Upload
vuongthuy
View
237
Download
5
Embed Size (px)
Citation preview
ENVIRONMENTAL IMPACT ASSESSMENT
AND
ENVIRONMENTAL MANAGEMENT PLAN FOR
ENVIRONMENTAL CLEARANCE
FOR
JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL)
(For enhancemement in Production Capacity from 0.60 MTPA to 1.50 MTPA with increase in land area from 174.28 ha to 449.63 ha Land)
PREPARED AS PER TOR RECEIVED FROM MOEF VIDE ITS LETTER NO. J – 11015/225/2014- IA. II(M) dated 21.11.2014
January – 2015
Central Mine Planning & Design Institute Limited A Mini – Ratna Company
SUBMISSION
This Environmental impact assessment (EIA)/ Environmental Management Plan (EMP) has been prepared based on the Terms of Reference (TOR) issued by MOEF vide its letter no. J-11015/225/2014-IA. II (M) dated 21/11/2014.
The copy of the TOR has been enclosed as Annexure – I.
The Public Consultation/ Public Hearing as per EIA Notification, 2006 has been completed on 05.02.2013. The minutes of the Public Hearing have been attached at Annexure – III.
CONTENTS
Chapter
No.
Name of the Chapter
Compliance of TOR
I Introduction
II Project Profile
III Description of Environment
IV Anticipated Environmental Impacts & Mitigation
Measur
V Environmental Monitoring Programm
VI Additional Studies
VII Project Benefits
VIII Environmental cost –Benefit Anal
IX Environmental Management Plan
X Summary & Conclusion
XI Disclosure of Consultants Engaged
XII Check List
XIII Annexures
LIST OF PLATES
Plate No. PARTICULARS
I Loaction Plan
II Topo – Sheet Plan Showing main drainage in Core & Buffer Zone
III Land Use/cover mapping of Core,Buffer and Impact Zone of
Junad OCP based on LISS- III Satellite data of 2011
IV Revenue Plan
V Topographical & Geological Plan
VI Proposed Quarry & Surface layout Plan
VII Existing Longitudinal & Transverse Section of Proposed Quarry
Layout
VIII Post Mining Land Use Plan
IX Post Mining Longitudinal & Transverse Section of Quarry Layout
X AAQM Stations
LIST OF ANNEXURES
ANNEXURE No.
PARTICULARS
I Generic ToR NO. J – 11015/225/2014- IA. II(M) dated 21.11.2014
II Duly filled in Proforma for Appraisal of Mining Project III Copy of Minutes of Public Hearing held on 05.02.2013
IV Copy of Cerificate of Compliance of Conditions of earlier EC as issued by MOEF, Bhopal & corresponding ATR Submitted.
V Copy of Environmental (Audit) Statement 2013-14
Junad Deep Extn. OC. COMPLIANCE OF TERMS OF REFERENCE
Ref.:- MOEF’s letter no. J-11015/225/2014-IA. II (M) dated 21/11/2014.
Sr. No.
TOR Condition Compliance
Generic conditions for opencast coal mine
1 An EIA-EMP Report would be prepared for 0.60 MTPA (Norm) 1.5 MTPA (Peak) rated capacity in an ML/project area of 174.28 ha to 449.63 ha based on the generic structure specified in Appendix III of the EIA Notification 2006.
This EIA/EMP has been prepared for 0.60 MTPA (Norm) 1.5 MTPA (Peak) rated capacity in an ML/project area of 174.28 ha to 449.63 ha based on generic structure as specified in Appendix III EIA Notification 2006.
2 An EIA-EMP Report would be prepared for 0.60 MTPA(Norm) 1.55 MTPA (Peak) rated capacity cover the impacts and management plan for the project specific activities on the environment of the region, and the environmental quality ?air, water, land, biotic community, etc. through collection of data and information, generation of data on impacts including prediction modelling for 0.60 MTPA(Norm) 1.55 MTPA (Peak) of coal production based on approval of project/Mining Plan For 0.60 MTPA(Norm) 1.5 MTPA (Peak) Baseline data collection can be for any season except monsoon.
This EIA/EMP report has been prepared for 0.60 MTPA (Norm) 1.55 MTPA (Peak) production capacity with increase in ML area from 174.28 ha to 449.63 ha. For this, baseline , socio-economic and Flora Fauna study were conducted in surrounding area from 01st April`2013 to 30th June`2013 covering the impacts and Management plan for the project specific activities on the environment of the region and the environmental quality – air, water land, biotic community etc. through collection of baseline data (Pre-Monsoon Season of 2013)
3 A map specifying locations of the State, District and Project location.
The map showing the project location specifying the State & district has been attached in as Plate – I.
4 A Study area map of the core zone and 10km area of the buffer zone (1: 50,000 scale) clearly delineating the major topographical features such as the land use, surface drainage of
There is no ecologically sensitive areas such as Biosphere Reserves / National Parks / WL Sanctuaries / Elephant Reserves, forests (Reserved/Protected), migratory corridors of fauna and areas where endangered fauna and plants of medicinal and economic importance
Sr. No.
TOR Condition Compliance
rivers/streams/nalas/canals, locations of human habitations, major constructions including railways, roads, pipelines, major industries/mines and other polluting sources. In case of ecologically sensitive areas such as Biosphere Reserves/National Parks/WL Sanctuaries/ Elephant Reserves, forests (Reserved/Protected), migratory corridors of fauna, and areas where endangered fauna and plants of medicinal and economic importance found in the 15 km area of the buffer zone should be given.
are found in the 15 km area of the buffer zone, however the study area map showing core Zone and Buffer Zone (10 km) clearly delineating the major topographical features such as the land use, surface drainage of rivers / streams / Nalas / canals, Locations of human habitations, major constructions including railways, roads, pipelines, major industries/mines and other polluting sources has been attached as Plate – II (Topo – Sheet Plan) & III (Staellite Imagery).
5 Land use map (1: 50,000 scale) based on a recent satellite imagery of the study area may also be provided with explanatory note of the land use. Satellite imagery per se is not required.
The land use map based on a recent satellite imagery of the study area with explanatory note of the land use is attached in the final EIA/EMP. The land involved in project is mostly agricultural land and there is no forestland involved in the project and has been attached as III (Staellite Imagery).
6 Map showing the core zone delineating the agricultural land (irrigated and unirrigated, uncultivable land (as defined in the revenue records), forest areas (as per records), along with other physical features such as water bodies, etc. should be furnished.
The map of the core zone showing the proposed mining area has been attached as Plate – III (Satellite Imagery) & IV ( Revenue Plan). The land is mostly agricultural land and there is no forestland involved in the project.
7 A contour map showing the area drainage of the core zone and 2-5 km of the buffer zone (where the water courses of the core zone ultimately join the major rivers/streams outside the lease/project area) should also be clearly indicated as a separate map.
The Topographical & Geological Plan of the site showing all the details has been enclosed as Plate- V.
Sr. No.
TOR Condition Compliance
8 A detailed Site plan of the mine showing the various proposed break-up of the land for mining operations such as the quarry area, OB dumps, green belt, safety zone, buildings, infrastructure, CHP, ETP, Stockyard, township/colony (within and adjacent to the ML), undisturbed area and if any, in topography such as existing roads, drains/natural water bodies are to be left undisturbed along with any natural drainage adjoining the lease /project and modification of thereof in terms of construction of embankments/bunds, proposed diversion/re-channelling of the water courses, etc., approach roads, major haul roads, etc.
The Quarry and Surface Layout Plan of the site showing all the details has been enclosed as Plate- VI.
9 In case of any proposed diversion of nallah/ canal/ river, the proposed route of diversion/ modification of drainage and their realignment, construction of embankment etc. should also be shown on the map.
The Quarry and Surface Layout Plan of the site showing all the details has been enclosed as Plate VI.
10 Similarly if the project involves diversion of any road/railway line passing through the ML/project area, the proposed route of diversion and its realignment should be shown.
Diversion of Water pipe line A water pipeline serving to Pragati Nagar colony passing along the arterial road from Ukni to Kolar Pimpri OCP partly falls over the dip side dumping area (External OB Dump No.1) of Junad Extension OC. It is required to divert this water pipeline partly so that the volume of required OB can be dumped in external OB dump, keeping safe distance from the dump. Provision for diversion of this water pipeline is proposed in the PR. Part Diversion of Approach Road Existing approach road to the project will be partly diverted because of extension of Junad OC mine (Reference – Plate – VI) Surface Layout Plan). Diversion of existing approach road is
Sr. No.
TOR Condition Compliance
proposed over the safety embankment, 30 m wide at top. Proper capital provision has been made in this report for this diversion.
11 Break up of lease/project area as per different land uses and their stage of acquisition.
The details are as given below
Sl.No. Particulars Land already acquired in existing Junad OC Mine
Land to be acquired under proposed Junad Extn. OC Mine
Total
1. Tenancy Land
174.28 ha
269.25 ha*
443.53
2. Govt. Land
- 6.10 ha 6.10
3. Forest Land
NIL NIL NIL
TOTAL 174.28 275.35 ha
449.63 ha
This 269.25 ha of land to be acquired includes 5.20 ha land of Kolar Pimpri Extn.Project and 13.85 ha of acquired land by existing Pimpalgaon OC Project. Both the projects are adjacent to Junad Extension OC Mine.
Thus, the total land involved in this project is 449.63 ha, out of which 174.28 ha land has already been acquired in existing Junad OC mine and balance 275.35 ha will have to be acquired.
Compensation bill against additional land acquisition approved by Ministry of Coal.
12 Break-up of lease/project area as per mining operations.
Details as given below:-
S.No. Particulars Area (ha)
1 Total Quarry Area
101.70
2 External OB Dump 175.00
3 Infrastructure including approach road, etc.
15.00
4 Embankment 20.00
5 Colony 0.00
6 Area needed for 137.93
Sr. No.
TOR Condition Compliance
rationalization & safe blasting zone
TOTAL 449.63
13 Impact of changes in the land use due to the start of the projects if much of the land being acquired is agricultural land/forestland/grazing land.
Detailed discussion in Chapter IV as indiacted in compliance above.
14 Collection of one-season (non-monsoon) primary baseline data on environmental quality - air (PM10, PM2.5, SOx, NOxand heavy metals such as Hg, Pb, Cr, As, etc), noise, water (surface and groundwater), soil along with one-season met data coinciding with the same season for AAQ collection period.
Baseline data in the surrounding area was carried out from 1st April 2013 to 30th June 2013 and the details of data generated are given in Chapter- III.
15 Map of the study area (1: 50, 000 scale) (core and buffer zone clearly delineating the location of various stations superimposed with location of habitats, other industries/mines, polluting sources. The number and location of the stations in both core zone and buffer zone should be selected on the basis of size of lease/project area, the proposed impacts in the downwind (air)/downstream (surface water)/groundwater regime (based on flow). One station should be in the upwind/ upstream/ nonimpact/non-polluting area as a control station. The monitoring should be as per CPCB guidelines and parameters for water testing for both ground water and surface water as per ISI standards and CPCB classification wherever applicable. Values should be
A map showing study area (core and buffer zone) clearly delineating the location of various stations superimposed with location of habitats, other industries/mines, polluting sources has been attached as Plate – X The number and location of the stations in both core & buffer zone have been selected on the basis of size of lease area / project area, the proposed impacts in the downwind (air) / downstream (surface water) / groundwater regime (based on flow). One station has been in the upwind / upstream / non-impact / non-polluting area as a control station. The monitoring will be as per CPCB guidelines and parameters for water testing for both ground water and surface water as per ISI standards and CPCB classification wherever applicable.
Sr. No.
TOR Condition Compliance
provided based on desirable limits.
16 Study on the existing flora and fauna in the study area (10km) carried out by an institution of relevant discipline and the list of flora and fauna duly authenticated separately for the core and buffer zone and a statement clearly specifying whether the study area forms a part of the migratory corridor of any endangered fauna. If the study area has endangered flora and fauna, or if the area is occasionally visited or used as a habitat by Schedule-I fauna, or if the project falls within 15 km of an ecologically sensitive area, or used as a migratory corridor then a comprehensive Conservation Plan should be prepared and submitted with EIA-EMP Report and comments from the CWLW of the State Govt. also obtained and furnished.
The details of flora and fauna in the core and buffer zone has been given in Chapter – III. There is no endangered flora and fauna in the Core as well as in the buffer Zone.
17 Details of mineral reserves, geological status of the study are and the seams to be worked, ultimate working depth and progressive stage-wise working scheme until end of mine life should be reflected on the basis of the approved rated capacity and calendar plans of production from the approved Mining Plan. Geological maps and sections should be included. The progressive mine development and Conceptual Final Mine Closure Plan should also be
The details of mineral reserves, geological status of the study area and the seams to be worked, ultimate working depth and progressive stage-wise working scheme until end of mine life has been reflected on the basis of the approved rated capacity and calendar plans of production from the approved Mining Plan in Chapter - II. Revenue Plan, Geological maps, Quarry layout Plan and sections have also been included as Plate – IV, V, VI, VII & VIII.
Sr. No.
TOR Condition Compliance
shown in figures.
18 Details of mining methods, technology, equipment to be used, etc., rationale for selection of that technology and equipment proposed to be used vis-à-vis the potential impacts.
Details of mining methods, technology, equipment to be used, etc., rationale for selection of that technology and equipment proposed to be used vis-à-vis the potential impacts has been given in Chapter – II.
19 Impact of mining on hydrology, modification of natural drainage, diversion and channelling of the existing rivers/water courses flowing though the ML and adjoining the lease/project and the impact on the existing users and impacts of mining operations thereon.
The detailed hydrogeological assessment has been incorporated in Chapter-III and the impact assessment has been incorporated in Chapter-IV along with hydrographs.
20 Detailed water balance should be provided. The breakup of water requirement for the various mine operations should be given separately.
As desired the detailed water balance in the study area has been given at page no. 135 in Chapter – III.
21 Source of water for use in mine, sanction of the competent authority in the State Govt. and impacts vis-à-vis the competing users.
Source of water in use in the mine is mine pumped out water. The details of competing user have been given in Chapter – III.
22 Impact of mining and water abstraction use in mine on the hydrogeology and groundwater regime within the core zone and 10 km buffer zone including long term modelling studies on. Details of rainwater harvesting and measures for recharge of groundwater should be reflected in case there us a declining trend of groundwater availability and/or if the area falls within dark/grey zone.
The impact on ground water due to abstraction of mine water covering core and Buffer Zone has been discussed in detail in Chapter – III & IV.
23 Impact of blasting, noise and vibrations.
The impact of blasting, noise and vibrations has been discussed in detail in Chapter – IV.
Sr. No.
TOR Condition Compliance
24 Impacts of mining on the AAQ, predictive modelling using the ISCST-3 (Revised) or latest model.
Impact of mining on AAQ, predictive modelling has been done using FDM Model and results have been reported in chapter – IV.
25 Impacts of mineral transportation within and outside the lease/project along with flow-chart indicating the specific areas generating fugitive emissions. Impacts of transportation, handling, transfer of mineral and waste on air quality, generation of effluents from workshop, management plan for maintenance of HEMM, machinery, equipment. Details of various facilities to be provided in terms of parking, rest areas, canteen, and effluents/pollution load from these activities.
The impact of mining on the various environmental attributes has been discussed in details in Chapter – IV.
26 Details of waste generation OB, topsoil as per the approved calendar programme, and their management shown in figures as well explanatory chapter with tables giving progressive development and mine closure plan, green belt development, backfilling programme and conceptual post mining land use. OB dump heights and terracing should based on slope stability studies with a max of 28o angle as the ultimate slope. Sections of dumps (ultimate) (both longitudinal and cross section) with relation to the adjacent area should be shown.
The details have been discussed in Chapter – IV. Sections have been shown in Plate – VI & VIII.
27 Progressive Green belt and afforestation plan (both in text, figures as well as in tables prepared by MOEF) and selection of species (local) for the afforestation/plantation
Details have been given in chapter – IV. The details of Stage wise land use & reclamation Area and Stage wise Cumulative plantation have been duly filed in Table 1 & 2 respectively in the subsequent pages.
Sr. No.
TOR Condition Compliance
programme based on original survey/landuse.
28 Conceptual Final Mine Closure Plan, post mining land use and restoration of land/habitat to pre- mining. A Plan for the ecological restoration of the area post mining and for land use should be prepared with detailed cost provisions. Impact and management of wastes and issues of rehandling (wherever applicable) and backfilling and progressive mine closure and reclamation.
Mine closure plan has been an intergral part of project report. Relevant table is given in chapter – IV. The details of post mining land use have been duly filed in table 3 in the subsequent pages.
29 Flow chart of water balance. Treatment of effluents from workshop, township, domestic wastewater, mine water discharge, etc. Details of STP in colony and ETP in mine. Recycling of water to the maximum possible extent.
The details have been discussed in Chapter – III.
30 Occupational health issues. Baseline data on the health of the population in the impact zone and measures for occupational health and safety of the personnel and manpower for the mine.
WCL has full fledged medical set up in all areas to check up and monitor all the Occupational diseases endangering the health of its preciuos workforce. The periodical medical Examinationfor all workman is compulsory as per Statute.It is carried out once in every five years for each and every worker and proper records are maintained and submitted to Directorate General of Mines Safety as it is a statutory requirement.
In case of workers, above 50 years of age and employed in underground mine, this periodical medical Examinationis carried out every two and half years interval. In Pathakhera Area, under whose administrative control, the mine under consideration is being worked is no exception. All the statutory obligations under the Occupational health are strictly followed. Set up of Occupational Health Services At WCL: WCL is having Occupational health committee at
Sr. No.
TOR Condition Compliance
the corporate (HQ) level as well as at the unit (Area /Project level).
At corporate level, the committee consists of the following: -
Chief General Manager (Safety)
Chief of Medical Services
Periodical Medical Examination(PME) Incharge of HQ.
The committee scrutinizes the report of the area every quarter.
At Unit level, the committee consists of the following: -
General Manager (Operations)
Area Medical Officer
Area Safety Officer
Periodical Medical Examination (PME) Incharge of Area.
The above committee takes the review at area level every month. There are 11 hospitals having PME Centres in the hospitals. The PME Centres are well equipped with Spirometry (Lung Function test), Audiometry (for testing hearing impairment) along with the facilities for X – Ray & other bio – chemical tests.
The details are as follows: -
Periodical Medical Examination(PME) Centres – 11
(Occupational Health Centres)
Nos. of Doctors engaged in Periodical Medical ExamiNAtion - 11
Nos. of Doctors trained in Periodical Medical ExamiNAtion - 22
Nos. of X – Ray machines (300 mA) - 9
Nos. of X – Ray machines (500 mA) - 2
Nos. of ILO film Tests - 10
Nos. of Audiometer units - 7 (4 units are under process of procurement)
Sr. No.
TOR Condition Compliance
Nos. of Spirometer units - 11
Nos. of Pathology Labs - 11
Nos. of X – Ray technicians - 14
Nos. of Laboratory Technicians - 22
All the PME Centres are fully computerised.
As per the Statute / Mines Act, 1952, all the workers are examined every five years and the disease profile is maintained in PME Centres in different colour codes as given below: -
Yellow Card – Hypertension
Green Card – Diabetes
Red Card - Ischaemic Heart Disease Workers exposed to high decibel machineries i.e. more than 90 decibels and are found to have developed hearing impairment, are subjected to repeated audiometric tests.
In suitable cases, as per the recommendation of the Apex Medical Board, the change of job is also suggested and implemented accordingly. In addition, the Welfare Board of WCL time to time makes visits to different area hospitals & PME Centres so as take stock of the ground realities.
31 Risk Assessment and Disaster Preparedness and Management Plan.
The details have been discussed in Chapter – VI.
32 Integrating in the Env. Management Plan with measures for minimising use of natural resources - water, land, energy, etc.
The EIA/EMP has been prepared accordingly.
33 Including cost of EMP (capital and recurring) in the project cost and for progressive and final mine closure plan.
The details have been discussed in Chapter – IX.
34 Details of R&R. Detailed project specific R&R Plan with data on the existing socioeconomic status of the population (including
The details have been discussed in Chapter – V.
Sr. No.
TOR Condition Compliance
tribals, SC/ST, BPL families) found in the study area and broad plan for resettlement of the displaced population, site for the resettlement colony, alternate livelihood concerns/employment for the displaced people, civic and housing amenities being offered, etc and costs along with the schedule of the implementation of the R&R Plan.
35 CSR Plan along with details of villages and specific budgetary provisions (capital and recurring) for specific activities over the life of the project.
Details has been given in Chapter - V
36 Public Hearing should cover the details of notices issued in the newspaper, proceedings/minutes of public hearing, the points raised by the general public and commitments made by the proponent should be presented in a tabular form. If the Public Hearing is in the regional language, an authenticated English Translation of the same should be provided.
The Public hearing was conducted on 05.02.2013. PH Minutes have been attached as Annexure No. -- III.
37 In built mechanism of self-monitoring of compliance of environmental regulations.
The inbuilt mechanism for compliance of all statutory requirements has been incorporated in Chapter –IX
38 Status of any litigations/ court cases filed/pending on the project.
There are no such cases pending against this project.
39 Submission of sample test analysis of Characteristics of coal - this includes grade of coal and other characteristics ?ash, S and heavy metals including levels of Hg, As, Pb, Cr etc.
Relevent details are given in Chapter – II.
Sr. No.
TOR Condition Compliance
41 Copy of clearances/approvals such as Forestry clearances, Mining Plan Approval, NOC from Flood and Irrigation Dept. (if req.), etc. wherever applicable.
No forest land is involved in the project.
42 Corporate Environment Responsibility: a) The Company must have a well laid down Environment Policy approved by the Board of Directors. b) The Environment Policy must prescribe for standard operating process/procedures to bring into focus any infringements/deviation/violation of the environmental or forest norms/conditions. c) The hierarchical system or Administrative Order of the company to deal with environmental issues and for ensuring compliance with the environmental clearance conditions must be furnished. d) To have proper checks and balances, the company should have a well laid down system of reporting of non-compliances/violations of environmental norms to the Board of Directors of the company and/or shareholders or stakeholders at large.
A well laid corporate Environmental Policy is approved by coal India Limited Board. Western Coalfields Limited being a subsidiary company of Coal India Limited subscribes to the said policy.
LANDUSE DETAILS FOR OPENCAST PROJECT
S.N. LANDUSE Within ML Area (ha)
Outside ML Area (ha) TOTAL
1. Agricultural land 443.53 ---- 443.53
2. Forest land NIL ---- NIL
3. Wasteland(Govt. Land) 6.10 ---- 6.10
4. Grazing land ----- ---- ----
5. Surface water bodies ---- ---- ----
6. Settlements ---- ---- ----
7. Others (specify) ----- ---- ----
TOTAL
449.63 ---- 449.63
OB Management
Project Total waste generation
(Mm3)
Topsoil (Mm3)
Total OB generation
(Mm3)
Total OB in Ext. Dump
(Mm3)
Total OB Backfilled
(Mm3)
Original Project (ha) 10.33 Included in OB
10.33 9.58 & 0.75 in Embankment
----
Expansion Project (ha) (balance life)
50.62 Included in OB
50.62 50.62 ----
TOTAL (Mm3)
60.95 60.95 60.20 & 0.75 in Embankment
The capacity of external OB dumps proposed is about 60.20 Mm3. Remaining 0.75 Mm3 of OB will be used is construction of safety embankment.
The break up of OB quantities in external OB dumps is given in following table.
No. Dump Capacity in Mm3
0-30m 0.60m Total
i) Dump – 1 25.70 16.95 42.65
ii) Dump – 2 10.30 7.25 17.55
Total 60.20 .
SCHEDULE OF OVERBURDEN DUMPING
The following Table No. 8.3 shows the yearwise OB dumping in external OB dump No.1 and No.2
Year Programmed
Excavation of
OB(Mm3)
External OB
Dump-1
(Mm3)
External OB Dump-2
(Mm3)Excluding Rehandling
1. 8.15 8.15 -
2. 7.40 7.40/15.55 -
3. 5.26 5.26/20.81 -
4. 5.25 5.25/26.06 -
5. 5.25 5.25/31.31 -
6. 4.70 4.70/36.01 -
7. 4.50 4.50/40.51 -
8. 4.40 2.14/42.65 2.26
9. 4.40 - 4.40/6.66
10. 1.10 - 1.10/7.76
11. 0.21 - 0.21/7.97
Total 50.62 42.65 7.97
Table 1: Stage-wise Landuse and Reclamation Area (ha)
S.N. Land use category Present (1st year)
5th year End of Mine Life
Post Mining
1 Backfilled Area (Reclaimed with plantation)
0 0 0 0
0 0 0 0
2 Excavated Area (Not reclaimed)/void
60 80 101.7 101.7
3 Ext. OB dump (Reclaimed with plantation)
35 100 175 175
0 25 110 175
4 Reclaimed Top soil dump 0 0 0 0
0 0 0 0
5 Green Built Area 0 0 0 0
6 Undisturbed area (brought under plantation)
319.63 234.63 137.93 137.93
0 10 125.93 137.93
7 Roads (avenue plantation) 25 25 25 25
0 0 17 17
8 Area around buildings and Infrastructures
10 10 10 10
0 0 3 3
Total 449.63 449.63 449.63 449.63
Table 2: Stage-wise Cumulative Plantation
Sl.No. year Green Belt External
Dump(OB + Top Soil)
Backfilled area
Others (undisturbed
area/etc.) Total
Area (ha)
No. of
trees
Area (ha)
No. of trees
Area (ha)
No. of
trees
Area (ha)
No. of trees
Area (ha)
No. of trees
1 1st year
0 0 0 0 0 0 0 0 0 0
2 3rd year
0 0 0 0 0 0 0 0 0 0
3 5th year
0 0 25 62.5 0 0 10 25 35 87.5
4 End of mine life
0 0 110 275 0 0 145.93 364.825 255.93 1
5 Post mining
0 0 175 437.50 0 0 157.93 394.825 332.93 832.33
Table 3 : Post-mining Landuse pattern of ML/Project Area (ha)
S.N. Land use during mining
Land use (ha)
Plantation Water Body
Public use Undisturbed Total
1 External OB Dump 175 0 0 0 175
2 Top soil dump 0 0 0 0 0
3 Excavation 0 101.7 0 0 101.7
4 Roads including embankment
17 8 25
5 Built up area 3 0 7 0 10
6 Green Belt 0 0 0 0 0
7 Undisturbed Area 137.93 0 0 0 137.93
Total 332.93 101.7 15 0 449.63
(A) FORESTRY CLEARANCE
TOTAL ML/PROJECT AREA (ha)
TOTAL FORESTLAND (ha)
Date of FC
Extent of forestland
Balance area for which FC is yet to be obtained
Status of appl. for diversion of forestland
If more than one, provide details of each FC
449.63 Nil Not Applicable
Not Applicable
Not Applicable
Not Applicable
GENERAL CONDITIONS AND ADDITIONAL POINTS OF TOR
The following general points noted: (i) All documents should be properly indexed, page numbered. (ii) Period/date of data collection should be clearly indicated. (iii) Authenticated English translation of all material provided in Regional languages. (iv) After the preparation of the draft EIA-EMP Report as per the aforesaid TOR, the
proponent shall get the Public Hearing conducted as prescribed in the EIA Notification 2006 and take necessary action for obtaining environmental clearance under the provisions of the EIA Notification 2006.
(v) The letter/application for EC should quote the MOEF file No. and also attach a copy of the letter prescribing the TOR. (vi) The copy of the letter received from the Ministry on the TOR prescribed for the project should be attached as an annexure to the final EIA-EMP Report. (vii) The final EIA-EMP report submitted to the Ministry must incorporate the issues in TOR
and that raised in Public Hearing. The index of the final EIA-EMP report, must indicate the specific chapter and page no. of the EIA-EMP Report where the specific TOR prescribed by Ministry and the issue raised in the P.H. have been incorporated. Mining Questionnaire (posted on MOEF website) with all sections duly filled in shall also be submitted at the time of applying for EC.
(viii) General Instructions for the preparation and presentation before the EAC of TOR/EC projects of Coal Sector should be incorporated/followed.
(viii) The aforesaid TOR has a validity of two years only.
The following additional points are also to be noted:
(i) Grant of TOR does not necessarily mean grant of EC. (ii) Grant of TOR/EC to the present project does not necessarily mean grant of TOR/EC to the captive/linked project.
(iii) Grant of TOR/EC to the present project does not necessarily mean grant of approvals in other regulations such as the Forest (Conservation) Act 1980 or the Wildlife (Protection) Act, 1972. (iv) Grant of EC is also subject to Circulars issued under the EIA Notification 2006, which are available on the MOEF website: www.envfor.nic.in
______
CHAPTER – I
INTRODUCTION 1.0 GENERAL
The proposed Junad Extension OC Project is an extension of existing Junad OC
mine in Junad block located on the western limb of Wardha Valley Coalfield in
Yeotmal district of Maharashtra. The P.R. for Junad OC mine was prepared by
CMPDI in October, 1989 and was sanctioned by the WCL Board in May, 1990 for
a capital of Rs. 19.148 Crores for a production capacity of 0.32 Mty. The actual
mining operations at the project could be started in November, 1998 due to
delay in land acquisition. This is expansion of existing Junad Opencast with mine
able reserve of 6.13 Mt and with maximum coal production target of 1.50 MTPA.
The Form – 1 was submitted to MOEF &CC vide letter no. WCL/HQ/ENV/11-
C/213-A dated 28.06.2014. The project was discussed in the 21st EAC meeting
held on 19.09.2014. As per the minutes of the meeting of EAC, the project was
recommended with generic TOR. Subsequently Generic ToR was issued vide
Letter No. J- 11015/225/2014 – IA. II(M) dated 21.11.2014. As indicated in the
aforesaid TOR, the PH has been completed on 05.02.2013. Based on the minutes
of PH and generic TOR, this EMP has now been prepared for obtaining
Environmental Clearance from Ministry of Environment, Forests & Climate
Change.
1.1NEED OF THE PROJECT
There is a substantial gap between demand and availability of coal for the
mines of WCL as a whole. It is in national interest to open new mines/projects &
to go for expansion of existing projects urgently so as to meet the requirement of
coal for power and various other sectors.
The justification of this mine has been studied in the light of estimated demand
for non-coking coal from power sector in Maharashtra and production forecast
from existing, completed and ongoing projects of WCL.
1.2 LOCATION & COMMUNICATION
The Junad Block, covering an area of about 4.05 sq.km is located on the
western limb of Wardha Valley Coalfield and lies in the East of Ukni/Pimpalgaon
Block and south of New Majri – Chargaon block across Wardha river. The area is
bounded by Longitude 79o 3' 9" and 79o 5' 00" E and Latitude 20 deg 1' 5" and
20o 4' 10" N. It is situated in Wani Tahsil of Yeotmal District, Maharashtra and is
covered by Survey of India Toposheet No. 55 P/4.
Junad Block is an interior of under developed region and communication, either
by rail or road, does not exist. However, the block is presently connected by a 3
km fare-weather road with Aheri village which, in turn, is connected with Wani
town towards North-West by a 19 km metalled road. The block may also be
approached by a 3 km road from Ukni/Pimpalgaon project which is being
connected with Wani town via Bhalar village.
1.3 TOPOGRAPHY & DRAINAGE :-
The area of Junad Extension OC Mine exhibits gently undulating topography.The
general slope of the ground is from west to east. The HFL of Wardha river
recorded in New Majri in 1979 was 190.74m and a major portion of the proposed
area is below HFL. The external OB dump of existing Junad OC mine is 15-45 m
high, located in the dip-side of mine.
Junad Block exhibits moderately undulating topography. The elevation varies
from 180.83 m to 195.18 m. The Wardha river flowing from north to sourth is the
main drainage channel of the area. Considerable area of the block including
the potential opencast area for expansion is below HFL 190.74 m of Wardha river
as per national grid.
1.4 CLIMATE :-
Junad Block has extreme climate with maximum temperature of 48oC during
summer months and about 10oC during winter months. The average annual
rainfall is about 1250 mm. The bulk of rainfall takes place during wet months viz.
July, August and September. The maximum rainfall in a day of 24 hrs. was 249.4
mm recorded in Chandrapur on 14.9.1959. The direction of wind is mainly South-
Westerly, Westerly and North-Westerly.
1.5 PRESENT LAND USE PATTERN :-
The entire land to be acquired for extension of the Junad OC project is covered
by black cotton soil and is very fertile and is generally used for growing mainly
the cash crops like cotton, sugarcane, chillies etc apart from standard
agricultural products like rice, wheat & jawar. No village is falling in the proposed
leasehold boundary of the project. All the land losers will be given
compensation as per Company’s norms.
1.6 SITE DESCRIPTION: -
The study area has been divided into two heads Core Zone
Buffer Zone
a) Core zone: The core zone consists of the mining leasehold area where
mining and allied activities take place. The core zone comprises of 449.63 ha of
land. The land usage is given below.
Sl.
No
Land Particulars Total Land
1. Agricultural land 443.53 ha
2. Waste Land (Govt. Land) 6.10 ha
3. Forest Land -
Total 449.63 ha
b) FEATURES IN BUFFER ZONE
Sl. No. FEATURES DETAILS DISTANCE FROM
MINE
1 Industries Nil Nil
2 Railway Lines Wani Railway Siding About 9.0 km
3 State Highway State Highway No.- 84 About 5.0 km
4 Other Coal Mines Ukni OC, Pimpalgaon
OC , Kolar Pimpri OC
3.0 – 5.0 km
5 Water Bodies Wardha River 125 m from mine
boundary
6 Human Settlement 40 villages & WCL township within buffer zone
1.7 SOURCES OF DATA
This report has been formulated using various data from the following
sources:
Sl.
No.
Type of Data Sources
1 Mining and economic
parameters and other
miscellaneous data
CMPDIL and Wani North Area,
WCL.
2 Environmental data including
meteorological data, air
quality, dust fall rate, water
quality and noise level data.
Environmental-data generation
for proposed Junad Extn.
(Deep) OC of Wani North Area
of WCL, Maharashtra carried
out by CMPDI.
3 Socio-economic study & Land
use/cover mapping buffer
zone.
Census data & base line Socio -
Economic survey.
4 Flora and fauna Survey Report prepared by the
competent authority in this field.
5 Surface hydrology and
hydrogeology
CMPDIL, RI- IV, Nagpur.
6 Meteorological data Environmental-data generation
for Junad. Extn (Deep) OC of
Wani North Area Maharashtra
carried out by CMPDI.
7 Land use/cover mapping core
zone.
As per State Govt. Record, data
supplied by the concerned
WCL area office.
CHAPTER- II PROJECT PROFILE
2.0 REGIONAL GEOLOGY
Regional geological sequence of coalfield is as follows
TABLE No1
Age Formation Lithology
Recent to Sub-recent Detrital mantle Black cotton soil, sandy soil,
Kankar, etc.
Upper Cretaceous to
Eocene
Deccan Trap Basalt
------------UNCONFORMITY ------------
Cretaceous Lametas Cherty Limestone, silicified
sandstone
------------UNCONFORMITY ------------
Upper Permian Kamthi Red, brown, medium to coarse
grained sandstone, variegated
clay and shale bands.
------------UNCONFORMITY ------------
Age Formation Lithology
Lower Permian Barakar Predominantly grey to white,
medium to coarse grained
sandstones with minor shales,
carbonaceous shales and one
thick (15-25 m) coal seam.
Lower Permian – Upper
Carboniferous
Talchir Greenish to grey coloured
sandstone, siltstones and
shales.
------------UNCONFORMITY ------------
Precambrian Sullavai White to light brown quartzitic
sandstones, conglomerates.
Pakhal Grey, bluish or pinkish
limestones and cherts
------------UNCONFORMITY ------------
Archaean Metamorphics Gneisses and Schists
BROAD STRUCTURE OF THE BASIN
The major structural feature of the Coalfield is a well defined anticlinal
configuration having central non-coal bearing area with (a) eastern coal
bearing limb (from Belgaon block in the north to Sasti Dhuptala in south), (b)
western coal bearing limb (Yekona to Mugoli in the South and (c) three
separate narrow coal bearing "rifts" namely (i) Rajur-Chinchala (ii) Ghonsa-
Kumbharkhani and (iii) Markir-Mangli in the western part of the Coalfield.
COAL BEARING FORMATION
The coal bearing Barakar formation overlies Talchir sediments conformably and
is overlapped by Kamthi formation unconformably. The thickness of Barakars
varies from 12.78 to 133.55 m.
STATUS OF EXPLORATION
MECL drilled 55 boreholes in addition to 4 boreholes of D.G.M.(MS). 2 more
boreholes drilled by CMPDI for coal depth determination. The details of
boreholes are given in Table-5.3.
TABLE No.2
Drilling Agency No. of Boreholes Meterage Name of Geological Report
MECL 55 (MWJ-Series) 8546.00
Geological Report on
Exploration for Coal, Junad
Block, MECL, June-1990
DGM (MS) 4 (JUD-Series) 716.53 -
CMPDI 2 (CMJU-Series) 79.00
Geological Note on
Production Support Drilling in
a part of Junad OC, CMPDI,
Sept.2001
Total 61 9341.53
DENSITY OF BOREHOLES
In all, 61 boreholes fall in 4.05 sq.km. area of Junad Block. Density of boreholes is
therefore 15 boreholes per sq.km. However, borehole density for quarry area is
12 boreholes per sq.km.
SURVEYING
PREVIOUS SURVEY WORK
The co-ordinates and reduced levels of boreholes were determined with
reference to Base stations A & B located at 2 km in the west outside the block
boundary. The details of these base stations are furnished below.
TABLE No.3
Station Total Latitude
(m)
Total
Departure (m)
R.L. in (m) Remarks
A 10,000.00 10,000.00 219.110 Common Pillar
B 10,010.547 9,805.255 219.420 Common Pillar
WCB of A – B = 273 Deg. 06 Minutes 00 Second
Distance A-B = 195.030 m
Survey Work
The reduced levels of the base stations were fixed with reference to reduced
level of Niljai block which in turn were established with reference to reduced
levels of Ghughus Colliery. The bench mark at the Robertson Incline of Ghughus
Colliery with assumed R.L. of 215.93 m was reported as the origin by Colliery
authorities. As such, all the contour values and RLs of boreholes are determined
with reference to these assumed figures. It may be mentioned that the
topography of the area adjacent to Wardha River is constantly changing due to
action of the river water especially during the floods.
Transposition of Grid System from Local Grid to National Grid
In order to determine the co-ordinates of the boreholes in National Grid Co-
ordinates of four boreholes were determined in both the systems as detailed
below:
TABLE No.4
B.H. No. National Grid values Local Grid values
Northing (m) Earthing (m) R.L. (m) Northing
(m)
Earthing
(m)
R.L. (m)
MWJ-37 1089492.5248 3006636.4166 185.497 12696.18 10409.14 206.49
MWJ-38 1089199.0492 3006921.2580 183.052 12804.48 10240.41 205.05
MWJ-39 1088995.8795 3007239.7493 181.737 13120.24 10032.64 203.73
MWJ-20 1089366.1377 3006810.6422 184.492 13245.95 10692.16 212.05
The GTS bench mark is (-) 22.00 m below the R.L. of Temporary bench mark.
However, the various geological plan show both levels: local as well as G.T.S.
bench mark.
RELIABILITY OF DATA
Junad Opencast is presently a working mine. There is no major change
observed during mining as per structure interpreted. The density of borehole is 12
boreholes per sq.km which is reasonable considering the developed mine so far.
2.1 GEOLOGY OF THE MINING BLOCK
BRIEF GEOLOGICAL SETTING
The geological formation encountered in the present quarriable area are as
follows :-
Formation Thickness (m) Lithology
Minimum Maximum
Soil
3.00 24.00
Black clayey soil and sandy soil (MWJ-24) (MWJ-27)
Kamthis
6.00 101.00 Yellow, brown, red, yellowish white
ferruginous sandstone, occasionally
grey sandy shale/shale. (MWJ-37) (MWJ-12)
Barakar 12.78 133.55 Grey white medium to grey
sandstone with shale, coal seams with
shaly coal, etc.
(MWJ-20) (MWJ-27)
SEQUENCE OF COAL SEAMS & PARTING
The coal seam in Junad Block is thick Composite Seam, ranges in thickness from
14.82 m (MWJ-50) to 18.83 m (MWJ-24). MECL, however, divided seam in two
parts as Top Section and Bottom Section by a parting ranging from 0.09 m
(MWJ-24) to 2.21 m (MWJ-26).
GEOLOGICAL STRUCTURE
Geological structure of Junad block is based mainly on sub-surface data of
boreholes. Strike is mainly NW-SE, coal seam dips due south west and gradient
varying from 1 in 2.5 to 1 in 3.5 in quarriable area.
Only 3 faults viz. Fault F3-F3, F4-F4 and F5-F5 are intersected in quarry. The fault
F3-F4 is minor in nature and throw is 5 m. The throw of F4-F4 & F5-F5 is 20 m
towards NE and 40 m SW respectively.
DESCRIPTION OF FAULTS
Designated
No. of Fault
Strike Throw Linear Extension Nature and evidence
F3- F3 N40oW
-S40oE
5 m
toward
s SW
0.95 km, dies out
on either sides
1. Strike fault
2. Intersected in boreholes
MWJ-12, and MWJ-27
resulting in reduction of
seam thickness.
F4- F4 N63oW
-S63oE
to
N25oW
-S25oE
20 m
toward
s NE
0.875 km, abuts
against F5 on
either sides.
1. Oblique fault
2. Intersected in borehole
MWJ-21 resulting in
reduction of seam
thickness.
F5- F5 N45oW
-S45oE
40 m
toward
s SW
1.115 km, join F4
in the NW and
dies out. It may
continue in SE
direction
beyond the
block boundary
1. Strike fault
2. Intersected in boreholes
MWJ-52 & 55 resulting in
omission of coal seam.
INTRUSIVES OF SURFACE BURNING
There is no evidence of any intrusives nor any effect of burning in any borehole
analysis.
DESCRIPTION OF COAL SEAM
SEAM THICKNESS RANGE & VARIATION PATTERNS
The coal seam in Junad Block is thick Composite Seam ranges in thickness from
14.82 (MWJ-50) to 18.83 (MWJ-24). MECL, however, divided seam in two parts as
Top Section and Bottom Section by a parting ranging from 0.09 (MWJ-24) to 2.21
in (MWJ-26). However, for opencast proposed quarry, it is thick one Composite
Seam. The parting is generally composed of shale, carbonaceous shale and
occasionally intercalation of sandstone and shale.
The summarized details of coal seam under proposed quarry are as follows:-
1. The range of quarriable
thickness
14.82 m (MWJ-50)
to
18.83 m (MWJ-24)
(including parting)
2. The depth range 20.57 (CMWJU-1) to 205.82 (MWJ-27)
3. The parting range 0.09 m (MWJ-24) to 2.21 m (MWJ-26)
PARTING
Parting between Top Section and Bottom Section varies from 0.09 m to 2.21 m
and consist of shale, carb. shale and occasionally intercalation of shale and
sandstone.
ROOF & FLOOR CHARACTERISTICS
The immediate roof of seam is mainly carbonaceous Shale, occasionally
shale/sandy shale. The floor is mainly sandstone or sandy shale.
DIRT BANDS BEHAVIOUR
The distribution of dirt bands is as follows :-
Section Carb. Shale Shale Band
No. Total
Thickness (m)
% No. Total
Thickness (m)
%
Top
Section
1-5 0.10-1.05 1-16 Nil to 6 N il – 0.90 Nil – 9
Bottom
Section
Nil – 3 Nil – 0.25 Nil – 4 Nil to 4 N il – 0.82 Nil – 12
For details of distribution of dirt bands see Annexure-IVA & IVB (Top & Bottom
Section)
QUALITY PARAMETERS
The thickness of Composite Seam including the thickness of Top Section, Bottom
Section and intervening parting as intersected in 6 boreholes, varies from 14.82
m (MWJ-50) to 18.83 (MWJ-24). The following table furnishes the summarized
quality details on equilibrated basis (determined and calculated) of boreholes
falling within and in the vicinity of quarry area.
Quality Parameters – Composite Seam
Grade
M% Ash% VM% G.C.V.
(K.Cal./kg)
U.H.V.
(K.Cal./kg.)
MWJ-10 16.40 7.6 22.5 28.8 5390 4745 D on 60% RH & 40oC
MWJ-13* 17.99 7.7 24.0 - - 4525 D
MWJ-22 17.28 7.2 25.3 - - 4361 D
MWJ-24 18.83 8.5 25.5 - - 4362 D
MWJ-30* 15.71 6.7 29.7 25.6 4800 3877 E on 60% RH & 40oC
MWJ-35* 15.89 5.3 29.5 - - 3920 E
MWJ-38 15.87 7.0 26.4 27.0 5060 4291 D on 60% RH & 40oC
On Equilibriated BasisB.H. No. Effective
Thickness
QUALITY OF ROM COAL
The present practice of mining in Junad Opencast is to mine whole coal seam
from roof to floor. The parting between the Top Section and Bottom Section is
practically not possible to remove because of its steep gradient. Therefore,
quality (including parting) has been assessed for the boreholes falling within the
proposed quarry are given in the following table No.5.11. The dilution of 5 cm at
each contact point is also considered at roof and floor of seam.
RANGE OF COAL QUALITY OF UNDILUTED & DILUTED COAL OF ROM
B.H. No.
Thick. (m)
ONLY COAL (WITHOUT DILUTION) WITH DILUTION 5 cm AT EACH CONTACT
Remarks
M% Ash% UHV K.Cal/kg
Gr. GCV K.Cal/kg
M% Ash% UHV K.Cal/kg
Gr. GCV K.Cal/kg
MWJ-10
17.59 7.16 26.6 4241 D 5010 7.12 27.0 4191 E 4978
MWJ-22
18.76 8.31 36.65 2696 F 3897 8.26 37.02 2651 F 3870
MWJ-24
18.83 8.45 25.46 4220 D 4930 8.42 25.7 4191 E 4912
MWJ-26
16.84 5.89 32.76 3566 E 4615 5.88 33.04 3529 E 4591 Including parting of 2.21m between Top & Bottom Section
MWJ-38
16.8 6.75 28.86 3986 E 4857 6.72 29.21 3942 E 4829
MWJ-50
14.82 6.36 24.56 4633 D 5319 6.33 24.94 4585 D 5287
From the above table, the weighted quality of coal without dilution and with
dilution is as follows:-
Particulars Without
dilution
With dilution of
5 cm at each contact point
M% 7.22 7.18
Ash% 29.29 29.62
U.H.V. (K.Cal/kg) 3862 3822
Grade E E
G.C.V. (K.Cal/kg) 4748 4724
Special Tests
Results of special tests carried out for MWJ boreholes are furnished in the
following table.
Ultimate Analysis
The ultimate analysis of borehole is available and the details are shown in Table
below.
B.H. No. Thick.
(m)
Ultimate Analysis
Carbon
%
Hydrogen
%
Nitrogen
%
Sulphur
%
Oxygen
%
MWJ-10 17.59 78.88 4.30 1.66 0.24 15.22
MWJ-11 18.92 77.57 4.24 1.67 0.21 16.31
MWJ-11 13.10 80.68 4.25 1.56 0.47 13.04
MWJ-30 16.91 81.32 4.59 1.98 0.31 11.80
MWJ-40 17.96 81.37 4.98 1.65 0.21 11.83
From the available analytical data on 60%RH & 40oC.
Ash Fusion Temperature Range
The data pertaining to Ash Fusion Range is also available for 5 boreholes. The
summarized details are given below:-
B.H. No. Thick.
(m)
Ash Fusion Temperature Range
Initial
Deformation
Temp. (oC)
Hemispherical
Deformation Temp.
(oC)
Flow
Temp.
(oC)
MWJ-10 17.59 1390 >1400 >1400
MWJ-11 18.72 1290 >1400 >1400
MWJ-17 13.10 1230 1370 >1400
MWJ-30 16.91 1360 >1400 >1400
MWJ-40 17.96 1350 >1400 >1400
Ash Analysis
The Ash analysis is also available for 5 boreholes. The details are shown in the
following table.
B.H. No.
Thick. (m)
SiO2 %
Al2O3 %
Fe2O3 %
TiO2 %
CaO %
MgO %
MnO %
P2O5%
SO2%
Alkalies by
difference
Total %
MWJ-10
17.59 56.330 26.790 4.660 1.672 4.541 0.552 0.136 0.485 4.530 0.304 100.00
MWJ-11
18.92 52.650 25.750 5.000 1.420 7.290 0.450 0.081 0.753 6.358 0.248 100.00
MWJ-17
13.10 52.140 27.460 11.380 1.380 3.300 0.110 0.088 0.902 3.000 0.240 100.00
MWJ-30
16.91 55.175 25.980 4.395 1.685 7.061 0.852 0.130 0.590 3.700 0.432 100.00
MWJ-40
17.96 59.340 26.235 6.710 1.360 3.652 0.667 0.190 0.590 0.780 0.476 100.00
The data pertaining to total sulphur of Composite Seam for 14 boreholes and
sulphur distribution for 4 boreholes are given in the following table.
B.H. No. Depth of Coal Seam
(m)
Total
Sulphur %
Distribution
From To Pyritic % Sulphate % Organic %
MWJ-8 141.73 157.92 2.05 - - -
MWJ-9 134.58 151.29 1.58 - - -
MWJ-10* 58.08 75.67 1.37 1.16 0.05 0.16
MWJ-11 179.48 198.20 1.63 1.41 0.08 0.14
MWJ-13 89.36 110.05 1.28 - - -
MWJ-15 72.50 89.72 1.61 - - -
MWJ-16 86.44 102.51 2.25 - - -
MWJ-17 89.40 102.50 2.21 1.59 0.29 0.33
MWJ-24 42.57 61.40 0.75 - - -
MWJ-26 153.73 170.57 0.56 - - -
MWJ-29 174.96 193.21 1.20 - - -
MWJ-30 106.97 123.88 0.59 0.35 0.05 0.19
MWJ-35 30.00 46.72 0.91 - - -
MWJ-38* 24.88 41.68 1.09 - - -
H.G.I.
The H.G.I. for two boreholes MWJ-26 & 29 is available and given in the following
table.
B.H. No. Depth (m) Thick. (m) Seam/Section H.G.I.
From To
MWJ-26 153.73 160.88 7.15 Top Section 60
163.09 170.57 7.48 Bottom
Section
49
153.73 170.57 14.63 Top & Bottom
Section
52
MWJ-29 174.96 184.51 9.19 Top Section 54
184.61 193.21 8.60 Bottom
Section
50
174.96 193.21 17.79 Top & Bottom
Section
52
RESERVES
Based on the data of 61 boreholes drilled by different agencies in an area of
4.05 sq.km. of Junad Block, the opencast (up to 1:7 Coal : OB ratio line) and
underground reserves beyond 1:7 Coal : OB ratio line have been calculated.
AREAL EXTENT OF BLOCK
The limits of reserves estimation are as follows :-
East - Half sub-crop line in North. Eastern part near MWJ-5 & 53) and
also the eastern bank of Wardha river.
West- Seam position against the major fault F1-F1.
North- Southern bank of Wardha river.
South- Eastern bank of wardha river and also seam position against
the fault F1-F1.
The overall reserves of Junad block are grouped as under:-
1) Proved quarriable net in-situ reserves of composite seam estimated
from western bank of Wardha river to 1:7 Coal/OB ratio line.
2) Indicated quarriable reserves from half way of the sub-crop of coal
seam to western bank of river Wardha. This is for coal that occurs below
the river bed.
3) Proved underground net in-situ reserves separately for top and bottom
sections beyond 1:7 coal to OB ratio line.
4) Proved quarriable reserves in the area between eastern bank of
Wardha river and 1:7 Coal: OB ratio have been estimated while the
reserves of coal located below the river bed i.e. between half sub-crop
and western bank of river are grouped under indicated category.
5) For estimating the net geological reserves under quarriable category
and to arrive at the effective thickness of coal, obvious dirt bands of
thickness more than 0.15 are excluded. The bands having thickness less
than 0.15 m however are included. The carbonaceous bands less than
1.00 m are included and more than 1.00 m are excluded to get the
effective thickness.
Total 9 Sectors, Viz. Q1 to Q5 under opencast category and U1 to U4 a
underground category have been identified based on the faults, OCP – UG
limit i.e. 1:7 coal to Overburden ratio line (See Plate – V).
Junad Block is divided into two parts because of upthrown portion by fault F6-F6.
The downthrown portion can be named as river side part with sectors as Q1, Q4
quarriable and underground reserves in U1 & U2 sectors these reserves have not
been considered for the present Junad Extension OC proposed project as
separate mine has to be planned in future.
The upthrown block of fault F6-F6 is the main Junad block consists of sectors Q2,
Q3, Q5 (quarriable) and U3 & U4 (underground) of which only Q3 and part U3
are considered for the present Junad Extension OC project report.
Sector boundaries –
Sector Q3 :
East - Incrop and fault F4-F4 and Wardha river barrier
West - 1:7 Coal : Overburden ratio line.
North - Wardha river barrier.
South - 1:7 Coal:Overburden ratio line and Wardha river barrier.
Sector U3 :
East - Sector Q3
West - Fault F1-F1
North - Wardha river barrier.
South - Sector Q3 & U4 and Fault F1-F1
Sectorwise Net Geological reserves in Junad Block
(Figures in Mt)
OPENCAST (Upto 1:7
Coal/OB Ratio line
UNDERGROUND
Beyond 1:7 to Fault F1-F1
Sector Proved Indicate
d
Total Sector Proved Indicated Total
Q1 3.839 - 3.839 U1 7.168 - 7.168
Q2 0.577 - 0.577 U2 - 1.683 1.683
Q3 19.689 - 19.689 U3 37.254 - 37.254
Q4 - 4.418 4.418 U4 - 1.489 1.489
Q5 - 6.991 6.991
Total 24.105 11.409 35.514 Total 44.422 3.172 47.594
GRAND TOTAL 83.108
As stated above, only Sectors Q3 & U3 considered for present Junad Extension
OC, the Net Geological reserves of these sectors are as follows of which only
44.018 Mt are below 250 m depth.
Particulars Sector Total
Q3 U3
Incrop to 1:7 Coal:OB Ratio line 19.689 - 19.689
Beyond 1:7 Coal:OB Ratio line
to
250 m Depth
- 24.329 24.329
Sub-Total 19.689 24.329 44.018
Beyond 250 m depth sub-total - 12.925 12.925
Total 19.689 37.254 56.943
BLOCK BOUNDARIES
The proposed Junad Extension OC mine has been envisaged in Junad block
and is a dip side extension of the existing Junad OC Project. Geological
strucuture of Junad block is based mainly on sub-surface data of boreholes.
Strike is mainly NW-SE, coal seams dips due south-west with gradient varying
from 1 in 2.5 to 1 in 3.5 in quarriable area. It is proposed to deepen existing
Junad OC mine from the floor limit of the quarry as per R.C.E. report (88 m depth
100 m FRL) to 170 m depth about 1:10 coal:OB ratio line (20 m FRL) and will be
named as Junad Extension OC. The geological block boundaries of Junad
block is as follows :
a) Junad Block
East : Half sub-crop line in north-eastern part near boreholes MWJ-51 & 53 &
eastern bank of Wardha river.
West : Seam position against the major fault F1F1
North : Southern bank of Wardha River.
South : Eastern bank of Wardha River and also seam position against the fault
F1F1
Quarry Boundaries
Quarry Boundaries of existing Junad OC Mine as per sanctioned R.C.E. report -
North : Safe distance of 125 m from Wardha river.
South : Safe distance of 125 m from Wardha river
East : Floor of decoaled existing Junad OC mine as on 1.4.2004
(as given by Area Plan)
West : Projected floor as on 1.4.2006 (100m floor contour line, 88 m
depth)
At present, existing Junad OC mine is being worked in Junad geological block.
The Dip side limit of existing Junad OC mine is fixed at 88 m depth which
corresponds to about 100m FRL. Different alternatives have been done in Sector
Q3 and Sector U3 to arrive at an optimum stripping ratio with sufficient reserves
for mining. Alternative 1a, 1b, 1c are studied in Sectors Q3/U3 by deepening of
existing Junad OC mine.
The details of the alternatives done are given in the table below-
ALT. No.
Quarry
Quarry Boundaries Depth (m) COAL (Mt)
OB (Mm3)
SR (m3/t)
Eastern (rise)side
West (Dip) side
South boundary
North boundary
Min Max
(1a)
Quarry
in
Sector
Q3
Floor of
composit
e seam of
existing
quarry as
on
31.3.2006
(RCE limit)
150m
depth
(40 m
FRL)
Keeping
quarry
surface
at 125m
distance
from
Wardha
river
Keeping
quarry
surface
at 125m
distance
from
Wardha
river
88
150
4.18 28.35 6.78
(1b)
Quarry
in
Sector
Q3
Floor of
composit
e seam of
existing
quarry as
on
31.3.2006
(RCE limit)
170m
depth
(20 m
FRL)
Keeping
quarry
surface
at 125 m
distance
from
Wardha
river
Keeping
quarry
surface
at 125 m
distance
from
Wardha
river
88
170
6.13 50.62 8.26
(1c)
Quarry
in
Sector
Q3
Floor of
composit
e seam of
existing
quarry as
on
31.3.2006
(RCE limit)
200m
depth
(-10m
FRL)
Keeping
quarry
surface
at 100 m
distance
from
Wardha
river
Keeping
quarry
surface
at 100 m
distance
from
Wardha
river
88 200 7.75 70.80 9.13
Alternative IB is selected on the basis of conservation point of view and
increased reserves resulting in increased life of the project and also from
optimum stripping ratio point of view. The selection of this alternative is also due
to lack of dumping space in the dip side of the block. The mineable reserves
and stripping ratio of Alternative I B considered in this PR is summarized below:-
Particulars OB (Mm3) Coal (Mt) S.R. (m3/t)
Alternative I B. depth 170
m, dip side FRL limit 20 m 50.62 6.13* 8.26
* Reserves/Stripping Ratio is considered beyond the Quarry Floor limit of
sanctioned R.C.E. of existing Junad OC mine and excludes rehandling of existing
dipside OB dump.
Eastern Boundary (Rise side boundary)
The eastern boundary of the main extension quarry will be the decoaled existing
Junad OC mine as on 1.4.2006 and half subcrop of the composite coal seam in
virgin area in north direction along strike and along fault F4-F4 in south.
Western Boundary (Dip side boundary)
The composite coal seam is dipping in west direction and west side quarry floor
boundary is proposed at 170 m depth at the floor of composite seam which
corresponds to average 20 m FRL as per National Grid.
Northern Boundary
Wardha river is flowing along the northern boundary of Junad block. The floor of
the quarry is proposed such that the quarry surface in north direction is kept at a
safe distance ranging from 125 m from Wardha river. Between surface of the
quarry in north direction and Wardha river, there is a proposed embankment
having width 30 m at the top and height ranging from 6-10 m. Safe distance of
25 m and 15 m is kept from the toe of embankment to the edge of Wardha river
and quarry surface respectively.
Southern Boundary
Wardha river is also flowing along the south-eastern part of Junad block. Thus,
the floor of the quarry is proposed such that the quarry surface is kept at a safe
distance of 125 m from the Wardha river. Between surface of the quarry in south
direction and Wardha river, there is a proposed embankment having width 30 m
at the top and height ranging from 6-10 m. Safe distance of 25 m and 15 m is
kept from the toe of embankment to the edge of Wardha river and quarry
surface respectively. A 400 kV high tension line is passing across the Junad block
at a distance of about 500 m from the southern quarry surface limit. Thus, the
boundary fixation of the extended quarry in southern side is limited by Wardha
river, 400 kV line, safety embankment and also considering optimum quarry
shape avoiding tail shape of the quarry in dip side of southern limit.
MINE PARAMETERS
In Junad Extension OC mine, it is proposed to extend existing OC mine in dip
side upto 170m depth.
The mine parameters of the proposed extended quarry are detailed below:-
Sl.
No.
Particulars
(As on 1.4.2006)
Extension
Quarry
6.2.1
a)
b)
Face length (km)
On the floor of composite seam
On Surface
1.15 – 1.28
1.50 – 1.70
6.2.2
a)
b)
Depth (m) upto floor of
composite coal seam
Initial
Final
30 - 88
170
6.2.3
a)
b)
Width Below the decoaled void
of existing Junad Extn.OC
On the floor of composite seam
On Surface
250-325
400-525
6.2.4
a)
b)
Area of the quarry
On floor (ha)
On Surface (ha)
35.20
70.50
MINEABLE RESERVES
GROSS RESERVES IN PROPOSED JUNAD OC MINE
The upthrown block of fault F6 – F6 is the main Junad block which consists of
Sectors Q2, Q3, Q5 (opencast) and Sectors U3 & U4 (underground).(Please refer
Geological Plan of Junad OCP of WCL) This division of sectors in Junad block is
based as per Geological Report of Junad block, June, 1990. As per this G.R.,
reserves upto 1:7 coal:OB ratio line are defined as opencast sectors, and
reserves beyond 1:7 coal:OB ratio line are considered as underground reserves.
However, due to application of hiring HEMMs, greater depths with higher
stripping ratio can be worked by opencast method of mining. Therefore, the
revised geological break-up is given below which considers opencast reserves
upto 250m depth. The proposed Junad extension OC mine has been planned
below the RCE limit of existing Junad OC mine upto a depth of 170m at the floor
of composite coal seam. Therefore, in this report the sectors earlier identified for
underground mining in the geological notes is proposed to be worked by
opencast method of mining upto a depth of 170m.
Sector Q2 is a very narrow patch, bounded between downthrow fault F4-F4 & F5-
F5. The net geological reserve of Sector Q2 is only 0.557 MT and considering its
width and strike, it is not viable for opencast coal mining.
Sector Q5 lies below the Wardha river in south-east direction. The net Indicated
geological reserve of Sector Q5 is 6.99 MT but the opencast mining can be done
only after the diversion of Wardha river.
Sector U4 is a small patch below Wardha river, bounded beyond 1:7 coal:OB
ratio line and boundary fault F1-F1. The net indicated a geological reserve of
Sector U4 is 1.489 MT.
Thereby Sectors, Q2, Q5 and U4 of main Junad block are not considered in this
PR for opencast coal mining.
The sectors considered in this PR are Sector Q3 & U3. The boundary of Sector Q3
& U3 are defined as under :-
Sector Q3 :
East - Incrop and fault F4-F4 and Wardha river barrier
West - 1:7 Coal : Overburden ratio line.
North - Wardha river barrier.
South - 1:7 Coal : Overburden ratio line and Wardha river barrier.
Sector U3 :
East - Sector Q3
West - Fault F1-F1
North - Wardha river barrier.
South - Sector Q3 & U4 and Fault F1-F1
In the proposed quarriable area, the coal seam has split in two sections namely
top section and bottom section with an intervening parting of average 0.8 m
thickness varying from 0.09 m to 2.21 m. Due to steep gradient, it is not feasible
to work this parting separately. In the existing Junad OC mine, the coal is being
extracted along with parting. It is therefore proposed in this report to extract the
top and bottom section of coal seam along with intervening parting as a
composite coal seam. The gross reserve in the proposed extended quarry has
been estimated considering coal thickness from roof to floor.
COAL BLOCKED UNDER VARIOUS HEADS
As stated above, only Sectors Q3 & U3 are considered for quarry planning in
proposed Junad Extension OC. The Net Geological reserve of these sectors up
to 250 m depth is 44.018 MT and upto major boundary fault F1-F1 is 56.943 MT.
The break-up of reserves in Sectors Q3 & U3 up to 250 m depth and beyond 250
m depth to boundary fault F1-F1 is given in following table.
Particulars Sector Total
Q3 U3
Incrop to 1:7 Coal:OB Ratio
line
19.689 - 19.689
Beyond 1:7 Coal:OB Ratio line
to 250 m Depth
- 24.329 24.329
Beyond 250 m depth - 12.925 12.925
Total
19.689
37.254
56.943
As per sanctiond RCE of Junad OC Mine in 1999, net geological reserves are
3.63Mt (3.26 Mt net mineable reserves). For Junad Extension OC, starting from
1.4.2008, 6.81 Mt net geological reserves (6.13 Mt net mineable reserves) are
proposed to be exploited. Therefore in total, 3.63 Mt + 6.81 Mt = 10.44 Mt
reserves from Sectors Q3 and U3 falls in quarriable area. Balance reserves in
Sectors Q3 and U3 upto major boundary fault F1-F1, is 46.503 Mt. and it falls in
the dip side and southern side of the proposed quarry.
MINING LOSS
To arrive at the mineable reserves from the gross reserves available in the
proposed extension quarry, following mining losses have been considered:-
i) 10% mining loss due to variation in seam thickness.
ii) Loss of 20 cm of coal at each contact point of coal seam thus
aggregating 40 cm (two contact points at roof and floor) which
corresponds to about 2.5% loss.
iii) 0.5% of coal loss for blasting for coal seam
iv) 0.5% loss due to spillage in coal transportation.
Considering the above mining losses, the net mineable reserves in Junad
Extension OC mine are as under:
Quarry
Gross
Geological
Reserves
(Mt)
Mining
Losses
(Mt)
Mineable
Reserves (Mt)
Quarry as per Alternative
IB, depth 170 m
7.086* 0.956 6.13
TARGET OUTPUT AND MINE LIFE
The proposed Junad Extension OC mine has been planned for a target
capacity of 0.60 Mt/annum. The parameters of opencast mine field and
technical conditions of its development make this target feasible with normal
indices namely strike length, width and depth of the excavated block, number
of coal seams, method of mining, location of equipment, deployment, etc. The
target production from extension quarry along with strike length and rate of
deepening are tabulated below:
Sl.
No.
Quarry Max.
target
Production
(Mt)
Depth
Range
(m)
Strike
Length
(Km)
Average
Rate of
deepening
(m/year)
1. Quarry as per
Alternative IB, depth
170 m
0.60 88-170 1.5 -1.70 8 – 9
From above it is clear that the maximum rate of deepening is about 8 – 9
m/year in proposed Junad Extension quarry.
In proposed Junad Extension OC mine, target production of 0.60 MT will be
achieved in Year-I i.e, in the year 2008-09. With a mineable reserve of 6.13 Mt
and target production of 0.60 Mty, the revenue life of the mine comes out to be
11 years. However for EC, the peak capacity assumed as 1.50 MTPA.
GEO-MINING CHARACTERISTICS
Seam Gradient
Geological structure of Junad block is based mainly on sub-surface data of
boreholes. Strike is mainly NW-SE, coal seam dips due south west and gradient
varying from 1 in 2.5 to 1 in 3.5 in quarriable area.
Geological Disturbances
Only 3 faults viz. Fault F3-F3, F4-F4 and F5-F5 are intersected in quarry. The fault
F3-F4 is minor in nature and throw is 5 m. The throw of F4-F4 & F5-F5 is 20 m
towards NE and 40 m SW respectively.
SELECTION OF MINING METHOD
The steep gradient of the seam (gradient 1 in 2.5 to 1 in 3.5) rules out the
application of dragline method of working and surface miner working in
proposed Junad Extension OC mine. Shovel-Dumper system has been
considered to be the most suitable method of opencast mining under the
prevailing geo-mining conditions. With Shovel-Dumper system, two stripping
methods are possible:
1. Inclined slicing method &
2. Horizontal slicing method
In steep gradient, positioning of HEMM is difficult in inclined slicing method as
the benches in coal are made parallel to the seam in this method. Hence this
method is ruled out in proposed Junad Extension OC mine. In horizontal slicing,
benches in coal are made horizontal and therefore there is no problem in
positioning of HEMM. In horizontal slicing method, the sump can be made either
on the bottom most horizontal bench in coal or in the roof of coal seam. With
the sump at the roof of coal seam, the coal and overburden benches with
proper grading can be worked in almost water-free condition throughout the
year. However, with this arrangement, initial excavation is high because of the
running slope of quarry is further reduced to this type of sump arrangement. It is
therefore proposed in this report to make the sump at the horizontal bench in
coal in one side of the quarry and to make the coal benches slightly grading
towards the sump.
Thus, the shovel dumper system of mining with horizontal slicing method is
recommended for the proposed extension project with sump at the bottom-
most horizontal bench in coal seam.
SEAM THICKNESS RANGE & VARIATION PATTERNS
The coal seam in Junad Block is thick Composite Seam ranges in thickness from
14.82 (MWJ-50) to 18.83 (MWJ-24). MECL, however, divided seam in two parts as
Top Section and Bottom Section by a parting ranging from 0.09 (MWJ-24) to 2.21
in (MWJ-26), However, for opencast proposed quarry, it is thick one Composite
Seam. The parting is generally composed of shale, carbonaceous shale and
occasionally intercalation of sandstone and shale.
The summarized details of coal seam under proposed quarry are as follows:-
Sl.No. Particulars Minimum Maximum
1. The range of
quarriable
thickness
14.82 m (MWJ-50) 18.83 m (MWJ-24)
(including parting
2. The depth range 20.57 (MWJ-37) (MWJ-10)
3. The parting range 0.09 m (MWJ-24) 2.21 m (MWJ-26)
Because of very steep gradient of coal seam (1 in 2.5 to 1 in 3.5), it is difficult to
remove the parting between top and bottom section even in horizontal slicing
and with shovel dumper system with blasting method. In the existing Junad OC
mine, the coal is being extracted along with parting. In the Junad Extension OC
mine also, it is proposed to extract the entire composite coal seam along with
parting varying in thickness from 0.09m (MWJ-24) to 2.21m (MWJ-26). The quality
of coal has been assessed taking into account the mixing of parting with the
coal.
System Parameters – Bench Height, Elements of Mining System
Volume Regime
The proposed Junad Extension OC mine is an extension of existing Junad OC
Mine beyond RCE floor unit.
The access trench of existing Junad OC mine, will serve the entry to Junad
Extension OC mine also. Thus the Quarry of proposed Junad Extension OC will
be approached by the existing access trench of Junad OC mine.
To calculate the coal, OB and stripping ratio at different depths in Extension
quarry, cuts have been made at 100m FRL (Cut-I), 70m FRL (Cut-II), 40m FRL
(Cut-III), and upto 170 m depth line (Balance cut). The cut-wise OB and coal in
proposed Junad Extension OC is given below in Table below.
CUTWISE COAL, OB & STRIPPING RATIO (Volume Regime Table)
FOR JUNAD EXTENSION QUARRY (FROM 1.4.2008 ONWARDS)
Cut FRL (m) Mineable
Reserves
(Mt)
Total OB
(Mm3)
Stripping
Ratio (m3/t) From To
Cut-I Upto 100m FRL 1.05 14.23 13.55
Cut-II 140 70 2.14 18.78 8.77
Cut-III 70 40 2.24 16.56 7.39
Balance
Cut
40 20 0.70 1.05 1.50
(Upto 170m depth line)
TOTAL 6.13 50.62 8.26
Thus the total mineable reserve in the Junad Extension OC mine is 6.13 Mt with
an average stripping ratio of 8.26 m3/t.
Width and Height of Benches
The maximum height of benches in overburden considered in this report is 10m
which will be drilled and blasted in one go. In unconsolidated strata/alluvium
soil, the bench height is kept as 5m. In coal also, the height of the bench is
considered as 5m. The bench width considered in this report is 20m and 30m for
non-working and working benches respectively for planning purpose.
In final batter of the quarry, the height of the benches in consolidated strata is
10m and a berm of 5m width will be maintained between two benches.
However, in unconsolidated strata/alluvium soil, the bench height considered in
final batter is 5m and the bench width (berm) is 10m. Three to four transport
horizons will be maintained in the batter at an interval of 30m.
Slope of Benches and Quarry
i) During Mining Operation
The slope of individual benches depends on the type of strata. In this report, the
slope of individual bench is proposed as 45o in soil, alluvium and clay whereas it
is 70o in hard strata as well as in coal.
The overall slope of the quarry benches during mining operation varies from 10o
to 20o (from horizontal plane) due to multiple seams.
Rise side batter remains same in the quarry during mining operation or at the
end of the quarry. The overall angle of the rise side batter of existing Junad OC
mine varies from 20o to 35o.
ii) At the end of the quarry
The slope of individual benches in the batter at the end of quarry remains same
as that during mining operations i.e, 45o in soil , alluvium and clay and 70o in
hard strata and coal. The slope of the batter at the end of the quarry in dip side
is flatter in upper horizon because of unconsolidated strata like soil, clay, etc. In
deeper horizon, the angle of batter measured from horizontal plane is steeper
compared to upper horizon. It is 15o to 30o in upper horizon (in unconsolidated
strata) and 35o to 45o in hard strata. The slope of rise side batter is same as
discussed above under point (i).
Drilling and Blasting
The degree of fragmentation in opencast mine has to be optimized so that total
cost of drilling, blasting, excavation, transport and crushing as total system is
minimized. In order to reduce the excessive vibrations at nearby surface
structure, river, road, village, etc. and also to achieve satisfactory blasting
results, an optimized control blasting system depending upon rock formations
using combination of delays and relays will have to be evolved. It is further
recommended that at the time of actual excavation, proper study on ground
vibration should be made with scientific methods.
In proposed Junad Extension OC mine, the powder factor for OB and coal has
been worked out to be 3.0m3/kg and 7.0/t respectively in partial hiring
option.However, it is proposed in this report to undertake scientific study to
assess the powder factor for OB and coal. Adequate capital provision has been
made in this report for above study.
Mine Transport
Shovel Dumper system has been proposed in this report and the coal as well as
OB will be transported by dumpers/trucks.
Haul roads with proper gradient have been proposed for Quarry and the coal
will be transported by dumpers/trucks through these haul roads and existing
access trench of Junad OC mine from quarry to coal stock yard near the
access trench. The gradient of haul roads is proposed as 1:16.
For the transportation of OB, transport horizons (benches) have been proposed
in the dip side & side benches/batter. The OB from benches will be transported
by dumpers/trucks through these transport horizons and ramps to suitable
intervals will be made to join other benches with the transport benches. The OB
below the bottom-most transport horizon can also be transported through the
haul roads where the dump is in rise side.
SEQUENCE OF MINING
The Quarry proposed in Junad Extension OC mine, is below the existing
decoaled Junad OC mine. The total mineable coal and OB in extended Quarry
are 6.13 Mt and 50.62 Mm3 respectively and the stripping ratio works out to be
8.26 m3/t.
GEO - MINING PARAMETERS
Sl. No. Particulars EXTENSION QUARRY
1. FACE LENGTH (km)
a) On the floor of composite seam 1.15 – 1.28
b) On surface 1.50 – 1.70
2. DEPTH UPTO FLOOR OF COMPOSITE
SEAM(m)
a) Initial 30 - 88
b) Final 170
3. WIDTH BELOW THE DECOALED VOID OF
EXISTING OC (m)
a) On the floor of composite seam 250 - 325
b) On surface 400 – 525
4. AREA OF THE QUARRY (ha)
a) On the floor 35.20
b) On surface 70.50
5. Gradient of Seam 1 in 3
6. GRADE OF SEAM (WITH 5 CM
CONTAMINATION)
E
7. U.H.V. (WITH 5 CM CONTAMINATION) 3822
8. AVG. SEAM THICKNESS(m) 17
9. NET MINEABLE RESERVES (Mt) 6.13
10. Average stripping ratio (t:m3) 1:8.26
The shovel dumper system of mining with horizontal slicing method is
recommended for the proposed extension project with sump at the bottom-
most horizon bench in the coal seam.
2.2 WASTE DISPOSAL & REHANDLING OF EXISTING OB DUMP
Two external OB dumps are proposed in dip side of the extended quarry beyond
the major boundary Fault F1-F1 at a depth ranging from 350-400 m at the floor of
coal seam. The main external OB dump No.1 lies exactly in the dip side of
extended quarry from Aheri village in north to approach road for the project in
south. The dump No.1 is proposed keeping safe distance from Pragati Nagar
township, existing water pipeline, Wardha river and approach road to the
project. External OB dump No.2 is located on other side of approach road.
In addition, about 10.33 Mm3 of OB already dumped by existing Junad OC in dip
side of the quarry over coal bearing area where Junad Extension OCP is
proposed also requires to be rehandled. The capacity of external OB dumps
proposed is about 60.20 Mm3. Remaining 0.75 Mm3 of OB will be used is
construction of safety embankment. The break up of OB quantities in external OB
dumps is given in following table.
No. Dump Capacity in Mm3
0-30m 30 -60m Total
i) Dump – 1 25.70 16.92 42.65
ii) Dump – 2 5.80 2.17 17.55
Total 60.20
The entire extension quarry which is 50.62 M.Cu.m. of existing Junad OC mine is
dumped in dump no. 1 and 2 . About 10.33 M.Cu.m. of OB to be rehandled will
also be dumped in dump no.2 (9.58 M.Cu.m.) and also used for construction of
embankment(0.75 M.Cu.m.).
The external dumps have two benches each of 30m height and final angle of
slope is proposed to be kept at maximum 28o.
2.3 COAL HANDLING PLANT & SURFACE DESPATCH ARRANGEMENT
INTRODUCTION
A small coal handling plant is already in operation, installed at Pimpalgaon
project for Junad OCP. The same CHP will cater to the needs of Junad
extension OC. The CHP has facilities for crushing of coal to (-)200 mm size.
Despatch of coal from the CHP to the customer is being done by roadways.
Details are given in the following paragraphs.
COAL FLOW
Rear discharge dumpers or tipping trucks will carry coal from mine and
discharge on to the hopper of feeder breaker. Oversize material will be
broken inside the feeder breaker to crush the same to conveyable size of (-) 200
mm.
A conveyor C1 of 1200 mm wide has been provided below the feeder breaker
to collect (-) 200 mm size crushed coal from feeder breaker along with dust and
mucks from below the chain of feeder breaker.
The coal thus collected is conveyed by the belt conveyor C1 to a considerable
height and then allowed to fall in ground to create coal heap.
Coal heap, thus created, is being liquidated by front-end loaders and loaded in to
Customer’s trucks.
An electronic road weigh- bridge, with printout facility, has also been provided
for weighment, records of bills and despatches.
Provision has now being given in this report for storing of coal in over-head truck.
Loading hoppers, instead of creating coal heap. This will facilitate truck loading
and maintaining the quality of coal. Two numbers of 100te. over head truck
loading hoppers have been provided for this purpose. The conveyor C1,
discussed earlier, will be extended to load these hoppers.
Both the coal hoppers will be provided with a vibratory feeder at their discharge
end for even loading customer’s truck etc. from below these hoppers. The
hoppers will have PCC / reinforced flooring for better life.
Facilities like dust suppression and fire fighting have also been provided in the report.
All the equipment in the plant will operate on 415V, 3 phase, 50Hz. AC supply.
For this purpose a unitized sub station 630kVA, 3300V/440V has been provided.
All the gantries various houses and the CHP yard will be suitably illuminated. The
feeder breaker, the conveyors and vibratory screen will be sequentially
controlled.
2.4 PRE-MINING LAND USE
The total land within the proposed mine boundary of Junad Extension OC is
449.63 ha (existing land of Junad OC mine +proposed land for Junad Extension
OCP) whose break-up is given below:
Sl.No. Particulars Land in existing
Junad OC
Mine
Land to be acquired
under proposed Junad
Extn. OC Mine
Total
1. Tenancy Land 174.28 ha 269.25 ha* 443.53
2. Govt. Land - 6.10 ha 6.10
3. Forest Land NIL NIL NIL
TOTAL 174.28 275.35 ha 449.63 ha
*This 269.25 ha of land to be acquired includes 5.20 ha land of Kolar Pimpri
Extn.Project and 13.85 ha of acquired land by existing Pimpalgaon OC Project.
Both the projects are adjacent to Junad Extension OC Mine.
Thus, the total land involved in this project is 449.63 ha, out of which 174.28 ha
land has already been acquired in existing Junad OC mine and balance 275.35
ha will have to be acquired.
FORESTRY CLEARANCE
LAND USE PATTERN
During mining, land use pattern within the mine boundary for Junad Extension
OC (including existing Junad OC) would be as follows :-
S.No. Particulars Area (ha)
1 Total Quarry Area 101.70
2 External OB Dump 175
3 Infrastructure including approach road, etc. 15
4 Embankment 20
5 Colony 0
6 Area needed for rationalization & safe blasting zone 137.93
TOTAL 449.63
Land use pattern – During Mining Stage
Changes of Land Use during Mining:
TOTAL ML/PROJECT AREA (ha)
TOTAL FOREST LAND (ha)
Date of FC Extent of forestland
Balance area for which FC is yet to be obtained
Status of appl. for diversion of forestland
If more than one, provide details of each FC
449.63 Nil Not Applicable Not Applicable
Not Applicable Not Applicable
Sl. No. Particulars Area (ha)
1 Quarry Area 101.70
2 External OB Dump 175.00
3 Infrastructure includin approach road etc. 15.00
4 Diversion of Nala 00.00
5 Embankment 20.00
6 Area needed for rationalization & safe
blasting zone
137.93
TOTAL 449.63
Stage-wise Cumulative Plantation
Sl.No.
year Green Belt External
Dump(OB + Top Soil)
Backfilled area
Others (undisturbed
area/etc.) Total
Area (ha)
No. of
trees
Area (ha)
No. of trees
Area (ha)
No. of
trees
Area (ha)
No. of trees
Area (ha)
No. of trees
1 1st year 0 0 0 0 0 0 0 0 0 0
2 3rd year 0 0 0 0 0 0 0 0 0 0
3 5th year 0 0 25 62.5 0 0 10 25 35 87.5
4 End of mine life
0 0 110 275 0 0 145.93 364.825 255.93 1
5 Post mining
0 0 175 437.50 0 0 157.93 394.825 332.93 832.33
Post-mining Landuse pattern of ML/Project Area (ha)
S.N. Land use during mining
Land use (ha)
Plantation Water Body
Public use Undisturbed Total
1 External OB Dump 175 0 0 0 175
2 Top soil dump 0 0 0 0 0
3 Excavation 0 101.7 0 0 101.7
4 Roads including embankment
17 8 25
5 Built up area 3 0 7 0 10
6 Green Belt 0 0 0 0 0
7 Undisturbed Area 137.93 0 0 0 137.93
Total 332.93 101.7 15 0 449.63
CHAPTER - III
DESCRIPTION OF ENVIRONMENT
3.1 General :
In order to assess the present scenario in the surrounding of the project i.e. base
line scenario w.r.t. the proposed project, the environmental data generated in
the surrounding in & around during April – to June 2013 has been considered.
The scenario as stated above represents the present scenario before the start of
the project and this will serve as pre – mining condition w.r.t. the proposed Deep
Extension project.
3.2 Socio Economic Environment
The study of socio-economic environment is a part of Environment Impact
Assessment (EIA). A family’s socioeconomic status is based on family income,
parental education level, parental education level, parental occupation and
social status in the community. The study includes demographic structure of the
area (Core zone and Buffer zone 15 Kms. radius from mine lease area), housing,
education, health and medical services, occupation, water supply, sanitation,
communication, transportation, prevailing disease pattern as well as features of
aesthetic significance such as temples, historical monuments scenic beauty
etc., as per census. This would help in visualizing and predicting the likely impact
depending upon the nature and magnitude of the project. In order to validate
the census report, house hold survey was made to collect the data of 250 house
holds falling within core and buffer zone by floating questionnaire to residence
and local people of different villages (respondents selected on basis of socio-
economic condition), village head (Sarapanch/Police patil). The occupational
health status data is collected from the mine Hospital / local Doctor.
The basic amenities as per the census and the information from the residents of
the surveyed villages are described in the following sub-sections.
SOCIO- ECONOMICS DATA
The data collected for baseline study as per district census includes:
a) Number and names of Villages falling within the study area,
b) Social Profile, c) Economic, d) Infrastructure Facilities and
e) Occupational Health
The above information would help in predicting and evaluating likely impacts of
the socio-economic environment due to proposed mining activities.
Description of study area
The study area comprises of the following Districts and Tahesils of Maharashtra
state: The study area, Core and Buffer zone (10 Km) comprises of the following District and Tahsils of
Maharashtra State.
DISTRICT NAME TAHSIL NAME
Chandrapur Bhadravati
Yavatmal Wani
NUMBER & NAMES OF VILLAGES FALLING WITHIN THE STUDY AREA
Chargaon, Junada, Aheri and Borgaon are in the core zone of the project.
There is no village within the distance of 500m from the mine lease area.
Chargaon is in Bhadrawati Tahesil of Chandrapur district. Junada, Aheri and
Borgaon are in Wani Tahesil of Yavatmal district. There are 30 villages within the
study area.
There are 55 villages with 27,042 house holds and 111872 populations within
the study area. The house hold size varies between 1 and 5 with an average
of 4 persons per family.
SOCIAL PROFILE
Total population:
The percentage population is 52.08 % male and 47.92 % female. The
percentage population of scheduled cast (SC), scheduled tribe (ST) and
others are 15.71, 8.85 and 75.44 % respectively.
The Religions which occoures in Yavatmal district are Buddhists,Christians, Hindus,
Jains, Muslims. Christians are more numerous in urban area.
The sex ratio varies between 0 and 1065 with an average of 899. There are
quite a few villages in the study area with sex ratio greater than 1000 for the
age group of 0 to 6 years with an average of 996.
The other cast present are Kunbi, Mali (akosaria, Phulmali, Bhange, Bawane, Jire,
Harde, ghase and Pahad), Banjara, Andh Gond , Pardhans and Kolam.
Major languages which are spoken in Yavatmal district are Banjari, Gondi,
Gujrathi, Hindi, Kolami, Marathi, Sindhi, and Telugu. Marthi is the principal
language and is the mother tounge of the population
The population of Gondi and Kolami speakers are higher and rural areas while
the the proportions of Gujrathi , Hindi.Sindi and Urdu speakers are higher in urban
areas.Telugu spearkers are fairly distributes over rural and urban areas.
Literacy level:
The literacy status of the study area is 79.59 % with 54.73 % male and 45.27%
female.
The illiteracy status of the study area is 20.41 % with 41.74 % male and 58.56 %
female.
Average House holds size:
The average house hold size varies from 4.0 to 6.0 persons per family.
ECONOMIC
The total population is divided into workers and non workers. The workers are
again subdivided into main and marginal workers.
WORKERS: There are 40.02 % workers with 70.81 % male workers and 29.19 %
female workers.
NON-WORKERS: The percentage of non-workers is 59.98 with 39.58 % male
and 60.42 % female.
OCCUPATIONAL STRUCTURE:
MAIN WORKERS: The percentage of main workers is 86.53 with 74.75 % male
and 25.25 % female.
MARGINAL WORKERS: The percentage of marginal workers is 13.47 with
45.48 % male and 54.52 % female.
MAIN WORKERS:
The percentage of main causal workers is 15.35 with 66.61 % male and 33.39 %
female.
The percentage of main agricultural workers is 23.69 with 49.72 % male and
50.53 % female.
The percentage of main house hold workers is 1.93 with 77.30 % male and
22.70 % female.
The percentage of main others workers is 58.92 with 86.90 % male and 13.10 %
female.
MARGINAL WORKERS:
The % of marginal causal workers is 9.02 with 25.92 % male and 74.08 %
female.
The % of marginal agricultural workers is 42.91 with 25.98 % male and 74.02 %
female.
The % of marginal house hold workers is 4.06 with 39.59 % male and 60.41 %
female.
The % of marginal others workers is 44.0 with 69.05 % male and 30.95 % female.
CLASSIFICATION OF MARGINAL WORKERS:
MARGINAL WORKERS (3 - 6 months)
The % of marginal cultivators is 8.98 with 27.55 % male and 72.45 % female.
The % of marginal agricultural labors is 44.73 with 26.77 % male and 73.23 %
female.
The % of marginal house hold workers is 3.43 with 46.59% male and 53.41 %
female.
The % of marginal others workers is 42.86 with 68.79 % male and 31.21%
female.
MARGINAL WORKERS (0 - 3 months)
The % of marginal cultivators is 9.28 with 16.87 % male and 83.13 % female.
The % of marginal agricultural labors is 32.44 with 19.66 % male and 80.34 %
female.
The % of marginal house hold workers is 7.72 with 21.74 % male and 78.26 %
female.
The % of marginal others workers is 50.56 with 70.35 % male and 29.65 %
female.
Land use Pattern:
The land use pattern of the study area is given as below:
i) Forest land is 6.45%,
ii) Irrigated land is 1.34%,
iii) Un-irrigated land is 63.83%,
iv) Waste land is 5.90% and
v) Uncultivated land is 22.48%.
INFRASTRUCTURE FACILITIES
The houses are made of Bricks or earthen walls with cement or earthen
flooring. The roofs are tiled, sheets and of terrace roof. The grouping of the
houses as per the wall material shows the level of prosperity in the village.
Most of the houses are without toilet facilities of their own and they use the open
land in the village for the purpose. There are no public toilets.
The migration from the villages during the past is not much. The migration is to
the nearest town is for employment / study purpose or for labour work due to the
lack of employment in the village.
Drinking water is taken care of in some villages through pipeline supply. Other
villages are depended on hand pumps. The quality of water is reasonably well.
The difficulty arises in summer when the hand pumps do not yield even half of
the normal water supply.
These villages are connected with Electric lines but power is intermittently
supplied as in all rural areas of the state.
The fuel for cooking purpose is L.P.G, kerosene/ coal or firewood.
Most of the villages are connected with tar / mud roads with state transport
facilities. Motor cycles, Cycles are used for traveling purposes. Bullock carts /
Tractors are used for carrying materials.
OCCUPATIONAL HEALTH SURVEY
An occupational health risk is a leading cause of morbidity and mortality. The
occupational risk factors account for a number of morbid conditions, including
back pain, hearing loss, chronic obstructive lung disease, asthma, injuries,
cancer, leukemia etc.
OCCUPATIONAL HEALTH HAZARDS:
It is observed during the survey that, the habitation is away from the mining site.
Therefore there will be a minimum effect of mining activities on the locals.
The risk of tropical diseases such as malaria and dengue fever is substantial
during the rainy season. Eradication of mosquitoes and improved sanitation will
controlled these hazards effectively.
It is observed during the survey that malaria, dysentery / diarrhea and skin
disorders are common among all the sex / ages.
OCCURANCE OF HISTORICAL/ARCHAEOLOGICAL SITES
Wani is tahsil headquarter situated on the bank of Nirguda river. The famous
temple of Shir Ranganarh swami is in this town. Thousands of pilgrims visit the
temple from Falguna vadi to Chitra Sud 15. Wani is an important center of trade
in cattle and bullocks. There are coal mines near Wani. The place is well
connected with important places in the district by state roadways and also by
Rail.
The project is having a Hospital at Township with Bed facilities. There is no
Medical facility available in the villages on regular basis except for intermittent
visiting Doctors (Once a week or so).
The house-to-house sample survey registers the data generally in tune with the
census figures. It also further updates the data particularly in respect of literacy,
persons on jobs, Toilet facilities, housing standards, medical facilities, item of
source of cooking energy, vehicles in villages etc.
PUBLIC AWARENESS AND OPINION ABOUT THE PROJECT
Most of the respondents are aware about the project. 75% respondents have
favorable opinion, 20% have unfavorable opinion and 5% have not given any
opinion.
The respondents were asked to opine about the project. They expected job
opportunities, improvement in educational, transport, medical and Increase in
housing facilities.
Unfavorable opinion can be attributed to increase in environmental pollution,
crimes and increase in the cost of commodities.
3.3 EXISTING LAND USE PATTERN
Land use pattern has been classified into four broad categories.
- Forest land;
- Agriculture ( Irrigated & Un-irrigated ) land
- Cultivable waste land;
- Not available for cultivation.
a) Core Zone - Total land requirement of the project is as given below:-
Break up is given below.
Sl.
No.
Particulars Land
already
acquired
in
existing Junad
OC Mine
Land to be acquired
under proposed Junad
Extn. OC Mine
Total
1. Agricultural
Land
171.15
3.13
269.25 ha*
449.63 ha 2. Waste Land
(Govt. Land)
6.10 ha
3. Forest Land NIL NIL NIL
TOTAL
174.28
ha
275.35 ha 449.63 ha
3.4 Base Line Environmental quality:
SCOPE AND METHODOLOGY
Preamble
The scope of the study (Period – Pre – MonsoonSeason 2013 – i.e. April 2013 to June
2013) and the present report covers the detailed characterisation of the existing
environmental status in the study area for major environmental components viz.
micrometeorology, ambient air quality, water/waste water quality, noise level and
soil quality.
Micrometeorology
As a part of this study, micrometeorology and microclimatic parameters were
recorded by installing a meteorological station at Core zone. Data of wind
velocity, wind direction, ambient temperature, relative humidity and cloud cover
were recorded at hourly intervals in a day throughout the study period. Further
rainfall also has been recorded and reported.
Wind velocity and wind direction were recorded using cup anemometer and
wind vane respectively. Ambient temperature was noted by wet and dry bulb
thermometer. Relative humidity was measured from hygrometer and a self-
recording rain gauge was used for rainfall data collection. Cloud cover data
has been collected by visual inspection.
Ambient air quality
To assess the ambient air quality status, monitoring stations were identified on the
basis of meteorology in the upwind and downwind direction as well as to
represent the cross sectional scenario of the project site. Based on the production
activities, the parameters chosen for assessment of air quality are Suspended
Particulate Matter (SPM) ,Particulate Matter <10 (PM10), Particulate Matter <2.5
(PM2.5), Sulphur dioxide (SO2), Oxides of Nitrogen (NOx) and heavy metals like
Arsenic ( As), Mercury ( Hg), Nickel ( Ni), Lead ( Pb) and Chromium ( Cr) .
Calibrated Respirable Dust sampler (with an average flow of 1.2 - 1.4 m3/min.)
were used for monitoring of SPM and PM10 and a tapping provided in the
hopper of the same sampler was utilised for sampling of SO2,NOx , with proper
flow controller (1 L/min).The heavy metal like Arsenic ( As), Mercury ( Hg), Nickel (
Ni), Lead ( Pb) and
Chromium (Cr) was also collected in EPM 2000 filter paper by using High volume
sampler. Calibrated APM 550 Fine Particle Sampler (with an average flow of 16.7
LPM) was used for monitoring of PM2.5. A temporary field laboratory for the
purpose of calibration of equipments and standardisation of analytical
procedures was also established.
SPM & PM10
Calibrated Respirable Dust Sampler with Whatman’s GF/A micro fibre filter
paper was used for the determination of PM & PM10 is a measure of particulate
matter having size <10microns.The dust particles having size >10 microns is being
collected in the cyclone and measured. This along with PM10 value gives total
PM.
PM2.5
Calibrated APM 550 Fine Particle Sampler with Whatman’s standard PTFE 47 mm
diameter filter media was used for the determination of Fine Particles (PM2.5).
PM2.5 is a measure of particulate matter having size <2.5 microns. APM 550 Fine
Particle Sampler is based on impactor designs standardized by USEPA for
ambient air quality monitoring.
SO2 (Modified West & Geake Spectrophotometer method)
Ambient air is bubbled at the rate of 1.0 l/min in an Impinger containing a
scrubbing solution of Sodium-Tetra Chloro Mercurate. The resultant complex is
reacted with P-Rosaniline and Formaldehyde to form coloured Para-Rosaniline
methyl sulphuric acid. The absorbance of the solution is measured in a
Spectrophotometer at a wavelength of 560nm. The SO2 is then calculated from
standard graph.
NO2 (Jacob & Hocheiser modified method)
Ambient air is bubbled at the rate of 1.0 l/min in an Impinger containing a
solution of Sodium Hydroxide and Sodium Arsenate. The resultant Nitrite Ion is
reacted with Phosphoric acid, Sulphanilamide and N-ethylene di-amine di-
hydro chloride to form a coloured complex. The absorbance is measured in a
Spectrophotometer at a wavelength of 540 nm. The concentration of NO2 is then
calculated by using standard graph.
Heavy metals
The AAS technique makes use of absorption spectrophotometry to assess the
concentration of metals in the sample. The method is based on active sampling
using PM10 high volume sampler and then sample analysis is done by Atomic
absorption spectrophotometer.
The methodology adopted for sampling and analysis of ambient air quality
parameters are given as follows:
S.No. Parameters Methodology
1 Particulate Matter <10 Gravimetric analysis
2 PM2.5 Gravimetric method
3 Sulphur di-oxide Improved West-Geake-
Spectrophotometric Method
4 Oxide of Nitrogen Jacob and Hocheiser Modified Method
5 Heavy Metals AAS method after sampling on EPM 2000
Filter paper
Water quality
Water samples were collected and analyzed as per procedures outlined in IS-
2488/ IS-3025 / AWWA / APHA. Sterilized bottles were used for collection of water
sample for bacteriological analysis, stored in icebox and transported to the
laboratory for the analysis. Parameters like pH, Temperature, Dissolved Oxygen,
Residual Chlorine, Conductivity, Free Ammonia, Total Hardness, Calcium
Hardness and Magnesium Hardness were analyzed in the field while collecting
the samples. MPN index of Coliforms are determined in the laboratory as per
standard methods.
The analyses were carried out as per the BIS & APHA standard methods.
Noise levels
Ambient noise level measurements in four co-ordinal directions were carried out
using CYGNET sound level meter, with windscreen during daytime as well as night
time. Noise measurements were made at 1.5 m above ground and about 3m
away from walls, buildings or other sound reflecting sources. The readings were
taken from morning 6.0 AM to 10 PM at 4 hours regular intervals which give day
time Noise level. The average Leq values during Day time are reported. Similarly
Night time noise levels were taken from 10 PM to 6 AM at four hours interval.
Ambient noise levels are compared with CPCB Norms.
Soil quality
To assess the baseline soil quality, soil samples were collected from identified
locations in core & buffer zones using augers at depths 30, 60 and 100 cms. The
samples were analyzed for chemical parameters like pH, EC, N, P, K and
engineering parameters like textural class, bulk density, liquid limit, field capacity,
wilting coefficient and available water storage capacity.
3.4.1 MICROMETEOROLOGICAL STATUS
Rationale behind sampling
Meteorological parameters are important factors in the study of air pollution.
The transport and diffusion of the pollutants in the atmosphere are governed by
meteorological factors. Factors like wind velocity, wind direction and
atmospheric-stability are known as primary / basic meteorological parameters
since the dispersion and diffusion of pollutants depend mainly on these factors.
Factors like ambient temperature, humidity, rainfall, atmospheric pressure, etc.,
are known as secondary meteorological parameters as these factors control the
dispersion of the pollutants indirectly by affecting the primary factors. Thus, to
assess the air pollution impact it becomes essential to collect the above-
mentioned meteorological parameters in the project area.
Micrometeorological and microclimatic parameters were recorded by installing
a meteorology station in Core zone as it represents the prevailing
micrometeorological aspects of the study area. During the study period, hourly
reading of wind velocity, wind direction, temperature, humidity, cloud cover
etc., were recorded and reported. Further daily rainfall has been recorded and
reported.
Data presentation & analysis
The micrometeorological data thus collected has been processed and analyzed
as per standard procedures. The seasonal wind distribution is given in the Table
below. Seasonal wind distribution data
Season: Pre Monsoon (1st April – 30th June`13)
Location : Core Zone
Wind Direction
Wind Velocity, Kmph (% Duration)
< 1.0 1 – 5 5 – 11 11 – 19 19 - 29
N
1.65 1.97 0.64 -
NNE 0.82 1.42 0.09 -
NE 1.42 2.43 0.69 -
ENE 0.32 0.46 0.23 -
E 0.23 0.05 0.00 -
ESE 0.14 0.14 0.00 -
SE 0.96 0.92 0.23 -
SSE 0.05 0.18 0.18 -
S 0.32 0.60 0.05 -
SSW 2.01 2.84 1.24 -
SW 4.30 5.40 2.15 0.09
WSW 2.66 3.98 0.96 -
W 1.65 1.65 0.87 -
WNW 4.95 6.09 1.79 0.05
NW 10.35 13.05 4.03 -
NNW 4.67 6.82 2.24 -
Season 36.49 47.99 15.38 0.14
TABLE : 1 METEOROLOGICAL DATA
Date : 01.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 5.0 NW 27.0 54 2 0
2 02.00 5.7 NW 27.0 57 3 0
3 03.00 6.4 NNW 26.5 50 3 0
4 04.00 7.0 NNW 25.0 63 3 0
5 05.00 6.9 SW 25.0 65 3 0
6 06.00 4.7 SW 25.0 70 3 0
7 07.00 6.8 SSW 26.5 65 2 0
8 08.00 10.6 SW 27.0 57 2 0
9 09.00 9.9 NW 28.0 53 1 0
10 10.00 12.4 NW 30.0 48 1 0
11 11.00 7.9 NE 32.0 41 1 0
12 12.00 11.3 NE 33.0 41 1 0
13 13.00 15.6 NE 34.0 35 0 0
14 14.00 11.4 NNE 34.5 31 0 0
15 15.00 8.5 NW 35.0 28 0 0
16 16.00 4.8 NNW 34.5 34 0 0
17 17.00 6.1 NW 34.0 35 1 0
18 18.00 4.2 NW 33.0 41 1 0
19 19.00 4.0 WNW 32.5 44 1 0
20 20.00 6.2 SW 31.0 46 1 0
21 21.00 12.5 SSW 30.5 47 1 0
22 22.00 8.1 SW 29.0 50 2 0
23 23.00 6.8 NW 28.0 52 2 0
24 24.00 4.1 NNW 27.5 58 2 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 4.0 Max : 15.6 Avg : 7.8
3. Ambient Temperature (°C) Min : 25.0 Max : 35.0 Avg : 29.8
4. Relative Humidity (%) Min : 28.0 Max : 70.0 Avg : 48.5
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 2 METEOROLOGICAL DATA
Date : 02.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 1.3 NW 27.0 56 2 0
2 02.00 3.0 NW 27.5 59 3 0
3 03.00 2.5 NW 26.5 62 3 0
4 04.00 2.3 NNW 25.0 65 3 0
5 05.00 6.9 NW 25.0 68 3 0
6 06.00 3.0 NW 25.0 63 3 0
7 07.00 3.6 NW 26.5 59 2 0
8 08.00 4.7 NW 27.0 56 2 0
9 09.00 6.9 NNW 28.0 48 1 0
10 10.00 8.1 NNW 30.0 44 1 0
11 11.00 4.9 NW 31.0 41 1 0
12 12.00 7.3 NW 32.0 41 1 0
13 13.00 7.1 NW 33.0 35 0 0
14 14.00 9.3 NW 34.0 34 0 0
15 15.00 13.0 WNW 35.0 31 0 0
16 16.00 12.3 WNW 36.0 29 0 0
17 17.00 10.1 WNW 35.5 35 1 0
18 18.00 3.4 NE 34.0 41 1 0
19 19.00 6.0 NE 32.5 44 1 0
20 20.00 4.3 NNE 32.0 46 1 0
21 21.00 5.0 NNE 30.5 47 1 0
22 22.00 6.4 NNE 30.0 50 2 0
23 23.00 7.0 NE 29.0 52 2 0
24 24.00 8.1 NE 28.0 51 2 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.3 Max : 13.0 Avg : 6.1
3. Ambient Temperature (°C) Min : 25.0 Max : 36.0 Avg : 30.0
4. Relative Humidity (%) Min : 29.0 Max : 68.0 Avg : 48.2
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 3 METEOROLOGICAL DATA
Date : 03.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 2.4 NW 27.0 56 2 0
2 02.00 2.6 NE 27.0 59 3 0
3 03.00 4.5 NE 26.5 62 3 0
4 04.00 3.5 NNE 25.0 68 3 0
5 05.00 6.9 NNW 25.0 68 3 0
6 06.00 4.7 NNW 25.0 76 3 0
7 07.00 6.8 NW 26.5 59 2 0
8 08.00 10.6 NW 27.0 56 2 0
9 09.00 9.9 NW 28.0 48 1 0
10 10.00 12.4 NW 30.0 44 1 0
11 11.00 7.9 WNW 32.0 41 1 0
12 12.00 8.6 NW 34.0 41 1 0
13 13.00 7.3 NE 35.0 35 0 0
14 14.00 6.5 NNE 35.5 29 0 0
15 15.00 4.3 NE 35.0 31 0 0
16 16.00 3.2 WNW 34.0 34 0 0
17 17.00 1.2 WNW 33.0 35 1 0
18 18.00 2.3 NW 32.5 41 1 0
19 19.00 1.5 WNW 32.0 44 1 0
20 20.00 1.9 WNW 31.0 46 1 0
21 21.00 5.3 NNE 29.5 47 1 0
22 22.00 8.1 NE 29.0 50 2 0
23 23.00 6.8 NE 28.0 52 2 0
24 24.00 4.1 NW 27.0 58 2 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph)
: Min : 1.2 Max : 12.4 Avg : 5.6 3. Ambient Temperature (°C) : Min : 25.0 Max : 35.5 Avg : 29.8 4. Relative Humidity (%) : Min : 29.0 Max : 76.0 Avg : 49.2
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 4 METEOROLOGICAL DATA
Date : 04.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 1.9 NW 27.0 56 2 0
2 02.00 2.3 WNW 27.5 59 3 0
3 03.00 4.6 WSW 26.5 62 3 0
4 04.00 2.3 WSW 25.0 65 3 0
5 05.00 6.9 SW 25.0 68 3 0
6 06.00 3.0 WSW 25.0 63 3 0
7 07.00 3.6 SSW 26.5 59 2 0
8 08.00 4.7 SW 27.0 56 2 0
9 09.00 6.9 WSW 28.0 48 1 0
10 10.00 8.1 WSW 30.0 44 1 0
11 11.00 4.9 WSW 31.0 41 1 0
12 12.00 7.3 WSW 32.0 41 1 0
13 13.00 7.1 WNW 33.0 35 0 0
14 14.00 9.3 WNW 34.0 34 0 0
15 15.00 8.6 NW 35.0 31 0 0
16 16.00 10.3 WNW 36.0 29 0 0
17 17.00 8.6 WSW 35.5 35 1 0
18 18.00 4.3 WSW 34.0 41 1 0
19 19.00 2.3 SW 32.5 44 1 0
20 20.00 2.8 WSW 32.0 46 1 0
21 21.00 1.6 WSW 30.5 47 1 0
22 22.00 1.5 SW 30.0 50 2 0
23 23.00 1.6 SSW 29.5 52 2 0
24 24.00 4.3 S 29.0 51 2 0
OBSERVATIONS
1. Predominant WindDirection (from) : WSW 2. Wind Velocity (Kmph) Min : 1.5 Max : 10.3 Avg : 5.0
3. Ambient Temperature (°C) Min : 25.0 Max : 36.0 Avg : 30.1
4. Relative Humidity (%) Min : 29.0 Max : 68.0 Avg : 48.2
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 5 METEOROLOGICAL DATA
Date : 05.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 1.6 NW 27.5 56 2 0
2 02.00 1.9 NNW 27.0 59 3 0
3 03.00 2.0 NW 26.5 62 3 0
4 04.00 3.4 NNW 25.0 68 3 0
5 05.00 6.9 NW 25.0 68 3 0
6 06.00 2.0 NNE 25.0 76 3 0
7 07.00 3.1 WNW 26.5 59 2 0
8 08.00 5.8 NE 27.0 56 2 0
9 09.00 3.8 NW 28.0 48 1 0
10 10.00 5.4 ENE 30.0 44 1 0
11 11.00 11.7 WNW 32.0 41 1 0
12 12.00 10.3 NE 34.0 41 1 0
13 13.00 9.6 NE 35.5 35 0 0
14 14.00 8.5 NNW 36.0 34 0 0
15 15.00 4.3 NNW 37.0 31 0 0
16 16.00 3.6 WNW 36.0 34 0 0
17 17.00 4.0 NNW 35.5 35 1 0
18 18.00 3.9 NE 34.0 41 1 0
19 19.00 2.6 NW 32.5 44 1 0
20 20.00 4.3 NW 32.0 46 1 0
21 21.00 6.0 NNW 30.5 47 1 0
22 22.00 9.1 NW 30.0 50 2 0
23 23.00 13.1 NW 29.5 52 2 0
24 24.00 10.6 NNW 29.0 55 2 0
OBSERVATIONS
1. Predominant WindDirection (from) : NNW 2. Wind Velocity (Kmph) Min : 1.6 Max : 13.1 Avg : 5.7
3. Ambient Temperature (°C) Min : 25.0 Max : 37.0 Avg : 30.5
4. Relative Humidity (%) Min : 31.0 Max : 76.0 Avg : 49.3
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 6 METEOROLOGICAL DATA
Date : 06.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 2.3 NW 28.0 56 2 0
2 02.00 2.4 NW 27.0 59 3 0
3 03.00 3.6 WNW 26.5 62 3 0
4 04.00 3.4 WNW 25.0 68 3 0
5 05.00 6.9 WNW 25.0 68 3 0
6 06.00 2.0 NW 25.0 76 3 0
7 07.00 3.1 NW 26.5 59 2 0
8 08.00 4.4 NW 27.0 56 2 0
9 09.00 3.8 NNE 28.0 48 1 0
10 10.00 5.4 NW 30.0 44 1 0
11 11.00 11.7 NW 32.0 41 1 0
12 12.00 13.1 NW 34.0 41 1 0
13 13.00 12.3 NE 35.5 35 0 0
14 14.00 9.3 ENE 36.0 34 0 0
15 15.00 8.2 SE 38.0 32 0 0
16 16.00 3.6 S 36.0 34 0 0
17 17.00 4.0 SE 35.5 35 1 0
18 18.00 3.9 SW 34.0 41 1 0
19 19.00 4.6 SW 32.5 44 1 0
20 20.00 7.6 S 32.0 46 1 0
21 21.00 6.0 SW 30.5 47 1 0
22 22.00 9.1 WSW 30.0 50 2 0
23 23.00 13.1 SW 29.5 52 2 0
24 24.00 10.6 S 29.0 55 2 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.0 Max : 13.1 Avg : 6.4
3. Ambient Temperature (°C) Min : 25.0 Max : 38.0 Avg : 30.5
4. Relative Humidity (%) Min : 32.0 Max : 76.0 Avg : 49.3
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 7 METEOROLOGICAL DATA
Date : 07.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 8.8 NW 27.5 56 2 0
2 02.00 6.0 WNW 27.0 59 3 0
3 03.00 5.5 NW 26.5 62 3 0
4 04.00 4.2 NNW 25.0 68 3 0
5 05.00 6.9 NNW 25.0 68 3 0
6 06.00 4.3 NW 25.0 72 3 0
7 07.00 6.0 NW 26.0 66 2 0
8 08.00 7.5 NW 28.0 54 1 0
9 09.00 7.4 NNW 28.5 51 1 0
10 10.00 9.8 NNW 30.0 47 1 0
11 11.00 11.2 NNW 32.5 44 1 0
12 12.00 15.9 ENE 34.0 43 1 0
13 13.00 9.6 ENE 36.0 38 0 0
14 14.00 8.2 ENE 36.5 34 0 0
15 15.00 6.6 NE 38.5 32 0 0
16 16.00 4.9 NW 36.5 34 0 0
17 17.00 3.9 WNW 36.0 38 0 0
18 18.00 4.3 NW 34.5 41 1 0
19 19.00 6.1 NW 34.0 43 1 0
20 20.00 7.5 NW 32.5 44 1 0
21 21.00 6.6 WNW 32.0 46 1 0
22 22.00 4.8 NW 30.0 50 1 0
23 23.00 6.2 WNW 29.5 52 1 0
24 24.00 4.2 WNW 29.0 55 2 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 3.9 Max : 15.9 Avg : 6.9
3. Ambient Temperature (°C) Min : 25.0 Max : 38.5 Avg : 30.8
4. Relative Humidity (%) Min : 32.0 Max : 72.0 Avg : 49.9
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 8 METEOROLOGICAL DATA
Date : 08.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 3.0 NW 28.5 57 2 0
2 02.00 2.5 NW 27.5 59 3 0
3 03.00 5.1 NW 27.0 70 3 0
4 04.00 4.0 NW 26.0 76 3 0
5 05.00 6.9 NNW 26.0 76 3 0
6 06.00 5.7 NW 36.5 69 3 0
7 07.00 9.1 NW 38.0 54 3 0
8 08.00 12.0 NNW 30.0 51 2 0
9 09.00 9.3 NNW 30.5 44 2 0
10 10.00 14.7 NW 32.5 44 1 0
11 11.00 17.5 NW 34.5 43 1 0
12 12.00 15.0 NW 36.0 43 1 0
13 13.00 11.0 SW 36.5 38 0 0
14 14.00 8.8 SSW 38.0 36 0 0
15 15.00 9.3 SSW 38.5 32 0 0
16 16.00 8.0 SW 36.5 38 0 0
17 17.00 6.1 SW 36.0 43 1 0
18 18.00 7.3 SW 34.5 43 1 0
19 19.00 6.4 SSW 32.5 44 1 0
20 20.00 7.4 SW 32.0 46 2 0
21 21.00 7.0 SE 30.5 47 2 0
22 22.00 9.1 SE 30.0 50 2 0
23 23.00 3.4 SE 29.5 52 3 0
24 24.00 2.3 SE 29.0 55 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.3 Max : 17.5 Avg : 8.0
3. Ambient Temperature (°C) Min : 26.0 Max : 38.5 Avg : 32.4
4. Relative Humidity (%) Min : 32.0 Max : 76.0 Avg : 50.4
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 9 METEOROLOGICAL DATA
Date : 09.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 4.5 NW 27.5 56 3 0
2 02.00 6.0 SW 27.0 59 3 0
3 03.00 5.3 SE 26.5 62 3 0
4 04.00 4.1 NE 26.0 69 3 0
5 05.00 6.9 NE 26.0 73 3 0
6 06.00 4.0 ESE 27.5 77 3 0
7 07.00 1.6 NE 28.0 66 2 0
8 08.00 8.4 ESE 29.0 44 2 0
9 09.00 7.0 SE 32.0 55 1 0
10 10.00 12.3 SE 34.0 51 1 0
11 11.00 11.3 SE 34.5 46 1 0
12 12.00 16.8 WSW 36.0 43 1 0
13 13.00 9.4 SW 36.5 38 0 0
14 14.00 5.0 SW 38.0 34 0 0
15 15.00 7.2 SW 38.5 32 0 0
16 16.00 6.1 WSW 38.0 36 0 0
17 17.00 6.5 SW 36.0 38 0 0
18 18.00 4.0 SW 34.5 41 1 0
19 19.00 3.1 WSW 34.0 43 1 0
20 20.00 4.5 SW 32.0 44 1 0
21 21.00 8.2 SW 30.5 47 1 0
22 22.00 2.4 SW 30.0 50 1 0
23 23.00 1.6 SW 29.0 52 1 0
24 24.00 2.0 SSW 28.5 54 2 0
OBSERVATIONS
1. Predominant WindDirection (from) : SW 2. Wind Velocity (Kmph) Min : 1.6 Max : 16.8 Avg : 6.2
3. Ambient Temperature (°C) Min : 26.0 Max : 38.5 Avg : 31.6
4. Relative Humidity (%) Min : 32.0 Max : 77.0 Avg : 50.4
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 10 METEOROLOGICAL DATA
Date : 10.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 2.3 NW 28.0 57 2 0
2 02.00 4.9 SW 27.5 59 2 0
3 03.00 5.1 WNW 27.0 70 3 0
4 04.00 3.6 NW 26.5 73 3 0
5 05.00 6.9 NNW 26.0 76 3 0
6 06.00 4.0 NNW 27.0 73 3 0
7 07.00 4.7 NNW 28.0 64 3 0
8 08.00 7.0 NW 30.0 47 2 0
9 09.00 10.3 NE 30.5 42 2 0
10 10.00 15.6 NNW 32.5 41 1 0
11 11.00 12.7 NNW 34.0 41 1 0
12 12.00 7.4 NNW 36.0 34 1 0
13 13.00 9.9 NW 38.0 32 0 0
14 14.00 9.1 NW 38.5 28 0 0
15 15.00 8.7 NNW 40.0 23 0 0
16 16.00 5.6 NNE 38.5 28 0 0
17 17.00 7.6 NE 38.0 28 1 0
18 18.00 8.8 NE 36.0 30 1 0
19 19.00 4.9 NE 35.0 35 1 0
20 20.00 6.3 NNE 34.0 36 1 0
21 21.00 5.0 NNE 32.0 39 1 0
22 22.00 3.4 NNW 30.5 44 1 0
23 23.00 3.4 NW 30.0 47 1 0
24 24.00 4.3 NW 29.0 52 2 0
OBSERVATIONS
1. Predominant WindDirection (from) : NNW 2. Wind Velocity (Kmph) Min : 2.3 Max : 15.6 Avg : 6.7
3. Ambient Temperature (°C) Min : 26.0 Max : 40.0 Avg : 32.2
4. Relative Humidity (%) Min : 23.0 Max : 76.0 Avg : 45.8
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 11 METEOROLOGICAL DATA
Date : 11.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 2.6 NW 28.5 54 2 0
2 02.00 5.9 NW 28.0 57 2 0
3 03.00 4.3 NW 27.5 66 3 0
4 04.00 8.3 NW 27.0 70 3 0
5 05.00 6.9 NW 26.0 76 3 0
6 06.00 3.0 WNW 28.0 70 3 0
7 07.00 3.7 NW 28.5 64 2 0
8 08.00 4.8 WNW 29.0 51 2 0
9 09.00 7.9 NW 32.0 49 1 0
10 10.00 10.3 NNW 34.0 46 1 0
11 11.00 11.2 NW 34.5 43 1 0
12 12.00 12.6 NE 36.0 43 1 0
13 13.00 14.5 SE 38.0 40 0 0
14 14.00 12.0 SSE 38.5 36 0 0
15 15.00 9.6 SE 40.0 34 0 0
16 16.00 8.3 SE 38.5 36 0 0
17 17.00 7.9 SSE 38.0 40 1 0
18 18.00 6.3 NW 36.0 43 1 0
19 19.00 5.0 SW 34.5 43 1 0
20 20.00 4.5 SSW 34.0 46 1 0
21 21.00 6.4 SW 32.5 46 1 0
22 22.00 8.7 SW 32.0 49 1 0
23 23.00 7.0 SSW 30.5 50 2 0
24 24.00 4.3 SSW 30.0 53 2 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.6 Max : 14.5 Avg : 7.3
3. Ambient Temperature (°C) Min : 26.0 Max : 40.0 Avg : 32.6
4. Relative Humidity (%) Min : 34.0 Max : 76.0 Avg : 50.2
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 12 METEOROLOGICAL DATA
Date : 12.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 5.7 NW 29.5 58 2 0
2 02.00 6.0 SSW 29.0 61 3 0
3 03.00 5.4 SSW 28.5 64 3 0
4 04.00 4.2 SW 27.0 66 3 0
5 05.00 6.9 SW 26.5 76 3 0
6 06.00 6.7 SSW 28.0 67 3 0
7 07.00 5.9 SW 28.5 64 2 0
8 08.00 7.6 SW 29.5 52 2 0
9 09.00 9.1 SW 30.0 47 1 0
10 10.00 11.4 SSE 32.0 44 1 0
11 11.00 9.7 SE 32.5 41 1 0
12 12.00 13.0 SSE 34.5 41 1 0
13 13.00 11.6 SE 36.0 38 0 0
14 14.00 17.8 SW 38.0 36 0 0
15 15.00 9.1 SW 40.5 34 0 0
16 16.00 8.7 SSW 40.0 38 0 0
17 17.00 9.5 SW 38.5 45 5 0
18 18.00 6.3 SW 38.0 52 4 0
19 19.00 4.6 WSW 36.5 53 4 0
20 20.00 7.8 SW 36.0 55 3 0
21 21.00 10.3 SSW 34.5 56 3 0
22 22.00 6.1 SW 34.0 59 3 0
23 23.00 8.4 SSW 32.5 61 3 0
24 24.00 2.6 SW 30.5 62 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : SW 2. Wind Velocity (Kmph) Min : 2.6 Max : 17.8 Avg : 8.1
3. Ambient Temperature (°C) Min : 26.5 Max : 40.5 Avg : 32.9
4. Relative Humidity (%) Min : 34.0 Max : 76.0 Avg : 52.9
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 13 METEOROLOGICAL DATA
Date : 13.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 5.5 NW 30.0 65 3 0
2 02.00 6.0 SW 28.5 67 3 0
3 03.00 4.2 SW 28.0 70 3 0
4 04.00 3.8 SSW 27.0 73 3 0
5 05.00 6.9 SSW 27.0 77 3 0
6 06.00 7.4 NW 29.0 68 3 0
7 07.00 11.4 NW 29.5 64 2 0
8 08.00 14.0 NW 30.0 59 2 0
9 09.00 15.7 NW 30.5 47 1 0
10 10.00 13.0 SW 32.0 44 1 0
11 11.00 14.3 SW 34.0 41 1 0
12 12.00 14.4 SSW 36.0 38 1 0
13 13.00 16.7 SSW 38.0 36 0 0
14 14.00 9.3 SW 40.0 34 0 0
15 15.00 8.6 SSW 42.0 32 0 0
16 16.00 7..0 SW 40.0 34 0 0
17 17.00 6.7 SW 38.5 36 2 0
18 18.00 5.4 SW 38.0 45 2 0
19 19.00 9.1 SSW 36.5 50 2 0
20 20.00 9.6 NW 36.0 53 3 0
21 21.00 10.9 NNW 34.5 54 3 0
22 22.00 17.6 SW 34.0 56 3 0
23 23.00 11.9 SW 32.5 64 3 0
24 24.00 14.7 SW 32.0 67 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : SW 2. Wind Velocity (Kmph) Min : 3.8 Max : 17.6 Avg : 10.3
3. Ambient Temperature (°C) Min : 27.0 Max : 42.0 Avg : 33.5
4. Relative Humidity (%) Min : 32.0 Max : 77.0 Avg : 53.1
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 14 METEOROLOGICAL DATA
Date : 14.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 5.0 NW 30.5 68 3 0
2 02.00 5.4 SSW 30.0 72 3 0
3 03.00 4.5 SW 29.5 74 3 0
4 04.00 4.6 SW 29.0 78 3 0
5 05.00 6.9 SW 29.0 78 3 0
6 06.00 2.1 WSW 30.0 72 3 0
7 07.00 1.7 SSW 32.0 70 3 0
8 08.00 3.1 NW 32.5 67 2 0
9 09.00 6.6 NW 34.0 56 2 0
10 10.00 9.6 NW 38.0 47 1 0
11 11.00 7.3 NNW 38.5 45 1 0
12 12.00 5.8 NW 40.0 38 1 0
13 13.00 8.6 NW 40.5 34 0 0
14 14.00 5.0 NNW 42.0 32 0 0
15 15.00 4.1 NNW 42.5 32 0 0
16 16.00 3.9 NNE 42.0 36 0 0
17 17.00 4.6 NE 40.5 38 1 0
18 18.00 7.8 NNE 40.0 42 1 0
19 19.00 7.0 NW 38.5 45 1 0
20 20.00 6.7 NW 38.0 50 1 0
21 21.00 6.0 NW 36.5 53 1 0
22 22.00 3.4 WNW 36.0 55 1 0
23 23.00 4.1 WNW 34.5 56 1 0
24 24.00 4.6 NW 34.0 59 2 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.7 Max : 9.6 Avg : 5.4
3. Ambient Temperature (°C) Min : 29.0 Max : 42.5 Avg : 35.8
4. Relative Humidity (%) Min : 32.0 Max : 78.0 Avg : 54.0
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 15 METEOROLOGICAL DATA
Date : 15.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 6.3 NW 32.5 61 2 0
2 02.00 2.7 NNE 32.0 64 2 0
3 03.00 4.0 NNW 30.0 68 3 0
4 04.00 5.4 NE 29.5 71 3 0
5 05.00 6.9 NNE 29.0 74 3 0
6 06.00 5.4 N 30.0 72 3 0
7 07.00 6.0 N 30.5 65 2 0
8 08.00 5.1 N 32.0 61 2 0
9 09.00 8.2 N 34.0 56 1 0
10 10.00 12.6 NW 36.0 48 1 0
11 11.00 10.4 NNE 36.5 45 1 0
12 12.00 9.8 NW 38.0 45 1 0
13 13.00 15.3 NE 38.5 40 0 0
14 14.00 12.6 NW 40.0 34 0 0
15 15.00 6.1 N 42.5 32 0 0
16 16.00 18.0 NNE 40.0 34 0 0
17 17.00 15.7 N 38.5 36 1 0
18 18.00 11.4 NW 38.0 45 1 0
19 19.00 7.0 NNW 36.5 50 1 0
20 20.00 4.0 NNW 36.0 53 1 0
21 21.00 3.0 WNW 34.5 54 1 0
22 22.00 8.0 WNW 34.0 56 1 0
23 23.00 6.7 NW 32.5 64 2 0
24 24.00 9.1 NNW 32.0 67 2 0
OBSERVATIONS
1. Predominant WindDirection (from) : N 2. Wind Velocity (Kmph) Min : 2.7 Max : 18.0 Avg : 8.3
3. Ambient Temperature (°C) Min : 29.0 Max : 42.5 Avg : 34.7
4. Relative Humidity (%) Min : 32.0 Max : 74.0 Avg : 54.0
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 16 METEOROLOGICAL DATA
Date : 16.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 2.6 NW 30.5 68 2 0
2 02.00 3.2 WNW 30.0 72 2 0
3 03.00 4.2 NW 29.5 74 3 0
4 04.00 5.3 NW 29.0 78 3 0
5 05.00 6.9 N 29.0 78 3 0
6 06.00 8.4 N 30.0 72 3 0
7 07.00 3.6 NE 32.5 67 2 0
8 08.00 5.3 WNW 34.0 56 2 0
9 09.00 7.6 NW 34.5 51 1 0
10 10.00 9.6 NW 36.0 48 1 0
11 11.00 12.9 WNW 36.5 45 1 0
12 12.00 8.1 SW 38.5 40 1 0
13 13.00 14.5 SW 40.0 34 0 0
14 14.00 10.4 SW 40.5 30 0 0
15 15.00 8.5 W 42.0 29 0 0
16 16.00 7.0 W 40.0 34 0 0
17 17.00 6.7 W 38.5 40 1 0
18 18.00 7.2 WSW 38.0 45 1 0
19 19.00 5.5 WSW 36.5 48 1 0
20 20.00 4.1 W 36.0 53 1 0
21 21.00 7.4 NW 34.5 54 1 0
22 22.00 8.7 NW 34.0 56 1 0
23 23.00 4.3 NW 32.5 58 2 0
24 24.00 6.1 NW 32.0 61 2 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.6 Max : 14.5 Avg : 7.0
3. Ambient Temperature (°C) Min : 29.0 Max : 42.0 Avg : 34.8
4. Relative Humidity (%) Min : 29.0 Max : 78.0 Avg : 53.8
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 17 METEOROLOGICAL DATA
Date : 17.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 6.3 NW 30.5 62 3 0
2 02.00 2.7 NW 30.0 65 3 0
3 03.00 4.0 NNW 29.5 68 3 0
4 04.00 5.4 NNW 29.5 74 3 0
5 05.00 6.9 NW 29.0 74 3 0
6 06.00 7.1 WNW 30.0 72 2 0
7 07.00 10.7 NW 32.0 58 2 0
8 08.00 12.0 NNW 32.5 49 2 0
9 09.00 9.9 NW 34.0 46 1 0
10 10.00 13.1 NW 34.5 46 1 0
11 11.00 14.9 NW 36.0 43 1 0
12 12.00 16.4 NW 36.5 38 1 0
13 13.00 11.0 WSW 38.0 36 0 0
14 14.00 18.3 SW 38.5 32 0 0
15 15.00 17.1 SSW 40.0 30 0 0
16 16.00 10.4 SE 39.0 29 1 0
17 17.00 8.0 SSE 38.5 40 1 0
18 18.00 8.6 SE 38.0 45 2 0
19 19.00 7.4 SW 36.5 48 2 0
20 20.00 8.8 SW 36.0 53 3 0
21 21.00 6.3 WSW 34.5 54 3 0
22 22.00 5.4 WSW 34.0 56 3 0
23 23.00 5.7 SSW 32.5 61 3 0
24 24.00 9.6 SW 32.0 64 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.7 Max : 18.3 Avg : 9.4
3. Ambient Temperature (°C) Min : 29.0 Max : 40.0 Avg : 34.2
4. Relative Humidity (%) Min : 29.0 Max : 74.0 Avg : 51.8
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 18 METEOROLOGICAL DATA
Date : 18.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 2.3 NW 30.5 65 2 0 2 02.00 2.6 WNW 30.0 68 3 0 3 03.00 3.5 N 29.0 71 3 0
4 04.00 4.6 WNW 28.0 77 3 0
5 05.00 6.9 WNW 28.0 77 3 0
6 06.00 1.8 NNW 28.5 74 3 0 7 07.00 4.8 NW 30.5 59 2 0 8 08.00 6.9 WNW 32.0 49 2 0 9 09.00 6.1 NW 32.5 44 1 0
10 10.00 10.4 NNW 34.0 43 1 0
11 11.00 16.0 NNW 36.5 43 1 0
12 12.00 15.0 WNW 38.0 40 1 0 13 13.00 9.6 WNW 38.5 36 0 0 14 14.00 6.6 NW 40.0 34 0 0 15 15.00 8.0 NNW 40.5 30 0 0
16 16.00 7.4 NW 40.0 38 0 0
17 17.00 6.7 NNW 39.5 39 0 0
18 18.00 7.6 NNW 36.0 43 0 0 19 19.00 5.5 WNW 34.0 43 1 0 20 20.00 8.8 WNW 32.0 44 1 0 21 21.00 6.0 NNW 30.0 47 1 0
22 22.00 4.7 NNW 29.5 49 1 0
23 23.00 2.9 N 29.0 52 1 0
24 24.00 4.4 N 28.5 54 2 0
OBSERVATIONS
1. Predominant WindDirection (from) : NNW 2. Wind Velocity (Kmph) Min : 1.8 Max : 16.0 Avg : 6.6
3. Ambient Temperature (°C) Min : 28.0 Max : 40.5 Avg : 33.1
4. Relative Humidity (%) Min : 30.0 Max : 77.0 Avg : 50.8
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 19 METEOROLOGICAL DATA
Date : 19.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 6.3 NW 28.0 57 2 0
2 02.00 2.7 NW 27.5 59 3 0
3 03.00 4.0 NW 27.0 63 3 0
4 04.00 5.4 NW 26.0 76 3 0
5 05.00 6.9 NW 26.0 76 3 0
6 06.00 6.3 N 38.0 67 3 0
7 07.00 9.0 NW 29.0 61 2 0
8 08.00 8.4 NW 32.0 55 2 0
9 09.00 9.6 NNW 34.0 48 1 0
10 10.00 12.1 NNW 36.0 43 1 0
11 11.00 10.4 NW 36.5 43 1 0
12 12.00 7.9 W 38.0 40 1 0
13 13.00 8.4 NNW 38.5 40 0 0
14 14.00 6.0 NW 40.0 38 0 0
15 15.00 5.5 NNWNW 40.5 34 0 0
16 16.00 4.7 WNW 40.0 38 0 0
17 17.00 6.4 NNE 38.5 40 0 0
18 18.00 7.1 NW 38.0 40 1 0
19 19.00 4.8 WNW 36.5 43 1 0
20 20.00 5.9 NW 36.0 43 1 0
21 21.00 5.4 NNW 34.5 46 1 0
22 22.00 3.8 NNW 34.0 51 1 0
23 23.00 4.3 NW 32.5 52 1 0
24 24.00 1.2 NNE 32.0 61 1 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.2 Max : 12.1 Avg : 6.4
3. Ambient Temperature (°C) Min : 26.0 Max : 40.5 Avg : 34.1
4. Relative Humidity (%) Min : 34.0 Max : 76.0 Avg : 50.6
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 20 METEOROLOGICAL DATA
Date : 20.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 2.3 NW 30.0 62 3 0
2 02.00 2.6 NNW 29.0 64 3 0
3 03.00 2.4 WNW 28.0 67 3 0
4 04.00 3.5 WNW 27.0 73 3 0
5 05.00 6.9 WNW 27.0 73 3 0
6 06.00 4.0 W 29.0 68 3 0
7 07.00 6.1 W 29.5 64 2 0
8 08.00 11.6 WSW 30.0 59 2 0
9 09.00 8.6 WSW 30.5 47 1 0
10 10.00 12.0 W 32.0 44 1 0
11 11.00 14.2 WSW 34.0 41 1 0
12 12.00 4.9 WW 36.0 38 1 0
13 13.00 12.7 W 38.0 36 0 0
14 14.00 11.2 WSW 40.0 34 0 0
15 15.00 9.0 SW 42.0 32 0 0
16 16.00 12.1 SW 40.0 34 1 0
17 17.00 2.5 WSW 38.5 36 1 0
18 18.00 3.3 SW 38.0 45 2 0
19 19.00 9.0 SW 36.5 50 2 0
20 20.00 4.7 WSW 36.0 53 2 0
21 21.00 9.4 WSW 34.5 54 2 0
22 22.00 7.6 W 34.0 56 3 0
23 23.00 13.7 WSW 32.5 64 3 0
24 24.00 16.5 WSW 32.0 67 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : WSW 2. Wind Velocity (Kmph) Min : 2.3 Max : 16.5 Avg : 8.0
3. Ambient Temperature (°C) Min : 27.0 Max : 42.0 Avg : 33.5
4. Relative Humidity (%) Min : 32.0 Max : 73.0 Avg : 52.5
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 21 METEOROLOGICAL DATA
Date : 21.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 6.3 NW 30.5 68 3 0
2 02.00 2.7 WSW 30.0 72 3 0
3 03.00 4.0 WSW 28.0 77 3 0
4 04.00 5.4 SW 27.0 77 3 0
5 05.00 6.9 SW 27.0 77 3 0
6 06.00 7.0 SW 27.0 73 3 0
7 07.00 9.1 SW 28.0 64 2 0
8 08.00 8.5 SW 28.5 51 2 0
9 09.00 10.4 WSW 29.0 49 2 0
10 10.00 7.9 WSW 29.5 46 1 0
11 11.00 11.7 WSW 30.0 42 1 0
12 12.00 19.5 SW 32.0 39 1 0
13 13.00 20.2 SW 36.5 38 0 0
14 14.00 17.8 SW 38.0 36 0 0
15 15.00 12.0 SW 38.5 32 0 0
16 16.00 4.1 SSW 38.0 36 1 0
17 17.00 5.8 SSW 36.5 38 1 0
18 18.00 5.3 SSW 36.0 43 2 0
19 19.00 6.5 WSW 34.0 43 2 0
20 20.00 7.0 WSW 32.5 44 2 0
21 21.00 5.8 WNW 32.0 46 2 0
22 22.00 11.5 WNW 30.0 47 3 0
23 23.00 4.9 NW 29.0 49 3 0
24 24.00 3.9 NW 28.5 54 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : SW 2. Wind Velocity (Kmph) Min : 2.7 Max : 20.2 Avg : 8.5
3. Ambient Temperature (°C) Min : 27.0 Max : 38.5 Avg : 31.5
4. Relative Humidity (%) Min : 32.0 Max : 77.0 Avg : 51.7
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 22 METEOROLOGICAL DATA
Date : 22.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 3.5 NW 28.0 57 2 0
2 02.00 5.1 NW 26.5 59 3 0
3 03.00 4.6 NNW 26.0 69 3 0
4 04.00 3.2 NW 25.0 76 3 0
5 05.00 6.9 NW 25.0 76 3 0
6 06.00 4.2 NNW 25.5 72 3 0
7 07.00 4.6 NNW 26.0 62 2 0
8 08.00 7.2 NW 26.5 55 2 0
9 09.00 8.5 NW 27.0 50 1 0
10 10.00 9.2 NW 28.0 45 1 0
11 11.00 10.5 NE 29.0 40 1 0
12 12.00 8.0 NE 30.0 36 1 0
13 13.00 10.2 NE 32.0 34 0 0
14 14.00 14.0 NNE 34.0 32 0 0
15 15.00 12.4 NE 36.0 30 0 0
16 16.00 6.7 NNE 35.0 35 0 0
17 17.00 8.1 NE 34.5 36 1 0
18 18.00 5.3 NNW 34.0 41 1 0
19 19.00 4.8 NW 32.5 41 1 0
20 20.00 3.4 NW 32.0 44 1 0
21 21.00 2.8 WNW 30.5 44 1 0
22 22.00 3.0 NW 30.0 47 1 0
23 23.00 3.4 NW 28.5 48 1 0
24 24.00 4.2 NNW 28.0 51 2 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.8 Max : 14.0 Avg : 6.4
3. Ambient Temperature (°C) Min : 25.0 Max : 36.0 Avg : 29.6
4. Relative Humidity (%) Min : 30.0 Max : 76.0 Avg : 49.2
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 23 METEOROLOGICAL DATA
Date : 23.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 6.3 NW 27.5 53 2 0
2 02.00 2.7 N 27.0 56 3 0
3 03.00 4.0 N 26.5 59 3 0
4 04.00 5.4 N 25.0 76 3 0
5 05.00 6.9 NW 25.0 76 3 0
6 06.00 4.3 N 26.0 69 3 0
7 07.00 6.9 NNW 27.5 59 3 0
8 08.00 9.6 N 28.0 51 2 0
9 09.00 13.0 NW 28.5 45 1 0
10 10.00 14.7 NNW 29.0 40 1 0
11 11.00 12.3 N 30.5 36 1 0
12 12.00 12.0 N 32.0 34 1 0
13 13.00 18.9 NW 32.5 29 0 0
14 14.00 10.1 N 34.0 27 0 0
15 15.00 7.9 NNW 36.0 26 0 0
16 16.00 8.5 NNW 35.5 35 0 0
17 17.00 5.0 NNW 34.0 41 1 0
18 18.00 6.9 NW 32.5 44 1 0
19 19.00 3.0 NW 32.0 46 1 0
20 20.00 2.5 WNW 30.5 47 1 0
21 21.00 3.6 NNW 30.0 50 1 0
22 22.00 6.1 NW 29.5 52 1 0
23 23.00 9.0 NW 29.0 55 2 0
24 24.00 11.5 N 27.5 56 2 0
OBSERVATIONS
1. Predominant WindDirection (from) : N 2. Wind Velocity (Kmph) Min : 2.5 Max : 18.9 Avg : 8.0
3. Ambient Temperature (°C) Min : 25.0 Max : 36.0 Avg : 29.8
4. Relative Humidity (%) Min : 26.0 Max : 76.0 Avg : 48.4
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 24 METEOROLOGICAL DATA
Date : 24.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 6.3 NW 27.0 59 2 0
2 02.00 2.7 NW 26.5 62 2 0
3 03.00 4.0 NW 26.5 66 3 0
4 04.00 5.4 NW 25.0 68 3 0
5 05.00 6.9 NNW 25.0 68 3 0
6 06.00 5.4 NW 25.5 76 3 0
7 07.00 6.0 NW 27.0 59 2 0
8 08.00 5.1 NW 28.0 57 2 0
9 09.00 8.3 SW 28.5 48 1 0
10 10.00 12.6 SSW 29.0 46 1 0
11 11.00 10.4 SSW 30.0 42 1 0
12 12.00 9.8 SW 30.5 36 1 0
13 13.00 15.3 NW 32.5 34 0 0
14 14.00 12.6 NW 34.5 32 0 0
15 15.00 6.1 SW 36.0 30 0 0
16 16.00 17.0 SW 35.0 35 0 0
17 17.00 15.7 SW 34.5 36 1 0
18 18.00 11.4 NW 34.0 41 1 0
19 19.00 7.0 NNW 32.5 44 1 0
20 20.00 4.9 NW 32.0 46 1 0
21 21.00 8.0 NE 30.5 47 1 0
22 22.00 6.9 NNE 30.0 50 2 0
23 23.00 9.1 NNW 29.5 52 2 0
24 24.00 6.8 NW 27.5 56 2 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.7 Max : 17.0 Avg : 8.5
3. Ambient Temperature (°C) Min : 25.0 Max : 36.0 Avg : 29.9
4. Relative Humidity (%) Min : 30.0 Max : 76.0 Avg : 49.6
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 25 METEOROLOGICAL DATA
Date : 25.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 3.2 NW 27.0 59 2 0
2 02.00 2.4 N 26.5 62 3 0
3 03.00 2.0 NNE 26.5 66 3 0
4 04.00 1.5 NNW 25.0 68 3 0
5 05.00 6.9 NNW 25.0 68 3 0
6 06.00 3.2 NW 28.0 70 3 0
7 07.00 1.5 NNW 29.0 58 2 0
8 08.00 2.0 NNW 30.0 53 1 0
9 09.00 1.8 NW 32.0 49 1 0
10 10.00 3.9 NNW 34.0 41 1 0
11 11.00 5.0 NNW 36.0 38 2 Cloudy
12 12.00 10.2 NNW 38.0 36 2 8
13 13.00 11.2 NW 40.0 34 2 Cloudy
14 14.00 13.1 NNW 42.0 32 5 0
15 15.00 10.2 NNE 44.0 31 4 0
16 16.00 8.5 NNE 42.5 32 3 0
17 17.00 6.2 NE 42.0 36 3 0
18 18.00 4.9 NE 40.5 38 3 0
19 19.00 5.2 N 40.0 42 3 0
20 20.00 4.5 N 38.5 45 3 0
21 21.00 3.0 NW 38.0 47 3 0
22 22.00 2.5 WNW 36.5 48 3 0
23 23.00 4.5 WNW 36.0 50 3 0
24 24.00 3.6 NW 34.5 52 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NNW 2. Wind Velocity (Kmph) Min : 1.5 Max : 13.1 Avg : 5.0
3. Ambient Temperature (°C) Min : 25.0 Max : 44.0 Avg : 34.6
4. Relative Humidity (%) Min : 31.0 Max : 70.0 Avg : 48.1
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 26 METEOROLOGICAL DATA
Date : 26.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 3.5 NW 34.0 62 3 0
2 02.00 5.1 NW 32.0 64 3 0
3 03.00 4.6 NW 29.0 64 3 0
4 04.00 3.2 NW 28.0 77 3 0
5 05.00 6.9 NW 28.0 77 3 0
6 06.00 4.2 WNW 38.0 70 3 0
7 07.00 4.6 WNW 38.5 64 2 0
8 08.00 7.2 NNE 29.0 51 2 0
9 09.00 8.5 NNW 32.0 49 1 0
10 10.00 9.2 NW 34.0 46 1 0
11 11.00 10.5 NNE 34.5 43 1 0
12 12.00 8.0 NNW 36.0 43 1 0
13 13.00 10.2 N 38.0 40 1 0
14 14.00 14.0 NW 38.5 36 0 0
15 15.00 12.4 NNW 40.0 34 0 0
16 16.00 6.7 NW 38.5 36 2 0
17 17.00 8.1 WNW 38.0 40 3 0
18 18.00 5.3 WNW 36.0 43 2 0
19 19.00 4.8 WSW 34.5 43 2 0
20 20.00 3.4 WSW 34.0 46 2 0
21 21.00 2.8 SW 32.5 46 2 0
22 22.00 3.0 SW 32.0 49 3 0
23 23.00 3.4 SW 30.5 50 3 0
24 24.00 4.2 SW 30.0 53 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.8 Max : 14.0 Avg : 6.4
3. Ambient Temperature (°C) Min : 28.0 Max : 40.0 Avg : 34.0
4. Relative Humidity (%) Min : 34.0 Max : 77.0 Avg : 51.1
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 27 METEOROLOGICAL DATA
Date : 27.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 3.2 NW 29.5 58 3 0
2 02.00 2.4 NW 29.0 61 3 0
3 03.00 2.0 WNW 28.5 64 3 0
4 04.00 1.5 NW 27.0 66 3 0
5 05.00 6.9 NW 26.5 76 3 0
6 06.00 3.2 NNW 28.0 67 3 0
7 07.00 1.5 WNW 29.0 58 3 0
8 08.00 2.0 N 30.0 53 3 0
9 09.00 1.8 NW 32.0 49 2 0
10 10.00 3.9 WNW 34.0 41 1 0
11 11.00 5.0 N 36.0 38 4 0
12 12.00 10.2 NW 38.0 36 2 5
13 13.00 11.2 NW 40.0 34 2 7
14 14.00 13.1 WNW 42.0 32 2 4
15 15.00 10.2 N 44.0 31 0 6
16 16.00 8.5 NW 42.5 32 0 0
17 17.00 6.2 WNW 42.0 36 2 0
18 18.00 4.9 NW 40.5 38 2 0
19 19.00 5.2 NW 40.0 42 2 0
20 20.00 4.5 NW 38.5 45 2 0
21 21.00 3.0 W 38.0 47 3 0
22 22.00 2.5 W 36.5 48 3 0
23 23.00 4.5 NW 36.0 50 3 0
24 24.00 3.6 NNW 34.5 51 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.5 Max : 13.1 Avg : 5.0
3. Ambient Temperature (°C) Min : 26.5 Max : 44.0 Avg : 35.1
4. Relative Humidity (%) Min : 31.0 Max : 76.0 Avg : 48.0
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 28 METEOROLOGICAL DATA
Date : 28.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 3.4 NW 34.0 62 3 0
2 02.00 4.2 WNW 32.0 64 3 0
3 03.00 3.6 WNW 29.0 64 3 0
4 04.00 4.5 SW 28.0 77 3 0
5 05.00 6.9 SW 28.0 77 3 0
6 06.00 2.8 WSW 29.0 58 3 0
7 07.00 4.2 WSW 30.0 56 2 0
8 08.00 5.0 SW 32.0 55 2 0
9 09.00 5.6 WSW 34.0 51 1 0
10 10.00 6.2 SW 36.0 50 1 0
11 11.00 8.5 SW 38.0 45 1 0
12 12.00 6.7 SW 40.0 42 1 0
13 13.00 7.6 SSW 42.0 40 0 0
14 14.00 10.2 S 44.0 34 0 0
15 15.00 12.5 SSW 46.0 29 0 0
16 16.00 13.7 SSW 44.0 31 0 0
17 17.00 11.5 SSW 42.5 32 1 0
18 18.00 8.6 SW 42.0 36 1 0
19 19.00 5.2 WSW 40.5 38 1 0
20 20.00 4.8 SW 40.0 42 1 0
21 21.00 4.0 SSW 38.0 45 2 0
22 22.00 3.5 WSW 36.0 48 2 0
23 23.00 3.1 SW 34.5 48 2 0
24 24.00 2.6 SSW 34.0 51 2 0
OBSERVATIONS
1. Predominant WindDirection (from) : SW 2. Wind Velocity (Kmph) Min : 2.6 Max : 13.7 Avg : 6.2
3. Ambient Temperature (°C) Min : 28.0 Max : 46.0 Avg : 36.4
4. Relative Humidity (%) Min : 29.0 Max : 77.0 Avg : 49.0
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 29 METEOROLOGICAL DATA
Date : 29.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 3.8 NW 32.0 52 3 0
2 02.00 4.0 WSW 30.0 59 3 0
3 03.00 4.5 W 29.0 61 3 0
4 04.00 5.3 W 27.0 73 3 0
5 05.00 6.9 W 27.0 73 3 0
6 06.00 5.0 WSW 29.0 71 3 0
7 07.00 6.2 WSW 29.5 64 3 0
8 08.00 7.5 SW 30.0 59 2 0
9 09.00 8.2 WSW 30.5 47 2 0
10 10.00 10.5 WSW 32.0 44 1 0
11 11.00 12.6 W 34.0 41 1 0
12 12.00 9.5 W 36.0 38 1 0
13 13.00 8.7 WSW 38.0 36 0 0
14 14.00 13.0 WSW 40.0 34 0 0
15 15.00 14.5 SW 42.0 32 0 0
16 16.00 11.3 SW 40.0 34 0 0
17 17.00 10.5 SW 38.5 36 1 0
18 18.00 9.3 SSW 38.0 45 1 0
19 19.00 4.6 SSW 36.5 50 2 0
20 20.00 3.9 SSW 36.0 53 2 0
21 21.00 4.0 SW 34.5 54 2 0
22 22.00 5.3 SW 34.0 56 2 0
23 23.00 6.9 WSW 32.5 64 3 0
24 24.00 7.4 W 32.0 67 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : WSW 2. Wind Velocity (Kmph) Min : 3.8 Max : 14.5 Avg : 7.6
3. Ambient Temperature (°C) Min : 27.0 Max : 42.0 Avg : 33.7
4. Relative Humidity (%) Min : 32.0 Max : 73.0 Avg : 51.8
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 30 METEOROLOGICAL DATA
Date : 30.04.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 1.9 NW 30.5 68 3 0
2 02.00 2.9 W 30.0 72 3 0
3 03.00 4.0 W 28.0 77 3 0
4 04.00 4.5 W 27.0 77 3 0
5 05.00 6.9 WSW 27.0 77 3 0
6 06.00 3.6 WSW 30.0 72 3 0
7 07.00 4.4 WSW 32.0 70 2 0
8 08.00 6.1 WSW 32.5 67 2 0
9 09.00 9.4 SW 34.0 56 1 0
10 10.00 7.9 SW 38.0 47 1 0
11 11.00 11.7 SW 38.5 45 1 0
12 12.00 10.9 SSW 40.0 38 1 0
13 13.00 15.7 SSW 40.5 34 0 0
14 14.00 8.5 SSW 42.0 32 0 0
15 15.00 4.8 SW 42.5 32 0 0
16 16.00 5.3 WSW 42.0 36 0 0
17 17.00 3.0 W 40.5 38 1 0
18 18.00 2.6 W 40.0 42 1 0
19 19.00 4.6 WNW 38.5 45 1 0
20 20.00 7.1 WNW 38.0 50 2 0
21 21.00 4.3 WNW 36.5 53 2 0
22 22.00 8.7 WNW 36.0 55 2 0
23 23.00 4.0 W 34.5 56 3 0
24 24.00 3.4 W 34.0 59 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : W 2. Wind Velocity (Kmph) Min : 1.9 Max : 15.7 Avg : 6.1
3. Ambient Temperature (°C) Min : 27.0 Max : 42.5 Avg : 35.5
4. Relative Humidity (%) Min : 32.0 Max : 77.0 Avg : 54.1
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 31 METEOROLOGICAL DATA
Date : 01.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 5.7 WNW 32.5 61 3 0
2 02.00 6.0 SSW 32.0 64 3 0
3 03.00 5.4 SW 30.0 68 3 0
4 04.00 4.2 SW 29.5 71 3 0
5 05.00 3.6 SW 29.0 74 3 0
6 06.00 3.6 SW 29.0 72 3 0
7 07.00 6.1 WSW 30.5 65 2 0
8 08.00 10.3 WSW 32.0 61 2 0
9 09.00 9.5 SW 34.0 56 2 0
10 10.00 12.6 SW 36.0 48 1 0
11 11.00 12.6 SSW 36.5 45 1 0
12 12.00 13.8 SSW 38.0 45 1 0
13 13.00 11.3 SSW 38.5 40 0 0
14 14.00 8.0 SSW 40.0 34 0 0
15 15.00 3.4 SW 42.5 32 0 0
16 16.00 4.8 SW 42.0 32 1 0
17 17.00 6.6 SW 42.0 32 1 0
18 18.00 6.9 WSW 40.0 38 2 0
19 19.00 7.0 WSW 38.0 40 2 0
20 20.00 3.2 WSW 36.5 53 2 0
21 21.00 2.3 WSW 34.5 54 2 0
22 22.00 1.6 WSW 34.0 56 3 0
23 23.00 1.9 SW 32.5 63 3 0
24 24.00 1.5 SW 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): SW 2. Wind Velocity (Kmph) : Min 1.5 Max : 13.8 Avg : 6.3
3. Ambient Temperature (°C) : Min : 29.0 Max : 42.5 Avg : 35.1
4. Relative Humidity (%) : Min : 32.0 Max : 74.0 Avg : 52.9
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 32 METEOROLOGICAL DATA
Date : 02.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity (%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 13.0 WNW 30.5 68 3 0
2 02.00 10.6 WSW 30.0 72 3 0
3 03.00 9.1 WSW 29.5 74 3 0
4 04.00 9.3 W 29.0 78 3 0
5 05.00 8.6 W 29.0 72 3 0
6 06.00 4.7 W 30.0 61 2 0
7 07.00 4.9 W 32.0 56 2 0
8 08.00 6.2 WSW 34.0 53 2 0
9 09.00 9.6 WSW 36.0 45 1 0
10 10.00 5.9 SW 38.0 40 1 0
11 11.00 11.5 SW 40.0 36 1 0
12 12.00 12.6 SW 42.0 31 1 0
13 13.00 14.0 SSW 42.5 27 0 0
14 14.00 13.5 SSW 44.0 31 0 0
15 15.00 10.7 S 44.5 32 0 0
16 16.00 9.8 S 44.0 38 1 0
17 17.00 7.6 S 42.0 40 1 0
18 18.00 5.3 WSW 40.0 53 2 0
19 19.00 4.4 WSW 38.0 54 2 0
20 20.00 4.2 WSW 36.0 56 3 0
21 21.00 4.0 SW 34.5 6 3 0
22 22.00 5.5 SSW 34.0 67 3 0
23 23.00 6.9 SSW 32.5 63 3 0
24 24.00 7.4 WSW 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): WSW 2. Wind Velocity (Kmph) : Min 4.0 Max : 14.0 Avg : 8.3
3. Ambient Temperature (°C) : Min : 29.0 Max : 44.5 Avg : 36.0
4. Relative Humidity (%) : Min : 6.0 Max : 78.0 Avg : 50.8
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 33 METEOROLOGICAL DATA
Date : 03.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C) Relative
Humidity (%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 9.0 WNW 30.5 68 3 0
2 02.00 11.7 WNW 30.0 72 3 0
3 03.00 12.0 WNW 29.5 74 3 0
4 04.00 10.0 NW 29.5 74 3 0
5 05.00 9.5 WNW 29.5 72 3 0
6 06.00 3.0 NW 31.0 65 2 0
7 07.00 3.7 NW 34.0 56 2 0
8 08.00 4.8 WNW 36.0 53 2 0
9 09.00 7.9 WNW 38.0 45 1 0
10 10.00 10.3 W 38.5 40 1 0
11 11.00 11.2 W 40.0 38 1 0
12 12.00 12.6 WSW 40.5 36 1 0
13 13.00 14.5 WSW 42.5 32 0 0
14 14.00 12.0 W 44.5 31 0 0
15 15.00 9.6 WSW 46.0 29 0 0
16 16.00 8.3 W 44.0 31 1 0
17 17.00 7.9 WNW 42.0 32 1 0
18 18.00 6.3 WNW 40.5 40 2 0
19 19.00 5.0 NW 38.0 53 2 0
20 20.00 4.5 NW 36.0 54 3 0
21 21.00 6.4 WNW 34.5 56 3 0
22 22.00 8.7 WNW 34.0 59 3 0
23 23.00 7.0 W 32.5 63 3 0
24 24.00 4.3 WSW 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): WNW 2. Wind Velocity (Kmph) : Min : 3.0 Max : 14.5 Avg : 8.3
3. Ambient Temperature (°C) : Min : 29.5 Max : 46.0 Avg : 36.4
4. Relative Humidity (%) : Min : 29.0 Max : 74.0 Avg : 51.6
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 34 METEOROLOGICAL DATA
Date : 04.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C) Relative
Humidity (%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 5.7 WNW 30.5 68 3 0
2 02.00 6.0 WSW 30.0 72 3 0
3 03.00 5.4 WSW 29.5 70 3 0
4 04.00 4.2 WNW 29.0 68 3 0
5 05.00 3.6 NW 29.0 66 3 0
6 06.00 3.4 NNW 30.0 65 3 0
7 07.00 3.2 WNW 32.0 61 2 0
8 08.00 4.0 NNW 34.5 56 2 0
9 09.00 6.1 NW 36.0 53 2 0
10 10.00 8.3 NW 38.0 45 1 0
11 11.00 6.4 WNW 40.0 42 1 0
12 12.00 11.1 NW 42.5 40 1 0
13 13.00 13.2 NW 44.0 36 0 0
14 14.00 14.0 NW 44.5 31 0 0
15 15.00 11.4 WNW 40.0 27 0 0
16 16.00 9.3 NW 38.5 34 1 0
17 17.00 8.0 NNW 38.0 36 1 0
18 18.00 11.4 WNW 36.5 45 2 0
19 19.00 13.0 WNW 34.5 50 2 0
20 20.00 1.6 WSW 34.0 53 2 0
21 21.00 2.1 WSW 33.5 54 2 0
22 22.00 4.1 SW 33.0 56 3 0
23 23.00 7.0 SW 32.0 63 3 0
24 24.00 6.4 SSW 30.5 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): WNW 2. Wind Velocity (Kmph) : Min 1.6 Max : 14.0 Avg : 7.0
3. Ambient Temperature (°C) : Min : 29.0 Max : 44.5 Avg : 35.0
4. Relative Humidity (%) : Min : 27.0 Max : 72.0 Avg : 52.3
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 35 METEOROLOGICAL DATA
Date : 05.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 5.0 WNW 30.5 68 3 0
2 02.00 4.4 SW 30.0 72 3 0
3 03.00 3.6 SW 29.5 74 3 0
4 04.00 4.0 SSW 29.0 76 3 0
5 05.00 4.9 NW 29.0 78 3 0
6 06.00 3.0 NW 30.0 74 2 0
7 07.00 2.3 NW 30.5 65 2 0
8 08.00 1.5 NE 32.0 61 2 0
9 09.00 1.7 ENE 34.0 56 1 0
10 10.00 5.0 NE 36.0 48 1 0
11 11.00 8.9 NE 36.5 45 1 0
12 12.00 12.3 NW 38.0 43 1 0
13 13.00 9.4 NW 40.0 40 0 0
14 14.00 12.1 NNW 42.0 34 0 0
15 15.00 11.4 WNW 42.5 26 0 0
16 16.00 8.4 NNW 40.0 33 1 0
17 17.00 5.1 NW 38.5 40 1 0
18 18.00 4.0 WNW 38.0 46 2 0
19 19.00 6.4 NW 36.5 49 2 0
20 20.00 5.5 WNW 36.0 53 3 0
21 21.00 5.9 NW 34.5 54 3 0
22 22.00 4.1 NW 34.0 56 3 0
23 23.00 3.4 NW 32.5 63 3 0
24 24.00 5.6 NNW 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): NW 2. Wind Velocity (Kmph) : Min : 1.5 Max : 12.3 Avg : 5.7
3. Ambient Temperature (°C) : Min : 29.0 Max : 42.5 Avg : 34.6
4. Relative Humidity (%) : Min : 26.0 Max : 78.0 Avg : 55.0
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 36 METEOROLOGICAL DATA
Date : 06.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 5.9 WNW 30.5 65 3 0
2 02.00 7.8 NW 30.0 69 3 0
3 03.00 4.5 NNW 29.5 72 3 0
4 04.00 3.6 NNW 29.0 74 3 0
5 05.00 2.0 NW 29.0 76 3 0
6 06.00 2.3 NW 30.5 72 3 0
7 07.00 6.4 NW 32.0 70 2 0
8 08.00 9.7 NW 32.5 67 2 0
9 09.00 16.6 NE 34.0 56 1 0
10 10.00 14.3 NE 36.0 47 1 0
11 11.00 9.3 NE 38.5 45 1 0
12 12.00 7.6 SE 40.0 38 1 0
13 13.00 6.0 SE 40.5 34 0 0
14 14.00 5.3 SE 42.5 32 0 0
15 15.00 5.7 NNW 42.0 32 0 0
16 16.00 4.3 NNW 41.0 36 1 0
17 17.00 7.0 NW 40.0 38 1 0
18 18.00 7.4 NW 38.0 38 2 0
19 19.00 8.3 NW 36.0 40 2 0
20 20.00 5.1 WNW 34.5 53 2 0
21 21.00 5.7 WNW 34.0 54 2 0
22 22.00 3.8 NW 32.5 56 3 0
23 23.00 2.1 NW 32.0 63 3 0
24 24.00 1.7 NW 30.5 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): NW 2. Wind Velocity (Kmph) : Min : 1.7 Max : 16.6 Avg : 6.4
3. Ambient Temperature (°C) : Min : 29.0 Max : 42.5 Avg : 34.8
4. Relative Humidity (%) : Min : 32.0 Max : 76.0 Avg : 53.8
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 37 METEOROLOGICAL DATA
Date : 07.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 1.3 WNW 30.5 65 3 0
2 02.00 3.0 NW 30.0 69 3 0
3 03.00 2.5 NNW 29.5 72 3 0
4 04.00 2.3 NNW 29.0 74 3 0
5 05.00 2.8 NNE 29.0 76 3 0
6 06.00 3.0 N 30.5 72 3 0
7 07.00 3.6 NW 32.5 70 2 0
8 08.00 4.7 NNW 34.5 67 2 0
9 09.00 6.9 NW 36.0 56 2 0
10 10.00 8.1 NW 38.5 47 1 0
11 11.00 4.9 NNW 40.0 45 1 0
12 12.00 7.3 NNW 42.0 38 1 0
13 13.00 7.1 NW 42.5 34 0 0
14 14.00 9.3 NE 44.0 32 0 0
15 15.00 13.0 NNW 44.5 27 0 0
16 16.00 12.3 NNW 44.0 32 1 0
17 17.00 10.1 NNW 42.0 38 1 0
18 18.00 3.4 WNW 40.0 38 2 0
19 19.00 6.0 WNW 38.0 40 2 0
20 20.00 4.3 N 36.0 53 2 0
21 21.00 5.0 N 34.5 54 2 0
22 22.00 6.4 NNE 34.0 56 3 0
23 23.00 7.0 NNE 32.5 63 3 0
24 24.00 8.1 N 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): NW 2. Wind Velocity (Kmph) : Min 1.3 Max : 13.0 Avg : 5.9
3. Ambient Temperature (°C) : Min : 29.0 Max : 44.5 Avg : 36.1
4. Relative Humidity (%) : Min : 27.0 Max : 76.0 Avg : 53.5
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 38 METEOROLOGICAL DATA
Date : 08.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C) Relative
Humidity (%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 12.0 WNW 30.5 68 3 0
2 02.00 10.6 N 30.5 72 3 0
3 03.00 9.3 N 29.5 74 3 0
4 04.00 5.8 N 29.0 75 3 0
5 05.00 6.0 NW 29.0 76 3 0
6 06.00 3.3 N 30.0 65 2 0
7 07.00 5.9 NNW 32.5 61 2 0
8 08.00 11.2 N 34.5 56 2 0
9 09.00 8.3 NW 36.0 53 1 0
10 10.00 5.1 NNW 38.5 45 1 0
11 11.00 4.2 N 40.0 42 1 0
12 12.00 1.7 N 42.0 40 1 0
13 13.00 2.0 NW 42.5 36 0 0
14 14.00 2.6 N 44.0 31 0 0
15 15.00 2.4 NNW 44.5 27 0 0
16 16.00 1.9 NNW 44.0 31 1 0
17 17.00 3.0 NNW 42.0 32 1 0
18 18.00 3.4 NW 40.0 38 2 0
19 19.00 4.0 NW 38.0 40 2 0
20 20.00 3.8 WNW 36.0 53 3 0
21 21.00 5.7 NNW 34.5 54 3 0
22 22.00 2.4 NW 32.5 56 3 0
23 23.00 3.5 NW 32.0 63 3 0
24 24.00 1.9 N 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): N 2. Wind Velocity (Kmph) : Min 1.7 Max : 12.0 Avg : 5.0
3. Ambient Temperature (°C) : Min : 29.0 Max : 44.5 Avg : 36.0
4. Relative Humidity (%) : Min : 27.0 Max : 76.0 Avg : 52.2
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 39 METEOROLOGICAL DATA
Date : 09.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity (%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 2.5 WNW 30.5 68 3 0
2 02.00 3.1 NW 30.0 72 3 0
3 03.00 3.3 N 29.5 74 3 0
4 04.00 2.8 WNW 29.0 75 3 0
5 05.00 2.1 NW 29.0 76 3 0
6 06.00 4.7 NW 30.5 65 3 0
7 07.00 4.9 ENE 34.0 62 2 0
8 08.00 6.2 NE 36.5 53 2 0
9 09.00 9.6 NE 37.0 45 2 0
10 10.00 8.9 WNW 38.0 40 1 0
11 11.00 11.4 NW 40.0 38 1 0
12 12.00 5.9 NNW 40.5 36 1 0
13 13.00 4.7 NW 42.0 32 0 0
14 14.00 5.9 ENE 44.0 31 0 0
15 15.00 4.1 SSE 46.0 29 0 0
16 16.00 7.6 NE 44.0 31 1 0
17 17.00 5.9 NNW 42.5 32 1 0
18 18.00 4.4 NW 40.0 38 2 0
19 19.00 4.2 NW 38.0 40 2 0
20 20.00 4.0 NE 36.0 53 2 0
21 21.00 5.5 NE 34.5 54 2 0
22 22.00 6.9 NW 34.0 56 3 0
23 23.00 7.4 ENE 32.5 63 3 0
24 24.00 3.5 NE 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): NW 2. Wind Velocity (Kmph) : Min : 2.1 Max : 11.4 Avg : 5.4
3. Ambient Temperature (°C) : Min : 29.0 Max : 46.0 Avg : 36.3
4. Relative Humidity (%) : Min : 29.0 Max : 76.0 Avg : 51.2
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 40 METEOROLOGICAL DATA
Date : 10.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 11.7 WNW 32.5 68 3 0
2 02.00 11.5 NW 32.0 72 3 0
3 03.00 10.2 NW 30.0 74 3 0
4 04.00 9.5 NW 29.5 78 3 0
5 05.00 7.1 NW 29.0 72 3 0
6 06.00 3.0 NNW 30.0 72 2 0
7 07.00 3.7 NW 32.5 61 2 0
8 08.00 4.9 W 34.5 56 2 0
9 09.00 7.9 NNE 36.0 53 1 0
10 10.00 10.3 NNE 38.5 45 1 0
11 11.00 7.3 NW 40.5 42 1 0
12 12.00 6.1 WNW 42.0 40 1 0
13 13.00 7.0 NW 42.5 36 0 0
14 14.00 3.4 NNE 44.0 31 0 0
15 15.00 1.3 NE 44.5 27 0 0
16 16.00 3.0 NE 44.0 31 1 0
17 17.00 4.1 ENE 42.5 32 1 0
18 18.00 6.3 E 40.0 38 2 0
19 19.00 5.0 NE 38.0 40 2 0
20 20.00 4.5 SSE 36.0 53 3 0
21 21.00 6.4 SSE 34.5 54 3 0
22 22.00 8.1 SE 34.0 56 3 0
23 23.00 7.0 ESE 32.5 63 3 0
24 24.00 4.3 NE 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): NW 2. Wind Velocity (Kmph) : Min 1.3 Max : 11.7 Avg : 6.4
3. Ambient Temperature (°C) : Min : 29.0 Max : 44.5 Avg : 36.3
4. Relative Humidity (%) : Min : 27.0 Max : 78.0 Avg : 52.5
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 41 METEOROLOGICAL DATA
Date : 11.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 5.7 WNW 32.5 68 3 0
2 02.00 6.0 NW 32.0 72 3 0
3 03.00 5.4 NNW 30.0 70 3 0
4 04.00 4.2 NW 31.0 68 3 0
5 05.00 3.6 NNE 31.5 66 3 0
6 06.00 4.8 ENE 32.0 67 3 0
7 07.00 9.6 NE 34.0 59 2 0
8 08.00 13.6 NW 34.5 53 2 0
9 09.00 15.6 NW 36.0 48 1 0
10 10.00 16.3 NW 36.5 46 1 0
11 11.00 17.0 NW 38.0 44 1 0
12 12.00 15.2 NW 40.0 42 1 0
13 13.00 14.4 NNW 42.0 36 0 0
14 14.00 14.0 NNE 44.5 31 0 0
15 15.00 11.7 NNE 46.0 26 0 0
16 16.00 8.5 E 44.0 31 1 0
17 17.00 11.4 ENE 42.0 32 1 0
18 18.00 12.4 NNE 40.0 38 2 0
19 19.00 10.0 NNW 38.0 40 2 0
20 20.00 7.4 NNW 36.0 43 2 0
21 21.00 6.6 NW 34.5 46 2 0
22 22.00 4.3 NE 34.0 51 3 0
23 23.00 5.4 NE 32.5 63 3 0
24 24.00 6.1 NE 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): NW 2. Wind Velocity (Kmph) : Min 3.6 Max : 17.0 Avg : 9.6
3. Ambient Temperature (°C) : Min : 30.0 Max : 46.0 Avg : 36.4
4. Relative Humidity (%) : Min : 26.0 Max : 72.0 Avg : 50.2
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 42 METEOROLOGICAL DATA
Date : 12.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C) Relative
Humidity (%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 5.0 WNW 30.0 64 3 0
2 02.00 5.7 WNW 29.0 66 3 0
3 03.00 6.4 N 28.0 68 3 0
4 04.00 7.0 WNW 27.0 72 3 0
5 05.00 6.9 WNW 27.0 73 3 0
6 06.00 4.7 NNW 30.0 67 3 0
7 07.00 6.8 NW 34.0 58 2 0
8 08.00 10.6 WNW 36.0 53 2 0
9 09.00 9.9 NW 38.5 45 2 0
10 10.00 12.4 NNW 40.0 40 1 0
11 11.00 7.9 NNW 41.0 38 1 0
12 12.00 11.3 WNW 42.5 36 1 0
13 13.00 15.6 WNW 44.0 32 0 0
14 14.00 11.4 NW 46.5 31 0 0
15 15.00 8.5 NNW 44.0 29 0 0
16 16.00 4.8 NW 42.5 31 1 0
17 17.00 6.1 NNW 40.0 32 1 0
18 18.00 4.2 NNW 38.0 38 2 0
19 19.00 4.0 WNW 36.0 40 2 0
20 20.00 6.2 WNW 34.5 53 2 0
21 21.00 12.5 NNW 34.0 54 2 0
22 22.00 8.1 NNW 32.5 56 3 0
23 23.00 6.8 N 32.0 63 3 0
24 24.00 4.1 N 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): NNW 2. Wind Velocity (Kmph) : Min 4.0 Max : 15.6 Avg : 7.8
3. Ambient Temperature (°C) : Min : 27.0 Max : 46.5 Avg : 35.8
4. Relative Humidity (%) : Min : 29.0 Max : 73.0 Avg : 50.2
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 43 METEOROLOGICAL DATA
Date : 13.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 9.6 WNW 30.5 66 3 0
2 02.00 7.3 N 30.0 72 3 0
3 03.00 5.6 N 29.5 74 3 0
4 04.00 5.0 N 29.0 76 3 0
5 05.00 5.3 NW 29.0 76 3 0
6 06.00 4.0 N 30.0 71 2 0
7 07.00 3.4 NNW 32.0 64 2 0
8 08.00 4.7 N 34.0 59 2 0
9 09.00 7.0 NW 36.5 53 1 0
10 10.00 16.9 NNW 38.5 45 1 0
11 11.00 17.0 N 40.0 42 1 0
12 12.00 14.9 N 42.0 40 1 0
13 13.00 15.6 NW 42.5 36 0 0
14 14.00 6.1 N 44.0 31 0 0
15 15.00 4.0 NNW 44.5 32 0 0
16 16.00 5.8 NNW 44.0 34 1 0
17 17.00 6.2 NNW 42.0 38 1 0
18 18.00 6.7 NW 42.0 40 2 0
19 19.00 3.2 NW 40.0 53 2 0
20 20.00 2.6 WNW 38.5 54 3 0
21 21.00 1.8 NNW 36.5 56 3 0
22 22.00 1.4 NW 34.5 60 3 0
23 23.00 2.0 NW 33.0 63 3 0
24 24.00 1.5 N 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): N 2. Wind Velocity (Kmph) : Min 1.4 Max : 17.0 Avg : 6.6
3. Ambient Temperature (°C) : Min : 29.0 Max : 44.5 Avg : 36.4
4. Relative Humidity (%) : Min : 31.0 Max : 76.0 Avg : 54.2
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 44 METEOROLOGICAL DATA
Date : 14.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 8.6 WNW 32.0 66 3 0
2 02.00 10.5 WNW 31.0 68 3 0
3 03.00 9.2 WNW 30.0 70 3 0
4 04.00 6.2 W 29.0 72 3 0
5 05.00 4.3 WNW 29.0 68 3 0
6 06.00 4.2 WNW 30.5 65 3 0
7 07.00 5.0 W 32.5 61 2 0
8 08.00 6.3 WNW 34.5 56 2 0
9 09.00 5.1 NW 36.5 53 1 0
10 10.00 4.8 NW 38.0 47 1 0
11 11.00 3.5 NNW 40.0 43 1 0
12 12.00 4.9 NNW 41.0 38 1 0
13 13.00 6.3 NW 42.5 36 0 0
14 14.00 10.5 WNW 44.0 32 0 0
15 15.00 12.3 WNW 46.0 29 0 0
16 16.00 11.5 WNW 44.0 31 1 0
17 17.00 9.3 W 42.5 35 1 0
18 18.00 8..7 W 39.0 39 2 0
19 19.00 10.2 WNW 37.0 47 2 0
20 20.00 6.4 WNW 35.0 51 2 0
21 21.00 5.2 NW 34.0 56 2 0
22 22.00 4.0 NNW 33.0 62 3 0
23 23.00 3.5 NNW 32.5 63 3 0
24 24.00 5.9 NW 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): WNW 2. Wind Velocity (Kmph) : Min 3.5 Max : 12.3 Avg : 6.9
3. Ambient Temperature (°C) : Min : 29.0 Max : 46.0 Avg : 36.1
4. Relative Humidity (%) : Min : 29.0 Max : 72.0 Avg : 52.2
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 45 METEOROLOGICAL DATA
Date : 15.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 4.6 WNW 30.5 68 3 0
2 02.00 3.5 WSW 30.0 72 3 0
3 03.00 2.8 WSW 29.5 70 3 0
4 04.00 3.5 SW 29.5 68 3 0
5 05.00 3.4 WSW 29.0 66 3 0
6 06.00 5.2 WSW 30.5 63 2 0
7 07.00 6.5 WSW 32.5 61 2 0
8 08.00 7.0 SW 34.5 56 2 0
9 09.00 8.5 WSW 36.0 53 1 0
10 10.00 9.2 WSW 38.5 45 1 0
11 11.00 10.5 SW 40.0 42 1 0
12 12.00 13.4 WSW 42.5 40 1 0
13 13.00 15.0 WSW 44.0 36 0 0
14 14.00 13.2 SW 42.0 31 0 0
15 15.00 14.5 SSW 40.0 27 0 0
16 16.00 9.3 SSW 39.0 34 1 0
17 17.00 8.5 SW 38.0 45 1 0
18 18.00 6.4 WSW 37.0 48 2 0
19 19.00 3.8 WSW 36.0 50 2 0
20 20.00 4.0 SW 35.5 53 3 0
21 21.00 4.5 WSW 34.0 54 3 0
22 22.00 6.2 WSW 33.0 58 3 0
23 23.00 5.1 SW 32.5 63 3 0
24 24.00 5.5 SSW 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): WSW 2. Wind Velocity (Kmph) : Min 2.8 Max : 15.0 Avg : 7.3
3. Ambient Temperature (°C) : Min : 29.0 Max : 44.0 Avg : 35.3
4. Relative Humidity (%) : Min : 27.0 Max : 72.0 Avg : 52.8
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 46 METEOROLOGICAL DATA
Date : 16.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 4.5 WNW 30.5 64 3 0
2 02.00 4.0 S 30.0 66 3 0
3 03.00 3.3 SSW 29.5 68 3 0
4 04.00 2.9 SSW 29.0 72 3 0
5 05.00 2.5 SSW 29.0 73 3 0
6 06.00 4.2 S 30.0 72 3 0
7 07.00 5.0 SSW 30.5 65 2 0
8 08.00 6.8 SSW 32.0 61 2 0
9 09.00 7.2 S 34.5 56 1 0
10 10.00 6.9 SSW 36.0 48 1 0
11 11.00 10.2 SSW 37.0 45 1 0
12 12.00 13.5 SW 38.0 40 1 0
13 13.00 18.6 SW 39.0 34 0 0
14 14.00 12.5 SSW 40.0 31 0 0
15 15.00 11.0 SSW 42.5 33 0 0
16 16.00 5.9 S 41.0 36 1 0
17 17.00 6.4 SSW 40.0 38 1 0
18 18.00 5.0 SW 39.0 42 2 0
19 19.00 4.8 SW 38.0 45 2 0
20 20.00 3.5 SSW 36.5 50 2 0
21 21.00 4.2 SSW 36.0 53 2 0
22 22.00 3.7 SW 35.5 55 3 0
23 23.00 4.0 SW 35.0 63 3 0
24 24.00 5.1 S 34.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): SSW 2. Wind Velocity (Kmph) : Min 2.5 Max : 18.6 Avg : 6.5
3. Ambient Temperature (°C) : Min : 29.0 Max : 42.5 Avg : 35.1
4. Relative Humidity (%) : Min : 31.0 Max : 73.0 Avg : 53.1
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear
TABLE : 47 METEOROLOGICAL DATA
Date : 17.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 3.2 WNW 32.5 64 3 0
2 02.00 2.4 SW 32.0 66 3 0
3 03.00 2.0 SSW 31.0 68 3 0
4 04.00 1.5 SW 30.0 72 3 0
5 05.00 1.2 SW 29.0 73 3 0
6 06.00 3.2 SSW 30.0 72 3 0
7 07.00 1.5 S 32.0 70 2 0
8 08.00 2.0 S 33.0 67 2 0
9 09.00 1.8 SSW 34.5 56 1 0
10 10.00 3.9 SW 36.0 47 1 0
11 11.00 5.0 SW 38.0 45 1 0
12 12.00 10.2 SSW 40.0 38 1 0
13 13.00 11.2 SW 41.0 34 0 0
14 14.00 13.1 SW 42.5 32 0 0
15 15.00 10.2 SSW 44.0 27 0 0
16 16.00 8.5 S 43.0 31 1 0
17 17.00 6.2 SSW 42.0 32 1 0
18 18.00 4.9 SSW 40.0 38 2 0
19 19.00 5.2 SW 39.5 40 2 0
20 20.00 4.5 SW 38.0 53 2 0
21 21.00 3.0 SSW 36.0 54 2 0
22 22.00 2.5 SW 34.0 56 3 0
23 23.00 4.5 SSW 32.5 63 3 0
24 24.00 3.6 SSW 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): SW
2. Wind Velocity (Kmph) : Min 1.2 Max : 13.1 Avg : 4.8
3. Ambient Temperature (°C) : Min : 29.0 Max : 44.0 Avg : 35.9
4. Relative Humidity (%) : Min : 27.0 Max : 73.0 Avg : 52.6
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 750
7. Sky Appearance : Clear
TABLE : 48 METEOROLOGICAL DATA
Date : 18.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 4.1 WNW 30.5 66 3 0
2 02.00 2.0 SW 30.0 72 3 0
3 03.00 2.8 SSW 29.5 70 3 0
4 04.00 3.1 SW 29.5 68 3 0
5 05.00 2.6 SW 31.0 66 3 0
6 06.00 5.6 SSW 32.5 65 2 0
7 07.00 6.3 SW 34.0 56 2 0
8 08.00 9.7 SW 36.5 53 2 0
9 09.00 16.0 SSW 38.0 45 1 0
10 10.00 14.3 SSW 40.0 40 1 0
11 11.00 9.3 SW 40.5 38 1 0
12 12.00 7.6 SW 42.0 36 1 0
13 13.00 17.2 WSW 44.0 32 0 0
14 14.00 12.0 WSW 46.0 31 0 0
15 15.00 8.4 SW 42.0 29 0 0
16 16.00 5.6 SW 40.5 36 1 0
17 17.00 4.0 WSW 40.0 38 1 0
18 18.00 4.4 SW 38.5 42 2 0
19 19.00 6.2 SW 37.0 44 2 0
20 20.00 12.6 SSW 36.0 50 3 0
21 21.00 11.0 SW 35.5 53 3 0
22 22.00 8.9 SW 35.0 55 3 0
23 23.00 6.8 SSW 34.0 63 3 0
24 24.00 5.9 SW 33.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): SW
2. Wind Velocity (Kmph) : Min 2.0 Max : 17.2 Avg : 7.8
3. Ambient Temperature (°C) : Min : 29.5 Max : 46.0 Avg : 36.5
4. Relative Humidity (%) : Min : 29.0 Max : 72.0 Avg : 50.5
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 750
7. Sky Appearance : Clear
TABLE : 49 METEOROLOGICAL DATA
Date : 19.05.13
Location : Corezone
Sl.No
Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C) Relative
Humidity (%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 4.1 WNW 32.5 67 3 0
2 02.00 3.0 WSW 32.0 72 3 0
3 03.00 2.8 W 30.0 70 3 0
4 04.00 3.1 W 29.5 68 3 0
5 05.00 2.6 WNW 29.0 66 3 0
6 06.00 5.6 WNW 30.0 65 3 0
7 07.00 6.3 W 32.5 61 2 0
8 08.00 9.7 W 34.0 56 2 0
9 09.00 16.0 W 36.0 53 2 0
10 10.00 14.3 WNW 38.0 45 1 0
11 11.00 9.3 W 40.0 42 1 0
12 12.00 7.6 W 42.0 40 1 0
13 13.00 19.0 WNW 43.0 36 0 0
14 14.00 12.0 W 44.0 31 0 0
15 15.00 8.4 W 44.5 29 0 0
16 16.00 5.6 WNW 43.0 31 1 0
17 17.00 4.0 NW 42.5 34 1 0
18 18.00 4.4 NW 40.0 38 2 0
19 19.00 6.2 WNW 38.0 40 2 0
20 20.00 12.6 W 36.5 46 2 0
21 21.00 11.0 W 35.0 51 2 0
22 22.00 8.9 WNW 34.0 57 3 0
23 23.00 6.8 W 32.5 63 3 0
24 24.00 5.9 WSW 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): W
2. Wind Velocity (Kmph) : Min 2.6 Max : 19.0 Avg : 7.9 3. Ambient Temperature (°C) : Min : 29.0 Max : 44.5 Avg : 36.3
4. Relative Humidity (%) : Min : 29.0 Max : 72.0 Avg : 51.1
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 750
7. Sky Appearance : Clear
TABLE : 50 METEOROLOGICAL DATA
Date : 20.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 3.5 WNW 32.5 66 3 0
2 02.00 5.1 WNW 32.0 72 3 0
3 03.00 4.6 W 30.0 70 3 0
4 04.00 3.2 W 31.0 68 3 0
5 05.00 2.5 WSW 31.5 66 3 0
6 06.00 4.2 WSW 32.0 65 2 0
7 07.00 4.6 W 34.5 62 2 0
8 08.00 7.2 WSW 36.0 53 2 0
9 09.00 8.5 WSW 38.0 45 1 0
10 10.00 9.2 W 39.0 40 1 0
11 11.00 10.5 WSW 40.0 38 1 0
12 12.00 8.0 WSW 41.0 36 1 0
13 13.00 10.2 SW 42.0 32 0 0
14 14.00 14.0 SW 44.0 31 0 0
15 15.00 12.4 WSW 46.5 29 0 0
16 16.00 6.7 WSW 44.0 31 1 0
17 17.00 8.1 WSW 42.0 32 1 0
18 18.00 5.3 SW 40.0 38 2 0
19 19.00 4.8 WSW 39.0 40 2 0
20 20.00 3.4 WSW 37.5 53 3 0
21 21.00 2.8 SW 36.0 54 3 0
22 22.00 3.0 SW 34.5 56 3 0
23 23.00 3.4 WSW 33.0 63 3 0
24 24.00 4.2 WSW 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): WSW
2. Wind Velocity (Kmph) : Min : 2.5 Max : 14.0 Avg : 6.2
3. Ambient Temperature (°C) : Min : 30.0 Max : 46.5 Avg : 37.0
4. Relative Humidity (%) : Min : 29.0 Max : 72.0 Avg : 50.2
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 750
7. Sky Appearance : Clear
TABLE : 51 METEOROLOGICAL DATA
Date : 21.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 3.4 WNW 32.5 64 3 0
2 02.00 4.2 W 32.0 66 3 0
3 03.00 3.6 W 30.0 68 3 0
4 04.00 4.5 WNW 31.0 72 3 0
5 05.00 5.1 WNW 31.5 73 3 0
6 06.00 2.8 NW 32.0 73 3 0
7 07.00 4.2 NW 34.0 68 2 0
8 08.00 5.0 WNW 35.0 62 2 0
9 09.00 5.6 WNW 36.0 58 2 0
10 10.00 6.2 W 37.5 45 1 0
11 11.00 8.5 WNW 38.0 43 1 0
12 12.00 6.7 WNW 40.0 42 1 0
13 13.00 7.6 NW 42.0 36 0 0
14 14.00 10.2 NW 44.5 31 0 0
15 15.00 12.5 WNW 43.0 33 0 0
16 16.00 13.7 WNW 42.5 36 1 0
17 17.00 11.5 W 40.0 40 1 0
18 18.00 8.6 W 38.5 46 2 0
19 19.00 5.2 WNW 36.0 53 2 0
20 20.00 4.8 WNW 34.5 56 2 0
21 21.00 4.0 W 34.0 58 2 0
22 22.00 3.5 WSW 32.5 61 3 0
23 23.00 3.1 WSW 32.0 63 3 0
24 24.00 2.6 WSW 31.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): WNW
2. Wind Velocity (Kmph) : Min 2.6 Max : 13.7 Avg : 6.1
3. Ambient Temperature (°C) : Min : 30.0 Max : 44.5 Avg : 35.8
4. Relative Humidity (%) : Min : 31.0 Max : 73.0 Avg : 54.7
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 750
7. Sky Appearance : Clear
TABLE : 52 METEOROLOGICAL DATA
Date : 22.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 5.1 WNW 32.5 68 3 0
2 02.00 4.5 NNW 32.0 72 3 0
3 03.00 6.1 NW 30.0 70 3 0
4 04.00 5.6 NNW 29.5 68 3 0
5 05.00 4.8 NW 29.0 66 3 0
6 06.00 5.2 NNE 32.0 67 2 0
7 07.00 6.5 WNW 34.0 63 2 0
8 08.00 7.3 NE 35.0 57 2 0
9 09.00 10.5 NW 36.0 51 1 0
10 10.00 14.6 ENE 37.0 48 1 0
11 11.00 17.0 WNW 38.0 43 1 0
12 12.00 18.5 NE 40.0 42 1 0
13 13.00 15.3 NE 42.0 36 0 0
14 14.00 14.0 NNW 44.5 31 0 0
15 15.00 12.5 NNW 46.0 26 0 0
16 16.00 8.9 WNW 44.0 29 1 0
17 17.00 5.2 NNW 42.5 31 1 0
18 18.00 6.0 NE 41.0 33 2 0
19 19.00 5.4 NW 40.0 38 2 0
20 20.00 7.1 NW 38.5 45 3 0
21 21.00 6.5 NNW 36.5 48 3 0
22 22.00 3.8 NW 35.0 53 3 0
23 23.00 3.4 NW 34.0 63 3 0
24 24.00 4.3 NNW 32.5 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): NW
2. Wind Velocity (Kmph) : Min 3.4 Max : 18.5 Avg : 8.3
3. Ambient Temperature (°C) : Min : 29.0 Max : 46.0 Avg : 36.7
4. Relative Humidity (%) : Min : 26.0 Max : 72.0 Avg : 50.5
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 750
7. Sky Appearance : Clear
TABLE : 53 METEOROLOGICAL DATA
Date : 23.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 3.9 WNW 32.5 68 3 0
2 02.00 5.7 NW 32.0 72 3 0
3 03.00 5.3 NW 30.0 70 3 0
4 04.00 3.8 NNW 29.5 68 3 0
5 05.00 4.5 NNW 31.0 66 3 0
6 06.00 6.2 NW 32.5 67 3 0
7 07.00 5.6 NW 34.0 63 2 0
8 08.00 9.2 SW 36.0 57 2 0
9 09.00 10.4 SW 38.5 51 2 0
10 10.00 11.3 SW 39.0 48 1 0
11 11.00 15.5 SW 40.0 43 1 0
12 12.00 13.4 SW 41.5 42 1 0
13 13.00 6.9 SW 42.0 36 0 0
14 14.00 8.5 SW 44.0 31 0 0
15 15.00 4.9 SSW 46.0 26 0 0
16 16.00 6.6 SW 44.0 30 1 0
17 17.00 5.0 SSW 42.5 31 1 0
18 18.00 4.8 NW 40.0 33 2 0
19 19.00 3.6 NW 39.0 38 2 0
20 20.00 7.1 NNW 38.0 45 2 0
21 21.00 6.5 NW 36.5 48 2 0
22 22.00 3.9 NNW 34.0 53 3 0
23 23.00 4.2 NNW 33.0 63 3 0
24 24.00 4.6 NW 32.5 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): NW
2. Wind Velocity (Kmph) : Min 3.6 Max : 15.5 Avg : 6.7
3. Ambient Temperature (°C) : Min : 29.5 Max : 46.0 Avg : 37.0
4. Relative Humidity (%) : Min : 26.0 Max : 72.0 Avg : 50.6
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 750
7. Sky Appearance : Clear
TABLE : 54 METEOROLOGICAL DATA
Date : 24.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 3.8 WNW 32.5 68 3 0
2 02.00 4.0 WSW 32.0 72 3 0
3 03.00 4.5 SW 30.0 70 3 0
4 04.00 5.3 NW 29.5 68 3 0
5 05.00 4.0 NNW 31.0 66 3 0
6 06.00 5.0 NNW 32.0 67 2 0
7 07.00 6.2 NNW 34.5 62 2 0
8 08.00 7.5 NW 36.0 53 2 0
9 09.00 8.2 NW 38.0 45 1 0
10 10.00 10.5 NW 39.0 40 1 0
11 11.00 12.6 NW 40.0 38 1 0
12 12.00 9.5 NW 41.0 36 1 0
13 13.00 8.7 NW 42.0 32 0 0
14 14.00 13.0 NW 44.5 31 0 0
15 15.00 14.5 NNW 46.5 29 0 0
16 16.00 11.3 NNW 44.0 31 1 0
17 17.00 10.5 NW 42.0 32 1 0
18 18.00 9.3 NW 40.0 36 2 0
19 19.00 4.6 WNW 39.0 38 2 0
20 20.00 3.9 WNW 38.0 40 3 0
21 21.00 4.0 NW 36.0 53 3 0
22 22.00 5.3 SSW 34.5 56 3 0
23 23.00 6.9 SW 33.0 63 3 0
24 24.00 7.4 SW 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): NW
2. Wind Velocity (Kmph) : Min 3.8 Max : 14.5 Avg : 7.5
3. Ambient Temperature (°C) : Min : 29.5 Max : 46.5 Avg : 37.0
4. Relative Humidity (%) : Min : 29.0 Max : 72.0 Avg : 49.6
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 750
7. Sky Appearance : Clear
TABLE : 55 METEOROLOGICAL DATA
Date : 25.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 8.6 WNW 32.5 68 3 0
2 02.00 10.5 NNW 32.0 72 3 0
3 03.00 9.2 NW 30.0 70 3 0
4 04.00 6.2 NNW 29.5 68 3 0
5 05.00 4.3 NW 31.0 66 3 0
6 06.00 4.2 NNE 32.0 66 3 0
7 07.00 5.0 WNW 34.5 62 2 0
8 08.00 6.3 NE 36.0 53 2 0
9 09.00 5.1 NW 38.0 45 1 0
10 10.00 4.8 ENE 39.0 40 1 0
11 11.00 3.5 WNW 40.0 38 1 0
12 12.00 4.9 NE 41.0 36 1 0
13 13.00 6.3 NE 42.0 32 0 0
14 14.00 10.5 NNW 44.5 31 0 0
15 15.00 12.3 NNW 45.0 29 0 0
16 16.00 11.5 WNW 44.0 31 1 0
17 17.00 9.3 NNW 42.0 32 1 0
18 18.00 8..7 NE 40.0 36 2 0
19 19.00 10.2 NW 39.0 38 2 0
20 20.00 6.4 NW 38.0 40 2 0
21 21.00 5.2 NNW 36.0 53 2 0
22 22.00 4.0 NW 34.5 56 3 0
23 23.00 3.5 NW 33.0 63 3 0
24 24.00 5.9 NNW 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): NW
2. Wind Velocity (Kmph) : Min 3.5 Max : 12.3 Avg : 6.9
3. Ambient Temperature (°C) : Min : 29.5 Max : 45.0 Avg : 36.9
4. Relative Humidity (%) : Min : 29.0 Max : 72.0 Avg : 49.6
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 750
7. Sky Appearance : Clear
TABLE : 56 METEOROLOGICAL DATA
Date : 26.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 4.6 WNW 32.5 61 3 0
2 02.00 3.5 NW 32.0 66 3 0
3 03.00 2.8 NW 30.0 68 3 0
4 04.00 3.5 NNW 29.5 72 3 0
5 05.00 3.4 NNW 29.0 73 3 0
6 06.00 5.2 NW 30.0 72 3 0
7 07.00 6.5 NNW 31.0 65 2 0
8 08.00 7.0 NW 32.0 61 2 0
9 09.00 8.5 SW 33.0 56 1 0
10 10.00 9.2 SW 34.5 49 1 0
11 11.00 10.5 SW 36.0 48 1 0
12 12.00 13.4 SW 38.0 45 1 0
13 13.00 15.0 SW 40.0 40 0 0
14 14.00 13.2 SW 42.5 34 0 0
15 15.00 14.5 SW 41.5 35 0 0
16 16.00 9.3 SSE 40.0 43 1 0
17 17.00 8.5 S 39.0 50 1 0
18 18.00 6.4 S 38.0 52 2 0
19 19.00 3.8 SE 37.5 54 2 0
20 20.00 4.0 SSE 36.0 56 2 0
21 21.00 4.5 SE 35.5 58 2 0
22 22.00 6.2 SSE 34.0 61 3 0
23 23.00 5.1 SE 33.0 63 3 0
24 24.00 5.5 SSW 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): SW
2. Wind Velocity (Kmph) : Min 2.8 Max : 15.0 Avg : 7.3
3. Ambient Temperature (°C) : Min 29.0 Max : 42.5 Avg : 34.9
4. Relative Humidity (%) : Min : 34.0 Max : 73.0 Avg : 56.1
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 750
7. Sky Appearance : Clear
TABLE : 57 METEOROLOGICAL DATA
Date : 27.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 4.5 WNW 32.5 65 3 0
2 02.00 4.0 NNW 32.0 66 3 0
3 03.00 3.3 WNW 30.0 68 3 0
4 04.00 2.9 WNW 29.5 72 3 0
5 05.00 2.5 WNW 29.0 73 3 0
6 06.00 4.2 W 30.0 72 2 0
7 07.00 5.0 W 31.0 65 2 0
8 08.00 6.8 WSW 32.0 61 2 0
9 09.00 7.2 WSW 33.0 56 1 0
10 10.00 6.9 W 34.5 49 1 0
11 11.00 10.2 WSW 36.0 48 1 0
12 12.00 13.5 WW 39.5 45 1 0
13 13.00 14.6 W 42.0 40 0 0
14 14.00 12.5 WSW 44.0 31 0 0
15 15.00 11.0 SW 42.5 35 0 0
16 16.00 5.9 SW 40.0 43 1 0
17 17.00 6.4 WSW 39.0 50 1 0
18 18.00 5.0 SW 38.0 52 2 0
19 19.00 4.8 SW 37.5 54 2 0
20 20.00 3.5 WSW 36.0 56 3 0
21 21.00 4.2 WSW 35.5 58 3 0
22 22.00 3.7 W 34.0 61 3 0
23 23.00 4.0 WSW 33.0 63 3 0
24 24.00 5.1 WSW 32.0 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): WSW
2. Wind Velocity (Kmph) : Min 2.5 Max : 14.6 Avg : 6.3
3. Ambient Temperature (°C) : Min 29.0 Max : 44.0 Avg : 35.1
4. Relative Humidity (%) : Min : 31.0 Max : 73.0 Avg : 56.2
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 750
7. Sky Appearance : Clear
TABLE : 58 METEOROLOGICAL DATA
Date : 28.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidit
y (%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 3.2 WNW 32.5 64 3 0
2 02.00 2.4 WSW 32.0 66 3 0
3 03.00 2.0 WSW 30.0 68 3 0
4 04.00 1.5 SW 29.5 72 3 0
5 05.00 1.2 SW 29.0 73 3 0
6 06.00 3.2 SW 30.5 72 2 0
7 07.00 1.5 SW 32.0 70 2 0
8 08.00 2.0 SW 32.5 67 2 0
9 09.00 1.8 WSW 34.0 56 1 0
10 10.00 3.9 WSW 36.0 47 1 0
11 11.00 5.0 WSW 38.5 45 1 0
12 12.00 10.2 SW 40.0 38 1 0
13 13.00 11.2 SW 40.5 34 0 0
14 14.00 13.1 SW 42.5 29 0 0
15 15.00 10.2 SW 42.0 32 0 0
16 16.00 8..5 SSW 41.0 36 1 0
17 17.00 6.2 SSW 40.0 38 1 0
18 18.00 4.9 SSW 38.0 38 2 0
19 19.00 5.2 WSW 36.0 40 2 0
20 20.00 4.5 WSW 34.5 53 3 0
21 21.00 3.0 WNW 34.0 54 3 0
22 22.00 2.5 WNW 32.5 56 3 0
23 23.00 4.5 NW 32.0 63 3 0
24 24.00 3.6 NW 30.5 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): WSW
2. Wind Velocity (Kmph) : Min : 1.2 Max : 13.1 Avg : 4.6
3. Ambient Temperature (°C) : Min : 29.0 Max : 42.5 Avg : 35.0
4. Relative Humidity (%) : Min : 29.0 Max : 73.0 Avg : 53.2
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 750
7. Sky Appearance : Clear
TABLE : 59 METEOROLOGICAL DATA
Date : 29.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 2.4 WNW 32.5 62 3 0
2 02.00 2.1 NNW 32.0 66 3 0
3 03.00 3.1 N 30.0 68 3 0
4 04.00 3.8 NNW 29.5 72 3 0
5 05.00 4.2 N 29.0 73 3 0
6 06.00 2.8 NNW 30.5 72 3 0
7 07.00 3.6 NNW 32.0 70 2 0
8 08.00 4.0 N 32.5 67 2 0
9 09.00 5.7 NNW 34.0 56 1 0
10 10.00 6.9 NNW 36.0 47 1 0
11 11.00 7.0 N 38.5 45 1 0
12 12.00 11.0 N 40.0 38 1 0
13 13.00 13.0 NNW 41.0 30 0 0
14 14.00 7.6 NW 43.0 28 0 0
15 15.00 5.9 NW 42.0 32 0 0
16 16.00 4.8 NNW 41.0 36 1 0
17 17.00 3.8 NW 40.0 38 1 0
18 18.00 4.0 NW 38.0 38 2 0
19 19.00 3.6 NNW 36.0 40 2 0
20 20.00 2.9 NNW 34.5 53 2 0
21 21.00 5.5 NNW 34.0 54 2 0
22 22.00 3.4 NW 32.5 56 3 0
23 23.00 4.4 NNW 32.0 63 3 0
24 24.00 4.5 NW 30.5 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): NNW
2. Wind Velocity (Kmph) : Min 2.1 Max : 13.0 Avg : 5.0
3. Ambient Temperature (°C) : Min 29.0 Max : 43.0 Avg : 35.0
4. Relative Humidity (%) : Min : 28.0 Max : 73.0 Avg : 52.9
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 750
7. Sky Appearance : Clear
TABLE : 60 METEOROLOGICAL DATA
Date : 30.05.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 6.0 WNW 32.5 63 3 0
2 02.00 7.1 NW 32.0 66 3 0
3 03.00 5.0 NNW 30.0 68 3 0
4 04.00 4.0 NW 29.5 72 3 0
5 05.00 3.0 NW 29.0 73 3 0
6 06.00 7.3 NW 30.5 72 3 0
7 07.00 11.4 NW 32.0 70 2 0
8 08.00 12.0 NW 32.5 67 2 0
9 09.00 10.6 NW 34.0 56 1 0
10 10.00 11.7 NNW 36.0 47 1 0
11 11.00 10.9 SW 38.5 45 1 0
12 12.00 8.1 SW 40.0 38 1 0
13 13.00 7.4 SW 42.0 29 1 0
14 14.00 4.5 SW 43.5 27 0 0
15 15.00 6.7 SSW 42.0 32 1 0
16 16.00 5.4 SW 41.0 36 2 0
17 17.00 4.3 SW 40.0 38 3 0
18 18.00 3.8 WSW 38.0 38 3 0
19 19.00 6.9 SW 35.0 58 3 0
20 20.00 6.4 NW 34.0 69 3 0
21 21.00 9.2 NW 32.0 54 3 0
22 22.00 3.6 NW 31.0 61 3 0
23 23.00 8.6 NNW 31.0 63 3 0
24 24.00 4.5 NW 30.5 65 3 0
OBSERVATIONS
1. Predominant WindDirection (from): NW
2. Wind Velocity (Kmph) : Min 3.0 Max : 12.0 Avg : 7.0
3. Ambient Temperature (°C) : Min 29.0 Max : 43.5 Avg : 34.9
4. Relative Humidity (%) : Min : 27.0 Max : 73.0 Avg : 54.5
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 750
7. Sky Appearance : Cloudy
TABLE : 61 METEOROLOGICAL DATA
Date : 31.05.12
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 1.9 WNW 32.5 65 3 0
2 02.00 2.9 WNW 32.0 66 3 0
3 03.00 4.0 NW 30.0 68 3 0
4 04.00 4.5 NW 29.5 72 3 0
5 05.00 3.8 NW 29.0 73 3 0
6 06.00 3.6 NNW 30.0 72 3 0
7 07.00 4.4 SW 31.0 65 2 0
8 08.00 6.1 SW 32.0 61 2 0
9 09.00 9.4 SW 33.0 56 1 0
10 10.00 7.9 NW 34.5 49 1 0
11 11.00 11.7 NW 36.0 48 1 0
12 12.00 10.9 NNW 39.5 45 1 0
13 13.00 15.7 NW 42.0 40 0 0
14 14.00 8.5 WNW 44.5 31 1 0
15 15.00 4.8 NW 43.0 35 2 0
16 16.00 5.3 NW 41.5 43 2 0
17 17.00 3.0 N 39.0 50 2 0
18 18.00 9.6 N 36.0 52 2 0
19 19.00 11.8 SW 33.5 54 3 0
20 20.00 13.5 SW 32.0 56 3 0
21 21.00 4.3 SSW 31.0 58 3 0
22 22.00 8.7 SW 31.0 60 3 0
23 23.00 4.0 SW 31.0 64 3 0
24 24.00 3.4 WSW 30.5 66 3 0
OBSERVATIONS
1. Predominant WindDirection (from): NW 2. Wind Velocity (Kmph) : Min 1.9 Max : 15.7 Avg : 6.8
3. Ambient Temperature (°C) : Min 29.0 Max : 44.5 Avg : 34.3
4. Relative Humidity (%) : Min : 31.0 Max : 73.0 Avg : 56.2
5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 751 7. Sky Appearance : Cloudy
TABLE : 62 METEOROLOGICAL DATA
Date : 01.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 2.6 NW 29.5 62 3 0
2 02.00 5.9 NNW 29.5 65 3 0
3 03.00 4.3 NW 30.0 68 3 0
4 04.00 8.3 NW 30.5 74 3 0
5 05.00 6.9 NW 31.0 74 3 0
6 06.00 3.0 NNW 31.5 72 3 0
7 07.00 3.7 WNW 32.5 67 3 0
8 08.00 4.8 NW 34.0 67 2 0
9 09.00 7.9 NW 38.0 56 2 0
10 10.00 10.3 WNW 38.5 47 2 0
11 11.00 11.2 NW 40.0 45 2 0
12 12.00 12.6 NW 40.5 38 2 0
13 13.00 14.5 NW 42.0 34 1 0
14 14.00 12.0 NNW 42.5 32 1 0
15 15.00 9.6 NNW 42.0 32 1 0
16 16.00 8.3 NW 40.5 36 1 0
17 17.00 7.9 NNW 40.0 38 1 0
18 18.00 6.3 NW 38.5 42 2 0
19 19.00 5.0 NNW 38.0 45 2 0
20 20.00 4.5 NW 36.5 50 2 0
21 21.00 2.3 NNW 36.0 53 2 0
22 22.00 8.7 NW 34.5 55 2 0
23 23.00 7.0 NW 34.0 56 3 0
24 24.00 4.3 NW 32.5 59 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.3 Max : 14.5 Avg : 7.2
3. Ambient Temperature (°C) Min : 29.5 Max : 42.5 Avg : 35.9
4. Relative Humidity (%) Min : 32.0 Max : 74.0 Avg : 52.8
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 748
7. Sky Appearance : Clear
TABLE : 63 METEOROLOGICAL DATA
Date : 02.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 5.5 NW 32.5 61 3 0
2 02.00 6.0 N 32.0 64 3 0
3 03.00 4.2 NNE 30.0 68 3 0
4 04.00 3.8 NNW 29.0 74 3 0
5 05.00 6.9 NNW 29.0 74 3 0
6 06.00 7.4 NW 30.5 72 3 0
7 07.00 11.4 NNW 32.0 70 2 0
8 08.00 14.0 NNW 32.5 67 1 0
9 09.00 15.7 NW 34.0 56 1 0
10 10.00 13.0 NNW 38.0 47 1 0
11 11.00 14.3 NNW 38.5 45 1 0
12 12.00 14.4 NNW 40.0 38 1 0
13 13.00 16.7 NW 40.5 34 0 0
14 14.00 9.3 NNW 42.0 32 0 0
15 15.00 8.6 NNE 42.5 32 0 0
16 16.00 7..0 NNE 40.0 34 0 0
17 17.00 6.7 NE 38.5 40 1 0
18 18.00 5.4 NE 38.0 45 1 0
19 19.00 9.1 N 36.5 48 1 0
20 20.00 9.6 N 36.0 53 2 0
21 21.00 10.9 NW 34.5 54 2 0
22 22.00 17.6 WNW 34.0 56 2 0
23 23.00 11.9 WNW 32.5 58 2 0
24 24.00 14.7 NW 32.0 61 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NNW 2. Wind Velocity (Kmph) Min : 3.8 Max : 17.6 Avg : 10.3
3. Ambient Temperature (°C) Min : 29.0 Max : 42.5 Avg : 35.2
4. Relative Humidity (%) Min : 32.0 Max : 74.0 Avg : 53.5
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 748
7. Sky Appearance : Clear
TABLE : 64 METEOROLOGICAL DATA
Date : 03.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 6.3 NW 30.5 62 3 0
2 02.00 2.7 NW 30.0 65 3 0
3 03.00 4.0 NW 29.5 68 3 0
4 04.00 5.4 N 29.0 74 3 0
5 05.00 6.9 NW 29.0 74 3 0
6 06.00 5.4 NW 32.5 67 3 0
7 07.00 6.0 NNW 34.0 59 2 0
8 08.00 5.1 NW 36.5 50 1 0
9 09.00 8.2 NW 38.0 45 1 0
10 10.00 12.6 NNW 38.5 45 1 0
11 11.00 10.4 NW 40.0 42 1 0
12 12.00 9.8 NW 42.0 40 1 0
13 13.00 15.3 NW 42.5 36 0 0
14 14.00 12.6 N 44.0 31 0 0
15 15.00 6.1 NNW 44.5 31 0 0
16 16.00 18.0 NNW 44.0 31 0 0
17 17.00 15.7 NNW 42.5 32 1 0
18 18.00 11.4 NW 40.0 34 1 0
19 19.00 7.0 NW 38.5 40 2 0
20 20.00 4.0 WNW 36.5 43 4 0
21 21.00 3.0 NNW 34.5 68 6 1.2
22 22.00 8.0 NW 34.0 56 5 0
23 23.00 6.7 NW 32.0 58 4 0
24 24.00 9.1 NW 28.5 60 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.7 Max : 18.0 Avg : 8.3
3. Ambient Temperature (°C) Min : 28.5 Max : 44.5 Avg : 36.3
4. Relative Humidity (%) Min : 31.0 Max : 74.0 Avg : 50.5
5. Rainfall (mm) : 1.2
6. Atm. Pressure (mm of Hg) : 745
7. Sky Appearance : Rainy
TABLE : 65 METEOROLOGICAL DATA
Date : 04.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 2.6 NW 28.0 64 3 0
2 02.00 3.2 WNW 27.0 66 3 0
3 03.00 4.2 N 27.0 66 3 0
4 04.00 5.3 WNW 25.0 68 3 0
5 05.00 6.9 WNW 25.0 68 3 0
6 06.00 8.4 NNW 27.5 75 3 0
7 07.00 3.6 NW 28.0 66 2 0
8 08.00 5.3 WNW 30.0 59 1 0
9 09.00 7.6 NW 30.5 47 1 0
10 10.00 9.6 NNW 32.5 44 1 0
11 11.00 12.9 NNW 34.5 41 1 0
12 12.00 8.1 WNW 36.5 38 1 0
13 13.00 14.5 WNW 38.5 36 0 0
14 14.00 10.4 NW 40.0 34 0 0
15 15.00 8.5 NNW 42.0 32 0 0
16 16.00 7.0 NW 40.0 34 0 0
17 17.00 6.7 NNW 38.5 36 1 0
18 18.00 7.2 NNW 38.0 45 1 0
19 19.00 5.5 WNW 36.5 50 2 0
20 20.00 4.1 WNW 36.0 53 2 0
21 21.00 7.4 NNW 34.5 54 2 0
22 22.00 8.7 NNW 34.0 56 2 0
23 23.00 4.3 N 32.5 64 3 0
24 24.00 6.1 N 32.0 67 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NNW 2. Wind Velocity (Kmph) Min : 2.6 Max : 14.5 Avg : 7.0
3. Ambient Temperature (°C) Min : 25.0 Max : 42.0 Avg : 33.1
4. Relative Humidity (%) Min : 32.0 Max : 75.0 Avg : 52.6
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 745
7. Sky Appearance : Clear
TABLE : 66 METEOROLOGICAL DATA
Date : 05.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 6.3 NW 30.5 68 3 0
2 02.00 2.7 NW 30.0 72 3 0
3 03.00 4.0 NNW 28.0 77 3 0
4 04.00 5.4 NNW 27.0 77 3 0
5 05.00 6.9 NW 27.0 77 3 0
6 06.00 7.1 WNW 28.0 77 3 0
7 07.00 10.7 NW 32.5 61 2 0
8 08.00 12.0 NNW 34.5 56 1 0
9 09.00 9.9 NW 36.5 53 1 0
10 10.00 13.1 NW 38.5 45 1 0
11 11.00 14.9 NW 40.0 42 1 0
12 12.00 16.4 NW 42.0 40 1 0
13 13.00 11.0 WSW 42.0 40 0 0
14 14.00 18.3 SW 44.0 31 0 0
15 15.00 17.1 SSW 44.5 31 0 0
16 16.00 10.4 SE 42.0 36 0 0
17 17.00 8.0 SSE 40.5 38 1 0
18 18.00 8.6 SE 40.0 42 1 0
19 19.00 7.4 SW 38.5 45 1 0
20 20.00 8.8 SW 38.0 50 2 0
21 21.00 6.3 WSW 36.5 53 2 0
22 22.00 5.4 WSW 36.0 55 2 0
23 23.00 5.7 SSW 34.5 56 2 0
24 24.00 9.6 SW 34.0 59 2 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.7 Max : 18.3 Avg : 9.4
3. Ambient Temperature (°C) Min : 27.0 Max : 44.5 Avg : 36.0
4. Relative Humidity (%) Min : 31.0 Max : 77.0 Avg : 53.4
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 745
7. Sky Appearance : Clear
TABLE : 67 METEOROLOGICAL DATA
Date : 06.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 2.3 NW 32.5 61 3 0
2 02.00 2.6 NNE 30.5 65 3 0
3 03.00 3.5 NNW 28.5 70 3 0
4 04.00 4.6 NE 26.0 76 3 0
5 05.00 6.9 NNE 26.0 76 5 2.0
6 06.00 1.8 NW 27.5 84 3 2.0
7 07.00 4.8 NW 28.0 74 2 0
8 08.00 6.9 NW 30.5 65 2 0
9 09.00 6.1 NW 32.5 64 2 0
10 10.00 10.4 NW 37.5 59 2 0
11 11.00 16.0 NNE 36.0 53 2 0
12 12.00 15.0 NW 36.5 53 2 0
13 13.00 9.6 NE 38.0 50 2 0
14 14.00 6.6 NW 38.5 50 2 0
15 15.00 8.0 N 40.0 47 2 0
16 16.00 7.4 NNE 39.5 50 2 0
17 17.00 6.7 N 38.0 51 2 0
18 18.00 7.6 NW 38.0 51 2 0
19 19.00 5.5 NNW 37.0 52 2 0
20 20.00 8.8 NNW 36.5 58 3 0
21 21.00 6.0 WNW 34.0 59 3 0
22 22.00 4.7 WNW 33.0 63 3 0
23 23.00 2.9 NW 30.0 68 3 0
24 24.00 4.4 NNW 29.0 71 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.8 Max : 16.0 Avg : 6.6
3. Ambient Temperature (°C) Min : 26.0 Max : 40.0 Avg : 33.5
4. Relative Humidity (%) Min : 47.0 Max : 84.0 Avg : 61.3
5. Rainfall (mm) : 4.0
6. Atm. Pressure (mm of Hg) : 745
7. Sky Appearance : Rainy
TABLE : 68 METEOROLOGICAL DATA
Date : 07.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 2.3 NW 29.0 71 3 0
2 02.00 2.6 SW 28.5 74 3 0
3 03.00 2.4 SW 27.0 77 3 0
4 04.00 3.5 SSW 27.0 77 3 0
5 05.00 6.9 SSW 27.0 77 3 0
6 06.00 4.0 NW 30.0 72 3 0
7 07.00 6.1 NW 30.5 65 2 0
8 08.00 11.6 NW 32.0 61 1 0
9 09.00 8.6 NW 34.0 56 1 0
10 10.00 12.0 SW 36.0 58 1 0
11 11.00 14.2 SW 36.5 45 1 0
12 12.00 4.9 SSW 38.0 45 1 0
13 13.00 12.7 SSW 38.5 40 0 0
14 14.00 11.2 SW 40.0 34 0 0
15 15.00 9.0 SSW 42.5 25 0 0
16 16.00 12.1 SW 40.0 34 0 0
17 17.00 2.5 SW 38.5 36 1 0
18 18.00 3.3 SW 38.0 40 1 0
19 19.00 9.0 SSW 36.5 45 1 0
20 20.00 4.7 NW 36.0 45 2 0
21 21.00 9.4 NNW 34.5 54 2 0
22 22.00 7.6 SW 34.0 56 2 0
23 23.00 13.7 SW 32.5 64 2 0
24 24.00 16.5 SW 32.0 67 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : SW 2. Wind Velocity (Kmph) Min : 2.3 Max : 16.5 Avg : 8.0
3. Ambient Temperature (°C) Min : 27.0 Max : 42.5 Avg : 34.1
4. Relative Humidity (%) Min : 25.0 Max : 77.0 Avg : 54.9
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 748
7. Sky Appearance : Clear
TABLE : 69 METEOROLOGICAL DATA
Date : 08.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 3.5 NW 30.5 68 3 0
2 02.00 5.1 WNW 30.0 72 3 0
3 03.00 4.6 NW 29.5 74 3 0
4 04.00 3.2 NNW 29.0 78 3 0
5 05.00 6.9 NNW 29.0 78 3 0
6 06.00 4.2 NW 30.0 65 3 0
7 07.00 4.6 NW 32.5 61 2 0
8 08.00 7.2 NW 34.0 56 3 0
9 09.00 8.5 NNW 36.5 53 3 0
10 10.00 9.2 NNW 38.5 45 2 0
11 11.00 10.5 NNW 40.0 42 2 0
12 12.00 8.0 ENE 42.0 40 2 0
13 13.00 10.2 ENE 42.5 36 3 0
14 14.00 14.0 ENE 44.0 27 3 0
15 15.00 12.4 NE 44.0 27 3 0
16 16.00 6.7 NW 42.0 36 3 0
17 17.00 8.1 WNW 40.5 38 4 0
18 18.00 5.3 NW 40.0 42 5 0
19 19.00 4.8 NW 38.5 45 5 0
20 20.00 3.4 NW 38.0 50 5 0
21 21.00 2.8 WNW 36.5 53 4 0
22 22.00 3.0 NW 36.0 55 3 0
23 23.00 3.4 WNW 34.5 56 3 0
24 24.00 4.2 WNW 32.5 59 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.8 Max : 14.0 Avg : 6.4
3. Ambient Temperature (°C) Min : 29.0 Max : 44.0 Avg : 36.3
4. Relative Humidity (%) Min : 27.0 Max : 78.0 Avg : 52.3
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 748
7. Sky Appearance : Clear
TABLE : 70 METEOROLOGICAL DATA
Date : 09.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 4.1 NW 29.0 66 3 0
2 02.00 3.0 NW 28.5 79 3 0
3 03.00 2.8 NW 26.0 84 3 0
4 04.00 3.1 NNW 26.0 84 3 0
5 05.00 2.6 NW 26.0 84 3 0
6 06.00 5.6 NW 27.0 70 3 0
7 07.00 6.3 NW 28.5 67 2 0
8 08.00 9.7 NW 29.0 64 1 0
9 09.00 16.0 NNW 30.5 62 1 0
10 10.00 14.3 NNW 32.0 58 1 0
11 11.00 9.3 NW 34.5 54 1 0
12 12.00 7.6 NW 36.5 52 1 0
13 13.00 19.0 NW 38.5 45 1 0
14 14.00 12.0 NW 40.5 38 1 0
15 15.00 8.4 WNW 42.5 36 1 0
16 16.00 5.6 WNW 40.5 62 6 1.0
17 17.00 4.0 WNW 38.5 64 5 0
18 18.00 4.4 NE 34.5 70 6 1.0
19 19.00 6.2 NE 34.0 58 5 0
20 20.00 12.6 NNE 32.5 60 4 0
21 21.00 19.0 NNE 30.5 60 4 0
22 22.00 8.9 NNE 30.0 60 4 0
23 23.00 6.8 NE 29.5 64 4 0
24 24.00 5.9 NE 28.5 67 4 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.6 Max : 19.0 Avg : 8.2
3. Ambient Temperature (°C) Min : 26.0 Max : 42.5 Avg : 32.2
4. Relative Humidity (%) Min : 36.0 Max : 84.0 Avg : 62.8
5. Rainfall (mm) : 2.0
6. Atm. Pressure (mm of Hg) : 748
7. Sky Appearance : Rainy
TABLE : 71 METEOROLOGICAL DATA
Date : 10.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 6.3 WNW 28.5 67 4 0
2 02.00 2.7 WNW 28.0 70 4 0
3 03.00 4.0 WNW 27.0 73 4 0
4 04.00 5.4 NW 25.0 80 4 0
5 05.00 6.9 WNW 25.0 80 4 0
6 06.00 7.1 NW 25.0 80 4 0
7 07.00 10.7 NW 27.5 73 3 0
8 08.00 12.0 WNW 28.0 64 2 0
9 09.00 9.9 WNW 29.0 51 2 0
10 10.00 13.1 W 32.5 49 1 0
11 11.00 14.9 W 34.0 46 1 0
12 12.00 16.4 WSW 34.5 42 1 0
13 13.00 11.0 WSW 36.0 39 1 0
14 14.00 18.3 W 36.5 38 1 0
15 15.00 17.1 WSW 38.0 36 2 0
16 16.00 10.4 W 38.5 34 2 0
17 17.00 8.0 WNW 36.0 46 3 0
18 18.00 8.6 WNW 33.5 38 3 0
19 19.00 7.4 NW 29.5 41 3 1.0
20 20.00 8.8 NW 29.0 43 4 2.0
21 21.00 6.3 WNW 29.0 44 5 2.0
22 22.00 5.4 WNW 28.5 47 5 0
23 23.00 5.7 W 28.5 50 5 0
24 24.00 9.6 WSW 28.0 52 4 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.7 Max : 18.3 Avg : 9.4
3. Ambient Temperature (°C) Min : 25.0 Max : 38.5 Avg : 30.6
4. Relative Humidity (%) Min : 34.0 Max : 80.0 Avg : 53.5
5. Rainfall (mm) : 5.0
6. Atm. Pressure (mm of Hg) : 745
7. Sky Appearance : Rainy
TABLE : 72 METEOROLOGICAL DATA
Date : 11.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 8.6 WNW 27.5 57 3 0
2 02.00 10.5 NW 27.0 70 3 0
3 03.00 9.2 NNW 26.5 84 3 0
4 04.00 6.2 NNW 26.5 84 3 0
5 05.00 4.3 NW 26.5 84 3 0
6 06.00 4.2 NW 27.0 81 3 0
7 07.00 5.0 NW 27.5 80 2 0
8 08.00 6.3 NW 28.0 79 2 0
9 09.00 5.1 NE 28.0 79 1 0
10 10.00 4.8 NE 28.5 78 1 0
11 11.00 3.5 NE 29.0 78 2 0
12 12.00 4.9 SE 29.5 77 2 0
13 13.00 6.3 SE 28.5 88 4 9.0
14 14.00 10.5 SE 27.5 98 4 11.0
15 15.00 12.3 NNW 29.5 100 3 2.0
16 16.00 11.5 NNW 28.0 84 3 0
17 17.00 9.3 NW 28.0 84 3 0
18 18.00 8..7 NW 27.5 88 3 0
19 19.00 10.2 NW 27.5 78 3 0
20 20.00 6.4 WNW 27.0 78 3 0
21 21.00 5.2 WNW 27.0 80 3 0
22 22.00 4.0 NW 26.5 82 3 0
23 23.00 3.5 NW 26.5 100 3 2.5
24 24.00 5.9 NW 26.0 100 4 5.5
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 3.5 Max : 12.3 Avg : 6.9
3. Ambient Temperature (°C) Min : 26.0 Max : 29.5 Avg : 27.5
4. Relative Humidity (%) Min : 57.0 Max : 100.0 Avg : 83.0
5. Rainfall (mm) : 30.0
6. Atm. Pressure (mm of Hg) : 748
7. Sky Appearance : Rainy
TABLE : 73 METEOROLOGICAL DATA
Date : 12.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 13.0 WNW 26.0 86 4 0
2 02.00 10.6 NW 25.5 86 5 0
3 03.00 9.1 N 25.5 94 5 1.5
4 04.00 9.3 WNW 24.5 100 5 0.5
5 05.00 8.6 NW 24.5 87 5 0
6 06.00 4.7 NW 25.0 84 4 0
7 07.00 4.9 ENE 25.0 83 4 0
8 08.00 6.2 NE 25.5 82 4 0
9 09.00 9.6 NE 25.5 81 3 0
10 10.00 5.9 WNW 25.0 80 4 0
11 11.00 11.5 NW 25.0 94 5 1.0
12 12.00 12.6 NNW 25.5 98 5 2.5
13 13.00 14.0 NW 26.0 77 4 0
14 14.00 13.5 ENE 26.0 76 4 0
15 15.00 10.7 SSE 26.5 75 4 0
16 16.00 9.8 NE 26.5 77 4 0
17 17.00 7.6 NNW 26.0 78 4 0
18 18.00 5.3 NW 26.0 79 4 0
19 19.00 4.4 NW 25.5 80 4 0
20 20.00 4.2 NE 25.5 82 4 0
21 21.00 4.0 NE 25.5 89 5 2.0
22 22.00 5.5 NW 25.5 96 5 1.5
23 23.00 6.9 ENE 25.5 100 5 2.0
24 24.00 7.4 NE 24.5 88 5 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 4.0 Max : 14.0 Avg : 8.3
3. Ambient Temperature (°C) Min : 24.5 Max : 26.5 Avg : 25.5
4. Relative Humidity (%) Min : 75.0 Max : 100.0 Avg : 85.5
5. Rainfall (mm) : 11.0
6. Atm. Pressure (mm of Hg) : 745
7. Sky Appearance : Rainy
TABLE : 74 METEOROLOGICAL DATA
Date : 13.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 5.9 WNW 24.5 94 5 2.0
2 02.00 7.8 WNW 24.0 98 5 2.0
3 03.00 4.5 N 24.5 98 5 1.5
4 04.00 3.6 WNW 23.5 98 5 2.5
5 05.00 2.0 WNW 23.0 98 5 3.5
6 06.00 2.3 NNW 23.5 98 5 2.5
7 07.00 6.4 NW 23.0 98 5 3.5
8 08.00 9.7 WNW 23.5 100 5 1.5
9 09.00 16.6 NW 24.0 90 4 0
10 10.00 14.3 NNW 24.5 87 4 0
11 11.00 9.3 NNW 24.5 87 4 0
12 12.00 7.6 WNW 25.0 85 3 0
13 13.00 6.0 WNW 25.5 85 2 0
14 14.00 5.3 NW 26.0 86 2 0
15 15.00 5.7 NNW 25.5 85 4 0
16 16.00 4.3 NW 24.5 94 5 3.5
17 17.00 7.0 NNW 24.0 98 5 2.0
18 18.00 7.4 NNW 23.5 98 5 1.5
19 19.00 8.3 WNW 23.5 89 4 0
20 20.00 5.1 WNW 24.0 90 3 0
21 21.00 5.7 NNW 24.0 90 3 0
22 22.00 3.8 NNW 24.0 91 3 0
23 23.00 2.1 N 23.5 91 4 0
24 24.00 1.7 N 23.5 92 4 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.7 Max : 16.6 Avg : 6.4
3. Ambient Temperature (°C) Min : 23.0 Max : 26.0 Avg : 24.1
4. Relative Humidity (%) Min : 85.0 Max : 100.0 Avg : 92.5
5. Rainfall (mm) : 26.0
6. Atm. Pressure (mm of Hg) : 745
7. Sky Appearance : Rainy
TABLE : 75 METEOROLOGICAL DATA
Date : 14.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 5.7 WNW 23.0 98 4 1.0
2 02.00 6.0 WNW 23.0 99 5 2.5
3 03.00 5.4 WNW 22.5 98 5 3.5
4 04.00 4.2 W 23.5 99 4 1.5
5 05.00 3.6 WNW 23.5 94 4 0
6 06.00 4.8 WNW 25.0 98 5 3.5
7 07.00 9.6 W 25.5 100 5 4.5
8 08.00 13.6 WNW 26.0 98 5 2.5
9 09.00 15.6 NW 26.0 90 4 0
10 10.00 16.3 NW 27.0 75 4 0
11 11.00 17.0 NNW 28.0 74 4 0
12 12.00 15.2 NNW 29.0 94 5 2.0
13 13.00 14.4 NW 30.0 98 3 1.0
14 14.00 14.0 WNW 30.5 61 3 0
15 15.00 11.7 WNW 31.5 59 3 0
16 16.00 8.5 WNW 31.0 60 2 0
17 17.00 11.4 W 28.0 64 3 0
18 18.00 12.4 W 27.0 67 3 0
19 19.00 10.0 WNW 26.5 69 4 0
20 20.00 7.4 WNW 26.0 69 4 0
21 21.00 6.6 NW 25.5 72 4 0
22 22.00 4.3 NNW 25.5 77 4 0
23 23.00 5.4 NNW 25.0 82 4 0
24 24.00 6.1 NW 25.0 84 4 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 3.6 Max : 17.0 Avg : 9.6
3. Ambient Temperature (°C) Min : 22.5 Max : 31.5 Avg : 26.4
4. Relative Humidity (%) Min : 59.0 Max : 100.0 Avg : 82.5
5. Rainfall (mm) : 22.0
6. Atm. Pressure (mm of Hg) : 745
7. Sky Appearance : Clear
TABLE : 76 METEOROLOGICAL DATA
Date : 15.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 5.5 WNW 24.5 98 5 2.5
2 02.00 4.2 NW 24.5 98 5 1.5
3 03.00 8.3 NW 24.0 94 5 3.5
4 04.00 6.2 NNW 24.0 98 5 3.0
5 05.00 4.3 NNW 24.0 100 5 2.5
6 06.00 5.3 NW 24.5 92 5 0
7 07.00 7.2 NW 24.5 90 5 0
8 08.00 6.1 SW 25.0 89 4 0
9 09.00 9.4 SW 25.5 85 4 0
10 10.00 8.5 SW 25.5 86 4 0
11 11.00 10.6 SW 26.0 84 4 0
12 12.00 11.7 SW 26.0 83 3 0
13 13.00 12.9 SW 26.5 70 3 0
14 14.00 13.8 SW 27.0 74 3 0
15 15.00 11.6 SSW 27.5 88 4 1.5
16 16.00 10.1 SW 27.0 75 3 0
17 17.00 9.8 SSW 26.5 77 4 0
18 18.00 10.3 NW 25.5 80 4 0
19 19.00 8.4 NW 25.0 84 3 0
20 20.00 7.6 NNW 24.5 85 3 0
21 21.00 6.3 NW 24.0 87 3 0
22 22.00 5.2 NNW 23.5 88 4 0
23 23.00 4.5 NNW 23.0 98 5 1.0
24 24.00 4.0 NW 23.0 98 5 1.0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 4.0 Max : 13.8 Avg : 8.0
3. Ambient Temperature (°C) Min : 23.0 Max : 27.5 Avg : 25.0
4. Relative Humidity (%) Min : 70.0 Max : 100.0 Avg : 87.5
5. Rainfall (mm) : 16.5
6. Atm. Pressure (mm of Hg) : 745
7. Sky Appearance : Cloudy
TABLE : 77 METEOROLOGICAL DATA
Date : 16.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 2.3 NW 22.5 93 5 0
2 02.00 2.6 NW 22.5 94 5 0
3 03.00 3.5 NW 23.5 95 5 0
4 04.00 4.6 N 23.0 95 5 1.5
5 05.00 6.9 NW 22.0 95 5 1.0
6 06.00 1.8 NW 23.5 92 5 0
7 07.00 4.8 NNW 24.0 90 5 0
8 08.00 6.9 NW 24.5 85 5 0
9 09.00 6.1 NW 25.0 84 5 0
10 10.00 10.4 NNW 25.5 84 4 0
11 11.00 16.0 NW 26.0 85 3 0
12 12.00 15.0 NW 27.0 82 3 0
13 13.00 9.6 NW 28.5 76 2 0
14 14.00 6.6 N 30.0 75 2 0
15 15.00 8.0 NNW 31.0 71 2 0
16 16.00 7.4 NNW 29.5 72 2 0
17 17.00 6.7 NNW 29.5 73 2 0
18 18.00 7.6 NW 29.0 73 2 0
19 19.00 5.5 NW 28.0 75 2 0
20 20.00 8.8 WNW 26.5 75 3 0
21 21.00 6.0 NNW 26.0 76 3 0
22 22.00 4.7 NW 26.0 76 3 0
23 23.00 2.9 NW 27.0 77 3 0
24 24.00 4.4 NW 27.5 78 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.8 Max : 16.0 Avg : 6.6
3. Ambient Temperature (°C) Min : 22.0 Max : 31.0 Avg : 26.1
4. Relative Humidity (%) Min : 71.0 Max : 95.0 Avg : 82.1
5. Rainfall (mm) : 2.5
6. Atm. Pressure (mm of Hg) : 748
7. Sky Appearance : Rainy
TABLE : 78 METEOROLOGICAL DATA
Date : 17.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 1.5 WSW 28.0 75 3 0
2 02.00 1.9 SW 27.5 76 3 0
3 03.00 2.3 WSW 27.5 78 3 0
4 04.00 2.6 WNW 27.0 77 2 0
5 05.00 3.0 WNW 27.0 76 2 0
6 06.00 2.9 NNW 27.0 73 2 0
7 07.00 4.2 NNW 28.0 72 2 0
8 08.00 5.6 NNW 28.5 70 2 0
9 09.00 3.1 NW 29.5 68 1 0
10 10.00 4.8 WNW 30.0 66 1 0
11 11.00 3.2 SW 31.5 65 1 0
12 12.00 5.3 SW 32.5 60 0 0
13 13.00 4.2 SSW 33.5 59 0 0
14 14.00 5.6 NW 35.0 55 1 0
15 15.00 6.8 NNW 36.5 48 1 0
16 16.00 7.9 NNW 35.0 52 2 0
17 17.00 12.3 NW 34.5 55 2 0
18 18.00 13.6 NW 33.5 68 5 1.0
19 19.00 14.2 NW 32.0 88 5 2.0
20 20.00 15.3 NNW 30.0 90 5 2.0
21 21.00 8.3 NNW 29.5 88 4 0
22 22.00 5.9 NW 29.0 84 3 0
23 23.00 2.0 NW 28.5 84 3 0
24 24.00 3.2 NW 28.0 85 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.5 Max : 15.3 Avg : 5.8
3. Ambient Temperature (°C) Min : 27.0 Max : 36.5 Avg : 30.4
4. Relative Humidity (%) Min : 48.0 Max : 90.0 Avg : 71.3
5. Rainfall (mm) : 5.0
6. Atm. Pressure (mm of Hg) : 748
7. Sky Appearance : Clear
TABLE : 79 METEOROLOGICAL DATA
Date : 18.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 2.5 WNW 28.0 85 3 0 2 02.00 3.1 WNW 25.5 82 3 0 3 03.00 2.8 NW 26.0 79 3 0
4 04.00 3.1 NW 25.5 77 2 0
5 05.00 2.7 NW 25.5 78 2 0
6 06.00 2.3 NNW 26.0 76 2 0
7 07.00 3.4 SW 26.5 74 2 0 8 08.00 2.4 SW 27.5 75 2 0 9 09.00 1.9 SW 29.0 73 1 0
10 10.00 6.7 NW 28.0 68 1 0
11 11.00 5.9 NW 27.5 71 1 0
12 12.00 8.9 NNW 27.5 71 0 0 13 13.00 10.5 NW 29.0 66 0 0 14 14.00 8.2 WNW 30.5 55 1 0 15 15.00 6.5 NW 31.5 48 1 0
16 16.00 6.4 NW 30.5 50 2 0
17 17.00 4.9 N 29.5 53 2 0
18 18.00 3.7 N 28.5 55 3 0 19 19.00 7.8 SW 28.0 58 3 0 20 20.00 8.1 SW 27.5 62 3 0 21 21.00 1.9 SSW 27.0 65 3 0
22 22.00 2.4 SW 27.0 68 3 0
23 23.00 3.5 SW 26.5 69 3 0
24 24.00 2.9 WSW 26.0 74 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.9 Max : 10.5 Avg : 4.7
3. Ambient Temperature (°C) Min : 25.5 Max : 31.5 Avg : 27.7
4. Relative Humidity (%) Min : 48.0 Max : 85.0 Avg : 68.0
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 750
7. Sky Appearance : Drizzling
TABLE : 80 METEOROLOGICAL DATA
Date : 19.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 1.6 WSW 26.0 84 3 0
2 02.00 4.2 SW 26.0 79 3 0
3 03.00 3.6 WSW 25.5 75 3 0
4 04.00 4.5 WNW 25.5 77 2 0
5 05.00 6.9 NW 25.5 76 2 0
6 06.00 2.8 WNW 25.0 80 2 0
7 07.00 4.2 NNW 26.0 79 2 0
8 08.00 5.0 NW 27.0 76 2 0
9 09.00 5.6 NW 28.5 74 1 0
10 10.00 6.2 WNW 29.0 73 1 0
11 11.00 8.5 NW 30.0 71 1 0
12 12.00 6.7 WNW 31.5 69 0 0
13 13.00 7.6 NW 33.0 67 0 0
14 14.00 10.2 NW 34.0 60 1 0
15 15.00 12.5 NNW 34.0 56 1 0
16 16.00 15.4 NNW 33.5 54 2 0
17 17.00 11.5 NNW 33.0 53 2 0
18 18.00 8.6 NW 32.5 55 3 0
19 19.00 5.2 NW 32.0 56 3 0
20 20.00 4.8 NW 31.5 59 3 0
21 21.00 4.0 WNW 31.0 62 3 0
22 22.00 3.5 W 30.5 65 3 0
23 23.00 3.1 W 30.0 67 3 0
24 24.00 2.6 NW 29.5 68 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.6 Max : 15.4 Avg : 6.2
3. Ambient Temperature (°C) Min : 25.0 Max : 34.0 Avg : 29.6
4. Relative Humidity (%) Min : 53.0 Max : 84.0 Avg : 68.1
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 751
7. Sky Appearance : Clear
TABLE : 81 METEOROLOGICAL DATA
Date : 20.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 3.2 NW 29.0 75 3 0
2 02.00 2.4 SW 28.0 77 3 0
3 03.00 2.0 SE 27.0 79 3 0
4 04.00 1.5 NE 26.5 80 2 0
5 05.00 6.9 NE 26.5 82 2 0
6 06.00 3.2 ESE 25.0 87 2 0
7 07.00 1.5 NE 25.5 86 2 0
8 08.00 2.0 ESE 26.5 70 2 0
9 09.00 1.8 SE 28.5 68 1 0
10 10.00 3.9 SE 29.5 66 1 0
11 11.00 10.6 SE 30.5 65 1 0
12 12.00 12.3 WSW 32.5 60 0 0
13 13.00 13.5 SW 33.5 59 0 0
14 14.00 16.8 SW 35.0 55 1 0
15 15.00 10.2 SW 35.5 42 1 0
16 16.00 8.5 WSW 35.0 44 2 0
17 17.00 6.2 SW 32.5 47 2 0
18 18.00 4.9 SW 31.5 48 3 0
19 19.00 5.2 WSW 31.0 50 3 0
20 20.00 4.5 SW 30.5 53 3 0
21 21.00 1.6 SW 30.0 56 3 0
22 22.00 2.3 SW 29.5 63 3 0
23 23.00 1.6 SW 29.0 67 3 0
24 24.00 1.5 SSW 28.5 70 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : SW 2. Wind Velocity (Kmph) Min : 1.5 Max : 16.8 Avg : 5.3
3. Ambient Temperature (°C) Min : 25.0 Max : 35.5 Avg : 29.9
4. Relative Humidity (%) Min : 42.0 Max : 87.0 Avg : 64.5
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 751
7. Sky Appearance : Drizzling
TABLE : 82 METEOROLOGICAL DATA
Date : 21.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 5.7 SSW 28.0 72 3 0
2 02.00 6.0 SSW 28.0 76 3 0
3 03.00 5.4 SW 27.5 75 3 0
4 04.00 4.2 SW 27.5 74 2 0
5 05.00 3.6 SSW 27.5 72 2 0
6 06.00 3.0 SSW 28.0 70 2 0
7 07.00 3.7 SW 28.5 69 2 0
8 08.00 4.9 SSW 29.0 65 2 0
9 09.00 7.9 SSW 30.0 64 1 0
10 10.00 12.5 SW 31.5 63 1 0
11 11.00 7.3 SSW 32.0 60 1 0
12 12.00 6.1 SSW 32.5 59 0 0
13 13.00 7.0 S 33.5 56 0 0
14 14.00 3.4 SSW 34.5 55 1 0
15 15.00 2.8 SSW 35.0 54 1 0
16 16.00 3.0 S 34.5 55 2 0
17 17.00 4.1 SSW 32.5 57 2 0
18 18.00 6.3 SSW 30.0 59 3 0
19 19.00 5.0 SW 29.5 62 3 0
20 20.00 4.5 SW 29.0 64 3 0
21 21.00 6.4 SSW 28.5 67 3 0
22 22.00 8.1 SW 27.5 69 3 0
23 23.00 7.0 SW 27.0 70 3 0
24 24.00 4.3 SSW 26.5 72 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : SSW 2. Wind Velocity (Kmph) Min : 2.8 Max : 12.5 Avg : 5.5
3. Ambient Temperature (°C) Min : 26.5 Max : 35.0 Avg : 29.9
4. Relative Humidity (%) Min : 54.0 Max : 76.0 Avg : 65.0
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 751
7. Sky Appearance : Cloudy
TABLE : 83 METEOROLOGICAL DATA
Date : 22.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 5.9 WSW 26.5 78 3 0
2 02.00 7.8 WNW 26.5 80 3 0
3 03.00 4.5 N 26.0 82 3 0
4 04.00 3.6 WNW 26.0 79 2 0
5 05.00 2.0 WNW 26.0 77 2 0
6 06.00 3.0 NNW 26.5 78 2 0
7 07.00 2.3 NNW 27.0 80 2 0
8 08.00 1.5 WNW 27.5 78 2 0
9 09.00 1.7 NW 28.0 76 1 0
10 10.00 5.0 WNW 28.5 74 1 0
11 11.00 8.9 NNW 29.0 72 1 0
12 12.00 12.3 N 29.5 70 0 0
13 13.00 9.4 NW 30.0 69 0 0
14 14.00 12.1 WNW 30.5 67 1 0
15 15.00 11.4 WNW 31.5 65 1 9
16 16.00 8.4 WNW 29.5 66 2 8
17 17.00 5.1 NW 28.5 68 2 0
18 18.00 4.0 NW 27.5 70 3 0
19 19.00 6.4 WNW 26.5 72 3 0
20 20.00 5.5 NNW 26.0 74 3 0
21 21.00 5.9 NNW 25.0 75 3 0
22 22.00 4.1 WNW 24.5 88 3 2.0
23 23.00 3.4 WNW 23.5 94 3 2.0
24 24.00 5.6 WNW 23.0 98 3 1.0
OBSERVATIONS
1. Predominant WindDirection (from) : WNW 2. Wind Velocity (Kmph) Min : 1.5 Max : 12.3 Avg : 5.8
3. Ambient Temperature (°C) Min : 23.0 Max : 31.5 Avg : 27.2
4. Relative Humidity (%) Min : 65.0 Max : 98.0 Avg : 76.3
5. Rainfall (mm) : 5
6. Atm. Pressure (mm of Hg) : 745
7. Sky Appearance : Rainy
TABLE : 84 METEOROLOGICAL DATA
Date : 23.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 1.3 NW 23.0 79 3 0
2 02.00 3.0 NW 23.0 80 3 0
3 03.00 2.5 WSW 23.0 82 3 0
4 04.00 2.3 NW 22.5 79 2 0
5 05.00 2.8 NW 23.5 77 2 0
6 06.00 2.3 NNW 24.5 84 2 0
7 07.00 6.4 NW 25.0 83 2 0
8 08.00 9.7 NNW 25.5 82 2 0.0
9 09.00 16.6 WNW 26.0 80 1 3.0
10 10.00 14.3 NW 26.5 76 1 5.0
11 11.00 9.3 WSW 27.0 74 1 2.0
12 12.00 7.6 NW 27.5 75 0 2.0
13 13.00 6.0 NW 28.0 73 0 2.0
14 14.00 5.3 NNW 27.0 80 1 2.0
15 15.00 5.7 NNE 25.5 84 1 1.0
16 16.00 4.3 NNE 25.5 85 2 0.0
17 17.00 7.0 NW 25.5 86 2 0.0
18 18.00 7.4 WNW 25.0 87 3 0.0
19 19.00 8.3 WNW 25.0 85 3 0
20 20.00 5.1 WSW 25.0 84 3 0
21 21.00 5.7 WSW 24.5 84 3 0
22 22.00 3.8 WSW 24.5 83 3 0
23 23.00 2.1 W 24.5 82 3 0
24 24.00 1.7 W 24.5 80 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.3 Max : 16.6 Avg : 5.9
3. Ambient Temperature (°C) Min : 22.5 Max : 28.0 Avg : 25.1
4. Relative Humidity (%) Min : 73.0 Max : 87.0 Avg : 81.0
5. Rainfall (mm) : 17
6. Atm. Pressure (mm of Hg) : 745
7. Sky Appearance : Rainy
TABLE : 85 METEOROLOGICAL DATA
Date : 24.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 4.1 NW 25.5 78 3 0
2 02.00 2.0 WNW 25.0 79 3 0
3 03.00 2.8 NW 24.5 81 3 0
4 04.00 3.1 NW 24.0 79 2 0
5 05.00 2.6 N 24.0 77 2 0
6 06.00 4.8 N 24.5 84 2 0
7 07.00 9.6 NE 24.5 83 2 0
8 08.00 13.6 WNW 25.0 82 2 0
9 09.00 15.6 NW 25.0 88 1 3.0
10 10.00 16.3 NW 26.5 90 1 5.0
11 11.00 17.0 WNW 26.5 98 1 2.0
12 12.00 15.2 SW 27.0 100 0 5.0
13 13.00 14.4 SW 27.0 98 0 2.0
14 14.00 14.0 SW 27.5 100 1 2.0
15 15.00 11.7 W 28.0 100 1 3.0
16 16.00 8.5 W 27.5 85 2 0.0
17 17.00 11.4 W 27.5 86 2 0.0
18 18.00 12.4 WSW 27.0 85 3 0.0
19 19.00 10.0 WSW 26.5 88 3 0.0
20 20.00 7.4 W 26.5 84 3 0
21 21.00 6.6 NW 26.0 86 3 0
22 22.00 4.3 NW 25.5 88 3 0
23 23.00 5.4 NW 25.0 85 3 0
24 24.00 6.1 NW 24.5 81 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.0 Max : 17.0 Avg : 9.1
3. Ambient Temperature (°C) Min : 24.0 Max : 28.0 Avg : 25.9
4. Relative Humidity (%) Min : 77.0 Max : 100.0 Avg : 86.9
5. Rainfall (mm) : 22
6. Atm. Pressure (mm of Hg) : 745
7. Sky Appearance : Rainy
TABLE : 86 METEOROLOGICAL DATA
Date : 25.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 1.3 WNW 24.0 90 6 0
2 02.00 3.0 NW 23.5 94 7 5
3 03.00 2.5 NW 23.0 95 6 6
4 04.00 2.3 NW 23.0 100 5 10
5 05.00 2.8 WNW 23.0 100 5 10
6 06.00 4.0 NW 24.0 100 5 20
7 07.00 3.4 NNW 24.5 98 5 15
8 08.00 4.7 NNE 25.0 100 5 6
9 09.00 7.0 NE 25.0 100 5 5
10 10.00 16.9 NW 26.0 100 5 0
11 11.00 17.0 NW 26.5 88 5 0
12 12.00 14.9 NW 27.0 100 5 4
13 13.00 15.6 NW 27.0 100 5 3
14 14.00 6.1 NW 27.5 100 5 2
15 15.00 4.0 NW 28.5 100 5 9
16 16.00 5.8 NNE 27.5 98 5 8
17 17.00 6.2 NW 27.5 98 6 0
18 18.00 6.7 NE 26.5 87 5 0
19 19.00 9.6 NNW 26.5 85 5 0
20 20.00 12.1 WNW 26.0 84 5 0
21 21.00 9.8 NW 25.5 85 5 0
22 22.00 10.3 NW 25.0 86 5 0
23 23.00 9.4 NW 25.0 85 5 0
24 24.00 13.0 NW 24.5 84 5 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.3 Max : 17.0 Avg : 7.9
3. Ambient Temperature (°C) Min : 23.0 Max : 28.5 Avg : 25.5
4. Relative Humidity (%) Min : 84.0 Max : 100.0 Avg : 94.0
5. Rainfall (mm) : 103
6. Atm. Pressure (mm of Hg) : 745
7. Sky Appearance : Rainy
TABLE : 87 METEOROLOGICAL DATA
Date : 26.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 2.9 NNW 24.0 85 3 0
2 02.00 3.6 NNW 23.5 86 3 0
3 03.00 2.4 NE 23.0 85 3 0
4 04.00 4.0 NE 23.0 82 2 0
5 05.00 3.6 NNE 23.0 83 2 2.0
6 06.00 5.2 WNW 23.5 87 2 2.0
7 07.00 6.5 NNW 23.5 86 2 0
8 08.00 7.0 NNW 23.5 84 2 0
9 09.00 8.5 NW 24.0 83 1 0
10 10.00 9.2 NNW 24.0 82 1 0
11 11.00 10.5 NNW 24.5 80 1 0
12 12.00 13.4 NNE 24.5 79 0 0
13 13.00 15.0 NNE 25.0 78 0 0
14 14.00 13.2 NE 25.0 77 1 0
15 15.00 14.5 WNW 25.5 76 1 0
16 16.00 9.3 NW 25.0 78 2 0
17 17.00 8.5 NNW 24.5 79 2 0
18 18.00 6.4 NNW 24.5 80 3 0
19 19.00 3.8 NW 24.0 81 3 0
20 20.00 4.0 WNW 24.0 82 3 0
21 21.00 4.5 NNW 24.0 84 3 0
22 22.00 6.2 NNW 23.5 86 3 0
23 23.00 5.1 NNW 23.5 85 3 0
24 24.00 5.5 NW 23.5 84 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NNW 2. Wind Velocity (Kmph) Min : 2.4 Max : 15.0 Avg : 7.2
3. Ambient Temperature (°C) Min : 23.0 Max : 25.5 Avg : 24.0
4. Relative Humidity (%) Min : 76.0 Max : 87.0 Avg : 82.2
5. Rainfall (mm) : 4
6. Atm. Pressure (mm of Hg) : 748
7. Sky Appearance : Rainy
TABLE : 88 METEOROLOGICAL DATA
Date : 27.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 1.3 WNW 24.5 84 3 0
2 02.00 3.0 WNW 23.5 84 3 0
3 03.00 2.5 NNW 23.0 84 3 0
4 04.00 2.3 NW 23.0 85 2 0
5 05.00 2.8 NNW 23.0 86 2 0
6 06.00 4.8 NNW 23.5 87 2 0
7 07.00 9.6 NNW 24.5 85 2 0
8 08.00 13.6 NW 26.5 77 2 0
9 09.00 15.6 NW 27.0 72 1 0
10 10.00 16.3 NW 27.5 70 1 0
11 11.00 17.0 N 28.0 69 1 Cloudy
12 12.00 15.2 N 28.5 88 0 10
13 13.00 14.4 N 29.0 100 0 4
14 14.00 14.0 NW 29.5 100 1 2
15 15.00 11.7 NNW 30.0 98 1 2
16 16.00 8.5 NW 29.5 67 2 0
17 17.00 11.4 NNW 29.0 68 2 0
18 18.00 12.4 NNW 28.5 69 3 0
19 19.00 10.0 NNE 28.5 72 3 0
20 20.00 7.4 NNE 28.0 73 3 0
21 21.00 6.6 NE 28.0 75 3 0
22 22.00 4.3 NE 27.5 76 3 0
23 23.00 5.4 NNE 27.0 74 3 0
24 24.00 6.1 NNW 27.0 75 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.3 Max : 17.0 Avg : 9.0
3. Ambient Temperature (°C) Min : 23.0 Max : 30.0 Avg : 26.8
4. Relative Humidity (%) Min : 67.0 Max : 100.0 Avg : 79.9
5. Rainfall (mm) : 18
6. Atm. Pressure (mm of Hg) : 745
7. Sky Appearance : Rainy
TABLE : 89 METEOROLOGICAL DATA
Date : 28.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 3.0 NW 26.5 78 3 0
2 02.00 2.5 NW 26.0 79 3 0
3 03.00 1.6 NNW 25.5 79 3 0
4 04.00 2.5 NW 25.5 80 2 0
5 05.00 1.0 NW 26.0 80 2 0
6 06.00 3.6 NNW 27.0 77 2 0
7 07.00 5.0 NNW 27.5 73 2 0
8 08.00 6.8 NW 27.5 69 2 0
9 09.00 7.2 NW 28.0 66 1 0
10 10.00 6.9 NW 28.0 65 1 0
11 11.00 10.2 NE 27.0 72 1 0
12 12.00 13.5 NE 27.0 75 0 0
13 13.00 18.6 NE 28.0 77 0 0
14 14.00 12.5 NNE 28.5 68 1 0
15 15.00 11.0 NE 29.0 72 1 0
16 16.00 5.9 NNE 28.5 73 2 0
17 17.00 6.4 NE 28.0 75 2 0
18 18.00 5.0 NNW 27.5 76 3 0
19 19.00 4.8 NW 27.0 78 3 0
20 20.00 3.5 NW 26.5 76 3 0
21 21.00 4.2 WNW 26.5 75 3 0
22 22.00 3.7 NW 26.0 74 3 0
23 23.00 4.0 NW 25.5 77 3 0
24 24.00 5.1 NNW 25.5 78 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.0 Max : 18.6 Avg : 6.2
3. Ambient Temperature (°C) Min : 25.5 Max : 29.0 Avg : 27.0
4. Relative Humidity (%) Min : 65.0 Max : 80.0 Avg : 74.7
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 748
7. Sky Appearance : Clear
TABLE : 90 METEOROLOGICAL DATA
Date : 29.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 3.2 NNW 25.0 77 3 0
2 02.00 2.4 NW 25.0 79 3 0
3 03.00 2.0 NW 24.5 81 3 0
4 04.00 1.5 NW 24.5 83 2 0
5 05.00 1.2 NW 24.0 84 2 0
6 06.00 4.8 NNW 24.5 83 2 0
7 07.00 9.6 N 25.0 76 2 0
8 08.00 13.6 N 26.0 68 2 0
9 09.00 15.6 N 27.5 66 1 0
10 10.00 16.3 NW 28.0 64 1 0
11 11.00 17.0 NW 28.5 62 1 0
12 12.00 15.2 NNW 29.0 61 0 0
13 13.00 14.4 NW 29.5 60 0 0
14 14.00 14.0 WNW 30.0 59 1 0
15 15.00 11.7 NW 30.5 57 1 0
16 16.00 8.5 NW 29.5 63 2 0
17 17.00 11.4 N 29.0 65 2 0
18 18.00 12.4 N 29.0 66 3 0
19 19.00 10.0 WNW 28.5 67 3 0
20 20.00 7.4 WSW 28.0 68 3 0
21 21.00 6.6 WSW 28.0 72 3 0
22 22.00 4.3 WSW 26.5 73 3 0
23 23.00 5.4 SW 26.0 74 3 0
24 24.00 6.1 SW 26.0 75 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.2 Max : 17.0 Avg : 8.9
3. Ambient Temperature (°C) Min : 24.0 Max : 30.5 Avg : 27.2
4. Relative Humidity (%) Min : 57.0 Max : 84.0 Avg : 70.1
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 748
7. Sky Appearance : Clear
TABLE : 91 METEOROLOGICAL DATA
Date : 30.06.13
Location : Corezone
Sl.No Time (Hrs)
Wind Velocity (Kmph)
Wind Direction
(from)
Temp. (°C)
Relative Humidity
(%)
Cloud Cover
(Oktas)
Rainfall (mm)
Dry
1 01.00 4.5 NW 25.0 76 3 0
2 02.00 4.0 WNW 25.0 77 3 0
3 03.00 3.3 WNW 24.5 79 3 0
4 04.00 2.9 SW 24.5 81 2 0
5 05.00 2.5 SW 25.0 83 2 0
6 06.00 4.7 WSW 26.0 82 2 0
7 07.00 6.8 WSW 27.5 81 2 0
8 08.00 10.6 SW 29.0 74 2 0
9 09.00 9.9 WSW 30.0 69 1 0
10 10.00 12.4 SW 31.5 64 1 0
11 11.00 7.9 SW 32.0 62 1 0
12 12.00 11.3 SW 33.0 58 0 0
13 13.00 15.6 SSW 34.0 54 0 0
14 14.00 11.4 S 35.5 52 1 0
15 15.00 8.5 SSW 34.0 55 1 0
16 16.00 4.8 SSW 33.0 57 2 0
17 17.00 6.1 SSW 32.0 63 2 0
18 18.00 4.2 SW 31.5 65 3 0
19 19.00 4.0 WSW 30.0 67 3 0
20 20.00 6.2 SW 29.0 69 3 0
21 21.00 12.5 SSW 28.5 71 3 0
22 22.00 8.1 WSW 28.5 73 3 0
23 23.00 6.8 SW 28.0 75 3 0
24 24.00 4.1 SSW 28.0 77 3 0
OBSERVATIONS
1. Predominant WindDirection (from) : SW 2. Wind Velocity (Kmph) Min : 2.5 Max : 15.6 Avg : 7.2
3. Ambient Temperature (°C) Min : 24.5 Max : 35.5 Avg : 29.4
4. Relative Humidity (%) Min : 52.0 Max : 83.0 Avg : 69.3
5. Rainfall (mm) : 0
6. Atm. Pressure (mm of Hg) : 748
7. Sky Appearance : Clear
3.6 AMBIENT AIR QUALITY STATUS
3.6.1 Preamble
The principle objective of the ambient air quality monitoring is to assess the existing
levels of air pollutants as well as the regional background concentration in and
around the project area. Air pollution forms an important and critical factor to
study the environmental issues in the mining areas. Air quality has to be frequently
monitored to know the extent of pollution due to mining and allied activities. The
ambient air quality monitoring was carried out at eight stations.
The monitoring stations were identified on the basis of meteorology in the upwind
and downwind direction as well as to represent the cross sectional scenario of the
project site. The monitoring network was designed based on the available
meteorological and climatologically norms of predominant wind direction and
wind speed of the study region.
The parameters selected for analyzing the air quality status are Suspended
Particulate Matter <10 & 2.5, Sulphur dioxide (SO2), Nitrogen oxides (NOx) and
Heavy Metals. As per the existing norms, air quality monitoring was carried out on
24 hourly basis for SPM & RPM, SO2 and NOx samples for two days in a week for
twelve weeks in the season. The location details of ambient air quality monitoring
stations are given in the Table below.
Details of Ambient air quality-monitoring stations
SI.
No. Location Name Location Code
1. Core Zone A - 1
2. Pimpri Village A - 2
3. Borgaon Village A - 3
4. Pimpalgaon Village A - 4
5. Kunada Village A - 5
6. Telwasa Village A - 6
Data Presentation
The ambient air quality data are given in the Tables below.
Ambient Air Quality Status
Location Name & Code
MIN MAX 98th AM GM STD CPCB Limit
SPM
Core Zone (A1) 121 261 260 221.9 217.5 41.2
-
Pimpri Village (A2) 151 239 238 209.5 207.5 27.9
Borgaon Village (A3) 134 206 203 180.6 179.4 20.7
Pimpalgaon Village (A4) 110 145 144 131.8 131.4 10.5
Kunada Village (A5) 102 133 132 119.9 119.4 10.9
Telwasa Village (A6) 84 119 118 105.2 104.6 11.2
PM10
Core Zone (A1) 62 91 90 79.3 78.8 9.1
100
Pimpri Village (A2) 52 83 83 70.8 70.0 9.9
Borgaon Village (A3) 49 81 80 68.5 67.8 10.0
Pimpalgaon Village (A4) 41 72 70 58.3 57.7 8.6
Kunada Village (A5) 31 52 51 44.3 43.8 6.4
Telwasa Village (A6) 36 54 54 43.7 43.4 5.1
PM2.5
Core Zone (A1) 30 45.0 44.0 36.2 35.9 4.6
60
Pimpri Village (A2) 28 41.0 39.0 33.8 33.7 3.2
Borgaon Village (A3) 24 36.0 35.0 29.8 29.6 3.7
Pimpalgaon Village (A4) 20 35.0 34.0 27.7 27.3 4.7
Kunada Village (A5) 17 27.0 27.0 22.3 22.1 2.8
Telwasa Village (A6) 16 28.0 26.0 20.5 20.2 3.2
SO2
Core Zone (A1) 15.5 20.2 20.0 18.3 18.3 1.2
80
Pimpri Village (A2) 12.5 19.6 19.5 15.9 15.7 2.5
Borgaon Village (A3) 12.5 19.6 19.4 16.4 16.3 2.4
Pimpalgaon Village (A4) 12.7 19.8 18.7 16.4 16.3 1.7
Kunada Village (A5) 14.7 19.4 18.8 17.1 17.0 1.3
Telwasa Village (A6) 13.1 20.4 19.8 16.7 16.6 1.8
NOX
Core Zone (A1) 20.1 28.6 27.6 24.5 24.3 2.4
80
Pimpri Village (A2) 15.6 27.5 26.8 22.0 21.7 3.8
Borgaon Village (A3) 14.6 27.4 26.7 21.7 21.3 3.7
Pimpalgaon Village (A4) 16.7 27.3 26.8 22.0 21.8 2.6
Kunada Village (A5) 17.1 28.7 27.3 22.3 22.2 2.8
Telwasa Village (A6) 16.9 26.4 26.3 21.6 21.4 2.7
Data Analysis
Core zone
The Suspended Particulate Matter (SPM) values were ranging from 121 g/m3 to
260 g/m3 PM10 and PM2.5 values are ranging from 62 g/m3 to 90 g/m3 and
30 g/m3 to 44 g/m3 respectively.
SO2 and NOx values are varying between 15.5 to 20.0 g/m3 and 20.1 to 27.6
g/m3 respectivelyThe heavy metals like Arsenic ( As) and Mercury ( Hg) were
found to be Below Detectable Limit ( BDL) and other metals like Nickel ( Ni), Lead
( Pb) and Chromium ( Cr) values are found to be very low and negligible. All
the values are found to be well within the NAAQ Standards prescribed by CPCB.
Buffer zone
The Suspended Particulate Matter ( SPM) values were ranging from 84 g/m3 to
237 g/m3PM10 and PM2.5 values are ranging from 31 g/m3 to 83 g/m3 and
16 g/m3 to 27 g/m3 respectively. SO2 and NOx values are varying between
12.5 to 17.6 g/m3 and 14.6 to 24.3 g/m3 respectively. respectivelyThe heavy
metals like Arsenic ( As) and Mercury ( Hg) were found to be Below Detectable
Limit ( BDL) and other metals like Nickel ( Ni), Lead ( Pb) and Chromium ( Cr)
values are found to be very low and negligible. All the values are found to be
well within the NAAQ Standards prescribed by CPCB.
Summary
In general, all the values are found to be well within the NAAQ Standards prescribed by CPCB.
The latest data on PM-10 & PM-2.5 along with Pb,Cr etc has been generated in
the surrounding villages during the pre- monsoon season 2013 and has given in
subsequent pages.
AMBIENT AIR QUALITY DATA
Location : Core Zone (JA1)
Week Date SPM
µg/m3 PM10
µg/m3 PM2.5
µg/m3 SO2
µg/m3 NOx
µg/m3 Hg
ng/m3 Pb
µg/m3 Cr
ng/m3 Ni
ng/m3 As
ng/m3
I 07.04.2013 259 89 44 19.8 25.9 BDL 0.12 0.10 0.22 BDL
08.04.2013 260 91 41 20.2 27.6 BDL 0.10 0.09 0.21 BDL
II 15.04.2013 243 82 35 18.7 24.6 BDL 0.13 0.08 0.20 BDL
16.04.2013 255 85 42 19.2 25.1 BDL 0.10 0.06 0.24 BDL
III 22.04.2013 258 87 38 20.0 26.3 BDL 0.09 0.07 0.23 BDL
23.04.2013 238 82 34 17.5 22.3 BDL 0.12 0.05 0.22 BDL
IV 28.04.2013 240 79 39 18.2 23.5 BDL 0.11 0.08 0.20 BDL
29.04.2013 249 84 36 19.4 26.1 BDL 0.10 0.04 0.18 BDL
V 08.05.2013 252 86 37 19.2 25.9 BDL 0.13 0.06 0.19 BDL
09.05.2013 234 76 36 17.7 24.3 BDL 0.13 0.08 0.17 BDL
VI 17.05.2013 226 75 34 16.8 26.8 BDL 0.14 0.09 0.15 BDL
18.05.2013 247 83 43 18.6 24.7 BDL 0.13 0.08 0.14 BDL
VII 23.05.2013 261 90 45 19.2 25.8 BDL 0.12 0.07 0.12 BDL
24.05.2013 252 88 40 19.7 27.3 BDL 0.10 0.05 0.13 BDL
VIII 29.05.2013 245 84 36 18.6 28.6 BDL 0.08 0.06 0.18 BDL
30.05.2013 234 81 33 17.6 27.4 BDL 0.07 0.07 0.21 BDL
IX 07.06.2013 214 86 37 18.7 23.9 BDL 0.06 0.11 0.22 BDL
08.06.2013 208 82 35 17.2 21.3 BDL 0.11 0.10 0.24 BDL
X 14.06.2013 158 62 32 17.3 20.7 BDL 0.12 0.08 0.23 BDL
15.06.2013 143 70 30 15.5 20.1 BDL 0.10 0.09 0.24 BDL
XI 22.06.2013 168 66 31 17.9 21.9 BDL 0.09 0.10 0.18 BDL
23.06.2013 121 64 30 15.9 21.8 BDL 0.08 0.11 0.20 BDL
XII 28.06.2013 188 62 30 18.5 22.4 BDL 0.10 0.10 0.22 BDL
29.06.2013 172 70 30 18.5 22.8 BDL 0.13 0.09 0.24 BDL
CPCB LIMIT - 100 60 80 80 - 1.0(µg/m3) - 20 6.0
AMBIENT AIR QUALITY DATA
Location : Pimri Village (BZ) (JA2)
Week Date SPM
µg/m3 PM10
µg/m3 PM2.5
µg/m3 SO2
µg/m3 NOx
µg/m3 Hg
ng/m3 Pb
µg/m3 Cr
ng/m3 Ni
ng/m3 As
ng/m3
I 07.04.2013 238 83 41 19.6 27.5 BDL 0.08 0.04 BDL BDL
08.04.2013 229 79 39 18.4 26.8 BDL 0.10 0.08 BDL BDL
II 15.04.2013 226 81 37 17.2 25.4 BDL 0.07 0.05 BDL BDL
16.04.2013 234 75 35 18.7 24.6 BDL 0.10 0.04 BDL BDL
III 22.04.2013 215 72 33 12.8 17.5 BDL 0.12 0.02 0.06 BDL
23.04.2013 237 73 35 16.9 20.9 BDL 0.14 0.02 0.06 BDL
IV 28.04.2013 229 79 37 18.2 23.8 BDL 0.10 0.02 0.04 BDL
29.04.2013 231 80 34 19.5 26.1 BDL 0.08 BDL 0.06 BDL
V 08.05.2013 239 83 38 17.9 25.4 BDL 0.12 BDL 0.06 BDL
09.05.2013 224 75 35 13.2 18.0 BDL 0.10 BDL 0.04 BDL
VI 17.05.2013 212 71 32 12.8 15.6 BDL 0.12 BDL 0.04 BDL
18.05.2013 225 77 36 18.7 26.3 BDL 0.14 BDL BDL BDL
VII 23.05.2013 219 73 34 17.5 24.8 BDL 0.10 0.02 BDL BDL
24.05.2013 227 78 32 14.8 17.3 BDL 0.11 0.02 BDL BDL
VIII 29.05.2013 235 81 35 18.9 26.4 BDL 0.06 0.05 BDL BDL
30.05.2013 218 73 34 13.8 16.7 BDL 0.06 0.04 0.07 BDL
IX 07.06.2013 162 56 30 12.5 22.2 BDL 0.10 0.03 0.09 BDL
08.06.2013 177 58 32 13.5 21.9 BDL 0.08 0.04 0.10 BDL
X 14.06.2013 188 64 32 14.1 24.1 BDL 0.11 BDL 0.12 BDL
15.06.2013 160 54 31 14.1 19.8 BDL 0.08 BDL 0.08 BDL
XI 22.06.2013 176 60 30 15.3 20.4 BDL 0.09 BDL 0.09 BDL
23.06.2013 151 62 30 15.6 17.5 BDL 0.11 BDL 0.09 BDL
XII 28.06.2013 183 59 32 13.8 16.8 BDL 0.14 BDL 0.12 BDL
29.06.2013 192 52 28 13.5 23.2 BDL 0.12 BDL 0.13 BDL
CPCB LIMIT - 100 60 80 80 - 1.0(µg/m3) - 20 6.0
AMBIENT AIR QUALITY DATA
Location : Bargaon Village (BZ) (JA3)
Week Date SPM
µg/m3 PM10
µg/m3 PM2.5
µg/m3 SO2
µg/m3 NOx
µg/m3 Hg
ng/m3 Pb
µg/m3 Cr
ng/m3 Ni
ng/m3 As
ng/m3
I 07.04.2013 206 80 36 19.2 26.5 BDL 0.04 0.04 0.03 BDL
08.04.2013 189 76 33 17.8 22.4 BDL 0.07 0.08 0.04 BDL
II 15.04.2013 198 79 31 18.3 25.9 BDL 0.05 0.05 0.06 BDL
16.04.2013 201 81 35 19.1 24.8 BDL 0.10 0.04 0.08 BDL
III 22.04.2013 192 73 32 18.9 23.4 BDL 0.05 BDL 0.06 BDL
23.04.2013 185 65 28 15.6 22.6 BDL 0.11 BDL 0.06 BDL
IV 28.04.2013 203 78 34 17.8 21.8 BDL 0.17 BDL 0.04 BDL
29.04.2013 187 72 29 18.1 24.7 BDL 0.04 BDL 0.06 BDL
V 08.05.2013 196 79 32 17.5 20.7 BDL 0.09 BDL 0.06 BDL
09.05.2013 185 65 27 13.7 15.3 BDL 0.10 BDL BDL BDL
VI 17.05.2013 181 62 25 12.9 14.6 BDL 0.12 BDL BDL BDL
18.05.2013 190 73 30 17.8 19.8 BDL 0.12 BDL BDL BDL
VII 23.05.2013 202 79 33 18.3 27.4 BDL 0.10 BDL BDL BDL
24.05.2013 194 77 32 19.6 26.7 BDL 0.07 BDL BDL BDL
VIII 29.05.2013 199 80 35 19.4 25.1 BDL 0.05 BDL BDL BDL
30.05.2013 182 64 26 13.3 15.0 BDL 0.06 0.02 BDL BDL
IX 07.06.2013 166 59 32 16.6 22.9 BDL 0.10 0.03 BDL BDL
08.06.2013 154 53 27 13.5 19.8 BDL 0.08 0.04 BDL BDL
X 14.06.2013 147 59 30 15.6 20.3 BDL 0.11 0.04 BDL BDL
15.06.2013 160 49 24 12.5 17.2 BDL 0.08 0.03 0.06 BDL
XI 22.06.2013 179 51 24 14.3 21.5 BDL 0.09 0.02 0.04 BDL
23.06.2013 143 62 25 13.2 18.6 BDL 0.13 0.02 0.06 BDL
XII 28.06.2013 134 68 28 15.1 22.8 BDL 0.12 0.02 0.05 BDL
29.06.2013 162 61 27 16.6 20.2 BDL 0.13 0.02 0.04 BDL
CPCB LIMIT - 100 60 80 80 - 1.0(µg/m3) - 20 6.0
AMBIENT AIR QUALITY DATA
Location : Pimpalgaori Village (JA4)
Week Date SPM
µg/m3 PM10
µg/m3 PM2.5
µg/m3 SO2
µg/m3 NOx
µg/m3 Hg
ng/m3 Pb
µg/m3 Cr
ng/m3 Ni
ng/m3 As
ng/m3
I 07.04.2013 138 61 31 15.6 23.4 BDL 0.07 0.04 BDL BDL
08.04.2013 141 69 34 16.2 26.8 BDL 0.09 0.08 BDL BDL
II 15.04.2013 145 70 35 19.8 27.3 BDL 0.06 0.05 BDL BDL
16.04.2013 134 59 29 17.3 21.9 BDL 0.09 0.04 0.08 BDL
III 22.04.2013 129 57 27 12.7 16.7 BDL 0.11 BDL 0.06 BDL
23.04.2013 137 63 30 14.8 20.6 BDL 0.13 BDL 0.06 BDL
IV 28.04.2013 140 68 33 18.4 24.1 BDL 0.09 BDL 0.04 BDL
29.04.2013 132 54 25 15.9 19.5 BDL 0.07 BDL 0.06 BDL
V 08.05.2013 143 67 31 17.6 23.2 BDL 0.11 BDL BDL BDL
09.05.2013 131 56 28 16.2 20.7 BDL 0.06 BDL BDL BDL
VI 17.05.2013 137 65 31 15.3 19.3 BDL 0.09 BDL BDL BDL
18.05.2013 144 72 33 18.7 25.8 BDL 0.11 BDL BDL BDL
VII 23.05.2013 133 52 24 17.9 22.4 BDL 0.13 BDL BDL BDL
24.05.2013 139 64 28 18.5 23.2 BDL 0.09 BDL BDL BDL
VIII 29.05.2013 142 67 32 16.8 21.6 BDL 0.07 BDL BDL BDL
30.05.2013 136 62 27 17.1 22.8 BDL 0.11 BDL BDL BDL
IX 07.06.2013 113 51 33 16.0 21.3 BDL 0.09 BDL BDL BDL
08.06.2013 124 48 21 17.4 22.1 BDL 0.11 0.04 BDL BDL
X 14.06.2013 138 41 22 15.7 23.7 BDL 0.13 0.04 0.06 BDL
15.06.2013 116 54 24 14.1 19.1 BDL 0.09 0.03 0.04 BDL
XI 22.06.2013 119 56 25 16.4 20.6 BDL 0.10 0.04 0.06 BDL
23.06.2013 128 46 20 13.6 18.3 BDL 0.05 BDL 0.05 BDL
XII 28.06.2013 114 49 22 16.2 20.4 BDL 0.05 BDL 0.08 BDL
29.06.2013 110 48 20 15.3 22.3 BDL 0.09 BDL 0.06 BDL
CPCB LIMIT - 100 60 80 80 - 1.0(µg/m3) - 20 6.0
AMBIENT AIR QUALITY DATA
Location : kunad Village (JA5)
Week Date SPM
µg/m3 PM10
µg/m3 PM2.5
µg/m3 SO2
µg/m3 NOx
µg/m3 Hg
ng/m3 Pb
µg/m3 Cr
ng/m3 Ni
ng/m3 As
ng/m3
I 09.04.2013 132 52 27 18.3 24.6 BDL 0.04 0.04 BDL BDL
10.04.2013 128 50 24 17.6 22.2 BDL 0.06 0.08 BDL BDL
II 17.04.2013 123 47 21 16.8 23.8 BDL 0.03 0.05 BDL BDL
18.04.2013 130 49 26 18.4 21.4 BDL 0.06 0.04 BDL BDL
III 24.04.2013 126 43 23 15.1 19.1 BDL 0.08 0.02 BDL BDL
25.04.2013 133 51 25 17.2 23.8 BDL BDL BDL BDL BDL
IV 29.04.2013 127 45 22 15.9 20.3 BDL BDL BDL BDL BDL
30.04.2013 124 47 23 16.5 24.6 BDL BDL BDL BDL BDL
V 10.05.2013 129 45 21 17.8 22.4 BDL 0.08 BDL BDL BDL
11.05.2013 132 51 26 17.1 24.0 BDL 0.03 BDL BDL BDL
VI 19.05.2013 125 49 25 16.4 28.7 BDL 0.06 BDL 0.04 BDL
20.05.2013 130 51 27 18.0 21.2 BDL 0.08 BDL 0.05 BDL
VII 25.05.2013 126 47 22 17.3 25.5 BDL 0.10 BDL 0.02 BDL
26.05.2013 131 42 25 18.1 23.8 BDL BDL BDL 0.02 BDL
VIII 30.05.2013 118 46 20 19.4 27.3 BDL BDL BDL 0.04 BDL
31.05.2013 114 45 20 15.3 22.1 BDL BDL 0.04 0.07 BDL
IX 09.06.2013 111 34 22 14.8 21.4 BDL 0.06 0.03 0.06 BDL
10.06.2013 108 39 21 17.2 22.6 BDL 0.08 0.04 BDL BDL
X 16.06.2013 106 38 20 18.8 23.1 BDL 0.10 0.04 BDL BDL
17.06.2013 105 46 21 17.5 20.7 BDL 0.06 BDL BDL BDL
XI 24.06.2013 110 31 18 14.7 18.2 BDL 0.07 BDL BDL BDL
25.06.2013 103 33 17 15.3 18.5 BDL BDL BDL BDL BDL
XII 29.06.2013 105 49 19 17.6 17.1 BDL BDL BDL BDL BDL
30.06.2013 102 33 20 18.8 19.4 BDL BDL BDL BDL BDL
CPCB LIMIT - 100 60 80 80 - 1.0(µg/m3) - 20 6.0
AMBIENT AIR QUALITY DATA
Location : Telwasa Village (JA6)
Week
Date SPM
µg/m3
PM10 µg/m
3
PM2.5
µg/m3
SO2 µg/m
3
NOx µg/m
3
Hg ng/m
3
Pb µg/m
3
Cr ng/m
3
Ni ng/m
3
As ng/m
3
I 09.04.2013 118 54 26 18.5 22.1 BDL 0.07 0.04 BDL BDL
10.04.2013 109 41 19 16.8 18.6 BDL 0.09 0.08 BDL BDL
II 17.04.2013 106 42 16 15.6 21.3 BDL 0.06 0.05 BDL BDL
18.04.2013 117 49 22 17.0 22.9 BDL BDL 0.04 BDL BDL
III 24.04.2013 112 44 21 18.4 23.6 BDL BDL 0.02 BDL BDL
25.04.2013 118 53 24 19.8 24.8 BDL BDL BDL BDL BDL
IV 29.04.2013 116 50 23 18.1 21.3 BDL BDL BDL BDL BDL
30.04.2013 111 43 19 16.9 19.5 BDL 0.07 BDL BDL BDL
V 10.05.2013 115 46 23 15.7 20.8 BDL 0.04 BDL BDL BDL
11.05.2013 108 42 18 16.3 22.2 BDL 0.06 BDL BDL BDL
VI 19.05.2013 116 47 25 20.4 26.4 BDL 0.09 BDL BDL BDL
20.05.2013 107 43 22 18.2 24.8 BDL 0.08 BDL 0.04 BDL
VII 25.05.2013 109 40 19 17.5 25.7 BDL 0.09 BDL 0.02 BDL
26.05.2013 119 54 28 19.5 26.3 BDL 0.09 BDL 0.02 BDL
VIII 30.05.2013 106 44 22 15.3 21.0 BDL 0.07 BDL BDL BDL
31.05.2013 110 42 19 14.8 21.3 BDL 0.10 BDL BDL BDL
IX 09.06.2013 86 41 18 15.7 20.5 BDL BDL 0.03 BDL BDL
10.06.2013 88 38 17 17.6 22.1 BDL BDL 0.04 BDL BDL
X 16.06.2013 92 37 20 16.4 20.6 BDL BDL BDL 0.06 BDL
17.06.2013 90 36 18 15.2 18.0 BDL BDL BDL 0.04 BDL
XI 24.06.2013 95 40 16 14.6 17.2 BDL BDL BDL 0.06 BDL
25.06.2013 84 42 17 13.1 16.9 BDL BDL BDL 0.05 BDL
XII 29.06.2013 95 39 20 14.1 18.5 BDL 0.05 0.04 0.08 BDL
30.06.2013 98 41 19 16.2 21.7 BDL 0.09 0.03 0.06 BDL
CPCB LIMIT - 100 60 80 80 - 1.0(µg/m3) - 20 6.0
3.7 BASE LINE WATER QUALITY STATUS
Rationale behind sampling
Any adverse impact or pollution consequence of water will have serious effect on
the environment. Hence, it becomes important to assess the water quality
periodically in the mining area. Thus, to assess the water quality, five locations are
identified and samples (5 Nos.) were collected and analyzed for physico-
chemical and heavy metal parameters. Bacterial examination was also carried
out to find out the Coliform contamination (if any) at water sources. The water
quality assessment has been made from the following monitoring stations:-
Wardha River, UP Stream - W1
Wardha River, Down Stream - W2
Drinking Water, Kunada Village - W3
Drinking Water, - W4
Bore Well Water,Telwasa Village - W5
In addition the quality of existing mine effluent has also been considered and
given in subsequent pages.
3.7.2 Data Presentation
The detailed water quality data generated are given in subsequent pages. The abstract
of water quality status is furnished in Table below.
Ground Water quality status
Source pH Turbidity
(NTU)
TDS (mg/l) Total
Hardness (mg/l)
Iron (mg/l) Chloride
(mg/l) Sulphate
(mg/l) Fluoride
(mg/l)
Min Max Min Max Min Max Min Max Min Max Min Max Min Max
Drinking / Ground
Water 7.94 8.19 4 - 5 694 924 301 497 0.04 0.08 45 70 30 281 0.01 0.12
IS 10500 Norms
6.5-8.5 10 500-2000 300-600 0.3-1.0 250-1000 200-1000 1.0
Surface water quality status
Source pH
Colour (Hazen Units )
TDS (mg/l) Iron (mg/l) Chloride
(mg/l) Sulphate
(mg/l) Fluoride (mg/l)
Min Max Min Max Min Max Min Max Min Max Min Max Min Max
River 8.21 8.23 12 13 788 778 0.18 49 55 215 230 0.24 0.26
IS:2296-1982
6.5-8.5 300 1500 50 600 400 1.5
WATER QUALITY DATA Location Name : Near Wardha River UP Stream Date of Sampling : 21.05.2013
Sl. No. Parameter Unit Result IS:2296-1982 Tolerance limits for Inland Surface
water (Class C)
1 pH - 8.21 6.5 – 8.5
2 Colour Hazen Units 12 300
3 Temperature oC 33.0 -
4 Turbidity NTU 18 -
5 Total suspended solids mg/l 56 -
6 Total dissolved solids mg/l 788 1500
7 Total volatile solids mg/l - -
8 Dissolved Oxygen mg/l 5.3 4.0
9 BOD - 3 days, 27oC mg/l 2 3.0
10 COD mg/l 26 -
11 Oil & grease mg/l Nil -
12 Residual chlorine mg/l Nil -
13 Chloride (as CI) mg/l 55 600
14 Flouride (as F) mg/l 0.26 1.5
15 Sulphate (as SO4) mg/l 230 400
16 Sulphide (as S) mg/l Nil -
17 Cyanide (as CN) mg/l <0.01 0.05
18 Insecticides/pesticides mg/l Nil Absent
19 Phenols (as C6H5OH) mg/l <0.001 0.005
20 Chromium (as Cr) mg/l <0.01 0.05
21 Copper (as Cu) mg/l <0.01 1.5
22 Selenium (as Se) mg/l <0.01 0.05
23 Arsenic (as As) mg/l <0.01 0.2
24 Barium (as Ba) mg/l <0.01 -
25 Cadmium mg/l <0.01 0.01
26 Nickel (as Ni) mg/l <0.01 -
27 Boron (as B) mg/l <0.01 -
28 Mercury (as Hg) mg/l <0.001 -
29 Silver (as Ag) mg/l <0.01 -
30 Lead (as Pb) mg/l <0.01 0.1
31 Zinc (as Pb) mg/l 1.3 15
32 Alkalinity to phenolphthalein mg/l Nil -
33 Alkalinity to methyl orange mg/l 233 -
34 Iron (as Fe) mg/l 0.18 50
35 Calcium (as Ca) mg/l 68 -
36 Magnesium (as Mg) mg/l 41 -
37 Total Nitrogen (as N) mg/l 2.8 -
38 Percent sodium % 31.55 -
39 Coliform organisms MPN/100ml 2100 5000
40 Sodium (as Na) mg/l 80 -
41 Potassium (as K) mg/l 31 -
WATER QUALITY DATA Location Name : Near Wardha River Down Stream Date of Sampling : 21.05.2013
Sl. No.
Parameter Unit Result IS:2296-1982 Tolerance limits for Inland Surface
water (Class C)
1 pH - 8.23 6.5 – 8.5
2 Colour Hazen Units 13 300
3 Temperature oC 33.0 -
4 Turbidity NTU 19 -
5 Total suspended solids mg/l 58 -
6 Total dissolved solids mg/l 778 1500
7 Total volatile solids mg/l - -
8 Dissolved Oxygen mg/l 5.2 4.0
9 BOD - 3 days, 27oC mg/l 2 3.0
10 COD mg/l 26 -
11 Oil & grease mg/l Nil -
12 Residual chlorine mg/l Nil -
13 Chloride (as CI) mg/l 49 600
14 Flouride (as F) mg/l 0.24 1.5
15 Sulphate (as SO4) mg/l 215 400
16 Sulphide (as S) mg/l Nil -
17 Cyanide (as CN) mg/l <0.01 0.05
18 Insecticides/pesticides mg/l Nil Absent
19 Phenols (as C6H5OH) mg/l <0.001 0.005
20 Chromium (as Cr) mg/l <0.01 0.05
21 Copper (as Cu) mg/l <0.001 1.5
22 Selenium (as Se) mg/l <0.001 0.05
23 Arsenic (as As) mg/l <0.001 0.2
24 Barium (as Ba) mg/l <0.01 -
25 Cadmium mg/l <0.001 0.01
26 Nickel (as Ni) mg/l <0.01 -
27 Boron (as B) mg/l <0.1 -
28 Mercury (as Hg) mg/l <0.001 -
29 Silver (as Ag) mg/l <0.01 -
30 Lead (as Pb) mg/l <0.001 0.1
31 Zinc (as Pb) mg/l 0.72 15
32 Alkalinity to phenolphthalein mg/l Nil -
33 Alkalinity to methyl orange mg/l 248 -
34 Iron (as Fe) mg/l 0.18 50
35 Calcium (as Ca) mg/l 63 -
36 Magnesium (as Mg) mg/l 43 -
37 Total Nitrogen (as N) mg/l 2.4 -
38 Percent sodium % 31.59 -
39 Coliform organisms MPN/100ml 2100 5000
40 Sodium (as Na) mg/l 79 -
41 Potassium (as K) mg/l 30 -
WATER QUALITY DATA Location Name : Drinking Water Kunada Village Date of Sampling : 21.05.2013
Sl. No.
Parameter Unit Result IS: 10500-1991
Norms Desirable/ Permissible
1 pH - 7.94 6.5 – 8.5/ 6.5-8.5
2 Colour Hazen Units <5 5/25
3 Temperature oC 30.5 -
4 Turbidity NTU 4 5/10
5 Total suspended solids mg/l <2 -
6 Total dissolved solids mg/l 924 500/2000
7 Total volatile solids mg/l - -
8 Dissolved Oxygen mg/l 5.2 >3.0
9 BOD - 3 days at 27oC mg/l - -
10 COD mg/l 16 -
11 Oil & grease mg/l Nil -
12 Residual chlorine mg/l Nil 0.2 min.
13 Chloride (as CI) mg/l 45 250/1000
14 Flouride (as F) mg/l 0.08 1.0/1.5
15 Sulphate (as SO4) mg/l 281 200/400
16 Sulphide (as S) mg/l Nil -
17 Cyanide (as CN) mg/l Nil 0.05
18 Insecticides/pesticides mg/l Nil Absent
19 Phenols (as C6H5OH) mg/l <0.001 0.001/0.002
20 Chromium (as Cr) mg/l <0.01 0.05
21 Copper (as Cu) mg/l <0.01 0.05
22 Selenium (as Se) mg/l <0.01 0.01
23 Arsenic (as As) mg/l <0.01 0.05
24 Barium (as Ba) mg/l <0.01 -
25 Cadmium mg/l <0.01 0.01
26 Nickel (as Ni) mg/l <0.01 -
27 Boron (as B) mg/l <0.01 1.0/5.0
28 Mercury (as Hg) mg/l <0.001 0.001
29 Silver (as Ag) mg/l <0.01 -
30 Lead (as Pb) mg/l <0.01 0.05
31 Zinc (as Pb) mg/l 0.05 5/15
32 Alkalinity to phenolphthalein mg/l Nil -
33 Alkalinity to methyl orange mg/l 294 200/600
34 Iron (as Fe) mg/l 0.04 0.3/1.0
35 Total Hardness mg/l 389
300/600
36 Calcium (as Ca) mg/l 59 75/200
37 Magnesium (as Mg) mg/l 58 30/100
38 Total Nitrogen (as N) mg/l Nil -
39 Percent sodium % 35.30 -
40 Coliform organisms MPN/100ml -0- Absent
41 Sodium,(as Na) mg/l 106 -
42 Potassium (as K) mg/l 29 -
WATER QUALITY DATA Location Name : Drinking Water, Juna Kunada (Adjcent mine) Date of Sampling : 21.05.2013
Sl. No.
Parameter Unit Result
IS: 10500-1991 Norms
Desirable/ Permissible
1 pH - 8.19 6.5 – 8.5/ 6.5-8.5
2 Colour Hazen Units <5 5/25
3 Temperature oC 30.0 -
4 Turbidity NTU 4 5/10
5 Total suspended solids mg/l <2 -
6 Total dissolved solids mg/l 782 500/2000
7 Total volatile solids mg/l - -
8 Dissolved Oxygen mg/l 5.3 >3.0
9 BOD - 3 days at 27oC mg/l - -
10 COD mg/l 18 -
11 Oil & grease mg/l Nil -
12 Residual chlorine mg/l Nil 0.2 min.
13 Chloride (as CI) mg/l 68 250/1000
14 Flouride (as F) mg/l 0.12 1.0/1.5
15 Sulphate (as SO4) mg/l 233 200/400
16 Sulphide (as S) mg/l Nil -
17 Cyanide (as CN) mg/l Nil 0.05
18 Insecticides/pesticides mg/l Nil Absent
19 Phenols (as C6H5OH) mg/l <0.001 0.001/0.002
20 Chromium (as Cr) mg/l <0.01 0.05
21 Copper (as Cu) mg/l <0.01 0.05
22 Selenium (as Se) mg/l <0.01 0.01
23 Arsenic (as As) mg/l <0.01 0.05
24 Barium (as Ba) mg/l <0.01 -
25 Cadmium mg/l <0.01 0.01
26 Nickel (as Ni) mg/l <0.01 -
27 Boron (as B) mg/l <0.01 1.0/5.0
28 Mercury (as Hg) mg/l <0.001 0.001
29 Silver (as Ag) mg/l <0.01 -
30 Lead (as Pb) mg/l <0.01 0.05
31 Zinc (as Pb) mg/l 0.08 5/15
32 Alkalinity to phenolphthalein mg/l Nil -
33 Alkalinity to methyl orange mg/l 217 200/600
34 Iron (as Fe) mg/l 0.08 0.3/1.0
35 Total Hardness mg/l 301
300/600
36 Calcium (as Ca) mg/l 52 75/200
37 Magnesium (as Mg) mg/l 41 30/100
38 Total Nitrogen (as N) mg/l Nil -
39 Percent sodium % 40.76 -
40 Coliform organisms MPN/100ml -0- Absent
41 Sodium,(as Na) mg/l 104 -
42 Potassium (as K) mg/l 24 -
WATER QUALITY DATA Location name : Bore Well Water, Telwasa Village Date of Sampling : 21.05.2013
Sl. No.
Parameter Unit Result IS: 10500-1991
Norms Desirable/ Permissible
1 pH - 8.14 6.5 – 8.5/ 6.5-8.5
2 Colour Hazen Units <5 5/25
3 Temperature oC 30.5 -
4 Turbidity NTU 5 5/10
5 Total suspended solids mg/l <2 -
6 Total dissolved solids mg/l 694 500/2000
7 Total volatile solids mg/l - -
8 Dissolved Oxygen mg/l 4.8 >3.0
9 BOD - 3 days at 27oC mg/l - -
10 COD mg/l 15 -
11 Oil & grease mg/l Nil -
12 Residual chlorine mg/l Nil 0.2 min.
13 Chloride (as CI) mg/l 70 250/1000
14 Flouride (as F) mg/l 0.01 1.0/1.5
15 Sulphate (as SO4) mg/l 30 200/400
16 Sulphide (as S) mg/l Nil -
17 Cyanide (as CN) mg/l Nil 0.05
18 Insecticides/pesticides mg/l Nil Absent
19 Phenols (as C6H5OH) mg/l <0.001 0.001/0.002
20 Chromium (as Cr) mg/l <0.01 0.05
21 Copper (as Cu) mg/l <0.01 0.05
22 Selenium (as Se) mg/l <0.01 0.01
23 Arsenic (as As) mg/l <0.01 0.05
24 Barium (as Ba) mg/l <0.01 -
25 Cadmium mg/l <0.01 0.01
26 Nickel (as Ni) mg/l <0.01 -
27 Boron (as B) mg/l <0.01 1.0/5.0
28 Mercury (as Hg) mg/l <0.001 0.001
29 Silver (as Ag) mg/l <0.01 -
30 Lead (as Pb) mg/l <0.01 0.05
31 Zinc (as Pb) mg/l 0.07 5/15
32 Alkalinity to phenolphthalein mg/l Nil -
33 Alkalinity to methyl orange mg/l 152 200/600
34 Iron (as Fe) mg/l 0.06 0.3/1.0
35 Total Hardness mg/l 497
300/600
36 Calcium (as Ca) mg/l 99 75/200
37 Magnesium (as Mg) mg/l 60 30/100
38 Total Nitrogen (as N) mg/l Nil -
39 Percent sodium % 31.06 -
40 Coliform organisms MPN/100ml -0- Absent
41 Sodium,(as Na) mg/l 65 -
42 Potassium (as K) mg/l 18 -
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2013
NAME OF THE AREA : WANI NORTH Q.E. : DEC
NAME OF THE PROJECT : JUNAD OCP DATE : 19.11.13
Name of the Location ; Mine water discharge
Sl. No
Parameters Analysis Result Satandard for discharge
Part-A, Schedule VI
1 pH value 8.24 5.5 – 9.0 2 Temperature (oC) 22.3oC Te<Ts + 5oC 3 Color (Hz) 9 * 4 Odour Unobjectiona
ble Unobjectionable
5 Turbidity, NTU 71 * 6 Conductivity (µs/cm) 952 * 7 Total Suspended Solids (mg/l) 66 100 8 Oil & Greese <2 10 9 Dissolve Oxygen (mg/l) 5.3 *
10 C.O.D. (mg/l) <40 250 11 B.O.D. 3 days at 27oC 4 30 12 Total Residual Chlorine (mg/l) <0.02 1 (Max.)
13 Total Kjehldal Nitrogen(mg/l) 4.5 100 14 Free Ammonia(mg/l) <0.01 5.0 15 Arsenic(mg/l) <0.0005 0.2 16 Lead(mg/l) <0.0005 0.1 17 Hexavalent Chromium (mg/l) <0.01 0.1 18 Total Chromium(mg/l) <0.06 2 19 Copper (mg/l) <0.03 3 20 Zinc(mg/l) <0.01 5 21 Selenium (mg/l) <0.0005 0.05 22 Nickel (mg/l) <0.1 3 23 Cadmium (mg/l) <0.0005 2 24 Fluoride(mg/l) 0.32 2 25 Dissolve Phosphate (mg/l) 0.54 5 26 Sulphide (mg/l) <0.005 2 27 Iron (mg/l) <0.06 3 28 Manganese (mg/l) <0.02 2
29 Nitrate Nitrogen (mg/l)
0.4 10
* Limits not specified
Summary At all locations, Oil and grease, phenolic compounds, cyanides, sulphides and insecticides are found to be absent and all heavy metal values except Iron and Zinc are found to be below the detectable limit. In general, the water quality at all eight locations are found to be well within the prescribed norms of GSR: 422E, IS: 10500 – 1991(permissible) and IS: 2296 - 1982.
3.8 HYDROGEOLOGY OF JUNAD DEEP OC MINE
Aquifers:
The area in and around the Junad block is mostly covered by Kamthi and
Alluvium / detrital mantle which are concealed under soil layer of limited
thickness. Whereas the area situated in the east of the river is covered by
Kamthis and Talchirs under soil layer. Generally sand / sandstone horizons serve
as aquifer zones whereas shale and clay beds act as aquicludes. Groundwater
occurs below the water table withinthe intergranular pore spaces of semi-
consolidated sandstone and also in secondary porous structures associated with
them.
Groundwater exists under both confined and unconfined conditions in the area.
Unconfined aquifer generally extends up to a depth of 25 m below ground level
(bgl) and occurs in alluvium / detrital mantle and Kamthis. Whereas confined /
semi-confined aquifer is encountered at relatively greater depths in Kamthi and
Barakarformations and is harnessed by shallow / deep tube wells. The types of
aquifers are given in the following table.
Sl.
No. Type of aquifer
Depth
range
(m)
Core zone Buffer zone
1.
Unconfined
0 - 25
Alluvium and
Kamthis
Alluvium, Kamthis
and weathered
VindhyansTalchirs.
2.
Semiconfined/
confined
Beyond
25 to
200
Sandstone
horizons in
Kamthi and
Barakars
Kamthis/Barakars,
sandstones/lime
stones of Vindhyans
and sandstone in
Talchirs.
Ground water levels:
The depth to water table in unconfined aquifer is being monitored four times in
a year from May’04 located in the core and the buffer zone of Junad Deep
Extn. OCM area. The average water levels in the wells measured from the area
in and around Junad Deep Extn OC area are given below.
Pre monsoon period Core Zone 14.00 to 17.80
buffer zone 3.90 to 12.65
Post monsoon Core Zone 12.50 to 15.25
buffer zone 1.50 to 8.85
The water level fluctuation between the two extreme seasons of pre monsoon
and post monsoon period for the year 2010 and 2011 varies from 0.65 to 5.60 m
with an average fluctuation of 3.4 m in Kamthis and Barakar formation and
about 7.0 m in Talchir formation
Water level trend:
Hydrographs of two permanent observation wells fixed by CMPDI, Regional
Institute-IV are presented in 3.3.1& 3.3.2 to assess the water level trends from
May’04 to Jan’12.
The water level trend of well No (M-33) situated in the core zone (village
Chargaon) of Junad Deep Extn OC mine and about 1 km N-W of existingJunad
Deep OCM indicate no impact on water table as shown in the following figure.
.
0
2
4
6
8
10
12
14
16
18
20
HYDROGRAPH OF OB WELL (No M-33) AT VILLAGE Chargaon , IN MAJRI AREA
A rising trend both in post and pre-monsoon water levels has also been
observed at the station Borgaon (WN-9A) situated in buffer zone of Junad Deep
Extn (about 3 km south from the project area) it also indicate that there is no
impact on ground water level as shown in figure below.
0
5
10
15
20
25
HYDROGRAPH OF OB WELL (No WN-9A) AT VILLAGE BORGAON IN BUFFER ZONE OF
JUNAD DEEP EXTN. OCM
The water table elevation ranges from 174 to 200 m above MSL in pre-monsoon
season (CGWB report). The water table in general has a configuration similar to
that of topography but with reduced relief. The direction of groundwater flow in
the water table aquifer is towards the major river Wardha i.e. east and south-
easterly in the area west of the river and west and south-westerly in the east of
the river. Moderate to low hydraulic gradient indicates moderate hydraulic
conductivity of formations. Normally groundwater flows in from recharge zone to
discharge area. The drainage pattern and effluent nature of the Wardhariver
corroborates the flow direction of ground water. It was reported that the dug
wells tapping the unconfined aquifer are with poor to moderate yield. The water
levels in the core zone Junad Deep Extn OC are at deeper level due to
difference of relief between the surface and the base flow of river. The tube
wells located in the core zone of Junad Deep Extn area show water levels from
16 to 17m bgl.
General aquifer parameters-
No detailed hydrogeological investigations have been carried out at Junad
Deep Extn OC mine area. However, the aquifer parameters evaluated by
CMPDI in Wardha Valley Coalfield and Baranj block (nearest to study area) in
particular have been considered and attributed for the study area. The
projected hydraulic parameters of the aquifers in Kamthi&Barakar formations
are as follows:
Hydraulic conductivity: Kamthis - 5.0 m/day
Barakar - 2.0 m/day
Storage coefficient - 7.7 x 10-2 to 9.8 x 10-4
Specific yield : Alluvium(clayey) - 6 %
Kamthis (sandst.) - 4 %
Talchir (sandy sh.) - 2 %
The tubewells constructed in Gondwanas and also borewells tapping different
aquifers/formations in and around Junad Deep Extn OC cumulatively have
registered moderate yield ranging from 2 LPS to 5 LPS. However, the borewells
tapping Talchirs in general recorded low yield varying from negligible to 3.0 LPS
with some exceptions of moderate yield due to secondary porosity and
favourable physical settings. By judicious judgment of these facts and review of
formation logs, the above parameters have been arrived from the wide range
of regional values.
GROUND WATER RESOURCES IN THE AREA
Ground Water Recharge
Precipitation is the main source for groundwater recharge in the area. The
average annual rainfall of the area is around 1150 mm. The quantity of rain
water falling over the study area of 314 Sq.km (10 km radius) is 361.10 million
cubic meters (MCM). The quantum of groundwater recharge (recoverable
reserve) depends on various factors viz. nature of soil cover, geology,
topography, vegetation, intensity and duration of rainfall etc. As per the
Groundwater Estimation Committee, Govt. of India, the rainfall infiltration factor
for Alluvium/Kamthis and Talchirs is around 13% and 4% respectively. Major part
of the area (about 77%) is covered by Kamthis and alluvium. Accordingly,
ground water recharge in Alluvium, Kamthis and Talchir formations has been
worked out to be 41.59 MCM as given below.
Ground water recharge from other sources is negligible since canals;
ponds/dams and other water conservation structures are not available in the
area. Further, negligible area (110 ha only) is under irrigation. However, the
recharge from return waters from irrigation and mine water pumping has been
worked out to be around 0.11 MCM and 1.78 MCM respectively which is equal
to 1.89 MCM. Thus the gross annual recharge of water comes to 41.59 MCM out
of which about 10% (4.16 MCM) goes as the natural discharge to streams / rivers
and other losses thereby net ground water availability works out to 37.43 MCM.
a) Recharge from rainfall : 39.70MCM
i)Alluvium / Kamthis (244 Sq.Km.) - 36.48 MCM
ii) Talchirsarea (70 Sq.Km)) - 3.22 MCM
b) Recharge from other sources : 1.89MCM
i) Irrigation return flow - 0.11 MCM
ii) Return flow from mines effluent - 1.78 MCM.
c) Gross groundwater recharge (a+b) : 41.59 MCM
Groundwater draft:
The groundwater withdrawal is generally for domestic, industry and irrigation
requirement and is quantified as under in Table-4.2.0.1.
Water requirement for domestic and irrigation purpose.
Sl No. Purpose No./Area Water
consumption
per capita
Total qty. of withdrawal
(MCM)
1.
a) Domestic
(Human Population)
60738
Nos.
70 Lit/day
1.55
b) Domestic (Animals) 34540 Nos
20 Lit/day
0.25
2.
Irrigation (for 120
days)
110ha.
40000
Lit/ha/day
0.53*
3 Mine discharge 10nos combined 8.90
Total 11.23
Ground water withdrawal is mostly for domestic use since negligible area (110
ha only) is under irrigation.
In addition to the above, groundwater is being pump out by the existing coal
mines in the on west and east of river Wardha to the tune of 8.9 MCM.
Groundwater balance :
i) Gross groundwater recharge : 41.59 MCM
ii) Natural discharge to drains & other
losses (Approx.10 % of item (i) ) : 4.16 MCM
iii) Net annual groundwater availability : 37.43 MCM
iv) Allocation/ projection upto next
25 years for domestic & industrial use : 2.30 MCM
v) Annual groundwater draft for all uses : 11.23 MCM
vi) Groundwater balance (Item iii-iv & v) : 23.90 MCM
Level/Stage of Ground Water Development-
It is seen from the figures of net annual ground water availability and gross
annual ground water draft (11.23 MCM) that surplus ground water to the tune of
23.90 MCM is available for future utilization and development. Thus the present
stage of ground water development in and around the project has been
around 30% which can be categorized as safe area.
As per GSDA and CGWB report of Yavatmal and Chandrapur districts of
Maharashtra, the stage of ground water development in Bhadravati and
WaniTahsilin which Junad Deep Extn Project and its buffer zone lie is 5.95% and
10 % respectively and classified as safe category.
GROUND WATER BALANCE OF JUNAD DEEP EXTN.OCM
(All values in MCM)
QUANTITY OF WATER FALLING OVER
THE AREA OF 314 sq.km. FROM RAINFALL
OF 1.15 m, Total = 361.1 MCM
Actual Evapotranspiration
Surface run-off
RAINFALL RECHARGE
39.70
RECHARGE FROM OTHER
SOURCES 1.89
Infiltration
GROSS RECHARGE
41.59
Alluvium/Kamthi-13% and Talchirs-4%
NET ANNUAL GROUND
WATER AVAILABILITY 37.43
90 %NATURAL DISCHARGE AND
THERS LOSSES 4.16
PRESENT
DOMESTIC 1.80
INDUSTRIAL
NILIRRIGATION
0.53EXISTING MINE
PUMPING 8.90
GROSS DRAFT
11.23
TOTAL DRAFT
13.53
GROUND WATER BALANCE / AVAILABILITY 23.90
Allocation for domestic & industrial
water supply upto next 25 years 2.30
10 %
Addition Subtraction
Dynamic & Static resources:
The dynamic and static reserves for the core and buffer zones are estimated by
utilizing the aquifer parameters mentioned at the head of 3.3. The opencast
mine actsas large diameter well/ sink wherein all the aquifers overlying the
working seam would be converted into unconfined state and the inflow to the
mine is contributed from the saturated overburden formation i.e. multiple
aquifer system. However the unconfined aquifer is the most affected in
opencast mining area. The groundwater status in the area has been computed
as under.
The average mine depth of 130 m was considered as exploitable depth for
static reserve estimation in core zone with an area of 462 ha.
Whereas for the buffer zone with an area of 309.38Sq.km. (314.00-4.62), the floor
of unconfined aquifer (25.0 m) has been considered as extractable depth. The
pre-monsoon water level (average) is about 8.50 m bgl in the area covered by
Alluvium/Kamthi and Talchir formations and the water table fluctuation is
around 3.40 m and 7m respectively between the two extreme seasons. The
dynamic & static resources estimated for core and buffer zones are given in
Table below.
Dynamic & Static resources estimated for core and buffer zones
Zone Dynamic reserve Static reserve
Area
(Sq.km)
Wate
r level
Fluc.
(m)
Sy
Potenti
al
MCM
Area
(Sq.km)
Extracta
ble
thick. of
aquifer
below
Fluc.
zone (m)
Sy
Potenti
al
MCM
Core 4.62 5.00 0.04 0.92 4.62 120 0.04 22.18
Buffer 239.48(A) 3.40 0.04 32.57 239.48(A) 10 0.04 95.79
70(B) 7.00 0.02 9.8 70(B) 10 0.02 14.00
Total
43.29
say
43.3
131.97
A) Area covered by alluvium/Kamthis
B) Area covered by Talchirs
Thus, the dynamic and static ground water reserves as estimated are 43.3 and
131.97 respectively.
WATER QUALITY
Generally, the water quality is mostly alkaline in nature with pH value of 7.53 to
7.79 of potable quality with moderate to high concentration of total dissolved
solids values ranging from 550 mg/l to 3560 mg/l.
GROUND WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2013-14
NAME OF THE AREA : WANI NORTH AREA
Sl.
No Test Parameters
Analysis Results
Sampling Code, Location & Sample collection date
Detection
Limit
Standard ( IS : 10500 : 2012 )
WN-1
WANJRI
9.1.14
WN-5
KOLAR
12.1.14
WN-9A
BORGAON
10.1.14
Desirable
limit
Permissible limit
in the absence
of alternate
source
1 Colour ( Hz ) 1 1 3 1.0 5 15
2 Odour Agreeable Agreeable Agreeable Qualitativ
e Agreeable Agreeable
3 Turbidity (NTU) 1 3 4 1.0 1 5
4 pH Value 7.79 7.53 7.76 0.01 6.5 to 8.5 No relaxation
5 Total Hardness as CaCO3–
mg/l
276 800 276 4.0
200 600
6 Iron (as Fe) -mg/l BDL BDL BDL 0.06 0.3 No relaxation
7 Chlorides (as Cl)- mg/l 44 1150 44 2.0 250 1000
8 Residual Chlorine -mg/l
(min.) 0.03 0.01 BDL 0.02
0.2 1
9 Fluoride (as F)- mg/l 0.82 0.84 0.46 0.02 1.0 1.5
10 TDS -mg/l 550 3560 470 25 500 2000
11 Calcium (as Ca) -mg/l 65.6 208.0 72.4 1.6 75 200
12 Magnesium (as Mg) –mg/l 27.21 68.04 29.16 1.0 30 100
13 Copper as(Cu) -mg/l BDL BDL BDL 0.03 0.05 1.5
14 Manganese as (Mn)- mg/l BDL BDL BDL 0.02 0.1 0.3
15 Sulphate (as SO4) -mg/l 53.62 272.5 103.12 2.0 200 400
16 Nitrates (as NO3) - mg/l 22.78 63.78 9.16 0.3 45 No relaxation
17 Cadmium as (Cd)- mg/l BDL BDL BDL 0.005 0.003 No relaxation
18 Selenium as (Se) -mg/l BDL BDL BDL 0.005 0.01 No relaxation
19 Arsenic as (As) -mg/l BDL BDL BDL 0.0005 0.01 0.05
20 Lead as (Pb) -mg/l BDL BDL BDL 0.005 0.01 No relaxation
21 Zinc as (Zn) -mg/l BDL 1.1151 BDL 0.01 5 15
22 Chromium as (Cr +6) -mg/l 0.002 0.004 0.005 0.01 0.05 No relaxation
23 Aluminum as (Al)- mg/l BDL BDL BDL 0.008 0.03 0.2
24 Boron as (B) -mg/l BDL BDL BDL 0.2 0.5 1.0
25 Alkalinity -mg/l 144 124 116 4 200 600
26 Conductivity -µs/cm 850 5.48ms 721 - - -
MINE DRAINAGE/ PUMPING
The entire quarriable area is covered by Kamthis varying in thickness from about
10.0 m to 25.0 m which is overlained by soil/alluvium having thickness of 4.55 m
to 7.60 m.. The semiconsolidatedGondwanas are mostly stratified formations
underlying the alluvium/soil. The permeable beds (Sandstone horizons) act as
individual hydrogeological units and develop multi-aquifer system by the
intercalation/interfringing of shale beds. As such under these circumstances, the
groundwater flow/velocity along the bedding planes is higher than across the
plane. It is imperative that horizontal hydraulic conductivity is many folds higher
than the vertical hydraulic conductivity.
The opencast mine acts as large diameter well/sink resulted in by cutting
/extraction of different aquifer zones/formations overlying the working coal
seam. As soon as depression / pit is created due to mine cut, the initial
discharge is generally heavy due to concentration of flow to that region thereby
creating depletion/draw-down in water levels in the surrounding area and the
inflow stabilizes due to partial desaturation over the period of progressive
mining. With increase in depth of incision, the semiconfined aquifer would also
be exposed /punctured thereby the total system would be converted into water
table condition and a cone of depression would be formed by the gravity
drainage from different aquifer zones. In opencast mining, the unconfined
aquifer is the most affected and the semiconfined aquifer is least affected. The
mine effluent & influence is directly proportional to the mine area and depth.
The groundwater inflow computation has been done by utilising the above
mentioned aquifer and mine parameters. The classic Theis equation has been
modified by introducing mine expansion rate and the groundwater inflow to the
mine has been estimated to be around 3000 m3/day (1.1 MCM) at the at an
average quarry depth of 130m.
RADIUS OF MINE INFLUENCE
In the opencast mines, the different aquifers overlying the working coal seam
would be contributing groundwater to the mine by gravity drainage since they
are exposed/removed at the mine. The present mine water inflow during non
monsoon period from the Junad OCM is about 1350 m3/day. The anticipated
groundwater inflow as worked out at the average quarry depth of about 130m
would be about
3000 m3/day. As such due to this pumping, cone of depression would be
formed. The shape and extent of the cone would depend on mainly hydraulic
conductivity and specific yield of aquifers and recharge discharge boundries
and geological structures such as major faults etc. The maximum radius of
influence may expand less than 1000 m from the edge of the mine at the final
depth mine of 170m and at the end of mine age. However the average cone
of influence would be around 600m from the mine edge as determined.
Generally steep draw down cone would be formed in poor potential aquifers
thereby, the influence area would be up to smaller distance and reverse is
established in respect of aquifers with high hydraulic conductivity. The radius of
mine influence area has been estimated for Junad Deep Extn OCM based on
the above mentioned aquifer and mine parameters and works out to about
initially from 300 at the initial depth of depth of 70m to about 1000 m at the final
depth of 170m It may be appropriated to mention here that the presence of
prominent boundaries such as river/water bodies, faults and also interfringing of
sandstone and shale beds may restrict the propagation of draw down cone or
radius of mine influence.
Mine induced effect may be distinctly noticed within a distance of 200 to 500m
from the mine edge in the down-dip side and becomes milder/ insignificant
thereafter. However, the effect is limited/negligible in the up-dip side of the
incrop zone due to shallow mine depth & area and further mine development is
towards dip-side only
3.9 BASE LINE NOISE LEVEL STATUS
3.9.1 Rationale behind Sampling
To know the background ambient noise level at the proposed Junad Deep and
surrounding environment, 6 locations (one in core zone and five in buffer zone)
were identified for baseline study.
AMBIENT NOISE LEVEL MONITORING STATIONS
SI.
No. Location Name Location Code
1. Core Zone N- 1
2. Pimpri Village N- 2
3. Bargaon Village N- 3
4. Pimpalgaori Village N- 4
5. Kunad Village N- 5
6. Telwasa Village N- 6
Data presentation & analysis
The generated noise level data are given in table below.
Noise level status
Location
Noise level dB(A) Noise level
Standards Daytime Nighttime
Daytime Nighttime
Core zone 64.9 - 67.8 54.8 - 57.4 75 70
Buffer zone 43.2 - 49.1 38.8 - 41.9 55 45
Mean Leq noise levels at day time and night time are ranging from 64.9 to 67.8
dB(A) and 54.8 to 57.4 dB(A) respectively in the core zone. Mean Leq noise levels
at day time and night time are ranging from 43.2 to 49.1 dB(A) and 38.8 to 41.9
dB(A) respectively in the Buffer zone. While comparing with IS: 4954 -1986 norms
for acceptable outdoor noise levels all values are found to be well within the
prescribed limits.
Summary
While comparing with IS: 4954 -1986 norms for acceptable outdoor noise levels the
Leq values are found to be within the limits.
NOISE LEVEL STATUS
Project : Junad OCP Season : Winter `09-10
S.No. Location name Daytime Leq. Nighttime Leq.
1 Corezone(N1) 63.8 58.6
2 Chargaon village (N2) 54.2 48.6
3 Dhorwasa village (N3) 48.6 44.2
4 Navi Ukni (N4) 52.1 46.3
5 Besa Village (N5) 46.8 41.2
6 Pimpalgaon village (N6) 45.2 40.6
Base Line NOISE LEVEL DATA
Location: Pimri Village
Sl. No. Time (Hrs.)
Leq Noise Level, dB(A)
May`13 June`13
1.
Day
06-10 47.9 48.2
2. 10-14 48.1 49.5
3. 14-18 49.3 50.3
4. 18-22 46.5 48.4
Leq. Noise (Mean) 47.9 49.1
5.
Night
22-02 39.2 38.8
6. 02-06 40.5 39.0
Leq. Noise (Mean) 39.8 38.8
Location: Borgaon Village
Sl. No. Time (Hrs.) Leq Noise Level, dB(A)
MAY- 2013 JUNE- 2013
1.
Day
06-10 40.9 41.1
2. 10-14 44.3 43.8
3. 14-18 46.3 45.9
4. 18-22 41.1 43.3
Leq. (Mean) 43.2 43.5
5.
Night
22-02 40.9 39.8
6. 02-06 38.2 41.0
Leq. (Mean) 39.6 40.4
NOISE LEVEL DATA
Location: Pimpalgaon Village
Sl. No. Time (Hrs.) Leq Noise Level, dB(A)
MAY- 2013 JUNE- 2013
1.
Day
06-10 41.9 43
2. 10-14 43.9 45.7
3. 14-18 46.9 47.8
4. 18-22 44.4 45.2
Leq. (Mean) 44.3 45.4
5.
Night
22-02 42.6 40.0 6. 02-06 41.1 41.2
Leq. (Mean) 41.9 40.6
Location: Kunada Village
Sl. No. Time (Hrs.) Leq Noise Level, dB(A)
MAY- 2013 JUNE- 2013
1.
Day
06-10 42.7 43.3
2. 10-14 45.4 45.2
3. 14-18 47.2 47.1 4. 18-22 43.9 41.0 Leq. (Mean) 44.8 44.2
5.
Night
22-02 40.1 38.3
6. 02-06 41.3 39.4
Leq. (Mean) 40.7 38.9
NOISE LEVEL DATA
Location: Telwasa Village
Sl. No. Time (Hrs.) Leq Noise Level, dB(A)
MAY- 2013 JUNE- 2013
1.
Day
06-10 41.7 42.8
2. 10-14 43.7 45.5
3. 14-18 46.7 47.6
4. 18-22 44.2 45.0
Leq. (Mean) 44.1 45.2
5.
Night
22-02 42.1 39.5
6. 02-06 40.6 40.7
Leq. (Mean) 41.4 40.1
3.10 SOIL QUALITY
Rationale Behind Sampling
Soil characteristics, erosion aspects, soil fertility etc., have direct bearing on the
environment. Knowledge of soil parameters is essential for the planning and
implementation of a-forestation. Further, major mining activities affect the soil
regime of the surrounding areas directly or indirectly. Hence, it becomes important
to study the soil characteristics.
By keeping the above aspects in view, three locations are selected in the study
area. Locations are selected in such a way that different type of soils for supporting
different species of vegetation are covered. The soil quality monitoring stations are
furnished below.
Barren Land, Core zone S1
Proposed OB dump, Core zone S2
Existing OB Dump, Core zone S3
Data presentation & analysis
The soil quality data collected are given in Table below
Soil quality status
S.No. Parameters Range of
Concentration
1 pH 7.28 - 7.69
2. Organic Carbon (%) 2.1 - 3.5
3. Potassium (kg/ha) 195 - 262
4. Nitrogen (Kg/ha) 288 - 592
5. Magnesium (Kg/Ha) 319 - 436
6. Texture Class Sandy Loam
Summary
The soil quality in the project area appears to be good and would support after
suitable reclamation measures.
SOIL QUALITY DATA
Location: Barren Land, Core zone (S1) Date : 22.05.2013
Sl.
No. Parameter
Depth, cm
0-30 30-60 60-90
1 pH 7.36 7.48 7.53
2 Temperature (oC) 34.0 35.0 34.5
3 Electrical conductivity (m-mhos/cm at
20C)
156 168 173
4 Nitrogen, kg/ha 288 298 304
5 Phosphorus, kg/ha 5.3 5.6 5.7
6 Potassium, kg/ha 176 184 182
7 Calcium, kg/ha 526 584 576
8 Magnesium, kg/ha 418 436 422
9 Organic matter (%) 2.1 2.3 2.2
10 Grain size distribution
Sand
Clay
Silt
13
71
16
12
73
15
11
77
12
11 Sodium Absorption Ratio (SAR) 0.13 0.14 0.12
12 Natural Moisture content (%) 3.2 3.7 3.6
13 Field Capacity (%) - 4.2 -
14 Wilting Co-efficient (%) - 1.20 -
15 Available Water Storage Capacity (%) - 4.8 -
16 Bulk Density (gms /cc) 1.22 1.24 1.25
17 Cation exchange Capacity (cm/hr) 2.38 2.42 2.39
18 Infiltration rate (cm/hr) - 2.9 -
SOIL QUALITY DATA
Location : Proposed OB dump, Core zone (S2) Date: 22.05.2013
Sl.
No. Parameter
Depth, cm
0-30 30-60 60-90
1 pH 7.28 7.32 7.43
2 Temperature (oC) 33.5 34.0 34.5
3 Electrical conductivity (m-mhos/cm at
20C)
356 372 368
4 Nitrogen, kg/ha 563 576 558
5 Phosphorus, kg/ha 5.3 5.9 5.1
6 Potassium, kg/ha 236 262 244
7 Calcium, kg/ha 726 742 716
8 Magnesium, kg/ha 326 342 319
9 Organic matter (%) 3.2 3.5 3.1
10 Grain size distribution
Sand
Clay
Silt
23
54
23
19
51
30
15
50
35
11 Sodium Absorption Ratio (SAR) 2.3 2.7 2.4
12 Natural Moisture content (%) 3.0 3.2 3.1
13 Field Capacity (%) - 7.4 -
14 Wilting Co-efficient (%) - 1.4 -
15 Available Water Storage Capacity (%) - 4.7 -
16 Bulk Density (gms /cc) 1.26 1.29 1.27
17 Cation exchange Capacity (cm/hr) 1.32 1.35 1.32
18 Infiltration rate (cm/hr) - 7.3 -
SOIL QUALITY DATA
Location : Existing OB Dump, Core Zone (S3) Date: 22.05.2013
Sl.
No. Parameter
Depth, cm
0-30 30-60 60-90
1. pH 7.58 7.69 7.58
2. Temperature (oC) 32.5 32.0 32.0
3. Electrical conductivity (m-mhos/cm
at 20C)
224 232 229
4. Nitrogen, kg/ha 586 592 578
5. Phosphorus, kg/ha 6.3 6.4 6.2
6. Potassium, kg/ha 195 216 214
7. Calcium, kg/ha 812 832 838
8. Magnesium, kg/ha 356 376 382
9. Organic matter (%) 3.4 3.3 3.2
10. Grain size distribution
Sand
Clay
Silt
53
36
11
48
40
12
50
35
15
11 Sodium Absorption Ratio (SAR) 2.3 2.5 2.4
12 Natural Moisture content (%) 3.7 3.9 3.8
13 Field Capacity (%) - 8.3 -
14 Wilting Co-efficient (%) - 0.7 -
15 Available Water Storage Capacity (%)
- 6.3 -
16 Bulk Density (gms /cc) 1.26 1.28 1.27
17 Cation exchange Capacity (cm/hr) 1.32 1.35 1.33
18 Infiltration rate (cm/hr) - 7.6 -
3.11 Flora & Fauna
A. INTRODUCTION
Topographically the areas are encompassed by undulating terrain of flat ridges
with fragments of natural vegetation, which is characterized by tropical dry
deciduous forest type. Mean annual temperatures are recorded between 250c
to 400c. Average annual precipitation recorded from 800 to1200mm mostly
during south west monsoon period. Generally the soils are sandy loam but
predominantly sandy brown at slopes of hilly terrain.
B. OBJECTIVE(S):
To generate baseline data on flora and fauna in core and buffer zone of the
project.
To assess environmental impacts and potential damages to terrestrial flora,
fauna and aquatic bodies
To suggest environment mitigation measures and conservation plan for the
biodiversity, of the core and buffer zones.
C. METHODOLOGY:
A natural eco system is a structural and functional unit of nature. It has
components, which exists in harmony and survives by inter dependents. Eco
systems have self sustaining ability and control the numbers of organisms at any
level by cybernetic rule. The effects of these are – that an eco system does not
become imbalance.
Primary survey was conducted to:
Walk through the areas to assess the biological resources which
include plants & animals.
Study of fauna, and
Collection of ethno botanical data
The data on flora & fauna was collected based on field survey in the core and
buffer zone (10 KM radius) and from local offices of forest department. The
results of the study are given in Tables below separately for Core & Buffer Zone
for flora & fauna.
FLORA OF CORE ZONE
Flora Local Name Botanical Name Family
Agricultural crops
Cereals Makka (Maize) Zea mays Poaceae
Jawas Linum usitatissimum Linaceae
Pulses Tuar Cajanus cajan Fabaceae
Mung Phaseolus mungo Fabaceae
Commercial crops / Cash Crops
Vegetables
Aloo (Sweet
Potato) Ipomoea batatas Convolvulaceae
Onion/ Kanda Allium cepa -
Baigan Solanum melongena Solanaceae
Tamator (Tomato) Lycopersicum
esculentum Solanaceae
Bean Lablab purpureus Leguminosae
Band Gobi
(Cobbage) Brassica spp. Cruciferae
Bhindi Abelmoschus esculentus Malvaceae
Pumpkin Cucurbeta moschata Cucurbetaceae
Karela Momordica charantia Cucurbetaceae
Oil yielding
plants Sarson (Mustard) Brassica compestris Brassicaceae
Cash Crops Arandi Ricinus communis Euphorbiaceae
Kappas Gossypium hirsutum Malvaceae
Spices
Dhaniya Coriandrum sativum Umbelliferae
Lahsun (Garlic) Allium stivum Liliaceae
Mirchi Capsicum annum Solanaceae
Haldi (Turmeric) Curcuma domestica Zinziberaceae
Fruits
Jam (Guava) Psidium guajava Myrataceae
Bor Ziziphus mauritiana Rhamnaceae
Jackfruit (Kathal) Artrocarpus hetarophylla Moraceae
Bel Aegl marmalas Rutaaceae
Jambhul/Jamun Syzygium cumini Myrtaceae
Amba Magnifera indica Anacardiaceae
Lemon Citrus Lemon Rutaceae
Sitaphal Annona squamosa Annonaceae
Plantation
Planted by
WCL
Ashok Sarracca indica -
Neem Azadirachta indica Meliaceae
Karanj Pongamia pinnata Fabaceae
Babul Acacia nilotica Fabaceae
Flora Local Name Botanical Name Family
Natural vegetation / Forest type
Herbs
Tulsi Ocimum sancturm Lamiaceae
Bhui neem Andrographis
paniculata
Acanthaceae
Gajar gawat Parthenium
hysterophorus
Compositeae
Dhudhi Euphorbia hirta Euphorbiaceae
Shrubs
Katumbar Ficus hispida Moraceae
Arandi Ricinus communis Euphorbiaceae
Bhor Ziziphus jujuba Rhamnaceae
Trees
Sagwan Tectona grandis Verbenaceae
Amba Magnifera indica Anacardiaceae
Sisam Dalbergia sissoo Fabaceae
Karanj Pongamia pinnata Fabaceae
Peepal Ficus religiosa Moraceae
Maharukh Ailanthus excelsa Simarubiaceae
Ashok Sarracca indica -
Neem Azadirachta indica Meliaceae
Arjun Terminalia arjuna Combretaceae
Endangered
species Nil Nil Nil
Endemic
species Nil Nil Nil
FLORA OF BUFFER ZONE
Flora Local Name Botanical Name Family
Agricultural crops
Cereals
Dhan (Paddy) Oryza sativa Poaceae
Makka (Maize) Zea mays Poaceae
Jewas Linum usitatissimum Poaceae
Ragi (Mundua) Eleusine coracana Poaceae
Pulses
Urad (Black Gram) Vigna mungo Fabaceae
Chana Cicer arietinum Fabaceae
Tuar (Red Gram) Cajanus cajan Fabaceae
Kulthi (Horse Gram) Dilichos biflorus Fabaceae
Mung (Green
Gram)
Vigna radiata Fabaceae
Commercial crops
Vegetables
Baigan Solanum melongena Solanaceae
Aloo (Sweet
Potato) Ipomoea batatas Convolvulaceae
Kanda (Onion) Allium cepa
Tamator (Tomato) Lycopersicum
esculentum Solanaceae
Bean Lablab purpureus Leguminosae
Band Gobi
(Cobbage) Brassica spp. Cruciferae
Bhindi Abelmoschus
esculentus Malvaceae
Jhinga Luffa acutangula Cucurbetaceae
Karela Momordica charantia Cucurbetaceae
Kohra Benincasa hispida Cucurbetaceae
Kundri Coccinia grandis Cucurbetaceae
Kaddu Hibiscus esculentus Malvaceae
Nenua Luffa cylindrica Cucurbetaceae
Kheera Cucumis stiva Cucurbetaceae
Kheera Cucrbaltus sativus Cucurbetaceae
Phool Gobi B. oleracea var, botrytis Cruciferae
Muli Raphanus sativus Cruciferae
Oil yielding
plants
Sarson (Mustard) Brassica compestris Brassicaceae
Arandi Ricinus communis Euphorbiaceae
Soyabean Glucine max Fabaceae
Cash Crops Soyabean Glucine max Fabaceae
Kappas Gossypium hirsutum Malvaceae
Spices
Mirch (Capsicum) Capsicum species Solanaceae
Dhaniya Coriandrum sativum Apiaceae
Lahsun (Garlic) Allium stivum Alliaceae
Haldi (Turmeric) Curcuma domestica Zingiberaceae
Adrak (Ginger) Zingiber officinale Zingiberaceae
Fruits Aam Magnifera indica Anacardiaceae
Anar Punica granatum Lythraceae
Amrud (Guava Psidium guajava Myrataceae
Jamun (Black Berry) Sysygium jambolana Myrtaceae
Kathal (Jackfruit) Articarous
heterophyllus
Moraceae
Bel Angle marmelos Rutaaceae
Papaya Carica papaya Caricaceae
Flora Local Name Botanical Name Family
Plantation
Planted by
WCL
Shisam Dalbergia sisso Leguminosae
Mango Magnifera indica Anacardiaceae
Amaltas Casia fistula Leguminosae
Kathal (Jackfruit) Articarous
heterophyllus
Moraceae
Gulmohar Delonix regia Caesalpiniaceae
Arjun Terminalia arjuna Combretaceae
Babul Acasia nilotica Momoseae
Karanj Pongamia pinnata Fabaceae
Sagwan Tectona grandis Verbenaceae
Natural vegetation / Forest type
Flora Local Name Botanical Name Family
Trees (Top
Story)
Karanj Pongamia pinnata Fabaceae
Sitaphal Annona squamosa Annonaceae
Bija Pterocarpus marsupium Leguminosae
Katang bamboo Bambusa arundinacea Graminae
Aam Mangifera indica Anacardiaceae
Bhilma Semicarpus ancardium Anacardiaceae
Mohwai
Lannea
coromandelica Anacardiaceae
Ashok Polythia longifolia -
Gulmohor Delonix regia Caesalpiniaceae
Apta Bauhinia racemosa Leguminosae
Chinch (Imli) Tamarindus indica Leguminosae
Dhawda Anogiessus latifolia Combretaceae
Ain Terminalia alata Combretaceae
Arjun/kahu T. arjuna Combretaceae
Behada T. bellarica Combretaceae
Tendu Diospyros melanoxylon Ebenaceae
Awla Phyllanthus emblica Euphorbiaceae
Palas Butea monosperma Leguminosae
Sisam Dalbergia sissoo Leguminosae
Khair A. catechu Leguminosae
Hiwar A. leucophloea Leguminosae
Babul A. nilotica Leguminosae
Sirish Albizzia lebbeck Leguminosae
Sagwan Tectona grandis Verbenaceae
Wad Ficus benghalensis Urticaceae
Neem Azadirachta indica Meliaceae
Pimpal F. religiosa Moraceae
Shevga Moringa oleifera Moringaceae
Sirish A. procera Leguminosae
Jambhul/jamun Syzygium cumini Myrtaceae
Bel Aegle marmelos Rutaceae
Kumbhi Careya arborea Myrtaceae
Limbu Citrus aurantifolia Rutaceae
Austrelian babul Acacia auriculoformis Mimosaceae
Flora Local Name Botanical Name Family
Herbs
(Lower Story)
Kukada Celosia argentia -
Aradhi Achyranthus aspera -
Amaltas Cassia fistula Leguminosae
Tarota C tora -
Kamarmodi Tridax procumbens Astraceae
Gajar gawat
Parthenium
hysterophorus Astraceae
Tulsi Ocimum basilicum Lamiaceae
Ratantulsi O.bassilicum Lamiaceae
Kala dhotra Datura metal Solanaceae
Ratrani Cestrum nocturnum Solanaceae
Gokhru Tribulus teristris Zygophyllaceae
Shrubs
(Middle Story)
Pandra kuda
Holarrhena
antidysenterica Apocynaceae
Kanher Nerium indicum -
Bharati Maytenus emarginata Celastraceae
Ratanjyoti Jatropha gossypifolia Euphorbiaceae
Katumbar Ficus hispida Moraceae
Lokhandi Ventilago denticulata Rhamnaceae
Bhor Ziziphus jujuba Rhamnaceae
Eroni Z. oenoplia Rhamnaceae
Mehndi Lowsonia immermis -
Nirgundi Vitex nigunda -
Climbers
Amar vel Cuscuta reflexa Convolvulaceae
Indrayani Citrullus calexynthis -
Jangli kundru Cephalandra indica Cucurbitaceae
Dudhi Cryptolepis buchanani Periplocaceae
Rabarachavel
Cryptostegia
grandiflora Asclepiadaceae
Arasphari Olax scandens Periplocaceae
Grasses
Doob Cynodon dactylum Gramineae
Bans/Bamboo Dendrocalamus strictus Gramineae
Sabai Eulaliopsis binata Gramineae
Munj Sacchanum munja Gramineae
Jharoo grass Thysanolaena agrostis Gramineae
Chor kanta Chrysopogon
auciculatus
Gramineae
Endangered
species Nil Nil
Endemic
species Nil Nil
FAUNA OF CORE ZONE
Fauna Common Name Zoological Name
LISTED UNDER WILDLIFE PROTECTION ACT,1972
Terrestrial Fauna
Schedule-I Nil -
Schedule-II Nil -
Schedule-III Nil -
Sch.-II, Part II, Sec. 2C Jungle cat Felis chaus
Schedule-IV, Section 6A Indian Grey Mongoose Herpestes edwardsi
Schedule-V, Section 6,
Section 3
Indian Mouse Bandicota bengalensis
House rat Rattus rattus
Schedule-V, Section 3 Fulvous Fruit Bat Rousettus Leschenaulti
Amphibians & Reptiles
Schedule-II Nil Calotes verosicolor
Schedule-IV Toad Bufo melanostictus
Avi Fauna
Schedule-IV, Section 11
Bhagule Ardea purpurea
Koel Eudynamys scolopacea
Kabutar Columbia livia
House swift Apus affinis
Titavi Vanellus indicus
Bhardwaj Centropus sinesis
Pandubi Prodiceps ruficollis
Schedule-V Kavvwa Corvus splendens,
NOT LISTED UNDER WILDLIFE PROTECTION ACT,1972
Mammals / (Domestic
Animals)
Goat Capra species
Bull Bos indicus
Cow Bos indicus
Buffalo Bubalus bubalis
Birds Tota (Parrot) Pisttaculus krameri
Aquatic fauna
Marad Channa punctatus
Magur Clarias batrachus
Katla Catla catla
Invertebrates
Cockroach Blata orientalis
Madhumakkhi Apis indica
Tilchatta Blata orientails
Chinti Solpopsis Spp.
Honey bee Apis dorsata
Lahi Kerria laxxa
Birni Polistis Spp.
Jugnu Photinus Spp.
Gojar Scolopendra Spp.
ENDANGERED SPECIES Nil -
ENDEMIC SPECIES Nil -
MIGRATORY SPECIES Nil -
FAUNA OF BUFFER ZONE
Fauna Common Name Zoological Name
LISTED UNDER WILDLIFE PROTECTION ACT,1972
Terrestrial Fauna
Schedule-I Nil -
Schedule-II
Lomdi (Common Fox) Vulpes bengalensis
Siyar (Jackal) Vulpes vulpes
Jungle Cat Felis chaus
Common langur Presbytis chtellus
Ban suar Sus scrofa
Schedule-IV
Mongoose Herpestes edwardsi
Squirrel Funambulus pennanti
House Rat Rattus species
Mice Mus Musculas
Schedule-V, Section 3 Fulvous Fruit Bat Rousettus Leschenaulti
Amphibians & Reptiles
Schedule-II
Common Garden
Lizards
Varanus species
Cobra Naja species
Dhamon or Rat Snake Ptyas Mucosus
Schedule-IV
Tode Bufo melanostictus
Karait Bungurus Caeruleaus
Water snake Natrix piscator
Dhorwa Natrix Sp.
Avi Fauna
Schedule-IV, Section 11
House swift Apus affinis
Bhagule Ardea purpurea
Koel Eudynamys scolopacea
Kabutar Columbia livia
Titavi Vanellus indicus
Bhardwaj Centropus sinesis
Pandubi Prodiceps ruficollis
Schedule-V Common Crow Corvus splendens
NOT LISTED UNDER WILDLIFE PROTECTION ACT,1972
Mammals (Domestic
Animals)
Goat Capra species
Bull Bos indicus
Cow Bos indicus
Buffalo Bubalus bubalis
Dog Canis familaris
Sheep Capra Sp.
Pig Sus scrofa
Horse Equus Sp,
Birds (Domestic Birds) Sparrow Passer domesticus
Duck Nettopus
Coromandelianus
Fauna Common Name Zoological Name
Amphibian
Frog Rana Tigerina
Tree frog Hyle Spp.
Flying frog Rhacopnonis Spp.
Aquatic fauna (Fishes)
Rohu Labco rohita
Catla Cyprindiae
Garai Channa punctatus
Mangoor Clarias batrachus
Pothia Punctius ticta
Bokwa Eutropichttys baacha
Zebra fish Danio rerio
Invertebrates
Birni Polistis Spp.
Grosshopper Hierogylphus banian
Tidha Schistocerca gregaria
Moth Antheria mylita
Black Bee Apis dorsata
Bee Apis indica
Stem Borer Chilo auricilia
Cockroach Blata orientalis
Madhumakkhi Apis indica
Chinti Solpopsis Spp.
Lahi Kerria laxxa
Jugnu Photinus Spp.
Gojar Scolopendra Spp.
Aquatic Insect Daphnia Nepa Spp.
Prawn Chaetogaster
ENDANGERED SPECIES Nil -
ENDEMIC SPECIES Nil -
MIGRATORY SPECIES Tree Pipit Anthus Trivialis
Cuckoo Cuculus Micropterus
OBSERVATION
The floristic component of the study area does not include any rare or
endangered species. Thus, impact on rare and endangered species of flora is
not envisaged.
The proposed project does not envisage destruction or displacement of any
fauna species. Thus, indirect impact on fauna due to loss of habitat is not
foreseen.
However, it is reported that animals like Langur, Jangli Billi, Jackal, etc. enter
into the agricultural field of the villages and needs conservation.
Common Species of Flora & Fauna observed in the study area are as follows:
Flora Local Name
Agricultural crops
Cereals Dhan , Makka
Pulses Urad (Black Gram), Chhana, Tuar (Red gram),
Kulthi (Horse Gram), Mung (Green Gram)
Commercial crops
Vegetables Baigan, Tamator, Cobbage, Bean, Jhinga,
Kohra, Bhindi
Oil yielding plants Sarson, Arandi etc
Spices Mirch, Dhania, Adrak, Lahsun etc.
Fruits Aam, Amrudh, Jamun, Papita, Kathal, Ber,
Orange etc
Cash crops Kappas, Soyabean
Natural vegetation / forest type
Herbs Amaltas, Dhudhi, Rantulsi, Ratrani etc
Shrubs Ratanjoyati, Katumber, Lokhandi, Bhor etc
Trees Aam, Sitaphal, Neem,Peepal, Mahua etc
Grasses Baans, Doob,etc
SL.
NO. COMMON NAME SCHEDULE
01. House Rat V
02. Jackal II
03. Jungle Cat II
04. Fulvous Fruit Bat V
05. Common crow V
06. Common Langur II
Results of study
From the above study, it is observed that there is no endangered and endemic
species found in the area as per Red Book of Botanical Survey and Zoological
survey of India as per Wild Life (Protection) Act 1972 and its subsequent
amendments.
The main agricultural crops of the village area under study is Rice and Maize.
The major commercial crop grown here during the summer season is Lady
Finger, Brinjal, Chilies, Onion, Beans, Karela etc. The forest of the area is mainly
southern Tropical Dry Deciduous Forest. Yet, plantation has also been done by
M/s WCL and Forest Department and is categorized as B-Type forest. The main
constituents of forest are Palash, Sisam, Bel, Babul, Mango, Mahua, Jamun,
Eucaliputas, Kathal, Neem etc.
Trees of terminalla species were found, besides, Palash, Sisam, Teak, Sal, Mango,
Ashok, Kathal, Gulmohar etc. are planted and maintained by M/s WCL and
Forest Department.
The grass land vegetation mainly covered by Moraba, Chor kanta, Dubh, Munj
species, Bans/Bamboo etc.
As there is B-Type forest, hence major fauna elements were absent in this area.
Mainly Fox, Newla, Jungle Cat are observed/reported. No endemic and
endangered species of fauna elements has been reported as per Wild Life
(Protection) Act 1972 and its subsequent amendments. No migratory species
and there path/corridor have been found/reported in the area.
CHAPTER- IV
ANTICIPATED ENVIRONMENTAL IMPACTS
&
MITIGATION MEASURES 4.1 AIR POLLUTION IMPACT ASSESSMENT
The impact assessment has been carried out dealing with the following
points:
(a) Phase-wise inventory of air pollution emission sources
(b) Impact assessment
a. Phase-wise inventory of air pollution emission sources
The pollution sources are obvious and to assess the impact, the project life
is divided into following time frames:
Operation phase
Post-operational stage
The activities associated with these time frames and having impact on the
ambient air quality along with the pollutants are enumerated in the
following sections:
Operational phase
During this phase, activities necessary for mining of coal, its handling and
transport are taken up. Such activities having impact on ambient air
quality are detailed below:
(i) Drilling : Dust
(ii) Blasting of coal and
overburden
: Dust and noxious gases
(iii) Handling of coal : Dust and noxious gases
(iv) Overburden handling : Dust and noxious gases
(v) Dump formation (internal) : Dust and exhaust fumes from
dumpers and dust till the
development of green cover
(vi) Movement of vehicles : Dust and noxious fumes
Post-operational stage
During this stage of the project, the activities related to the closure of
mine are to be carried out. Preparation of mine closure plan shall be
carried out during the period four to five years before the closure of the
mine. Some of the activities for the closure are:
Modifications in physical and biological reclamation of backfilled area
Salvaging and shifting operation of HEMMs and other equipment
Clearing of coal and other materials, restoration of infrastructure
area & colony area to the extent possible and necessary if not useful
for other projects
Management of hydrology and hydrogeology.
Redeployment of workforce, etc.
Arrangement & implementation of post-operation monitoring mainly
keeping watch, vigil, etc.
The activities having impact on the ambient air quality are enumerated
below:
(i) Movement of HEMMs for physical
reclamation of backfilled area
: Dust and obnoxious
fumes
(ii) Movement of vehicles for shifting and
salvaging operation of HEMMs and other
equipment
: Dust and obnoxious
fumes
(iii) Movement of vehicles for clearing of coal
and other materials
: Dust and obnoxious
gases
b. Impact assessment
The mining and its related activities create ambient air pollution. The
impact of mining on ambient air quality are highlighted in the following
paragraphs:
(a) The ambient air quality is influenced due to the presence of RPM, SPM,
SO2, NOx, etc., which are generated due to various activities like
drilling, blasting and handling related to the project. Further, the
ambient air quality is affected marginally to a varying degree due to
the mining activities of other nearby opencast and underground coal
mines of the same coalfield. The concentration of pollutants may vary
depending upon the various micro-meteorological parameters and
the seasons of a year.
(b) The baseline ambient air quality has been generated at six locations
surrounding the existing Junad OC to assess the present ambient air
quality scenario corresponding to the pre-mining status of the
proposed Deep Extension OC project. The details of baseline data
have been given in previous chapter. All the monitored parameters
are well within the permissible limit. Thus it can be concluded that
although the mine under consideration as well as the neighbouring
mines are operating since long but ambient air quality in the
surrounding area has not been affected adversely.
Now, with the proposed expansion in production capacity in the
existing OC project, there is likelihood of addition of pollution to the
existing concentration level of different attributes of ambient air. Efforts
will be made by implementation of proper abatement measures so as
to maintain the sinking capacity of ambient air to absorb the
additional load, if any, thereby maintaining the quality of ambient air
to the pre – mining level to the extent possible.
(c) Further, as per TOR received from MOEF, AAQ Prediction modeling has
been done with FDM and it has been found that there will be
insignificant increase in the level of pollutants as such there will be
negligible impact on the Ambient air quality due to proposed
expansion of the mine.
Existing Ambient Air Quality Monitoring
The ambient air quality monitoring is being carried out on regular basis as per
the Env (Protection) Amendment Rule, 2000 so as to ascertain the likely load of
various air pollutants and thereby suitably modifying the various control
measures.
Hence , it is expected that pollution load to be generated due to increased
production at Junad OC will be well within the permissible limit as the existing
air pollution control measures will be further strengthened with close monitoring
for efficient & effective implementation of the pollution control measures to
make the operation eco-friendly and it is expected that ambient air quality will
have no harmful effect on human being, flora and fauna, soil quality, surface
structures and aesthetic value of the surrounding environment.
4.2 AIR POLLUTION CONTROL MEASURES
Since Junad OC is an operating mine, the environmental monitoring data
generation is being done at four locations on regular basis as per the Env
(Protection) Amendment Rule published Vide Gazette of dated 25.9.2000. In
addition to data generation, following abatement measures have also been
taken in order to suppress the dust and noxious gases generation to the
maximum possible extent.
4.2.1 Drilling Operations
In order to reduce dust generated by drilling operation wet drilling is done.
4.2.2 Blasting Operation
In order to minimize the generation of dust during blasting, the following
measures are adopted:
(a) Blast holes are properly placed/spaced/positioned.
(b) Blast is properly designed in respect of hole-spacing. Hole placing and
blast design are looked into as a fresh case every time, by a competent
Blasting Officer who takes into consideration the actual geo-mining
conditions of the site.
(c) Blasting is being done between shifts or during the rest interval when the
minimum number of persons is present around the blast area. In order to
quickly disperse the dust generated in blasting operations, blasting is
avoided when there is wind. Blasting is avoided in the mornings and during
cloudy situations.
(d) Adaptation of Controlled Blasting Technique as permitted by DGMS.
4.2.3 Loading & Transport
Movement of vehicles and HEMM on haul roads, particularly when they are un -
metalled, is another major source of dust generation. To minimize dust
generation due to this operation, the following abatement measures will be
taken.
(a) All long-life haul roads and service roads are properly constructed and
metalled. Unmetalled roads are being kept free of ruts, potholes etc.
(b) All haul-roads are regularly sprayed with water. Water sprinklers are
regularly used in the project.
(c) Overloading of vehicles are avoided.
(d) Covering of loaded trucks by tarpauline.
(e) Regular cleaning of transportation roads.
(f) Adequate green belt have been developed all along the coal
transportation road on both sides.
All the above-mentioned control measures will be continued during the
balance life of the project.
4.2.4 OB Dumps
On the dump slopes and top surface, plantation of grass and trees will be done
in phases and the details are as follows ;- Stage-wise Cumulative Plantation
year Green Belt
External Dump(OB +
Top Soil) Backfilled area
Others (undisturbed
area/etc.) Total
1 Area (ha)
No. of trees
Area (ha)
No. of trees
Area (ha)
No. of
trees
Area (ha)
No. of trees
Area (ha)
No. of trees
2 1st year
0 0 0 0 0 0 0 0 0 0
3 3rd year
0 0 0 0 0 0 0 0 0 0
4 5th year
0 0 25 62.5 0 0 10 25 35 87.5
year Green Belt
External Dump(OB +
Top Soil) Backfilled area
Others (undisturbed
area/etc.) Total
5 End of mine life
0 0 110 275 0 0 145.93 364.825 255.93 1
6 Post mining
0 0 175 437.50 0 0 157.93 394.825 332.93 832.33
2.5 Coal Handling Plant
Lot of dust is generated in coal handling plant during operations like coal
crushing, transfer and conveying. Following abatement measures are adopted
for Coal Handling Plant.
i) Enclosure of the crusher house where maximum dust is generated. Also
installation of dust suppression system in the crusher house (specially
above the hopper in such a way that air borne dust is suppressed without
adding much water to the coal).
ii) Minimising the height of coal-fall at transfer points (to reduce dust
formation) and, if necessary, installing dust suppression measures.
iii) Enclosure of the belt conveyor to reduce the generation of dust due to
blowing wind.
iv) Creation of a green belt on both sides of belt conveyors and around coal
stocks and the CHP building.
Noxious gasses are emitted through exhaust fumes during the operation of
diesel / petrol operated equipment. In order to reduce such emission, regular
maintenance of the diesel / petrol operated vehicles will also be carried out so
that the emissions from these vehicles are under control. However, wherever, the
condition will permit, petrol / diesel operated HEMM will be replaced by
electrically operated ones.
Water sprinkling on coal stock/face, blanketing of exposed surface will be
carried out to avoid spontaneous heating and minimize air pollution.
4.2.7 Plantation to Check Air Pollution
Plantation has been under taken in the mine area as mitigatives measure
against air pollution, noise pollution and to increase the aesthetic value. The
plantation will be developed at suitable places like overburden dump, along
the road sides, unused land etc to arrest as well as reduce the rate of dispersion
of dust generated due to various mining operations viz. quarrying, coal and OB
transportation, OB dumping, CHP operation. Species to be planted
(recommended by Forest Department) in the area are as follow.
a) Ornamental trees viz Gulmohar, Eucalyptus and fruit trees like Mango, Guava,
Jamun and medicinal plant like Neem etc. will be planted in colony area,
schools, dispensary, community buildings, play ground etc.
b) Ornamental shady trees will be planted e.g. around colony along roads, haul
roads, and around industrial buildings etc.
c) The fast growing varieties of trees like Eucalyptus act as sound barriers where
as ornamental shady trees e.g. Subabul, Kikar and karanj will add to the
aesthetic look of the area.
d) The Species to be planted on OB dumps etc are: Gravalia, Robusia, Punis,
Vanetis, Semal, Karanj, Babul, etc
59,325 nos. of trees have ben planted till date on embankment, vacant land & along coal transportation road.
4.3 WATER QUALITY
Impact Assessment on Water
Identification of the sources of water pollution
Likely sources of water pollution from this project along with the type of
pollutants are as follows:
(i) Sanitary (domestic) wastewater : Suspended solids and BOD.
(ii) Industrial wastewater from
workshop
: Suspended solids, oil & grease;
(iii) Wastewater from mine : Suspended solids of coal, clay
and oil;
(iv) Surface run-off passing through
coal stockpiles
: Suspended solids;
(v) Storm water from leasehold
area and built-up area
: Suspended solids.
Impact assessment
Mining and its related activities may create water quality problems. The
impact of mining at the project on both surface and ground water
sources has been assessed and given below:
(a) Surface water sources
Deterioration of water quality and pollution of water bodies due to
discharge of mine effluent, if not treated. Change in relief pattern
due to mining may cause flooding, siltation, choking and pollution.
Mitigatory measures would involve provision of (i) garland drains on
periphery to prevent surface run-off from entering into the quarry ,
(ii) catch drain around the dumps for avoiding siltation and (iii)
sedimentation ponds for reducing the pollution of surface water
bodies.
Possible overflow of water from nearby rivers/nallahs must be
safeguarded by stone pitching and strengthening the embankment
along the side of the water course
In order to assess the existing quality of surface as well as ground
water quality surrounding the project site, water samples from six
locations have been collected & analysed. The details are
incorporated in the previous chapter. All the parameters are well
within the permissible limit.
The mine water discharge quality of existing opencast project is
being monitored regularly as per Env. (Protection) Amendment Rule
, 2000 . The result indicates that even in untreated condition mine
pumped out water does not contain any pollution load.
However, due care will be taken to treat the mine water discharge
by sedimentation for the proposed project. Effluents from workshop
is continue to be treated in ETP and moreover water will be mostly
recycled in Workshop & CHP. As such, possibility of adverse impact
on natural watercourses after mixing is very remote. Garland drain
around the OB dump & coal dump will be made to avoid siltation
of natural water course.
Based on the data collected at the existing coal mine, it can be concluded that
the impact due to proposed mining operation, the adverse impacts on water
both surface as well as ground water will be insignificant.
4.3.1 WATER POLLUTION CONTROL MEASURES
Salient controls measures have been taken are as follows:
i) Industrial Effluent
The wastewater from workshop and CHP, which normally remain laden with oil
and grease, suspended and dissolved solids etc. are treated in the Effluent
Treatment Plant (ETP). Clear water coming out from the treatment plant is taken
into the closed water circuit and recycled for its reuse. All parameter of ETP
waste discharge are monitored regularly as per Env. (Protection) Amendment
Rule, 2000 and found to be within permissible limits.
ii) Mine Water
Most of the suspended particles are settled in the mine sump as initial settlement
and the supernatant water is pumped out. This water is passed through
sedimentation pond on surface, before being discharged in to natural drain.
iii) Surface Run-off
Adequate numbers of vegetation will be grown on the top surface and slopes
of the dumps in order to arrest the erosion of soil and it also reduces surface run-
off, which helps averting siltation of natural watercourses.
Catch drains of suitable size have been provided around periphery of the OB
dump as well as soil dumps to arrest site and sediment flows from the respective
dump sites.
In case of OB benches in the quarry, cross drainage have been provided which
carries silt and sediments into main sump made at the floor of the seam which
will accumulate all the silts and act as first stage settling pond. The water is then
pumped out through pumps on to the surface and discharged in to surface
settling tank/sedimentation pond. The clear water from the surface
sedimentation tank is used for watering the mine area, roads and green belt
development. The catch drains mentioned above are regularly desilted and
maintained properly. In addition, garland drains have also been provided
around the periphery of the excavated area, which carries surface run off and
the drains are regularly desilted before onset of monsoon.
These drains allows accumulation of silt materials and sufficient retention time for
settling of silt materials.
The domestic sewage disposal arrangement has been provided in the township.
Regular water quality/effluent quality monitoring is also carried out so as to
ascertain the likely load of pollutants and thereby suitably modifying the control
measures.
The existing water pollution control measures can be summarized as below :-
MINE WATER :- TWO STAGE SEDIMENTATION
INITIAL SEDIMENTATION - AT MINE SUMP
(SIZE- 800mX60mX4m)
FINAL SEDIMENTATION - SEDIMENTATION POND AT
SURFACE (SIZE- 24mX8mX1.5m)
INDUSTRIAL / WORKSHOP EFFLUENT:
WORKSHOP EFFLUENT IS BEING TREATED IN
WORKSHOP ETP .
DOMESTIC EFFLUENT:
THERE IS ONE INTEGRATED DOMESTIC EFFLUENT
TREATMENT PLANT AT COMBINED TOWNSHIP(0.6MLD) AT BHALAR.
EXISTING WATER POLLUTION CONTROL MEASURES
In addition to the above, provision have also been made for augmentation/
strengthening of existing sedimentation pond as well as Workshop Effluent
Treatment Plant.
4.4 IMPACT ON HYDRO-GEOLOGICAL REGIME
The mining activity creates dis-equilibrium in environmental scenario of the area
and disturbs the groundwater conditions/regime in particular. The impact on
water regime due to mining activity can be broadly classified as under :
i) Impact on topography & soil
ii) Impact on surface water and quality
iii) Impact on groundwater & quality
A brief description/out-line on these aspects are given below :
Impact on topography & soil:
A local change in ground topography will be created at Junad Deep Extension
OC mine area due to mining operations such as open pit, embankments,
dumps of overburden and coal, diversion of nallah and roads, mine voids etc.
As a result, there would be marginal change in the drainage and surface run-
off. During these courses, soil is most susceptible for changes due to erosion,
leaching phenomena/process etc. Further the fine dust particles of coal &
overburden may adversely affect the physical & chemical characteristics of
soil.
Within the core zone area, cracks and loosening of soil would be resulted in due
to mine and associated activities such as drilling, blasting etc thereby
physical/texural changes would occur in soil/formations. This mine induced
process increases the rate of infiltration and recharge. The studies carried out in
Wardha Valley coalfield have established that rainfall-infiltration rates have
been increased by 100% (doubled) in the core zone area of opencast mines
thereby increasing the scope of groundwater recharge. So also the back filled
area may be a good media for high groundwater recharge due to high-
induced permeability. Further, the void proposed to be left out would store
substantial quantity of rain water which can be utilised for domestic &
agriculture use and also for recharging the groundwater source. It may be
appropriate to high light the fact that temporary groundwater loss/deficit
created during activemining stage would be compensated by these different
means in the post mining stage so that the initial groundwater levels are
regained to normalcy at the earliest for the utility of the area. Appropriate
reclamation measures would be adopted to normalize the ground topography
and soil as far as possible. However, overburden dumps, embankments etc. are
unavoidable structures to be left in the post mining stage.
Impact on surface water & quality :
As mentioned earlier, there would be minor change in the ground topography
and infiltration capacity/rate of soil/formation due to mining operations resulting
in some local change in drainage pattern and surface run-off in core zone. It is
established that high infiltration zone would serve as good media for high
groundwater recharge and reduces the surface run-off considerably in the core
zone. In view of this, the mine has to handle more water in the monsoon besides
the additional contribution from the surface run-off from the catchment area. As
such the surface run-off contribution to the natural drains from the mining area
would be minimum thereby some minor change is expected in hydrologic
regime of the river/nalla system.
The surface run-off from the dumps of overburden material and coal and mine
water discharge/effluent are laden with suspended particles of coal and other
associated materials. This water is collected by foot drains with stoppage
arrangement and passed through sedimentation tank/pond. This treated water
will be utilised for mine site requirement and the surplus would be utilised to
supplement the water shortage for domestic & agriculture use of villages if
required or otherwise discharged into land surface/natural drains.
Impact on groundwater & its quality:
Mining is associated with groundwater problems, particularly when it is below
water table. The impact of mining on groundwater is dependent mainly on mine
and aquifer parameters, groundwater recharge-discharge process etc. In the
opencast mining, the unconfined aquifer gets affected more whereas the
semiconfined aquifers are least affected due to continuous gravity drainage
and conventional sump pumping or advance dewatering schemes for efficient
and safe working. As such, during this exercise, basically the water level is to be
depressed/depleted below the working seam depth in which case large scale
mine water pumping can not avoided.
Consequently the mine dewatering would drain out some area around the mine
with decline in groundwater levels. However, these mine-induced effects are
temporary as increased infiltration rate at as rain water harvesting to balance
the mine dewatering. Further, the mine effluent would contaminate the other
resources of water if discharged untreated. The expected mine effluent from
Junad Deep Exn. OCM area would be no different from the exiting mine
possessing similar hydrogeological sep-up. However, water quality monitoring
would be undertaken at the stipulated intervals immediately after the mine
development starts and continued during the mine life.
Groundwater inflow and mine influence area have been estimated and the
groundwater monitoring would be undertaken as corrective measure to avoid
adverse effects. The mine discharge after passing through sedimentation pond /
tank would be discharged into land/natural drains with earthen check dam at
suitable locations so that the groundwater gets additional recharge by the
return flow. The artificial recharge by water conservation structures in mine
influence area proper may not be a viable solution because of the reason that
recharged water would drain to the mine at a faster rate due to the steep
hydraulic gradients resulted in during mining activity. As mentioned earlier the
mine impact may be for temporary period during mine life and the area would
regain the normalcy/benefits in many ways by appropriate reclamation
measures during post-mining period. However, the temporary water shortage in
the mine influence area would be supplemented from the treated mine water
discharge for both domestic & irrigation use of affected villages if any.
WATER POLLUTION CONTROL MEASURES
Salient controls measures have been taken are as follows:
i) Industrial Effluent
The waste-water from workshop and CHP, which normally remain
laden with oil and grease, suspended and dissolved solids etc. is
being treated in the Effluent Treatment Plant (ETP). Clear water
coming out from the treatment plant is taken into the closed water
circuit and recycled for its reuse. All parameter of ETP waste
discharge are being monitored regularly as per Env.(Protection)
Amendment Rule, 2000 and have been found within permissible
limits.
ii) Mine Water
Most of the suspended particles are settled in the sump and the
supernatant water is pumped out. This water is passed through
sedimentation pond, before being discharged in to natural drain .
iii) Surface Run-off
Adequate numbers of vegetation is already grown on the top
surface and slopes of the dumps in order to arrest the erosion of soil
and it also reduces surface run-off, which helps averting siltation of
natural water courses.
In Junad Extn OC mine will have garland drain along the periphery of the OB
dumps to make the surface run – off to pass through the settling lagoons before
it is either put to reuse or allowed to enter into surface water course.
In addition to above adequate sewage disposal arrangement exists in the
township.
Remedial measures to control ground water depletion
The following methodology and remedial measures have been taken to
minimize the mine induced impact on ground water levels and also adverse
effects in the area.
(i) Artificial recharge to ground water system at the periphery of the
anticipated influence area by local stagnation in low lying areas/drains
by providing low height dams/bunds or by injection of mine water
discharge, surface water through tubewells /percolation structures.
(ii) The water shortage in the villages, if any, in the influence area can be
supplemented by supply of water from outside source or from the mine
water after treatment.
(iii) Sprinkler irrigation system is recommended to support agriculture in the
mine influence area thereby water rehandling is avoided at the mine.
(iv) While reclamation of the mined area, void at the deepest portion of
the pit has to be left. This residual pit void would initially serve as
access for future expansion and subsequently it could be
backfilled.
(v) Well water monitoring in nearby villages is being carried out quarterly
as per MoEF' guidelines. No adverse remarks have so far been observed.
(vi) Regular water quality/effluent quality monitoring is being carried out
so as to ascertain the likely load of pollutants and thereby suitably
modifying the control measures. As seen from Analysis Data, the mine
pumped out water does not contain significant pollution load and the
discharge water quality even without treatment is quite satisfactory.
4.5 NOISE QUALITY
In order to assess the existing ambient noise level in the surrounding of proposed
project site corresponding to pre-mining scenario ,baseline noise level data has
been generated & details are enclosed as Annexure – III. All the values are well
within the permissible limit.
Proposed mine would be associated with following activities that may generate
noise during operation :
(a) Drilling
(b) Blasting
(c) Shovel operation
(d) Dozing
(e) Movement of dumper
(f) Operation of CHP / Workshop
The following are some of the important activities responsible for high noise level
generation, with their expected noise levels :
a. All mining activities i.e. drilling, blasting, shoveling, dozing and
dumping are associated with high noise level [about 100 dB(A)].
b. Operation of most HEMMs produce high noise level. The noise level
are in range of 80 – 100 dB(A). Noise level have been found to be
related to engine capacity.
c. Crusher – General noise level due to crusher ranges from 90 dB(A) –
105 dB(A). Some of noisy equipment produce noise whose level is
around 120 dB(A).
The average sound pressure level of some of the HEMM associated with mining
operation which are responsible for high noise level generation are as follows :
EQUIPMENT NOISE LEVEL
[dB(A)]
Dozer 98
Dumper 92
Power shovel 93
Drilling machine 96
ACCEPTABLE INDUSTRIAL NOISE LEVEL
As per Env. (Protection) Amendment Rules, 2000 the ambient air quality
standards in respect of noise in industrial , commercial , residential and silence
zones area as follows :
Sl.
No.
Category of
area
Limits [dB(A)]
Day time (6.00 AM to 10.00 PM
)
Night time (10.00 PM to 6.00 AM )
1. Industrial 75 70
2. Commercial 65 55
3. Residential 55 45
4. Silence zone 50 40
Assessment of the degree of noise to which a workplace noise is harmful, is done
by comparing the values measured at workplace to the permissible limit
adopted by statutory bodies like DGMS.
The Director General of Mines Safety vide their circular no. DG ( Tech.)/18 of
1975 has prescribed the permissible limit for noise level as 90 dB(A) , for the
workers engaged in mining occupation likely to be exposed to in an 8 hour shift
period with unprotected ear . Whereas , the following table shows the maximum
permissible noise exposure levels , as per American Standards , for the industrial
workers.
Exposure time
(Hrs./day)
Noise level
[dB(A)]
8 90
6 92
4 95
3 97
2 100
1.5 102
1 105
0.5 108
0.25 or less 115
EXPOSURE TO PULSE OR IMPACT NOISE
SHOULD NOT EXCEED 140 dB(A)
The impact of mining on ambient noise quality are highlighted in the following
paragraphs:
(a) The ambient noise quality is influenced by various activities like drilling,
blasting and material handling related to the project. Further, the ambient
noise quality is affected marginally to a varying degree due to the mining
activities of other nearby opencast and underground coal mines of the
same coalfield.
(b) The baseline ambient noise quality has been generated at six locations
surrounding the existing Junad OC to assess the present ambient noise
quality scenario corresponding to the pre-mining status of the proposed
Deep Extension OC project. The details of baseline data have been given
in previous chapter. All the monitored parameters are well within the
permissible limit.
(c) Thus it can be concluded that although the mine under consideration as
well as the neighbouring mines are operating since long but ambient
noise quality in the surrounding area has not been affected adversely.
Now, with the proposed expansion in production capacity in the existing OC
project, there is likelihood of addition of noise load to the existing concentration
level of ambient noise. Efforts will be made by implementation of proper
abatement measures so as to maintain the sinking capacity of ambient noise to
absorb the additional load, if any, thereby maintaining the quality of ambient
noise to the pre – mining level to the extent possible.
4.5.1 NOISE POLLUTION CONTROL MEASURES
Monitoring of the noise control will be carried out on regular basis as per the Env
(Protection) Amendment Rule 2000. While planning for an effective noise
attenuation measures, the concept of source, path and receiver has been
considered.
(A) Noise Control at Source
There are two areas where the noise generation can be checked at source.
(i) Proper Design
Since the generation of noise can be reduced by reducing the vibration
amplitude, the area of vibrating part and frequency of vibration will be taken
care that all loose contact between metal parts avoided.
(ii) Proper Maintenance
All machines and equipment will be properly maintained. Sound muffler system
and bearing lubricating system etc. of equipment will be kept in proper
condition.
(B) Noise Control at Receiver End
Even after adopting above measures, if desired noise level is not achieved at
receiver end, in that case, following measures are suggested:
(a) The workers exposed to high noise level are provided with earplugs.
(b) Provision of enclosed booths at the worksite to protect worker from noisy
environment.
4.6 IMPACT ON LAND
LAND USE (CORE ZONE)(contd.)
6.10 ha--
449.63 ha
NIL
443.53 ha
TOTAL
174.28 ha
NIL
174.28 ha
LAND
ALREADY
ACQUIRED
275.35 haTOTAL
NILFOREST LAND3.
6.10 haGOVT. LAND
(WASTE LAND)
2.
269.25 haAGRICULTURAL
LAND
1.
LAND TO BE
ACQUIRED
PARTICULARSSL.
NO
FORESTRY CLEARANCE
TOTAL ML/PROJECT AREA (ha)
TOTAL FORESTLAND (ha)
Date of FC Extent of forestland
Balance area for which FC is yet to be obtained
Status of appl. for diversion of forestland
If more than one, provide details of each FC
449.63 Nil Not Applicable
Not Applicable
Not Applicable Not Applicable
The during-mining land use is as follows: -
CHANGE IN LAND USE DURING MINING
67.43RATIONALISATION AREA6
70.50BLASTING ZONE5
449.63
20.00
15.00
175.00
101.70
AREA (ha)
TOTAL
EMBANKMENT4
INFRASTRUCTURE INCLUDING
APPROACH ROAD ETC.
3
EXT. OB DUMP2
QUARRY AREA1
PARTICULARSSL. NO.
4.6.1 LAND RECLAMATION / LAND MANAGEMENT
The following activities have been proposed for reclamation of land.
1. Backfilling of the excavated area to the extent possible.
2. Leveling of the backfilled area and carpeting with the topsoil.
3. Creation of garland drains in order to arrest the silt load, due to erosion, to
enter into natural watercourses during surface run-off.
4. Grass, legumes and different types of plants etc. will be planted on such
reclaimed land in order to make it, as far as possible, conducive to
agricultural growth.
5. Technical and biological reclamation of external OB dump.
The density of trees is around 2000 – 2500 plants/Ha.
OB Management
Project Total waste generation
(Mm3)
Topsoil (Mm3)
Total OB generation
(Mm3)
Total OB in Ext. Dump
(Mm3)
Total OB Backfilled
(Mm3)
Original Project (ha) 10.33 Included in OB
10.33 9.58 & 0.75 in
Embankment
----
Expansion Project (ha) (balance life)
50.62 Included in OB
50.62 50.62 ----
TOTAL (Mm3)
60.95 60.95 60.20 & 0.75 in
Embankment
The capacity of external OB dumps proposed is about 60.20 Mm3. Remaining 0.75 Mm3 of OB will be used is construction of safety embankment.
The break up of OB quantities in external OB dumps is given in following table.
No. Dump Capacity in Mm3
0-30m 0.60m Total
i) Dump – 1 25.70 16.95 42.65
ii) Dump – 2 10.30 7.25 17.55
Total 60.20
SCHEDULE OF OVERBURDEN DUMPING
The following Table shows the yearwise OB dumping in external OB dump No.1 and No.2
Year Programmed Excavation of
OB(Mm3)
External OB Dump-1 (Mm
3)
External OB Dump-2
(Mm3)Excluding
Rehandling
1. 8.15 8.15 -
2. 7.40 7.40/15.55 -
3. 5.26 5.26/20.81 -
4. 5.25 5.25/26.06 -
5. 5.25 5.25/31.31 -
6. 4.70 4.70/36.01 -
7. 4.50 4.50/40.51 -
8. 4.40 2.14/42.65 2.26
9. 4.40 - 4.40/6.66
10. 1.10 - 1.10/7.76
11. 0.21 - 0.21/7.97
Total 50.62 42.65 7.97
Points for reclamation of void of Junad OC Extn. mine
i. Due to steep gradient and in order to maintain proper haul road of 1 in 16
gradient it will not be possible for backfilling of the void in the present
proposal.
ii. In order to backfill the void of Junad Extn. OC to the extent of –35 m it is
proposed that the OB of adjacent Pimpalgaon Extn. OC could be utilized.
iii. The approx. quantity of OB of proposed Pimpalgaon Extn . OC is 200 M.Cu.m.
and is at a distance of about 5 k.m.
iv. This will simultaneously help in reduction of land required for external OB
dump of proposed Pimpalgaon Extn. OC.
Post mining land use plan (Conceptual)
The post-mining land use pattern at Junad Extn. Deep OCP will be as follows:-
Post-mining Landuse pattern of ML/Project Area (ha)
S.N. Land use during mining
Land use (ha)
Plantation Water Body Public use Undisturbed Total
1 External OB Dump 175 0 0 0 175
2 Top soil dump 0 0 0 0 0
3 Excavation 0 101.7 0 0 101.7
4 Roads including embankment
17 8 25
5 Built up area 3 0 7 0 10
6 Green Belt 0 0 0 0 0
7 Undisturbed Area 137.93 0 0 0 137.93
Total 332.93 101.7 15 0 449.63
Stage-wise Cumulative Plantation
year Green Belt
External Dump(OB +
Top Soil) Backfilled area
Others (undisturbed
area/etc.) Total
1 Area (ha)
No. of trees
Area (ha)
No. of trees
Area (ha)
No. of
trees
Area (ha)
No. of trees
Area (ha)
No. of trees
2 1st year
0 0 0 0 0 0 0 0 0 0
3 3rd year
0 0 0 0 0 0 0 0 0 0
4 5th year
0 0 25 62.5 0 0 10 25 35 87.5
5 End of mine life
0 0 110 275 0 0 145.93 364.825 255.93 1
6 Post mining
0 0 175 437.50 0 0 157.93 394.825 332.93 832.33
Land Reclamation Monitoring
Land restoration / reclamation monitoring of fourteen opencast coal mines
including Junad OCP of Western Coalfield Limited (WCL) producing less than 5
million cu.m. (Coal+OB) per year, based on satellite data on regular basis at an
interval of three years has been started w.e.f 2011.
Objective of the land restoration / reclamation monitoring is to assess the area
of backfilled, plantation, social forestry, active mining area, water bodies, and
distribution of wasteland, agricultural land and forest in the leasehold area of
the project. This will help in assessing the progressive status of mined land
reclamation and to take up remedial measures, if any, required for
environmental protection.
Projectwise Land Reclamation Status in Opencast Project of WCL
< 5 Million Cu.M of coal + OB) based on Satellite Data of the year 2011 (% Calculated in terms of Total Excavated Area) in Ha
Area inHa
Sl. No.
Project Name
Leashold Plantation Backfilled Active Mining
Total Excavated Area
Total Reclaimed area
i ii iii iv ii+iii+iv ii+iii
in (Ha) 2011 2011 2011 2011 2011
38.18 66.35 42.20 146.73 104.53
1 Junad 163.64 17.98 71.25 30.52 119.75 89.23 15.01 55.15 23.62 74.51
4.6.2 PROGRESSIVE & FINAL MINE CLOSURE PLAN
A. OBJECTIVES OF CLOSURE PLANNING
Mine closure planning has to be carried out at the starting of the mine and
needs periodic reviewing and revision during its life cycle to cope with the
geo-technical constraints, safety and economic risks, social and
environmental challenges. Various other objectives are as follows:
(a) To allow a productive and sustainable after-use of the site which
is acceptable to the mine owner and the regulatory authority;
(b) To protect public health and safety;
(c) To alleviate or eliminate environmental damage and thereby
encourage environmental sustainability;
(d) To minimize adverse socio-economic impacts.
B. DIFFERENT ASPECTS OF MINE CLOSURE PLANNING
The mine closure planning broadly involves the following aspects:
(a) Technical aspects;
(b) Environmental aspects
(c) Social aspects;
(d) Financial aspects.
C. MINE CLOSURE OBLIGATIONS
There is need to define the liabilities, responsibilities and authorities of the mine
management, other regulatory bodies, Central and State Governments after
mine closure. Some obligations relating to the Mine Management
Companies are as follows:
(a) Health & Safety: Regulation Nos. 6, 61, 106, 112 of Coal Mines
Regulations, 1957 and its related DGMS Circulars;
(b) Environment
(i) Water (Prevention & Control of Pollution) Act, 1974;
(ii) Air (Prevention & Control of Pollution) Act, 1981;
(iii) Environmental (Protection) Act, 1986 and Environmental
Protection (Amendment) Rule , 2000;
(iii) DGMS Directives on Noise & Ground Vibration;
(c) Forest : Forest (Conservation) Act, 1980 – Not applicable in this case.
(d) Rehabilitation : As per Company Policy.
(e) Decommissioning/asset disposal, etc.
D. CLOSURE ACTION PLAN
Closure planning is a whole-of-life exercise that begins at the start of a mine
and continues till post-closure. The dynamic nature of closure planning
requires regular and critical review to reflect changing circumstances as a
result of any operational change, new regulation, new technology and
remain flexible enough to cope with unexpected events.
The following steps have to be undertaken in relation to Mine Closure
Planning:
(a) Prior to the surface demolition/restoration a surface audit should be
undertaken on all surface structures, spoil heaps, lagoons, etc. to assess
whether there are any hazardous materials that could cause problems;
viz. explosives, chemicals, etc. A list of surface assets should be
prepared and made available to potential purchasers, prospective
purchasers could be invited and asked to submit sealed bids, this could
ensure that the sale of assets give better financial gain.
(b) In order to identify potential impact, necessary hydro-geological studies
into post-mining ground water recharge has to be done. The void of the
mine can be proposed as a water resource to be utilized for aqua-
culture.
(c) Work force on roll of WCL may be re-deployed for gainful utilization of
employees of WCL.
(d) As a detailed component of the Closure Plan, a Decommissioning Plan
is to be developed towards the final stages preferably 5 years prior to
tentative closure of the mine. Once established, it may be updated
annually.
E. PROTECTIVE MEASURES TO BE TAKEN
Protective measures must include the following:
(a) The protection of mine boundary, building and other structure on the
project site against access by unauthorized persons;
(b) The maintenance of all mechanical, hydraulic and waste management
system;
(c) The continuation of all monitoring programmes;
(d) The control of all contaminated effluents;
(e) The securing of all petroleum products, chemicals and waste;
(f) The rendering of all tailings, dams and piles of earth, rock and waste
resulting from work done on the project site in a stable and safe
condition.
F. CLOSURE COSTS
A financial provision of Rs. 6.00 lakhs per ha will be provided in the the Mine
Closure Plan as per guidelines of MoC for the entire life of the mine to
undertake mine closure activities (for plantation in slope of dumps & quarry,
for protection of mine boundary and continuation of monitoring programme
and control of contaminated effluents). Closure cost may be reviewed under
the changing circumstances and new legislative requirements.
4.7 Blasting vibration control measures
All provisions of Coal Mines Regulations will be followed.
The quantity of explosive will be decided as per condition imposed by
DGMS.
Blasting will be done in daytime during the shift change over period as per
requirement keeping in view DGMS permission, meteorological conditions,
geo-mining condition and method of mining.
Proper conformation to measures for safe blasting, to avoid damage to any
structure or annoyance to the people in the colony area or neighbouring
villages.
A safe blasting zone will be kept around the periphery of the quarry. This
zone will be kept free from village habitation and community infrastructure
and thus impact of vibration after blasting on the surface structures is
avoided.
Controlled blasting will be done near built-up areas
4.8 Impact on flora & fauna
There is no forest land in the core zone.
o There is no endangered and endemic species in core and buffer zone .
o The area is not the migratory route for any wild animal.
o Both core and buffer zones are found to be free from ecologically
sensitive and biologically rich areas/habitats, such as, national parks,
sanctuaries, biosphere reserves etc.
o WCL in association with local people will make all efforts to conserve the
flora & fauna in the immediate surrounding of the mine area.
CONTROL MEASURES TO REDUCE IMPACT ON FLORA AND FAUNA
The enhancement of forest area will occur due to creation of greenbelt.
This project is not likely to have any impact on diversity of flora & fauna
species within terrestrial and aquatic habitats.
WCL in association with local people will make all efforts to conserve the
flora & fauna in the immediate surrounding of the mine area.
Mine water will be discharged only after suitable treatment to natural
water course. So, no adverse impact on downstream aquatic life of
surface water courses is expected.
4.9 Visual/Aesthetic Impacts
Suitable mitigatory measures will be taken to eliminate spots of eyesore due to
excavation of coal and OB as well as transportation, water logging by provision
of proper drainage, land reclamation (both technical and biological) and
afforestation.
Hence it can be concluded that the mining activities at proposed Junad Deep
Extension OC mine will not affect the different attributes of environment to any
significant extent.
VISUAL/AESTHETIC EFFECT CONTROL MEASURES
Regular supervision to detect the spots of eyesore and to remove the
same immediately.
Proper housekeeping is envisaged.
Physical and biological reclamation of mined out land to the extent
possible to ameliorate the environment.
CHAPTER- V
ENVIRONMENTAL MONITORING PROGRAMME
5.0 ENVIRONMENTAL MONITORING –
The environmental monitoring programme at present is being carried at the
mine and will be continued as per details given below: -
S
N
Items Parameters Frequency No. of
Stations
1 Ambient
Air Quality
Monitoring
SPM, RPM, SO2,
Nox, CO & Fugitive
dust
Every Fortnight as per
EPA, Rule 2000
4
2 Water
Quality
Monitoring
1) 4 Parameters
viz. p H, Total
Suspended Solids
(TSS), Chemical
Oxygen Demand
(COD) & Oil and
Grease.
2) 35 Parameters
Every Fortnight
Once in a Year
2
3 Noise
Quality
Monitoring
Noise Levels Every Fortnight 2
4 Environme
ntal
Statement
Annual
5 Ground
Water
Level
Monitoring
& Quality
Water Level &
Quality
Parameters.
Water Level –
Quarterly.
Water Quality – Yearly.
In Buffer
Zone
Villages.
6 Complian
ce Report
of EC
Conditions
All conditions both
Specific & General
1st June &
1st December
Not
Applica
ble
CHAPTER- VI
ADDITIONAL STUDIES
6.0 INTRODUCTION:
Mining is a hazardous industry. There is risk to life and property associated with
various mining and allied activities of the project. As such a detailed study has
been carried out covering identification and assessment of risk, and
recommendation of measures to prevent damage to life and property against
such risks. They are discussed below.
6.1 PUBLIC CONSULTATION
The Environmental Public Hearing in respect of proposed Junad Opencast
Expansion Project of M/s Western Coalfields Ltd., Wani North Area, Tal. Wani ,
Dist. Yavatmal for enhancement in production capacity from 0.60 MTPA to 1.50
MTPA and increase in lease area from 174.28 ha to 449.63 ha was held on
05/02/2013, 11.00 am at Kamgar Manoranjan Kendra, Bhalar Township, At Post
Bhalar, Tal. Wani, Dist. Yavatmal. The public hearing was conducted under the
Chairmanship of Shri Rajendra Deshmukh, Additional District Magistrate,
Yavatmal (The representative nominated by District Magistrate, Chandrapur).
Shri S.D.Patil, Sub Regional Officer, MPCB, Chandrapur was the Convener of the
Public Hearing. Shri N.G. Nihul, Regional Officer, MPCB, Chandrapur was the
Member of Public Hearing panel. Shri M.P.Barhanpurkar, District Mining Officer,
Yavatmal, Shri L.S.Varhade, SDO, Wani and Shri Misal, Tahsildar,Wani were also
present during the public hearing. The public hearing started at 11.00 am with
the permission of the Chairman of the Public Hearing Panel.
First of all, the Convener welcomed all present for Public Hearing. He told that,
the Public Hearing is being conducted as per the provisions of EIA Notification
dated 14/09/2006 and amended Notification dated 01/12/2009 of Ministry of
Environment & Forests, New Delhi. He told that the project proponent received
TOR (Terms of Reference) for this project from Ministry of Environment & Forests,
New Delhi on 11/07/2008. Accordingly, project proponent prepared Draft EIA &
EMP Report and submitted their application on 15/02/2010 to the Board
requesting for conducting the Public Hearing.
The Public Hearing for this project was earlier scheduled on 31.08.2010 and
21.12.2010 but during hearing it was cancelled at both the times due to some
reasons. Thereafter, the public hearing was scheduled on 10.10.2012. The public
notice for the said public hearing was published on 08.09.2012 in Daily Lokmat
(Marathi) and Daily Hitawad (English) stating date, venue and time of public
hearing. The said public hearing was postponed due to some unavoidable
reasons at that time as per District Collector, Yavatmal letter no. 937/2012 dated
06.10.2012. The notice about postponement of Public Hearing was published in
Marathi Dialy Lokmat and English Daily Hitavada on 08.10.2012. Afterwards the
public hearing is scheduled on 05.02.2013 and the public notice in this behalf
was published on 02.01.2013 in Daily Lokmat (Marathi) and Daily Hitawad
(English) stating date, venue and time of public hearing.
The copies of Draft EIA/EMP and Executive Summary in English and Marathi were
made available vide letter no. 1288/2010 dated 28.07.2010 to the offices of
District Collector, Yavatmal, District Industries Centre, Yavatmal, Zilha Parishad,
Yavatmal, MPC Board (HQ), Mumbai, Regional Office and Sub Regional Office,
MPC Board, Chandrapur, Environment Department, Mantralaya, Mumbai, Tahsil
Office, Wani and offices of the concerned Gram Panchayat Pimpalgaon, Tal.
Wani for the knowledge of concerned. While issuing the notice of
postponement, it was requested to above offices for making available the
documents submitted by project proponent for the concerned to study till the
date of Public Hearing. Also, through this notice it was requested to file their
objections/suggestions within 30 days from the date of public notice to the Sub
Regional Officer, MPC Board, Chandrapur. The Member Secretary, MPC Board,
Mumbai has issued the Panel Order no. E-15 of 2013 dated 29/01/2013 for the
Public Hearing.
The Minutes of Public Hearing in respect of proposed Junad Opencast Expansion
Project of M/s Western Coalfields Ltd., Wani North Area, Tal. Wani , Dist.
Yavatmal conducted on 05/02/2013 11.00 am Kamgar Manoranjan Kendra,
Bhalar Township, At Post Bhalar, Tal. Wani, Dist. Yavatmal is placed at Annexure –
III and the isuues and replies in tabular form are given against Point no. 48 at
Annexure - II.
6.2 Disaster Management Plan
The project report has been drawn in conformity with the prevailing statutory
provisions as per Mines Act 1952, CMR 1957 applicable for safety in Opencast
Mines. However, the following matters related to safety during opencast
operations has been given a special consideration.
The rain water falling within the project area would be diverted from quarry area
providing garland drains and shall be collected towards low lying area.
However, sufficient space has been left between quarry boundary and Wardha
River for accommodating flood protection embankment.
The bench height and width would be kept as per the Statute. The gradient of
haul road should not be steeper than 1 in 16. Adequate care must be taken for
proper construction and maintenance of haul road.
The HEMM deployed in the project are equipped with suitable in-built safety
devices like audio-visual alarm, fire extinguishers, etc.
The fencing should be erected round the quarry surface so that entry to
unauthorized persons is checked. Hard hat, safety boots, dust respirators, etc.
has been provided for safe working. Necessary fund provision has been made
for the same.
SAFETY ASPECTS FOR BLASTING OPERATIONS
As explosives are required in bulk for blasting in opencast mines, provision of
Regulation-16A of CMR, 1957 should be ensured.
All blasting operations are carried out in day light. Suitable precautions are
being taken as per the Statute before and after blasting operations. Controlled
blasting technique are being practiced to minimize fly off rocks and ground
vibrations and keep them within safe limits. In order to keep the ground
vibrations within the permissible limit as per DGMS Circular No. 7 of 1997 to avoid
flying of rock fragments and also to achieve satisfactory blasting results,
optimized drilling/blasting parameters depending upon rock formation using
combination of relays/delays have been evolved.
SAFETY ASPECTS FOR OUTSOURCING/HIRING OF HEMM
Special precaution should be taken while deploying workers in the mine. Before
employing any labour to the mine proper vocational training should be
imparted and recommendations of VIII Safety Conference should be strictly
followed. Terms and conditions shall be fixed by management for deployment
of labours by leaser of HEMM as well as machineries. Some of the major
aspects are as follows :
A) For persons :
i) No persons shall be deployed unless he is trained at VTC
ii) Records in Form-B & Form-D shall be maintained.
iii) Records of Vocational Training Certificate and driving license of
operators shall be kept by HEMM outsourcing agency and shall be
made readily available for inspection by management
iv) Salaries shall be distributed in front of management representative
v) No person shall be employed unless person holds VTC certificate
and Management is informed. A record of it shall be maintained.
vi) Adequate supervision shall be maintained by qualified competent
persons.
B) For Machineries as recommended by DGMS Cir. (Tech) 1 of 1999:
i) All the machineries to be deployed in mines should be checked
before deployment.
ii) Regular checking of machine deployed by leaser of HEMM shall be
done. No unfit m/c shall be deployed before the defect is
rectified.
iii) A proper record of repair and maintenance alongwith inspection
done by management and defect pointed out shall be maintained
and signed by authorised person.
iv) The trucks deployed by leaser of HEMM shall be provided with
Audio visual alarms, proper light for use at night and period when
natural light is not sufficient. Also audio visual alarms for reversing
on trucks shall be provided.
Other precautions for machines
i) RTO certificate photo copies of all vehicles shall be submitted to
management.
ii) Daily welding, monitoring, inspection shall be done by the HEMM
outsourcing agencies mechanic as directed by management.
iii) Machine manufacturers should be asked to give risk analysis.
iv) Suitable type of the fire extinguishers shall be provided in
machines.
C) General:
No person/vehicle shall be deployed at any place other than authorised
place.
All workers should obey lawful instruction of mine management.
Risk Management Plan of tipper/pay loader shall be made and
implemented.
All drivers shall obey systematic traffic rules prepared by management.
Before deploying workers they must be trained and briefed about safety
aspects in opencast mine. However during course of execution of the work, if
any accident occurs whether major or minor, the matter shall have to be
immediately informed to mine management i.e., Colliery Manager/Agent/GM
of Area so that Notices of accidents in accordance of (Reg. 9 of CMR 1957) and
Section 23 of Mines Act 1952 may be given and other necessary steps may be
taken in accordance of Section 23 of Mines Act 1952 & Reg. 9 of CMR 1957 and
other relevant laws.
MODEL TRAFFIC RULES FOR HEMM & LIGHT VEHICLES
Suitable traffic rules as per recommendations of VII Safety Conference may be
framed by Manager and implemented to ensure safe operation of dumpers,
light vehicles and other HEMM deployed in the project.
6.2.1 PRECAUTION AGAINST FIRE
(1) Wild or herbaceous plants shall be removed from the mine.
(2) No person shall deposit heated material or ashes on any opencast
working. Also no person shall light a fire or permit a fire to be
lighted in any OC working except by the permission in writing of
the Manager and only for a special purpose specified therein.
(3) No coal shall be left exposed in coal benches more than its
incubation period to avoid fire in seam due to spontaneous
heating.
(4) Proper type of the extinguisher to be kept in each HEMM ready for
use in case of emergency.
(5) In coal stock coal shall be despatched on the basis of first in first
out . 6.3 GENERAL LIGHTING The standards of lighting to be provided in opencast coal mines during
working hours at different places or areas where natural light is not sufficient
has been specified in notification as GSR 804
Dt.18.6.75[Cir.(legis)1/1976] under regulation 154 of CMR 1957. The standards
are summarised below.
Sl.
No.
Location Minimum
standard
of illumination
(LUX)
Level in which
illumination is
to be
provided
1. Operational area of Dragline &
Shovel
5
10
Horizontal
Vertical
2. Operational area of drills 10 Vertical
3. Operators cabin of shovel,
dragline
drill etc.
30 Horizontal
4. Dumper haul road 0.5 to 3.0 Horizontal
5. OB & Coal Dumps 3.0 Horizontal
6. Roadways & foot path from
bench to bench
3.0 Horizontal
7. Coal handling plant, workshop &
service buildings.
As per BIS
Specification
8. Picking conveyor of CHP 50 Horizontal at
level of belt at
work site
9. Working area of Dozer 10 Horizontal at
level of
crawler
Lighting near the faces and haul road may be arranged by cluster of high
pressure sodium vapour lamps/metal halide/HPMV lamps located on the top
of an adjustable telescopic mast, mounted on a platform with rubber tyred
which or skids and having portable diesel generating set.
6.4 DUST SUPPRESSION
For suppression of dust water sprinkler has to be provided. Suppression of
mine dust may be done by using suitable bond, for methodology of
application DGMS Circular No.8 of 1997 may be referred.
6.5 SLOPE STABILITY
It is suggested that following action may be taken to deal with slope
stability problem.
i) Vulnerable area may be identified and marked on quarry plan.
ii) Observation of actual alignment of fault, its throw, joints, etc. may
be recorded during the process of exploitation.
iii) Water drainage system may be properly implemented to prevent
accumulation of water in cracks. Also dumps shall be leveled to
prevent accumulation of water over it. Proper drainage in dumps
shall be also provided to prevent erosion of toe of dump.
iv) Regular monitoring of tension cracks, horizontal and vertical
movement of strata in critical area may be done.
v) Rise side slope to be reinforced if required because it has to stand
through out quarry life. No dumps/surface structures to be located
within 15m of quarry edge as it will act as surcharge there by
destabilizing the slope.
vi) No undercutting of slopes to be done.
vii) Proper hydrogeological studies to be done if water table is at level
of slope it should be brought down by using submersible pumps to
prevent hydrostatic pressure.
viii) Proper selection of site for dumping to be done before dumping
place shall be made free from loose material. Dumping shall not be
done at an angle more than angle of repose of material being
dumped .
ix) After completion of dumping operations dumps to be stabilized by
growing vegetation.
x) Every person deployed by leaser of HEMM must be trained &
briefed about aspects related to slope stability.
6.6 HEIGHT & WIDTH OF BENCHES & MANNER OF EXTRACTION
Height of benches (both in coal & OB) shall in no case be more than
cutting/digging height of excavation.
Width of bench in coal & OB shall not be less than :
Widest equipment + 5m Ht of bench
3x largest dumper’s width.
Width of bench adopted as the maximum value amongst (a), (b) & (c)
Each cycle of operation shall consist removal of overburden followed by
extraction of the exposed coal. After extraction of coal no body shall be
employed/no work to be done at any of the benches or bottom of quarry till
benches in OB & coal are provided again from top downwards and coal is
again exposed.
6.7 RISK MANAGEMENT :
Ninth Conference on Safety in Mines recommended to adopt Risk Management
as a tool for development of appropriate health & safety management in Indian
Mines.
The Safety Management System established by a mine must ensure all risk are
identified and critical risks are controlled to ensure long term health and safety.
A Safety Management System should set the culture, framework and actions
necessary to ensure that mining operations are carried out safely.
In order to turn these commonly agreed principles into an effective safety
management system for the mine, the system may include the following
elements:
- Health & Safety Policy of the company and the mine
- Roles and Responsibilities of all levels in the organization
- Specified competencies of staff
- Safety Committee, formation and role
- Method to identify and control high risk
- Forward Programme to ensure actions to control hazards are carried out
- Emergency prepardness to cope with a hazard if it should occur
- Monitoring processes for all identified hazards with or without residual
risks
- Identification of trigger points and resultant actions if these are reached
- Safety clearance for new equipment, work methods and materials used
- Accidents Statistics collection, analysis & Actions.
- Reporting and record keeping requirements
- Auditing and review process.
6.8 CONSERVATION
Quarry limits are finalized in such a way to exploit maximum possible coal.
Although for calculation of mineable coal reserves, 10% mining losses has been
taken into account, but, in practice, all efforts would be made to minimize the
losses. If these losses are minimized to 4.5% (15 cm at each contact zone of coal
& OB + 0.5% due to blasting + 1% due to transportation of coal) then coal
reserves may increase by about 0.84 Mt, which, in turn, may reduce stripping
ratio by about 0.57 m3/t.
Separate excavator will be engaged for mining coal. OB benches would be
kept sufficient advanced to avoid mixing of coal and OB.
6.9 Socio-economic Impact
The socio –economic impacts of the project is given below.
Although a few mines already exist in the buffer zone, the opening of Junad OC
mine has definitely affected its surroundings and the employment scenario.
The direct employment opportunities have already improved around the coal
mine areas & with the expansion of this project it will improve further. With the
proposed expansion of the mine the occupational structure of the area is going
to change further and many people are likely to be involved in the job of mining
and allied activities. Hence, income levels of these people are likely to improve
to significant level.
The monetary inflow in this area through salary & wages payable to the project
employees will increase because almost 50% of this amount is being spent
locally to meet the day to day domestic demand.
This regular expenditure may lead to adequate & impressive economic-
development of the area. This monetary inflow may also lead to improvement
of civic amenities because people will go for more and more consumer goods,
better educational facilities & communication.
Simultaneously various small scales & medium scale manufacturing engineering
units may also come up giving adequate alternate employment opportunities
for local people.
Employment opportunities both direct & indirect in this project are likely to cause
migration from outside. Amenities like medical educational, recreational etc.
are available to local people and their quality of life will definitely improve.
Impact on Health
At present there is a dispensary with qualified doctors & paramedical staffs in
the project. At area level there is a full-fledged hospital. The Periodical medical
examination is being carried out regularly as per statute. The circulars and orders
of DGMS including the rules and regulations under Mines Act are being adhered
to in respect of occupational health and safety.
No major occupational health hazard is anticipated due to the proposed
expansion of the project.
The medical facilities are being extended to nearby villages. The situation is
likely to improve further.
Impact on Flora & Fauna
o There is no endangered and endemic species in core and buffer zone.
o By developing plantation of native species efforts are being made to
improve the green cover in and around the immediate vicinity of the
mine area.
o WCL in association with local people will make all efforts to conserve the
flora & fauna in the immediate surrounding of the mine area.
o Improved blasting techniques will be used to minimise the noise & ground
vibrations.
Both core and buffer zones are found to be free from ecologically sensitive
and biologically rich areas / habitats. As such impact on flora & fauna is likely
to be insignificant.
CONCLUSION
From earlier paragraphs, it can be inferred that the adverse impact on physical
environmental attributes due to proposed mine is almost insignificant/ negligible.
6.10 Peripheral development:
As per the present practices in WCL coal mines, adequate steps are being
taken for the local villagers by providing various infrastructural and welfare
facilities and giving assistance in health care in Wani North Area of WCL, under
which the mine under consideration is operating.
The various development works like construction of Primary, School, Post
office, Shopping center, diversion of cart track for villagers, establishment of
bank, diversion of irrigation canal etc; have been completed, mainly for
catering to the needs/socio-economic upliftment of the neighbouring
population.
COMMUNITY DEVELOPMENT WORKS
SOME OF THE IMPORTANT COMMUNITY DEVELOPMENT WORKS DONE BY THE AREA AMOUNTING TO Rs. 97.45 LAKHS
ARE GIVEN BELOW.
STREET LIGHT FROM PIMPALGAON CHP TO AHERI
VILLAGE – 2 KM
6
STRRET LIGHT FROM CGM OFFICE TO UKNI VILLAGE , 1.8 KM
5
INTERNAL ROAD AT UKNI VILLAGE , 800 m4
WANI GHUGUS ROAD TO PIMPALGAON VILLAGE
APPROACH ROAD
3
APPROACH ROAD TO KOLERA VILLAGE , 1.5 KM2
BHALLAR VILLAGE INTERNAL ROAD REPAIRING WBM
& ZP SCHOOL BUILDING REPARING
1
DESCRIPTIONSL . NO.
COMMUNITY DEVELOPMENT WORKS (contd.)
CONSTRUCTION OF A HALL AT RAMAIBAI MAHILA
MANDAL AT RAJUR
14
SPORTS MATERIAL FOR Z. P. SCHOOL RAJUR13
REPAIRING OF PRIMARY SCHOOL RAJUR12
BOUNDARY WALL OF Z. P. SCHOOL RAJUR 11
HAND PUMP AT NEELPUR AND PIMPALGAON
VILLAGE
10
REPAIRING OF Z. P. PRIMARY SCHOOL AT RAJUR9
ONE BOREHOLE AT BHANDEWADA VILLAGE
INCLUDING WATER TANK
8
REPAIR OF Z. P. BUILDING AT AHERI VILLAGE7
DESCRIPTIONSL . NO.
CSR Activities at nearby villages
2010- 11
Sl.No Name of CSR Work Amount
(Rs.in Lakhs)
Remarks
1. Construction of Concrete road
at Junad Village (90m X 3 m)
1.85 Completed
2. Providing 2 Nos. of Hand Pump
at Ukni Village
1.07 Completed
3. Construction of concrete road
at Pimpalgaon Village (150 m X
3 m)
2.48 Completed
4. Construction of cement
concrete raod at Borgaon
Village
4.23 Completed
5. WBM road at Borgaon Viallge 2.31 Completed
6. Repairing of existing approach
road at Aheri village
1.16 Completed
7. Repair of WBM road from
village junction to Magazine
Building at Ukni Village
2.69 Completed
8. Boundary wall at Z.P. School at
Pimpalgaon Village
7.88 Completed
2011- 12
Sl.No Name of CSR Work Amount
(Rs.in Lakhs)
Remarks
1. Construction of concrete road
at Junad Village (200 m X 3 m)
4.17 Completed
2. Construction of two class
rooms for Z.P. School at Junad
Village
4.29 Completed
3. Construction of cremation
shed at Ukni Village
4.13 Completed
4. Construction of Bituminous
internal roads of Borgaon
Village
3.82 Completed
5. Reapairing and cleaning of
drains of Borgaon Village
1.58 Completed
6. Repairing of black – topped
roads from Ukni Village to
Arterial Road
6.73 Completed
The details of CSR works done during 2012-13, 2013-14 at Juand OCP & Wani
North Area as a whole sre given in subsequent pages.
CSR ACTIVITIES OF THE YEAR 2012-13
Within 25 Km of Junad OCM, WANI NORTH AREA
SR.No.
Name of the Project/CSR Activity 2012-13
Total amount spent on
documentation and
dissemination
Expenditure Details of
evaluation report
(A) Infrastructure(construction, repair)
Construction of cement concrete road at Brahmani village
5.20 Completed & Finalised
stone pitching and development of bund with pathway cement benches etc of pond at Brahmni village 1 nos
7.19 Completed & Finalised
Construction of cement concrete road from main road junction towards village Nilapur (200mt)
5.52 Completed & Finalised
Construction of cement concrete road at Junad village (200 m) 7.62
7.56 Completed & Finalised
Construction of cement concrete road at Borgaon village (200mts) 2.11
1.98 Completed & Finalised
Construction of cement concrete road at Naigaon village
6.07 Completed & Finalised
Constructionof cement concrete road at Pimpalgaon village
7.00 Completed
Construction of WBM road at Ukni village (650mts)
5.54 Completed
Construction of cement concrete road at Lathi village (250 mts)
9.15 Finalised
widening and b.c of approach road from BTS turning to Lathi village
14.90 Finalised
Renovation of bus stand shed of Lathi village (1 nos)
1.04 Finalised
Construction of community hall and development work at Lathi village (6x15m)
16.21 Completed
stone pitching and development of bund with pathway cement benches etc of pond at Bhalar village 1 nos 6.91
2.22 Completed
Construction of cement concrete road from main road hanuman mandir and drain at Bhalar village (160m) 5.44
4.99 Completed & Finalised
Providing display boards at different villages under CSR of WNA (20 nos) 2.00
1.86 Completed
SUB TOTAL 96.42 Completed
SR.No.
Name of the Project/CSR Activity
Total amount spent on
documentation and
dissemination
Expenditure Details of
evaluation report
(B) WATER SUPPLY AND DRINKING WATER
23 Water supply arrangement by providing 1 no tube well with submersible pump at Sewa Nagar ward 19 of Wani
1.51 Completed &
Finalised
SUB TOTAL 1.51
( C) Medical Camps and sports
1 15 nos medical camps@ 15000
2.19
15 nos completed
2 Provision of mobile medical van 3.86
3 medicine for mobile van camp 0.05
KP Mishra 0.05
sub total 6.10
(D) Sports and cultural 0.00 Completed
Sports camps 2 nos 0.25 Completed
RK Singh 0.25
sub total 0.50
GRAND TOTAL 104.53
GRAND TOTAL for 10-11, 11-12, 12-13, 13-14
331.24
CSR ACTIVITIES OF THE YEAR 2013-14
Within 25 Km of Junad OCM, WANI NORTH AREA
SR.No. Name of the Project/CSR Activity 2013-
14
Total amount spent on
documentation and
dissemination Expenditure
Details of evaluation
report 2013-
14 2014-
15
EDUCATION
1 Providing cupboard, chair and playing equipment for school at Ukni village
under Ukni Sub Area
4.18 Completed 2 Providing Desk, benches, Almirah& chairs
3 Desk Bench & Steel Almirah at Zila Parishad
7 One No. Computer & desk bench for Zila
parisad School, lathi
Total 4.18
INFRASTRUCTURE
8 Making Cremation shed & hand pump at Lathi .
2.50 Completed.
9 Extension of main drain at Gowari village for storm water drainage under Gowari
gram panchayat.(200 mt.)
3.55 Completed.
10 Making cement concrete drain at
Boregaon
4.25 Completed
11 Waste water drains at ghonsa village. 4.29 Completed
12 Making cement concrete road (250 m) at
lathi
4.80
Completed
13 Const of 300 mtr cement concrete road
at Bhandewada village near RIC Mine at RSA
8.75 Completed
14 Wall compound & gate for Zila parisad
School , Lathi
1.89 Completed
15 Bus stop near Junad village(Phata) 1.63 Completed
20 Black Topping of road at various wards of
Ukni Village
0.00
Work Completed
21 Cement concrete road at Pimpalgaon at
New Basti
5.27 Completed
Total 36.92
SR.No. Name of the Project/CSR Activity
Total amount spent on
documentation and
Expenditure Details of
evaluation report
dissemination
WATER SUPPLY & DRINKING WATER
23 One no. Hand pump near Bus stand at
lathi
0.66 Completed
24 Providing and fixing hand pump 2(two)
Nos at Ukni Village
0.00
Work in progress
25 Provision of one no. Water coolers &
water purifier at Sirpur
0.80 Completed
Total 1.46
Sports And Culture 0.00
27 Village Sports Tournament(Volleyball,
Kabbadi)
1.25 Completed
28 Providing Sports Material 0.55 Completed
29 Village Sports Coaching Camp(Kabbadi,
Volleyball)
1.25 Completed
Total 3.05
Social Empowerment 0.00
30 Providing training program on tailoring 0.10 Completed
31 Providing Sewing machine to mahila
mandal
0.69
Completed
Total 0.79
Health Care 0.00
33 Hiring charges for medical Van 1.13
34 Village Medical Camp 15 nos@15000 2.23 Completed
35 Medicine for 15 nos of medical camp 1.25
Total 4.61
STREET LIGHTS
36 Street light lamps with shades - 1.00 Completed
37 Street light lamps with shades - 1.00
Total 1.99
ENVIRONMENT 0.00
38 Plantation on 100 ha. Degraded forest
land - 33.12
Work in progress
39 Service Tax 5.44
Grand Total 91.57
GRAND TOTAL for 10-11, 11-12, 12-13, 13-14
422.81
6.11 REHABILITATION SCHEME
There is no house oustees involved in the project. Only land losers are involved
who will be suitably rehabilitated as per company norms.
Existing Mine & Proposed Deep OC:-
Total Land Acquired: - Agricultural – 171.15 ha + Govt. Land – 3.13 ha
Total nos. of employment given – 77 nos.
Now for Deep Extn. OC 275.35 ha is proposed to be acquired.
Out of this 109.14 ha of agricultural land has been acquired against which, 50
land losers have been provided employment & 26 have been provided with
monetary compensation.
CHAPTER – VII
PROJECT BENEFITS 7.0 PROJECT BENEFITS
The benefits of the project can be summarized as below:-
- The physical infrastructure in the area will be improved substantially by
following ways:-
a) Development of road, thereby improving the communication.
b) Improvement in Power, Telephone (including Mobile) facility.
c) Improvement in Health Care facility & Educational facility.
d) Improvement in Market / Trade & Business.
- The social infrastructure by way of cultural mixing of people of other states with
local community glorifying “UNITY IN DIVERSITY”.
- Substantial employment in the project & indirect employment for business &
trading, contractor, transportation, vehicle contractor, nursery development.
CHAPTER - VIII
ENVIRONMENTAL COST – BENEFIT ANALYSIS
Ministry of Environment & Forests while issuing TOR has not specifically indicated
for carrying out “Cost Benefit” Analysis, hence the same has not been carried
out.
CHAPTER - IX
ENVIRONMENT MANAGEMENT PLAN
9.0 GENERAL
Close monitoring of the environment and implementation of various protective
measures discussed in the report forms an important part of EMP. In the earlier
chapters the causes of various pollutions along with the preventive and
mitigating measures have been discussed. In this chapter description of the
administrative aspects of ensuring that mitigative measures are implemented
and their effectiveness monitored, after approval of the EIA is being discussed.
9.1 MONITORING ORGANISATION
To have a close watch on the environmental condition and implementation of
the various measures suggested, a multi-disciplinary approach is essential.
(a) WCL headquarter acts as an apex body which supervises the activities
relating to environment at project level through the General Manager.
(b) General Manager of the area coordinates the activities of various disciplines
in the area to render all necessary assistance at the implementing level i.e. the
Project. Area Nodal Officer (Environment) monitors all aspects of environment
on behalf of the General Manager. He also takes suitable steps for generation of
environment data along with its analysis and interpretations.
As far as plantation is concerned horticulturist with suitable backup staff shall be
provided in the area for undertaking the plantation jobs including raising of a
nursery. Plantation will have to be done on a large area. Therefore, it may be
desired that an outside agency may have to be employed for this purpose. The
horticulturist along with the supervisor shall only monitor and guide the agency
for selection of site, treatment of soil, selection of species etc.
(c) Sub Area Manager is responsible for mechanical reclamation of the area. He
is also responsible for biological reclamation with the assistance of GM's office.
ORGANISATION FOR ENVIRONMENT MANAGEMENT
Sl.
No
.
Measures/Actions Agency
1. Environmental Control 1 Chief General Manager, Wani North Area
2 Nodal Officer, (Environment),
Wani North Area
3 Project Officer, Junad OC
4 Staff Officer (Civil), Wani North Area
5 Environmental Cell (WCL H.Q.)
2. Environmental
Monitoring
1 Chief General Manager, Wani North Area
2 Staff Officer (Civil), Wani North Area
3 Nodal Officer (Environment),
Wani North Area
4 Project Officer, Junad OC.
5 Environment Cell of
WCL Headquarters
6 Environmental Laboratory of
CMPDI, RI-IV
3. Reclamation 1 Project Officer, Junad OC.
2 Nodal Officer (Environment),
Wani North Area
3 Environmental Supervisor
4 Horticulturist
9.2 ENVIRONMENTAL COST PROJECTION The details of expenditure incurred on environmental pollution control measures are given as below :-
EXPENDITURE INCURRED ON POLLUTION CONTROL MEASURES
72.04TOTAL
10.28WATER POLLUTION CONTROL MEASURES
3
37.26PLANTATION2
24.50AIR POLLUTION CONTROL MEASURES1
AMOUNT IN
Rs. LAKH
PARTICULARSSL.
NO.
The details of capital provision on environmental protection measures for
proposed expansion project are as given below :-
PROPOSED CAPITAL FOR ADDITIONAL POLLUTION CONTROL MEASURES
37.16TOTAL
10.16WATER TANKER 5
6.0LAND RECLAMATION MEASURES
INCLUDING LAND USE MAPPING
THROUGH REMOTE SENSING
4
5.0DUST SUPPRESSION ARRANGEMENT AT
HAUL ROAD , STOCKYARD ETC.
3
8.0STRENGTHENING OF ETP FOR
WORKSHOP EFFLUENT
2
8.0STRENGTHENING OF SEDIMENTATION
POND FOR TREATMENT OF MINE WASTER WATER
1
AMOUNT IN
Rs. LAKH
PARTICULARSSL.
NO.
CHAPTER – X
SUMMARY AND CONCLUSION 10.1 INTRODUCTION:
The proposed Junad Extension OC Project is an extension of existing Junad OC
mine in Junad block located on the western limb of Wardha Valley Coalfield in
Yeotmal district of Maharashtra. The P.R. for Junad OC mine was prepared by
CMPDI in October, 1989 and was sanctioned by the WCL Board in May, 1990 for
a capital of Rs. 19.148 Crores for a production capacity of 0.32 Mty. The actual
mining operations at the project could be started in November, 1998 due to
delay in land acquisition. This is expansion of existing Junad Opencast with mine
able reserve of 6.13 Mt and with maximum coal production target of 1.50 MTPA.
The Form – 1 was submitted to MOEF &CC vide letter no. WCL/HQ/ENV/11-
C/213-A dated 28.06.2014. The project was discussed in the 21st EAC meeting
held on 19.09.2014. As per the minutes of the meeting of EAC, the project was
recommended with generic TOR. Subsequently Generic ToR was issued vide
Letter No. J- 11015/225/2014 – IA. II(M) dated 21.11.2014. As indicated in the
aforesaid TOR, the PH has been completed on 05.02.2013. Based on the minutes
of PH and generic TOR, this EMP has now been prepared for obtaining
Environmental Clearance from Ministry of Environment, Forests & Climate
Change.
10.2 NEED OF THE PROJECT
There is a substantial gap between demand and availability of coal for the
mines of WCL as a whole. It is in national interest to open new mines/projects &
to go for expansion of existing projects urgently so as to meet the requirement of
coal for power and various other sectors.
The justification of this mine has been studied in the light of estimated demand
for non-coking coal from power sector in Maharashtra and production forecast
from existing, completed and ongoing projects of WCL.
10.2.1 LOCATION & COMMUNICATION
Junad Deep OC Extn. mine is located in the Yavatmal district of Maharashtra
state. It is bounded by Latitudes 20o 01' 05" to 20o 04' 10" N & Longitudes 79o 03'
09" to 79o 05' 00" E and falling in Survey of India Topo Sheet No. 55 P/4.
The existing mine is at a distance of about 140 km from Nagpur . However, the
block is presently connected by a 3 km fair weather road with Aheri village
which, in turn, is connected with Wani town towards North-West by a 19 km
metalled road. The block may also be approached by a 3 km road from Ukni /
Pimpalgaon project which is also being connected with Wani town via Bhalar
village.
10.2.2 TOPOGRAPHY & DRAINAGE :-
The area of Junad Extension OC mine exhibits gently undulating topography.
The general slope of the ground is from west to east. The elevation varies from
180 m to 195 m. The Wardha River flowing from north to south is the main
drainage channel of the area.
10.2.3 CLIMATE :-
Junad block has extreme climate with temp. of 480 C during summer months
and about 100 C during winter months . The average annual rainfall is about
1250 mm.
10.2.4 PRESENT LAND USE PATTERN :-
The entire land to be acquired for extension of the Junad OC project is covered
by black cotton soil and is fertile and is generally used for growing mainly the
cash crops like cotton, sugarcane, chillies etc apart from standard agricultural
products like rice , wheat & jawar. No village is falling in the proposed leasehold
boundary of the project. All the land losers will be given compensation as per
Company’s norms.
10.2.5 SITE DESCRIPTION: -
The study area has been divided into two heads Core Zone
Buffer Zone
a) Core zone: The core zone consists of the mining leasehold area where
mining and allied activities take place. The core zone comprises of 449.63 ha of
land. The land usage is given below.
Sl.
No
Land Particulars Total Land
1. Agricultural land 443.53 ha
2. Waste Land
(Govt. Land)
6.10 ha
3. Forest Land -
Total 449.63 ha
b) FEATURES IN BUFFER ZONE
Sl.
No.
FEATURES DETAILS DISTANCE
FROM MINE
1 Industries Nil Nil
2 Railway Lines Wani Railway Siding About 9.0 km
3 State Highway State Highway No.- 84 About 5.0 km
4 Other Coal
Mines
Ukni OC, Pimpalgaon
OC , Kolar Pimpri OC
3.0 – 5.0 km
5 Water Bodies Wardha River 125 m from
mine boundary
6 Human
Settlement
40 villages & WCL township within buffer
zone
10.2.6 JUSTIFICATION: -
There is a substantial gap between demand and availability of coal for the
mines of WCL as a whole. It is in national interest to open new mines/projects
urgently so as to meet the requirement of coal for power and various other
sectors.
The justification of this mine has been studied in the light of estimated demand
for non-coking coal from power sector in Maharashtra and production
forecast from existing, completed and ongoing projects of WCL.
10.3 SOURCES OF DATA
This report has been formulated using various data from the following
sources:
Sl.
No.
Type of Data Sources
1 Mining and economic
parameters and other
miscellaneous data
CMPDIL and Wani North Area,
WCL.
2
Environmental data including
meteorological data, air
quality, dust fall rate, water
quality and noise level data.
Environmental-data generation
for proposed Junad Extn.
(Deep) OC of Wani North Area
of WCL, Maharashtra carried
out by CMPDI.
3 Socio-economic study & Land
use/cover mapping buffer
zone.
Census data & base line Socio -
Economic survey.
4 Flora and fauna Survey Report prepared by the
competent authority in this
field.
5 Surface hydrology and
hydrogeology
CMPDIL, RI- IV, Nagpur.
6 Meteorological data Environmental-data generation
for Junad. Extn (Deep) OC of
Wani North Area Maharashtra
carried out by CMPDI.
7 Land use/cover mapping core
zone.
As per State Govt. Record,
data supplied by the
concerned WCL area office.
10.4 GEOLOGY OF THE MINING BLOCK
The geological formation encountered in the present quarriable area are as
follows :-
Formation Thickness (m) Lithology
Minimum Maximum
Soil 3.00 24.00 Black clayey soil and sandy soil
(MWJ-24) (MWJ-27)
Kamthis 6.00 101.00 Yellow, brown, red, yellowish white
ferruginous sandstone, occasionally
grey sandy shale/shale. (MWJ-37) (MWJ-12)
Barakar 12.78 133.55 Grey white medium to grey
sandstone with shale, coal seams with
shaly coal, etc. (MWJ-20) (MWJ-27)
GEOLOGICAL STRUCTURE
Only 3 faults viz. Fault F3-F3, F4-F4 and F5-F5 are intersected in quarry. The fault
F3-F3 is minor in nature and throw is 5 m. The throw of F4-F4 & F5-F5 is 20 m
towards NE and 40 m SW respectively.
GEO - MINING PARAMETERS
Sl. No. Particulars EXTENSION QUARRY
1. FACE LENGTH (km)
a) On the floor of composite seam 1.15 – 1.28
b) On surface 1.50 – 1.70
2. DEPTH UPTO FLOOR OF COMPOSITE
SEAM(m)
a) Initial 30 - 88
b) Final 170
3. WIDTH BELOW THE DECOALED VOID OF
EXISTING OC (m)
a) On the floor of composite seam 250 - 325
b) On surface 400 – 525
4. AREA OF THE QUARRY (ha)
a) On the floor 35.20
b) On surface 70.50
5. GRADIENT OF SEAM 1 in 3
6. GRADE OF SEAM (WITH 5 CM
CONTAMINATION)
E
7. U.H.V. (WITH 5 CM CONTAMINATION) 3822
8. AVG. SEAM THICKNESS(m) 17
9. NET MINEABLE RESERVES (Mt) 6.13
10. Average stripping ratio (t:m3) 1:8.26
The shovel dumper system of mining with horizontal slicing method is
recommended for the proposed extension project with sump at the bottom-
most horizon bench in the coal seam.
2.2 WASTE DISPOSAL & REHANDLING OF EXISTING OB DUMP
Two external OB dumps are proposed in dip side of the extended quarry beyond
the major boundary Fault F1-F1 at a depth ranging from 350-400 m at the floor of
coal seam. The main external OB dump No.1 lies exactly in the dip side of
extended quarry from Aheri village in north to approach road for the project in
south. The dump No.1 is proposed keeping safe distance from Pragati Nagar
township, existing water pipeline, Wardha river and approach road to the
project. External OB dump No.2 is located on other side of approach road.
In addition, about 10.33 Mm3 of OB already dumped by existing Junad OC in dip
side of the quarry over coal bearing area where Junad Extension OCP is
proposed also requires to be rehandled. The capacity of external OB dumps
proposed is about 60.20 Mm3. Remaining 0.75 Mm3 of OB will be used is
construction of safety embankment. The break up of OB quantities in external OB
dumps is given in following table.
No. Dump Capacity in Mm3
0-30m 30 -60m Total
i) Dump – 1 25.70 16.92 42.65
ii) Dump – 2 5.80 2.17 17.55
Total 60.20
The entire extension quarry which is 50.62 M.Cu.m. of existing Junad OC mine is
dumped in dump no. 1 and 2 . About 10.33 M.Cu.m. of OB to be rehandled will
also be dumped in dump no.2 (9.58 M.Cu.m.) and also used for construction of
embankment(0.75 M.Cu.m.).
The external dumps have two benches each of 30m height and final angle of
slope is proposed to be kept at maximum 28o.
A small coal handling plant is already in operation, installed at Pimpalgaon
project (about 5 km away) for Junad OCP. The same CHP will cater to the
needs of Junad Extension OC.
The CHP has facilities For crushing of coal to (-)200 mm size .The crushed coal
is being loaded in trucks by pay loader and transported to Wani Siding for
rail despatch.
Break up is given below .
Sl.
No.
Particulars Land
already
acquired in
existing
Junad OC
Mine
Land to be
acquired
under
proposed Junad
Extn. OC
Mine
Total
1. Agricultura
l Land
174.28 ha
269.25 ha*
449.63 ha 2. Waste Land
(Govt.
Land)
6.10ha
3. Forest
Land
NIL NIL NIL
TOTAL
174.28 ha 275.35 ha 449.63 ha
* This 269.25ha of land to be acquired includes 5.20 ha of land of Kolar pimpri
extn oc and 13.85 ha of acquired land by existing pimpalgaon oc project. Both
the projects are adjacent to Junad extension OC mine.
{Source of Data: - Sanctioned Project Report}
Changes of Land Use during Mining:
Sl. No. Particulars Area (ha)
1 Quarry Area 101.70
2 External OB Dump 175.00
3 Infrastructure including
approach road etc.
15.00
4 Diversion of Nala 00.00
5 Embankment 20.00
6 Area needed for
rationalization & safe
blasting zone
137.93
TOTAL 449.63
Table 2: Stage-wise Cumulative Plantation
year Green Belt
External Dump(OB +
Top Soil) Backfilled area
Others (undisturbed
area/etc.) Total
1 Area (ha)
No. of trees
Area (ha)
No. of trees
Area (ha)
No. of
trees
Area (ha)
No. of trees
Area (ha)
No. of trees
2 1st year
0 0 0 0 0 0 0 0 0 0
3 3rd year
0 0 0 0 0 0 0 0 0 0
4 5th year
0 0 25 62.5 0 0 10 25 35 87.5
5 End of mine life
0 0 110 275 0 0 145.93 364.825 255.93 1
6 Post mining
0 0 175 437.50 0 0 157.93 394.825 332.93 832.33
Post mining land use plan (Conceptual)
The post-mining land use pattern at Junad Extn. Deep OCP will be as follows:-
Post-mining Landuse pattern of ML/Project Area (ha)
S.N. Land use during mining
Land use (ha)
Plantation Water Body Public use Undisturbed Total
1 External OB Dump 175 0 0 0 175
2 Top soil dump 0 0 0 0 0
3 Excavation 0 101.7 0 0 101.7
4 Roads including embankment
17 8 25
5 Built up area 3 0 7 0 10
6 Green Belt 0 0 0 0 0
7 Undisturbed Area 137.93 0 0 0 137.93
Total 332.93 101.7 15 0 449.63
10.5 Base line Environmental Scenario
The baseline data has been collected for various environmental components
such as, Air, Water, Noise and Soil. Baseline data collection has been carried out
within 10 KM radius from the boundary of the core zone during Pre – Monsoon
season of 2013. The statutory guidelines and practices with present norms for
coal mine projects have been followed during the baseline data generation/
collection.
Micrometeorological data generation
A meteorology station has been set up at core zone and micrometeorological
parameters like wind velocity, wind direction, temperature, relative humidity,
cloud cover etc. are recorded on hourly basis for Pre Monsoon season 2013.
Daily rainfall also has been recorded and reported.
Ambient air quality monitoring
Ambient air quality was monitored at 6 locations i.e. one in core zone and the
remaining five in buffer zone. A total of 24 samples (24-hrly) for SPM, PM10, PM2.5,
SO2, NOx and heavy metals samples were collected from each location during
the study period.
Water quality monitoring
Representative water samples 6 nos. one in surface water and five from ground
water i.e. dug well and tube well in buffer zone have been collected, preserved
and transported to R&C Environmental Egg. Laboratory, Chennai and analyzed
as per standard methods.
Noise levels recording
Noise levels were recorded by using CYGNET Integrated sound level meter
(100X) from Six ambient air quality locations during day time and night time at
an interval of four hours for one day for two months.
Soil quality monitoring
Soil samples from three locations, one in core zone, two in buffer zone were
collected at depths of 30, 60 and 100 cms and analyzed for various physico-
chemical, engineering and fertility parameters.
DATA ANALYSIS AND RESULTS
Micrometeorology
The wind velocity readings were ranging from 1.0 - 20.2 m/sec. Predominant
wind was from North-West direction. The maximum temperature recorded was
47.0C and the minimum was 22.5 C. The relative humidity ranges from 25% to
100% and 29.4 cm rainfall was recorded during the study period.
Air quality
Core zone
The Suspended Particulate Matter (SPM) values were ranging from 121 g/m3 to
260 g/m3 PM10 and PM2.5 values are ranging from 62 g/m3 to 90 g/m3 and
30 g/m3 to 44 g/m3 respectively. SO2 and NOx values are varying between
15.5 to 20.0 g/m3 and 20.1 to 27.6 g/m3 respectivelyThe heavy metals like
Arsenic ( As) and Mercury ( Hg) were found to be Below Detectable Limit ( BDL)
and other metals like Nickel ( Ni), Lead ( Pb) and Chromium ( Cr) values are
found to be very low and negligible. All the values are found to be well within
the NAAQ Standards prescribed by CPCB.
Buffer zone
The Suspended Particulate Matter ( SPM) values were ranging from 84 g/m3 to
237 g/m3PM10 and PM2.5 values are ranging from 31 g/m3 to 83 g/m3 and
16 g/m3 to 27 g/m3 respectively. SO2 and NOx values are varying between
12.5 to 17.6 g/m3 and 14.6 to 24.3 g/m3 respectively. respectivelyThe heavy
metals like Arsenic ( As) and Mercury ( Hg) were found to be Below Detectable
Limit ( BDL) and other metals like Nickel ( Ni), Lead ( Pb) and Chromium ( Cr)
values are found to be very low and negligible. All the values are found to be
well within the NAAQ Standards prescribed by CPCB.
Water quality
The water samples (6 Nos.) collected from different water sources i.e. Surface &
ground water etc. are analyzed as per procedures outlined in IS: 2488 / IS: 3025
/APHA.
At all locations, Oil and grease, phenolic compounds, cyanides, sulphides and
insecticides are found to be absent and all heavy metal values except Iron and
Zinc are found to be below the detectable limit. In general, the water quality at all
six locations are found to be well within the prescribed norms of IS: 10500 - 1991
(permissible limit) and IS: 2296 - 1982
Noise levels
Mean Leq noise levels at day time and night time are ranging from 64.9 to 67.8
dB(A) and 54.8 to 57.4 dB(A) respectively in the core zone. Mean Leq noise levels
at day time and night time are ranging from 43.2 to 49.1 dB(A) and 38.8 to 41.9
dB(A) respectively in the Buffer zone. While comparing with IS: 4954 -1986 norms
for acceptable outdoor noise levels all values are found to be well within the
prescribed limits.
Soil quality
The soil quality of the project area appears to be good and would support
vegetation after suitable reclamation / modification.
CONCLUSIONS
The following conclusions are drawn based on the baseline data collected at
core and buffer zone area.
i) Ambient air quality parameters viz., PM10, PM2.5, SO2, NOx, and all heavy
metals are well within the NAAQ standards 2009 prescribed by CPCB.
ii) The quality of ground water in and around the project site are exceeding
the IS: 10500-1991 desirable limit. The observed values were well within the
permissible limit of IS: 10500-1991. The quality of one surface water of
Wartha River found to be good and well within the IS 2296 Norms.
iii) The Noise levels in residential and commercial areas in respect of buffer
zone and Industrial area in respect of core zone are within the norms of IS:
4954 - 1986.
iv) The soil quality in the project area appears to be good and would support
vegetation after suitable reclamation measures.
10.7 Anticipated Impacts & Pollution Control Measures
AIR POLLUTION IMPACT ASSESSMENT
The impact assessment has been carried out dealing with the following
points:
(a) Phase-wise inventory of air pollution emission sources
(b) Impact assessment
a. Phase-wise inventory of air pollution emission sources
The pollution sources are obvious and to assess the impact, the project life
is divided into following time frames:
Operation phase
Post-operational stage
The activities associated with these time frames and having impact on the
ambient air quality along with the pollutants are enumerated in the
following sections:
Operational phase
During this phase, activities necessary for mining of coal, its handling and
transport are taken up. Such activities having impact on ambient air
quality are detailed below:
(i) Drilling : Dust
(ii) Blasting of coal and
overburden
: Dust and noxious gases
(iii) Handling of coal : Dust and noxious gases
(iv) Overburden handling : Dust and noxious gases
(v) Dump formation (internal) : Dust and exhaust fumes from
dumpers and dust till the
development of green cover
(vi) Movement of vehicles : Dust and noxious fumes
Post-operational stage
During this stage of the project, the activities related to the closure of
mine are to be carried out. Preparation of mine closure plan shall be
carried out during the period four to five years before the closure of the
mine. Some of the activities for the closure are:
Modifications in physical and biological reclamation of backfilled area
Salvaging and shifting operation of HEMMs and other equipment
Clearing of coal and other materials, restoration of infrastructure
area & colony area to the extent possible and necessary if not useful
for other projects
Management of hydrology and hydrogeology.
Redeployment of workforce, etc.
Arrangement & implementation of post-operation monitoring mainly
keeping watch, vigil, etc.
The activities having impact on the ambient air quality are enumerated
below:
(i) Movement of HEMMs for physical
reclamation of backfilled area
: Dust and obnoxious
fumes
(ii) Movement of vehicles for shifting and
salvaging operation of HEMMs and other
equipment
: Dust and obnoxious
fumes
(iii) Movement of vehicles for clearing of coal
and other materials
: Dust and obnoxious
gases
b. Impact assessment
The mining and its related activities create ambient air pollution. The
impact of mining on ambient air quality are highlighted in the following
paragraphs:
(a)The ambient air quality is influenced due to the presence of RPM, SPM,
SO2, NOx, etc., which are generated due to various activities like drilling,
blasting and handling related to the project. Further, the ambient air
quality is affected marginally to a varying degree due to the mining
activities of other nearby opencast and underground coal mines of the
same coalfield. The concentration of pollutants may vary depending
upon the various micro-meteorological parameters and the seasons of a
year.
(b) The baseline ambient air quality has been generated at six locations
surrounding the existing Junad OC to assess the present ambient air
quality scenario corresponding to the pre-mining status of the proposed
Deep Extension OC project. The details of baseline data have been
given in previous chapter. All the monitored parameters are well within
the permissible limit. Thus it can be concluded that although the mine
under consideration as well as the neighbouring mines are operating
since long but ambient air quality in the surrounding area has not been
affected adversely.
Now, with the proposed expansion in production capacity in the
existing OC project, there is likelihood of addition of pollution to the
existing concentration level of different attributes of ambient air. Efforts
will be made by implementation of proper abatement measures so as
to maintain the sinking capacity of ambient air to absorb the
additional load, if any, thereby maintaining the quality of ambient air
to the pre – mining level to the extent possible.
(c) Further, as per TOR received from MOEF, AAQ Prediction modeling has
been done with FDM and it has been found that there will be
insignificant increase in the level of pollutants as such there will be
negligible impact on the Ambient air quality due to proposed
expansion of the mine.
Existing Ambient Air Quality Monitoring
The ambient air quality monitoring is being carried out on regular basis as per
the Env (Protection) Amendment Rule, 2000 so as to ascertain the likely load of
various air pollutants and thereby suitably modifying the various control
measures.
Hence , it is expected that pollution load to be generated due to increased
production at Junad OC will be well within the permissible limit as the existing
air pollution control measures will be further strengthened with close monitoring
for efficient & effective implementation of the pollution control measures to
make the operation eco-friendly and it is expected that ambient air quality will
have no harmful effect on human being, flora and fauna, soil quality, surface
structures and aesthetic value of the surrounding environment.
AIR POLLUTION CONTROL MEASURES
Since Junad OC is an operating mine, the environmental monitoring data
generation is being done at four locations on regular basis as per the Env
(Protection) Amendment Rule published Vide Gazette of dated 25.9.2000. In
addition to data generation, following abatement measures have also been
taken in order to suppress the dust and noxious gases generation to the
maximum possible extent.
Drilling Operations
In order to reduce dust generated by drilling operation wet drilling is done.
Blasting Operation
In order to minimize the generation of dust during blasting, the following
measures are adopted:
(a) Blast holes are properly placed/spaced/positioned.
(b Blast is properly designed in respect of hole-spacing. Hole placing and blast
design are looked into as a fresh case every time, by a competent
Blasting Officer who takes into consideration the actual geo-mining
conditions of the site.
(c) Blasting is being done between shifts or during the rest interval when the
minimum number of persons is present around the blast area. In order to
quickly disperse the dust generated in blasting operations, blasting is
avoided when there is wind. Blasting is avoided in the mornings and during
cloudy situations.
(e) Adaptation of Controlled Blasting Technique as permitted by DGMS.
Loading & Transport
Movement of vehicles and HEMM on haul roads, particularly when they are un -
metalled, is another major source of dust generation. To minimize dust
generation due to this operation, the following abatement measures will be
taken.
(a) All long-life haul roads and service roads are properly constructed and
metalled. Unmetalled roads are being kept free of ruts, potholes etc.
(b) All haul-roads are regularly sprayed with water. Water sprinklers are
regularly used in the project.
(c) Overloading of vehicles are avoided.
(d) Covering of loaded trucks by tarpauline.
(e) Regular cleaning of transportation roads.
(f) Adequate green belt have been developed all along the coal
transportation road on both sides.
All the above-mentioned control measures will be continued during the
balance life of the project.
OB Dumps
On the dump slopes and top surface, plantation of grass and trees will be done
in phases and the details are as follows ;- Stage-wise Cumulative Plantation
year Green Belt
External Dump(OB +
Top Soil) Backfilled area
Others (undisturbed
area/etc.) Total
1 Area (ha)
No. of trees
Area (ha)
No. of trees
Area (ha)
No. of
trees
Area (ha)
No. of trees
Area (ha)
No. of trees
2 1st year
0 0 0 0 0 0 0 0 0 0
3 3rd year
0 0 0 0 0 0 0 0 0 0
4 5th year
0 0 25 62.5 0 0 10 25 35 87.5
5 End of mine life
0 0 110 275 0 0 145.93 364.825 255.93 1
6 Post mining
0 0 175 437.50 0 0 157.93 394.825 332.93 832.33
Coal Handling Plant
Lot of dust is generated in coal handling plant during operations like coal
crushing, transfer and conveying. Following abatement measures are adopted
for Coal Handling Plant.
i) Enclosure of the crusher house where maximum dust is generated. Also
installation of dust suppression system in the crusher house (specially
above the hopper in such a way that air borne dust is suppressed without
adding much water to the coal).
ii) Minimising the height of coal-fall at transfer points (to reduce dust
formation) and, if necessary, installing dust suppression measures.
iii) Enclosure of the belt conveyor to reduce the generation of dust due to
blowing wind.
iv) Creation of a green belt on both sides of belt conveyors and around coal
stocks and the CHP building.
Noxious gasses are emitted through exhaust fumes during the operation of
diesel / petrol operated equipment. In order to reduce such emission, regular
maintenance of the diesel / petrol operated vehicles will also be carried out so
that the emissions from these vehicles are under control. However, wherever, the
condition will permit, petrol / diesel operated HEMM will be replaced by
electrically operated ones.
Water sprinkling on coal stock/face, blanketing of exposed surface will be
carried out to avoid spontaneous heating and minimize air pollution.
WATER QUALITY
Impact Assessment on Water
Identification of the sources of water pollution
Likely sources of water pollution from this project along with the type of
pollutants are as follows:
(i) Sanitary (domestic) wastewater : Suspended solids and BOD.
(ii) Industrial wastewater from
workshop
: Suspended solids, oil & grease;
(iii) Wastewater from mine : Suspended solids of coal, clay
and oil;
(iv) Surface run-off passing through
coal stockpiles
: Suspended solids;
(v) Storm water from leasehold
area and built-up area
: Suspended solids.
Impact assessment
Mining and its related activities may create water quality problems. The
impact of mining at the project on both surface and ground water
sources has been assessed and given below:
(a) Surface water sources
Deterioration of water quality and pollution of water bodies due to
discharge of mine effluent, if not treated. Change in relief pattern
due to mining may cause flooding, siltation, choking and pollution.
Mitigatory measures would involve provision of (i) garland drains on
periphery to prevent surface run-off from entering into the quarry ,
(ii) catch drain around the dumps for avoiding siltation and (iii)
sedimentation ponds for reducing the pollution of surface water
bodies.
Possible overflow of water from nearby rivers/nallahs must be
safeguarded by stone pitching and strengthening the embankment
along the side of the water course
In order to assess the existing quality of surface as well as ground
water quality surrounding the project site , water samples from six
locations have been collected & analysed .
The details are incorporated in the previous chapter. All the
parameters are well within the permissible limit.
The mine water discharge quality of existing opencast project is
being monitored regularly as per Env. (Protection) Amendment Rule
, 2000 . The result indicates that even in untreated condition mine
pumped out water does not contain any pollution load.
However, due care will be taken to treat the mine water discharge
by sedimentation for the proposed project. Effluents from workshop
is continue to be treated in ETP and moreover water will be mostly
recycled in Workshop & CHP. As such, possibility of adverse impact
on natural watercourses after mixing is very remote. Garland drain
around the OB dump & coal dump will be made to avoid siltation
of natural water course.
Based on the data collected at the existing coal mine, it can be concluded that
the impact due to proposed mining operation, the adverse impacts on water
both surface as well as ground water will be insignificant.
WATER POLLUTION CONTROL MEASURES
Salient controls measures have been taken are as follows:
i) Industrial Effluent
The wastewater from workshop and CHP, which normally remain laden with oil
and grease, suspended and dissolved solids etc. are treated in the Effluent
Treatment Plant (ETP). Clear water coming out from the treatment plant is taken
into the closed water circuit and recycled for its reuse. All parameter of ETP
waste discharge are monitored regularly as per Env. (Protection) Amendment
Rule, 2000 and found to be within permissible limits.
ii) Mine Water
Most of the suspended particles are settled in the mine sump as initial settlement
and the supernatant water is pumped out. This water is passed through
sedimentation pond on surface, before being discharged in to natural drain.
iii) Surface Run-off
Adequate numbers of vegetation will be grown on the top surface and slopes
of the dumps in order to arrest the erosion of soil and it also reduces surface run-
off, which helps averting siltation of natural watercourses.
Catch drains of suitable size have been provided around periphery of the OB
dump as well as soil dumps to arrest site and sediment flows from the respective
dump sites.
In case of OB benches in the quarry, cross drainage have been provided which
carries silt and sediments into main sump made at the floor of the seam which
will accumulate all the silts and act as first stage settling pond. The water is then
pumped out through pumps on to the surface and discharged in to surface
settling tank/sedimentation pond. The clear water from the surface
sedimentation tank is used for watering the mine area, roads and green belt
development. The catch drains mentioned above are regularly desilted and
maintained properly. In addition, garland drains have also been provided
around the periphery of the excavated area, which carries surface run off and
the drains are regularly desilted before onset of monsoon. These drains allow
accumulation of silt materials and sufficient retention time for settling of silt
materials.
The domestic sewage disposal arrangement has been provided in the township.
Regular water quality/effluent quality monitoring is also carried out so as to
ascertain the likely load of pollutants and thereby suitably modifying the control
measures.
The existing water pollution control measures can be summarized as below :-
MINE WATER :- TWO STAGE SEDIMENTATION
INITIAL SEDIMENTATION - AT MINE SUMP
(SIZE- 800mX60mX4m)
FINAL SEDIMENTATION - SEDIMENTATION POND AT
SURFACE (SIZE- 24mX8mX1.5m)
INDUSTRIAL / WORKSHOP EFFLUENT:
WORKSHOP EFFLUENT IS BEING TREATED IN
WORKSHOP ETP .
DOMESTIC EFFLUENT:
THERE IS ONE INTEGRATED DOMESTIC EFFLUENT
TREATMENT PLANT AT COMBINED TOWNSHIP(0.6MLD) AT BHALAR.
EXISTING WATER POLLUTION CONTROL MEASURES
In addition to the above, provision have also been made for augmentation/
strengthening of existing sedimentation pond as well as Workshop Effluent
Treatment Plant.
NOISE QUALITY
In order to assess the existing ambient noise level in the surrounding of proposed
project site corresponding to pre-mining scenario , baseline noise level data has
been generated & details are enclosed as Annexure – III. All the values are well
within the permissible limit.
Proposed mine would be associated with following activities that may generate
noise during operation :
(a) Drilling
(b) Blasting
(c) Shovel operation
(d) Dozing
(e) Movement of dumper
(f) Operation of CHP / Workshop
The following are some of the important activities responsible for high noise level
generation, with their expected noise levels :
a. All mining activities i.e. drilling, blasting, shoveling, dozing and
dumping are associated with high noise level [about 100 dB(A)].
b. Operation of most HEMMs produce high noise level. The noise level
are in range of 80 – 100 dB(A). Noise level have been found to be
related to engine capacity.
c. Crusher – General noise level due to crusher ranges from 90 dB(A) –
105 dB(A). Some of noisy equipment produce noise whose level is
around 120 dB(A).
The average sound pressure level of some of the HEMM associated with mining
operation which are responsible for high noise level generation are as follows :
EQUIPMENT NOISE LEVEL
[dB(A)]
Dozer 98
Dumper 92
Power shovel 93
Drilling machine 96
ACCEPTABLE INDUSTRIAL NOISE LEVEL
As per Env. (Protection) Amendment Rules, 2000 the ambient air quality
standards in respect of noise in industrial , commercial , residential and silence
zones area as follows :
Sl.
No.
Category of
area
Limits [dB(A)]
Day time (6.00 AM to 10.00 PM
)
Night time (10.00 PM to 6.00 AM )
1. Industrial 75 70
2. Commercial 65 55
3. Residential 55 45
4. Silence zone 50 40
Assessment of the degree of noise to which a workplace noise is harmful, is done
by comparing the values measured at workplace to the permissible limit
adopted by statutory bodies like DGMS.
The impact of mining on ambient noise quality are highlighted in the following
paragraphs:
(a) The ambient noise quality is influenced by various activities like drilling,
blasting and material handling related to the project. Further, the ambient
noise quality is affected marginally to a varying degree due to the mining
activities of other nearby opencast and underground coal mines of the
same coalfield.
(b) The baseline ambient noise quality has been generated at six locations
surrounding the existing Junad OC to assess the present ambient noise
quality scenario corresponding to the pre-mining status of the proposed
Deep Extension OC project. The details of baseline data have been given
in previous chapter. All the monitored parameters are well within the
permissible limit.
(c) Thus it can be concluded that although the mine under consideration as
well as the neighbouring mines are operating since long but ambient
noise quality in the surrounding area has not been affected adversely.
Now, with the proposed expansion in production capacity in the existing OC
project, there is likelihood of addition of noise load to the existing concentration
level of ambient noise. Efforts will be made by implementation of proper
abatement measures so as to maintain the sinking capacity of ambient noise to
absorb the additional load, if any, thereby maintaining the quality of ambient
noise to the pre – mining level to the extent possible.
NOISE POLLUTION CONTROL MEASURES
Monitoring of the noise control will be carried out on regular basis as per the Env
(Protection) Amendment Rule 2000. While planning for an effective noise
attenuation measures, the concept of source, path and receiver has been
considered.
(A) Noise Control at Source
There are two areas where the noise generation can be checked at source.
(i) Proper Design
Since the generation of noise can be reduced by reducing the vibration
amplitude, the area of vibrating part and frequency of vibration will be taken
care that all loose contact between metal parts avoided.
Shock absorbing pads will be fixed in the foundation of vibrating equipment /
machines. In case of aerodynamic noise producing sources, mufflers will be
provided with the machines.
(ii) Proper Maintenance
All machines and equipment will be properly maintained. Sound muffler system
and bearing lubricating system etc. of equipment will be kept in proper
condition.
(B) Noise Control at Receiver End
Even after adopting above measures, if desired noise level is not achieved at
receiver end, in that case, following measures are suggested:
(a) The workers exposed to high noise level are provided with earplugs.
(b) Provision of enclosed booths at the worksite to protect worker from noisy
environment.
IMPACT ON LAND
LAND USE (CORE ZONE)(contd.)
6.10 ha--
449.63 ha
NIL
443.53 ha
TOTAL
174.28 ha
NIL
174.28 ha
LAND
ALREADY
ACQUIRED
275.35 haTOTAL
NILFOREST LAND3.
6.10 haGOVT. LAND
(WASTE LAND)
2.
269.25 haAGRICULTURAL
LAND
1.
LAND TO BE
ACQUIRED
PARTICULARSSL.
NO
FORESTRY CLEARANCE
The during-mining land use is as follows: -
CHANGE IN LAND USE DURING MINING
67.43RATIONALISATION AREA6
70.50BLASTING ZONE5
449.63
20.00
15.00
175.00
101.70
AREA (ha)
TOTAL
EMBANKMENT4
INFRASTRUCTURE INCLUDING
APPROACH ROAD ETC.
3
EXT. OB DUMP2
QUARRY AREA1
PARTICULARSSL. NO.
LAND RECLAMATION / LAND MANAGEMENT
The following activities have been proposed for reclamation of land.
1. Backfilling of the excavated area to the extent possible.
2. Leveling of the backfilled area and carpeting with the topsoil.
3. Creation of garland drains in order to arrest the silt load, due to erosion, to
enter into natural watercourses during surface run-off.
TOTAL ML/PROJECT AREA (ha)
TOTAL FORESTLAND (ha)
Date of FC Extent of forestland
Balance area for which FC is yet to be obtained
Status of appl. for diversion of forestland
If more than one, provide details of each FC
449.63 Nil Not Applicable
Not Applicable
Not Applicable Not Applicable
4. Grass, legumes and different types of plants etc. will be planted on such
reclaimed land in order to make it, as far as possible, conducive to
agricultural growth.
5. Technical and biological reclamation of external OB dump.
The density of trees is around 2000 – 2500 plants/Ha.
OB Management
Project Total waste generation
(Mm3)
Topsoil (Mm3)
Total OB generation
(Mm3)
Total OB in Ext. Dump
(Mm3)
Total OB Backfilled
(Mm3)
Original Project (ha) 10.33 Included in OB
10.33 9.58 & 0.75 in
Embankment
----
Expansion Project (ha) (balance life)
50.62 Included in OB
50.62 50.62 ----
TOTAL (Mm3)
60.95 60.95 60.20 & 0.75 in
Embankment
The capacity of external OB dumps proposed is about 60.20 Mm3. Remaining 0.75 Mm3 of OB will be used is construction of safety embankment.
The break up of OB quantities in external OB dumps is given in following table.
No. Dump Capacity in Mm3
0-30m 0.60m Total
i) Dump – 1 25.70 16.95 42.65
ii) Dump – 2 10.30 7.25 17.55
Total 60.20 SCHEDULE OF OVERBURDEN DUMPING
The following Table No. 8.3 shows the yearwise OB dumping in external OB dump No.1 and No.2
Year Programmed Excavation of
OB(Mm3)
External OB Dump-1 (Mm
3)
External OB Dump-2
(Mm3)Excluding
Rehandling
1. 8.15 8.15 -
2. 7.40 7.40/15.55 -
3. 5.26 5.26/20.81 -
4. 5.25 5.25/26.06 -
5. 5.25 5.25/31.31 -
6. 4.70 4.70/36.01 -
7. 4.50 4.50/40.51 -
8. 4.40 2.14/42.65 2.26
9. 4.40 - 4.40/6.66
10. 1.10 - 1.10/7.76
11. 0.21 - 0.21/7.97
Total 50.62 42.65 7.97
Points for reclamation of void of Junad OC Extn. mine
i. Due to steep gradient and in order to maintain proper haul road of 1 in 16
gradient it will not be possible for backfilling of the void in the present
proposal.
ii. In order to backfill the void of Junad Extn. OC to the extent of –35 m it is
proposed that the OB of adjacent Pimpalgaon Extn. OC could be utilized.
iii. The approx. quantity of OB of proposed Pimpalgaon Extn . OC is 200 M.Cu.m.
and is at a distance of about 5 k.m.
iv. This will simultaneously help in reduction of land required for external OB
dump of proposed Pimpalgaon Extn. OC.
Post mining land use plan (Conceptual)
The post-mining land use pattern at Junad Extn. Deep OCP will be as follows:-
Post-mining Landuse pattern of ML/Project Area (ha)
S.N. Land use during mining
Land use (ha)
Plantation Water Body Public use Undisturbed Total
1 External OB Dump 175 0 0 0 175
2 Top soil dump 0 0 0 0 0
3 Excavation 0 101.7 0 0 101.7
4 Roads including embankment
17 8 25
5 Built up area 3 0 7 0 10
6 Green Belt 0 0 0 0 0
7 Undisturbed Area 137.93 0 0 0 137.93
Total 332.93 101.7 15 0 449.63
Stage-wise Cumulative Plantation
year Green Belt
External Dump(OB +
Top Soil) Backfilled area
Others (undisturbed
area/etc.) Total
1 Area (ha)
No. of trees
Area (ha)
No. of trees
Area (ha)
No. of
trees
Area (ha)
No. of trees
Area (ha)
No. of trees
2 1st year
0 0 0 0 0 0 0 0 0 0
3 3rd year
0 0 0 0 0 0 0 0 0 0
4 5th year
0 0 25 62.5 0 0 10 25 35 87.5
5 End of mine life
0 0 110 275 0 0 145.93 364.825 255.93 1
6 Post mining
0 0 175 437.50 0 0 157.93 394.825 332.93 832.33
10.8 ENVIRONMENTAL MONITORING –
The environmental monitoring programme at present is being carried at the
mine and will be continued as per details given below: -
S
N
Items Parameters Frequency No. of
Stations
1 Ambient
Air Quality
Monitoring
SPM, RPM, SO2,
Nox, CO & Fugitive
dust
Every Fortnight as per
EPA, Rule 2000
4
2 Water
Quality
Monitoring
1) 4 Parameters
viz. p H, Total
Suspended Solids
(TSS), Chemical
Oxygen Demand
(COD) & Oil and
Grease.
2) 35 Parameters
Every Fortnight
Once in a Year
2
3 Noise
Quality
Monitoring
Noise Levels Every Fortnight 2
4 Environme
ntal
Statement
Annual
5 Ground
Water
Level
Monitoring
& Quality
Water Level &
Quality
Parameters.
Water Level –
Quarterly.
Water Quality – Yearly.
In Buffer
Zone
Villages.
6 Complian
ce Report
of EC
Conditions
All conditions both
Specific & General
1st June &
1st December
Not
Applica
ble
10.9 PUBLIC CONSULTATION
The Environmental Public Hearing in respect of proposed Junad Opencast
Expansion Project of M/s Western Coalfields Ltd., Wani North Area, Tal. Wani ,
Dist. Yavatmal for enhancement in production capacity from 0.60 MTPA to 1.50
MTPA and increase in lease area from 174.28 ha to 449.63 ha was held on
05/02/2013, 11.00 am at Kamgar Manoranjan Kendra, Bhalar Township, At Post
Bhalar, Tal. Wani, Dist. Yavatmal. The public hearing was conducted under the
Chairmanship of Shri Rajendra Deshmukh, Additional District Magistrate,
Yavatmal (The representative nominated by District Magistrate, Chandrapur).
Shri S.D.Patil, Sub Regional Officer, MPCB, Chandrapur was the Convener of the
Public Hearing. Shri N.G. Nihul, Regional Officer, MPCB, Chandrapur was the
Member of Public Hearing panel. Shri M.P.Barhanpurkar, District Mining Officer,
Yavatmal, Shri L.S.Varhade, SDO, Wani and Shri Misal, Tahsildar,Wani were also
present during the public hearing. The public hearing started at 11.00 am with
the permission of the Chairman of the Public Hearing Panel.
First of all, the Convener welcomed all present for Public Hearing. He told that,
the Public Hearing is being conducted as per the provisions of EIA Notification
dated 14/09/2006 and amended Notification dated 01/12/2009 of Ministry of
Environment & Forests, New Delhi. He told that the project proponent received
TOR (Terms of Reference) for this project from Ministry of Environment & Forests,
New Delhi on 11/07/2008. Accordingly, project proponent prepared Draft EIA &
EMP Report and submitted their application on 15/02/2010 to the Board
requesting for conducting the Public Hearing.
The Public Hearing for this project was earlier scheduled on 31.08.2010 and
21.12.2010 but during hearing it was cancelled at both the times due to some
reasons. Thereafter, the public hearing was scheduled on 10.10.2012. The public
notice for the said public hearing was published on 08.09.2012 in Daily Lokmat
(Marathi) and Daily Hitawad (English) stating date, venue and time of public
hearing. The said public hearing was postponed due to some unavoidable
reasons at that time as per District Collector, Yavatmal letter no. 937/2012 dated
06.10.2012. The notice about postponement of Public Hearing was published in
Marathi Dialy Lokmat and English Daily Hitavada on 08.10.2012. Afterwards the
public hearing is scheduled on 05.02.2013 and the public notice in this behalf
was published on 02.01.2013 in Daily Lokmat (Marathi) and Daily Hitawad
(English) stating date, venue and time of public hearing.
The copies of Draft EIA/EMP and Executive Summary in English and Marathi were
made available vide letter no. 1288/2010 dated 28.07.2010 to the offices of
District Collector, Yavatmal, District Industries Centre, Yavatmal, Zilha Parishad,
Yavatmal, MPC Board (HQ), Mumbai, Regional Office and Sub Regional Office,
MPC Board, Chandrapur, Environment Department, Mantralaya, Mumbai, Tahsil
Office, Wani and offices of the concerned Gram Panchayat Pimpalgaon, Tal.
Wani for the knowledge of concerned. While issuing the notice of
postponement, it was requested to above offices for making available the
documents submitted by project proponent for the concerned to study till the
date of Public Hearing. Also, through this notice it was requested to file their
objections/suggestions within 30 days from the date of public notice to the Sub
Regional Officer, MPC Board, Chandrapur. The Member Secretary, MPC Board,
Mumbai has issued the Panel Order no. E-15 of 2013 dated 29/01/2013 for the
Public Hearing.
The Minutes of Public Hearing in respect of proposed Junad Opencast Expansion
Project of M/s Western Coalfields Ltd., Wani North Area, Tal. Wani , Dist.
Yavatmal conducted on 05/02/2013 11.00 am Kamgar Manoranjan Kendra,
Bhalar Township, At Post Bhalar, Tal. Wani, Dist. Yavatmal is enclosed herewith at
Annexure – III.
10.10 PROJECT BENEFITS
The benefits of the project can be summarized as below:-
- The physical infrastructure in the area will be improved substantially by
following ways:-
a) Development of road, thereby improving the communication.
b) Improvement in Power, Telephone (including Mobile) facility.
c) Improvement in Health Care facility & Educational facility.
d) Improvement in Market / Trade & Business.
- The social infrastructure by way of cultural mixing of people of other states with
local community glorifying “UNITY IN DIVERSITY”.
- Substantial employment in the project & indirect employment for business &
trading, contractor, transportation, vehicle contractor, nursery development.
10.11 ENVIRONMENT MANAGEMENT PLAN
Close monitoring of the environment and implementation of various protective
measures discussed in the report forms an important part of EMP. In the earlier
chapters the causes of various pollutions along with the preventive and
mitigating measures have been discussed. In this chapter description of the
administrative aspects of ensuring that mitigative measures are implemented
and their effectiveness monitored, after approval of the EIA is being discussed.
MONITORING ORGANISATION
To have a close watch on the environmental condition and implementation of
the various measures suggested, a multi-disciplinary approach is essential.
(a) WCL headquarter acts as an apex body which supervises the activities
relating to environment at project level through the General Manager.
(b) General Manager of the area coordinates the activities of various disciplines
in the area to render all necessary assistance at the implementing level i.e. the
Project. Area Nodal Officer (Environment) monitors all aspects of environment
on behalf of the General Manager. He also takes suitable steps for generation of
environment data along with its analysis and interpretations.
As far as plantation is concerned horticulturist with suitable backup staff shall be
provided in the area for undertaking the plantation jobs including raising of a
nursery. Plantation will have to be done on a large area.
Therefore, it may be desired that an outside agency may have to be employed
for this purpose. The horticulturist along with the supervisor shall only monitor and
guide the agency for selection of site, treatment of soil, selection of species etc.
(c) Sub Area Manager is responsible for mechanical reclamation of the area. He
is also responsible for biological reclamation with the assistance of GM's office.
ORGANISATION FOR ENVIRONMENT MANAGEMENT
Sl. No. Measures/Actions Agency
1. Environmental
Control
1 Chief General Manager, Wani North Area
2 Nodal Officer, (Environment),
Wani North Area
3 Project Officer, Junad OC
4 Staff Officer (Civil), Wani North Area
5 Environmental Cell (WCL H.Q.)
2. Environmental
Monitoring
1 Chief General Manager, Wani North Area
2 Staff Officer (Civil), Wani North Area
3 Nodal Officer (Environment),
Wani North Area
4 Project Officer, Junad OC.
5 Environment Cell of
WCL Headquarters
6 Environmental Laboratory of
CMPDI, RI-IV
3. Reclamation 1 Project Officer, Junad OC.
2 Nodal Officer (Environment),
Wani North Area
3 Environmental Supervisor
4 Horticulturist
10.12 DISCLOSURE OF CONSULTANTS ENGAGED:
CMPDI is an ISO 9001 company and one of the subsidiary companies of Coal
India Ltd. (CIL) – A Nava Ratna Company. Its registered corporate office is
situated at Gondwana Place, Kanke Road, Ranchi-834008, a capital cityof
Jharkhand state. It operates through the strategically located Regional Institutes
over six states territories of India. These Regional Institutes are engaged in
exploration, planning & design works of other subsidiaries companies of CIL,
namely, ECL, BCCL, CCL, MCL, NCL, WCL, SECL and NECL.
The company was formerly known as Coal Mines Authority Limited. And, the
Central Mine Planning & Design Institute Limited (herein after called as CMPDI) is
a planning & design division of Coal India Limited (herein after called as CIL) as
per Memorandum of Association of the company. The CIL is a holding company
since November 01, 1975, and the CMPDIL is one of its subsidiaries since then. It is
under Ministry of Coal, Government of India
10.13 CONCLUSION
From earlier paragraphs, it can be inferred that the adverse impact on physical
environmental attributes due to proposed mine is almost insignificant/ negligible.
CHAPTER-XI
DISCLOSURE OF CONSULTANTS ENGAGED
11.1 Name of Consultant
Central Mine Planning & Design Institute Limited briefly, it is called as ‘CMPDI’. It
is an ISO 9001 Company.
Its registered corporate office is situated at Gondwana Place, Kanke Road,
Ranchi – 834008, a capital city of Jharkhand State. It operates through seven
strategically located Regional Institutes over six states territories of India. Details
of all seven Institutes including its corporate office are given as in Table-11.1.
Table-11.1
SN Offices Addresses Tel/Fax
Postal E-Mail Website
1 Corporate Gondwan
a Place,
Kanke
Road,
Ranchi-
834008,
Jharkhand
c.in,
cmpdihq@cmp
di.co.in
http://www
.cmpdi.co.i
n
+916512230483,22301
16 /+916512231447,
2232249
2 Regional
Institute-I
West End,
GT Road,
asansole –
713301,
West
Bengal
- - +913412253504/
+913412250935
3 Regional
Institute-II
Koyla
Bhawan,
Koyla
Nagar,
Dhanbad-
826005,
Jharkhand
+913262230850,22307
89/ +913262265575
4 Regional
Institute-III
Gondwan
a Place,
Kanke
Road,
Ranchi-
834008,
Jharkhand
+916512231506/
+916512231501
5 Regional
Institute-IV
Kasturba
Nagar,
Jaripatka-
440014
http://www
.cmpdi.co.i
n
+917122642134/
+917122643231
6 Regional
Institute- V
SECL
Complex,
Seepat
Road,
Bilaspur,
Chhatisgar
h.
+917752246482/
+917752246481
7 Regional
Institute-VI
CWS
Colony,
P.O.
Jayant
Colliery,
Sidhi-
486890,
M.P.
+917805222329,
222172/
+917805222330
8 Regional
Institute-VII
Griha
Nirman
Bhawan,
Sachiwala
ya Marg,
Unit 3,
Bhubanesh
war-
751001,
Orissa
+916742394357,
2394760/
+916742395128
All the above Regional Institutes are dedicated to render services to seven
subsidiaries of the CIL AS follows:
Table-11.2
Sl. No. Institutes Dedicated to
1 Regional Institute-I Eastern Coalfields Ltd. (ECL)
2 Regional Institute-II Bharat Coking Coal Ltd. (BCCL)
3 Regional Institute-III Central Coalfields Ltd. (CCL)
4 Regional Institute-IV Western Coalfields Ltd. (WCL)
5 Regional Institute-V South Eastern Coalfields Ltd. (SECL)
6 Regional Institute-VI Northern Coalfields Ltd. (NCL)
7 Regional Institute-VII Mahanadi Coalfields Ltd. (MCL)
Hqrs. Ranchi is committed to render services to NEC & Non-CIL clients and
specialized assignments for both CIL & Non-CIL clients.
11.2 Brief Resume of the Consultants:
11.2.1 Establishment Background:
The company was formerly known as Coal Mines Authority Limited. And, the
Central Mine Planning & Design Institute Limited (herein after called as CMPDI) is
a planning & design division of Coal India Limited (herein after called as CIL) as
per Memorandum of Association of the company. The CIL is a holding company
since November 01, 1975, and the CMPDIL is one of its subsidiaries since then. It is
under Ministry of Coal, Government of India.
11.2.2 Strength & Resources
a) Manpower:
CMPDI has more than 800 multidisciplinary technical executive professionals
who combine innovation and initiative to deliver faster and effective solutions in
planning, implementation and management of projects.
b) Resources:
CMPDI is equipped with modern laboratory facilities for undertaking various
analytical works to supplement its services. It has well equipped network of six
environmental laboratories located in various coalfields to regularly monitor air,
water and noise parameters. The central unit at Ranchi is accredited with
Central Pollution Board, New Delhi. Besides its own strength, CMPDI has access
to the vast resources with its principal, CIL, India’s largest coal producer and a
Nava Ratan Company.
11.2.3 Recognition:
CMPDI is recognized as preferred consultant by India and overseas clients,
United Nation agencies and international financial institutions and the company
is registered with
World Bank
Asian Development Bank
African Development Bank
United Nations Development Programme
11.2.4 Main Functional Area:
The main functional area of the CMPDI is to provide adequate and up-to-date
planning, design and technological supports to the CIL and its coal producing
subsidiaries to enable them to produce the planned quantity of coal efficiently
and economically with due attention to safety, conservation, quality and
environment. In addition to these, CMPDI also provides necessary consultancy
for clients outside the CIL in India and abroad. The Quality Management System
of CMPDI, Ranchi is certified under international standard – ISO-2000 by BVQI
(UK). Services covered under are as follows:
Consultancy in Mineral Exploration and Environmental Management.
Planning & Design in Mining, Civil & Architectural Engineering, Coal
Preparation & Utilization, Electrical & Mechanical Engineering, Mining
Electronics, Geomatics and Mine Construction.
Laboratory testing facilities for the above
Technical & Management Training in Mineral & Mining Sector
11.3 Nature of consultancy rendered:
CMPDI has been offering services in the fields enumerated in Table – 11.3
Table – 11.3
Sl. No. Services Offered
1 Exploration & Resource Evaluation
2 Mine Planning & Design Services
3 Infrastructures Engineering
4 Environmental Services
5 Beneficiation Services
6 Management Services
7 Specialized Services
8 Laboratory Services
9 ITC in Mining
10 Research & Development
12.3.1 Exploration & Resource Evaluation:
New generation exploration technology coupled with skilled manpower has
made CMPDI a twenty first century leader in mineral exploration, deposit
modeling, resource evaluation, resource management, mining geology, hydro-
geological & geophysical studies, engineering, geological investigations etc.
Services rendered under this head are described in brief in Table-11.3.1
hereinafter.
Table-11.3.1
Sl.No. Sub-heads of
Services
Services Rendered in
1 Geological
Support for
mining
Production support or mine development drilling
and prediction of faults and pinch / wash outs.
Delineation of roof / floor and dirt bands
2 Drilling Coring-Diamond rotary drills up to a capacity of
1280 m depth
Non-coring-Direct rotary and DTH drills for
geophysical logging, hydro-geological
investigations, dewatering, etc.
3 Deposit
modeling
Using geo-statistical and geological software
packages including MINEX and in-house developed
CEMPGEODOC and SASLINT software
4 Resource
Evaluation
Deposits of coal, lignite, manganese, iron ore
(magnetite and hematite), phosphorite, coal bed
methane etc.
5 Resource
Management
Strategic planning for future exploration
depending upon market demand.
Updating of reserve / resource of individual
blocks or coalfields.
6 Hydro-
geological
studies
Systematic ground water investigations.
Mining hydro-geological studies
7 Geo-
engineering
works
Determination of strength properties of rocks and coal
and RQD (Rock Quality Designation) to assess strength
characteristics of strata
8 Master
planning for
assessment of
resource
potential with
respect to
CBM, globally
an emerging
environment
friendly
alternate
energy
source.
Creation of data packages of potential CBM
blocks.
Resource evaluation of CBM / CMM / AMM.
Formulation of policy guidelines for harnessing
CBM resources.
Implementation of CIL-ONGC Consortium’s
venture in developing CBM in coalfields.
To provide quality services, CMPDI is effectively utilizing technology like remote
sensing, combination drilling (coring and non-coring), multi-probe geophysical
borehole logging, seismic refraction survey etc.
CMPDI has already undertaken over 500 integrated exploration projects in
varying geological and terrain conditions.
11.3.2 Mine Planning & Design Services:
CMPDI is a premier consultant in open pit and underground mine planning &
design in coal, lignite and other minerals. It has prepared more than 950 mining
project reports with individual capacity up to 35 Million ton per annum. CMPDI
uses advance software like MINEX for resource modeling; mine planning and
scheduling of open cast and underground mine projects. It has helped its
subsidiaries to achieve unprecedented growth from open cast mines in their
organizations. Its experience in mechanized underground mining technology
spans exploitation of coal seams from 1.00 m to 20 m thickness, at different
gradients from flat to 750, with soft to extremely hard coal, liable to spontaneous
heating and gassiness and under varying roof strata conditions. Services offered
to be manifold and are enumerated briefly in Table-11.3.2.
Table-11.3.2
Sl. No. Services Offered
1 Master planning of coalfield
2 Perspective planning
3 Conceptual engineering studies
4 Techno-economic feasibility studies
5 Detailed project reports
6 Detailed engineering with working drawings
7 Mine ventilation & transport planning
8 Operational planning
9 Mining plans for mining lease
10 Mine capacity assessment
11 Performance analysis of equipment
12 Prediction of surface subsidence through numerical
modeling software
13 Geophysical logging, Seismic survey, Resistivity Survey.
11.3.3 Infrastructure Engineering:
CMPDI provides engineering logistic or support services for development of
infrastructure. It has developed multi-disciplinary engineering skills for
implementing projects of various complexities. In particular, it has offered
complete planning & design services for architectural planning, civil, structural,
electrical and mechanical engineering in various projects. A few of them are
enumerated in Table-11.3.3.
Table – 11.3.3
Sl. No. Services Offered
1 Planning of large capacity, high speed bulk material
handling plants
2 Turnkey execution of coal handling plants
3 Planning of high voltage sub-stations
4 Planning of workshops of various types and capacities
5 Township planning including roads, water supply, water
supply system, drainage, Water / sewerage treatment
plants and detailed planning and design of all township
infrastructure
6 Site selection of pit head thermal power plants based on
remote sensing data
7 Rail corridor alignment through remote sensing
8 Techno-economic feasibility study of captive power plants
based on pulverized coal and FBC technology
11.3.4 Environmental Services:
CMPDI holds a position of eminence in the field of environmental planning,
impact assessment, management and environmental engineering in coal and
other sectors. It is the nodal agency for co-ordination and monitoring of ongoing
environmental up-gradation schemes sanctioned by Ministry of Coal and Mines
under the head “Environmental Measures and Subsidence Control”. It
undertakes technical scrutiny of new proposals, visits to project sites and
disbursement of funds to the implementing agencies.
A few of the new areas in which CMPDI has diversified are environmental and
hydro-geological studies for disposal of fly ash, development of air quality
model, bio-treatment of industrial effluents, carrying capacity base
development planning, watershed modeling and rain water harvesting. Services
offered with respect to environmental quality monitoring, engineering,
management and planning are briefly given in Table-11.3.4.
Table-11.3.4
Sl. No. Sub-heads of
Services
Services rendered
1 Environmental
Monitoring
Air quality
Water quality
Noise level
Soil quality
Micro-meteorological studies
Stack monitoring
2 Environmental
Engineering
Industrial/ Municipal effluent
treatment and recycling plants
Hazardous waste disposal site
engineering
Municipal effluent disposal site
engineering
3 Natural resource
management
Land use planning
Rain water harvesting
Watershed management plans
4 Regional planning Regional environment
management plans
Regional environment status plans
5 Environment
assessment plans
Environment assessment plans
6 Special studies Review of existing mining and
environment policies, legislations,
standards and mechanisms for
monitoring compliance,
institutional strengthening for
regulatory and counterpart
institutions.
Study of environmental problems
and action plan for restoration of
environmental quality.
Mine closure planning
11.3.5 Beneficiation Services:
CMPDI specializes in planning, design and construction of new washeries and
modification of existing washeries for coal and mineral beneficiation. Services
with respect to beneficiation offered to are given in Table-11.3.5.
Table-11.3.5
Sl. No. Services Offered to for
1 Planning of coal and mineral beneficiation plants
2 Preparation of feasibility / project reports including macro
level analysis, washability studies, environmental impact
assessment and techno-economic analysis.
3 Technical studies, performance evaluation and operation
and maintenance related consultancy for existing washeries.
11.3.6 Management Services:
Management services enumerated in Table-11.3.6 have been offered by CMPDI
to different organizations or bodies.
Table-11.3.6
SN Sub-heads of Services Services rendered for
1 Coal Investment
promotion Services
Assistance to Government of India in
identification and assessment of coal mining
properties for investments through private
sector participation.
2 Quality Management
Services
Consultancy for implementation, certification
and maintenance of ISO 9001 Quality
Management System and its industry specific
translations, ISO 14001 Environment
Management System and OHSAS 18001
Occupational Health and Safety Assurance
System.
3 Human Resource
Services
Creating knowledge and skill based
workforce, CMPDI through its Staff Training
College (STC) imparts training to its clients’
personnel. Under UNDP, CMPDI has trained
professionals from Nigeria, Sultanate of Oman
and North Korea. Through its STC it has
organized training programmes under five
major categories such as (i) Technical, (ii)
Managerial, (iii) Computer application, (iv)
Quality Skills, (v) Quality System, etc. It has also
organized and conducted off-campus
training programmes with respect to Quality
System at various subsidiaries of CIL.
CMPDI diversified into management system consultancy in 1998. While
continuing to provide consultancy for ISO 9000 Quality Management System
(QMS) and ISO 14000 Environmental Management System (EMS), it made forays
into consultancy for ISO 17025 (Testing and calibrating laboratories) under
consultancy scope as:
Creation of Management system
Providing training support
Implementation, certification and post certification support
11.3.7 Specialized Services:
With a view to catering to specific requirements of clients, CMPDI has been
providing field oriented specialized services to its clients. Descript services
rendered under this category have been remote sensing, terrestrial survey,
blasting, ventilation design & gas assessment in underground mines, energy
audit and non-destructive testing. Main services rendered are described in brief
in Table-11.3.7.
Table-11.3.7
SN Sub-heads of Services Services rendered in
1 Geomatics Geomatic services in mining sector ranging fro
topographical survey, baseline data generation
and monitoring of land use / land cover for
environmental management, water resource
survey and coal mine fire mapping. It has also
imparted expertise services in the field of remote
sensing applications, terrain mapping, co-
relation survey for underground mines, GPS / GIS
survey, cartography and digital image
processing.
2 Blasting Carrying out controlled blasting and ground
vibration study, vibration monitoring,
fragmentation improvement studies, random
sampling & testing of explosives and accessories
and performance evaluation of new explosives
with sophisticated testing equipment, in both
coal and non-coal sectors.
3 Non-destructive Testing
(NDT)
Services for non-destructive testing of
components of machinery, installations and
other structural elements have been provided
at site during periodic maintenance to avoid
accidental failure.
4 Ventilation and Gas
Survey
CMPDI has been offering services for ventilation
monitoring, planning & design of ventilation
system including gas assessment and testing for
underground mines.
5 Energy Audit CMPDI is empanelled as an accredited energy
auditor with Govt. of West Bengal and
Petroleum Conservation Research Association
(PCRA) under Ministry of Petroleum and Natural
Gas, Govt. of India. Over 130 reports on
electrical and diesel energy conservation have
been prepared.
6 Inspection services CMPDI has been rendering pre-dispatch third
party inspection services for plants and
equipment at the manufacturers’ workstations
for materials procured by its clients.
7 Captive power plants Reports on optimum utilization, conceptual
notes and tender documents
11.3.8 Laboratory Services:
CMPDI has well equipped laboratories for carrying out investigations and
analysis for geo-chemical, petrography coal washability and geo-mechanical
properties.
For coal and lignite characterization, CMPDI has laboratories with highly skilled
manpower and state of art equipment. The data generated by these
laboratories form basis of characterization and grading of coal in exploration,
mine feasibility reports, washery design and down stream utilization. Brief
description of Laboratory Services rendered by CMPDI is given in Table-11.3.8.
Table-11.3.8
SN Sub-heads of Services Services rendered in
1 Geo-chemical
Laboratory
CMPDI has been rendering services like geo-
chemical analysis like proximate & ultimate
analysis, GCV determination of coal and lignite
and other special test through microprocessor
based automatic calorimeter and analyzer.
2 Petrographic
Laboratory
CMPDI has been carrying out evaluation for
hydro carbons, oil shales and coal bed
methane for coal coke and source rock through
sophisticated microscopes, identifying mineral
phases in coal, rocks and metal through X-Ray
diffractometer, and micro-area analysis and
cleat studies for CBM through Scanning Electron
Microscope accredited by International
Committee for Coal and Organic Petrology
(ICCP).
3 Mining Laboratory CMPDI has been determining physico-
mechanical properties of rocks for design inputs
for mine planning and other technical services
and undertaking testing of roof supports and
building materials for design support systems for
underground workings.
4 Washery Laboratory CMPDI has been determining washability
characteristics of coarse, small and fine coal
and shattering & pulverized characteristics of
coal for assistance in planning and design of
coal beneficiation plants.
7 Captive power plants Reports on optimum utilization, conceptual
notes and tender documents
11.3.9 IT Services in Mining:
CMPDI has been gearing up itself fully to meet challenges of IT sector requisite
for mining industries as per IT implementation scheme with a view to
revolutionizing mining industry and mining operations in coming years. IT services
provided by CMPDI have been tabulated in Table-11.3.9.
Table-11.3.9
Sl. No. Services Offered to for
1 Mine communication and mine safety systems
2 Establishing internet and internet facilities
3 Real time fleet management system for large OC mines
using GIS & GPS.
4 Land information system using enterprise GIS.
11.3.10 R & D Services:
The Research & Development activities in coal and lignite are being
administered through the Scientific Advisory Committee (SSRC) with Secretary
(Coal) as its Chairman. The committee is entrusted with the task of planning,
budgeting and overseeing the implementation of R & D programme in coal and
lignite sector and also for application of research findings. And, CMPDI is the
Nodal Agency to co-ordinate S & T / R & D activities in coal and lignite sectors
and assist SSRC in areas mentioned herein after.
CMPDI applied research and development in the field of mining, beneficiation,
utilization, environment, exploration, etc. serving as nodal agency for all S & T
schemes funded by Ministry of Coal and R & D schemes funded by R & D Board
of CIL (constituted in August 1995).
Field oriented research projects including transfer and absorption of new
technology concerning main areas of coal research have been as follows:
Production, productivity and safety.
Coal beneficiation and utilization.
Environment and Ecology.
***********************
Checklist
PROPOSED JUNAD DEEP EXTN. OC PROJECT
WESTERN COALFIELDS LIMITED
I. PROJECT DETAILS
1 Name of the project JUNAD DEEP EXTN. OC PROJECT
2 Name of the Company Address Tele No. E-mail
Western Coalfields Limited Coal Estate, Civil Lines, Nagpur – 440 001 0712 – 2510151 [email protected]
3 Latitude and Longitude of the project
Latitude : N 200 01’.05” to N 200 04’.10” Longitude : E 79o03’.09” to E 79o05’.00” Topo sheet no :55-P/4
4 If a Joint venture, the names & addresses of the JV partners
No
5 Details of Coal Linkage Linked to Thermal Power Plants of MAHAGENCO
6 Whether the project is in the Critically Polluted Area (CPA):
NO
7 Cost of the project Rs.54.7840 Crores ( Additional capital- Rs 38.7577 crores)
8 Whether new or expansion project If expansion:
Expansion Project - Enhancement in in production from 0.60 MTPA to 1.50 MTPA and increase in land area from 174.28 ha to 449.63 ha
(i) from ……. MT to …….. MT 0. 60 MTPA TO 1.50 MTPA
(ii) What is the % of expansion 150 %
9 If for expansion, whether the application is under 7(ii) of the EIA Notification, 2006.
NO
10 If for expansion, please indicate the number and date of certified Compliance Report of Regional Office of the MoEF
The compliance of earlier EC certificate has been obtained from MOEF, Regional Office, Bhopal vide its letter dated 16/17.12.2013. Action Taken Report/ Revised Compliance submitted to MOEF New – Delhi & MOEF, Bhopal vide our letter dated 26.08.2014.
11 No. and Date of the TOR letter issued by the MOEF (if this is a case for EC)
J-11015/225/2014-IA.II(M) dated 21.11.2014.
12 No. and Date of the EC letter issued by the MoEF (if this is a case for reconsideration. If so, what specific reconsideration(s) being sought by the proponent)
Applying for EC with fresh TOR vide MOEF’s letter dated 21.11.2014.
13 If the project was considered in EAC, Please give date of meeting (s)
Consider for grant of TOR in the EAC Meeting held on 19.09.2014.
14 Type of Mine OPENCAST
15 Capacity of the mine applied for 0. 6 MTPA TO 1.50 MTPA.
16 ML Area Increase in land area from 174.28 ha to 449.63 ha.
(a) As per block allotment Not applicable.
(b) As per approved mine plan 449.63 ha.
17 Date of approval of mine plans, mine closure plan status & date
The PR has been approved by WCL board in its 207th meeting held on15/11/2007 with capital of Rs.54.7840 Crores ( Additional capital- Rs 38.7577 crores)
18 Date of Board’s approval: 15/11/2007
19 Date of Ground water clearance
Not Applicable, As it is not falling in critical area as per CGWA.
20 Date of mine closure approval 25.08.2012.
21 Any river/Nallah flowing near or adjacent to the proposed mine. If yes, please give details.
YES. Wardha river is flowing near the mine lease boundary of the project at distance 125 m north easterly.
II. TECHNICAL DETAILS
22 Geological Reserve:
i. Total geological reserve ii. Mineable reserve iii. Extractable reserve iv. Per cent (%) of extraction v. Range of ground water level vi. Total estimated water requirement:
14.581 Mt 6.13 Mt. 6.13 Mt 42.045 % 3.90 m to12.65 m. bgl pre monsoon 1.5m to 8.85 m bgl in post monsoon 645 KL/day ( Average Demand )
23 Details of Seams
i. No of seams
ii Thickness of seams to be worked on
iii. Grade of coal iv. Stripping ratio v. Category of gaseousness vi. Average gradient vii. Maximum thickness of seams
1 no Composite seam with two sections top and bottom.
Coal seam/ Parting Thickness range (m)
Minimum Maximum
Composite Seam 14.82 18.83
Parting 0.09 2.21
GCV 4748 k Cal /kg (Grade G-9) 1:8.26 m3 /t Not applicable
1 in 2.5 to 1 in 3.5 18.83 m
24 Method of mining OPENCAST WITH SHOVEL-DUMPER COMBINATION
25 Life of mine 11 years
26 Whether ambient air quality seasonal data has been documented. If so, from which season to which season and whether the results are within the prescribed limits.
Yes, Ambient air quality data has been generated Pre- Monsoon- 2013 Yes, parameters are within the prescribed limits.
27 Whether the certificate of compliance of earlier EC from MoEF Regional Office has been obtained, if the proposal is for expansion.
The compliance of earlier EC certificate has been obtained from MOEF, Regional Office, Bhopal vide its letter dated 16/17.12.2013. Action Taken Report/ Revised Compliance submitted to MOEF New – Delhi & MOEF, Bhopal vide our letter dated 26.08.2014.
28 Details of O.B.
i. External OB dumps Yes
ii. No of OB dumps 2 No. of OB DUMP
iii. Area 175.00 ha
iv. Height 60m
v. Quantity (in MCm) 60.95 m3
vi. Year of back filling Not applicable
29 Details of Internal Dumps No internal dump
i. Number of internal dumps Not applicable
ii. Area Not applicable
iii. Height Not applicable
iv. Quantity Not applicable
30 Details of final Mine Voids
i. Area 101.70 ha
ii. Depth 170 m
31 Details of Quarry
Total Quarry Area 101.70 ha.
Backfilled quarry area of ….ha shall be reclaimed with plantation
0.00 ha
A void of…. Ha at a depth of …m which is proposed to be converted into a water body.
101.70 ha at 170 m depth
32 Details of Land usage
i.Land Use Details Land use details
S.N. LAND USE Within ML Area (ha)
Outside ML Area (ha)
Total
1 Tenancy land 443.53 Nil 443.53
2 Forest land Nil Nil Nil
3 Govt. land/Waste land 6.10 Nil 6.10
Total 449.63 Nil 449.63
ii. Pre-Mining The total land requirement for this project is 449.53 ha out of which 174.28 ha has already been acquired in existing Junad OC mine and balance 275.35 ha will have to be acquired.
Land use details
S.N. LAND USE Within ML Area (ha)
Outside ML Area (ha)
Total
1 Tenancy land 443.53 Nil 443.53
2 Forest land Nil Nil Nil
3 Govt. land/Waste land 6.10 Nil 6.10
Total 449.63 Nil 449.63
iii. Post- Mining Post-mining Land use pattern of ML/Project Area (ha)
S. N.
Land use during mining
Land use (ha)
Plantation Water Body
Public use Undisturbed Total
1 External OB Dump
175.00 - - - 175.00
2 Excavation - 101.70 - - 101.70
3 Infrastructure 3.00 - 7.00 - 10.00
4 Green belt 15 - - - 15.00
5 Diversion of roads including embankment
17.0 - 8.00 - 25.00
6 Danger zone and rationalization of
area
- - - 122.93 122.93
Total 210.0 101.70 15.0 122.93 449.63
33 Details of Forest issues
i. Total forest area involved (in ha) for mining
Nil
ii. Status of Forest Clearance NA
iii. Is there any National Park, eco-sensitive Zones, within 10 km radius? If so, give the details.
NA
iv. If the project is within 10KM of radius of wild life sanctuary, whether the Wild Life Management Plan has been prepared and Approved. If, so, please give the status, date of approval with budgetary provision.
NA
v. Extent of forest land in the project (including safety zone and all types of forest land) (in ha)
NA
vi. Total forest land for which Stage-1 FC is available (give area in ha), provide breakup of this area in following format:
NA
vii. Balance forest land for which Stage-1 FC is not available (give area in ha)
NA
viii Details of wildlife issues involved, if any. If so, whether WL management plan has been prepared and please indicate the status.
NA
34 Costs of the project : i)Total capital Cost: ii) Cost of Production: iii) Sale Price: iv) CSR cost: v) R&R Cost: vi) No of PAFs: vii)Environmental Management cost:
The capital Cost of the project is RS 57.784 Crores Rs 1263.44 per tonne at 100% capacity and Rs 1342.44 per tonne at 85% capacity Rs. 1477.02 per tonne agreed as per MOU with MAHAGENCO Rs. 5 per tonne Rs 8.11 Crore Only land oustee families. To be determined at the time of acquisition. Capital – Rs 37.16 Lakhs and Revenue- @ Rs 3.85/t
35 Details of transportation of coal i. In pit: ii. Surface to siding:
ii. Siding to loading:
Dumpers Dumpers & Pay loaders
36 Details of reclamation
a Total Afforestation plan shall be implemented covering an area of: ………. ha at the end of mining. This will include: i. Reclaimed external OB dump ( in ha) : ii. internal dump (in ha), iii. Green belt ( in ha) iv. Density of tree plantation (in no of plants) v. void (in ha) at a depth of (in m) which is proposed to be converted into water body.
210.00 ha Plantation is planned after end of mine life No internal dump 15.00 ha 2500 plants /ha 101.70 ha at a maximum depth of 170 m
III. LEGAL ISSUES
37 Please give details, if the proposal is under any investigation
Not Applicable
38 Any court cases pending. If so, please provide a list with details as annexure.
Not Applicable
39 Any violation cases pending. If so, please provide a list with details as annexure
Not Applicable
40 Give details of actual coal production vis-à-vis sanctioned capacity since the inception of mine in following format :
Not Applicable
Year EC sanctioned capacity (MTPA)
Actual Production (MTPA)
Excess production beyond the EC sanctioned capacity
2009-10 0.6 MTPA 0.402 MTPA NIL
2010-11 0.6 MTPA 0.473 MTPA NIL
2011-12 0.6 MTPA 0.599 MTPA NIL
2012-13 0.6 MTPA 0.60 MTPA NIL
2013-14 0.6 MTPA 0.420 MTPA NIL
IV. PUBLIC HEARING ISSUES
41 Date and Place of public hearing:
05.02.2013 at Bhalar township, Wani, Yavatmal
42 Issues raised during Public Hearing and assurance given along with the financial provisions, if any, by the project proponent. (Please attach as an annexure in a tabular form.)
Details attached in subsequent pages as Annexure - I
V. CONSULTANT
43 Name of the consultant who prepared the EIA/EMP report
Central Mine Planning and Design Institute
44 Whether the consultant has been accredited by the QCI and NABL and whether it is accredited with Quality Council of India (QCI) / National
YES
Accreditation Board of Education and Training (NABET) as per MoEF OM 2nd December 2009
VI Whether the project was considered by the IMG of Ministry of Coal for any irregularities. If so the no. and date of the show cause notice and response to MoC
Not Applicable
ANNEXURE - II
PROFORMA FOR ENVIRONMENTAL APPRAISAL OF
MINING PROJECTS (MINING SECTOR PROJECTS)
Note1 :All information to be given in the form of Annex/s should be properly
numbered and form part of reply to this proforma.
Note 2: Please enter / in appropriate box where answer is Yes/No
Note 3: No abbreviation to be used – Not available or Not
applicable should be clearly mentioned.
Note 4: Core zone is the mining lease area.
Buffer zone in case of ML area upto 25 ha. is to be considered as 5 km all around
the periphery of the core zone and for ML area above 25 ha. an area 10 km all
around the periphery of the core zone.
Note 5: Adopt Scoping process in carrying out EIA study
Note 6: Please indicate source of data
1. General Information
(a) Name of the project : Junad Deep Extn. OC Project (1.50 MTPA)
Name of the proponent : M/s WESTERN COALFIELDS LIMITED
Mailing Address : C/o Chief General Manager
Wani North Area , WCL, Bhallar Township
Dist. Yavatmal ( M. S.)
E- mail : [email protected]
Telephone : 07239 – 241347
Fax No. : 07239 – 241357 (CGM Office)
(b) Objective of the project :
To meet the demand of power
coal
(c) Location of mine(s)
Village(s) Tehsil District State
Borgaon & Junad Wani Yavatmal Maharashtra
(d) Does the proposal relate to
(i) New mine : No
(ii) Expansion : Yes
Increase in ML area : Yes
Increase in annual production : Yes
(iii) Renewal of ML : No
(iv) Modernization : No
e) Site information
Geographical Location
Latitude : 200 01’05” to 200 04’10” N
Longitude : 790 03’09” to 790 05’ 00” E
Topo sheet no : 55 P/4
Total mining lease area (in ha) : 449.63
( Location Plan is enclosed as Plate- I)
(ii) Dominant nature of terrain :
Flat
Undulated : Yes , Gently undulating.
Hilly
2. Land usage of the mining lease area (in ha).
(a) Agricultural Land : 443.53
(b) Waste land(Govt.land) : 6.10
(c) Forest /Zudpi Jungle : Nil
(d) Surface water bodies : Nil
(e) Others (Specify) : Nil
Total : 449.63
3. Indicate the seismic zone in which ML area falls. In case of zone IV & V,
details of earth quakes in last 10 years. : Seismic zone no. – II
(a) Severity (Richter Scale) : Not applicable
(b) Impact i.e. Damage to
Life : No
Property : No
Existing mine : No
4. Break-up of Mining lease area (in ha.) as per approved conceptual plan :
Purpose
Mining Lease Area
Total
Area acquired Area to be acquired
Government Private Government Private Government Private
Forest Others Agri. Other
s Forest Others Agri.
Oth
ers Forest Others Agri. Others
1. Area to be excavated --- --- 101.70 ---- 101.70 --- ---- 31.70 --- 70.00
2. Storage for top soil Included in Sl.No. 3 below
3. Overburden/Dumps ----- ---- 175.00 175.00 ---- 40.00 135.00
4. Mineral storage
5.Infrastructure(Work-
shop, Administrative
Building)
3.13 6.87
10.00
3.13 6.87
---
6. Roads Covered in Sl.No. 5 Above Covered in Sl.No. 5 Above
7. Railways
8. Green Belt 15.00 ha in Rationalization Area & in the
Blasting Zone. In addition to the existing
plantation over OB dump, and other plantation.
Presently
23.73 ha
has been
covered
with
Plantation
15.00 ha in Rationalization Area & in
the Blasting Zone. In addition to the
existing plantation over OB dump,
and other plantation.
9. Tailings pond
10. Effluent treatment
Plant
11.Coal handling
plant/mineral
separation plant
Covered in Sl.No. 5 Above Covered in Sl.No. 5 Above
12. Township area(for
additional Quarters)
Outside the leasehold in the existing Combined
Colony at Bhallar Township
---
13.Others ( Specify )
a) Diversion of Roads
b) Danger Zone &
Rationalization Area
6.10 15.00
141.83
15.00
147.93
5.00
87.58
6.10 10.00
54.25
Total 9.23 440.40 Nil 449.63 --- 3.13 171.15 Nil ---- 6.10 269.25
5. Township (outside mining lease) : (a) Total area (in ha) : Combined Colony In Bhallar Township)
(b) No. of dwelling units : 417
(c) Distance from mine site : 5 km
6. Distance of water bodies (in km)
Distance from River Bank* Other water bodies* Sea / Creek
/Lake / nalla etc. (specify)
Mining lease
boundary
Wardha river –
150 m
-
Ancillary facilities - -
[* from highest flood line/high tide line] -
7. For projects falling within the Coastal Regulation Zone (CRZ) : Not
applicable
Whether the mineral to be mined is of rare nature and not available outside
CRZ?
If yes, annex a scaled location map showing low tide line (LTL), high tide line
(HTL) duly demarcated by one of the authorized agencies*[*Director, Space
Application Centre, Ahmedabad: Centre for Earth Sciences Studies,
Thiruvananthapuram: Institute of Remote Sensing, Anna University, Chennai,
Institute of Wetland Management & Ecological designs, Kolkata, Naval
Hydrographer’s Office, Dehradun: National Institute of Oceanography, Panjim,
Goa: and National Institute of Ocean Technology, Chennai] boundary of mining
lease area, diastance of ML area from LTL and HTL CRZ boundary and CRZ
classification of the project area as per the approved Coastal Zone
Management Plan, and settlements, sand dunes, mangroves, forest
land/patches, turties breeding and nesting sites etc., if any, in the project area.
8. Indicate aerial distance from the periphery of core zone/area from the
periphery of the buffer zone to the boundary of following (upto 10 km)
Given below ;-
a) BUFFER ZONE – It is the area within the radius of 10 km of mining lease area
and the details of features within buffer zone is as given below ;-
[*Buffer zone in case of ML area upto 25 ha. is to be considered as 5 km all
around the periphery of the core zone and for ML area above 25 ha. an area 10
km all around the periphery of the core zone].
9. Description of flora & fauna separately in the core and buffer zones*
[*Consult the Wildlife(Protection) Act, 1972 as amended subsequently and list
species with (1) Common name (2) Scientific name and (3) under which
schedule of the Wildlife (Protection) Act the identified species fall. Get the list
authenticated by an Expert in the field/credible scientific
institute/University/Chief Wildlife Warden office. Information to be based on field
survey].
The details given in Chapter – III.
Area
10. Details of mineral reserves (as per approved Mining Plan)
(Quantity in million tonnes )
(a) Proved : 68.527 Million Tonnes
(b) Indicated : 14.581 Million Tonnes
(b) Inferred :
(c) Mineable reserves : 6.13 Million Tonnes
Sectorwise Net Geological reserves in Junad Block
(Figures in Mt)
OPENCAST (Upto 1:7 Coal/OB
Ratio line
UNDERGROUND
Beyond 1:7 to Fault F1-F1
Sector Proved Indicated Total Sector Proved Indicated Total
Q1 3.839 - 3.839 U1 7.168 - 7.168
Q2 0.577 - 0.577 U2 - 1.683 1.683
Q3 19.689 - 19.689 U3 37.254 - 37.254
Q4 - 4.418 4.418 U4 - 1.489 1.489
Q5 - 6.991 6.991
Total 24.105 11.409 35.514 Total 44.422 3.172 47.594
GRAND TOTAL 83.108
As stated above, only Sectors Q3 & U3 considered for present Junad Extension
OC, the Net Geological reserves of these sectors are as follows of which only
44.018 Mt are below 250 m depth.
Particulars Sector Total
Q3 U3
Incrop to 1:7 Coal:OB Ratio
line
19.689 - 19.689
Beyond 1:7 Coal:OB Ratio
line to
250 m Depth
- 24.329 24.329
Sub-Total 19.689 24.329 44.018
Beyond 250 m depth sub-
total
- 12.925 12.925
Total 19.689 37.254 56.943
11. Major geological formation/disturbances in the mining lease area
(a) Geological maps submitted : Yes
(b) Geological sections submitted : Yes
(c) Contour map submitted : Yes
(d) Whether the presence, if any noted of
(i) Faults : Yes (Details given Chapter – III)
(ii) Dykes : No
(iii) Shear Zone : No
(iv) Folds : No
(v) Other weak zones : Yes, presence of sympathetic
faults and Minor slips can not be
ruled out.
(e) Source of data (Indicate) : Geological report & PR
prepared by CMPDI
12. Production of mineral(s) and life of mine
(a) Rated capacity of mine mineral wise (tonnes/annum) : 1.50 MTPA
(Maximum
Achievable)
(b) Life of mine at proposed capacity (years) : 16 years
(c) Lease period (Years) : Not applicable
(d) Date of expiry of lease (D/M/Y) : Not applicable
(e) Indicate in case of existing mines :
Date of opening of mine : 1993-94
b. Production in the last 5 years
From year 08-09 to year 13-14 in million tones. : As given below
2008-09 – 0.58 Mte
2009-10- 0.40 Mte
2010-11- 0.47 Mte
2011-12 – 0.59 Mte
2012-13 -0.60 Mte
2013-14 – 0.42 Mte
i) Projected production for the balance
Years : Maximum
Achievable
1.50 MTPA
ii) Whether mining was suspended after : No
opening of the mine ?
If yes, details thereof including last production
figures and reason for the same.
(f) Whether plans & sections provided ? : Yes
13. Type and method of mining operations
Type
Method
Opencast Yes By
Mechnised
method
Manual Mechanised
Yes
Undergrou
nd
x X
Both x x
14. MINING DETAILS:-
In Junad Extension OC mine, it is proposed to extend existing OC mine in dip
side upto 170m depth. The mine parameters of the proposed extended quarry
are detailed below:-
Sl.
No.
Particulars
(As on 1.4.2006)
Extension Quarry
1
a)
b)
Face length (km)
On the floor of composite
seam
On Surface
1.15 – 1.28
1.50 – 1.70
2
a)
b)
Depth (m) upto floor of
composite coal seam
Initial
Final
30 - 88
170
3
a)
b)
Width Below the decoaled
void of existing Junad
Extn.OC
On the floor of composite
seam
On Surface
250-325
400-525
4
a)
b)
Area of the quarry
On floor (ha)
On Surface (ha)
35.20
70.50
MINEABLE RESERVES
GROSS RESERVES IN PROPOSED JUNAD OC MINE
The upthrown block of fault F6 – F6 is the main Junad block which consists of
Sectors Q2, Q3, Q5 (opencast) and Sectors U3 & U4 (underground).(Please refer
Geological Plan of Junad OCP of WCL) This division of sectors in Junad block is
based as per Geological Report of Junad block, June, 1990. As per this G.R.,
reserves upto 1:7 coal:OB ratio line are defined as opencast sectors, and
reserves beyond 1:7 coal:OB ratio line are considered as underground reserves.
However, due to application of hiring HEMMs, greater depths with higher
stripping ratio can be worked by opencast method of mining. Therefore, the
revised geological break-up is given below which considers opencast reserves
upto 250m depth. The proposed Junad extension OC mine has been planned
below the RCE limit of existing Junad OC mine upto a depth of 170m at the floor
of composite coal seam. Therefore, in this report the sectors earlier identified for
underground mining in the geological notes is proposed to be worked by
opencast method of mining upto a depth of 170m.
Sector Q2 is a very narrow patch, bounded between downthrow fault F4-F4 & F5-
F5. The net geological reserves of Sector Q2 is only 0.557 Mt and considering its
width and strike, it is not viable for opencast coal mining.
Sector Q5 lies below the Wardha river in south-east direction. The net Indicated
geological reserves of Sector Q5 is 6.99 Mt but the opencast mining can be
done only after the diversion of Wardha river.
Sector U4 is a small patch below Wardha river, bounded beyond 1:7 coal:OB
ratio line and boundary fault F1-F1. The net indicated geological reserves of
Sector U4 is 1.489 Mt.
Thereby Sectors, Q2, Q5 and U4 of main Junad block are not considered in this
PR for opencast coal mining.
The sectors considered in this PR are Sector Q3 & U3. The boundary of Sector Q3
& U3 are defined as under :-
Sector Q3 :
East - Incrop and fault F4-F4 and Wardha river barrier
West - 1:7 Coal : Overburden ratio line.
North - Wardha river barrier.
South - 1:7 Coal : Overburden ratio line and Wardha river barrier.
Sector U3 :
East - Sector Q3
West - Fault F1-F1
North - Wardha river barrier.
South - Sector Q3 & U4 and Fault F1-F1
In the proposed quarriable area, the coal seam has split in two sections namely
top section and bottom section with an intervening parting of average 0.8 m
thickness varying from 0.09 m to 2.21 m. Due to steep gradient, it is not feasible
to work this parting separately. In the existing Junad OC mine, the coal is being
extracted along with parting. It is therefore proposed in this report to extract the
top and bottom section of coal seam along with intervening parting as a
composite coal seam. The gross reserve in the proposed extended quarry has
been estimated considering coal thickness from roof to floor.
COAL BLOCKED UNDER VARIOUS HEADS
As stated above, only Sectors Q3 & U3 are considered for quarry planning in
proposed Junad Extension OC. The Net Geological reserves of these sectors up
to 250 m depth is 44.018 Mt.and upto major boundary Fault F1-F1 is 56.943 Mt.
The break-up of reserves in Sectors Q3 & U3 up to 250 m depth and beyond 250
m depth to boundary fault F1-F1 is given in following table.
Particulars Sector Total
Q3 U3
Incrop to 1:7 Coal:OB Ratio
line
19.689 - 19.689
Beyond 1:7 Coal:OB Ratio line
to 250 m Depth
- 24.329 24.329
Beyond 250 m depth - 12.925 12.925
Total
19.689
37.254
56.943
As per sanctiond RCE of Junad OC Mine in 1999, net geological reserves are
3.63Mt (3.26 Mt net mineable reserves). For Junad Extension OC, starting from
1.4.2008, 6.81 Mt net geological reserves (6.13 Mt net mineable reserves) are
proposed to be exploited. Therefore in total, 3.63 Mt + 6.81 Mt = 10.44 Mt
reserves from Sectors Q3 and U3 falls in quarriable area. Balance reserves in
Sectors Q3 and U3 upto major boundary fault F1-F1, is 46.503 Mt. and it falls in
the dip side and southern side of the proposed quarry.
MINING LOSS
To arrive at the mineable reserves from the gross reserves available in the
proposed extension quarry, following mining losses have been considered :-
i) 10% mining loss due to variation in seam thickness.
ii) Loss of 20 cm of coal at each contact point of coal seam thus
aggregating 40 cm (two contact points at roof and floor) which
corresponds to about 2.5% loss.
iii) 0.5% of coal loss for blasting for coal seam
iv) 0.5% loss due to spillage in coal transportation.
Considering the above mining losses, the net mineable reserves in Junad
Extension OC mine are as under:
Quarry
Gross
Geological
Reserves
(Mt)
Mining
Losses
(Mt)
Mineable
Reserves (Mt)
Quarry as per
Alternative IB, depth
170 m
7.086* 0.956 6.13
TARGET OUTPUT AND MINE LIFE
The proposed Junad Extension OC mine has been planned for a target
capacity of 0.60 Mt/annum. The parameters of opencast mine field and
technical conditions of its development make this target feasible with normal
indices namely strike length, width and depth of the excavated block, number
of coal seams, method of mining, location of equipment, deployment, etc. The
target production from extension quarry along with strike length and rate of
deepening are tabulated below :
Sl.
No.
Quarry Max.
target
Production
(Mt)
Depth
Range
(m)
Strike
Length
(Km)
Average
Rate of
deepening
(m/year)
1. Quarry as per
Alternative IB, depth
170 m
0.60 88-170 1.5 -
1.70
8 – 9
From above it is clear that the maximum rate of deepening is about 8 – 9
m/year in proposed Junad Extension quarry.
In proposed Junad Extension OC mine, target production of 0.60 Mt will be
achieved in Year-I i.e, in the year 2008-09. With a mineable reserve of 6.13 Mt
and target production of 0.60 Mty, the revenue life of the mine comes out to be
11 years. However for EC , the peak capacity assumed as 1.50 MTPA.
GEO-MINING CHARACTERISTICS
Seam Gradient
Geological structure of Junad block is based mainly on sub-surface data of
boreholes. Strike is mainly NW-SE, coal seam dips due south west and gradient
varying from 1 in 2.5 to 1 in 3.5 in quarriable area.
Geological Disturbances
Only 3 faults viz. Fault F3-F3, F4-F4 and F5-F5 are intersected in quarry. The fault
F3-F4 is minor in nature and throw is 5 m. The throw of F4-F4 & F5-F5 is 20 m
towards NE and 40 m SW respectively.
SELECTION OF MINING METHOD
The steep gradient of the seam (gradient 1 in 2.5 to 1 in 3.5) rules out the
application of dragline method of working and surface miner working in
proposed Junad Extension OC mine. Shovel-Dumper system has been
considered to be the most suitable method of opencast mining under the
prevailing geo-mining conditions. With Shovel-Dumper system, two stripping
methods are possible:
1. Inclined slicing method &
2. Horizontal slicing method
In steep gradient, positioning of HEMM is difficult in inclined slicing method as
the benches in coal are made parallel to the seam in this method. Hence this
method is ruled out in proposed Junad Extension OC mine. In horizontal slicing,
benches in coal are made horizontal and therefore there is no problem in
positioning of HEMM. In horizontal slicing method, the sump can be made either
on the bottom most horizontal bench in coal or in the roof of coal seam. With
the sump at the roof of coal seam, the coal and overburden benches with
proper grading can be worked in almost water-free condition throughout the
year.
However, with this arrangement, initial excavation is high because of the
running slope of quarry is further reduced to this type of sump arrangement. It is
therefore proposed in this report to make the sump at the horizontal bench in
coal in one side of the quarry and to make the coal benches slightly grading
towards the sump.
Thus, the shovel dumper system of mining with horizontal slicing method is
recommended for the proposed extension project with sump at the bottom-
most horizontal bench in coal seam.
SEAM THICKNESS RANGE & VARIATION PATTERNS
The coal seam in Junad Block is thick Composite Seam ranges in thickness from
14.82 (MWJ-50) to 18.83 (MWJ-24). MECL, however, divided seam in two parts as
Top Section and Bottom Section by a parting ranging from 0.09 (MWJ-24) to 2.21
in (MWJ-26), However, for opencast proposed quarry, it is thick one Composite
Seam. The parting is generally composed of shale, carbonaceous shale and
occasionally intercalation of sandstone and shale.
The summarized details of coal seam under proposed quarry are as follows :-
Sl.No. Particulars Minimum Maximum
1. The range of
quarriable
thickness
14.82 m (MWJ-50) 18.83 m (MWJ-24)
(including parting
2. The depth range 20.57 (MWJ-37) (MWJ-10)
3. The parting range 0.09 m (MWJ-24) 2.21 m (MWJ-26)
ause of very steep gradient of coal seam (1 in 2.5 to 1 in 3.5), it is difficult to
remove the parting between top and bottom section even in horizontal slicing
and with shovel dumper system with blasting method. In the existing Junad OC
mine, the coal is being extracted along with parting. In the Junad Extension OC
mine also, it is proposed to extract the entire composite coal seam along with
parting varying in thickness from 0.09m (MWJ-24) to 2.21m (MWJ-26). The quality
of coal has been assessed taking into account the mixing of parting with the
coal.
System Parameters – Bench Height, Elements of Mining System
Volume Regime
The proposed Junad Extension OC mine is an extension of existing Junad OC
Mine beyond RCE floor unit.
The access trench of existing Junad OC mine, will serve the entry to Junad
Extension OC mine also. Thus the Quarry of proposed Junad Extension OC will
be approached by the existing access trench of Junad OC mine.
To calculate the coal, OB and stripping ratio at different depths in Extension
quarry, cuts have been made at 100m FRL (Cut-I), 70m FRL (Cut-II), 40m FRL
(Cut-III), and upto 170 m depth line (Balance cut).
The cut-wise OB and coal in proposed Junad Extension OC is given below in
Table below.
CUTWISE COAL, OB & STRIPPING RATIO(Volume Regime Table)
FOR JUNAD EXTENSION QUARRY(FROM 1.4.2008 ONWARDS)
Cut FRL (m) Mineable
Reserves
(Mt)
Total OB
(Mm3)
Stripping
Ratio (m3/t) From To
Cut-I Upto 100m FRL 1.05 14.23 13.55
Cut-II 140 70 2.14 18.78 8.77
Cut-III 70 40 2.24 16.56 7.39
Balance
Cut
40 20 0.70 1.05 1.50
(Upto 170m depth line)
TOTAL 6.13 50.62 8.26
Thus the total mineable reserves in the Junad Extension OC mine is 6.13 Mt with
an average stripping ratio of 8.26 m3/t.
Width and Height of Benches
The maximum height of benches in overburden considered in this report is 10m
which will be drilled and blasted in one go. In unconsolidated strata/alluvium
soil, the bench height is kept as 5m. In coal also, the height of the bench is
considered as 5m. The bench width considered in this report is 20m and 30m for
non-working and working benches respectively for planning purpose.
In final batter of the quarry, the height of the benches in consolidated strata is
10m and a berm of 5m width will be maintained between two benches.
However, in unconsolidated strata/alluvium soil, the bench height considered in
final batter is 5m and the bench width (berm) is 10m. Three to four transport
horizons will be maintained in the batter at an interval of 30m.
Slope of Benches and Quarry
i) During Mining Operation
The slope of individual benches depends on the type of strata. In this report, the
slope of individual bench is proposed as 45o in soil, alluvium and clay whereas it
is 70o in hard strata as well as in coal.
The overall slope of the quarry benches during mining operation varies from 10o
to 20o (from horizontal plane) due to multiple seams.
Rise side batter remains same in the quarry during mining operation or at the
end of the quarry. The overall angle of the rise side batter of existing Junad OC
mine varies from 20o to 35o.
ii) At the end of the quarry
The slope of individual benches in the batter at the end of quarry remains same
as that during mining operations i.e, 45o in soil , alluvium and clay and 70o in
hard strata and coal.
The slope of the batter at the end of the quarry in dip side is flatter in upper
horizon because of unconsolidated strata like soil, clay, etc. In deeper horizon,
the angle of batter measured from horizontal plane is steeper compared to
upper horizon. It is 15o to 30o in upper horizon (in unconsolidated strata) and 35o
to 45o in hard strata. The slope of rise side batter is same as discussed above
under point (i).
Drilling and Blasting
The degree of fragmentation in opencast mine has to be optimized so that total
cost of drilling, blasting, excavation, transport and crushing as total system is
minimized. In order to reduce the excessive vibrations at nearby surface
structure, river, road, village, etc. and also to achieve satisfactory blasting
results, an optimized control blasting system depending upon rock formations
using combination of delays and relays will have to be evolved. It is further
recommended that at the time of actual excavation, proper study on ground
vibration should be made with scientific methods.
In proposed Junad Extension OC mine, the powder factor for OB and coal has
been worked out to be 3.0m3/kg and 7.0/t respectively in partial hiring
option.However, it is proposed in this report to undertake scientific study to
assess the powder factor for OB and coal. Adequate capital provision has been
made in this report for above study.
Mine Transport
Shovel Dumper system has been proposed in this report and the coal as well as
OB will be transported by dumpers/trucks .
Haul roads with proper gradient have been proposed for Quarry and the coal
will be transported by dumpers/trucks through these haul roads and existing
access trench of Junad OC mine from quarry to coal stock yard near the
access trench. The gradient of haul roads is proposed as 1:16.
For the transportation of OB, transport horizons (benches) have been proposed
in the dip side & side benches/batter. The OB from benches will be transported
by dumpers/trucks through these transport horizons and ramps to suitable
intervals will be made to join other benches with the transport benches. The OB
below the bottom-most transport horizon can also be transported through the
haul roads where the dump is in rise side.
SEQUENCE OF MINING
The Quarry proposed in Junad Extension OC mine, is below the existing
decoaled Junad OC mine. The total mineable coal and OB in extended Quarry
are 6.13 Mt and 50.62 Mm3 respectively and the stripping ratio works out to be
8.26 m3/t.
GEO - MINING PARAMETERS
Sl. No. Particulars EXTENSION QUARRY
1. FACE LENGTH (km)
a) On the floor of composite seam 1.15 – 1.28
b) On surface 1.50 – 1.70
2. DEPTH UPTO FLOOR OF COMPOSITE
SEAM(m)
a) Initial 30 - 88
b) Final 170
3. WIDTH BELOW THE DECOALED VOID OF
EXISTING OC (m)
a) On the floor of composite seam 250 - 325
b) On surface 400 – 525
4. AREA OF THE QUARRY (ha)
a) On the floor 35.20
b) On surface 70.50
5. Gradient of Seam 1 in 3
6. GRADE OF SEAM (WITH 5 CM
CONTAMINATION)
E
7. U.H.V. (WITH 5 CM CONTAMINATION) 3822
8. AVG. SEAM THICKNESS(m) 17
9. NET MINEABLE RESERVES (Mt) 6.13
10. Average stripping ratio (t:m3) 1:8.26
The shovel dumper system of mining with horizontal slicing method is
recommended for the proposed extension project with sump at the bottom-
most horizon bench in the coal seam.
15. Mine details.
(a) Opencast mine :
(i) Stripping ratio (mineral in tones to over burden in m3 ) : 1 : 8.26
(ii) Ultimate working depth (in m bgl) : 170
(iii) Indicate present working depth in case of : 114
existing mine (in m bgl)
(iv) Thickness of top soil (in m)
Minimum : 5.00
Maximum : 10.00
Average : 7.50
iii) Thickness of overburden (in m)
Minimum : 15.00
Maximum : 60.00
Average : 37.50
iv) Mining Plan
Height and width of the
bench in
Overburden/waste.
: Bench height – 10 m
Width –
Working Bench- 30m
Non-working width-
20m
Height & width of the
bench in ore body / coal
seam
: Bench height – 5 m
Width –
Working Bench- 30m
Non-working width-
20m
Proposed inclination /
slope of the sides of the
opencast mine
(separately for
overburden , coal/ ore
and overall slope of the pit
sides ) both while
operating the mine as well
as at the time of closure
of the mine.
: Individual Bench
slope-
Coal - 700
OB ( hard strata ) -700
OB ( soft soil ) - 450
Overall slope –
rise side - 270 to 370
(while operating &
closure )
dip side-
while operating-180-
200
while closure - 400
The recommendation
of Slope stability study
being implemented.
Whether transverse
sections across the
opencast mine at the end
of fifth year and at the
end of the life of the mine
have been submitted
: Yes
(vii) Type of blasting, if any, to be adopted. : Controlled Blasting
(b) Underground : Not Applicable
(i) Seam/Ore body Min.Depth (m) Max. Depth (m) Avg.thicikness (m)
Rate of dip in degree Direction of dip.
Mode of entry into the mine
Shaft
Adit
Incline
Details of machinery
On surface
At face
For transportation
Others
Method of stopping (metalliferrous mines)
Open
Filled
Shrinkage
Caving
Combination of above
Others (specify)
Extraction method
Caving
Stowing
Partial Extraction
Subsidence
Predicted max. subsidence (in m)
Max. value of tensile strain (in mm/m)
Max. slope change (in mm/m)
Whether identified possible subsidence
Area (s) superimposed on Surface
Plan has been submitted ?
Major impacts on surface features like
Natural drainage pattern, houses, buildings,
Water bodies, roads, forests etc.
Salient features of subsidence management
(monitoring and control).
16. Surface drainage pattern at mine site.
(a) Whether the pre-mining surface drainage
plan submitted?
: Yes
(b) Do you propose any modification/diversion in
the existing natural drainage pattern at any
stage? If yes, when. Provide location map
existing natural drainage indicating contours,
dimensions of pattern proposed to be
diverted, direction of flow of water, proposed
route/changes, if any i.e. realignment of
river / nallah / any other water body falling
within core zone and its impact.
: No major change-
modification / diversion
in water body and there
will not be any
adverse impact on
existing natural drainage
pattern
17. Embankment and/or weir construction
(a) Do you propose, at any stage, construction of
(i) Embankment for protection against flood : Yes
(ii) Weir for water storage for the mine : No
(b) If so, provide details thereof.
( Quantum of OB proposed for embankment ) : Details in Chapter – II.
(b) Impact of embankment on HFL and settlement around : No impact
anticipated.
(d) Impact of weir on down stream users of water : Not Applicable.
18. Vehicular traffic density (outside the ML area)
Type of vehicles No. of vehicles per day
a) Existing -- Coal Tippers 190 trucks/day
Light vehicles
(b) After the proposed activity -- Coal Tippers Approx. 450 /day
& Light vehicles (at peak capacity of 1.50
MTPA)
(c) Whether the existing road network is adequate ? : Yes
If no, provide details of alternative proposal ? : NA
* Considering maximum achievable capacity of 1.50 MTPA.
19. Loading, transportation and unloading of mineral and waste rocks on
surface:
(a) Manual
(b) Tubs, mine cars, etc.
(c) Scraper, shovels, dumpers/trucks ------ Yes (Shovel & Dumper
only)
(d) Conveyors (belt chain, etc)
(e) Others (specify)
20. Mineral(s) transportation outside the ML area
Qty.(in TPD) Percentage(%)
(a) Road 4545 100
(b) Rail -
(c) Conveyors
(d) Ropeway
(e) Water ways
(f) Pipeline
(g) Others (specify)
Total 4545 100%
Considering Peak Capacity at 1.50 MTPA.
21. Baseline Meteorological and Air Quality data
(a) Micro-meteorological data : [Continuous monitoring through autographic instrument for one full season other than monsoon]
(i) Wind rose pattern for one full season (16 points of compass i.e. N, NNE,NE,…) based on 24 hourly data. For Coastal
Area also furnish day-time and night time data. : Predominant wind is from North- East (NE)quadrant.
Windrose diagram is shown in Plate – XII
Day time
Night time
24 – hours period
(ii) Site specific monitored data : Predominant Wind Direction: From ENE quadrant
Month
Post
Monson
Wind Speed (m/s) Temperature (oC) Relative Humidity(%) Rain Fall *(mm) Cloud
Cover**
(Octas of
sky)
Min. Max. % of
calm
Mean
(Dry Bulb)
Highest Lowest Mean Highest Lowest Total 24-hours
Highest
No.of
Rainy
days
Mean
0.4 13.6 30.69 18.5 26.00 11.00 49.8 64.5 35 - - - Clear (Sky
Appearance)
24-hours rainfall should be reported from 08.30 hrs. IST of previous day to 08.30 hrs. IST of the day.
Rainy day is considered when 24 hrs. rainfall is > 2.5 mm.
** Visual observations of cloud cover should be recorded four times a day at regular intervals.
(iii) Indicate name and distance of the nearest IMD meteorological : Nearest IMD is located at Chandrapur.
station from which climatological data have been obtained For EIA prediction the micro-meteorological data
for reporting in the EIA report , if any. collected at the site has been considered.
(b) Ambient air quality data* (RPM,SPM, SO2 and NOx)
[*Monitoring should be carried out covering one full season except monsoon – same season as in 21 (a) (i)]
[*Frequency of sampling: Sampling to be done twice a week for the entire season 24 hourly for SPM & RPM. For gaseous pollutants 24
hourly data be given irrespective of the sampling period].
(i) Season and period for which monitoring has been carried out : Winter , December 2009 – February, 2010
(ii) No.of samples collected at each monitoring station. : ***
Name of monitoring equipment
used
SPM RPM SO2 NOx Pb**
High Volume
Sampler
High Volume
Sampler
High Volume
Sampler
High Volume
Sampler
-----
Equipment sensitivity
Permissible AAQ R
standard (CPCB) I
S
200 ug/m3 100 ug/m
3 80 ug/m
3 80 ug/m
3
600 ug/m3
300 ug/m3 120 ug/m
3 120 ug/m
3
100 ug/m3 75 ug/m
3 30 ug/m
3 30 ug/m
3
Monitoring
Location
No.of
Samples
Drawn
Category*
(R,I,S)
Min. Max. 95%
tile*
Min. Max. 95%
tile*
Min. Max. 95%
tile*
Min. Max. 95%
tile*
Min. Max 95
%
tile
Core zone
A1
*** I 226 294 292 112 138 136 6.4 11.3 10.8 8.9 16.6 15.3 Not done
BUFFER
zone
A2
(Chargaon
Village)
*** R 134 169 165 52 72 70 6.0 9.4 9.0 8.6 12.5 11.7
Not done
A3
(Dhorwasa
Village)
*** R 126 168 161 42 70 68 5.6 8.0 7.5 7.1 11.7 10.6
Not done
A4
(Navi Ukni
Village)
*** R 140 173 172 50 73 67 8.4 11.4 10.9 9.6 13.6 13.1
Not done
Name of monitoring equipment
used
SPM RPM SO2 NOx Pb**
High Volume
Sampler
High Volume
Sampler
High Volume
Sampler
High Volume
Sampler
-----
Equipment sensitivity
Permissible AAQ R
standard (CPCB) I
S
200 ug/m3 100 ug/m
3 80 ug/m
3 80 ug/m
3
600 ug/m3
300 ug/m3 120 ug/m
3 120 ug/m
3
100 ug/m3 75 ug/m
3 30 ug/m
3 30 ug/m
3
A5
(Besa
Village)
*** R 128 164 164 61 78 78 6.8 8.9 8.6 8.0 11.4 10.5 Not done
A6
(Pimpalgaon
Village)
*** R 146 180 176 51 80 78 6.8 9.2 8.9 8.4 11.3 11.0 Not done
*R = Residential; I= Industrial; S= Sensitive **Pb for mineral specific sites only
*** SPM & RPM – 2 samples (24 hrly ) in a week for 12 weeks in a season i.e. 24 samples , For SOx & NOx – 72 samples – 3x2x12
( 3 samples in a day , 2 days in a week & 12 weeks in the season ).
# Annex a location map indicating location of AAQ stations, their direction and distance with respect to project site: -
Location map indicating location of AAQ stations is enclosed as Plate – XII .
The baseline ambient air quality data along with direction of AAQ stations & distance with respect to project site have been given
in Chpater - III .
22. Stack and emission details, if any* : Not applicable
Sl.No Process/Unit of
operation (e.g. DG
Set, Boiler)
Height of
stack(m)
Internal
top dia.
(m)
Flue gas
exit
velocity
(m/sec)
Emission rate (kg/hr) Heat emission
rate from top
of stack
(k.cal/hr)
Exhaust/Flue gas
SPM SO2 NOx CO Temp oC
Density Specific
Heat
Volumetric
flow rate
(m3/hr)
23. Details of fugitive emissions during mining operations * : Insignificant as such not required.
24. Air quality Impact Prediction (AQIP)*
(a) Details of model(s) used for AQIP including grid : Qualitative assessment has been done on the basis of recorded data at
size, terrain features, and input meteorological data. the site and around covering the buffer zone.
The details of which are given in Chapter – IV.
However, AQIP model (ISCST-3) has been given in Chapter –IV.
(b) Maximum incremental GLC values of pollutants based on prediction exercise.
(in ug/m3 )
S.No. Pollutants Incremental Value Ambient Air Quality Resultant Air Quality
1. SPM 180 240 (Core Zone) 420
(Within permissible limit)
2** SO2 Not applicable
3** NOx Not applicable
[*Question Number 22, 23 & 24 need not be filled-in for mines having ML area of 25 ha .or less]
[**Information of item No.2 & 3 to be provided in cases with captive power generation of 500 KVA and above.].
25. Water requirement (m3/day)
Purpose Avg. Demand Peak Demand
Mine site 1. Mine operation/workshop 2. Land reclamation 3. Dust suppression 4. Drinking (752 manpower) 5. Green Belt 6. Beneficiation(CHP) 7. Washeries 8. Fire Service 9. Others B. Township Green Belt Domestic Other (specify)
20 -
395
30
50
50
100
Existing
30 --
450 35
80
60
100
Existing
Total 645 755
26. Source of water supply*
S.No. Source m3/day
1. River (name)
2. Ground water
3. Mine water (sump/pit) 755
4. Other surface water bodies(specify) -
[*Annex a copy of sanction letter/permission from the concerned authority (Central Ground Water Authority in case of ground water abstraction is from notified area/State Ground Water Board in case of non-notified area/State Irrigation Department for surface water pumping) for drawing water]
27. Lean season flow in case of pumping from river/nalla (cumecs) : Not Applicable 28. Ground water potential of the study area
28.1 Ground water availability
(a) Range of water table (m bgl) (i) Pre-monsoon (April/May)
Core Zone : 14.00 – 17.80 m Buffer zone : 3.90 – 12.65 m
(ii) Post-monsoon (November)
Core zone : 12.50 – 15.25 m Buffer zone : 1.50 – 8.85 m
(b) Total annual replenishable recharge (million m3/ year)
By ground water table fluctuation method : 43.30 MCM By rainfall infiltration factor method : 41.59 MCM
( c) Annual draft excluding estimated draft through : 2.30 MCM
mine discharge (million m3/year)
(d) Estimated draft through mine discharge (million m3/year) : 8.90 MCM
(e) Net annual ground water availability (million m3/year) : 37.43 MCM
(f) Stage of ground water development in % : 30 % 28.2. Water demand – Competing users of the water source
S. No. Usage Present consumption Additional proposed
Total (m3/day)
Surface Ground Surface Ground Surface Ground
1. Domestic 500 4450 -- 1500 -- 6450
2. Irrigation 6000 4416 -- 2000 -- 6416
3. Industry -- -- -- -- -- --
4. Mining -- 3000 -- 1000 -- 4000
5. Others (Specify)
-- -- -- -- -- --
Total 6500 11866 -- 4500 -- 16366
29. Water quality* : (a) Annex physico-chemical analysis of water at intake point : Not Applicable
(b) In case of existing mine, annex report on quality of water : Enclosed discharge i.e. complete physico-chemical analysis**
[*For non-discharging mines at least four ground water samples to be taken preferably from downstream direction of the mine in pre-monsoon and post-monsoon periods and analysed. For discharging mines six samples are to be analysed ]. ** All parameters as per BIS 10500. Indicate name of Methodology, Equipment used for analysis, and Detection Level (DL) for each parameter.
*** Wherever any analytical parameter is below detection level, “BDL” (Below Detection Level) should be written instead of ‘NIL’. 30. Impact on ground water regime/stream/lake/springs due to mine
dewatering* (a) Radius of influence (in m) : 500 - 600 m (Final mine depth-170 m) [To be estimated based on analysis of pumping test data and application of empirical formula]. (b) Whether saline water ingress will take place ? : NA (applicable to coastal areas) (c) Impact on stream/lake/springs : NA
[*Provide a comprehensive hydro-geological assessment report. If the average mine dewatering is more than 100 m3/day and or going below water table in non-monsoon period. The report should be based on preferably latest one year pre-monsoon and post-monsoon baseline data covering information on ground water situation, aquifer characteristics, water level conditions (April – May and November), estimate of ground water resources, predicted impact of the project on ground water regime and detailed remedial/conservation measures such as artificial recharge of ground water etc. The report should be based on actual field inventory out of existing wells, at least 30 observation wells in the buffer zone with supplementary information from secondary sources (mention name). For estimation** of ground water resource (refer question No.28 above) be designated study area of the buffer zone may be sub-divided into command and non-command areas, watershed-wise (in case of hard rock/consolidated formations)/ block-wise/mandal-wise in case of alluvial/unconsolidated formations)].
[**For estimating ground water resources in the area follow the Ground Water Estimation Committee recommendations of 1997]
31. Waste Water Management
Mine (a) Daily average discharge (m3/day) from different sources
i. Mine water discharge : during Lean period : 3000 m3/day Monsoon period : 4500 m3/day
ii. Workshop : iii. Domestic (mine site) : iv. Beneficiation/Washeries : 645 m3/day consumption at site v. Coal Handling Plant : vi. Tailings pond :
vii. Others Total : 3645 m3/ day (average) (b) Waste water treatment plant/flow sheet : As given below for treatment process attached
The strata seepage water gets accumulated in main mine sump provided at the floor of the seam which allows significant settlement of suspended particles. Thereafter, supernatant mine water is pumped out on surface & passed through sedimentation pond for second stage settlement.
For, Workshop Effluent Treatment (100 kld) , a Zero – Discharge Workshop
Effluent Treatment Plant has already been set up and is being and will continue
to be operated. (c) Quantity of water recycled/reused/ to be recycled in (i) Percentage : 15 % (ii) m3/day : 546 (2910 m3/day goes as return flow)
d) Point of final discharge : Local drainage
Final Point Quantity discharged (in m3/day)
Surface (i) Agricultural land (ii) Waste land (iii) Forest land (iv) Green belt
---
2. River/nallah 3099
3. Lake
4. Sea
5. Others (specify)
Total 3099
(e) Users of discharge water
(i) Human : (ii) Livestock : (iii) Irrigation : Irrigation. (iv) Industry (mine site ) : (v) Others (specify) :
(f) Details of the river/nalla,if final effluent is/will be discharged (cumecs) : Local Seasonal Nullah/ Seasonal drain (i) Average flow rate :
(ii) Lean season flow rate : (iii) Aquatic life : Presently not a perennial water body. (iv) Analysis of river water 100 m : upstream and 100 m downstream of discharge point submitted.
Township :
(a) Waste water generation from township (m3/day) : About 70 m3/day (b) Are you planning to provide sewage treatment plant? : --
(c) Usage of treated water : The treated water is being discharged
into local nullah & is being used by local population for agricultural purposes.
32. Attach water balance statement in the form of a flow diagram : In Chapter - III indicating source(s), consumption (Section-wise) and output
33. Ambient noise level leq dB(A) : Baseline noise level data is given in Chapter – III
of
EIA/EMP. Details given below
AMBIENT NOISE LEVEL MONITORING STATIONS
SI.
No. Location Name Location Code
1. Core Zone N- 1
2. Pimpri Village N- 2
3. Bargaon Village N- 3
4. Pimpalgaori Village N- 4
5. Kunad Village N- 5
6. Telwasa Village N- 6
Data presentation & analysis
The generated noise level data are given in table below.
Noise level status
Location
Noise level dB(A) Noise level
Standards Daytime Nighttime
Daytime Nighttime
Core zone 64.9 - 67.8 54.8 - 57.4 75 70
Buffer zone 43.2 - 49.1 38.8 - 41.9 55 45
Mean Leq noise levels at day time and night time are ranging from 64.9 to 67.8
dB(A) and 54.8 to 57.4 dB(A) respectively in the core zone. Mean Leq noise levels
at day time and night time are ranging from 43.2 to 49.1 dB(A) and 38.8 to 41.9
dB(A) respectively in the Buffer zone. While comparing with IS: 4954 -1986 norms
for acceptable outdoor noise levels all values are found to be well within the
prescribed limits.
Summary
While comparing with IS: 4954 -1986 norms for acceptable outdoor noise levels the
Leq values are found to be within the limits.
34. Solid Waste
(a) Top soil and Solid waste quantity and quality
Name
(Lump/fines/
slurry/
sludge/others )
Composition
Quantity
(m3/month)
Method of Disposal
Mining activity*
a. Top Soil
b. Over burden
c. Others
(Specify)
Clay, Alluvium,
Shale,
Sandstone,
Quantity year –
wise given in
chapter – IV.
Dumping on surface as
external OB dump ,quarry
backfilling & embankment
construction .
Effluent Treatment
Plant (Sludge)
Oil & Grease
Silt
Is being and will continue
to be disposed off through
approved Recyclers.
Secured Land-fill
TOTAL ..
[* Annex layout plan indicating the dump sites Attached]
(b) (i) Does waste(s) contain any hazardous/ : No
toxic substance/radioactive materials
or heavy metals ?
(ii) If yes, whether details and precautionary : Not applicable
measures provided ?
(c) Recovery and recycling possibilities : Not applicable
(d) Possible user(s) of the solid waste : Quarry backfilling, External OB
Dumping
And embankment construction.
(e) (i) Is the solid waste suitable for backfilling ? : Yes
(ii) If yes, when do you propose : Already Started.
to start backfilling
(in million m3)
OB Management
Project Total waste generation
(Mm3)
Topsoil (Mm3)
Total OB generation
(Mm3)
Total OB in Ext. Dump
(Mm3)
Total OB Backfilled
(Mm3)
Original Project (ha) 10.33 Included in OB
10.33 9.58 & 0.75 in
Embankment
----
Expansion Project (ha) (balance life)
50.62 Included in OB
50.62 50.62 ----
TOTAL (Mm3)
60.95 60.95 60.20 & 0.75 in
Embankment
The capacity of external OB dumps proposed is about 60.20 Mm3. Remaining 0.75 Mm3 of OB will be used is construction of safety embankment.
The break up of OB quantities in external OB dumps is given in following table.
No. Dump Capacity in Mm3
0-30m 0.60m Total
i) Dump – 1 25.70 16.95 42.65
ii) Dump – 2 10.30 7.25 17.55
Total 60.20
SCHEDULE OF OVERBURDEN DUMPING
The following shows the yearwise OB dumping in external OB dump No.1 and No.2
Year Programmed Excavation of
OB(Mm3)
External OB Dump-1 (Mm
3)
External OB Dump-2
(Mm3)Excluding
Rehandling
1. 8.15 8.15 -
2. 7.40 7.40/15.55 -
3. 5.26 5.26/20.81 -
4. 5.25 5.25/26.06 -
5. 5.25 5.25/31.31 -
6. 4.70 4.70/36.01 -
7. 4.50 4.50/40.51 -
8. 4.40 2.14/42.65 2.26
9. 4.40 - 4.40/6.66
10. 1.10 - 1.10/7.76
11. 0.21 - 0.21/7.97
Total 50.62 42.65 7.97
(f) In case waste is to be dumped on the ground, indicate :
(i) Associated environmental problems : Fugitive emission of dust by
wind &
surface run off.
(ii) Number & type of waste dumps :
No.of external dumps : 01
Max. projected height of dumps (in m) : 60
No.of terraces and height of each stage : Four terraces, each of 15 m
with berm of 6 m at + 15 m &
+ 45m level and transportation
bench of 20 m at + 30 m
level.
Overall slope of the dump (degree) : 28o
Proposed reclamation measures :
Development of grasses ,
legumes & plants. OB
dump will be first
technically reclaimed with
proper benches & slopes.
Then it will be taken up for
biological reclamation
(afforestation) in phases
along with embankment.
The year – wise Calendar
Programme is given
below:-
(iii) Section of the waste dump in relation to : Yes
the adjacent ground profile attached
The details of green belt / Afforestation plan is as given below :-
Stage-wise Cumulative Plantation
year Green Belt
External Dump(OB +
Top Soil) Backfilled area
Others (undisturbed
area/etc.) Total
1 Area (ha)
No. of trees
Area (ha)
No. of trees
Area (ha)
No. of
trees
Area (ha)
No. of trees
Area (ha)
No. of trees
2 1st year
0 0 0 0 0 0 0 0 0 0
3 3rd year
0 0 0 0 0 0 0 0 0 0
4 5th year
0 0 25 62.5 0 0 10 25 35 87.5
5 End of mine life
0 0 110 275 0 0 145.93 364.825 255.93 1
6 Post mining
0 0 175 437.50 0 0 157.93 394.825 332.93 832.33
Post mining land use plan (Conceptual)
The post-mining land use pattern at Junad Extn. Deep OCP will be as follows:-
Conceptual Post Mining land use plan (Conceptual)
Post-mining Landuse pattern of ML/Project Area (ha)
S.N. Land use during mining
Land use (ha)
Plantation Water Body Public use Undisturbed Total
1 External OB Dump 175 0 0 0 175
2 Top soil dump 0 0 0 0 0
3 Excavation 0 101.7 0 0 101.7
4 Roads including embankment
17 8 25
5 Built up area 3 0 7 0 10
6 Green Belt 0 0 0 0 0
7 Undisturbed Area 137.93 0 0 0 137.93
Total 332.93 101.7 15 0 449.63
35. Fuel/Energy requirements*
[*To be furnished for mines having ML area more than 25 ha or captive
power generation of 500 KVA and above].
(a) Total power requirement – 4230 kVA
(in
kVA)
S.No Mine site Township Others (specify) Total
1 Present As given below
2 Proposed As given below
Total
(b) Source of power : - MAHAGENCO.
( Due approval from MAHAGENCO taken at area level for no. of mines
together).
S.No SEB/Grid* Captive
power
plant
DG sets
1. Present
As given
below
Nil
2. Proposed Nil
Total
[*Annex a copy of the sanction letter from the concerned authority]
SALIENT FEATURES OF THE ELECTRICAL PARAMETERS :
ITEM HEAD VALUE
i) Connected load - a) total 2352 kW
b) Only Mine 2088 kW
c) Only Township 264 kW
ii) Load in Operation – a) total 2133 kW
b) Only Mine 1869 kW
c) Only Township 264 kW
iii) Projected maximum demand - a) Total 853 kVA
b) Only Mine 776 kVA
c) Only Township 121 kVA
iv)Specific Energy Consumption (a)Total 8.52 kWh/t
b) OB -
c) Coal 1.32 kWh/t
d) Common 7.20 kWh/t
v) Specific Power Cost Rs. 44.97/t
vi) Fixed cost of power 77.22 %
vii) Variable cost of power 22.78 %
viii) Specific demand 1.495 MVA / Mt
ix) Capacitor bank provided– a) Total 425 kVAR
b) Only Mine 375 kVAR
c) Only Township 50 kVAR
x) Production of Coal 0.6 MTY
(c) Details of fuels : Deployment of HEMM proposed through partial hiring.
S.No. Fuel Daily consumption
(TPD)
Calorific
value
(Kcals/kg)
% Ash % Sulphur
1.
2.
3.
HSD
LSHS
Other
(Lub.)
Existing
15048 lpd
Proposed
25000 lpd
36. Storage of inflammable/explosive materials
S.No. Name Number of
Storages
Consumption
(in TPD)
Maximum Quantity at
any point of time.
1. Fuels Central
Storage
25000 lpd Maximum storage for 3
days only.
2. Explosives Magazine 5500 kg/day Maximum storage for 3
days only.
37. Human Settlement
Core Zone Buffer Zone
Population* All details
regarding
socio –
economic
have been
given in
Chapter – III.
All details regarding socio –
economic have been given in
Chapter – III.
No. of villages Nil
Number of households Village-
wise
[*As per actual survey]
38. Rehabilitation & Resettlement ( R & R) Plan*
[*Provide a comprehensive rehabilitation plan, if more than 1000 people are
likely to be displaced, other-wise a summary plan]
a) Villages falling within the study area :
Villages
Number Name
Core Zone Nil NA
500 m from the blasting
site(s)
Buffer zone All details regarding socio –
economic details have
been given in Chapter – III.
Shown in Index Plan
(Plate – II))
Township site --- ---
(b) Details of village(s) in the core zone : Nil.
( c) Population to be displaced and/or Land oustees : Only Land Oustees –
Yet to be finalized.
Name of
village(s) falling
within
Number of oustees
Land (only) Homestead
(only)
Land and Homestead
(both)
Mining Lease Yet to be finalized Nil As given in previous
Column.
Township Site Nil
(d) Whether R&R package has been finalized?
If yes, salient features of R & R plan for oustees : Not Applicable
(i) Site details where the people are proposed to
be resettled & facilities existing/to be created : Not applicable
(ii) Funds earmarked for compensation package * : Not Applicable
(iii) Agency/Authority responsible for their resettlement: Not Applicable
(iv) Time of commencement of resettlement : Not Applicable
of Project Affected People (PAP)
(v) Period by which resettlement of PAP will : Not Applicable
39. Lease-wise plantation details
(a) Lease area (in ha.) New mine Existing Mine
(i) Area broken up :
(ii) To be broken up : 101.70 (including existing Quarry)
(iii) Area not to be broken up : 347.93
(b) Township area (in ha) Combined Township.
( c) Area afforested and proposed (in ha)
Afforested -23.73 ha ; Proposed –The proposed afforestation plan is given below.
On the dump slopes and top surface, plantation of grass and trees will be done
in phases and the details are as follows ;-
(d) No. and type of trees planted and proposed :
(i) Existing : 59325
a. When plantation was started? 1998-99
No.of plant species planted
Number of saplings (per ha.)
As per details given below 2500
(ii) Proposed : As given Below ;-
No. of plant species to be
planted
Number of saplings (per ha)
Native Species in line with
existing plantation
2500
Stage-wise Cumulative Plantation
year Green Belt
External Dump(OB +
Top Soil) Backfilled area
Others (undisturbed
area/etc.) Total
1 Area (ha)
No. of trees
Area (ha)
No. of trees
Area (ha)
No. of
trees
Area (ha)
No. of trees
Area (ha)
No. of trees
2 1st year
0 0 0 0 0 0 0 0 0 0
3 3rd year
0 0 0 0 0 0 0 0 0 0
4 5th year
0 0 25 62.5 0 0 10 25 35 87.5
5 End of mine life
0 0 110 275 0 0 145.93 364.825 255.93 1
6 Post mining
0 0 175 437.50 0 0 157.93 394.825 332.93 832.33
This is a tentaive programme drawn with the consideration of the maximum
achieavable capacity of 1.50 MTPA and may undergo changes depending on
the actual progress of the mine
40. Environmental health and safety
(a) What major health and safety hazards
are anticipated?
No major health & safety
hazards anticipated. However,
coal mining activities are itself
hazardous and as such disaster
management plan has been
worked out considering the
probable risks / hazards &
their mitigative measures have
been given in detail in Chapter
– VI.
(b) What provisions have been made/proposed
to be made to conform to health and safety
requirement? :
Mine will be worked as per
statute. Dispensary, First
aid center at the mine
level, full fledged hospital
at Area level to cater to
the needs of all employees.
Emergency Response Plan will
be prepared and mock
rehearsal will be done
regularly.
( c) In case of an existing mine :
(i) Comprehensive report on health status : Periodical Medical Examination
of all workmen once in five years.
Mineralogical composition of RPM (dust) :
Free silica as SiO2 - 11.5
Chromium* (Total as well as Hexavalent) - Not applicable
Lead ** - Not applicable
[*Only for Chromite mines] [** Only for Base Metal mines]
(d) Information on radiation protection measures, if applicable : Not Applicable
41. Environmental Management Plan
Salient features of environmental protection measures.
S.No. Environmental issues* Already practiced, if
applicable
Proposed.
1. Air pollution Green belt development,
plantation at all suitable
vacant areas, OB dump,
Wet Drilling, water
spraying on
haul road & coal
transportation
road etc.
To be continued
2. Water pollution Sedimentation pond for
mine pumped out
water
Workshop Effluent
Treatment Plant for
workshop effluent
To be continued
3. Water conservation Earthen check dams Earthen check dams
4. Noise pollution Providing personal
protective gears / ear
muffs & ear plugs,
maintenance of P&M,
green belt development
etc.
To be continued
5. Solid waste/Tailings Backfilling in decoaled
void, embankment
construction, external OB
dump & biological
reclamation thereafter.
To be continued
6. Land degradation Technical & biological
reclamation
To be continued
7. Erosion & Sediment Plantation on OB dump &
embankment, garland
drains around OB dump
& coal dump , green belt
on plain land.
To be continued
8. Top soil Initiallty to be dumped at
earmarked site and
thereafter being used
concurrently
9. Ground vibration Controlled Blasting To be continued
10. Wildlife conservation Not Applicable Not Applicable
11. Forest protection Not Applicable Not Applicable
12. Others (specify) Social development works
in nearby villages.
To be continued as per the
CSR Policy of the Company (* As applicable)
42. Compliance with environmental safeguards (for existing units) :
(a) Status of the compliance of conditions of : Certificate of Compliance
environmental clearance issued by MOEF Enclosed – Annexure – IV.
if any, enclosed
(b) Status of the compliance of ‘ Consent to : Complied
operate’ issued by SPCB, if any, enclosed.
(c) Latest ‘environmental statement’ enclosed : Annexure – V.
43. Scoping of EIA
Whether environmental impact assessment : Yes
of the project has been carried out by following
scoping process?
If yes, a copy of scoping of EIA annexed : Details given below.
IMPORTANT ENVIRONMENTAL ASPECTS (Scoping )
1. Forest land involved No
2. Wild life sanctuary ( 10 km. radius) None
3. Fragile Eco/ Bio- diversity system
nearby (10 km. radius)
None
4. Coastal area nearby (10 km. radius) None
5. Environmental impact on the region. No adverse impact anticipated.
However the project will be beneficial
to the local people of the region.
6. Impact on quality & quantity of ground
water specific to the project.
The detailed impact assessment has
been done and given in Chapter – III
& IV. Impact will be insignificant.
7. Risk & Hazards involved due to the
project
Risk & hazards associated with
mining will be limited to mine area
only. However, the mine is being
worked and will continue to be
worked as per the statute.
8. Env. Pollution control
measures
Environmental Pollution control
measures are being implemented and
will continue to be effectively
implemented & regular monitoring will
be done.
9. Rehabilitation & resettlement. There is no Resettlement of house
oustees involved in this
proposal.There is Rehabilitation of
land oustees involved due to
acquisition of additional agricultural
land.
Entire Rehabilitation of land oustees
will be carried out as per Company’s
Policy.
44. Mine closure
(a) Have you planned mine closure : Yes
(b) Submitted a conceptual mine : Yes
closure plan
(c) If yes, indicate estimated amount : As per MOC Guidelines – Aug,2009
for implementing the same (in Rs.lakhs)
Details of Progressive Mine Closure Plan is given below;-
OBJECTIVES OF CLOSURE PLANNING
Mine closure planning has to be carried out at the starting of the mine and
needs periodic reviewing and revision during its life cycle to cope with the geo-
technical constraints, safety and economic risks, social & environmental
challenges. Various other objectives are as follows.
a) To allow a productive and sustainable after-use of the site which is
acceptable to the mine owner and the regulatory authority.
b) To protect public health and safety.
c) To alleviate or eliminate environmental damage and thereby
encourage environmental sustainability.
d) To minimise adverse socio-economic impacts.
CLOSURE ACTION PLAN
Closure planning is a whole-of-life exercise that begins at the start of a mine and
continues till post closure. The dynamic nature of closure planning requires
regular and critical review to reflect changing circumstances as a result of any
operational change, new regulation, new technology and remain flexible
enough to cope with unexpected events. Following steps have to be
undertaken in relation to Mine Closure Planning :
(a) Prior to the surface demolition/restoration a surface audit should be
undertaken on all surface structures, spoil heaps, lagoons, etc. to assess
whether there are any hazardous materials that could cause problems viz;
explosives, chemicals, etc. A list of surface assets should be prepared and
made available to potential purchasers, prospective purchasers could be
invited and asked to submit sealed bids.
(b) This could ensure that the sale of assets give better financial gain.
(c) In order to identify potential impact, necessary hydro-geological studies
into post-mining groundwater recharge has to be done. The void of the
mine can be proposed as a water resource to be utilised for aquaculture.
(d) Work force on roll of WCL may be redeployed for gainful utilisation of
employees of WCL.
(e) As a detailed component of the Closure Plan, a Decommissioning Plan is
to be developed towards the final stages preferably 5 years prior to
tentative closure of mine. Once established it may be updated annually.
PROTECTIVE MEASURES TO BE TAKEN
Protective measures must include the following :
a) The protection of mine boundary, building and other structure on the
project site against access by unauthorised persons.
(b) The maintenance of all mechanical, hydraulic and waste management
system
(c) The continuation of all monitoring programs.
(d) The control of all contaminated effluents
(e) The securing of all petroleum products, chemicals and waste.
(f) The rendering of all tailings, dams and piles of earth, rock and waste
resulting from work done on the project site in a stable and safe condition.
CLOSURE COSTS
The proposed Junad Extn. Deep OC Project has been planned upto 170 m
depth and it is most likely that this will be extended further in dip side in future. A
financial provision of Rs.6.00 lakhs/ ha as per the guidelines issued by MoC will
be provided throughout the mine life in order to undertake mine closure
activities (for plantation in slope of dumps & quarry, for protection of mine
boundary and continuation of monitoring programme and control of
contaminated effluents). Closure cost may be reviewed under the changing
circumstances and new legislative requirements.
45. Capital cost of the project (in Rs. Lakh) : 5478.40
(Based on approved Project Report)
46. Cost of environmental protection measures : As shown below (in Rs.
Lakh)
ENVIRONMENTAL COST PROJECTION
The total expenditure made for environmental protection under both Capital &
Revenue head is given below:-
EXPENDITURE INCURRED ON POLLUTION CONTROL MEASURES
72.04TOTAL
10.28WATER POLLUTION CONTROL MEASURES
3
37.26PLANTATION2
24.50AIR POLLUTION CONTROL MEASURES1
AMOUNT IN
Rs. LAKH
PARTICULARSSL.
NO.
The details of capital provision on environmental protection measures for
proposed expansion project are as given below :-
PROPOSED CAPITAL FOR ADDITIONAL POLLUTION CONTROL MEASURES
37.16TOTAL
10.16WATER TANKER 5
6.0LAND RECLAMATION MEASURES
INCLUDING LAND USE MAPPING
THROUGH REMOTE SENSING
4
5.0DUST SUPPRESSION ARRANGEMENT AT
HAUL ROAD , STOCKYARD ETC.
3
8.0STRENGTHENING OF ETP FOR
WORKSHOP EFFLUENT
2
8.0STRENGTHENING OF SEDIMENTATION
POND FOR TREATMENT OF MINE WASTER WATER
1
AMOUNT IN
Rs. LAKH
PARTICULARSSL.
NO.
47. Amount earmarked for socio-economic : As per the CSR Policy of CIL
welfare measures for the nearby villages Details given in Chapter – VI.
other than R & R plans.
48. Public Hearing
a. Date of advertisement : 02.01.2013
b. Newspapers in which the advertisement appeared : The Hitavada &
Daily Lokmat
c. Date of public hearing (DD/MM/YY) : 05.02.2013
d. Public Hearing Panel chaired by & members present : Addl. District
Magistrate
Yavtmal & MPCB
Officials
e. No. of people attended the public hearing meeting : Panel Members
&
and number of people from the lease area No. of villagers - 250
(approx.)
f. Summary/details of public hearing in tabular form :
The Environmental Public Hearing in respect of proposed Junad Opencast
Expansion Project of M/s Western Coalfields Ltd., Wani North Area, Tal. Wani ,
Dist. Yavatmal for enhancement in production capacity from 0.60 MTPA to 1.50
MTPA and increase in lease area from 174.28 ha to 449.63 ha was held on
05/02/2013, 11.00 am at Kamgar Manoranjan Kendra, Bhalar Township, At Post
Bhalar, Tal. Wani, Dist. Yavatmal. The public hearing was conducted under the
Chairmanship of Shri Rajendra Deshmukh, Additional District Magistrate,
Yavatmal (The representative nominated by District Magistrate, Chandrapur).
Shri S.D.Patil, Sub Regional Officer, MPCB, Chandrapur was the Convener of the
Public Hearing. Shri N.G. Nihul, Regional Officer, MPCB, Chandrapur was the
Member of Public Hearing panel. Shri M.P.Barhanpurkar, District Mining Officer,
Yavatmal, Shri L.S.Varhade, SDO, Wani and Shri Misal, Tahsildar,Wani were also
present during the public hearing. The public hearing started at 11.00 am with
the permission of the Chairman of the Public Hearing Panel.
First of all, the Convener welcomed all present for Public Hearing. He told that,
the Public Hearing is being conducted as per the provisions of EIA Notification
dated 14/09/2006 and amended Notification dated 01/12/2009 of Ministry of
Environment & Forests, New Delhi. He told that the project proponent received
TOR (Terms of Reference) for this project from Ministry of Environment & Forests,
New Delhi on 11/07/2008. Accordingly, project proponent prepared Draft EIA &
EMP Report and submitted their application on 15/02/2010 to the Board
requesting for conducting the Public Hearing.
The Public Hearing for this project was earlier scheduled on 31.08.2010 and
21.12.2010 but during hearing it was cancelled at both the times due to some
reasons.
Thereafter, the public hearing was scheduled on 10.10.2012. The public notice
for the said public hearing was published on 08.09.2012 in Daily Lokmat (Marathi)
and Daily Hitawad (English) stating date, venue and time of public hearing. The
said public hearing was postponed due to some unavoidable reasons at that
time as per District Collector, Yavatmal letter no. 937/2012 dated 06.10.2012. The
notice about postponement of Public Hearing was published in Marathi Dialy
Lokmat and English Daily Hitavada on 08.10.2012. Afterwards the public hearing
is scheduled on 05.02.2013 and the public notice in this behalf was published on
02.01.2013 in Daily Lokmat (Marathi) and Daily Hitawad (English) stating date,
venue and time of public hearing.
The copies of Draft EIA/EMP and Executive Summary in English and Marathi were
made available vide letter no. 1288/2010 dated 28.07.2010 to the offices of
District Collector, Yavatmal, District Industries Centre, Yavatmal, Zilha Parishad,
Yavatmal, MPC Board (HQ), Mumbai, Regional Office and Sub Regional Office,
MPC Board, Chandrapur, Environment Department, Mantralaya, Mumbai, Tahsil
Office, Wani and offices of the concerned Gram Panchayat Pimpalgaon, Tal.
Wani for the knowledge of concerned. While issuing the notice of
postponement, it was requested to above offices for making available the
documents submitted by project proponent for the concerned to study till the
date of Public Hearing. Also, through this notice it was requested to file their
objections/suggestions within 30 days from the date of public notice to the Sub
Regional Officer, MPC Board, Chandrapur. The Member Secretary, MPC Board,
Mumbai has issued the Panel Order no. E-15 of 2013 dated 29/01/2013 for the
Public Hearing.
The Minutes of Public Hearing in respect of proposed Junad Opencast Expansion
Project of M/s Western Coalfields Ltd., Wani North Area, Tal. Wani , Dist.
Yavatmal conducted on 05/02/2013 11.00 am Kamgar Manoranjan Kendra,
Bhalar Township, At Post Bhalar, Tal. Wani, Dist. Yavatmal is enclosed herewith at
Annexure – III.
The replies to the queries raised during the Public Hearing are already
incorporated in the said minutes.
Sr. No.
Issues WCL Comments
1 Crop compensation. Sub Area Manager Junad Opencast Mine said that Rs. 16 Lakhs were sanctioned by WCL Board and it was decided by the Board that the fund should be utilized for community development through SDO.
2 Acquisition of balance land beyond what has been notified.
Shri Patil, Area Planning officer Wani North Area tlold that section 9 is completed in respect of land of Junad, Pimpalgaon and Borgaon villages and it is acquired. He added that land is required in future and remaining land will be acquired at that time. It will take at least 3 years to complete the whole process and to start the project.
3 Rehabilitation of Kolar, Pimpri, and Aheri village.
Shri Patil, Area Planning officer Wani North Area said that the rehabilitation of Kolar, Pimpri and Aheri villages is proposed. Socio-economical survey was carried out in these villages with the help of an NGO.
4 Suppression of dust on Nilapur – Brahmni road
Shri Murthy, WCL Wani North Area said that Nilapur- Brahmni road is not owned by WCL hence fixed rain-guns could’t be provided there. Water tanker will be deployed on this road.
5 Venue of Public Hearing Shri N.G. Nihul said that the public hearing can be conducted at the place in close proximity of project site and further clarified thatclose proximity means the place which s nearby to the project site. Chairman Shri Rajendra Deshmukh last time the public hearing was conducted at project site, at that time presentation was not viewable due to sunlight. Hence due to such issues this venue is decided which is 5-6 km from the project site and this is not a too long distance. The facilities are available here for convenience of people.
6 Tree Plantation Shri Sujit Sen WCL Wani North Area said that total 17 lakhs 20 thousand trees have been planted in Wani North Area since 1994 to 2013.Contract for the said work is given to Forest Development Corporation of Maharashtra (FDCM) and the work will start soon. Shri Maji Sub Area Manager Junad Open Cast said that tree plantation will be carried out at earliest by using manpower in the existing project.
7 Street lights Shri Maji, Sub Area Manager Junad Opencast Mine said that street lights will be provided using CSR funds.
49. Whether the following approvals*(wherever applicable) have been obtained ?
(i) Site clearance from MOEF : Not Applicable
(TOR issued attached in Annexure - I).
(ii) Consent for Establishment’ from the : To be obtained for 1.50 MTPA
State Pollution Control Board.
(iii) NOC from Atomic Mineral Division : Not applicable
(iv) Mining plan approval from IBM/ : Approved by WCL Board.
Ministry of Coal
(v) In case of existing mines, mining : Not Applicable
scheme approval from IBM
(vi) Forestry clearance under FCA, 1980 : Not Applicable
(vii) NOC from Chief Controller of : Existing Mine already obtained.
Explosives
(viii) Commitment regarding availability/ : Not applicable as water
pumping of water from the concerned requirement will be met
authorities from mine pumped out water.
(ix) In case of ML area falling in notified areas : Not Applicable
of the Central Ground Water Authority
NOC from them.
[*Annex copies of approvals and number them]
50. Was / is there any court case relating : Not applicable
to the project or related activities ?
If so, provide details present status.
Verification: The data and information given in this proforma are true to the best
of my knowledge and belief.
Signature of the applicant*
with Full name & address
[*Owner or his authorized signatory]
Date:
Place: NAGPUR
Given under the seal of organization on
behalf of whom the applicant is
signing.
Annexure – I