaction of the company (TTi Norte, Spain) that repaired at no cost all the already produced units
64 units in operation since mid-2017 without very few failures !
300 units total delivered and successfully tested
21 May 2109 [email protected] 24
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
November 2011 March 2014 January 2017
September 2017
2020201920182017
IT-3841, FINALS
Technical Specification to be finalized taking into account Drivers outcome
Power level request increased
Cavity 1.4 to 1.6 MW
Amplifier from 1.6 to 2.0 MW !
21 May 2109 [email protected] 25
2011 2012 2013 2014 2015 2016
December 2014
Drivers
TSMS TS
IT-3841, FINALS ADDITIONAL COSTS
Drivers IT-3842 cost 5500 CHF per 1.25 kW unit
SSPA & IOT 176 kCHF
Tetrodes 1’408 kCHF
Diacrodes 1’056 kCHF
Combiner cost (defined by CERN) SSPA & IOT 2’760 kCHF
Tetrode 3’160 kCHF
Diacrode 800 kCHF
Total additional cost per technology SSPA & IOT 2’936 kCHF
Tetrode 4’568 kCHF
Diacrode 1’856 kCHF
21 May 2109 [email protected] 26
IT-3841, FINALS BIDDERS CONFERENCE
Defined the scope of the contract being as fair as possible regarding the
technology
Defining a quite costly Demonstrator in order to disqualify ‘non serious’ companies (we do not want to be R&D at low cost)
Not a single CHF paid in case of failure of the demonstrator
Taking into account tubes on an as long as possible period (over 5 years)
Including spares in order to operate during 20 years
Answered 102 questions from the suppliers
21 May 2109 [email protected] 27
20202019201820172011 2012 2013 2014 2015 2016
20 January 2015
IT-3841, REQUIREMENTSRequirements Integration within the given building
Repetition rate 0.1 Hz to 500 kHz (require a CW and a pulsed amplifier)
Full reflection all phases 100 ms (equivalent to 4 time the power level along the lines)
Non conventional way to measure the BW (required by LLRF and TWC)
Very good linearity
Two tone at many power levels
A lot of tests to qualify the Finals Supercycle test, short circuit test, BW, linearity, …
Short duration tests to qualify an Amplifier within one week
Long duration tests to check reliability within one month
21 May 2109 [email protected] 28
2020201920182017
IT-3841
74 companies consulted
19 selected
8 declined
7 offered
No discussion about the Drivers neither the combiners costs
21 May 2109 [email protected] 30
2011 2012 2013 2014 2015 2016
Consulted
Selected
Unable to submit a competitive bid due to quantity being beyond our production capacity and we could not provide installation support
Dear all, We are sorry but we are not able to finish every documents within deadline. So we must decline to participate with our offer. Thank you for your opportunity. Best regards
We are not on time with the documents required
We believe that the chances are too low to get the contract by bidding Solid State Amplifier solutions. Additionally, the known dumping price structure of competitors in the field of Solid State Amplifiers, which get development provided free of costs by public institutes (already known due to the preceding call for tender for preamplifiers of the same frequency) also makes the chance to win the bid too small for the required work load for bid preparation
13 March 2015, bids opening
IT-3841
74 companies consulted
19 selected
8 declined
7 offers
March 2015 lowest bid is Thales Communication & Security for 8.002 MCHF
Very careful verification of the offer
September 2015 CERN FC approval
21 May 2109 [email protected] 31
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
13 March 2015, bids opening
Consulted
Selected
0
5
10
15
20
SSPA
- F
R
Dia
crode -
CH
/FR
Dia
crode -
FR/SP
SSPA
- S
P
SSPA
- S
P
Tetr
ode -
SP
SSPA
- G
B
€ / Wpeak
Offered17 September 2015, FC approval
1.75 €/Wp
(2019 rates)
IT-3841, FINALS
One Transmitter will be composed of
16 x 150 kW RF amplifiers
One RF amplifier will be composed of
2 x 40:1 cavity combiner
One Cavity combiner will be composed of
40 x 1 kW RF blocs
In total
Two transmitters
32 RF amplifiers
64 cavity combiners
5120 RF blocs
21 May 2109 [email protected] 32
2 x 16 x 150 kW
RF Amplifiers
IT-3841, SCHEDULE
21 May 2109 [email protected] 33
20202019201820172016
Contract
FC Sep 15 Start contract negotiation
8 weeks Nov 15 Contract signed
10 weeks Feb 16 Design Report
36 weeks Sep 16 Demonstrator FAT report completed
44 weeks Nov 16 Demonstrator SAT report
94 weeks Oct 17 1st Transmitter SAT report
120 weeks Apr 18 2nd Transmitter SAT report
144 weeks Oct 18 All spares delivered
DR
Demonstrator FAT
Demonstrator SAT
1st Transmitter SAT
2nd Transmitter SAT
Ready for LLRF
TRUE LIFE
21 May 2109 [email protected] 34
20202019201820172016
#10 Demonstrator SAT
1st Transmitter SAT
2nd Transmitter SAT
Ready for LLRFFirst Demonstrator SAT
20202019201820172016
Contract
DR
Demonstrator FAT
Demonstrator SAT
1st Transmitter SAT
2nd Transmitter SAT
Ready for LLRF
VISIT AND TECHNICAL DETAILS
Several technical details are still under a NDA
I will answer your questions during the visit as much as within the respect of the NDA
Thanks for your visit to CERN
21 May 2109 [email protected] 35