92
INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE SESAR JU #SESAR @WorldATM_now

INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

INTRODUCTION AND SETTING THE SCENE

OLIVIER MONGÉNIESESAR JU

#SESAR @WorldATM_now

Page 2: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Agenda

• 16:00 – Introduction by the SJU

Olivier Mongénie, SESAR Joint Undertaking, Airport Integration & Throughput Programme Manager

• 16:10 – GBAS concept and technology

José Manuel Rísquez, ENAIRE (INECO), OFA01.01.01 (LVPs using GBAS) Coordinator

• 16:25 – How is the GBAS SESAR Solution validated?

– Operational validation activities in Release 4

Andreas Lipp, EUROCONTROL, OFA01.01.01 Contributor

– Technical validation activities in Release 4

• Overview of the technical validations and ground system

Udo Knick, Thales, 15.03.06 (GBAS Cat II/III L1 Approach) Project Manager

• Airborne system (mainline aircraft)

Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project Manager

• Airborne system (business aircraft)

Jolana Dvorska, Honeywell, OFA01.01.01 Contributor

• 17:00 – Demonstration activities: Augmented Approaches to Land Large Scale Demonstration Project

Jolana Dvorska, Honeywell, Augmented Approaches to Land Contributor

• 17:05 – Standardisation activities

Andreas Lipp, EUROCONTROL, OFA01.01.01 Contributor

• 17:15 – Regulatory activities

Maria Algar Ruiz, EASA, ATM/ANS-SESAR Coordinator

• 17:25 – Conclusion and Q&A session

Olivier Mongénie, SESAR Joint Undertaking, Airport Integration & Throughput Programme Manager

• 17:45 – Wrap up and close

2

Page 3: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Inn

ova

tio

n p

ipel

ine Phase 1

Phase 2/1

Phase 2/2

Phase 3

Delivery

3

The SESAR Pipeline

Page 4: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

SESAR Scope

SESAR Development Methodology

Gather and access ATM performance

needs

Scope operational concept and

develop validation plans

Iteratively develop and evaluate

concept

Build, consolidate and test

Industrialisation and approval

4

ATM needs Scope Feasibility

Pre-industrial development & integration Industrialisation

V0 V4V1 V2 V3

European Operational Concept Validation Methodology (E-OCVM)

Concept validation

Requirements development

Concept development

Technical development and verification

Integration

Page 5: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

SESAR Airport Domain

ACI/SJU SURFACE MANAGEMENT AND RUNWAY MANAGEMENT

WORKSHOP

Time based separation

Enhanced situational awareness

Ground safety nets

Dynamic vortexseparationEnhanced ROT

Low Visibility procedures using satellite GBAS

System interoperability with air & ground data sharing

Surface planning & routing

Arrival & Departure Management

Airport Operations Planning

User DrivenPrioritisation Process

Integrated Controller Working Position

Remote TowerSurveillance Ground System Enhancement

Enhanced situational awareness

Enhanced Decision Support Tools

LVPs using GBAS

Airport Safety Nets

Enhanced Runway Throughput

Integrated Arrival/DepartureManagement at Airports

Integrated Surface Management

Airport Operations Management

CWP Airport

Remote Tower

The SESAR Airport Concept Elements

Pilot enhanced visionEnhanced Vision SystemSynthetic Vision Guidance SystemCombined Vision System

Page 6: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

SESAR Airport Domain

ACI/SJU SURFACE MANAGEMENT AND RUNWAY MANAGEMENT

WORKSHOPEnhanced situational awareness

Ground safety nets

System interoperability with air & ground data sharing

Surface planning & routing

Arrival & Departure Management

Airport Operations Planning

User DrivenPrioritisation Process

Integrated Controller Working Position

Remote TowerSurveillance Ground System Enhancement

Enhanced situational awareness

Enhanced Decision Support Tools

Airport Safety Nets

Integrated Arrival/DepartureManagement at Airports

Integrated Surface Management

Airport Operations Management

CWP Airport

Remote Tower

The SESAR Airport Concept Elements

Pilot enhanced visionEnhanced Vision SystemSynthetic Vision Guidance SystemCombined Vision System

Low Visibility procedures using satellite GBAS

LVPs using GBAS

Enhanced Runway Throughput

Time based separation

Dynamic vortexseparationEnhanced ROT

Page 7: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

The SESAR GBAS Community

7

Page 8: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

GBAS SESAR Solution

• Precision approaches using GBAS CAT II/III based on GPS L1

– Part of Release 4

– Supported by 3 V3 validation exercises

• 1 operational validation

• 2 technical validations

– All validation activities have taken place

– Initial validation results and final documents still need to be consolidated and assessed

– SESAR Solution data pack expected by end 2015

8

Page 9: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

GBAS CONCEPT & TECHNOLOGY

JOSÉ MANUEL RISQUEZENAIRE/INECO

#SESAR @WorldATM_now

Page 10: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Agenda

• Augmentation principles

• GBAS applications in SESAR

• SESAR SOLUTION: Validation & Demonstration Strategy

10

Page 11: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Augmentation Principles

11

Page 12: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Augmentation principles

• NAVSTAR GPS fully operational in 1995 (Enroute-TMA)

• However…not good enough to allow safe landings

• ICAO and industry foresaw an alternative solution to ILS, to provide an approach supported by the GPS and appropriate augmentation.

• The system is called the Ground Based Augmentation System (GBAS)

12

Page 13: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Augmentation principles

GBAS relies on differential GNSS (e.g.GPS) signal

1. Satellites(e.g. GPS) producing ranging signals.

2. Ground subsystem providing a VDB(the final approach path,corrections and data for integrity)

3. Airborne subsystem:

• Receives and processes GPS andVDB data,

• Computes a position anddeviations

13

Page 14: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

GBAS concept Quiz

14

Your flight GPS position is40,49° N – 3,67° W

GBAS ground system informs you thatthere is an error of 0,02 °N and 0,01°W

Your more accurate position with GBAS would be 40,xx ° N – 3,yy° W ???

Antenna real position is40,40° N – 3,60° W

Antenna GPS position is40,42° N – 3,61° W

Page 15: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

GBAS concept Quiz: Solution

15

Your flight GPS position is40,49° N – 3,67° W

GBAS ground system informs you thatthere is an error of 0,02 ° N and 0,01°W

Your more accurate position with GBAS would be 40,47 ° N – 3,66° W

Antenna real position is40,40° N – 3,60° W

Antenna GPS position is40,42° N – 3,61° W

Page 16: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Augmentation principles: GBAS CAT I Ground Stations

16

GBAS precursor (S-CAT I)

GBAS for private operations

Extracted from

flyGLS.net

Public CAT I approached in operation

Page 17: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

GBAS applications in SESAR

17

Page 18: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

GBAS Apps in SESAR: Displaced Thresholds

• GLS approach - Less risk of wake vortex encounter: Reduced separation (GLS:GBAS Landing System)

• GBAS can transmit multiple Final Approach Segments: better cost-effectiveness vs ILS.

• Less RWY Occupancy time and noise impact reduction are other benefits.

18

Page 19: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

GBAS Apps in SESAR: Increase Glide Slopes

• GBAS is capable of transmitting multiple Final Approach Segments and even different Glide Path Angles (GPA) with a single installation.

• GLS-Noise-reduced approaches are possible by avoiding low-flying over densely populated areas

19

3º 3.2º 3.4º

Page 20: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

GBAS Apps in SESAR: RNP-GLS-Curved Approches

• RNP: Very predictable Initial and Intermediate curved approach segments (Radius to Fix turns)

• GBAS: GLS Final Approach Segment (i.e. different slopes, different THR, shortest possible length)

• Noise-reduced approaches are possible due to a more flexible approach path adaption

20

Page 21: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

SESAR SOLUTION:

GBAS CAT II/III

Validation & Demonstration Strategy

21

Page 22: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

• CAT I approaches using GBAS (GAST-C) already certified

• However, CATII/III approaches require better performance as well as new functions and monitors in ground stations and on board receivers…

• GBAS Approach Service Type D CATII/III (GAST-D) is based on existing GPS constellation…

• Additional GNSS constellation may improve resilience

22

SESAR Solution: GBAS CAT II/III (1/5)

CAT I

Photos CourtesyThales

CAT II

CAT IIIb

Automatic

Landing

Page 23: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

SESAR Solution: GBAS CAT II/III (2/5)

23

0 500 1000 1500 2000m

C1-1

C1-41-3

C1-6

C2-1

A 2-4

TW R

C1-5

C

Why?

• When low-visibility conditions occur on an airport, a better quality of ILS signal has to be provided to arrivals.

• Larger protection areas must be respected

• Larger arrival separation must be provided.

• Higher delays and flight cancellations.

ARR

DEP

0 500 1000 1500 2000m

C1-1

C1-41-3

C1-6

C2-1

A 2-4

TW R

C1-5

C

Page 24: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

SESAR Solution: GBAS CAT II/III (3/5)

24

GBAS GAST-D can overcome these limitations.

SESAR Solution:

an integrated set of system and operational elements that will allow performing ILS look-alike CATII/III operations without such protection areas.

Page 25: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

SESAR Solution: GBAS CATII/III (4/5)

Operational Concept:

• ATC can use a less constraininglanding clearance line for aircraftvacating the runway.

• ATC can provide the pilots withlate landing clearance, up to 1NMbefore threshold

• ATC can reduce the final approachspacing in LVP in front of GBASequipped aircraft

25

0 500 1000 1500 2000m

C1-1

C1-41-3

C1-6

C2-1

A 2-4

TW R

C1-5

C

0 500 1000 1500 2000m

C1-1

C1-41-3

C1-6

C2-1

A 2-4

TW R

C1-5

C

Page 26: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Benefits:

• Under Low Visibility Conditions, GBAS CATII/III operation vs ILS CATII/III operation will bring us:

– higher airport resilience

– better predictability

– less delays

– less use of alternative airports and

– less flight cancellations

26

SESAR Solution: GBAS CATII/III (5/5)

Page 27: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

To deploy properly all these elements in any European airport in an homogeneous way, it is required to accomplish in parallel a great standardization and regulatory challenge

SESAR Advantage: people involved in R&D project are also involved in official standardization and regulatory activities

Airborne equipments

Ground System

equipments

Flight Procedures

design

ATC Procedures

…Phraseology

Standardization and Regulatory process

27

Page 28: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Validation & Demonstration Strategy

28

GroundSystems

Two airports

AirborneSystemsMainlineBusiness

OperationalConcept

RTS

Interoperability

v0 v1 v2 v3 v4 v5 v6 v7

ATM

Needs

Scope Feasibility

Pre-industrial development &

Integration

Industr. Deploym. Operat. Decom.

European – Operational Concept Validation Methodology (Iterative Process)

Safety

Human PerformanceTr

ansv

ersa

l Are

as

Page 29: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

HOW IS THE GBAS SESAR SOLUTION VALIDATED?OPERATIONAL VALIDATION ACTIVITIES RELEASE 4

ANDREAS LIPPEUROCONTROL

#SESAR @WorldATM_now

Page 30: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Agenda

• Operational concept description

• Validation objectives and method

• Validation scenarios and platforms

• Validation execution

• Achievements

30

Page 31: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

GBAS Cat II/III – Operational Improvements

Optimised Low visibility operations using GBAS concept based on:

ATC to use a landing clearance line for aircraft vacating the runway, instead of today’s ILS CAT III holding

ATC to provide the pilots with late landing clearance, up to 1NM before threshold

ATC to reduce the final approach spacing in LVP in front of GBAS equipped aircraft

Main actors affected; final approach and tower air traffic controllers as well as pilots

Page 32: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

To reach V3 maturity based on previous V2 validation exercises (fast-time)

To assess the increase of runway throughput in LVP considering: Runway configurations

Arrival only (segregated runway)

Arrival and departure (mixed mode runway)

Aircraft fleet equipage

Only GBAS aircraft

Mix of aircraft equipage between GBAS (60%) and ILS (40%)

To evaluate the suitability of runway safety nets and assess the safety of optimised LVP operations based on GBAS

To evaluate the ATC workload and the new ATC procedures for final approach spacing.

To validate that provision of late landing clearance by ATC does not impair the pilot capability to prepare the landing

Validation objectives

Page 33: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Validation approach

Real-time simulation Simulation Platforms

EUROCONTROL eDEP/ITWP - Early Demonstration and Evaluation Platform / Integrated Tower working position

EUROCONTROL ESCAPE – A real-time air traffic control simulator for en-route, TMA and approach

EUROCONTROL MCS - Multi Cockpit simulator

Simulation scenario

Charles de Gaulle Airport

Page 34: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Simulation Airport

The simulated Airport is Paris CDG

The setup of the scenarios was such as to apply to a generic airport

Peak traffic in order to achieve the optimised throughput

34

Only north RWY 27L simulated

RWY 27L was used for arrivals only and in mixed mode arrivals/departures

- CDG Airport TMA -

- CDG Airport north runways -

Page 35: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

eDEP/ITWP - low visibility settings

35

Page 36: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

eDEP/ITWP - Controller working position

36

Page 37: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

eDEP/ITWP – GBAS specific HMI changes

37

Page 38: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

38

ESCAPE/Approach - controller working positions

Page 39: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

ESCAPE/Approach – GBAS specific HMI changes

39

Page 40: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Cockpit simulator

40

Page 41: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Validation Scenarios

The simulations included six validation scenarios

ILS arrivals only (baseline scenario)

ILS arrival/departures (baseline scenario)

GBAS arrivals only

GBAS arrival/departures

GBAS/ILS arrival only

GBAS/ILS arrivals/departures

Each scenario was run in a simulation hour

Several safety scripts, failure scenarios included

41

Page 42: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Validation Execution

Real Time Simulation schedule

Training: ENAV Air Traffic Controllers training with the new RTS platforms from 16 to 18 September 2014

Simulation: One week, 29 September – 3 October 2014 in EUROCONTROL Experimental Centre, Bretigny

Participants:

Three air traffic controllers from ENAV, licensed for both Approach and Tower

Three pilots from Novair, TuiFly and Airfrance using MCS

Other visitors from ATC Unions and SJU

Page 43: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Validation results

In all validation scenarios an increase of runway throughput or at least the same level was recorded.

ATC workload considered acceptable

Good situational awareness by ATC

The safety of operations is maintained.

The final approach spacing for arrival only runway configuration was considered appropriate

The final approach spacing for mixed mode runway need to be fine tuned according to airport local constraints.

Positive feedback on GBAS HMI elements

43

Page 44: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

HOW IS THE GBAS SESAR SOLUTION VALIDATED?TECHNICAL VALIDATION ACTIVITIES IN RELEASE 4

& GROUND SYSTEM

UDO KNICKTHALES

#SESAR @WorldATM_now

Page 45: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Agenda

Project Objectives

SESAR CAT II/III Validation

GBAS CAT III Ground Station

Ground Subsystem Performance Demonstration

CAT III Ground Station Prototype Performance Summary

Page 46: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

GBAS CAT III projects Objectives

GBAS CAT III technology based on GPS L1 C/A (single frequency) to support

Automatic approach and landing (including automatic roll-out) down to CAT IIIb

Guided take off

GBAS CAT III validation performed in SESAR projects for

Cat IIIb (including automatic roll-out and guided Take off) for mainline aircraft

Cat II or Cat IIIa for business and regional Aircraft

SESAR system validation for V3 level of maturity at end of SESAR 1 -Demonstration of readiness of the solution for industrialization & approval

Confirm that GBAS CAT III has no operationally relevant critical & sensitive zones

Verify GBAS CAT III touch-down performance by autoland flight tests & ground and airborne analysis, simulation & measurements

Validate GBAS CAT III system standard

Page 47: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

SESAR CAT II/III Validation

Aircraft Integration &

Validation

MMR Development &

Verification

Airbus ThalesToulouse Valence/Paris

CAT IIIb

Flight Tests &

System

Validation

Mainline aircraft

Airborne Development & Verification

Thales DSNAStuttgart Toulouse

Ground Development & Verification

Airport Implementation & Validation

GBAS Site

Prototype I

Ground & System Development

Business Aircraft

9.12 Airborne Development & VerificationIndraNavia DFSNorway Frankfurt

Prototype II

Ground / System Development

Interoperability

Flights

CAT II/IIIa

Flight Tests &

System

Validation

optional

Honeywell Honeywell Aircraft Integration &

Validation

Avionics Receiver

Development & Verification

BrnoBrno

Page 48: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Prototype 1: GBAS CAT III Ground Station

Thales DGRS 610/615 VDB Transmitter Receiver Antenna

GNSS Reference Receiver & Antenna

Air Traffic Controller Windows

Portable Maintenance Data Terminal

GNSS Antenna sites

GBAS Shelter

VDB TransmiterAntenna

Toulouse GBAS GAST D Installation

Thales Ground Equipment used in SESAR Release 4 Validation

Page 49: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Prototype 2: GBAS CAT III Ground Station

49

4

Page 50: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Ground Subsystem Performance Demonstration

ISPA 2013: 23/10/201350

Hardware (HW) /Software (SW) Implementation

Lab TestHardware in the Loop Simulation & Test

Field TestOperation of Equipment & Data logging

Algo-rithm

Software Implemen-

tation&

Hardware Integration

a Confirmation of Error bounding

a Confirmation of continuous fault free operation

Analysis

Data logging Long term

observation Specialized test

scenarios

Site Implementation

Long-term evaluation of ground equipment algorithm performance by Thaleslong-term evaluation of performance at user level conducted by DSNA

Page 51: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

CAT III Ground Station Prototype Performance Summary

Accuracy: Very accurate GBAS correction information (<5 cm); User position accuracy ~ 0,5 m a Requirement far exceeded

Continuity: Capability of extreme low monitor false alarm rate (one Ground monitor induced missed approach per 20 Million landings) demonstrated

Integrity: Capability to ensure CAT III ranging source integrity (Catastrophic event is extremely improbable) demonstrated

Availability: No unscheduled interruption of service in more than one year

51

Accuracy limit: 95% Ground Error Contribution

Ground Performance: Accuracy & Integrity & Continuity & Availability a Aircraft Touch-Down Performance

Pos. Error (95%) ~ 0.5 m

E-W Error0 m-2 m 2 m

N-S

Err

or

2 m

-2 m

0 m

Probability of False Alarm below

ContinuityLimit

Probability of missed detection

below Integrity

limit

Airborne Range Error

Pro

bab

ilit

y

2 m10

-10

Page 52: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Initial System Validation Results

Ground Correction

Performance

Airborne Navigation

Performance

Aircraft Landing Performance

Safe Landing& &

200ft 2700/3000ft

+/- 70ft

Threshold

Landing Box

Confirmed by Ground

PerformanceResults

Confirmed by Airborne

Performance Results

Confirmed by Autopilot

Simulation & Flight Test

Results

Page 53: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Summary

Very Positive Mainline & Business Aircraft Flight test results

CAT III GBAS validation exercise using GBAS ground station in Toulouse successfully conducted

Results significantly contribute to ICAO GBAS CAT III standard validation

Validation results are expected to demonstrate full V3 maturity on GBAS CAT II/III technology

Development of GBAS towards CAT IIIb is on the way for implementation

Page 54: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

AIRBORNE SYSTEM (MAINLINE AIRCRAFT)

DIETMAR KLEINITZAIRBUS

#SESAR @WorldATM_now

Page 55: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Agenda

Validation Ojectives

GBAS Cat II/III (GAST-D) prototype development

Airbus Flight Test campaign 2013/14

Flight Test installation

Flight Test conduction

Validation Results

55

Page 56: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Validation Objectives

56

Validate the GBAS GAST-D System Specification

Verify the performance of a Mainline aircraft system implementation under operational conditions

Verify the performance of an airborne component (Multi Mode Receiver, MMR) with respect to the functional implementation

Validate test means (tools) and methods to ensure the Certification

from CAT I to

CAT IIIb

Page 57: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

GBAS GAST-D prototype development

57

Activities/Milestones DatesPrototype specification Nov. 2011Incremental Function Implementation onThales and Airbus side

Jan. 2012 –Jun. 2013

Prototype flight test readiness July 2013Airbus A380 flight test (prelim. validation) with ground station prototype 1 , Toulouse/Blagnac

Nov.-Dec. 2013

Analysis of preliminary flight test results, prototype and test set up adaptations

Dec. 2013 –April 2014

Airbus A320 flight test (design&product validation, ) with ground station prototype 1, Toulouse/Blagnac

Sept.- Oct. 2014

Page 58: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Airbus Flight Test campaign 2013/14

58

A320 and A380 test A/C applied to represent the extreme examples of the Airbus mainline aircraft spectrum.

Up to now, Airbus aircraft are certified for GBAS approaches with Cat I minima.

GBAS Cat II/III approaches require better performance with respect to integrity and continuity.

Page 59: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Flight Test installation 1/2

59

Installation within A320 test A/C

Page 60: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Flight Test installation 2/2

60

HMI function implementation on test A/C

HMI is not changed specifically for GBAS Cat II/III;

“ILS-look alike”- concept applied to make the precisionapproach procedure transparent to the crew.

Page 61: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Flight Test conduction

61

Approach in GAST-D during

A380 flight F966

flight trajctorytrace on ground

19 approaches with Toulouse-Blagnac ground station

from inside and outside of approach areas

all combinations of runway and landing directions

Touchdown and roll out manoeuvers

Taxiing

GAST-D and GAST-C configurations tested

further GBAS operational aspects checked:Guided Takeoff

Page 62: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Validation Results*

62

Positive GBAS GAST-D operation validation results achieved with Airbus mainline aircraft A380 and A320. Flight test scenarios and manoeuvers have been applied, verifying the good functioning of the

GBAS Cat II/III function implementation at aircraft architecture and MMR level;

Touch down performance of automatic flight and NSE (navigation sensor error)well within expectations;

The Thales Multi Mode Receiver (MMR) prototype based on a certified Line Replacable Unit (LRU) has been successfully tested in operational GLS (GNSS Landing System) conditions;

Interoperability between aircraft implementation and GAST-D ground system can be confirmed;

Capability to ensure Cat III positioning source Integrity was demonstrated;

Results indicate that Continuity requirements can be achieved.

GBAS GAST-D function and operation concept validation results should allow to reach full V3 maturity on GBAS Cat II/III technology, system components ready to enter product phase.

* SESAR JU assessment of the validatioin results is ongoing

Page 63: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

AIRBORNE SYSTEM (BUSINESS AIRCRAFT)

JOLANA DVORSKAHONEYWELL

#SESAR @WorldATM_now

Page 64: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Agenda

• Airborne Subsystem – Business Aircraft GBAS CAT II/III Validation – Validation Objectives

– Data Collection Campaign

– Aircraft Installation & Displays

– Flying GBAS

– Validation Results

• LSD – Augmented

Approaches to Land– Project Objectives

– Key Stakeholders

– Live Trials

– RNP to GBAS Landing System

64 Honeywell Confidential Proprietary Information

Page 65: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Jolana Dvorska, HoneywellMarch 10, 2015

AIRBORNE SYSTEM –BUSINESS AC

GBAS CAT II/III VALIDATION

Page 66: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

• Verify performance in operational environment for business aircraft.

• Verify performance of Honeywell avionics receiver VIDL/G to perform GBAS CAT II/III approaches.

• Collect data to support validation of simulation tools.

66

Business Aircraft – Validation Objectives

Honeywell Confidential Proprietary Information

Page 67: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Business Aircraft – Data Collection Campaign

Flight Tests: Phase 1 – Sep /Oct 2013

Phase 2 – Jun / Jul 2014

Honeywell exp. Dassault F900EX

Tests included: GBAS CAT I and CAT II/III flights ,

In nominal, non-nominal conditions, regression tests

Overview of tested airports & systems

67

F900 EX

Integration testing in hangar

Airport Name ID City State Ground Station Phase

New Century

AirCenter

Airport

KIXD Olathe KSHoneywell – GAST

D experimental1

George Bush

Intercontinen

tal Airport

KIAH Houston TXHoneywell – GAST C

certified1 & 2

Atlantic City

Int’lKACY

Atlantic

CityNJ

FAA /HON–

GAST D

experimental

1 & 2

Frankfurt

AirportEDDF Frankfurt Germany

NATMIG –

GAST D

experimental

1 & 2

Toulouse-

Blagnac

Airport

LFBO Toulouse France

Thales –

GAST D

experimental

1 & 2

City Airport

BremenEDDW Bremen Germany

Honeywell – GAST C

certified2

A total of 150 approaches were successfully flown and data were collected to support validation.

Honeywell Confidential Proprietary Information

Page 68: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Business Aircraft Installation Test Setup

68

VIDL-G

MCMF Receiver

Novatel Truthing

System

Telerad

TIU

PC

Tuning

Head

PC

PC

GLS

Display

ARINC 429

(All Output Data)

USB

(Novatel Output Data)

ARINC 429

(Tuning Commands)

RS232 + ARINC 429

(All Output Data)

1 PPS Synchronization Pulse

VHF

NAV/LOC

Antenna

GPS Dual

Freq Antenna

RS485

(VDB Data)

ASCB Data

(to be recorded)

Test Units

Recording &

Display & Tuning

UnitsInputs

RS232

(Output Data)

Generic I/O

ModuleAuto PilotASCB

Aircraft Avionics

Tested avionics receiver coupled with autopilot enabled automatic GBAS CAT II/III approaches.

Honeywell Confidential Proprietary Information

Page 69: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Business Aircraft: Experimental Display

69

Prototype GBAS Landing System Annunciations – designed for flight

test only.

Honeywell experimental display - GBAS CAT II/III approach in

Atlantic City.

Honeywell Confidential Proprietary Information

Page 70: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Let’s Fly GBAS…

70 Honeywell Confidential Proprietary Information

Page 71: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Business Aircraft: Validation Results

• Complex campaign successfully performed.– 16 different validation scenarios completed

– 6 airports with 4 different ground stations tested

• Pilots confirm very good performance in operational conditions.

• Honeywell avionics receiver with GBAS CAT II/III capability successfully tested.

• Thorough data analysis performed confirms good performance.– Full V3 maturity level should be enabled with these

results.

• Simulation tools used to provide further inputs to concept validation.

• Inputs provided to standardization.

71

Good performance of GBAS CAT II/III avionics system in operational conditions confirmed.

50010001500200025003000350040004500

-1

0

1

ALL (FIX):

vertical NSE [m], 30 sec solution, GAST D, nominal approaches

Reference height above LTP [ft]

[m]

mean

std

RMS

500100015002000250030003500400045000

20

40

60Number of measurements

Reference height above LTP [ft]

num

ber

of

measure

ments

Navigation Sensor Error during CAT II/III approaches well within expectations.

Honeywell Confidential Proprietary Information

Page 72: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Jolana DvorskaMarch 10, 2015

LSD02.02 AUGMENTED APPROACHES TO LAND

Page 73: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Demonstration of benefits of augmented vision and GNSS augmented navigation solutions:

• improved access

• reduced environmental impact

• to all types of airport

• for all types of Airspace users

Presentation focus is on

RNP to GBAS approaches.

73

Demonstration Project Objectives

Bridging gap between research and deployment.

Page 74: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

74

Joint Effort of Key Stakeholders

DomainConsortium

Member

Airspace Users

EBAALufthansa

NetJetsSWISS

Air Navigation Service Providers

ANS CRDFS

DSNASkyguide

Airport OperatorsFraport

Zurich AirportAirframe

ManufacturersAirbus

Dassault Aviation

Avionics SuppliersElbit Systems

Honeywell

Procedure Design DLR

- Demonstration of procedures and technologies in real operational environment.

- Speed up deployment and adaptation in EU.

- Over 200 demonstration flights in 2015/16.

Page 75: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Demonstration - Live Trials

SWISS A320FAM aircraft Lufthansa A319 (photo by: Ingrid Friedl)

Lufthansa A380 (photo by: M. Lindner und Lutz Borck) Lufthansa B747-8 (photo by: Jürgen Mai)

Honeywell’s experimental F900 (photo by: Ivo Carvan ICARcz) Dassault experimental Falcon 7X MSN1

Page 76: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

RNP to GBAS Landing System

Building on current infrastructure

• RNP to GLS will be demonstrated on certified GBAS CAT I stations:

– Frankfurt– Bremen– Zurich

Over 130 approaches on revenue and business aircraft.

Expected benefits

– Shorter path,

– accuracy of flight,

– decreased noise,

– lower fuel consumption,

– lower CO2 emissions.

76

Page 77: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

STANDARDISATION ACTIVITIES

ANDREAS LIPPEUROCONTROL

#SESAR @WorldATM_now

Page 78: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

GBAS Standardisation WAC, March 2015

78

Standardization and Regulation

• Aviation - a global activity

• ICAO with 191 member states

• Multiple players in Europe

– EASA

– National authorities (NSA/NAA – examples)

• LBA, BAF

• DGAC/DSNA

• BAZL

• AESA (Spain)

– EUROCAE/RTCA – Industry standards

– Other standardisation bodies

• EC, through:

• ETSI, CEN, CENELEC

Page 79: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Complex Interactions

Sate-llite

Ground

System

Aircraft

GBAS Standardisation WAC, March 2015

79

Airline

Airport

Oper-ation

ANSP

ICAO

Reg.Stds

Regula-tions

ITU

Procedures- Design- ATC- Training- Maintenance

Design- Safety- Security- Hardware- Software- Redundancy

Page 80: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Typical Timeline and Outlook

GBAS Standardisation WAC, March 2015

80

GBAS CAT III (GPS L1)

GBAS CAT I

GBAS CAT III (MC/MF)

- To be developed

1989 20001985 2008 2012 2014

2004 2014 2019

EASA, NSA/NAA and Industry committmentneeded to complete for

Europe

Page 81: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Current Status

• GBAS CAT I

– All required standards exist

– Improvement and maintenance (SESAR)

– Extension of capabilities (SESAR)

• GBAS CAT III using GPS L1

– ICAO SARPS in final review (SESAR)

– RTCA and EUROCAE MOPS development in final stages (SESAR)

– ARC has concluded on airborne regulations and given a recommendation for further processing to FAA (SESAR)

• GBAS CAT III using GALILEO

– Draft standards in development (SESAR)

GBAS Standardisation WAC, March 2015

81

Page 82: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Summary

• Complex and long process

• Significant interaction with development

• National specificities

• Differing timescales and priorities

• Harmonisation is a must, since global operations

Early consideration by and active involvement from regulatory and standardisation bodies, as well as European industry is needed

GBAS Standardisation WAC, March 2015

82

Page 83: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

REGULATORY ACTIVITIES

MARIA ALGAR RUIZEASA

#SESAR @WorldATM_now

Page 84: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Involvement of EASA GBAS activities within SESAR and future plans to support

deployment

Maria Algar RuizATM/ANS-SESAR CoordinatorEuropean Aviation Safety Agency (EASA)

World ATM Congress Madrid 10/03/2015

Page 85: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

EASA activities –GBAS Cat I Operations

ETSO-c161a based on DO-253C published in 2012

Certification of airborne installations (e.g. A320, A340, A380, A350 families)

Plans to amend AIR OPS requirements to include training and operational aspects on GBAS Cat I landing systems

10/03/2015 WAC Madrid 2015 85

Page 86: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

EASA’s activities in GBAS Cat II/III within SESAR (R&D)

GBAS Workshop on the 28&29 of May 2013 and follow up of theoutcome

Review of document ‘SARPs for GNSS elements and signals (GBAS).Conceptual Framework for the Proposal for GBAS to Support CAT IIIOperations’ under the LoA with SJU

Participation in validation exercise on the 28 of July 2014 ‘SESAR9.12 Frankfurt Tests Phase 2 – Honeywell Business Aircraft’

Participation in series of meetings and telephone calls within theumbrella of AWOH ARC

Informal discussions with Industry and also regulators

EASA is prepared for a deeper involvement in the work to supportthe further maturity in readiness for deployment

10/03/2015 WAC Madrid 2015 86

Page 87: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

EASA planned activities in GBAS Cat II/III outside SESAR –general regulatory activities

10/03/2015 WAC Madrid 2015 87

Participation in development of industry standards (EUROCAE and possibly RTCA) if not physically at

least reviewing the proposals

Continuing participating in AWOH ARC

Review of proposed standards to ICAO Annex 10

Initiate regulatory activities with aims at:

Review and amend ETSO-C161a if necessary

Review and complement if necessary Certification Specifications

Complement AIR OPS rules if necessary and develop AMC/GM as needed to support flight operations

Regulatory framework for ground stations ‘acceptance’ for manufacturing industry and supporting guidelines for ANSPs installations if necessary slide 7

Safe, interoperable and harmonised

implementation across EU

Page 88: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

GBAS Cat II/III – roles and responsibilities in the implementation (I)

10/03/2015 WAC Madrid 2015 88

Page 89: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Airborne-A/C:

TC/STC holder for the airborne installation

EASA as airworthiness certification authority

Ground stations:

Industry for development and ANSP/ADR operator for installation/operation/maintenance

NSA/NAA approval of the ground installation (incl. the review of technical file and the ground station tech specs)

Aircraft operations:

Airlines-A/C operators for training of flight crews and operational procedures

NAA for the approval

10/03/2015 WAC Madrid 2015 89

GBAS Cat II/III – roles and responsibilities in the implementation (II)

Page 90: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

EASA proposal for ground stations:Ground stations ‘technical acceptance’ by EASA

ANSP/ADR operator installation’s approval by NSA/NAA (approval of safety cases for the changes) based on the ‘technical acceptance’ by EASA

Advantages:Single ‘technical acceptance’ of industry’s ground stations by EASA that can be used by all ANSPs/ADR operators and their NSA/NAA in EU

Ensuring harmonisation and level playing field

Optimisation of resources

Air-ground (end-to-end) safety and interoperability ensured

10/03/2015 WAC Madrid 2015 90

GBAS Cat II/III – roles and responsibilities in the implementation (III)

Page 91: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

CONCLUSIONS AND Q&A

OLIVIER MONGÉNIESESAR JU

#SESAR @WorldATM_now

Page 92: INTRODUCTION AND SETTING THE SCENE - SESAR JU · 2017-03-06 · INTRODUCTION AND SETTING THE SCENE OLIVIER MONGÉNIE ... Dietmar Kleinitz, Airbus, 09.12 (GBAS Cat II/III) Project

Thanks for your attention

92

#SESAR @WorldATM_now