Interface Article

Embed Size (px)

Citation preview

  • 8/2/2019 Interface Article

    1/7

    Interface Management

    INTRODUCTION

    In recent times, the projects have become very challenging as deliveries crunch and big designs roll out

    faster with the aid of sophisticated software. Construction can be simulated to identify potential issues

    in advance. In this process, many of the concepts learnt a few years back become redundant and many

    remain.

    The fundamentals remain strong and they are continuously being adapted with changing scenario of EPC

    and computer world. This article intends to present the need for identifying interface and emphasize on

    the importance of interface in a project. Interfaces exist at all stages of the project life cycle.

    BASICS OF A PROJECT

    The question what is a project? is answered in many ways. A fit for purpose definition would perhaps

    sound as follows: A project is an endeavor to create something unique.

    A simple flow of the various stages of the project for a project is as shown below:

    There are many sources from where a project can initiate. In oil and gas industry, typically a project can

    initiate from any of the following business streams or verticals:

    Exploration Petroleum technology

    Drilling and well technology Concept development and engineering Project development

    Plant operation, maintenance and modifications including HSE, Risk, legal requirement etc.

    Marketing and supply

    - oil and products

    - gas sales and supply

    Concpet FEED Invitation to BidEngineering,

    Procurement,

    Construction

    Transportation,Installation,

    Hookup

    Precommissiongand

    Commissioning

  • 8/2/2019 Interface Article

    2/7

    Once the intent for doing a project is established, the basic process to achieve the intent is defined. The

    first stage is called as feasibility study and the second stage is referred to as Concept stage of the

    project.

    Front End Engineering and Design (FEED) is a project stage in which the concept is turned into a tangible

    idea. This is a very important phase of the project as it identifies various technical solutions and defines

    financial requirements of the project and thus prepares the business case for funding and recovery of

    the investment in the project by interested parties. The project funding should comply with government

    rules and regulations

    It is the choice of the owner to decide whether a FEED stage should exist in a project or not and if it

    does, then what is the extent of it. Many times, FEED is an extension of concept itself.

    Thus it is amply clear that the following interfaces are to be addressed at FEED stage of the project:

    1. Interface with financial institutions.

    2. Interface with Contractor.3. Interface with government agencies.

    The accurate determination of investment capital and project costs in all projects as well as its stages

    has strong affect to the project success and efficiency. The required levels of accuracy of project cost

    estimates vary at different stages of project development, but at all times, the need to cover the various

    risks associated with finance need to be addressed (for eg: contract currency, rate of exchange etc) .

    It is well known that design decisions made at the beginning stage of a project life cycle are more

    tentative than those made at a later stage, the cost estimates made at the earlier stage are expected to

    be less accurate. Generally, the accuracy of a cost estimate will reflect the information available at the

    time of estimation.

    The project cost estimates may be viewed from different perspectives because of different institutional

    requirements. The risk factors for a project need to be clearly documented to arrive at a logical project

    cost.

    More often than not, the result of the FEED studies lead to defining the tender package (also called as

    ITT, ITB etc). The tender package defines the commercial, legal, financial and technical requirement of

    the project. It is floated to various companies to get the best possible technical solution at the best

    possible price. There can be different business models in the ITB or maybe proposed by the bidder. It is

    the onus of the tendering committee to sift through all the responses to the ITB and answer the queries

    within. It is the work of the tender committee to then rank the bidders and submit it to the owner(s) for

    making an award of contract.

    Once an award is made, then the project enters into the next stages of Engineering, Procurement,

    Construction, Transportation, Installation, Hookup, Pre-commissioning and finally commissioning of the

    project. All the terms are self-explanatory.

  • 8/2/2019 Interface Article

    3/7

    DEFINING INTERFACE

    There are many ways of defining interface . In general terms, interface management is systematic

    control of communication that is generated during execution of the project.{1}

    It is a very important aspect of the project. The objective of the Interface management process

    is to facilitate agreements with concerned regarding roles & responsibilities, timing for providing

    information and identification of critical interfaces early in the project through a well-defined process.

    The overall goal is the early identification of issues with potential for impact to cost or schedule, to

    minimize or remove their impact and promote clear, accurate, timely, and consistent communication

    with other stake holders for exchanging interface in order to avoid mistakes, miscommunication, wrong

    procurement, erroneous fabrication etc .

    Thus interface management initiates its presence from the tendering stage and up-to the mechanical

    acceptance or performance guarantee of the facility. The owner has a different set of interface afteraccepting the facility and this part is called as operation. Operation is thus differentiated from project

    and is more focused on running day to day matters.

    In broad, there are two types of interface for a project group:

    Internal Interface for eg: those related to engineering, procurement, installation,

    commissioning etc.

    External Interface for eg: land acquisition, power sanction, environmental clearance, legal,

    financial etc.

    INTERFACE PROCESS

    Irrespective of the type of interface, the interface management process involves many stages. The first

    stage is to identify an interface. The second stage is to provide a method to formally document and track

    the exchange of information between project participants. The last stage is to monitor the performance

    of all involved in the register in making available the required information. The interface register can

    have any format, but it should address the following issues clearly:

    Identification and recording an interface

    Creating an interface agreement

    Agreeing / Resolving Conflict

    Monitoring the status Reporting the status

    Closing the interface agreement

    The Stake holder/ promoter /owner is usually in-charge of external interfaces. The steps involved in

    external interface are different from one project to another.

  • 8/2/2019 Interface Article

    4/7

    We will look more towards internal interfaces as many steps here remain unchanged irrespective of the

    project.

    DEFINING INTERNAL INTERFACES

    The important interfaces in a project are related to the following areas:

    Scope Controlling the planning, execution, and content of the project is

    essential. At the end it is important that what you intended to make in

    the first place.

    Time Managing everything that affects the projects schedule is crucial. A

    delayed project can be a lost opportunity.

    Cost Projects cost money, and this knowledge area centers on costestimating, budgeting, and control. It can so happen that the timing of

    the project can be such that the cost is down.

    Quality No project is a good project if the deliverable looks like tyre instead of

    donut. Quality work requires a continuous commitment by all, it needs

    monitoring, feedback and correction cycle to be working full time. Many

    times quality can result in overrun of schedule and budget and hence it

    needs to be defined correctly.

    Human Resources The members of the project team must get their work done. Hiring or

    assigning people who are competent and managing is important for the

    success of the project.

    Communications Project managers spend 90 percent of their time communicating.

    Communications management focuses on who needs what information

    and when. In addition to formal communication, informal

    communication goes a long way in success of a project. Many times

    something not said produces better result.

    Project Risk This knowledge area is about avoiding disaster. The focus is on how to

    anticipate risks, handle them when they arise, and take advantage of

    the opportunities that can help a project.

    Procurement This knowledge area is concerned with the processes to create vendor

    contracts and to purchase goods and services as per project

    specification and in the cost and time allotted for the same.

    Integration What happens in one area affects attributes of the other areas.

    Integration needs a very pragmatic handling since its purpose is to

    ensure the coordination of all the other knowledge areas.

  • 8/2/2019 Interface Article

    5/7

    Fig 2: The Famous Project Triangle: Change to one side, affects other.

    The INTERFACE CIRCLE

    Management defines the procedures and rules for the Man and Machine to work in order to complete

    the project keeping all the external factors related to Man,Management and Machine in view.

    Man Machine

    Management

    External Influences

    PROJECT

  • 8/2/2019 Interface Article

    6/7

    Interface examples:

    As we have noted above, there are many types of interface in a project and there is a definite need for

    an interface register for a successful project. Some typical example for defining interface is noted

    below:

    Example 1:

    Interface No Work Activity Responsibility Start Finish Remark

    1 Key Plan A XX.XX YY.YY Northing

    and easting

    by surveyor

    2 Elevation drawing B xx.xx yy.yy See Plan for

    dependent

    activity

    3 Process Flow C Xx.Xx Yy.Yy Concept byClient

  • 8/2/2019 Interface Article

    7/7

    Example 2:

    Conclusion:

    The information shared above is generic and it can be adapted to any project model. Modern projects

    use sophisticated commercial software to simple XLS to maintain interfaces.

    The biggest interface of human to human and appreciating the work of another person is the most

    important interface for a successful project.

    Interface Matrix

    Internal Interface External Interface

    Home Office

    Design Center

    Procurement Div

    QA / QC

    Finance

    Project Office

    Store

    Fabrication

    Erection/ Testing

    Commissioning

    Design Review

    Valid License

    Progress Register

    QA / QC

    Finance

    Common!