19
INSTALLATION INSTRUCTIONS /6$& /6$& IMPORTANT

INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

3DJH �

PRODUCT LITERATURE

¤1997

/LWKR 8�6�$�

TABLE OF CONTENTS

SHIPPING AND PACKING LIST 1. . . . . . . . . . . . . . . . . . . . . .

GENERAL INFORMATION 1. . . . . . . . . . . . . . . . . . . . . . . . . .

UNIT DIMENSIONS 2. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PARTS ARRANGEMENT 3. . . . . . . . . . . . . . . . . . . . . . . . . . .

SETTING THE UNIT 4. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

RIGGING 4. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

ELECTRICAL 5. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PLUMBING 7. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

REFRIGERATION 14. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

LEAK TESTING 15. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

EVACUATION & DEHYDRATION 15. . . . . . . . . . . . . . . . . . .

START--UP 16. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

CHARGING 17. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SYSTEM OPERATION 18. . . . . . . . . . . . . . . . . . . . . . . . . . . . .

MAINTENANCE 18. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

START--UP AND PERFORMANCE CHECK LIST 19. . . . . .

SHIPPING AND PACKING LIST

1 -- Assembled condensing unit

1 -- Filter drier

Check unit for shipping damage. Consult last carrier

immediately if damage is found.

INSTALLATION

INSTRUCTIONS

/6$���& ��� 721�

/6$���& ��� 721�

&21'(16,1* 81,76

�������0����

GENERAL INFORMATION

These instructions are intended as a general guide and

do not supersede national or local codes in any way.

Authorities having jurisdiction shouldbe consultedbe-

fore installation.

IMPORTANT

The Clean Air Act of 1990 bans the intentionalventingof refrigerant (CFC�s andHCFC�s) as of July1, 1992. Approved methods of recovery, recyclingor reclaiming must be followed. Fines and/or in-carceration may be levied for non--compliance.

LSA180C/240C

Page 2: INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

3DJH �

LSA180C AND LSA240C DIMENSIONS--INCHES (MM)

CORNER WEIGHT � lbs. (kg)

Model AA BB CC DDModelNo. lbs. kg lbs. kg lbs. kg lbs. kg

LSA180C 230 104 230 104 230 104 230 104

LSA240C 262 119 262 119 262 119 262 119

CENTER OF GRAVITY � in. (mm)

Model NoEE FF

Model No.inch mm inch mm

LSA180C 29-5/16 745 32-1/2 826

LSA240C 29-5/16 745 32-1/2 826

65(1651)

57-5/8(1464)

49-7/8(1267)

OUTDOORFANS ANDGUARDS (4)

FRONT VIEW SIDE VIEW

TOP VIEW

OUTDOORCOILS

SLIDE OUTCONTROL BOX

LIFTING HOLES(For Rigging)

REFRIGERANT LINECONNECTIONS(flush with unit)

COMPRESSORS (2)

8-1/4(210)

14-3/8(365)

3-3/8(86)

14-3/8(365)

3-3/8(86)

8-1/4(210)

CENTEROF GRAVITY

AA BB

CCDD

ELECTRICALINLETS

(Both Sides)

SLIDE OUTCONTROL BOXDISCHARGE AIR

INLETAIR

INLETAIR

INLETAIR

INLETAIR ACCESS

PANELACCESSPANEL

INLETAIR

3-1/4(83)

ELECTRICALINLETS

(Both Sides)

INLETAIR

INLETAIR

INLETAIR

INLETAIR

REFRIGERANT LINECONNECTIONS(flush with unit)

FF

EE

OPTIONAL DISCONNECT(Factory Installed)

OPTIONAL115 VOLT OUTLET(Factory Installed)

7-1/2(191)

7-1/2(191)

REFRIGERANTLINE

CONNECTIONS

15-1/2(394)

OPTIONAL HAIL GUARD(Field Installed Both Sides)

Page 3: INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

3DJH �

LSA180C, 240C UNITS ---- PARTS ARRANGEMENT

LSA180C, 240C PARTS ARRANGEMENT

FIGURE 1

LOW PRESSURE

SWITCH (S87)

SUCTION LINE

SERVICE VALVE

(TYP.)

FILTER DRIER

LIQUID LINE

SERVICE

VALVE (TYP.)

THERMOWELL

HIGH PRESSURE

SWITCH (S4)

LOW AMBIENT SWITCH

(S11) ON LIQUID LINE NOT SHOWN

CONDENSER FANS

(B4, B5, B21, B22)

LOW AMBIENT

SWITCH (S84)

HIGH PRESSURE

SWITCH (S7)

LOW PRESSURE

SWITCH (S88)

COMPRESSORS

(B2, B1)

CONTROL BOX

FAN GUARDS

ACCESS PANEL

LSA180C, 240C CONTROL BOX ARRANGEMENT

FIGURE 2

LSA180C, 240C CONTROL BOX

K167 LATCHING 1

K168 LATCHING 2

K66 STAGE 1 COOL

K67 STAGE 2 COOL

K58 LOW AMB. KIT

K68 OUTDOOR FAN 2

K10 OUTDOOR FAN 1

K149 OUTDOOR FAN 3

K150 OUTDOOR FAN 4

CIRCUIT BREAKER

CB7

CONTACTOR K1 CONTACTOR K2

TIMER DL33

TIMER DL34

C1 C2 C18 C19

THERMOSTAT LOW

AMBIENT S41

TRANSFORMER T18

TERMINAL STRIP

TB34

Page 4: INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

3DJH �

WARNING

Product contains fiberglass wool.

Disturbing the insulation in this product duringinstallation, maintenance, or repair will exposeyou to fiberglass wool. Breathing this may causelung cancer. (Fiberglass wool is known to theState of California to cause cancer.)

Fiberglass wool may also cause respiratory, skin,and eye irritation.

To reduce exposure to this substanceor for furtherinformation, consult material safety data sheetsavailable from address shown below, or contactyour supervisor.

Lennox Industries Inc.P.O. Box 799900Dallas, TX 75379--9900

SETTING THE UNIT

Refer to unit dimensions onpage 1 for sizingmounting

slab, platforms or supports. Refer to figure 3 for instal-

lation clearances.

A--Slab Mounting

When installing unit at grade level, install on a level

slabhighenoughabovegrade toallowadequatedrain-

age of water. Top of slab should be located so run--off

water from higher ground will not collect around unit.

B--Roof Mounting

Install unit at aminimumof 4 inches above surface of the

roof. Caremust be taken to ensure weight of unit is prop-

erly distributed over roof joists and rafters. Either red-

wood or steel supports are recommended.

NOTE-- 48� (1219mm) CLEARANCE REQUIRED

ON TOP OF UNIT.

LSA180C, 240C INSTALLATION CLEARANCES

FIGURE 3

36(914)

36(914)

48(1219)

36(914)

RIGGING UNIT FOR LIFTING

Rig unit for lifting by attaching four cables to holes in unit

base rail. See figure 4.

1 -- Detach wooden base protection before rigging.

2 -- Connect rigging to the unit base using both holes in

each corner.

3 -- All panels must be in place for rigging.

4 -- Place field-provided H-style pick in place just above

topedge of unit. Framemust beof adequate strength

and length. (H-style pick prevents damage to top of

unit.)

Note -- Lifting frame is not required if each of the four

hoisting cables is at least 15 feet (5m) long.

&$87,21 � � 'R QRW

ZDON RQ XQLW�

,03257$17 � � $// 3$1(/6 0867

%( ,1 3/$&( )25 5,**,1*�

/,)7,1* 32,17 6+28/' %( ',5(&7/<

$%29( &(17(5 2) *5$9,7<

�������

������

81,7 :(,*+7

/%6� .*�

0D[LPXP ZHLJKW ZLWK DOO DYDLODEOHIDFWRU\� �LQVWDOOHG DFFHVVRULHV�

/6$���&/6$���&

1RWH � � /LIWLQJ IUDPH LV QRW UHTXLUHG LIHDFK RI WKH IRXU KRLVWLQJ FDEOHV LV DW

OHDVW �� IHHW ��P� ORQJ�

RIGGING INSTRUCTIONS

FIGURE 4

Page 5: INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

3DJH �

ELECTRICAL

Wiringmust conform to current standards of theNational

Electric Code (NEC), Canadian Electrical Code (CEC) and

local codes. Refer to theblower coil or furnace installation

instructions for additional wiring application diagrams

and refer to unit rating plate for minimum circuit ampac-

ity and maximum overcurrent protection size.

WARNING

Unit must be grounded in accordance withnational and local codes.Electric Shock Hazard.Can cause injury or death.

Knockouts are provided in both sides of the cabinet

to facilitate field wiring.

A--Line Voltage

Power wiring enters the make--up box through the bot-

tom and connects to the top of the terminal / disconnect

switch. Separate line voltage connections may be made

to theoptional ground fault interrupter (GFI). See figure5.

Note -- Units are approved for use with copper conduc-

tors only.

B--24V, Class II Circuit

24V, Class II Circuit wiring enters the make--up box

through the bottom and connections aremade in the

low voltage section of themake--up box. Refer to fig-

ure 5 and 6 for field wiring.

Note -- A complete unit wiring diagram is located inside

the unit access panel.

FIGURE 5

Knockouts

GFI line voltage wiring

Unit line voltage wiring

Low voltage wiring

Make--up box

GFI receptacle

Disconnect switch

Y RG

LSA CONDENSING

UNIT CB17/CBH17

BLOWER

CONTACTOR

ROOM THERMOSTAT

24v

COMMON

Y1

TO 24V CLASS II POWER SOURCE

70 VA MINIMUM

NOTE--IF INDOOR UNIT IS NOT EQUIPPED WITH BLOWER RELAY,

IT MUST BE FIELD PROVIDED AND INSTALLED

(P--8--3251 OR EQUIVALENT)

NOTE--SEE UNIT WIRING DIAGRAM

FOR POWER SUPPLY CONNECTIONS.

LINE VOLTAGE FIELD INSTALLED

24V, CLASS II VOLTAGE FIELD INSTALLED

CONDENSING UNIT

FIELD WIRING DIAGRAM

(CB17/CBH17 Shown)FIELD PROVIDED

TRANSFORMER

TO

POWER

SUPPLY

6 4

LOW VOLTAGE

MAKE-UP BOX

BLUE BLUE

YELLOW

RED

RED

RED

BLOWER

MOTOR

CONTROL

RELAY

FIGURE 6

Page 6: INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

3DJH �

7<3,&$/ 81,7 :,5,1* ',$*5$0

/6$���&� ���&

Page 7: INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

3DJH �

PLUMBING

Field refrigerant piping consists of liquid and suction

lines from the condensing unit. Pipingmay be brought

into the unit through either side. Remove the knock-

outs on the mullions and install the provided rubber

grommets into the piping holes. Remove the plugs

from the liquid and suction lines. Refer to table 1 for

field-fabricated refrigerant line sizes for runs up to 50

linear feet (15m).

7$%/( �5()5,*(5$17 /,1( 6,=(6

/6$

81,7

/,48,'

/,1(

68&7,21

/,1(

���&�� ���� LQ���� PP�

���&��� LQ�

��� PP��� ���� LQ���� PP�

��� LQ���� PP�

Refrigerant Line Brazing Procedure

1 -- End of refrigerant line must be cut square, kept

round, free from nicks or dents and deburred (I.D.

and O.D.)

2 -- Wrapawet cloth around the valvebodywhenbraz-

ing to prevent possible heat damage to the valve

core and port.

3 -- Install filter drier, provided with unit, in the liquid

line as close as possible to the expansion device.

Refrigerant Line Limitations

Unit applications with line set lengths up to 50 linear

feet (15m) (excluding equivalent lengthof fittings)may

be installed using refrigerant line sizes as outlined in

table 1. Refrigerant lines from 50 to 100 linear feet (15

to 30m) should be sized in accordancewith the follow-

ing section. Line lengths greater than 100 feet (30m)

are not recommended. Contact Lennox� Application

Department for engineering assistance.

Maximum suction lift must not exceed 70 linear feet

(21m) and maximum liquid lift must not exceed 50 lin-

ear feet (15m).

When line lengths exceed50 feet (15m), a liquid line so-

lenoid should be installed at the evaporator coil. In

addition, only expansion valvesmay be used (RFC and

cap-tube expansion devices are not acceptable). In

applications where the lines exceed 75 feet (23m),

the solenoid valve should be installed with a non-re-

cycling pump-down control.

NOTE -- When refrigerant line solenoid valves are

installed, velocities should not exceed300 fpm inorder

to avoid liquid line hammer.

In applications where cooling operation below 50qF

(10qC) is anticipated andaneconomizer is not beingused,

low ambient (head pressure) controls must be installed.

Due to the additional refrigerant required to fill the

lines, the likelihood of slugging is greatly increased

with lines over 50 feet (15m) in length. An incremental

increase in liquid line size results in a 40 to 50 percent

increase in liquid to fill the line. Therefore, it is desir-

able to use the smallest liquid line size possible.

Addition of Refrigeration Oil Line Lengths� 50 ft.

Add 3 oz. refrigeration oil to the system for each 10 ft.

(3m) above 50 ft. (15m) for suction lines 7/8� and small-

er. Suction lines 1--1/8� and larger require an additional

4 oz. per each 10 ft. (3m) over 50 ft. (15m) in length. Use

non-foaming refrigeration oilwith a viscosity above 200

(3G or 4G).

Pipe Sizing, Line Layout and Design

[Line Set Lengths of 50 -- 100 Linear Feet (15 -- 30m)]

Start by making a sketch of the system showing rela-

tive locations of condensing unit and evaporator,

length of each piping segment, elbows, tees, valves,

etc. This information will be used to determine the

equivalent length of the piping run. Also, take note of

any difference in elevation between the outdoor and

indoor units. Vapor and liquid lift must be considered

to ensure proper pipe sizing.

Liquid Line Function and Design

The liquid linemust convey a full columnof liquid from

the condenser to themetering device at the evaporator

coil without flashing. In order to ensure this, liquid line

pressure drop and pressure across the expansion de-

vice and distributor must be considered.

NOTE -- In units over 5 tons, subcooled liquid begins to

form flash gas at 245psi.

7$%/( �

+&)&��� 6$785$7,21 7(03(5$785(6

�&RQGHQVLQJ 7HPSHUDWXUHV DW 'LIIHUHQW 3UHVVXUHV�

HCFC-22 Pressure Temperature Table (Psig)

Degrees F (qC) HCFC22 Degrees F (qC) HCFC22 Degrees F (qC) HCFC22 Degrees F (qC) HCFC22 Degrees F (qC) HCFC22

--40 (--41) 0.6 18 (--8) 41.1 36 (2) 63.3 75 (24) 133.4 120 (49) 262.5

--30 (--34) 409 20 (--7) 43.3 38 (3) 66.1 80 (27) 145.0 125 (52) 280.7

--20 (--28) 10.2 22 (--6) 45.5 40 (4) 69.0 85 (29) 157.2 130 (54) 299.7

--10 (--23) 16.6 24 (--4) 47.9 45 (7) 76.6 90 (32) 170.0 135 (57) 319.6

0 (--18) 24.1 26 (--3) 50.3 50 (10) 84.7 95 (35) 183.6 140 (60) 340.3

10 (--12) 32.9 28 (--2) 52.7 55 (13) 93.3 100 (38) 197.9 145 (63) 362.0

12 (--11) 34.9 30 (--1) 55.2 60 (16) 102.4 105 (41) 212.9 150 (66) 384.6

14 (--10) 36.9 32 (0) 57.8 65 (18) 112.2 110 (43) 228.6 155 (68) 406.3

16 (--9) 39.0 34 (1) 60.5 70 (21) 122.5 115 (46) 245.2 160 (71) 433.3

Page 8: INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

3DJH �

HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITYAt 45EF Evaporating Temperature and 125EF Condensing Temperature

30

25

20

15

10

9

8

7

6

5

4

3

2

1.5

1.0

.9

.8

.7

10 9 8 7 6 5 4 3 2 1.5 1.0 .9 .8 .7 .6 .5 .4 .3 .2

HCFC-22 LIQUID LINE PRESSURE DROP (lbs./100 Feet)

COOLINGCAPACITY(TONS)

30

25

20

15

10

9

8

7

6

5

4

3

2

1.5

1.0

.9

.8

.7

COOLINGCAPACITY(TONS)

10 9 8 7 6 5 4 3 2 1.5 1.0 .9 .8 .7 .6 .5 .4 .3 .2HCFC-22 LIQUID LINE PRESSURE DROP (lbs./100 Feet)

NOTE -- Shaded area denotes unacceptable velocity range.

FIGURE 7

12.5

To use this chart, first find capacity (tons) on left side of chart. To find pipe size, proceed right to smallest pipe size. Pressure drop (verticalline) and velocity (diagonal lines) can then be determined for the pipe size selected. For example, for 15 ton unit, select 3/4 in. O.D. line.

EXAMPLE:

15 TON UNIT

3/4 IN. O.D. LINE 3.2 PSI

DROP PER 100 FEET

275 FPM VELOCITY

40 30 20 15

40 30 20 15

Page 9: INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

3DJH �

7$%/( �

Equivalent Length in Feet of Straight Pipefor Valves and Fittings

LineSizeO.D.in.

Solenoid/GlobeValve

AngleValve

90ELong*RadiusElbow

45ELong*RadiusElbow

TeeLine

TeeBranch

3/8 7 4 0.8 0.3 0.5 1.5

1/2 9 5 0.9 0.4 0.6 2.0

5/8 12 6 1.0 0.5 0.8 2.5

3/4 14 7 1.3 0.6 0.9 3.0

7/8 15 8 1.5 0.7 1.0 3.5

1-1/8 22 12 1.8 0.9 1.5 4.5

1-3/8 28 15 2.4 1.2 1.8 6.0

1-5/8 35 17 2.8 1.4 2.0 7.0

2-1/8 45 22 3.9 1.8 3.0 10

2-5/8 51 26 4.6 2.2 3.5 12

Long radius elbow. Multiply factor by 1.5 for short radius elbow equivalentlength.

Lennoxequipment above five tons in capacity typically

operates at a saturated condensing temperature of

125qF (280psi per table 2). Lennox equipment is de-

signed to hold a charge allowing 10qF subcooling at

95qF (35qC) ambient. The condensing temperature and

the subcooling are used to calculate the maximum al-

lowable pressure drop as detailed below.

NOTE -- 95qF (35qC) ambient is an arbitrary temperature

chosen to represent typical summer operating condi-

tions used to calculate maximum allowable pressure

drop. This temperature (and the corresponding sub-

cooling) may vary with regional climate.

Example ---- Calculating maximum allowable pressure

drop: Find themaximumallowable liquid line pressure

drop of a unit operating at 10qF subcooling and 125qF

(280 psi) condensing temperature. Subtract 10qF sub-

cooling temperature from 125qF condensing tempera-

ture to equal 115qF subcooled liquid temperature (245

psi / point at which flash gas will begin to form). Sub-

tract 245psi subcooledpressure from280psi condens-

ing pressure to find a maximum allowable pressure

drop of 35 psi.

To calculate actual pressure drop in the liquid line, cal-

culate pressure drop due to friction and pressure drop

due to vertical lift and add the two.

Pressure drop due to friction in pipe, fittings and field-

installed accessories such as driers, solenoid valves or

other devices must all be considered. Pressure drop

ratings for different pipe sizes are given in figure 7.

Pressuredrop ratingsof field-installeddevices are typi-

cally supplied by the manufacturer.

Pressure drop due to vertical lift (1/2 pound per foot) is

typically large and can be a limiting factor in the design

of the system.

The liquid refrigerant pressure must be sufficient to

produce the required flow through the expansion de-

vice. Liquid refrigerant (free of flash gas) should be de-

livered to the expansion valve at a minimum of 175psi

to ensure the 100 psi necessary to produce full refriger-

ant flow at the rated capacity.

Example ---- Liquid Line Pipe Sizing

Given: 15-ton condensing unit on ground level with a

15-ton evaporator on the third level above ground and

a total of 96 linear feet of piping. Unit is charged with

10EF subcooling at 125EF condensing temperature

(280 psi HCFC-22 liquid). Refer to figure 8.

Find: Select tube size from figure 7.

15 TON

CONDENSING

UNIT

15 TON

EVAPORATOR

53 FT.

3 FT. 40 FT.

GIVEN; 15 TON EVAPORATOR15 TON CONDENSING UNITWITH 10EF SUBCOOLING at 125EFLENGTH OF LINE ---- 96 FT.

FIND; LIQUID LINE SIZE

LIQUID LINE SIZING EXAMPLE

),*85( �

FILTER/DRIER

3.2 psi100 ft.

x 98.6 ft. = 3.15 psi

ANSWER: 3/4� O.D. COPPER TUBING CAN BE USED. PRESSURE LOSS DOES NOTEXCEEDMAXIMUMALLOWABLEPRESSUREDROP (6EFTO7EFSUBCOOLINGWILLBE AVAILABLE AT THE EXPANSION VALVE) AND VELOCITY IS ACCEPTABLE.

SELECT A PROPOSED TUBINGSIZE: 3/4in. COPPER

SOLUTION: PRESSURE DROPCANNOT EXCEED 35 psi.

TOTAL PRESSURE DROP=TOTAL FRICTION LOSSES + LIFT LOSSES + FILTER/DRIER

TOTAL EQUIVALENT LENGTH =LINEAR LENGTH + EQUIVALENT LENGTH OF FITTINGS

TWO 90E LONG RADIUS ELBOWS @ 3/4in. O.D. = 1.3 EQUIV. FT. EA.

TOTAL EQUIVALENT LENGTH = 98.6 ft.

TOTAL FRICTION LOSSES =

LIFT LOSSES = 40ft. x 1/2psi per foot = 20psi

TOTAL PRESSURE DROP = 20 psi + 3.15 psi + 1 psi = 24.15 psi

FILTER DROP = 1 psi (by manufacturer)

Figure 7 illustrates the relationship between liquid line

sizing, pressure drop per 100 feet, velocity range and

tonnage. Remember, when using liquid line solenoid

valves, velocities should not exceed 300 fpm. Enter fig-

ure 7 from the left and extend to the right to the small-

est tube size that will not exceed 300 fpm velocity.

Solution: For a 15 ton system, 3/4 inch O.D. linewith 3.2

psi per 100 ft. drop (per figure 7) is selected.Now, calcu-

late pressure drop due to friction and liquid lift to deter-

mine if this is a good selection.

The total friction drop for the application will include 96

feet of 3/4 inch O.D. pipe plus 1 equivalent foot per el-

bow (two elbows) to equal 98.6 equivalent feet.

In a 15-ton system,we canexpect 3.2 psi drop per 100

feet of 3/4 inch O.D. copper (per figure 7). Multiply

3.2/100 by 98.6 equivalent feet to calculate the total

friction loss of 3.15 psi.

Now, we must add the pressure drop for vertical lift.

HCFC-22 pressure drop is 1/2 psi per foot of vertical lift.

In this applicationwhich has a 40-foot (12m) vertical lift,

we find that pressure drop due to lift equals 20 psi.

Page 10: INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

3DJH ��

Finally, we have added a filter drier to the liquid line

which has a 1 psi pressure drop (this number provided

by manufacturer).

Add the three components of pressure drop together

to find that the total pressure drop in this 3/4 inch line

equals 24.15 psi which is well within our acceptable

range. The 3/4 inch line, therefore, is a good selection

because it is well below the maximum allowable pres-

sure drop, is in a satisfactory velocity range, usesmini-

mum refrigerant and provides sufficient pressure at

the expansion valve.

Alternative Sizing: Suppose 7/8 inch O.D. line with 1.7

psi drop per 100 feet had been selected. The total equiv-

alent length is computed by adding the linear length (96

ft.) plus the equivalent length of the fittings (from table

3, two90E ells at 1.5 ft. each). The total equivalent length

is 99 feet. The total friction drop would have been

1.7/100 multiplied by 99 = 1.68 psi. When the pressure

drop due to lift (20 psi) and the filter drier (1 psi) are add-

ed we find that the total pressure drop for 7/8 inch line

equals 22.68 psi.

Though the 7/8 inch line provides a lower pressure

drop, the larger diameter pipe will require more refrig-

erant which will increase the risk of refrigerant slug-

ging. In addition, the smaller linewill be less costly. The

smaller line should be used.

Suction Line Function and Design

The suction line returns refrigerant vapor and oil from

the evaporator to the compressor. Suction line design

is critical. The design must minimize pressure loss in

order to achievemaximum unit efficiency and provide

adequate oil return to the compressor under all condi-

tions.

Because oil separates from refrigerant in the evapora-

tor, the suction velocitymust be adequate to sweep the

oil along the pipe. Horizontal suction lines require a

minimumof 800 fpmvelocity for oil entrainment. In or-

der to ensure oil entrainment, suction risers require a

minimum velocity of 1200 fpm (1500 fpm is preferred)

regardless of the length of the riser.

Figure 11 illustrates the relationship between suction

line sizing, pressure drop, velocity and cooling capac-

ity. Use this chart to determine suction line pressure

drop and velocity. As the pipe size increases, so does

the velocity required to ensure oil entrainment.

Vertical lift has no significant effect on systemcapacity.

However, systems loose approximately 1 percent of

capacity for every pound of pressure drop due to fric-

tion in the suction line. In order to calculate capacity

loss, you must first estimate pressure drop in the total

equivalent length of the piping run (refer to figure 11).

Capacity ratings given in the Lennox Engineering

Handbook include the loss for a25-foot refrigerant line.

Therefore, subtract the pressure loss of 25 feet of pip-

ing from the total calculated for your particular applica-

tion.

OUTDOOR

UNIT

INDOOR

UNIT

DETERMINING SUCTION LINE CAPACITY LOSSIF PRESSURE DROP IS KNOWN

Total Pressure DropFor Equivalent Length

25Ft.Line

Once Pressure Drop Is Found:Btuh lost = 1% x (Total Press. Drop minus 25Ft.) x rated capacity

FIGURE 9

Total Pressure DropMinus Press. Dropin 25Ft. of Line

When an evaporator is located above or on the same

level as the condensing unit, the suction line must rise

to the top of the evaporator. See figure 10. This helps

prevent liquid from migrating to the compressor dur-

ing the off cycle. Traps should also be installed at the

bottom of all vertical risers for migration protection in

the off cycle.

OUTDOORUNIT

INDOORCOIL

SUCTION PIPINGIndoor Coil Above or On Same Level with Outdoor Unit

),*85( ��

OUTDOORUNIT

INDOORCOIL

VAPOR LINE

VAPOR LINE

If equipment is on same level, inverted trap should still be usedin order to prevent liquid migration to compressor during off cycle.

TRAP

RAISE PIPETO TOP LEVEL

OF COIL

INSTALL TRAPS ATBOTTOM OFEACH RISER

Horizontal suction lines should be level or slightly

sloped toward the condensing unit. Pipe must avoid

dips or low spots that can collect oil. For this reason,

hard copper should be used, especially on long hori-

zontal runs.

As with liquid line sizing, begin bymaking a sketch of the

layout complete with fittings, driers, valves etc. Measure

the linear length of each line and determine the number

of ells, tees, valves, driers etc. Add equivalent length of

fittings (table 3) to linear lengthofpipe toget total equiva-

lent length used in determining friction loss. Again, refer

to manufacturer�s data for pressure drop information

on accessory components. The resultant pressure

drop must be considered.

Page 11: INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

3DJH ��

HCFC-22 SUCTION LINE PRESSURE DROP/VELOCITY PER 100ft. OF LINEAt 45EF Evaporating Temperature and 125EF Condensing Temperature

30

25

20

15

10

9

8

7

6

5

4

3

2

1.5

1.0

.9

.8

.7

10 9 8 7 6 5 4 3 2 1.5 1.0.9 .8 .7 .6 .5 .4 .3 .2

HCFC-22 SUCTION LINE PRESSURE DROP (lbs./100 Feet)

COOLINGCAPACITY(TONS)

30

25

20

15

10

9

8

7

6

5

4

3

2

1.5

1.0

.9

.8

.7

COOLINGCAPACITY(TONS)

10 9 8 7 6 5 4 3 2 1.5 1.0.9 .8 .7 .6 .5 .4 .3 .2

HCFC-22 SUCTION LINE PRESSURE DROP (lbs./100 Feet)

NOTE -- Shaded area denotes unacceptable velocity range.

FIGURE 11

40 30 20 15

40 30 20 15

EXAMPLE: 20 TON UNIT

2-1/8 IN. O.D. LINE

1.3 PSI DROP PER 100 FEET

1900 FPM VELOCITY

12.512.5

To use this chart, first find capacity (tons) on left side of chart. To find pipe size, proceed right to smallest pipe size. Pressure drop (verticalline) and velocity (diagonal lines) can then be determined for the pipe size selected. For example, for 20 ton unit, select 2-1/8 in. O.D. line.

Example ---- Suction Line Pipe Sizing

Given: 20 ton condensing unit with evaporator lower

than condenser. Application includes 82 linear feet of

piping and 4 ells. There is a 20-foot vertical lift and 62

feet of horizontal run. Refer to figure 12.

Find: Select tube size from figure 11.

Solution: 2-1/8 inch O.D. line with 1.3 psi per 100 feet

pressure drop and 1900 fpm velocity is selected. Now,

calculate pressure drop due to friction to determine if

this is a good selection.

Page 12: INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

3DJH ��

INDOOR COIL

EXAMPLE - Indoor Coil Below Condenser

SUCTION LINE

SUCTION RISER

OIL TRAP

�� )7�

� )7�

�� )7�

FIGURE 12

From table 3, four ells at 3.9 equivalent feet each

equals 15.6 equivalent feet. When added to the 82 feet

of pipe, the total equivalent feet becomes 97.6 feet

(round up to 98 feet).

Multiply 1.3/100 by 98 equivalent feet to calculate total

friction loss of 1.27 psi.

Use figure 11 to calculate the pressure drop in 25 feet of

2-1/8 inch line. Multiply 1.3/100 by 25 feet to calculate

friction loss of 0.33 psi. This loss has already been in-

cluded in the capacity given in Lennox� Engineering

Handbook, so it should be subtracted from the total.

The capacity lost in the �total equivalent length� of the

refrigerant line (using figures 9 and 11) equals 1 per-

cent x (1.27 --0.33) x 240,000.

Btuh lost= 0.01 x (0.94) x 240,000 = 2256

Capacity loss for the line selected is approximately 0.94

percent.

Theprecedingcalculation shows that this is aworkable

system, and that it will result in negligible losses in

both capacity and efficiency.

Alternative Sizing: Using the same (20 ton) example,

this time select 2--5/8 inch O.D. line. 2--5/8 inch O.D. line

with 0.42 psi per 100 feet pressure drop has 1250 fpm

velocity. Now calculate pressure drop due to friction

loss to determine if this is a better selection.

From table3, four ells at 4.6 equivalent feet eachequals

18.4 equivalent feet.When added to the 82 feet of pipe,

the total equivalent feet becomes 100.4 feet (round up

to 101 feet).

Multiply 0.42/100 by 101 equivalent feet to calculate to-

tal friction loss of 0.42 psi.

Use figure 11 to calculate the pressure drop in 25 feet of

2-5/8 inch line. Multiply 0.42/100 by 25 feet to calculate

friction loss of 0.11 psi. This loss has already been in-

cluded in the capacity given in Lennox� Engineering

Handbook, so it should be subtracted from the total.

The capacity lost in the �total equivalent length� of the

refrigerant line (using figures 9 and 11) equals 1 per-

cent x (0.42 -- 0.11) x 240,000.

Btuh lost= 0.01 x (0.31) x 240,000 = 774

Capacity loss for the line selected is approximately 0.31

percent.

The conditions in this example will allow either 2-1/8

inch or 2-5/8 inch suction line to be used, since capacity

loss is minimized and velocity is sufficient to return oil

to the compressor.

Double Suction Risers

If the condensing unit is equipped to run with a capac-

ity reduction of less than 50 percent, suction lines can

generally be sized in accordancewith the previous sec-

tions. If the suction velocity is high enough to entrain

oil when the unit is operating at reduced capacity,

double suction risers are generally not required.

In general, double suction risers are required any time

the minimum load on the compressor does not create

sufficient velocity in vertical suction risers to return oil to

the compressor. Double suction risers are also generally

required any time the pressure drop or velocity in a

single suction riser is excessive.

Figure 13 shows a typical double suction riser installa-

tion. A trap is installed between the two risers as shown.

During partial load operation when gas velocity is not

sufficient to returnoil throughboth risers, the trapgradu-

ally fills with oil until the second riser is sealed off. When

this occurs, the vapor travels up the first riser only. With

only the first riser being used, there is enough velocity to

carry the oil. This trapmust be close coupled to limit the

oil holding capacity to a minimum. Otherwise, the trap

could accumulate enoughoil on a partial load to serious-

ly lower the compressor crankcase oil level.

The second suction riser must enter the main suction

line from the top to avoid oil draining down the second

riser during a partial load.

Typical double suction riser construction is detailed in

figure 14.

EVAPORATOR

CONDENSINGUNIT

HORIZONTAL SUCTION LINE IS SIZED

TO HANDLE TOTAL LOAD.

IN THE VERTICAL PORTION OF THE LINE,

A SMALLER LINE IS SIZED TO HANDLE

THE REDUCED CAPACITY.

TYPICAL DOUBLE SUCTION RISER

DOUBLE SUCTIONRISER

THE REMAINING LINE IS SIZED TO

HANDLE THE REMAINING CAPACITY

FIGURE 13

Page 13: INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

3DJH ��

DOUBLE SUCTION RISER CONSTRUCTION

Method �A�

90E STREET ELL

METHOD

Method �B�

U-BEND

METHOD

�A� �B�VAPOR LINEFROM AIR HANDLER(Slope to Compressor)

REDUCING TEE

U-BEND

VAPOR LINETO COMPRESSOR

�A� �B�VAPOR LINEFROM AIR HANDLER(Slope to Compressor)

REDUCINGTEE

90ESTREETELBOW

90ESTREET ELBOW

REDUCING TEE

STREET ELL

VAPOR LINETO COMPRESSOR

FIGURE 14

FIGURE 15

EVAPORATOR

15 TONCONDENSING

15 FT.

40 FT.

2 FT.

DOUBLE SUCTION RISER EXAMPLE

DOUBLE SUCTIONRISER

A

B

Example ---- Double Suction Riser Sizing

Given: 15-ton condensing unit. Matched evaporator is

located below condensing unit. Piping will require 57

(linear) feet of pipe (figure 15). Construction without

double suction risers will only require 2 ells.

Find: Select tube sizes for horizontal runs and risers (fig-

ure 11). Determine if double suction risers are needed.

Size double suction riser for proper system perfor-

mance.

Solution: Size each segment based on the tons of re-

frigerant that will flow in the segment.

Full load capacity = 15 tons. Minimum load capacity is

35% of 15 tons = 5.25 tons. The difference between full

capacity and part load capacity is 9.75 tons.

From figure 11, select a pipe size for full load capacity.

1-5/8 inch O.D. pipe with 3.0 psi drop per 100 feet and

2600 fpm velocity is selected. Now, by using figure 11,

find the velocity for the selected pipe size at part loadca-

pacity. The part load velocity is approximately 900 fpm.

900 fpm is sufficient to return oil in horizontal runs but

not in vertical risers.

If we tried to size this systemby simply reducing the riser

size to 1-3/8 inch,wewould find the velocity in the riser to

be excessive (3600 fpm)when the system is operating at

full capacity. As a result of these obstacles, this system

will require construction of double suction risers.

Construction of double suction riserwill require five ells

and two tees total for a system.

Size small riser

(Riser carrying smallest part of load)

The unit produces 5.25 tons capacity atminimum load.

Select from figure 11 a 1--1/8 inch O.D. line (smallest

line with acceptable velocity). When operating at 5.25

tons capacity, this linewill operate at 2000 fpmandwill

produce 3.1 psi drop per 100 ft.

Size large riser

(Riser carrying largest part of load)

The larger line carries 9.75 tons capacity at full load. Se-

lect from figure 11 a 1-3/8 inch O.D. line (smallest line

with acceptable velocity). When operating at 9.75 tons

capacity, this line will operate at 2400 fpm and will pro-

duce 3.0 psi drop per 100 ft.

Putting the Segments Together

Next, we must determine if the line sizes we selected

will result in satisfactory pressure drop between the

condensing unit and the evaporator.

Start by finding the total equivalent feet of the large (B)

riser. Fifteen feet of pipe, plus two tees (branch side of

teeat 6.0 equivalent feet each), plus four ells (2.4 equiva-

lent feet each) = 36.6 equivalent feet length.

Now, find the total equivalent feet of the small (A) riser.

Fifteen feet of pipe, plus one ell (1.8 equivalent feet),

plus one tee (branch side of tee at 4.5 equivalent feet),

plus one tee (line side of tee at 1.5 equivalent feet) =

22.8 equivalent feet length.

Use the total equivalent lengthof each riser to compute

the pressure drop of each riser. For the large (B) riser,

1-3/8 inch O.D. suction line with 9.75 tons capacity has

3.0 psi drop per 100 feet.Multiply 3.0/100by 36.6 equiv-

alent feet to calculate the total friction loss of 1.1 psi.

For the small (A) riser, 1--1/8 inch O.D. suction line with

5.25 tons capacity has 3.1 psi drop per 100 feet.Multiply

3.1/100 by 22.8 equivalent feet to calculate the total fric-

tion loss of 0.71 psi.

Page 14: INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

3DJH ��

The total pressuredrop for the riser is equal to theaver-

age of the pressure drop in both risers:

1.1 (B riser drop) + 0.71 (A riser drop) = 1.81

1.81w 2 = 0.91 (average pressure drop through A and B

risers).

Find the pressure drop for the horizontal run of pipe.

1-5/8 inch pipe at 15 tons capacity has 3.0 psi drop per

100 feet. Multiply 3.0/100 by 42 feet calculate the total

friction loss of 1.26 psi.

The pressure drop through the risers is added to the

pressure drop through the horizontal run to find the to-

tal pressure drop for the system:

1.26 psi (horiz. run) + 0.91 psi (avg. riser) = 2.17 psi.

Use figure 11 to calculate the pressure drop in 25 feet of

1-5/8 inch line. Multiply 3.0/100 by 25 feet to calculate

the friction loss of 0.75 psi.

The capacity lost in the �total equivalent length� of the

refrigerant line (using figures 9 and 11) = 1% x (2.17 --

0.75) x 240,000.

Btuh lost= 0.01 x (1.42) x 240,000 = 3408

Capacity loss for the line selected is approximately 1.42

percent.

REFRIGERATION

Service Valves and Gauge Manifold Attachment

The liquid line and suction line service valves and

gauge ports are accessible on inside of unit. These

gauge ports are used for leak testing, evacuating,

charging and checking charge.

IMPORTANT -- Service valves are closed to line set con-

nections. Do not openuntil refrigerant lines and indoor

coil have been leak tested and evacuated. All precau-

tions should be exercised to keep the system free from

dirt, moisture and air.

Liquid Line Service Valve

LSA180C AND LSA240C units use liquid line valves

shown in figure 16. A schrader valve is factory

installed. A service port is supplied to protect the

schrader valve from contamination and serve as the

primary leak seal.

To Access Schrader Port:

1 -- Remove service port cap with an adjustable wrench.

2 -- Connect gauge to the service port.

3 -- When testing is completed, replace service port cap.

Tighten finger tight, then an additional 1/6 turn.

LIQUID LINE SERVICE VALVE (VALVE OPEN)

FIGURE 16

LIQUID LINE SERVICE VALVE (VALVE CLOSED)

STEM

CAP

SCHRADER VALVE OPEN

TO LINE SET WHEN VALVE

IS CLOSED (FRONT SEATED)

SERVICE

PORT

SERVICE

PORT CAP

RETAINING RING

OUTLET (TO

COMPRESSOR)

(VALVE FRONT

SEATED)

INLET

(TO INDOOR COIL)

SCHRADER

VALVE

SERVICE

PORT

SERVICE

PORT

CAP

INSERT

WRENCH HERE

INLET (TO

INDOOR COIL)

OUTLET (TO

COMPRESSOR)

STEM

CAP

To Open Liquid Line Service Valve:

1 -- Remove stem cap with an adjustable wrench.

2 -- Using service wrench back the stem out counter-

clockwise until the valve stem just touches the retain-

ing ring.

Do not attempt to backseat this valve. Attempts tobackseat this valve will cause snap ring to explodefrom valve body under pressure of refrigerant.Personal injury and unit damage will result.

'$1*(5

To Close Liquid Line Service Valve:

1 -- Remove stem cap with an adjustable wrench.

2 -- Using service wrench turn stem clockwise to seat the

valve. Tighten firmly.

3 -- Replace stem cap. Tighten finger tight, then tighten

an additional 1/6 turn.

Page 15: INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

3DJH ��

FIGURE 17

STEMCAP

VALVESTEM

INLET (TOINDOOR COIL)

OUTLET (TOCOMPRESSOR)

SERVICE PORT

SERVICEPORTCAP

NO SCHRADER

SERVICEPORT

SERVICEPORTCAP

NO SCHRADER

LSA180C AND LSA240C

SUCTION LINE SERVICE VALVE

Suction Line Service Valve

LSA180C and LSA240 units are equipped with a full ser-

vice front- and back-seating suction line service valve as

shown in figure 17. The valve is equipped with a ser-

vice port. There is no schrader valve installed in the

suction line service port. A service port cap is supplied

to seal off the port.

To Access Schrader Port:

1 -- Remove service port cap with an adjustable wrench.

2 -- Connect gauge to the service port.

3 -- When testing is completed, replace service port

cap. Tighten finger tight, then tighten an addi-

tional 1/6 turn.

To Open Suction Line Service Valve:

1 -- Remove stem cap with an adjustable wrench.

2 -- Using servicewrench and 5/16�hex head extension

(part #49A71) back the stem out counterclockwise

until the valve stem just touches the retaining ring.

3 -- Replace stem cap tighten firmly. Tighten finger tight,

then tighten an additional 1/6 turn.

To Close Suction Line Service Valve:

1 -- Remove stem cap with an adjustable wrench.

2 -- Using service wrench and 5/16� hex head exten-

sion (part #49A71) turn stem in clockwise to seat the

valve. Tighten firmly.

3 -- Replace stem cap. Tighten finger tight, then tight-

en an additional 1/6 turn.

LEAK TESTING

After the line set has been connected to the indoor and

outdoor units, the line set connections and indoor unit

must be checked for leaks.

WARNING

Never use oxygen to pressurize refrigeration or airconditioning system. Oxygenwill explode on con-tact with oil and could cause personal injury.When using high pressure gas such as nitrogen orCO2 for this purpose, be sure to use a regulatorthat can control the pressure down to 1 or 2 psig(6.9 to 13.8 kPa).

Using an Electronic Leak Detector or Halide

1 -- Connect a cylinder of nitrogen with a pressure reg-

ulating valve to the center port of the manifold

gauge set.

2 -- Connect the high pressure hose of the manifold

gauge set to the service port of the suction valve.

(Normally, the high pressure hose is connected to

the liquid line port, however, connecting it to the

suction port better protects themanifold gauge set

from high pressure damage.)

3 -- With both manifold valves closed, open the valve

on the HCFC-22 bottle (vapor only).

4 -- Open the high pressure side of the manifold to al-

low HCFC-22 into the line set and indoor unit.

Weigh in a trace amount of HCFC-22. [A trace

amount is a maximum of 2 ounces (57g) refriger-

ant or 3 pounds (31 kPa) pressure]. Close the valve

on the HCFC-22 bottle and the valve on the high

pressure side of the manifold gauge set. Discon-

nect HCFC-22 bottle.

5 -- Adjust nitrogenpressure to150psig (1034 kPa).Open

the valve on the high side of the manifold gauge set

which will pressurize line set and indoor unit.

6 -- After a short period of time, open a refrigerant port

tomake sure the refrigerant added is adequate tobe

detected. (Amounts of refrigerant will vary with line

lengths.) Check all joints for leaks. Purge nitrogen

and HCFC-22 mixture. Correct any leaks and re-

check.

EVACUATION & DEHYDRATION

Evacuating the system of non-condensables is critical

for proper operation of the unit. Non-condensables are

gases that will not condense under temperatures and

pressures present during operation of an air condition-

ing system. Non-condensables and water vapor com-

bine with refrigerant to produce substances that cor-

rode copper piping and compressor parts.

Page 16: INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

3DJH ��

1 -- Connect manifold gauge set to the service valve

ports as follows: low pressure gauge to suction

line service valve; high pressure gauge to liquid

line service valve.

,03257$17 � � &RPSOLDQW VFUROO FRPSUHVVRUV �DV ZLWK

DQ\ UHIULJHUDQW FRPSUHVVRU� VKRXOG QHYHU EH XVHG WR

HYDFXDWH D UHIULJHUDWLRQ RU DLU FRQGLWLRQLQJ V\VWHP�

NOTE -- A temperature vacuum gauge, mercury

vacuum or thermocouple gauge should be used.

The usual Bourdon tube gauges are inaccurate in

the vacuum range.

2 -- Connect the vacuum pump (with vacuum gauge)

to the center port of the manifold gauge set.

3 -- Openbothmanifoldvalves andstart vacuumpump.

4 -- Evacuate the line set and indoor unit to an absolute

pressure of 23mm of mercury or approximately 1

inch ofmercury. During the early stages of evacua-

tion, it is desirable to close the manifold gauge

valve at least once to determine if there is a rapid

rise in absolute pressure. A rapid rise in pressure

indicates a relatively large leak. If this occurs, the

leak testing procedure must be repeated.

NOTE -- The term absolute pressuremeans the to-

tal actual pressure within a given volume or sys-

tem, above the absolute zero of pressure. Absolute

pressure in a vacuum is equal to atmospheric pres-

sure minus vacuum pressure.

5 -- When theabsolute pressure reaches 23mmofmer-

cury, close the manifold gauge valves, turn off the

vacuum pump and disconnect themanifold gauge

center port hose from vacuum pump. Attach the

manifold center port hose to a nitrogen cylinder

with pressure regulator set to 150 psig (1034 kPa)

and purge the hose. Open the manifold gauge

valves to break the vacuum in the line set and in-

door unit. Close the manifold gauge valves.

&$87,21

Danger of Equipment Damage.Avoid deep vacuum operation. Do not use com-pressors to evacuate a system.Extremely low vacuums can cause internal arcingand compressor failure.Damage caused by deep vacuum operation willvoid warranty.

6 -- Shutoff thenitrogen cylinder and remove theman-

ifold gauge hose from the cylinder. Open the man-

ifold gauge valves to release the nitrogen from the

line set and indoor unit.

7 -- Reconnect the manifold gauge to the vacuum

pump, turn the pump on and continue to evacuate

the line set and indoor unit until the absolute pres-

sure does not rise above .5mmofmercury within a

20 minute period after shutting off the vacuum

pump and closing the manifold gauge valves.

8 -- Depending on the equipment used to determine

the vacuum level, absolute pressure of .5mm of

mercury is equal to 500 microns.

9-- When theabsolute pressure requirement abovehas

been met, disconnect the manifold hose from the

vacuumpump and connect it to an upright bottle of

HCFC-22 refrigerant. Open the manifold gauge

valves to break the vacuum in the line set and in-

door unit. Closemanifold gauge valves and shut off

HCFC-22 bottle and remove manifold gauge set.

START--UP

Cooling Start--up

IMPORTANT

Crankcase heater should be energized 24 hoursbefore unit start--up to prevent compressor dam-age as a result of slugging.

1 -- Rotate the fan to check for frozenbearings or binding.

2 -- Inspect all factory and field--installed wiring for

loose connections.

3 -- Open liquid line and suction line service valves to

release refrigerant charge (contained in condens-

ing unit) into system. Replace and tighten caps.

Use a back-up wrench on the suction and liquid

valves when removing or replacing valve caps.

4 -- To open suction valve, remove hex cap and turn

valve stem fully open using an Allen (hex) wrench.

To open liquid valve, remove cap and turn valve

stem until it is fully open and back-seated.

NOTE -- When replacing valve caps, the caps

should be made finger tight and then tightened an

additional 1/6th of a turn.

5 -- Check voltage supply at the disconnect switch. The

voltage must be within range listed on unit name-

plate. If not, do not start equipment until the power

company has been consulted and the voltage

condition corrected.

6 -- Set thermostat for a cooling demand, turn on pow-

er to blower and close condensing unit disconnect

switch to start.

7 -- Recheck unit voltage with unit running. Power

must be within range shown on unit nameplate.

Check amperage draw of unit. Refer to unit name-

plate for correct running amps.

Page 17: INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

3DJH ��

CHARGING

TABLE 4

UNIT MODEL

NUMBER

MATCHED

INDOOR UNIT

HCFC-22 FOR 25 FEET

(7.62M) OF LINE

LIQUID LINE

DIAMETER

ADJUSTMENT PER

FOOT (.305M) OF

LINE*

1/2 in. (13mm) 1.1 ozs. (31 g)

LSA180C CB17/CBH17--185V 15 lbs. (6.8 Kg.) 5/8 in. (16mm) 1.8 ozs. (51 g)g

3/4 in. (19mm) 2.6 ozs. (74 g)

1/2 in. (13mm) 1.1 ozs. (31 g)

LSA240C CB17/CBH17--275V 24 lbs. (11.0 Kg) 5/8 in. (16mm) 1.8 ozs. (51 g)

3/4 in. (19mm) 2.6 ozs. (74 g)

,I OLQH OHQJWK LV JUHDWHU WKDQ �� IW� ��P�� DGG WKLV DPRXQW� ,I OLQH OHQJWK LV OHVV WKDQ �� IW� ��P�� VXEWUDFW WKLV DPRXQW�

127( � � 5HIULJHUDQW OLQH VHWV VKRXOG QRW EH ORQJHU WKDQ ��� IHHW ���P�� 5HIULJHUDQW OLQH ORVVHV GHGXFW IURP WKH QHW FDSDFLW\

RI WKH V\VWHP� $GGLWLRQDO UHIULJHUDQW UHTXLUHG IRU VXFK V\VWHPV PD\ DOVR XSVHW WKH UHIULJHUDQW�WR�RLO UDWLR�

127( � � ,I WKH GLIIHUHQFH LQ HOHYDWLRQ EHWZHHQ WKH /6$ XQLW DQG WKH LQGRRU XQLW H[FHHGV �� IHHW ��P�� DGG �� R]V� ����J� RI

UHIULJHUDQW IRU WKH QH[W �� IW� ��P� LQFUHDVH LQ HOHYDWLRQ� ,I WKH GLIIHUHQFH LQ HOHYDWLRQ EHWZHHQ WKH WZR XQLWV LV JUHDWHU WKDQ ��

IHHW ��P�� FRQVXOW WKH /HQQR[ 7HFKQLFDO 6XSSRUW 'HSDUWPHQW IRU DSSOLFDWLRQ DVVLVWDQFH�

Suction+ 5psig

Discharge+ 10psig

TABLE 5NORMAL OPERATING PRESSURES

OutdoorCoil

EnteringAir Temp.

CIRCUIT 1 CIRCUIT 2

Suction+ 5psig

Discharge+ 10psig

*LSA180C tested with CB17/CBH17--185V.

Suction+ 5psig

Discharge+ 10psig

CIRCUIT 1 CIRCUIT 2

Suction+ 5psig

Discharge+ 10psig

**LSA240C tested with CB17/CBH17--275V.

LSA180C* LSA240C**

65qF (18qC)

75qF (24qC)

85qF (29qC)

95qF (35qC)

105qF (41qC)

115q F (46qC)

181

208

235

268

299

320

68

70

73

75

76

80

178

205

232

264

294

325

66

70

72

74

75

79

181

206

236

268

305

335

71

73

76

78

79

82

188

213

241

271

308

334

71

73

74

77

79

82

Units are shipped with a holding charge of dry air

andheliumwhichmustbe removedbefore theunit is

charged with refrigerant. In new installations, the

recommended and most accurate method of charg-

ing is to weigh the refrigerant into the unit as out-

lined in table 4. If weighing facilities are not avail-

able, or if chargeneeds tobe checked, use the follow-

ing method:

1 -- Attach gauge manifolds and operate unit in cool-

ing mode until system stabilizes (approximately

five minutes).

2 -- Use a thermometer to accurately measure the out-

door ambient temperature.

3 -- Apply the outdoor temperature to table 5 to deter-

mine normal operating pressures.

4 -- Compare the normal operating pressures to the

pressures obtained from the gauges. Minor varia-

tions in these pressures may be expected due to

differences in installations. Significant differences

couldmean that the system is notproperly charged

or that a problem exists with some component in

the system. Correct any system problems before

proceeding.

5 -- If discharge pressure is high, remove refrigerant

from the system. If discharge pressure is low, add

refrigerant to the system.

- Add or remove charge in increments.

- Allow the system to stabilize each time

refrigerant is added or removed.

6 -- Use approach method to confirm readings.

Page 18: INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

3DJH ��

Charge Verification Using Approach Method

1 -- Use the same thermometer to takeboth the liquid

line temperature and the outdoor ambient tem-

perature. Compare liquid line temperature to the

outdoor ambient temperature. Approach tem-

perature equals the liquid line temperature mi-

nus the outdoor ambient temperature.

2 -- The approach temperature should match values

given in table 6. An approach temperature great-

er than the value shown indicates an under-

charge. An approach temperature less than the

value shown indicates an overcharge.

3 -- Do not use the approach method if system pres-

sures donotmatch thepressures given in table 5.

The approach method is not valid for grossly

over- or undercharged systems.

TABLE 6

APPROACH TEMPERATURE

LIQUID TEMP. MINUS AMBIENT TEMP.

Circuit 1 Circuit 2

16EF + 1 (8.9EC + 0.5) 11EF + 1 (6.1EC+ 0.5)

18EF + 1 (10EC + 0.5)17EF + 1 (9.5EC+ 0.5)

MODEL NO.

LSA180C

LSA240C

NOTE -- For best results, the same thermometer should be usedto check both outdoor ambient and liquid temperatures.

SYSTEM OPERATION

Condensing unit and indoor blower cycle on demand

from room thermostat. When thermostat blower

switch is moved to ON position, indoor blower oper-

ates continuously.

Crankcase Heater

LSA180C and 240C units are equipped with external,

belly-band crankcase heaters. The crankcase heater

should be energized 24 hours before unit start--up to

prevent compressor damage as a result of slugging.

Minimum Run Timer Control

All units are equipped with a minimum run timer con-

trol. This control prevents compressor short cycling to

ensure proper oil return to the compressor. When a

cooling cycle begins, the run timer control keeps the

compressor in operation for a minimum of 4 minutes,

regardless of whether the cooling demand has been

satisfied. Do not bypass this control.

High Pressure Switch

LSA180Cand240Cunits areequippedwithahighpres-

sure switch that is located in the discharge line of each

compressor. The switch (SPST,manual reset, normally

closed) removes power from the compressor when

discharge pressure rises above factory setting at 410 +

10 psi.

Low Pressure Switch

LSA180C and 240C units are also equipped with a low

pressure switch that is located in the suction line of

each compressor. The switch (SPST, auto--reset, nor-

mally closed) removes power from the compressor

when suction line pressure drops below factory setting

at 25 + 5 psi.

MAINTENANCE

At the beginning of each cooling season, the system

should be checked as follows:

WARNING

Electric shock hazard. Can cause injuryor death. Before attempting to per-form any service or maintenance, turnthe electrical power to unit OFF at dis-connect switch(es). Unit may havemultiple power supplies.

Condensing Unit

1 -- Clean and inspect condenser coil. Coil may be

flushed with a water hose.

2 -- Condenser fanmotor is prelubricated and sealed. No

further lubrication is needed.

3 -- Visually inspect connecting lines and coils for evi-

dence of oil leaks.

4 -- Check wiring for loose connections.

5 -- Check for correct voltage at unit (unit operating).

6 -- Check amp--draw condenser fan motor.

Unit nameplate _________ Actual ____________ .

NOTE -- If owner complains of insufficient cooling,the unit should be gauged and refrigerant chargechecked. Refer to section on refrigerant charging inthis instruction.

Evaporator Coil

1 -- Clean coil, if necessary.

2 -- Check connecting lines and coils for evidence of oil

leaks.

3 -- Check condensate line and clean, if necessary.

Indoor Unit

1 -- Clean or change filters.

2 -- Adjust blower speed for cooling. The pressure dropover the coil should be measured to determine thecorrect blower CFM. Refer to unit information ser-vicemanual for pressure drop tables and procedure.

3 -- On belt drive blowers, check belt for wear and

proper tension.

4 -- Check all wiring for loose connections

5 -- Check for correct voltage at unit (blower operat-

ing).

6 -- Check amp--draw on blower motor

Unit nameplate_________ Actual ____________.

Page 19: INSTALLATION INSTRUCTIONSwebmanuals.lennoxeurope.com/Out of Production/Condensing... · 2009. 3. 25. · 3DJH HCFC-22 LIQUID LINE PRESSURE DROP/VELOCITY At 45 E F EvaporatingemperatureT

3DJH ��

LSA180C AND 240C START-UP AND PERFORMANCE CHECK LIST

-RE 1DPH

-RE /RFDWLRQ

,QVWDOOHU

8QLW 0RGHO 1R�

1DPHSODWH 9ROWDJH

0LQLPXP &LUFXLW $PSDFLW\

0D[LPXP 2YHUFXUUHQW 3URWHFWLRQ 6L]H

5HIULJHUDQW /LQHV�

6HUYLFH 9DOYHV %DFNVHDWHG"

&RQGHQVHU )DQ &KHFNHG"

-RE 1R�

&LW\

&LW\

6HULDO 1R�

'DWH

6WDWH

6WDWH

6HUYLFHPDQ

$PSV�

6XSSO\ &RQGHQVHU )DQ

&RPSUHVVRU

,QGRRU )LOWHU &OHDQ"

,QGRRU %ORZHU 530

(OHFWULFDO &RQQHFWLRQV 7LJKW"

6XSSO\ 9ROWDJH �8QLW 2II�

6�3� 'URS 2YHU (YDSRUDWRU �'U\�

&RQGHQVHU (QWHULQJ $LU 7HPSHUDWXUH

'LVFKDUJH 3UHVVXUH 6XFWLRQ 3UHVVXUH

&22/,1* 6(&7,21

7+(50267$7

5HIULJHUDQW &KDUJH &KHFNHG"

&DOLEUDWHG" 3URSHUO\ 6HW"

/HYHO"

3URSHUO\ ,QVXODWHG"

6HUYLFH 9DOYH &DSV 7LJKW"

9ROWDJH :LWK &RPSUHVVRU 2SHUDWLQJ

/HDN &KHFNHG"

6HUYLFH 9DOYH &DSV 7LJKW"