Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m
Dr. Des DillonEPRI, Sr. Technical Leader
DOE Project Closeout MeetingMorgantown, March 25th 2020
Initial Engineering Design of a
Post-Combustion CO2 Capture
System for Duke Energy’s East
Bend Station Using Membrane
Based TechnologyDE-FE0031589
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m2
Meeting Agenda
▪ Project Overview (EPRI)
▪ Background & Technical Approach– Project objectives and structure
▪ Analysis of Integration Options (Nexant)
▪ Final Membrane Capture system design for East Bend (MTR/Trimeric) – Membrane system and CPU description (Flow sheets)
– MTR Module arrangement and design
▪ Final BOP and Aux Power Design for East Bend (Nexant/Bechtel) – BOP and Aux Power Design
– Performance
– Layout
– Preliminary HAZOP & Constructability ?
▪ Comprehensive Cost Estimates (Nexant)– Capital and O&M Cost Estimate
▪ Summary of Economic Evaluation and Final Report (EPRI) COE, CO2 avoided cost and marginal operational cost estimated– Final Report
▪ Additional Questions and Discussions
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m3
Advantages of the Membrane Capture Process
▪ Simple, passive operation with no chemical handling, emissions, or disposal issues
▪ Membrane not effected by O2, SOx or NOx; co-capture possible
– O2, SOx or NOx permeate and therefore impact the overall process design
▪ Modular technology – high volume manufacturing to lower cost, pre-assembled, containerized skids
▪ No steam use → no modifications to existing boiler/turbines
▪ Near instantaneous response; high turndown possible
▪ Very efficient at partial capture (40-60% CO2 recovery)
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m4
Challenges of the Membrane Capture Process
▪ Develop a design that will minimize the impact on the power plant by disrupting as little of the existing facilities as possible.
• Also shorten the amount of downtime before the plant can resume normal operations
▪ Develop a design that will minimize the cost of each tonne of captured CO2 while also maintaining the net 600 MW output of the East Bend Station (EBS).
• This will be done by optimizing the percentage of CO2 captured (~60%) and by adding a natural-gas-fired combustion turbine (CT) or possibly a combined cycle to offset the new auxiliary loads
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m5
Project Structure - Team
TEAM MEMBER FUNDER ROLE
US DOE NETL √ Funder
EPRI √ Lead Organization, Project management Economic Evaluation, Dispatch Modelling
Duke Energy √ East Bend Station Owners, Site Hosts, Operators, Data Gathering
Nexant Engineering Designer, System integration and Costing
- Bechtel Auxiliary Power Source Specification, Engineering and Costing
Membrane Technology and Research (MTR) √ Membrane System technology provider, Design costing and optimization.
- Trimeric Design and costing of CO2 compression / condensation / fractionation Unit in the PCC
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m6
Technical Approach 1/2
▪ Following a data gathering task that will include several site visit to the EBS, a preliminary process design will be developed for one Post Combustion Capture (PCC) system which captures CO2 from the entire flue gas stream of the power plant.
▪ This preliminary design will then be subjected to a series of analyses to examine various options for minimizing the cost of CO2 capture on a $/tonne-captured basis.
▪ The analysis will also examine several options for providing the PCC system’s auxiliary power via a CT-based power plant.
▪ Once an optimized process design has been identified, that design will be detailed and documented in a complete Process Design Package (PDP).
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m7
Technical Approach 2/2
▪ As part of this effort a HAZOP and constructability review of the design will be conducted.
▪ The PDP data will be used to carry out a techno-economic analysis that will include a +/-30% accuracy capital cost estimate as well as an estimate of the first year cost of electricity and $/tonne cost of CO2
capture for the retrofitted power plant.
▪ The marginal operating cost of the retrofitted plant with also be calculated and used in a unit dispatch model to predict how the retrofit will impact how often the coal plant is called on to operate.
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m8
Supplying the Membrane System Power Requirements
▪ Unlike solvent PCC systems - No steam requirement, but power is required to drive the membrane systems fans, blowers, vacuum compressors pumps and CO2 compression
▪ 4 ways to supply power have been considered:
– Option 1: New natural gas-fired simple cycle,
– Option 2: New natural gas-fired combined cycle
– Option 3: New simple cycle with HRSG steam to the coal plant FWH
– Option 4: Auxiliary power supplied from the existing coal station
▪ Examine which option is best suited for MTR PCC integration implementation at EBS
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m9
Product
CO2
CW
Boiler
Ash
Primary & Secondary Air
AirPreheater
Stack
Ash
ESP
HP
Turbine Generator
IP LP ~
CW
Lime
CaSO3
SCR
HP FW Htr
LP FW Htr
DeaeratorBFW Pump
Cond Pump
88 F(31 C )
95 F(35 C )
100 F(38 C )
120 F(49 C )
>120 F(>49 C )
105 F(40.5 C )
Membrane-Based CO2 Capture and
Purification Section
Treated Flue Gas
ID + Booster
SurfaceCondenser
WFGD
Coal
MTR PCC Plant Battery Limit (MTR Design)
EBS Unit 2
CW
To FGD
Makeup
To CT
Makeup
~
MTR PCC BOP (Nexant Design)
Power to
PCC Plant
PCC
CW Supply PCC
CW Return
Gas Turbine Simple Cycle Cooling Tower
Natural Gas
from Pipeline
Exhaust to
Vent
(Actual 7F.04 GT SC Power Output available at 92 F is approximately 80% of Iso-rated values)
Aux Power Option 1: New natural gas-fired simple cycle
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m10
Aux Power impact on cost of CO2 Capture & COE
Note: Preliminary evaluation to help facilitate auxiliary power selection (NOT FINAL RESULTS))
$3.50/MSCF NG cost
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m11
Results From Auxiliary Power Assessment
▪ Similar cost of CO2 capture for all integration options (within margin of error)
▪ Selection of best option may be based on overall ease of integration instead of cost
▪ Recommend simple cycle (Option 1) using single GE7F04 turbine
– Lowest upfront cost of all the external power options considered
– Allow phased implementation of feedwater preheat (Option 3)
– Enough temperature & heat available for future EBS HP feedwater preheating if desired
– Potential for future addition of a full size HRSG, should the owner at a later date, consider additional power export of value
– GE 7F.04 was the old GE 7FA GT and its operation is well established commercially
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m12
Design Approach
▪ Assess Key Attributes of East Bend Station– Flue gas composition, temperature, pressure and flow
rate– Operability requirements– Desired capture rates and quantities– Cooling water availability and conditions– Cost of power assumptions
▪ Define project assumptions– Membrane cost and performance values– Set range of process pressure conditions– Consider process design – options for membrane
stages, steps, and recycles.
▪ Conduct process simulations
Plot for capture island
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m13
Flue Gas Composition at East Bend Station
10.1%
11.7%12.2%
12.8%
15.6%
0%
1%
2%
3%
4%
5%
6%
7%
8%
9%
10%
11%
12%
13%
14%
15%
16%
17%
EBS - wet EBS - dry EBS - wet, low leak Typical - wet Typical - dry
CO2 Content in Flue Gas
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m14
Initial Process Design Parameters
▪ Membrane:– First-of-a-kind membrane performance
– Lower CO2 content benefits from a two-stage, two-step design
▪ Flue gas flow rate required two direct contact coolers
▪ Process equipment sized for summer design conditions
▪ Design basis cases include:– Annual average
– Summer design
– Turn down (50%)
Typical two-stage design
Two-stage, two-step design
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m15
Modular Membrane Container
▪ Capture process based on modular membrane containers
▪ Systems are scaled using multiple repeating units
▪ Flanged connections for flue gas in, flue gas out, and CO2
rich stream out.
▪ Inexpensive transportation, installation and changeout.
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m16
East Bend Station – Capture System Flowsheet
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m17
East Bend Station – Capture System Flowsheet – Island A
2 x 50%
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m18
East Bend Station – Capture System Flowsheet – Island B
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m19
East Bend Station – Capture System Flowsheet – Island C
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m20
East Bend Station – Capture System Flowsheet – Island D3 x 33%
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m21
Purchased Equipment Cost for the Capture Island
$124,175,000
$32,780,000
$70,494,000
$14,378,000
$17,150,000
$14,613,000
$0
$50,000,000
$100,000,000
$150,000,000
$200,000,000
$250,000,000
$300,000,000
Liquifaction andPurifcation
RefigerationPackage
Heat Exchangersand Knockouts
Vacuum andCompressionEquipment
MembraneStage 2
MembraneStage 1
($000)
Purchased Equipment $273,590
Labor and Materials $225,639
Bare Erected Cost $499,229
Engineering and Const. Management $49,923
Process and Project Contingencies $157,257
Total Plant Cost – Capture Island $706,409
Most of the PEC cost is attributable to the membrane and the rotating equipment
• 57% Membrane
• 26% Fans, Blowers and Compressors
• 17% Balance
$273,590,000
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m22
Plan view
General ArrangementFlue Gas Return
DCC
Flue Gas Feed
Membrane Stage 1
Vacuum Compressors
Stage 2, Step 1 Membrane
Stage 2, Step 2 Membrane
Compression and
Liquefaction
Capture plant is arranged in two
trains (2 x 50%) for: the DCC, flue
gas fan, and flue gas distribution
to the first stage membrane.
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m23
Key Findings and Takeaways from MTR
▪ This project significantly advanced MTR’s understanding of large-scale design
▪ Vendor product options were identified for all parts of the capture plant
▪ Host site and locational conditions are important:
– Reducing air inleak: potential to reduce membrane area/cost by ~27%
▪ Moving from FOAK to NOAK membrane manufacturing will be impactful
▪ Where possible, emphasize shop fabrication vs. field assembly to reduce
installation costs
▪ Carefully manage and optimize flue gas distribution in ductwork (CapEx vs. OpEx)
▪ The power output from the GT and the power demand of the capture island
divergent with increasing ambient temperatures
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m24
EBS PCC Retrofit BOP & Aux Power Systems
Flue Gas
Handling
Equipment includes:
• MTR membrane systems
• Auxiliaries (vacuum fans,
blowers, intercoolers, heat
exchangers, CO2 pumps,
refrigeration units, etc.…)
EBS Flue GasMTR PCC
Equipment includes:
• Gas turbine package
• Natural gas supply pipeline
CO2 Product
Power
Supply
Natural Gas
Power
Equipment includes:
• Flue gas ducting
• Flue gas blower
• DCC/caustic scrubber and
auxiliaries
Cooling
Water
System
Makeup Water
Cooling Water
Supply & Return
Equipment includes:
• Cooling tower package
• CW circulation system
• MU water treatment system
Balance of
Plant
Equipment includes:
• Plant/instrument air system
• Electrical system
• Instrumentation and control
• Fire protection system
• Flare and relief system
Buildings
Includes:
• Admin building
• Control system building
• Laboratory and warehouse
• Water treatment building
Equipment design provided by Nexant
Equipment design provided by MTR
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m25
Key Considerations For Retrofit Design
▪ Avoid triggering New Source Review▪ EBS Net power export remains the same as before PCC retrofit
▪ Add new gas-fired power generation to supply all PCC auxiliary power demand (Normally no net power export from new generation facility)
▪ Exception is Case 4, which does not add new generation capacity and the MTR PCC simply buys its power needs from EBS
▪ No (or minimum) modification to existing EBS power train
▪ Assume tie-in to existing EBS plant to allow ▪ Safe shutdown of PCC facilities in emergencies
▪ Planned black start-up of PCC facilities
▪ Minor PCC power in-balances during GT transient operations
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m26
Initial Final Design Findings
▪ FindingMTR Island Summer Design power consumptions for 60% CO2 recovery increased to 148 MW from the 130 MW estimated for the Integration Evaluation.
▪ Issue1 x 7F.04 GTSC can’t supply the total PCC Summer Design (92 °F ambient temperature) power demand when including the roughly 30 MW non-MTR BOP facilities demands.
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m27
Possible Solutions to Initial Final Design Issues
1. Bigger GT: 250 MW 7F.05 next size range machines
2. Evaporative Cooling: Cool 92 oF ambient air at 77 oF WBT down to about 82 oF saturation to increase 7F.04 output to roughly 170 MW
3. Optimize Compressor/Blower Efficiency: Work with OEM to reduce power demands
4. Reduce 92 oF CO2 Recovery: Design for 60% recovery at lower ambient temperature for when 7F.04 can generate higher output.
High Ambient Temperature Occurance Frequency
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
60 65 70 75 80 85 90 95
Ambient Temperature, deg F
% o
f Tim
e Te
mpe
ratu
re E
xcee
ds
Annual Occurance May thru Sept Occurance
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m28
Final Design Condition Selection
▪ Minimize capital investment on idling capacity and maximize equipment capacity utilization at continuous design operations:
– Don’t add evaporative cooling or change to larger 7F.05 GT since these will be used less than 10% of the time in a year and less than 20% during summer months.
– Work with compressor/blower OEM to optimize machine efficiencies.
– Design for 60% recovery at lower ambient temperature (average annual ambient temperature).
– Reduce flue gas flow through MTR island during 92 oF summer ambient conditions to keep total power demand within 7F.04 GT output capacity
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m29
Revised Final PCC Pre-FEED Design Basis
Summer AnnualBypass Average
Design Ambient Temperature
- Dry Bulb Temperature 92 oF 54 oF
- Wet Bulb Temperature 77 oF 48 oF
Cooling Water
– Maximum Supply Temperature 88 oF 70 oF
– Maximum Return Temperature 113 oF 90 oF
– Cooling Water Cycles of Concentration 3 3
CO2 Recovery
– % of CO2 in EBS Flue Gas As Calc 60%
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m30
EBS MTR PCC Retrofit Operating Scenarios
▪ Scenarios evaluated:– 100% annual average
– 75% summer bypass (25% flue gas bypass MTR)
– 50% minimum turndown at annual average ambient conditions
Plant EBS MTR PCC Retrofit
Scenario 100% annual average
75% summer w 25% bypass
50% minimum turndown
EBS Performance Rate Guaranteed Guaranteed Min. turndown EBS Gross Power Output, MWe 640 640 250Operating Ambient Conditions Annual average Summer design Annual averageFlue Gas Bypass MTR 0% 25% 0%CO2 Generated from EBS, stpd 16,090 16,090 6,838CO2 to MTR PCC Plant, stpd
Gas Turbine Exhaust CO2, stpd
16,090
2,444
12,068
2,409
6,838
1,622
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m31
Major BOP and Power Supply Systems
▪ Duct works to divert desulfurized Flue Gas (FG) from three existing EBS WFGD to the new MTR PCC, and to return CO2-depleted FG to existing EBS stack for release to atmosphere.
▪ Two 50% FG blowers to offset supply and return duct work pressure drops
▪ Two 50% FG feed conditioning systems
▪ One 198 MW GE7F.04 Gas Turbine Genset
▪ Twenty miles of 10” diameter natural gas supply pipeline
▪ A 10-cell cooling tower (CT) with circulation pumps, and underground cooling water (CW) distribution lines
▪ Electrical distribution system
▪ Makeup water and wastewater treating systems, plant and instrument air system, fire protection system, flare and relief system, and Buildings
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m32
Flue Gas Feed Blower and Conditioning Systems
▪ Two 50% FG blowers are included to offset pressure drops through the feed conditioning, supply and return duct works. Each blower is sized to handle 1,000,000 cubic feet per minute of FG at a head of 60” wc.
▪ Two 50% FG feed conditioning trains are included to reduce the flue gas feed sulfur and moisture before going to the MTR CO2 Capture Island. – Each train consists of a Direct Contact Column with circulation pumps and Plate &
Frame heat exchangers
– Each Contact Column has two packed bed sections:– Deep Flue Gas Desulfurization (DFGD) bottom bed to reduce the FG sulfur
content down below 5 ppm with caustic scrubbing
– Direct Contact Cooler (DCC) top bed to cool the FG to lowest temperature achievable with available cooling water (CW) to minimize MTR feed moisture content
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m33
DFGD/DCC Operation @ Annual Avg Temp w 70 °F CW:
70 °F
(21 °C )
95 °F
80 °F
(27 °C )
120 °F
(49 °C )
~148 °F
(~64 °C )
86 °F
(30 °C )
CW
To MTR PCC
Capture Island
Caustic
Makeup
Spent Caustic
DCC
Bed
DFGD
Bed
120 °F
(49 °C )
Direct Contactor
51’ ID x 127’ T/T
FG Blower10,150 MkW
2.2 PSI Head
One of Two
Identical Trains
Flue Gas
from WFGD
DCC Condensate to
FGD or CT Makeup
115 °F
(46 °C )
15,330 GPM
957 MkW
DCC Cooler
263 MM
11,000 GPM
576 MkW
125 °F
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m34
DFGD/DCC Operation @ Annual Avg Temp w 88 °F CW:
88 °F
(31 °C )
108 °F
99 °F
(37 °C )
120 °F
(49 °C )
~145 °F
(~63 °C )
105 °F
(40.5 °C )
CW
Feed To MTR PCC
Capture Island
Caustic
Makeup
Spent Caustic
DCC
Bed
DFGD
Bed
120 °F
(49 °C )
Direct Contactor
51’ ID x 127’ T/T
FG Blower9,370 MkW
2.0 PSI Head
One of Two
Identical Trains
Flue Gas
from WFGD
DCC Condensate to
FGD or CT Makeup
114 °F
(46 °C ) DCC Cooler
122 MM
15,570 GPM
974 MkW
8,240 GPM
432 MkW
125 °F
Treated Gas from MTR
PCC Capture Island
25%
Bypass
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m35
Electrical Distribution Systems
▪ Not true stand-alone islanded operation
▪ Assume tie-in to existing EBS plant to allow
▪ Safe startup and shutdown of PCC facilities in emergencies
▪ Planned black start-up of PCC facilities
▪ Minor PCC power in-balances during GT transient operations
▪ No net power export on annual operation basis
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m36
Retrofit Operating Scenarios & CO2 Capture Performances
▪ Scenarios evaluated:– 100% annual average
– 75% summer bypass (25% flue gas bypass MTR)
– 50% minimum turndown at annual average ambient conditions
Plant EBS MTR PCC RetrofitScenario 100% annual
average75% summer w 25% bypass
50% minimum turndown
EBS Performance Rate Guaranteed Guaranteed Min. turndown EBS Gross Power Output, MWe 640 640 250Operating Ambient Conditions Annual average Summer design Annual averageFlue Gas Bypass MTR 0% 25% 0%CO2 Generated from EBS, stpd 16,090 16,090 6,838CO2 to MTR PCC Plant, stpdEBS Flue Gas CO2 Captured by MTR, stpdCO2 Capture Rate, % of EBS Flue Gas CO2 onlyGas Turbine Exhaust CO2, stpdNet CO2 Capture Rate (incl GT CO2 emissions)
16,0909,68860%
2,44452%
12,0688,39552%
2,40945%
6,8383,97358%
1,62247%
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m37
EBS MTR PCC Retrofit Overall Plant Performance
Plant EBS MTR PCC RetrofitScenario 100% annual
average75% summer w
25% bypass50% minimum
turndownEBS Flue Gas CO2 Captured, stpd 9,688 8,395 3,973CO2 Capture Rate, % of EBS Flue Gas CO2 only 60% 52% 58%Net CO2 Capture Rate (incl GT CO2 emissions) 52% 45% 47%POWER BALANCE, MWe
GenerationGas Turbine Output 165.3 162.8 89.1
Auxiliary LoadsGas Turbine Auxiliary Loads 2.5 2.5 2.3Makeup and Waste Water Pump 0.2 0.2 0.1CW Pump and CT Fans 8.8 7.7 5.0Flue Gas Feed Blower 25.3 22.7 13.5DCC Circulating Water Pump 3.1 2.9 1.7MTR PCC Loads 125.5 126.9 66.5
Total Auxiliary Loads 165.3 162.8 89.1NET POWER OUTPUT 0.0 0.0 0.0COOLING DUTY, MMBtu/hr
DCC 529 228 250MTR PCC 685 762 378
TOTAL COOLING LOAD 1,215 990 628
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m38
Overall Incremental Water Balances – 100% Annual
Average Operation
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m39
Overall Incremental Water Balances – 75% Summer
Design Operation
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m40
Plant Tie-in and Layout
▪ The MTR carbon capture unit is located to the south-east of the existing Unit 2 stack, with the power block located south-east of the MTR modules.
▪ Flue gas is routed east from the outlet of the 3 Absorbers via three 22 foot diameter round ducts to a common rectangular duct. This duct runs at a high elevation to clear existing structures and to allow clear access.
▪ The rectangular duct supplies the gas via vertical branch ducts to two, 2 stage at-grade axial flow fans that discharge into dedicated 22 foot square ducts to deliver the flue gas to the two Direct Contract Coolers (DCC’s).
▪ The supply ducts use carbon steel with a stainless cladding for corrosion protection.▪ The return gas from the MTR unit is routed in a common rectangular duct which is 36’ x
26’ in cross-section.▪ The return duct is split into 2 branches at the stack and will tie into the existing bypass
duct stack penetrations.▪ The return duct material of construction is coated carbon steel.▪ Overall pressure drop in the duct and DCC’s is approximately 2 psi.
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m41
Plant Tie-in and Layout
▪ Refer to the next two slides for the plot plan and location of the new cooling tower.
▪ A new 10 cell wet cooling tower will be constructed for the MTR unit.
▪ New cooling tower will be located to the east of the existing cooling tower, at a sufficient distance to preclude recirculation effects.
▪ Cooling water supply and return piping will be routed underground to the MTR unit and back to the cooling tower.
▪ New cooling water pumps will be installed at the cooling tower basin to supply the MTR unit.
▪ Makeup water will be pumped from the river water pumping station using new cooling tower makeup forwarding pumps.
▪ Makeup water piping will also be routed underground
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m42
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m43
Preliminary HAZOP (HAZID) Review
▪ PFD Based Review (No P&ID)
▪ More of a HAZID review than traditional HAZOP review
▪ Emphasize on identifying startup, shutdown, transient, and emergency operational needs
▪ Identify items need further attention during FEED phase
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m44
Preliminary Constructability Review
▪ Generalized review on:
▪ Construction sequences
▪ Critical path items
▪ Construction utility resources
▪ Potential lay down areas
▪ Large equipment transportations
▪ Identify items need further attention during FEED phase
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m45
Total Plant Cost Details (End 2018 Cost Basis)
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m46
Total Plant Cost Details
Overall EBS Retrofit
TPC = $1,044 MM
Overall MTR PCC System
TPC = $706 MM
▪ TPC is essentially evenly distributed among:
– MTR membrane cost [33%]
– MTR non-membrane cost (within MTR PCC capture block) [34%]
– Retrofit BOP cost (flue gas handling, power supply etc…) [32]
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m47
Retrofit Operating Scenarios & CO2 Capture Performances
▪ Scenarios evaluated:– 100% annual average
– 75% summer bypass (25% flue gas bypass MTR)
– 50% minimum turndown at annual average ambient conditions
Plant EBS MTR PCC RetrofitScenario 100% annual
average75% summer w 25% bypass
50% minimum turndown
EBS Performance Rate Guaranteed Guaranteed Min. turndown EBS Gross Power Output, MWe 640 640 250Operating Ambient Conditions Annual average Summer design Annual averageFlue Gas Bypass MTR 0% 25% 0%CO2 Generated from EBS, stpd 16,090 16,090 6,838CO2 to MTR PCC Plant, stpdEBS Flue Gas CO2 Captured by MTR, stpdCO2 Capture Rate, % of EBS Flue Gas CO2 onlyGas Turbine Exhaust CO2, stpdNet CO2 Capture Rate (incl GT CO2 emissions)
16,0909,68860%
2,44452%
12,0688,39552%
2,40945%
6,8383,97358%
1,62247%
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m48
EBS MTR PCC Retrofit Overall Plant Performance Plant EBS MTR PCC RetrofitScenario 100% annual
average75% summer w
25% bypass50% minimum
turndownEBS Flue Gas CO2 Captured, stpd 9,688 8,395 3,973CO2 Capture Rate, % of EBS Flue Gas CO2 only 60% 52% 58%Net CO2 Capture Rate (incl GT CO2 emissions) 52% 45% 47%POWER BALANCE, MWe
GenerationGas Turbine Output 165.3 162.8 89.1
Auxiliary LoadsGas Turbine Auxiliary Loads 2.5 2.5 2.3Makeup and Waste Water Pump 0.2 0.2 0.1CW Pump and CT Fans 8.8 7.7 5.0Flue Gas Feed Blower 25.3 22.7 13.5DCC Circulating Water Pump 3.1 2.9 1.7MTR PCC Loads 125.5 126.9 66.5
Total Auxiliary Loads 165.3 162.8 89.1NET POWER OUTPUT 0.0 0.0 0.0COOLING DUTY, MMBtu/hr
DCC 529 228 250MTR PCC 685 762 378
TOTAL COOLING LOAD 1,215 990 628
MTR PCC plant operates at 75% flue gas load during summer conditions
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m49
Fixed Operating Cost
Plant EBS MTR PCC RetrofitCost Basis Year End 2018Average All-In Labor Rate $70,000 /yrOperating Labor Positions 9Overhead Labor Positions 10Fixed OPEX $MM/yr
Operating Labor 42 operating staff 2.9
Maintenance Labor (excl MTR Membrane TPC) 1% of TPC 7.0Maintenance Material (excl MTR Membrane TPC) 1% of TPC 7.0Labor Overhead 10 admin staff 0.7Insurance 1% of TPC 10.4Property Tax 1% of TPC 10.4Total Fixed Operating Cost 38.5
Maintenance labor and material for MTR membrane is estimated within membrane replacement costs
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m50
Variable Operating Cost
Plant EBS MTR PCC RetrofitOperating Scenario 100% Annual AverageCost Basis Year End 2018Operating hours 8,000/yrVariable OPEX
Unit CostProcess Consumables Consumption Units per year ($ per unit) $MM/yr
Natural Gas Feed 13,154,400 MSCF 3.5 46.0
River Water 15,537 1000 gallons 0.38 0.01
CO2 Product Export 3,229,200 ston -- --
Net Power Export 531 MWh -- --
Process Waste Water 9,864 1000 gallons 0.04 0.004
TOTAL PROCESS CONSUMABLES 46.1
Catalysts and Chemicals
MU Water, CW and WWT Chemicals 0.77
Caustic Scrubber NaOH 3,104 ston 408 1.3
Membrane Replacement 10.3% Membrane Eqpt162.6MM
16.7
Membrane Disposal 0.04% Cost 0.07
Refrigerant Makeup 2.5 ston 1,200 0.003
CO2 Dryer Desiccant 0.8 beds 78,000 0.06
TOTAL CATALYST AND CHEMICALS 18.8
Total Variable Operating Costs 64.9
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m51
Operating Costs for Various Operating Scenarios
Plant EBS MTR PCC RetrofitCost Basis Year End 2018Operating hours 8,000/yrScenario 100% annual
average 75% summer bypass 50% minimum
turndownEBS Flue Gas CO2 Captured, stpd 9,688 8,395 3,973EBS Flue Gas CO2 Emitted, stpd 6,402 7,695 2,865Gas Turbine Exhaust CO2, stpd (includes CO2 from air) 2,444 2,409 1,622CO2 Capture Rate, % of EBS Flue Gas CO2 only 60.2% 52.2% 58.1%Net CO2 Capture Rate (incl GT CO2 emissions) 52.3% 45.4% 47.0%
$MM/yr $MM/yr $MM/yr
Fixed OPEX 38.5 38.5 38.5
Variable OPEX
TOTAL PROCESS CONSUMABLES 46.1 45.4 30.6
TOTAL CATALYST AND CHEMICALS 18.8 18.4 18.0
Total OPEX 103.4 102.3 87.2
Total Operating Costs ($/ston CO2) 32.0 36.6 65.8
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m52
Interest rate on debt 5.0%
Nominal escalation rate 3.0%
Debt term 15 years
Years to construct 3 years
Natural gas price $3.50/MMscf
CO2 trans. & storage cost $10/metric ton
Internal rate of return on equity 10%
Operational life time 30 years
Discounted cash flow analysis suggests (additional) cost of electricity
between about $50 and $60 per megawatt-hour
• This is the additional revenue required from the sale of the original plant’s electric output to generate a return on investment in the capture process
• Based on operation at the “annual average” performance• 600 MWe net power to grid• No change in plant availability due to the presence of
the capture process• Key economic assumptions:
48
50
52
54
56
58
60
62
70
80
90
100
110
120
130
140
70.0% 72.5% 75.0% 77.5% 80.0% 82.5% 85.0% 87.5% 90.0%
Co
st o
f el
ectr
icit
y (U
SD/M
Wh
)
Co
st o
f C
O2
Cap
ture
d o
r A
void
ed (
USD
/met
ric
ton
)
Capacity Factor
45% debt financing
55% debt financing
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m53
Operating caseAnnual Average
Summer Bypass
Min. Turndown
Net Output (MWh/day) 14,402 14,402 14,418
EBS Emitted (t/net MWh) 0.403 0.485 0.180CT Emitted (t/net MWh) 0.154 0.152 0.102
Total 0.557 0.636 0.282
CO2 captured (t/MWh 0.610 0.529 0.250
EBS only capture rate 60.2% 52.2% 58.1%Overall capture rate 52.3% 45.4% 47.0%
No capture emissions (t/MWh) 1.014 1.014 0.431
Short run dispatch costs (USD/MWh)Natural gas 9.59 9.45 6.38
CO2 T&S 6.10 5.29 2.50Everything else 3.79 3.71 3.62
Total 19.49 18.45 12.50
Short-run costs are about equally fuel distributed between fuel and other VOM costs
Portion of capital that is debt financed 45% 55%
Capital 24.69 23.93
USD/MWh
VOM (excl. T&S) 13.38 13.38
T&S 6.10 6.10
FOM 9.84 9.84
COE 54.02 53.26
Cost captured 78.53 77.27USD/metric ton
Cost avoided 118.37 116.69
Capital costs contribute about 45% of the added cost of electricity
After accounting for the emissions from natural gas, about half of the
original emissions are avoided
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m54
Final Report
▪ A final report will be written that shall include:
– A description of the existing plant and the retrofit changes required to add CO2 capture.
– Process descriptions with process flow diagrams, and heat and material balances for the PCC plant including CO2 compression.
– A plot plan to establish the space required for the PCC plant.
– Equipment lists with sizing of major items for the PCC plant.
– Breakdown of costs by system for the PCC plant.
– Power, cooling water, and consumables used by the PCC plant.
– Description on preliminary PCC startup, shutdown, and bypass operating procedures with flow diagrams, and equipment requirements for integration with the existing power plant.
– All environmental emissions from the retrofitted PCC plant, including all disposal
requirements.
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m55
Acknowledgement and Disclaimer
AcknowledgementThis material is based upon work supported by the Department of Energy under Award Number DE-FE0031589. DisclaimerThis report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.
© 2020 Electric Power Research Institute, Inc. All rights reserved.w w w . e p r i . c o m56
Together…Shaping the Future of Electricity