Project Update April 11 th , 2011

March 2011 Project Update

Embed Size (px)

DESCRIPTION

March 2011 Project Update

Citation preview

Page 1: March 2011 Project Update

Project Update

April 11th , 2011

Page 2: March 2011 Project Update

Roadway Projects

Page 3: March 2011 Project Update

• Opened both Northbound lanes 2/22 • Street lighting conflict with CenterPoint

power lines scheduled for completion by the end of April

• Work continues on the project to complete outstanding items

Cullen Parkway

Page 4: March 2011 Project Update

Cullen Parkway

Page 5: March 2011 Project Update

Phase II – Mary’s Creek Bypass to SH35

• Opened to 4 lanes on 4/6 • Completed landscape and irrigation

installation; conducted substantial completion inspection with TxDOT

• Completed major sidewalk and brick paver installation

• Continued traffic signal installation network

Dixie Farm Road

Page 6: March 2011 Project Update
Page 7: March 2011 Project Update

• One lane closure between SH 35 and Veterans allowing only westbound traffic

• Brush cleared between Veterans and BNSF railroad tracks

• Began installing 10x4 RCB east of Veterans • Conflicts were identified with the relocation

of three CenterPoint Energy power poles and a resolution has been initiated.

• Utility relocation continues

Walnut Reconstruction

Page 8: March 2011 Project Update

Construction Phase III – Morgan to Harkey and CR 89

• Contractor completed paving at the remediation areas east of FM 1128

• CenterPoint installed 2nd arm for Southfork streetlights; working on plan for Magnolia streetlights

• Initiated ditch re-grading, base and asphalt work on east side of FM 1128

• Late April/Early May opening

Magnolia Road

Page 9: March 2011 Project Update
Page 10: March 2011 Project Update

• Green Armor installation is scheduled to be

complete by mid-April • Final walk-through scheduled for the end of

April

Town Ditch Phase III

Page 11: March 2011 Project Update
Page 12: March 2011 Project Update

• Orange Street has been closed to westbound traffic between SH 35 and Mykawa to begin the installation of utilities and grading

• Began installation of inlets • Continued coordination with the utility

companies • AT&T has many conflicts that are affecting

the project

Orange Street

Page 13: March 2011 Project Update

• Returned plan review of 100% plans with

drainage updates to the engineer for revisions • Traffic counts and noise measurements

completed for Noise Impact Analysis; Engineer working on draft report submission

• ROW acquisition underway – 61 of 65 parcels acquired, 4 in condemnation (May 16th)

Bailey Road (Veterans to FM1128)

Page 14: March 2011 Project Update

• Irrigation and landscaping ongoing; working with HOA for upgrades

• Final clean-up in progress

McHard Road (Country Place to Cullen)

Page 15: March 2011 Project Update

McHard Road (Soundwall Construction)

• CenterPoint installed new transmission lines

along north side of McHard in order to de-energize and remove lines on the south side.

• North side wall placement complete with the exception of Sound Fighter gate installation

• Majority of south side mow strip, column, and panel placement complete

Page 16: March 2011 Project Update
Page 17: March 2011 Project Update

• Two lanes of paving Flea Market to Walmart • Working with TxDOT to address local

business concerns • USACE issued permit for low water crossing

on Hickory Slough • All utilities have been relocated along SH35

with the exception of the contaminated soil area & water line on bridge

SH35 – BW8 to FM518

Page 18: March 2011 Project Update
Page 19: March 2011 Project Update

• Utility relocates and coordination ongoing • Initiated slip form from Kirby to Clear

Creek Bridge • Bridge deck at Clear Creek Bridge poured • Storm Sewer Completed

FM 2234 Widening

Page 20: March 2011 Project Update
Page 21: March 2011 Project Update

• Cabinet box, controller and signal heads delivered to contractor site

• Bollards installed and painted • CenterPoint pole adjustments and tree

clearing scheduled for completion this month

Interim Traffic Signal Installation – Mykawa Road at Brookside Road

Page 22: March 2011 Project Update
Page 23: March 2011 Project Update

Drainage Projects

Page 24: March 2011 Project Update

Detention Pond • Pond B excavation complete; Pilot channel

installation in progress • Excavation of diversion channel from Pond A to

CR 143 complete • Hauling activities and fill placement at designated

fill sites continued • City staff finalized pump configuration • Waiting for engineer to complete plan revisions

for pump station

Cowart Creek Diversion

Page 25: March 2011 Project Update
Page 26: March 2011 Project Update

Diversion Ditch • Conoco Phillips issued NTP • CR100 closure thru next week • Veterans closure late April – 4-6 weeks • Awaiting re-submittal of 90% N/S Ditch

plans

Cowart Creek Diversion

Page 27: March 2011 Project Update

Facility Projects

Page 28: March 2011 Project Update

• Completed below slab utilities, water, sewer,

electrical, and data • 95% complete on Site Utilities, including internal

drainage, electrical and phone and prep’d for installation of fiber optic to PSB

• Poured slab with cut outs for tilt wall panels • Reviewing Building access control options and costs

Hillhouse Road Service Center

Page 29: March 2011 Project Update
Page 30: March 2011 Project Update

• Continuing work on Interview Room Recording System – New cameras & mics were installed in two rooms for a

three week test period – Audio, video, and playback of new equipments meets

needs – Contractor directed to install this setup in all interview

rooms • Performed Final Acceptance Walkthrough on

March 21st . The contractor is working to complete additional items

Public Safety Building

Page 31: March 2011 Project Update

• Held final walk-through • Continued working through warranty items,

Fire Marshal’s issues, and Architectural Barrier issues resolved

• All furniture has arrived • Intercom system was installed

Fire Station #5

Page 32: March 2011 Project Update
Page 33: March 2011 Project Update

• Underground utilities complete • Began erection of pre-engineered building • Driveways and 50% of parking/paving has

been poured

Fire Station #6

Page 34: March 2011 Project Update

• HGAC grant application has been submitted • Staff has reviewed 60% design plans and

specs • Working to advertise the project once the

HGAC grant is approved

Pearland Gateway – Project Stars

Page 35: March 2011 Project Update

Parks

Page 36: March 2011 Project Update

• Revised plans received from architect. Held pre-development meeting with Planning to clarify permitting issues with shade structures

• Plans submitted for review through development department and CIP review processes

Trail Connectivity

Page 37: March 2011 Project Update

• Held progress meeting to review park amenities, type and cost of fields, and brought project in line with current budget and cost estimates

• Met with BDD4 to review pond function, H&H model, access, and property acquisition, and identified need for Interlocal Agreement

• CR403 Extension per SPA with MUD#16 • Set up coordination meeting with MUD #16

Engineer and developer

Sports Complex at Max Road

Page 38: March 2011 Project Update

Utility Projects

Page 39: March 2011 Project Update

30” Waterline Interconnect

• The sub-contractor has drilled the piers on the North side of Clear Creek for the aerial crossing

• The 30” waterline has been pressure tested from McHard to the Alice Street Water Plant

• Completed installation of 20” distribution waterline from Alice Street Water Plant along McHard to Old Alvin Rd.

• Fuqua line and meter station underway • CoH 72” line scheduled for completion in July 2011

City of Houston Interconnect

Page 40: March 2011 Project Update

20” waterline with Gate Valve at Alice Street Water Plant

Page 41: March 2011 Project Update

City of Houston Interconnect

Alice Street Water Plant • Industrial TX continued working on the pump

building and chemical facility • Preload completed the construction of the interior

of the ground storage tank • Upon completion of the 30” waterline, Preload

will test the ground storage tank • Poured the slab for the turbine facility

Page 42: March 2011 Project Update
Page 43: March 2011 Project Update

South SH 35 Interim Lift Station at Industrial Drive

• Plans were revised. Request for proposal submitted to the contractor

• Proposal received from contractor and is currently under review

• Revisions will result in a deductive Change Order

Page 44: March 2011 Project Update

• Revised Design Services proposal to remove filter lift station & filter evaluation from design effort after filter evaluation letter report was completed

• Negotiated revised design contract • Prepared contract for presentation to

Council for award

Longwood WWTP Rehabilitation

Page 45: March 2011 Project Update

• Plant personnel are cleaning out the old storage basin to be reconstructed as the new thickener, for surveyor work on topographic plant site

• Met with geotech engineer and structural engineer on site to discuss bridge design issues

• Structural design of bridge and thickener equipment is underway

Barry Rose WWTP Rehabilitation

Page 46: March 2011 Project Update

• Negotiated design contract • Engineer prepared revised proposal • Presenting agreement and proposal to Council for

consideration

Hatfield Basin Trunk Sewer

Page 47: March 2011 Project Update

• Held project kick-off meeting • PER phase underway

Twin Creek Regional Lift Station

Page 48: March 2011 Project Update

Far Northwest Wastewater Treatment Plant Improvements

• Staff received and reviewed proposal for

equipment repairs and upgrades from decanter manufacturer

• Scheduling to meet with UV system manufacturer

Page 49: March 2011 Project Update

Old Alvin 20” Waterline

• Contract for PER services awarded at Council • Held Kick-off meeting

Page 50: March 2011 Project Update

Project Update

Questions/Comments