18
Dan Woodfin Director, System Operations Lessons Learned in Wind Integration in ERCOT National Conference of State Legislatures Energy Program Webinar April 25, 2013

Lessons Learned in Wind Integration in ERCOT

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Lessons Learned in Wind Integration in ERCOT

Dan Woodfin Director, System Operations

Lessons Learned in Wind Integration in ERCOT

National Conference of State Legislatures Energy Program Webinar April 25, 2013

Page 2: Lessons Learned in Wind Integration in ERCOT

The ERCOT Region

The interconnected electrical system serving most of Texas, with limited external connections • 75% of Texas land; 85% of Texas load • 68,294 MW peak demand (set August 3, 2011) • More than 40,000 miles of transmission lines • 2 DC ties with SPP; 3 DC ties with Mexico;

1106 MW total • 550+ generation units

April 25, 2013 2

Markets • Fully unbundled Wholesale market

• ERCOT operates a single Control Area with ancillary services markets • Generators are paid Locational Marginal Prices (LMPs) at their node • Load-serving entities pay averaged load-zone prices

• Full Retail competition except in municipal & co-op utility areas

Transmission Service • All transmission costs are rolled-in to single postage-stamp rate paid by load • All generators have, essentially, “network service”

NCSL Webinar

Page 3: Lessons Learned in Wind Integration in ERCOT

ERCOT ISO

April 25, 2013

ERCOT Inc.: A non-profit corporation designated the “Independent Organization” under state law and assigned these responsibilities [Texas Public Utility Regulatory Act (PURA) 39.151]: • Maintaining System Reliability • Ensuring Open Access to Transmission • Facilitating the Competitive Wholesale

Market • Facilitating the Competitive Retail Market

Regulatory Characteristics: • ERCOT is regulated by the Texas

Public Utility Commission with oversight by the Texas Legislature

• ERCOT is not a market participant and does not own generation or transmission/distribution wires

• ERCOT is the sole Reliability Coordinator, Balancing Authority, Planning Authority, Interchange Authority, and Transmission Service Provider for the ERCOT Region

3 NCSL Webinar

Page 4: Lessons Learned in Wind Integration in ERCOT

Installed Wind Generation in ERCOT

April 25, 2013 NCSL Webinar 4

1,224

3,620 4,189 4,389

116

816 977 1,173 1,385 1,854

2,875

4,785

8,005

8,916 9,400

9,604 10,407

11,794

14,190 14,759

14,959

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

MW

Cumulative MW Installed

Cumulative Planned (Signed Interconnection Agreement)

ERCOT Wind Installations by Year (as of March 31, 2013)

The data presented here is based upon the latest registration data provided to ERCOT by the resource owners and can change without notice. Any capacity changes will be reflected in current and subsequent years' totals. Scheduling delays will also be reflected in the planned projects as that information is received.

This chart now reflects planned units in calendar year of installation rather than installation by peak of year shown

10,570

Currently, 10,570 MW nameplate capacity installed

Page 5: Lessons Learned in Wind Integration in ERCOT

Wind Output

• Peak wind generation output on 9,481MW on 2/9/13 – 27.8% of Load at the time

• 8.7% of Nameplate Capacity of wind counted towards reserve margin

% Energy Produced by Fuel Type 2012

0

500

1000

1500

2000

2500

3000

3500

4000

4500

5000

25,000

30,000

35,000

40,000

45,000

50,000

55,000

60,000

65,000

70,000

8/9/10 8/9/10 8/10/10 8/10/10 8/11/10 8/11/10 8/12/10 8/12/10 8/13/10 8/13/10 8/14/10 8/14/10 8/15/10 8/15/10 8/16/10 8/16/10

Load

MW

Integrated Load Actual Integrated Wind Output

Wind M

W

Load

Wind

April 25, 2013 5 NCSL Webinar

Natural Gas, 44.6

Coal, 33.8

Nuclear, 11.8

Wind, 9.2

Water, 0.1 Other, 0.5

Page 6: Lessons Learned in Wind Integration in ERCOT

Competitive Renewable Energy Zones (CREZ)

• Transmission Plan designed to serve approximately 18GW:

– ~4600 circuit miles of 345 kV

– $6.7 billion project cost • All line certification

cases completed – Construction underway – All lines expected to be

complete by end of 2013

• Lines are open-access; use not limited to wind

April 25, 2013 6 NCSL Webinar

Page 7: Lessons Learned in Wind Integration in ERCOT

Operational Challenges for Wind Integration

• Uncertainty • Variability • Interconnection

7 NCSL Webinar April 25, 2013

Page 8: Lessons Learned in Wind Integration in ERCOT

Wind Forecast

8 NCSL Webinar April 25, 2013

• Wind power production forecast – Hourly 50% probability

of exceedance forecast for a rolling 48 hour period

– Provided for each wind farm and total for system

• Used to determine need for “residual” unit commitment

Forecasted and Actual Wind Power Production: Current Day

Graph Updated: Apr 24, 2012 15:20

Wind Power Production: 2,585 MW

Updated: Apr 24, 2012 15:35

Current Day Next Day

STWPF

Actual

Hour-ahead

Day-ahead

Page 9: Lessons Learned in Wind Integration in ERCOT

Wind Forecast Error

9 NCSL Webinar April 25, 2013

0

50

100

150

200

250

<-4250 -3750 to -3250

-2750 to -2250

-1750 to -1250

-750 to -250

250 to 750

1250 to 1750

2250 to 2750

3250 to 3750

> 4250

Freq

uenc

y

MW Error (Estimated Uncurtailed Output - STWPF)

Histogram of Hour-Ahead MW Forecast Error All Hours

(Estimated Uncurtailed Output -STWPF) [MW]

0

1000

2000

3000

4000

5000

6000

0%

2%

4%

6%

8%

10%

12% Monthly M

ean Estimated U

ncurtailed Power O

utput [MW

]

Mon

thly

Mea

n Ab

solu

te P

erce

nt E

rror

of I

nsta

lled

Cap

acity

[%]

WIND POWER FORECAST Mean Absolute Percent Error

Monthly Mean Estimated Uncurtailed Power Output [MW] Day-Ahead 1430 STWPF Hour-Ahead STWPF

Average hour-ahead wind forecast error is significant

(MAPE is ~7%)

MW errors may be high (>1000 MW; occasionally

>2000 MW)

Page 10: Lessons Learned in Wind Integration in ERCOT

Wind Forecasting

• ERCOT Large Ramp Alert System (ELRAS) – Probabilistic forecast

which alerts Operators of ramps during the next 6 hours

– Provided on the system and regional level

10

Predicting Large Ramps in Wind Power Output

April 25, 2013 NCSL Webinar

Page 11: Lessons Learned in Wind Integration in ERCOT

Ancillary Services - Regulation

• ERCOT typically dispatches generation each five minutes • Regulation Service is used to balance the variation in load and

generation between five-minute economic dispatch executions • Primary driver for determining required amount of regulation is

historical deployments – Adjusted for increase in installed wind capacity

11 NCSL Webinar April 25, 2013

Page 12: Lessons Learned in Wind Integration in ERCOT

Ancillary Services – Non-Spin

• Non-spin Reserve Service – 30 minute product that can be provided by unloaded capacity,

offline Generators, and Load Resources – Wind power forecast error is one of the inputs used for

calculating the requirement for this service

12 NCSL Webinar April 25, 2013

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

MW

Operating Hour

Actual Aggregated Wind Power Output Hour-Ahead COP HSL Day-Ahead COP HSL

Actual Wind, Wind Hour-Ahead COPs and Wind Day-Ahead COPs on June 27, 2011

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

30,000

35,000

40,000

45,000

50,000

55,000

60,000

65,000

Load MW

ERCOT Load PRC Wind Generation

Wind & PRC MW

2,300EEA Level 1 PRC below 2,300 MW for 1 minute

5,351 MW

1,135 MW

Non- Spin Deployed

Page 13: Lessons Learned in Wind Integration in ERCOT

Primary Frequency Response

• All generation in ERCOT is required to provide governor response with a 5% droop setting

• Wind farms are required to provide primary frequency response to frequency deviations from 60 Hz.

13 NCSL Webinar April 25, 2013

100

110

120

130

140

150

160

170

100

110

120

130

140

150

160

170

CPS1

Ave

rage

Monthly Average 12 Month Rolling Average

Page 14: Lessons Learned in Wind Integration in ERCOT

Generation Ramps

14 NCSL Webinar April 25, 2013

0

5000

10000

15000

20000

25000

30000

35000

40000

0

2000

4000

6000

8000

10000

12000

14000

16000

18000

1 10 19 28 37 46 55 64 73 82 91 100

109

118

127

136

145

154

163

172

181

190

199

208

217

226

235

244

253

262

271

280

289

298

307

316

325

334

343

352

361

370

379

Agg

rega

te M

W O

utpu

t by

Typ

e

15 Minute Interval - Starting 4/17 0:00

Wind

Total Gen

Gas_CC

Coal

Gas

Nuclear

DC Ties

Hydro

Biomass

Other

Solar

Page 15: Lessons Learned in Wind Integration in ERCOT

Interconnection-Related Requirements

April 25, 2013 NCSL Webinar

• Inverter-connected resources may not fit with traditional technical requirements

• Need to address these issues to maintain system reliability:

15

• Static and dynamic reactive capability

• Voltage-ride through capability

• Modeling o Collector system and

support device modeling o Dynamic model and

parameters

Page 16: Lessons Learned in Wind Integration in ERCOT

Impact of Wind Generation on Prices

• There is a clear shift down in the duration curve of real-time prices for higher levels of wind power output

16 NCSL Webinar April 25, 2013

Page 17: Lessons Learned in Wind Integration in ERCOT

Summary

• Sufficiently large Balancing Area • Nodal market mechanisms with short dispatch cycle to incent

flexibility in generation fleet and efficiently allocate curtailment • Accurate wind forecast and wind ramp projections • All generators required to contribute to system needs for

voltage support and frequency control • Incorporation of wind uncertainty and variability into ancillary

services requirements

17 NCSL Webinar April 25, 2013

Page 18: Lessons Learned in Wind Integration in ERCOT

Questions?