Development of Deoghar Inter State Bus Terminal (ISBT) on Public Private Partnership (PPP) Structure
Background
Deoghar is located in north east side of Jharkhand, Deoghar is a major Hindu pilgrimage and a famous health resort. It has the ancient temple of Baba Baidyanath, which is one of the twelve 'jyotirlingas' in India. BaidyanathDham, situated in the SanthalParganas of Bihar, is a very important piligrim centre. It's famous for the temple of Shiva-Baidyanath and the place is a popular holiday centre.
Deoghar is about 229 km from Patna (capital of Bihar) and 322 km from Ranchi (capital of Jharkhand) and about 315 km from Kolkata. Government of Jharkhand has proposed to develop a modern Inter State Bus Terminal (ISBT) in order to address the high urbanization trend, rapidly growing Urban Transport related issues witnessed in Deoghar in Jharkhand.
Dhanbad ISBT Site Features
Location: Deoghar –Sultanganj road in Baghmara village
About 4-5km from city bus stand ISBT Site area – About 20 acres
Mandatory Facilities to be developed
A. Bus Terminal Facility
Bus Bays (for Boarding and Alighting ) Bus Circulation Area & Approach Roads Ticketing Counters/ Reservation Counters
Enquiry Counters Tourist Information Centers Administration requirements like Traffic
Officer’s office, Supervisor Office, Duty List branch, etc
Operators/Concessionaire’s Office Entry & Exit to the Bus Terminal Facility Passenger Entry & Exit to the Bus Terminal
Facility Interconnecting Subways, Pathways, Foot-
over bridges, Ramps between various components, if applicable
Management Information System including public address system
Toilets for staff Store Room Passenger Information System
Project Facilities: Projected bus trips - 484 trips per day
(Design Period of 2045) Provision for 17 Active Bus Bays Idle bus parking for 109 buses Auto-Taxi /car Parking space for 236
Equivalent Car Space (ECS)
Permissible Floor Area Ratio (FAR) – 2.00
Site Area:
20 acre transferred to ULB 44 dismal private land for railway station
approach access to be acquired
Minimum Built-up Area to be developed:
Terminal Building– 9,000Sq.m Workshop – 800Sq.m Commercial Block- for Future
DevelopmentProject Cost – Rs. 72.86 Crore
Developer Selection Process: Open, Transparent Bidding Process Implementation Structure – DBFOT
model Concession Period -30 years Construction period – 2 years Equitycash support would be provided for
Development of ISBT Concessionaire shall pay Annual Lease
Rentals during operations period
Layout plan for Deoghar ISBT
3 D Views