Upload
nguyentruc
View
213
Download
1
Embed Size (px)
Citation preview
John Hart Generating Station
Replacement Project
March 2016
Community Construction Update
Report #33
Prepared by: Stephen Watson, BC Hydro
(O) 250-755-4795 or (C) 250-616-9888
Twitter: @Puntledge Email: [email protected]
• Powerhouse cavern work continues to progress, with bench 4 well underway and bench 7 beginning in parallel thanks to access from the opened draft tube.
• Bypass inlets off the power tunnel are proceeding with excavation
• Blasting continues in the realigned main access tunnel, currently working with canopy tubes to provide additional support in the area nearest the loose cobble feature that was encountered last year.
• Vertical excavation on the downstream side has reached the elevation of the intake – rock support being installed
• Drilling underway to prepare for blasting on reservoir-side of the dam, with blasting expected to begin by end of the month.
• Work continues on the road accessing the new surge tower location, located adjacent to the trail access to the Suspension Bridge.
Powerhouse cavern excavation. Project
status is work continues to progress on all
fronts.
Details on the community site event will be
provided by May.
Construction Pictures – John Hart Dam Area
3
Mar 30
Construction Pictures – Cofferdam Area
4
Drilling and blasting is underway on the
upstream side of the dam, with blasting
expected to begin at the end of March.
The rock removal will go down in front of
the dam to make room for the
construction of the water intake
maintenance gate.
Construction Pictures – Downstream Work
Area Below John Hart Dam Area
5 Mar 27
Construction Pictures – Downstream of John
Hart Dam
6
The approximate area
where the power tunnel
vertical drop shaft will be
tunnelled out. The shaft
will be 6.5 metres in
diameter.
The vertical excavation on the downstream side
has reached the elevation of the intake to the
power tunnel. The excavated intake area, for the
intake structure, is 26 metres x 9 metres.
Construction Pictures – Surge Tank Area
7
The soils or overburden removal are
nearing completion. The surge shaft
excavation is scheduled to begin in
August.
The surge tank will perform the same
function for the power tunnel as the
three existing white surge towers
currently do in controlling pressure in
the three penstocks.
Construction Pictures – Powerhouse Cavern
8
View from the upstream side of the cavern, looking back to
the service tunnel entrance on the downstream side.
Construction Pictures – Powerhouse Cavern
9
View towards the service tunnel entrance.
Construction Pictures – Powerhouse Cavern
10
As the powerhouse deepens, the service tunnel is now too high for use (right picture).
Rock from the blasts are now all being removed from the upstream side of the
powerhouse cavern: trucks go through the power tunnel and then Adit B, a temporary
construction tunnel, where they then enter the service tunnel to the surface. We are
working on the fourth rock level or bench downward.
11
A perspective of how
far the powerhouse
cavern excavation has
advanced since this
2015 picture.
Construction Pictures – Main Access Tunnel
12
View of the steel canopy
tubes on the top right
corner of the Main
Access Tunnel. InPower
BC is almost through the
low rock cover area and
will then resume full
blasting in the rock mass
along the tunnel
alignment.
Construction Pictures – Tailrace
13
The new tailrace area beside the existing generating station taken from the other side of
the Campbell River, and at top, from the other direction.
Environment Update
14
• Annual owl surveys conducted (reports/details to come) as well as egg mass surveys for red-
legged frogs in wetlands neighbouring the construction project.
• One size doesn’t fit all for spill protection – a specially designed spill tray was created for and
placed under the largest crane at the water intake area. All parked equipment on site is
required to have these trays to protect against any potential spill of fluids.
• Seven red-legged frogs have recently been found. Because it is breeding season, the
exclusion fence around the wetland areas has been opened in places to allow easier access
for frogs looking to lay their eggs.
Egg sacs found for future northwestern salamanders during regular checks on wetlands
next to the project site.
Recent Community Donations
15
1: Support to the Mountain Avian Rescue Society for the
March 2016 Eagle Festival in Campbell River.
2: BC Hydro provided $5,000 to the Campbell River
Salmon Foundation towards their fish restoration projects.
3: We also provided $2,400 to the Campbell River Bike
Park Society to aid in the construction of the new
Mountain Bike Skills Park.
1 2
3
City of Campbell River Water Supply Project
16
• The source of the City’s domestic water supply, the John Hart penstocks, will be removed and
replaced with an underground tunnel. The City and BC Hydro developed a memorandum of
understanding for the City to construct a new and separate domestic water supply system into
the John Hart reservoir.
• In March, the City began working on the next phase of the project (shown below with blue
line) after essentially completing the Highway 28 section last year. In this phase the City
contractor is placing the new water pipe along Brewster Lake Road before eventually moving
off the road and toward the future pumphouse and water treatment building near the reservoir
shoreline. Information on the project can be found at: www.campbellriver.ca/city-
services/capital-improvement-projects.
• The public sometimes confuses the City project as being part of the John Hart hydroelectric
project.
• Please obey traffic control in this area when entering the Elk Falls and John Hart Project
Interpretive Centre parking lot. Access to the parking lot will remain open during this work.
People Profile – Anders Jonsson
Background:
With a Master’s degree in Civil Engineering from Lund University (Sweden),
Anders’ began his career working as a geotechnical engineer before joining
the international construction circuit with Skanska International. He has 19
years of experience in the construction industry including project management
positions with hydro power and transportation projects – most recently on the
Brilliant Expansion in BC and Calgary West LRT project.
Home:
Anders grew up in Gothenburg on the west coast of Sweden before moving to
Lund (southern part of Sweden) for university. He moved to the West
Kootenays, BC, in 2003 for project work and has since called Canada home.
While he’s in Campbell River for day-to-day project work, his primary
residence is in Calgary where he lives with his wife, two kids (7 year old, boy
and girl, twins) and two dogs.
Hobbies:
He enjoys spending time with his family, playing golf, fly-fishing, skiing or just being outdoors.
Project Responsibility:
As the Deputy Site Manager for SNC-Lavalin, Anders has a responsibility to oversee site operations through coordination and management of subcontractors, and liaise with BC Hydro and other stakeholders to ensure smooth execution of the project work.
“I truly enjoy working on the John Hart project not only for the beauty of Campbell River and its surroundings but also for being part of building something that matters and makes a difference in peoples lives.”
About Anders
Construction – Point Of Interest
Hydrophones monitor blasting.
Each month, BC Hydro and InPower BC will provide a construction
fact, occurrence, or situation.
With blasting underway next to the Campbell River the
project is ensuring that resulting vibrations don’t harm
fish:
• Two hydrophones have been installed in the river, 1.5
m apart in depth, next to the tailrace area;
• Extensive calculations are conducted in advance of
the blasting to ensure that the planning is accurate
and protects the adjacent river;
• Hydrophone results, which measure the pressure
travelling through the water as a result of blasting,
are monitored and recorded;
• No blasting has come anywhere near the DFO limits
– with up to 100,000 Pa allowed and only 8.6 Pa
being the highest recorded to date; and
• Hydrophones like these ones in the river (shown on
right) have been installed in the reservoir as well, with
blasting now underway at new water intake next to
the John Hart dam.