Upload
william-ball
View
213
Download
0
Embed Size (px)
Citation preview
Lidar distribution system for OLC lidar
Rudie Watzig, Senior GIS AnalystOregon Dept. of Geology and Mineral Industries
Framework Review Committee, April 29th, 2015
Oregon Lidar Consortium:
Framework Review Committee, April 29th, 2015
• $16.4 million collected from 64 unique partners for 32,841 square miles of lidar data.
• 25,800 square miles has been completed.• DOGAMI expects to collect an additional 3,932 square miles of data in 2015• Existing data is approximately 40 terabytes capacity. • DOGAMI anticipates a total of 60 terabytes be the end of the 15-17 biennium.
• Current state data center rates, 60 terabytes of storage would be approximately $7,200 monthly
Relation to the framework:
Framework Review Committee, April 29th, 2015
• E-FIT Goal 2: Provide professional and well-coordinated elevation services that support the diverse needs of Oregon.
• Expanding the distribution of high quality lidar data, E-FIT can provide more benefits to other FITS, such as Hazards, Geoscience, Hydrography, Utilities, Transportation, Land Cover and Preparedness.
Current system of lidar delivery:
Framework Review Committee, April 29th, 2015
• OLC lidar data is finalized• OLC partners supply hard drive via mail to DOGAMI• DOGAMI organizes data for each partner, uploads to drives• DOGAMI ships the drives to the OLC partner• Typically, OLC partner gets only the current project data.
• DOGAMI gets a constant stream of requests for both LAS points and Raster data. Custom data requests are a poor use of our limited staff.
Current system:
Framework Review Committee, April 29th, 2015
• There is a lidar imagery service on Imagery Explorer, but it is very much out of date.
• The data on imagery explorer was developed with second hand copies, and we do not support them, and our QC Certifications do not apply to this data. There are errors in imagery explorer data.
• If DOGAMI served the data, we would support it and certify its accuracy.• To get LAS files, one must go through the USGS, which is a clunky system
and limits users to 100 tiles per search.
Native OLC data Imagery Explorer data
Proposed system:
Framework Review Committee, April 29th, 2015
• 60 terabyte server connected to the internet• PSOB has 1GBPs data connection, DAS has promised to allocate
800MBPs to DOGAMI. We will have the bandwidth to serve large amounts of data, and DOGAMI will cover bandwidth costs.
• Web facing site:• Map where user can click on lidar project areas (likely Javascript
map built on ESRI WebApp Builder platform.)• Project areas will have ability to download 3 foot raster files for
entire project (or subsets for very large project areas)• More detailed zoom level will show 1/100th Quad OLC tiles, click to
download LAS or LAZ.
Products available on download site:
Framework Review Committee, April 29th, 2015
Product Tiling Format
Classified point cloud1/100th USGS 7.5" quad LAS 1.4*
Bare Earth DEM 3ft cell USGS 7.5" quad Esri GridHighest Hit DEM 3ft cell USGS 7.5" quad Esri GridIntensity image 1.5 ft or 0.5 m cell USGS 7.5" quad Esri Grid
Metadataembedded in ESRI files xml
* required by USGS but not a standard OLC product
Project timeline:
Framework Review Committee, April 29th, 2015
Task15-Jul 15-Aug 15-Sep Oct-15 Nov-15 Dec-15
Acquire and install server
Migrate and organize data
Build interface
Launch web site
Project costs:
Framework Review Committee, April 29th, 2015
Budget - Full Project Scope
Item Description Time Cost
Hardware acquisition Digital Data Storage $12,762
Lidar Database Coordinator (ISS-6) Data copy/organization 4 weeks $7,510
Sr GIS Analyst (ISS-5) Install Device 2 weeks $4,352
Sr GIS Analyst (ISS-5) Build interface / test 6 weeks $12,975
TOTAL: $37,599
Benefits:
Framework Review Committee, April 29th, 2015
• Fast delivery to OLC lidar partners• Everyone will have access to ALL OLC lidar for FREE!• Accuracy of lidar data is assured – DOGAMI is the state steward
of lidar data.