338
ENVIRONMENTAL IMPACT ASSESSMENT AND ENVIRONMENTAL MANAGEMENT PLAN FOR ENVIRONMENTAL CLEARANCE FOR JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) (For enhancemement in Production Capacity from 0.60 MTPA to 1.50 MTPA with increase in land area from 174.28 ha to 449.63 ha Land) PREPARED AS PER TOR RECEIVED FROM MOEF VIDE ITS LETTER NO. J 11015/225/2014- IA. II(M) dated 21.11.2014 January 2015 Central Mine Planning & Design Institute Limited A Mini Ratna Company

JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Embed Size (px)

Citation preview

Page 1: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

ENVIRONMENTAL IMPACT ASSESSMENT

AND

ENVIRONMENTAL MANAGEMENT PLAN FOR

ENVIRONMENTAL CLEARANCE

FOR

JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL)

(For enhancemement in Production Capacity from 0.60 MTPA to 1.50 MTPA with increase in land area from 174.28 ha to 449.63 ha Land)

PREPARED AS PER TOR RECEIVED FROM MOEF VIDE ITS LETTER NO. J – 11015/225/2014- IA. II(M) dated 21.11.2014

January – 2015

Central Mine Planning & Design Institute Limited A Mini – Ratna Company

Page 2: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

SUBMISSION

This Environmental impact assessment (EIA)/ Environmental Management Plan (EMP) has been prepared based on the Terms of Reference (TOR) issued by MOEF vide its letter no. J-11015/225/2014-IA. II (M) dated 21/11/2014.

The copy of the TOR has been enclosed as Annexure – I.

The Public Consultation/ Public Hearing as per EIA Notification, 2006 has been completed on 05.02.2013. The minutes of the Public Hearing have been attached at Annexure – III.

Page 3: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

CONTENTS

Chapter

No.

Name of the Chapter

Compliance of TOR

I Introduction

II Project Profile

III Description of Environment

IV Anticipated Environmental Impacts & Mitigation

Measur

V Environmental Monitoring Programm

VI Additional Studies

VII Project Benefits

VIII Environmental cost –Benefit Anal

IX Environmental Management Plan

X Summary & Conclusion

XI Disclosure of Consultants Engaged

XII Check List

XIII Annexures

Page 4: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

LIST OF PLATES

Plate No. PARTICULARS

I Loaction Plan

II Topo – Sheet Plan Showing main drainage in Core & Buffer Zone

III Land Use/cover mapping of Core,Buffer and Impact Zone of

Junad OCP based on LISS- III Satellite data of 2011

IV Revenue Plan

V Topographical & Geological Plan

VI Proposed Quarry & Surface layout Plan

VII Existing Longitudinal & Transverse Section of Proposed Quarry

Layout

VIII Post Mining Land Use Plan

IX Post Mining Longitudinal & Transverse Section of Quarry Layout

X AAQM Stations

LIST OF ANNEXURES

ANNEXURE No.

PARTICULARS

I Generic ToR NO. J – 11015/225/2014- IA. II(M) dated 21.11.2014

II Duly filled in Proforma for Appraisal of Mining Project III Copy of Minutes of Public Hearing held on 05.02.2013

IV Copy of Cerificate of Compliance of Conditions of earlier EC as issued by MOEF, Bhopal & corresponding ATR Submitted.

V Copy of Environmental (Audit) Statement 2013-14

Page 5: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Junad Deep Extn. OC. COMPLIANCE OF TERMS OF REFERENCE

Ref.:- MOEF’s letter no. J-11015/225/2014-IA. II (M) dated 21/11/2014.

Sr. No.

TOR Condition Compliance

Generic conditions for opencast coal mine

1 An EIA-EMP Report would be prepared for 0.60 MTPA (Norm) 1.5 MTPA (Peak) rated capacity in an ML/project area of 174.28 ha to 449.63 ha based on the generic structure specified in Appendix III of the EIA Notification 2006.

This EIA/EMP has been prepared for 0.60 MTPA (Norm) 1.5 MTPA (Peak) rated capacity in an ML/project area of 174.28 ha to 449.63 ha based on generic structure as specified in Appendix III EIA Notification 2006.

2 An EIA-EMP Report would be prepared for 0.60 MTPA(Norm) 1.55 MTPA (Peak) rated capacity cover the impacts and management plan for the project specific activities on the environment of the region, and the environmental quality ?air, water, land, biotic community, etc. through collection of data and information, generation of data on impacts including prediction modelling for 0.60 MTPA(Norm) 1.55 MTPA (Peak) of coal production based on approval of project/Mining Plan For 0.60 MTPA(Norm) 1.5 MTPA (Peak) Baseline data collection can be for any season except monsoon.

This EIA/EMP report has been prepared for 0.60 MTPA (Norm) 1.55 MTPA (Peak) production capacity with increase in ML area from 174.28 ha to 449.63 ha. For this, baseline , socio-economic and Flora Fauna study were conducted in surrounding area from 01st April`2013 to 30th June`2013 covering the impacts and Management plan for the project specific activities on the environment of the region and the environmental quality – air, water land, biotic community etc. through collection of baseline data (Pre-Monsoon Season of 2013)

3 A map specifying locations of the State, District and Project location.

The map showing the project location specifying the State & district has been attached in as Plate – I.

4 A Study area map of the core zone and 10km area of the buffer zone (1: 50,000 scale) clearly delineating the major topographical features such as the land use, surface drainage of

There is no ecologically sensitive areas such as Biosphere Reserves / National Parks / WL Sanctuaries / Elephant Reserves, forests (Reserved/Protected), migratory corridors of fauna and areas where endangered fauna and plants of medicinal and economic importance

Page 6: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Sr. No.

TOR Condition Compliance

rivers/streams/nalas/canals, locations of human habitations, major constructions including railways, roads, pipelines, major industries/mines and other polluting sources. In case of ecologically sensitive areas such as Biosphere Reserves/National Parks/WL Sanctuaries/ Elephant Reserves, forests (Reserved/Protected), migratory corridors of fauna, and areas where endangered fauna and plants of medicinal and economic importance found in the 15 km area of the buffer zone should be given.

are found in the 15 km area of the buffer zone, however the study area map showing core Zone and Buffer Zone (10 km) clearly delineating the major topographical features such as the land use, surface drainage of rivers / streams / Nalas / canals, Locations of human habitations, major constructions including railways, roads, pipelines, major industries/mines and other polluting sources has been attached as Plate – II (Topo – Sheet Plan) & III (Staellite Imagery).

5 Land use map (1: 50,000 scale) based on a recent satellite imagery of the study area may also be provided with explanatory note of the land use. Satellite imagery per se is not required.

The land use map based on a recent satellite imagery of the study area with explanatory note of the land use is attached in the final EIA/EMP. The land involved in project is mostly agricultural land and there is no forestland involved in the project and has been attached as III (Staellite Imagery).

6 Map showing the core zone delineating the agricultural land (irrigated and unirrigated, uncultivable land (as defined in the revenue records), forest areas (as per records), along with other physical features such as water bodies, etc. should be furnished.

The map of the core zone showing the proposed mining area has been attached as Plate – III (Satellite Imagery) & IV ( Revenue Plan). The land is mostly agricultural land and there is no forestland involved in the project.

7 A contour map showing the area drainage of the core zone and 2-5 km of the buffer zone (where the water courses of the core zone ultimately join the major rivers/streams outside the lease/project area) should also be clearly indicated as a separate map.

The Topographical & Geological Plan of the site showing all the details has been enclosed as Plate- V.

Page 7: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Sr. No.

TOR Condition Compliance

8 A detailed Site plan of the mine showing the various proposed break-up of the land for mining operations such as the quarry area, OB dumps, green belt, safety zone, buildings, infrastructure, CHP, ETP, Stockyard, township/colony (within and adjacent to the ML), undisturbed area and if any, in topography such as existing roads, drains/natural water bodies are to be left undisturbed along with any natural drainage adjoining the lease /project and modification of thereof in terms of construction of embankments/bunds, proposed diversion/re-channelling of the water courses, etc., approach roads, major haul roads, etc.

The Quarry and Surface Layout Plan of the site showing all the details has been enclosed as Plate- VI.

9 In case of any proposed diversion of nallah/ canal/ river, the proposed route of diversion/ modification of drainage and their realignment, construction of embankment etc. should also be shown on the map.

The Quarry and Surface Layout Plan of the site showing all the details has been enclosed as Plate VI.

10 Similarly if the project involves diversion of any road/railway line passing through the ML/project area, the proposed route of diversion and its realignment should be shown.

Diversion of Water pipe line A water pipeline serving to Pragati Nagar colony passing along the arterial road from Ukni to Kolar Pimpri OCP partly falls over the dip side dumping area (External OB Dump No.1) of Junad Extension OC. It is required to divert this water pipeline partly so that the volume of required OB can be dumped in external OB dump, keeping safe distance from the dump. Provision for diversion of this water pipeline is proposed in the PR. Part Diversion of Approach Road Existing approach road to the project will be partly diverted because of extension of Junad OC mine (Reference – Plate – VI) Surface Layout Plan). Diversion of existing approach road is

Page 8: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Sr. No.

TOR Condition Compliance

proposed over the safety embankment, 30 m wide at top. Proper capital provision has been made in this report for this diversion.

11 Break up of lease/project area as per different land uses and their stage of acquisition.

The details are as given below

Sl.No. Particulars Land already acquired in existing Junad OC Mine

Land to be acquired under proposed Junad Extn. OC Mine

Total

1. Tenancy Land

174.28 ha

269.25 ha*

443.53

2. Govt. Land

- 6.10 ha 6.10

3. Forest Land

NIL NIL NIL

TOTAL 174.28 275.35 ha

449.63 ha

This 269.25 ha of land to be acquired includes 5.20 ha land of Kolar Pimpri Extn.Project and 13.85 ha of acquired land by existing Pimpalgaon OC Project. Both the projects are adjacent to Junad Extension OC Mine.

Thus, the total land involved in this project is 449.63 ha, out of which 174.28 ha land has already been acquired in existing Junad OC mine and balance 275.35 ha will have to be acquired.

Compensation bill against additional land acquisition approved by Ministry of Coal.

12 Break-up of lease/project area as per mining operations.

Details as given below:-

S.No. Particulars Area (ha)

1 Total Quarry Area

101.70

2 External OB Dump 175.00

3 Infrastructure including approach road, etc.

15.00

4 Embankment 20.00

5 Colony 0.00

6 Area needed for 137.93

Page 9: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Sr. No.

TOR Condition Compliance

rationalization & safe blasting zone

TOTAL 449.63

13 Impact of changes in the land use due to the start of the projects if much of the land being acquired is agricultural land/forestland/grazing land.

Detailed discussion in Chapter IV as indiacted in compliance above.

14 Collection of one-season (non-monsoon) primary baseline data on environmental quality - air (PM10, PM2.5, SOx, NOxand heavy metals such as Hg, Pb, Cr, As, etc), noise, water (surface and groundwater), soil along with one-season met data coinciding with the same season for AAQ collection period.

Baseline data in the surrounding area was carried out from 1st April 2013 to 30th June 2013 and the details of data generated are given in Chapter- III.

15 Map of the study area (1: 50, 000 scale) (core and buffer zone clearly delineating the location of various stations superimposed with location of habitats, other industries/mines, polluting sources. The number and location of the stations in both core zone and buffer zone should be selected on the basis of size of lease/project area, the proposed impacts in the downwind (air)/downstream (surface water)/groundwater regime (based on flow). One station should be in the upwind/ upstream/ nonimpact/non-polluting area as a control station. The monitoring should be as per CPCB guidelines and parameters for water testing for both ground water and surface water as per ISI standards and CPCB classification wherever applicable. Values should be

A map showing study area (core and buffer zone) clearly delineating the location of various stations superimposed with location of habitats, other industries/mines, polluting sources has been attached as Plate – X The number and location of the stations in both core & buffer zone have been selected on the basis of size of lease area / project area, the proposed impacts in the downwind (air) / downstream (surface water) / groundwater regime (based on flow). One station has been in the upwind / upstream / non-impact / non-polluting area as a control station. The monitoring will be as per CPCB guidelines and parameters for water testing for both ground water and surface water as per ISI standards and CPCB classification wherever applicable.

Page 10: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Sr. No.

TOR Condition Compliance

provided based on desirable limits.

16 Study on the existing flora and fauna in the study area (10km) carried out by an institution of relevant discipline and the list of flora and fauna duly authenticated separately for the core and buffer zone and a statement clearly specifying whether the study area forms a part of the migratory corridor of any endangered fauna. If the study area has endangered flora and fauna, or if the area is occasionally visited or used as a habitat by Schedule-I fauna, or if the project falls within 15 km of an ecologically sensitive area, or used as a migratory corridor then a comprehensive Conservation Plan should be prepared and submitted with EIA-EMP Report and comments from the CWLW of the State Govt. also obtained and furnished.

The details of flora and fauna in the core and buffer zone has been given in Chapter – III. There is no endangered flora and fauna in the Core as well as in the buffer Zone.

17 Details of mineral reserves, geological status of the study are and the seams to be worked, ultimate working depth and progressive stage-wise working scheme until end of mine life should be reflected on the basis of the approved rated capacity and calendar plans of production from the approved Mining Plan. Geological maps and sections should be included. The progressive mine development and Conceptual Final Mine Closure Plan should also be

The details of mineral reserves, geological status of the study area and the seams to be worked, ultimate working depth and progressive stage-wise working scheme until end of mine life has been reflected on the basis of the approved rated capacity and calendar plans of production from the approved Mining Plan in Chapter - II. Revenue Plan, Geological maps, Quarry layout Plan and sections have also been included as Plate – IV, V, VI, VII & VIII.

Page 11: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Sr. No.

TOR Condition Compliance

shown in figures.

18 Details of mining methods, technology, equipment to be used, etc., rationale for selection of that technology and equipment proposed to be used vis-à-vis the potential impacts.

Details of mining methods, technology, equipment to be used, etc., rationale for selection of that technology and equipment proposed to be used vis-à-vis the potential impacts has been given in Chapter – II.

19 Impact of mining on hydrology, modification of natural drainage, diversion and channelling of the existing rivers/water courses flowing though the ML and adjoining the lease/project and the impact on the existing users and impacts of mining operations thereon.

The detailed hydrogeological assessment has been incorporated in Chapter-III and the impact assessment has been incorporated in Chapter-IV along with hydrographs.

20 Detailed water balance should be provided. The breakup of water requirement for the various mine operations should be given separately.

As desired the detailed water balance in the study area has been given at page no. 135 in Chapter – III.

21 Source of water for use in mine, sanction of the competent authority in the State Govt. and impacts vis-à-vis the competing users.

Source of water in use in the mine is mine pumped out water. The details of competing user have been given in Chapter – III.

22 Impact of mining and water abstraction use in mine on the hydrogeology and groundwater regime within the core zone and 10 km buffer zone including long term modelling studies on. Details of rainwater harvesting and measures for recharge of groundwater should be reflected in case there us a declining trend of groundwater availability and/or if the area falls within dark/grey zone.

The impact on ground water due to abstraction of mine water covering core and Buffer Zone has been discussed in detail in Chapter – III & IV.

23 Impact of blasting, noise and vibrations.

The impact of blasting, noise and vibrations has been discussed in detail in Chapter – IV.

Page 12: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Sr. No.

TOR Condition Compliance

24 Impacts of mining on the AAQ, predictive modelling using the ISCST-3 (Revised) or latest model.

Impact of mining on AAQ, predictive modelling has been done using FDM Model and results have been reported in chapter – IV.

25 Impacts of mineral transportation within and outside the lease/project along with flow-chart indicating the specific areas generating fugitive emissions. Impacts of transportation, handling, transfer of mineral and waste on air quality, generation of effluents from workshop, management plan for maintenance of HEMM, machinery, equipment. Details of various facilities to be provided in terms of parking, rest areas, canteen, and effluents/pollution load from these activities.

The impact of mining on the various environmental attributes has been discussed in details in Chapter – IV.

26 Details of waste generation OB, topsoil as per the approved calendar programme, and their management shown in figures as well explanatory chapter with tables giving progressive development and mine closure plan, green belt development, backfilling programme and conceptual post mining land use. OB dump heights and terracing should based on slope stability studies with a max of 28o angle as the ultimate slope. Sections of dumps (ultimate) (both longitudinal and cross section) with relation to the adjacent area should be shown.

The details have been discussed in Chapter – IV. Sections have been shown in Plate – VI & VIII.

27 Progressive Green belt and afforestation plan (both in text, figures as well as in tables prepared by MOEF) and selection of species (local) for the afforestation/plantation

Details have been given in chapter – IV. The details of Stage wise land use & reclamation Area and Stage wise Cumulative plantation have been duly filed in Table 1 & 2 respectively in the subsequent pages.

Page 13: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Sr. No.

TOR Condition Compliance

programme based on original survey/landuse.

28 Conceptual Final Mine Closure Plan, post mining land use and restoration of land/habitat to pre- mining. A Plan for the ecological restoration of the area post mining and for land use should be prepared with detailed cost provisions. Impact and management of wastes and issues of rehandling (wherever applicable) and backfilling and progressive mine closure and reclamation.

Mine closure plan has been an intergral part of project report. Relevant table is given in chapter – IV. The details of post mining land use have been duly filed in table 3 in the subsequent pages.

29 Flow chart of water balance. Treatment of effluents from workshop, township, domestic wastewater, mine water discharge, etc. Details of STP in colony and ETP in mine. Recycling of water to the maximum possible extent.

The details have been discussed in Chapter – III.

30 Occupational health issues. Baseline data on the health of the population in the impact zone and measures for occupational health and safety of the personnel and manpower for the mine.

WCL has full fledged medical set up in all areas to check up and monitor all the Occupational diseases endangering the health of its preciuos workforce. The periodical medical Examinationfor all workman is compulsory as per Statute.It is carried out once in every five years for each and every worker and proper records are maintained and submitted to Directorate General of Mines Safety as it is a statutory requirement.

In case of workers, above 50 years of age and employed in underground mine, this periodical medical Examinationis carried out every two and half years interval. In Pathakhera Area, under whose administrative control, the mine under consideration is being worked is no exception. All the statutory obligations under the Occupational health are strictly followed. Set up of Occupational Health Services At WCL: WCL is having Occupational health committee at

Page 14: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Sr. No.

TOR Condition Compliance

the corporate (HQ) level as well as at the unit (Area /Project level).

At corporate level, the committee consists of the following: -

Chief General Manager (Safety)

Chief of Medical Services

Periodical Medical Examination(PME) Incharge of HQ.

The committee scrutinizes the report of the area every quarter.

At Unit level, the committee consists of the following: -

General Manager (Operations)

Area Medical Officer

Area Safety Officer

Periodical Medical Examination (PME) Incharge of Area.

The above committee takes the review at area level every month. There are 11 hospitals having PME Centres in the hospitals. The PME Centres are well equipped with Spirometry (Lung Function test), Audiometry (for testing hearing impairment) along with the facilities for X – Ray & other bio – chemical tests.

The details are as follows: -

Periodical Medical Examination(PME) Centres – 11

(Occupational Health Centres)

Nos. of Doctors engaged in Periodical Medical ExamiNAtion - 11

Nos. of Doctors trained in Periodical Medical ExamiNAtion - 22

Nos. of X – Ray machines (300 mA) - 9

Nos. of X – Ray machines (500 mA) - 2

Nos. of ILO film Tests - 10

Nos. of Audiometer units - 7 (4 units are under process of procurement)

Page 15: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Sr. No.

TOR Condition Compliance

Nos. of Spirometer units - 11

Nos. of Pathology Labs - 11

Nos. of X – Ray technicians - 14

Nos. of Laboratory Technicians - 22

All the PME Centres are fully computerised.

As per the Statute / Mines Act, 1952, all the workers are examined every five years and the disease profile is maintained in PME Centres in different colour codes as given below: -

Yellow Card – Hypertension

Green Card – Diabetes

Red Card - Ischaemic Heart Disease Workers exposed to high decibel machineries i.e. more than 90 decibels and are found to have developed hearing impairment, are subjected to repeated audiometric tests.

In suitable cases, as per the recommendation of the Apex Medical Board, the change of job is also suggested and implemented accordingly. In addition, the Welfare Board of WCL time to time makes visits to different area hospitals & PME Centres so as take stock of the ground realities.

31 Risk Assessment and Disaster Preparedness and Management Plan.

The details have been discussed in Chapter – VI.

32 Integrating in the Env. Management Plan with measures for minimising use of natural resources - water, land, energy, etc.

The EIA/EMP has been prepared accordingly.

33 Including cost of EMP (capital and recurring) in the project cost and for progressive and final mine closure plan.

The details have been discussed in Chapter – IX.

34 Details of R&R. Detailed project specific R&R Plan with data on the existing socioeconomic status of the population (including

The details have been discussed in Chapter – V.

Page 16: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Sr. No.

TOR Condition Compliance

tribals, SC/ST, BPL families) found in the study area and broad plan for resettlement of the displaced population, site for the resettlement colony, alternate livelihood concerns/employment for the displaced people, civic and housing amenities being offered, etc and costs along with the schedule of the implementation of the R&R Plan.

35 CSR Plan along with details of villages and specific budgetary provisions (capital and recurring) for specific activities over the life of the project.

Details has been given in Chapter - V

36 Public Hearing should cover the details of notices issued in the newspaper, proceedings/minutes of public hearing, the points raised by the general public and commitments made by the proponent should be presented in a tabular form. If the Public Hearing is in the regional language, an authenticated English Translation of the same should be provided.

The Public hearing was conducted on 05.02.2013. PH Minutes have been attached as Annexure No. -- III.

37 In built mechanism of self-monitoring of compliance of environmental regulations.

The inbuilt mechanism for compliance of all statutory requirements has been incorporated in Chapter –IX

38 Status of any litigations/ court cases filed/pending on the project.

There are no such cases pending against this project.

39 Submission of sample test analysis of Characteristics of coal - this includes grade of coal and other characteristics ?ash, S and heavy metals including levels of Hg, As, Pb, Cr etc.

Relevent details are given in Chapter – II.

Page 17: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Sr. No.

TOR Condition Compliance

41 Copy of clearances/approvals such as Forestry clearances, Mining Plan Approval, NOC from Flood and Irrigation Dept. (if req.), etc. wherever applicable.

No forest land is involved in the project.

42 Corporate Environment Responsibility: a) The Company must have a well laid down Environment Policy approved by the Board of Directors. b) The Environment Policy must prescribe for standard operating process/procedures to bring into focus any infringements/deviation/violation of the environmental or forest norms/conditions. c) The hierarchical system or Administrative Order of the company to deal with environmental issues and for ensuring compliance with the environmental clearance conditions must be furnished. d) To have proper checks and balances, the company should have a well laid down system of reporting of non-compliances/violations of environmental norms to the Board of Directors of the company and/or shareholders or stakeholders at large.

A well laid corporate Environmental Policy is approved by coal India Limited Board. Western Coalfields Limited being a subsidiary company of Coal India Limited subscribes to the said policy.

Page 18: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

LANDUSE DETAILS FOR OPENCAST PROJECT

S.N. LANDUSE Within ML Area (ha)

Outside ML Area (ha) TOTAL

1. Agricultural land 443.53 ---- 443.53

2. Forest land NIL ---- NIL

3. Wasteland(Govt. Land) 6.10 ---- 6.10

4. Grazing land ----- ---- ----

5. Surface water bodies ---- ---- ----

6. Settlements ---- ---- ----

7. Others (specify) ----- ---- ----

TOTAL

449.63 ---- 449.63

OB Management

Project Total waste generation

(Mm3)

Topsoil (Mm3)

Total OB generation

(Mm3)

Total OB in Ext. Dump

(Mm3)

Total OB Backfilled

(Mm3)

Original Project (ha) 10.33 Included in OB

10.33 9.58 & 0.75 in Embankment

----

Expansion Project (ha) (balance life)

50.62 Included in OB

50.62 50.62 ----

TOTAL (Mm3)

60.95 60.95 60.20 & 0.75 in Embankment

The capacity of external OB dumps proposed is about 60.20 Mm3. Remaining 0.75 Mm3 of OB will be used is construction of safety embankment.

The break up of OB quantities in external OB dumps is given in following table.

No. Dump Capacity in Mm3

0-30m 0.60m Total

i) Dump – 1 25.70 16.95 42.65

ii) Dump – 2 10.30 7.25 17.55

Total 60.20 .

Page 19: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

SCHEDULE OF OVERBURDEN DUMPING

The following Table No. 8.3 shows the yearwise OB dumping in external OB dump No.1 and No.2

Year Programmed

Excavation of

OB(Mm3)

External OB

Dump-1

(Mm3)

External OB Dump-2

(Mm3)Excluding Rehandling

1. 8.15 8.15 -

2. 7.40 7.40/15.55 -

3. 5.26 5.26/20.81 -

4. 5.25 5.25/26.06 -

5. 5.25 5.25/31.31 -

6. 4.70 4.70/36.01 -

7. 4.50 4.50/40.51 -

8. 4.40 2.14/42.65 2.26

9. 4.40 - 4.40/6.66

10. 1.10 - 1.10/7.76

11. 0.21 - 0.21/7.97

Total 50.62 42.65 7.97

Table 1: Stage-wise Landuse and Reclamation Area (ha)

S.N. Land use category Present (1st year)

5th year End of Mine Life

Post Mining

1 Backfilled Area (Reclaimed with plantation)

0 0 0 0

0 0 0 0

2 Excavated Area (Not reclaimed)/void

60 80 101.7 101.7

3 Ext. OB dump (Reclaimed with plantation)

35 100 175 175

0 25 110 175

4 Reclaimed Top soil dump 0 0 0 0

0 0 0 0

5 Green Built Area 0 0 0 0

6 Undisturbed area (brought under plantation)

319.63 234.63 137.93 137.93

0 10 125.93 137.93

7 Roads (avenue plantation) 25 25 25 25

0 0 17 17

8 Area around buildings and Infrastructures

10 10 10 10

0 0 3 3

Total 449.63 449.63 449.63 449.63

Page 20: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Table 2: Stage-wise Cumulative Plantation

Sl.No. year Green Belt External

Dump(OB + Top Soil)

Backfilled area

Others (undisturbed

area/etc.) Total

Area (ha)

No. of

trees

Area (ha)

No. of trees

Area (ha)

No. of

trees

Area (ha)

No. of trees

Area (ha)

No. of trees

1 1st year

0 0 0 0 0 0 0 0 0 0

2 3rd year

0 0 0 0 0 0 0 0 0 0

3 5th year

0 0 25 62.5 0 0 10 25 35 87.5

4 End of mine life

0 0 110 275 0 0 145.93 364.825 255.93 1

5 Post mining

0 0 175 437.50 0 0 157.93 394.825 332.93 832.33

Table 3 : Post-mining Landuse pattern of ML/Project Area (ha)

S.N. Land use during mining

Land use (ha)

Plantation Water Body

Public use Undisturbed Total

1 External OB Dump 175 0 0 0 175

2 Top soil dump 0 0 0 0 0

3 Excavation 0 101.7 0 0 101.7

4 Roads including embankment

17 8 25

5 Built up area 3 0 7 0 10

6 Green Belt 0 0 0 0 0

7 Undisturbed Area 137.93 0 0 0 137.93

Total 332.93 101.7 15 0 449.63

(A) FORESTRY CLEARANCE

TOTAL ML/PROJECT AREA (ha)

TOTAL FORESTLAND (ha)

Date of FC

Extent of forestland

Balance area for which FC is yet to be obtained

Status of appl. for diversion of forestland

If more than one, provide details of each FC

449.63 Nil Not Applicable

Not Applicable

Not Applicable

Not Applicable

Page 21: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

GENERAL CONDITIONS AND ADDITIONAL POINTS OF TOR

The following general points noted: (i) All documents should be properly indexed, page numbered. (ii) Period/date of data collection should be clearly indicated. (iii) Authenticated English translation of all material provided in Regional languages. (iv) After the preparation of the draft EIA-EMP Report as per the aforesaid TOR, the

proponent shall get the Public Hearing conducted as prescribed in the EIA Notification 2006 and take necessary action for obtaining environmental clearance under the provisions of the EIA Notification 2006.

(v) The letter/application for EC should quote the MOEF file No. and also attach a copy of the letter prescribing the TOR. (vi) The copy of the letter received from the Ministry on the TOR prescribed for the project should be attached as an annexure to the final EIA-EMP Report. (vii) The final EIA-EMP report submitted to the Ministry must incorporate the issues in TOR

and that raised in Public Hearing. The index of the final EIA-EMP report, must indicate the specific chapter and page no. of the EIA-EMP Report where the specific TOR prescribed by Ministry and the issue raised in the P.H. have been incorporated. Mining Questionnaire (posted on MOEF website) with all sections duly filled in shall also be submitted at the time of applying for EC.

(viii) General Instructions for the preparation and presentation before the EAC of TOR/EC projects of Coal Sector should be incorporated/followed.

(viii) The aforesaid TOR has a validity of two years only.

The following additional points are also to be noted:

(i) Grant of TOR does not necessarily mean grant of EC. (ii) Grant of TOR/EC to the present project does not necessarily mean grant of TOR/EC to the captive/linked project.

(iii) Grant of TOR/EC to the present project does not necessarily mean grant of approvals in other regulations such as the Forest (Conservation) Act 1980 or the Wildlife (Protection) Act, 1972. (iv) Grant of EC is also subject to Circulars issued under the EIA Notification 2006, which are available on the MOEF website: www.envfor.nic.in

______

Page 22: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

CHAPTER – I

INTRODUCTION 1.0 GENERAL

The proposed Junad Extension OC Project is an extension of existing Junad OC

mine in Junad block located on the western limb of Wardha Valley Coalfield in

Yeotmal district of Maharashtra. The P.R. for Junad OC mine was prepared by

CMPDI in October, 1989 and was sanctioned by the WCL Board in May, 1990 for

a capital of Rs. 19.148 Crores for a production capacity of 0.32 Mty. The actual

mining operations at the project could be started in November, 1998 due to

delay in land acquisition. This is expansion of existing Junad Opencast with mine

able reserve of 6.13 Mt and with maximum coal production target of 1.50 MTPA.

The Form – 1 was submitted to MOEF &CC vide letter no. WCL/HQ/ENV/11-

C/213-A dated 28.06.2014. The project was discussed in the 21st EAC meeting

held on 19.09.2014. As per the minutes of the meeting of EAC, the project was

recommended with generic TOR. Subsequently Generic ToR was issued vide

Letter No. J- 11015/225/2014 – IA. II(M) dated 21.11.2014. As indicated in the

aforesaid TOR, the PH has been completed on 05.02.2013. Based on the minutes

of PH and generic TOR, this EMP has now been prepared for obtaining

Environmental Clearance from Ministry of Environment, Forests & Climate

Change.

1.1NEED OF THE PROJECT

There is a substantial gap between demand and availability of coal for the

mines of WCL as a whole. It is in national interest to open new mines/projects &

to go for expansion of existing projects urgently so as to meet the requirement of

coal for power and various other sectors.

The justification of this mine has been studied in the light of estimated demand

for non-coking coal from power sector in Maharashtra and production forecast

from existing, completed and ongoing projects of WCL.

1.2 LOCATION & COMMUNICATION

The Junad Block, covering an area of about 4.05 sq.km is located on the

western limb of Wardha Valley Coalfield and lies in the East of Ukni/Pimpalgaon

Block and south of New Majri – Chargaon block across Wardha river. The area is

bounded by Longitude 79o 3' 9" and 79o 5' 00" E and Latitude 20 deg 1' 5" and

20o 4' 10" N. It is situated in Wani Tahsil of Yeotmal District, Maharashtra and is

covered by Survey of India Toposheet No. 55 P/4.

Junad Block is an interior of under developed region and communication, either

by rail or road, does not exist. However, the block is presently connected by a 3

km fare-weather road with Aheri village which, in turn, is connected with Wani

town towards North-West by a 19 km metalled road. The block may also be

approached by a 3 km road from Ukni/Pimpalgaon project which is being

Page 23: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

connected with Wani town via Bhalar village.

1.3 TOPOGRAPHY & DRAINAGE :-

The area of Junad Extension OC Mine exhibits gently undulating topography.The

general slope of the ground is from west to east. The HFL of Wardha river

recorded in New Majri in 1979 was 190.74m and a major portion of the proposed

area is below HFL. The external OB dump of existing Junad OC mine is 15-45 m

high, located in the dip-side of mine.

Junad Block exhibits moderately undulating topography. The elevation varies

from 180.83 m to 195.18 m. The Wardha river flowing from north to sourth is the

main drainage channel of the area. Considerable area of the block including

the potential opencast area for expansion is below HFL 190.74 m of Wardha river

as per national grid.

1.4 CLIMATE :-

Junad Block has extreme climate with maximum temperature of 48oC during

summer months and about 10oC during winter months. The average annual

rainfall is about 1250 mm. The bulk of rainfall takes place during wet months viz.

July, August and September. The maximum rainfall in a day of 24 hrs. was 249.4

mm recorded in Chandrapur on 14.9.1959. The direction of wind is mainly South-

Westerly, Westerly and North-Westerly.

1.5 PRESENT LAND USE PATTERN :-

The entire land to be acquired for extension of the Junad OC project is covered

by black cotton soil and is very fertile and is generally used for growing mainly

the cash crops like cotton, sugarcane, chillies etc apart from standard

agricultural products like rice, wheat & jawar. No village is falling in the proposed

leasehold boundary of the project. All the land losers will be given

compensation as per Company’s norms.

1.6 SITE DESCRIPTION: -

The study area has been divided into two heads Core Zone

Buffer Zone

a) Core zone: The core zone consists of the mining leasehold area where

mining and allied activities take place. The core zone comprises of 449.63 ha of

land. The land usage is given below.

Sl.

No

Land Particulars Total Land

1. Agricultural land 443.53 ha

2. Waste Land (Govt. Land) 6.10 ha

3. Forest Land -

Total 449.63 ha

Page 24: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

b) FEATURES IN BUFFER ZONE

Sl. No. FEATURES DETAILS DISTANCE FROM

MINE

1 Industries Nil Nil

2 Railway Lines Wani Railway Siding About 9.0 km

3 State Highway State Highway No.- 84 About 5.0 km

4 Other Coal Mines Ukni OC, Pimpalgaon

OC , Kolar Pimpri OC

3.0 – 5.0 km

5 Water Bodies Wardha River 125 m from mine

boundary

6 Human Settlement 40 villages & WCL township within buffer zone

1.7 SOURCES OF DATA

This report has been formulated using various data from the following

sources:

Sl.

No.

Type of Data Sources

1 Mining and economic

parameters and other

miscellaneous data

CMPDIL and Wani North Area,

WCL.

2 Environmental data including

meteorological data, air

quality, dust fall rate, water

quality and noise level data.

Environmental-data generation

for proposed Junad Extn.

(Deep) OC of Wani North Area

of WCL, Maharashtra carried

out by CMPDI.

3 Socio-economic study & Land

use/cover mapping buffer

zone.

Census data & base line Socio -

Economic survey.

4 Flora and fauna Survey Report prepared by the

competent authority in this field.

5 Surface hydrology and

hydrogeology

CMPDIL, RI- IV, Nagpur.

6 Meteorological data Environmental-data generation

for Junad. Extn (Deep) OC of

Wani North Area Maharashtra

carried out by CMPDI.

7 Land use/cover mapping core

zone.

As per State Govt. Record, data

supplied by the concerned

WCL area office.

Page 25: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

CHAPTER- II PROJECT PROFILE

2.0 REGIONAL GEOLOGY

Regional geological sequence of coalfield is as follows

TABLE No1

Age Formation Lithology

Recent to Sub-recent Detrital mantle Black cotton soil, sandy soil,

Kankar, etc.

Upper Cretaceous to

Eocene

Deccan Trap Basalt

------------UNCONFORMITY ------------

Cretaceous Lametas Cherty Limestone, silicified

sandstone

------------UNCONFORMITY ------------

Upper Permian Kamthi Red, brown, medium to coarse

grained sandstone, variegated

clay and shale bands.

------------UNCONFORMITY ------------

Age Formation Lithology

Lower Permian Barakar Predominantly grey to white,

medium to coarse grained

sandstones with minor shales,

carbonaceous shales and one

thick (15-25 m) coal seam.

Lower Permian – Upper

Carboniferous

Talchir Greenish to grey coloured

sandstone, siltstones and

shales.

------------UNCONFORMITY ------------

Precambrian Sullavai White to light brown quartzitic

sandstones, conglomerates.

Pakhal Grey, bluish or pinkish

limestones and cherts

------------UNCONFORMITY ------------

Archaean Metamorphics Gneisses and Schists

BROAD STRUCTURE OF THE BASIN

The major structural feature of the Coalfield is a well defined anticlinal

configuration having central non-coal bearing area with (a) eastern coal

bearing limb (from Belgaon block in the north to Sasti Dhuptala in south), (b)

western coal bearing limb (Yekona to Mugoli in the South and (c) three

separate narrow coal bearing "rifts" namely (i) Rajur-Chinchala (ii) Ghonsa-

Kumbharkhani and (iii) Markir-Mangli in the western part of the Coalfield.

Page 26: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

COAL BEARING FORMATION

The coal bearing Barakar formation overlies Talchir sediments conformably and

is overlapped by Kamthi formation unconformably. The thickness of Barakars

varies from 12.78 to 133.55 m.

STATUS OF EXPLORATION

MECL drilled 55 boreholes in addition to 4 boreholes of D.G.M.(MS). 2 more

boreholes drilled by CMPDI for coal depth determination. The details of

boreholes are given in Table-5.3.

TABLE No.2

Drilling Agency No. of Boreholes Meterage Name of Geological Report

MECL 55 (MWJ-Series) 8546.00

Geological Report on

Exploration for Coal, Junad

Block, MECL, June-1990

DGM (MS) 4 (JUD-Series) 716.53 -

CMPDI 2 (CMJU-Series) 79.00

Geological Note on

Production Support Drilling in

a part of Junad OC, CMPDI,

Sept.2001

Total 61 9341.53

DENSITY OF BOREHOLES

In all, 61 boreholes fall in 4.05 sq.km. area of Junad Block. Density of boreholes is

therefore 15 boreholes per sq.km. However, borehole density for quarry area is

12 boreholes per sq.km.

SURVEYING

PREVIOUS SURVEY WORK

The co-ordinates and reduced levels of boreholes were determined with

reference to Base stations A & B located at 2 km in the west outside the block

boundary. The details of these base stations are furnished below.

TABLE No.3

Station Total Latitude

(m)

Total

Departure (m)

R.L. in (m) Remarks

A 10,000.00 10,000.00 219.110 Common Pillar

B 10,010.547 9,805.255 219.420 Common Pillar

WCB of A – B = 273 Deg. 06 Minutes 00 Second

Distance A-B = 195.030 m

Page 27: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Survey Work

The reduced levels of the base stations were fixed with reference to reduced

level of Niljai block which in turn were established with reference to reduced

levels of Ghughus Colliery. The bench mark at the Robertson Incline of Ghughus

Colliery with assumed R.L. of 215.93 m was reported as the origin by Colliery

authorities. As such, all the contour values and RLs of boreholes are determined

with reference to these assumed figures. It may be mentioned that the

topography of the area adjacent to Wardha River is constantly changing due to

action of the river water especially during the floods.

Transposition of Grid System from Local Grid to National Grid

In order to determine the co-ordinates of the boreholes in National Grid Co-

ordinates of four boreholes were determined in both the systems as detailed

below:

TABLE No.4

B.H. No. National Grid values Local Grid values

Northing (m) Earthing (m) R.L. (m) Northing

(m)

Earthing

(m)

R.L. (m)

MWJ-37 1089492.5248 3006636.4166 185.497 12696.18 10409.14 206.49

MWJ-38 1089199.0492 3006921.2580 183.052 12804.48 10240.41 205.05

MWJ-39 1088995.8795 3007239.7493 181.737 13120.24 10032.64 203.73

MWJ-20 1089366.1377 3006810.6422 184.492 13245.95 10692.16 212.05

The GTS bench mark is (-) 22.00 m below the R.L. of Temporary bench mark.

However, the various geological plan show both levels: local as well as G.T.S.

bench mark.

RELIABILITY OF DATA

Junad Opencast is presently a working mine. There is no major change

observed during mining as per structure interpreted. The density of borehole is 12

boreholes per sq.km which is reasonable considering the developed mine so far.

Page 28: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

2.1 GEOLOGY OF THE MINING BLOCK

BRIEF GEOLOGICAL SETTING

The geological formation encountered in the present quarriable area are as

follows :-

Formation Thickness (m) Lithology

Minimum Maximum

Soil

3.00 24.00

Black clayey soil and sandy soil (MWJ-24) (MWJ-27)

Kamthis

6.00 101.00 Yellow, brown, red, yellowish white

ferruginous sandstone, occasionally

grey sandy shale/shale. (MWJ-37) (MWJ-12)

Barakar 12.78 133.55 Grey white medium to grey

sandstone with shale, coal seams with

shaly coal, etc.

(MWJ-20) (MWJ-27)

SEQUENCE OF COAL SEAMS & PARTING

The coal seam in Junad Block is thick Composite Seam, ranges in thickness from

14.82 m (MWJ-50) to 18.83 m (MWJ-24). MECL, however, divided seam in two

parts as Top Section and Bottom Section by a parting ranging from 0.09 m

(MWJ-24) to 2.21 m (MWJ-26).

GEOLOGICAL STRUCTURE

Geological structure of Junad block is based mainly on sub-surface data of

boreholes. Strike is mainly NW-SE, coal seam dips due south west and gradient

varying from 1 in 2.5 to 1 in 3.5 in quarriable area.

Only 3 faults viz. Fault F3-F3, F4-F4 and F5-F5 are intersected in quarry. The fault

F3-F4 is minor in nature and throw is 5 m. The throw of F4-F4 & F5-F5 is 20 m

towards NE and 40 m SW respectively.

Page 29: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

DESCRIPTION OF FAULTS

Designated

No. of Fault

Strike Throw Linear Extension Nature and evidence

F3- F3 N40oW

-S40oE

5 m

toward

s SW

0.95 km, dies out

on either sides

1. Strike fault

2. Intersected in boreholes

MWJ-12, and MWJ-27

resulting in reduction of

seam thickness.

F4- F4 N63oW

-S63oE

to

N25oW

-S25oE

20 m

toward

s NE

0.875 km, abuts

against F5 on

either sides.

1. Oblique fault

2. Intersected in borehole

MWJ-21 resulting in

reduction of seam

thickness.

F5- F5 N45oW

-S45oE

40 m

toward

s SW

1.115 km, join F4

in the NW and

dies out. It may

continue in SE

direction

beyond the

block boundary

1. Strike fault

2. Intersected in boreholes

MWJ-52 & 55 resulting in

omission of coal seam.

INTRUSIVES OF SURFACE BURNING

There is no evidence of any intrusives nor any effect of burning in any borehole

analysis.

DESCRIPTION OF COAL SEAM

SEAM THICKNESS RANGE & VARIATION PATTERNS

The coal seam in Junad Block is thick Composite Seam ranges in thickness from

14.82 (MWJ-50) to 18.83 (MWJ-24). MECL, however, divided seam in two parts as

Top Section and Bottom Section by a parting ranging from 0.09 (MWJ-24) to 2.21

in (MWJ-26). However, for opencast proposed quarry, it is thick one Composite

Seam. The parting is generally composed of shale, carbonaceous shale and

occasionally intercalation of sandstone and shale.

The summarized details of coal seam under proposed quarry are as follows:-

1. The range of quarriable

thickness

14.82 m (MWJ-50)

to

18.83 m (MWJ-24)

(including parting)

2. The depth range 20.57 (CMWJU-1) to 205.82 (MWJ-27)

3. The parting range 0.09 m (MWJ-24) to 2.21 m (MWJ-26)

Page 30: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

PARTING

Parting between Top Section and Bottom Section varies from 0.09 m to 2.21 m

and consist of shale, carb. shale and occasionally intercalation of shale and

sandstone.

ROOF & FLOOR CHARACTERISTICS

The immediate roof of seam is mainly carbonaceous Shale, occasionally

shale/sandy shale. The floor is mainly sandstone or sandy shale.

DIRT BANDS BEHAVIOUR

The distribution of dirt bands is as follows :-

Section Carb. Shale Shale Band

No. Total

Thickness (m)

% No. Total

Thickness (m)

%

Top

Section

1-5 0.10-1.05 1-16 Nil to 6 N il – 0.90 Nil – 9

Bottom

Section

Nil – 3 Nil – 0.25 Nil – 4 Nil to 4 N il – 0.82 Nil – 12

For details of distribution of dirt bands see Annexure-IVA & IVB (Top & Bottom

Section)

QUALITY PARAMETERS

The thickness of Composite Seam including the thickness of Top Section, Bottom

Section and intervening parting as intersected in 6 boreholes, varies from 14.82

m (MWJ-50) to 18.83 (MWJ-24). The following table furnishes the summarized

quality details on equilibrated basis (determined and calculated) of boreholes

falling within and in the vicinity of quarry area.

Quality Parameters – Composite Seam

Grade

M% Ash% VM% G.C.V.

(K.Cal./kg)

U.H.V.

(K.Cal./kg.)

MWJ-10 16.40 7.6 22.5 28.8 5390 4745 D on 60% RH & 40oC

MWJ-13* 17.99 7.7 24.0 - - 4525 D

MWJ-22 17.28 7.2 25.3 - - 4361 D

MWJ-24 18.83 8.5 25.5 - - 4362 D

MWJ-30* 15.71 6.7 29.7 25.6 4800 3877 E on 60% RH & 40oC

MWJ-35* 15.89 5.3 29.5 - - 3920 E

MWJ-38 15.87 7.0 26.4 27.0 5060 4291 D on 60% RH & 40oC

On Equilibriated BasisB.H. No. Effective

Thickness

Page 31: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

QUALITY OF ROM COAL

The present practice of mining in Junad Opencast is to mine whole coal seam

from roof to floor. The parting between the Top Section and Bottom Section is

practically not possible to remove because of its steep gradient. Therefore,

quality (including parting) has been assessed for the boreholes falling within the

proposed quarry are given in the following table No.5.11. The dilution of 5 cm at

each contact point is also considered at roof and floor of seam.

RANGE OF COAL QUALITY OF UNDILUTED & DILUTED COAL OF ROM

B.H. No.

Thick. (m)

ONLY COAL (WITHOUT DILUTION) WITH DILUTION 5 cm AT EACH CONTACT

Remarks

M% Ash% UHV K.Cal/kg

Gr. GCV K.Cal/kg

M% Ash% UHV K.Cal/kg

Gr. GCV K.Cal/kg

MWJ-10

17.59 7.16 26.6 4241 D 5010 7.12 27.0 4191 E 4978

MWJ-22

18.76 8.31 36.65 2696 F 3897 8.26 37.02 2651 F 3870

MWJ-24

18.83 8.45 25.46 4220 D 4930 8.42 25.7 4191 E 4912

MWJ-26

16.84 5.89 32.76 3566 E 4615 5.88 33.04 3529 E 4591 Including parting of 2.21m between Top & Bottom Section

MWJ-38

16.8 6.75 28.86 3986 E 4857 6.72 29.21 3942 E 4829

MWJ-50

14.82 6.36 24.56 4633 D 5319 6.33 24.94 4585 D 5287

From the above table, the weighted quality of coal without dilution and with

dilution is as follows:-

Particulars Without

dilution

With dilution of

5 cm at each contact point

M% 7.22 7.18

Ash% 29.29 29.62

U.H.V. (K.Cal/kg) 3862 3822

Grade E E

G.C.V. (K.Cal/kg) 4748 4724

Special Tests

Results of special tests carried out for MWJ boreholes are furnished in the

following table.

Page 32: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Ultimate Analysis

The ultimate analysis of borehole is available and the details are shown in Table

below.

B.H. No. Thick.

(m)

Ultimate Analysis

Carbon

%

Hydrogen

%

Nitrogen

%

Sulphur

%

Oxygen

%

MWJ-10 17.59 78.88 4.30 1.66 0.24 15.22

MWJ-11 18.92 77.57 4.24 1.67 0.21 16.31

MWJ-11 13.10 80.68 4.25 1.56 0.47 13.04

MWJ-30 16.91 81.32 4.59 1.98 0.31 11.80

MWJ-40 17.96 81.37 4.98 1.65 0.21 11.83

From the available analytical data on 60%RH & 40oC.

Ash Fusion Temperature Range

The data pertaining to Ash Fusion Range is also available for 5 boreholes. The

summarized details are given below:-

B.H. No. Thick.

(m)

Ash Fusion Temperature Range

Initial

Deformation

Temp. (oC)

Hemispherical

Deformation Temp.

(oC)

Flow

Temp.

(oC)

MWJ-10 17.59 1390 >1400 >1400

MWJ-11 18.72 1290 >1400 >1400

MWJ-17 13.10 1230 1370 >1400

MWJ-30 16.91 1360 >1400 >1400

MWJ-40 17.96 1350 >1400 >1400

Ash Analysis

The Ash analysis is also available for 5 boreholes. The details are shown in the

following table.

B.H. No.

Thick. (m)

SiO2 %

Al2O3 %

Fe2O3 %

TiO2 %

CaO %

MgO %

MnO %

P2O5%

SO2%

Alkalies by

difference

Total %

MWJ-10

17.59 56.330 26.790 4.660 1.672 4.541 0.552 0.136 0.485 4.530 0.304 100.00

MWJ-11

18.92 52.650 25.750 5.000 1.420 7.290 0.450 0.081 0.753 6.358 0.248 100.00

MWJ-17

13.10 52.140 27.460 11.380 1.380 3.300 0.110 0.088 0.902 3.000 0.240 100.00

MWJ-30

16.91 55.175 25.980 4.395 1.685 7.061 0.852 0.130 0.590 3.700 0.432 100.00

MWJ-40

17.96 59.340 26.235 6.710 1.360 3.652 0.667 0.190 0.590 0.780 0.476 100.00

Page 33: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

The data pertaining to total sulphur of Composite Seam for 14 boreholes and

sulphur distribution for 4 boreholes are given in the following table.

B.H. No. Depth of Coal Seam

(m)

Total

Sulphur %

Distribution

From To Pyritic % Sulphate % Organic %

MWJ-8 141.73 157.92 2.05 - - -

MWJ-9 134.58 151.29 1.58 - - -

MWJ-10* 58.08 75.67 1.37 1.16 0.05 0.16

MWJ-11 179.48 198.20 1.63 1.41 0.08 0.14

MWJ-13 89.36 110.05 1.28 - - -

MWJ-15 72.50 89.72 1.61 - - -

MWJ-16 86.44 102.51 2.25 - - -

MWJ-17 89.40 102.50 2.21 1.59 0.29 0.33

MWJ-24 42.57 61.40 0.75 - - -

MWJ-26 153.73 170.57 0.56 - - -

MWJ-29 174.96 193.21 1.20 - - -

MWJ-30 106.97 123.88 0.59 0.35 0.05 0.19

MWJ-35 30.00 46.72 0.91 - - -

MWJ-38* 24.88 41.68 1.09 - - -

H.G.I.

The H.G.I. for two boreholes MWJ-26 & 29 is available and given in the following

table.

B.H. No. Depth (m) Thick. (m) Seam/Section H.G.I.

From To

MWJ-26 153.73 160.88 7.15 Top Section 60

163.09 170.57 7.48 Bottom

Section

49

153.73 170.57 14.63 Top & Bottom

Section

52

MWJ-29 174.96 184.51 9.19 Top Section 54

184.61 193.21 8.60 Bottom

Section

50

174.96 193.21 17.79 Top & Bottom

Section

52

RESERVES

Based on the data of 61 boreholes drilled by different agencies in an area of

4.05 sq.km. of Junad Block, the opencast (up to 1:7 Coal : OB ratio line) and

underground reserves beyond 1:7 Coal : OB ratio line have been calculated.

Page 34: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

AREAL EXTENT OF BLOCK

The limits of reserves estimation are as follows :-

East - Half sub-crop line in North. Eastern part near MWJ-5 & 53) and

also the eastern bank of Wardha river.

West- Seam position against the major fault F1-F1.

North- Southern bank of Wardha river.

South- Eastern bank of wardha river and also seam position against

the fault F1-F1.

The overall reserves of Junad block are grouped as under:-

1) Proved quarriable net in-situ reserves of composite seam estimated

from western bank of Wardha river to 1:7 Coal/OB ratio line.

2) Indicated quarriable reserves from half way of the sub-crop of coal

seam to western bank of river Wardha. This is for coal that occurs below

the river bed.

3) Proved underground net in-situ reserves separately for top and bottom

sections beyond 1:7 coal to OB ratio line.

4) Proved quarriable reserves in the area between eastern bank of

Wardha river and 1:7 Coal: OB ratio have been estimated while the

reserves of coal located below the river bed i.e. between half sub-crop

and western bank of river are grouped under indicated category.

5) For estimating the net geological reserves under quarriable category

and to arrive at the effective thickness of coal, obvious dirt bands of

thickness more than 0.15 are excluded. The bands having thickness less

than 0.15 m however are included. The carbonaceous bands less than

1.00 m are included and more than 1.00 m are excluded to get the

effective thickness.

Total 9 Sectors, Viz. Q1 to Q5 under opencast category and U1 to U4 a

underground category have been identified based on the faults, OCP – UG

limit i.e. 1:7 coal to Overburden ratio line (See Plate – V).

Junad Block is divided into two parts because of upthrown portion by fault F6-F6.

The downthrown portion can be named as river side part with sectors as Q1, Q4

quarriable and underground reserves in U1 & U2 sectors these reserves have not

been considered for the present Junad Extension OC proposed project as

separate mine has to be planned in future.

The upthrown block of fault F6-F6 is the main Junad block consists of sectors Q2,

Q3, Q5 (quarriable) and U3 & U4 (underground) of which only Q3 and part U3

are considered for the present Junad Extension OC project report.

Page 35: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Sector boundaries –

Sector Q3 :

East - Incrop and fault F4-F4 and Wardha river barrier

West - 1:7 Coal : Overburden ratio line.

North - Wardha river barrier.

South - 1:7 Coal:Overburden ratio line and Wardha river barrier.

Sector U3 :

East - Sector Q3

West - Fault F1-F1

North - Wardha river barrier.

South - Sector Q3 & U4 and Fault F1-F1

Sectorwise Net Geological reserves in Junad Block

(Figures in Mt)

OPENCAST (Upto 1:7

Coal/OB Ratio line

UNDERGROUND

Beyond 1:7 to Fault F1-F1

Sector Proved Indicate

d

Total Sector Proved Indicated Total

Q1 3.839 - 3.839 U1 7.168 - 7.168

Q2 0.577 - 0.577 U2 - 1.683 1.683

Q3 19.689 - 19.689 U3 37.254 - 37.254

Q4 - 4.418 4.418 U4 - 1.489 1.489

Q5 - 6.991 6.991

Total 24.105 11.409 35.514 Total 44.422 3.172 47.594

GRAND TOTAL 83.108

As stated above, only Sectors Q3 & U3 considered for present Junad Extension

OC, the Net Geological reserves of these sectors are as follows of which only

44.018 Mt are below 250 m depth.

Particulars Sector Total

Q3 U3

Incrop to 1:7 Coal:OB Ratio line 19.689 - 19.689

Beyond 1:7 Coal:OB Ratio line

to

250 m Depth

- 24.329 24.329

Sub-Total 19.689 24.329 44.018

Beyond 250 m depth sub-total - 12.925 12.925

Total 19.689 37.254 56.943

Page 36: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

BLOCK BOUNDARIES

The proposed Junad Extension OC mine has been envisaged in Junad block

and is a dip side extension of the existing Junad OC Project. Geological

strucuture of Junad block is based mainly on sub-surface data of boreholes.

Strike is mainly NW-SE, coal seams dips due south-west with gradient varying

from 1 in 2.5 to 1 in 3.5 in quarriable area. It is proposed to deepen existing

Junad OC mine from the floor limit of the quarry as per R.C.E. report (88 m depth

100 m FRL) to 170 m depth about 1:10 coal:OB ratio line (20 m FRL) and will be

named as Junad Extension OC. The geological block boundaries of Junad

block is as follows :

a) Junad Block

East : Half sub-crop line in north-eastern part near boreholes MWJ-51 & 53 &

eastern bank of Wardha river.

West : Seam position against the major fault F1F1

North : Southern bank of Wardha River.

South : Eastern bank of Wardha River and also seam position against the fault

F1F1

Quarry Boundaries

Quarry Boundaries of existing Junad OC Mine as per sanctioned R.C.E. report -

North : Safe distance of 125 m from Wardha river.

South : Safe distance of 125 m from Wardha river

East : Floor of decoaled existing Junad OC mine as on 1.4.2004

(as given by Area Plan)

West : Projected floor as on 1.4.2006 (100m floor contour line, 88 m

depth)

At present, existing Junad OC mine is being worked in Junad geological block.

The Dip side limit of existing Junad OC mine is fixed at 88 m depth which

corresponds to about 100m FRL. Different alternatives have been done in Sector

Q3 and Sector U3 to arrive at an optimum stripping ratio with sufficient reserves

for mining. Alternative 1a, 1b, 1c are studied in Sectors Q3/U3 by deepening of

existing Junad OC mine.

Page 37: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

The details of the alternatives done are given in the table below-

ALT. No.

Quarry

Quarry Boundaries Depth (m) COAL (Mt)

OB (Mm3)

SR (m3/t)

Eastern (rise)side

West (Dip) side

South boundary

North boundary

Min Max

(1a)

Quarry

in

Sector

Q3

Floor of

composit

e seam of

existing

quarry as

on

31.3.2006

(RCE limit)

150m

depth

(40 m

FRL)

Keeping

quarry

surface

at 125m

distance

from

Wardha

river

Keeping

quarry

surface

at 125m

distance

from

Wardha

river

88

150

4.18 28.35 6.78

(1b)

Quarry

in

Sector

Q3

Floor of

composit

e seam of

existing

quarry as

on

31.3.2006

(RCE limit)

170m

depth

(20 m

FRL)

Keeping

quarry

surface

at 125 m

distance

from

Wardha

river

Keeping

quarry

surface

at 125 m

distance

from

Wardha

river

88

170

6.13 50.62 8.26

(1c)

Quarry

in

Sector

Q3

Floor of

composit

e seam of

existing

quarry as

on

31.3.2006

(RCE limit)

200m

depth

(-10m

FRL)

Keeping

quarry

surface

at 100 m

distance

from

Wardha

river

Keeping

quarry

surface

at 100 m

distance

from

Wardha

river

88 200 7.75 70.80 9.13

Alternative IB is selected on the basis of conservation point of view and

increased reserves resulting in increased life of the project and also from

optimum stripping ratio point of view. The selection of this alternative is also due

to lack of dumping space in the dip side of the block. The mineable reserves

and stripping ratio of Alternative I B considered in this PR is summarized below:-

Particulars OB (Mm3) Coal (Mt) S.R. (m3/t)

Alternative I B. depth 170

m, dip side FRL limit 20 m 50.62 6.13* 8.26

* Reserves/Stripping Ratio is considered beyond the Quarry Floor limit of

sanctioned R.C.E. of existing Junad OC mine and excludes rehandling of existing

dipside OB dump.

Page 38: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Eastern Boundary (Rise side boundary)

The eastern boundary of the main extension quarry will be the decoaled existing

Junad OC mine as on 1.4.2006 and half subcrop of the composite coal seam in

virgin area in north direction along strike and along fault F4-F4 in south.

Western Boundary (Dip side boundary)

The composite coal seam is dipping in west direction and west side quarry floor

boundary is proposed at 170 m depth at the floor of composite seam which

corresponds to average 20 m FRL as per National Grid.

Northern Boundary

Wardha river is flowing along the northern boundary of Junad block. The floor of

the quarry is proposed such that the quarry surface in north direction is kept at a

safe distance ranging from 125 m from Wardha river. Between surface of the

quarry in north direction and Wardha river, there is a proposed embankment

having width 30 m at the top and height ranging from 6-10 m. Safe distance of

25 m and 15 m is kept from the toe of embankment to the edge of Wardha river

and quarry surface respectively.

Southern Boundary

Wardha river is also flowing along the south-eastern part of Junad block. Thus,

the floor of the quarry is proposed such that the quarry surface is kept at a safe

distance of 125 m from the Wardha river. Between surface of the quarry in south

direction and Wardha river, there is a proposed embankment having width 30 m

at the top and height ranging from 6-10 m. Safe distance of 25 m and 15 m is

kept from the toe of embankment to the edge of Wardha river and quarry

surface respectively. A 400 kV high tension line is passing across the Junad block

at a distance of about 500 m from the southern quarry surface limit. Thus, the

boundary fixation of the extended quarry in southern side is limited by Wardha

river, 400 kV line, safety embankment and also considering optimum quarry

shape avoiding tail shape of the quarry in dip side of southern limit.

Page 39: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

MINE PARAMETERS

In Junad Extension OC mine, it is proposed to extend existing OC mine in dip

side upto 170m depth.

The mine parameters of the proposed extended quarry are detailed below:-

Sl.

No.

Particulars

(As on 1.4.2006)

Extension

Quarry

6.2.1

a)

b)

Face length (km)

On the floor of composite seam

On Surface

1.15 – 1.28

1.50 – 1.70

6.2.2

a)

b)

Depth (m) upto floor of

composite coal seam

Initial

Final

30 - 88

170

6.2.3

a)

b)

Width Below the decoaled void

of existing Junad Extn.OC

On the floor of composite seam

On Surface

250-325

400-525

6.2.4

a)

b)

Area of the quarry

On floor (ha)

On Surface (ha)

35.20

70.50

MINEABLE RESERVES

GROSS RESERVES IN PROPOSED JUNAD OC MINE

The upthrown block of fault F6 – F6 is the main Junad block which consists of

Sectors Q2, Q3, Q5 (opencast) and Sectors U3 & U4 (underground).(Please refer

Geological Plan of Junad OCP of WCL) This division of sectors in Junad block is

based as per Geological Report of Junad block, June, 1990. As per this G.R.,

reserves upto 1:7 coal:OB ratio line are defined as opencast sectors, and

reserves beyond 1:7 coal:OB ratio line are considered as underground reserves.

However, due to application of hiring HEMMs, greater depths with higher

stripping ratio can be worked by opencast method of mining. Therefore, the

revised geological break-up is given below which considers opencast reserves

upto 250m depth. The proposed Junad extension OC mine has been planned

below the RCE limit of existing Junad OC mine upto a depth of 170m at the floor

of composite coal seam. Therefore, in this report the sectors earlier identified for

underground mining in the geological notes is proposed to be worked by

opencast method of mining upto a depth of 170m.

Page 40: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Sector Q2 is a very narrow patch, bounded between downthrow fault F4-F4 & F5-

F5. The net geological reserve of Sector Q2 is only 0.557 MT and considering its

width and strike, it is not viable for opencast coal mining.

Sector Q5 lies below the Wardha river in south-east direction. The net Indicated

geological reserve of Sector Q5 is 6.99 MT but the opencast mining can be done

only after the diversion of Wardha river.

Sector U4 is a small patch below Wardha river, bounded beyond 1:7 coal:OB

ratio line and boundary fault F1-F1. The net indicated a geological reserve of

Sector U4 is 1.489 MT.

Thereby Sectors, Q2, Q5 and U4 of main Junad block are not considered in this

PR for opencast coal mining.

The sectors considered in this PR are Sector Q3 & U3. The boundary of Sector Q3

& U3 are defined as under :-

Sector Q3 :

East - Incrop and fault F4-F4 and Wardha river barrier

West - 1:7 Coal : Overburden ratio line.

North - Wardha river barrier.

South - 1:7 Coal : Overburden ratio line and Wardha river barrier.

Sector U3 :

East - Sector Q3

West - Fault F1-F1

North - Wardha river barrier.

South - Sector Q3 & U4 and Fault F1-F1

In the proposed quarriable area, the coal seam has split in two sections namely

top section and bottom section with an intervening parting of average 0.8 m

thickness varying from 0.09 m to 2.21 m. Due to steep gradient, it is not feasible

to work this parting separately. In the existing Junad OC mine, the coal is being

extracted along with parting. It is therefore proposed in this report to extract the

top and bottom section of coal seam along with intervening parting as a

composite coal seam. The gross reserve in the proposed extended quarry has

been estimated considering coal thickness from roof to floor.

Page 41: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

COAL BLOCKED UNDER VARIOUS HEADS

As stated above, only Sectors Q3 & U3 are considered for quarry planning in

proposed Junad Extension OC. The Net Geological reserve of these sectors up

to 250 m depth is 44.018 MT and upto major boundary fault F1-F1 is 56.943 MT.

The break-up of reserves in Sectors Q3 & U3 up to 250 m depth and beyond 250

m depth to boundary fault F1-F1 is given in following table.

Particulars Sector Total

Q3 U3

Incrop to 1:7 Coal:OB Ratio

line

19.689 - 19.689

Beyond 1:7 Coal:OB Ratio line

to 250 m Depth

- 24.329 24.329

Beyond 250 m depth - 12.925 12.925

Total

19.689

37.254

56.943

As per sanctiond RCE of Junad OC Mine in 1999, net geological reserves are

3.63Mt (3.26 Mt net mineable reserves). For Junad Extension OC, starting from

1.4.2008, 6.81 Mt net geological reserves (6.13 Mt net mineable reserves) are

proposed to be exploited. Therefore in total, 3.63 Mt + 6.81 Mt = 10.44 Mt

reserves from Sectors Q3 and U3 falls in quarriable area. Balance reserves in

Sectors Q3 and U3 upto major boundary fault F1-F1, is 46.503 Mt. and it falls in

the dip side and southern side of the proposed quarry.

MINING LOSS

To arrive at the mineable reserves from the gross reserves available in the

proposed extension quarry, following mining losses have been considered:-

i) 10% mining loss due to variation in seam thickness.

ii) Loss of 20 cm of coal at each contact point of coal seam thus

aggregating 40 cm (two contact points at roof and floor) which

corresponds to about 2.5% loss.

iii) 0.5% of coal loss for blasting for coal seam

iv) 0.5% loss due to spillage in coal transportation.

Considering the above mining losses, the net mineable reserves in Junad

Extension OC mine are as under:

Quarry

Gross

Geological

Reserves

(Mt)

Mining

Losses

(Mt)

Mineable

Reserves (Mt)

Quarry as per Alternative

IB, depth 170 m

7.086* 0.956 6.13

Page 42: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TARGET OUTPUT AND MINE LIFE

The proposed Junad Extension OC mine has been planned for a target

capacity of 0.60 Mt/annum. The parameters of opencast mine field and

technical conditions of its development make this target feasible with normal

indices namely strike length, width and depth of the excavated block, number

of coal seams, method of mining, location of equipment, deployment, etc. The

target production from extension quarry along with strike length and rate of

deepening are tabulated below:

Sl.

No.

Quarry Max.

target

Production

(Mt)

Depth

Range

(m)

Strike

Length

(Km)

Average

Rate of

deepening

(m/year)

1. Quarry as per

Alternative IB, depth

170 m

0.60 88-170 1.5 -1.70 8 – 9

From above it is clear that the maximum rate of deepening is about 8 – 9

m/year in proposed Junad Extension quarry.

In proposed Junad Extension OC mine, target production of 0.60 MT will be

achieved in Year-I i.e, in the year 2008-09. With a mineable reserve of 6.13 Mt

and target production of 0.60 Mty, the revenue life of the mine comes out to be

11 years. However for EC, the peak capacity assumed as 1.50 MTPA.

GEO-MINING CHARACTERISTICS

Seam Gradient

Geological structure of Junad block is based mainly on sub-surface data of

boreholes. Strike is mainly NW-SE, coal seam dips due south west and gradient

varying from 1 in 2.5 to 1 in 3.5 in quarriable area.

Geological Disturbances

Only 3 faults viz. Fault F3-F3, F4-F4 and F5-F5 are intersected in quarry. The fault

F3-F4 is minor in nature and throw is 5 m. The throw of F4-F4 & F5-F5 is 20 m

towards NE and 40 m SW respectively.

SELECTION OF MINING METHOD

The steep gradient of the seam (gradient 1 in 2.5 to 1 in 3.5) rules out the

application of dragline method of working and surface miner working in

proposed Junad Extension OC mine. Shovel-Dumper system has been

considered to be the most suitable method of opencast mining under the

prevailing geo-mining conditions. With Shovel-Dumper system, two stripping

methods are possible:

Page 43: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

1. Inclined slicing method &

2. Horizontal slicing method

In steep gradient, positioning of HEMM is difficult in inclined slicing method as

the benches in coal are made parallel to the seam in this method. Hence this

method is ruled out in proposed Junad Extension OC mine. In horizontal slicing,

benches in coal are made horizontal and therefore there is no problem in

positioning of HEMM. In horizontal slicing method, the sump can be made either

on the bottom most horizontal bench in coal or in the roof of coal seam. With

the sump at the roof of coal seam, the coal and overburden benches with

proper grading can be worked in almost water-free condition throughout the

year. However, with this arrangement, initial excavation is high because of the

running slope of quarry is further reduced to this type of sump arrangement. It is

therefore proposed in this report to make the sump at the horizontal bench in

coal in one side of the quarry and to make the coal benches slightly grading

towards the sump.

Thus, the shovel dumper system of mining with horizontal slicing method is

recommended for the proposed extension project with sump at the bottom-

most horizontal bench in coal seam.

SEAM THICKNESS RANGE & VARIATION PATTERNS

The coal seam in Junad Block is thick Composite Seam ranges in thickness from

14.82 (MWJ-50) to 18.83 (MWJ-24). MECL, however, divided seam in two parts as

Top Section and Bottom Section by a parting ranging from 0.09 (MWJ-24) to 2.21

in (MWJ-26), However, for opencast proposed quarry, it is thick one Composite

Seam. The parting is generally composed of shale, carbonaceous shale and

occasionally intercalation of sandstone and shale.

The summarized details of coal seam under proposed quarry are as follows:-

Sl.No. Particulars Minimum Maximum

1. The range of

quarriable

thickness

14.82 m (MWJ-50) 18.83 m (MWJ-24)

(including parting

2. The depth range 20.57 (MWJ-37) (MWJ-10)

3. The parting range 0.09 m (MWJ-24) 2.21 m (MWJ-26)

Because of very steep gradient of coal seam (1 in 2.5 to 1 in 3.5), it is difficult to

remove the parting between top and bottom section even in horizontal slicing

and with shovel dumper system with blasting method. In the existing Junad OC

mine, the coal is being extracted along with parting. In the Junad Extension OC

mine also, it is proposed to extract the entire composite coal seam along with

parting varying in thickness from 0.09m (MWJ-24) to 2.21m (MWJ-26). The quality

of coal has been assessed taking into account the mixing of parting with the

coal.

Page 44: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

System Parameters – Bench Height, Elements of Mining System

Volume Regime

The proposed Junad Extension OC mine is an extension of existing Junad OC

Mine beyond RCE floor unit.

The access trench of existing Junad OC mine, will serve the entry to Junad

Extension OC mine also. Thus the Quarry of proposed Junad Extension OC will

be approached by the existing access trench of Junad OC mine.

To calculate the coal, OB and stripping ratio at different depths in Extension

quarry, cuts have been made at 100m FRL (Cut-I), 70m FRL (Cut-II), 40m FRL

(Cut-III), and upto 170 m depth line (Balance cut). The cut-wise OB and coal in

proposed Junad Extension OC is given below in Table below.

CUTWISE COAL, OB & STRIPPING RATIO (Volume Regime Table)

FOR JUNAD EXTENSION QUARRY (FROM 1.4.2008 ONWARDS)

Cut FRL (m) Mineable

Reserves

(Mt)

Total OB

(Mm3)

Stripping

Ratio (m3/t) From To

Cut-I Upto 100m FRL 1.05 14.23 13.55

Cut-II 140 70 2.14 18.78 8.77

Cut-III 70 40 2.24 16.56 7.39

Balance

Cut

40 20 0.70 1.05 1.50

(Upto 170m depth line)

TOTAL 6.13 50.62 8.26

Thus the total mineable reserve in the Junad Extension OC mine is 6.13 Mt with

an average stripping ratio of 8.26 m3/t.

Width and Height of Benches

The maximum height of benches in overburden considered in this report is 10m

which will be drilled and blasted in one go. In unconsolidated strata/alluvium

soil, the bench height is kept as 5m. In coal also, the height of the bench is

considered as 5m. The bench width considered in this report is 20m and 30m for

non-working and working benches respectively for planning purpose.

In final batter of the quarry, the height of the benches in consolidated strata is

10m and a berm of 5m width will be maintained between two benches.

However, in unconsolidated strata/alluvium soil, the bench height considered in

final batter is 5m and the bench width (berm) is 10m. Three to four transport

horizons will be maintained in the batter at an interval of 30m.

Page 45: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Slope of Benches and Quarry

i) During Mining Operation

The slope of individual benches depends on the type of strata. In this report, the

slope of individual bench is proposed as 45o in soil, alluvium and clay whereas it

is 70o in hard strata as well as in coal.

The overall slope of the quarry benches during mining operation varies from 10o

to 20o (from horizontal plane) due to multiple seams.

Rise side batter remains same in the quarry during mining operation or at the

end of the quarry. The overall angle of the rise side batter of existing Junad OC

mine varies from 20o to 35o.

ii) At the end of the quarry

The slope of individual benches in the batter at the end of quarry remains same

as that during mining operations i.e, 45o in soil , alluvium and clay and 70o in

hard strata and coal. The slope of the batter at the end of the quarry in dip side

is flatter in upper horizon because of unconsolidated strata like soil, clay, etc. In

deeper horizon, the angle of batter measured from horizontal plane is steeper

compared to upper horizon. It is 15o to 30o in upper horizon (in unconsolidated

strata) and 35o to 45o in hard strata. The slope of rise side batter is same as

discussed above under point (i).

Drilling and Blasting

The degree of fragmentation in opencast mine has to be optimized so that total

cost of drilling, blasting, excavation, transport and crushing as total system is

minimized. In order to reduce the excessive vibrations at nearby surface

structure, river, road, village, etc. and also to achieve satisfactory blasting

results, an optimized control blasting system depending upon rock formations

using combination of delays and relays will have to be evolved. It is further

recommended that at the time of actual excavation, proper study on ground

vibration should be made with scientific methods.

In proposed Junad Extension OC mine, the powder factor for OB and coal has

been worked out to be 3.0m3/kg and 7.0/t respectively in partial hiring

option.However, it is proposed in this report to undertake scientific study to

assess the powder factor for OB and coal. Adequate capital provision has been

made in this report for above study.

Mine Transport

Shovel Dumper system has been proposed in this report and the coal as well as

OB will be transported by dumpers/trucks.

Page 46: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Haul roads with proper gradient have been proposed for Quarry and the coal

will be transported by dumpers/trucks through these haul roads and existing

access trench of Junad OC mine from quarry to coal stock yard near the

access trench. The gradient of haul roads is proposed as 1:16.

For the transportation of OB, transport horizons (benches) have been proposed

in the dip side & side benches/batter. The OB from benches will be transported

by dumpers/trucks through these transport horizons and ramps to suitable

intervals will be made to join other benches with the transport benches. The OB

below the bottom-most transport horizon can also be transported through the

haul roads where the dump is in rise side.

SEQUENCE OF MINING

The Quarry proposed in Junad Extension OC mine, is below the existing

decoaled Junad OC mine. The total mineable coal and OB in extended Quarry

are 6.13 Mt and 50.62 Mm3 respectively and the stripping ratio works out to be

8.26 m3/t.

GEO - MINING PARAMETERS

Sl. No. Particulars EXTENSION QUARRY

1. FACE LENGTH (km)

a) On the floor of composite seam 1.15 – 1.28

b) On surface 1.50 – 1.70

2. DEPTH UPTO FLOOR OF COMPOSITE

SEAM(m)

a) Initial 30 - 88

b) Final 170

3. WIDTH BELOW THE DECOALED VOID OF

EXISTING OC (m)

a) On the floor of composite seam 250 - 325

b) On surface 400 – 525

4. AREA OF THE QUARRY (ha)

a) On the floor 35.20

b) On surface 70.50

5. Gradient of Seam 1 in 3

6. GRADE OF SEAM (WITH 5 CM

CONTAMINATION)

E

7. U.H.V. (WITH 5 CM CONTAMINATION) 3822

8. AVG. SEAM THICKNESS(m) 17

9. NET MINEABLE RESERVES (Mt) 6.13

10. Average stripping ratio (t:m3) 1:8.26

The shovel dumper system of mining with horizontal slicing method is

recommended for the proposed extension project with sump at the bottom-

most horizon bench in the coal seam.

Page 47: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

2.2 WASTE DISPOSAL & REHANDLING OF EXISTING OB DUMP

Two external OB dumps are proposed in dip side of the extended quarry beyond

the major boundary Fault F1-F1 at a depth ranging from 350-400 m at the floor of

coal seam. The main external OB dump No.1 lies exactly in the dip side of

extended quarry from Aheri village in north to approach road for the project in

south. The dump No.1 is proposed keeping safe distance from Pragati Nagar

township, existing water pipeline, Wardha river and approach road to the

project. External OB dump No.2 is located on other side of approach road.

In addition, about 10.33 Mm3 of OB already dumped by existing Junad OC in dip

side of the quarry over coal bearing area where Junad Extension OCP is

proposed also requires to be rehandled. The capacity of external OB dumps

proposed is about 60.20 Mm3. Remaining 0.75 Mm3 of OB will be used is

construction of safety embankment. The break up of OB quantities in external OB

dumps is given in following table.

No. Dump Capacity in Mm3

0-30m 30 -60m Total

i) Dump – 1 25.70 16.92 42.65

ii) Dump – 2 5.80 2.17 17.55

Total 60.20

The entire extension quarry which is 50.62 M.Cu.m. of existing Junad OC mine is

dumped in dump no. 1 and 2 . About 10.33 M.Cu.m. of OB to be rehandled will

also be dumped in dump no.2 (9.58 M.Cu.m.) and also used for construction of

embankment(0.75 M.Cu.m.).

The external dumps have two benches each of 30m height and final angle of

slope is proposed to be kept at maximum 28o.

2.3 COAL HANDLING PLANT & SURFACE DESPATCH ARRANGEMENT

INTRODUCTION

A small coal handling plant is already in operation, installed at Pimpalgaon

project for Junad OCP. The same CHP will cater to the needs of Junad

extension OC. The CHP has facilities for crushing of coal to (-)200 mm size.

Despatch of coal from the CHP to the customer is being done by roadways.

Details are given in the following paragraphs.

COAL FLOW

Rear discharge dumpers or tipping trucks will carry coal from mine and

discharge on to the hopper of feeder breaker. Oversize material will be

broken inside the feeder breaker to crush the same to conveyable size of (-) 200

mm.

Page 48: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

A conveyor C1 of 1200 mm wide has been provided below the feeder breaker

to collect (-) 200 mm size crushed coal from feeder breaker along with dust and

mucks from below the chain of feeder breaker.

The coal thus collected is conveyed by the belt conveyor C1 to a considerable

height and then allowed to fall in ground to create coal heap.

Coal heap, thus created, is being liquidated by front-end loaders and loaded in to

Customer’s trucks.

An electronic road weigh- bridge, with printout facility, has also been provided

for weighment, records of bills and despatches.

Provision has now being given in this report for storing of coal in over-head truck.

Loading hoppers, instead of creating coal heap. This will facilitate truck loading

and maintaining the quality of coal. Two numbers of 100te. over head truck

loading hoppers have been provided for this purpose. The conveyor C1,

discussed earlier, will be extended to load these hoppers.

Both the coal hoppers will be provided with a vibratory feeder at their discharge

end for even loading customer’s truck etc. from below these hoppers. The

hoppers will have PCC / reinforced flooring for better life.

Facilities like dust suppression and fire fighting have also been provided in the report.

All the equipment in the plant will operate on 415V, 3 phase, 50Hz. AC supply.

For this purpose a unitized sub station 630kVA, 3300V/440V has been provided.

All the gantries various houses and the CHP yard will be suitably illuminated. The

feeder breaker, the conveyors and vibratory screen will be sequentially

controlled.

2.4 PRE-MINING LAND USE

The total land within the proposed mine boundary of Junad Extension OC is

449.63 ha (existing land of Junad OC mine +proposed land for Junad Extension

OCP) whose break-up is given below:

Sl.No. Particulars Land in existing

Junad OC

Mine

Land to be acquired

under proposed Junad

Extn. OC Mine

Total

1. Tenancy Land 174.28 ha 269.25 ha* 443.53

2. Govt. Land - 6.10 ha 6.10

3. Forest Land NIL NIL NIL

TOTAL 174.28 275.35 ha 449.63 ha

*This 269.25 ha of land to be acquired includes 5.20 ha land of Kolar Pimpri

Extn.Project and 13.85 ha of acquired land by existing Pimpalgaon OC Project.

Page 49: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Both the projects are adjacent to Junad Extension OC Mine.

Thus, the total land involved in this project is 449.63 ha, out of which 174.28 ha

land has already been acquired in existing Junad OC mine and balance 275.35

ha will have to be acquired.

FORESTRY CLEARANCE

LAND USE PATTERN

During mining, land use pattern within the mine boundary for Junad Extension

OC (including existing Junad OC) would be as follows :-

S.No. Particulars Area (ha)

1 Total Quarry Area 101.70

2 External OB Dump 175

3 Infrastructure including approach road, etc. 15

4 Embankment 20

5 Colony 0

6 Area needed for rationalization & safe blasting zone 137.93

TOTAL 449.63

Land use pattern – During Mining Stage

Changes of Land Use during Mining:

TOTAL ML/PROJECT AREA (ha)

TOTAL FOREST LAND (ha)

Date of FC Extent of forestland

Balance area for which FC is yet to be obtained

Status of appl. for diversion of forestland

If more than one, provide details of each FC

449.63 Nil Not Applicable Not Applicable

Not Applicable Not Applicable

Sl. No. Particulars Area (ha)

1 Quarry Area 101.70

2 External OB Dump 175.00

3 Infrastructure includin approach road etc. 15.00

4 Diversion of Nala 00.00

5 Embankment 20.00

6 Area needed for rationalization & safe

blasting zone

137.93

TOTAL 449.63

Page 50: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Stage-wise Cumulative Plantation

Sl.No.

year Green Belt External

Dump(OB + Top Soil)

Backfilled area

Others (undisturbed

area/etc.) Total

Area (ha)

No. of

trees

Area (ha)

No. of trees

Area (ha)

No. of

trees

Area (ha)

No. of trees

Area (ha)

No. of trees

1 1st year 0 0 0 0 0 0 0 0 0 0

2 3rd year 0 0 0 0 0 0 0 0 0 0

3 5th year 0 0 25 62.5 0 0 10 25 35 87.5

4 End of mine life

0 0 110 275 0 0 145.93 364.825 255.93 1

5 Post mining

0 0 175 437.50 0 0 157.93 394.825 332.93 832.33

Post-mining Landuse pattern of ML/Project Area (ha)

S.N. Land use during mining

Land use (ha)

Plantation Water Body

Public use Undisturbed Total

1 External OB Dump 175 0 0 0 175

2 Top soil dump 0 0 0 0 0

3 Excavation 0 101.7 0 0 101.7

4 Roads including embankment

17 8 25

5 Built up area 3 0 7 0 10

6 Green Belt 0 0 0 0 0

7 Undisturbed Area 137.93 0 0 0 137.93

Total 332.93 101.7 15 0 449.63

Page 51: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

CHAPTER - III

DESCRIPTION OF ENVIRONMENT

3.1 General :

In order to assess the present scenario in the surrounding of the project i.e. base

line scenario w.r.t. the proposed project, the environmental data generated in

the surrounding in & around during April – to June 2013 has been considered.

The scenario as stated above represents the present scenario before the start of

the project and this will serve as pre – mining condition w.r.t. the proposed Deep

Extension project.

3.2 Socio Economic Environment

The study of socio-economic environment is a part of Environment Impact

Assessment (EIA). A family’s socioeconomic status is based on family income,

parental education level, parental education level, parental occupation and

social status in the community. The study includes demographic structure of the

area (Core zone and Buffer zone 15 Kms. radius from mine lease area), housing,

education, health and medical services, occupation, water supply, sanitation,

communication, transportation, prevailing disease pattern as well as features of

aesthetic significance such as temples, historical monuments scenic beauty

etc., as per census. This would help in visualizing and predicting the likely impact

depending upon the nature and magnitude of the project. In order to validate

the census report, house hold survey was made to collect the data of 250 house

holds falling within core and buffer zone by floating questionnaire to residence

and local people of different villages (respondents selected on basis of socio-

economic condition), village head (Sarapanch/Police patil). The occupational

health status data is collected from the mine Hospital / local Doctor.

The basic amenities as per the census and the information from the residents of

the surveyed villages are described in the following sub-sections.

SOCIO- ECONOMICS DATA

The data collected for baseline study as per district census includes:

a) Number and names of Villages falling within the study area,

b) Social Profile, c) Economic, d) Infrastructure Facilities and

e) Occupational Health

The above information would help in predicting and evaluating likely impacts of

the socio-economic environment due to proposed mining activities.

Page 52: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Description of study area

The study area comprises of the following Districts and Tahesils of Maharashtra

state: The study area, Core and Buffer zone (10 Km) comprises of the following District and Tahsils of

Maharashtra State.

DISTRICT NAME TAHSIL NAME

Chandrapur Bhadravati

Yavatmal Wani

NUMBER & NAMES OF VILLAGES FALLING WITHIN THE STUDY AREA

Chargaon, Junada, Aheri and Borgaon are in the core zone of the project.

There is no village within the distance of 500m from the mine lease area.

Chargaon is in Bhadrawati Tahesil of Chandrapur district. Junada, Aheri and

Borgaon are in Wani Tahesil of Yavatmal district. There are 30 villages within the

study area.

There are 55 villages with 27,042 house holds and 111872 populations within

the study area. The house hold size varies between 1 and 5 with an average

of 4 persons per family.

SOCIAL PROFILE

Total population:

The percentage population is 52.08 % male and 47.92 % female. The

percentage population of scheduled cast (SC), scheduled tribe (ST) and

others are 15.71, 8.85 and 75.44 % respectively.

The Religions which occoures in Yavatmal district are Buddhists,Christians, Hindus,

Jains, Muslims. Christians are more numerous in urban area.

The sex ratio varies between 0 and 1065 with an average of 899. There are

quite a few villages in the study area with sex ratio greater than 1000 for the

age group of 0 to 6 years with an average of 996.

The other cast present are Kunbi, Mali (akosaria, Phulmali, Bhange, Bawane, Jire,

Harde, ghase and Pahad), Banjara, Andh Gond , Pardhans and Kolam.

Major languages which are spoken in Yavatmal district are Banjari, Gondi,

Gujrathi, Hindi, Kolami, Marathi, Sindhi, and Telugu. Marthi is the principal

language and is the mother tounge of the population

The population of Gondi and Kolami speakers are higher and rural areas while

the the proportions of Gujrathi , Hindi.Sindi and Urdu speakers are higher in urban

areas.Telugu spearkers are fairly distributes over rural and urban areas.

Page 53: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Literacy level:

The literacy status of the study area is 79.59 % with 54.73 % male and 45.27%

female.

The illiteracy status of the study area is 20.41 % with 41.74 % male and 58.56 %

female.

Average House holds size:

The average house hold size varies from 4.0 to 6.0 persons per family.

ECONOMIC

The total population is divided into workers and non workers. The workers are

again subdivided into main and marginal workers.

WORKERS: There are 40.02 % workers with 70.81 % male workers and 29.19 %

female workers.

NON-WORKERS: The percentage of non-workers is 59.98 with 39.58 % male

and 60.42 % female.

OCCUPATIONAL STRUCTURE:

MAIN WORKERS: The percentage of main workers is 86.53 with 74.75 % male

and 25.25 % female.

MARGINAL WORKERS: The percentage of marginal workers is 13.47 with

45.48 % male and 54.52 % female.

MAIN WORKERS:

The percentage of main causal workers is 15.35 with 66.61 % male and 33.39 %

female.

The percentage of main agricultural workers is 23.69 with 49.72 % male and

50.53 % female.

The percentage of main house hold workers is 1.93 with 77.30 % male and

22.70 % female.

The percentage of main others workers is 58.92 with 86.90 % male and 13.10 %

female.

MARGINAL WORKERS:

The % of marginal causal workers is 9.02 with 25.92 % male and 74.08 %

female.

The % of marginal agricultural workers is 42.91 with 25.98 % male and 74.02 %

female.

Page 54: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

The % of marginal house hold workers is 4.06 with 39.59 % male and 60.41 %

female.

The % of marginal others workers is 44.0 with 69.05 % male and 30.95 % female.

CLASSIFICATION OF MARGINAL WORKERS:

MARGINAL WORKERS (3 - 6 months)

The % of marginal cultivators is 8.98 with 27.55 % male and 72.45 % female.

The % of marginal agricultural labors is 44.73 with 26.77 % male and 73.23 %

female.

The % of marginal house hold workers is 3.43 with 46.59% male and 53.41 %

female.

The % of marginal others workers is 42.86 with 68.79 % male and 31.21%

female.

MARGINAL WORKERS (0 - 3 months)

The % of marginal cultivators is 9.28 with 16.87 % male and 83.13 % female.

The % of marginal agricultural labors is 32.44 with 19.66 % male and 80.34 %

female.

The % of marginal house hold workers is 7.72 with 21.74 % male and 78.26 %

female.

The % of marginal others workers is 50.56 with 70.35 % male and 29.65 %

female.

Land use Pattern:

The land use pattern of the study area is given as below:

i) Forest land is 6.45%,

ii) Irrigated land is 1.34%,

iii) Un-irrigated land is 63.83%,

iv) Waste land is 5.90% and

v) Uncultivated land is 22.48%.

INFRASTRUCTURE FACILITIES

The houses are made of Bricks or earthen walls with cement or earthen

flooring. The roofs are tiled, sheets and of terrace roof. The grouping of the

houses as per the wall material shows the level of prosperity in the village.

Most of the houses are without toilet facilities of their own and they use the open

land in the village for the purpose. There are no public toilets.

Page 55: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

The migration from the villages during the past is not much. The migration is to

the nearest town is for employment / study purpose or for labour work due to the

lack of employment in the village.

Drinking water is taken care of in some villages through pipeline supply. Other

villages are depended on hand pumps. The quality of water is reasonably well.

The difficulty arises in summer when the hand pumps do not yield even half of

the normal water supply.

These villages are connected with Electric lines but power is intermittently

supplied as in all rural areas of the state.

The fuel for cooking purpose is L.P.G, kerosene/ coal or firewood.

Most of the villages are connected with tar / mud roads with state transport

facilities. Motor cycles, Cycles are used for traveling purposes. Bullock carts /

Tractors are used for carrying materials.

OCCUPATIONAL HEALTH SURVEY

An occupational health risk is a leading cause of morbidity and mortality. The

occupational risk factors account for a number of morbid conditions, including

back pain, hearing loss, chronic obstructive lung disease, asthma, injuries,

cancer, leukemia etc.

OCCUPATIONAL HEALTH HAZARDS:

It is observed during the survey that, the habitation is away from the mining site.

Therefore there will be a minimum effect of mining activities on the locals.

The risk of tropical diseases such as malaria and dengue fever is substantial

during the rainy season. Eradication of mosquitoes and improved sanitation will

controlled these hazards effectively.

It is observed during the survey that malaria, dysentery / diarrhea and skin

disorders are common among all the sex / ages.

OCCURANCE OF HISTORICAL/ARCHAEOLOGICAL SITES

Wani is tahsil headquarter situated on the bank of Nirguda river. The famous

temple of Shir Ranganarh swami is in this town. Thousands of pilgrims visit the

temple from Falguna vadi to Chitra Sud 15. Wani is an important center of trade

in cattle and bullocks. There are coal mines near Wani. The place is well

connected with important places in the district by state roadways and also by

Rail.

The project is having a Hospital at Township with Bed facilities. There is no

Medical facility available in the villages on regular basis except for intermittent

visiting Doctors (Once a week or so).

Page 56: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

The house-to-house sample survey registers the data generally in tune with the

census figures. It also further updates the data particularly in respect of literacy,

persons on jobs, Toilet facilities, housing standards, medical facilities, item of

source of cooking energy, vehicles in villages etc.

PUBLIC AWARENESS AND OPINION ABOUT THE PROJECT

Most of the respondents are aware about the project. 75% respondents have

favorable opinion, 20% have unfavorable opinion and 5% have not given any

opinion.

The respondents were asked to opine about the project. They expected job

opportunities, improvement in educational, transport, medical and Increase in

housing facilities.

Unfavorable opinion can be attributed to increase in environmental pollution,

crimes and increase in the cost of commodities.

3.3 EXISTING LAND USE PATTERN

Land use pattern has been classified into four broad categories.

- Forest land;

- Agriculture ( Irrigated & Un-irrigated ) land

- Cultivable waste land;

- Not available for cultivation.

a) Core Zone - Total land requirement of the project is as given below:-

Break up is given below.

Sl.

No.

Particulars Land

already

acquired

in

existing Junad

OC Mine

Land to be acquired

under proposed Junad

Extn. OC Mine

Total

1. Agricultural

Land

171.15

3.13

269.25 ha*

449.63 ha 2. Waste Land

(Govt. Land)

6.10 ha

3. Forest Land NIL NIL NIL

TOTAL

174.28

ha

275.35 ha 449.63 ha

Page 57: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

3.4 Base Line Environmental quality:

SCOPE AND METHODOLOGY

Preamble

The scope of the study (Period – Pre – MonsoonSeason 2013 – i.e. April 2013 to June

2013) and the present report covers the detailed characterisation of the existing

environmental status in the study area for major environmental components viz.

micrometeorology, ambient air quality, water/waste water quality, noise level and

soil quality.

Micrometeorology

As a part of this study, micrometeorology and microclimatic parameters were

recorded by installing a meteorological station at Core zone. Data of wind

velocity, wind direction, ambient temperature, relative humidity and cloud cover

were recorded at hourly intervals in a day throughout the study period. Further

rainfall also has been recorded and reported.

Wind velocity and wind direction were recorded using cup anemometer and

wind vane respectively. Ambient temperature was noted by wet and dry bulb

thermometer. Relative humidity was measured from hygrometer and a self-

recording rain gauge was used for rainfall data collection. Cloud cover data

has been collected by visual inspection.

Ambient air quality

To assess the ambient air quality status, monitoring stations were identified on the

basis of meteorology in the upwind and downwind direction as well as to

represent the cross sectional scenario of the project site. Based on the production

activities, the parameters chosen for assessment of air quality are Suspended

Particulate Matter (SPM) ,Particulate Matter <10 (PM10), Particulate Matter <2.5

(PM2.5), Sulphur dioxide (SO2), Oxides of Nitrogen (NOx) and heavy metals like

Arsenic ( As), Mercury ( Hg), Nickel ( Ni), Lead ( Pb) and Chromium ( Cr) .

Calibrated Respirable Dust sampler (with an average flow of 1.2 - 1.4 m3/min.)

were used for monitoring of SPM and PM10 and a tapping provided in the

hopper of the same sampler was utilised for sampling of SO2,NOx , with proper

flow controller (1 L/min).The heavy metal like Arsenic ( As), Mercury ( Hg), Nickel (

Ni), Lead ( Pb) and

Chromium (Cr) was also collected in EPM 2000 filter paper by using High volume

sampler. Calibrated APM 550 Fine Particle Sampler (with an average flow of 16.7

LPM) was used for monitoring of PM2.5. A temporary field laboratory for the

purpose of calibration of equipments and standardisation of analytical

procedures was also established.

Page 58: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

SPM & PM10

Calibrated Respirable Dust Sampler with Whatman’s GF/A micro fibre filter

paper was used for the determination of PM & PM10 is a measure of particulate

matter having size <10microns.The dust particles having size >10 microns is being

collected in the cyclone and measured. This along with PM10 value gives total

PM.

PM2.5

Calibrated APM 550 Fine Particle Sampler with Whatman’s standard PTFE 47 mm

diameter filter media was used for the determination of Fine Particles (PM2.5).

PM2.5 is a measure of particulate matter having size <2.5 microns. APM 550 Fine

Particle Sampler is based on impactor designs standardized by USEPA for

ambient air quality monitoring.

SO2 (Modified West & Geake Spectrophotometer method)

Ambient air is bubbled at the rate of 1.0 l/min in an Impinger containing a

scrubbing solution of Sodium-Tetra Chloro Mercurate. The resultant complex is

reacted with P-Rosaniline and Formaldehyde to form coloured Para-Rosaniline

methyl sulphuric acid. The absorbance of the solution is measured in a

Spectrophotometer at a wavelength of 560nm. The SO2 is then calculated from

standard graph.

NO2 (Jacob & Hocheiser modified method)

Ambient air is bubbled at the rate of 1.0 l/min in an Impinger containing a

solution of Sodium Hydroxide and Sodium Arsenate. The resultant Nitrite Ion is

reacted with Phosphoric acid, Sulphanilamide and N-ethylene di-amine di-

hydro chloride to form a coloured complex. The absorbance is measured in a

Spectrophotometer at a wavelength of 540 nm. The concentration of NO2 is then

calculated by using standard graph.

Heavy metals

The AAS technique makes use of absorption spectrophotometry to assess the

concentration of metals in the sample. The method is based on active sampling

using PM10 high volume sampler and then sample analysis is done by Atomic

absorption spectrophotometer.

Page 59: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

The methodology adopted for sampling and analysis of ambient air quality

parameters are given as follows:

S.No. Parameters Methodology

1 Particulate Matter <10 Gravimetric analysis

2 PM2.5 Gravimetric method

3 Sulphur di-oxide Improved West-Geake-

Spectrophotometric Method

4 Oxide of Nitrogen Jacob and Hocheiser Modified Method

5 Heavy Metals AAS method after sampling on EPM 2000

Filter paper

Water quality

Water samples were collected and analyzed as per procedures outlined in IS-

2488/ IS-3025 / AWWA / APHA. Sterilized bottles were used for collection of water

sample for bacteriological analysis, stored in icebox and transported to the

laboratory for the analysis. Parameters like pH, Temperature, Dissolved Oxygen,

Residual Chlorine, Conductivity, Free Ammonia, Total Hardness, Calcium

Hardness and Magnesium Hardness were analyzed in the field while collecting

the samples. MPN index of Coliforms are determined in the laboratory as per

standard methods.

The analyses were carried out as per the BIS & APHA standard methods.

Noise levels

Ambient noise level measurements in four co-ordinal directions were carried out

using CYGNET sound level meter, with windscreen during daytime as well as night

time. Noise measurements were made at 1.5 m above ground and about 3m

away from walls, buildings or other sound reflecting sources. The readings were

taken from morning 6.0 AM to 10 PM at 4 hours regular intervals which give day

time Noise level. The average Leq values during Day time are reported. Similarly

Night time noise levels were taken from 10 PM to 6 AM at four hours interval.

Ambient noise levels are compared with CPCB Norms.

Page 60: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Soil quality

To assess the baseline soil quality, soil samples were collected from identified

locations in core & buffer zones using augers at depths 30, 60 and 100 cms. The

samples were analyzed for chemical parameters like pH, EC, N, P, K and

engineering parameters like textural class, bulk density, liquid limit, field capacity,

wilting coefficient and available water storage capacity.

3.4.1 MICROMETEOROLOGICAL STATUS

Rationale behind sampling

Meteorological parameters are important factors in the study of air pollution.

The transport and diffusion of the pollutants in the atmosphere are governed by

meteorological factors. Factors like wind velocity, wind direction and

atmospheric-stability are known as primary / basic meteorological parameters

since the dispersion and diffusion of pollutants depend mainly on these factors.

Factors like ambient temperature, humidity, rainfall, atmospheric pressure, etc.,

are known as secondary meteorological parameters as these factors control the

dispersion of the pollutants indirectly by affecting the primary factors. Thus, to

assess the air pollution impact it becomes essential to collect the above-

mentioned meteorological parameters in the project area.

Micrometeorological and microclimatic parameters were recorded by installing

a meteorology station in Core zone as it represents the prevailing

micrometeorological aspects of the study area. During the study period, hourly

reading of wind velocity, wind direction, temperature, humidity, cloud cover

etc., were recorded and reported. Further daily rainfall has been recorded and

reported.

Page 61: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Data presentation & analysis

The micrometeorological data thus collected has been processed and analyzed

as per standard procedures. The seasonal wind distribution is given in the Table

below. Seasonal wind distribution data

Season: Pre Monsoon (1st April – 30th June`13)

Location : Core Zone

Wind Direction

Wind Velocity, Kmph (% Duration)

< 1.0 1 – 5 5 – 11 11 – 19 19 - 29

N

1.65 1.97 0.64 -

NNE 0.82 1.42 0.09 -

NE 1.42 2.43 0.69 -

ENE 0.32 0.46 0.23 -

E 0.23 0.05 0.00 -

ESE 0.14 0.14 0.00 -

SE 0.96 0.92 0.23 -

SSE 0.05 0.18 0.18 -

S 0.32 0.60 0.05 -

SSW 2.01 2.84 1.24 -

SW 4.30 5.40 2.15 0.09

WSW 2.66 3.98 0.96 -

W 1.65 1.65 0.87 -

WNW 4.95 6.09 1.79 0.05

NW 10.35 13.05 4.03 -

NNW 4.67 6.82 2.24 -

Season 36.49 47.99 15.38 0.14

Page 62: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 1 METEOROLOGICAL DATA

Date : 01.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 5.0 NW 27.0 54 2 0

2 02.00 5.7 NW 27.0 57 3 0

3 03.00 6.4 NNW 26.5 50 3 0

4 04.00 7.0 NNW 25.0 63 3 0

5 05.00 6.9 SW 25.0 65 3 0

6 06.00 4.7 SW 25.0 70 3 0

7 07.00 6.8 SSW 26.5 65 2 0

8 08.00 10.6 SW 27.0 57 2 0

9 09.00 9.9 NW 28.0 53 1 0

10 10.00 12.4 NW 30.0 48 1 0

11 11.00 7.9 NE 32.0 41 1 0

12 12.00 11.3 NE 33.0 41 1 0

13 13.00 15.6 NE 34.0 35 0 0

14 14.00 11.4 NNE 34.5 31 0 0

15 15.00 8.5 NW 35.0 28 0 0

16 16.00 4.8 NNW 34.5 34 0 0

17 17.00 6.1 NW 34.0 35 1 0

18 18.00 4.2 NW 33.0 41 1 0

19 19.00 4.0 WNW 32.5 44 1 0

20 20.00 6.2 SW 31.0 46 1 0

21 21.00 12.5 SSW 30.5 47 1 0

22 22.00 8.1 SW 29.0 50 2 0

23 23.00 6.8 NW 28.0 52 2 0

24 24.00 4.1 NNW 27.5 58 2 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 4.0 Max : 15.6 Avg : 7.8

3. Ambient Temperature (°C) Min : 25.0 Max : 35.0 Avg : 29.8

4. Relative Humidity (%) Min : 28.0 Max : 70.0 Avg : 48.5

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 63: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 2 METEOROLOGICAL DATA

Date : 02.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 1.3 NW 27.0 56 2 0

2 02.00 3.0 NW 27.5 59 3 0

3 03.00 2.5 NW 26.5 62 3 0

4 04.00 2.3 NNW 25.0 65 3 0

5 05.00 6.9 NW 25.0 68 3 0

6 06.00 3.0 NW 25.0 63 3 0

7 07.00 3.6 NW 26.5 59 2 0

8 08.00 4.7 NW 27.0 56 2 0

9 09.00 6.9 NNW 28.0 48 1 0

10 10.00 8.1 NNW 30.0 44 1 0

11 11.00 4.9 NW 31.0 41 1 0

12 12.00 7.3 NW 32.0 41 1 0

13 13.00 7.1 NW 33.0 35 0 0

14 14.00 9.3 NW 34.0 34 0 0

15 15.00 13.0 WNW 35.0 31 0 0

16 16.00 12.3 WNW 36.0 29 0 0

17 17.00 10.1 WNW 35.5 35 1 0

18 18.00 3.4 NE 34.0 41 1 0

19 19.00 6.0 NE 32.5 44 1 0

20 20.00 4.3 NNE 32.0 46 1 0

21 21.00 5.0 NNE 30.5 47 1 0

22 22.00 6.4 NNE 30.0 50 2 0

23 23.00 7.0 NE 29.0 52 2 0

24 24.00 8.1 NE 28.0 51 2 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.3 Max : 13.0 Avg : 6.1

3. Ambient Temperature (°C) Min : 25.0 Max : 36.0 Avg : 30.0

4. Relative Humidity (%) Min : 29.0 Max : 68.0 Avg : 48.2

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 64: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 3 METEOROLOGICAL DATA

Date : 03.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 2.4 NW 27.0 56 2 0

2 02.00 2.6 NE 27.0 59 3 0

3 03.00 4.5 NE 26.5 62 3 0

4 04.00 3.5 NNE 25.0 68 3 0

5 05.00 6.9 NNW 25.0 68 3 0

6 06.00 4.7 NNW 25.0 76 3 0

7 07.00 6.8 NW 26.5 59 2 0

8 08.00 10.6 NW 27.0 56 2 0

9 09.00 9.9 NW 28.0 48 1 0

10 10.00 12.4 NW 30.0 44 1 0

11 11.00 7.9 WNW 32.0 41 1 0

12 12.00 8.6 NW 34.0 41 1 0

13 13.00 7.3 NE 35.0 35 0 0

14 14.00 6.5 NNE 35.5 29 0 0

15 15.00 4.3 NE 35.0 31 0 0

16 16.00 3.2 WNW 34.0 34 0 0

17 17.00 1.2 WNW 33.0 35 1 0

18 18.00 2.3 NW 32.5 41 1 0

19 19.00 1.5 WNW 32.0 44 1 0

20 20.00 1.9 WNW 31.0 46 1 0

21 21.00 5.3 NNE 29.5 47 1 0

22 22.00 8.1 NE 29.0 50 2 0

23 23.00 6.8 NE 28.0 52 2 0

24 24.00 4.1 NW 27.0 58 2 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph)

: Min : 1.2 Max : 12.4 Avg : 5.6 3. Ambient Temperature (°C) : Min : 25.0 Max : 35.5 Avg : 29.8 4. Relative Humidity (%) : Min : 29.0 Max : 76.0 Avg : 49.2

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 65: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 4 METEOROLOGICAL DATA

Date : 04.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 1.9 NW 27.0 56 2 0

2 02.00 2.3 WNW 27.5 59 3 0

3 03.00 4.6 WSW 26.5 62 3 0

4 04.00 2.3 WSW 25.0 65 3 0

5 05.00 6.9 SW 25.0 68 3 0

6 06.00 3.0 WSW 25.0 63 3 0

7 07.00 3.6 SSW 26.5 59 2 0

8 08.00 4.7 SW 27.0 56 2 0

9 09.00 6.9 WSW 28.0 48 1 0

10 10.00 8.1 WSW 30.0 44 1 0

11 11.00 4.9 WSW 31.0 41 1 0

12 12.00 7.3 WSW 32.0 41 1 0

13 13.00 7.1 WNW 33.0 35 0 0

14 14.00 9.3 WNW 34.0 34 0 0

15 15.00 8.6 NW 35.0 31 0 0

16 16.00 10.3 WNW 36.0 29 0 0

17 17.00 8.6 WSW 35.5 35 1 0

18 18.00 4.3 WSW 34.0 41 1 0

19 19.00 2.3 SW 32.5 44 1 0

20 20.00 2.8 WSW 32.0 46 1 0

21 21.00 1.6 WSW 30.5 47 1 0

22 22.00 1.5 SW 30.0 50 2 0

23 23.00 1.6 SSW 29.5 52 2 0

24 24.00 4.3 S 29.0 51 2 0

OBSERVATIONS

1. Predominant WindDirection (from) : WSW 2. Wind Velocity (Kmph) Min : 1.5 Max : 10.3 Avg : 5.0

3. Ambient Temperature (°C) Min : 25.0 Max : 36.0 Avg : 30.1

4. Relative Humidity (%) Min : 29.0 Max : 68.0 Avg : 48.2

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 66: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 5 METEOROLOGICAL DATA

Date : 05.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 1.6 NW 27.5 56 2 0

2 02.00 1.9 NNW 27.0 59 3 0

3 03.00 2.0 NW 26.5 62 3 0

4 04.00 3.4 NNW 25.0 68 3 0

5 05.00 6.9 NW 25.0 68 3 0

6 06.00 2.0 NNE 25.0 76 3 0

7 07.00 3.1 WNW 26.5 59 2 0

8 08.00 5.8 NE 27.0 56 2 0

9 09.00 3.8 NW 28.0 48 1 0

10 10.00 5.4 ENE 30.0 44 1 0

11 11.00 11.7 WNW 32.0 41 1 0

12 12.00 10.3 NE 34.0 41 1 0

13 13.00 9.6 NE 35.5 35 0 0

14 14.00 8.5 NNW 36.0 34 0 0

15 15.00 4.3 NNW 37.0 31 0 0

16 16.00 3.6 WNW 36.0 34 0 0

17 17.00 4.0 NNW 35.5 35 1 0

18 18.00 3.9 NE 34.0 41 1 0

19 19.00 2.6 NW 32.5 44 1 0

20 20.00 4.3 NW 32.0 46 1 0

21 21.00 6.0 NNW 30.5 47 1 0

22 22.00 9.1 NW 30.0 50 2 0

23 23.00 13.1 NW 29.5 52 2 0

24 24.00 10.6 NNW 29.0 55 2 0

OBSERVATIONS

1. Predominant WindDirection (from) : NNW 2. Wind Velocity (Kmph) Min : 1.6 Max : 13.1 Avg : 5.7

3. Ambient Temperature (°C) Min : 25.0 Max : 37.0 Avg : 30.5

4. Relative Humidity (%) Min : 31.0 Max : 76.0 Avg : 49.3

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 67: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 6 METEOROLOGICAL DATA

Date : 06.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 2.3 NW 28.0 56 2 0

2 02.00 2.4 NW 27.0 59 3 0

3 03.00 3.6 WNW 26.5 62 3 0

4 04.00 3.4 WNW 25.0 68 3 0

5 05.00 6.9 WNW 25.0 68 3 0

6 06.00 2.0 NW 25.0 76 3 0

7 07.00 3.1 NW 26.5 59 2 0

8 08.00 4.4 NW 27.0 56 2 0

9 09.00 3.8 NNE 28.0 48 1 0

10 10.00 5.4 NW 30.0 44 1 0

11 11.00 11.7 NW 32.0 41 1 0

12 12.00 13.1 NW 34.0 41 1 0

13 13.00 12.3 NE 35.5 35 0 0

14 14.00 9.3 ENE 36.0 34 0 0

15 15.00 8.2 SE 38.0 32 0 0

16 16.00 3.6 S 36.0 34 0 0

17 17.00 4.0 SE 35.5 35 1 0

18 18.00 3.9 SW 34.0 41 1 0

19 19.00 4.6 SW 32.5 44 1 0

20 20.00 7.6 S 32.0 46 1 0

21 21.00 6.0 SW 30.5 47 1 0

22 22.00 9.1 WSW 30.0 50 2 0

23 23.00 13.1 SW 29.5 52 2 0

24 24.00 10.6 S 29.0 55 2 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.0 Max : 13.1 Avg : 6.4

3. Ambient Temperature (°C) Min : 25.0 Max : 38.0 Avg : 30.5

4. Relative Humidity (%) Min : 32.0 Max : 76.0 Avg : 49.3

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 68: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 7 METEOROLOGICAL DATA

Date : 07.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 8.8 NW 27.5 56 2 0

2 02.00 6.0 WNW 27.0 59 3 0

3 03.00 5.5 NW 26.5 62 3 0

4 04.00 4.2 NNW 25.0 68 3 0

5 05.00 6.9 NNW 25.0 68 3 0

6 06.00 4.3 NW 25.0 72 3 0

7 07.00 6.0 NW 26.0 66 2 0

8 08.00 7.5 NW 28.0 54 1 0

9 09.00 7.4 NNW 28.5 51 1 0

10 10.00 9.8 NNW 30.0 47 1 0

11 11.00 11.2 NNW 32.5 44 1 0

12 12.00 15.9 ENE 34.0 43 1 0

13 13.00 9.6 ENE 36.0 38 0 0

14 14.00 8.2 ENE 36.5 34 0 0

15 15.00 6.6 NE 38.5 32 0 0

16 16.00 4.9 NW 36.5 34 0 0

17 17.00 3.9 WNW 36.0 38 0 0

18 18.00 4.3 NW 34.5 41 1 0

19 19.00 6.1 NW 34.0 43 1 0

20 20.00 7.5 NW 32.5 44 1 0

21 21.00 6.6 WNW 32.0 46 1 0

22 22.00 4.8 NW 30.0 50 1 0

23 23.00 6.2 WNW 29.5 52 1 0

24 24.00 4.2 WNW 29.0 55 2 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 3.9 Max : 15.9 Avg : 6.9

3. Ambient Temperature (°C) Min : 25.0 Max : 38.5 Avg : 30.8

4. Relative Humidity (%) Min : 32.0 Max : 72.0 Avg : 49.9

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 69: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 8 METEOROLOGICAL DATA

Date : 08.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 3.0 NW 28.5 57 2 0

2 02.00 2.5 NW 27.5 59 3 0

3 03.00 5.1 NW 27.0 70 3 0

4 04.00 4.0 NW 26.0 76 3 0

5 05.00 6.9 NNW 26.0 76 3 0

6 06.00 5.7 NW 36.5 69 3 0

7 07.00 9.1 NW 38.0 54 3 0

8 08.00 12.0 NNW 30.0 51 2 0

9 09.00 9.3 NNW 30.5 44 2 0

10 10.00 14.7 NW 32.5 44 1 0

11 11.00 17.5 NW 34.5 43 1 0

12 12.00 15.0 NW 36.0 43 1 0

13 13.00 11.0 SW 36.5 38 0 0

14 14.00 8.8 SSW 38.0 36 0 0

15 15.00 9.3 SSW 38.5 32 0 0

16 16.00 8.0 SW 36.5 38 0 0

17 17.00 6.1 SW 36.0 43 1 0

18 18.00 7.3 SW 34.5 43 1 0

19 19.00 6.4 SSW 32.5 44 1 0

20 20.00 7.4 SW 32.0 46 2 0

21 21.00 7.0 SE 30.5 47 2 0

22 22.00 9.1 SE 30.0 50 2 0

23 23.00 3.4 SE 29.5 52 3 0

24 24.00 2.3 SE 29.0 55 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.3 Max : 17.5 Avg : 8.0

3. Ambient Temperature (°C) Min : 26.0 Max : 38.5 Avg : 32.4

4. Relative Humidity (%) Min : 32.0 Max : 76.0 Avg : 50.4

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 70: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 9 METEOROLOGICAL DATA

Date : 09.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 4.5 NW 27.5 56 3 0

2 02.00 6.0 SW 27.0 59 3 0

3 03.00 5.3 SE 26.5 62 3 0

4 04.00 4.1 NE 26.0 69 3 0

5 05.00 6.9 NE 26.0 73 3 0

6 06.00 4.0 ESE 27.5 77 3 0

7 07.00 1.6 NE 28.0 66 2 0

8 08.00 8.4 ESE 29.0 44 2 0

9 09.00 7.0 SE 32.0 55 1 0

10 10.00 12.3 SE 34.0 51 1 0

11 11.00 11.3 SE 34.5 46 1 0

12 12.00 16.8 WSW 36.0 43 1 0

13 13.00 9.4 SW 36.5 38 0 0

14 14.00 5.0 SW 38.0 34 0 0

15 15.00 7.2 SW 38.5 32 0 0

16 16.00 6.1 WSW 38.0 36 0 0

17 17.00 6.5 SW 36.0 38 0 0

18 18.00 4.0 SW 34.5 41 1 0

19 19.00 3.1 WSW 34.0 43 1 0

20 20.00 4.5 SW 32.0 44 1 0

21 21.00 8.2 SW 30.5 47 1 0

22 22.00 2.4 SW 30.0 50 1 0

23 23.00 1.6 SW 29.0 52 1 0

24 24.00 2.0 SSW 28.5 54 2 0

OBSERVATIONS

1. Predominant WindDirection (from) : SW 2. Wind Velocity (Kmph) Min : 1.6 Max : 16.8 Avg : 6.2

3. Ambient Temperature (°C) Min : 26.0 Max : 38.5 Avg : 31.6

4. Relative Humidity (%) Min : 32.0 Max : 77.0 Avg : 50.4

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 71: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 10 METEOROLOGICAL DATA

Date : 10.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 2.3 NW 28.0 57 2 0

2 02.00 4.9 SW 27.5 59 2 0

3 03.00 5.1 WNW 27.0 70 3 0

4 04.00 3.6 NW 26.5 73 3 0

5 05.00 6.9 NNW 26.0 76 3 0

6 06.00 4.0 NNW 27.0 73 3 0

7 07.00 4.7 NNW 28.0 64 3 0

8 08.00 7.0 NW 30.0 47 2 0

9 09.00 10.3 NE 30.5 42 2 0

10 10.00 15.6 NNW 32.5 41 1 0

11 11.00 12.7 NNW 34.0 41 1 0

12 12.00 7.4 NNW 36.0 34 1 0

13 13.00 9.9 NW 38.0 32 0 0

14 14.00 9.1 NW 38.5 28 0 0

15 15.00 8.7 NNW 40.0 23 0 0

16 16.00 5.6 NNE 38.5 28 0 0

17 17.00 7.6 NE 38.0 28 1 0

18 18.00 8.8 NE 36.0 30 1 0

19 19.00 4.9 NE 35.0 35 1 0

20 20.00 6.3 NNE 34.0 36 1 0

21 21.00 5.0 NNE 32.0 39 1 0

22 22.00 3.4 NNW 30.5 44 1 0

23 23.00 3.4 NW 30.0 47 1 0

24 24.00 4.3 NW 29.0 52 2 0

OBSERVATIONS

1. Predominant WindDirection (from) : NNW 2. Wind Velocity (Kmph) Min : 2.3 Max : 15.6 Avg : 6.7

3. Ambient Temperature (°C) Min : 26.0 Max : 40.0 Avg : 32.2

4. Relative Humidity (%) Min : 23.0 Max : 76.0 Avg : 45.8

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 72: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 11 METEOROLOGICAL DATA

Date : 11.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 2.6 NW 28.5 54 2 0

2 02.00 5.9 NW 28.0 57 2 0

3 03.00 4.3 NW 27.5 66 3 0

4 04.00 8.3 NW 27.0 70 3 0

5 05.00 6.9 NW 26.0 76 3 0

6 06.00 3.0 WNW 28.0 70 3 0

7 07.00 3.7 NW 28.5 64 2 0

8 08.00 4.8 WNW 29.0 51 2 0

9 09.00 7.9 NW 32.0 49 1 0

10 10.00 10.3 NNW 34.0 46 1 0

11 11.00 11.2 NW 34.5 43 1 0

12 12.00 12.6 NE 36.0 43 1 0

13 13.00 14.5 SE 38.0 40 0 0

14 14.00 12.0 SSE 38.5 36 0 0

15 15.00 9.6 SE 40.0 34 0 0

16 16.00 8.3 SE 38.5 36 0 0

17 17.00 7.9 SSE 38.0 40 1 0

18 18.00 6.3 NW 36.0 43 1 0

19 19.00 5.0 SW 34.5 43 1 0

20 20.00 4.5 SSW 34.0 46 1 0

21 21.00 6.4 SW 32.5 46 1 0

22 22.00 8.7 SW 32.0 49 1 0

23 23.00 7.0 SSW 30.5 50 2 0

24 24.00 4.3 SSW 30.0 53 2 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.6 Max : 14.5 Avg : 7.3

3. Ambient Temperature (°C) Min : 26.0 Max : 40.0 Avg : 32.6

4. Relative Humidity (%) Min : 34.0 Max : 76.0 Avg : 50.2

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 73: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 12 METEOROLOGICAL DATA

Date : 12.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 5.7 NW 29.5 58 2 0

2 02.00 6.0 SSW 29.0 61 3 0

3 03.00 5.4 SSW 28.5 64 3 0

4 04.00 4.2 SW 27.0 66 3 0

5 05.00 6.9 SW 26.5 76 3 0

6 06.00 6.7 SSW 28.0 67 3 0

7 07.00 5.9 SW 28.5 64 2 0

8 08.00 7.6 SW 29.5 52 2 0

9 09.00 9.1 SW 30.0 47 1 0

10 10.00 11.4 SSE 32.0 44 1 0

11 11.00 9.7 SE 32.5 41 1 0

12 12.00 13.0 SSE 34.5 41 1 0

13 13.00 11.6 SE 36.0 38 0 0

14 14.00 17.8 SW 38.0 36 0 0

15 15.00 9.1 SW 40.5 34 0 0

16 16.00 8.7 SSW 40.0 38 0 0

17 17.00 9.5 SW 38.5 45 5 0

18 18.00 6.3 SW 38.0 52 4 0

19 19.00 4.6 WSW 36.5 53 4 0

20 20.00 7.8 SW 36.0 55 3 0

21 21.00 10.3 SSW 34.5 56 3 0

22 22.00 6.1 SW 34.0 59 3 0

23 23.00 8.4 SSW 32.5 61 3 0

24 24.00 2.6 SW 30.5 62 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : SW 2. Wind Velocity (Kmph) Min : 2.6 Max : 17.8 Avg : 8.1

3. Ambient Temperature (°C) Min : 26.5 Max : 40.5 Avg : 32.9

4. Relative Humidity (%) Min : 34.0 Max : 76.0 Avg : 52.9

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 74: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 13 METEOROLOGICAL DATA

Date : 13.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 5.5 NW 30.0 65 3 0

2 02.00 6.0 SW 28.5 67 3 0

3 03.00 4.2 SW 28.0 70 3 0

4 04.00 3.8 SSW 27.0 73 3 0

5 05.00 6.9 SSW 27.0 77 3 0

6 06.00 7.4 NW 29.0 68 3 0

7 07.00 11.4 NW 29.5 64 2 0

8 08.00 14.0 NW 30.0 59 2 0

9 09.00 15.7 NW 30.5 47 1 0

10 10.00 13.0 SW 32.0 44 1 0

11 11.00 14.3 SW 34.0 41 1 0

12 12.00 14.4 SSW 36.0 38 1 0

13 13.00 16.7 SSW 38.0 36 0 0

14 14.00 9.3 SW 40.0 34 0 0

15 15.00 8.6 SSW 42.0 32 0 0

16 16.00 7..0 SW 40.0 34 0 0

17 17.00 6.7 SW 38.5 36 2 0

18 18.00 5.4 SW 38.0 45 2 0

19 19.00 9.1 SSW 36.5 50 2 0

20 20.00 9.6 NW 36.0 53 3 0

21 21.00 10.9 NNW 34.5 54 3 0

22 22.00 17.6 SW 34.0 56 3 0

23 23.00 11.9 SW 32.5 64 3 0

24 24.00 14.7 SW 32.0 67 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : SW 2. Wind Velocity (Kmph) Min : 3.8 Max : 17.6 Avg : 10.3

3. Ambient Temperature (°C) Min : 27.0 Max : 42.0 Avg : 33.5

4. Relative Humidity (%) Min : 32.0 Max : 77.0 Avg : 53.1

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 75: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 14 METEOROLOGICAL DATA

Date : 14.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 5.0 NW 30.5 68 3 0

2 02.00 5.4 SSW 30.0 72 3 0

3 03.00 4.5 SW 29.5 74 3 0

4 04.00 4.6 SW 29.0 78 3 0

5 05.00 6.9 SW 29.0 78 3 0

6 06.00 2.1 WSW 30.0 72 3 0

7 07.00 1.7 SSW 32.0 70 3 0

8 08.00 3.1 NW 32.5 67 2 0

9 09.00 6.6 NW 34.0 56 2 0

10 10.00 9.6 NW 38.0 47 1 0

11 11.00 7.3 NNW 38.5 45 1 0

12 12.00 5.8 NW 40.0 38 1 0

13 13.00 8.6 NW 40.5 34 0 0

14 14.00 5.0 NNW 42.0 32 0 0

15 15.00 4.1 NNW 42.5 32 0 0

16 16.00 3.9 NNE 42.0 36 0 0

17 17.00 4.6 NE 40.5 38 1 0

18 18.00 7.8 NNE 40.0 42 1 0

19 19.00 7.0 NW 38.5 45 1 0

20 20.00 6.7 NW 38.0 50 1 0

21 21.00 6.0 NW 36.5 53 1 0

22 22.00 3.4 WNW 36.0 55 1 0

23 23.00 4.1 WNW 34.5 56 1 0

24 24.00 4.6 NW 34.0 59 2 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.7 Max : 9.6 Avg : 5.4

3. Ambient Temperature (°C) Min : 29.0 Max : 42.5 Avg : 35.8

4. Relative Humidity (%) Min : 32.0 Max : 78.0 Avg : 54.0

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 76: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 15 METEOROLOGICAL DATA

Date : 15.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 6.3 NW 32.5 61 2 0

2 02.00 2.7 NNE 32.0 64 2 0

3 03.00 4.0 NNW 30.0 68 3 0

4 04.00 5.4 NE 29.5 71 3 0

5 05.00 6.9 NNE 29.0 74 3 0

6 06.00 5.4 N 30.0 72 3 0

7 07.00 6.0 N 30.5 65 2 0

8 08.00 5.1 N 32.0 61 2 0

9 09.00 8.2 N 34.0 56 1 0

10 10.00 12.6 NW 36.0 48 1 0

11 11.00 10.4 NNE 36.5 45 1 0

12 12.00 9.8 NW 38.0 45 1 0

13 13.00 15.3 NE 38.5 40 0 0

14 14.00 12.6 NW 40.0 34 0 0

15 15.00 6.1 N 42.5 32 0 0

16 16.00 18.0 NNE 40.0 34 0 0

17 17.00 15.7 N 38.5 36 1 0

18 18.00 11.4 NW 38.0 45 1 0

19 19.00 7.0 NNW 36.5 50 1 0

20 20.00 4.0 NNW 36.0 53 1 0

21 21.00 3.0 WNW 34.5 54 1 0

22 22.00 8.0 WNW 34.0 56 1 0

23 23.00 6.7 NW 32.5 64 2 0

24 24.00 9.1 NNW 32.0 67 2 0

OBSERVATIONS

1. Predominant WindDirection (from) : N 2. Wind Velocity (Kmph) Min : 2.7 Max : 18.0 Avg : 8.3

3. Ambient Temperature (°C) Min : 29.0 Max : 42.5 Avg : 34.7

4. Relative Humidity (%) Min : 32.0 Max : 74.0 Avg : 54.0

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 77: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 16 METEOROLOGICAL DATA

Date : 16.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 2.6 NW 30.5 68 2 0

2 02.00 3.2 WNW 30.0 72 2 0

3 03.00 4.2 NW 29.5 74 3 0

4 04.00 5.3 NW 29.0 78 3 0

5 05.00 6.9 N 29.0 78 3 0

6 06.00 8.4 N 30.0 72 3 0

7 07.00 3.6 NE 32.5 67 2 0

8 08.00 5.3 WNW 34.0 56 2 0

9 09.00 7.6 NW 34.5 51 1 0

10 10.00 9.6 NW 36.0 48 1 0

11 11.00 12.9 WNW 36.5 45 1 0

12 12.00 8.1 SW 38.5 40 1 0

13 13.00 14.5 SW 40.0 34 0 0

14 14.00 10.4 SW 40.5 30 0 0

15 15.00 8.5 W 42.0 29 0 0

16 16.00 7.0 W 40.0 34 0 0

17 17.00 6.7 W 38.5 40 1 0

18 18.00 7.2 WSW 38.0 45 1 0

19 19.00 5.5 WSW 36.5 48 1 0

20 20.00 4.1 W 36.0 53 1 0

21 21.00 7.4 NW 34.5 54 1 0

22 22.00 8.7 NW 34.0 56 1 0

23 23.00 4.3 NW 32.5 58 2 0

24 24.00 6.1 NW 32.0 61 2 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.6 Max : 14.5 Avg : 7.0

3. Ambient Temperature (°C) Min : 29.0 Max : 42.0 Avg : 34.8

4. Relative Humidity (%) Min : 29.0 Max : 78.0 Avg : 53.8

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 78: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 17 METEOROLOGICAL DATA

Date : 17.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 6.3 NW 30.5 62 3 0

2 02.00 2.7 NW 30.0 65 3 0

3 03.00 4.0 NNW 29.5 68 3 0

4 04.00 5.4 NNW 29.5 74 3 0

5 05.00 6.9 NW 29.0 74 3 0

6 06.00 7.1 WNW 30.0 72 2 0

7 07.00 10.7 NW 32.0 58 2 0

8 08.00 12.0 NNW 32.5 49 2 0

9 09.00 9.9 NW 34.0 46 1 0

10 10.00 13.1 NW 34.5 46 1 0

11 11.00 14.9 NW 36.0 43 1 0

12 12.00 16.4 NW 36.5 38 1 0

13 13.00 11.0 WSW 38.0 36 0 0

14 14.00 18.3 SW 38.5 32 0 0

15 15.00 17.1 SSW 40.0 30 0 0

16 16.00 10.4 SE 39.0 29 1 0

17 17.00 8.0 SSE 38.5 40 1 0

18 18.00 8.6 SE 38.0 45 2 0

19 19.00 7.4 SW 36.5 48 2 0

20 20.00 8.8 SW 36.0 53 3 0

21 21.00 6.3 WSW 34.5 54 3 0

22 22.00 5.4 WSW 34.0 56 3 0

23 23.00 5.7 SSW 32.5 61 3 0

24 24.00 9.6 SW 32.0 64 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.7 Max : 18.3 Avg : 9.4

3. Ambient Temperature (°C) Min : 29.0 Max : 40.0 Avg : 34.2

4. Relative Humidity (%) Min : 29.0 Max : 74.0 Avg : 51.8

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 79: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 18 METEOROLOGICAL DATA

Date : 18.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 2.3 NW 30.5 65 2 0 2 02.00 2.6 WNW 30.0 68 3 0 3 03.00 3.5 N 29.0 71 3 0

4 04.00 4.6 WNW 28.0 77 3 0

5 05.00 6.9 WNW 28.0 77 3 0

6 06.00 1.8 NNW 28.5 74 3 0 7 07.00 4.8 NW 30.5 59 2 0 8 08.00 6.9 WNW 32.0 49 2 0 9 09.00 6.1 NW 32.5 44 1 0

10 10.00 10.4 NNW 34.0 43 1 0

11 11.00 16.0 NNW 36.5 43 1 0

12 12.00 15.0 WNW 38.0 40 1 0 13 13.00 9.6 WNW 38.5 36 0 0 14 14.00 6.6 NW 40.0 34 0 0 15 15.00 8.0 NNW 40.5 30 0 0

16 16.00 7.4 NW 40.0 38 0 0

17 17.00 6.7 NNW 39.5 39 0 0

18 18.00 7.6 NNW 36.0 43 0 0 19 19.00 5.5 WNW 34.0 43 1 0 20 20.00 8.8 WNW 32.0 44 1 0 21 21.00 6.0 NNW 30.0 47 1 0

22 22.00 4.7 NNW 29.5 49 1 0

23 23.00 2.9 N 29.0 52 1 0

24 24.00 4.4 N 28.5 54 2 0

OBSERVATIONS

1. Predominant WindDirection (from) : NNW 2. Wind Velocity (Kmph) Min : 1.8 Max : 16.0 Avg : 6.6

3. Ambient Temperature (°C) Min : 28.0 Max : 40.5 Avg : 33.1

4. Relative Humidity (%) Min : 30.0 Max : 77.0 Avg : 50.8

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 80: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 19 METEOROLOGICAL DATA

Date : 19.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 6.3 NW 28.0 57 2 0

2 02.00 2.7 NW 27.5 59 3 0

3 03.00 4.0 NW 27.0 63 3 0

4 04.00 5.4 NW 26.0 76 3 0

5 05.00 6.9 NW 26.0 76 3 0

6 06.00 6.3 N 38.0 67 3 0

7 07.00 9.0 NW 29.0 61 2 0

8 08.00 8.4 NW 32.0 55 2 0

9 09.00 9.6 NNW 34.0 48 1 0

10 10.00 12.1 NNW 36.0 43 1 0

11 11.00 10.4 NW 36.5 43 1 0

12 12.00 7.9 W 38.0 40 1 0

13 13.00 8.4 NNW 38.5 40 0 0

14 14.00 6.0 NW 40.0 38 0 0

15 15.00 5.5 NNWNW 40.5 34 0 0

16 16.00 4.7 WNW 40.0 38 0 0

17 17.00 6.4 NNE 38.5 40 0 0

18 18.00 7.1 NW 38.0 40 1 0

19 19.00 4.8 WNW 36.5 43 1 0

20 20.00 5.9 NW 36.0 43 1 0

21 21.00 5.4 NNW 34.5 46 1 0

22 22.00 3.8 NNW 34.0 51 1 0

23 23.00 4.3 NW 32.5 52 1 0

24 24.00 1.2 NNE 32.0 61 1 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.2 Max : 12.1 Avg : 6.4

3. Ambient Temperature (°C) Min : 26.0 Max : 40.5 Avg : 34.1

4. Relative Humidity (%) Min : 34.0 Max : 76.0 Avg : 50.6

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 81: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 20 METEOROLOGICAL DATA

Date : 20.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 2.3 NW 30.0 62 3 0

2 02.00 2.6 NNW 29.0 64 3 0

3 03.00 2.4 WNW 28.0 67 3 0

4 04.00 3.5 WNW 27.0 73 3 0

5 05.00 6.9 WNW 27.0 73 3 0

6 06.00 4.0 W 29.0 68 3 0

7 07.00 6.1 W 29.5 64 2 0

8 08.00 11.6 WSW 30.0 59 2 0

9 09.00 8.6 WSW 30.5 47 1 0

10 10.00 12.0 W 32.0 44 1 0

11 11.00 14.2 WSW 34.0 41 1 0

12 12.00 4.9 WW 36.0 38 1 0

13 13.00 12.7 W 38.0 36 0 0

14 14.00 11.2 WSW 40.0 34 0 0

15 15.00 9.0 SW 42.0 32 0 0

16 16.00 12.1 SW 40.0 34 1 0

17 17.00 2.5 WSW 38.5 36 1 0

18 18.00 3.3 SW 38.0 45 2 0

19 19.00 9.0 SW 36.5 50 2 0

20 20.00 4.7 WSW 36.0 53 2 0

21 21.00 9.4 WSW 34.5 54 2 0

22 22.00 7.6 W 34.0 56 3 0

23 23.00 13.7 WSW 32.5 64 3 0

24 24.00 16.5 WSW 32.0 67 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : WSW 2. Wind Velocity (Kmph) Min : 2.3 Max : 16.5 Avg : 8.0

3. Ambient Temperature (°C) Min : 27.0 Max : 42.0 Avg : 33.5

4. Relative Humidity (%) Min : 32.0 Max : 73.0 Avg : 52.5

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 82: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 21 METEOROLOGICAL DATA

Date : 21.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 6.3 NW 30.5 68 3 0

2 02.00 2.7 WSW 30.0 72 3 0

3 03.00 4.0 WSW 28.0 77 3 0

4 04.00 5.4 SW 27.0 77 3 0

5 05.00 6.9 SW 27.0 77 3 0

6 06.00 7.0 SW 27.0 73 3 0

7 07.00 9.1 SW 28.0 64 2 0

8 08.00 8.5 SW 28.5 51 2 0

9 09.00 10.4 WSW 29.0 49 2 0

10 10.00 7.9 WSW 29.5 46 1 0

11 11.00 11.7 WSW 30.0 42 1 0

12 12.00 19.5 SW 32.0 39 1 0

13 13.00 20.2 SW 36.5 38 0 0

14 14.00 17.8 SW 38.0 36 0 0

15 15.00 12.0 SW 38.5 32 0 0

16 16.00 4.1 SSW 38.0 36 1 0

17 17.00 5.8 SSW 36.5 38 1 0

18 18.00 5.3 SSW 36.0 43 2 0

19 19.00 6.5 WSW 34.0 43 2 0

20 20.00 7.0 WSW 32.5 44 2 0

21 21.00 5.8 WNW 32.0 46 2 0

22 22.00 11.5 WNW 30.0 47 3 0

23 23.00 4.9 NW 29.0 49 3 0

24 24.00 3.9 NW 28.5 54 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : SW 2. Wind Velocity (Kmph) Min : 2.7 Max : 20.2 Avg : 8.5

3. Ambient Temperature (°C) Min : 27.0 Max : 38.5 Avg : 31.5

4. Relative Humidity (%) Min : 32.0 Max : 77.0 Avg : 51.7

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 83: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 22 METEOROLOGICAL DATA

Date : 22.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 3.5 NW 28.0 57 2 0

2 02.00 5.1 NW 26.5 59 3 0

3 03.00 4.6 NNW 26.0 69 3 0

4 04.00 3.2 NW 25.0 76 3 0

5 05.00 6.9 NW 25.0 76 3 0

6 06.00 4.2 NNW 25.5 72 3 0

7 07.00 4.6 NNW 26.0 62 2 0

8 08.00 7.2 NW 26.5 55 2 0

9 09.00 8.5 NW 27.0 50 1 0

10 10.00 9.2 NW 28.0 45 1 0

11 11.00 10.5 NE 29.0 40 1 0

12 12.00 8.0 NE 30.0 36 1 0

13 13.00 10.2 NE 32.0 34 0 0

14 14.00 14.0 NNE 34.0 32 0 0

15 15.00 12.4 NE 36.0 30 0 0

16 16.00 6.7 NNE 35.0 35 0 0

17 17.00 8.1 NE 34.5 36 1 0

18 18.00 5.3 NNW 34.0 41 1 0

19 19.00 4.8 NW 32.5 41 1 0

20 20.00 3.4 NW 32.0 44 1 0

21 21.00 2.8 WNW 30.5 44 1 0

22 22.00 3.0 NW 30.0 47 1 0

23 23.00 3.4 NW 28.5 48 1 0

24 24.00 4.2 NNW 28.0 51 2 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.8 Max : 14.0 Avg : 6.4

3. Ambient Temperature (°C) Min : 25.0 Max : 36.0 Avg : 29.6

4. Relative Humidity (%) Min : 30.0 Max : 76.0 Avg : 49.2

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 84: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 23 METEOROLOGICAL DATA

Date : 23.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 6.3 NW 27.5 53 2 0

2 02.00 2.7 N 27.0 56 3 0

3 03.00 4.0 N 26.5 59 3 0

4 04.00 5.4 N 25.0 76 3 0

5 05.00 6.9 NW 25.0 76 3 0

6 06.00 4.3 N 26.0 69 3 0

7 07.00 6.9 NNW 27.5 59 3 0

8 08.00 9.6 N 28.0 51 2 0

9 09.00 13.0 NW 28.5 45 1 0

10 10.00 14.7 NNW 29.0 40 1 0

11 11.00 12.3 N 30.5 36 1 0

12 12.00 12.0 N 32.0 34 1 0

13 13.00 18.9 NW 32.5 29 0 0

14 14.00 10.1 N 34.0 27 0 0

15 15.00 7.9 NNW 36.0 26 0 0

16 16.00 8.5 NNW 35.5 35 0 0

17 17.00 5.0 NNW 34.0 41 1 0

18 18.00 6.9 NW 32.5 44 1 0

19 19.00 3.0 NW 32.0 46 1 0

20 20.00 2.5 WNW 30.5 47 1 0

21 21.00 3.6 NNW 30.0 50 1 0

22 22.00 6.1 NW 29.5 52 1 0

23 23.00 9.0 NW 29.0 55 2 0

24 24.00 11.5 N 27.5 56 2 0

OBSERVATIONS

1. Predominant WindDirection (from) : N 2. Wind Velocity (Kmph) Min : 2.5 Max : 18.9 Avg : 8.0

3. Ambient Temperature (°C) Min : 25.0 Max : 36.0 Avg : 29.8

4. Relative Humidity (%) Min : 26.0 Max : 76.0 Avg : 48.4

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 85: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 24 METEOROLOGICAL DATA

Date : 24.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 6.3 NW 27.0 59 2 0

2 02.00 2.7 NW 26.5 62 2 0

3 03.00 4.0 NW 26.5 66 3 0

4 04.00 5.4 NW 25.0 68 3 0

5 05.00 6.9 NNW 25.0 68 3 0

6 06.00 5.4 NW 25.5 76 3 0

7 07.00 6.0 NW 27.0 59 2 0

8 08.00 5.1 NW 28.0 57 2 0

9 09.00 8.3 SW 28.5 48 1 0

10 10.00 12.6 SSW 29.0 46 1 0

11 11.00 10.4 SSW 30.0 42 1 0

12 12.00 9.8 SW 30.5 36 1 0

13 13.00 15.3 NW 32.5 34 0 0

14 14.00 12.6 NW 34.5 32 0 0

15 15.00 6.1 SW 36.0 30 0 0

16 16.00 17.0 SW 35.0 35 0 0

17 17.00 15.7 SW 34.5 36 1 0

18 18.00 11.4 NW 34.0 41 1 0

19 19.00 7.0 NNW 32.5 44 1 0

20 20.00 4.9 NW 32.0 46 1 0

21 21.00 8.0 NE 30.5 47 1 0

22 22.00 6.9 NNE 30.0 50 2 0

23 23.00 9.1 NNW 29.5 52 2 0

24 24.00 6.8 NW 27.5 56 2 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.7 Max : 17.0 Avg : 8.5

3. Ambient Temperature (°C) Min : 25.0 Max : 36.0 Avg : 29.9

4. Relative Humidity (%) Min : 30.0 Max : 76.0 Avg : 49.6

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 86: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 25 METEOROLOGICAL DATA

Date : 25.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 3.2 NW 27.0 59 2 0

2 02.00 2.4 N 26.5 62 3 0

3 03.00 2.0 NNE 26.5 66 3 0

4 04.00 1.5 NNW 25.0 68 3 0

5 05.00 6.9 NNW 25.0 68 3 0

6 06.00 3.2 NW 28.0 70 3 0

7 07.00 1.5 NNW 29.0 58 2 0

8 08.00 2.0 NNW 30.0 53 1 0

9 09.00 1.8 NW 32.0 49 1 0

10 10.00 3.9 NNW 34.0 41 1 0

11 11.00 5.0 NNW 36.0 38 2 Cloudy

12 12.00 10.2 NNW 38.0 36 2 8

13 13.00 11.2 NW 40.0 34 2 Cloudy

14 14.00 13.1 NNW 42.0 32 5 0

15 15.00 10.2 NNE 44.0 31 4 0

16 16.00 8.5 NNE 42.5 32 3 0

17 17.00 6.2 NE 42.0 36 3 0

18 18.00 4.9 NE 40.5 38 3 0

19 19.00 5.2 N 40.0 42 3 0

20 20.00 4.5 N 38.5 45 3 0

21 21.00 3.0 NW 38.0 47 3 0

22 22.00 2.5 WNW 36.5 48 3 0

23 23.00 4.5 WNW 36.0 50 3 0

24 24.00 3.6 NW 34.5 52 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NNW 2. Wind Velocity (Kmph) Min : 1.5 Max : 13.1 Avg : 5.0

3. Ambient Temperature (°C) Min : 25.0 Max : 44.0 Avg : 34.6

4. Relative Humidity (%) Min : 31.0 Max : 70.0 Avg : 48.1

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 87: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 26 METEOROLOGICAL DATA

Date : 26.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 3.5 NW 34.0 62 3 0

2 02.00 5.1 NW 32.0 64 3 0

3 03.00 4.6 NW 29.0 64 3 0

4 04.00 3.2 NW 28.0 77 3 0

5 05.00 6.9 NW 28.0 77 3 0

6 06.00 4.2 WNW 38.0 70 3 0

7 07.00 4.6 WNW 38.5 64 2 0

8 08.00 7.2 NNE 29.0 51 2 0

9 09.00 8.5 NNW 32.0 49 1 0

10 10.00 9.2 NW 34.0 46 1 0

11 11.00 10.5 NNE 34.5 43 1 0

12 12.00 8.0 NNW 36.0 43 1 0

13 13.00 10.2 N 38.0 40 1 0

14 14.00 14.0 NW 38.5 36 0 0

15 15.00 12.4 NNW 40.0 34 0 0

16 16.00 6.7 NW 38.5 36 2 0

17 17.00 8.1 WNW 38.0 40 3 0

18 18.00 5.3 WNW 36.0 43 2 0

19 19.00 4.8 WSW 34.5 43 2 0

20 20.00 3.4 WSW 34.0 46 2 0

21 21.00 2.8 SW 32.5 46 2 0

22 22.00 3.0 SW 32.0 49 3 0

23 23.00 3.4 SW 30.5 50 3 0

24 24.00 4.2 SW 30.0 53 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.8 Max : 14.0 Avg : 6.4

3. Ambient Temperature (°C) Min : 28.0 Max : 40.0 Avg : 34.0

4. Relative Humidity (%) Min : 34.0 Max : 77.0 Avg : 51.1

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 88: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 27 METEOROLOGICAL DATA

Date : 27.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 3.2 NW 29.5 58 3 0

2 02.00 2.4 NW 29.0 61 3 0

3 03.00 2.0 WNW 28.5 64 3 0

4 04.00 1.5 NW 27.0 66 3 0

5 05.00 6.9 NW 26.5 76 3 0

6 06.00 3.2 NNW 28.0 67 3 0

7 07.00 1.5 WNW 29.0 58 3 0

8 08.00 2.0 N 30.0 53 3 0

9 09.00 1.8 NW 32.0 49 2 0

10 10.00 3.9 WNW 34.0 41 1 0

11 11.00 5.0 N 36.0 38 4 0

12 12.00 10.2 NW 38.0 36 2 5

13 13.00 11.2 NW 40.0 34 2 7

14 14.00 13.1 WNW 42.0 32 2 4

15 15.00 10.2 N 44.0 31 0 6

16 16.00 8.5 NW 42.5 32 0 0

17 17.00 6.2 WNW 42.0 36 2 0

18 18.00 4.9 NW 40.5 38 2 0

19 19.00 5.2 NW 40.0 42 2 0

20 20.00 4.5 NW 38.5 45 2 0

21 21.00 3.0 W 38.0 47 3 0

22 22.00 2.5 W 36.5 48 3 0

23 23.00 4.5 NW 36.0 50 3 0

24 24.00 3.6 NNW 34.5 51 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.5 Max : 13.1 Avg : 5.0

3. Ambient Temperature (°C) Min : 26.5 Max : 44.0 Avg : 35.1

4. Relative Humidity (%) Min : 31.0 Max : 76.0 Avg : 48.0

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 89: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 28 METEOROLOGICAL DATA

Date : 28.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 3.4 NW 34.0 62 3 0

2 02.00 4.2 WNW 32.0 64 3 0

3 03.00 3.6 WNW 29.0 64 3 0

4 04.00 4.5 SW 28.0 77 3 0

5 05.00 6.9 SW 28.0 77 3 0

6 06.00 2.8 WSW 29.0 58 3 0

7 07.00 4.2 WSW 30.0 56 2 0

8 08.00 5.0 SW 32.0 55 2 0

9 09.00 5.6 WSW 34.0 51 1 0

10 10.00 6.2 SW 36.0 50 1 0

11 11.00 8.5 SW 38.0 45 1 0

12 12.00 6.7 SW 40.0 42 1 0

13 13.00 7.6 SSW 42.0 40 0 0

14 14.00 10.2 S 44.0 34 0 0

15 15.00 12.5 SSW 46.0 29 0 0

16 16.00 13.7 SSW 44.0 31 0 0

17 17.00 11.5 SSW 42.5 32 1 0

18 18.00 8.6 SW 42.0 36 1 0

19 19.00 5.2 WSW 40.5 38 1 0

20 20.00 4.8 SW 40.0 42 1 0

21 21.00 4.0 SSW 38.0 45 2 0

22 22.00 3.5 WSW 36.0 48 2 0

23 23.00 3.1 SW 34.5 48 2 0

24 24.00 2.6 SSW 34.0 51 2 0

OBSERVATIONS

1. Predominant WindDirection (from) : SW 2. Wind Velocity (Kmph) Min : 2.6 Max : 13.7 Avg : 6.2

3. Ambient Temperature (°C) Min : 28.0 Max : 46.0 Avg : 36.4

4. Relative Humidity (%) Min : 29.0 Max : 77.0 Avg : 49.0

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 90: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 29 METEOROLOGICAL DATA

Date : 29.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 3.8 NW 32.0 52 3 0

2 02.00 4.0 WSW 30.0 59 3 0

3 03.00 4.5 W 29.0 61 3 0

4 04.00 5.3 W 27.0 73 3 0

5 05.00 6.9 W 27.0 73 3 0

6 06.00 5.0 WSW 29.0 71 3 0

7 07.00 6.2 WSW 29.5 64 3 0

8 08.00 7.5 SW 30.0 59 2 0

9 09.00 8.2 WSW 30.5 47 2 0

10 10.00 10.5 WSW 32.0 44 1 0

11 11.00 12.6 W 34.0 41 1 0

12 12.00 9.5 W 36.0 38 1 0

13 13.00 8.7 WSW 38.0 36 0 0

14 14.00 13.0 WSW 40.0 34 0 0

15 15.00 14.5 SW 42.0 32 0 0

16 16.00 11.3 SW 40.0 34 0 0

17 17.00 10.5 SW 38.5 36 1 0

18 18.00 9.3 SSW 38.0 45 1 0

19 19.00 4.6 SSW 36.5 50 2 0

20 20.00 3.9 SSW 36.0 53 2 0

21 21.00 4.0 SW 34.5 54 2 0

22 22.00 5.3 SW 34.0 56 2 0

23 23.00 6.9 WSW 32.5 64 3 0

24 24.00 7.4 W 32.0 67 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : WSW 2. Wind Velocity (Kmph) Min : 3.8 Max : 14.5 Avg : 7.6

3. Ambient Temperature (°C) Min : 27.0 Max : 42.0 Avg : 33.7

4. Relative Humidity (%) Min : 32.0 Max : 73.0 Avg : 51.8

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 91: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 30 METEOROLOGICAL DATA

Date : 30.04.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 1.9 NW 30.5 68 3 0

2 02.00 2.9 W 30.0 72 3 0

3 03.00 4.0 W 28.0 77 3 0

4 04.00 4.5 W 27.0 77 3 0

5 05.00 6.9 WSW 27.0 77 3 0

6 06.00 3.6 WSW 30.0 72 3 0

7 07.00 4.4 WSW 32.0 70 2 0

8 08.00 6.1 WSW 32.5 67 2 0

9 09.00 9.4 SW 34.0 56 1 0

10 10.00 7.9 SW 38.0 47 1 0

11 11.00 11.7 SW 38.5 45 1 0

12 12.00 10.9 SSW 40.0 38 1 0

13 13.00 15.7 SSW 40.5 34 0 0

14 14.00 8.5 SSW 42.0 32 0 0

15 15.00 4.8 SW 42.5 32 0 0

16 16.00 5.3 WSW 42.0 36 0 0

17 17.00 3.0 W 40.5 38 1 0

18 18.00 2.6 W 40.0 42 1 0

19 19.00 4.6 WNW 38.5 45 1 0

20 20.00 7.1 WNW 38.0 50 2 0

21 21.00 4.3 WNW 36.5 53 2 0

22 22.00 8.7 WNW 36.0 55 2 0

23 23.00 4.0 W 34.5 56 3 0

24 24.00 3.4 W 34.0 59 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : W 2. Wind Velocity (Kmph) Min : 1.9 Max : 15.7 Avg : 6.1

3. Ambient Temperature (°C) Min : 27.0 Max : 42.5 Avg : 35.5

4. Relative Humidity (%) Min : 32.0 Max : 77.0 Avg : 54.1

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 92: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 31 METEOROLOGICAL DATA

Date : 01.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 5.7 WNW 32.5 61 3 0

2 02.00 6.0 SSW 32.0 64 3 0

3 03.00 5.4 SW 30.0 68 3 0

4 04.00 4.2 SW 29.5 71 3 0

5 05.00 3.6 SW 29.0 74 3 0

6 06.00 3.6 SW 29.0 72 3 0

7 07.00 6.1 WSW 30.5 65 2 0

8 08.00 10.3 WSW 32.0 61 2 0

9 09.00 9.5 SW 34.0 56 2 0

10 10.00 12.6 SW 36.0 48 1 0

11 11.00 12.6 SSW 36.5 45 1 0

12 12.00 13.8 SSW 38.0 45 1 0

13 13.00 11.3 SSW 38.5 40 0 0

14 14.00 8.0 SSW 40.0 34 0 0

15 15.00 3.4 SW 42.5 32 0 0

16 16.00 4.8 SW 42.0 32 1 0

17 17.00 6.6 SW 42.0 32 1 0

18 18.00 6.9 WSW 40.0 38 2 0

19 19.00 7.0 WSW 38.0 40 2 0

20 20.00 3.2 WSW 36.5 53 2 0

21 21.00 2.3 WSW 34.5 54 2 0

22 22.00 1.6 WSW 34.0 56 3 0

23 23.00 1.9 SW 32.5 63 3 0

24 24.00 1.5 SW 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): SW 2. Wind Velocity (Kmph) : Min 1.5 Max : 13.8 Avg : 6.3

3. Ambient Temperature (°C) : Min : 29.0 Max : 42.5 Avg : 35.1

4. Relative Humidity (%) : Min : 32.0 Max : 74.0 Avg : 52.9

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 93: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 32 METEOROLOGICAL DATA

Date : 02.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity (%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 13.0 WNW 30.5 68 3 0

2 02.00 10.6 WSW 30.0 72 3 0

3 03.00 9.1 WSW 29.5 74 3 0

4 04.00 9.3 W 29.0 78 3 0

5 05.00 8.6 W 29.0 72 3 0

6 06.00 4.7 W 30.0 61 2 0

7 07.00 4.9 W 32.0 56 2 0

8 08.00 6.2 WSW 34.0 53 2 0

9 09.00 9.6 WSW 36.0 45 1 0

10 10.00 5.9 SW 38.0 40 1 0

11 11.00 11.5 SW 40.0 36 1 0

12 12.00 12.6 SW 42.0 31 1 0

13 13.00 14.0 SSW 42.5 27 0 0

14 14.00 13.5 SSW 44.0 31 0 0

15 15.00 10.7 S 44.5 32 0 0

16 16.00 9.8 S 44.0 38 1 0

17 17.00 7.6 S 42.0 40 1 0

18 18.00 5.3 WSW 40.0 53 2 0

19 19.00 4.4 WSW 38.0 54 2 0

20 20.00 4.2 WSW 36.0 56 3 0

21 21.00 4.0 SW 34.5 6 3 0

22 22.00 5.5 SSW 34.0 67 3 0

23 23.00 6.9 SSW 32.5 63 3 0

24 24.00 7.4 WSW 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): WSW 2. Wind Velocity (Kmph) : Min 4.0 Max : 14.0 Avg : 8.3

3. Ambient Temperature (°C) : Min : 29.0 Max : 44.5 Avg : 36.0

4. Relative Humidity (%) : Min : 6.0 Max : 78.0 Avg : 50.8

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 94: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 33 METEOROLOGICAL DATA

Date : 03.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C) Relative

Humidity (%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 9.0 WNW 30.5 68 3 0

2 02.00 11.7 WNW 30.0 72 3 0

3 03.00 12.0 WNW 29.5 74 3 0

4 04.00 10.0 NW 29.5 74 3 0

5 05.00 9.5 WNW 29.5 72 3 0

6 06.00 3.0 NW 31.0 65 2 0

7 07.00 3.7 NW 34.0 56 2 0

8 08.00 4.8 WNW 36.0 53 2 0

9 09.00 7.9 WNW 38.0 45 1 0

10 10.00 10.3 W 38.5 40 1 0

11 11.00 11.2 W 40.0 38 1 0

12 12.00 12.6 WSW 40.5 36 1 0

13 13.00 14.5 WSW 42.5 32 0 0

14 14.00 12.0 W 44.5 31 0 0

15 15.00 9.6 WSW 46.0 29 0 0

16 16.00 8.3 W 44.0 31 1 0

17 17.00 7.9 WNW 42.0 32 1 0

18 18.00 6.3 WNW 40.5 40 2 0

19 19.00 5.0 NW 38.0 53 2 0

20 20.00 4.5 NW 36.0 54 3 0

21 21.00 6.4 WNW 34.5 56 3 0

22 22.00 8.7 WNW 34.0 59 3 0

23 23.00 7.0 W 32.5 63 3 0

24 24.00 4.3 WSW 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): WNW 2. Wind Velocity (Kmph) : Min : 3.0 Max : 14.5 Avg : 8.3

3. Ambient Temperature (°C) : Min : 29.5 Max : 46.0 Avg : 36.4

4. Relative Humidity (%) : Min : 29.0 Max : 74.0 Avg : 51.6

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 95: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 34 METEOROLOGICAL DATA

Date : 04.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C) Relative

Humidity (%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 5.7 WNW 30.5 68 3 0

2 02.00 6.0 WSW 30.0 72 3 0

3 03.00 5.4 WSW 29.5 70 3 0

4 04.00 4.2 WNW 29.0 68 3 0

5 05.00 3.6 NW 29.0 66 3 0

6 06.00 3.4 NNW 30.0 65 3 0

7 07.00 3.2 WNW 32.0 61 2 0

8 08.00 4.0 NNW 34.5 56 2 0

9 09.00 6.1 NW 36.0 53 2 0

10 10.00 8.3 NW 38.0 45 1 0

11 11.00 6.4 WNW 40.0 42 1 0

12 12.00 11.1 NW 42.5 40 1 0

13 13.00 13.2 NW 44.0 36 0 0

14 14.00 14.0 NW 44.5 31 0 0

15 15.00 11.4 WNW 40.0 27 0 0

16 16.00 9.3 NW 38.5 34 1 0

17 17.00 8.0 NNW 38.0 36 1 0

18 18.00 11.4 WNW 36.5 45 2 0

19 19.00 13.0 WNW 34.5 50 2 0

20 20.00 1.6 WSW 34.0 53 2 0

21 21.00 2.1 WSW 33.5 54 2 0

22 22.00 4.1 SW 33.0 56 3 0

23 23.00 7.0 SW 32.0 63 3 0

24 24.00 6.4 SSW 30.5 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): WNW 2. Wind Velocity (Kmph) : Min 1.6 Max : 14.0 Avg : 7.0

3. Ambient Temperature (°C) : Min : 29.0 Max : 44.5 Avg : 35.0

4. Relative Humidity (%) : Min : 27.0 Max : 72.0 Avg : 52.3

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 96: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 35 METEOROLOGICAL DATA

Date : 05.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 5.0 WNW 30.5 68 3 0

2 02.00 4.4 SW 30.0 72 3 0

3 03.00 3.6 SW 29.5 74 3 0

4 04.00 4.0 SSW 29.0 76 3 0

5 05.00 4.9 NW 29.0 78 3 0

6 06.00 3.0 NW 30.0 74 2 0

7 07.00 2.3 NW 30.5 65 2 0

8 08.00 1.5 NE 32.0 61 2 0

9 09.00 1.7 ENE 34.0 56 1 0

10 10.00 5.0 NE 36.0 48 1 0

11 11.00 8.9 NE 36.5 45 1 0

12 12.00 12.3 NW 38.0 43 1 0

13 13.00 9.4 NW 40.0 40 0 0

14 14.00 12.1 NNW 42.0 34 0 0

15 15.00 11.4 WNW 42.5 26 0 0

16 16.00 8.4 NNW 40.0 33 1 0

17 17.00 5.1 NW 38.5 40 1 0

18 18.00 4.0 WNW 38.0 46 2 0

19 19.00 6.4 NW 36.5 49 2 0

20 20.00 5.5 WNW 36.0 53 3 0

21 21.00 5.9 NW 34.5 54 3 0

22 22.00 4.1 NW 34.0 56 3 0

23 23.00 3.4 NW 32.5 63 3 0

24 24.00 5.6 NNW 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): NW 2. Wind Velocity (Kmph) : Min : 1.5 Max : 12.3 Avg : 5.7

3. Ambient Temperature (°C) : Min : 29.0 Max : 42.5 Avg : 34.6

4. Relative Humidity (%) : Min : 26.0 Max : 78.0 Avg : 55.0

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 97: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 36 METEOROLOGICAL DATA

Date : 06.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 5.9 WNW 30.5 65 3 0

2 02.00 7.8 NW 30.0 69 3 0

3 03.00 4.5 NNW 29.5 72 3 0

4 04.00 3.6 NNW 29.0 74 3 0

5 05.00 2.0 NW 29.0 76 3 0

6 06.00 2.3 NW 30.5 72 3 0

7 07.00 6.4 NW 32.0 70 2 0

8 08.00 9.7 NW 32.5 67 2 0

9 09.00 16.6 NE 34.0 56 1 0

10 10.00 14.3 NE 36.0 47 1 0

11 11.00 9.3 NE 38.5 45 1 0

12 12.00 7.6 SE 40.0 38 1 0

13 13.00 6.0 SE 40.5 34 0 0

14 14.00 5.3 SE 42.5 32 0 0

15 15.00 5.7 NNW 42.0 32 0 0

16 16.00 4.3 NNW 41.0 36 1 0

17 17.00 7.0 NW 40.0 38 1 0

18 18.00 7.4 NW 38.0 38 2 0

19 19.00 8.3 NW 36.0 40 2 0

20 20.00 5.1 WNW 34.5 53 2 0

21 21.00 5.7 WNW 34.0 54 2 0

22 22.00 3.8 NW 32.5 56 3 0

23 23.00 2.1 NW 32.0 63 3 0

24 24.00 1.7 NW 30.5 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): NW 2. Wind Velocity (Kmph) : Min : 1.7 Max : 16.6 Avg : 6.4

3. Ambient Temperature (°C) : Min : 29.0 Max : 42.5 Avg : 34.8

4. Relative Humidity (%) : Min : 32.0 Max : 76.0 Avg : 53.8

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 98: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 37 METEOROLOGICAL DATA

Date : 07.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 1.3 WNW 30.5 65 3 0

2 02.00 3.0 NW 30.0 69 3 0

3 03.00 2.5 NNW 29.5 72 3 0

4 04.00 2.3 NNW 29.0 74 3 0

5 05.00 2.8 NNE 29.0 76 3 0

6 06.00 3.0 N 30.5 72 3 0

7 07.00 3.6 NW 32.5 70 2 0

8 08.00 4.7 NNW 34.5 67 2 0

9 09.00 6.9 NW 36.0 56 2 0

10 10.00 8.1 NW 38.5 47 1 0

11 11.00 4.9 NNW 40.0 45 1 0

12 12.00 7.3 NNW 42.0 38 1 0

13 13.00 7.1 NW 42.5 34 0 0

14 14.00 9.3 NE 44.0 32 0 0

15 15.00 13.0 NNW 44.5 27 0 0

16 16.00 12.3 NNW 44.0 32 1 0

17 17.00 10.1 NNW 42.0 38 1 0

18 18.00 3.4 WNW 40.0 38 2 0

19 19.00 6.0 WNW 38.0 40 2 0

20 20.00 4.3 N 36.0 53 2 0

21 21.00 5.0 N 34.5 54 2 0

22 22.00 6.4 NNE 34.0 56 3 0

23 23.00 7.0 NNE 32.5 63 3 0

24 24.00 8.1 N 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): NW 2. Wind Velocity (Kmph) : Min 1.3 Max : 13.0 Avg : 5.9

3. Ambient Temperature (°C) : Min : 29.0 Max : 44.5 Avg : 36.1

4. Relative Humidity (%) : Min : 27.0 Max : 76.0 Avg : 53.5

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 99: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 38 METEOROLOGICAL DATA

Date : 08.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C) Relative

Humidity (%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 12.0 WNW 30.5 68 3 0

2 02.00 10.6 N 30.5 72 3 0

3 03.00 9.3 N 29.5 74 3 0

4 04.00 5.8 N 29.0 75 3 0

5 05.00 6.0 NW 29.0 76 3 0

6 06.00 3.3 N 30.0 65 2 0

7 07.00 5.9 NNW 32.5 61 2 0

8 08.00 11.2 N 34.5 56 2 0

9 09.00 8.3 NW 36.0 53 1 0

10 10.00 5.1 NNW 38.5 45 1 0

11 11.00 4.2 N 40.0 42 1 0

12 12.00 1.7 N 42.0 40 1 0

13 13.00 2.0 NW 42.5 36 0 0

14 14.00 2.6 N 44.0 31 0 0

15 15.00 2.4 NNW 44.5 27 0 0

16 16.00 1.9 NNW 44.0 31 1 0

17 17.00 3.0 NNW 42.0 32 1 0

18 18.00 3.4 NW 40.0 38 2 0

19 19.00 4.0 NW 38.0 40 2 0

20 20.00 3.8 WNW 36.0 53 3 0

21 21.00 5.7 NNW 34.5 54 3 0

22 22.00 2.4 NW 32.5 56 3 0

23 23.00 3.5 NW 32.0 63 3 0

24 24.00 1.9 N 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): N 2. Wind Velocity (Kmph) : Min 1.7 Max : 12.0 Avg : 5.0

3. Ambient Temperature (°C) : Min : 29.0 Max : 44.5 Avg : 36.0

4. Relative Humidity (%) : Min : 27.0 Max : 76.0 Avg : 52.2

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 100: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 39 METEOROLOGICAL DATA

Date : 09.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity (%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 2.5 WNW 30.5 68 3 0

2 02.00 3.1 NW 30.0 72 3 0

3 03.00 3.3 N 29.5 74 3 0

4 04.00 2.8 WNW 29.0 75 3 0

5 05.00 2.1 NW 29.0 76 3 0

6 06.00 4.7 NW 30.5 65 3 0

7 07.00 4.9 ENE 34.0 62 2 0

8 08.00 6.2 NE 36.5 53 2 0

9 09.00 9.6 NE 37.0 45 2 0

10 10.00 8.9 WNW 38.0 40 1 0

11 11.00 11.4 NW 40.0 38 1 0

12 12.00 5.9 NNW 40.5 36 1 0

13 13.00 4.7 NW 42.0 32 0 0

14 14.00 5.9 ENE 44.0 31 0 0

15 15.00 4.1 SSE 46.0 29 0 0

16 16.00 7.6 NE 44.0 31 1 0

17 17.00 5.9 NNW 42.5 32 1 0

18 18.00 4.4 NW 40.0 38 2 0

19 19.00 4.2 NW 38.0 40 2 0

20 20.00 4.0 NE 36.0 53 2 0

21 21.00 5.5 NE 34.5 54 2 0

22 22.00 6.9 NW 34.0 56 3 0

23 23.00 7.4 ENE 32.5 63 3 0

24 24.00 3.5 NE 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): NW 2. Wind Velocity (Kmph) : Min : 2.1 Max : 11.4 Avg : 5.4

3. Ambient Temperature (°C) : Min : 29.0 Max : 46.0 Avg : 36.3

4. Relative Humidity (%) : Min : 29.0 Max : 76.0 Avg : 51.2

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 101: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 40 METEOROLOGICAL DATA

Date : 10.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 11.7 WNW 32.5 68 3 0

2 02.00 11.5 NW 32.0 72 3 0

3 03.00 10.2 NW 30.0 74 3 0

4 04.00 9.5 NW 29.5 78 3 0

5 05.00 7.1 NW 29.0 72 3 0

6 06.00 3.0 NNW 30.0 72 2 0

7 07.00 3.7 NW 32.5 61 2 0

8 08.00 4.9 W 34.5 56 2 0

9 09.00 7.9 NNE 36.0 53 1 0

10 10.00 10.3 NNE 38.5 45 1 0

11 11.00 7.3 NW 40.5 42 1 0

12 12.00 6.1 WNW 42.0 40 1 0

13 13.00 7.0 NW 42.5 36 0 0

14 14.00 3.4 NNE 44.0 31 0 0

15 15.00 1.3 NE 44.5 27 0 0

16 16.00 3.0 NE 44.0 31 1 0

17 17.00 4.1 ENE 42.5 32 1 0

18 18.00 6.3 E 40.0 38 2 0

19 19.00 5.0 NE 38.0 40 2 0

20 20.00 4.5 SSE 36.0 53 3 0

21 21.00 6.4 SSE 34.5 54 3 0

22 22.00 8.1 SE 34.0 56 3 0

23 23.00 7.0 ESE 32.5 63 3 0

24 24.00 4.3 NE 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): NW 2. Wind Velocity (Kmph) : Min 1.3 Max : 11.7 Avg : 6.4

3. Ambient Temperature (°C) : Min : 29.0 Max : 44.5 Avg : 36.3

4. Relative Humidity (%) : Min : 27.0 Max : 78.0 Avg : 52.5

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 102: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 41 METEOROLOGICAL DATA

Date : 11.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 5.7 WNW 32.5 68 3 0

2 02.00 6.0 NW 32.0 72 3 0

3 03.00 5.4 NNW 30.0 70 3 0

4 04.00 4.2 NW 31.0 68 3 0

5 05.00 3.6 NNE 31.5 66 3 0

6 06.00 4.8 ENE 32.0 67 3 0

7 07.00 9.6 NE 34.0 59 2 0

8 08.00 13.6 NW 34.5 53 2 0

9 09.00 15.6 NW 36.0 48 1 0

10 10.00 16.3 NW 36.5 46 1 0

11 11.00 17.0 NW 38.0 44 1 0

12 12.00 15.2 NW 40.0 42 1 0

13 13.00 14.4 NNW 42.0 36 0 0

14 14.00 14.0 NNE 44.5 31 0 0

15 15.00 11.7 NNE 46.0 26 0 0

16 16.00 8.5 E 44.0 31 1 0

17 17.00 11.4 ENE 42.0 32 1 0

18 18.00 12.4 NNE 40.0 38 2 0

19 19.00 10.0 NNW 38.0 40 2 0

20 20.00 7.4 NNW 36.0 43 2 0

21 21.00 6.6 NW 34.5 46 2 0

22 22.00 4.3 NE 34.0 51 3 0

23 23.00 5.4 NE 32.5 63 3 0

24 24.00 6.1 NE 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): NW 2. Wind Velocity (Kmph) : Min 3.6 Max : 17.0 Avg : 9.6

3. Ambient Temperature (°C) : Min : 30.0 Max : 46.0 Avg : 36.4

4. Relative Humidity (%) : Min : 26.0 Max : 72.0 Avg : 50.2

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 103: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 42 METEOROLOGICAL DATA

Date : 12.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C) Relative

Humidity (%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 5.0 WNW 30.0 64 3 0

2 02.00 5.7 WNW 29.0 66 3 0

3 03.00 6.4 N 28.0 68 3 0

4 04.00 7.0 WNW 27.0 72 3 0

5 05.00 6.9 WNW 27.0 73 3 0

6 06.00 4.7 NNW 30.0 67 3 0

7 07.00 6.8 NW 34.0 58 2 0

8 08.00 10.6 WNW 36.0 53 2 0

9 09.00 9.9 NW 38.5 45 2 0

10 10.00 12.4 NNW 40.0 40 1 0

11 11.00 7.9 NNW 41.0 38 1 0

12 12.00 11.3 WNW 42.5 36 1 0

13 13.00 15.6 WNW 44.0 32 0 0

14 14.00 11.4 NW 46.5 31 0 0

15 15.00 8.5 NNW 44.0 29 0 0

16 16.00 4.8 NW 42.5 31 1 0

17 17.00 6.1 NNW 40.0 32 1 0

18 18.00 4.2 NNW 38.0 38 2 0

19 19.00 4.0 WNW 36.0 40 2 0

20 20.00 6.2 WNW 34.5 53 2 0

21 21.00 12.5 NNW 34.0 54 2 0

22 22.00 8.1 NNW 32.5 56 3 0

23 23.00 6.8 N 32.0 63 3 0

24 24.00 4.1 N 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): NNW 2. Wind Velocity (Kmph) : Min 4.0 Max : 15.6 Avg : 7.8

3. Ambient Temperature (°C) : Min : 27.0 Max : 46.5 Avg : 35.8

4. Relative Humidity (%) : Min : 29.0 Max : 73.0 Avg : 50.2

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 104: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 43 METEOROLOGICAL DATA

Date : 13.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 9.6 WNW 30.5 66 3 0

2 02.00 7.3 N 30.0 72 3 0

3 03.00 5.6 N 29.5 74 3 0

4 04.00 5.0 N 29.0 76 3 0

5 05.00 5.3 NW 29.0 76 3 0

6 06.00 4.0 N 30.0 71 2 0

7 07.00 3.4 NNW 32.0 64 2 0

8 08.00 4.7 N 34.0 59 2 0

9 09.00 7.0 NW 36.5 53 1 0

10 10.00 16.9 NNW 38.5 45 1 0

11 11.00 17.0 N 40.0 42 1 0

12 12.00 14.9 N 42.0 40 1 0

13 13.00 15.6 NW 42.5 36 0 0

14 14.00 6.1 N 44.0 31 0 0

15 15.00 4.0 NNW 44.5 32 0 0

16 16.00 5.8 NNW 44.0 34 1 0

17 17.00 6.2 NNW 42.0 38 1 0

18 18.00 6.7 NW 42.0 40 2 0

19 19.00 3.2 NW 40.0 53 2 0

20 20.00 2.6 WNW 38.5 54 3 0

21 21.00 1.8 NNW 36.5 56 3 0

22 22.00 1.4 NW 34.5 60 3 0

23 23.00 2.0 NW 33.0 63 3 0

24 24.00 1.5 N 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): N 2. Wind Velocity (Kmph) : Min 1.4 Max : 17.0 Avg : 6.6

3. Ambient Temperature (°C) : Min : 29.0 Max : 44.5 Avg : 36.4

4. Relative Humidity (%) : Min : 31.0 Max : 76.0 Avg : 54.2

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 105: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 44 METEOROLOGICAL DATA

Date : 14.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 8.6 WNW 32.0 66 3 0

2 02.00 10.5 WNW 31.0 68 3 0

3 03.00 9.2 WNW 30.0 70 3 0

4 04.00 6.2 W 29.0 72 3 0

5 05.00 4.3 WNW 29.0 68 3 0

6 06.00 4.2 WNW 30.5 65 3 0

7 07.00 5.0 W 32.5 61 2 0

8 08.00 6.3 WNW 34.5 56 2 0

9 09.00 5.1 NW 36.5 53 1 0

10 10.00 4.8 NW 38.0 47 1 0

11 11.00 3.5 NNW 40.0 43 1 0

12 12.00 4.9 NNW 41.0 38 1 0

13 13.00 6.3 NW 42.5 36 0 0

14 14.00 10.5 WNW 44.0 32 0 0

15 15.00 12.3 WNW 46.0 29 0 0

16 16.00 11.5 WNW 44.0 31 1 0

17 17.00 9.3 W 42.5 35 1 0

18 18.00 8..7 W 39.0 39 2 0

19 19.00 10.2 WNW 37.0 47 2 0

20 20.00 6.4 WNW 35.0 51 2 0

21 21.00 5.2 NW 34.0 56 2 0

22 22.00 4.0 NNW 33.0 62 3 0

23 23.00 3.5 NNW 32.5 63 3 0

24 24.00 5.9 NW 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): WNW 2. Wind Velocity (Kmph) : Min 3.5 Max : 12.3 Avg : 6.9

3. Ambient Temperature (°C) : Min : 29.0 Max : 46.0 Avg : 36.1

4. Relative Humidity (%) : Min : 29.0 Max : 72.0 Avg : 52.2

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 106: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 45 METEOROLOGICAL DATA

Date : 15.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 4.6 WNW 30.5 68 3 0

2 02.00 3.5 WSW 30.0 72 3 0

3 03.00 2.8 WSW 29.5 70 3 0

4 04.00 3.5 SW 29.5 68 3 0

5 05.00 3.4 WSW 29.0 66 3 0

6 06.00 5.2 WSW 30.5 63 2 0

7 07.00 6.5 WSW 32.5 61 2 0

8 08.00 7.0 SW 34.5 56 2 0

9 09.00 8.5 WSW 36.0 53 1 0

10 10.00 9.2 WSW 38.5 45 1 0

11 11.00 10.5 SW 40.0 42 1 0

12 12.00 13.4 WSW 42.5 40 1 0

13 13.00 15.0 WSW 44.0 36 0 0

14 14.00 13.2 SW 42.0 31 0 0

15 15.00 14.5 SSW 40.0 27 0 0

16 16.00 9.3 SSW 39.0 34 1 0

17 17.00 8.5 SW 38.0 45 1 0

18 18.00 6.4 WSW 37.0 48 2 0

19 19.00 3.8 WSW 36.0 50 2 0

20 20.00 4.0 SW 35.5 53 3 0

21 21.00 4.5 WSW 34.0 54 3 0

22 22.00 6.2 WSW 33.0 58 3 0

23 23.00 5.1 SW 32.5 63 3 0

24 24.00 5.5 SSW 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): WSW 2. Wind Velocity (Kmph) : Min 2.8 Max : 15.0 Avg : 7.3

3. Ambient Temperature (°C) : Min : 29.0 Max : 44.0 Avg : 35.3

4. Relative Humidity (%) : Min : 27.0 Max : 72.0 Avg : 52.8

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 107: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 46 METEOROLOGICAL DATA

Date : 16.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 4.5 WNW 30.5 64 3 0

2 02.00 4.0 S 30.0 66 3 0

3 03.00 3.3 SSW 29.5 68 3 0

4 04.00 2.9 SSW 29.0 72 3 0

5 05.00 2.5 SSW 29.0 73 3 0

6 06.00 4.2 S 30.0 72 3 0

7 07.00 5.0 SSW 30.5 65 2 0

8 08.00 6.8 SSW 32.0 61 2 0

9 09.00 7.2 S 34.5 56 1 0

10 10.00 6.9 SSW 36.0 48 1 0

11 11.00 10.2 SSW 37.0 45 1 0

12 12.00 13.5 SW 38.0 40 1 0

13 13.00 18.6 SW 39.0 34 0 0

14 14.00 12.5 SSW 40.0 31 0 0

15 15.00 11.0 SSW 42.5 33 0 0

16 16.00 5.9 S 41.0 36 1 0

17 17.00 6.4 SSW 40.0 38 1 0

18 18.00 5.0 SW 39.0 42 2 0

19 19.00 4.8 SW 38.0 45 2 0

20 20.00 3.5 SSW 36.5 50 2 0

21 21.00 4.2 SSW 36.0 53 2 0

22 22.00 3.7 SW 35.5 55 3 0

23 23.00 4.0 SW 35.0 63 3 0

24 24.00 5.1 S 34.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): SSW 2. Wind Velocity (Kmph) : Min 2.5 Max : 18.6 Avg : 6.5

3. Ambient Temperature (°C) : Min : 29.0 Max : 42.5 Avg : 35.1

4. Relative Humidity (%) : Min : 31.0 Max : 73.0 Avg : 53.1

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 750 7. Sky Appearance : Clear

Page 108: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 47 METEOROLOGICAL DATA

Date : 17.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 3.2 WNW 32.5 64 3 0

2 02.00 2.4 SW 32.0 66 3 0

3 03.00 2.0 SSW 31.0 68 3 0

4 04.00 1.5 SW 30.0 72 3 0

5 05.00 1.2 SW 29.0 73 3 0

6 06.00 3.2 SSW 30.0 72 3 0

7 07.00 1.5 S 32.0 70 2 0

8 08.00 2.0 S 33.0 67 2 0

9 09.00 1.8 SSW 34.5 56 1 0

10 10.00 3.9 SW 36.0 47 1 0

11 11.00 5.0 SW 38.0 45 1 0

12 12.00 10.2 SSW 40.0 38 1 0

13 13.00 11.2 SW 41.0 34 0 0

14 14.00 13.1 SW 42.5 32 0 0

15 15.00 10.2 SSW 44.0 27 0 0

16 16.00 8.5 S 43.0 31 1 0

17 17.00 6.2 SSW 42.0 32 1 0

18 18.00 4.9 SSW 40.0 38 2 0

19 19.00 5.2 SW 39.5 40 2 0

20 20.00 4.5 SW 38.0 53 2 0

21 21.00 3.0 SSW 36.0 54 2 0

22 22.00 2.5 SW 34.0 56 3 0

23 23.00 4.5 SSW 32.5 63 3 0

24 24.00 3.6 SSW 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): SW

2. Wind Velocity (Kmph) : Min 1.2 Max : 13.1 Avg : 4.8

3. Ambient Temperature (°C) : Min : 29.0 Max : 44.0 Avg : 35.9

4. Relative Humidity (%) : Min : 27.0 Max : 73.0 Avg : 52.6

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 750

7. Sky Appearance : Clear

Page 109: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 48 METEOROLOGICAL DATA

Date : 18.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 4.1 WNW 30.5 66 3 0

2 02.00 2.0 SW 30.0 72 3 0

3 03.00 2.8 SSW 29.5 70 3 0

4 04.00 3.1 SW 29.5 68 3 0

5 05.00 2.6 SW 31.0 66 3 0

6 06.00 5.6 SSW 32.5 65 2 0

7 07.00 6.3 SW 34.0 56 2 0

8 08.00 9.7 SW 36.5 53 2 0

9 09.00 16.0 SSW 38.0 45 1 0

10 10.00 14.3 SSW 40.0 40 1 0

11 11.00 9.3 SW 40.5 38 1 0

12 12.00 7.6 SW 42.0 36 1 0

13 13.00 17.2 WSW 44.0 32 0 0

14 14.00 12.0 WSW 46.0 31 0 0

15 15.00 8.4 SW 42.0 29 0 0

16 16.00 5.6 SW 40.5 36 1 0

17 17.00 4.0 WSW 40.0 38 1 0

18 18.00 4.4 SW 38.5 42 2 0

19 19.00 6.2 SW 37.0 44 2 0

20 20.00 12.6 SSW 36.0 50 3 0

21 21.00 11.0 SW 35.5 53 3 0

22 22.00 8.9 SW 35.0 55 3 0

23 23.00 6.8 SSW 34.0 63 3 0

24 24.00 5.9 SW 33.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): SW

2. Wind Velocity (Kmph) : Min 2.0 Max : 17.2 Avg : 7.8

3. Ambient Temperature (°C) : Min : 29.5 Max : 46.0 Avg : 36.5

4. Relative Humidity (%) : Min : 29.0 Max : 72.0 Avg : 50.5

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 750

7. Sky Appearance : Clear

Page 110: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 49 METEOROLOGICAL DATA

Date : 19.05.13

Location : Corezone

Sl.No

Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C) Relative

Humidity (%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 4.1 WNW 32.5 67 3 0

2 02.00 3.0 WSW 32.0 72 3 0

3 03.00 2.8 W 30.0 70 3 0

4 04.00 3.1 W 29.5 68 3 0

5 05.00 2.6 WNW 29.0 66 3 0

6 06.00 5.6 WNW 30.0 65 3 0

7 07.00 6.3 W 32.5 61 2 0

8 08.00 9.7 W 34.0 56 2 0

9 09.00 16.0 W 36.0 53 2 0

10 10.00 14.3 WNW 38.0 45 1 0

11 11.00 9.3 W 40.0 42 1 0

12 12.00 7.6 W 42.0 40 1 0

13 13.00 19.0 WNW 43.0 36 0 0

14 14.00 12.0 W 44.0 31 0 0

15 15.00 8.4 W 44.5 29 0 0

16 16.00 5.6 WNW 43.0 31 1 0

17 17.00 4.0 NW 42.5 34 1 0

18 18.00 4.4 NW 40.0 38 2 0

19 19.00 6.2 WNW 38.0 40 2 0

20 20.00 12.6 W 36.5 46 2 0

21 21.00 11.0 W 35.0 51 2 0

22 22.00 8.9 WNW 34.0 57 3 0

23 23.00 6.8 W 32.5 63 3 0

24 24.00 5.9 WSW 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): W

2. Wind Velocity (Kmph) : Min 2.6 Max : 19.0 Avg : 7.9 3. Ambient Temperature (°C) : Min : 29.0 Max : 44.5 Avg : 36.3

4. Relative Humidity (%) : Min : 29.0 Max : 72.0 Avg : 51.1

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 750

7. Sky Appearance : Clear

Page 111: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 50 METEOROLOGICAL DATA

Date : 20.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 3.5 WNW 32.5 66 3 0

2 02.00 5.1 WNW 32.0 72 3 0

3 03.00 4.6 W 30.0 70 3 0

4 04.00 3.2 W 31.0 68 3 0

5 05.00 2.5 WSW 31.5 66 3 0

6 06.00 4.2 WSW 32.0 65 2 0

7 07.00 4.6 W 34.5 62 2 0

8 08.00 7.2 WSW 36.0 53 2 0

9 09.00 8.5 WSW 38.0 45 1 0

10 10.00 9.2 W 39.0 40 1 0

11 11.00 10.5 WSW 40.0 38 1 0

12 12.00 8.0 WSW 41.0 36 1 0

13 13.00 10.2 SW 42.0 32 0 0

14 14.00 14.0 SW 44.0 31 0 0

15 15.00 12.4 WSW 46.5 29 0 0

16 16.00 6.7 WSW 44.0 31 1 0

17 17.00 8.1 WSW 42.0 32 1 0

18 18.00 5.3 SW 40.0 38 2 0

19 19.00 4.8 WSW 39.0 40 2 0

20 20.00 3.4 WSW 37.5 53 3 0

21 21.00 2.8 SW 36.0 54 3 0

22 22.00 3.0 SW 34.5 56 3 0

23 23.00 3.4 WSW 33.0 63 3 0

24 24.00 4.2 WSW 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): WSW

2. Wind Velocity (Kmph) : Min : 2.5 Max : 14.0 Avg : 6.2

3. Ambient Temperature (°C) : Min : 30.0 Max : 46.5 Avg : 37.0

4. Relative Humidity (%) : Min : 29.0 Max : 72.0 Avg : 50.2

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 750

7. Sky Appearance : Clear

Page 112: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 51 METEOROLOGICAL DATA

Date : 21.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 3.4 WNW 32.5 64 3 0

2 02.00 4.2 W 32.0 66 3 0

3 03.00 3.6 W 30.0 68 3 0

4 04.00 4.5 WNW 31.0 72 3 0

5 05.00 5.1 WNW 31.5 73 3 0

6 06.00 2.8 NW 32.0 73 3 0

7 07.00 4.2 NW 34.0 68 2 0

8 08.00 5.0 WNW 35.0 62 2 0

9 09.00 5.6 WNW 36.0 58 2 0

10 10.00 6.2 W 37.5 45 1 0

11 11.00 8.5 WNW 38.0 43 1 0

12 12.00 6.7 WNW 40.0 42 1 0

13 13.00 7.6 NW 42.0 36 0 0

14 14.00 10.2 NW 44.5 31 0 0

15 15.00 12.5 WNW 43.0 33 0 0

16 16.00 13.7 WNW 42.5 36 1 0

17 17.00 11.5 W 40.0 40 1 0

18 18.00 8.6 W 38.5 46 2 0

19 19.00 5.2 WNW 36.0 53 2 0

20 20.00 4.8 WNW 34.5 56 2 0

21 21.00 4.0 W 34.0 58 2 0

22 22.00 3.5 WSW 32.5 61 3 0

23 23.00 3.1 WSW 32.0 63 3 0

24 24.00 2.6 WSW 31.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): WNW

2. Wind Velocity (Kmph) : Min 2.6 Max : 13.7 Avg : 6.1

3. Ambient Temperature (°C) : Min : 30.0 Max : 44.5 Avg : 35.8

4. Relative Humidity (%) : Min : 31.0 Max : 73.0 Avg : 54.7

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 750

7. Sky Appearance : Clear

Page 113: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 52 METEOROLOGICAL DATA

Date : 22.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 5.1 WNW 32.5 68 3 0

2 02.00 4.5 NNW 32.0 72 3 0

3 03.00 6.1 NW 30.0 70 3 0

4 04.00 5.6 NNW 29.5 68 3 0

5 05.00 4.8 NW 29.0 66 3 0

6 06.00 5.2 NNE 32.0 67 2 0

7 07.00 6.5 WNW 34.0 63 2 0

8 08.00 7.3 NE 35.0 57 2 0

9 09.00 10.5 NW 36.0 51 1 0

10 10.00 14.6 ENE 37.0 48 1 0

11 11.00 17.0 WNW 38.0 43 1 0

12 12.00 18.5 NE 40.0 42 1 0

13 13.00 15.3 NE 42.0 36 0 0

14 14.00 14.0 NNW 44.5 31 0 0

15 15.00 12.5 NNW 46.0 26 0 0

16 16.00 8.9 WNW 44.0 29 1 0

17 17.00 5.2 NNW 42.5 31 1 0

18 18.00 6.0 NE 41.0 33 2 0

19 19.00 5.4 NW 40.0 38 2 0

20 20.00 7.1 NW 38.5 45 3 0

21 21.00 6.5 NNW 36.5 48 3 0

22 22.00 3.8 NW 35.0 53 3 0

23 23.00 3.4 NW 34.0 63 3 0

24 24.00 4.3 NNW 32.5 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): NW

2. Wind Velocity (Kmph) : Min 3.4 Max : 18.5 Avg : 8.3

3. Ambient Temperature (°C) : Min : 29.0 Max : 46.0 Avg : 36.7

4. Relative Humidity (%) : Min : 26.0 Max : 72.0 Avg : 50.5

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 750

7. Sky Appearance : Clear

Page 114: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 53 METEOROLOGICAL DATA

Date : 23.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 3.9 WNW 32.5 68 3 0

2 02.00 5.7 NW 32.0 72 3 0

3 03.00 5.3 NW 30.0 70 3 0

4 04.00 3.8 NNW 29.5 68 3 0

5 05.00 4.5 NNW 31.0 66 3 0

6 06.00 6.2 NW 32.5 67 3 0

7 07.00 5.6 NW 34.0 63 2 0

8 08.00 9.2 SW 36.0 57 2 0

9 09.00 10.4 SW 38.5 51 2 0

10 10.00 11.3 SW 39.0 48 1 0

11 11.00 15.5 SW 40.0 43 1 0

12 12.00 13.4 SW 41.5 42 1 0

13 13.00 6.9 SW 42.0 36 0 0

14 14.00 8.5 SW 44.0 31 0 0

15 15.00 4.9 SSW 46.0 26 0 0

16 16.00 6.6 SW 44.0 30 1 0

17 17.00 5.0 SSW 42.5 31 1 0

18 18.00 4.8 NW 40.0 33 2 0

19 19.00 3.6 NW 39.0 38 2 0

20 20.00 7.1 NNW 38.0 45 2 0

21 21.00 6.5 NW 36.5 48 2 0

22 22.00 3.9 NNW 34.0 53 3 0

23 23.00 4.2 NNW 33.0 63 3 0

24 24.00 4.6 NW 32.5 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): NW

2. Wind Velocity (Kmph) : Min 3.6 Max : 15.5 Avg : 6.7

3. Ambient Temperature (°C) : Min : 29.5 Max : 46.0 Avg : 37.0

4. Relative Humidity (%) : Min : 26.0 Max : 72.0 Avg : 50.6

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 750

7. Sky Appearance : Clear

Page 115: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 54 METEOROLOGICAL DATA

Date : 24.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 3.8 WNW 32.5 68 3 0

2 02.00 4.0 WSW 32.0 72 3 0

3 03.00 4.5 SW 30.0 70 3 0

4 04.00 5.3 NW 29.5 68 3 0

5 05.00 4.0 NNW 31.0 66 3 0

6 06.00 5.0 NNW 32.0 67 2 0

7 07.00 6.2 NNW 34.5 62 2 0

8 08.00 7.5 NW 36.0 53 2 0

9 09.00 8.2 NW 38.0 45 1 0

10 10.00 10.5 NW 39.0 40 1 0

11 11.00 12.6 NW 40.0 38 1 0

12 12.00 9.5 NW 41.0 36 1 0

13 13.00 8.7 NW 42.0 32 0 0

14 14.00 13.0 NW 44.5 31 0 0

15 15.00 14.5 NNW 46.5 29 0 0

16 16.00 11.3 NNW 44.0 31 1 0

17 17.00 10.5 NW 42.0 32 1 0

18 18.00 9.3 NW 40.0 36 2 0

19 19.00 4.6 WNW 39.0 38 2 0

20 20.00 3.9 WNW 38.0 40 3 0

21 21.00 4.0 NW 36.0 53 3 0

22 22.00 5.3 SSW 34.5 56 3 0

23 23.00 6.9 SW 33.0 63 3 0

24 24.00 7.4 SW 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): NW

2. Wind Velocity (Kmph) : Min 3.8 Max : 14.5 Avg : 7.5

3. Ambient Temperature (°C) : Min : 29.5 Max : 46.5 Avg : 37.0

4. Relative Humidity (%) : Min : 29.0 Max : 72.0 Avg : 49.6

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 750

7. Sky Appearance : Clear

Page 116: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 55 METEOROLOGICAL DATA

Date : 25.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 8.6 WNW 32.5 68 3 0

2 02.00 10.5 NNW 32.0 72 3 0

3 03.00 9.2 NW 30.0 70 3 0

4 04.00 6.2 NNW 29.5 68 3 0

5 05.00 4.3 NW 31.0 66 3 0

6 06.00 4.2 NNE 32.0 66 3 0

7 07.00 5.0 WNW 34.5 62 2 0

8 08.00 6.3 NE 36.0 53 2 0

9 09.00 5.1 NW 38.0 45 1 0

10 10.00 4.8 ENE 39.0 40 1 0

11 11.00 3.5 WNW 40.0 38 1 0

12 12.00 4.9 NE 41.0 36 1 0

13 13.00 6.3 NE 42.0 32 0 0

14 14.00 10.5 NNW 44.5 31 0 0

15 15.00 12.3 NNW 45.0 29 0 0

16 16.00 11.5 WNW 44.0 31 1 0

17 17.00 9.3 NNW 42.0 32 1 0

18 18.00 8..7 NE 40.0 36 2 0

19 19.00 10.2 NW 39.0 38 2 0

20 20.00 6.4 NW 38.0 40 2 0

21 21.00 5.2 NNW 36.0 53 2 0

22 22.00 4.0 NW 34.5 56 3 0

23 23.00 3.5 NW 33.0 63 3 0

24 24.00 5.9 NNW 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): NW

2. Wind Velocity (Kmph) : Min 3.5 Max : 12.3 Avg : 6.9

3. Ambient Temperature (°C) : Min : 29.5 Max : 45.0 Avg : 36.9

4. Relative Humidity (%) : Min : 29.0 Max : 72.0 Avg : 49.6

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 750

7. Sky Appearance : Clear

Page 117: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 56 METEOROLOGICAL DATA

Date : 26.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 4.6 WNW 32.5 61 3 0

2 02.00 3.5 NW 32.0 66 3 0

3 03.00 2.8 NW 30.0 68 3 0

4 04.00 3.5 NNW 29.5 72 3 0

5 05.00 3.4 NNW 29.0 73 3 0

6 06.00 5.2 NW 30.0 72 3 0

7 07.00 6.5 NNW 31.0 65 2 0

8 08.00 7.0 NW 32.0 61 2 0

9 09.00 8.5 SW 33.0 56 1 0

10 10.00 9.2 SW 34.5 49 1 0

11 11.00 10.5 SW 36.0 48 1 0

12 12.00 13.4 SW 38.0 45 1 0

13 13.00 15.0 SW 40.0 40 0 0

14 14.00 13.2 SW 42.5 34 0 0

15 15.00 14.5 SW 41.5 35 0 0

16 16.00 9.3 SSE 40.0 43 1 0

17 17.00 8.5 S 39.0 50 1 0

18 18.00 6.4 S 38.0 52 2 0

19 19.00 3.8 SE 37.5 54 2 0

20 20.00 4.0 SSE 36.0 56 2 0

21 21.00 4.5 SE 35.5 58 2 0

22 22.00 6.2 SSE 34.0 61 3 0

23 23.00 5.1 SE 33.0 63 3 0

24 24.00 5.5 SSW 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): SW

2. Wind Velocity (Kmph) : Min 2.8 Max : 15.0 Avg : 7.3

3. Ambient Temperature (°C) : Min 29.0 Max : 42.5 Avg : 34.9

4. Relative Humidity (%) : Min : 34.0 Max : 73.0 Avg : 56.1

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 750

7. Sky Appearance : Clear

Page 118: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 57 METEOROLOGICAL DATA

Date : 27.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 4.5 WNW 32.5 65 3 0

2 02.00 4.0 NNW 32.0 66 3 0

3 03.00 3.3 WNW 30.0 68 3 0

4 04.00 2.9 WNW 29.5 72 3 0

5 05.00 2.5 WNW 29.0 73 3 0

6 06.00 4.2 W 30.0 72 2 0

7 07.00 5.0 W 31.0 65 2 0

8 08.00 6.8 WSW 32.0 61 2 0

9 09.00 7.2 WSW 33.0 56 1 0

10 10.00 6.9 W 34.5 49 1 0

11 11.00 10.2 WSW 36.0 48 1 0

12 12.00 13.5 WW 39.5 45 1 0

13 13.00 14.6 W 42.0 40 0 0

14 14.00 12.5 WSW 44.0 31 0 0

15 15.00 11.0 SW 42.5 35 0 0

16 16.00 5.9 SW 40.0 43 1 0

17 17.00 6.4 WSW 39.0 50 1 0

18 18.00 5.0 SW 38.0 52 2 0

19 19.00 4.8 SW 37.5 54 2 0

20 20.00 3.5 WSW 36.0 56 3 0

21 21.00 4.2 WSW 35.5 58 3 0

22 22.00 3.7 W 34.0 61 3 0

23 23.00 4.0 WSW 33.0 63 3 0

24 24.00 5.1 WSW 32.0 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): WSW

2. Wind Velocity (Kmph) : Min 2.5 Max : 14.6 Avg : 6.3

3. Ambient Temperature (°C) : Min 29.0 Max : 44.0 Avg : 35.1

4. Relative Humidity (%) : Min : 31.0 Max : 73.0 Avg : 56.2

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 750

7. Sky Appearance : Clear

Page 119: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 58 METEOROLOGICAL DATA

Date : 28.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidit

y (%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 3.2 WNW 32.5 64 3 0

2 02.00 2.4 WSW 32.0 66 3 0

3 03.00 2.0 WSW 30.0 68 3 0

4 04.00 1.5 SW 29.5 72 3 0

5 05.00 1.2 SW 29.0 73 3 0

6 06.00 3.2 SW 30.5 72 2 0

7 07.00 1.5 SW 32.0 70 2 0

8 08.00 2.0 SW 32.5 67 2 0

9 09.00 1.8 WSW 34.0 56 1 0

10 10.00 3.9 WSW 36.0 47 1 0

11 11.00 5.0 WSW 38.5 45 1 0

12 12.00 10.2 SW 40.0 38 1 0

13 13.00 11.2 SW 40.5 34 0 0

14 14.00 13.1 SW 42.5 29 0 0

15 15.00 10.2 SW 42.0 32 0 0

16 16.00 8..5 SSW 41.0 36 1 0

17 17.00 6.2 SSW 40.0 38 1 0

18 18.00 4.9 SSW 38.0 38 2 0

19 19.00 5.2 WSW 36.0 40 2 0

20 20.00 4.5 WSW 34.5 53 3 0

21 21.00 3.0 WNW 34.0 54 3 0

22 22.00 2.5 WNW 32.5 56 3 0

23 23.00 4.5 NW 32.0 63 3 0

24 24.00 3.6 NW 30.5 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): WSW

2. Wind Velocity (Kmph) : Min : 1.2 Max : 13.1 Avg : 4.6

3. Ambient Temperature (°C) : Min : 29.0 Max : 42.5 Avg : 35.0

4. Relative Humidity (%) : Min : 29.0 Max : 73.0 Avg : 53.2

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 750

7. Sky Appearance : Clear

Page 120: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 59 METEOROLOGICAL DATA

Date : 29.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 2.4 WNW 32.5 62 3 0

2 02.00 2.1 NNW 32.0 66 3 0

3 03.00 3.1 N 30.0 68 3 0

4 04.00 3.8 NNW 29.5 72 3 0

5 05.00 4.2 N 29.0 73 3 0

6 06.00 2.8 NNW 30.5 72 3 0

7 07.00 3.6 NNW 32.0 70 2 0

8 08.00 4.0 N 32.5 67 2 0

9 09.00 5.7 NNW 34.0 56 1 0

10 10.00 6.9 NNW 36.0 47 1 0

11 11.00 7.0 N 38.5 45 1 0

12 12.00 11.0 N 40.0 38 1 0

13 13.00 13.0 NNW 41.0 30 0 0

14 14.00 7.6 NW 43.0 28 0 0

15 15.00 5.9 NW 42.0 32 0 0

16 16.00 4.8 NNW 41.0 36 1 0

17 17.00 3.8 NW 40.0 38 1 0

18 18.00 4.0 NW 38.0 38 2 0

19 19.00 3.6 NNW 36.0 40 2 0

20 20.00 2.9 NNW 34.5 53 2 0

21 21.00 5.5 NNW 34.0 54 2 0

22 22.00 3.4 NW 32.5 56 3 0

23 23.00 4.4 NNW 32.0 63 3 0

24 24.00 4.5 NW 30.5 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): NNW

2. Wind Velocity (Kmph) : Min 2.1 Max : 13.0 Avg : 5.0

3. Ambient Temperature (°C) : Min 29.0 Max : 43.0 Avg : 35.0

4. Relative Humidity (%) : Min : 28.0 Max : 73.0 Avg : 52.9

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 750

7. Sky Appearance : Clear

Page 121: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 60 METEOROLOGICAL DATA

Date : 30.05.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 6.0 WNW 32.5 63 3 0

2 02.00 7.1 NW 32.0 66 3 0

3 03.00 5.0 NNW 30.0 68 3 0

4 04.00 4.0 NW 29.5 72 3 0

5 05.00 3.0 NW 29.0 73 3 0

6 06.00 7.3 NW 30.5 72 3 0

7 07.00 11.4 NW 32.0 70 2 0

8 08.00 12.0 NW 32.5 67 2 0

9 09.00 10.6 NW 34.0 56 1 0

10 10.00 11.7 NNW 36.0 47 1 0

11 11.00 10.9 SW 38.5 45 1 0

12 12.00 8.1 SW 40.0 38 1 0

13 13.00 7.4 SW 42.0 29 1 0

14 14.00 4.5 SW 43.5 27 0 0

15 15.00 6.7 SSW 42.0 32 1 0

16 16.00 5.4 SW 41.0 36 2 0

17 17.00 4.3 SW 40.0 38 3 0

18 18.00 3.8 WSW 38.0 38 3 0

19 19.00 6.9 SW 35.0 58 3 0

20 20.00 6.4 NW 34.0 69 3 0

21 21.00 9.2 NW 32.0 54 3 0

22 22.00 3.6 NW 31.0 61 3 0

23 23.00 8.6 NNW 31.0 63 3 0

24 24.00 4.5 NW 30.5 65 3 0

OBSERVATIONS

1. Predominant WindDirection (from): NW

2. Wind Velocity (Kmph) : Min 3.0 Max : 12.0 Avg : 7.0

3. Ambient Temperature (°C) : Min 29.0 Max : 43.5 Avg : 34.9

4. Relative Humidity (%) : Min : 27.0 Max : 73.0 Avg : 54.5

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 750

7. Sky Appearance : Cloudy

Page 122: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 61 METEOROLOGICAL DATA

Date : 31.05.12

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 1.9 WNW 32.5 65 3 0

2 02.00 2.9 WNW 32.0 66 3 0

3 03.00 4.0 NW 30.0 68 3 0

4 04.00 4.5 NW 29.5 72 3 0

5 05.00 3.8 NW 29.0 73 3 0

6 06.00 3.6 NNW 30.0 72 3 0

7 07.00 4.4 SW 31.0 65 2 0

8 08.00 6.1 SW 32.0 61 2 0

9 09.00 9.4 SW 33.0 56 1 0

10 10.00 7.9 NW 34.5 49 1 0

11 11.00 11.7 NW 36.0 48 1 0

12 12.00 10.9 NNW 39.5 45 1 0

13 13.00 15.7 NW 42.0 40 0 0

14 14.00 8.5 WNW 44.5 31 1 0

15 15.00 4.8 NW 43.0 35 2 0

16 16.00 5.3 NW 41.5 43 2 0

17 17.00 3.0 N 39.0 50 2 0

18 18.00 9.6 N 36.0 52 2 0

19 19.00 11.8 SW 33.5 54 3 0

20 20.00 13.5 SW 32.0 56 3 0

21 21.00 4.3 SSW 31.0 58 3 0

22 22.00 8.7 SW 31.0 60 3 0

23 23.00 4.0 SW 31.0 64 3 0

24 24.00 3.4 WSW 30.5 66 3 0

OBSERVATIONS

1. Predominant WindDirection (from): NW 2. Wind Velocity (Kmph) : Min 1.9 Max : 15.7 Avg : 6.8

3. Ambient Temperature (°C) : Min 29.0 Max : 44.5 Avg : 34.3

4. Relative Humidity (%) : Min : 31.0 Max : 73.0 Avg : 56.2

5. Rainfall (mm) : 0 6. Atm. Pressure (mm of Hg) : 751 7. Sky Appearance : Cloudy

Page 123: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 62 METEOROLOGICAL DATA

Date : 01.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 2.6 NW 29.5 62 3 0

2 02.00 5.9 NNW 29.5 65 3 0

3 03.00 4.3 NW 30.0 68 3 0

4 04.00 8.3 NW 30.5 74 3 0

5 05.00 6.9 NW 31.0 74 3 0

6 06.00 3.0 NNW 31.5 72 3 0

7 07.00 3.7 WNW 32.5 67 3 0

8 08.00 4.8 NW 34.0 67 2 0

9 09.00 7.9 NW 38.0 56 2 0

10 10.00 10.3 WNW 38.5 47 2 0

11 11.00 11.2 NW 40.0 45 2 0

12 12.00 12.6 NW 40.5 38 2 0

13 13.00 14.5 NW 42.0 34 1 0

14 14.00 12.0 NNW 42.5 32 1 0

15 15.00 9.6 NNW 42.0 32 1 0

16 16.00 8.3 NW 40.5 36 1 0

17 17.00 7.9 NNW 40.0 38 1 0

18 18.00 6.3 NW 38.5 42 2 0

19 19.00 5.0 NNW 38.0 45 2 0

20 20.00 4.5 NW 36.5 50 2 0

21 21.00 2.3 NNW 36.0 53 2 0

22 22.00 8.7 NW 34.5 55 2 0

23 23.00 7.0 NW 34.0 56 3 0

24 24.00 4.3 NW 32.5 59 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.3 Max : 14.5 Avg : 7.2

3. Ambient Temperature (°C) Min : 29.5 Max : 42.5 Avg : 35.9

4. Relative Humidity (%) Min : 32.0 Max : 74.0 Avg : 52.8

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 748

7. Sky Appearance : Clear

Page 124: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 63 METEOROLOGICAL DATA

Date : 02.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 5.5 NW 32.5 61 3 0

2 02.00 6.0 N 32.0 64 3 0

3 03.00 4.2 NNE 30.0 68 3 0

4 04.00 3.8 NNW 29.0 74 3 0

5 05.00 6.9 NNW 29.0 74 3 0

6 06.00 7.4 NW 30.5 72 3 0

7 07.00 11.4 NNW 32.0 70 2 0

8 08.00 14.0 NNW 32.5 67 1 0

9 09.00 15.7 NW 34.0 56 1 0

10 10.00 13.0 NNW 38.0 47 1 0

11 11.00 14.3 NNW 38.5 45 1 0

12 12.00 14.4 NNW 40.0 38 1 0

13 13.00 16.7 NW 40.5 34 0 0

14 14.00 9.3 NNW 42.0 32 0 0

15 15.00 8.6 NNE 42.5 32 0 0

16 16.00 7..0 NNE 40.0 34 0 0

17 17.00 6.7 NE 38.5 40 1 0

18 18.00 5.4 NE 38.0 45 1 0

19 19.00 9.1 N 36.5 48 1 0

20 20.00 9.6 N 36.0 53 2 0

21 21.00 10.9 NW 34.5 54 2 0

22 22.00 17.6 WNW 34.0 56 2 0

23 23.00 11.9 WNW 32.5 58 2 0

24 24.00 14.7 NW 32.0 61 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NNW 2. Wind Velocity (Kmph) Min : 3.8 Max : 17.6 Avg : 10.3

3. Ambient Temperature (°C) Min : 29.0 Max : 42.5 Avg : 35.2

4. Relative Humidity (%) Min : 32.0 Max : 74.0 Avg : 53.5

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 748

7. Sky Appearance : Clear

Page 125: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 64 METEOROLOGICAL DATA

Date : 03.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 6.3 NW 30.5 62 3 0

2 02.00 2.7 NW 30.0 65 3 0

3 03.00 4.0 NW 29.5 68 3 0

4 04.00 5.4 N 29.0 74 3 0

5 05.00 6.9 NW 29.0 74 3 0

6 06.00 5.4 NW 32.5 67 3 0

7 07.00 6.0 NNW 34.0 59 2 0

8 08.00 5.1 NW 36.5 50 1 0

9 09.00 8.2 NW 38.0 45 1 0

10 10.00 12.6 NNW 38.5 45 1 0

11 11.00 10.4 NW 40.0 42 1 0

12 12.00 9.8 NW 42.0 40 1 0

13 13.00 15.3 NW 42.5 36 0 0

14 14.00 12.6 N 44.0 31 0 0

15 15.00 6.1 NNW 44.5 31 0 0

16 16.00 18.0 NNW 44.0 31 0 0

17 17.00 15.7 NNW 42.5 32 1 0

18 18.00 11.4 NW 40.0 34 1 0

19 19.00 7.0 NW 38.5 40 2 0

20 20.00 4.0 WNW 36.5 43 4 0

21 21.00 3.0 NNW 34.5 68 6 1.2

22 22.00 8.0 NW 34.0 56 5 0

23 23.00 6.7 NW 32.0 58 4 0

24 24.00 9.1 NW 28.5 60 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.7 Max : 18.0 Avg : 8.3

3. Ambient Temperature (°C) Min : 28.5 Max : 44.5 Avg : 36.3

4. Relative Humidity (%) Min : 31.0 Max : 74.0 Avg : 50.5

5. Rainfall (mm) : 1.2

6. Atm. Pressure (mm of Hg) : 745

7. Sky Appearance : Rainy

Page 126: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 65 METEOROLOGICAL DATA

Date : 04.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 2.6 NW 28.0 64 3 0

2 02.00 3.2 WNW 27.0 66 3 0

3 03.00 4.2 N 27.0 66 3 0

4 04.00 5.3 WNW 25.0 68 3 0

5 05.00 6.9 WNW 25.0 68 3 0

6 06.00 8.4 NNW 27.5 75 3 0

7 07.00 3.6 NW 28.0 66 2 0

8 08.00 5.3 WNW 30.0 59 1 0

9 09.00 7.6 NW 30.5 47 1 0

10 10.00 9.6 NNW 32.5 44 1 0

11 11.00 12.9 NNW 34.5 41 1 0

12 12.00 8.1 WNW 36.5 38 1 0

13 13.00 14.5 WNW 38.5 36 0 0

14 14.00 10.4 NW 40.0 34 0 0

15 15.00 8.5 NNW 42.0 32 0 0

16 16.00 7.0 NW 40.0 34 0 0

17 17.00 6.7 NNW 38.5 36 1 0

18 18.00 7.2 NNW 38.0 45 1 0

19 19.00 5.5 WNW 36.5 50 2 0

20 20.00 4.1 WNW 36.0 53 2 0

21 21.00 7.4 NNW 34.5 54 2 0

22 22.00 8.7 NNW 34.0 56 2 0

23 23.00 4.3 N 32.5 64 3 0

24 24.00 6.1 N 32.0 67 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NNW 2. Wind Velocity (Kmph) Min : 2.6 Max : 14.5 Avg : 7.0

3. Ambient Temperature (°C) Min : 25.0 Max : 42.0 Avg : 33.1

4. Relative Humidity (%) Min : 32.0 Max : 75.0 Avg : 52.6

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 745

7. Sky Appearance : Clear

Page 127: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 66 METEOROLOGICAL DATA

Date : 05.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 6.3 NW 30.5 68 3 0

2 02.00 2.7 NW 30.0 72 3 0

3 03.00 4.0 NNW 28.0 77 3 0

4 04.00 5.4 NNW 27.0 77 3 0

5 05.00 6.9 NW 27.0 77 3 0

6 06.00 7.1 WNW 28.0 77 3 0

7 07.00 10.7 NW 32.5 61 2 0

8 08.00 12.0 NNW 34.5 56 1 0

9 09.00 9.9 NW 36.5 53 1 0

10 10.00 13.1 NW 38.5 45 1 0

11 11.00 14.9 NW 40.0 42 1 0

12 12.00 16.4 NW 42.0 40 1 0

13 13.00 11.0 WSW 42.0 40 0 0

14 14.00 18.3 SW 44.0 31 0 0

15 15.00 17.1 SSW 44.5 31 0 0

16 16.00 10.4 SE 42.0 36 0 0

17 17.00 8.0 SSE 40.5 38 1 0

18 18.00 8.6 SE 40.0 42 1 0

19 19.00 7.4 SW 38.5 45 1 0

20 20.00 8.8 SW 38.0 50 2 0

21 21.00 6.3 WSW 36.5 53 2 0

22 22.00 5.4 WSW 36.0 55 2 0

23 23.00 5.7 SSW 34.5 56 2 0

24 24.00 9.6 SW 34.0 59 2 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.7 Max : 18.3 Avg : 9.4

3. Ambient Temperature (°C) Min : 27.0 Max : 44.5 Avg : 36.0

4. Relative Humidity (%) Min : 31.0 Max : 77.0 Avg : 53.4

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 745

7. Sky Appearance : Clear

Page 128: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 67 METEOROLOGICAL DATA

Date : 06.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 2.3 NW 32.5 61 3 0

2 02.00 2.6 NNE 30.5 65 3 0

3 03.00 3.5 NNW 28.5 70 3 0

4 04.00 4.6 NE 26.0 76 3 0

5 05.00 6.9 NNE 26.0 76 5 2.0

6 06.00 1.8 NW 27.5 84 3 2.0

7 07.00 4.8 NW 28.0 74 2 0

8 08.00 6.9 NW 30.5 65 2 0

9 09.00 6.1 NW 32.5 64 2 0

10 10.00 10.4 NW 37.5 59 2 0

11 11.00 16.0 NNE 36.0 53 2 0

12 12.00 15.0 NW 36.5 53 2 0

13 13.00 9.6 NE 38.0 50 2 0

14 14.00 6.6 NW 38.5 50 2 0

15 15.00 8.0 N 40.0 47 2 0

16 16.00 7.4 NNE 39.5 50 2 0

17 17.00 6.7 N 38.0 51 2 0

18 18.00 7.6 NW 38.0 51 2 0

19 19.00 5.5 NNW 37.0 52 2 0

20 20.00 8.8 NNW 36.5 58 3 0

21 21.00 6.0 WNW 34.0 59 3 0

22 22.00 4.7 WNW 33.0 63 3 0

23 23.00 2.9 NW 30.0 68 3 0

24 24.00 4.4 NNW 29.0 71 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.8 Max : 16.0 Avg : 6.6

3. Ambient Temperature (°C) Min : 26.0 Max : 40.0 Avg : 33.5

4. Relative Humidity (%) Min : 47.0 Max : 84.0 Avg : 61.3

5. Rainfall (mm) : 4.0

6. Atm. Pressure (mm of Hg) : 745

7. Sky Appearance : Rainy

Page 129: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 68 METEOROLOGICAL DATA

Date : 07.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 2.3 NW 29.0 71 3 0

2 02.00 2.6 SW 28.5 74 3 0

3 03.00 2.4 SW 27.0 77 3 0

4 04.00 3.5 SSW 27.0 77 3 0

5 05.00 6.9 SSW 27.0 77 3 0

6 06.00 4.0 NW 30.0 72 3 0

7 07.00 6.1 NW 30.5 65 2 0

8 08.00 11.6 NW 32.0 61 1 0

9 09.00 8.6 NW 34.0 56 1 0

10 10.00 12.0 SW 36.0 58 1 0

11 11.00 14.2 SW 36.5 45 1 0

12 12.00 4.9 SSW 38.0 45 1 0

13 13.00 12.7 SSW 38.5 40 0 0

14 14.00 11.2 SW 40.0 34 0 0

15 15.00 9.0 SSW 42.5 25 0 0

16 16.00 12.1 SW 40.0 34 0 0

17 17.00 2.5 SW 38.5 36 1 0

18 18.00 3.3 SW 38.0 40 1 0

19 19.00 9.0 SSW 36.5 45 1 0

20 20.00 4.7 NW 36.0 45 2 0

21 21.00 9.4 NNW 34.5 54 2 0

22 22.00 7.6 SW 34.0 56 2 0

23 23.00 13.7 SW 32.5 64 2 0

24 24.00 16.5 SW 32.0 67 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : SW 2. Wind Velocity (Kmph) Min : 2.3 Max : 16.5 Avg : 8.0

3. Ambient Temperature (°C) Min : 27.0 Max : 42.5 Avg : 34.1

4. Relative Humidity (%) Min : 25.0 Max : 77.0 Avg : 54.9

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 748

7. Sky Appearance : Clear

Page 130: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 69 METEOROLOGICAL DATA

Date : 08.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 3.5 NW 30.5 68 3 0

2 02.00 5.1 WNW 30.0 72 3 0

3 03.00 4.6 NW 29.5 74 3 0

4 04.00 3.2 NNW 29.0 78 3 0

5 05.00 6.9 NNW 29.0 78 3 0

6 06.00 4.2 NW 30.0 65 3 0

7 07.00 4.6 NW 32.5 61 2 0

8 08.00 7.2 NW 34.0 56 3 0

9 09.00 8.5 NNW 36.5 53 3 0

10 10.00 9.2 NNW 38.5 45 2 0

11 11.00 10.5 NNW 40.0 42 2 0

12 12.00 8.0 ENE 42.0 40 2 0

13 13.00 10.2 ENE 42.5 36 3 0

14 14.00 14.0 ENE 44.0 27 3 0

15 15.00 12.4 NE 44.0 27 3 0

16 16.00 6.7 NW 42.0 36 3 0

17 17.00 8.1 WNW 40.5 38 4 0

18 18.00 5.3 NW 40.0 42 5 0

19 19.00 4.8 NW 38.5 45 5 0

20 20.00 3.4 NW 38.0 50 5 0

21 21.00 2.8 WNW 36.5 53 4 0

22 22.00 3.0 NW 36.0 55 3 0

23 23.00 3.4 WNW 34.5 56 3 0

24 24.00 4.2 WNW 32.5 59 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.8 Max : 14.0 Avg : 6.4

3. Ambient Temperature (°C) Min : 29.0 Max : 44.0 Avg : 36.3

4. Relative Humidity (%) Min : 27.0 Max : 78.0 Avg : 52.3

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 748

7. Sky Appearance : Clear

Page 131: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 70 METEOROLOGICAL DATA

Date : 09.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 4.1 NW 29.0 66 3 0

2 02.00 3.0 NW 28.5 79 3 0

3 03.00 2.8 NW 26.0 84 3 0

4 04.00 3.1 NNW 26.0 84 3 0

5 05.00 2.6 NW 26.0 84 3 0

6 06.00 5.6 NW 27.0 70 3 0

7 07.00 6.3 NW 28.5 67 2 0

8 08.00 9.7 NW 29.0 64 1 0

9 09.00 16.0 NNW 30.5 62 1 0

10 10.00 14.3 NNW 32.0 58 1 0

11 11.00 9.3 NW 34.5 54 1 0

12 12.00 7.6 NW 36.5 52 1 0

13 13.00 19.0 NW 38.5 45 1 0

14 14.00 12.0 NW 40.5 38 1 0

15 15.00 8.4 WNW 42.5 36 1 0

16 16.00 5.6 WNW 40.5 62 6 1.0

17 17.00 4.0 WNW 38.5 64 5 0

18 18.00 4.4 NE 34.5 70 6 1.0

19 19.00 6.2 NE 34.0 58 5 0

20 20.00 12.6 NNE 32.5 60 4 0

21 21.00 19.0 NNE 30.5 60 4 0

22 22.00 8.9 NNE 30.0 60 4 0

23 23.00 6.8 NE 29.5 64 4 0

24 24.00 5.9 NE 28.5 67 4 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.6 Max : 19.0 Avg : 8.2

3. Ambient Temperature (°C) Min : 26.0 Max : 42.5 Avg : 32.2

4. Relative Humidity (%) Min : 36.0 Max : 84.0 Avg : 62.8

5. Rainfall (mm) : 2.0

6. Atm. Pressure (mm of Hg) : 748

7. Sky Appearance : Rainy

Page 132: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 71 METEOROLOGICAL DATA

Date : 10.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 6.3 WNW 28.5 67 4 0

2 02.00 2.7 WNW 28.0 70 4 0

3 03.00 4.0 WNW 27.0 73 4 0

4 04.00 5.4 NW 25.0 80 4 0

5 05.00 6.9 WNW 25.0 80 4 0

6 06.00 7.1 NW 25.0 80 4 0

7 07.00 10.7 NW 27.5 73 3 0

8 08.00 12.0 WNW 28.0 64 2 0

9 09.00 9.9 WNW 29.0 51 2 0

10 10.00 13.1 W 32.5 49 1 0

11 11.00 14.9 W 34.0 46 1 0

12 12.00 16.4 WSW 34.5 42 1 0

13 13.00 11.0 WSW 36.0 39 1 0

14 14.00 18.3 W 36.5 38 1 0

15 15.00 17.1 WSW 38.0 36 2 0

16 16.00 10.4 W 38.5 34 2 0

17 17.00 8.0 WNW 36.0 46 3 0

18 18.00 8.6 WNW 33.5 38 3 0

19 19.00 7.4 NW 29.5 41 3 1.0

20 20.00 8.8 NW 29.0 43 4 2.0

21 21.00 6.3 WNW 29.0 44 5 2.0

22 22.00 5.4 WNW 28.5 47 5 0

23 23.00 5.7 W 28.5 50 5 0

24 24.00 9.6 WSW 28.0 52 4 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.7 Max : 18.3 Avg : 9.4

3. Ambient Temperature (°C) Min : 25.0 Max : 38.5 Avg : 30.6

4. Relative Humidity (%) Min : 34.0 Max : 80.0 Avg : 53.5

5. Rainfall (mm) : 5.0

6. Atm. Pressure (mm of Hg) : 745

7. Sky Appearance : Rainy

Page 133: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 72 METEOROLOGICAL DATA

Date : 11.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 8.6 WNW 27.5 57 3 0

2 02.00 10.5 NW 27.0 70 3 0

3 03.00 9.2 NNW 26.5 84 3 0

4 04.00 6.2 NNW 26.5 84 3 0

5 05.00 4.3 NW 26.5 84 3 0

6 06.00 4.2 NW 27.0 81 3 0

7 07.00 5.0 NW 27.5 80 2 0

8 08.00 6.3 NW 28.0 79 2 0

9 09.00 5.1 NE 28.0 79 1 0

10 10.00 4.8 NE 28.5 78 1 0

11 11.00 3.5 NE 29.0 78 2 0

12 12.00 4.9 SE 29.5 77 2 0

13 13.00 6.3 SE 28.5 88 4 9.0

14 14.00 10.5 SE 27.5 98 4 11.0

15 15.00 12.3 NNW 29.5 100 3 2.0

16 16.00 11.5 NNW 28.0 84 3 0

17 17.00 9.3 NW 28.0 84 3 0

18 18.00 8..7 NW 27.5 88 3 0

19 19.00 10.2 NW 27.5 78 3 0

20 20.00 6.4 WNW 27.0 78 3 0

21 21.00 5.2 WNW 27.0 80 3 0

22 22.00 4.0 NW 26.5 82 3 0

23 23.00 3.5 NW 26.5 100 3 2.5

24 24.00 5.9 NW 26.0 100 4 5.5

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 3.5 Max : 12.3 Avg : 6.9

3. Ambient Temperature (°C) Min : 26.0 Max : 29.5 Avg : 27.5

4. Relative Humidity (%) Min : 57.0 Max : 100.0 Avg : 83.0

5. Rainfall (mm) : 30.0

6. Atm. Pressure (mm of Hg) : 748

7. Sky Appearance : Rainy

Page 134: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 73 METEOROLOGICAL DATA

Date : 12.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 13.0 WNW 26.0 86 4 0

2 02.00 10.6 NW 25.5 86 5 0

3 03.00 9.1 N 25.5 94 5 1.5

4 04.00 9.3 WNW 24.5 100 5 0.5

5 05.00 8.6 NW 24.5 87 5 0

6 06.00 4.7 NW 25.0 84 4 0

7 07.00 4.9 ENE 25.0 83 4 0

8 08.00 6.2 NE 25.5 82 4 0

9 09.00 9.6 NE 25.5 81 3 0

10 10.00 5.9 WNW 25.0 80 4 0

11 11.00 11.5 NW 25.0 94 5 1.0

12 12.00 12.6 NNW 25.5 98 5 2.5

13 13.00 14.0 NW 26.0 77 4 0

14 14.00 13.5 ENE 26.0 76 4 0

15 15.00 10.7 SSE 26.5 75 4 0

16 16.00 9.8 NE 26.5 77 4 0

17 17.00 7.6 NNW 26.0 78 4 0

18 18.00 5.3 NW 26.0 79 4 0

19 19.00 4.4 NW 25.5 80 4 0

20 20.00 4.2 NE 25.5 82 4 0

21 21.00 4.0 NE 25.5 89 5 2.0

22 22.00 5.5 NW 25.5 96 5 1.5

23 23.00 6.9 ENE 25.5 100 5 2.0

24 24.00 7.4 NE 24.5 88 5 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 4.0 Max : 14.0 Avg : 8.3

3. Ambient Temperature (°C) Min : 24.5 Max : 26.5 Avg : 25.5

4. Relative Humidity (%) Min : 75.0 Max : 100.0 Avg : 85.5

5. Rainfall (mm) : 11.0

6. Atm. Pressure (mm of Hg) : 745

7. Sky Appearance : Rainy

Page 135: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 74 METEOROLOGICAL DATA

Date : 13.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 5.9 WNW 24.5 94 5 2.0

2 02.00 7.8 WNW 24.0 98 5 2.0

3 03.00 4.5 N 24.5 98 5 1.5

4 04.00 3.6 WNW 23.5 98 5 2.5

5 05.00 2.0 WNW 23.0 98 5 3.5

6 06.00 2.3 NNW 23.5 98 5 2.5

7 07.00 6.4 NW 23.0 98 5 3.5

8 08.00 9.7 WNW 23.5 100 5 1.5

9 09.00 16.6 NW 24.0 90 4 0

10 10.00 14.3 NNW 24.5 87 4 0

11 11.00 9.3 NNW 24.5 87 4 0

12 12.00 7.6 WNW 25.0 85 3 0

13 13.00 6.0 WNW 25.5 85 2 0

14 14.00 5.3 NW 26.0 86 2 0

15 15.00 5.7 NNW 25.5 85 4 0

16 16.00 4.3 NW 24.5 94 5 3.5

17 17.00 7.0 NNW 24.0 98 5 2.0

18 18.00 7.4 NNW 23.5 98 5 1.5

19 19.00 8.3 WNW 23.5 89 4 0

20 20.00 5.1 WNW 24.0 90 3 0

21 21.00 5.7 NNW 24.0 90 3 0

22 22.00 3.8 NNW 24.0 91 3 0

23 23.00 2.1 N 23.5 91 4 0

24 24.00 1.7 N 23.5 92 4 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.7 Max : 16.6 Avg : 6.4

3. Ambient Temperature (°C) Min : 23.0 Max : 26.0 Avg : 24.1

4. Relative Humidity (%) Min : 85.0 Max : 100.0 Avg : 92.5

5. Rainfall (mm) : 26.0

6. Atm. Pressure (mm of Hg) : 745

7. Sky Appearance : Rainy

Page 136: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 75 METEOROLOGICAL DATA

Date : 14.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 5.7 WNW 23.0 98 4 1.0

2 02.00 6.0 WNW 23.0 99 5 2.5

3 03.00 5.4 WNW 22.5 98 5 3.5

4 04.00 4.2 W 23.5 99 4 1.5

5 05.00 3.6 WNW 23.5 94 4 0

6 06.00 4.8 WNW 25.0 98 5 3.5

7 07.00 9.6 W 25.5 100 5 4.5

8 08.00 13.6 WNW 26.0 98 5 2.5

9 09.00 15.6 NW 26.0 90 4 0

10 10.00 16.3 NW 27.0 75 4 0

11 11.00 17.0 NNW 28.0 74 4 0

12 12.00 15.2 NNW 29.0 94 5 2.0

13 13.00 14.4 NW 30.0 98 3 1.0

14 14.00 14.0 WNW 30.5 61 3 0

15 15.00 11.7 WNW 31.5 59 3 0

16 16.00 8.5 WNW 31.0 60 2 0

17 17.00 11.4 W 28.0 64 3 0

18 18.00 12.4 W 27.0 67 3 0

19 19.00 10.0 WNW 26.5 69 4 0

20 20.00 7.4 WNW 26.0 69 4 0

21 21.00 6.6 NW 25.5 72 4 0

22 22.00 4.3 NNW 25.5 77 4 0

23 23.00 5.4 NNW 25.0 82 4 0

24 24.00 6.1 NW 25.0 84 4 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 3.6 Max : 17.0 Avg : 9.6

3. Ambient Temperature (°C) Min : 22.5 Max : 31.5 Avg : 26.4

4. Relative Humidity (%) Min : 59.0 Max : 100.0 Avg : 82.5

5. Rainfall (mm) : 22.0

6. Atm. Pressure (mm of Hg) : 745

7. Sky Appearance : Clear

Page 137: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 76 METEOROLOGICAL DATA

Date : 15.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 5.5 WNW 24.5 98 5 2.5

2 02.00 4.2 NW 24.5 98 5 1.5

3 03.00 8.3 NW 24.0 94 5 3.5

4 04.00 6.2 NNW 24.0 98 5 3.0

5 05.00 4.3 NNW 24.0 100 5 2.5

6 06.00 5.3 NW 24.5 92 5 0

7 07.00 7.2 NW 24.5 90 5 0

8 08.00 6.1 SW 25.0 89 4 0

9 09.00 9.4 SW 25.5 85 4 0

10 10.00 8.5 SW 25.5 86 4 0

11 11.00 10.6 SW 26.0 84 4 0

12 12.00 11.7 SW 26.0 83 3 0

13 13.00 12.9 SW 26.5 70 3 0

14 14.00 13.8 SW 27.0 74 3 0

15 15.00 11.6 SSW 27.5 88 4 1.5

16 16.00 10.1 SW 27.0 75 3 0

17 17.00 9.8 SSW 26.5 77 4 0

18 18.00 10.3 NW 25.5 80 4 0

19 19.00 8.4 NW 25.0 84 3 0

20 20.00 7.6 NNW 24.5 85 3 0

21 21.00 6.3 NW 24.0 87 3 0

22 22.00 5.2 NNW 23.5 88 4 0

23 23.00 4.5 NNW 23.0 98 5 1.0

24 24.00 4.0 NW 23.0 98 5 1.0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 4.0 Max : 13.8 Avg : 8.0

3. Ambient Temperature (°C) Min : 23.0 Max : 27.5 Avg : 25.0

4. Relative Humidity (%) Min : 70.0 Max : 100.0 Avg : 87.5

5. Rainfall (mm) : 16.5

6. Atm. Pressure (mm of Hg) : 745

7. Sky Appearance : Cloudy

Page 138: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 77 METEOROLOGICAL DATA

Date : 16.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 2.3 NW 22.5 93 5 0

2 02.00 2.6 NW 22.5 94 5 0

3 03.00 3.5 NW 23.5 95 5 0

4 04.00 4.6 N 23.0 95 5 1.5

5 05.00 6.9 NW 22.0 95 5 1.0

6 06.00 1.8 NW 23.5 92 5 0

7 07.00 4.8 NNW 24.0 90 5 0

8 08.00 6.9 NW 24.5 85 5 0

9 09.00 6.1 NW 25.0 84 5 0

10 10.00 10.4 NNW 25.5 84 4 0

11 11.00 16.0 NW 26.0 85 3 0

12 12.00 15.0 NW 27.0 82 3 0

13 13.00 9.6 NW 28.5 76 2 0

14 14.00 6.6 N 30.0 75 2 0

15 15.00 8.0 NNW 31.0 71 2 0

16 16.00 7.4 NNW 29.5 72 2 0

17 17.00 6.7 NNW 29.5 73 2 0

18 18.00 7.6 NW 29.0 73 2 0

19 19.00 5.5 NW 28.0 75 2 0

20 20.00 8.8 WNW 26.5 75 3 0

21 21.00 6.0 NNW 26.0 76 3 0

22 22.00 4.7 NW 26.0 76 3 0

23 23.00 2.9 NW 27.0 77 3 0

24 24.00 4.4 NW 27.5 78 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.8 Max : 16.0 Avg : 6.6

3. Ambient Temperature (°C) Min : 22.0 Max : 31.0 Avg : 26.1

4. Relative Humidity (%) Min : 71.0 Max : 95.0 Avg : 82.1

5. Rainfall (mm) : 2.5

6. Atm. Pressure (mm of Hg) : 748

7. Sky Appearance : Rainy

Page 139: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 78 METEOROLOGICAL DATA

Date : 17.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 1.5 WSW 28.0 75 3 0

2 02.00 1.9 SW 27.5 76 3 0

3 03.00 2.3 WSW 27.5 78 3 0

4 04.00 2.6 WNW 27.0 77 2 0

5 05.00 3.0 WNW 27.0 76 2 0

6 06.00 2.9 NNW 27.0 73 2 0

7 07.00 4.2 NNW 28.0 72 2 0

8 08.00 5.6 NNW 28.5 70 2 0

9 09.00 3.1 NW 29.5 68 1 0

10 10.00 4.8 WNW 30.0 66 1 0

11 11.00 3.2 SW 31.5 65 1 0

12 12.00 5.3 SW 32.5 60 0 0

13 13.00 4.2 SSW 33.5 59 0 0

14 14.00 5.6 NW 35.0 55 1 0

15 15.00 6.8 NNW 36.5 48 1 0

16 16.00 7.9 NNW 35.0 52 2 0

17 17.00 12.3 NW 34.5 55 2 0

18 18.00 13.6 NW 33.5 68 5 1.0

19 19.00 14.2 NW 32.0 88 5 2.0

20 20.00 15.3 NNW 30.0 90 5 2.0

21 21.00 8.3 NNW 29.5 88 4 0

22 22.00 5.9 NW 29.0 84 3 0

23 23.00 2.0 NW 28.5 84 3 0

24 24.00 3.2 NW 28.0 85 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.5 Max : 15.3 Avg : 5.8

3. Ambient Temperature (°C) Min : 27.0 Max : 36.5 Avg : 30.4

4. Relative Humidity (%) Min : 48.0 Max : 90.0 Avg : 71.3

5. Rainfall (mm) : 5.0

6. Atm. Pressure (mm of Hg) : 748

7. Sky Appearance : Clear

Page 140: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 79 METEOROLOGICAL DATA

Date : 18.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 2.5 WNW 28.0 85 3 0 2 02.00 3.1 WNW 25.5 82 3 0 3 03.00 2.8 NW 26.0 79 3 0

4 04.00 3.1 NW 25.5 77 2 0

5 05.00 2.7 NW 25.5 78 2 0

6 06.00 2.3 NNW 26.0 76 2 0

7 07.00 3.4 SW 26.5 74 2 0 8 08.00 2.4 SW 27.5 75 2 0 9 09.00 1.9 SW 29.0 73 1 0

10 10.00 6.7 NW 28.0 68 1 0

11 11.00 5.9 NW 27.5 71 1 0

12 12.00 8.9 NNW 27.5 71 0 0 13 13.00 10.5 NW 29.0 66 0 0 14 14.00 8.2 WNW 30.5 55 1 0 15 15.00 6.5 NW 31.5 48 1 0

16 16.00 6.4 NW 30.5 50 2 0

17 17.00 4.9 N 29.5 53 2 0

18 18.00 3.7 N 28.5 55 3 0 19 19.00 7.8 SW 28.0 58 3 0 20 20.00 8.1 SW 27.5 62 3 0 21 21.00 1.9 SSW 27.0 65 3 0

22 22.00 2.4 SW 27.0 68 3 0

23 23.00 3.5 SW 26.5 69 3 0

24 24.00 2.9 WSW 26.0 74 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.9 Max : 10.5 Avg : 4.7

3. Ambient Temperature (°C) Min : 25.5 Max : 31.5 Avg : 27.7

4. Relative Humidity (%) Min : 48.0 Max : 85.0 Avg : 68.0

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 750

7. Sky Appearance : Drizzling

Page 141: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 80 METEOROLOGICAL DATA

Date : 19.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 1.6 WSW 26.0 84 3 0

2 02.00 4.2 SW 26.0 79 3 0

3 03.00 3.6 WSW 25.5 75 3 0

4 04.00 4.5 WNW 25.5 77 2 0

5 05.00 6.9 NW 25.5 76 2 0

6 06.00 2.8 WNW 25.0 80 2 0

7 07.00 4.2 NNW 26.0 79 2 0

8 08.00 5.0 NW 27.0 76 2 0

9 09.00 5.6 NW 28.5 74 1 0

10 10.00 6.2 WNW 29.0 73 1 0

11 11.00 8.5 NW 30.0 71 1 0

12 12.00 6.7 WNW 31.5 69 0 0

13 13.00 7.6 NW 33.0 67 0 0

14 14.00 10.2 NW 34.0 60 1 0

15 15.00 12.5 NNW 34.0 56 1 0

16 16.00 15.4 NNW 33.5 54 2 0

17 17.00 11.5 NNW 33.0 53 2 0

18 18.00 8.6 NW 32.5 55 3 0

19 19.00 5.2 NW 32.0 56 3 0

20 20.00 4.8 NW 31.5 59 3 0

21 21.00 4.0 WNW 31.0 62 3 0

22 22.00 3.5 W 30.5 65 3 0

23 23.00 3.1 W 30.0 67 3 0

24 24.00 2.6 NW 29.5 68 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.6 Max : 15.4 Avg : 6.2

3. Ambient Temperature (°C) Min : 25.0 Max : 34.0 Avg : 29.6

4. Relative Humidity (%) Min : 53.0 Max : 84.0 Avg : 68.1

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 751

7. Sky Appearance : Clear

Page 142: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 81 METEOROLOGICAL DATA

Date : 20.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 3.2 NW 29.0 75 3 0

2 02.00 2.4 SW 28.0 77 3 0

3 03.00 2.0 SE 27.0 79 3 0

4 04.00 1.5 NE 26.5 80 2 0

5 05.00 6.9 NE 26.5 82 2 0

6 06.00 3.2 ESE 25.0 87 2 0

7 07.00 1.5 NE 25.5 86 2 0

8 08.00 2.0 ESE 26.5 70 2 0

9 09.00 1.8 SE 28.5 68 1 0

10 10.00 3.9 SE 29.5 66 1 0

11 11.00 10.6 SE 30.5 65 1 0

12 12.00 12.3 WSW 32.5 60 0 0

13 13.00 13.5 SW 33.5 59 0 0

14 14.00 16.8 SW 35.0 55 1 0

15 15.00 10.2 SW 35.5 42 1 0

16 16.00 8.5 WSW 35.0 44 2 0

17 17.00 6.2 SW 32.5 47 2 0

18 18.00 4.9 SW 31.5 48 3 0

19 19.00 5.2 WSW 31.0 50 3 0

20 20.00 4.5 SW 30.5 53 3 0

21 21.00 1.6 SW 30.0 56 3 0

22 22.00 2.3 SW 29.5 63 3 0

23 23.00 1.6 SW 29.0 67 3 0

24 24.00 1.5 SSW 28.5 70 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : SW 2. Wind Velocity (Kmph) Min : 1.5 Max : 16.8 Avg : 5.3

3. Ambient Temperature (°C) Min : 25.0 Max : 35.5 Avg : 29.9

4. Relative Humidity (%) Min : 42.0 Max : 87.0 Avg : 64.5

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 751

7. Sky Appearance : Drizzling

Page 143: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 82 METEOROLOGICAL DATA

Date : 21.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 5.7 SSW 28.0 72 3 0

2 02.00 6.0 SSW 28.0 76 3 0

3 03.00 5.4 SW 27.5 75 3 0

4 04.00 4.2 SW 27.5 74 2 0

5 05.00 3.6 SSW 27.5 72 2 0

6 06.00 3.0 SSW 28.0 70 2 0

7 07.00 3.7 SW 28.5 69 2 0

8 08.00 4.9 SSW 29.0 65 2 0

9 09.00 7.9 SSW 30.0 64 1 0

10 10.00 12.5 SW 31.5 63 1 0

11 11.00 7.3 SSW 32.0 60 1 0

12 12.00 6.1 SSW 32.5 59 0 0

13 13.00 7.0 S 33.5 56 0 0

14 14.00 3.4 SSW 34.5 55 1 0

15 15.00 2.8 SSW 35.0 54 1 0

16 16.00 3.0 S 34.5 55 2 0

17 17.00 4.1 SSW 32.5 57 2 0

18 18.00 6.3 SSW 30.0 59 3 0

19 19.00 5.0 SW 29.5 62 3 0

20 20.00 4.5 SW 29.0 64 3 0

21 21.00 6.4 SSW 28.5 67 3 0

22 22.00 8.1 SW 27.5 69 3 0

23 23.00 7.0 SW 27.0 70 3 0

24 24.00 4.3 SSW 26.5 72 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : SSW 2. Wind Velocity (Kmph) Min : 2.8 Max : 12.5 Avg : 5.5

3. Ambient Temperature (°C) Min : 26.5 Max : 35.0 Avg : 29.9

4. Relative Humidity (%) Min : 54.0 Max : 76.0 Avg : 65.0

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 751

7. Sky Appearance : Cloudy

Page 144: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 83 METEOROLOGICAL DATA

Date : 22.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 5.9 WSW 26.5 78 3 0

2 02.00 7.8 WNW 26.5 80 3 0

3 03.00 4.5 N 26.0 82 3 0

4 04.00 3.6 WNW 26.0 79 2 0

5 05.00 2.0 WNW 26.0 77 2 0

6 06.00 3.0 NNW 26.5 78 2 0

7 07.00 2.3 NNW 27.0 80 2 0

8 08.00 1.5 WNW 27.5 78 2 0

9 09.00 1.7 NW 28.0 76 1 0

10 10.00 5.0 WNW 28.5 74 1 0

11 11.00 8.9 NNW 29.0 72 1 0

12 12.00 12.3 N 29.5 70 0 0

13 13.00 9.4 NW 30.0 69 0 0

14 14.00 12.1 WNW 30.5 67 1 0

15 15.00 11.4 WNW 31.5 65 1 9

16 16.00 8.4 WNW 29.5 66 2 8

17 17.00 5.1 NW 28.5 68 2 0

18 18.00 4.0 NW 27.5 70 3 0

19 19.00 6.4 WNW 26.5 72 3 0

20 20.00 5.5 NNW 26.0 74 3 0

21 21.00 5.9 NNW 25.0 75 3 0

22 22.00 4.1 WNW 24.5 88 3 2.0

23 23.00 3.4 WNW 23.5 94 3 2.0

24 24.00 5.6 WNW 23.0 98 3 1.0

OBSERVATIONS

1. Predominant WindDirection (from) : WNW 2. Wind Velocity (Kmph) Min : 1.5 Max : 12.3 Avg : 5.8

3. Ambient Temperature (°C) Min : 23.0 Max : 31.5 Avg : 27.2

4. Relative Humidity (%) Min : 65.0 Max : 98.0 Avg : 76.3

5. Rainfall (mm) : 5

6. Atm. Pressure (mm of Hg) : 745

7. Sky Appearance : Rainy

Page 145: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 84 METEOROLOGICAL DATA

Date : 23.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 1.3 NW 23.0 79 3 0

2 02.00 3.0 NW 23.0 80 3 0

3 03.00 2.5 WSW 23.0 82 3 0

4 04.00 2.3 NW 22.5 79 2 0

5 05.00 2.8 NW 23.5 77 2 0

6 06.00 2.3 NNW 24.5 84 2 0

7 07.00 6.4 NW 25.0 83 2 0

8 08.00 9.7 NNW 25.5 82 2 0.0

9 09.00 16.6 WNW 26.0 80 1 3.0

10 10.00 14.3 NW 26.5 76 1 5.0

11 11.00 9.3 WSW 27.0 74 1 2.0

12 12.00 7.6 NW 27.5 75 0 2.0

13 13.00 6.0 NW 28.0 73 0 2.0

14 14.00 5.3 NNW 27.0 80 1 2.0

15 15.00 5.7 NNE 25.5 84 1 1.0

16 16.00 4.3 NNE 25.5 85 2 0.0

17 17.00 7.0 NW 25.5 86 2 0.0

18 18.00 7.4 WNW 25.0 87 3 0.0

19 19.00 8.3 WNW 25.0 85 3 0

20 20.00 5.1 WSW 25.0 84 3 0

21 21.00 5.7 WSW 24.5 84 3 0

22 22.00 3.8 WSW 24.5 83 3 0

23 23.00 2.1 W 24.5 82 3 0

24 24.00 1.7 W 24.5 80 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.3 Max : 16.6 Avg : 5.9

3. Ambient Temperature (°C) Min : 22.5 Max : 28.0 Avg : 25.1

4. Relative Humidity (%) Min : 73.0 Max : 87.0 Avg : 81.0

5. Rainfall (mm) : 17

6. Atm. Pressure (mm of Hg) : 745

7. Sky Appearance : Rainy

Page 146: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 85 METEOROLOGICAL DATA

Date : 24.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 4.1 NW 25.5 78 3 0

2 02.00 2.0 WNW 25.0 79 3 0

3 03.00 2.8 NW 24.5 81 3 0

4 04.00 3.1 NW 24.0 79 2 0

5 05.00 2.6 N 24.0 77 2 0

6 06.00 4.8 N 24.5 84 2 0

7 07.00 9.6 NE 24.5 83 2 0

8 08.00 13.6 WNW 25.0 82 2 0

9 09.00 15.6 NW 25.0 88 1 3.0

10 10.00 16.3 NW 26.5 90 1 5.0

11 11.00 17.0 WNW 26.5 98 1 2.0

12 12.00 15.2 SW 27.0 100 0 5.0

13 13.00 14.4 SW 27.0 98 0 2.0

14 14.00 14.0 SW 27.5 100 1 2.0

15 15.00 11.7 W 28.0 100 1 3.0

16 16.00 8.5 W 27.5 85 2 0.0

17 17.00 11.4 W 27.5 86 2 0.0

18 18.00 12.4 WSW 27.0 85 3 0.0

19 19.00 10.0 WSW 26.5 88 3 0.0

20 20.00 7.4 W 26.5 84 3 0

21 21.00 6.6 NW 26.0 86 3 0

22 22.00 4.3 NW 25.5 88 3 0

23 23.00 5.4 NW 25.0 85 3 0

24 24.00 6.1 NW 24.5 81 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 2.0 Max : 17.0 Avg : 9.1

3. Ambient Temperature (°C) Min : 24.0 Max : 28.0 Avg : 25.9

4. Relative Humidity (%) Min : 77.0 Max : 100.0 Avg : 86.9

5. Rainfall (mm) : 22

6. Atm. Pressure (mm of Hg) : 745

7. Sky Appearance : Rainy

Page 147: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 86 METEOROLOGICAL DATA

Date : 25.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 1.3 WNW 24.0 90 6 0

2 02.00 3.0 NW 23.5 94 7 5

3 03.00 2.5 NW 23.0 95 6 6

4 04.00 2.3 NW 23.0 100 5 10

5 05.00 2.8 WNW 23.0 100 5 10

6 06.00 4.0 NW 24.0 100 5 20

7 07.00 3.4 NNW 24.5 98 5 15

8 08.00 4.7 NNE 25.0 100 5 6

9 09.00 7.0 NE 25.0 100 5 5

10 10.00 16.9 NW 26.0 100 5 0

11 11.00 17.0 NW 26.5 88 5 0

12 12.00 14.9 NW 27.0 100 5 4

13 13.00 15.6 NW 27.0 100 5 3

14 14.00 6.1 NW 27.5 100 5 2

15 15.00 4.0 NW 28.5 100 5 9

16 16.00 5.8 NNE 27.5 98 5 8

17 17.00 6.2 NW 27.5 98 6 0

18 18.00 6.7 NE 26.5 87 5 0

19 19.00 9.6 NNW 26.5 85 5 0

20 20.00 12.1 WNW 26.0 84 5 0

21 21.00 9.8 NW 25.5 85 5 0

22 22.00 10.3 NW 25.0 86 5 0

23 23.00 9.4 NW 25.0 85 5 0

24 24.00 13.0 NW 24.5 84 5 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.3 Max : 17.0 Avg : 7.9

3. Ambient Temperature (°C) Min : 23.0 Max : 28.5 Avg : 25.5

4. Relative Humidity (%) Min : 84.0 Max : 100.0 Avg : 94.0

5. Rainfall (mm) : 103

6. Atm. Pressure (mm of Hg) : 745

7. Sky Appearance : Rainy

Page 148: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 87 METEOROLOGICAL DATA

Date : 26.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 2.9 NNW 24.0 85 3 0

2 02.00 3.6 NNW 23.5 86 3 0

3 03.00 2.4 NE 23.0 85 3 0

4 04.00 4.0 NE 23.0 82 2 0

5 05.00 3.6 NNE 23.0 83 2 2.0

6 06.00 5.2 WNW 23.5 87 2 2.0

7 07.00 6.5 NNW 23.5 86 2 0

8 08.00 7.0 NNW 23.5 84 2 0

9 09.00 8.5 NW 24.0 83 1 0

10 10.00 9.2 NNW 24.0 82 1 0

11 11.00 10.5 NNW 24.5 80 1 0

12 12.00 13.4 NNE 24.5 79 0 0

13 13.00 15.0 NNE 25.0 78 0 0

14 14.00 13.2 NE 25.0 77 1 0

15 15.00 14.5 WNW 25.5 76 1 0

16 16.00 9.3 NW 25.0 78 2 0

17 17.00 8.5 NNW 24.5 79 2 0

18 18.00 6.4 NNW 24.5 80 3 0

19 19.00 3.8 NW 24.0 81 3 0

20 20.00 4.0 WNW 24.0 82 3 0

21 21.00 4.5 NNW 24.0 84 3 0

22 22.00 6.2 NNW 23.5 86 3 0

23 23.00 5.1 NNW 23.5 85 3 0

24 24.00 5.5 NW 23.5 84 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NNW 2. Wind Velocity (Kmph) Min : 2.4 Max : 15.0 Avg : 7.2

3. Ambient Temperature (°C) Min : 23.0 Max : 25.5 Avg : 24.0

4. Relative Humidity (%) Min : 76.0 Max : 87.0 Avg : 82.2

5. Rainfall (mm) : 4

6. Atm. Pressure (mm of Hg) : 748

7. Sky Appearance : Rainy

Page 149: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 88 METEOROLOGICAL DATA

Date : 27.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 1.3 WNW 24.5 84 3 0

2 02.00 3.0 WNW 23.5 84 3 0

3 03.00 2.5 NNW 23.0 84 3 0

4 04.00 2.3 NW 23.0 85 2 0

5 05.00 2.8 NNW 23.0 86 2 0

6 06.00 4.8 NNW 23.5 87 2 0

7 07.00 9.6 NNW 24.5 85 2 0

8 08.00 13.6 NW 26.5 77 2 0

9 09.00 15.6 NW 27.0 72 1 0

10 10.00 16.3 NW 27.5 70 1 0

11 11.00 17.0 N 28.0 69 1 Cloudy

12 12.00 15.2 N 28.5 88 0 10

13 13.00 14.4 N 29.0 100 0 4

14 14.00 14.0 NW 29.5 100 1 2

15 15.00 11.7 NNW 30.0 98 1 2

16 16.00 8.5 NW 29.5 67 2 0

17 17.00 11.4 NNW 29.0 68 2 0

18 18.00 12.4 NNW 28.5 69 3 0

19 19.00 10.0 NNE 28.5 72 3 0

20 20.00 7.4 NNE 28.0 73 3 0

21 21.00 6.6 NE 28.0 75 3 0

22 22.00 4.3 NE 27.5 76 3 0

23 23.00 5.4 NNE 27.0 74 3 0

24 24.00 6.1 NNW 27.0 75 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.3 Max : 17.0 Avg : 9.0

3. Ambient Temperature (°C) Min : 23.0 Max : 30.0 Avg : 26.8

4. Relative Humidity (%) Min : 67.0 Max : 100.0 Avg : 79.9

5. Rainfall (mm) : 18

6. Atm. Pressure (mm of Hg) : 745

7. Sky Appearance : Rainy

Page 150: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 89 METEOROLOGICAL DATA

Date : 28.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 3.0 NW 26.5 78 3 0

2 02.00 2.5 NW 26.0 79 3 0

3 03.00 1.6 NNW 25.5 79 3 0

4 04.00 2.5 NW 25.5 80 2 0

5 05.00 1.0 NW 26.0 80 2 0

6 06.00 3.6 NNW 27.0 77 2 0

7 07.00 5.0 NNW 27.5 73 2 0

8 08.00 6.8 NW 27.5 69 2 0

9 09.00 7.2 NW 28.0 66 1 0

10 10.00 6.9 NW 28.0 65 1 0

11 11.00 10.2 NE 27.0 72 1 0

12 12.00 13.5 NE 27.0 75 0 0

13 13.00 18.6 NE 28.0 77 0 0

14 14.00 12.5 NNE 28.5 68 1 0

15 15.00 11.0 NE 29.0 72 1 0

16 16.00 5.9 NNE 28.5 73 2 0

17 17.00 6.4 NE 28.0 75 2 0

18 18.00 5.0 NNW 27.5 76 3 0

19 19.00 4.8 NW 27.0 78 3 0

20 20.00 3.5 NW 26.5 76 3 0

21 21.00 4.2 WNW 26.5 75 3 0

22 22.00 3.7 NW 26.0 74 3 0

23 23.00 4.0 NW 25.5 77 3 0

24 24.00 5.1 NNW 25.5 78 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.0 Max : 18.6 Avg : 6.2

3. Ambient Temperature (°C) Min : 25.5 Max : 29.0 Avg : 27.0

4. Relative Humidity (%) Min : 65.0 Max : 80.0 Avg : 74.7

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 748

7. Sky Appearance : Clear

Page 151: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 90 METEOROLOGICAL DATA

Date : 29.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 3.2 NNW 25.0 77 3 0

2 02.00 2.4 NW 25.0 79 3 0

3 03.00 2.0 NW 24.5 81 3 0

4 04.00 1.5 NW 24.5 83 2 0

5 05.00 1.2 NW 24.0 84 2 0

6 06.00 4.8 NNW 24.5 83 2 0

7 07.00 9.6 N 25.0 76 2 0

8 08.00 13.6 N 26.0 68 2 0

9 09.00 15.6 N 27.5 66 1 0

10 10.00 16.3 NW 28.0 64 1 0

11 11.00 17.0 NW 28.5 62 1 0

12 12.00 15.2 NNW 29.0 61 0 0

13 13.00 14.4 NW 29.5 60 0 0

14 14.00 14.0 WNW 30.0 59 1 0

15 15.00 11.7 NW 30.5 57 1 0

16 16.00 8.5 NW 29.5 63 2 0

17 17.00 11.4 N 29.0 65 2 0

18 18.00 12.4 N 29.0 66 3 0

19 19.00 10.0 WNW 28.5 67 3 0

20 20.00 7.4 WSW 28.0 68 3 0

21 21.00 6.6 WSW 28.0 72 3 0

22 22.00 4.3 WSW 26.5 73 3 0

23 23.00 5.4 SW 26.0 74 3 0

24 24.00 6.1 SW 26.0 75 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : NW 2. Wind Velocity (Kmph) Min : 1.2 Max : 17.0 Avg : 8.9

3. Ambient Temperature (°C) Min : 24.0 Max : 30.5 Avg : 27.2

4. Relative Humidity (%) Min : 57.0 Max : 84.0 Avg : 70.1

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 748

7. Sky Appearance : Clear

Page 152: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

TABLE : 91 METEOROLOGICAL DATA

Date : 30.06.13

Location : Corezone

Sl.No Time (Hrs)

Wind Velocity (Kmph)

Wind Direction

(from)

Temp. (°C)

Relative Humidity

(%)

Cloud Cover

(Oktas)

Rainfall (mm)

Dry

1 01.00 4.5 NW 25.0 76 3 0

2 02.00 4.0 WNW 25.0 77 3 0

3 03.00 3.3 WNW 24.5 79 3 0

4 04.00 2.9 SW 24.5 81 2 0

5 05.00 2.5 SW 25.0 83 2 0

6 06.00 4.7 WSW 26.0 82 2 0

7 07.00 6.8 WSW 27.5 81 2 0

8 08.00 10.6 SW 29.0 74 2 0

9 09.00 9.9 WSW 30.0 69 1 0

10 10.00 12.4 SW 31.5 64 1 0

11 11.00 7.9 SW 32.0 62 1 0

12 12.00 11.3 SW 33.0 58 0 0

13 13.00 15.6 SSW 34.0 54 0 0

14 14.00 11.4 S 35.5 52 1 0

15 15.00 8.5 SSW 34.0 55 1 0

16 16.00 4.8 SSW 33.0 57 2 0

17 17.00 6.1 SSW 32.0 63 2 0

18 18.00 4.2 SW 31.5 65 3 0

19 19.00 4.0 WSW 30.0 67 3 0

20 20.00 6.2 SW 29.0 69 3 0

21 21.00 12.5 SSW 28.5 71 3 0

22 22.00 8.1 WSW 28.5 73 3 0

23 23.00 6.8 SW 28.0 75 3 0

24 24.00 4.1 SSW 28.0 77 3 0

OBSERVATIONS

1. Predominant WindDirection (from) : SW 2. Wind Velocity (Kmph) Min : 2.5 Max : 15.6 Avg : 7.2

3. Ambient Temperature (°C) Min : 24.5 Max : 35.5 Avg : 29.4

4. Relative Humidity (%) Min : 52.0 Max : 83.0 Avg : 69.3

5. Rainfall (mm) : 0

6. Atm. Pressure (mm of Hg) : 748

7. Sky Appearance : Clear

Page 153: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

3.6 AMBIENT AIR QUALITY STATUS

3.6.1 Preamble

The principle objective of the ambient air quality monitoring is to assess the existing

levels of air pollutants as well as the regional background concentration in and

around the project area. Air pollution forms an important and critical factor to

study the environmental issues in the mining areas. Air quality has to be frequently

monitored to know the extent of pollution due to mining and allied activities. The

ambient air quality monitoring was carried out at eight stations.

The monitoring stations were identified on the basis of meteorology in the upwind

and downwind direction as well as to represent the cross sectional scenario of the

project site. The monitoring network was designed based on the available

meteorological and climatologically norms of predominant wind direction and

wind speed of the study region.

The parameters selected for analyzing the air quality status are Suspended

Particulate Matter <10 & 2.5, Sulphur dioxide (SO2), Nitrogen oxides (NOx) and

Heavy Metals. As per the existing norms, air quality monitoring was carried out on

24 hourly basis for SPM & RPM, SO2 and NOx samples for two days in a week for

twelve weeks in the season. The location details of ambient air quality monitoring

stations are given in the Table below.

Details of Ambient air quality-monitoring stations

SI.

No. Location Name Location Code

1. Core Zone A - 1

2. Pimpri Village A - 2

3. Borgaon Village A - 3

4. Pimpalgaon Village A - 4

5. Kunada Village A - 5

6. Telwasa Village A - 6

Page 154: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Data Presentation

The ambient air quality data are given in the Tables below.

Ambient Air Quality Status

Location Name & Code

MIN MAX 98th AM GM STD CPCB Limit

SPM

Core Zone (A1) 121 261 260 221.9 217.5 41.2

-

Pimpri Village (A2) 151 239 238 209.5 207.5 27.9

Borgaon Village (A3) 134 206 203 180.6 179.4 20.7

Pimpalgaon Village (A4) 110 145 144 131.8 131.4 10.5

Kunada Village (A5) 102 133 132 119.9 119.4 10.9

Telwasa Village (A6) 84 119 118 105.2 104.6 11.2

PM10

Core Zone (A1) 62 91 90 79.3 78.8 9.1

100

Pimpri Village (A2) 52 83 83 70.8 70.0 9.9

Borgaon Village (A3) 49 81 80 68.5 67.8 10.0

Pimpalgaon Village (A4) 41 72 70 58.3 57.7 8.6

Kunada Village (A5) 31 52 51 44.3 43.8 6.4

Telwasa Village (A6) 36 54 54 43.7 43.4 5.1

PM2.5

Core Zone (A1) 30 45.0 44.0 36.2 35.9 4.6

60

Pimpri Village (A2) 28 41.0 39.0 33.8 33.7 3.2

Borgaon Village (A3) 24 36.0 35.0 29.8 29.6 3.7

Pimpalgaon Village (A4) 20 35.0 34.0 27.7 27.3 4.7

Kunada Village (A5) 17 27.0 27.0 22.3 22.1 2.8

Telwasa Village (A6) 16 28.0 26.0 20.5 20.2 3.2

SO2

Core Zone (A1) 15.5 20.2 20.0 18.3 18.3 1.2

80

Pimpri Village (A2) 12.5 19.6 19.5 15.9 15.7 2.5

Borgaon Village (A3) 12.5 19.6 19.4 16.4 16.3 2.4

Pimpalgaon Village (A4) 12.7 19.8 18.7 16.4 16.3 1.7

Kunada Village (A5) 14.7 19.4 18.8 17.1 17.0 1.3

Telwasa Village (A6) 13.1 20.4 19.8 16.7 16.6 1.8

NOX

Core Zone (A1) 20.1 28.6 27.6 24.5 24.3 2.4

80

Pimpri Village (A2) 15.6 27.5 26.8 22.0 21.7 3.8

Borgaon Village (A3) 14.6 27.4 26.7 21.7 21.3 3.7

Pimpalgaon Village (A4) 16.7 27.3 26.8 22.0 21.8 2.6

Kunada Village (A5) 17.1 28.7 27.3 22.3 22.2 2.8

Telwasa Village (A6) 16.9 26.4 26.3 21.6 21.4 2.7

Page 155: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Data Analysis

Core zone

The Suspended Particulate Matter (SPM) values were ranging from 121 g/m3 to

260 g/m3 PM10 and PM2.5 values are ranging from 62 g/m3 to 90 g/m3 and

30 g/m3 to 44 g/m3 respectively.

SO2 and NOx values are varying between 15.5 to 20.0 g/m3 and 20.1 to 27.6

g/m3 respectivelyThe heavy metals like Arsenic ( As) and Mercury ( Hg) were

found to be Below Detectable Limit ( BDL) and other metals like Nickel ( Ni), Lead

( Pb) and Chromium ( Cr) values are found to be very low and negligible. All

the values are found to be well within the NAAQ Standards prescribed by CPCB.

Buffer zone

The Suspended Particulate Matter ( SPM) values were ranging from 84 g/m3 to

237 g/m3PM10 and PM2.5 values are ranging from 31 g/m3 to 83 g/m3 and

16 g/m3 to 27 g/m3 respectively. SO2 and NOx values are varying between

12.5 to 17.6 g/m3 and 14.6 to 24.3 g/m3 respectively. respectivelyThe heavy

metals like Arsenic ( As) and Mercury ( Hg) were found to be Below Detectable

Limit ( BDL) and other metals like Nickel ( Ni), Lead ( Pb) and Chromium ( Cr)

values are found to be very low and negligible. All the values are found to be

well within the NAAQ Standards prescribed by CPCB.

Summary

In general, all the values are found to be well within the NAAQ Standards prescribed by CPCB.

The latest data on PM-10 & PM-2.5 along with Pb,Cr etc has been generated in

the surrounding villages during the pre- monsoon season 2013 and has given in

subsequent pages.

Page 156: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

AMBIENT AIR QUALITY DATA

Location : Core Zone (JA1)

Week Date SPM

µg/m3 PM10

µg/m3 PM2.5

µg/m3 SO2

µg/m3 NOx

µg/m3 Hg

ng/m3 Pb

µg/m3 Cr

ng/m3 Ni

ng/m3 As

ng/m3

I 07.04.2013 259 89 44 19.8 25.9 BDL 0.12 0.10 0.22 BDL

08.04.2013 260 91 41 20.2 27.6 BDL 0.10 0.09 0.21 BDL

II 15.04.2013 243 82 35 18.7 24.6 BDL 0.13 0.08 0.20 BDL

16.04.2013 255 85 42 19.2 25.1 BDL 0.10 0.06 0.24 BDL

III 22.04.2013 258 87 38 20.0 26.3 BDL 0.09 0.07 0.23 BDL

23.04.2013 238 82 34 17.5 22.3 BDL 0.12 0.05 0.22 BDL

IV 28.04.2013 240 79 39 18.2 23.5 BDL 0.11 0.08 0.20 BDL

29.04.2013 249 84 36 19.4 26.1 BDL 0.10 0.04 0.18 BDL

V 08.05.2013 252 86 37 19.2 25.9 BDL 0.13 0.06 0.19 BDL

09.05.2013 234 76 36 17.7 24.3 BDL 0.13 0.08 0.17 BDL

VI 17.05.2013 226 75 34 16.8 26.8 BDL 0.14 0.09 0.15 BDL

18.05.2013 247 83 43 18.6 24.7 BDL 0.13 0.08 0.14 BDL

VII 23.05.2013 261 90 45 19.2 25.8 BDL 0.12 0.07 0.12 BDL

24.05.2013 252 88 40 19.7 27.3 BDL 0.10 0.05 0.13 BDL

VIII 29.05.2013 245 84 36 18.6 28.6 BDL 0.08 0.06 0.18 BDL

30.05.2013 234 81 33 17.6 27.4 BDL 0.07 0.07 0.21 BDL

IX 07.06.2013 214 86 37 18.7 23.9 BDL 0.06 0.11 0.22 BDL

08.06.2013 208 82 35 17.2 21.3 BDL 0.11 0.10 0.24 BDL

X 14.06.2013 158 62 32 17.3 20.7 BDL 0.12 0.08 0.23 BDL

15.06.2013 143 70 30 15.5 20.1 BDL 0.10 0.09 0.24 BDL

XI 22.06.2013 168 66 31 17.9 21.9 BDL 0.09 0.10 0.18 BDL

23.06.2013 121 64 30 15.9 21.8 BDL 0.08 0.11 0.20 BDL

XII 28.06.2013 188 62 30 18.5 22.4 BDL 0.10 0.10 0.22 BDL

29.06.2013 172 70 30 18.5 22.8 BDL 0.13 0.09 0.24 BDL

CPCB LIMIT - 100 60 80 80 - 1.0(µg/m3) - 20 6.0

Page 157: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

AMBIENT AIR QUALITY DATA

Location : Pimri Village (BZ) (JA2)

Week Date SPM

µg/m3 PM10

µg/m3 PM2.5

µg/m3 SO2

µg/m3 NOx

µg/m3 Hg

ng/m3 Pb

µg/m3 Cr

ng/m3 Ni

ng/m3 As

ng/m3

I 07.04.2013 238 83 41 19.6 27.5 BDL 0.08 0.04 BDL BDL

08.04.2013 229 79 39 18.4 26.8 BDL 0.10 0.08 BDL BDL

II 15.04.2013 226 81 37 17.2 25.4 BDL 0.07 0.05 BDL BDL

16.04.2013 234 75 35 18.7 24.6 BDL 0.10 0.04 BDL BDL

III 22.04.2013 215 72 33 12.8 17.5 BDL 0.12 0.02 0.06 BDL

23.04.2013 237 73 35 16.9 20.9 BDL 0.14 0.02 0.06 BDL

IV 28.04.2013 229 79 37 18.2 23.8 BDL 0.10 0.02 0.04 BDL

29.04.2013 231 80 34 19.5 26.1 BDL 0.08 BDL 0.06 BDL

V 08.05.2013 239 83 38 17.9 25.4 BDL 0.12 BDL 0.06 BDL

09.05.2013 224 75 35 13.2 18.0 BDL 0.10 BDL 0.04 BDL

VI 17.05.2013 212 71 32 12.8 15.6 BDL 0.12 BDL 0.04 BDL

18.05.2013 225 77 36 18.7 26.3 BDL 0.14 BDL BDL BDL

VII 23.05.2013 219 73 34 17.5 24.8 BDL 0.10 0.02 BDL BDL

24.05.2013 227 78 32 14.8 17.3 BDL 0.11 0.02 BDL BDL

VIII 29.05.2013 235 81 35 18.9 26.4 BDL 0.06 0.05 BDL BDL

30.05.2013 218 73 34 13.8 16.7 BDL 0.06 0.04 0.07 BDL

IX 07.06.2013 162 56 30 12.5 22.2 BDL 0.10 0.03 0.09 BDL

08.06.2013 177 58 32 13.5 21.9 BDL 0.08 0.04 0.10 BDL

X 14.06.2013 188 64 32 14.1 24.1 BDL 0.11 BDL 0.12 BDL

15.06.2013 160 54 31 14.1 19.8 BDL 0.08 BDL 0.08 BDL

XI 22.06.2013 176 60 30 15.3 20.4 BDL 0.09 BDL 0.09 BDL

23.06.2013 151 62 30 15.6 17.5 BDL 0.11 BDL 0.09 BDL

XII 28.06.2013 183 59 32 13.8 16.8 BDL 0.14 BDL 0.12 BDL

29.06.2013 192 52 28 13.5 23.2 BDL 0.12 BDL 0.13 BDL

CPCB LIMIT - 100 60 80 80 - 1.0(µg/m3) - 20 6.0

Page 158: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

AMBIENT AIR QUALITY DATA

Location : Bargaon Village (BZ) (JA3)

Week Date SPM

µg/m3 PM10

µg/m3 PM2.5

µg/m3 SO2

µg/m3 NOx

µg/m3 Hg

ng/m3 Pb

µg/m3 Cr

ng/m3 Ni

ng/m3 As

ng/m3

I 07.04.2013 206 80 36 19.2 26.5 BDL 0.04 0.04 0.03 BDL

08.04.2013 189 76 33 17.8 22.4 BDL 0.07 0.08 0.04 BDL

II 15.04.2013 198 79 31 18.3 25.9 BDL 0.05 0.05 0.06 BDL

16.04.2013 201 81 35 19.1 24.8 BDL 0.10 0.04 0.08 BDL

III 22.04.2013 192 73 32 18.9 23.4 BDL 0.05 BDL 0.06 BDL

23.04.2013 185 65 28 15.6 22.6 BDL 0.11 BDL 0.06 BDL

IV 28.04.2013 203 78 34 17.8 21.8 BDL 0.17 BDL 0.04 BDL

29.04.2013 187 72 29 18.1 24.7 BDL 0.04 BDL 0.06 BDL

V 08.05.2013 196 79 32 17.5 20.7 BDL 0.09 BDL 0.06 BDL

09.05.2013 185 65 27 13.7 15.3 BDL 0.10 BDL BDL BDL

VI 17.05.2013 181 62 25 12.9 14.6 BDL 0.12 BDL BDL BDL

18.05.2013 190 73 30 17.8 19.8 BDL 0.12 BDL BDL BDL

VII 23.05.2013 202 79 33 18.3 27.4 BDL 0.10 BDL BDL BDL

24.05.2013 194 77 32 19.6 26.7 BDL 0.07 BDL BDL BDL

VIII 29.05.2013 199 80 35 19.4 25.1 BDL 0.05 BDL BDL BDL

30.05.2013 182 64 26 13.3 15.0 BDL 0.06 0.02 BDL BDL

IX 07.06.2013 166 59 32 16.6 22.9 BDL 0.10 0.03 BDL BDL

08.06.2013 154 53 27 13.5 19.8 BDL 0.08 0.04 BDL BDL

X 14.06.2013 147 59 30 15.6 20.3 BDL 0.11 0.04 BDL BDL

15.06.2013 160 49 24 12.5 17.2 BDL 0.08 0.03 0.06 BDL

XI 22.06.2013 179 51 24 14.3 21.5 BDL 0.09 0.02 0.04 BDL

23.06.2013 143 62 25 13.2 18.6 BDL 0.13 0.02 0.06 BDL

XII 28.06.2013 134 68 28 15.1 22.8 BDL 0.12 0.02 0.05 BDL

29.06.2013 162 61 27 16.6 20.2 BDL 0.13 0.02 0.04 BDL

CPCB LIMIT - 100 60 80 80 - 1.0(µg/m3) - 20 6.0

Page 159: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

AMBIENT AIR QUALITY DATA

Location : Pimpalgaori Village (JA4)

Week Date SPM

µg/m3 PM10

µg/m3 PM2.5

µg/m3 SO2

µg/m3 NOx

µg/m3 Hg

ng/m3 Pb

µg/m3 Cr

ng/m3 Ni

ng/m3 As

ng/m3

I 07.04.2013 138 61 31 15.6 23.4 BDL 0.07 0.04 BDL BDL

08.04.2013 141 69 34 16.2 26.8 BDL 0.09 0.08 BDL BDL

II 15.04.2013 145 70 35 19.8 27.3 BDL 0.06 0.05 BDL BDL

16.04.2013 134 59 29 17.3 21.9 BDL 0.09 0.04 0.08 BDL

III 22.04.2013 129 57 27 12.7 16.7 BDL 0.11 BDL 0.06 BDL

23.04.2013 137 63 30 14.8 20.6 BDL 0.13 BDL 0.06 BDL

IV 28.04.2013 140 68 33 18.4 24.1 BDL 0.09 BDL 0.04 BDL

29.04.2013 132 54 25 15.9 19.5 BDL 0.07 BDL 0.06 BDL

V 08.05.2013 143 67 31 17.6 23.2 BDL 0.11 BDL BDL BDL

09.05.2013 131 56 28 16.2 20.7 BDL 0.06 BDL BDL BDL

VI 17.05.2013 137 65 31 15.3 19.3 BDL 0.09 BDL BDL BDL

18.05.2013 144 72 33 18.7 25.8 BDL 0.11 BDL BDL BDL

VII 23.05.2013 133 52 24 17.9 22.4 BDL 0.13 BDL BDL BDL

24.05.2013 139 64 28 18.5 23.2 BDL 0.09 BDL BDL BDL

VIII 29.05.2013 142 67 32 16.8 21.6 BDL 0.07 BDL BDL BDL

30.05.2013 136 62 27 17.1 22.8 BDL 0.11 BDL BDL BDL

IX 07.06.2013 113 51 33 16.0 21.3 BDL 0.09 BDL BDL BDL

08.06.2013 124 48 21 17.4 22.1 BDL 0.11 0.04 BDL BDL

X 14.06.2013 138 41 22 15.7 23.7 BDL 0.13 0.04 0.06 BDL

15.06.2013 116 54 24 14.1 19.1 BDL 0.09 0.03 0.04 BDL

XI 22.06.2013 119 56 25 16.4 20.6 BDL 0.10 0.04 0.06 BDL

23.06.2013 128 46 20 13.6 18.3 BDL 0.05 BDL 0.05 BDL

XII 28.06.2013 114 49 22 16.2 20.4 BDL 0.05 BDL 0.08 BDL

29.06.2013 110 48 20 15.3 22.3 BDL 0.09 BDL 0.06 BDL

CPCB LIMIT - 100 60 80 80 - 1.0(µg/m3) - 20 6.0

Page 160: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

AMBIENT AIR QUALITY DATA

Location : kunad Village (JA5)

Week Date SPM

µg/m3 PM10

µg/m3 PM2.5

µg/m3 SO2

µg/m3 NOx

µg/m3 Hg

ng/m3 Pb

µg/m3 Cr

ng/m3 Ni

ng/m3 As

ng/m3

I 09.04.2013 132 52 27 18.3 24.6 BDL 0.04 0.04 BDL BDL

10.04.2013 128 50 24 17.6 22.2 BDL 0.06 0.08 BDL BDL

II 17.04.2013 123 47 21 16.8 23.8 BDL 0.03 0.05 BDL BDL

18.04.2013 130 49 26 18.4 21.4 BDL 0.06 0.04 BDL BDL

III 24.04.2013 126 43 23 15.1 19.1 BDL 0.08 0.02 BDL BDL

25.04.2013 133 51 25 17.2 23.8 BDL BDL BDL BDL BDL

IV 29.04.2013 127 45 22 15.9 20.3 BDL BDL BDL BDL BDL

30.04.2013 124 47 23 16.5 24.6 BDL BDL BDL BDL BDL

V 10.05.2013 129 45 21 17.8 22.4 BDL 0.08 BDL BDL BDL

11.05.2013 132 51 26 17.1 24.0 BDL 0.03 BDL BDL BDL

VI 19.05.2013 125 49 25 16.4 28.7 BDL 0.06 BDL 0.04 BDL

20.05.2013 130 51 27 18.0 21.2 BDL 0.08 BDL 0.05 BDL

VII 25.05.2013 126 47 22 17.3 25.5 BDL 0.10 BDL 0.02 BDL

26.05.2013 131 42 25 18.1 23.8 BDL BDL BDL 0.02 BDL

VIII 30.05.2013 118 46 20 19.4 27.3 BDL BDL BDL 0.04 BDL

31.05.2013 114 45 20 15.3 22.1 BDL BDL 0.04 0.07 BDL

IX 09.06.2013 111 34 22 14.8 21.4 BDL 0.06 0.03 0.06 BDL

10.06.2013 108 39 21 17.2 22.6 BDL 0.08 0.04 BDL BDL

X 16.06.2013 106 38 20 18.8 23.1 BDL 0.10 0.04 BDL BDL

17.06.2013 105 46 21 17.5 20.7 BDL 0.06 BDL BDL BDL

XI 24.06.2013 110 31 18 14.7 18.2 BDL 0.07 BDL BDL BDL

25.06.2013 103 33 17 15.3 18.5 BDL BDL BDL BDL BDL

XII 29.06.2013 105 49 19 17.6 17.1 BDL BDL BDL BDL BDL

30.06.2013 102 33 20 18.8 19.4 BDL BDL BDL BDL BDL

CPCB LIMIT - 100 60 80 80 - 1.0(µg/m3) - 20 6.0

Page 161: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

AMBIENT AIR QUALITY DATA

Location : Telwasa Village (JA6)

Week

Date SPM

µg/m3

PM10 µg/m

3

PM2.5

µg/m3

SO2 µg/m

3

NOx µg/m

3

Hg ng/m

3

Pb µg/m

3

Cr ng/m

3

Ni ng/m

3

As ng/m

3

I 09.04.2013 118 54 26 18.5 22.1 BDL 0.07 0.04 BDL BDL

10.04.2013 109 41 19 16.8 18.6 BDL 0.09 0.08 BDL BDL

II 17.04.2013 106 42 16 15.6 21.3 BDL 0.06 0.05 BDL BDL

18.04.2013 117 49 22 17.0 22.9 BDL BDL 0.04 BDL BDL

III 24.04.2013 112 44 21 18.4 23.6 BDL BDL 0.02 BDL BDL

25.04.2013 118 53 24 19.8 24.8 BDL BDL BDL BDL BDL

IV 29.04.2013 116 50 23 18.1 21.3 BDL BDL BDL BDL BDL

30.04.2013 111 43 19 16.9 19.5 BDL 0.07 BDL BDL BDL

V 10.05.2013 115 46 23 15.7 20.8 BDL 0.04 BDL BDL BDL

11.05.2013 108 42 18 16.3 22.2 BDL 0.06 BDL BDL BDL

VI 19.05.2013 116 47 25 20.4 26.4 BDL 0.09 BDL BDL BDL

20.05.2013 107 43 22 18.2 24.8 BDL 0.08 BDL 0.04 BDL

VII 25.05.2013 109 40 19 17.5 25.7 BDL 0.09 BDL 0.02 BDL

26.05.2013 119 54 28 19.5 26.3 BDL 0.09 BDL 0.02 BDL

VIII 30.05.2013 106 44 22 15.3 21.0 BDL 0.07 BDL BDL BDL

31.05.2013 110 42 19 14.8 21.3 BDL 0.10 BDL BDL BDL

IX 09.06.2013 86 41 18 15.7 20.5 BDL BDL 0.03 BDL BDL

10.06.2013 88 38 17 17.6 22.1 BDL BDL 0.04 BDL BDL

X 16.06.2013 92 37 20 16.4 20.6 BDL BDL BDL 0.06 BDL

17.06.2013 90 36 18 15.2 18.0 BDL BDL BDL 0.04 BDL

XI 24.06.2013 95 40 16 14.6 17.2 BDL BDL BDL 0.06 BDL

25.06.2013 84 42 17 13.1 16.9 BDL BDL BDL 0.05 BDL

XII 29.06.2013 95 39 20 14.1 18.5 BDL 0.05 0.04 0.08 BDL

30.06.2013 98 41 19 16.2 21.7 BDL 0.09 0.03 0.06 BDL

CPCB LIMIT - 100 60 80 80 - 1.0(µg/m3) - 20 6.0

3.7 BASE LINE WATER QUALITY STATUS

Rationale behind sampling

Any adverse impact or pollution consequence of water will have serious effect on

the environment. Hence, it becomes important to assess the water quality

periodically in the mining area. Thus, to assess the water quality, five locations are

identified and samples (5 Nos.) were collected and analyzed for physico-

chemical and heavy metal parameters. Bacterial examination was also carried

out to find out the Coliform contamination (if any) at water sources. The water

quality assessment has been made from the following monitoring stations:-

Wardha River, UP Stream - W1

Wardha River, Down Stream - W2

Drinking Water, Kunada Village - W3

Drinking Water, - W4

Bore Well Water,Telwasa Village - W5

Page 162: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

In addition the quality of existing mine effluent has also been considered and

given in subsequent pages.

3.7.2 Data Presentation

The detailed water quality data generated are given in subsequent pages. The abstract

of water quality status is furnished in Table below.

Ground Water quality status

Source pH Turbidity

(NTU)

TDS (mg/l) Total

Hardness (mg/l)

Iron (mg/l) Chloride

(mg/l) Sulphate

(mg/l) Fluoride

(mg/l)

Min Max Min Max Min Max Min Max Min Max Min Max Min Max

Drinking / Ground

Water 7.94 8.19 4 - 5 694 924 301 497 0.04 0.08 45 70 30 281 0.01 0.12

IS 10500 Norms

6.5-8.5 10 500-2000 300-600 0.3-1.0 250-1000 200-1000 1.0

Surface water quality status

Source pH

Colour (Hazen Units )

TDS (mg/l) Iron (mg/l) Chloride

(mg/l) Sulphate

(mg/l) Fluoride (mg/l)

Min Max Min Max Min Max Min Max Min Max Min Max Min Max

River 8.21 8.23 12 13 788 778 0.18 49 55 215 230 0.24 0.26

IS:2296-1982

6.5-8.5 300 1500 50 600 400 1.5

Page 163: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

WATER QUALITY DATA Location Name : Near Wardha River UP Stream Date of Sampling : 21.05.2013

Sl. No. Parameter Unit Result IS:2296-1982 Tolerance limits for Inland Surface

water (Class C)

1 pH - 8.21 6.5 – 8.5

2 Colour Hazen Units 12 300

3 Temperature oC 33.0 -

4 Turbidity NTU 18 -

5 Total suspended solids mg/l 56 -

6 Total dissolved solids mg/l 788 1500

7 Total volatile solids mg/l - -

8 Dissolved Oxygen mg/l 5.3 4.0

9 BOD - 3 days, 27oC mg/l 2 3.0

10 COD mg/l 26 -

11 Oil & grease mg/l Nil -

12 Residual chlorine mg/l Nil -

13 Chloride (as CI) mg/l 55 600

14 Flouride (as F) mg/l 0.26 1.5

15 Sulphate (as SO4) mg/l 230 400

16 Sulphide (as S) mg/l Nil -

17 Cyanide (as CN) mg/l <0.01 0.05

18 Insecticides/pesticides mg/l Nil Absent

19 Phenols (as C6H5OH) mg/l <0.001 0.005

20 Chromium (as Cr) mg/l <0.01 0.05

21 Copper (as Cu) mg/l <0.01 1.5

22 Selenium (as Se) mg/l <0.01 0.05

23 Arsenic (as As) mg/l <0.01 0.2

24 Barium (as Ba) mg/l <0.01 -

25 Cadmium mg/l <0.01 0.01

26 Nickel (as Ni) mg/l <0.01 -

27 Boron (as B) mg/l <0.01 -

28 Mercury (as Hg) mg/l <0.001 -

29 Silver (as Ag) mg/l <0.01 -

30 Lead (as Pb) mg/l <0.01 0.1

31 Zinc (as Pb) mg/l 1.3 15

32 Alkalinity to phenolphthalein mg/l Nil -

33 Alkalinity to methyl orange mg/l 233 -

34 Iron (as Fe) mg/l 0.18 50

35 Calcium (as Ca) mg/l 68 -

36 Magnesium (as Mg) mg/l 41 -

37 Total Nitrogen (as N) mg/l 2.8 -

38 Percent sodium % 31.55 -

39 Coliform organisms MPN/100ml 2100 5000

40 Sodium (as Na) mg/l 80 -

41 Potassium (as K) mg/l 31 -

Page 164: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

WATER QUALITY DATA Location Name : Near Wardha River Down Stream Date of Sampling : 21.05.2013

Sl. No.

Parameter Unit Result IS:2296-1982 Tolerance limits for Inland Surface

water (Class C)

1 pH - 8.23 6.5 – 8.5

2 Colour Hazen Units 13 300

3 Temperature oC 33.0 -

4 Turbidity NTU 19 -

5 Total suspended solids mg/l 58 -

6 Total dissolved solids mg/l 778 1500

7 Total volatile solids mg/l - -

8 Dissolved Oxygen mg/l 5.2 4.0

9 BOD - 3 days, 27oC mg/l 2 3.0

10 COD mg/l 26 -

11 Oil & grease mg/l Nil -

12 Residual chlorine mg/l Nil -

13 Chloride (as CI) mg/l 49 600

14 Flouride (as F) mg/l 0.24 1.5

15 Sulphate (as SO4) mg/l 215 400

16 Sulphide (as S) mg/l Nil -

17 Cyanide (as CN) mg/l <0.01 0.05

18 Insecticides/pesticides mg/l Nil Absent

19 Phenols (as C6H5OH) mg/l <0.001 0.005

20 Chromium (as Cr) mg/l <0.01 0.05

21 Copper (as Cu) mg/l <0.001 1.5

22 Selenium (as Se) mg/l <0.001 0.05

23 Arsenic (as As) mg/l <0.001 0.2

24 Barium (as Ba) mg/l <0.01 -

25 Cadmium mg/l <0.001 0.01

26 Nickel (as Ni) mg/l <0.01 -

27 Boron (as B) mg/l <0.1 -

28 Mercury (as Hg) mg/l <0.001 -

29 Silver (as Ag) mg/l <0.01 -

30 Lead (as Pb) mg/l <0.001 0.1

31 Zinc (as Pb) mg/l 0.72 15

32 Alkalinity to phenolphthalein mg/l Nil -

33 Alkalinity to methyl orange mg/l 248 -

34 Iron (as Fe) mg/l 0.18 50

35 Calcium (as Ca) mg/l 63 -

36 Magnesium (as Mg) mg/l 43 -

37 Total Nitrogen (as N) mg/l 2.4 -

38 Percent sodium % 31.59 -

39 Coliform organisms MPN/100ml 2100 5000

40 Sodium (as Na) mg/l 79 -

41 Potassium (as K) mg/l 30 -

Page 165: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

WATER QUALITY DATA Location Name : Drinking Water Kunada Village Date of Sampling : 21.05.2013

Sl. No.

Parameter Unit Result IS: 10500-1991

Norms Desirable/ Permissible

1 pH - 7.94 6.5 – 8.5/ 6.5-8.5

2 Colour Hazen Units <5 5/25

3 Temperature oC 30.5 -

4 Turbidity NTU 4 5/10

5 Total suspended solids mg/l <2 -

6 Total dissolved solids mg/l 924 500/2000

7 Total volatile solids mg/l - -

8 Dissolved Oxygen mg/l 5.2 >3.0

9 BOD - 3 days at 27oC mg/l - -

10 COD mg/l 16 -

11 Oil & grease mg/l Nil -

12 Residual chlorine mg/l Nil 0.2 min.

13 Chloride (as CI) mg/l 45 250/1000

14 Flouride (as F) mg/l 0.08 1.0/1.5

15 Sulphate (as SO4) mg/l 281 200/400

16 Sulphide (as S) mg/l Nil -

17 Cyanide (as CN) mg/l Nil 0.05

18 Insecticides/pesticides mg/l Nil Absent

19 Phenols (as C6H5OH) mg/l <0.001 0.001/0.002

20 Chromium (as Cr) mg/l <0.01 0.05

21 Copper (as Cu) mg/l <0.01 0.05

22 Selenium (as Se) mg/l <0.01 0.01

23 Arsenic (as As) mg/l <0.01 0.05

24 Barium (as Ba) mg/l <0.01 -

25 Cadmium mg/l <0.01 0.01

26 Nickel (as Ni) mg/l <0.01 -

27 Boron (as B) mg/l <0.01 1.0/5.0

28 Mercury (as Hg) mg/l <0.001 0.001

29 Silver (as Ag) mg/l <0.01 -

30 Lead (as Pb) mg/l <0.01 0.05

31 Zinc (as Pb) mg/l 0.05 5/15

32 Alkalinity to phenolphthalein mg/l Nil -

33 Alkalinity to methyl orange mg/l 294 200/600

34 Iron (as Fe) mg/l 0.04 0.3/1.0

35 Total Hardness mg/l 389

300/600

36 Calcium (as Ca) mg/l 59 75/200

37 Magnesium (as Mg) mg/l 58 30/100

38 Total Nitrogen (as N) mg/l Nil -

39 Percent sodium % 35.30 -

40 Coliform organisms MPN/100ml -0- Absent

41 Sodium,(as Na) mg/l 106 -

42 Potassium (as K) mg/l 29 -

Page 166: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

WATER QUALITY DATA Location Name : Drinking Water, Juna Kunada (Adjcent mine) Date of Sampling : 21.05.2013

Sl. No.

Parameter Unit Result

IS: 10500-1991 Norms

Desirable/ Permissible

1 pH - 8.19 6.5 – 8.5/ 6.5-8.5

2 Colour Hazen Units <5 5/25

3 Temperature oC 30.0 -

4 Turbidity NTU 4 5/10

5 Total suspended solids mg/l <2 -

6 Total dissolved solids mg/l 782 500/2000

7 Total volatile solids mg/l - -

8 Dissolved Oxygen mg/l 5.3 >3.0

9 BOD - 3 days at 27oC mg/l - -

10 COD mg/l 18 -

11 Oil & grease mg/l Nil -

12 Residual chlorine mg/l Nil 0.2 min.

13 Chloride (as CI) mg/l 68 250/1000

14 Flouride (as F) mg/l 0.12 1.0/1.5

15 Sulphate (as SO4) mg/l 233 200/400

16 Sulphide (as S) mg/l Nil -

17 Cyanide (as CN) mg/l Nil 0.05

18 Insecticides/pesticides mg/l Nil Absent

19 Phenols (as C6H5OH) mg/l <0.001 0.001/0.002

20 Chromium (as Cr) mg/l <0.01 0.05

21 Copper (as Cu) mg/l <0.01 0.05

22 Selenium (as Se) mg/l <0.01 0.01

23 Arsenic (as As) mg/l <0.01 0.05

24 Barium (as Ba) mg/l <0.01 -

25 Cadmium mg/l <0.01 0.01

26 Nickel (as Ni) mg/l <0.01 -

27 Boron (as B) mg/l <0.01 1.0/5.0

28 Mercury (as Hg) mg/l <0.001 0.001

29 Silver (as Ag) mg/l <0.01 -

30 Lead (as Pb) mg/l <0.01 0.05

31 Zinc (as Pb) mg/l 0.08 5/15

32 Alkalinity to phenolphthalein mg/l Nil -

33 Alkalinity to methyl orange mg/l 217 200/600

34 Iron (as Fe) mg/l 0.08 0.3/1.0

35 Total Hardness mg/l 301

300/600

36 Calcium (as Ca) mg/l 52 75/200

37 Magnesium (as Mg) mg/l 41 30/100

38 Total Nitrogen (as N) mg/l Nil -

39 Percent sodium % 40.76 -

40 Coliform organisms MPN/100ml -0- Absent

41 Sodium,(as Na) mg/l 104 -

42 Potassium (as K) mg/l 24 -

Page 167: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

WATER QUALITY DATA Location name : Bore Well Water, Telwasa Village Date of Sampling : 21.05.2013

Sl. No.

Parameter Unit Result IS: 10500-1991

Norms Desirable/ Permissible

1 pH - 8.14 6.5 – 8.5/ 6.5-8.5

2 Colour Hazen Units <5 5/25

3 Temperature oC 30.5 -

4 Turbidity NTU 5 5/10

5 Total suspended solids mg/l <2 -

6 Total dissolved solids mg/l 694 500/2000

7 Total volatile solids mg/l - -

8 Dissolved Oxygen mg/l 4.8 >3.0

9 BOD - 3 days at 27oC mg/l - -

10 COD mg/l 15 -

11 Oil & grease mg/l Nil -

12 Residual chlorine mg/l Nil 0.2 min.

13 Chloride (as CI) mg/l 70 250/1000

14 Flouride (as F) mg/l 0.01 1.0/1.5

15 Sulphate (as SO4) mg/l 30 200/400

16 Sulphide (as S) mg/l Nil -

17 Cyanide (as CN) mg/l Nil 0.05

18 Insecticides/pesticides mg/l Nil Absent

19 Phenols (as C6H5OH) mg/l <0.001 0.001/0.002

20 Chromium (as Cr) mg/l <0.01 0.05

21 Copper (as Cu) mg/l <0.01 0.05

22 Selenium (as Se) mg/l <0.01 0.01

23 Arsenic (as As) mg/l <0.01 0.05

24 Barium (as Ba) mg/l <0.01 -

25 Cadmium mg/l <0.01 0.01

26 Nickel (as Ni) mg/l <0.01 -

27 Boron (as B) mg/l <0.01 1.0/5.0

28 Mercury (as Hg) mg/l <0.001 0.001

29 Silver (as Ag) mg/l <0.01 -

30 Lead (as Pb) mg/l <0.01 0.05

31 Zinc (as Pb) mg/l 0.07 5/15

32 Alkalinity to phenolphthalein mg/l Nil -

33 Alkalinity to methyl orange mg/l 152 200/600

34 Iron (as Fe) mg/l 0.06 0.3/1.0

35 Total Hardness mg/l 497

300/600

36 Calcium (as Ca) mg/l 99 75/200

37 Magnesium (as Mg) mg/l 60 30/100

38 Total Nitrogen (as N) mg/l Nil -

39 Percent sodium % 31.06 -

40 Coliform organisms MPN/100ml -0- Absent

41 Sodium,(as Na) mg/l 65 -

42 Potassium (as K) mg/l 18 -

Page 168: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

EFFLUENT WATER QUALITY MONITORING DATA

NAME OF THE COMPANY : WCL YEAR : 2013

NAME OF THE AREA : WANI NORTH Q.E. : DEC

NAME OF THE PROJECT : JUNAD OCP DATE : 19.11.13

Name of the Location ; Mine water discharge

Sl. No

Parameters Analysis Result Satandard for discharge

Part-A, Schedule VI

1 pH value 8.24 5.5 – 9.0 2 Temperature (oC) 22.3oC Te<Ts + 5oC 3 Color (Hz) 9 * 4 Odour Unobjectiona

ble Unobjectionable

5 Turbidity, NTU 71 * 6 Conductivity (µs/cm) 952 * 7 Total Suspended Solids (mg/l) 66 100 8 Oil & Greese <2 10 9 Dissolve Oxygen (mg/l) 5.3 *

10 C.O.D. (mg/l) <40 250 11 B.O.D. 3 days at 27oC 4 30 12 Total Residual Chlorine (mg/l) <0.02 1 (Max.)

13 Total Kjehldal Nitrogen(mg/l) 4.5 100 14 Free Ammonia(mg/l) <0.01 5.0 15 Arsenic(mg/l) <0.0005 0.2 16 Lead(mg/l) <0.0005 0.1 17 Hexavalent Chromium (mg/l) <0.01 0.1 18 Total Chromium(mg/l) <0.06 2 19 Copper (mg/l) <0.03 3 20 Zinc(mg/l) <0.01 5 21 Selenium (mg/l) <0.0005 0.05 22 Nickel (mg/l) <0.1 3 23 Cadmium (mg/l) <0.0005 2 24 Fluoride(mg/l) 0.32 2 25 Dissolve Phosphate (mg/l) 0.54 5 26 Sulphide (mg/l) <0.005 2 27 Iron (mg/l) <0.06 3 28 Manganese (mg/l) <0.02 2

29 Nitrate Nitrogen (mg/l)

0.4 10

* Limits not specified

Page 169: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Summary At all locations, Oil and grease, phenolic compounds, cyanides, sulphides and insecticides are found to be absent and all heavy metal values except Iron and Zinc are found to be below the detectable limit. In general, the water quality at all eight locations are found to be well within the prescribed norms of GSR: 422E, IS: 10500 – 1991(permissible) and IS: 2296 - 1982.

3.8 HYDROGEOLOGY OF JUNAD DEEP OC MINE

Aquifers:

The area in and around the Junad block is mostly covered by Kamthi and

Alluvium / detrital mantle which are concealed under soil layer of limited

thickness. Whereas the area situated in the east of the river is covered by

Kamthis and Talchirs under soil layer. Generally sand / sandstone horizons serve

as aquifer zones whereas shale and clay beds act as aquicludes. Groundwater

occurs below the water table withinthe intergranular pore spaces of semi-

consolidated sandstone and also in secondary porous structures associated with

them.

Groundwater exists under both confined and unconfined conditions in the area.

Unconfined aquifer generally extends up to a depth of 25 m below ground level

(bgl) and occurs in alluvium / detrital mantle and Kamthis. Whereas confined /

semi-confined aquifer is encountered at relatively greater depths in Kamthi and

Barakarformations and is harnessed by shallow / deep tube wells. The types of

aquifers are given in the following table.

Sl.

No. Type of aquifer

Depth

range

(m)

Core zone Buffer zone

1.

Unconfined

0 - 25

Alluvium and

Kamthis

Alluvium, Kamthis

and weathered

VindhyansTalchirs.

2.

Semiconfined/

confined

Beyond

25 to

200

Sandstone

horizons in

Kamthi and

Barakars

Kamthis/Barakars,

sandstones/lime

stones of Vindhyans

and sandstone in

Talchirs.

Page 170: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Ground water levels:

The depth to water table in unconfined aquifer is being monitored four times in

a year from May’04 located in the core and the buffer zone of Junad Deep

Extn. OCM area. The average water levels in the wells measured from the area

in and around Junad Deep Extn OC area are given below.

Pre monsoon period Core Zone 14.00 to 17.80

buffer zone 3.90 to 12.65

Post monsoon Core Zone 12.50 to 15.25

buffer zone 1.50 to 8.85

The water level fluctuation between the two extreme seasons of pre monsoon

and post monsoon period for the year 2010 and 2011 varies from 0.65 to 5.60 m

with an average fluctuation of 3.4 m in Kamthis and Barakar formation and

about 7.0 m in Talchir formation

Water level trend:

Hydrographs of two permanent observation wells fixed by CMPDI, Regional

Institute-IV are presented in 3.3.1& 3.3.2 to assess the water level trends from

May’04 to Jan’12.

The water level trend of well No (M-33) situated in the core zone (village

Chargaon) of Junad Deep Extn OC mine and about 1 km N-W of existingJunad

Deep OCM indicate no impact on water table as shown in the following figure.

.

0

2

4

6

8

10

12

14

16

18

20

HYDROGRAPH OF OB WELL (No M-33) AT VILLAGE Chargaon , IN MAJRI AREA

Page 171: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

A rising trend both in post and pre-monsoon water levels has also been

observed at the station Borgaon (WN-9A) situated in buffer zone of Junad Deep

Extn (about 3 km south from the project area) it also indicate that there is no

impact on ground water level as shown in figure below.

0

5

10

15

20

25

HYDROGRAPH OF OB WELL (No WN-9A) AT VILLAGE BORGAON IN BUFFER ZONE OF

JUNAD DEEP EXTN. OCM

The water table elevation ranges from 174 to 200 m above MSL in pre-monsoon

season (CGWB report). The water table in general has a configuration similar to

that of topography but with reduced relief. The direction of groundwater flow in

the water table aquifer is towards the major river Wardha i.e. east and south-

easterly in the area west of the river and west and south-westerly in the east of

the river. Moderate to low hydraulic gradient indicates moderate hydraulic

conductivity of formations. Normally groundwater flows in from recharge zone to

discharge area. The drainage pattern and effluent nature of the Wardhariver

corroborates the flow direction of ground water. It was reported that the dug

wells tapping the unconfined aquifer are with poor to moderate yield. The water

levels in the core zone Junad Deep Extn OC are at deeper level due to

difference of relief between the surface and the base flow of river. The tube

wells located in the core zone of Junad Deep Extn area show water levels from

16 to 17m bgl.

Page 172: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

General aquifer parameters-

No detailed hydrogeological investigations have been carried out at Junad

Deep Extn OC mine area. However, the aquifer parameters evaluated by

CMPDI in Wardha Valley Coalfield and Baranj block (nearest to study area) in

particular have been considered and attributed for the study area. The

projected hydraulic parameters of the aquifers in Kamthi&Barakar formations

are as follows:

Hydraulic conductivity: Kamthis - 5.0 m/day

Barakar - 2.0 m/day

Storage coefficient - 7.7 x 10-2 to 9.8 x 10-4

Specific yield : Alluvium(clayey) - 6 %

Kamthis (sandst.) - 4 %

Talchir (sandy sh.) - 2 %

The tubewells constructed in Gondwanas and also borewells tapping different

aquifers/formations in and around Junad Deep Extn OC cumulatively have

registered moderate yield ranging from 2 LPS to 5 LPS. However, the borewells

tapping Talchirs in general recorded low yield varying from negligible to 3.0 LPS

with some exceptions of moderate yield due to secondary porosity and

favourable physical settings. By judicious judgment of these facts and review of

formation logs, the above parameters have been arrived from the wide range

of regional values.

GROUND WATER RESOURCES IN THE AREA

Ground Water Recharge

Precipitation is the main source for groundwater recharge in the area. The

average annual rainfall of the area is around 1150 mm. The quantity of rain

water falling over the study area of 314 Sq.km (10 km radius) is 361.10 million

cubic meters (MCM). The quantum of groundwater recharge (recoverable

reserve) depends on various factors viz. nature of soil cover, geology,

topography, vegetation, intensity and duration of rainfall etc. As per the

Groundwater Estimation Committee, Govt. of India, the rainfall infiltration factor

for Alluvium/Kamthis and Talchirs is around 13% and 4% respectively. Major part

of the area (about 77%) is covered by Kamthis and alluvium. Accordingly,

ground water recharge in Alluvium, Kamthis and Talchir formations has been

worked out to be 41.59 MCM as given below.

Ground water recharge from other sources is negligible since canals;

ponds/dams and other water conservation structures are not available in the

area. Further, negligible area (110 ha only) is under irrigation. However, the

recharge from return waters from irrigation and mine water pumping has been

worked out to be around 0.11 MCM and 1.78 MCM respectively which is equal

to 1.89 MCM. Thus the gross annual recharge of water comes to 41.59 MCM out

Page 173: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

of which about 10% (4.16 MCM) goes as the natural discharge to streams / rivers

and other losses thereby net ground water availability works out to 37.43 MCM.

a) Recharge from rainfall : 39.70MCM

i)Alluvium / Kamthis (244 Sq.Km.) - 36.48 MCM

ii) Talchirsarea (70 Sq.Km)) - 3.22 MCM

b) Recharge from other sources : 1.89MCM

i) Irrigation return flow - 0.11 MCM

ii) Return flow from mines effluent - 1.78 MCM.

c) Gross groundwater recharge (a+b) : 41.59 MCM

Groundwater draft:

The groundwater withdrawal is generally for domestic, industry and irrigation

requirement and is quantified as under in Table-4.2.0.1.

Water requirement for domestic and irrigation purpose.

Sl No. Purpose No./Area Water

consumption

per capita

Total qty. of withdrawal

(MCM)

1.

a) Domestic

(Human Population)

60738

Nos.

70 Lit/day

1.55

b) Domestic (Animals) 34540 Nos

20 Lit/day

0.25

2.

Irrigation (for 120

days)

110ha.

40000

Lit/ha/day

0.53*

3 Mine discharge 10nos combined 8.90

Total 11.23

Ground water withdrawal is mostly for domestic use since negligible area (110

ha only) is under irrigation.

In addition to the above, groundwater is being pump out by the existing coal

mines in the on west and east of river Wardha to the tune of 8.9 MCM.

Page 174: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Groundwater balance :

i) Gross groundwater recharge : 41.59 MCM

ii) Natural discharge to drains & other

losses (Approx.10 % of item (i) ) : 4.16 MCM

iii) Net annual groundwater availability : 37.43 MCM

iv) Allocation/ projection upto next

25 years for domestic & industrial use : 2.30 MCM

v) Annual groundwater draft for all uses : 11.23 MCM

vi) Groundwater balance (Item iii-iv & v) : 23.90 MCM

Level/Stage of Ground Water Development-

It is seen from the figures of net annual ground water availability and gross

annual ground water draft (11.23 MCM) that surplus ground water to the tune of

23.90 MCM is available for future utilization and development. Thus the present

stage of ground water development in and around the project has been

around 30% which can be categorized as safe area.

As per GSDA and CGWB report of Yavatmal and Chandrapur districts of

Maharashtra, the stage of ground water development in Bhadravati and

WaniTahsilin which Junad Deep Extn Project and its buffer zone lie is 5.95% and

10 % respectively and classified as safe category.

GROUND WATER BALANCE OF JUNAD DEEP EXTN.OCM

(All values in MCM)

QUANTITY OF WATER FALLING OVER

THE AREA OF 314 sq.km. FROM RAINFALL

OF 1.15 m, Total = 361.1 MCM

Actual Evapotranspiration

Surface run-off

RAINFALL RECHARGE

39.70

RECHARGE FROM OTHER

SOURCES 1.89

Infiltration

GROSS RECHARGE

41.59

Alluvium/Kamthi-13% and Talchirs-4%

NET ANNUAL GROUND

WATER AVAILABILITY 37.43

90 %NATURAL DISCHARGE AND

THERS LOSSES 4.16

PRESENT

DOMESTIC 1.80

INDUSTRIAL

NILIRRIGATION

0.53EXISTING MINE

PUMPING 8.90

GROSS DRAFT

11.23

TOTAL DRAFT

13.53

GROUND WATER BALANCE / AVAILABILITY 23.90

Allocation for domestic & industrial

water supply upto next 25 years 2.30

10 %

Addition Subtraction

Page 175: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Dynamic & Static resources:

The dynamic and static reserves for the core and buffer zones are estimated by

utilizing the aquifer parameters mentioned at the head of 3.3. The opencast

mine actsas large diameter well/ sink wherein all the aquifers overlying the

working seam would be converted into unconfined state and the inflow to the

mine is contributed from the saturated overburden formation i.e. multiple

aquifer system. However the unconfined aquifer is the most affected in

opencast mining area. The groundwater status in the area has been computed

as under.

The average mine depth of 130 m was considered as exploitable depth for

static reserve estimation in core zone with an area of 462 ha.

Whereas for the buffer zone with an area of 309.38Sq.km. (314.00-4.62), the floor

of unconfined aquifer (25.0 m) has been considered as extractable depth. The

pre-monsoon water level (average) is about 8.50 m bgl in the area covered by

Alluvium/Kamthi and Talchir formations and the water table fluctuation is

around 3.40 m and 7m respectively between the two extreme seasons. The

dynamic & static resources estimated for core and buffer zones are given in

Table below.

Dynamic & Static resources estimated for core and buffer zones

Zone Dynamic reserve Static reserve

Area

(Sq.km)

Wate

r level

Fluc.

(m)

Sy

Potenti

al

MCM

Area

(Sq.km)

Extracta

ble

thick. of

aquifer

below

Fluc.

zone (m)

Sy

Potenti

al

MCM

Core 4.62 5.00 0.04 0.92 4.62 120 0.04 22.18

Buffer 239.48(A) 3.40 0.04 32.57 239.48(A) 10 0.04 95.79

70(B) 7.00 0.02 9.8 70(B) 10 0.02 14.00

Total

43.29

say

43.3

131.97

A) Area covered by alluvium/Kamthis

B) Area covered by Talchirs

Thus, the dynamic and static ground water reserves as estimated are 43.3 and

131.97 respectively.

Page 176: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

WATER QUALITY

Generally, the water quality is mostly alkaline in nature with pH value of 7.53 to

7.79 of potable quality with moderate to high concentration of total dissolved

solids values ranging from 550 mg/l to 3560 mg/l.

GROUND WATER QUALITY MONITORING DATA

NAME OF THE COMPANY : WCL YEAR : 2013-14

NAME OF THE AREA : WANI NORTH AREA

Sl.

No Test Parameters

Analysis Results

Sampling Code, Location & Sample collection date

Detection

Limit

Standard ( IS : 10500 : 2012 )

WN-1

WANJRI

9.1.14

WN-5

KOLAR

12.1.14

WN-9A

BORGAON

10.1.14

Desirable

limit

Permissible limit

in the absence

of alternate

source

1 Colour ( Hz ) 1 1 3 1.0 5 15

2 Odour Agreeable Agreeable Agreeable Qualitativ

e Agreeable Agreeable

3 Turbidity (NTU) 1 3 4 1.0 1 5

4 pH Value 7.79 7.53 7.76 0.01 6.5 to 8.5 No relaxation

5 Total Hardness as CaCO3–

mg/l

276 800 276 4.0

200 600

6 Iron (as Fe) -mg/l BDL BDL BDL 0.06 0.3 No relaxation

7 Chlorides (as Cl)- mg/l 44 1150 44 2.0 250 1000

8 Residual Chlorine -mg/l

(min.) 0.03 0.01 BDL 0.02

0.2 1

9 Fluoride (as F)- mg/l 0.82 0.84 0.46 0.02 1.0 1.5

10 TDS -mg/l 550 3560 470 25 500 2000

11 Calcium (as Ca) -mg/l 65.6 208.0 72.4 1.6 75 200

12 Magnesium (as Mg) –mg/l 27.21 68.04 29.16 1.0 30 100

13 Copper as(Cu) -mg/l BDL BDL BDL 0.03 0.05 1.5

14 Manganese as (Mn)- mg/l BDL BDL BDL 0.02 0.1 0.3

15 Sulphate (as SO4) -mg/l 53.62 272.5 103.12 2.0 200 400

16 Nitrates (as NO3) - mg/l 22.78 63.78 9.16 0.3 45 No relaxation

17 Cadmium as (Cd)- mg/l BDL BDL BDL 0.005 0.003 No relaxation

18 Selenium as (Se) -mg/l BDL BDL BDL 0.005 0.01 No relaxation

19 Arsenic as (As) -mg/l BDL BDL BDL 0.0005 0.01 0.05

20 Lead as (Pb) -mg/l BDL BDL BDL 0.005 0.01 No relaxation

21 Zinc as (Zn) -mg/l BDL 1.1151 BDL 0.01 5 15

22 Chromium as (Cr +6) -mg/l 0.002 0.004 0.005 0.01 0.05 No relaxation

23 Aluminum as (Al)- mg/l BDL BDL BDL 0.008 0.03 0.2

24 Boron as (B) -mg/l BDL BDL BDL 0.2 0.5 1.0

25 Alkalinity -mg/l 144 124 116 4 200 600

26 Conductivity -µs/cm 850 5.48ms 721 - - -

Page 177: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

MINE DRAINAGE/ PUMPING

The entire quarriable area is covered by Kamthis varying in thickness from about

10.0 m to 25.0 m which is overlained by soil/alluvium having thickness of 4.55 m

to 7.60 m.. The semiconsolidatedGondwanas are mostly stratified formations

underlying the alluvium/soil. The permeable beds (Sandstone horizons) act as

individual hydrogeological units and develop multi-aquifer system by the

intercalation/interfringing of shale beds. As such under these circumstances, the

groundwater flow/velocity along the bedding planes is higher than across the

plane. It is imperative that horizontal hydraulic conductivity is many folds higher

than the vertical hydraulic conductivity.

The opencast mine acts as large diameter well/sink resulted in by cutting

/extraction of different aquifer zones/formations overlying the working coal

seam. As soon as depression / pit is created due to mine cut, the initial

discharge is generally heavy due to concentration of flow to that region thereby

creating depletion/draw-down in water levels in the surrounding area and the

inflow stabilizes due to partial desaturation over the period of progressive

mining. With increase in depth of incision, the semiconfined aquifer would also

be exposed /punctured thereby the total system would be converted into water

table condition and a cone of depression would be formed by the gravity

drainage from different aquifer zones. In opencast mining, the unconfined

aquifer is the most affected and the semiconfined aquifer is least affected. The

mine effluent & influence is directly proportional to the mine area and depth.

The groundwater inflow computation has been done by utilising the above

mentioned aquifer and mine parameters. The classic Theis equation has been

modified by introducing mine expansion rate and the groundwater inflow to the

mine has been estimated to be around 3000 m3/day (1.1 MCM) at the at an

average quarry depth of 130m.

RADIUS OF MINE INFLUENCE

In the opencast mines, the different aquifers overlying the working coal seam

would be contributing groundwater to the mine by gravity drainage since they

are exposed/removed at the mine. The present mine water inflow during non

monsoon period from the Junad OCM is about 1350 m3/day. The anticipated

groundwater inflow as worked out at the average quarry depth of about 130m

would be about

3000 m3/day. As such due to this pumping, cone of depression would be

formed. The shape and extent of the cone would depend on mainly hydraulic

conductivity and specific yield of aquifers and recharge discharge boundries

and geological structures such as major faults etc. The maximum radius of

influence may expand less than 1000 m from the edge of the mine at the final

depth mine of 170m and at the end of mine age. However the average cone

of influence would be around 600m from the mine edge as determined.

Page 178: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Generally steep draw down cone would be formed in poor potential aquifers

thereby, the influence area would be up to smaller distance and reverse is

established in respect of aquifers with high hydraulic conductivity. The radius of

mine influence area has been estimated for Junad Deep Extn OCM based on

the above mentioned aquifer and mine parameters and works out to about

initially from 300 at the initial depth of depth of 70m to about 1000 m at the final

depth of 170m It may be appropriated to mention here that the presence of

prominent boundaries such as river/water bodies, faults and also interfringing of

sandstone and shale beds may restrict the propagation of draw down cone or

radius of mine influence.

Mine induced effect may be distinctly noticed within a distance of 200 to 500m

from the mine edge in the down-dip side and becomes milder/ insignificant

thereafter. However, the effect is limited/negligible in the up-dip side of the

incrop zone due to shallow mine depth & area and further mine development is

towards dip-side only

3.9 BASE LINE NOISE LEVEL STATUS

3.9.1 Rationale behind Sampling

To know the background ambient noise level at the proposed Junad Deep and

surrounding environment, 6 locations (one in core zone and five in buffer zone)

were identified for baseline study.

AMBIENT NOISE LEVEL MONITORING STATIONS

SI.

No. Location Name Location Code

1. Core Zone N- 1

2. Pimpri Village N- 2

3. Bargaon Village N- 3

4. Pimpalgaori Village N- 4

5. Kunad Village N- 5

6. Telwasa Village N- 6

Data presentation & analysis

The generated noise level data are given in table below.

Noise level status

Location

Noise level dB(A) Noise level

Standards Daytime Nighttime

Daytime Nighttime

Core zone 64.9 - 67.8 54.8 - 57.4 75 70

Buffer zone 43.2 - 49.1 38.8 - 41.9 55 45

Page 179: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Mean Leq noise levels at day time and night time are ranging from 64.9 to 67.8

dB(A) and 54.8 to 57.4 dB(A) respectively in the core zone. Mean Leq noise levels

at day time and night time are ranging from 43.2 to 49.1 dB(A) and 38.8 to 41.9

dB(A) respectively in the Buffer zone. While comparing with IS: 4954 -1986 norms

for acceptable outdoor noise levels all values are found to be well within the

prescribed limits.

Summary

While comparing with IS: 4954 -1986 norms for acceptable outdoor noise levels the

Leq values are found to be within the limits.

NOISE LEVEL STATUS

Project : Junad OCP Season : Winter `09-10

S.No. Location name Daytime Leq. Nighttime Leq.

1 Corezone(N1) 63.8 58.6

2 Chargaon village (N2) 54.2 48.6

3 Dhorwasa village (N3) 48.6 44.2

4 Navi Ukni (N4) 52.1 46.3

5 Besa Village (N5) 46.8 41.2

6 Pimpalgaon village (N6) 45.2 40.6

Base Line NOISE LEVEL DATA

Location: Pimri Village

Sl. No. Time (Hrs.)

Leq Noise Level, dB(A)

May`13 June`13

1.

Day

06-10 47.9 48.2

2. 10-14 48.1 49.5

3. 14-18 49.3 50.3

4. 18-22 46.5 48.4

Leq. Noise (Mean) 47.9 49.1

5.

Night

22-02 39.2 38.8

6. 02-06 40.5 39.0

Leq. Noise (Mean) 39.8 38.8

Page 180: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Location: Borgaon Village

Sl. No. Time (Hrs.) Leq Noise Level, dB(A)

MAY- 2013 JUNE- 2013

1.

Day

06-10 40.9 41.1

2. 10-14 44.3 43.8

3. 14-18 46.3 45.9

4. 18-22 41.1 43.3

Leq. (Mean) 43.2 43.5

5.

Night

22-02 40.9 39.8

6. 02-06 38.2 41.0

Leq. (Mean) 39.6 40.4

NOISE LEVEL DATA

Location: Pimpalgaon Village

Sl. No. Time (Hrs.) Leq Noise Level, dB(A)

MAY- 2013 JUNE- 2013

1.

Day

06-10 41.9 43

2. 10-14 43.9 45.7

3. 14-18 46.9 47.8

4. 18-22 44.4 45.2

Leq. (Mean) 44.3 45.4

5.

Night

22-02 42.6 40.0 6. 02-06 41.1 41.2

Leq. (Mean) 41.9 40.6

Page 181: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Location: Kunada Village

Sl. No. Time (Hrs.) Leq Noise Level, dB(A)

MAY- 2013 JUNE- 2013

1.

Day

06-10 42.7 43.3

2. 10-14 45.4 45.2

3. 14-18 47.2 47.1 4. 18-22 43.9 41.0 Leq. (Mean) 44.8 44.2

5.

Night

22-02 40.1 38.3

6. 02-06 41.3 39.4

Leq. (Mean) 40.7 38.9

NOISE LEVEL DATA

Location: Telwasa Village

Sl. No. Time (Hrs.) Leq Noise Level, dB(A)

MAY- 2013 JUNE- 2013

1.

Day

06-10 41.7 42.8

2. 10-14 43.7 45.5

3. 14-18 46.7 47.6

4. 18-22 44.2 45.0

Leq. (Mean) 44.1 45.2

5.

Night

22-02 42.1 39.5

6. 02-06 40.6 40.7

Leq. (Mean) 41.4 40.1

3.10 SOIL QUALITY

Rationale Behind Sampling

Soil characteristics, erosion aspects, soil fertility etc., have direct bearing on the

environment. Knowledge of soil parameters is essential for the planning and

implementation of a-forestation. Further, major mining activities affect the soil

regime of the surrounding areas directly or indirectly. Hence, it becomes important

to study the soil characteristics.

Page 182: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

By keeping the above aspects in view, three locations are selected in the study

area. Locations are selected in such a way that different type of soils for supporting

different species of vegetation are covered. The soil quality monitoring stations are

furnished below.

Barren Land, Core zone S1

Proposed OB dump, Core zone S2

Existing OB Dump, Core zone S3

Data presentation & analysis

The soil quality data collected are given in Table below

Soil quality status

S.No. Parameters Range of

Concentration

1 pH 7.28 - 7.69

2. Organic Carbon (%) 2.1 - 3.5

3. Potassium (kg/ha) 195 - 262

4. Nitrogen (Kg/ha) 288 - 592

5. Magnesium (Kg/Ha) 319 - 436

6. Texture Class Sandy Loam

Summary

The soil quality in the project area appears to be good and would support after

suitable reclamation measures.

Page 183: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

SOIL QUALITY DATA

Location: Barren Land, Core zone (S1) Date : 22.05.2013

Sl.

No. Parameter

Depth, cm

0-30 30-60 60-90

1 pH 7.36 7.48 7.53

2 Temperature (oC) 34.0 35.0 34.5

3 Electrical conductivity (m-mhos/cm at

20C)

156 168 173

4 Nitrogen, kg/ha 288 298 304

5 Phosphorus, kg/ha 5.3 5.6 5.7

6 Potassium, kg/ha 176 184 182

7 Calcium, kg/ha 526 584 576

8 Magnesium, kg/ha 418 436 422

9 Organic matter (%) 2.1 2.3 2.2

10 Grain size distribution

Sand

Clay

Silt

13

71

16

12

73

15

11

77

12

11 Sodium Absorption Ratio (SAR) 0.13 0.14 0.12

12 Natural Moisture content (%) 3.2 3.7 3.6

13 Field Capacity (%) - 4.2 -

14 Wilting Co-efficient (%) - 1.20 -

15 Available Water Storage Capacity (%) - 4.8 -

16 Bulk Density (gms /cc) 1.22 1.24 1.25

17 Cation exchange Capacity (cm/hr) 2.38 2.42 2.39

18 Infiltration rate (cm/hr) - 2.9 -

Page 184: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

SOIL QUALITY DATA

Location : Proposed OB dump, Core zone (S2) Date: 22.05.2013

Sl.

No. Parameter

Depth, cm

0-30 30-60 60-90

1 pH 7.28 7.32 7.43

2 Temperature (oC) 33.5 34.0 34.5

3 Electrical conductivity (m-mhos/cm at

20C)

356 372 368

4 Nitrogen, kg/ha 563 576 558

5 Phosphorus, kg/ha 5.3 5.9 5.1

6 Potassium, kg/ha 236 262 244

7 Calcium, kg/ha 726 742 716

8 Magnesium, kg/ha 326 342 319

9 Organic matter (%) 3.2 3.5 3.1

10 Grain size distribution

Sand

Clay

Silt

23

54

23

19

51

30

15

50

35

11 Sodium Absorption Ratio (SAR) 2.3 2.7 2.4

12 Natural Moisture content (%) 3.0 3.2 3.1

13 Field Capacity (%) - 7.4 -

14 Wilting Co-efficient (%) - 1.4 -

15 Available Water Storage Capacity (%) - 4.7 -

16 Bulk Density (gms /cc) 1.26 1.29 1.27

17 Cation exchange Capacity (cm/hr) 1.32 1.35 1.32

18 Infiltration rate (cm/hr) - 7.3 -

Page 185: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

SOIL QUALITY DATA

Location : Existing OB Dump, Core Zone (S3) Date: 22.05.2013

Sl.

No. Parameter

Depth, cm

0-30 30-60 60-90

1. pH 7.58 7.69 7.58

2. Temperature (oC) 32.5 32.0 32.0

3. Electrical conductivity (m-mhos/cm

at 20C)

224 232 229

4. Nitrogen, kg/ha 586 592 578

5. Phosphorus, kg/ha 6.3 6.4 6.2

6. Potassium, kg/ha 195 216 214

7. Calcium, kg/ha 812 832 838

8. Magnesium, kg/ha 356 376 382

9. Organic matter (%) 3.4 3.3 3.2

10. Grain size distribution

Sand

Clay

Silt

53

36

11

48

40

12

50

35

15

11 Sodium Absorption Ratio (SAR) 2.3 2.5 2.4

12 Natural Moisture content (%) 3.7 3.9 3.8

13 Field Capacity (%) - 8.3 -

14 Wilting Co-efficient (%) - 0.7 -

15 Available Water Storage Capacity (%)

- 6.3 -

16 Bulk Density (gms /cc) 1.26 1.28 1.27

17 Cation exchange Capacity (cm/hr) 1.32 1.35 1.33

18 Infiltration rate (cm/hr) - 7.6 -

Page 186: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

3.11 Flora & Fauna

A. INTRODUCTION

Topographically the areas are encompassed by undulating terrain of flat ridges

with fragments of natural vegetation, which is characterized by tropical dry

deciduous forest type. Mean annual temperatures are recorded between 250c

to 400c. Average annual precipitation recorded from 800 to1200mm mostly

during south west monsoon period. Generally the soils are sandy loam but

predominantly sandy brown at slopes of hilly terrain.

B. OBJECTIVE(S):

To generate baseline data on flora and fauna in core and buffer zone of the

project.

To assess environmental impacts and potential damages to terrestrial flora,

fauna and aquatic bodies

To suggest environment mitigation measures and conservation plan for the

biodiversity, of the core and buffer zones.

C. METHODOLOGY:

A natural eco system is a structural and functional unit of nature. It has

components, which exists in harmony and survives by inter dependents. Eco

systems have self sustaining ability and control the numbers of organisms at any

level by cybernetic rule. The effects of these are – that an eco system does not

become imbalance.

Primary survey was conducted to:

Walk through the areas to assess the biological resources which

include plants & animals.

Study of fauna, and

Collection of ethno botanical data

The data on flora & fauna was collected based on field survey in the core and

buffer zone (10 KM radius) and from local offices of forest department. The

results of the study are given in Tables below separately for Core & Buffer Zone

for flora & fauna.

Page 187: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

FLORA OF CORE ZONE

Flora Local Name Botanical Name Family

Agricultural crops

Cereals Makka (Maize) Zea mays Poaceae

Jawas Linum usitatissimum Linaceae

Pulses Tuar Cajanus cajan Fabaceae

Mung Phaseolus mungo Fabaceae

Commercial crops / Cash Crops

Vegetables

Aloo (Sweet

Potato) Ipomoea batatas Convolvulaceae

Onion/ Kanda Allium cepa -

Baigan Solanum melongena Solanaceae

Tamator (Tomato) Lycopersicum

esculentum Solanaceae

Bean Lablab purpureus Leguminosae

Band Gobi

(Cobbage) Brassica spp. Cruciferae

Bhindi Abelmoschus esculentus Malvaceae

Pumpkin Cucurbeta moschata Cucurbetaceae

Karela Momordica charantia Cucurbetaceae

Oil yielding

plants Sarson (Mustard) Brassica compestris Brassicaceae

Cash Crops Arandi Ricinus communis Euphorbiaceae

Kappas Gossypium hirsutum Malvaceae

Spices

Dhaniya Coriandrum sativum Umbelliferae

Lahsun (Garlic) Allium stivum Liliaceae

Mirchi Capsicum annum Solanaceae

Haldi (Turmeric) Curcuma domestica Zinziberaceae

Fruits

Jam (Guava) Psidium guajava Myrataceae

Bor Ziziphus mauritiana Rhamnaceae

Jackfruit (Kathal) Artrocarpus hetarophylla Moraceae

Bel Aegl marmalas Rutaaceae

Jambhul/Jamun Syzygium cumini Myrtaceae

Amba Magnifera indica Anacardiaceae

Lemon Citrus Lemon Rutaceae

Sitaphal Annona squamosa Annonaceae

Plantation

Planted by

WCL

Ashok Sarracca indica -

Neem Azadirachta indica Meliaceae

Karanj Pongamia pinnata Fabaceae

Babul Acacia nilotica Fabaceae

Page 188: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Flora Local Name Botanical Name Family

Natural vegetation / Forest type

Herbs

Tulsi Ocimum sancturm Lamiaceae

Bhui neem Andrographis

paniculata

Acanthaceae

Gajar gawat Parthenium

hysterophorus

Compositeae

Dhudhi Euphorbia hirta Euphorbiaceae

Shrubs

Katumbar Ficus hispida Moraceae

Arandi Ricinus communis Euphorbiaceae

Bhor Ziziphus jujuba Rhamnaceae

Trees

Sagwan Tectona grandis Verbenaceae

Amba Magnifera indica Anacardiaceae

Sisam Dalbergia sissoo Fabaceae

Karanj Pongamia pinnata Fabaceae

Peepal Ficus religiosa Moraceae

Maharukh Ailanthus excelsa Simarubiaceae

Ashok Sarracca indica -

Neem Azadirachta indica Meliaceae

Arjun Terminalia arjuna Combretaceae

Endangered

species Nil Nil Nil

Endemic

species Nil Nil Nil

Page 189: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

FLORA OF BUFFER ZONE

Flora Local Name Botanical Name Family

Agricultural crops

Cereals

Dhan (Paddy) Oryza sativa Poaceae

Makka (Maize) Zea mays Poaceae

Jewas Linum usitatissimum Poaceae

Ragi (Mundua) Eleusine coracana Poaceae

Pulses

Urad (Black Gram) Vigna mungo Fabaceae

Chana Cicer arietinum Fabaceae

Tuar (Red Gram) Cajanus cajan Fabaceae

Kulthi (Horse Gram) Dilichos biflorus Fabaceae

Mung (Green

Gram)

Vigna radiata Fabaceae

Commercial crops

Vegetables

Baigan Solanum melongena Solanaceae

Aloo (Sweet

Potato) Ipomoea batatas Convolvulaceae

Kanda (Onion) Allium cepa

Tamator (Tomato) Lycopersicum

esculentum Solanaceae

Bean Lablab purpureus Leguminosae

Band Gobi

(Cobbage) Brassica spp. Cruciferae

Bhindi Abelmoschus

esculentus Malvaceae

Jhinga Luffa acutangula Cucurbetaceae

Karela Momordica charantia Cucurbetaceae

Kohra Benincasa hispida Cucurbetaceae

Kundri Coccinia grandis Cucurbetaceae

Kaddu Hibiscus esculentus Malvaceae

Nenua Luffa cylindrica Cucurbetaceae

Kheera Cucumis stiva Cucurbetaceae

Kheera Cucrbaltus sativus Cucurbetaceae

Phool Gobi B. oleracea var, botrytis Cruciferae

Muli Raphanus sativus Cruciferae

Oil yielding

plants

Sarson (Mustard) Brassica compestris Brassicaceae

Arandi Ricinus communis Euphorbiaceae

Soyabean Glucine max Fabaceae

Cash Crops Soyabean Glucine max Fabaceae

Kappas Gossypium hirsutum Malvaceae

Spices

Mirch (Capsicum) Capsicum species Solanaceae

Dhaniya Coriandrum sativum Apiaceae

Lahsun (Garlic) Allium stivum Alliaceae

Haldi (Turmeric) Curcuma domestica Zingiberaceae

Adrak (Ginger) Zingiber officinale Zingiberaceae

Fruits Aam Magnifera indica Anacardiaceae

Anar Punica granatum Lythraceae

Page 190: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Amrud (Guava Psidium guajava Myrataceae

Jamun (Black Berry) Sysygium jambolana Myrtaceae

Kathal (Jackfruit) Articarous

heterophyllus

Moraceae

Bel Angle marmelos Rutaaceae

Papaya Carica papaya Caricaceae

Flora Local Name Botanical Name Family

Plantation

Planted by

WCL

Shisam Dalbergia sisso Leguminosae

Mango Magnifera indica Anacardiaceae

Amaltas Casia fistula Leguminosae

Kathal (Jackfruit) Articarous

heterophyllus

Moraceae

Gulmohar Delonix regia Caesalpiniaceae

Arjun Terminalia arjuna Combretaceae

Babul Acasia nilotica Momoseae

Karanj Pongamia pinnata Fabaceae

Sagwan Tectona grandis Verbenaceae

Natural vegetation / Forest type

Flora Local Name Botanical Name Family

Trees (Top

Story)

Karanj Pongamia pinnata Fabaceae

Sitaphal Annona squamosa Annonaceae

Bija Pterocarpus marsupium Leguminosae

Katang bamboo Bambusa arundinacea Graminae

Aam Mangifera indica Anacardiaceae

Bhilma Semicarpus ancardium Anacardiaceae

Mohwai

Lannea

coromandelica Anacardiaceae

Ashok Polythia longifolia -

Gulmohor Delonix regia Caesalpiniaceae

Apta Bauhinia racemosa Leguminosae

Chinch (Imli) Tamarindus indica Leguminosae

Dhawda Anogiessus latifolia Combretaceae

Ain Terminalia alata Combretaceae

Arjun/kahu T. arjuna Combretaceae

Behada T. bellarica Combretaceae

Tendu Diospyros melanoxylon Ebenaceae

Awla Phyllanthus emblica Euphorbiaceae

Palas Butea monosperma Leguminosae

Sisam Dalbergia sissoo Leguminosae

Khair A. catechu Leguminosae

Hiwar A. leucophloea Leguminosae

Babul A. nilotica Leguminosae

Sirish Albizzia lebbeck Leguminosae

Sagwan Tectona grandis Verbenaceae

Page 191: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Wad Ficus benghalensis Urticaceae

Neem Azadirachta indica Meliaceae

Pimpal F. religiosa Moraceae

Shevga Moringa oleifera Moringaceae

Sirish A. procera Leguminosae

Jambhul/jamun Syzygium cumini Myrtaceae

Bel Aegle marmelos Rutaceae

Kumbhi Careya arborea Myrtaceae

Limbu Citrus aurantifolia Rutaceae

Austrelian babul Acacia auriculoformis Mimosaceae

Flora Local Name Botanical Name Family

Herbs

(Lower Story)

Kukada Celosia argentia -

Aradhi Achyranthus aspera -

Amaltas Cassia fistula Leguminosae

Tarota C tora -

Kamarmodi Tridax procumbens Astraceae

Gajar gawat

Parthenium

hysterophorus Astraceae

Tulsi Ocimum basilicum Lamiaceae

Ratantulsi O.bassilicum Lamiaceae

Kala dhotra Datura metal Solanaceae

Ratrani Cestrum nocturnum Solanaceae

Gokhru Tribulus teristris Zygophyllaceae

Shrubs

(Middle Story)

Pandra kuda

Holarrhena

antidysenterica Apocynaceae

Kanher Nerium indicum -

Bharati Maytenus emarginata Celastraceae

Ratanjyoti Jatropha gossypifolia Euphorbiaceae

Katumbar Ficus hispida Moraceae

Lokhandi Ventilago denticulata Rhamnaceae

Bhor Ziziphus jujuba Rhamnaceae

Eroni Z. oenoplia Rhamnaceae

Mehndi Lowsonia immermis -

Nirgundi Vitex nigunda -

Climbers

Amar vel Cuscuta reflexa Convolvulaceae

Indrayani Citrullus calexynthis -

Jangli kundru Cephalandra indica Cucurbitaceae

Dudhi Cryptolepis buchanani Periplocaceae

Rabarachavel

Cryptostegia

grandiflora Asclepiadaceae

Arasphari Olax scandens Periplocaceae

Grasses

Doob Cynodon dactylum Gramineae

Bans/Bamboo Dendrocalamus strictus Gramineae

Sabai Eulaliopsis binata Gramineae

Munj Sacchanum munja Gramineae

Page 192: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Jharoo grass Thysanolaena agrostis Gramineae

Chor kanta Chrysopogon

auciculatus

Gramineae

Endangered

species Nil Nil

Endemic

species Nil Nil

FAUNA OF CORE ZONE

Fauna Common Name Zoological Name

LISTED UNDER WILDLIFE PROTECTION ACT,1972

Terrestrial Fauna

Schedule-I Nil -

Schedule-II Nil -

Schedule-III Nil -

Sch.-II, Part II, Sec. 2C Jungle cat Felis chaus

Schedule-IV, Section 6A Indian Grey Mongoose Herpestes edwardsi

Schedule-V, Section 6,

Section 3

Indian Mouse Bandicota bengalensis

House rat Rattus rattus

Schedule-V, Section 3 Fulvous Fruit Bat Rousettus Leschenaulti

Amphibians & Reptiles

Schedule-II Nil Calotes verosicolor

Schedule-IV Toad Bufo melanostictus

Avi Fauna

Schedule-IV, Section 11

Bhagule Ardea purpurea

Koel Eudynamys scolopacea

Kabutar Columbia livia

House swift Apus affinis

Titavi Vanellus indicus

Bhardwaj Centropus sinesis

Pandubi Prodiceps ruficollis

Schedule-V Kavvwa Corvus splendens,

NOT LISTED UNDER WILDLIFE PROTECTION ACT,1972

Mammals / (Domestic

Animals)

Goat Capra species

Bull Bos indicus

Cow Bos indicus

Buffalo Bubalus bubalis

Birds Tota (Parrot) Pisttaculus krameri

Aquatic fauna

Marad Channa punctatus

Magur Clarias batrachus

Katla Catla catla

Invertebrates

Cockroach Blata orientalis

Madhumakkhi Apis indica

Tilchatta Blata orientails

Chinti Solpopsis Spp.

Honey bee Apis dorsata

Page 193: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Lahi Kerria laxxa

Birni Polistis Spp.

Jugnu Photinus Spp.

Gojar Scolopendra Spp.

ENDANGERED SPECIES Nil -

ENDEMIC SPECIES Nil -

MIGRATORY SPECIES Nil -

FAUNA OF BUFFER ZONE

Fauna Common Name Zoological Name

LISTED UNDER WILDLIFE PROTECTION ACT,1972

Terrestrial Fauna

Schedule-I Nil -

Schedule-II

Lomdi (Common Fox) Vulpes bengalensis

Siyar (Jackal) Vulpes vulpes

Jungle Cat Felis chaus

Common langur Presbytis chtellus

Ban suar Sus scrofa

Schedule-IV

Mongoose Herpestes edwardsi

Squirrel Funambulus pennanti

House Rat Rattus species

Mice Mus Musculas

Schedule-V, Section 3 Fulvous Fruit Bat Rousettus Leschenaulti

Amphibians & Reptiles

Schedule-II

Common Garden

Lizards

Varanus species

Cobra Naja species

Dhamon or Rat Snake Ptyas Mucosus

Schedule-IV

Tode Bufo melanostictus

Karait Bungurus Caeruleaus

Water snake Natrix piscator

Dhorwa Natrix Sp.

Avi Fauna

Schedule-IV, Section 11

House swift Apus affinis

Bhagule Ardea purpurea

Koel Eudynamys scolopacea

Kabutar Columbia livia

Titavi Vanellus indicus

Bhardwaj Centropus sinesis

Pandubi Prodiceps ruficollis

Schedule-V Common Crow Corvus splendens

NOT LISTED UNDER WILDLIFE PROTECTION ACT,1972

Mammals (Domestic

Animals)

Goat Capra species

Bull Bos indicus

Cow Bos indicus

Buffalo Bubalus bubalis

Page 194: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Dog Canis familaris

Sheep Capra Sp.

Pig Sus scrofa

Horse Equus Sp,

Birds (Domestic Birds) Sparrow Passer domesticus

Duck Nettopus

Coromandelianus

Fauna Common Name Zoological Name

Amphibian

Frog Rana Tigerina

Tree frog Hyle Spp.

Flying frog Rhacopnonis Spp.

Aquatic fauna (Fishes)

Rohu Labco rohita

Catla Cyprindiae

Garai Channa punctatus

Mangoor Clarias batrachus

Pothia Punctius ticta

Bokwa Eutropichttys baacha

Zebra fish Danio rerio

Invertebrates

Birni Polistis Spp.

Grosshopper Hierogylphus banian

Tidha Schistocerca gregaria

Moth Antheria mylita

Black Bee Apis dorsata

Bee Apis indica

Stem Borer Chilo auricilia

Cockroach Blata orientalis

Madhumakkhi Apis indica

Chinti Solpopsis Spp.

Lahi Kerria laxxa

Jugnu Photinus Spp.

Gojar Scolopendra Spp.

Aquatic Insect Daphnia Nepa Spp.

Prawn Chaetogaster

ENDANGERED SPECIES Nil -

ENDEMIC SPECIES Nil -

MIGRATORY SPECIES Tree Pipit Anthus Trivialis

Cuckoo Cuculus Micropterus

Page 195: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

OBSERVATION

The floristic component of the study area does not include any rare or

endangered species. Thus, impact on rare and endangered species of flora is

not envisaged.

The proposed project does not envisage destruction or displacement of any

fauna species. Thus, indirect impact on fauna due to loss of habitat is not

foreseen.

However, it is reported that animals like Langur, Jangli Billi, Jackal, etc. enter

into the agricultural field of the villages and needs conservation.

Common Species of Flora & Fauna observed in the study area are as follows:

Flora Local Name

Agricultural crops

Cereals Dhan , Makka

Pulses Urad (Black Gram), Chhana, Tuar (Red gram),

Kulthi (Horse Gram), Mung (Green Gram)

Commercial crops

Vegetables Baigan, Tamator, Cobbage, Bean, Jhinga,

Kohra, Bhindi

Oil yielding plants Sarson, Arandi etc

Spices Mirch, Dhania, Adrak, Lahsun etc.

Fruits Aam, Amrudh, Jamun, Papita, Kathal, Ber,

Orange etc

Cash crops Kappas, Soyabean

Natural vegetation / forest type

Herbs Amaltas, Dhudhi, Rantulsi, Ratrani etc

Shrubs Ratanjoyati, Katumber, Lokhandi, Bhor etc

Trees Aam, Sitaphal, Neem,Peepal, Mahua etc

Grasses Baans, Doob,etc

SL.

NO. COMMON NAME SCHEDULE

01. House Rat V

02. Jackal II

03. Jungle Cat II

04. Fulvous Fruit Bat V

05. Common crow V

06. Common Langur II

Page 196: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Results of study

From the above study, it is observed that there is no endangered and endemic

species found in the area as per Red Book of Botanical Survey and Zoological

survey of India as per Wild Life (Protection) Act 1972 and its subsequent

amendments.

The main agricultural crops of the village area under study is Rice and Maize.

The major commercial crop grown here during the summer season is Lady

Finger, Brinjal, Chilies, Onion, Beans, Karela etc. The forest of the area is mainly

southern Tropical Dry Deciduous Forest. Yet, plantation has also been done by

M/s WCL and Forest Department and is categorized as B-Type forest. The main

constituents of forest are Palash, Sisam, Bel, Babul, Mango, Mahua, Jamun,

Eucaliputas, Kathal, Neem etc.

Trees of terminalla species were found, besides, Palash, Sisam, Teak, Sal, Mango,

Ashok, Kathal, Gulmohar etc. are planted and maintained by M/s WCL and

Forest Department.

The grass land vegetation mainly covered by Moraba, Chor kanta, Dubh, Munj

species, Bans/Bamboo etc.

As there is B-Type forest, hence major fauna elements were absent in this area.

Mainly Fox, Newla, Jungle Cat are observed/reported. No endemic and

endangered species of fauna elements has been reported as per Wild Life

(Protection) Act 1972 and its subsequent amendments. No migratory species

and there path/corridor have been found/reported in the area.

Page 197: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

CHAPTER- IV

ANTICIPATED ENVIRONMENTAL IMPACTS

&

MITIGATION MEASURES 4.1 AIR POLLUTION IMPACT ASSESSMENT

The impact assessment has been carried out dealing with the following

points:

(a) Phase-wise inventory of air pollution emission sources

(b) Impact assessment

a. Phase-wise inventory of air pollution emission sources

The pollution sources are obvious and to assess the impact, the project life

is divided into following time frames:

Operation phase

Post-operational stage

The activities associated with these time frames and having impact on the

ambient air quality along with the pollutants are enumerated in the

following sections:

Operational phase

During this phase, activities necessary for mining of coal, its handling and

transport are taken up. Such activities having impact on ambient air

quality are detailed below:

(i) Drilling : Dust

(ii) Blasting of coal and

overburden

: Dust and noxious gases

(iii) Handling of coal : Dust and noxious gases

(iv) Overburden handling : Dust and noxious gases

(v) Dump formation (internal) : Dust and exhaust fumes from

dumpers and dust till the

development of green cover

(vi) Movement of vehicles : Dust and noxious fumes

Post-operational stage

During this stage of the project, the activities related to the closure of

mine are to be carried out. Preparation of mine closure plan shall be

carried out during the period four to five years before the closure of the

mine. Some of the activities for the closure are:

Page 198: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Modifications in physical and biological reclamation of backfilled area

Salvaging and shifting operation of HEMMs and other equipment

Clearing of coal and other materials, restoration of infrastructure

area & colony area to the extent possible and necessary if not useful

for other projects

Management of hydrology and hydrogeology.

Redeployment of workforce, etc.

Arrangement & implementation of post-operation monitoring mainly

keeping watch, vigil, etc.

The activities having impact on the ambient air quality are enumerated

below:

(i) Movement of HEMMs for physical

reclamation of backfilled area

: Dust and obnoxious

fumes

(ii) Movement of vehicles for shifting and

salvaging operation of HEMMs and other

equipment

: Dust and obnoxious

fumes

(iii) Movement of vehicles for clearing of coal

and other materials

: Dust and obnoxious

gases

b. Impact assessment

The mining and its related activities create ambient air pollution. The

impact of mining on ambient air quality are highlighted in the following

paragraphs:

(a) The ambient air quality is influenced due to the presence of RPM, SPM,

SO2, NOx, etc., which are generated due to various activities like

drilling, blasting and handling related to the project. Further, the

ambient air quality is affected marginally to a varying degree due to

the mining activities of other nearby opencast and underground coal

mines of the same coalfield. The concentration of pollutants may vary

depending upon the various micro-meteorological parameters and

the seasons of a year.

(b) The baseline ambient air quality has been generated at six locations

surrounding the existing Junad OC to assess the present ambient air

quality scenario corresponding to the pre-mining status of the

proposed Deep Extension OC project. The details of baseline data

have been given in previous chapter. All the monitored parameters

are well within the permissible limit. Thus it can be concluded that

although the mine under consideration as well as the neighbouring

mines are operating since long but ambient air quality in the

surrounding area has not been affected adversely.

Now, with the proposed expansion in production capacity in the

existing OC project, there is likelihood of addition of pollution to the

Page 199: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

existing concentration level of different attributes of ambient air. Efforts

will be made by implementation of proper abatement measures so as

to maintain the sinking capacity of ambient air to absorb the

additional load, if any, thereby maintaining the quality of ambient air

to the pre – mining level to the extent possible.

(c) Further, as per TOR received from MOEF, AAQ Prediction modeling has

been done with FDM and it has been found that there will be

insignificant increase in the level of pollutants as such there will be

negligible impact on the Ambient air quality due to proposed

expansion of the mine.

Existing Ambient Air Quality Monitoring

The ambient air quality monitoring is being carried out on regular basis as per

the Env (Protection) Amendment Rule, 2000 so as to ascertain the likely load of

various air pollutants and thereby suitably modifying the various control

measures.

Hence , it is expected that pollution load to be generated due to increased

production at Junad OC will be well within the permissible limit as the existing

air pollution control measures will be further strengthened with close monitoring

for efficient & effective implementation of the pollution control measures to

make the operation eco-friendly and it is expected that ambient air quality will

have no harmful effect on human being, flora and fauna, soil quality, surface

structures and aesthetic value of the surrounding environment.

4.2 AIR POLLUTION CONTROL MEASURES

Since Junad OC is an operating mine, the environmental monitoring data

generation is being done at four locations on regular basis as per the Env

(Protection) Amendment Rule published Vide Gazette of dated 25.9.2000. In

addition to data generation, following abatement measures have also been

taken in order to suppress the dust and noxious gases generation to the

maximum possible extent.

4.2.1 Drilling Operations

In order to reduce dust generated by drilling operation wet drilling is done.

4.2.2 Blasting Operation

In order to minimize the generation of dust during blasting, the following

measures are adopted:

(a) Blast holes are properly placed/spaced/positioned.

(b) Blast is properly designed in respect of hole-spacing. Hole placing and

blast design are looked into as a fresh case every time, by a competent

Page 200: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Blasting Officer who takes into consideration the actual geo-mining

conditions of the site.

(c) Blasting is being done between shifts or during the rest interval when the

minimum number of persons is present around the blast area. In order to

quickly disperse the dust generated in blasting operations, blasting is

avoided when there is wind. Blasting is avoided in the mornings and during

cloudy situations.

(d) Adaptation of Controlled Blasting Technique as permitted by DGMS.

4.2.3 Loading & Transport

Movement of vehicles and HEMM on haul roads, particularly when they are un -

metalled, is another major source of dust generation. To minimize dust

generation due to this operation, the following abatement measures will be

taken.

(a) All long-life haul roads and service roads are properly constructed and

metalled. Unmetalled roads are being kept free of ruts, potholes etc.

(b) All haul-roads are regularly sprayed with water. Water sprinklers are

regularly used in the project.

(c) Overloading of vehicles are avoided.

(d) Covering of loaded trucks by tarpauline.

(e) Regular cleaning of transportation roads.

(f) Adequate green belt have been developed all along the coal

transportation road on both sides.

All the above-mentioned control measures will be continued during the

balance life of the project.

4.2.4 OB Dumps

On the dump slopes and top surface, plantation of grass and trees will be done

in phases and the details are as follows ;- Stage-wise Cumulative Plantation

year Green Belt

External Dump(OB +

Top Soil) Backfilled area

Others (undisturbed

area/etc.) Total

1 Area (ha)

No. of trees

Area (ha)

No. of trees

Area (ha)

No. of

trees

Area (ha)

No. of trees

Area (ha)

No. of trees

2 1st year

0 0 0 0 0 0 0 0 0 0

3 3rd year

0 0 0 0 0 0 0 0 0 0

4 5th year

0 0 25 62.5 0 0 10 25 35 87.5

Page 201: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

year Green Belt

External Dump(OB +

Top Soil) Backfilled area

Others (undisturbed

area/etc.) Total

5 End of mine life

0 0 110 275 0 0 145.93 364.825 255.93 1

6 Post mining

0 0 175 437.50 0 0 157.93 394.825 332.93 832.33

2.5 Coal Handling Plant

Lot of dust is generated in coal handling plant during operations like coal

crushing, transfer and conveying. Following abatement measures are adopted

for Coal Handling Plant.

i) Enclosure of the crusher house where maximum dust is generated. Also

installation of dust suppression system in the crusher house (specially

above the hopper in such a way that air borne dust is suppressed without

adding much water to the coal).

ii) Minimising the height of coal-fall at transfer points (to reduce dust

formation) and, if necessary, installing dust suppression measures.

iii) Enclosure of the belt conveyor to reduce the generation of dust due to

blowing wind.

iv) Creation of a green belt on both sides of belt conveyors and around coal

stocks and the CHP building.

Noxious gasses are emitted through exhaust fumes during the operation of

diesel / petrol operated equipment. In order to reduce such emission, regular

maintenance of the diesel / petrol operated vehicles will also be carried out so

that the emissions from these vehicles are under control. However, wherever, the

condition will permit, petrol / diesel operated HEMM will be replaced by

electrically operated ones.

Water sprinkling on coal stock/face, blanketing of exposed surface will be

carried out to avoid spontaneous heating and minimize air pollution.

4.2.7 Plantation to Check Air Pollution

Plantation has been under taken in the mine area as mitigatives measure

against air pollution, noise pollution and to increase the aesthetic value. The

plantation will be developed at suitable places like overburden dump, along

the road sides, unused land etc to arrest as well as reduce the rate of dispersion

of dust generated due to various mining operations viz. quarrying, coal and OB

transportation, OB dumping, CHP operation. Species to be planted

(recommended by Forest Department) in the area are as follow.

Page 202: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

a) Ornamental trees viz Gulmohar, Eucalyptus and fruit trees like Mango, Guava,

Jamun and medicinal plant like Neem etc. will be planted in colony area,

schools, dispensary, community buildings, play ground etc.

b) Ornamental shady trees will be planted e.g. around colony along roads, haul

roads, and around industrial buildings etc.

c) The fast growing varieties of trees like Eucalyptus act as sound barriers where

as ornamental shady trees e.g. Subabul, Kikar and karanj will add to the

aesthetic look of the area.

d) The Species to be planted on OB dumps etc are: Gravalia, Robusia, Punis,

Vanetis, Semal, Karanj, Babul, etc

59,325 nos. of trees have ben planted till date on embankment, vacant land & along coal transportation road.

4.3 WATER QUALITY

Impact Assessment on Water

Identification of the sources of water pollution

Likely sources of water pollution from this project along with the type of

pollutants are as follows:

(i) Sanitary (domestic) wastewater : Suspended solids and BOD.

(ii) Industrial wastewater from

workshop

: Suspended solids, oil & grease;

(iii) Wastewater from mine : Suspended solids of coal, clay

and oil;

(iv) Surface run-off passing through

coal stockpiles

: Suspended solids;

(v) Storm water from leasehold

area and built-up area

: Suspended solids.

Impact assessment

Mining and its related activities may create water quality problems. The

impact of mining at the project on both surface and ground water

sources has been assessed and given below:

(a) Surface water sources

Deterioration of water quality and pollution of water bodies due to

discharge of mine effluent, if not treated. Change in relief pattern

due to mining may cause flooding, siltation, choking and pollution.

Mitigatory measures would involve provision of (i) garland drains on

Page 203: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

periphery to prevent surface run-off from entering into the quarry ,

(ii) catch drain around the dumps for avoiding siltation and (iii)

sedimentation ponds for reducing the pollution of surface water

bodies.

Possible overflow of water from nearby rivers/nallahs must be

safeguarded by stone pitching and strengthening the embankment

along the side of the water course

In order to assess the existing quality of surface as well as ground

water quality surrounding the project site, water samples from six

locations have been collected & analysed. The details are

incorporated in the previous chapter. All the parameters are well

within the permissible limit.

The mine water discharge quality of existing opencast project is

being monitored regularly as per Env. (Protection) Amendment Rule

, 2000 . The result indicates that even in untreated condition mine

pumped out water does not contain any pollution load.

However, due care will be taken to treat the mine water discharge

by sedimentation for the proposed project. Effluents from workshop

is continue to be treated in ETP and moreover water will be mostly

recycled in Workshop & CHP. As such, possibility of adverse impact

on natural watercourses after mixing is very remote. Garland drain

around the OB dump & coal dump will be made to avoid siltation

of natural water course.

Based on the data collected at the existing coal mine, it can be concluded that

the impact due to proposed mining operation, the adverse impacts on water

both surface as well as ground water will be insignificant.

4.3.1 WATER POLLUTION CONTROL MEASURES

Salient controls measures have been taken are as follows:

i) Industrial Effluent

The wastewater from workshop and CHP, which normally remain laden with oil

and grease, suspended and dissolved solids etc. are treated in the Effluent

Treatment Plant (ETP). Clear water coming out from the treatment plant is taken

into the closed water circuit and recycled for its reuse. All parameter of ETP

waste discharge are monitored regularly as per Env. (Protection) Amendment

Rule, 2000 and found to be within permissible limits.

Page 204: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

ii) Mine Water

Most of the suspended particles are settled in the mine sump as initial settlement

and the supernatant water is pumped out. This water is passed through

sedimentation pond on surface, before being discharged in to natural drain.

iii) Surface Run-off

Adequate numbers of vegetation will be grown on the top surface and slopes

of the dumps in order to arrest the erosion of soil and it also reduces surface run-

off, which helps averting siltation of natural watercourses.

Catch drains of suitable size have been provided around periphery of the OB

dump as well as soil dumps to arrest site and sediment flows from the respective

dump sites.

In case of OB benches in the quarry, cross drainage have been provided which

carries silt and sediments into main sump made at the floor of the seam which

will accumulate all the silts and act as first stage settling pond. The water is then

pumped out through pumps on to the surface and discharged in to surface

settling tank/sedimentation pond. The clear water from the surface

sedimentation tank is used for watering the mine area, roads and green belt

development. The catch drains mentioned above are regularly desilted and

maintained properly. In addition, garland drains have also been provided

around the periphery of the excavated area, which carries surface run off and

the drains are regularly desilted before onset of monsoon.

These drains allows accumulation of silt materials and sufficient retention time for

settling of silt materials.

The domestic sewage disposal arrangement has been provided in the township.

Regular water quality/effluent quality monitoring is also carried out so as to

ascertain the likely load of pollutants and thereby suitably modifying the control

measures.

The existing water pollution control measures can be summarized as below :-

Page 205: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

MINE WATER :- TWO STAGE SEDIMENTATION

INITIAL SEDIMENTATION - AT MINE SUMP

(SIZE- 800mX60mX4m)

FINAL SEDIMENTATION - SEDIMENTATION POND AT

SURFACE (SIZE- 24mX8mX1.5m)

INDUSTRIAL / WORKSHOP EFFLUENT:

WORKSHOP EFFLUENT IS BEING TREATED IN

WORKSHOP ETP .

DOMESTIC EFFLUENT:

THERE IS ONE INTEGRATED DOMESTIC EFFLUENT

TREATMENT PLANT AT COMBINED TOWNSHIP(0.6MLD) AT BHALAR.

EXISTING WATER POLLUTION CONTROL MEASURES

In addition to the above, provision have also been made for augmentation/

strengthening of existing sedimentation pond as well as Workshop Effluent

Treatment Plant.

4.4 IMPACT ON HYDRO-GEOLOGICAL REGIME

The mining activity creates dis-equilibrium in environmental scenario of the area

and disturbs the groundwater conditions/regime in particular. The impact on

water regime due to mining activity can be broadly classified as under :

i) Impact on topography & soil

ii) Impact on surface water and quality

iii) Impact on groundwater & quality

A brief description/out-line on these aspects are given below :

Impact on topography & soil:

A local change in ground topography will be created at Junad Deep Extension

OC mine area due to mining operations such as open pit, embankments,

dumps of overburden and coal, diversion of nallah and roads, mine voids etc.

As a result, there would be marginal change in the drainage and surface run-

off. During these courses, soil is most susceptible for changes due to erosion,

leaching phenomena/process etc. Further the fine dust particles of coal &

Page 206: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

overburden may adversely affect the physical & chemical characteristics of

soil.

Within the core zone area, cracks and loosening of soil would be resulted in due

to mine and associated activities such as drilling, blasting etc thereby

physical/texural changes would occur in soil/formations. This mine induced

process increases the rate of infiltration and recharge. The studies carried out in

Wardha Valley coalfield have established that rainfall-infiltration rates have

been increased by 100% (doubled) in the core zone area of opencast mines

thereby increasing the scope of groundwater recharge. So also the back filled

area may be a good media for high groundwater recharge due to high-

induced permeability. Further, the void proposed to be left out would store

substantial quantity of rain water which can be utilised for domestic &

agriculture use and also for recharging the groundwater source. It may be

appropriate to high light the fact that temporary groundwater loss/deficit

created during activemining stage would be compensated by these different

means in the post mining stage so that the initial groundwater levels are

regained to normalcy at the earliest for the utility of the area. Appropriate

reclamation measures would be adopted to normalize the ground topography

and soil as far as possible. However, overburden dumps, embankments etc. are

unavoidable structures to be left in the post mining stage.

Impact on surface water & quality :

As mentioned earlier, there would be minor change in the ground topography

and infiltration capacity/rate of soil/formation due to mining operations resulting

in some local change in drainage pattern and surface run-off in core zone. It is

established that high infiltration zone would serve as good media for high

groundwater recharge and reduces the surface run-off considerably in the core

zone. In view of this, the mine has to handle more water in the monsoon besides

the additional contribution from the surface run-off from the catchment area. As

such the surface run-off contribution to the natural drains from the mining area

would be minimum thereby some minor change is expected in hydrologic

regime of the river/nalla system.

The surface run-off from the dumps of overburden material and coal and mine

water discharge/effluent are laden with suspended particles of coal and other

associated materials. This water is collected by foot drains with stoppage

arrangement and passed through sedimentation tank/pond. This treated water

will be utilised for mine site requirement and the surplus would be utilised to

supplement the water shortage for domestic & agriculture use of villages if

required or otherwise discharged into land surface/natural drains.

Impact on groundwater & its quality:

Mining is associated with groundwater problems, particularly when it is below

water table. The impact of mining on groundwater is dependent mainly on mine

and aquifer parameters, groundwater recharge-discharge process etc. In the

opencast mining, the unconfined aquifer gets affected more whereas the

Page 207: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

semiconfined aquifers are least affected due to continuous gravity drainage

and conventional sump pumping or advance dewatering schemes for efficient

and safe working. As such, during this exercise, basically the water level is to be

depressed/depleted below the working seam depth in which case large scale

mine water pumping can not avoided.

Consequently the mine dewatering would drain out some area around the mine

with decline in groundwater levels. However, these mine-induced effects are

temporary as increased infiltration rate at as rain water harvesting to balance

the mine dewatering. Further, the mine effluent would contaminate the other

resources of water if discharged untreated. The expected mine effluent from

Junad Deep Exn. OCM area would be no different from the exiting mine

possessing similar hydrogeological sep-up. However, water quality monitoring

would be undertaken at the stipulated intervals immediately after the mine

development starts and continued during the mine life.

Groundwater inflow and mine influence area have been estimated and the

groundwater monitoring would be undertaken as corrective measure to avoid

adverse effects. The mine discharge after passing through sedimentation pond /

tank would be discharged into land/natural drains with earthen check dam at

suitable locations so that the groundwater gets additional recharge by the

return flow. The artificial recharge by water conservation structures in mine

influence area proper may not be a viable solution because of the reason that

recharged water would drain to the mine at a faster rate due to the steep

hydraulic gradients resulted in during mining activity. As mentioned earlier the

mine impact may be for temporary period during mine life and the area would

regain the normalcy/benefits in many ways by appropriate reclamation

measures during post-mining period. However, the temporary water shortage in

the mine influence area would be supplemented from the treated mine water

discharge for both domestic & irrigation use of affected villages if any.

WATER POLLUTION CONTROL MEASURES

Salient controls measures have been taken are as follows:

i) Industrial Effluent

The waste-water from workshop and CHP, which normally remain

laden with oil and grease, suspended and dissolved solids etc. is

being treated in the Effluent Treatment Plant (ETP). Clear water

coming out from the treatment plant is taken into the closed water

circuit and recycled for its reuse. All parameter of ETP waste

discharge are being monitored regularly as per Env.(Protection)

Amendment Rule, 2000 and have been found within permissible

limits.

Page 208: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

ii) Mine Water

Most of the suspended particles are settled in the sump and the

supernatant water is pumped out. This water is passed through

sedimentation pond, before being discharged in to natural drain .

iii) Surface Run-off

Adequate numbers of vegetation is already grown on the top

surface and slopes of the dumps in order to arrest the erosion of soil

and it also reduces surface run-off, which helps averting siltation of

natural water courses.

In Junad Extn OC mine will have garland drain along the periphery of the OB

dumps to make the surface run – off to pass through the settling lagoons before

it is either put to reuse or allowed to enter into surface water course.

In addition to above adequate sewage disposal arrangement exists in the

township.

Remedial measures to control ground water depletion

The following methodology and remedial measures have been taken to

minimize the mine induced impact on ground water levels and also adverse

effects in the area.

(i) Artificial recharge to ground water system at the periphery of the

anticipated influence area by local stagnation in low lying areas/drains

by providing low height dams/bunds or by injection of mine water

discharge, surface water through tubewells /percolation structures.

(ii) The water shortage in the villages, if any, in the influence area can be

supplemented by supply of water from outside source or from the mine

water after treatment.

(iii) Sprinkler irrigation system is recommended to support agriculture in the

mine influence area thereby water rehandling is avoided at the mine.

(iv) While reclamation of the mined area, void at the deepest portion of

the pit has to be left. This residual pit void would initially serve as

access for future expansion and subsequently it could be

backfilled.

(v) Well water monitoring in nearby villages is being carried out quarterly

as per MoEF' guidelines. No adverse remarks have so far been observed.

(vi) Regular water quality/effluent quality monitoring is being carried out

so as to ascertain the likely load of pollutants and thereby suitably

Page 209: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

modifying the control measures. As seen from Analysis Data, the mine

pumped out water does not contain significant pollution load and the

discharge water quality even without treatment is quite satisfactory.

4.5 NOISE QUALITY

In order to assess the existing ambient noise level in the surrounding of proposed

project site corresponding to pre-mining scenario ,baseline noise level data has

been generated & details are enclosed as Annexure – III. All the values are well

within the permissible limit.

Proposed mine would be associated with following activities that may generate

noise during operation :

(a) Drilling

(b) Blasting

(c) Shovel operation

(d) Dozing

(e) Movement of dumper

(f) Operation of CHP / Workshop

The following are some of the important activities responsible for high noise level

generation, with their expected noise levels :

a. All mining activities i.e. drilling, blasting, shoveling, dozing and

dumping are associated with high noise level [about 100 dB(A)].

b. Operation of most HEMMs produce high noise level. The noise level

are in range of 80 – 100 dB(A). Noise level have been found to be

related to engine capacity.

c. Crusher – General noise level due to crusher ranges from 90 dB(A) –

105 dB(A). Some of noisy equipment produce noise whose level is

around 120 dB(A).

The average sound pressure level of some of the HEMM associated with mining

operation which are responsible for high noise level generation are as follows :

EQUIPMENT NOISE LEVEL

[dB(A)]

Dozer 98

Dumper 92

Power shovel 93

Drilling machine 96

Page 210: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

ACCEPTABLE INDUSTRIAL NOISE LEVEL

As per Env. (Protection) Amendment Rules, 2000 the ambient air quality

standards in respect of noise in industrial , commercial , residential and silence

zones area as follows :

Sl.

No.

Category of

area

Limits [dB(A)]

Day time (6.00 AM to 10.00 PM

)

Night time (10.00 PM to 6.00 AM )

1. Industrial 75 70

2. Commercial 65 55

3. Residential 55 45

4. Silence zone 50 40

Assessment of the degree of noise to which a workplace noise is harmful, is done

by comparing the values measured at workplace to the permissible limit

adopted by statutory bodies like DGMS.

The Director General of Mines Safety vide their circular no. DG ( Tech.)/18 of

1975 has prescribed the permissible limit for noise level as 90 dB(A) , for the

workers engaged in mining occupation likely to be exposed to in an 8 hour shift

period with unprotected ear . Whereas , the following table shows the maximum

permissible noise exposure levels , as per American Standards , for the industrial

workers.

Exposure time

(Hrs./day)

Noise level

[dB(A)]

8 90

6 92

4 95

3 97

2 100

1.5 102

1 105

0.5 108

0.25 or less 115

EXPOSURE TO PULSE OR IMPACT NOISE

SHOULD NOT EXCEED 140 dB(A)

The impact of mining on ambient noise quality are highlighted in the following

paragraphs:

(a) The ambient noise quality is influenced by various activities like drilling,

blasting and material handling related to the project. Further, the ambient

noise quality is affected marginally to a varying degree due to the mining

Page 211: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

activities of other nearby opencast and underground coal mines of the

same coalfield.

(b) The baseline ambient noise quality has been generated at six locations

surrounding the existing Junad OC to assess the present ambient noise

quality scenario corresponding to the pre-mining status of the proposed

Deep Extension OC project. The details of baseline data have been given

in previous chapter. All the monitored parameters are well within the

permissible limit.

(c) Thus it can be concluded that although the mine under consideration as

well as the neighbouring mines are operating since long but ambient

noise quality in the surrounding area has not been affected adversely.

Now, with the proposed expansion in production capacity in the existing OC

project, there is likelihood of addition of noise load to the existing concentration

level of ambient noise. Efforts will be made by implementation of proper

abatement measures so as to maintain the sinking capacity of ambient noise to

absorb the additional load, if any, thereby maintaining the quality of ambient

noise to the pre – mining level to the extent possible.

4.5.1 NOISE POLLUTION CONTROL MEASURES

Monitoring of the noise control will be carried out on regular basis as per the Env

(Protection) Amendment Rule 2000. While planning for an effective noise

attenuation measures, the concept of source, path and receiver has been

considered.

(A) Noise Control at Source

There are two areas where the noise generation can be checked at source.

(i) Proper Design

Since the generation of noise can be reduced by reducing the vibration

amplitude, the area of vibrating part and frequency of vibration will be taken

care that all loose contact between metal parts avoided.

(ii) Proper Maintenance

All machines and equipment will be properly maintained. Sound muffler system

and bearing lubricating system etc. of equipment will be kept in proper

condition.

(B) Noise Control at Receiver End

Even after adopting above measures, if desired noise level is not achieved at

receiver end, in that case, following measures are suggested:

Page 212: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

(a) The workers exposed to high noise level are provided with earplugs.

(b) Provision of enclosed booths at the worksite to protect worker from noisy

environment.

4.6 IMPACT ON LAND

LAND USE (CORE ZONE)(contd.)

6.10 ha--

449.63 ha

NIL

443.53 ha

TOTAL

174.28 ha

NIL

174.28 ha

LAND

ALREADY

ACQUIRED

275.35 haTOTAL

NILFOREST LAND3.

6.10 haGOVT. LAND

(WASTE LAND)

2.

269.25 haAGRICULTURAL

LAND

1.

LAND TO BE

ACQUIRED

PARTICULARSSL.

NO

FORESTRY CLEARANCE

TOTAL ML/PROJECT AREA (ha)

TOTAL FORESTLAND (ha)

Date of FC Extent of forestland

Balance area for which FC is yet to be obtained

Status of appl. for diversion of forestland

If more than one, provide details of each FC

449.63 Nil Not Applicable

Not Applicable

Not Applicable Not Applicable

Page 213: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

The during-mining land use is as follows: -

CHANGE IN LAND USE DURING MINING

67.43RATIONALISATION AREA6

70.50BLASTING ZONE5

449.63

20.00

15.00

175.00

101.70

AREA (ha)

TOTAL

EMBANKMENT4

INFRASTRUCTURE INCLUDING

APPROACH ROAD ETC.

3

EXT. OB DUMP2

QUARRY AREA1

PARTICULARSSL. NO.

4.6.1 LAND RECLAMATION / LAND MANAGEMENT

The following activities have been proposed for reclamation of land.

1. Backfilling of the excavated area to the extent possible.

2. Leveling of the backfilled area and carpeting with the topsoil.

3. Creation of garland drains in order to arrest the silt load, due to erosion, to

enter into natural watercourses during surface run-off.

4. Grass, legumes and different types of plants etc. will be planted on such

reclaimed land in order to make it, as far as possible, conducive to

agricultural growth.

5. Technical and biological reclamation of external OB dump.

The density of trees is around 2000 – 2500 plants/Ha.

Page 214: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

OB Management

Project Total waste generation

(Mm3)

Topsoil (Mm3)

Total OB generation

(Mm3)

Total OB in Ext. Dump

(Mm3)

Total OB Backfilled

(Mm3)

Original Project (ha) 10.33 Included in OB

10.33 9.58 & 0.75 in

Embankment

----

Expansion Project (ha) (balance life)

50.62 Included in OB

50.62 50.62 ----

TOTAL (Mm3)

60.95 60.95 60.20 & 0.75 in

Embankment

The capacity of external OB dumps proposed is about 60.20 Mm3. Remaining 0.75 Mm3 of OB will be used is construction of safety embankment.

The break up of OB quantities in external OB dumps is given in following table.

No. Dump Capacity in Mm3

0-30m 0.60m Total

i) Dump – 1 25.70 16.95 42.65

ii) Dump – 2 10.30 7.25 17.55

Total 60.20

SCHEDULE OF OVERBURDEN DUMPING

The following Table shows the yearwise OB dumping in external OB dump No.1 and No.2

Year Programmed Excavation of

OB(Mm3)

External OB Dump-1 (Mm

3)

External OB Dump-2

(Mm3)Excluding

Rehandling

1. 8.15 8.15 -

2. 7.40 7.40/15.55 -

3. 5.26 5.26/20.81 -

4. 5.25 5.25/26.06 -

5. 5.25 5.25/31.31 -

6. 4.70 4.70/36.01 -

7. 4.50 4.50/40.51 -

8. 4.40 2.14/42.65 2.26

9. 4.40 - 4.40/6.66

10. 1.10 - 1.10/7.76

11. 0.21 - 0.21/7.97

Total 50.62 42.65 7.97

Page 215: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Points for reclamation of void of Junad OC Extn. mine

i. Due to steep gradient and in order to maintain proper haul road of 1 in 16

gradient it will not be possible for backfilling of the void in the present

proposal.

ii. In order to backfill the void of Junad Extn. OC to the extent of –35 m it is

proposed that the OB of adjacent Pimpalgaon Extn. OC could be utilized.

iii. The approx. quantity of OB of proposed Pimpalgaon Extn . OC is 200 M.Cu.m.

and is at a distance of about 5 k.m.

iv. This will simultaneously help in reduction of land required for external OB

dump of proposed Pimpalgaon Extn. OC.

Post mining land use plan (Conceptual)

The post-mining land use pattern at Junad Extn. Deep OCP will be as follows:-

Post-mining Landuse pattern of ML/Project Area (ha)

S.N. Land use during mining

Land use (ha)

Plantation Water Body Public use Undisturbed Total

1 External OB Dump 175 0 0 0 175

2 Top soil dump 0 0 0 0 0

3 Excavation 0 101.7 0 0 101.7

4 Roads including embankment

17 8 25

5 Built up area 3 0 7 0 10

6 Green Belt 0 0 0 0 0

7 Undisturbed Area 137.93 0 0 0 137.93

Total 332.93 101.7 15 0 449.63

Page 216: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Stage-wise Cumulative Plantation

year Green Belt

External Dump(OB +

Top Soil) Backfilled area

Others (undisturbed

area/etc.) Total

1 Area (ha)

No. of trees

Area (ha)

No. of trees

Area (ha)

No. of

trees

Area (ha)

No. of trees

Area (ha)

No. of trees

2 1st year

0 0 0 0 0 0 0 0 0 0

3 3rd year

0 0 0 0 0 0 0 0 0 0

4 5th year

0 0 25 62.5 0 0 10 25 35 87.5

5 End of mine life

0 0 110 275 0 0 145.93 364.825 255.93 1

6 Post mining

0 0 175 437.50 0 0 157.93 394.825 332.93 832.33

Land Reclamation Monitoring

Land restoration / reclamation monitoring of fourteen opencast coal mines

including Junad OCP of Western Coalfield Limited (WCL) producing less than 5

million cu.m. (Coal+OB) per year, based on satellite data on regular basis at an

interval of three years has been started w.e.f 2011.

Objective of the land restoration / reclamation monitoring is to assess the area

of backfilled, plantation, social forestry, active mining area, water bodies, and

distribution of wasteland, agricultural land and forest in the leasehold area of

the project. This will help in assessing the progressive status of mined land

reclamation and to take up remedial measures, if any, required for

environmental protection.

Projectwise Land Reclamation Status in Opencast Project of WCL

< 5 Million Cu.M of coal + OB) based on Satellite Data of the year 2011 (% Calculated in terms of Total Excavated Area) in Ha

Area inHa

Sl. No.

Project Name

Leashold Plantation Backfilled Active Mining

Total Excavated Area

Total Reclaimed area

i ii iii iv ii+iii+iv ii+iii

in (Ha) 2011 2011 2011 2011 2011

38.18 66.35 42.20 146.73 104.53

1 Junad 163.64 17.98 71.25 30.52 119.75 89.23 15.01 55.15 23.62 74.51

Page 217: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar
Page 218: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

4.6.2 PROGRESSIVE & FINAL MINE CLOSURE PLAN

A. OBJECTIVES OF CLOSURE PLANNING

Mine closure planning has to be carried out at the starting of the mine and

needs periodic reviewing and revision during its life cycle to cope with the

geo-technical constraints, safety and economic risks, social and

environmental challenges. Various other objectives are as follows:

(a) To allow a productive and sustainable after-use of the site which

is acceptable to the mine owner and the regulatory authority;

(b) To protect public health and safety;

(c) To alleviate or eliminate environmental damage and thereby

encourage environmental sustainability;

(d) To minimize adverse socio-economic impacts.

B. DIFFERENT ASPECTS OF MINE CLOSURE PLANNING

The mine closure planning broadly involves the following aspects:

(a) Technical aspects;

(b) Environmental aspects

(c) Social aspects;

(d) Financial aspects.

C. MINE CLOSURE OBLIGATIONS

There is need to define the liabilities, responsibilities and authorities of the mine

management, other regulatory bodies, Central and State Governments after

mine closure. Some obligations relating to the Mine Management

Companies are as follows:

(a) Health & Safety: Regulation Nos. 6, 61, 106, 112 of Coal Mines

Regulations, 1957 and its related DGMS Circulars;

(b) Environment

(i) Water (Prevention & Control of Pollution) Act, 1974;

(ii) Air (Prevention & Control of Pollution) Act, 1981;

(iii) Environmental (Protection) Act, 1986 and Environmental

Protection (Amendment) Rule , 2000;

(iii) DGMS Directives on Noise & Ground Vibration;

(c) Forest : Forest (Conservation) Act, 1980 – Not applicable in this case.

(d) Rehabilitation : As per Company Policy.

(e) Decommissioning/asset disposal, etc.

Page 219: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

D. CLOSURE ACTION PLAN

Closure planning is a whole-of-life exercise that begins at the start of a mine

and continues till post-closure. The dynamic nature of closure planning

requires regular and critical review to reflect changing circumstances as a

result of any operational change, new regulation, new technology and

remain flexible enough to cope with unexpected events.

The following steps have to be undertaken in relation to Mine Closure

Planning:

(a) Prior to the surface demolition/restoration a surface audit should be

undertaken on all surface structures, spoil heaps, lagoons, etc. to assess

whether there are any hazardous materials that could cause problems;

viz. explosives, chemicals, etc. A list of surface assets should be

prepared and made available to potential purchasers, prospective

purchasers could be invited and asked to submit sealed bids, this could

ensure that the sale of assets give better financial gain.

(b) In order to identify potential impact, necessary hydro-geological studies

into post-mining ground water recharge has to be done. The void of the

mine can be proposed as a water resource to be utilized for aqua-

culture.

(c) Work force on roll of WCL may be re-deployed for gainful utilization of

employees of WCL.

(d) As a detailed component of the Closure Plan, a Decommissioning Plan

is to be developed towards the final stages preferably 5 years prior to

tentative closure of the mine. Once established, it may be updated

annually.

E. PROTECTIVE MEASURES TO BE TAKEN

Protective measures must include the following:

(a) The protection of mine boundary, building and other structure on the

project site against access by unauthorized persons;

(b) The maintenance of all mechanical, hydraulic and waste management

system;

(c) The continuation of all monitoring programmes;

(d) The control of all contaminated effluents;

(e) The securing of all petroleum products, chemicals and waste;

Page 220: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

(f) The rendering of all tailings, dams and piles of earth, rock and waste

resulting from work done on the project site in a stable and safe

condition.

F. CLOSURE COSTS

A financial provision of Rs. 6.00 lakhs per ha will be provided in the the Mine

Closure Plan as per guidelines of MoC for the entire life of the mine to

undertake mine closure activities (for plantation in slope of dumps & quarry,

for protection of mine boundary and continuation of monitoring programme

and control of contaminated effluents). Closure cost may be reviewed under

the changing circumstances and new legislative requirements.

4.7 Blasting vibration control measures

All provisions of Coal Mines Regulations will be followed.

The quantity of explosive will be decided as per condition imposed by

DGMS.

Blasting will be done in daytime during the shift change over period as per

requirement keeping in view DGMS permission, meteorological conditions,

geo-mining condition and method of mining.

Proper conformation to measures for safe blasting, to avoid damage to any

structure or annoyance to the people in the colony area or neighbouring

villages.

A safe blasting zone will be kept around the periphery of the quarry. This

zone will be kept free from village habitation and community infrastructure

and thus impact of vibration after blasting on the surface structures is

avoided.

Controlled blasting will be done near built-up areas

4.8 Impact on flora & fauna

There is no forest land in the core zone.

o There is no endangered and endemic species in core and buffer zone .

o The area is not the migratory route for any wild animal.

o Both core and buffer zones are found to be free from ecologically

sensitive and biologically rich areas/habitats, such as, national parks,

sanctuaries, biosphere reserves etc.

o WCL in association with local people will make all efforts to conserve the

flora & fauna in the immediate surrounding of the mine area.

CONTROL MEASURES TO REDUCE IMPACT ON FLORA AND FAUNA

The enhancement of forest area will occur due to creation of greenbelt.

This project is not likely to have any impact on diversity of flora & fauna

species within terrestrial and aquatic habitats.

Page 221: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

WCL in association with local people will make all efforts to conserve the

flora & fauna in the immediate surrounding of the mine area.

Mine water will be discharged only after suitable treatment to natural

water course. So, no adverse impact on downstream aquatic life of

surface water courses is expected.

4.9 Visual/Aesthetic Impacts

Suitable mitigatory measures will be taken to eliminate spots of eyesore due to

excavation of coal and OB as well as transportation, water logging by provision

of proper drainage, land reclamation (both technical and biological) and

afforestation.

Hence it can be concluded that the mining activities at proposed Junad Deep

Extension OC mine will not affect the different attributes of environment to any

significant extent.

VISUAL/AESTHETIC EFFECT CONTROL MEASURES

Regular supervision to detect the spots of eyesore and to remove the

same immediately.

Proper housekeeping is envisaged.

Physical and biological reclamation of mined out land to the extent

possible to ameliorate the environment.

Page 222: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

CHAPTER- V

ENVIRONMENTAL MONITORING PROGRAMME

5.0 ENVIRONMENTAL MONITORING –

The environmental monitoring programme at present is being carried at the

mine and will be continued as per details given below: -

S

N

Items Parameters Frequency No. of

Stations

1 Ambient

Air Quality

Monitoring

SPM, RPM, SO2,

Nox, CO & Fugitive

dust

Every Fortnight as per

EPA, Rule 2000

4

2 Water

Quality

Monitoring

1) 4 Parameters

viz. p H, Total

Suspended Solids

(TSS), Chemical

Oxygen Demand

(COD) & Oil and

Grease.

2) 35 Parameters

Every Fortnight

Once in a Year

2

3 Noise

Quality

Monitoring

Noise Levels Every Fortnight 2

4 Environme

ntal

Statement

Annual

5 Ground

Water

Level

Monitoring

& Quality

Water Level &

Quality

Parameters.

Water Level –

Quarterly.

Water Quality – Yearly.

In Buffer

Zone

Villages.

6 Complian

ce Report

of EC

Conditions

All conditions both

Specific & General

1st June &

1st December

Not

Applica

ble

Page 223: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

CHAPTER- VI

ADDITIONAL STUDIES

6.0 INTRODUCTION:

Mining is a hazardous industry. There is risk to life and property associated with

various mining and allied activities of the project. As such a detailed study has

been carried out covering identification and assessment of risk, and

recommendation of measures to prevent damage to life and property against

such risks. They are discussed below.

6.1 PUBLIC CONSULTATION

The Environmental Public Hearing in respect of proposed Junad Opencast

Expansion Project of M/s Western Coalfields Ltd., Wani North Area, Tal. Wani ,

Dist. Yavatmal for enhancement in production capacity from 0.60 MTPA to 1.50

MTPA and increase in lease area from 174.28 ha to 449.63 ha was held on

05/02/2013, 11.00 am at Kamgar Manoranjan Kendra, Bhalar Township, At Post

Bhalar, Tal. Wani, Dist. Yavatmal. The public hearing was conducted under the

Chairmanship of Shri Rajendra Deshmukh, Additional District Magistrate,

Yavatmal (The representative nominated by District Magistrate, Chandrapur).

Shri S.D.Patil, Sub Regional Officer, MPCB, Chandrapur was the Convener of the

Public Hearing. Shri N.G. Nihul, Regional Officer, MPCB, Chandrapur was the

Member of Public Hearing panel. Shri M.P.Barhanpurkar, District Mining Officer,

Yavatmal, Shri L.S.Varhade, SDO, Wani and Shri Misal, Tahsildar,Wani were also

present during the public hearing. The public hearing started at 11.00 am with

the permission of the Chairman of the Public Hearing Panel.

First of all, the Convener welcomed all present for Public Hearing. He told that,

the Public Hearing is being conducted as per the provisions of EIA Notification

dated 14/09/2006 and amended Notification dated 01/12/2009 of Ministry of

Environment & Forests, New Delhi. He told that the project proponent received

TOR (Terms of Reference) for this project from Ministry of Environment & Forests,

New Delhi on 11/07/2008. Accordingly, project proponent prepared Draft EIA &

EMP Report and submitted their application on 15/02/2010 to the Board

requesting for conducting the Public Hearing.

The Public Hearing for this project was earlier scheduled on 31.08.2010 and

21.12.2010 but during hearing it was cancelled at both the times due to some

reasons. Thereafter, the public hearing was scheduled on 10.10.2012. The public

notice for the said public hearing was published on 08.09.2012 in Daily Lokmat

(Marathi) and Daily Hitawad (English) stating date, venue and time of public

hearing. The said public hearing was postponed due to some unavoidable

reasons at that time as per District Collector, Yavatmal letter no. 937/2012 dated

06.10.2012. The notice about postponement of Public Hearing was published in

Marathi Dialy Lokmat and English Daily Hitavada on 08.10.2012. Afterwards the

Page 224: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

public hearing is scheduled on 05.02.2013 and the public notice in this behalf

was published on 02.01.2013 in Daily Lokmat (Marathi) and Daily Hitawad

(English) stating date, venue and time of public hearing.

The copies of Draft EIA/EMP and Executive Summary in English and Marathi were

made available vide letter no. 1288/2010 dated 28.07.2010 to the offices of

District Collector, Yavatmal, District Industries Centre, Yavatmal, Zilha Parishad,

Yavatmal, MPC Board (HQ), Mumbai, Regional Office and Sub Regional Office,

MPC Board, Chandrapur, Environment Department, Mantralaya, Mumbai, Tahsil

Office, Wani and offices of the concerned Gram Panchayat Pimpalgaon, Tal.

Wani for the knowledge of concerned. While issuing the notice of

postponement, it was requested to above offices for making available the

documents submitted by project proponent for the concerned to study till the

date of Public Hearing. Also, through this notice it was requested to file their

objections/suggestions within 30 days from the date of public notice to the Sub

Regional Officer, MPC Board, Chandrapur. The Member Secretary, MPC Board,

Mumbai has issued the Panel Order no. E-15 of 2013 dated 29/01/2013 for the

Public Hearing.

The Minutes of Public Hearing in respect of proposed Junad Opencast Expansion

Project of M/s Western Coalfields Ltd., Wani North Area, Tal. Wani , Dist.

Yavatmal conducted on 05/02/2013 11.00 am Kamgar Manoranjan Kendra,

Bhalar Township, At Post Bhalar, Tal. Wani, Dist. Yavatmal is placed at Annexure –

III and the isuues and replies in tabular form are given against Point no. 48 at

Annexure - II.

6.2 Disaster Management Plan

The project report has been drawn in conformity with the prevailing statutory

provisions as per Mines Act 1952, CMR 1957 applicable for safety in Opencast

Mines. However, the following matters related to safety during opencast

operations has been given a special consideration.

The rain water falling within the project area would be diverted from quarry area

providing garland drains and shall be collected towards low lying area.

However, sufficient space has been left between quarry boundary and Wardha

River for accommodating flood protection embankment.

The bench height and width would be kept as per the Statute. The gradient of

haul road should not be steeper than 1 in 16. Adequate care must be taken for

proper construction and maintenance of haul road.

The HEMM deployed in the project are equipped with suitable in-built safety

devices like audio-visual alarm, fire extinguishers, etc.

The fencing should be erected round the quarry surface so that entry to

unauthorized persons is checked. Hard hat, safety boots, dust respirators, etc.

Page 225: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

has been provided for safe working. Necessary fund provision has been made

for the same.

SAFETY ASPECTS FOR BLASTING OPERATIONS

As explosives are required in bulk for blasting in opencast mines, provision of

Regulation-16A of CMR, 1957 should be ensured.

All blasting operations are carried out in day light. Suitable precautions are

being taken as per the Statute before and after blasting operations. Controlled

blasting technique are being practiced to minimize fly off rocks and ground

vibrations and keep them within safe limits. In order to keep the ground

vibrations within the permissible limit as per DGMS Circular No. 7 of 1997 to avoid

flying of rock fragments and also to achieve satisfactory blasting results,

optimized drilling/blasting parameters depending upon rock formation using

combination of relays/delays have been evolved.

SAFETY ASPECTS FOR OUTSOURCING/HIRING OF HEMM

Special precaution should be taken while deploying workers in the mine. Before

employing any labour to the mine proper vocational training should be

imparted and recommendations of VIII Safety Conference should be strictly

followed. Terms and conditions shall be fixed by management for deployment

of labours by leaser of HEMM as well as machineries. Some of the major

aspects are as follows :

A) For persons :

i) No persons shall be deployed unless he is trained at VTC

ii) Records in Form-B & Form-D shall be maintained.

iii) Records of Vocational Training Certificate and driving license of

operators shall be kept by HEMM outsourcing agency and shall be

made readily available for inspection by management

iv) Salaries shall be distributed in front of management representative

v) No person shall be employed unless person holds VTC certificate

and Management is informed. A record of it shall be maintained.

vi) Adequate supervision shall be maintained by qualified competent

persons.

B) For Machineries as recommended by DGMS Cir. (Tech) 1 of 1999:

i) All the machineries to be deployed in mines should be checked

before deployment.

Page 226: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

ii) Regular checking of machine deployed by leaser of HEMM shall be

done. No unfit m/c shall be deployed before the defect is

rectified.

iii) A proper record of repair and maintenance alongwith inspection

done by management and defect pointed out shall be maintained

and signed by authorised person.

iv) The trucks deployed by leaser of HEMM shall be provided with

Audio visual alarms, proper light for use at night and period when

natural light is not sufficient. Also audio visual alarms for reversing

on trucks shall be provided.

Other precautions for machines

i) RTO certificate photo copies of all vehicles shall be submitted to

management.

ii) Daily welding, monitoring, inspection shall be done by the HEMM

outsourcing agencies mechanic as directed by management.

iii) Machine manufacturers should be asked to give risk analysis.

iv) Suitable type of the fire extinguishers shall be provided in

machines.

C) General:

No person/vehicle shall be deployed at any place other than authorised

place.

All workers should obey lawful instruction of mine management.

Risk Management Plan of tipper/pay loader shall be made and

implemented.

All drivers shall obey systematic traffic rules prepared by management.

Before deploying workers they must be trained and briefed about safety

aspects in opencast mine. However during course of execution of the work, if

any accident occurs whether major or minor, the matter shall have to be

immediately informed to mine management i.e., Colliery Manager/Agent/GM

of Area so that Notices of accidents in accordance of (Reg. 9 of CMR 1957) and

Section 23 of Mines Act 1952 may be given and other necessary steps may be

taken in accordance of Section 23 of Mines Act 1952 & Reg. 9 of CMR 1957 and

other relevant laws.

Page 227: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

MODEL TRAFFIC RULES FOR HEMM & LIGHT VEHICLES

Suitable traffic rules as per recommendations of VII Safety Conference may be

framed by Manager and implemented to ensure safe operation of dumpers,

light vehicles and other HEMM deployed in the project.

6.2.1 PRECAUTION AGAINST FIRE

(1) Wild or herbaceous plants shall be removed from the mine.

(2) No person shall deposit heated material or ashes on any opencast

working. Also no person shall light a fire or permit a fire to be

lighted in any OC working except by the permission in writing of

the Manager and only for a special purpose specified therein.

(3) No coal shall be left exposed in coal benches more than its

incubation period to avoid fire in seam due to spontaneous

heating.

(4) Proper type of the extinguisher to be kept in each HEMM ready for

use in case of emergency.

(5) In coal stock coal shall be despatched on the basis of first in first

out . 6.3 GENERAL LIGHTING The standards of lighting to be provided in opencast coal mines during

working hours at different places or areas where natural light is not sufficient

has been specified in notification as GSR 804

Dt.18.6.75[Cir.(legis)1/1976] under regulation 154 of CMR 1957. The standards

are summarised below.

Sl.

No.

Location Minimum

standard

of illumination

(LUX)

Level in which

illumination is

to be

provided

1. Operational area of Dragline &

Shovel

5

10

Horizontal

Vertical

2. Operational area of drills 10 Vertical

3. Operators cabin of shovel,

dragline

drill etc.

30 Horizontal

4. Dumper haul road 0.5 to 3.0 Horizontal

5. OB & Coal Dumps 3.0 Horizontal

6. Roadways & foot path from

bench to bench

3.0 Horizontal

7. Coal handling plant, workshop &

service buildings.

As per BIS

Specification

8. Picking conveyor of CHP 50 Horizontal at

level of belt at

work site

9. Working area of Dozer 10 Horizontal at

level of

crawler

Page 228: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Lighting near the faces and haul road may be arranged by cluster of high

pressure sodium vapour lamps/metal halide/HPMV lamps located on the top

of an adjustable telescopic mast, mounted on a platform with rubber tyred

which or skids and having portable diesel generating set.

6.4 DUST SUPPRESSION

For suppression of dust water sprinkler has to be provided. Suppression of

mine dust may be done by using suitable bond, for methodology of

application DGMS Circular No.8 of 1997 may be referred.

6.5 SLOPE STABILITY

It is suggested that following action may be taken to deal with slope

stability problem.

i) Vulnerable area may be identified and marked on quarry plan.

ii) Observation of actual alignment of fault, its throw, joints, etc. may

be recorded during the process of exploitation.

iii) Water drainage system may be properly implemented to prevent

accumulation of water in cracks. Also dumps shall be leveled to

prevent accumulation of water over it. Proper drainage in dumps

shall be also provided to prevent erosion of toe of dump.

iv) Regular monitoring of tension cracks, horizontal and vertical

movement of strata in critical area may be done.

v) Rise side slope to be reinforced if required because it has to stand

through out quarry life. No dumps/surface structures to be located

within 15m of quarry edge as it will act as surcharge there by

destabilizing the slope.

vi) No undercutting of slopes to be done.

vii) Proper hydrogeological studies to be done if water table is at level

of slope it should be brought down by using submersible pumps to

prevent hydrostatic pressure.

viii) Proper selection of site for dumping to be done before dumping

place shall be made free from loose material. Dumping shall not be

done at an angle more than angle of repose of material being

dumped .

ix) After completion of dumping operations dumps to be stabilized by

growing vegetation.

x) Every person deployed by leaser of HEMM must be trained &

briefed about aspects related to slope stability.

Page 229: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

6.6 HEIGHT & WIDTH OF BENCHES & MANNER OF EXTRACTION

Height of benches (both in coal & OB) shall in no case be more than

cutting/digging height of excavation.

Width of bench in coal & OB shall not be less than :

Widest equipment + 5m Ht of bench

3x largest dumper’s width.

Width of bench adopted as the maximum value amongst (a), (b) & (c)

Each cycle of operation shall consist removal of overburden followed by

extraction of the exposed coal. After extraction of coal no body shall be

employed/no work to be done at any of the benches or bottom of quarry till

benches in OB & coal are provided again from top downwards and coal is

again exposed.

6.7 RISK MANAGEMENT :

Ninth Conference on Safety in Mines recommended to adopt Risk Management

as a tool for development of appropriate health & safety management in Indian

Mines.

The Safety Management System established by a mine must ensure all risk are

identified and critical risks are controlled to ensure long term health and safety.

A Safety Management System should set the culture, framework and actions

necessary to ensure that mining operations are carried out safely.

In order to turn these commonly agreed principles into an effective safety

management system for the mine, the system may include the following

elements:

- Health & Safety Policy of the company and the mine

- Roles and Responsibilities of all levels in the organization

- Specified competencies of staff

- Safety Committee, formation and role

- Method to identify and control high risk

- Forward Programme to ensure actions to control hazards are carried out

- Emergency prepardness to cope with a hazard if it should occur

- Monitoring processes for all identified hazards with or without residual

risks

- Identification of trigger points and resultant actions if these are reached

- Safety clearance for new equipment, work methods and materials used

- Accidents Statistics collection, analysis & Actions.

- Reporting and record keeping requirements

- Auditing and review process.

Page 230: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

6.8 CONSERVATION

Quarry limits are finalized in such a way to exploit maximum possible coal.

Although for calculation of mineable coal reserves, 10% mining losses has been

taken into account, but, in practice, all efforts would be made to minimize the

losses. If these losses are minimized to 4.5% (15 cm at each contact zone of coal

& OB + 0.5% due to blasting + 1% due to transportation of coal) then coal

reserves may increase by about 0.84 Mt, which, in turn, may reduce stripping

ratio by about 0.57 m3/t.

Separate excavator will be engaged for mining coal. OB benches would be

kept sufficient advanced to avoid mixing of coal and OB.

6.9 Socio-economic Impact

The socio –economic impacts of the project is given below.

Although a few mines already exist in the buffer zone, the opening of Junad OC

mine has definitely affected its surroundings and the employment scenario.

The direct employment opportunities have already improved around the coal

mine areas & with the expansion of this project it will improve further. With the

proposed expansion of the mine the occupational structure of the area is going

to change further and many people are likely to be involved in the job of mining

and allied activities. Hence, income levels of these people are likely to improve

to significant level.

The monetary inflow in this area through salary & wages payable to the project

employees will increase because almost 50% of this amount is being spent

locally to meet the day to day domestic demand.

This regular expenditure may lead to adequate & impressive economic-

development of the area. This monetary inflow may also lead to improvement

of civic amenities because people will go for more and more consumer goods,

better educational facilities & communication.

Simultaneously various small scales & medium scale manufacturing engineering

units may also come up giving adequate alternate employment opportunities

for local people.

Employment opportunities both direct & indirect in this project are likely to cause

migration from outside. Amenities like medical educational, recreational etc.

are available to local people and their quality of life will definitely improve.

Impact on Health

At present there is a dispensary with qualified doctors & paramedical staffs in

the project. At area level there is a full-fledged hospital. The Periodical medical

Page 231: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

examination is being carried out regularly as per statute. The circulars and orders

of DGMS including the rules and regulations under Mines Act are being adhered

to in respect of occupational health and safety.

No major occupational health hazard is anticipated due to the proposed

expansion of the project.

The medical facilities are being extended to nearby villages. The situation is

likely to improve further.

Impact on Flora & Fauna

o There is no endangered and endemic species in core and buffer zone.

o By developing plantation of native species efforts are being made to

improve the green cover in and around the immediate vicinity of the

mine area.

o WCL in association with local people will make all efforts to conserve the

flora & fauna in the immediate surrounding of the mine area.

o Improved blasting techniques will be used to minimise the noise & ground

vibrations.

Both core and buffer zones are found to be free from ecologically sensitive

and biologically rich areas / habitats. As such impact on flora & fauna is likely

to be insignificant.

CONCLUSION

From earlier paragraphs, it can be inferred that the adverse impact on physical

environmental attributes due to proposed mine is almost insignificant/ negligible.

6.10 Peripheral development:

As per the present practices in WCL coal mines, adequate steps are being

taken for the local villagers by providing various infrastructural and welfare

facilities and giving assistance in health care in Wani North Area of WCL, under

which the mine under consideration is operating.

The various development works like construction of Primary, School, Post

office, Shopping center, diversion of cart track for villagers, establishment of

bank, diversion of irrigation canal etc; have been completed, mainly for

catering to the needs/socio-economic upliftment of the neighbouring

population.

Page 232: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

COMMUNITY DEVELOPMENT WORKS

SOME OF THE IMPORTANT COMMUNITY DEVELOPMENT WORKS DONE BY THE AREA AMOUNTING TO Rs. 97.45 LAKHS

ARE GIVEN BELOW.

STREET LIGHT FROM PIMPALGAON CHP TO AHERI

VILLAGE – 2 KM

6

STRRET LIGHT FROM CGM OFFICE TO UKNI VILLAGE , 1.8 KM

5

INTERNAL ROAD AT UKNI VILLAGE , 800 m4

WANI GHUGUS ROAD TO PIMPALGAON VILLAGE

APPROACH ROAD

3

APPROACH ROAD TO KOLERA VILLAGE , 1.5 KM2

BHALLAR VILLAGE INTERNAL ROAD REPAIRING WBM

& ZP SCHOOL BUILDING REPARING

1

DESCRIPTIONSL . NO.

Page 233: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

COMMUNITY DEVELOPMENT WORKS (contd.)

CONSTRUCTION OF A HALL AT RAMAIBAI MAHILA

MANDAL AT RAJUR

14

SPORTS MATERIAL FOR Z. P. SCHOOL RAJUR13

REPAIRING OF PRIMARY SCHOOL RAJUR12

BOUNDARY WALL OF Z. P. SCHOOL RAJUR 11

HAND PUMP AT NEELPUR AND PIMPALGAON

VILLAGE

10

REPAIRING OF Z. P. PRIMARY SCHOOL AT RAJUR9

ONE BOREHOLE AT BHANDEWADA VILLAGE

INCLUDING WATER TANK

8

REPAIR OF Z. P. BUILDING AT AHERI VILLAGE7

DESCRIPTIONSL . NO.

CSR Activities at nearby villages

2010- 11

Sl.No Name of CSR Work Amount

(Rs.in Lakhs)

Remarks

1. Construction of Concrete road

at Junad Village (90m X 3 m)

1.85 Completed

2. Providing 2 Nos. of Hand Pump

at Ukni Village

1.07 Completed

3. Construction of concrete road

at Pimpalgaon Village (150 m X

3 m)

2.48 Completed

4. Construction of cement

concrete raod at Borgaon

Village

4.23 Completed

5. WBM road at Borgaon Viallge 2.31 Completed

6. Repairing of existing approach

road at Aheri village

1.16 Completed

7. Repair of WBM road from

village junction to Magazine

Building at Ukni Village

2.69 Completed

8. Boundary wall at Z.P. School at

Pimpalgaon Village

7.88 Completed

Page 234: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

2011- 12

Sl.No Name of CSR Work Amount

(Rs.in Lakhs)

Remarks

1. Construction of concrete road

at Junad Village (200 m X 3 m)

4.17 Completed

2. Construction of two class

rooms for Z.P. School at Junad

Village

4.29 Completed

3. Construction of cremation

shed at Ukni Village

4.13 Completed

4. Construction of Bituminous

internal roads of Borgaon

Village

3.82 Completed

5. Reapairing and cleaning of

drains of Borgaon Village

1.58 Completed

6. Repairing of black – topped

roads from Ukni Village to

Arterial Road

6.73 Completed

The details of CSR works done during 2012-13, 2013-14 at Juand OCP & Wani

North Area as a whole sre given in subsequent pages.

Page 235: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

CSR ACTIVITIES OF THE YEAR 2012-13

Within 25 Km of Junad OCM, WANI NORTH AREA

SR.No.

Name of the Project/CSR Activity 2012-13

Total amount spent on

documentation and

dissemination

Expenditure Details of

evaluation report

(A) Infrastructure(construction, repair)

Construction of cement concrete road at Brahmani village

5.20 Completed & Finalised

stone pitching and development of bund with pathway cement benches etc of pond at Brahmni village 1 nos

7.19 Completed & Finalised

Construction of cement concrete road from main road junction towards village Nilapur (200mt)

5.52 Completed & Finalised

Construction of cement concrete road at Junad village (200 m) 7.62

7.56 Completed & Finalised

Construction of cement concrete road at Borgaon village (200mts) 2.11

1.98 Completed & Finalised

Construction of cement concrete road at Naigaon village

6.07 Completed & Finalised

Constructionof cement concrete road at Pimpalgaon village

7.00 Completed

Construction of WBM road at Ukni village (650mts)

5.54 Completed

Construction of cement concrete road at Lathi village (250 mts)

9.15 Finalised

widening and b.c of approach road from BTS turning to Lathi village

14.90 Finalised

Renovation of bus stand shed of Lathi village (1 nos)

1.04 Finalised

Construction of community hall and development work at Lathi village (6x15m)

16.21 Completed

stone pitching and development of bund with pathway cement benches etc of pond at Bhalar village 1 nos 6.91

2.22 Completed

Construction of cement concrete road from main road hanuman mandir and drain at Bhalar village (160m) 5.44

4.99 Completed & Finalised

Providing display boards at different villages under CSR of WNA (20 nos) 2.00

1.86 Completed

SUB TOTAL 96.42 Completed

Page 236: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

SR.No.

Name of the Project/CSR Activity

Total amount spent on

documentation and

dissemination

Expenditure Details of

evaluation report

(B) WATER SUPPLY AND DRINKING WATER

23 Water supply arrangement by providing 1 no tube well with submersible pump at Sewa Nagar ward 19 of Wani

1.51 Completed &

Finalised

SUB TOTAL 1.51

( C) Medical Camps and sports

1 15 nos medical camps@ 15000

2.19

15 nos completed

2 Provision of mobile medical van 3.86

3 medicine for mobile van camp 0.05

KP Mishra 0.05

sub total 6.10

(D) Sports and cultural 0.00 Completed

Sports camps 2 nos 0.25 Completed

RK Singh 0.25

sub total 0.50

GRAND TOTAL 104.53

GRAND TOTAL for 10-11, 11-12, 12-13, 13-14

331.24

Page 237: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

CSR ACTIVITIES OF THE YEAR 2013-14

Within 25 Km of Junad OCM, WANI NORTH AREA

SR.No. Name of the Project/CSR Activity 2013-

14

Total amount spent on

documentation and

dissemination Expenditure

Details of evaluation

report 2013-

14 2014-

15

EDUCATION

1 Providing cupboard, chair and playing equipment for school at Ukni village

under Ukni Sub Area

4.18 Completed 2 Providing Desk, benches, Almirah& chairs

3 Desk Bench & Steel Almirah at Zila Parishad

7 One No. Computer & desk bench for Zila

parisad School, lathi

Total 4.18

INFRASTRUCTURE

8 Making Cremation shed & hand pump at Lathi .

2.50 Completed.

9 Extension of main drain at Gowari village for storm water drainage under Gowari

gram panchayat.(200 mt.)

3.55 Completed.

10 Making cement concrete drain at

Boregaon

4.25 Completed

11 Waste water drains at ghonsa village. 4.29 Completed

12 Making cement concrete road (250 m) at

lathi

4.80

Completed

13 Const of 300 mtr cement concrete road

at Bhandewada village near RIC Mine at RSA

8.75 Completed

14 Wall compound & gate for Zila parisad

School , Lathi

1.89 Completed

15 Bus stop near Junad village(Phata) 1.63 Completed

20 Black Topping of road at various wards of

Ukni Village

0.00

Work Completed

21 Cement concrete road at Pimpalgaon at

New Basti

5.27 Completed

Total 36.92

SR.No. Name of the Project/CSR Activity

Total amount spent on

documentation and

Expenditure Details of

evaluation report

Page 238: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

dissemination

WATER SUPPLY & DRINKING WATER

23 One no. Hand pump near Bus stand at

lathi

0.66 Completed

24 Providing and fixing hand pump 2(two)

Nos at Ukni Village

0.00

Work in progress

25 Provision of one no. Water coolers &

water purifier at Sirpur

0.80 Completed

Total 1.46

Sports And Culture 0.00

27 Village Sports Tournament(Volleyball,

Kabbadi)

1.25 Completed

28 Providing Sports Material 0.55 Completed

29 Village Sports Coaching Camp(Kabbadi,

Volleyball)

1.25 Completed

Total 3.05

Social Empowerment 0.00

30 Providing training program on tailoring 0.10 Completed

31 Providing Sewing machine to mahila

mandal

0.69

Completed

Total 0.79

Health Care 0.00

33 Hiring charges for medical Van 1.13

34 Village Medical Camp 15 nos@15000 2.23 Completed

35 Medicine for 15 nos of medical camp 1.25

Total 4.61

STREET LIGHTS

36 Street light lamps with shades - 1.00 Completed

37 Street light lamps with shades - 1.00

Total 1.99

ENVIRONMENT 0.00

38 Plantation on 100 ha. Degraded forest

land - 33.12

Work in progress

39 Service Tax 5.44

Grand Total 91.57

GRAND TOTAL for 10-11, 11-12, 12-13, 13-14

422.81

Page 239: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

6.11 REHABILITATION SCHEME

There is no house oustees involved in the project. Only land losers are involved

who will be suitably rehabilitated as per company norms.

Existing Mine & Proposed Deep OC:-

Total Land Acquired: - Agricultural – 171.15 ha + Govt. Land – 3.13 ha

Total nos. of employment given – 77 nos.

Now for Deep Extn. OC 275.35 ha is proposed to be acquired.

Out of this 109.14 ha of agricultural land has been acquired against which, 50

land losers have been provided employment & 26 have been provided with

monetary compensation.

Page 240: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

CHAPTER – VII

PROJECT BENEFITS 7.0 PROJECT BENEFITS

The benefits of the project can be summarized as below:-

- The physical infrastructure in the area will be improved substantially by

following ways:-

a) Development of road, thereby improving the communication.

b) Improvement in Power, Telephone (including Mobile) facility.

c) Improvement in Health Care facility & Educational facility.

d) Improvement in Market / Trade & Business.

- The social infrastructure by way of cultural mixing of people of other states with

local community glorifying “UNITY IN DIVERSITY”.

- Substantial employment in the project & indirect employment for business &

trading, contractor, transportation, vehicle contractor, nursery development.

Page 241: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

CHAPTER - VIII

ENVIRONMENTAL COST – BENEFIT ANALYSIS

Ministry of Environment & Forests while issuing TOR has not specifically indicated

for carrying out “Cost Benefit” Analysis, hence the same has not been carried

out.

Page 242: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

CHAPTER - IX

ENVIRONMENT MANAGEMENT PLAN

9.0 GENERAL

Close monitoring of the environment and implementation of various protective

measures discussed in the report forms an important part of EMP. In the earlier

chapters the causes of various pollutions along with the preventive and

mitigating measures have been discussed. In this chapter description of the

administrative aspects of ensuring that mitigative measures are implemented

and their effectiveness monitored, after approval of the EIA is being discussed.

9.1 MONITORING ORGANISATION

To have a close watch on the environmental condition and implementation of

the various measures suggested, a multi-disciplinary approach is essential.

(a) WCL headquarter acts as an apex body which supervises the activities

relating to environment at project level through the General Manager.

(b) General Manager of the area coordinates the activities of various disciplines

in the area to render all necessary assistance at the implementing level i.e. the

Project. Area Nodal Officer (Environment) monitors all aspects of environment

on behalf of the General Manager. He also takes suitable steps for generation of

environment data along with its analysis and interpretations.

As far as plantation is concerned horticulturist with suitable backup staff shall be

provided in the area for undertaking the plantation jobs including raising of a

nursery. Plantation will have to be done on a large area. Therefore, it may be

desired that an outside agency may have to be employed for this purpose. The

horticulturist along with the supervisor shall only monitor and guide the agency

for selection of site, treatment of soil, selection of species etc.

(c) Sub Area Manager is responsible for mechanical reclamation of the area. He

is also responsible for biological reclamation with the assistance of GM's office.

Page 243: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

ORGANISATION FOR ENVIRONMENT MANAGEMENT

Sl.

No

.

Measures/Actions Agency

1. Environmental Control 1 Chief General Manager, Wani North Area

2 Nodal Officer, (Environment),

Wani North Area

3 Project Officer, Junad OC

4 Staff Officer (Civil), Wani North Area

5 Environmental Cell (WCL H.Q.)

2. Environmental

Monitoring

1 Chief General Manager, Wani North Area

2 Staff Officer (Civil), Wani North Area

3 Nodal Officer (Environment),

Wani North Area

4 Project Officer, Junad OC.

5 Environment Cell of

WCL Headquarters

6 Environmental Laboratory of

CMPDI, RI-IV

3. Reclamation 1 Project Officer, Junad OC.

2 Nodal Officer (Environment),

Wani North Area

3 Environmental Supervisor

4 Horticulturist

9.2 ENVIRONMENTAL COST PROJECTION The details of expenditure incurred on environmental pollution control measures are given as below :-

Page 244: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

EXPENDITURE INCURRED ON POLLUTION CONTROL MEASURES

72.04TOTAL

10.28WATER POLLUTION CONTROL MEASURES

3

37.26PLANTATION2

24.50AIR POLLUTION CONTROL MEASURES1

AMOUNT IN

Rs. LAKH

PARTICULARSSL.

NO.

The details of capital provision on environmental protection measures for

proposed expansion project are as given below :-

Page 245: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

PROPOSED CAPITAL FOR ADDITIONAL POLLUTION CONTROL MEASURES

37.16TOTAL

10.16WATER TANKER 5

6.0LAND RECLAMATION MEASURES

INCLUDING LAND USE MAPPING

THROUGH REMOTE SENSING

4

5.0DUST SUPPRESSION ARRANGEMENT AT

HAUL ROAD , STOCKYARD ETC.

3

8.0STRENGTHENING OF ETP FOR

WORKSHOP EFFLUENT

2

8.0STRENGTHENING OF SEDIMENTATION

POND FOR TREATMENT OF MINE WASTER WATER

1

AMOUNT IN

Rs. LAKH

PARTICULARSSL.

NO.

Page 246: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

CHAPTER – X

SUMMARY AND CONCLUSION 10.1 INTRODUCTION:

The proposed Junad Extension OC Project is an extension of existing Junad OC

mine in Junad block located on the western limb of Wardha Valley Coalfield in

Yeotmal district of Maharashtra. The P.R. for Junad OC mine was prepared by

CMPDI in October, 1989 and was sanctioned by the WCL Board in May, 1990 for

a capital of Rs. 19.148 Crores for a production capacity of 0.32 Mty. The actual

mining operations at the project could be started in November, 1998 due to

delay in land acquisition. This is expansion of existing Junad Opencast with mine

able reserve of 6.13 Mt and with maximum coal production target of 1.50 MTPA.

The Form – 1 was submitted to MOEF &CC vide letter no. WCL/HQ/ENV/11-

C/213-A dated 28.06.2014. The project was discussed in the 21st EAC meeting

held on 19.09.2014. As per the minutes of the meeting of EAC, the project was

recommended with generic TOR. Subsequently Generic ToR was issued vide

Letter No. J- 11015/225/2014 – IA. II(M) dated 21.11.2014. As indicated in the

aforesaid TOR, the PH has been completed on 05.02.2013. Based on the minutes

of PH and generic TOR, this EMP has now been prepared for obtaining

Environmental Clearance from Ministry of Environment, Forests & Climate

Change.

10.2 NEED OF THE PROJECT

There is a substantial gap between demand and availability of coal for the

mines of WCL as a whole. It is in national interest to open new mines/projects &

to go for expansion of existing projects urgently so as to meet the requirement of

coal for power and various other sectors.

The justification of this mine has been studied in the light of estimated demand

for non-coking coal from power sector in Maharashtra and production forecast

from existing, completed and ongoing projects of WCL.

10.2.1 LOCATION & COMMUNICATION

Junad Deep OC Extn. mine is located in the Yavatmal district of Maharashtra

state. It is bounded by Latitudes 20o 01' 05" to 20o 04' 10" N & Longitudes 79o 03'

09" to 79o 05' 00" E and falling in Survey of India Topo Sheet No. 55 P/4.

The existing mine is at a distance of about 140 km from Nagpur . However, the

block is presently connected by a 3 km fair weather road with Aheri village

which, in turn, is connected with Wani town towards North-West by a 19 km

metalled road. The block may also be approached by a 3 km road from Ukni /

Pimpalgaon project which is also being connected with Wani town via Bhalar

village.

Page 247: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

10.2.2 TOPOGRAPHY & DRAINAGE :-

The area of Junad Extension OC mine exhibits gently undulating topography.

The general slope of the ground is from west to east. The elevation varies from

180 m to 195 m. The Wardha River flowing from north to south is the main

drainage channel of the area.

10.2.3 CLIMATE :-

Junad block has extreme climate with temp. of 480 C during summer months

and about 100 C during winter months . The average annual rainfall is about

1250 mm.

10.2.4 PRESENT LAND USE PATTERN :-

The entire land to be acquired for extension of the Junad OC project is covered

by black cotton soil and is fertile and is generally used for growing mainly the

cash crops like cotton, sugarcane, chillies etc apart from standard agricultural

products like rice , wheat & jawar. No village is falling in the proposed leasehold

boundary of the project. All the land losers will be given compensation as per

Company’s norms.

10.2.5 SITE DESCRIPTION: -

The study area has been divided into two heads Core Zone

Buffer Zone

a) Core zone: The core zone consists of the mining leasehold area where

mining and allied activities take place. The core zone comprises of 449.63 ha of

land. The land usage is given below.

Sl.

No

Land Particulars Total Land

1. Agricultural land 443.53 ha

2. Waste Land

(Govt. Land)

6.10 ha

3. Forest Land -

Total 449.63 ha

b) FEATURES IN BUFFER ZONE

Sl.

No.

FEATURES DETAILS DISTANCE

FROM MINE

1 Industries Nil Nil

2 Railway Lines Wani Railway Siding About 9.0 km

3 State Highway State Highway No.- 84 About 5.0 km

4 Other Coal

Mines

Ukni OC, Pimpalgaon

OC , Kolar Pimpri OC

3.0 – 5.0 km

Page 248: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

5 Water Bodies Wardha River 125 m from

mine boundary

6 Human

Settlement

40 villages & WCL township within buffer

zone

10.2.6 JUSTIFICATION: -

There is a substantial gap between demand and availability of coal for the

mines of WCL as a whole. It is in national interest to open new mines/projects

urgently so as to meet the requirement of coal for power and various other

sectors.

The justification of this mine has been studied in the light of estimated demand

for non-coking coal from power sector in Maharashtra and production

forecast from existing, completed and ongoing projects of WCL.

10.3 SOURCES OF DATA

This report has been formulated using various data from the following

sources:

Sl.

No.

Type of Data Sources

1 Mining and economic

parameters and other

miscellaneous data

CMPDIL and Wani North Area,

WCL.

2

Environmental data including

meteorological data, air

quality, dust fall rate, water

quality and noise level data.

Environmental-data generation

for proposed Junad Extn.

(Deep) OC of Wani North Area

of WCL, Maharashtra carried

out by CMPDI.

3 Socio-economic study & Land

use/cover mapping buffer

zone.

Census data & base line Socio -

Economic survey.

4 Flora and fauna Survey Report prepared by the

competent authority in this

field.

5 Surface hydrology and

hydrogeology

CMPDIL, RI- IV, Nagpur.

6 Meteorological data Environmental-data generation

for Junad. Extn (Deep) OC of

Wani North Area Maharashtra

carried out by CMPDI.

7 Land use/cover mapping core

zone.

As per State Govt. Record,

data supplied by the

concerned WCL area office.

Page 249: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

10.4 GEOLOGY OF THE MINING BLOCK

The geological formation encountered in the present quarriable area are as

follows :-

Formation Thickness (m) Lithology

Minimum Maximum

Soil 3.00 24.00 Black clayey soil and sandy soil

(MWJ-24) (MWJ-27)

Kamthis 6.00 101.00 Yellow, brown, red, yellowish white

ferruginous sandstone, occasionally

grey sandy shale/shale. (MWJ-37) (MWJ-12)

Barakar 12.78 133.55 Grey white medium to grey

sandstone with shale, coal seams with

shaly coal, etc. (MWJ-20) (MWJ-27)

GEOLOGICAL STRUCTURE

Only 3 faults viz. Fault F3-F3, F4-F4 and F5-F5 are intersected in quarry. The fault

F3-F3 is minor in nature and throw is 5 m. The throw of F4-F4 & F5-F5 is 20 m

towards NE and 40 m SW respectively.

GEO - MINING PARAMETERS

Sl. No. Particulars EXTENSION QUARRY

1. FACE LENGTH (km)

a) On the floor of composite seam 1.15 – 1.28

b) On surface 1.50 – 1.70

2. DEPTH UPTO FLOOR OF COMPOSITE

SEAM(m)

a) Initial 30 - 88

b) Final 170

3. WIDTH BELOW THE DECOALED VOID OF

EXISTING OC (m)

a) On the floor of composite seam 250 - 325

b) On surface 400 – 525

4. AREA OF THE QUARRY (ha)

a) On the floor 35.20

b) On surface 70.50

5. GRADIENT OF SEAM 1 in 3

6. GRADE OF SEAM (WITH 5 CM

CONTAMINATION)

E

7. U.H.V. (WITH 5 CM CONTAMINATION) 3822

8. AVG. SEAM THICKNESS(m) 17

9. NET MINEABLE RESERVES (Mt) 6.13

10. Average stripping ratio (t:m3) 1:8.26

Page 250: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

The shovel dumper system of mining with horizontal slicing method is

recommended for the proposed extension project with sump at the bottom-

most horizon bench in the coal seam.

2.2 WASTE DISPOSAL & REHANDLING OF EXISTING OB DUMP

Two external OB dumps are proposed in dip side of the extended quarry beyond

the major boundary Fault F1-F1 at a depth ranging from 350-400 m at the floor of

coal seam. The main external OB dump No.1 lies exactly in the dip side of

extended quarry from Aheri village in north to approach road for the project in

south. The dump No.1 is proposed keeping safe distance from Pragati Nagar

township, existing water pipeline, Wardha river and approach road to the

project. External OB dump No.2 is located on other side of approach road.

In addition, about 10.33 Mm3 of OB already dumped by existing Junad OC in dip

side of the quarry over coal bearing area where Junad Extension OCP is

proposed also requires to be rehandled. The capacity of external OB dumps

proposed is about 60.20 Mm3. Remaining 0.75 Mm3 of OB will be used is

construction of safety embankment. The break up of OB quantities in external OB

dumps is given in following table.

No. Dump Capacity in Mm3

0-30m 30 -60m Total

i) Dump – 1 25.70 16.92 42.65

ii) Dump – 2 5.80 2.17 17.55

Total 60.20

The entire extension quarry which is 50.62 M.Cu.m. of existing Junad OC mine is

dumped in dump no. 1 and 2 . About 10.33 M.Cu.m. of OB to be rehandled will

also be dumped in dump no.2 (9.58 M.Cu.m.) and also used for construction of

embankment(0.75 M.Cu.m.).

The external dumps have two benches each of 30m height and final angle of

slope is proposed to be kept at maximum 28o.

A small coal handling plant is already in operation, installed at Pimpalgaon

project (about 5 km away) for Junad OCP. The same CHP will cater to the

needs of Junad Extension OC.

The CHP has facilities For crushing of coal to (-)200 mm size .The crushed coal

is being loaded in trucks by pay loader and transported to Wani Siding for

rail despatch.

Page 251: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Break up is given below .

Sl.

No.

Particulars Land

already

acquired in

existing

Junad OC

Mine

Land to be

acquired

under

proposed Junad

Extn. OC

Mine

Total

1. Agricultura

l Land

174.28 ha

269.25 ha*

449.63 ha 2. Waste Land

(Govt.

Land)

6.10ha

3. Forest

Land

NIL NIL NIL

TOTAL

174.28 ha 275.35 ha 449.63 ha

* This 269.25ha of land to be acquired includes 5.20 ha of land of Kolar pimpri

extn oc and 13.85 ha of acquired land by existing pimpalgaon oc project. Both

the projects are adjacent to Junad extension OC mine.

{Source of Data: - Sanctioned Project Report}

Changes of Land Use during Mining:

Sl. No. Particulars Area (ha)

1 Quarry Area 101.70

2 External OB Dump 175.00

3 Infrastructure including

approach road etc.

15.00

4 Diversion of Nala 00.00

5 Embankment 20.00

6 Area needed for

rationalization & safe

blasting zone

137.93

TOTAL 449.63

Page 252: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Table 2: Stage-wise Cumulative Plantation

year Green Belt

External Dump(OB +

Top Soil) Backfilled area

Others (undisturbed

area/etc.) Total

1 Area (ha)

No. of trees

Area (ha)

No. of trees

Area (ha)

No. of

trees

Area (ha)

No. of trees

Area (ha)

No. of trees

2 1st year

0 0 0 0 0 0 0 0 0 0

3 3rd year

0 0 0 0 0 0 0 0 0 0

4 5th year

0 0 25 62.5 0 0 10 25 35 87.5

5 End of mine life

0 0 110 275 0 0 145.93 364.825 255.93 1

6 Post mining

0 0 175 437.50 0 0 157.93 394.825 332.93 832.33

Post mining land use plan (Conceptual)

The post-mining land use pattern at Junad Extn. Deep OCP will be as follows:-

Post-mining Landuse pattern of ML/Project Area (ha)

S.N. Land use during mining

Land use (ha)

Plantation Water Body Public use Undisturbed Total

1 External OB Dump 175 0 0 0 175

2 Top soil dump 0 0 0 0 0

3 Excavation 0 101.7 0 0 101.7

4 Roads including embankment

17 8 25

5 Built up area 3 0 7 0 10

6 Green Belt 0 0 0 0 0

7 Undisturbed Area 137.93 0 0 0 137.93

Total 332.93 101.7 15 0 449.63

Page 253: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

10.5 Base line Environmental Scenario

The baseline data has been collected for various environmental components

such as, Air, Water, Noise and Soil. Baseline data collection has been carried out

within 10 KM radius from the boundary of the core zone during Pre – Monsoon

season of 2013. The statutory guidelines and practices with present norms for

coal mine projects have been followed during the baseline data generation/

collection.

Micrometeorological data generation

A meteorology station has been set up at core zone and micrometeorological

parameters like wind velocity, wind direction, temperature, relative humidity,

cloud cover etc. are recorded on hourly basis for Pre Monsoon season 2013.

Daily rainfall also has been recorded and reported.

Ambient air quality monitoring

Ambient air quality was monitored at 6 locations i.e. one in core zone and the

remaining five in buffer zone. A total of 24 samples (24-hrly) for SPM, PM10, PM2.5,

SO2, NOx and heavy metals samples were collected from each location during

the study period.

Water quality monitoring

Representative water samples 6 nos. one in surface water and five from ground

water i.e. dug well and tube well in buffer zone have been collected, preserved

and transported to R&C Environmental Egg. Laboratory, Chennai and analyzed

as per standard methods.

Noise levels recording

Noise levels were recorded by using CYGNET Integrated sound level meter

(100X) from Six ambient air quality locations during day time and night time at

an interval of four hours for one day for two months.

Soil quality monitoring

Soil samples from three locations, one in core zone, two in buffer zone were

collected at depths of 30, 60 and 100 cms and analyzed for various physico-

chemical, engineering and fertility parameters.

DATA ANALYSIS AND RESULTS

Micrometeorology

The wind velocity readings were ranging from 1.0 - 20.2 m/sec. Predominant

wind was from North-West direction. The maximum temperature recorded was

Page 254: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

47.0C and the minimum was 22.5 C. The relative humidity ranges from 25% to

100% and 29.4 cm rainfall was recorded during the study period.

Air quality

Core zone

The Suspended Particulate Matter (SPM) values were ranging from 121 g/m3 to

260 g/m3 PM10 and PM2.5 values are ranging from 62 g/m3 to 90 g/m3 and

30 g/m3 to 44 g/m3 respectively. SO2 and NOx values are varying between

15.5 to 20.0 g/m3 and 20.1 to 27.6 g/m3 respectivelyThe heavy metals like

Arsenic ( As) and Mercury ( Hg) were found to be Below Detectable Limit ( BDL)

and other metals like Nickel ( Ni), Lead ( Pb) and Chromium ( Cr) values are

found to be very low and negligible. All the values are found to be well within

the NAAQ Standards prescribed by CPCB.

Buffer zone

The Suspended Particulate Matter ( SPM) values were ranging from 84 g/m3 to

237 g/m3PM10 and PM2.5 values are ranging from 31 g/m3 to 83 g/m3 and

16 g/m3 to 27 g/m3 respectively. SO2 and NOx values are varying between

12.5 to 17.6 g/m3 and 14.6 to 24.3 g/m3 respectively. respectivelyThe heavy

metals like Arsenic ( As) and Mercury ( Hg) were found to be Below Detectable

Limit ( BDL) and other metals like Nickel ( Ni), Lead ( Pb) and Chromium ( Cr)

values are found to be very low and negligible. All the values are found to be

well within the NAAQ Standards prescribed by CPCB.

Water quality

The water samples (6 Nos.) collected from different water sources i.e. Surface &

ground water etc. are analyzed as per procedures outlined in IS: 2488 / IS: 3025

/APHA.

At all locations, Oil and grease, phenolic compounds, cyanides, sulphides and

insecticides are found to be absent and all heavy metal values except Iron and

Zinc are found to be below the detectable limit. In general, the water quality at all

six locations are found to be well within the prescribed norms of IS: 10500 - 1991

(permissible limit) and IS: 2296 - 1982

Noise levels

Mean Leq noise levels at day time and night time are ranging from 64.9 to 67.8

dB(A) and 54.8 to 57.4 dB(A) respectively in the core zone. Mean Leq noise levels

at day time and night time are ranging from 43.2 to 49.1 dB(A) and 38.8 to 41.9

dB(A) respectively in the Buffer zone. While comparing with IS: 4954 -1986 norms

for acceptable outdoor noise levels all values are found to be well within the

prescribed limits.

Soil quality

The soil quality of the project area appears to be good and would support

vegetation after suitable reclamation / modification.

Page 255: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

CONCLUSIONS

The following conclusions are drawn based on the baseline data collected at

core and buffer zone area.

i) Ambient air quality parameters viz., PM10, PM2.5, SO2, NOx, and all heavy

metals are well within the NAAQ standards 2009 prescribed by CPCB.

ii) The quality of ground water in and around the project site are exceeding

the IS: 10500-1991 desirable limit. The observed values were well within the

permissible limit of IS: 10500-1991. The quality of one surface water of

Wartha River found to be good and well within the IS 2296 Norms.

iii) The Noise levels in residential and commercial areas in respect of buffer

zone and Industrial area in respect of core zone are within the norms of IS:

4954 - 1986.

iv) The soil quality in the project area appears to be good and would support

vegetation after suitable reclamation measures.

10.7 Anticipated Impacts & Pollution Control Measures

AIR POLLUTION IMPACT ASSESSMENT

The impact assessment has been carried out dealing with the following

points:

(a) Phase-wise inventory of air pollution emission sources

(b) Impact assessment

a. Phase-wise inventory of air pollution emission sources

The pollution sources are obvious and to assess the impact, the project life

is divided into following time frames:

Operation phase

Post-operational stage

The activities associated with these time frames and having impact on the

ambient air quality along with the pollutants are enumerated in the

following sections:

Operational phase

During this phase, activities necessary for mining of coal, its handling and

transport are taken up. Such activities having impact on ambient air

quality are detailed below:

(i) Drilling : Dust

(ii) Blasting of coal and

overburden

: Dust and noxious gases

(iii) Handling of coal : Dust and noxious gases

(iv) Overburden handling : Dust and noxious gases

Page 256: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

(v) Dump formation (internal) : Dust and exhaust fumes from

dumpers and dust till the

development of green cover

(vi) Movement of vehicles : Dust and noxious fumes

Post-operational stage

During this stage of the project, the activities related to the closure of

mine are to be carried out. Preparation of mine closure plan shall be

carried out during the period four to five years before the closure of the

mine. Some of the activities for the closure are:

Modifications in physical and biological reclamation of backfilled area

Salvaging and shifting operation of HEMMs and other equipment

Clearing of coal and other materials, restoration of infrastructure

area & colony area to the extent possible and necessary if not useful

for other projects

Management of hydrology and hydrogeology.

Redeployment of workforce, etc.

Arrangement & implementation of post-operation monitoring mainly

keeping watch, vigil, etc.

The activities having impact on the ambient air quality are enumerated

below:

(i) Movement of HEMMs for physical

reclamation of backfilled area

: Dust and obnoxious

fumes

(ii) Movement of vehicles for shifting and

salvaging operation of HEMMs and other

equipment

: Dust and obnoxious

fumes

(iii) Movement of vehicles for clearing of coal

and other materials

: Dust and obnoxious

gases

b. Impact assessment

The mining and its related activities create ambient air pollution. The

impact of mining on ambient air quality are highlighted in the following

paragraphs:

(a)The ambient air quality is influenced due to the presence of RPM, SPM,

SO2, NOx, etc., which are generated due to various activities like drilling,

blasting and handling related to the project. Further, the ambient air

quality is affected marginally to a varying degree due to the mining

activities of other nearby opencast and underground coal mines of the

same coalfield. The concentration of pollutants may vary depending

Page 257: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

upon the various micro-meteorological parameters and the seasons of a

year.

(b) The baseline ambient air quality has been generated at six locations

surrounding the existing Junad OC to assess the present ambient air

quality scenario corresponding to the pre-mining status of the proposed

Deep Extension OC project. The details of baseline data have been

given in previous chapter. All the monitored parameters are well within

the permissible limit. Thus it can be concluded that although the mine

under consideration as well as the neighbouring mines are operating

since long but ambient air quality in the surrounding area has not been

affected adversely.

Now, with the proposed expansion in production capacity in the

existing OC project, there is likelihood of addition of pollution to the

existing concentration level of different attributes of ambient air. Efforts

will be made by implementation of proper abatement measures so as

to maintain the sinking capacity of ambient air to absorb the

additional load, if any, thereby maintaining the quality of ambient air

to the pre – mining level to the extent possible.

(c) Further, as per TOR received from MOEF, AAQ Prediction modeling has

been done with FDM and it has been found that there will be

insignificant increase in the level of pollutants as such there will be

negligible impact on the Ambient air quality due to proposed

expansion of the mine.

Existing Ambient Air Quality Monitoring

The ambient air quality monitoring is being carried out on regular basis as per

the Env (Protection) Amendment Rule, 2000 so as to ascertain the likely load of

various air pollutants and thereby suitably modifying the various control

measures.

Hence , it is expected that pollution load to be generated due to increased

production at Junad OC will be well within the permissible limit as the existing

air pollution control measures will be further strengthened with close monitoring

for efficient & effective implementation of the pollution control measures to

make the operation eco-friendly and it is expected that ambient air quality will

have no harmful effect on human being, flora and fauna, soil quality, surface

structures and aesthetic value of the surrounding environment.

Page 258: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

AIR POLLUTION CONTROL MEASURES

Since Junad OC is an operating mine, the environmental monitoring data

generation is being done at four locations on regular basis as per the Env

(Protection) Amendment Rule published Vide Gazette of dated 25.9.2000. In

addition to data generation, following abatement measures have also been

taken in order to suppress the dust and noxious gases generation to the

maximum possible extent.

Drilling Operations

In order to reduce dust generated by drilling operation wet drilling is done.

Blasting Operation

In order to minimize the generation of dust during blasting, the following

measures are adopted:

(a) Blast holes are properly placed/spaced/positioned.

(b Blast is properly designed in respect of hole-spacing. Hole placing and blast

design are looked into as a fresh case every time, by a competent

Blasting Officer who takes into consideration the actual geo-mining

conditions of the site.

(c) Blasting is being done between shifts or during the rest interval when the

minimum number of persons is present around the blast area. In order to

quickly disperse the dust generated in blasting operations, blasting is

avoided when there is wind. Blasting is avoided in the mornings and during

cloudy situations.

(e) Adaptation of Controlled Blasting Technique as permitted by DGMS.

Loading & Transport

Movement of vehicles and HEMM on haul roads, particularly when they are un -

metalled, is another major source of dust generation. To minimize dust

generation due to this operation, the following abatement measures will be

taken.

(a) All long-life haul roads and service roads are properly constructed and

metalled. Unmetalled roads are being kept free of ruts, potholes etc.

(b) All haul-roads are regularly sprayed with water. Water sprinklers are

regularly used in the project.

(c) Overloading of vehicles are avoided.

(d) Covering of loaded trucks by tarpauline.

(e) Regular cleaning of transportation roads.

Page 259: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

(f) Adequate green belt have been developed all along the coal

transportation road on both sides.

All the above-mentioned control measures will be continued during the

balance life of the project.

OB Dumps

On the dump slopes and top surface, plantation of grass and trees will be done

in phases and the details are as follows ;- Stage-wise Cumulative Plantation

year Green Belt

External Dump(OB +

Top Soil) Backfilled area

Others (undisturbed

area/etc.) Total

1 Area (ha)

No. of trees

Area (ha)

No. of trees

Area (ha)

No. of

trees

Area (ha)

No. of trees

Area (ha)

No. of trees

2 1st year

0 0 0 0 0 0 0 0 0 0

3 3rd year

0 0 0 0 0 0 0 0 0 0

4 5th year

0 0 25 62.5 0 0 10 25 35 87.5

5 End of mine life

0 0 110 275 0 0 145.93 364.825 255.93 1

6 Post mining

0 0 175 437.50 0 0 157.93 394.825 332.93 832.33

Coal Handling Plant

Lot of dust is generated in coal handling plant during operations like coal

crushing, transfer and conveying. Following abatement measures are adopted

for Coal Handling Plant.

i) Enclosure of the crusher house where maximum dust is generated. Also

installation of dust suppression system in the crusher house (specially

above the hopper in such a way that air borne dust is suppressed without

adding much water to the coal).

ii) Minimising the height of coal-fall at transfer points (to reduce dust

formation) and, if necessary, installing dust suppression measures.

iii) Enclosure of the belt conveyor to reduce the generation of dust due to

blowing wind.

iv) Creation of a green belt on both sides of belt conveyors and around coal

stocks and the CHP building.

Noxious gasses are emitted through exhaust fumes during the operation of

diesel / petrol operated equipment. In order to reduce such emission, regular

Page 260: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

maintenance of the diesel / petrol operated vehicles will also be carried out so

that the emissions from these vehicles are under control. However, wherever, the

condition will permit, petrol / diesel operated HEMM will be replaced by

electrically operated ones.

Water sprinkling on coal stock/face, blanketing of exposed surface will be

carried out to avoid spontaneous heating and minimize air pollution.

WATER QUALITY

Impact Assessment on Water

Identification of the sources of water pollution

Likely sources of water pollution from this project along with the type of

pollutants are as follows:

(i) Sanitary (domestic) wastewater : Suspended solids and BOD.

(ii) Industrial wastewater from

workshop

: Suspended solids, oil & grease;

(iii) Wastewater from mine : Suspended solids of coal, clay

and oil;

(iv) Surface run-off passing through

coal stockpiles

: Suspended solids;

(v) Storm water from leasehold

area and built-up area

: Suspended solids.

Impact assessment

Mining and its related activities may create water quality problems. The

impact of mining at the project on both surface and ground water

sources has been assessed and given below:

(a) Surface water sources

Deterioration of water quality and pollution of water bodies due to

discharge of mine effluent, if not treated. Change in relief pattern

due to mining may cause flooding, siltation, choking and pollution.

Mitigatory measures would involve provision of (i) garland drains on

periphery to prevent surface run-off from entering into the quarry ,

(ii) catch drain around the dumps for avoiding siltation and (iii)

sedimentation ponds for reducing the pollution of surface water

bodies.

Possible overflow of water from nearby rivers/nallahs must be

safeguarded by stone pitching and strengthening the embankment

along the side of the water course

Page 261: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

In order to assess the existing quality of surface as well as ground

water quality surrounding the project site , water samples from six

locations have been collected & analysed .

The details are incorporated in the previous chapter. All the

parameters are well within the permissible limit.

The mine water discharge quality of existing opencast project is

being monitored regularly as per Env. (Protection) Amendment Rule

, 2000 . The result indicates that even in untreated condition mine

pumped out water does not contain any pollution load.

However, due care will be taken to treat the mine water discharge

by sedimentation for the proposed project. Effluents from workshop

is continue to be treated in ETP and moreover water will be mostly

recycled in Workshop & CHP. As such, possibility of adverse impact

on natural watercourses after mixing is very remote. Garland drain

around the OB dump & coal dump will be made to avoid siltation

of natural water course.

Based on the data collected at the existing coal mine, it can be concluded that

the impact due to proposed mining operation, the adverse impacts on water

both surface as well as ground water will be insignificant.

WATER POLLUTION CONTROL MEASURES

Salient controls measures have been taken are as follows:

i) Industrial Effluent

The wastewater from workshop and CHP, which normally remain laden with oil

and grease, suspended and dissolved solids etc. are treated in the Effluent

Treatment Plant (ETP). Clear water coming out from the treatment plant is taken

into the closed water circuit and recycled for its reuse. All parameter of ETP

waste discharge are monitored regularly as per Env. (Protection) Amendment

Rule, 2000 and found to be within permissible limits.

ii) Mine Water

Most of the suspended particles are settled in the mine sump as initial settlement

and the supernatant water is pumped out. This water is passed through

sedimentation pond on surface, before being discharged in to natural drain.

iii) Surface Run-off

Adequate numbers of vegetation will be grown on the top surface and slopes

of the dumps in order to arrest the erosion of soil and it also reduces surface run-

off, which helps averting siltation of natural watercourses.

Page 262: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Catch drains of suitable size have been provided around periphery of the OB

dump as well as soil dumps to arrest site and sediment flows from the respective

dump sites.

In case of OB benches in the quarry, cross drainage have been provided which

carries silt and sediments into main sump made at the floor of the seam which

will accumulate all the silts and act as first stage settling pond. The water is then

pumped out through pumps on to the surface and discharged in to surface

settling tank/sedimentation pond. The clear water from the surface

sedimentation tank is used for watering the mine area, roads and green belt

development. The catch drains mentioned above are regularly desilted and

maintained properly. In addition, garland drains have also been provided

around the periphery of the excavated area, which carries surface run off and

the drains are regularly desilted before onset of monsoon. These drains allow

accumulation of silt materials and sufficient retention time for settling of silt

materials.

The domestic sewage disposal arrangement has been provided in the township.

Regular water quality/effluent quality monitoring is also carried out so as to

ascertain the likely load of pollutants and thereby suitably modifying the control

measures.

The existing water pollution control measures can be summarized as below :-

Page 263: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

MINE WATER :- TWO STAGE SEDIMENTATION

INITIAL SEDIMENTATION - AT MINE SUMP

(SIZE- 800mX60mX4m)

FINAL SEDIMENTATION - SEDIMENTATION POND AT

SURFACE (SIZE- 24mX8mX1.5m)

INDUSTRIAL / WORKSHOP EFFLUENT:

WORKSHOP EFFLUENT IS BEING TREATED IN

WORKSHOP ETP .

DOMESTIC EFFLUENT:

THERE IS ONE INTEGRATED DOMESTIC EFFLUENT

TREATMENT PLANT AT COMBINED TOWNSHIP(0.6MLD) AT BHALAR.

EXISTING WATER POLLUTION CONTROL MEASURES

In addition to the above, provision have also been made for augmentation/

strengthening of existing sedimentation pond as well as Workshop Effluent

Treatment Plant.

NOISE QUALITY

In order to assess the existing ambient noise level in the surrounding of proposed

project site corresponding to pre-mining scenario , baseline noise level data has

been generated & details are enclosed as Annexure – III. All the values are well

within the permissible limit.

Proposed mine would be associated with following activities that may generate

noise during operation :

(a) Drilling

(b) Blasting

(c) Shovel operation

(d) Dozing

(e) Movement of dumper

(f) Operation of CHP / Workshop

The following are some of the important activities responsible for high noise level

generation, with their expected noise levels :

Page 264: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

a. All mining activities i.e. drilling, blasting, shoveling, dozing and

dumping are associated with high noise level [about 100 dB(A)].

b. Operation of most HEMMs produce high noise level. The noise level

are in range of 80 – 100 dB(A). Noise level have been found to be

related to engine capacity.

c. Crusher – General noise level due to crusher ranges from 90 dB(A) –

105 dB(A). Some of noisy equipment produce noise whose level is

around 120 dB(A).

The average sound pressure level of some of the HEMM associated with mining

operation which are responsible for high noise level generation are as follows :

EQUIPMENT NOISE LEVEL

[dB(A)]

Dozer 98

Dumper 92

Power shovel 93

Drilling machine 96

ACCEPTABLE INDUSTRIAL NOISE LEVEL

As per Env. (Protection) Amendment Rules, 2000 the ambient air quality

standards in respect of noise in industrial , commercial , residential and silence

zones area as follows :

Sl.

No.

Category of

area

Limits [dB(A)]

Day time (6.00 AM to 10.00 PM

)

Night time (10.00 PM to 6.00 AM )

1. Industrial 75 70

2. Commercial 65 55

3. Residential 55 45

4. Silence zone 50 40

Assessment of the degree of noise to which a workplace noise is harmful, is done

by comparing the values measured at workplace to the permissible limit

adopted by statutory bodies like DGMS.

Page 265: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

The impact of mining on ambient noise quality are highlighted in the following

paragraphs:

(a) The ambient noise quality is influenced by various activities like drilling,

blasting and material handling related to the project. Further, the ambient

noise quality is affected marginally to a varying degree due to the mining

activities of other nearby opencast and underground coal mines of the

same coalfield.

(b) The baseline ambient noise quality has been generated at six locations

surrounding the existing Junad OC to assess the present ambient noise

quality scenario corresponding to the pre-mining status of the proposed

Deep Extension OC project. The details of baseline data have been given

in previous chapter. All the monitored parameters are well within the

permissible limit.

(c) Thus it can be concluded that although the mine under consideration as

well as the neighbouring mines are operating since long but ambient

noise quality in the surrounding area has not been affected adversely.

Now, with the proposed expansion in production capacity in the existing OC

project, there is likelihood of addition of noise load to the existing concentration

level of ambient noise. Efforts will be made by implementation of proper

abatement measures so as to maintain the sinking capacity of ambient noise to

absorb the additional load, if any, thereby maintaining the quality of ambient

noise to the pre – mining level to the extent possible.

NOISE POLLUTION CONTROL MEASURES

Monitoring of the noise control will be carried out on regular basis as per the Env

(Protection) Amendment Rule 2000. While planning for an effective noise

attenuation measures, the concept of source, path and receiver has been

considered.

(A) Noise Control at Source

There are two areas where the noise generation can be checked at source.

(i) Proper Design

Since the generation of noise can be reduced by reducing the vibration

amplitude, the area of vibrating part and frequency of vibration will be taken

care that all loose contact between metal parts avoided.

Shock absorbing pads will be fixed in the foundation of vibrating equipment /

machines. In case of aerodynamic noise producing sources, mufflers will be

provided with the machines.

Page 266: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

(ii) Proper Maintenance

All machines and equipment will be properly maintained. Sound muffler system

and bearing lubricating system etc. of equipment will be kept in proper

condition.

(B) Noise Control at Receiver End

Even after adopting above measures, if desired noise level is not achieved at

receiver end, in that case, following measures are suggested:

(a) The workers exposed to high noise level are provided with earplugs.

(b) Provision of enclosed booths at the worksite to protect worker from noisy

environment.

IMPACT ON LAND

LAND USE (CORE ZONE)(contd.)

6.10 ha--

449.63 ha

NIL

443.53 ha

TOTAL

174.28 ha

NIL

174.28 ha

LAND

ALREADY

ACQUIRED

275.35 haTOTAL

NILFOREST LAND3.

6.10 haGOVT. LAND

(WASTE LAND)

2.

269.25 haAGRICULTURAL

LAND

1.

LAND TO BE

ACQUIRED

PARTICULARSSL.

NO

Page 267: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

FORESTRY CLEARANCE

The during-mining land use is as follows: -

CHANGE IN LAND USE DURING MINING

67.43RATIONALISATION AREA6

70.50BLASTING ZONE5

449.63

20.00

15.00

175.00

101.70

AREA (ha)

TOTAL

EMBANKMENT4

INFRASTRUCTURE INCLUDING

APPROACH ROAD ETC.

3

EXT. OB DUMP2

QUARRY AREA1

PARTICULARSSL. NO.

LAND RECLAMATION / LAND MANAGEMENT

The following activities have been proposed for reclamation of land.

1. Backfilling of the excavated area to the extent possible.

2. Leveling of the backfilled area and carpeting with the topsoil.

3. Creation of garland drains in order to arrest the silt load, due to erosion, to

enter into natural watercourses during surface run-off.

TOTAL ML/PROJECT AREA (ha)

TOTAL FORESTLAND (ha)

Date of FC Extent of forestland

Balance area for which FC is yet to be obtained

Status of appl. for diversion of forestland

If more than one, provide details of each FC

449.63 Nil Not Applicable

Not Applicable

Not Applicable Not Applicable

Page 268: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

4. Grass, legumes and different types of plants etc. will be planted on such

reclaimed land in order to make it, as far as possible, conducive to

agricultural growth.

5. Technical and biological reclamation of external OB dump.

The density of trees is around 2000 – 2500 plants/Ha.

OB Management

Project Total waste generation

(Mm3)

Topsoil (Mm3)

Total OB generation

(Mm3)

Total OB in Ext. Dump

(Mm3)

Total OB Backfilled

(Mm3)

Original Project (ha) 10.33 Included in OB

10.33 9.58 & 0.75 in

Embankment

----

Expansion Project (ha) (balance life)

50.62 Included in OB

50.62 50.62 ----

TOTAL (Mm3)

60.95 60.95 60.20 & 0.75 in

Embankment

The capacity of external OB dumps proposed is about 60.20 Mm3. Remaining 0.75 Mm3 of OB will be used is construction of safety embankment.

The break up of OB quantities in external OB dumps is given in following table.

No. Dump Capacity in Mm3

0-30m 0.60m Total

i) Dump – 1 25.70 16.95 42.65

ii) Dump – 2 10.30 7.25 17.55

Total 60.20 SCHEDULE OF OVERBURDEN DUMPING

The following Table No. 8.3 shows the yearwise OB dumping in external OB dump No.1 and No.2

Year Programmed Excavation of

OB(Mm3)

External OB Dump-1 (Mm

3)

External OB Dump-2

(Mm3)Excluding

Rehandling

1. 8.15 8.15 -

2. 7.40 7.40/15.55 -

3. 5.26 5.26/20.81 -

4. 5.25 5.25/26.06 -

5. 5.25 5.25/31.31 -

6. 4.70 4.70/36.01 -

7. 4.50 4.50/40.51 -

8. 4.40 2.14/42.65 2.26

9. 4.40 - 4.40/6.66

10. 1.10 - 1.10/7.76

11. 0.21 - 0.21/7.97

Total 50.62 42.65 7.97

Page 269: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Points for reclamation of void of Junad OC Extn. mine

i. Due to steep gradient and in order to maintain proper haul road of 1 in 16

gradient it will not be possible for backfilling of the void in the present

proposal.

ii. In order to backfill the void of Junad Extn. OC to the extent of –35 m it is

proposed that the OB of adjacent Pimpalgaon Extn. OC could be utilized.

iii. The approx. quantity of OB of proposed Pimpalgaon Extn . OC is 200 M.Cu.m.

and is at a distance of about 5 k.m.

iv. This will simultaneously help in reduction of land required for external OB

dump of proposed Pimpalgaon Extn. OC.

Post mining land use plan (Conceptual)

The post-mining land use pattern at Junad Extn. Deep OCP will be as follows:-

Post-mining Landuse pattern of ML/Project Area (ha)

S.N. Land use during mining

Land use (ha)

Plantation Water Body Public use Undisturbed Total

1 External OB Dump 175 0 0 0 175

2 Top soil dump 0 0 0 0 0

3 Excavation 0 101.7 0 0 101.7

4 Roads including embankment

17 8 25

5 Built up area 3 0 7 0 10

6 Green Belt 0 0 0 0 0

7 Undisturbed Area 137.93 0 0 0 137.93

Total 332.93 101.7 15 0 449.63

Page 270: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Stage-wise Cumulative Plantation

year Green Belt

External Dump(OB +

Top Soil) Backfilled area

Others (undisturbed

area/etc.) Total

1 Area (ha)

No. of trees

Area (ha)

No. of trees

Area (ha)

No. of

trees

Area (ha)

No. of trees

Area (ha)

No. of trees

2 1st year

0 0 0 0 0 0 0 0 0 0

3 3rd year

0 0 0 0 0 0 0 0 0 0

4 5th year

0 0 25 62.5 0 0 10 25 35 87.5

5 End of mine life

0 0 110 275 0 0 145.93 364.825 255.93 1

6 Post mining

0 0 175 437.50 0 0 157.93 394.825 332.93 832.33

10.8 ENVIRONMENTAL MONITORING –

The environmental monitoring programme at present is being carried at the

mine and will be continued as per details given below: -

S

N

Items Parameters Frequency No. of

Stations

1 Ambient

Air Quality

Monitoring

SPM, RPM, SO2,

Nox, CO & Fugitive

dust

Every Fortnight as per

EPA, Rule 2000

4

2 Water

Quality

Monitoring

1) 4 Parameters

viz. p H, Total

Suspended Solids

(TSS), Chemical

Oxygen Demand

(COD) & Oil and

Grease.

2) 35 Parameters

Every Fortnight

Once in a Year

2

3 Noise

Quality

Monitoring

Noise Levels Every Fortnight 2

4 Environme

ntal

Statement

Annual

5 Ground

Water

Level

Monitoring

& Quality

Water Level &

Quality

Parameters.

Water Level –

Quarterly.

Water Quality – Yearly.

In Buffer

Zone

Villages.

Page 271: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

6 Complian

ce Report

of EC

Conditions

All conditions both

Specific & General

1st June &

1st December

Not

Applica

ble

10.9 PUBLIC CONSULTATION

The Environmental Public Hearing in respect of proposed Junad Opencast

Expansion Project of M/s Western Coalfields Ltd., Wani North Area, Tal. Wani ,

Dist. Yavatmal for enhancement in production capacity from 0.60 MTPA to 1.50

MTPA and increase in lease area from 174.28 ha to 449.63 ha was held on

05/02/2013, 11.00 am at Kamgar Manoranjan Kendra, Bhalar Township, At Post

Bhalar, Tal. Wani, Dist. Yavatmal. The public hearing was conducted under the

Chairmanship of Shri Rajendra Deshmukh, Additional District Magistrate,

Yavatmal (The representative nominated by District Magistrate, Chandrapur).

Shri S.D.Patil, Sub Regional Officer, MPCB, Chandrapur was the Convener of the

Public Hearing. Shri N.G. Nihul, Regional Officer, MPCB, Chandrapur was the

Member of Public Hearing panel. Shri M.P.Barhanpurkar, District Mining Officer,

Yavatmal, Shri L.S.Varhade, SDO, Wani and Shri Misal, Tahsildar,Wani were also

present during the public hearing. The public hearing started at 11.00 am with

the permission of the Chairman of the Public Hearing Panel.

First of all, the Convener welcomed all present for Public Hearing. He told that,

the Public Hearing is being conducted as per the provisions of EIA Notification

dated 14/09/2006 and amended Notification dated 01/12/2009 of Ministry of

Environment & Forests, New Delhi. He told that the project proponent received

TOR (Terms of Reference) for this project from Ministry of Environment & Forests,

New Delhi on 11/07/2008. Accordingly, project proponent prepared Draft EIA &

EMP Report and submitted their application on 15/02/2010 to the Board

requesting for conducting the Public Hearing.

The Public Hearing for this project was earlier scheduled on 31.08.2010 and

21.12.2010 but during hearing it was cancelled at both the times due to some

reasons. Thereafter, the public hearing was scheduled on 10.10.2012. The public

notice for the said public hearing was published on 08.09.2012 in Daily Lokmat

(Marathi) and Daily Hitawad (English) stating date, venue and time of public

hearing. The said public hearing was postponed due to some unavoidable

reasons at that time as per District Collector, Yavatmal letter no. 937/2012 dated

06.10.2012. The notice about postponement of Public Hearing was published in

Marathi Dialy Lokmat and English Daily Hitavada on 08.10.2012. Afterwards the

public hearing is scheduled on 05.02.2013 and the public notice in this behalf

was published on 02.01.2013 in Daily Lokmat (Marathi) and Daily Hitawad

(English) stating date, venue and time of public hearing.

The copies of Draft EIA/EMP and Executive Summary in English and Marathi were

made available vide letter no. 1288/2010 dated 28.07.2010 to the offices of

District Collector, Yavatmal, District Industries Centre, Yavatmal, Zilha Parishad,

Page 272: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Yavatmal, MPC Board (HQ), Mumbai, Regional Office and Sub Regional Office,

MPC Board, Chandrapur, Environment Department, Mantralaya, Mumbai, Tahsil

Office, Wani and offices of the concerned Gram Panchayat Pimpalgaon, Tal.

Wani for the knowledge of concerned. While issuing the notice of

postponement, it was requested to above offices for making available the

documents submitted by project proponent for the concerned to study till the

date of Public Hearing. Also, through this notice it was requested to file their

objections/suggestions within 30 days from the date of public notice to the Sub

Regional Officer, MPC Board, Chandrapur. The Member Secretary, MPC Board,

Mumbai has issued the Panel Order no. E-15 of 2013 dated 29/01/2013 for the

Public Hearing.

The Minutes of Public Hearing in respect of proposed Junad Opencast Expansion

Project of M/s Western Coalfields Ltd., Wani North Area, Tal. Wani , Dist.

Yavatmal conducted on 05/02/2013 11.00 am Kamgar Manoranjan Kendra,

Bhalar Township, At Post Bhalar, Tal. Wani, Dist. Yavatmal is enclosed herewith at

Annexure – III.

10.10 PROJECT BENEFITS

The benefits of the project can be summarized as below:-

- The physical infrastructure in the area will be improved substantially by

following ways:-

a) Development of road, thereby improving the communication.

b) Improvement in Power, Telephone (including Mobile) facility.

c) Improvement in Health Care facility & Educational facility.

d) Improvement in Market / Trade & Business.

- The social infrastructure by way of cultural mixing of people of other states with

local community glorifying “UNITY IN DIVERSITY”.

- Substantial employment in the project & indirect employment for business &

trading, contractor, transportation, vehicle contractor, nursery development.

10.11 ENVIRONMENT MANAGEMENT PLAN

Close monitoring of the environment and implementation of various protective

measures discussed in the report forms an important part of EMP. In the earlier

chapters the causes of various pollutions along with the preventive and

mitigating measures have been discussed. In this chapter description of the

administrative aspects of ensuring that mitigative measures are implemented

and their effectiveness monitored, after approval of the EIA is being discussed.

Page 273: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

MONITORING ORGANISATION

To have a close watch on the environmental condition and implementation of

the various measures suggested, a multi-disciplinary approach is essential.

(a) WCL headquarter acts as an apex body which supervises the activities

relating to environment at project level through the General Manager.

(b) General Manager of the area coordinates the activities of various disciplines

in the area to render all necessary assistance at the implementing level i.e. the

Project. Area Nodal Officer (Environment) monitors all aspects of environment

on behalf of the General Manager. He also takes suitable steps for generation of

environment data along with its analysis and interpretations.

As far as plantation is concerned horticulturist with suitable backup staff shall be

provided in the area for undertaking the plantation jobs including raising of a

nursery. Plantation will have to be done on a large area.

Therefore, it may be desired that an outside agency may have to be employed

for this purpose. The horticulturist along with the supervisor shall only monitor and

guide the agency for selection of site, treatment of soil, selection of species etc.

(c) Sub Area Manager is responsible for mechanical reclamation of the area. He

is also responsible for biological reclamation with the assistance of GM's office.

ORGANISATION FOR ENVIRONMENT MANAGEMENT

Sl. No. Measures/Actions Agency

1. Environmental

Control

1 Chief General Manager, Wani North Area

2 Nodal Officer, (Environment),

Wani North Area

3 Project Officer, Junad OC

4 Staff Officer (Civil), Wani North Area

5 Environmental Cell (WCL H.Q.)

2. Environmental

Monitoring

1 Chief General Manager, Wani North Area

2 Staff Officer (Civil), Wani North Area

3 Nodal Officer (Environment),

Wani North Area

4 Project Officer, Junad OC.

5 Environment Cell of

WCL Headquarters

6 Environmental Laboratory of

CMPDI, RI-IV

3. Reclamation 1 Project Officer, Junad OC.

2 Nodal Officer (Environment),

Wani North Area

3 Environmental Supervisor

4 Horticulturist

Page 274: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

10.12 DISCLOSURE OF CONSULTANTS ENGAGED:

CMPDI is an ISO 9001 company and one of the subsidiary companies of Coal

India Ltd. (CIL) – A Nava Ratna Company. Its registered corporate office is

situated at Gondwana Place, Kanke Road, Ranchi-834008, a capital cityof

Jharkhand state. It operates through the strategically located Regional Institutes

over six states territories of India. These Regional Institutes are engaged in

exploration, planning & design works of other subsidiaries companies of CIL,

namely, ECL, BCCL, CCL, MCL, NCL, WCL, SECL and NECL.

The company was formerly known as Coal Mines Authority Limited. And, the

Central Mine Planning & Design Institute Limited (herein after called as CMPDI) is

a planning & design division of Coal India Limited (herein after called as CIL) as

per Memorandum of Association of the company. The CIL is a holding company

since November 01, 1975, and the CMPDIL is one of its subsidiaries since then. It is

under Ministry of Coal, Government of India

10.13 CONCLUSION

From earlier paragraphs, it can be inferred that the adverse impact on physical

environmental attributes due to proposed mine is almost insignificant/ negligible.

Page 275: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

CHAPTER-XI

DISCLOSURE OF CONSULTANTS ENGAGED

11.1 Name of Consultant

Central Mine Planning & Design Institute Limited briefly, it is called as ‘CMPDI’. It

is an ISO 9001 Company.

Its registered corporate office is situated at Gondwana Place, Kanke Road,

Ranchi – 834008, a capital city of Jharkhand State. It operates through seven

strategically located Regional Institutes over six states territories of India. Details

of all seven Institutes including its corporate office are given as in Table-11.1.

Table-11.1

SN Offices Addresses Tel/Fax

Postal E-Mail Website

1 Corporate Gondwan

a Place,

Kanke

Road,

Ranchi-

834008,

Jharkhand

[email protected]

c.in,

cmpdihq@cmp

di.co.in

http://www

.cmpdi.co.i

n

+916512230483,22301

16 /+916512231447,

2232249

2 Regional

Institute-I

West End,

GT Road,

asansole –

713301,

West

Bengal

- - +913412253504/

+913412250935

3 Regional

Institute-II

Koyla

Bhawan,

Koyla

Nagar,

Dhanbad-

826005,

Jharkhand

+913262230850,22307

89/ +913262265575

4 Regional

Institute-III

Gondwan

a Place,

Kanke

Road,

Ranchi-

834008,

Jharkhand

+916512231506/

+916512231501

5 Regional

Institute-IV

Kasturba

Nagar,

Jaripatka-

440014

http://www

.cmpdi.co.i

n

+917122642134/

+917122643231

Page 276: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

6 Regional

Institute- V

SECL

Complex,

Seepat

Road,

Bilaspur,

Chhatisgar

h.

+917752246482/

+917752246481

7 Regional

Institute-VI

CWS

Colony,

P.O.

Jayant

Colliery,

Sidhi-

486890,

M.P.

+917805222329,

222172/

+917805222330

8 Regional

Institute-VII

Griha

Nirman

Bhawan,

Sachiwala

ya Marg,

Unit 3,

Bhubanesh

war-

751001,

Orissa

+916742394357,

2394760/

+916742395128

All the above Regional Institutes are dedicated to render services to seven

subsidiaries of the CIL AS follows:

Table-11.2

Sl. No. Institutes Dedicated to

1 Regional Institute-I Eastern Coalfields Ltd. (ECL)

2 Regional Institute-II Bharat Coking Coal Ltd. (BCCL)

3 Regional Institute-III Central Coalfields Ltd. (CCL)

4 Regional Institute-IV Western Coalfields Ltd. (WCL)

5 Regional Institute-V South Eastern Coalfields Ltd. (SECL)

6 Regional Institute-VI Northern Coalfields Ltd. (NCL)

7 Regional Institute-VII Mahanadi Coalfields Ltd. (MCL)

Hqrs. Ranchi is committed to render services to NEC & Non-CIL clients and

specialized assignments for both CIL & Non-CIL clients.

11.2 Brief Resume of the Consultants:

11.2.1 Establishment Background:

The company was formerly known as Coal Mines Authority Limited. And, the

Central Mine Planning & Design Institute Limited (herein after called as CMPDI) is

Page 277: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

a planning & design division of Coal India Limited (herein after called as CIL) as

per Memorandum of Association of the company. The CIL is a holding company

since November 01, 1975, and the CMPDIL is one of its subsidiaries since then. It is

under Ministry of Coal, Government of India.

11.2.2 Strength & Resources

a) Manpower:

CMPDI has more than 800 multidisciplinary technical executive professionals

who combine innovation and initiative to deliver faster and effective solutions in

planning, implementation and management of projects.

b) Resources:

CMPDI is equipped with modern laboratory facilities for undertaking various

analytical works to supplement its services. It has well equipped network of six

environmental laboratories located in various coalfields to regularly monitor air,

water and noise parameters. The central unit at Ranchi is accredited with

Central Pollution Board, New Delhi. Besides its own strength, CMPDI has access

to the vast resources with its principal, CIL, India’s largest coal producer and a

Nava Ratan Company.

11.2.3 Recognition:

CMPDI is recognized as preferred consultant by India and overseas clients,

United Nation agencies and international financial institutions and the company

is registered with

World Bank

Asian Development Bank

African Development Bank

United Nations Development Programme

11.2.4 Main Functional Area:

The main functional area of the CMPDI is to provide adequate and up-to-date

planning, design and technological supports to the CIL and its coal producing

subsidiaries to enable them to produce the planned quantity of coal efficiently

and economically with due attention to safety, conservation, quality and

environment. In addition to these, CMPDI also provides necessary consultancy

for clients outside the CIL in India and abroad. The Quality Management System

of CMPDI, Ranchi is certified under international standard – ISO-2000 by BVQI

(UK). Services covered under are as follows:

Consultancy in Mineral Exploration and Environmental Management.

Planning & Design in Mining, Civil & Architectural Engineering, Coal

Preparation & Utilization, Electrical & Mechanical Engineering, Mining

Electronics, Geomatics and Mine Construction.

Laboratory testing facilities for the above

Page 278: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Technical & Management Training in Mineral & Mining Sector

11.3 Nature of consultancy rendered:

CMPDI has been offering services in the fields enumerated in Table – 11.3

Table – 11.3

Sl. No. Services Offered

1 Exploration & Resource Evaluation

2 Mine Planning & Design Services

3 Infrastructures Engineering

4 Environmental Services

5 Beneficiation Services

6 Management Services

7 Specialized Services

8 Laboratory Services

9 ITC in Mining

10 Research & Development

12.3.1 Exploration & Resource Evaluation:

New generation exploration technology coupled with skilled manpower has

made CMPDI a twenty first century leader in mineral exploration, deposit

modeling, resource evaluation, resource management, mining geology, hydro-

geological & geophysical studies, engineering, geological investigations etc.

Services rendered under this head are described in brief in Table-11.3.1

hereinafter.

Table-11.3.1

Sl.No. Sub-heads of

Services

Services Rendered in

1 Geological

Support for

mining

Production support or mine development drilling

and prediction of faults and pinch / wash outs.

Delineation of roof / floor and dirt bands

2 Drilling Coring-Diamond rotary drills up to a capacity of

1280 m depth

Non-coring-Direct rotary and DTH drills for

geophysical logging, hydro-geological

investigations, dewatering, etc.

3 Deposit

modeling

Using geo-statistical and geological software

packages including MINEX and in-house developed

CEMPGEODOC and SASLINT software

4 Resource

Evaluation

Deposits of coal, lignite, manganese, iron ore

(magnetite and hematite), phosphorite, coal bed

methane etc.

5 Resource

Management

Strategic planning for future exploration

depending upon market demand.

Updating of reserve / resource of individual

Page 279: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

blocks or coalfields.

6 Hydro-

geological

studies

Systematic ground water investigations.

Mining hydro-geological studies

7 Geo-

engineering

works

Determination of strength properties of rocks and coal

and RQD (Rock Quality Designation) to assess strength

characteristics of strata

8 Master

planning for

assessment of

resource

potential with

respect to

CBM, globally

an emerging

environment

friendly

alternate

energy

source.

Creation of data packages of potential CBM

blocks.

Resource evaluation of CBM / CMM / AMM.

Formulation of policy guidelines for harnessing

CBM resources.

Implementation of CIL-ONGC Consortium’s

venture in developing CBM in coalfields.

To provide quality services, CMPDI is effectively utilizing technology like remote

sensing, combination drilling (coring and non-coring), multi-probe geophysical

borehole logging, seismic refraction survey etc.

CMPDI has already undertaken over 500 integrated exploration projects in

varying geological and terrain conditions.

11.3.2 Mine Planning & Design Services:

CMPDI is a premier consultant in open pit and underground mine planning &

design in coal, lignite and other minerals. It has prepared more than 950 mining

project reports with individual capacity up to 35 Million ton per annum. CMPDI

uses advance software like MINEX for resource modeling; mine planning and

scheduling of open cast and underground mine projects. It has helped its

subsidiaries to achieve unprecedented growth from open cast mines in their

organizations. Its experience in mechanized underground mining technology

spans exploitation of coal seams from 1.00 m to 20 m thickness, at different

gradients from flat to 750, with soft to extremely hard coal, liable to spontaneous

heating and gassiness and under varying roof strata conditions. Services offered

to be manifold and are enumerated briefly in Table-11.3.2.

Page 280: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Table-11.3.2

Sl. No. Services Offered

1 Master planning of coalfield

2 Perspective planning

3 Conceptual engineering studies

4 Techno-economic feasibility studies

5 Detailed project reports

6 Detailed engineering with working drawings

7 Mine ventilation & transport planning

8 Operational planning

9 Mining plans for mining lease

10 Mine capacity assessment

11 Performance analysis of equipment

12 Prediction of surface subsidence through numerical

modeling software

13 Geophysical logging, Seismic survey, Resistivity Survey.

11.3.3 Infrastructure Engineering:

CMPDI provides engineering logistic or support services for development of

infrastructure. It has developed multi-disciplinary engineering skills for

implementing projects of various complexities. In particular, it has offered

complete planning & design services for architectural planning, civil, structural,

electrical and mechanical engineering in various projects. A few of them are

enumerated in Table-11.3.3.

Table – 11.3.3

Sl. No. Services Offered

1 Planning of large capacity, high speed bulk material

handling plants

2 Turnkey execution of coal handling plants

3 Planning of high voltage sub-stations

4 Planning of workshops of various types and capacities

5 Township planning including roads, water supply, water

supply system, drainage, Water / sewerage treatment

plants and detailed planning and design of all township

infrastructure

6 Site selection of pit head thermal power plants based on

remote sensing data

7 Rail corridor alignment through remote sensing

8 Techno-economic feasibility study of captive power plants

based on pulverized coal and FBC technology

11.3.4 Environmental Services:

CMPDI holds a position of eminence in the field of environmental planning,

impact assessment, management and environmental engineering in coal and

Page 281: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

other sectors. It is the nodal agency for co-ordination and monitoring of ongoing

environmental up-gradation schemes sanctioned by Ministry of Coal and Mines

under the head “Environmental Measures and Subsidence Control”. It

undertakes technical scrutiny of new proposals, visits to project sites and

disbursement of funds to the implementing agencies.

A few of the new areas in which CMPDI has diversified are environmental and

hydro-geological studies for disposal of fly ash, development of air quality

model, bio-treatment of industrial effluents, carrying capacity base

development planning, watershed modeling and rain water harvesting. Services

offered with respect to environmental quality monitoring, engineering,

management and planning are briefly given in Table-11.3.4.

Table-11.3.4

Sl. No. Sub-heads of

Services

Services rendered

1 Environmental

Monitoring

Air quality

Water quality

Noise level

Soil quality

Micro-meteorological studies

Stack monitoring

2 Environmental

Engineering

Industrial/ Municipal effluent

treatment and recycling plants

Hazardous waste disposal site

engineering

Municipal effluent disposal site

engineering

3 Natural resource

management

Land use planning

Rain water harvesting

Watershed management plans

4 Regional planning Regional environment

management plans

Regional environment status plans

5 Environment

assessment plans

Environment assessment plans

6 Special studies Review of existing mining and

environment policies, legislations,

standards and mechanisms for

monitoring compliance,

institutional strengthening for

regulatory and counterpart

institutions.

Study of environmental problems

and action plan for restoration of

environmental quality.

Mine closure planning

Page 282: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

11.3.5 Beneficiation Services:

CMPDI specializes in planning, design and construction of new washeries and

modification of existing washeries for coal and mineral beneficiation. Services

with respect to beneficiation offered to are given in Table-11.3.5.

Table-11.3.5

Sl. No. Services Offered to for

1 Planning of coal and mineral beneficiation plants

2 Preparation of feasibility / project reports including macro

level analysis, washability studies, environmental impact

assessment and techno-economic analysis.

3 Technical studies, performance evaluation and operation

and maintenance related consultancy for existing washeries.

11.3.6 Management Services:

Management services enumerated in Table-11.3.6 have been offered by CMPDI

to different organizations or bodies.

Table-11.3.6

SN Sub-heads of Services Services rendered for

1 Coal Investment

promotion Services

Assistance to Government of India in

identification and assessment of coal mining

properties for investments through private

sector participation.

2 Quality Management

Services

Consultancy for implementation, certification

and maintenance of ISO 9001 Quality

Management System and its industry specific

translations, ISO 14001 Environment

Management System and OHSAS 18001

Occupational Health and Safety Assurance

System.

3 Human Resource

Services

Creating knowledge and skill based

workforce, CMPDI through its Staff Training

College (STC) imparts training to its clients’

personnel. Under UNDP, CMPDI has trained

professionals from Nigeria, Sultanate of Oman

and North Korea. Through its STC it has

organized training programmes under five

major categories such as (i) Technical, (ii)

Managerial, (iii) Computer application, (iv)

Quality Skills, (v) Quality System, etc. It has also

organized and conducted off-campus

training programmes with respect to Quality

System at various subsidiaries of CIL.

Page 283: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

CMPDI diversified into management system consultancy in 1998. While

continuing to provide consultancy for ISO 9000 Quality Management System

(QMS) and ISO 14000 Environmental Management System (EMS), it made forays

into consultancy for ISO 17025 (Testing and calibrating laboratories) under

consultancy scope as:

Creation of Management system

Providing training support

Implementation, certification and post certification support

11.3.7 Specialized Services:

With a view to catering to specific requirements of clients, CMPDI has been

providing field oriented specialized services to its clients. Descript services

rendered under this category have been remote sensing, terrestrial survey,

blasting, ventilation design & gas assessment in underground mines, energy

audit and non-destructive testing. Main services rendered are described in brief

in Table-11.3.7.

Table-11.3.7

SN Sub-heads of Services Services rendered in

1 Geomatics Geomatic services in mining sector ranging fro

topographical survey, baseline data generation

and monitoring of land use / land cover for

environmental management, water resource

survey and coal mine fire mapping. It has also

imparted expertise services in the field of remote

sensing applications, terrain mapping, co-

relation survey for underground mines, GPS / GIS

survey, cartography and digital image

processing.

2 Blasting Carrying out controlled blasting and ground

vibration study, vibration monitoring,

fragmentation improvement studies, random

sampling & testing of explosives and accessories

and performance evaluation of new explosives

with sophisticated testing equipment, in both

coal and non-coal sectors.

3 Non-destructive Testing

(NDT)

Services for non-destructive testing of

components of machinery, installations and

other structural elements have been provided

at site during periodic maintenance to avoid

accidental failure.

4 Ventilation and Gas

Survey

CMPDI has been offering services for ventilation

monitoring, planning & design of ventilation

system including gas assessment and testing for

underground mines.

5 Energy Audit CMPDI is empanelled as an accredited energy

Page 284: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

auditor with Govt. of West Bengal and

Petroleum Conservation Research Association

(PCRA) under Ministry of Petroleum and Natural

Gas, Govt. of India. Over 130 reports on

electrical and diesel energy conservation have

been prepared.

6 Inspection services CMPDI has been rendering pre-dispatch third

party inspection services for plants and

equipment at the manufacturers’ workstations

for materials procured by its clients.

7 Captive power plants Reports on optimum utilization, conceptual

notes and tender documents

11.3.8 Laboratory Services:

CMPDI has well equipped laboratories for carrying out investigations and

analysis for geo-chemical, petrography coal washability and geo-mechanical

properties.

For coal and lignite characterization, CMPDI has laboratories with highly skilled

manpower and state of art equipment. The data generated by these

laboratories form basis of characterization and grading of coal in exploration,

mine feasibility reports, washery design and down stream utilization. Brief

description of Laboratory Services rendered by CMPDI is given in Table-11.3.8.

Table-11.3.8

SN Sub-heads of Services Services rendered in

1 Geo-chemical

Laboratory

CMPDI has been rendering services like geo-

chemical analysis like proximate & ultimate

analysis, GCV determination of coal and lignite

and other special test through microprocessor

based automatic calorimeter and analyzer.

2 Petrographic

Laboratory

CMPDI has been carrying out evaluation for

hydro carbons, oil shales and coal bed

methane for coal coke and source rock through

sophisticated microscopes, identifying mineral

phases in coal, rocks and metal through X-Ray

diffractometer, and micro-area analysis and

cleat studies for CBM through Scanning Electron

Microscope accredited by International

Committee for Coal and Organic Petrology

(ICCP).

3 Mining Laboratory CMPDI has been determining physico-

mechanical properties of rocks for design inputs

for mine planning and other technical services

and undertaking testing of roof supports and

building materials for design support systems for

underground workings.

Page 285: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

4 Washery Laboratory CMPDI has been determining washability

characteristics of coarse, small and fine coal

and shattering & pulverized characteristics of

coal for assistance in planning and design of

coal beneficiation plants.

7 Captive power plants Reports on optimum utilization, conceptual

notes and tender documents

11.3.9 IT Services in Mining:

CMPDI has been gearing up itself fully to meet challenges of IT sector requisite

for mining industries as per IT implementation scheme with a view to

revolutionizing mining industry and mining operations in coming years. IT services

provided by CMPDI have been tabulated in Table-11.3.9.

Table-11.3.9

Sl. No. Services Offered to for

1 Mine communication and mine safety systems

2 Establishing internet and internet facilities

3 Real time fleet management system for large OC mines

using GIS & GPS.

4 Land information system using enterprise GIS.

11.3.10 R & D Services:

The Research & Development activities in coal and lignite are being

administered through the Scientific Advisory Committee (SSRC) with Secretary

(Coal) as its Chairman. The committee is entrusted with the task of planning,

budgeting and overseeing the implementation of R & D programme in coal and

lignite sector and also for application of research findings. And, CMPDI is the

Nodal Agency to co-ordinate S & T / R & D activities in coal and lignite sectors

and assist SSRC in areas mentioned herein after.

CMPDI applied research and development in the field of mining, beneficiation,

utilization, environment, exploration, etc. serving as nodal agency for all S & T

schemes funded by Ministry of Coal and R & D schemes funded by R & D Board

of CIL (constituted in August 1995).

Field oriented research projects including transfer and absorption of new

technology concerning main areas of coal research have been as follows:

Production, productivity and safety.

Coal beneficiation and utilization.

Environment and Ecology.

***********************

Page 286: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Checklist

PROPOSED JUNAD DEEP EXTN. OC PROJECT

WESTERN COALFIELDS LIMITED

I. PROJECT DETAILS

1 Name of the project JUNAD DEEP EXTN. OC PROJECT

2 Name of the Company Address Tele No. E-mail

Western Coalfields Limited Coal Estate, Civil Lines, Nagpur – 440 001 0712 – 2510151 [email protected]

3 Latitude and Longitude of the project

Latitude : N 200 01’.05” to N 200 04’.10” Longitude : E 79o03’.09” to E 79o05’.00” Topo sheet no :55-P/4

4 If a Joint venture, the names & addresses of the JV partners

No

5 Details of Coal Linkage Linked to Thermal Power Plants of MAHAGENCO

6 Whether the project is in the Critically Polluted Area (CPA):

NO

7 Cost of the project Rs.54.7840 Crores ( Additional capital- Rs 38.7577 crores)

8 Whether new or expansion project If expansion:

Expansion Project - Enhancement in in production from 0.60 MTPA to 1.50 MTPA and increase in land area from 174.28 ha to 449.63 ha

(i) from ……. MT to …….. MT 0. 60 MTPA TO 1.50 MTPA

(ii) What is the % of expansion 150 %

9 If for expansion, whether the application is under 7(ii) of the EIA Notification, 2006.

NO

10 If for expansion, please indicate the number and date of certified Compliance Report of Regional Office of the MoEF

The compliance of earlier EC certificate has been obtained from MOEF, Regional Office, Bhopal vide its letter dated 16/17.12.2013. Action Taken Report/ Revised Compliance submitted to MOEF New – Delhi & MOEF, Bhopal vide our letter dated 26.08.2014.

11 No. and Date of the TOR letter issued by the MOEF (if this is a case for EC)

J-11015/225/2014-IA.II(M) dated 21.11.2014.

12 No. and Date of the EC letter issued by the MoEF (if this is a case for reconsideration. If so, what specific reconsideration(s) being sought by the proponent)

Applying for EC with fresh TOR vide MOEF’s letter dated 21.11.2014.

13 If the project was considered in EAC, Please give date of meeting (s)

Consider for grant of TOR in the EAC Meeting held on 19.09.2014.

14 Type of Mine OPENCAST

15 Capacity of the mine applied for 0. 6 MTPA TO 1.50 MTPA.

16 ML Area Increase in land area from 174.28 ha to 449.63 ha.

(a) As per block allotment Not applicable.

(b) As per approved mine plan 449.63 ha.

Page 287: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

17 Date of approval of mine plans, mine closure plan status & date

The PR has been approved by WCL board in its 207th meeting held on15/11/2007 with capital of Rs.54.7840 Crores ( Additional capital- Rs 38.7577 crores)

18 Date of Board’s approval: 15/11/2007

19 Date of Ground water clearance

Not Applicable, As it is not falling in critical area as per CGWA.

20 Date of mine closure approval 25.08.2012.

21 Any river/Nallah flowing near or adjacent to the proposed mine. If yes, please give details.

YES. Wardha river is flowing near the mine lease boundary of the project at distance 125 m north easterly.

II. TECHNICAL DETAILS

22 Geological Reserve:

i. Total geological reserve ii. Mineable reserve iii. Extractable reserve iv. Per cent (%) of extraction v. Range of ground water level vi. Total estimated water requirement:

14.581 Mt 6.13 Mt. 6.13 Mt 42.045 % 3.90 m to12.65 m. bgl pre monsoon 1.5m to 8.85 m bgl in post monsoon 645 KL/day ( Average Demand )

23 Details of Seams

i. No of seams

ii Thickness of seams to be worked on

iii. Grade of coal iv. Stripping ratio v. Category of gaseousness vi. Average gradient vii. Maximum thickness of seams

1 no Composite seam with two sections top and bottom.

Coal seam/ Parting Thickness range (m)

Minimum Maximum

Composite Seam 14.82 18.83

Parting 0.09 2.21

GCV 4748 k Cal /kg (Grade G-9) 1:8.26 m3 /t Not applicable

1 in 2.5 to 1 in 3.5 18.83 m

24 Method of mining OPENCAST WITH SHOVEL-DUMPER COMBINATION

25 Life of mine 11 years

26 Whether ambient air quality seasonal data has been documented. If so, from which season to which season and whether the results are within the prescribed limits.

Yes, Ambient air quality data has been generated Pre- Monsoon- 2013 Yes, parameters are within the prescribed limits.

27 Whether the certificate of compliance of earlier EC from MoEF Regional Office has been obtained, if the proposal is for expansion.

The compliance of earlier EC certificate has been obtained from MOEF, Regional Office, Bhopal vide its letter dated 16/17.12.2013. Action Taken Report/ Revised Compliance submitted to MOEF New – Delhi & MOEF, Bhopal vide our letter dated 26.08.2014.

28 Details of O.B.

i. External OB dumps Yes

ii. No of OB dumps 2 No. of OB DUMP

iii. Area 175.00 ha

iv. Height 60m

Page 288: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

v. Quantity (in MCm) 60.95 m3

vi. Year of back filling Not applicable

29 Details of Internal Dumps No internal dump

i. Number of internal dumps Not applicable

ii. Area Not applicable

iii. Height Not applicable

iv. Quantity Not applicable

30 Details of final Mine Voids

i. Area 101.70 ha

ii. Depth 170 m

31 Details of Quarry

Total Quarry Area 101.70 ha.

Backfilled quarry area of ….ha shall be reclaimed with plantation

0.00 ha

A void of…. Ha at a depth of …m which is proposed to be converted into a water body.

101.70 ha at 170 m depth

32 Details of Land usage

i.Land Use Details Land use details

S.N. LAND USE Within ML Area (ha)

Outside ML Area (ha)

Total

1 Tenancy land 443.53 Nil 443.53

2 Forest land Nil Nil Nil

3 Govt. land/Waste land 6.10 Nil 6.10

Total 449.63 Nil 449.63

ii. Pre-Mining The total land requirement for this project is 449.53 ha out of which 174.28 ha has already been acquired in existing Junad OC mine and balance 275.35 ha will have to be acquired.

Land use details

S.N. LAND USE Within ML Area (ha)

Outside ML Area (ha)

Total

1 Tenancy land 443.53 Nil 443.53

2 Forest land Nil Nil Nil

3 Govt. land/Waste land 6.10 Nil 6.10

Total 449.63 Nil 449.63

iii. Post- Mining Post-mining Land use pattern of ML/Project Area (ha)

S. N.

Land use during mining

Land use (ha)

Plantation Water Body

Public use Undisturbed Total

1 External OB Dump

175.00 - - - 175.00

2 Excavation - 101.70 - - 101.70

3 Infrastructure 3.00 - 7.00 - 10.00

4 Green belt 15 - - - 15.00

5 Diversion of roads including embankment

17.0 - 8.00 - 25.00

6 Danger zone and rationalization of

area

- - - 122.93 122.93

Total 210.0 101.70 15.0 122.93 449.63

Page 289: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

33 Details of Forest issues

i. Total forest area involved (in ha) for mining

Nil

ii. Status of Forest Clearance NA

iii. Is there any National Park, eco-sensitive Zones, within 10 km radius? If so, give the details.

NA

iv. If the project is within 10KM of radius of wild life sanctuary, whether the Wild Life Management Plan has been prepared and Approved. If, so, please give the status, date of approval with budgetary provision.

NA

v. Extent of forest land in the project (including safety zone and all types of forest land) (in ha)

NA

vi. Total forest land for which Stage-1 FC is available (give area in ha), provide breakup of this area in following format:

NA

vii. Balance forest land for which Stage-1 FC is not available (give area in ha)

NA

viii Details of wildlife issues involved, if any. If so, whether WL management plan has been prepared and please indicate the status.

NA

34 Costs of the project : i)Total capital Cost: ii) Cost of Production: iii) Sale Price: iv) CSR cost: v) R&R Cost: vi) No of PAFs: vii)Environmental Management cost:

The capital Cost of the project is RS 57.784 Crores Rs 1263.44 per tonne at 100% capacity and Rs 1342.44 per tonne at 85% capacity Rs. 1477.02 per tonne agreed as per MOU with MAHAGENCO Rs. 5 per tonne Rs 8.11 Crore Only land oustee families. To be determined at the time of acquisition. Capital – Rs 37.16 Lakhs and Revenue- @ Rs 3.85/t

35 Details of transportation of coal i. In pit: ii. Surface to siding:

ii. Siding to loading:

Dumpers Dumpers & Pay loaders

Page 290: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

36 Details of reclamation

a Total Afforestation plan shall be implemented covering an area of: ………. ha at the end of mining. This will include: i. Reclaimed external OB dump ( in ha) : ii. internal dump (in ha), iii. Green belt ( in ha) iv. Density of tree plantation (in no of plants) v. void (in ha) at a depth of (in m) which is proposed to be converted into water body.

210.00 ha Plantation is planned after end of mine life No internal dump 15.00 ha 2500 plants /ha 101.70 ha at a maximum depth of 170 m

III. LEGAL ISSUES

37 Please give details, if the proposal is under any investigation

Not Applicable

38 Any court cases pending. If so, please provide a list with details as annexure.

Not Applicable

39 Any violation cases pending. If so, please provide a list with details as annexure

Not Applicable

40 Give details of actual coal production vis-à-vis sanctioned capacity since the inception of mine in following format :

Not Applicable

Year EC sanctioned capacity (MTPA)

Actual Production (MTPA)

Excess production beyond the EC sanctioned capacity

2009-10 0.6 MTPA 0.402 MTPA NIL

2010-11 0.6 MTPA 0.473 MTPA NIL

2011-12 0.6 MTPA 0.599 MTPA NIL

2012-13 0.6 MTPA 0.60 MTPA NIL

2013-14 0.6 MTPA 0.420 MTPA NIL

IV. PUBLIC HEARING ISSUES

41 Date and Place of public hearing:

05.02.2013 at Bhalar township, Wani, Yavatmal

42 Issues raised during Public Hearing and assurance given along with the financial provisions, if any, by the project proponent. (Please attach as an annexure in a tabular form.)

Details attached in subsequent pages as Annexure - I

V. CONSULTANT

43 Name of the consultant who prepared the EIA/EMP report

Central Mine Planning and Design Institute

44 Whether the consultant has been accredited by the QCI and NABL and whether it is accredited with Quality Council of India (QCI) / National

YES

Page 291: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Accreditation Board of Education and Training (NABET) as per MoEF OM 2nd December 2009

VI Whether the project was considered by the IMG of Ministry of Coal for any irregularities. If so the no. and date of the show cause notice and response to MoC

Not Applicable

Page 292: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

ANNEXURE - II

PROFORMA FOR ENVIRONMENTAL APPRAISAL OF

MINING PROJECTS (MINING SECTOR PROJECTS)

Note1 :All information to be given in the form of Annex/s should be properly

numbered and form part of reply to this proforma.

Note 2: Please enter / in appropriate box where answer is Yes/No

Note 3: No abbreviation to be used – Not available or Not

applicable should be clearly mentioned.

Note 4: Core zone is the mining lease area.

Buffer zone in case of ML area upto 25 ha. is to be considered as 5 km all around

the periphery of the core zone and for ML area above 25 ha. an area 10 km all

around the periphery of the core zone.

Note 5: Adopt Scoping process in carrying out EIA study

Note 6: Please indicate source of data

1. General Information

(a) Name of the project : Junad Deep Extn. OC Project (1.50 MTPA)

Name of the proponent : M/s WESTERN COALFIELDS LIMITED

Mailing Address : C/o Chief General Manager

Wani North Area , WCL, Bhallar Township

Dist. Yavatmal ( M. S.)

E- mail : [email protected]

Telephone : 07239 – 241347

Fax No. : 07239 – 241357 (CGM Office)

(b) Objective of the project :

To meet the demand of power

coal

(c) Location of mine(s)

Village(s) Tehsil District State

Borgaon & Junad Wani Yavatmal Maharashtra

Page 293: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

(d) Does the proposal relate to

(i) New mine : No

(ii) Expansion : Yes

Increase in ML area : Yes

Increase in annual production : Yes

(iii) Renewal of ML : No

(iv) Modernization : No

e) Site information

Geographical Location

Latitude : 200 01’05” to 200 04’10” N

Longitude : 790 03’09” to 790 05’ 00” E

Topo sheet no : 55 P/4

Total mining lease area (in ha) : 449.63

( Location Plan is enclosed as Plate- I)

(ii) Dominant nature of terrain :

Flat

Undulated : Yes , Gently undulating.

Hilly

2. Land usage of the mining lease area (in ha).

(a) Agricultural Land : 443.53

(b) Waste land(Govt.land) : 6.10

(c) Forest /Zudpi Jungle : Nil

(d) Surface water bodies : Nil

(e) Others (Specify) : Nil

Total : 449.63

3. Indicate the seismic zone in which ML area falls. In case of zone IV & V,

details of earth quakes in last 10 years. : Seismic zone no. – II

(a) Severity (Richter Scale) : Not applicable

(b) Impact i.e. Damage to

Life : No

Property : No

Existing mine : No

Page 294: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

4. Break-up of Mining lease area (in ha.) as per approved conceptual plan :

Purpose

Mining Lease Area

Total

Area acquired Area to be acquired

Government Private Government Private Government Private

Forest Others Agri. Other

s Forest Others Agri.

Oth

ers Forest Others Agri. Others

1. Area to be excavated --- --- 101.70 ---- 101.70 --- ---- 31.70 --- 70.00

2. Storage for top soil Included in Sl.No. 3 below

3. Overburden/Dumps ----- ---- 175.00 175.00 ---- 40.00 135.00

4. Mineral storage

5.Infrastructure(Work-

shop, Administrative

Building)

3.13 6.87

10.00

3.13 6.87

---

6. Roads Covered in Sl.No. 5 Above Covered in Sl.No. 5 Above

7. Railways

8. Green Belt 15.00 ha in Rationalization Area & in the

Blasting Zone. In addition to the existing

plantation over OB dump, and other plantation.

Presently

23.73 ha

has been

covered

with

Plantation

15.00 ha in Rationalization Area & in

the Blasting Zone. In addition to the

existing plantation over OB dump,

and other plantation.

9. Tailings pond

10. Effluent treatment

Plant

11.Coal handling

plant/mineral

separation plant

Covered in Sl.No. 5 Above Covered in Sl.No. 5 Above

12. Township area(for

additional Quarters)

Outside the leasehold in the existing Combined

Colony at Bhallar Township

---

13.Others ( Specify )

a) Diversion of Roads

b) Danger Zone &

Rationalization Area

6.10 15.00

141.83

15.00

147.93

5.00

87.58

6.10 10.00

54.25

Total 9.23 440.40 Nil 449.63 --- 3.13 171.15 Nil ---- 6.10 269.25

Page 295: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

5. Township (outside mining lease) : (a) Total area (in ha) : Combined Colony In Bhallar Township)

(b) No. of dwelling units : 417

(c) Distance from mine site : 5 km

6. Distance of water bodies (in km)

Distance from River Bank* Other water bodies* Sea / Creek

/Lake / nalla etc. (specify)

Mining lease

boundary

Wardha river –

150 m

-

Ancillary facilities - -

[* from highest flood line/high tide line] -

7. For projects falling within the Coastal Regulation Zone (CRZ) : Not

applicable

Whether the mineral to be mined is of rare nature and not available outside

CRZ?

If yes, annex a scaled location map showing low tide line (LTL), high tide line

(HTL) duly demarcated by one of the authorized agencies*[*Director, Space

Application Centre, Ahmedabad: Centre for Earth Sciences Studies,

Thiruvananthapuram: Institute of Remote Sensing, Anna University, Chennai,

Institute of Wetland Management & Ecological designs, Kolkata, Naval

Hydrographer’s Office, Dehradun: National Institute of Oceanography, Panjim,

Goa: and National Institute of Ocean Technology, Chennai] boundary of mining

lease area, diastance of ML area from LTL and HTL CRZ boundary and CRZ

classification of the project area as per the approved Coastal Zone

Management Plan, and settlements, sand dunes, mangroves, forest

land/patches, turties breeding and nesting sites etc., if any, in the project area.

8. Indicate aerial distance from the periphery of core zone/area from the

periphery of the buffer zone to the boundary of following (upto 10 km)

Given below ;-

a) BUFFER ZONE – It is the area within the radius of 10 km of mining lease area

and the details of features within buffer zone is as given below ;-

[*Buffer zone in case of ML area upto 25 ha. is to be considered as 5 km all

around the periphery of the core zone and for ML area above 25 ha. an area 10

km all around the periphery of the core zone].

9. Description of flora & fauna separately in the core and buffer zones*

[*Consult the Wildlife(Protection) Act, 1972 as amended subsequently and list

species with (1) Common name (2) Scientific name and (3) under which

schedule of the Wildlife (Protection) Act the identified species fall. Get the list

Page 296: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

authenticated by an Expert in the field/credible scientific

institute/University/Chief Wildlife Warden office. Information to be based on field

survey].

The details given in Chapter – III.

Area

10. Details of mineral reserves (as per approved Mining Plan)

(Quantity in million tonnes )

(a) Proved : 68.527 Million Tonnes

(b) Indicated : 14.581 Million Tonnes

(b) Inferred :

(c) Mineable reserves : 6.13 Million Tonnes

Sectorwise Net Geological reserves in Junad Block

(Figures in Mt)

OPENCAST (Upto 1:7 Coal/OB

Ratio line

UNDERGROUND

Beyond 1:7 to Fault F1-F1

Sector Proved Indicated Total Sector Proved Indicated Total

Q1 3.839 - 3.839 U1 7.168 - 7.168

Q2 0.577 - 0.577 U2 - 1.683 1.683

Q3 19.689 - 19.689 U3 37.254 - 37.254

Q4 - 4.418 4.418 U4 - 1.489 1.489

Q5 - 6.991 6.991

Total 24.105 11.409 35.514 Total 44.422 3.172 47.594

GRAND TOTAL 83.108

As stated above, only Sectors Q3 & U3 considered for present Junad Extension

OC, the Net Geological reserves of these sectors are as follows of which only

44.018 Mt are below 250 m depth.

Particulars Sector Total

Q3 U3

Incrop to 1:7 Coal:OB Ratio

line

19.689 - 19.689

Beyond 1:7 Coal:OB Ratio

line to

250 m Depth

- 24.329 24.329

Sub-Total 19.689 24.329 44.018

Beyond 250 m depth sub-

total

- 12.925 12.925

Total 19.689 37.254 56.943

11. Major geological formation/disturbances in the mining lease area

(a) Geological maps submitted : Yes

(b) Geological sections submitted : Yes

(c) Contour map submitted : Yes

Page 297: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

(d) Whether the presence, if any noted of

(i) Faults : Yes (Details given Chapter – III)

(ii) Dykes : No

(iii) Shear Zone : No

(iv) Folds : No

(v) Other weak zones : Yes, presence of sympathetic

faults and Minor slips can not be

ruled out.

(e) Source of data (Indicate) : Geological report & PR

prepared by CMPDI

12. Production of mineral(s) and life of mine

(a) Rated capacity of mine mineral wise (tonnes/annum) : 1.50 MTPA

(Maximum

Achievable)

(b) Life of mine at proposed capacity (years) : 16 years

(c) Lease period (Years) : Not applicable

(d) Date of expiry of lease (D/M/Y) : Not applicable

(e) Indicate in case of existing mines :

Date of opening of mine : 1993-94

b. Production in the last 5 years

From year 08-09 to year 13-14 in million tones. : As given below

2008-09 – 0.58 Mte

2009-10- 0.40 Mte

2010-11- 0.47 Mte

2011-12 – 0.59 Mte

2012-13 -0.60 Mte

2013-14 – 0.42 Mte

i) Projected production for the balance

Years : Maximum

Achievable

1.50 MTPA

ii) Whether mining was suspended after : No

opening of the mine ?

If yes, details thereof including last production

figures and reason for the same.

(f) Whether plans & sections provided ? : Yes

Page 298: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

13. Type and method of mining operations

Type

Method

Opencast Yes By

Mechnised

method

Manual Mechanised

Yes

Undergrou

nd

x X

Both x x

14. MINING DETAILS:-

In Junad Extension OC mine, it is proposed to extend existing OC mine in dip

side upto 170m depth. The mine parameters of the proposed extended quarry

are detailed below:-

Sl.

No.

Particulars

(As on 1.4.2006)

Extension Quarry

1

a)

b)

Face length (km)

On the floor of composite

seam

On Surface

1.15 – 1.28

1.50 – 1.70

2

a)

b)

Depth (m) upto floor of

composite coal seam

Initial

Final

30 - 88

170

3

a)

b)

Width Below the decoaled

void of existing Junad

Extn.OC

On the floor of composite

seam

On Surface

250-325

400-525

4

a)

b)

Area of the quarry

On floor (ha)

On Surface (ha)

35.20

70.50

MINEABLE RESERVES

GROSS RESERVES IN PROPOSED JUNAD OC MINE

The upthrown block of fault F6 – F6 is the main Junad block which consists of

Sectors Q2, Q3, Q5 (opencast) and Sectors U3 & U4 (underground).(Please refer

Geological Plan of Junad OCP of WCL) This division of sectors in Junad block is

based as per Geological Report of Junad block, June, 1990. As per this G.R.,

reserves upto 1:7 coal:OB ratio line are defined as opencast sectors, and

reserves beyond 1:7 coal:OB ratio line are considered as underground reserves.

Page 299: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

However, due to application of hiring HEMMs, greater depths with higher

stripping ratio can be worked by opencast method of mining. Therefore, the

revised geological break-up is given below which considers opencast reserves

upto 250m depth. The proposed Junad extension OC mine has been planned

below the RCE limit of existing Junad OC mine upto a depth of 170m at the floor

of composite coal seam. Therefore, in this report the sectors earlier identified for

underground mining in the geological notes is proposed to be worked by

opencast method of mining upto a depth of 170m.

Sector Q2 is a very narrow patch, bounded between downthrow fault F4-F4 & F5-

F5. The net geological reserves of Sector Q2 is only 0.557 Mt and considering its

width and strike, it is not viable for opencast coal mining.

Sector Q5 lies below the Wardha river in south-east direction. The net Indicated

geological reserves of Sector Q5 is 6.99 Mt but the opencast mining can be

done only after the diversion of Wardha river.

Sector U4 is a small patch below Wardha river, bounded beyond 1:7 coal:OB

ratio line and boundary fault F1-F1. The net indicated geological reserves of

Sector U4 is 1.489 Mt.

Thereby Sectors, Q2, Q5 and U4 of main Junad block are not considered in this

PR for opencast coal mining.

The sectors considered in this PR are Sector Q3 & U3. The boundary of Sector Q3

& U3 are defined as under :-

Sector Q3 :

East - Incrop and fault F4-F4 and Wardha river barrier

West - 1:7 Coal : Overburden ratio line.

North - Wardha river barrier.

South - 1:7 Coal : Overburden ratio line and Wardha river barrier.

Sector U3 :

East - Sector Q3

West - Fault F1-F1

North - Wardha river barrier.

South - Sector Q3 & U4 and Fault F1-F1

In the proposed quarriable area, the coal seam has split in two sections namely

top section and bottom section with an intervening parting of average 0.8 m

thickness varying from 0.09 m to 2.21 m. Due to steep gradient, it is not feasible

to work this parting separately. In the existing Junad OC mine, the coal is being

extracted along with parting. It is therefore proposed in this report to extract the

top and bottom section of coal seam along with intervening parting as a

Page 300: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

composite coal seam. The gross reserve in the proposed extended quarry has

been estimated considering coal thickness from roof to floor.

COAL BLOCKED UNDER VARIOUS HEADS

As stated above, only Sectors Q3 & U3 are considered for quarry planning in

proposed Junad Extension OC. The Net Geological reserves of these sectors up

to 250 m depth is 44.018 Mt.and upto major boundary Fault F1-F1 is 56.943 Mt.

The break-up of reserves in Sectors Q3 & U3 up to 250 m depth and beyond 250

m depth to boundary fault F1-F1 is given in following table.

Particulars Sector Total

Q3 U3

Incrop to 1:7 Coal:OB Ratio

line

19.689 - 19.689

Beyond 1:7 Coal:OB Ratio line

to 250 m Depth

- 24.329 24.329

Beyond 250 m depth - 12.925 12.925

Total

19.689

37.254

56.943

As per sanctiond RCE of Junad OC Mine in 1999, net geological reserves are

3.63Mt (3.26 Mt net mineable reserves). For Junad Extension OC, starting from

1.4.2008, 6.81 Mt net geological reserves (6.13 Mt net mineable reserves) are

proposed to be exploited. Therefore in total, 3.63 Mt + 6.81 Mt = 10.44 Mt

reserves from Sectors Q3 and U3 falls in quarriable area. Balance reserves in

Sectors Q3 and U3 upto major boundary fault F1-F1, is 46.503 Mt. and it falls in

the dip side and southern side of the proposed quarry.

MINING LOSS

To arrive at the mineable reserves from the gross reserves available in the

proposed extension quarry, following mining losses have been considered :-

i) 10% mining loss due to variation in seam thickness.

ii) Loss of 20 cm of coal at each contact point of coal seam thus

aggregating 40 cm (two contact points at roof and floor) which

corresponds to about 2.5% loss.

iii) 0.5% of coal loss for blasting for coal seam

iv) 0.5% loss due to spillage in coal transportation.

Considering the above mining losses, the net mineable reserves in Junad

Extension OC mine are as under:

Page 301: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Quarry

Gross

Geological

Reserves

(Mt)

Mining

Losses

(Mt)

Mineable

Reserves (Mt)

Quarry as per

Alternative IB, depth

170 m

7.086* 0.956 6.13

TARGET OUTPUT AND MINE LIFE

The proposed Junad Extension OC mine has been planned for a target

capacity of 0.60 Mt/annum. The parameters of opencast mine field and

technical conditions of its development make this target feasible with normal

indices namely strike length, width and depth of the excavated block, number

of coal seams, method of mining, location of equipment, deployment, etc. The

target production from extension quarry along with strike length and rate of

deepening are tabulated below :

Sl.

No.

Quarry Max.

target

Production

(Mt)

Depth

Range

(m)

Strike

Length

(Km)

Average

Rate of

deepening

(m/year)

1. Quarry as per

Alternative IB, depth

170 m

0.60 88-170 1.5 -

1.70

8 – 9

From above it is clear that the maximum rate of deepening is about 8 – 9

m/year in proposed Junad Extension quarry.

In proposed Junad Extension OC mine, target production of 0.60 Mt will be

achieved in Year-I i.e, in the year 2008-09. With a mineable reserve of 6.13 Mt

and target production of 0.60 Mty, the revenue life of the mine comes out to be

11 years. However for EC , the peak capacity assumed as 1.50 MTPA.

GEO-MINING CHARACTERISTICS

Seam Gradient

Geological structure of Junad block is based mainly on sub-surface data of

boreholes. Strike is mainly NW-SE, coal seam dips due south west and gradient

varying from 1 in 2.5 to 1 in 3.5 in quarriable area.

Geological Disturbances

Only 3 faults viz. Fault F3-F3, F4-F4 and F5-F5 are intersected in quarry. The fault

F3-F4 is minor in nature and throw is 5 m. The throw of F4-F4 & F5-F5 is 20 m

towards NE and 40 m SW respectively.

Page 302: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

SELECTION OF MINING METHOD

The steep gradient of the seam (gradient 1 in 2.5 to 1 in 3.5) rules out the

application of dragline method of working and surface miner working in

proposed Junad Extension OC mine. Shovel-Dumper system has been

considered to be the most suitable method of opencast mining under the

prevailing geo-mining conditions. With Shovel-Dumper system, two stripping

methods are possible:

1. Inclined slicing method &

2. Horizontal slicing method

In steep gradient, positioning of HEMM is difficult in inclined slicing method as

the benches in coal are made parallel to the seam in this method. Hence this

method is ruled out in proposed Junad Extension OC mine. In horizontal slicing,

benches in coal are made horizontal and therefore there is no problem in

positioning of HEMM. In horizontal slicing method, the sump can be made either

on the bottom most horizontal bench in coal or in the roof of coal seam. With

the sump at the roof of coal seam, the coal and overburden benches with

proper grading can be worked in almost water-free condition throughout the

year.

However, with this arrangement, initial excavation is high because of the

running slope of quarry is further reduced to this type of sump arrangement. It is

therefore proposed in this report to make the sump at the horizontal bench in

coal in one side of the quarry and to make the coal benches slightly grading

towards the sump.

Thus, the shovel dumper system of mining with horizontal slicing method is

recommended for the proposed extension project with sump at the bottom-

most horizontal bench in coal seam.

SEAM THICKNESS RANGE & VARIATION PATTERNS

The coal seam in Junad Block is thick Composite Seam ranges in thickness from

14.82 (MWJ-50) to 18.83 (MWJ-24). MECL, however, divided seam in two parts as

Top Section and Bottom Section by a parting ranging from 0.09 (MWJ-24) to 2.21

in (MWJ-26), However, for opencast proposed quarry, it is thick one Composite

Seam. The parting is generally composed of shale, carbonaceous shale and

occasionally intercalation of sandstone and shale.

Page 303: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

The summarized details of coal seam under proposed quarry are as follows :-

Sl.No. Particulars Minimum Maximum

1. The range of

quarriable

thickness

14.82 m (MWJ-50) 18.83 m (MWJ-24)

(including parting

2. The depth range 20.57 (MWJ-37) (MWJ-10)

3. The parting range 0.09 m (MWJ-24) 2.21 m (MWJ-26)

ause of very steep gradient of coal seam (1 in 2.5 to 1 in 3.5), it is difficult to

remove the parting between top and bottom section even in horizontal slicing

and with shovel dumper system with blasting method. In the existing Junad OC

mine, the coal is being extracted along with parting. In the Junad Extension OC

mine also, it is proposed to extract the entire composite coal seam along with

parting varying in thickness from 0.09m (MWJ-24) to 2.21m (MWJ-26). The quality

of coal has been assessed taking into account the mixing of parting with the

coal.

System Parameters – Bench Height, Elements of Mining System

Volume Regime

The proposed Junad Extension OC mine is an extension of existing Junad OC

Mine beyond RCE floor unit.

The access trench of existing Junad OC mine, will serve the entry to Junad

Extension OC mine also. Thus the Quarry of proposed Junad Extension OC will

be approached by the existing access trench of Junad OC mine.

To calculate the coal, OB and stripping ratio at different depths in Extension

quarry, cuts have been made at 100m FRL (Cut-I), 70m FRL (Cut-II), 40m FRL

(Cut-III), and upto 170 m depth line (Balance cut).

The cut-wise OB and coal in proposed Junad Extension OC is given below in

Table below.

CUTWISE COAL, OB & STRIPPING RATIO(Volume Regime Table)

FOR JUNAD EXTENSION QUARRY(FROM 1.4.2008 ONWARDS)

Cut FRL (m) Mineable

Reserves

(Mt)

Total OB

(Mm3)

Stripping

Ratio (m3/t) From To

Cut-I Upto 100m FRL 1.05 14.23 13.55

Cut-II 140 70 2.14 18.78 8.77

Cut-III 70 40 2.24 16.56 7.39

Balance

Cut

40 20 0.70 1.05 1.50

(Upto 170m depth line)

TOTAL 6.13 50.62 8.26

Page 304: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Thus the total mineable reserves in the Junad Extension OC mine is 6.13 Mt with

an average stripping ratio of 8.26 m3/t.

Width and Height of Benches

The maximum height of benches in overburden considered in this report is 10m

which will be drilled and blasted in one go. In unconsolidated strata/alluvium

soil, the bench height is kept as 5m. In coal also, the height of the bench is

considered as 5m. The bench width considered in this report is 20m and 30m for

non-working and working benches respectively for planning purpose.

In final batter of the quarry, the height of the benches in consolidated strata is

10m and a berm of 5m width will be maintained between two benches.

However, in unconsolidated strata/alluvium soil, the bench height considered in

final batter is 5m and the bench width (berm) is 10m. Three to four transport

horizons will be maintained in the batter at an interval of 30m.

Slope of Benches and Quarry

i) During Mining Operation

The slope of individual benches depends on the type of strata. In this report, the

slope of individual bench is proposed as 45o in soil, alluvium and clay whereas it

is 70o in hard strata as well as in coal.

The overall slope of the quarry benches during mining operation varies from 10o

to 20o (from horizontal plane) due to multiple seams.

Rise side batter remains same in the quarry during mining operation or at the

end of the quarry. The overall angle of the rise side batter of existing Junad OC

mine varies from 20o to 35o.

ii) At the end of the quarry

The slope of individual benches in the batter at the end of quarry remains same

as that during mining operations i.e, 45o in soil , alluvium and clay and 70o in

hard strata and coal.

The slope of the batter at the end of the quarry in dip side is flatter in upper

horizon because of unconsolidated strata like soil, clay, etc. In deeper horizon,

the angle of batter measured from horizontal plane is steeper compared to

upper horizon. It is 15o to 30o in upper horizon (in unconsolidated strata) and 35o

to 45o in hard strata. The slope of rise side batter is same as discussed above

under point (i).

Drilling and Blasting

The degree of fragmentation in opencast mine has to be optimized so that total

cost of drilling, blasting, excavation, transport and crushing as total system is

Page 305: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

minimized. In order to reduce the excessive vibrations at nearby surface

structure, river, road, village, etc. and also to achieve satisfactory blasting

results, an optimized control blasting system depending upon rock formations

using combination of delays and relays will have to be evolved. It is further

recommended that at the time of actual excavation, proper study on ground

vibration should be made with scientific methods.

In proposed Junad Extension OC mine, the powder factor for OB and coal has

been worked out to be 3.0m3/kg and 7.0/t respectively in partial hiring

option.However, it is proposed in this report to undertake scientific study to

assess the powder factor for OB and coal. Adequate capital provision has been

made in this report for above study.

Mine Transport

Shovel Dumper system has been proposed in this report and the coal as well as

OB will be transported by dumpers/trucks .

Haul roads with proper gradient have been proposed for Quarry and the coal

will be transported by dumpers/trucks through these haul roads and existing

access trench of Junad OC mine from quarry to coal stock yard near the

access trench. The gradient of haul roads is proposed as 1:16.

For the transportation of OB, transport horizons (benches) have been proposed

in the dip side & side benches/batter. The OB from benches will be transported

by dumpers/trucks through these transport horizons and ramps to suitable

intervals will be made to join other benches with the transport benches. The OB

below the bottom-most transport horizon can also be transported through the

haul roads where the dump is in rise side.

SEQUENCE OF MINING

The Quarry proposed in Junad Extension OC mine, is below the existing

decoaled Junad OC mine. The total mineable coal and OB in extended Quarry

are 6.13 Mt and 50.62 Mm3 respectively and the stripping ratio works out to be

8.26 m3/t.

GEO - MINING PARAMETERS

Sl. No. Particulars EXTENSION QUARRY

1. FACE LENGTH (km)

a) On the floor of composite seam 1.15 – 1.28

b) On surface 1.50 – 1.70

2. DEPTH UPTO FLOOR OF COMPOSITE

SEAM(m)

a) Initial 30 - 88

b) Final 170

3. WIDTH BELOW THE DECOALED VOID OF

EXISTING OC (m)

a) On the floor of composite seam 250 - 325

Page 306: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

b) On surface 400 – 525

4. AREA OF THE QUARRY (ha)

a) On the floor 35.20

b) On surface 70.50

5. Gradient of Seam 1 in 3

6. GRADE OF SEAM (WITH 5 CM

CONTAMINATION)

E

7. U.H.V. (WITH 5 CM CONTAMINATION) 3822

8. AVG. SEAM THICKNESS(m) 17

9. NET MINEABLE RESERVES (Mt) 6.13

10. Average stripping ratio (t:m3) 1:8.26

The shovel dumper system of mining with horizontal slicing method is

recommended for the proposed extension project with sump at the bottom-

most horizon bench in the coal seam.

15. Mine details.

(a) Opencast mine :

(i) Stripping ratio (mineral in tones to over burden in m3 ) : 1 : 8.26

(ii) Ultimate working depth (in m bgl) : 170

(iii) Indicate present working depth in case of : 114

existing mine (in m bgl)

(iv) Thickness of top soil (in m)

Minimum : 5.00

Maximum : 10.00

Average : 7.50

iii) Thickness of overburden (in m)

Minimum : 15.00

Maximum : 60.00

Average : 37.50

iv) Mining Plan

Height and width of the

bench in

Overburden/waste.

: Bench height – 10 m

Width –

Working Bench- 30m

Non-working width-

20m

Page 307: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Height & width of the

bench in ore body / coal

seam

: Bench height – 5 m

Width –

Working Bench- 30m

Non-working width-

20m

Proposed inclination /

slope of the sides of the

opencast mine

(separately for

overburden , coal/ ore

and overall slope of the pit

sides ) both while

operating the mine as well

as at the time of closure

of the mine.

: Individual Bench

slope-

Coal - 700

OB ( hard strata ) -700

OB ( soft soil ) - 450

Overall slope –

rise side - 270 to 370

(while operating &

closure )

dip side-

while operating-180-

200

while closure - 400

The recommendation

of Slope stability study

being implemented.

Whether transverse

sections across the

opencast mine at the end

of fifth year and at the

end of the life of the mine

have been submitted

: Yes

(vii) Type of blasting, if any, to be adopted. : Controlled Blasting

(b) Underground : Not Applicable

(i) Seam/Ore body Min.Depth (m) Max. Depth (m) Avg.thicikness (m)

Rate of dip in degree Direction of dip.

Mode of entry into the mine

Shaft

Adit

Incline

Details of machinery

On surface

At face

For transportation

Others

Method of stopping (metalliferrous mines)

Open

Filled

Shrinkage

Page 308: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Caving

Combination of above

Others (specify)

Extraction method

Caving

Stowing

Partial Extraction

Subsidence

Predicted max. subsidence (in m)

Max. value of tensile strain (in mm/m)

Max. slope change (in mm/m)

Whether identified possible subsidence

Area (s) superimposed on Surface

Plan has been submitted ?

Major impacts on surface features like

Natural drainage pattern, houses, buildings,

Water bodies, roads, forests etc.

Salient features of subsidence management

(monitoring and control).

16. Surface drainage pattern at mine site.

(a) Whether the pre-mining surface drainage

plan submitted?

: Yes

(b) Do you propose any modification/diversion in

the existing natural drainage pattern at any

stage? If yes, when. Provide location map

existing natural drainage indicating contours,

dimensions of pattern proposed to be

diverted, direction of flow of water, proposed

route/changes, if any i.e. realignment of

river / nallah / any other water body falling

within core zone and its impact.

: No major change-

modification / diversion

in water body and there

will not be any

adverse impact on

existing natural drainage

pattern

17. Embankment and/or weir construction

(a) Do you propose, at any stage, construction of

(i) Embankment for protection against flood : Yes

(ii) Weir for water storage for the mine : No

(b) If so, provide details thereof.

( Quantum of OB proposed for embankment ) : Details in Chapter – II.

(b) Impact of embankment on HFL and settlement around : No impact

anticipated.

Page 309: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

(d) Impact of weir on down stream users of water : Not Applicable.

18. Vehicular traffic density (outside the ML area)

Type of vehicles No. of vehicles per day

a) Existing -- Coal Tippers 190 trucks/day

Light vehicles

(b) After the proposed activity -- Coal Tippers Approx. 450 /day

& Light vehicles (at peak capacity of 1.50

MTPA)

(c) Whether the existing road network is adequate ? : Yes

If no, provide details of alternative proposal ? : NA

* Considering maximum achievable capacity of 1.50 MTPA.

19. Loading, transportation and unloading of mineral and waste rocks on

surface:

(a) Manual

(b) Tubs, mine cars, etc.

(c) Scraper, shovels, dumpers/trucks ------ Yes (Shovel & Dumper

only)

(d) Conveyors (belt chain, etc)

(e) Others (specify)

20. Mineral(s) transportation outside the ML area

Qty.(in TPD) Percentage(%)

(a) Road 4545 100

(b) Rail -

(c) Conveyors

(d) Ropeway

(e) Water ways

(f) Pipeline

(g) Others (specify)

Total 4545 100%

Considering Peak Capacity at 1.50 MTPA.

Page 310: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

21. Baseline Meteorological and Air Quality data

(a) Micro-meteorological data : [Continuous monitoring through autographic instrument for one full season other than monsoon]

(i) Wind rose pattern for one full season (16 points of compass i.e. N, NNE,NE,…) based on 24 hourly data. For Coastal

Area also furnish day-time and night time data. : Predominant wind is from North- East (NE)quadrant.

Windrose diagram is shown in Plate – XII

Day time

Night time

24 – hours period

(ii) Site specific monitored data : Predominant Wind Direction: From ENE quadrant

Month

Post

Monson

Wind Speed (m/s) Temperature (oC) Relative Humidity(%) Rain Fall *(mm) Cloud

Cover**

(Octas of

sky)

Min. Max. % of

calm

Mean

(Dry Bulb)

Highest Lowest Mean Highest Lowest Total 24-hours

Highest

No.of

Rainy

days

Mean

0.4 13.6 30.69 18.5 26.00 11.00 49.8 64.5 35 - - - Clear (Sky

Appearance)

24-hours rainfall should be reported from 08.30 hrs. IST of previous day to 08.30 hrs. IST of the day.

Rainy day is considered when 24 hrs. rainfall is > 2.5 mm.

** Visual observations of cloud cover should be recorded four times a day at regular intervals.

(iii) Indicate name and distance of the nearest IMD meteorological : Nearest IMD is located at Chandrapur.

station from which climatological data have been obtained For EIA prediction the micro-meteorological data

for reporting in the EIA report , if any. collected at the site has been considered.

Page 311: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

(b) Ambient air quality data* (RPM,SPM, SO2 and NOx)

[*Monitoring should be carried out covering one full season except monsoon – same season as in 21 (a) (i)]

[*Frequency of sampling: Sampling to be done twice a week for the entire season 24 hourly for SPM & RPM. For gaseous pollutants 24

hourly data be given irrespective of the sampling period].

(i) Season and period for which monitoring has been carried out : Winter , December 2009 – February, 2010

(ii) No.of samples collected at each monitoring station. : ***

Name of monitoring equipment

used

SPM RPM SO2 NOx Pb**

High Volume

Sampler

High Volume

Sampler

High Volume

Sampler

High Volume

Sampler

-----

Equipment sensitivity

Permissible AAQ R

standard (CPCB) I

S

200 ug/m3 100 ug/m

3 80 ug/m

3 80 ug/m

3

600 ug/m3

300 ug/m3 120 ug/m

3 120 ug/m

3

100 ug/m3 75 ug/m

3 30 ug/m

3 30 ug/m

3

Monitoring

Location

No.of

Samples

Drawn

Category*

(R,I,S)

Min. Max. 95%

tile*

Min. Max. 95%

tile*

Min. Max. 95%

tile*

Min. Max. 95%

tile*

Min. Max 95

%

tile

Core zone

A1

*** I 226 294 292 112 138 136 6.4 11.3 10.8 8.9 16.6 15.3 Not done

BUFFER

zone

A2

(Chargaon

Village)

*** R 134 169 165 52 72 70 6.0 9.4 9.0 8.6 12.5 11.7

Not done

A3

(Dhorwasa

Village)

*** R 126 168 161 42 70 68 5.6 8.0 7.5 7.1 11.7 10.6

Not done

A4

(Navi Ukni

Village)

*** R 140 173 172 50 73 67 8.4 11.4 10.9 9.6 13.6 13.1

Not done

Page 312: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Name of monitoring equipment

used

SPM RPM SO2 NOx Pb**

High Volume

Sampler

High Volume

Sampler

High Volume

Sampler

High Volume

Sampler

-----

Equipment sensitivity

Permissible AAQ R

standard (CPCB) I

S

200 ug/m3 100 ug/m

3 80 ug/m

3 80 ug/m

3

600 ug/m3

300 ug/m3 120 ug/m

3 120 ug/m

3

100 ug/m3 75 ug/m

3 30 ug/m

3 30 ug/m

3

A5

(Besa

Village)

*** R 128 164 164 61 78 78 6.8 8.9 8.6 8.0 11.4 10.5 Not done

A6

(Pimpalgaon

Village)

*** R 146 180 176 51 80 78 6.8 9.2 8.9 8.4 11.3 11.0 Not done

*R = Residential; I= Industrial; S= Sensitive **Pb for mineral specific sites only

*** SPM & RPM – 2 samples (24 hrly ) in a week for 12 weeks in a season i.e. 24 samples , For SOx & NOx – 72 samples – 3x2x12

( 3 samples in a day , 2 days in a week & 12 weeks in the season ).

# Annex a location map indicating location of AAQ stations, their direction and distance with respect to project site: -

Location map indicating location of AAQ stations is enclosed as Plate – XII .

The baseline ambient air quality data along with direction of AAQ stations & distance with respect to project site have been given

in Chpater - III .

Page 313: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

22. Stack and emission details, if any* : Not applicable

Sl.No Process/Unit of

operation (e.g. DG

Set, Boiler)

Height of

stack(m)

Internal

top dia.

(m)

Flue gas

exit

velocity

(m/sec)

Emission rate (kg/hr) Heat emission

rate from top

of stack

(k.cal/hr)

Exhaust/Flue gas

SPM SO2 NOx CO Temp oC

Density Specific

Heat

Volumetric

flow rate

(m3/hr)

23. Details of fugitive emissions during mining operations * : Insignificant as such not required.

24. Air quality Impact Prediction (AQIP)*

(a) Details of model(s) used for AQIP including grid : Qualitative assessment has been done on the basis of recorded data at

size, terrain features, and input meteorological data. the site and around covering the buffer zone.

The details of which are given in Chapter – IV.

However, AQIP model (ISCST-3) has been given in Chapter –IV.

(b) Maximum incremental GLC values of pollutants based on prediction exercise.

(in ug/m3 )

S.No. Pollutants Incremental Value Ambient Air Quality Resultant Air Quality

1. SPM 180 240 (Core Zone) 420

(Within permissible limit)

2** SO2 Not applicable

3** NOx Not applicable

[*Question Number 22, 23 & 24 need not be filled-in for mines having ML area of 25 ha .or less]

[**Information of item No.2 & 3 to be provided in cases with captive power generation of 500 KVA and above.].

Page 314: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

25. Water requirement (m3/day)

Purpose Avg. Demand Peak Demand

Mine site 1. Mine operation/workshop 2. Land reclamation 3. Dust suppression 4. Drinking (752 manpower) 5. Green Belt 6. Beneficiation(CHP) 7. Washeries 8. Fire Service 9. Others B. Township Green Belt Domestic Other (specify)

20 -

395

30

50

50

100

Existing

30 --

450 35

80

60

100

Existing

Total 645 755

26. Source of water supply*

S.No. Source m3/day

1. River (name)

2. Ground water

3. Mine water (sump/pit) 755

4. Other surface water bodies(specify) -

[*Annex a copy of sanction letter/permission from the concerned authority (Central Ground Water Authority in case of ground water abstraction is from notified area/State Ground Water Board in case of non-notified area/State Irrigation Department for surface water pumping) for drawing water]

27. Lean season flow in case of pumping from river/nalla (cumecs) : Not Applicable 28. Ground water potential of the study area

28.1 Ground water availability

(a) Range of water table (m bgl) (i) Pre-monsoon (April/May)

Core Zone : 14.00 – 17.80 m Buffer zone : 3.90 – 12.65 m

(ii) Post-monsoon (November)

Core zone : 12.50 – 15.25 m Buffer zone : 1.50 – 8.85 m

Page 315: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

(b) Total annual replenishable recharge (million m3/ year)

By ground water table fluctuation method : 43.30 MCM By rainfall infiltration factor method : 41.59 MCM

( c) Annual draft excluding estimated draft through : 2.30 MCM

mine discharge (million m3/year)

(d) Estimated draft through mine discharge (million m3/year) : 8.90 MCM

(e) Net annual ground water availability (million m3/year) : 37.43 MCM

(f) Stage of ground water development in % : 30 % 28.2. Water demand – Competing users of the water source

S. No. Usage Present consumption Additional proposed

Total (m3/day)

Surface Ground Surface Ground Surface Ground

1. Domestic 500 4450 -- 1500 -- 6450

2. Irrigation 6000 4416 -- 2000 -- 6416

3. Industry -- -- -- -- -- --

4. Mining -- 3000 -- 1000 -- 4000

5. Others (Specify)

-- -- -- -- -- --

Total 6500 11866 -- 4500 -- 16366

29. Water quality* : (a) Annex physico-chemical analysis of water at intake point : Not Applicable

(b) In case of existing mine, annex report on quality of water : Enclosed discharge i.e. complete physico-chemical analysis**

[*For non-discharging mines at least four ground water samples to be taken preferably from downstream direction of the mine in pre-monsoon and post-monsoon periods and analysed. For discharging mines six samples are to be analysed ]. ** All parameters as per BIS 10500. Indicate name of Methodology, Equipment used for analysis, and Detection Level (DL) for each parameter.

*** Wherever any analytical parameter is below detection level, “BDL” (Below Detection Level) should be written instead of ‘NIL’. 30. Impact on ground water regime/stream/lake/springs due to mine

dewatering* (a) Radius of influence (in m) : 500 - 600 m (Final mine depth-170 m) [To be estimated based on analysis of pumping test data and application of empirical formula]. (b) Whether saline water ingress will take place ? : NA (applicable to coastal areas) (c) Impact on stream/lake/springs : NA

Page 316: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

[*Provide a comprehensive hydro-geological assessment report. If the average mine dewatering is more than 100 m3/day and or going below water table in non-monsoon period. The report should be based on preferably latest one year pre-monsoon and post-monsoon baseline data covering information on ground water situation, aquifer characteristics, water level conditions (April – May and November), estimate of ground water resources, predicted impact of the project on ground water regime and detailed remedial/conservation measures such as artificial recharge of ground water etc. The report should be based on actual field inventory out of existing wells, at least 30 observation wells in the buffer zone with supplementary information from secondary sources (mention name). For estimation** of ground water resource (refer question No.28 above) be designated study area of the buffer zone may be sub-divided into command and non-command areas, watershed-wise (in case of hard rock/consolidated formations)/ block-wise/mandal-wise in case of alluvial/unconsolidated formations)].

[**For estimating ground water resources in the area follow the Ground Water Estimation Committee recommendations of 1997]

31. Waste Water Management

Mine (a) Daily average discharge (m3/day) from different sources

i. Mine water discharge : during Lean period : 3000 m3/day Monsoon period : 4500 m3/day

ii. Workshop : iii. Domestic (mine site) : iv. Beneficiation/Washeries : 645 m3/day consumption at site v. Coal Handling Plant : vi. Tailings pond :

vii. Others Total : 3645 m3/ day (average) (b) Waste water treatment plant/flow sheet : As given below for treatment process attached

The strata seepage water gets accumulated in main mine sump provided at the floor of the seam which allows significant settlement of suspended particles. Thereafter, supernatant mine water is pumped out on surface & passed through sedimentation pond for second stage settlement.

For, Workshop Effluent Treatment (100 kld) , a Zero – Discharge Workshop

Effluent Treatment Plant has already been set up and is being and will continue

to be operated. (c) Quantity of water recycled/reused/ to be recycled in (i) Percentage : 15 % (ii) m3/day : 546 (2910 m3/day goes as return flow)

Page 317: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

d) Point of final discharge : Local drainage

Final Point Quantity discharged (in m3/day)

Surface (i) Agricultural land (ii) Waste land (iii) Forest land (iv) Green belt

---

2. River/nallah 3099

3. Lake

4. Sea

5. Others (specify)

Total 3099

(e) Users of discharge water

(i) Human : (ii) Livestock : (iii) Irrigation : Irrigation. (iv) Industry (mine site ) : (v) Others (specify) :

(f) Details of the river/nalla,if final effluent is/will be discharged (cumecs) : Local Seasonal Nullah/ Seasonal drain (i) Average flow rate :

(ii) Lean season flow rate : (iii) Aquatic life : Presently not a perennial water body. (iv) Analysis of river water 100 m : upstream and 100 m downstream of discharge point submitted.

Township :

(a) Waste water generation from township (m3/day) : About 70 m3/day (b) Are you planning to provide sewage treatment plant? : --

(c) Usage of treated water : The treated water is being discharged

into local nullah & is being used by local population for agricultural purposes.

32. Attach water balance statement in the form of a flow diagram : In Chapter - III indicating source(s), consumption (Section-wise) and output

Page 318: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

33. Ambient noise level leq dB(A) : Baseline noise level data is given in Chapter – III

of

EIA/EMP. Details given below

AMBIENT NOISE LEVEL MONITORING STATIONS

SI.

No. Location Name Location Code

1. Core Zone N- 1

2. Pimpri Village N- 2

3. Bargaon Village N- 3

4. Pimpalgaori Village N- 4

5. Kunad Village N- 5

6. Telwasa Village N- 6

Data presentation & analysis

The generated noise level data are given in table below.

Noise level status

Location

Noise level dB(A) Noise level

Standards Daytime Nighttime

Daytime Nighttime

Core zone 64.9 - 67.8 54.8 - 57.4 75 70

Buffer zone 43.2 - 49.1 38.8 - 41.9 55 45

Mean Leq noise levels at day time and night time are ranging from 64.9 to 67.8

dB(A) and 54.8 to 57.4 dB(A) respectively in the core zone. Mean Leq noise levels

at day time and night time are ranging from 43.2 to 49.1 dB(A) and 38.8 to 41.9

dB(A) respectively in the Buffer zone. While comparing with IS: 4954 -1986 norms

for acceptable outdoor noise levels all values are found to be well within the

prescribed limits.

Summary

While comparing with IS: 4954 -1986 norms for acceptable outdoor noise levels the

Leq values are found to be within the limits.

Page 319: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

34. Solid Waste

(a) Top soil and Solid waste quantity and quality

Name

(Lump/fines/

slurry/

sludge/others )

Composition

Quantity

(m3/month)

Method of Disposal

Mining activity*

a. Top Soil

b. Over burden

c. Others

(Specify)

Clay, Alluvium,

Shale,

Sandstone,

Quantity year –

wise given in

chapter – IV.

Dumping on surface as

external OB dump ,quarry

backfilling & embankment

construction .

Effluent Treatment

Plant (Sludge)

Oil & Grease

Silt

Is being and will continue

to be disposed off through

approved Recyclers.

Secured Land-fill

TOTAL ..

[* Annex layout plan indicating the dump sites Attached]

(b) (i) Does waste(s) contain any hazardous/ : No

toxic substance/radioactive materials

or heavy metals ?

(ii) If yes, whether details and precautionary : Not applicable

measures provided ?

(c) Recovery and recycling possibilities : Not applicable

(d) Possible user(s) of the solid waste : Quarry backfilling, External OB

Dumping

And embankment construction.

(e) (i) Is the solid waste suitable for backfilling ? : Yes

(ii) If yes, when do you propose : Already Started.

to start backfilling

(in million m3)

Page 320: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

OB Management

Project Total waste generation

(Mm3)

Topsoil (Mm3)

Total OB generation

(Mm3)

Total OB in Ext. Dump

(Mm3)

Total OB Backfilled

(Mm3)

Original Project (ha) 10.33 Included in OB

10.33 9.58 & 0.75 in

Embankment

----

Expansion Project (ha) (balance life)

50.62 Included in OB

50.62 50.62 ----

TOTAL (Mm3)

60.95 60.95 60.20 & 0.75 in

Embankment

The capacity of external OB dumps proposed is about 60.20 Mm3. Remaining 0.75 Mm3 of OB will be used is construction of safety embankment.

The break up of OB quantities in external OB dumps is given in following table.

No. Dump Capacity in Mm3

0-30m 0.60m Total

i) Dump – 1 25.70 16.95 42.65

ii) Dump – 2 10.30 7.25 17.55

Total 60.20

SCHEDULE OF OVERBURDEN DUMPING

The following shows the yearwise OB dumping in external OB dump No.1 and No.2

Year Programmed Excavation of

OB(Mm3)

External OB Dump-1 (Mm

3)

External OB Dump-2

(Mm3)Excluding

Rehandling

1. 8.15 8.15 -

2. 7.40 7.40/15.55 -

3. 5.26 5.26/20.81 -

4. 5.25 5.25/26.06 -

5. 5.25 5.25/31.31 -

6. 4.70 4.70/36.01 -

7. 4.50 4.50/40.51 -

8. 4.40 2.14/42.65 2.26

9. 4.40 - 4.40/6.66

10. 1.10 - 1.10/7.76

11. 0.21 - 0.21/7.97

Total 50.62 42.65 7.97

(f) In case waste is to be dumped on the ground, indicate :

(i) Associated environmental problems : Fugitive emission of dust by

wind &

surface run off.

(ii) Number & type of waste dumps :

Page 321: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

No.of external dumps : 01

Max. projected height of dumps (in m) : 60

No.of terraces and height of each stage : Four terraces, each of 15 m

with berm of 6 m at + 15 m &

+ 45m level and transportation

bench of 20 m at + 30 m

level.

Overall slope of the dump (degree) : 28o

Proposed reclamation measures :

Development of grasses ,

legumes & plants. OB

dump will be first

technically reclaimed with

proper benches & slopes.

Then it will be taken up for

biological reclamation

(afforestation) in phases

along with embankment.

The year – wise Calendar

Programme is given

below:-

(iii) Section of the waste dump in relation to : Yes

the adjacent ground profile attached

Page 322: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

The details of green belt / Afforestation plan is as given below :-

Stage-wise Cumulative Plantation

year Green Belt

External Dump(OB +

Top Soil) Backfilled area

Others (undisturbed

area/etc.) Total

1 Area (ha)

No. of trees

Area (ha)

No. of trees

Area (ha)

No. of

trees

Area (ha)

No. of trees

Area (ha)

No. of trees

2 1st year

0 0 0 0 0 0 0 0 0 0

3 3rd year

0 0 0 0 0 0 0 0 0 0

4 5th year

0 0 25 62.5 0 0 10 25 35 87.5

5 End of mine life

0 0 110 275 0 0 145.93 364.825 255.93 1

6 Post mining

0 0 175 437.50 0 0 157.93 394.825 332.93 832.33

Post mining land use plan (Conceptual)

The post-mining land use pattern at Junad Extn. Deep OCP will be as follows:-

Conceptual Post Mining land use plan (Conceptual)

Post-mining Landuse pattern of ML/Project Area (ha)

S.N. Land use during mining

Land use (ha)

Plantation Water Body Public use Undisturbed Total

1 External OB Dump 175 0 0 0 175

2 Top soil dump 0 0 0 0 0

3 Excavation 0 101.7 0 0 101.7

4 Roads including embankment

17 8 25

5 Built up area 3 0 7 0 10

6 Green Belt 0 0 0 0 0

7 Undisturbed Area 137.93 0 0 0 137.93

Total 332.93 101.7 15 0 449.63

Page 323: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

35. Fuel/Energy requirements*

[*To be furnished for mines having ML area more than 25 ha or captive

power generation of 500 KVA and above].

(a) Total power requirement – 4230 kVA

(in

kVA)

S.No Mine site Township Others (specify) Total

1 Present As given below

2 Proposed As given below

Total

(b) Source of power : - MAHAGENCO.

( Due approval from MAHAGENCO taken at area level for no. of mines

together).

S.No SEB/Grid* Captive

power

plant

DG sets

1. Present

As given

below

Nil

2. Proposed Nil

Total

[*Annex a copy of the sanction letter from the concerned authority]

Page 324: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

SALIENT FEATURES OF THE ELECTRICAL PARAMETERS :

ITEM HEAD VALUE

i) Connected load - a) total 2352 kW

b) Only Mine 2088 kW

c) Only Township 264 kW

ii) Load in Operation – a) total 2133 kW

b) Only Mine 1869 kW

c) Only Township 264 kW

iii) Projected maximum demand - a) Total 853 kVA

b) Only Mine 776 kVA

c) Only Township 121 kVA

iv)Specific Energy Consumption (a)Total 8.52 kWh/t

b) OB -

c) Coal 1.32 kWh/t

d) Common 7.20 kWh/t

v) Specific Power Cost Rs. 44.97/t

vi) Fixed cost of power 77.22 %

vii) Variable cost of power 22.78 %

viii) Specific demand 1.495 MVA / Mt

ix) Capacitor bank provided– a) Total 425 kVAR

b) Only Mine 375 kVAR

c) Only Township 50 kVAR

x) Production of Coal 0.6 MTY

(c) Details of fuels : Deployment of HEMM proposed through partial hiring.

S.No. Fuel Daily consumption

(TPD)

Calorific

value

(Kcals/kg)

% Ash % Sulphur

1.

2.

3.

HSD

LSHS

Other

(Lub.)

Existing

15048 lpd

Proposed

25000 lpd

Page 325: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

36. Storage of inflammable/explosive materials

S.No. Name Number of

Storages

Consumption

(in TPD)

Maximum Quantity at

any point of time.

1. Fuels Central

Storage

25000 lpd Maximum storage for 3

days only.

2. Explosives Magazine 5500 kg/day Maximum storage for 3

days only.

37. Human Settlement

Core Zone Buffer Zone

Population* All details

regarding

socio –

economic

have been

given in

Chapter – III.

All details regarding socio –

economic have been given in

Chapter – III.

No. of villages Nil

Number of households Village-

wise

[*As per actual survey]

38. Rehabilitation & Resettlement ( R & R) Plan*

[*Provide a comprehensive rehabilitation plan, if more than 1000 people are

likely to be displaced, other-wise a summary plan]

a) Villages falling within the study area :

Villages

Number Name

Core Zone Nil NA

500 m from the blasting

site(s)

Buffer zone All details regarding socio –

economic details have

been given in Chapter – III.

Shown in Index Plan

(Plate – II))

Township site --- ---

(b) Details of village(s) in the core zone : Nil.

Page 326: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

( c) Population to be displaced and/or Land oustees : Only Land Oustees –

Yet to be finalized.

Name of

village(s) falling

within

Number of oustees

Land (only) Homestead

(only)

Land and Homestead

(both)

Mining Lease Yet to be finalized Nil As given in previous

Column.

Township Site Nil

(d) Whether R&R package has been finalized?

If yes, salient features of R & R plan for oustees : Not Applicable

(i) Site details where the people are proposed to

be resettled & facilities existing/to be created : Not applicable

(ii) Funds earmarked for compensation package * : Not Applicable

(iii) Agency/Authority responsible for their resettlement: Not Applicable

(iv) Time of commencement of resettlement : Not Applicable

of Project Affected People (PAP)

(v) Period by which resettlement of PAP will : Not Applicable

39. Lease-wise plantation details

(a) Lease area (in ha.) New mine Existing Mine

(i) Area broken up :

(ii) To be broken up : 101.70 (including existing Quarry)

(iii) Area not to be broken up : 347.93

(b) Township area (in ha) Combined Township.

( c) Area afforested and proposed (in ha)

Afforested -23.73 ha ; Proposed –The proposed afforestation plan is given below.

On the dump slopes and top surface, plantation of grass and trees will be done

in phases and the details are as follows ;-

Page 327: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

(d) No. and type of trees planted and proposed :

(i) Existing : 59325

a. When plantation was started? 1998-99

No.of plant species planted

Number of saplings (per ha.)

As per details given below 2500

(ii) Proposed : As given Below ;-

No. of plant species to be

planted

Number of saplings (per ha)

Native Species in line with

existing plantation

2500

Stage-wise Cumulative Plantation

year Green Belt

External Dump(OB +

Top Soil) Backfilled area

Others (undisturbed

area/etc.) Total

1 Area (ha)

No. of trees

Area (ha)

No. of trees

Area (ha)

No. of

trees

Area (ha)

No. of trees

Area (ha)

No. of trees

2 1st year

0 0 0 0 0 0 0 0 0 0

3 3rd year

0 0 0 0 0 0 0 0 0 0

4 5th year

0 0 25 62.5 0 0 10 25 35 87.5

5 End of mine life

0 0 110 275 0 0 145.93 364.825 255.93 1

6 Post mining

0 0 175 437.50 0 0 157.93 394.825 332.93 832.33

This is a tentaive programme drawn with the consideration of the maximum

achieavable capacity of 1.50 MTPA and may undergo changes depending on

the actual progress of the mine

Page 328: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

40. Environmental health and safety

(a) What major health and safety hazards

are anticipated?

No major health & safety

hazards anticipated. However,

coal mining activities are itself

hazardous and as such disaster

management plan has been

worked out considering the

probable risks / hazards &

their mitigative measures have

been given in detail in Chapter

– VI.

(b) What provisions have been made/proposed

to be made to conform to health and safety

requirement? :

Mine will be worked as per

statute. Dispensary, First

aid center at the mine

level, full fledged hospital

at Area level to cater to

the needs of all employees.

Emergency Response Plan will

be prepared and mock

rehearsal will be done

regularly.

( c) In case of an existing mine :

(i) Comprehensive report on health status : Periodical Medical Examination

of all workmen once in five years.

Mineralogical composition of RPM (dust) :

Free silica as SiO2 - 11.5

Chromium* (Total as well as Hexavalent) - Not applicable

Lead ** - Not applicable

[*Only for Chromite mines] [** Only for Base Metal mines]

(d) Information on radiation protection measures, if applicable : Not Applicable

Page 329: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

41. Environmental Management Plan

Salient features of environmental protection measures.

S.No. Environmental issues* Already practiced, if

applicable

Proposed.

1. Air pollution Green belt development,

plantation at all suitable

vacant areas, OB dump,

Wet Drilling, water

spraying on

haul road & coal

transportation

road etc.

To be continued

2. Water pollution Sedimentation pond for

mine pumped out

water

Workshop Effluent

Treatment Plant for

workshop effluent

To be continued

3. Water conservation Earthen check dams Earthen check dams

4. Noise pollution Providing personal

protective gears / ear

muffs & ear plugs,

maintenance of P&M,

green belt development

etc.

To be continued

5. Solid waste/Tailings Backfilling in decoaled

void, embankment

construction, external OB

dump & biological

reclamation thereafter.

To be continued

6. Land degradation Technical & biological

reclamation

To be continued

7. Erosion & Sediment Plantation on OB dump &

embankment, garland

drains around OB dump

& coal dump , green belt

on plain land.

To be continued

8. Top soil Initiallty to be dumped at

earmarked site and

thereafter being used

concurrently

9. Ground vibration Controlled Blasting To be continued

10. Wildlife conservation Not Applicable Not Applicable

11. Forest protection Not Applicable Not Applicable

12. Others (specify) Social development works

in nearby villages.

To be continued as per the

CSR Policy of the Company (* As applicable)

Page 330: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

42. Compliance with environmental safeguards (for existing units) :

(a) Status of the compliance of conditions of : Certificate of Compliance

environmental clearance issued by MOEF Enclosed – Annexure – IV.

if any, enclosed

(b) Status of the compliance of ‘ Consent to : Complied

operate’ issued by SPCB, if any, enclosed.

(c) Latest ‘environmental statement’ enclosed : Annexure – V.

43. Scoping of EIA

Whether environmental impact assessment : Yes

of the project has been carried out by following

scoping process?

If yes, a copy of scoping of EIA annexed : Details given below.

IMPORTANT ENVIRONMENTAL ASPECTS (Scoping )

1. Forest land involved No

2. Wild life sanctuary ( 10 km. radius) None

3. Fragile Eco/ Bio- diversity system

nearby (10 km. radius)

None

4. Coastal area nearby (10 km. radius) None

5. Environmental impact on the region. No adverse impact anticipated.

However the project will be beneficial

to the local people of the region.

6. Impact on quality & quantity of ground

water specific to the project.

The detailed impact assessment has

been done and given in Chapter – III

& IV. Impact will be insignificant.

7. Risk & Hazards involved due to the

project

Risk & hazards associated with

mining will be limited to mine area

only. However, the mine is being

worked and will continue to be

worked as per the statute.

8. Env. Pollution control

measures

Environmental Pollution control

measures are being implemented and

will continue to be effectively

implemented & regular monitoring will

be done.

9. Rehabilitation & resettlement. There is no Resettlement of house

oustees involved in this

proposal.There is Rehabilitation of

land oustees involved due to

acquisition of additional agricultural

land.

Entire Rehabilitation of land oustees

will be carried out as per Company’s

Policy.

Page 331: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

44. Mine closure

(a) Have you planned mine closure : Yes

(b) Submitted a conceptual mine : Yes

closure plan

(c) If yes, indicate estimated amount : As per MOC Guidelines – Aug,2009

for implementing the same (in Rs.lakhs)

Details of Progressive Mine Closure Plan is given below;-

OBJECTIVES OF CLOSURE PLANNING

Mine closure planning has to be carried out at the starting of the mine and

needs periodic reviewing and revision during its life cycle to cope with the geo-

technical constraints, safety and economic risks, social & environmental

challenges. Various other objectives are as follows.

a) To allow a productive and sustainable after-use of the site which is

acceptable to the mine owner and the regulatory authority.

b) To protect public health and safety.

c) To alleviate or eliminate environmental damage and thereby

encourage environmental sustainability.

d) To minimise adverse socio-economic impacts.

CLOSURE ACTION PLAN

Closure planning is a whole-of-life exercise that begins at the start of a mine and

continues till post closure. The dynamic nature of closure planning requires

regular and critical review to reflect changing circumstances as a result of any

operational change, new regulation, new technology and remain flexible

enough to cope with unexpected events. Following steps have to be

undertaken in relation to Mine Closure Planning :

(a) Prior to the surface demolition/restoration a surface audit should be

undertaken on all surface structures, spoil heaps, lagoons, etc. to assess

whether there are any hazardous materials that could cause problems viz;

explosives, chemicals, etc. A list of surface assets should be prepared and

made available to potential purchasers, prospective purchasers could be

invited and asked to submit sealed bids.

(b) This could ensure that the sale of assets give better financial gain.

(c) In order to identify potential impact, necessary hydro-geological studies

into post-mining groundwater recharge has to be done. The void of the

mine can be proposed as a water resource to be utilised for aquaculture.

(d) Work force on roll of WCL may be redeployed for gainful utilisation of

Page 332: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

employees of WCL.

(e) As a detailed component of the Closure Plan, a Decommissioning Plan is

to be developed towards the final stages preferably 5 years prior to

tentative closure of mine. Once established it may be updated annually.

PROTECTIVE MEASURES TO BE TAKEN

Protective measures must include the following :

a) The protection of mine boundary, building and other structure on the

project site against access by unauthorised persons.

(b) The maintenance of all mechanical, hydraulic and waste management

system

(c) The continuation of all monitoring programs.

(d) The control of all contaminated effluents

(e) The securing of all petroleum products, chemicals and waste.

(f) The rendering of all tailings, dams and piles of earth, rock and waste

resulting from work done on the project site in a stable and safe condition.

CLOSURE COSTS

The proposed Junad Extn. Deep OC Project has been planned upto 170 m

depth and it is most likely that this will be extended further in dip side in future. A

financial provision of Rs.6.00 lakhs/ ha as per the guidelines issued by MoC will

be provided throughout the mine life in order to undertake mine closure

activities (for plantation in slope of dumps & quarry, for protection of mine

boundary and continuation of monitoring programme and control of

contaminated effluents). Closure cost may be reviewed under the changing

circumstances and new legislative requirements.

45. Capital cost of the project (in Rs. Lakh) : 5478.40

(Based on approved Project Report)

46. Cost of environmental protection measures : As shown below (in Rs.

Lakh)

Page 333: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

ENVIRONMENTAL COST PROJECTION

The total expenditure made for environmental protection under both Capital &

Revenue head is given below:-

EXPENDITURE INCURRED ON POLLUTION CONTROL MEASURES

72.04TOTAL

10.28WATER POLLUTION CONTROL MEASURES

3

37.26PLANTATION2

24.50AIR POLLUTION CONTROL MEASURES1

AMOUNT IN

Rs. LAKH

PARTICULARSSL.

NO.

The details of capital provision on environmental protection measures for

proposed expansion project are as given below :-

PROPOSED CAPITAL FOR ADDITIONAL POLLUTION CONTROL MEASURES

37.16TOTAL

10.16WATER TANKER 5

6.0LAND RECLAMATION MEASURES

INCLUDING LAND USE MAPPING

THROUGH REMOTE SENSING

4

5.0DUST SUPPRESSION ARRANGEMENT AT

HAUL ROAD , STOCKYARD ETC.

3

8.0STRENGTHENING OF ETP FOR

WORKSHOP EFFLUENT

2

8.0STRENGTHENING OF SEDIMENTATION

POND FOR TREATMENT OF MINE WASTER WATER

1

AMOUNT IN

Rs. LAKH

PARTICULARSSL.

NO.

Page 334: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

47. Amount earmarked for socio-economic : As per the CSR Policy of CIL

welfare measures for the nearby villages Details given in Chapter – VI.

other than R & R plans.

48. Public Hearing

a. Date of advertisement : 02.01.2013

b. Newspapers in which the advertisement appeared : The Hitavada &

Daily Lokmat

c. Date of public hearing (DD/MM/YY) : 05.02.2013

d. Public Hearing Panel chaired by & members present : Addl. District

Magistrate

Yavtmal & MPCB

Officials

e. No. of people attended the public hearing meeting : Panel Members

&

and number of people from the lease area No. of villagers - 250

(approx.)

f. Summary/details of public hearing in tabular form :

The Environmental Public Hearing in respect of proposed Junad Opencast

Expansion Project of M/s Western Coalfields Ltd., Wani North Area, Tal. Wani ,

Dist. Yavatmal for enhancement in production capacity from 0.60 MTPA to 1.50

MTPA and increase in lease area from 174.28 ha to 449.63 ha was held on

05/02/2013, 11.00 am at Kamgar Manoranjan Kendra, Bhalar Township, At Post

Bhalar, Tal. Wani, Dist. Yavatmal. The public hearing was conducted under the

Chairmanship of Shri Rajendra Deshmukh, Additional District Magistrate,

Yavatmal (The representative nominated by District Magistrate, Chandrapur).

Shri S.D.Patil, Sub Regional Officer, MPCB, Chandrapur was the Convener of the

Public Hearing. Shri N.G. Nihul, Regional Officer, MPCB, Chandrapur was the

Member of Public Hearing panel. Shri M.P.Barhanpurkar, District Mining Officer,

Yavatmal, Shri L.S.Varhade, SDO, Wani and Shri Misal, Tahsildar,Wani were also

present during the public hearing. The public hearing started at 11.00 am with

the permission of the Chairman of the Public Hearing Panel.

First of all, the Convener welcomed all present for Public Hearing. He told that,

the Public Hearing is being conducted as per the provisions of EIA Notification

dated 14/09/2006 and amended Notification dated 01/12/2009 of Ministry of

Environment & Forests, New Delhi. He told that the project proponent received

TOR (Terms of Reference) for this project from Ministry of Environment & Forests,

Page 335: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

New Delhi on 11/07/2008. Accordingly, project proponent prepared Draft EIA &

EMP Report and submitted their application on 15/02/2010 to the Board

requesting for conducting the Public Hearing.

The Public Hearing for this project was earlier scheduled on 31.08.2010 and

21.12.2010 but during hearing it was cancelled at both the times due to some

reasons.

Thereafter, the public hearing was scheduled on 10.10.2012. The public notice

for the said public hearing was published on 08.09.2012 in Daily Lokmat (Marathi)

and Daily Hitawad (English) stating date, venue and time of public hearing. The

said public hearing was postponed due to some unavoidable reasons at that

time as per District Collector, Yavatmal letter no. 937/2012 dated 06.10.2012. The

notice about postponement of Public Hearing was published in Marathi Dialy

Lokmat and English Daily Hitavada on 08.10.2012. Afterwards the public hearing

is scheduled on 05.02.2013 and the public notice in this behalf was published on

02.01.2013 in Daily Lokmat (Marathi) and Daily Hitawad (English) stating date,

venue and time of public hearing.

The copies of Draft EIA/EMP and Executive Summary in English and Marathi were

made available vide letter no. 1288/2010 dated 28.07.2010 to the offices of

District Collector, Yavatmal, District Industries Centre, Yavatmal, Zilha Parishad,

Yavatmal, MPC Board (HQ), Mumbai, Regional Office and Sub Regional Office,

MPC Board, Chandrapur, Environment Department, Mantralaya, Mumbai, Tahsil

Office, Wani and offices of the concerned Gram Panchayat Pimpalgaon, Tal.

Wani for the knowledge of concerned. While issuing the notice of

postponement, it was requested to above offices for making available the

documents submitted by project proponent for the concerned to study till the

date of Public Hearing. Also, through this notice it was requested to file their

objections/suggestions within 30 days from the date of public notice to the Sub

Regional Officer, MPC Board, Chandrapur. The Member Secretary, MPC Board,

Mumbai has issued the Panel Order no. E-15 of 2013 dated 29/01/2013 for the

Public Hearing.

The Minutes of Public Hearing in respect of proposed Junad Opencast Expansion

Project of M/s Western Coalfields Ltd., Wani North Area, Tal. Wani , Dist.

Yavatmal conducted on 05/02/2013 11.00 am Kamgar Manoranjan Kendra,

Bhalar Township, At Post Bhalar, Tal. Wani, Dist. Yavatmal is enclosed herewith at

Annexure – III.

Page 336: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

The replies to the queries raised during the Public Hearing are already

incorporated in the said minutes.

Sr. No.

Issues WCL Comments

1 Crop compensation. Sub Area Manager Junad Opencast Mine said that Rs. 16 Lakhs were sanctioned by WCL Board and it was decided by the Board that the fund should be utilized for community development through SDO.

2 Acquisition of balance land beyond what has been notified.

Shri Patil, Area Planning officer Wani North Area tlold that section 9 is completed in respect of land of Junad, Pimpalgaon and Borgaon villages and it is acquired. He added that land is required in future and remaining land will be acquired at that time. It will take at least 3 years to complete the whole process and to start the project.

3 Rehabilitation of Kolar, Pimpri, and Aheri village.

Shri Patil, Area Planning officer Wani North Area said that the rehabilitation of Kolar, Pimpri and Aheri villages is proposed. Socio-economical survey was carried out in these villages with the help of an NGO.

4 Suppression of dust on Nilapur – Brahmni road

Shri Murthy, WCL Wani North Area said that Nilapur- Brahmni road is not owned by WCL hence fixed rain-guns could’t be provided there. Water tanker will be deployed on this road.

5 Venue of Public Hearing Shri N.G. Nihul said that the public hearing can be conducted at the place in close proximity of project site and further clarified thatclose proximity means the place which s nearby to the project site. Chairman Shri Rajendra Deshmukh last time the public hearing was conducted at project site, at that time presentation was not viewable due to sunlight. Hence due to such issues this venue is decided which is 5-6 km from the project site and this is not a too long distance. The facilities are available here for convenience of people.

6 Tree Plantation Shri Sujit Sen WCL Wani North Area said that total 17 lakhs 20 thousand trees have been planted in Wani North Area since 1994 to 2013.Contract for the said work is given to Forest Development Corporation of Maharashtra (FDCM) and the work will start soon. Shri Maji Sub Area Manager Junad Open Cast said that tree plantation will be carried out at earliest by using manpower in the existing project.

7 Street lights Shri Maji, Sub Area Manager Junad Opencast Mine said that street lights will be provided using CSR funds.

Page 337: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

49. Whether the following approvals*(wherever applicable) have been obtained ?

(i) Site clearance from MOEF : Not Applicable

(TOR issued attached in Annexure - I).

(ii) Consent for Establishment’ from the : To be obtained for 1.50 MTPA

State Pollution Control Board.

(iii) NOC from Atomic Mineral Division : Not applicable

(iv) Mining plan approval from IBM/ : Approved by WCL Board.

Ministry of Coal

(v) In case of existing mines, mining : Not Applicable

scheme approval from IBM

(vi) Forestry clearance under FCA, 1980 : Not Applicable

(vii) NOC from Chief Controller of : Existing Mine already obtained.

Explosives

(viii) Commitment regarding availability/ : Not applicable as water

pumping of water from the concerned requirement will be met

authorities from mine pumped out water.

(ix) In case of ML area falling in notified areas : Not Applicable

of the Central Ground Water Authority

NOC from them.

[*Annex copies of approvals and number them]

50. Was / is there any court case relating : Not applicable

to the project or related activities ?

If so, provide details present status.

Verification: The data and information given in this proforma are true to the best

of my knowledge and belief.

Signature of the applicant*

with Full name & address

[*Owner or his authorized signatory]

Date:

Place: NAGPUR

Given under the seal of organization on

behalf of whom the applicant is

signing.

Page 338: JUNAD DEEP EXTN. OC - environmentclearance.nic.in€¦ · JUNAD DEEP EXTN. OC (WANI NORTH AREA, WCL) ... partly diverted because of extension of Junad OC mine ... ha land of Kolar

Annexure – I