24
Nov-15 Dr. A.Helba CIV 416 E 1 A Guide to Designing Reinforced Concrete Water Tanks Helba Alaa Dr. Analysis of Circular R.C. slabs (Roofs Floors) Design of simply supported circular roof slabs Arrangement of st. rft. in circular s.s. slab Illustrative Example Lecture 5

Lecture 5 - Delta UnivDr. A.Helba CIV 416 E 12 Arrangement of Radial Steel A sr 2- calculate and check A sr required at mesh outer perimeter (at circle , r 1 = R/4 = 1 m, = 0.25 and

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • Nov-15

    Dr. A.Helba CIV 416 E 1

    A Guide to Designing Reinforced Concrete Water Tanks

    Helba AlaaDr.

    Analysis of Circular R.C. slabs (Roofs – Floors)

    Design of simply supported circular roof slabs

    Arrangement of st. rft. in circular s.s. slab

    Illustrative Example

    Lecture 5

  • Nov-15

    Dr. A.Helba CIV 416 E 2

    R R s.s. slab

    Fixed slab

  • Nov-15

    Dr. A.Helba CIV 416 E 3

    Moments and St. Rft. in Circular R.C Plates

    Ast

    Asr

    Asmax

    Steel required:

    As max , Asr radial steel and Ast tangential

    x

    Y

    r

    t

    Moments:

    M max

    Mr radial moment Mt tangential

    R = radius

    R

    Analysis of circular Simply Supported Slab

    • in a circular plate Radial Moments

    (Mr) and Tangential Moments (Mt) could be calculated from the following equations:

    Mr max = M+ve

    max

    B.Mr .D

    at center:

    2

    (3 )16

    wR

    Mredge=0

  • Nov-15

    Dr. A.Helba CIV 416 E 4

    Analysis of circular Simply Supported Slab

    • Tangential Moments (Mt)

    Mt max = M+ve

    max

    B.Mt.D

    at center: 2

    (3 )16

    wR

    At edge: Mt edge

    2

    (2 2 )16

    wR

    Moments at any point in S. S. circular Slab

    22

    22

    [(3 )(1 )]16

    [(3 ) (1 3 ) ]16

    = Poisson's ratio

    r and =

    R

    r

    t

    wRM

    wRM

    ( = 0 at center , = 1 at edge)

  • Nov-15

    Dr. A.Helba CIV 416 E 5

    • For concrete assume n = 0.2 then :

    2

    2

    2

    2

    (1

    (1 )5 2

    )5

    t

    r

    and

    wRM

    wRM

    + ve tension downside

    - ve tension upperside

    Table XII

    coeffs. for Moment in Circular Slab / No Center

    Support / Uniform Load / Fixed Edge

    0.0

    R

    0.1

    R

    0.2

    R

    0.3

    R

    0.4

    R

    0.5

    R

    0.6

    R

    0.7

    R

    0.8

    R

    0.9

    R

    1.0

    R

    Fixed

    Fixed

  • Nov-15

    Dr. A.Helba CIV 416 E 6

    Asr radial steel to resist Mr

    PLAN SEC. ELEV.

    Asr

    Ast r R

    Asr Ast

    Mr Mr

    Ast tangential steel to resist Mt

  • Nov-15

    Dr. A.Helba CIV 416 E 7

    Calculation and arrangement of Asr in circular S.S. slab

    The radial steel is distributed on the perimeter which varies along the slab radius , the radial steel should be calculated by its total amount.

    Calculate the radius (r) at which Asr (total) is maximum

    by putting

    0r totaldM

    dr

    (r) for Maximum Asr (total)

    (

    22 22

    2 3

    2(1 )(2 )

    5 5

    2

    5

    r total

    wR wR rM r r r

    R

    wR r r

    ( 2 22

    3 05

    10.577

    3 3

    r totaldM w R rdr

    Rr

  • Nov-15

    Dr. A.Helba CIV 416 E 8

    Maximum Mr total For simply supported circular slab the

    total radial steel (the maximum area) is only calculated at = 1/√3 = 0.58

    2 22

    2 3 3

    1

    3

    2(1 )(2 ) ( )(2 )

    5 5 3

    4 4

    15 16.515 3

    r total

    rat

    R

    wR wRM r r

    rwR wR wD

    Example: Design of Roof Slab

    Data: Dtank(inner)=7.5 m , H=5 m, fcu=25 N/mm2 ,mild steel

    Loads on roof slab:

    Assume troof = D / 50 = 7500 / 50 = 150 mm

    own wt. of slab = 0.15 X 25 = 3.75 kN/m2

    covering = 1 kN/m2 (may be ass. 0.75 to 1 kN/m2)

    L . L = 1 kN/m2 (inaccessible roof)

    w roof = 5.75 kN/m2

    wu = 1.5 w = 1.5 X 5.75 = 8.625 kN/m2

    assume twall (for practical purposes) = H/20 = 5/20 = 0.25 m

    radius of roof slab Rroof = 7.5/2 + 0.25 = 4 m

  • Nov-15

    Dr. A.Helba CIV 416 E 9

    Moments in Cicular Roof Slab • Maximum Moments:

    at middle of slab

    • Radial Moment Mr :

    Mr max +ve = wuR2/5 = 8.63 X 42 / 5 = 27.6 kN.m

    • Tangential Moment Mt :

    Mt max +ve = Mr max +ve = 27.6 kN.m

    mm

    bf

    R

    Md

    c

    u 88

    )1000(5.1

    25)214.0(

    106.27 6

    cumax

    min

    As max

    Asr radial steel Ast tangential st. Asmax square mesh at center in 0.25Dx0.25D

    Steel Rft. in circular roof slab

    Ast

    Asr

    As max

  • Nov-15

    Dr. A.Helba CIV 416 E 10

    Calculation of st. rft. in circular roof slab 1- calculate As mesh at center As max(at middle)=Mumax/ [bcrd(1-a/2)fy/s] = 27.6 X 106 / [ 0.9 X 110 X (1 - 0.23/2)(240/1.15)]

    = 1511.4 mm2 chosen 8 f 16 / m' as a square mesh in middle area of 2m X 2m (area of 0.5 R X 0.5 R)

    (Check As min= 0.25 % Ac = 2.5 t = 2.5 x 150 = 375 mm2)

    mesh 16 f 16 in 2m

    2- calculate and arrange the radial steel Asr - Calculate Maximum Total Radial Steel Asr tot max

    Mur total max. = 8.625 X 83 / 16.5 = 267.7 kN.m

    3

    .16.5

    r total MAX

    wDM

    62

    , . . : 23

    12

    267.7 1012607

    240 0.1421 110

    1.15 2

    rusr total

    y

    cr

    s

    cr

    M RA N B to get use b

    fd

    mm

    a a

    b

    b

    Trial 1 : chosen 112 f 12 (with bcr =1)

  • Nov-15

    Dr. A.Helba CIV 416 E 11

    Arrangement of Radial Steel Asr At circle ❷ 112 f 12 (Asr tot at r2 =

    0.58 x 4 = 2.32 m) are distributed along a perimeter = 2 r2 = 14.6m at spacing s2 = 14600/112 = 130 mm < 200 mm

    At the support (outer edge of roof

    slab) R = 4m, and perimeter = 2 R = 25.13 m.

    Spacing of 112 bars at the edge circle ❸s3 = 25130/112 = 224.4 mm > 200 mm, in this case the solution is to increase the required number of bars so as to keep sedge to 200 mm, so,

    nreq = 25130/200 = 125.7 use 126 bars spaced with: sat (r=0. 58R) =2 (0.58R)/126=

    14577/126 = 115.7 mm.

    Trial 2: chosen 126 f 12

    Arrangement of Radial Steel Asr In order to cut off half the number of radial bars (63 out of 126) try the

    following: 1- calculate the perimeter required to limit spacing of bars to 80 mm, = 126

    x 80/1000 = 10.08 m at r = 10.08/2 = 1.6 m (at circle ❹ you can use 126/2 = 63 bars at = 0.4)

    Then As 4 total available = 63 x 113 = 7119 mm2

    Check with Asr required at circle ❹ as follows: - Calculate Mr4 at r4 = 1.6 m, = 0.4 Mr4 = wR

    2(1-2)/5 = 8.63(4)2[1-(.4)2]/5 = 23.2 kN.m Mr4 total = (2 r4) x 23.2 = 233.2 kN.m Then As 4 total required This trial cannot be done as As 4 total required >> As 4 total available .. Cancel it ..

    624 233.2 10 10807

    240 0.121 1101

    1.15 22

    ru

    ycrcr

    s

    Mmm

    fd

    a bb

  • Nov-15

    Dr. A.Helba CIV 416 E 12

    Arrangement of Radial Steel Asr 2- calculate and check Asr required at mesh outer perimeter

    (at circle ❶ , r1 = R/4 = 1 m, = 0.25 and perimeter = 6.28 m):

    - calculate Mr1 at r1 = 1.0 m , = 0.25: Mr1 = wR

    2(1-2)/5 = 8.63(4)2[1-(.25)2]/5 = 25.9 kN.m Mr1 total = (2 r1) x 25.9 = 162.7 kN.m Then As 1 total required Then Asr1 total required (7540 mm2) > As cut off avilable (7119 mm2) It needs 67 f 12 at s1 = 6280/67= 94 mm > 80 mm o.K That means using 67 x 2 = 134 bars Ld = 40 f = 40 x 12 = 480 mm use extension 0.5 m for overlap.

    621 162.7 10 7540

    240 0.121 1101

    1.15 22

    ru

    ycrcr

    s

    Mmm

    fd

    a bb

    Finally: chosen 134 f 12

    Arrangement of Radial Steel Asr Finally: Then Asr total required = 134 f 12 to be arranged as follows: 67 f 12 with length L1 and another 67 f 12

    with length L2 : L1 = R – r1 – cover + v

    al part + 2 hook = 4 – 1 - .030 + (0.15 -2 x .03) + 2 X 6f = 3.204 m L1 = 3.25 m L2 = R – r1 – cover + ld + 2 hook = 4 – 1 - .030 + 0.5 + 2 x 6 x 0.012 = 3.614 m

    L2 = 3.75 m

  • Nov-15

    Dr. A.Helba CIV 416 E 13

    3- calculate and arrange the tangential steel Ast - Calculate Maximum tangential Steel Ast max/m’ (at r = R/4 , r = 0.25)

    Mtu1 = wuR2(1-1

    2/2)/5

    =8.625 X 42 (1 – 0.252/2)/ 5 = 26.74 kN.m 6

    11

    27.7 10

    240 0.121 1101

    1.15 22

    tust

    ycrcr

    s

    MA

    fd

    a bb

    chosen 7 f 16 / m’ = 1377 mm

    2 (bcr = 0.9)

    And use 6 f 16 / m’ at Mt = 1206 x 0.9 x (240/1.15) x 0.95 x110 = 23.67 kN.m (corresponding to 2 = 2(1-5M/wR2) = 0.29 , = 0.535) at r5 = .535 x 4 = 2.14 m and so on .) starting from r = 2.2 m .

    150 mm

    PLAN Roof Slab rft.

    3.75 m

    3.75 m

    0.25 m

    0.25 m

  • Nov-15

    Dr. A.Helba CIV 416 E 14

    SEC. ELEV.

    Roof Slab rft.

    5.0 m

    0.15 m

    square mesh 16 f 16 in 2m

    C.L.

    Alternative choice and Arrangement of Radial Steel Asr

    (Note: if f 16 mm is chosen bcr = 0.9 and As = 13954 mm2 )

    At circle ❷ 70 f 16 (Asr tot at r2 = 0.58 x 4 = 2.32 m) are distributed along a

    perimeter = 2 r2 = 14.6m at spacing s2 = 14600/70 = 209 mm > 200 mm then the number of f 16 mm bars should be increased from 70 to 14600/200 = 73 bars to keep spacing of bars =< 200 mm)

    Check At the support (outer edge of roof slab) R = 4m, and perimeter =

    2R = 25.13 m. Spacing of 73 bars at the edge sedge = 25130/73 = 344 mm >> 200 mm, in

    this case the solution is to use 73 f 12 amid the other number of bars so as to get sedge = 25130/146 = 172 mm < 200 mm, so, these additional 73 f 12 are ended at s = 200mm at r = r2 = 2.32 m

    L = R – r2 = 4 – 2.32 = 1.68 m use L = 1.75

    Trial 1 : chosen 70 f 16 (with bcr = 0.9)

    Trial 2 : chosen 73 f 16 & add 73 f 12

  • Nov-15

    Dr. A.Helba CIV 416 E 15

    Finally: Then Asr total required = 73 f 16 with length L1 and 73 f 12 with length L2 : L1 = R – r1 – cover + ld + 2 hook = 4 – 1 - .030 + 0.5 + 2 X 6f = 3.614 m L1 = 3.75 m L2 = R – r2 – cover + v

    al part + 2 hook = 4 – 2.32 - .030 + (0.15 -2 x .03) + 2 x 6 x 0.012

    = 1.884 m

    L2 = 2 m r2 = 2.3 m

    Alternative choice and Arrangement of Radial Steel Asr

    150 mm

    PLAN

    Roof Slab rft.

    3.75 m

    3.75 m

    0.25 m

    0.25 m

    Alternative choice and Arrangement of Radial Steel Asr

  • Nov-15

    Dr. A.Helba CIV 416 E 16

    Plan (Sec. under floor level) An elevated Tank (Floor rests directly on 4 Columns)

    D t 0.71 D

    Case 1 n = number of Columns = 4 or 6 or 8

    D H

    (+…. m) Hw

    SEC. PLAN

    SEC. ELEV.

    Case 1

    V (Tank Capacity) = (πD2/4)x Hw

  • Nov-15

    Dr. A.Helba CIV 416 E 17

    Loads on Wall and Floor of an elevated Tank

    (Floor rests directly on columns)

    Sec. Elev.

    D

    H

    t

    Water Pressure

    Dead Load (D.L.)

    Final B.M.D. on Walls and Floor

    1- An elevated Tank rests directly on Columns

    MFinal at connection >> MF wall Calculate MFinal at connection by

    Moment Distribution

    MFinal

    Floor structural system

  • Nov-15

    Dr. A.Helba CIV 416 E 18

    Options of wall thickness

    Uniform t Tapered t1/t2 Haunch t1/t2 2Haunches in wall &

    floor

    Case 1

    Sec. ELEV. An elevated Tank (Floor rests directly on Columns)

    t1 = twall at top

    t2 = twall at base

    t

    t t2

    t1

    tfloor tfloor

    Plan (Sec. under floor level) An elevated Tank (Floor rests on Beams on Columns)

    t 0.71 D D

    0.15 D Main Beam

    Paneled Beams

    Main Beam

    Case 2

    Wall act as a Deep Beam between columns

  • Nov-15

    Dr. A.Helba CIV 416 E 19

    Final B.M.D. on Walls and Floor

    2-An elevated Tank rests on Beams on Columns

    C.L

    MFwall

    M1

    M2

    MFinal at connection = MF wall

    Floor is divided to slabs with Mx & My

    Wall acts as D

    ee

    p B

    eam

    Floor structural system

    M1 & M2 From 3-mom. Eq.

    Plan (Sec. under floor level) An elevated Tank rests on Circular Beam on Columns

    D t 0.71 Db

    Case 3

    Db

    Db diameter of C.L. of Circular beam

    b=bbeam

  • Nov-15

    Dr. A.Helba CIV 416 E 20

    Plan (Sec. under floor level) An elevated Tank rests on Circular Shaft

    D t

    Case 4

    Dsh

    Dsh diameter of C.L. of Circular shaft

    tsh=thickness of shaft wall

    Final B.M.D. on Wall and

    Floor

    3- Elevated Tank rests on Circular Beam on Columns

    C.L

    MFwall

    Mr1

    Mr2 = Mt2 MFinal at connection = MF wall

    Mr1 = MF wall + M due to P wall + M due to floor cant. part

    Floor is circular slab with Mr & Mt (Use superposition)

    Floor structural system

    4- Elevated Tank rests on Circular Shaft

  • Nov-15

    Dr. A.Helba CIV 416 E 21

    Final B.M.D. on Wall and Floor

    An elevated Tank Floor rests directly on Columns

    Study of Case 1

    Tension and Shear in Wall and Floor

  • Nov-15

    Dr. A.Helba CIV 416 E 22

    Tension and Shear in Wall and Floor

    Final Results of B.M & N.F

    Mr

    Mt

    1

    2

    3 4

    Tring acts horizontally in Wall

  • Nov-15

    Dr. A.Helba CIV 416 E 23

    Distribution of Mr & Mt in Floor slab (Values from table XII)

    -0.15

    -0.1

    -0.05

    0

    0.05

    0.1

    0 0.2 0.4 0.6 0.8 1

    Mr

    Mt

    Ring Tension in wall for Different Base Conditions

  • Nov-15

    Dr. A.Helba CIV 416 E 24

    Sections 1 & 4 Tension due to B.M is on Air-Side (design as Cracked sec.)

    Open Tank 1

    4

    2 3

    Sections 2 & 3 Tension due to B.M is on Water-Side (design as uncracked sec.)

    1

    4

    2

    3

    An elevated Tank (Floor rests directly on Columns)

    B . M . D

    Case 1

    General Procedure for Design( 7 steps)

    • Assign the overall Dimensions for tank (D & H)

    • Consider the Connection (distribute DM– get Mf)

    • Define sections for design & design values (M,Q,N)

    • Calculate t for different sections

    & Choose proper thicknesses.

    • Calculate As required for different sections.

    • Arrange steel at sections and connections.

    • Draw steel arrangements in plan and elevation