Liquid Soil Book

Embed Size (px)

Citation preview

  • 7/29/2019 Liquid Soil Book

    1/41

    LI QUI D SOI L

    SOI LCON Ltd. 21, Villiers Road SOUTHSEA PO5 2NR United Kingdom E-mail: [email protected] +44 (0)2392756166

    Green

    Respectful

    Sustainable

  • 7/29/2019 Liquid Soil Book

    2/41

    Liquid Soil is a construction material which is flowable during installationand which may be produced from nearly any kind of excavated material

    ApplicationsLiquid Soilmay be used in most backfill situations, such as filling utility or service trenches, backfilling excavationson construction sites, filling voids, tunnels and galleries and use on site requiring large quantities of material.

    Liquid Soil also offers the possibility of hanging its properties to suit the individual application requirements.

    PropertiesFlowable

    Pumpable

    Self-compacting

    May be laid under water

    No settlement

    No crowning

    Use of most type of soil and recycled

    aggregate possible

    Can be topped quickly

    Can be excavated again easily

    Gas permeable

    Mitigates vibration

    Non-toxic, non-hazardous

    Easy to produce and handle

    Liquid

  • 7/29/2019 Liquid Soil Book

    3/41

    AdvantagesQuicker completion with lower labour requirementsReduction of volumes handled

    Lower space requirements

    Improved operator safety

    No compaction in wet trenches

    Quality management gives defined properties

    Allow gas leaks to be detected

    Good bedding properties, leading to long-lasting service networks

    Homogeneous ground reinstatement avoids discontinuities

    Removable with a hand spade

    No Compaction damage may used with all types

    of pipe materials

    Technical dataDensity: 1.6 2.1 T/m3Compressve strength: 28 days= 0.2 - 0.8 N/mm2Deformation value (EV2): >45 N/mm2 (28 days)Permeability: 10-5 10-10 m/s

    Impermeable barrier against water movement Vibration mitigation against road traffic

    Road base Structural backfill Ability to fill deep trenches Slope stabilisation

    Fixed-plant Installation

    Mobile-plant Installation

    LiquidAreas of applications

    SOI LCON Ltd. CONSULTI NG & TRAI NI NG

    21, Villiers Road SOUTHSEA SERVI CE & TRADI NG

    PO5 2NR United Kingdom CONSOLIDATI ON WORKS

    + 44 (0)2392756166

    E-mail: [email protected]

    1 2

    3 4 5 6

  • 7/29/2019 Liquid Soil Book

    4/41

    SOI LCON Ltd . CONSULTI NG & TRAI NI NG

    21, Villiers Road SOUTHSEA SERVI CE & TRADI NGPO5 2NR United Kingdom CONSOLI DATI ON WORKS + 44 (0)2392756166

    E-mail: [email protected]

  • 7/29/2019 Liquid Soil Book

    5/41

  • 7/29/2019 Liquid Soil Book

    6/41

  • 7/29/2019 Liquid Soil Book

    7/41

  • 7/29/2019 Liquid Soil Book

    8/41

  • 7/29/2019 Liquid Soil Book

    9/41

  • 7/29/2019 Liquid Soil Book

    10/41

  • 7/29/2019 Liquid Soil Book

    11/41

  • 7/29/2019 Liquid Soil Book

    12/41

  • 7/29/2019 Liquid Soil Book

    13/41

  • 7/29/2019 Liquid Soil Book

    14/41

  • 7/29/2019 Liquid Soil Book

    15/41

  • 7/29/2019 Liquid Soil Book

    16/41

    LI QUI D SOI L FOR

    TELECOMMUNI CATI ONTRENCHES

    Liquid Soil is a material which can be produced from nearly all type of excavated material and used in

    site, such as for example in the case of a trench in urban site for the installation of

    Telecommunication wires or services.

    In this case Liquid Soil become a rapid and easy way to use a discharge product - reducing drastically

    the stand-by time and installing of the undertaken services- in a sustainable way!

    The following picture sequence shows how an existing bicycle path/sidewalk made with slip bricks,can be opened and rebuilt in an easy wayas nothing happened!

    The mixed soil obtained with Liquid Soil becomes hard in a few hours avoiding all dangerous and badeffects of the natural subsidence of t he traditional refilling methods.

    The use of small equipment (installed on mini-excavator or mini-dumper) is more suitable for small

    works where the agility is priority and spaces are small.In case of big quantity of treated soil with high daily production, the use of bigger equipment with

    concrete mixer truck is required.

    1. Slip br icks are removed and excavation executed

    SOI LCON Ltd. CONSULTI NG & TRAI NI NG

    21, Villiers Road SOUTHSEA SERVI CE & TRADI NGPO5 2NR United Kingdom CONSOLIDATI ON WORKS + 44 (0)2392756166

    E-mail: [email protected]

  • 7/29/2019 Liquid Soil Book

    17/41

    2. Plast ic hoses and cables are install ed

    3. Excavated soil is mix ed w it h liqui d soil and poured in t he opened tr ench

  • 7/29/2019 Liquid Soil Book

    18/41

    4. Liquid soil mat erial is hardening

    5. The orig inal slip br icks design is restored.

  • 7/29/2019 Liquid Soil Book

    19/41

    6. The bicycle path/ sidew alk is again in service

    Simple, quick, sustainable!

  • 7/29/2019 Liquid Soil Book

    20/41

  • 7/29/2019 Liquid Soil Book

    21/41

    Backfill using RSS Liquid Soil

    Much reduced construction time using RSS Liquid Soil

    Sewer ConstructionInstallation under congested conditions of a large diameter

    The Challenge

    The Solution

    LOGIC developed a technical solution for Karl Krumpholz Rohrbau GmbH,

    who used the properties of RSS Liquid Soil in such a way that the specified

    load could be achieved without an expensive reinforced concrete trench bed.

    This solution was put into place as an amendment by Karl Krumpholz Rohrbau

    GmbH. The project was completed to the client's satisfaction within time and

    on budget.

    In Bamberg a 2000 mm main sewer had to be installed in the Jckstrae

    whilst maintining single lane traffic. Because of the 6-7 m depth, sheet piling

    trench support was used which in turn called for an expensive concrete trench

    bed. In order to minimise the trench width, partial backfill with RSS Liquid

    Soil was specified since it would otherwise not have been possible to finish

    construction within the time allowed.

    Construction Period

    07.2007-10.2007

    ContractorKarl Krumpholz Rohrbau GmbH

    ClientEBB Entsorgungs- und Baubetrieb

    der Stadt Bamberg

    ProjectBamberg-Jckstrae

    sewer in an open-cut trench using sheet piling

  • 7/29/2019 Liquid Soil Book

    22/41

    No disruption to traffic flows

    Float-laying a sewer using RSS Liquid Soil

    Sewer ConstructionFloat-laying a sewer in difficult ground conditions

    The Challenge

    The Solution

    RSS Liquid Soil and the use of RSS pipe-laying acessories with floating pipe

    supports with no fixed connection to the soil bed. This gives consistent soil

    conditions which isolate the installed pipes from the heavy trafic loading and

    avoids long-term differential settlement.

    Installation of a wastewater pipe in very difficult, unstable ground sensitive to

    vibration with up to 7 m peat soil at the entrance to the port area of Lbeck.

    The area is intensively trafficked by heavy lorries. Avoidance of subsidence

    and the production of made ground with similar bearing properties to eventual

    nearby road construction particularly in the pipe trench area.

    Construction Period03.2007-04.2007

    ContractorBaugesellschaft Bergemann + Grper

    GmbH & Co. KG

    ClientEntsorgungsbetriebe Lbeck

    ProjectLbeck-Frankfurter Strae

  • 7/29/2019 Liquid Soil Book

    23/41

    Sewer ConstructionBackfill in the road and pavement area

    The Challenge

    The Solution

    RSS Liquid Soil allows all voids in these areas to be backfilled without

    subsidence or shrinkage without using mechanical compaction. Damage

    may be reliably avoided and the backfilled pipes remain accessible at

    any time.

    Backfilling around a multiplicity of crossing cables and conduits in an extremely

    congested space. Conventional compaction would probably lead to subsequent

    subsidence or impact damage.

    Backfill with RSS Liquid Soil is void-free

    Conventional compaction not possible

    Construction Period04.2007

    ContractorWolff & Mller GmbH & Co. KG

    ClientBerliner Wasserbetriebe

    ProjectBerlin-Thaerstrae

  • 7/29/2019 Liquid Soil Book

    24/41

    Screening the trench arisings to produce R Liquid SoilSS

    Backfill using Liquid SoilRSS

    Sewer ConstructionLaying a combined 500 mm sewer

    The Challenge

    The Solution

    Comprehensive trials resulted in the possibility of incorporating this material

    into RSS Liquid Soil, used to backfill the trench. Not only was replacing the

    soil avoided, but below-ground consistency was restored, reliably avoiding

    differential subsidence.

    As forecast in the soil investigation, blue clay with up to 20 percent by volume

    organic inclusions was encountered. Using traditional methods, all this material

    would have been disposed of in a landfill.

    Construction Period10.2005

    ContractorZMOOS AG

    ClientAJS Ingenieurs civils SA

    ProjectThielle Wavre/Switzerland

    DesignAJS Ingenieurs civils SA

  • 7/29/2019 Liquid Soil Book

    25/41

    RSS

    Manholes tailor-made for the project

    Laying pipes in a narrow trench using RSS Liquid Soil

    Sewer ConstructionInstallation of a separate sewer system and a water main

    The Challenge

    The Solution

    The use of Combi-Manholes, specially designed to accomodate local

    hydraulic conditions, allowed all the associated pipework to be laid and

    backfilled in a trench only 1.25 m wide including shuttering. Since the backfill

    was carried out using Liquid Soil, fast and efficient construction under

    optimum bedding conditions became possible and the planned removal of

    excavated soil was avoided. This resulted in large cost savings and minimal

    environmental impact.

    RSS

    RSS

    The project called for complete replacement of the drainage and wastewater

    service lines as well as of the mains drinking water supply, under very

    congested conditions in poor soil.

    Construction Period05.2005-10.2005

    ContractorFrank Schfer GmbH

    Straen- und Tiefbau

    ClientAZV Nebra, Vitzenburg

    ProjectVitzenburg-Cross-town link Liederstdt

  • 7/29/2019 Liquid Soil Book

    26/41

    Sewer Construction

    The Challenge

    The Solution

    The underground tank was bedded free of subsidence using Liquid Soil.

    Damage to the tank insulation and corrosion layers could be effectively excluded

    due to Liquid Soil. The silty excavated clay soil was re-used.

    RSS

    RSS

    A rainwater reservoir in a new residential area designed for the stockpiling of

    rain water for use as grey water or by the fire services had to be backfilled.

    Construction Period05.2005

    ClientKnittlingen Municipality

    ProjectKnittlingen-Am Rmerweg

    Construction of a rain water reservoir

    ContractorAm Rmerweg Joint Venture

    Harsch GmbH & Co. KG

    Karl Heinrich Bauunternehmen GmbH

    Drrwchter & Friedrich GmbH

    Backfill using RSS Liquid Soil

    On-site production of RSS Liquid Soil

  • 7/29/2019 Liquid Soil Book

    27/41

    Using RSS Liquid Soil allows narrow trenches

    Mobile self-contained plant for the production of RSS Liquid Soil

    Sewer ConstructionRelocation of a combined sewer within the existing space

    The Challenge

    The Solution

    The backfill material was produced dust-free on-site by the first mobile mixing

    plant specially designed to handle RSS Liquid Soil. The machine was equipped

    with special accessories for use with the wheel loader. Quality control was

    provided by PROV who gave support during the construction phase to the

    complete satisfaction of the client.

    Construction was carried out close to surrounding residential property

    where RSS Liquid Soil needed to be produced on-site from the existing

    excavation. The client was therefore highly demanding in terms of environ-

    mental management of the site.

    Construction Period10.2004-07.2005

    ContractorKllmer GmbH & Co. KG

    Client

    Gttingen City Water Authority

    ProjectGttingen- David Hilbert Str./

    Beethovenstrae

  • 7/29/2019 Liquid Soil Book

    28/41

    Installing an RSS Manhole

    Backfilling an RSS with RSS Liquid Soil

    Manhole

    Sewer ConstructionInstallation of a separate sewer system

    The Challenge

    The Solution

    The use of RSS system components allowed the full possibilities designed by

    the planner to be realised despite cramped site conditions. The RSS Combi-

    Manhole allowed drainage and wastewater lines to be connected to a single

    manhole. The volume of excavated soil and the consequent space requirement

    was reduced by 60% in comparison to a traditional design.

    The separate sewer system was designed as a 1000 mm rainwater reservoir

    for use as grey water or by the fire services.

    Construction Period08.2004-10.2004

    DesignI-motion GmbH Ing.-Ges. Fr

    moderne Tiefbauorganisation

    ClientIlsfeld Municipality

    ProjectIlsfeld-Auenstein/Mhlrhein

  • 7/29/2019 Liquid Soil Book

    29/41

    Hoisting a large diameter pre-cast

    Sewer ConstructionLaying a large diameter sewer in an open-cut trench

    The Challenge

    The Solution

    The use of RSS Liquid Soil led to an optimum organisation of the construction

    site. Since quality limits had been certified by PROV from the very start, con-

    struction of the road base could be started a few hours after backfilling had

    finished. The use of RSS Liquid Soil ensures that no subsidence will occur

    and that the best bedding quality will be achieved.

    A main sewer had to be installed in Wlfrath without disruption to normal traffic

    flows. The construction time and working area had to be reduced to a minimum.

    Construction Period05.2004

    ContractorDieter Ehlhardt Tief- und Straen-

    bau GmbH

    ClientWlfrath Municipality

    ProjectWlfrath-Main Sewer

    Backfilling the trench using Liquid SoilRSS

    concrete sewer segment

  • 7/29/2019 Liquid Soil Book

    30/41

    Connecting the pipes to the RSS Manhole

    Sewer ConstructionInstalling a sewer system under congested conditions in

    The Challenge

    The Solution

    The combination of the RSS Manhole System and RSS Liquid Soil allowed

    us to develop a solution for our client which not only respected the design

    requests but also prevented damage to buildings and inhabitants by a

    vibration-free backfill.

    Sewerage, rain water, drinking water and electric lines had to be installed in

    very congested conditions amidst a number of historic buildings. It was

    important that all the lines be accessible for future maintenance.

    Construction Period10.2003-12.2003

    ContractorMeliorations-, Straen- und Tiefbau

    GmbH Laucha

    Client

    Laucha Wastewater Authority

    ProjectLaucha-Hallesche Strae

    a conservation area

    Complex service pipe layout -ideal for RSS Liquid Soil

  • 7/29/2019 Liquid Soil Book

    31/41

    Service Pipe ConstructionElectricity substation

    The ChallengeBackfill of difficult or normally inaccessible areas around electric cables whilst

    assuring the eventual dispersion of heat generated by the cables.

    Delivery of RSS Liquid Soil

    Backfilling electricity cables with RSS Liquid Soil

    The Solution

    RSS Liquid Soil was installed by concrete pump. The composition was

    optimised to ensure much greater heat dispersion compared to that of a

    conventional siliceous sand bed.

    Construction Period10.2006-12.2006

    ContrctorKrause & Co.

    Hoch- und Tiefbau GmbH

    Clientenvia m

    ProjectHerlasgrn-Transformer Station

    Weighting cables with RSS Liquid Soil (k )

    P Backfilling areas where access is difficultto avoid them floating to the surface

  • 7/29/2019 Liquid Soil Book

    32/41

    Service Pipe ConstructionConstruction at a gas and steam plant

    The Challenge

    The Solution

    The complex pipe layout was designed using the RSS System. Whilst

    maintaining high quality levels, fast construction was achieved by using

    RSS Liquid Soil as backfill.

    Complex, space saving site development at a power plant whilst maintaining

    normal output at the plant.

    Chemical Industrial Park Knapsack

    Backfilling an RSS Manhole with RSS Liquid Soil

    Construction Period09.2006-10.2006

    ContractorEd Zblin AG

    ClientSiemens AG

    ProjectCologne-Chemical Industrial Park

    Knapsack

  • 7/29/2019 Liquid Soil Book

    33/41

    Service Pipe ConstructionCreation of more above-ground space

    The Challenge

    The Solution

    By using RSS Liquid Soil the trench was backfilled without voids. The pipes

    are then installed in a material which leaves them free of strain and vibration.

    Release of land to developers required services to be laid. Reduction of theavailable trench width led to the demand for the optimum backfill.

    Narrow trenches permit normal traffic flow

    Optimum bedding properties are obtained for service lines backfilled with RSS Liquid Soil

    Construction Period06.2006 - 08.2006

    ContractorLeonhard-Weiss GmbH & Co. KG

    Client

    Energie Baden-Wrttemberg AG(EnBW)

    ProjectStuttgart-Katharinen-Hospital

    by grouping services lines

  • 7/29/2019 Liquid Soil Book

    34/41

    Prepared utilities trench

    Service Pipe ConstructionDistrict heating

    The Challenge

    The Solution

    RSS Liquid Soil was used for this district heating project. The material avoided

    the formation of annular gaps, achieved good contact between the pipe and

    RSS Liquid Soil backfill and avoided complex additional measures. All the

    properties of the backfill required for use with plastic-jacketed pipes were

    certified by the FFI Hannover research institute for district heating.

    Ensuring compatibility with the pipe materials and complete void-free

    surrounding of the pipes with no annular spaces left after the expansion/

    contraction cycle.

    Backfilling plastic-jacketed pipes with RSS Liquid Soil

    Construction Period10.2005

    ContractorSKANSKA Asfalt I/S

    Client

    local provider

    ProjectBors/Sweden

  • 7/29/2019 Liquid Soil Book

    35/41

    BackfillBackfilling inside a building

    The Challenge

    The Solution

    PROV provided a special recipe for backfilling large voids with RSS Liquid Soil

    which allowed it to be pumped without any problems whilst maintaining its

    self-levelling and self-compacting properties..

    Backfilling inside a sewage plant.

    Construction Period04.2007

    ContractorIngo Warnke Tief- und

    Rohrleitungsbau GmbH

    ClientWaren Municipality - Mritz-Water-/

    Authority

    ProjectMllenhagen-Sewage works

    Delivering RSS Liquid Soil

    Pumping RSS Liquid Soil into the building

  • 7/29/2019 Liquid Soil Book

    36/41

    Backfilling in layers

    RSS Liquid Soil backfill in contact with stainless steel

    BackfillBackfilling a stainless steel swimming pool

    The Challenge

    The Solution

    RSS Liquid Soil, which was designed to the special requirements of this

    application. Certification regarding chemical compatibility of RSS Liquid Soil

    with the pool material was quickly provided by PROV.

    Avoiding external stresses and other harmful effects on the swimming pool

    material (stainless steel) and ensuring optimum stablity by equalising loading

    on all sides though providing a backfill with consistent compressive strength

    despite the complex geometry of the load-bearing parts.

    Construction Period

    03.2007-04.2007

    ContractorGB Tiefbau GmbH

    Tief,- Kanal- und Straenbau

    ClientReichenbach Municipality

    ProjectReichenbach-Swimming Pool

  • 7/29/2019 Liquid Soil Book

    37/41

    Backfill with no subsidence

    Backfilling using RSS Liquid Soil delivered by concrete pump

    BackfillBridge abutment at the Sachsenring racetrack

    The Challenge

    The Solution

    RSS Liquid Soil was quickly put into place with the help of a 56 m concretepump with minimal personnel. All geotechnical requirements were more thanmet. Normal business at the Sachsenring was not interrupted.

    The client demanded that the bridge abutment had to be backfilled during

    normal racing and training operations at the racetrack within a certain time

    -frame determined by the project manager.

    Construction Period06.2006

    ContractorHeli-Bau GmbH

    Client

    Verkehrssicherheitszentrum amSachsenring GmbH & Co. KG

    ProjectSachsenring

  • 7/29/2019 Liquid Soil Book

    38/41

    BackfillBackfilling elevated tanks outside a waterworks

    The Challenge

    The Solution

    RSS Liquid Soil was installed with little call on machinery or personnel. As aresult, better final properties were achieved than those possible with traditionalmethods regarding density, the avoidance of subsidence and the absorption ofvibration. The task of a providing void-free backfill was properly carried out.

    Due to the complicated geometry of the structure, not every zone could be

    backfilled properly using traditional methods.

    Construction Period06.2006

    Krause & Co.Contractor

    Hoch- und Tiefbau GmbH

    ClientSdsachsen Wasser GmbH

    ProjectEinsiedel-Waterworks

    View of the site

    Using RSS Liquid Soil to backfill in zones with difficult access

  • 7/29/2019 Liquid Soil Book

    39/41

    BackfillFoundations backfill

    The Challenge

    The Solution

    Recycling of excavated soil through the use of led to a

    massive reduction of equipment and personnel whilst still achieving the

    level grade required.

    RSS Liquid Soil

    Backfill of block and strip footings to provide a level grade for the subsequent

    installation of the hall floor.

    View of the site

    Preparation of the hall floor using RSS Liquid Soil

    Construction Period08.2004

    ContractorTiefbau GmbH Weber

    ClientFerroform

    ProjectLeinefelde-Industrial Park

    Backfilling working areas

  • 7/29/2019 Liquid Soil Book

    40/41

    Backfilling using a concrete pump to deliver RSS Liquid Soil near an auxiliary bridge

    BackfillBackfilling a workspace between a concrete wall and sheet

    The Challenge

    The Solution

    Vibration-free installation was achieved by using RSS Liquid Soil. The backfill

    was confirmed free of voids without any subsidence or shrinkage.

    The workspace between a concrete wall and sheet piling had to be backfilled

    without compaction and free of vibration during normal operation of the railway.

    The material had to be pumpable over long distances.

    Construction Period06.2004

    ContractorIngo Warnke Tief- und

    Rohrleitungsbau GmbH

    Client

    Municipality Waren (Mritz)Bau- und Wirtschaftsfrderungsamt

    ProjectWaren (Mritz)

    piling at a former railway embankment

    Fast filling of the workspace

  • 7/29/2019 Liquid Soil Book

    41/41

    Backfilling with RSS Liquid Soil with no

    View of the backfill area

    BackfillAbsorption of vibration

    The Challenge

    The Solution

    On the basis of its excellent vibration absorption together with simple processing,

    RSS Liquid Soil fulfilled all requirements.

    A winding machine foundation had to be designed to avoid causing vibration

    damage to other machines. Because of tight time constraints, backfill using

    soil compacted in layers would not have been possible.

    Construction Period03.2004

    ContractorMelorations-, Straen- und

    Tiefbau GmbH

    ClientKartogroup

    ProjectLeuna

    segregation during pouring