4 Months Industrial Training8th Semester At Premier Industry Pvt. Ltd. Industry ProfileWas established in the year 1964Engaged in manufacturing and supplying an impeccable assortment of C.I. Castings for Automobile, Disel Engines, Pumps, Engineering Products.In Manufacturing Facility, it have a state-of-the-art manufacturing unit with all the requisite machines and latest technology.Products Supplier and Manufacturerci castings Diesel engine partsGeneratorsCast productsGenerator setsFiltersGenerator spare . Sand Plant

This is basically used to for the automation of the sand preparation for the casting process.Sand is collected in knockout and moved to elevator via drum conveyorSand is then moved to the sieve seperating stone from sand

This sand is moved via conveyor to the hooper of where new sand and old sand are mixed.

Again this sand is moved to the elevator and is piled in moller where the sand is mixed with water and other agent. This sand is filled in cop and drag. Preparation of sand in Muller

Sand that is Green Sand required for casting is prepared ny mixing its constituents in muller m/c..Sand is mixed with water, betonite (binding agent) , coal dust (demoisturiser) and molases.

Moulding Material Major part of moulding material in casting70-85% silica sand10-12% betonite3-6% water Coal dust (demoisturiser) Moulding Machine

It is used to create cavity in the mould Cavity is replica of the core.Cop and Drag are placed simultaneously and mold material is filled from sand plant.

Melting of Metal

Induction furnaces are the most common type used by both ferrous and non-ferrous foundries. Copper coils heat the metal using alternating currents. The flux reacts with impurities.Capacity 300kg &500kgtemperature= 1400-1500 degree. Flux is added to remove slag from molten metal

Pouring of MetalAfter melting of metal molten metal is poured in the mould cavity which is replica of core. Before pouring provisions are made for the escape of dissolved gases . The gating system should be besigned to minimize the turbulent flow and erosion of mould cavity. The other important factors are the pouring temperature and pouring rate Solidification and Cooling The properties of the casting significantly depends on the solidification time cooling rate.Shrinkage of casting, during cooling of solidified metal should be restrained by the mould material, otherwise internal stresses may develop and form cracks in casting.Proper care should be taken at the design stage of casting so that the shrinkage can occur without casting defect. Shot Blasting Process

After cooling and solidification shot blasting is done in order to remove extra material from the cast product.Abrasive shot or sheet shots are used to remove material Grinding ProcessAs shot blasting is done cast products are checked thoroughly for the extra material . Grinding is carried out to remove that extra material. InspectionVisual Inspection- Cast product is visually inspected for the cracks and deforms etc.Sound test - This is a rough test to indicate a flaw or discontinuity in a casting. The casting is suspended from a suitable support free of all obstructions and tapped at various places on its surface with a small hammer. Any change in the tone produced indicates the existence of a flaw. Some other methodsMPT (Magnetic Particle test )Penetrant testUltrasonic testingRadiongraphy testing etc..