Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
Integrated Product, Organization and Process
design
John Kunz
The big idea:Integrated Product, Organization and Process design can support, at least design, fabrication, assembly and use of new products
Rate
Baseline
($K) Change
Year-1
(K$)
Revenue 100,000 2% 102,000
Cost of contracted work 85% 85,000 -2.0% 84,660
Cost of self-performed work 10% 10,000 2.0% 12,240
Gross Margin 5,000 5,100
Sales, G&A 2% 2,000 2,040
IT investment 70
Amortized costs of IT/yr 33% 23
Net income 3,000 3,037
Time to payback (years) 1.9
Net Income change (%) 1.2
*05-07-01
Finish
Final Program
Confirmation with
Pharmacology
Final Program
confirmation with LAR
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI
TechnicalAEI Core and
SRG LabHDCCO Costing
SRG
TechnicalKPFF
AEI Core
and TechHDCCO Core
Code Rev
ConsultantSolvent Tarter
H Block Crew
& Tech
SRG
Landscape
Tele Data
DesignCode Rev
Furniture
37.
*Reprogram
B#15 Shafts
34. *Finalize
Pharmacology
Program
33. *Finalize
LAR Program
32. *Finalize
Bio-Organic
Chemistry
Program
35. *Finalize
Protein Chemistry
Program 20. *Determine Scope of
package D including vivarium
changes
45. *Complete all
Basement/LAR Drawings
41. *Reprogram
bookends B#13 and
B#15
36. *Analyze
structural impacts
12. *Complete UG
utiliites
25. *Do Central Plant
design changes
19. *Determine vertical
utilities
22. *Complete catwalk drawings
52. Finalize landscape
26. *Finalize B#13 and
B#15
Exiting/architecural H
occupancy concept
*Lab and
vivarium
Programming
Complete
27. *Finalize B#13,
15 Shaft Size &
MEP Room
Locations
31.* AEI &
SRG
Determine
Design $/Time
Impact of
Change
23. *Reprogram
B#13 and B#15
Exterior Architecture
Bookend
Programming
Accepted by Genentech
Notice to proceed on
structural changes
Architect
program/MEP
oncepts
Established
By Design
Team
29. *Document
lab plan
1. *Redesign main MEP
distribution systems
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
5. *Finalize lab & Equipment
plans
Task 29
Task 28
30. *Approve
Change to
Design
Contract
21. *Prepare Plan Views for
Review of Concept w/City
39. *Finalize MEP
distribution and
section
Task4 Task22
Review 80%
documents
48. *Develop exiting
plan
49. Develop
reflected ceiling
plan
Turnover
reflected
ceiling plan to
AEI
Detailed Design 80 PC
Complete
3. Complete Tele Data Design
42. *Develop
Execution
Strategy
44. *Complete
B#14 Officing
Planning
18. *Detailed Lab
Program
Documentation
47. *Develop lab
DD plan
28. *Determine
segregation of lab
and tech space
G accept lab
equipment matrix
*Package B structural
modifications (CCD3A)
13. *Code Consultants
Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost
of Program
Review skin changes w/db team
Lab Planning Program
Meetings with
Pharmacology
Lab planning Program Meeting with Protein
Chemistry
BMS Controls Meetings
(Weekly)
Lab Planning Program meeting with Bio
Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing
Meetings
Genentech 80% Detailed Design
Review
Final Program
Confirmation with Officing
Weekly
Coordination
Meeting
Lab Planning Program
Meetings with Directors
50. Designate size, location of
13 MEP, teledata rooms
54. KPFF design
stairs for 13/1438. *SRG
Reprogram 13/14
interface, exiting,
stairs
43. *Changes in Steel
Forwarded to Steel
Detailers
46. *RA Furnture
Concept Complete
MEP, Teledata room design
*Design Budget &
Schedule for Changes
Approved
*Notice to proceed
with detailed design
24. *Complete B13,4 H
block occupancy
requirements on MEP
systems
17. *Risick
reprogram solvent
distribution and waste
Issue 80%
MEP CDs
(20) Incorporate
80% MEP review
comments
(19) Genentech review
80% drawings
53. Incorporate
comments, complete
Architectural detail
2. Initial redesign MEP branch
lateral distribution
G accept
13/14
Interface
*City Accept
exiting
*Package C
skin
modifications
55. KPFF design
stairs for 15/14
40. *SRG
Reprogram 15/14
interface, exiting,
stairs
B13 MEP HVAC,
conduit, piping mains
completed
MEP 80% Review
comments
incorporated
Package D and UG
addendum issued:
underground utilities,
vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
(3) *AEI design MEP
HVAC, Conduit &
piping mains B13
16. *HDCCO Determine
Schedule Impact
City Approval of
Alternate Means
for Program
8. Review Alternate
Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details,
update specs and p&ID's
(8) *Revise
MEP loads, MEP
Equipment
schedules
finalized
(13,15,16) MEP specs, P&ID's,
control sequences
Work Process
Meetings
(6) Coord B13 MEP
floor section
4. complete all Interior Architcture
*Cal OSHA Recommend
Determination of LFFH
51. Designate size, location
of 14 MEP, teledata rooms G accept
15/14
Interface
*Accept project
scope:budget
by Genentech
*City Approval of
H Concept
*Exterior
Programming
Accepted by Genentech
*Turnover lab and
vivarium DD plan
to AEI
Integrated Concurrent Engineering (ICE)
Product Modeling(BIM+)
Process ModelingCurrent State Process, T5 Rebar Detailing for Construction
Desig
nM
anufa
ctu
reE
ngin
eering
Release CAD
dwg, rebar
schedule (*.CSF)
in Documentum
Document
control delay
(1 week)
Preliminary
designGA drawings
Refine RC details
and concept for
buildability/
detailing
Use model to
develop and
communicate
methods
Prepare RC detail
drawings
(drafting)
Check and
coordinate detail
drawings
CAD check
(1d/dwg)
Check against
engineering calcs
(.5d /dwg)
Independent final
check & sign off
(2 weeks)
Building control
check & sign off
(BAA, time?)
Release paper P4
dwgs & bar
bending
schedules
Rebar factory
starts bending
Pre-assembly
Ship to site
Draft spec
Comment on
spec
Update spec Release spec
Model rebar
component (Use
digital
Prototyping tool)
Issue and resolve
TQ’s (Technical
Queries)
AutoCAD CAD RC IDEAS Arma +
Design input/
changes
Technology:
Detailed
engineering
design
information
Site assembly
Preliminary drafting
2 weeks
Back drafting
1 week
Checking
2 weeks
Document control
1 weekTimeline:
NOTE: Drawings are batched into sections-
then subdivided into building components.
Each component is an assembly package,
e.g. rail box floor, wall, etc.
The number of drawing sheets per building
component vary depending on the work. On
ART for example, each component may
consist of 8-15 GA drawings and 8-15 RC
detail drawings.
All of the GA drawings are complete -
pend ing changes f rom other des ign
disciplines
NOTE: Design changes
during detailing (from:
architecture, baggage,
s y s t e m s , e t c . ) a r e
upsetting RC drawing
development.
Other / None/
Unknown
Preliminary RC
detailing
Iterative
process
Consists of:
engineering
calculations,
sketches, etc.
Most of the checking
process is done
concurrently with RC
detail development.
BAA building control
accepts the opinion
of the independent
design check - and
does not perform a
check of its own
Assem
bly
Existing Process - 6 weeks
Client/Business Objectives
Project Objectives
Big Idea: Integrated design of Products, Organizations and
Processes of projects - Virtual Design and Construction (VDC)
Chalmers Integrated Product, Organization and Process Design (C)2015
Organization Modeling
14 July 2015 Chalmers Integrated Product,
Organization and Process Design
3
This week overview
Day Learning goals
Tuesday Theory: VDC, POP/FFB framework, types of models,
ICE, organizational modeling, templates
Practice: ICE session with Templates, Organization-
process model and analysis (SimVision) lab
Thursday Theory: Introduction Organization-process model and
analysis (SimVision),
Practice: Organization modeling lab
14 July 2015 Chalmers Integrated Product, Organization and Process Design 4
The next three weeks we will …
• Do integrated design with VDC of projects by
describing their POP - FFB using ICE and
templates,
• Predict project behavior using a prediction
tool and
• Consider big data analysis of measured
performance…
14 July 2015 Chalmers Integrated Product, Organization and Process Design 6
Chalmers Integrated Product, Organization and
Process Design Agenda: July 14
• Big ideas: Integrated design and analysis;
elements of VDC
• Introductions
• Models: how to recognize and use different
types
• Business goals and objectives
• Course goals (and non-goals)
• Course Organization
• ORID*05-07-01
Finish
Final Program
Confirmation with
Pharmacology
Final Program
confirmation with LAR
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI
TechnicalAEI Core and
SRG LabHDCCO Costing
SRG
TechnicalKPFF
AEI Core
and TechHDCCO Core
Code Rev
ConsultantSolvent Tarter
H Block Crew
& Tech
SRG
Landscape
Tele Data
DesignCode Rev
Furniture
37.
*Reprogram
B#15 Shafts
34. *Finalize
Pharmacology
Program
33. *Finalize
LAR Program
32. *Finalize
Bio-Organic
Chemistry
Program
35. *Finalize
Protein Chemistry
Program 20. *Determine Scope of
package D including vivarium
changes
45. *Complete all
Basement/LAR Drawings
41. *Reprogram
bookends B#13 and
B#15
36. *Analyze
structural impacts
12. *Complete UG
utiliites
25. *Do Central Plant
design changes
19. *Determine vertical
utilities
22. *Complete catwalk drawings
52. Finalize landscape
26. *Finalize B#13 and
B#15
Exiting/architecural H
occupancy concept
*Lab and
vivarium
Programming
Complete
27. *Finalize B#13,
15 Shaft Size &
MEP Room
Locations
31.* AEI &
SRG
Determine
Design $/Time
Impact of
Change
23. *Reprogram
B#13 and B#15
Exterior Architecture
Bookend
Programming
Accepted by Genentech
Notice to proceed on
structural changes
Architect
program/MEP
oncepts
Established
By Design
Team
29. *Document
lab plan
1. *Redesign main MEP
distribution systems
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
5. *Finalize lab & Equipment
plans
Task 29
Task 28
30. *Approve
Change to
Design
Contract
21. *Prepare Plan Views for
Review of Concept w/City
39. *Finalize MEP
distribution and
section
Task4 Task22
Review 80%
documents
48. *Develop exiting
plan
49. Develop
reflected ceiling
plan
Turnover
reflected
ceiling plan to
AEI
Detailed Design 80 PC
Complete
3. Complete Tele Data Design
42. *Develop
Execution
Strategy
44. *Complete
B#14 Officing
Planning
18. *Detailed Lab
Program
Documentation
47. *Develop lab
DD plan
28. *Determine
segregation of lab
and tech space
G accept lab
equipment matrix
*Package B structural
modifications (CCD3A)
13. *Code Consultants
Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost
of Program
Review skin changes w/db team
Lab Planning Program
Meetings with
Pharmacology
Lab planning Program Meeting with Protein
Chemistry
BMS Controls Meetings
(Weekly)
Lab Planning Program meeting with Bio
Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing
Meetings
Genentech 80% Detailed Design
Review
Final Program
Confirmation with Officing
Weekly
Coordination
Meeting
Lab Planning Program
Meetings with Directors
50. Designate size, location of
13 MEP, teledata rooms
54. KPFF design
stairs for 13/1438. *SRG
Reprogram 13/14
interface, exiting,
stairs
43. *Changes in Steel
Forwarded to Steel
Detailers
46. *RA Furnture
Concept Complete
MEP, Teledata room design
*Design Budget &
Schedule for Changes
Approved
*Notice to proceed
with detailed design
24. *Complete B13,4 H
block occupancy
requirements on MEP
systems
17. *Risick
reprogram solvent
distribution and waste
Issue 80%
MEP CDs
(20) Incorporate
80% MEP review
comments
(19) Genentech review
80% drawings
53. Incorporate
comments, complete
Architectural detail
2. Initial redesign MEP branch
lateral distribution
G accept
13/14
Interface
*City Accept
exiting
*Package C
skin
modifications
55. KPFF design
stairs for 15/14
40. *SRG
Reprogram 15/14
interface, exiting,
stairs
B13 MEP HVAC,
conduit, piping mains
completed
MEP 80% Review
comments
incorporated
Package D and UG
addendum issued:
underground utilities,
vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
(3) *AEI design MEP
HVAC, Conduit &
piping mains B13
16. *HDCCO Determine
Schedule Impact
City Approval of
Alternate Means
for Program
8. Review Alternate
Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details,
update specs and p&ID's
(8) *Revise
MEP loads, MEP
Equipment
schedules
finalized
(13,15,16) MEP specs, P&ID's,
control sequences
Work Process
Meetings
(6) Coord B13 MEP
floor section
4. complete all Interior Architcture
*Cal OSHA Recommend
Determination of LFFH
51. Designate size, location
of 14 MEP, teledata rooms G accept
15/14
Interface
*Accept project
scope:budget
by Genentech
*City Approval of
H Concept
*Exterior
Programming
Accepted by Genentech
*Turnover lab and
vivarium DD plan
to AEI
Object AttributeRequirement
Relationship Requirement
Predicte
d value
Observed
value -2 -1 0 1 2
Product
Product Scope
Product Scope . Building Spaces includes -
Project Goals
Project Goal . Capacity (people) >= 60 - ?o
Project Goal . Cost (M$) = 70 - ?o
Building
Goal . Net Energy Use (K-
BTU/ft2) <= 250 - ?o
Building
Goal . Quality conformance
(%) >= 12 - ?o
Organization Scope
Organization Scope . Actors includes - -
Organization Goals
Organization Goal . Predicted . Cost (K$) - <= - ?o
Organization
Goal . Observed . Response
Latency (days) 3 <= - ?o
Organization
Goal . Predicted . Peak
Backlog (days) 3 <= - ?o
Organization
Goal . Predicted . rework
(FTE-days) - <= - ?o
Process
Process Goals
Process Goal . Peak Quality Risk < 0.50 - -
Process
Goal . Schedule Growth
(months) < - ?o
Process Goal . Completion Date <= 1/1/09 - ?o
Process Task . Action: Object
Process Task . Design: Actor Actor that designs
Process Task . Predict: Actor Actor that predicts
Process Task . Assess: Actor Actor that assesses
Process Task . Build: Actor Actor that builds
Function Product Behavior
Organization
Qualitative Threshhold values
Introductions
Briefly, please share
• Name
• Field of study
• One personal goal for this class
14 July 2015 Chalmers Integrated Product, Organization and Process Design 7
Chalmers
Integrat
8
Chalmers
Integrat
9
Process modeling in practice:
Product and process models are linked
10Chalmers Integrated Product, Organization and Process Design (C)2015
Process modeling in practice:
Product and process models that are linked - Benefits
• QTO from 80 to 4 hours
• Estimate accuracy up 20%
• Tender duration from 5 to 2 days
11Chalmers Integrated Product, Organization and Process Design (C)2015
“You will not find any paper drawings on this site.”
Mark, General Superintendent for DPR on the $750M
Mission Bay Hospital in San Francisco, October 4, 2013
12Chalmers Integrated Product, Organization and Process Design (C)2015
Product models in the field
13Chalmers Integrated Product, Organization and Process Design (C)2015
14 July 2015 Chalmers Integrated Product, Organization and Process Design 14
Traditional product models
+: Work in practice
: Ambiguities to
stakeholders
: computer analysis ...?
– Show value to owner
– List components
– Estimate cost
– Plan construction
– Identify interferences
14 July 2015 Chalmers Integrated Product, Organization and Process Design 15
Models
• Physical
• Statistical
• Mathematical
Symbolic
Graphic
*05-07-01
Finish
Final Program
Confirmation with
Pharmacology
Final Program
confirmation with LAR
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI
TechnicalAEI Core and
SRG LabHDCCO Costing
SRG
TechnicalKPFF
AEI Core
and TechHDCCO Core
Code Rev
ConsultantSolvent Tarter
H Block Crew
& Tech
SRG
Landscape
Tele Data
DesignCode Rev
Furniture
37.
*Reprogram
B#15 Shafts
34. *Finalize
Pharmacology
Program
33. *Finalize
LAR Program
32. *Finalize
Bio-Organic
Chemistry
Program
35. *Finalize
Protein Chemistry
Program 20. *Determine Scope of
package D including vivarium
changes
45. *Complete all
Basement/LAR Drawings
41. *Reprogram
bookends B#13 and
B#15
36. *Analyze
structural impacts
12. *Complete UG
utiliites
25. *Do Central Plant
design changes
19. *Determine vertical
utilities
22. *Complete catwalk drawings
52. Finalize landscape
26. *Finalize B#13 and
B#15
Exiting/architecural H
occupancy concept
*Lab and
vivarium
Programming
Complete
27. *Finalize B#13,
15 Shaft Size &
MEP Room
Locations
31.* AEI &
SRG
Determine
Design $/Time
Impact of
Change
23. *Reprogram
B#13 and B#15
Exterior Architecture
Bookend
Programming
Accepted by Genentech
Notice to proceed on
structural changes
Architect
program/MEP
oncepts
Established
By Design
Team
29. *Document
lab plan
1. *Redesign main MEP
distribution systems
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
5. *Finalize lab & Equipment
plans
Task 29
Task 28
30. *Approve
Change to
Design
Contract
21. *Prepare Plan Views for
Review of Concept w/City
39. *Finalize MEP
distribution and
section
Task4 Task22
Review 80%
documents
48. *Develop exiting
plan
49. Develop
reflected ceiling
plan
Turnover
reflected
ceiling plan to
AEI
Detailed Design 80 PC
Complete
3. Complete Tele Data Design
42. *Develop
Execution
Strategy
44. *Complete
B#14 Officing
Planning
18. *Detailed Lab
Program
Documentation
47. *Develop lab
DD plan
28. *Determine
segregation of lab
and tech space
G accept lab
equipment matrix
*Package B structural
modifications (CCD3A)
13. *Code Consultants
Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost
of Program
Review skin changes w/db team
Lab Planning Program
Meetings with
Pharmacology
Lab planning Program Meeting with Protein
Chemistry
BMS Controls Meetings
(Weekly)
Lab Planning Program meeting with Bio
Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing
Meetings
Genentech 80% Detailed Design
Review
Final Program
Confirmation with Officing
Weekly
Coordination
Meeting
Lab Planning Program
Meetings with Directors
50. Designate size, location of
13 MEP, teledata rooms
54. KPFF design
stairs for 13/1438. *SRG
Reprogram 13/14
interface, exiting,
stairs
43. *Changes in Steel
Forwarded to Steel
Detailers
46. *RA Furnture
Concept Complete
MEP, Teledata room design
*Design Budget &
Schedule for Changes
Approved
*Notice to proceed
with detailed design
24. *Complete B13,4 H
block occupancy
requirements on MEP
systems
17. *Risick
reprogram solvent
distribution and waste
Issue 80%
MEP CDs
(20) Incorporate
80% MEP review
comments
(19) Genentech review
80% drawings
53. Incorporate
comments, complete
Architectural detail
2. Initial redesign MEP branch
lateral distribution
G accept
13/14
Interface
*City Accept
exiting
*Package C
skin
modifications
55. KPFF design
stairs for 15/14
40. *SRG
Reprogram 15/14
interface, exiting,
stairs
B13 MEP HVAC,
conduit, piping mains
completed
MEP 80% Review
comments
incorporated
Package D and UG
addendum issued:
underground utilities,
vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
(3) *AEI design MEP
HVAC, Conduit &
piping mains B13
16. *HDCCO Determine
Schedule Impact
City Approval of
Alternate Means
for Program
8. Review Alternate
Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details,
update specs and p&ID's
(8) *Revise
MEP loads, MEP
Equipment
schedules
finalized
(13,15,16) MEP specs, P&ID's,
control sequences
Work Process
Meetings
(6) Coord B13 MEP
floor section
4. complete all Interior Architcture
*Cal OSHA Recommend
Determination of LFFH
51. Designate size, location
of 14 MEP, teledata rooms G accept
15/14
Interface
*Accept project
scope:budget
by Genentech
*City Approval of
H Concept
*Exterior
Programming
Accepted by Genentech
*Turnover lab and
vivarium DD plan
to AEI
Object AttributeRequirement
Relationship Requirement
Predicte
d value
Observed
value -2 -1 0 1 2
Product
Product Scope
Product Scope . Building Spaces includes -
Project Goals
Project Goal . Capacity (people) >= 60 - ?o
Project Goal . Cost (M$) = 70 - ?o
Building
Goal . Net Energy Use (K-
BTU/ft2) <= 250 - ?o
Building
Goal . Quality conformance
(%) >= 12 - ?o
Organization Scope
Organization Scope . Actors includes - -
Organization Goals
Organization Goal . Predicted . Cost (K$) - <= - ?o
Organization
Goal . Observed . Response
Latency (days) 3 <= - ?o
Organization
Goal . Predicted . Peak
Backlog (days) 3 <= - ?o
Organization
Goal . Predicted . rework
(FTE-days) - <= - ?o
Process
Process Goals
Process Goal . Peak Quality Risk < 0.50 - -
Process
Goal . Schedule Growth
(months) < - ?o
Process Goal . Completion Date <= 1/1/09 - ?o
Process Task . Action: Object
Process Task . Design: Actor Actor that designs
Process Task . Predict: Actor Actor that predicts
Process Task . Assess: Actor Actor that assesses
Process Task . Build: Actor Actor that builds
Function Product Behavior
Organization
Qualitative Threshhold values
14 July 2015 16
Virtual Design and Construction: Fundamental method of this integrated design and analysis class
• Use of integrated multi-disciplinary computer-based performance models and analyses of design–construction projects– Product (building, device, service)
– Organization
– Work Process
• to support (explicit, public) business
objectives– Describe: Visualize and describe project
– Explain reasons for designs and choices
– Evaluate choices
– Predict project performance
*05-07-01
Finish
Final Program
Confirmation with
Pharmacology
Final Program
confirmation with LAR
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI
TechnicalAEI Core and
SRG LabHDCCO Costing
SRG
TechnicalKPFF
AEI Core
and TechHDCCO Core
Code Rev
ConsultantSolvent Tarter
H Block Crew
& Tech
SRG
Landscape
Tele Data
DesignCode Rev
Furniture
37.
*Reprogram
B#15 Shafts
34. *Finalize
Pharmacology
Program
33. *Finalize
LAR Program
32. *Finalize
Bio-Organic
Chemistry
Program
35. *Finalize
Protein Chemistry
Program 20. *Determine Scope of
package D including vivarium
changes
45. *Complete all
Basement/LAR Drawings
41. *Reprogram
bookends B#13 and
B#15
36. *Analyze
structural impacts
12. *Complete UG
utiliites
25. *Do Central Plant
design changes
19. *Determine vertical
utilities
22. *Complete catwalk drawings
52. Finalize landscape
26. *Finalize B#13 and
B#15
Exiting/architecural H
occupancy concept
*Lab and
vivarium
Programming
Complete
27. *Finalize B#13,
15 Shaft Size &
MEP Room
Locations
31.* AEI &
SRG
Determine
Design $/Time
Impact of
Change
23. *Reprogram
B#13 and B#15
Exterior Architecture
Bookend
Programming
Accepted by Genentech
Notice to proceed on
structural changes
Architect
program/MEP
oncepts
Established
By Design
Team
29. *Document
lab plan
1. *Redesign main MEP
distribution systems
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
5. *Finalize lab & Equipment
plans
Task 29
Task 28
30. *Approve
Change to
Design
Contract
21. *Prepare Plan Views for
Review of Concept w/City
39. *Finalize MEP
distribution and
section
Task4 Task22
Review 80%
documents
48. *Develop exiting
plan
49. Develop
reflected ceiling
plan
Turnover
reflected
ceiling plan to
AEI
Detailed Design 80 PC
Complete
3. Complete Tele Data Design
42. *Develop
Execution
Strategy
44. *Complete
B#14 Officing
Planning
18. *Detailed Lab
Program
Documentation
47. *Develop lab
DD plan
28. *Determine
segregation of lab
and tech space
G accept lab
equipment matrix
*Package B structural
modifications (CCD3A)
13. *Code Consultants
Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost
of Program
Review skin changes w/db team
Lab Planning Program
Meetings with
Pharmacology
Lab planning Program Meeting with Protein
Chemistry
BMS Controls Meetings
(Weekly)
Lab Planning Program meeting with Bio
Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing
Meetings
Genentech 80% Detailed Design
Review
Final Program
Confirmation with Officing
Weekly
Coordination
Meeting
Lab Planning Program
Meetings with Directors
50. Designate size, location of
13 MEP, teledata rooms
54. KPFF design
stairs for 13/1438. *SRG
Reprogram 13/14
interface, exiting,
stairs
43. *Changes in Steel
Forwarded to Steel
Detailers
46. *RA Furnture
Concept Complete
MEP, Teledata room design
*Design Budget &
Schedule for Changes
Approved
*Notice to proceed
with detailed design
24. *Complete B13,4 H
block occupancy
requirements on MEP
systems
17. *Risick
reprogram solvent
distribution and waste
Issue 80%
MEP CDs
(20) Incorporate
80% MEP review
comments
(19) Genentech review
80% drawings
53. Incorporate
comments, complete
Architectural detail
2. Initial redesign MEP branch
lateral distribution
G accept
13/14
Interface
*City Accept
exiting
*Package C
skin
modifications
55. KPFF design
stairs for 15/14
40. *SRG
Reprogram 15/14
interface, exiting,
stairs
B13 MEP HVAC,
conduit, piping mains
completed
MEP 80% Review
comments
incorporated
Package D and UG
addendum issued:
underground utilities,
vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
(3) *AEI design MEP
HVAC, Conduit &
piping mains B13
16. *HDCCO Determine
Schedule Impact
City Approval of
Alternate Means
for Program
8. Review Alternate
Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details,
update specs and p&ID's
(8) *Revise
MEP loads, MEP
Equipment
schedules
finalized
(13,15,16) MEP specs, P&ID's,
control sequences
Work Process
Meetings
(6) Coord B13 MEP
floor section
4. complete all Interior Architcture
*Cal OSHA Recommend
Determination of LFFH
51. Designate size, location
of 14 MEP, teledata rooms G accept
15/14
Interface
*Accept project
scope:budget
by Genentech
*City Approval of
H Concept
*Exterior
Programming
Accepted by Genentech
*Turnover lab and
vivarium DD plan
to AEI
AEC IT investment by General Contractor
Rate
Baseline
($M) Change
Revenue 100,000 22%
Cost of work 85% 85,000 -2.0%
CM, Design, GC fees 10% 10,000 2.0%
Gross Margin 5,000
Sales, G&A 2% 2,000
IT investment 1,000
Amortized costs of IT/yr 33%
Net income 3,000
Time to payback (years)
Year-1
122,000
101,260
14,640
6,100
2,440
333
3,327
3.1
3-
year
payb
Object AttributeRequirement
Relationship Requirement
Predicte
d value
Observed
value -2 -1 0 1 2
Product
Product Scope
Product Scope . Building Spaces includes -
Project Goals
Project Goal . Capacity (people) >= 60 - ?o
Project Goal . Cost (M$) = 70 - ?o
Building
Goal . Net Energy Use (K-
BTU/ft2) <= 250 - ?o
Building
Goal . Quality conformance
(%) >= 12 - ?o
Organization Scope
Organization Scope . Actors includes - -
Organization Goals
Organization Goal . Predicted . Cost (K$) - <= - ?o
Organization
Goal . Observed . Response
Latency (days) 3 <= - ?o
Organization
Goal . Predicted . Peak
Backlog (days) 3 <= - ?o
Organization
Goal . Predicted . rework
(FTE-days) - <= - ?o
Process
Process Goals
Process Goal . Peak Quality Risk < 0.50 - -
Process
Goal . Schedule Growth
(months) < - ?o
Process Goal . Completion Date <= 1/1/09 - ?o
Process Task . Action: Object
Process Task . Design: Actor Actor that designs
Process Task . Predict: Actor Actor that predicts
Process Task . Assess: Actor Actor that assesses
Process Task . Build: Actor Actor that builds
Function Product Behavior
Organization
Qualitative Threshhold values
Chalmers Integrated Product,
Organization and Process Design
14 July 2015 Chalmers Integrated Product, Organization and Process Design 18
Integrated design and analysis Big Ideas
• Build VDC project models early and often, before committing large money or time
• What– Objectives, Designs and Behaviors of Product, process,
organization
• How: – Detailed: to show the product, process, organization entities that
use > 10% of project time, money
– Virtual: in the computer
– Visual: multi-discipline, multi-view, for multiple stakeholders
– Integrated: relating the product, organization and process
– Objective-based: set and track explicit public objectives
19
Plus-Delta of Civil Engineering
• Provides fixed physical
assets and wealth
• High global demand for
infrastructure and
housing
• Opportunity to impact
global climate challenge
significantly
20
Plus-Delta of Civil Engineering
• Provides fixed physical
assets and wealth
• High global demand for
infrastructure and
housing
• Opportunity to impact
global climate challenge
significantly
• Low productivity
compete with other ways
to spend $
• High energy use and
rising energy costs
• Structural reliability <<
societal need (Chile)
Persson, Sustainable City of
Tomorrow
Guilllermo Gomez, PUChile
US Department of Commerce,
compiled by P. Teicholz
21
An example - Malmo, Sweden:
The best example of
sustainable development in
the world:
– Best design and analysis
methods (~2000)
– Best construction
methods
– Project provides some
good data on
performance vs.
predicted
But
• Energy: 20 of 20 buildings used more than predicted
– Prefabrication needed for intended energy performance
• Land: much greater density needed even for next project
– Development model did not last even a decade
• Data granularity: so coarse that improvement difficult to plan
• Human capital: people on project mostly lost to next phase
CEE 243 March 29 22
Malmo, Sweden: Actual energy
much worse than Predicted
23
An example - Malmo, Sweden:
Message: measure performance
The best example of
sustainable development in
the world:
– Best design and analysis
methods (~2000)
– Best construction
methods
– Project provides some
good data on
performance vs.
predicted
But
• Energy: 20 of 20 buildings used more than predicted
– Prefabrication needed for intended energy performance
• Land: much greater density needed even for next project
– Development model did not last even a decade
• Data granularity: so coarse that improvement difficult to plan
• Human capital: people on project mostly lost to next phase
Fundamental issue: outcome reliability
• Structures (Chile, post-earthquake) -- good:
– ~500K/~5M homes damaged or destroyed: <2σ
– ~4 joint failures /~100 in (collapsed) buildings: 2σ
– 4/~10,000 post-1985 buildings collapsed in major
damage area: >3σ
• Energy – not good:
– 20/20 buildings used more energy than predicted –
Malmo, Sweden, 2001 (range 70 – 340% greater)
– 121 LEED buildings use 30% more energy per
square foot than average for U.S. buildings
• Neither structure nor energy performance meets
societal needs
24
Fundamental issue: process reliability
• Structures (Chile, post-earthquake)
– ~4 joint failures /~100 in (collapsed) buildings: 2σ
• Sources of failure - infrequent but important problems:
quality of joint construction, material composition, soft story
design, asymmetrical designs
• Energy:
– ↑ prediction variability:
• ↑ Inter-tool with same designer
• ↑ Inter-consultant with same tool
– ↑ component performance variability, e.g., infiltration from
leaky building joints (Malmo)
• Structure and energy performance:
– Good (historically), but
– Neither meets societal needs need to manage risk25
27
(Multiple) Predictable performance objectives:
*Changed in 2010
Controllable Process
[Conformance to plans]
Outcome
[Performance]
Product, organization,
process designs
Latency: mean <= 1; 95% within 2
working days
Safety: 0 lost hours
Coordination activity:
planned, explicit, public,
informed > 90%
Field-generated Requests for
Information: 0
Schedule: 95% on-time
performance
Facility managed
Scope: 100% of items
with > 2% of value, time,
cost or energy
Rework volume: 0 (for field
construction work); objective = 10-
20% (virtual work)
Cost: >= 95% of
budgeted items within 2%
of budgeted cost
Prediction basis: > 80%
of predictions founded
*Function (quality) conformance
(%): >= 99%
Delivered Scope: 100%
satisfaction
Design versions: 2 or
more >= 80%
Schedule conformance (%): >=
80%
*Sustainability: >75%
better energy, water,
materials, than 2002,
profitably
Staff trained in VDC: >=
4/project
Cost conformance (%): >= 95%
14 July 2015 Chalmers Integrated Product, Organization and Process Design 28
Wasted human, technical, and biological resources
Photos: Courtesy SPS
Source: http://mainegov-
images.informe.org/spo/recycle/focus/midmaine/landfill.jpg
14 July 2015 Chalmers Integrated Product, Organization and Process Design 29
Integrated design and analysis – using VDC –
provides
Integrating theoretical framework to
• Describe functional intent and designs
• Describe and predict engineering behaviors
• Systematically manage projects and the
business using the predictions and observed
data, to
• Achieve measurable business objectives
• Address reliability
VDC model content:VDC templates help make managerial levers visible to all
14 July 2015 Chalmers Integrated Product, Organization and Process Design 30
• Elements of a project that can and must be managed:
– Product
– Organization
– Process (design + construction)
• Views of each element that must be managed– Functions
• Program Function, Schedule, Cost, Sustainability, ….
– Form (Scope) -- design choices for project elements
• Physical, organizational, process task elements
– Behaviors (predicted, observed)
• Quality (Functional performance), Cost, Schedule, Safety
14 July 2015 Chalmers Integrated Product, Organization and Process Design 31
In-class exercise - Tuesday
For a new-generation smart phone app, sketch and annotateto show:
• Product
– Functions: product design intent, to include
• Functions – things the phone does
• User interface (UI)
• Additional services
– Design forms: designed scope, e.g., buttons, …
– Behaviors: observable (or estimated) performance, e.g.,
• Cost, schedule, quality, e.g., designed buttons = actual = 3
• Organization: teams to design, build, test, including functions, form (names) of each, 2-3 behaviors
• Process: tasks to design, build, test
14 July 2015 Chalmers Integrated Product, Organization and Process Design 32
In-class exercise - Tuesday
• For a new-generation smart phone app,
sketch and annotate to show:
Function (Intent) Form (Design) Behavior: Name, Target/predicted values
Product
Organization
Process
14 July 2015 Chalmers Integrated Product, Organization and Process Design 33
Content of POP models
• For the most important or highest risks, check that:
– Each function has >=1 enabling forms
– Each product function has >=1 enabling organization
functions
– Each product form has >=1 enabling organization forms (i.e.,
teams or individuals)
– Product and Organization behaviors define name and target
values of measures of project success
– Process behaviors define name and target values of
frequent (weekly) measures of project success
– Each process task has a responsible organizational actor
14 July 2015 Chalmers Integrated Product, Organization and Process Design 34
In-class exercise - Tuesday
Deliverables:
• Sketches: product, organization, process
• Templates:
– Deliverables of a development project, from Product segment of Commitments template
14 July 2015 Chalmers Integrated Product, Organization and Process Design 35
In-class exercise - Tuesday
Deliverables:
• Sketches: product, organization, process
• Templates:
– Deliverables
– Metrics and Assessed performance templates
14 July 2015 Chalmers Integrated Product, Organization and Process Design 36
In-class exercise - Tuesday
Deliverables:
• Sketches: product, organization, process
• Templates:
– Deliverables
– Metrics and Assessed performance
– Controllable factors
Factor Type Factor Range of options Constraints Action(s) for this week
Action Taken?
(Yes, Partial,
No)
Product Detail of water line in 3DFeatures of size from 1 mm to >
1mNone important Model features size > 20 mm
Product Location of in-water equipmentAdjust both equipment location,
water width/depth profile Size of equipment model equipment located in water this week
Organization Number of BIM authors <1 – many FTEsAdjust author count up and down
slowlyBudget BIM author work
Organization Number of BIM reviewers Author team – hundreds Size of BIM review facility Budget BIM reviewer work
Process Construction duration 6 months to 2 yearsNeed to plan prefabrication early
to shorten construction periodGet owner preference
Process Size of weekly pre-con tasksOne task for whole team/week to
all tasks with > 0.5 FTE-day
Availability of staff to plan,
manage schedule
Build short-interval production plan and
schedule at feasible LOD
Controllable Factors
14 July 2015 Chalmers Integrated Product, Organization and Process Design 37
In-class exercise - Tuesday
Deliverables:
• Sketches: product, organization, process
• Templates:
– Deliverables
– Metrics and Assessed performance
– Controllable factors
– Risks and Next Steps
14 July 2015 Chalmers Integrated Product, Organization and Process Design 38
In-class exercise - Tuesday
Deliverables:• Sketches: product, organization, process
• Templates:
– Deliverables
– Metrics and Assessed performance
– Controllable factors
– Risks and Next Steps
Process:
• Groups of ~3
• 20 minutes for ICE session x 2
• 10 minutes for presentations, discussion after each session
Tuesday afternoon
• ICE session: project definition using
templates
14 July 2015 Chalmers Integrated Product, Organization and Process Design 39
14 July 2015 Chalmers Integrated Product, Organization and Process Design 41
Business uses of VDC models
• Plan – specify project goals, obectives and scope of VDC models and analyses
• Do – create project descriptions (templates) and product, organization and process models
• Check – compare and evaluate measured/predicted performance vs targets – for alternative functions and design forms;
• Act – perform the next steps for work that is OK; revise plans or models for work that is not OK
Class overview:http://www.stanford.edu/~kunz/Chalmers/
• Agenda
14 July 2015 42Chalmers Integrated Product, Organization and Process Design
14 July 2015 Chalmers Integrated Product, Organization and Process Design 43
Course Goals
• Build and interpret simple descriptive models of the Product,
Organization and Process (POP) of projects using Excel-based
templates;
• Build and interpret organization and process models using the
SimVision tool;
• Use the method of Integrated Concurrent Engineering (ICE);
• Discuss use of "big data" – interpret the status of large volumes of
operational energy system data;
• Create checklists to assure initial readiness for and final
completeness of tasks that high uncertainty and for which the
knowledge required exceeds that of any individual;
• Create a business plan to obtain significant funding for an enterprise
of personal interest.
14 July 2015 Chalmers Integrated Product, Organization and Process Design 44
Course Non-goals
• Study every system ever built
• Study every visualization/AI/design/planning
technology
• Development expertise
• Preparation for technology research
• Survey understanding only
• Excessive work
Course organization
• Instructor:
– John Kunz ([email protected])
• Office Hours: after class
• Class Schedule: 11:00 – 1:00 and 2:00 to 4:00 on
Tuesdays and Thursdays
• Classes will meet in the CIFE lab, Room 292, Y2E2, Please
work in groups of about three for ICE sessions and to prepare
submissions.
• Web site: http://www.stanford.edu/~kunz/Chalmers
14 July 2015 Chalmers Integrated Product, Organization and Process Design 45
Details
• Dinner in Palo Alto: Tuesday or Thursday next week?
• SimVision app for your laptop before Thursday class
14 July 2015 Chalmers Integrated Product, Organization and Process Design 46
ORID +/∆ Analysis
14 July 2015 Chalmers Integrated Product, Organization and Process Design 47
Level of Questions
Purpose Questions to Answer
OObjective
Level
To examine the data To identify factual
information
What do you see? What factual statements can
you make based on the data?
RReflective
Level
To encourage connections To encourage free flow of
ideas and imagination
What surprised you? What encouraged you? What discouraged you? How does this make you feel?
IInterpretive
Level
To identify patterns and determine their significance or meaning
To articulate underlying insights
What does the data tell us? What are insights for you? What is the good news? What are limits? What else is there to learn?
DDecisional
Level
To propose next steps To develop an action plan To make decisions To experience “coming
together”
What are next steps? What decisions can we make? What is our action plan for
moving forward?
ORID +/∆: Focused Conversation and Analysis
Objective
What do you
recall seeing?
Reflective
Positive
What do you
feel positive
about?
Reflective
Negative
What do you
find negative?
Interpretive
What sense do
you make of it?
Decisional
What
agreements
can be made
now?
(c) 2010 48
14 July 2015 Chalmers Integrated Product, Organization and Process Design 49
Product design forms: 3D drawing
14 July 2015 Chalmers Integrated Product, Organization and Process Design 50
Product design forms: Object-Oriented 3D BIM
Modeled objects:
• Walls
• Floors
• Windows
• Doors
• Columns
Content of POP form
model
14 July 2015 Chalmers Integrated Product, Organization and Process Design 51
Organization, Process Models
Model (SV)
• Organization
• (Design) work process
Simulation behavior
predictions:
• Gantt chart
• Risks
*05-07-01
Finish
Final Program
Confirmation with
Pharmacology
Final Program
confirmation with LAR
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI
TechnicalAEI Core and
SRG LabHDCCO Costing
SRG
TechnicalKPFF
AEI Core
and TechHDCCO Core
Code Rev
ConsultantSolvent Tarter
H Block Crew
& Tech
SRG
Landscape
Tele Data
DesignCode Rev
Furniture
37.
*Reprogram
B#15 Shafts
34. *Finalize
Pharmacology
Program
33. *Finalize
LAR Program
32. *Finalize
Bio-Organic
Chemistry
Program
35. *Finalize
Protein Chemistry
Program 20. *Determine Scope of
package D including vivarium
changes
45. *Complete all
Basement/LAR Drawings
41. *Reprogram
bookends B#13 and
B#15
36. *Analyze
structural impacts
12. *Complete UG
utiliites
25. *Do Central Plant
design changes
19. *Determine vertical
utilities
22. *Complete catwalk drawings
52. Finalize landscape
26. *Finalize B#13 and
B#15
Exiting/architecural H
occupancy concept
*Lab and
vivarium
Programming
Complete
27. *Finalize B#13,
15 Shaft Size &
MEP Room
Locations
31.* AEI &
SRG
Determine
Design $/Time
Impact of
Change
23. *Reprogram
B#13 and B#15
Exterior Architecture
Bookend
Programming
Accepted by Genentech
Notice to proceed on
structural changes
Architect
program/MEP
oncepts
Established
By Design
Team
29. *Document
lab plan
1. *Redesign main MEP
distribution systems
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
5. *Finalize lab & Equipment
plans
Task 29
Task 28
30. *Approve
Change to
Design
Contract
21. *Prepare Plan Views for
Review of Concept w/City
39. *Finalize MEP
distribution and
section
Task4 Task22
Review 80%
documents
48. *Develop exiting
plan
49. Develop
reflected ceiling
plan
Turnover
reflected
ceiling plan to
AEI
Detailed Design 80 PC
Complete
3. Complete Tele Data Design
42. *Develop
Execution
Strategy
44. *Complete
B#14 Officing
Planning
18. *Detailed Lab
Program
Documentation
47. *Develop lab
DD plan
28. *Determine
segregation of lab
and tech space
G accept lab
equipment matrix
*Package B structural
modifications (CCD3A)
13. *Code Consultants
Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost
of Program
Review skin changes w/db team
Lab Planning Program
Meetings with
Pharmacology
Lab planning Program Meeting with Protein
Chemistry
BMS Controls Meetings
(Weekly)
Lab Planning Program meeting with Bio
Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing
Meetings
Genentech 80% Detailed Design
Review
Final Program
Confirmation with Officing
Weekly
Coordination
Meeting
Lab Planning Program
Meetings with Directors
50. Designate size, location of
13 MEP, teledata rooms
54. KPFF design
stairs for 13/1438. *SRG
Reprogram 13/14
interface, exiting,
stairs
43. *Changes in Steel
Forwarded to Steel
Detailers
46. *RA Furnture
Concept Complete
MEP, Teledata room design
*Design Budget &
Schedule for Changes
Approved
*Notice to proceed
with detailed design
24. *Complete B13,4 H
block occupancy
requirements on MEP
systems
17. *Risick
reprogram solvent
distribution and waste
Issue 80%
MEP CDs
(20) Incorporate
80% MEP review
comments
(19) Genentech review
80% drawings
53. Incorporate
comments, complete
Architectural detail
2. Initial redesign MEP branch
lateral distribution
G accept
13/14
Interface
*City Accept
exiting
*Package C
skin
modifications
55. KPFF design
stairs for 15/14
40. *SRG
Reprogram 15/14
interface, exiting,
stairs
B13 MEP HVAC,
conduit, piping mains
completed
MEP 80% Review
comments
incorporated
Package D and UG
addendum issued:
underground utilities,
vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
(3) *AEI design MEP
HVAC, Conduit &
piping mains B13
16. *HDCCO Determine
Schedule Impact
City Approval of
Alternate Means
for Program
8. Review Alternate
Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details,
update specs and p&ID's
(8) *Revise
MEP loads, MEP
Equipment
schedules
finalized
(13,15,16) MEP specs, P&ID's,
control sequences
Work Process
Meetings
(6) Coord B13 MEP
floor section
4. complete all Interior Architcture
*Cal OSHA Recommend
Determination of LFFH
51. Designate size, location
of 14 MEP, teledata rooms G accept
15/14
Interface
*Accept project
scope:budget
by Genentech
*City Approval of
H Concept
*Exterior
Programming
Accepted by Genentech
*Turnover lab and
vivarium DD plan
to AEI
14 July 2015 Chalmers Integrated Product, Organization and Process Design 52
Integrated Concurrent Engineering (ICE)
Given
• Objective = “extreme collaboration”
(1 week)
• Excellent POP software
• Collocated team
• iRoom
• Good generic POP model
• SD (DD) phase
Performance change
XC
Good
traditio
nal
Latency
(secs)0
20000
40000
60000
Latency (secs)
Duration (days)
XC
Good traditional
0
50
100
150
200
250
300
Duration
Templates and checklists
Templates: standard
representations
• POP model: Function,
Form, Behavior of P, O, P
• Breakdown structures:
– Product
– Organization
– Process
• Task content: object,
action, resources (crew,
equipment)
Checklists: Tasks and OK
that was done well
• Run ICE sessions
• Create POP models
• Process to define project,
build BIM, exchange
data, do analyses (x5)
14 July 2015 Chalmers Integrated Product, Organization and Process Design 53
Example ChecklistStep in detailed
scheduleChecks to make
before start of step
Templates
14 July 2015 Chalmers Integrated Product, Organization and Process Design 55
14 July 2015 Chalmers Integrated Product, Organization and Process Design 56
How we spend time in meetings
DESCRIPTIVE (40%)
•When do we have access to
Area C?
•What wall sections do these
numbers refer to?
•Where are you placing the
crane?
EXPLANATIVE
(20%)
What drives the finish
times for the rides?
PREDICTIVE (10%)
Can we get access to the
lagoon a week earlier?
EVALUATIVE (30%)
Does this milestone
meet contract?
Submission-1: due midnight July 17 (Friday)
Task: describe and analyze your project and organization
design for a pre-defined test case
Submit:
• Template file (group submission)
• ORID analysis on what you learned this week
14 July 2015 Chalmers Integrated Product, Organization and Process Design 57
5 Elements for Successful Implementation
Vision Change+ + + + =Action PlanSkill Incentive Resources
Confusion+ + + =Action PlanSkill Incentive Resources
Vision Anxiety+ + + =Action PlanIncentive Resources
VisionGradual
Change+ + + =Action PlanSkill Resources
Vision Frustration+ + + =Action PlanSkill Incentive
Vision False Start+ + + =Skill Incentive Resources
Vision
Skill
Incentive
Resources
Action Plan
(Adapted from “Demystifying Six Sigma” by Alan Larson)
Chalmers Integrated Product, Organization and Process Design (C)2015
14 July 2015 Chalmers Integrated Product, Organization and Process Design 59
Skills for success
• Good engineer: design, analyze, manage
• Research methods
• Communication
– Written/Oral
– Programming
– Colleagues, sponsors, stakeholders
• Integrated use of quick-response, careful
analysis, reflection
14 July 2015 Chalmers Integrated Product,
Organization and Process Design
60
Speculations: VDC
Symbolic Model • Objectives • Testing • Representation • Reasoning • User Interfaces • Systems Interfaces
Pro
jectP
hase
Discipline
VDC will enable a small number of collaborating stakeholders
to do rapid Multidisciplinary Design and Analysis
Tuesday learning goals
Get basic familiarity with the POP project framework of VDC
• Models and analysis of Product – Organization – Process
(POP) and Function – Form – Behavior (FFB)
• Management methods: ICE, metrics
Understand class organization, opportunities, methods and
expectations
Motivate interest in Integrated Design enabled by VDC
• Opportunities in practice
• Fun, power and job opportunities of models, model-based
analyses
61Chalmers Integrated Product, Organization and Process Design (C)2015
14 July 2015 Chalmers Integrated Product, Organization and Process Design 62
2015?, … 2025?
2015?, … 2016?
What do you have? … What do you want?
14 July 2015 Chalmers Integrated Product,
Organization and Process Design
63
This week overview
Day Learning goals
Tuesday Theory: VDC POP/FFB framework, types of models,
ICE, organizational modeling, templates
Practice: ICE session with Templates, Organization-
process model and analysis (SimVision) lab
Thursday Theory: Introduction Organization-process model and
analysis (SimVision),
Practice: Organization modeling lab
Integrated Product, Organization and Process
design
John Kunz
The big idea:Integrated Product, Organization and Process design can support, at least design, fabrication, assembly and use of new products
Rate
Baseline
($K) Change
Year-1
(K$)
Revenue 100,000 2% 102,000
Cost of contracted work 85% 85,000 -2.0% 84,660
Cost of self-performed work 10% 10,000 2.0% 12,240
Gross Margin 5,000 5,100
Sales, G&A 2% 2,000 2,040
IT investment 70
Amortized costs of IT/yr 33% 23
Net income 3,000 3,037
Time to payback (years) 1.9
Net Income change (%) 1.2
*05-07-01
Finish
Final Program
Confirmation with
Pharmacology
Final Program
confirmation with LAR
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI
TechnicalAEI Core and
SRG LabHDCCO Costing
SRG
TechnicalKPFF
AEI Core
and TechHDCCO Core
Code Rev
ConsultantSolvent Tarter
H Block Crew
& Tech
SRG
Landscape
Tele Data
DesignCode Rev
Furniture
37.
*Reprogram
B#15 Shafts
34. *Finalize
Pharmacology
Program
33. *Finalize
LAR Program
32. *Finalize
Bio-Organic
Chemistry
Program
35. *Finalize
Protein Chemistry
Program 20. *Determine Scope of
package D including vivarium
changes
45. *Complete all
Basement/LAR Drawings
41. *Reprogram
bookends B#13 and
B#15
36. *Analyze
structural impacts
12. *Complete UG
utiliites
25. *Do Central Plant
design changes
19. *Determine vertical
utilities
22. *Complete catwalk drawings
52. Finalize landscape
26. *Finalize B#13 and
B#15
Exiting/architecural H
occupancy concept
*Lab and
vivarium
Programming
Complete
27. *Finalize B#13,
15 Shaft Size &
MEP Room
Locations
31.* AEI &
SRG
Determine
Design $/Time
Impact of
Change
23. *Reprogram
B#13 and B#15
Exterior Architecture
Bookend
Programming
Accepted by Genentech
Notice to proceed on
structural changes
Architect
program/MEP
oncepts
Established
By Design
Team
29. *Document
lab plan
1. *Redesign main MEP
distribution systems
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
5. *Finalize lab & Equipment
plans
Task 29
Task 28
30. *Approve
Change to
Design
Contract
21. *Prepare Plan Views for
Review of Concept w/City
39. *Finalize MEP
distribution and
section
Task4 Task22
Review 80%
documents
48. *Develop exiting
plan
49. Develop
reflected ceiling
plan
Turnover
reflected
ceiling plan to
AEI
Detailed Design 80 PC
Complete
3. Complete Tele Data Design
42. *Develop
Execution
Strategy
44. *Complete
B#14 Officing
Planning
18. *Detailed Lab
Program
Documentation
47. *Develop lab
DD plan
28. *Determine
segregation of lab
and tech space
G accept lab
equipment matrix
*Package B structural
modifications (CCD3A)
13. *Code Consultants
Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost
of Program
Review skin changes w/db team
Lab Planning Program
Meetings with
Pharmacology
Lab planning Program Meeting with Protein
Chemistry
BMS Controls Meetings
(Weekly)
Lab Planning Program meeting with Bio
Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing
Meetings
Genentech 80% Detailed Design
Review
Final Program
Confirmation with Officing
Weekly
Coordination
Meeting
Lab Planning Program
Meetings with Directors
50. Designate size, location of
13 MEP, teledata rooms
54. KPFF design
stairs for 13/1438. *SRG
Reprogram 13/14
interface, exiting,
stairs
43. *Changes in Steel
Forwarded to Steel
Detailers
46. *RA Furnture
Concept Complete
MEP, Teledata room design
*Design Budget &
Schedule for Changes
Approved
*Notice to proceed
with detailed design
24. *Complete B13,4 H
block occupancy
requirements on MEP
systems
17. *Risick
reprogram solvent
distribution and waste
Issue 80%
MEP CDs
(20) Incorporate
80% MEP review
comments
(19) Genentech review
80% drawings
53. Incorporate
comments, complete
Architectural detail
2. Initial redesign MEP branch
lateral distribution
G accept
13/14
Interface
*City Accept
exiting
*Package C
skin
modifications
55. KPFF design
stairs for 15/14
40. *SRG
Reprogram 15/14
interface, exiting,
stairs
B13 MEP HVAC,
conduit, piping mains
completed
MEP 80% Review
comments
incorporated
Package D and UG
addendum issued:
underground utilities,
vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
(3) *AEI design MEP
HVAC, Conduit &
piping mains B13
16. *HDCCO Determine
Schedule Impact
City Approval of
Alternate Means
for Program
8. Review Alternate
Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details,
update specs and p&ID's
(8) *Revise
MEP loads, MEP
Equipment
schedules
finalized
(13,15,16) MEP specs, P&ID's,
control sequences
Work Process
Meetings
(6) Coord B13 MEP
floor section
4. complete all Interior Architcture
*Cal OSHA Recommend
Determination of LFFH
51. Designate size, location
of 14 MEP, teledata rooms G accept
15/14
Interface
*Accept project
scope:budget
by Genentech
*City Approval of
H Concept
*Exterior
Programming
Accepted by Genentech
*Turnover lab and
vivarium DD plan
to AEI