88
Environmental Monitoring Report This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.. Project Number: 40648-034 September 2020 Period: January 2020 – June 2020 IND: Infrastructure Development Investment Program for Tourism - Tranche 3 Submitted by: Program Management Unit, Government of Uttarakhand, Dehradun

IND: Infrastructure Development Investment Program for ......IND: Infrastructure Development Investment Programme for Tourism, Uttarakhand (Tranche –III) Prepared by Dept. of Tourism,

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

  • Environmental Monitoring Report

    This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

    In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area..

    Project Number: 40648-034 September 2020 Period: January 2020 – June 2020

    IND: Infrastructure Development Investment Program for Tourism - Tranche 3

    Submitted by: Program Management Unit, Government of Uttarakhand, Dehradun

  • Recd. 15.09.20SFG Log 4340

  • 1

    Semi – Annual Environmental Monitoring Report

    Loan No: 3223 IND Period: Jan to June 2020

    IND: Infrastructure Development Investment Programme for Tourism, Uttarakhand (Tranche –III)

    Prepared by Dept. of Tourism, Government of Uttarakhand for Asian Development Bank September, 2020

    This Semi – Annual Environmental Monitoring Report is a document of the borrower. The views expressed

    herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be

    preliminary in nature.

  • 2

    Table of Contents

    1. INTRODUCTION ........................................................................................................................................................................................................................................................................................................................................................................................................................................................ 5555

    2. COMPLIANCE STATUS ........................................................................................................................................................................................................................................................................................................................................................................................................ 29292929

    3. COMPLIANCE STATUS WITH NATIONAL/ STATE/ LOCAL STATUTORY ENVIRONMENTAL

    REQUIREMENTS ........................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 31313131

    4. COMPLIANCE STATUS WITH THE ENVIRONMENTAL COVENANTS AS STIPULATED IN THE

    LOAN AGREEMENT .................................................................................................................................................................................................................................................................................................................................................................................................................................................... 34343434

    5. COMPLIANCE STATUS WITH ENVIRONMENT MANAGEMENT AND MONITORING PLANS AS

    STIPULATED IN THE ENVIRONMENTAL DOCUMENTATION AS AGREED WITH ADB. ........................................................ 35353535

    6. STATUS OF IMPLEMENTATION OF ENVIRONMENT MANAGEMENT PLAN ............................................................................................ 37373737

    7. APPROACH & METHODOLOGY ENGAGED FOR ENVIRONMENTAL MONITORING OF THE

    PROJECT .................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................... 60606060

    8. MONITORING OF ENVIRONMENTAL RECEPTORS/ ATTRIBUTES ................................................................................................................................................ 60606060

    9. IMPLEMENTATION OF ENVIRONMENTAL MONITORING PLAN ................................................................................................................................................................ 61616161

    10. IMPLEMENTATION OF COVID 19 (H&S PLAN) .................................................................................................................................................................................................................................................... 71717171

    11. INSTITUTIONAL ARRANGEMENTS .................................................................................................................................................................................................................................................................................................................... 71717171

    11.1 INSTITUTIONAL ARRANGEMENTS FOR EMP IMPLEMENTATION ................................................................................................................................................ 73737373

    12. PUBLIC CONSULTATION DETAILS .................................................................................................................................................................................................................................................................................................................... 74747474

    13. IMPLEMENTATION OF GRIEVANCE REDRESS MECHANISM ............................................................................................................................................................ 74747474

    14. ANY OTHER ENVIRONMENTAL ASPECTS, IMPACTS OBSERVED DURING

    IMPLEMENTATION WHICH WERE NOT COVERED EARLIER ........................................................................................................................................................................................................ 75757575

    15. DETAILS OF COMPLAINTS RECEIVED FROM PUBLIC AND ACTION TAKEN THEREOF TO

    RESOLVE ................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 75757575

    16. FOLLOW UP ACTIONS AND CONCLUSIONS ............................................................................................................................................................................................................................................................ 75757575

  • 3

    List of Table

    TABLE 1: SUB PROJECT DETAILS 7777

    TABLE 2: WORK PROGRESS AND RISKS FOR SUB PROJECTS TILL JUNE, 2020 9999

    TABLE 3: STATUS OF COMPLIANCE WITH EARF/ADB PROCEDURES 29292929

    TABLE 4: STATUS OF ENVIRONMENT, FOREST AND OTHER CLEARANCE 31313131

    TABLE 5: STATUS OF COMPLIANCE WITH ENVIRONMENTAL LOAN COVENANTS 34343434

    TABLE 6: EMP IMPLEMENTATION STATUS 35353535

    TABLE 7 (I): EMP MONITORING STATUS CHART- DEVELOPMENT OF TOURISM

    INFRASTRUCTURE IN KARTIKEYA SWAMI CIRCUIT (LOT-1) (TUNGESHWAR & DURGADHAR

    TEMPLE) 37373737

    TABLE 7 (II): EMP MONITORING STATUS CHART- DEVELOPMENT OF TOURISM

    INFRASTRUCTURE IN KARTIKEYA SWAMI CIRCUIT (LOT-2) (KARTIKEYA SWAMI TEMPLE) 39393939

    TABLE 7 (III): EMP MONITORING STATUS CHART- RURAL TOURISM IN DISTRICT

    RUDRAPRAYAG, CHAMOLI AND UTTARKASHI (8 VILLAGES) 41414141

    TABLE 7 (IV): EMP MONITORING STATUS CHART- CONSERVATION OF CULTURAL HERITAGE

    AND URBAN PLACE MAKING IN NAINITAL LOT-1 43434343

    TABLE 7 (V): EMP MONITORING STATUS CHART- RESTORATION AND ADAPTIVE REUSE OF

    ALMORA FORT (RANI MAHAL) 45454545

    TABLE 7 (VI): EMP MONITORING STATUS CHART- RESTORATION AND ADAPTIVE REUSE OF

    ALMORA FORT (MALLA MAHAL) 47474747

    TABLE 7 (VII): EMP MONITORING STATUS CHART- RESTORATION AND ADAPTIVE REUSE OF

    CHAMPAWAT FORT (BANASUR) 47474747

    TABLE 7(VIII): EMP MONITORING STATUS CHART – RESTORATION AND ADAPTIVE REUSE OF

    PITHORAGARH FORT, PITHORAGARH 49494949

    TABLE 7 (IX): EMP MONITORING STATUS CHART- CREATION OF PEDESTRIAN ROUTE FOR

    PILGRIMS AND TOURISTS IN HARIDWAR 51515151

  • 4

    TABLE 7(X): EMP MONITORING STATUS CHART- DEVELOPMENT OF TOURISM

    INFRASTRUCTURE IN SEM-MUKHEM 53535353

    TABLE 7(XI): EMP MONITORING STATUS CHART - DEVELOPMENT OF RURAL TOURISM

    INFRASTRUCTURE IN PAURI AND TEHRI DISTRICT 55555555

    TABLE 7(XII): EMP MONITORING STATUS CHART- DEVELOPMENT OF TRADITIONAL MEDICINE

    AND YOGA TRAINING CENTERS 56565656

    TABLE 7(XIII): EMP MONITORING STATUS CHART-DEVELOPMENT OF “GEORGE EVEREST

    HERITAGE PARK” 58585858

    TABLE 8: PARAMETERS AND METHODOLOGY FOR ENVIRONMENTAL MONITORING 61616161

    TABLE 9 (I): IMPLEMENTATION OF ENVIRONMENTAL MONITORING PLAN- FOR PROJECTS

    UNDER PIU DDN 61616161

    TABLE 10: PUBLIC CONSULTATION MEETINGS FOR TRANCHE III SUB-PROJECTS 74747474

    ANNEXURE: 1(I): PHOTO ILLUSTRATION OF WORK PROGRESS- PIU DEHRADUN 76767676

    ANNEXURE: 1(II): PHOTO ILLUSTRATION OF WORK PROGRESS- PIU KOTDWAR 77777777

    ANNEXURE: 1(III): PHOTO ILLUSTRATION OF WORK PROGRESS- PIUBHIMTAL 79797979

    ANNEXURE 2: CONSULTATION PHOTOGRAPHS AND ATTENDANCE RECORDS 80808080

    ANNEXURE 3: IMPLEMENTATION OF H&S PLAN (IN RESPONSE TO COVID-19) 85858585

  • 5

    1. Introduction

    Overall Project Description

    1. The Infrastructure Development Investment Program for Tourism Financing Facility (the Facility) will

    develop and improve basic urban infrastructure and services in the four participating states of Himachal

    Pradesh, Punjab, Uttarakhand and Tamil Nadu—to support the tourism sector as a key driver for

    economic growth. It will focus on: (i) strengthening connectivity to and among key tourist destinations;

    (ii) improving basic urban infrastructure and services, such as water supply, road and public transport,

    solid waste management and environmental improvement, at existing and emerging tourist destinations

    to ensure urban amenities and safety for the visitors, and protect nature and culture-based attractions.

    Physical infrastructure investments will be accompanied by: (iii) capacity building programs for

    concerned sector agencies and local communities for better management of the tourist destinations and

    for more active participation in the tourism-related economic activities, respectively.

    2. The proposed Project targets enhanced economic growth and provision of livelihood opportunities for

    local communities through tourism infrastructure development with a focus on preservation and

    development of natural and cultural heritage and incidental services. The Project supports the state of

    Uttarakhand to develop the tourism sector as a key driver for economic growth.

    3. The Executing Agency (EA) for the Investment Program is Dept. of Tourism, Govt. of Uttarakhand. The

    Loan Agreement and Project Agreement for the IDIPT, Uttarakhand is 3223-IND. Project

    Implementation Unit have been established in three towns respectively (Dehradun, Bhimtal and

    Kotdwar) for implementation of sub-projects. Design and Supervision Consultants (DSCs), has already

    been established in three towns for designing the Infrastructure, managing the tendering of Contractors

    and supervising construction, and providing support to the PIUs.

    Outputs of the Project

    4. The outputs of the Project are as follows:

    Component 1: Urban Infrastructure and Service Improvement

    Component 2: Improved connectivity

    Component 3: Quality Enhancement of Natural and Cultural Attractions

    Component 4: Greater participation by local communities

    Component 5: Capacity Development, Community Participation and Project Management

  • 6

    Environment Category:

    5. The project under IDIPT was categorized as Environment Category “B”, according to ADB’s Safeguard

    Policy Statement (2009). All the subprojects under execution have been categorized as category 'B'.

    Environment Performance Indicators, if any:

    6. For effective monitoring, selected environmental parameters have been identified as indicators which

    may be qualitatively and quantitatively measured and compared over a period of time in order to

    assess/ ensure the compliance to environmental management plans (EMPs). The environmental

    performance indicators selected are physical, biological and social characteristics identified as most

    important in affecting the environment at critical locations at all the sub projects. The parameters

    identified as performance indicators are:

    1. Compliance with environmental management and monitoring plan

    2. Compliance to State/ National environmental regulations.

    3. Monitoring of ambient air quality, water quality and noise levels and comparison with baseline

    environmental quality and State/ National Standards.

    Overall project progress, agreed milestones and Implementation schedule

    7. Construction works for the following sub projects are in progress and shown in Table 1.

  • 7

    Table 1: Sub Project Details

    SI. No.

    Package Ref No.

    General Description Goods or Works

    Contract Signing Date and Start

    date Name of the Contractor Contract Value

    Contract period

    1 UK/IDIPT-III/ DDN/01 Lot1

    Development of Tourism Infrastructure In Kartikeya Swami Circuit (Lot-1) (Tungeshwar & Durgadhar Temple)

    22.01.16

    M/s Aaradhya Engineers& construction pvt Ltd.,2ndTulsiVihar, Hardiwar road ,Post –Virbhadra ,Rishikesh (UA)

    INR 7.60 Cr. With variation 9.76 Cr.

    24 months

    Extnd 13.07 months

    2* UK/IDIPT-III/ DDN/02

    Development of Tourism Infrastructure in Kartikeya Swami Circuit (Kartikeya Swami Temple) 26.1.2019

    M/s Sky International, 177, Engineers enclave Phase-I, GMS Road, Dehradun-248001

    INR 2.66 Cr. With variation INR 3.24 Cr.

    12 months Extnd 4 months

    31.05.2020

    3 UK/IDIPT/III/DDN/03

    “Conservation & Development of Rural Tourism Sites of Rudraprayag, Chamoli and Uttarkashi Districts of Uttarakhand”

    02.08.2016

    M/S Navya Associates in JV with Agrawal Brothers INR 15.26 Cr. With variation 22.65 Cr.

    24 monthsExtnd12.

    03 months 31.05.2020

    4 UK/IDIPT/III/BHT/01

    Conservation of Cultural Heritage and urban place making in Nainital Lot-1

    19-10-2015

    M/s Bansal Construction in JV with M/s Technical Construction Company

    INR 10.53Crore. LOA issued to contractor on March 2020

    5 UK/IDIPT/III/BHT/03

    Restoration and adaptive reuse of Almora Fort (Rani Mahal)

    19-10-2015

    M/s Satya Sai Builders & Constructions INR 33.67 Crore.

    LOA issued to contractor on January 2020

    6 UK/IDIPT/III/ BHT/06

    Restoration and adaptive reuse of Almora Fort (Malla Mahal)

    4/2/2019 M/s SatyaSai Builders & Constructions INR 6.98 Crore 12 months 03.02.2020

    7 UK/IDIPT/III/BHT/05

    Restoration and adaptive reuse of Champawat Fort (Banasur)

    19-10-2015 M/s Simplex Project Limited 407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India

    INR 15.53Crore with variation 16.90 Cr.

    24 months Extnd. 26 months

    31.12.2019

    8 UK/IDIPT/III/ KOT/01

    Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar

    22/07/2015 M/s SS InfratechJv, Tikola Nagar, Roorkee, Haridwar 247670

    INR 22.38 Cr. With variation 23.87 Cr.

    48 months extn 28-2-2020

    9 UK/IDIPT/III/KOT/02

    Development of Tourism Infrastructure in Sem Mukhem

    22/08/2015 M/s Mangalam Engineers and Construction Company in JV with Sunil Garg and Company, Kesarganj, Meerut.

    INR 10.18 Cr. With variation 11.64 Cr.

    24 months Extnd 7 months

  • 8

    *S.no 5 Project has been bifurcated into 02 packages.

    8. Work Details In the reporting period has been shown in Table 2.

    10 UK/IDIPT/III/KOT-03

    Development of Rural Tourism Infrastructure in Pauri and Tehri District

    21/05/2018 M/s Bansal Construction in JV with M/s Technical Construction Company

    INR 20.05 Cr. 24 months

    11 UK/IDIPT/III/BHT/07

    Restoration and Adaptive Reuse of Pithoragarh Fort Phase II

    05/07/2016 M/S COX Infratech Private Limited in JV with Conaech Associates

    INR 27.11 Cr. With variation 35.47 Cr.

    24 months Extnd 19 months

    28.02.2020

    12 UKIDIPT/III/GEN/03

    Development of Traditional Medicine and Yoga Training Centers

    08/03/17 M/s Bansal Construction INR 3.75 Cr. With variation 5.05 Cr.

    24 months Extnd 9 months

    31.12.2019

    13* UK/IDIPT/III/ GEN/04

    Development of “ George Everest Heritage Park” sub project

    18/1/2019 M/s Arun Constructions Avantika Colony, near Rice Mill, Kailsa Road, Aurola, Uttarpradesh

    INR 23.66 Cr. With variation 24.37 Cr.

    15 Months

    Work progress of 13 packages is reported in table 2. The work of construction of toilets en route Char Dham tourist destinations was allotted to 03 existing

    contractors. IEE document was prepared for the same and was approved by ADB on 19.02.2020. Accordingly the table 2 reflects the additional scope in

    package UK/IDIPT-III/ DDN/01 Lot1 (Development of Tourism Infrastructure In Kartikeya Swami Circuit-Tungeshwar, DurgadharTemple), UK/IDIPT/III/DDN/03

    (Rural Tourism) and UK/IDIPT-III/KOT/01 (Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar). Photographs showing work progress are

    provided in Annexure 1.

  • 9

    Table 2: Work Progress and Risks For sub projects till June, 2020

    Name & No. of

    Package

    Name of

    the

    contractor

    Listing of works under the package

    Starting Date(land clearance)

    and schedule date of

    completion Type of works

    Continued at

    Present

    Progress %

    Expected

    change from

    Approved

    scope

    Fulfillment

    of objective

    Type of

    remedial

    measures

    needed

    Key assumption

    and risk affect

    attainment the

    objective Starting date Date of

    Completion

    UK/IDIPT-III/

    DDN/01 Lot1

    Development of

    Tourism

    Infrastructure In

    Kartikeya Swami

    Circuit (Lot-1)

    (Tungeshwar,

    DurgadharTemp

    le)

    Aradhya

    Engineers

    Durgadhar Temple precinct

    Upgradation of infrastructure around the approach area of the temple, including drinking water facilities and sanitation

    Parking facility and vehicular approach along with adjoining retaining walls

    Solid waste management

    Pathway development with railings & protection wall wherever necessary and signage and seating and lighting

    Temple entrance arch

    Improvement of the temple complex in terms of restructuring of the newly added temporary structures and overall landscaping to facilitate better movement and space for gathering of pilgrims and tourists

    Lodging facilities with rooms and dormitories and toilet block at the rear side of the temple complex and a langar hall

    Area confinement with edge wall , viewing decks etc

    Restoration of Temple premises Construction of C.C road(main road to Temple,400 mtr length with drain

    22.01.2016 28.02.2020

    DURGADHAR:-

    Works completed

    TUNGESHWAR:

    Works completed

    100%

    Nil Nil NA

  • 10

    Development of Solar lighting and Fire Fighting work.

    Capacity building for temple committee members for O&M activities.

    Tungeshwar Temple precinct

    Entrance area development with appropriate signage

    Development of the 1.5km long pathway with railing to the main temple, increase in width and edge protection wherever required.

    Seating arrangements , viewing decks and toilet facilities

    Signage along the pathway and Temple premises.

    Improvement in the temple precinct

    Construction of entrance gate

    Lodging facilities and langar hall

    Development of Solar lighting and Fire Fighting work

    Improvement in the drinking water facility for the approach areas

    Capacity building for temple committee members for O&M activities.

    Additional Scope:

    Construction of Toilets at Guldi road, Dharasu road, Mussoorie road, Nainbag, Kamand, Kandisour, Peepaldali, Ghansali, near police station and market, Pilwa, Devprayag, near tehsil and bus stand, Kolhukhet, Mussoorie lake, Kirtinagar,

    Construction of Toilets in Tehri district Guldi road Dharasu road Mussoorie road Nainbag Kamand Kandisour Peepaldali Ghansali, near police station and market. Pilwa Devprayag, near tehsil and bus stand Kolhukhet Mussoorie lake Kirtinagar Suwakholi bend Kempty fall Dhanolti Singh DwarHaridwar Ghansali near bridge

    35%

  • 11

    Suwakholi bend, Kempty fall, Dhanolti, Singh Dwar Haridwar, Ghansali near bridge

    UK/IDIPT/III/DDN

    /02

    Kartikeya Swami

    Temple

    M/s Sky

    Internation

    al

    (New

    Contractor

    for

    remaining

    works)

    Civil Work Pedestrian Pathway Sitting Arrangement Railing at Temple Premises Pathway Renovation Existing Dharamshala Rest Shelter Retaining & Breast Walls View Point Pre-fabricated Small Size Toilet Entrance Gate Renovation of Lodging Facility Furniture for Lodging Facility Camping Site development Renovation of Main Temple Solar Lighting Fire Fighting works Additional items Renovation of Existing Toilet and surface dressing of approx. 230 sqm land in front of toilet for 4-5 ECS parking Toilet Block Provision of Pathway Covering Shelter Directional Signage Informative Signage Solar Power Plant (2KW) Hill View location pointer model Extension of Temple Premises Electrical Work (Internal/External) From Provisional Sums Water Supply Connection Electricity Connection Rain Water Harvesting Capacity building for Temple Committee members for O&M activities

    26.1.2019

    15.09.2020

    Dharamshala flooring work in progress.

    Rest shelter finishing work in progress.

    Lodging facility work in progress

    Renovation of main temple work in progress.

    Toilet block finishing work in progress.

    Pathway covering shelter work in progress.

    Extn. Of temple premises work in progress

    22%

    Approx. 230

    sqm open

    land in front

    of toilet

    facility will be

    leveled and

    created as

    parking area

    for 4-5 ECS.

    Work to be

    expedited by

    new

    contractor

    Slow progress due

    to COVID 19

    pandemic and

    lockdown and

    weather

    disturbances may

    delay the works

  • 12

    UK/IDIPT/III/DD

    N/03

    Rural Tourism

    M/s Navya

    Associates

    JV with M/s

    Agarwal

    Brothers

    Name of Village

    Proposed Hardware Components

    Tungnath Restoration of Temple through removal of incongruent additions and preservative coating and foundation retrofitting of main temple(Dropped)

    Removal and reconstruction of bulged retaining walls

    Shivalinga water/Rain water disposal system of the temple/premises

    Up gradation of main entrance gateway

    Improvement of pathway upto new gateway structure

    Kaviltha Upgradation of Pathway

    Construction of Guest House

    Renovation of KalidasSmarak& Community centre

    Repair of existing Parking facility

    Repairing of Existing Water source

    Renovation of PanchayatBhawan

    Landscaping

    Informative Signage

    Directional Signage

    Renovation of Existing gate and Railing

    Furniture For Kaviltha Guest House and Kaviltha

    02.08.16 15.09.2020 1.Tungnath:-

    Construction of

    courtyard area,

    rest shelter roof,

    direction signage,

    main entrance

    gate, railing and

    bulged retaining

    wall re-

    construction.

    2.Kaviltha:

    finishing work is

    in progress.

    Tile work at water

    source in

    progress.

    Panchayat

    bhawan premises

    work in progress

    Gate and railing

    work in progress.

    80%

    Restoration

    of Temple

    through

    removal of

    incongruent

    additions and

    preservative

    coating and

    foundation

    retrofitting of

    main temple

    has been

    dropped

  • 13

    Library

    Solar light and Water Heater System

    Phalasi Up gradation of Pedestrian Pathway and providing retaining &breast Wall

    Construction of Toilet Block

    Directional and Informative Signage

    Solar Lighting

    Railing

    Sitting Benches

    Durgadhar (Bora)

    Up gradation of Pedestrian Pathway and covering shelter

    Construction of Toilet Block

    Directional and Informative Signage

    Solar Lighting

    Railing and Sitting Benches

    Renovation of Existing Panchayat bhawan

    Harshil

    Up gradation of Pedestrian Pathway and Pathway Covering Shelter and Construction of Retaining Walls

    Up gradation of existing Sitting Arrangement

    New Railing

    Renovation of Existing Entrance Gate

    Renovation of Existing Rain Shelter, Temple

    3.Phalasi:-

    project is handed

    over.

    4.Bora: Floor tile

    work at

    panchayat

    bhawan in

    progress.

    5.Harshil:-

    Directional

    signage and final

    finishing work in

    progress.

  • 14

    Premises, Parking Area and Water Tank

    Informative and Directional Signage

    Beautification of Existing Helipad

    Protection wall for Camping Site

    Solar Lighting

    Mukhwa Upgradation of existing Pedestrian Pathway and Construction of Pathway Covering Shelter, retaining and breast wall

    New Sitting Arrangement

    Renovation of Existing PanchayatBhawan& Temple Premises

    Construction Parking facility

    Entrance Gate

    Toilet Block -

    Directional and Informative Signage

    Railing

    Kanakchori (Pogatha)

    Upgradation of Pedestrian Pathway and Pathway Covering Shelter

    Retaining & Breast Wall

    Toilet Block - Small

    Directional and Informative Signage

    Solar Lighting

    Sitting Bench

    Niti Construction of Community Centre

    Renovation of open air

    6.Mukhwa:

    Directional

    signage and final

    finishing work in

    progress.

    7. Kanakchori

    Finishing work in

    progress.

    8. Niti:- finishing

    work is in

    progress.

  • 15

    theater and compound wall

    Construction of Parking facility

    Upgradation of gram panchayat bhawan

    Directional and Informative Signage

    upgradation of village Pathway with KC drain

    Seating Benches

    Toilet

    Upgradation of existing View Points

    Provision of Dust Bins

    Solar Light

    Erection of Glass House (View points)

    Lata No Hardware components proposed

    Additional Scope:

    Construction of Toilets at Chinyalisod, Barkot, Badatipul, Damta, Jankichatti, Bhatwadi Guptkashi, Ukhimat, Agastmuni, Narkota, Kalimath, Kanakchauri

    Construction of

    Toilet work in

    progress at

    Chinyalisod,

    Barkot,

    Badatipul,

    Damta,

    Jankichatti

    Bhatwadi

    Guptakashi

    Ukhimat

    Agastmuni

    Narkota

    Kalimath

    Kanakchauri

    39% progress

    of additional

    scope

    UK/IDIPT/III/BH

    T/01 Lot 1

    Conservation

    of Cultural

    Heritage and

    urban place

    making in

    M/s

    Simplex

    Project

    Limited

    407,

    Skipper

    Corner, 88

    Nehru

    Place, New

    Restoration of

    • Catholic Church

    • Methodist church

    • Bishop Shaw(Dropped)

    • Library Building

    • Municipality Building

    • DSA Flat

    • Gandhi Ashram- Takula

    • New Club(Dropped)

    19.10.2015

    30.06.2019

    Works of given components are not completed by the Contractor; new contractor ll resume the works 1) Library 2) DSA Flat

    66.18%

    Given

    components

    have been

    dropped:

    Bishop Shaw

    New Club

    Repaving of

    Nil

    Works may be

    delayed due to

    COVID 19

    Pandemic

  • 16

    Nainital Lot-1

    (Contract was

    terminated and

    balance works

    were awarded to

    new contractor)

    Delhi -

    110019,

    India

    M/s Bansal

    Constructio

    n,

    Mohallakan

    oongoyan,

    charthawal,

    M.Nagar

    (UP)

    • DSB College Chapel

    • Treatment of Dam Wall

    • Repaving of Upper Mall(Dropped)

    • Rickshaw Stand(Dropped)

    • Lake Front Development

    • Park Development(Dropped)

    • Railing & Band Stand

    • Construction of Toilets in Nainital-

    Cheena baba and National Hotel

    • Improvement of High mass light

    Electricity(Dropped)

    • Nature Heritage Trail: o Wayside furniture at pause points o Rain shelters at viewing points o Camping sites o Provision of portable toilets at

    appropriate points (water pipeline available)

    o Signages (informative &regulatory)

    Mechanical car parking component/

    package UK/IDIPT/III/BHT/01 Lot 2 has

    been dropped

    LOA issued to

    new

    contractor in

    March 2020.

    3) Methodist church

    4) Catholic church:

    5) DSB chapel- Pointing work

    6) Municipal building-

    10%.

    Upper Mall

    Rickshaw

    Stand

    Park

    Development

    &

    Improvement

    of High mass

    light Electricity

  • 17

    UK/IDIPT/III/BH

    T/03

    Restoration

    and adaptive

    reuse of

    Almora Fort

    (Rani Mahal)1

    The subproject

    was bid out in

    02 packages

    (i) Rani Mahal

    UK/IDIPT/III/BH

    T/03

    (Contract was

    terminated and

    balance works

    were awarded to

    new contractor)

    M/s

    Simplex

    Project

    Limited

    407,

    Skipper

    Corner, 88

    Nehru

    Place, New

    Delhi -

    110019,

    India

    M/s Satya

    Sai

    Builders &

    Const.

    (i) Scope of Rani Mahal package is

    • Restoration of Rani Mahal

    • Restoration of Courtyard+ RamshilaTemple

    • Restoration of Craft Centre + Toilet

    • Restoration of SDM office

    • Restoration of Fort Walls

    • Signage Plan

    • Civil work of Collectorate building in Almora

    • Site Development and Landscaping

    • Sanitary&

    • Electrical Works

    • Internal roads

    19.10.2015

    LOA to the new

    contractor

    issued on Jan

    2020

    31.12.2019

    Ramshila temple work in progress, Fort walls cleaning and washing in progress, Collectorate building, site development and landscaping, Sanitary and electrical works in progress.

    57.89%

    22%

    -

    works may be

    delayed due to

    COVID 19

    Pandemic

    (ii) Malla Mahal

    UK/IDIPT/III/BH

    T/06

    M/s Satya

    Sai

    Builders&

    Const.

    Following works shall be taken up in (ii) Malla Mahal package which is awarded

    • Museum on Kumaon culture in Malla Mahal and

    • Removal or concealment some buildings through strategic landscaping and foliage coverage of structures

    04-02-2019

    03-02-2020

    Work not yet

    started

    0.0%

    No Change

    -

    -

  • 18

    UK/IDIPT/III/BH

    T/05

    Restoration

    and adaptive

    reuse of

    Champawat

    Fort (Banasur)

    (Contract was

    terminated and

    balance works

    were included in

    the scope of

    new contractor)

    M/s

    Simplex

    Project

    Limited

    407,

    Skipper

    Corner, 88

    Nehru

    Place, New

    Delhi -

    110019,

    India

    M/s Satya

    Sai

    Builders &

    Constructio

    ns

    Project has 02 packages.

    Banasur Fort:

    • Removal of existing and undesired structures and relocation.

    • Remodelling and reconstruction of existing structures, shed on hilltop for café

    Construction of new Tehsil building

    • G+2 Tehsil building in 1400 m2 out of total land of 5400 m2. (Land to be transfer to Tourism dept. from KNVN)

    • 1 number Type II quarter and 1 number Type IV quarter

    • Garage facility and car parking

    • Litigation room

    • Boundary wall for whole area

    • Approach road to site Works in Rajbhunga have been dropped

    Present Scope of works includes the

    completion of few components to be taken up by the new contractor

    19.10.2015

    LOA issued

    on Jan 2020

    31.12.2019 work is in

    progress.

    26.65%

    23.44%

    Components

    of GoluDevta

    and Guru

    Gorakhnath

    temple have

    been

    dropped and

    Construction

    of New Tehsil

    building

    works have

    been

    dropped

    - -

    Restoration

    and Adaptive

    Reuse of

    Pithoragarh

    M/S Cox

    Infratech

    Private

    Limited in

    • New multi-level car parking near Dev Singh Ground

    • Construction of additional block near

    05.07.2016 28.02.2020

    Multilevel Parking ACP sheet work in progress.

    93% (i) 01

    additional

    block was

    added to the

    Appropriate

    measures

    have been

    taken for

    Works may be

    delayed due to

    COVID 19

  • 19

    Fort Phase II

    UK/IDIPT/III/BH

    T/07

    JV with

    Conaech

    Associates

    multi-level car parking site (Dev Singh Ground)

    • Tourist Rest House by converting tehsil staff quarter in Fort premises

    • New Tehsil office building

    • Construction of Patwari and Kanoongo chowki on Bypass Tanakpur road

    • Accommodation for rehabilitation of Tehsil Staff Quarter Type IV – 1 no and Type II-6 nos.

    • Signage and Waste bins

    Addendum for the additional components was submitted to ADB on 11.09.19 and approved 01.10.2019

    Tehsil building and staff quarter Painting work. Railing work. Plaster work. Water proofing.

    Multi-level

    car parking.

    (ii)

    Construction

    of Patwari and

    Kanoongo

    Chowki on

    bypass

    Tanakpur

    road.

    fulfillment of

    the

    objectives.

    pandemic

  • 20

    Name & No. of

    Package

    Name of the

    contractor Scope of Works under Package

    Starting Date(land clearance) and

    schedule date of completion Type of works

    Continued at

    Present

    Progress

    % age

    Expected

    change

    from

    Approved

    scope

    Fulfillment of

    objective

    Type of

    remedial

    measures

    needed

    Key assumption and risk

    affect attainment the

    objective Starting date Date of

    Completion

    UK/IDIPT-III/KOT/01

    Creation of

    Pedestrian Route

    for Pilgrims and

    Tourists in Haridwar

    M/s SS

    Infratech Jv

    Tikola

    Nagar,

    Roorkee

    a) Development of a pedestrian route or pathway for movement of pilgrims and tourist from near Mayapur Regulator to Jatwara Bridge and near Solani park to Mewar bridge at Roorkee. Total length of pedestrian pathway to be developed is 6.5 km. The entire stretch of 6.5 km length (from near Mayapur Regulator to Jathwara bridge and Solani Park to Mewar bridge), the existing KanwarPatri (Route followed by Kanwarias) will be developed to a pedestrian pathway). Landscaping, sitting arrangements, murals, etc. on the proposed pedestrian pathway. b) Landscaping, sitting arrangements, murals etc. c) Lighting or illumination on the proposed pedestrian route of 6.5 km. d) Providing safety hand railing on the pedestrian route on canal side.

    e) Providing solid waste bins on the side of proposed pedestrian route. f) Providing a toilet complex and drinking water facility on side of the proposed pedestrian route near Shankaracharya Chowk. g) At one location near the proposed pedestrian pathway (before LoheKaPul on railway track near Jwalapur) a multi

    22/07/2015 28.02.2020 • landscaping,

    sitting

    arrangement,

    safety hand

    railing, solid

    waste bins, and

    drinking water

    facility work in

    progress.

    • Floor tile

    finishing work

    at integrated

    complex.

    • Aluminum work

    of doors and

    windows

    finishing work

    at Multi Facility

    (integrated)

    complex.

    90%

    Foot Over

    bridge over

    NH-58 at

    Manglaur

    Crossing

    dropped

    due to

    work done

    by NHAI

    on the

    same

    location.

    FOB

    dropped

    due to

    delays and

    huge cost

    escalation

    by

    Railways.

    Parking

    facility for

    approx.

    120 ECS

    adjacent to

    the existing

    Work force

    to be

    increased by

    contractor

  • 21

    facility complex will be developed which will include a toilet complex, drinking water fountain, bathing and sanitation facilities, rest shelter, food distribution centre, police control room, solid waste bins, compound wall with entrance gate, landscaping, etc. h) Construction of a foot over bridge over Railway track near Jwalapur. (Dropped) i) Construction of a foot over bridge over National Highway (NH-58)atManglour Cross.(Dropped) j) Installation of tourist Signages on KanwarPatri from Har Ki Pauri to Mangalour Cross. Total length of the stretch of KanwarPatri to be taken up for the signage installation works is 42 km. Additional Scope:

    k) Construction of Toilets and TIC

    Construction of Toilet at

    Sahastradhara, Tapkeshwar, Juddo,

    Hatiyari and Construction of TIC at

    Jankichatti, Raithal, Barsu,

    Raturisera, Tapkeshwar,

    Sahastradhara, Karnprayag

    Construction

    of Toilets in

    Dehradun

    Sahastradhara Tapkeshwar Juddo Hatiyari Construction of TIC Jankichatti Raithal Barsu Raturisera Tapkeshwar Sahastradhara Karnprayag

    constructio

    n site of

    integrated

    complex.

    Addendum

    to the IEE

    was

    submitted

    to ADB

    and

    approved

    on

    14.01.2020

  • 22

    Name & No. of

    Package

    Name of the

    contractor Scope of Works under Package

    Starting Date(land clearance) and

    schedule date of completion

    Type of works

    Continued at

    Present

    Progress

    % age

    Expected

    change

    from

    Approved

    scope

    Fulfillment of

    objective

    Type of

    remedial

    measures

    needed

    Key assumption and risk

    affect attainment the

    objective

    Starting date Date of

    Completion

    UK/IDIPT-III/KOT/02

    Development of

    Tourism

    Infrastructure in

    Sem Mukhem

    (Tehri)

    M/s

    Mangalam

    and

    Constructio

    n Company

    in JV with

    Sunil Garg

    Company

    Meerut

    The main sub-project components

    include the following:

    i. Dharamshala/ rest shelter at fair ground.

    ii. Toilet complex at fair ground including septic tank with soak pit.

    iii. Water supply Arrangement at Fair Ground

    iv. Landscaping works at fair ground. Locally available materials shall be used for construction. The landscaping elements shall incorporate local foliages and flora of fairground so that the built environment is in sync with the background

    v. Development of pathway from main road to fair ground.

    vi. Solar lighting system along with normal outdoor lights is proposed at fair ground. Electricity source for illumination works is from Uttarakhand Power Corporation Limited and the same is reliable

    vii. Development of existing small lake near fair ground. The existing small lake covers about 1500 sqm. area, while water spread area is 500

    22/08/2015 31/03/2018 • Dharamshala/

    Rest shelter

    completed

    • Rest shed

    completed

    • Solid waste

    bins and

    compost pits

    completed

    • Solar lighting

    completed

    • Pathway at fair

    ground

    completed

    • Pathway for

    Mukhem

    Village is

    completed

    • Pujari cottage

    completed

    • Renovation of

    100% Canopy for

    a length of

    147 m,

    component

    dropped

    Appropriate

    measures

    have been

    taken for

    fulfillment of

    the

    objectives

    Not envisaged

  • 23

    sqm. viii. Solid waste bins and compost pits

    at Fair Ground. Solid wastes from Fair ground and Mandir complex will be collected in collection bins and ultimately dumped in to compost pit to be developed in the sub project.

    ix. Murals depicting the story of Lord Krishna at 4 locations.

    x. Providing solid waste bins and construction of compost pit in Mandir Complex. Solid wastes from Mandir complex will be collected in collection bins and ultimately dumped in to compost pit to be developed in the sub project.

    xi. Solar light at the temple complex. xii. Canopy for a length of 147 m on

    pathway in between fair ground and Nagraj Temple.

    xiii. Hand rails and finishing works on pathway between fair ground and temple complex.

    xiv. Facilities planned at Mukhem village are:

    a) Renovation of existing Temple in Mukhem village.

    b) Renovation of existing entry gate of Mukhem village.

    c) Development of internal roads in Mukhem village.

    d) Expansion of existing pipe water supply network.

    e) Installation of solar lighting system, f) Solid waste management with

    compost pits in Mukhem village. g) Tourism Signages on the 23Km

    road from Kodar to Fair Ground.

    Mukhem village

    temple

    completed.

    • Jheel work

    completed.

    • Septic tank

    completed.

    • Plumbing work

    completed

    • Landscaping

    work

    completed.

  • 24

    Name & No. of

    Package

    Name of the

    contractor Scope of Works under Package

    Starting Date(land clearance) and

    schedule date of completion Type of works

    Continued at

    Present

    Progress

    % age

    Expected

    change

    from

    Approved

    scope

    Fulfillment of

    objective

    Type of

    remedial

    measures

    needed

    Key assumption and risk

    affect attainment the

    objective Starting date Date of

    Completion

    UK/IDIPT-III/KOT/03

    Development of

    Rural Tourism in

    District Tehri and

    Pauri

    M/s Bansal

    Constructio

    n J/v M/s

    Technical

    Const.

    Company

    The main sub-project

    components include the

    following:

    Kanwashram

    • Construction of Lake

    • Embankment Wall

    • Railing work

    • Development of Island

    • Drainage works

    • Gazebo (7 nos)

    • Car Parking

    • Boundary Wall

    • Development of Kanva rishi ashram

    • Multi Facility Centre

    • Amphitheatre

    • Security Room

    • Bridge

    • Electrical work including water fountain

    • Outdoor Gym Equipment’s

    • Equipment’s for Children Park

    • Peddle Boat

    • Garden Benches

    • Dustbins Other Villages

    1. Kalalghati

    • Toilet Block (1no)

    • 700 m Water distribution line

    21/05/2018 20/11/2019 Site clearance

    works and

    construction of

    retaining wall was

    done till March,

    2019.

    Work held up

    since then due to

    PIL filed against

    the ongoing

    works on

    08.03.2019 and

    stay orders by the

    High Court

    15% Dropped till

    High Court

    verdict.

    Directions

    from Hon’ble

    High Court/

    other line

    agencies

    Irrigation

    Dept. to be

    complied

    with.

    Works may be delayed

    till the High court

    verdict is obtained.

  • 25

    • Solar Light,Garbage Bins 2. Mavakot

    • Training cum Production Centre along with toilet (1no)

    • Toilet Complex at Mela Ground (1no)

    • Drinking water fountain at Mela Ground (1 no)

    • Seating arrangement around tree at Mela Ground.

    • Garbage Bins (2 nos)

    • Electrical work for production centre. 3. Jaiharikhal

    • Urinal Complex (1 no)

    • Bench with shed (5 nos)

    • Solar lightning system.

    • Garbage Bins (4 nos)

    • Sign Board/Name Plate etc 4. Sendhikhal

    • Seating arrangement around tree near temple.

    • Hand Railing (300 m)

    • Bench with shed (5 nos)

    • Solar lightning system.

    • Garbage Bins (3 nos)

    • Sign Board/Name Plate etc 5. Kuthar

    • Training cum Production Centre along with toilet (1no)

    • Toilet Complex at Mela Ground (1no)

    • Repairing of existing Water Vat.

    • Desilting of existing water body and its side Development

    • Seating Arrangement along the tree

    • Fencing with Green Net -100m

    • Sign Board/Name plate etc.

    • Solar Lighting System.

    • Garbage Bins - 3 Nos

  • 26

    • Electrical Works 6. Gajana

    • Seating Arrangement (2 nos)

    • Hand Railing for trek (200 m)

    • Bench with shed (2 nos)

    • Solar Lightning System (5 nos)

    • Garbage Bins (2 nos)

    • Sign Board/Name Plate etc. 7. Chopariyal

    • Training cum Production Centre along with toilet (1no)

    • Kiosk (3 x 3 m)

    • Solar Lightning System (5 nos)

    • Garbage Bins (2 nos)

    • Sign Board/Name Plate etc.

    • Electrical work for production centre and kiosk

    8. Tipri

    • Toilet Block (1 no)

    • Bench with shed

    • Solar Lightning System

    • Garbage Bins (2 nos)

    • Sign Board/Name Plate etc.

    • Electrical work for toilet block 9. Mukhem

    • Bench with shed (5 nos)

    • Pathway (150 m)

    • Garbage Bins

    • Sign Board/Name Plate etc.

  • 27

    Name & No. of

    Package

    Name of the

    contractor Scope of Works under Package

    Starting Date(land clearance) and

    schedule date of completion

    Type of works

    Continued at

    Present

    Progress

    % age

    Expected

    change

    from

    Approved

    scope

    Fulfillment of

    objective

    Type of

    remedial

    measures

    needed

    Key assumption and risk

    affect attainment the

    objective

    Starting date

    Date of

    Completion

    UKIDIPT/III/ GEN/03

    Development of

    Traditional Medicine

    and Yoga Training

    centers

    M/s Bansal

    Const.,

    Muzaffarna

    gar

    Development of Traditional Medicine Panchkarma and Yoga Centers at 4 TRHs/Resorts operated by GMVN in Garhwal Region (Dhanaulti, Rishikesh, Lansdowne, Kaudiyala) and at 5 TRHs/ Resorts operated by KMVN (Chiliyanaula, Kausani, Choukori, Naukuchiyatal and Sukhatal). New construction of above facilities is to be carried out in Kaudiyala, Naukuchiyatal and Lansdowne.In the other locations facilities are planned within existing resorts by after interior refurbishment and slight alterations. The project progress includes civil component and procurements of equipments in a ratio of 60:40. Dhanaulti Sukhatal Chiliyanaula Kausani Chaukori Ganga Resort Lansdowne Naukuchiyatal Kaudiyala

    08/03/2017 31/12/2019 Location wise

    Progress update

    TRH

    Dhanaulti:workc

    ompleted

    TRH

    Sukhatal:Workco

    mpleted

    TRH Kausani,

    Work completed

    TRH

    Chiliyanaula

    Work completed

    TRH Chaukori

    Work completed

    TRH Ganga

    Resort

    Work Completed

    TRH Kaudiyala

    Work completed

    TRH Lansdowne

    Work completed

    TRH

    Naukuchiatal

    Work completed

    100%

    100%

    100%

    100%

    100%

    100%

    100%

    100%

    100%

    01 more

    location;

    Kaudiyala

    was added

    to the

    scope.

    Appropriate

    measures

    have been

    taken for

    fulfillment of

    the

    objectives

    Work completed

  • 28

    Name & No. of

    Package

    Name of the

    contractor Scope of Works under Package

    Starting Date(land clearance) and

    schedule date of completion

    Type of works

    Continued at

    Present

    Progress

    % age

    Expected

    change

    from

    Approved

    scope

    Fulfillment of

    objective

    Type of

    remedial

    measures

    needed

    Key assumption and risk

    affect attainment the

    objective

    Starting date

    Date of

    Completion

    UK/IDIPT/III/GEN/04

    Development of

    “George Everest

    Heritage Park”

    M/s Arun

    Constructio

    ns

    • Restoration & renovation of Sir George cottage & Observatory.

    • Cartographic Museum.

    • Approach road.

    • Trek route.

    • Public convenience.

    • Landscaping.

    • Parking.

    • Water supply & rain water harvesting.

    • Safeguards/selfie points

    • Interpretation centre

    18/1/2019 17/4/2020 Repair of

    approach road in

    progress

    34% Appropriate

    measures

    have been

    taken for

    fulfillment of

    the

    objectives

    Components entailing

    new works may be

    dropped if clearance of

    MoEFCC is not obtained

    Any other information useful for assessing environmental performance of the project:

    9. No additional information during this period

  • 29

    2. Compliance Status

    10. Status of Compliance with EARF/ADB Procedures is shown in Table 3.

    Table 3: Status of Compliance with EARF/ADB Procedures

    S.No

    Name & No. of Package Environment

    Category Status of preparation of IEE

    Status of Approval

    by ADB

    Date of

    Approval

    Further Action

    needed For

    Compliance &

    Responsibility

    1** UK/IDIPT-III/ DDN/01 B Completed and approved Approved 03.08.2015

    Regular monitoring and reporting of EMP

    2 UK/IDIPT-III/ DDN/02 B Completed and approved Approved 01.09.2015

    Regular monitoring and reporting of EMP

    3** UK/IDIPT-III/DDN/03 B Completed and approved Approved 25.05.2016

    Regular monitoring and reporting of EMP

    4 UK/IDIPT/III/BHT/01

    B Completed and approved Approved 08.09.2015 Regular monitoring and reporting of EMP

    5* UK/IDIPT/III/BHT/03 UK/IDIPT/III/BHT/06

    B Completed and approved Approved 09.07.2015 Regular monitoring and reporting of EMP

    6 UK/IDIPT/III/BHT/05 B Completed and approved Approved 06.08.2015

    Regular monitoring and reporting of EMP

    7

    UK/IDIPT/III/BHT/07 B Updated IEE due to addition in

    scope was submitted and

    approved

    Approved

    01.10.2019

    Regular monitoring and reporting of EMP

    8**

    UK/IDIPT-III/KOT/ 01 B

    Completed and approved

    Addendum to IEE due to

    addition in scope was

    submitted on 31.12.2019

    Approved 11.05.2015 Regular monitoring and reporting of EMP

    9 UK/IDIPT-III/KOT/ 02 B Completed and approved Approved 25.05.2015

    Regular monitoring and reporting of EMP

  • 30

    S.No

    Name & No. of Package Environment

    Category Status of preparation of IEE

    Status of Approval

    by ADB

    Date of

    Approval

    Further Action

    needed For

    Compliance &

    Responsibility

    10 UK/IDIPT-III/KOT/ 03 B Completed and approved Approved 28.03.2017

    Regular monitoring and reporting of EMP

    11

    UK/IDIPT/III/GEN/03 B

    Completed and approved

    Addendum to the IEE due to

    addition in scope (new location

    Kaudiyala added) was

    submitted and approved by

    ADB.

    Approved

    Approved

    03.03.2017

    11.12.2018

    Regular monitoring and

    reporting of EMP

    12 UK/IDIPT/III/GEN/04 B Completed and approved Approved 11.01.2019 Regular monitoring and

    reporting of EMP

    13 **Up gradation, Repair and Restoration of

    Toilet facilities and Tourist Information

    Centers Along Chardham routes in the

    state of Uttarakhand

    B Completed and approved Approved 19.02.2020 Regular monitoring and

    reporting of EMP

    *S.no 5 Project bifurcated into 02 packages. (Dropped packages have been removed from the list.)

    **Works indicated at S.no 13 “Up gradation, Repair and Restoration of Toilet facilities and Tourist Information Centers along Chardham routes in the state of Uttarakhand has been

    added to the scope of existing 03 contract packages listed at s.no1.Aradhya Engineers, s.no3.NavyaAssociates and s.no8. S.S Infratech JV.

  • 31

    3. Compliance status with National/ State/ Local statutory environmental requirements

    11. Status of Compliance with National/ State/ Local statutory environmental requirements is shown in Table 4.

    Table 4: Status of Environment, Forest and other Clearance

    Work (Package No.) Applicable Legislation/Type of

    clearance Clearance Given by and date Subject/Issue Remarks/Action needed

    UK/IDIPT-III/ DDN/01

    Development of Tourism Infrastructure in Kartikeya Swami Circuit (Lot-1) (Tungeshwar & Durgadhar Temple)

    No environmental and forest clearance required. No requirement of NOC from ASI

    Not applicable

    UK/IDIPT-III/ DDN/02

    Development of Tourism Infrastructure in

    Kartikeya Swami Circuit (Kartikeya Swami

    Temple)

    Forest clearance required. No

    requirement of Environmental

    Clearance or NOC from ASI

    Clearance received from

    MoEF&CC dt. 23.09.16

    Kartikeya Swami Temple and pathway

    are located in Reserve Forest area, for

    which forest clearance was needed.

    Works to be done as per

    Clearance conditions.

    UK/IDIPT-III/DDN/03

    Conservation and Development of Rural

    Tourism in district Rudraprayag, Chamoli

    and Uttarkashi

    No Environmental and forest

    clearance required. NOC required

    from Forest Dept. for Tungnath

    location. No requirement of NOC

    from ASI.

    NOC obtained from Forest

    Department, GoUk dt. 08/09/14

    Out of 9 rural sites, Tungnath lies in

    buffer zone of Kedarnath Wildlife

    Sanctuary

    NOC received from Forest Department

    Works to be done as per

    conditions of NOC given by the

    Forest department.

    UK/IDIPT-III/KOT/01 Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar

    No environmental and forest clearance required. No requirement of NOC from ASI.

    Not applicable

    UK/IDIPT-III/KOT/02 Development of Tourism Infrastructure in SemMukhem

    No Environmental and forest clearance required. (Only a minor canopy component was proposed in reserve forest since trek over which canopy has to be installed, falls in reserve forest). The same has been dropped.

    Not required The project is for creation of Tourism Infrastructure in SemMukhem. No forest land acquisition involved, so no forest clearance required. The project site is not in ASI regulated Zone.

    The canopy component has been dropped

  • 32

    Work (Package No.) Applicable Legislation/Type of

    clearance Clearance Given by and date Subject/Issue Remarks/Action needed

    UK/IDIPT-III/KOT/03 Development of Rural Tourism Infrastructure in Pauri and Tehri District

    No Environmental clearance required. Forest clearance taken for works in Kanwashram

    Forest Clearance obtained on 17.05.16

    Kanwashram site falls in Reserve Forest Site clearance and construction

    works were carried out till March,

    2019. Work held up since then due

    to PIL filed against the ongoing

    works on 08.03.2019 and stay

    orders by the High Court

    UK/IDIPT-III/BHT/01 Conservation of Cultural Heritage and Urban Place making in Nainital Lot 1

    NOC from PWD, forest clearance required for pre fab toilets and viewpoints on nature trail (Tiffin top and Tanki China). No requirement of NOC from ASI.

    NOC obtained from PWD

    Forest Clearance for nature trail for Tanki Cheena obtained.

    Forest clearance for Tiffin Top under process.

    The project is for conservation of cultural heritage involving mostly repair, restoration works. There are 02 nature trails falling in reserve forest where portable toilet and viewpoints are proposed. So forest clearance required. The project site is not in ASI regulated Zone.

    Works in Tiffin Top to commence only after obtaining the Forest Clearance.

    UK/IDIPT-III/BHT/03 Conservation and adaptive re-use of Almora Fort (Rani Mahal)

    No Environmental and forest clearance required. No requirement of NOC from ASI.

    Not applicable - -

    UK/IDIPT/III/BHT/06 Restoration and Adaptive reuse of Almora Fort (MallaMahal)

    No Environmental and forest clearance required

    Not applicable - -

    UK/IDIPT-III/BHT/05 Conservation and adaptive re-use of Champawat Fort (Banasur)

    No Environmental and forest clearance required. Requirement of NOC from State ASI for Banasur Fort.

    NOC obtained vide letter dt. 5th Dec, 2014.

    Banasur Fort is a State Protected Monument and the custodian is State Culture Dept. NOC received from State Culture Dept.

    Works as per NOC. Works should not interfere with the original character of the Fort structure.

    UK/IDIPT/III/BHT/07 Restoration, Adaptive Reuse and Revitalization of Pithoragarh Fort

    No Environmental and forest clearance required for the additional scope.

    NOCs from line agencies obtained

    NOC from District Administration for shifting Tehsil office NOC from Executive Engineer Nagarpalika Parishad Pithoragarh

    NOC from District Sport officer

    The project is for conservation of cultural heritage involving mostly repair, restoration works. Tehsil was housed in the Fort campus, which is to be relocated to carry on repair and restoration works in the Fort

    Works to be done as per conditions of NOC given by line agencies and in line with their suggestions

  • 33

    Work (Package No.) Applicable Legislation/Type of

    clearance Clearance Given by and date Subject/Issue Remarks/Action needed

    UKIDIPT/III/GEN/03

    Development of Traditional medicine and Yoga Training Centers

    No Environmental and forest clearance required

    Not applicable - No action needed

    UK/IDIPT/III/GEN/04/

    Development of “George Everest Heritage Park”

    forest clearance required Under process The site is a notified private forest as per UP private forest act 1948 clause (3) of section 3 of Govt. notification no.1927/XIV-134-47. Act is not applicable for the renovation and restoration of existing structures, but for all the new components proposed in the subproject this act is applicable and hence Forest clearance is to be taken before commencement of the works. Accordingly application for clearance is under process

    New works will be taken up only after getting forest clearance for new works.

    Up gradation, Repair and Restoration of Toilet facilities and Tourist Information Centers Along Chardham routes in the state of Uttarakhand

    No Environmental and forest clearance required

    Not applicable - No action needed.

  • 34

    4. Compliance status with the environmental covenants as stipulated in the Loan Agreement

    12. The status of compliance with environmental loan covenants is presented in Table 5.

    Table 5: Status of Compliance with Environmental Loan Covenants S. No Covenants Compliance

    1. The Borrower and the States shall ensure that the preparation, design, construction, implementation, operation and

    decommissioning of each Subproject and all Project facilities comply with (a) all applicable laws and regulations of the

    Borrower and the States relating to environment, health, and safety; (b) the Environment Safeguards; (c) the EAFR; and (d) all

    measures and requirements set forth in the respective IEE and EMP, and any corrective or preventative actions set forth in a

    Safeguard Monitoring Report.

    Compliance of (a) all applicable laws and regulations of the Borrower

    and the States relating to environment, health, and safety (b)

    Environment Safeguards; (c) the EARF; and (d) EMP is being

    ensured during sub projects implementation.

    Safeguards – Related Provisions in Bidding Documents and Works Contracts

    The States shall ensure that all bidding documents and contracts for Works contain provisions that require contractors to:

    (a) Comply with the measures and requirement relevant to the contractor set forth in the IEE, the EMPs, any RO and any

    IPP (to the extent they concern impacts on affected people during construction), and any corrective or preventative

    actions set out in a Safeguard Monitoring Report;

    (b) make available a budget for all such environment and social measures;

    © provide the relevant State with a written notice of any unanticipated environmental, resettlement or indigenous peoples

    risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the

    IEE, the EMP, the or the IPP (if any): and

    (d) Fully reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the

    completion of construction.

    Full EMP made part of the contract agreements of respective subprojects, thus its provisions being complied with.

    Orientation sessions are being carried out in each site for better understanding of Safeguards Compliance by the Contractor Environmental monitoring and mitigation costs allocated/ incorporated in contract agreements. No such environmental impact has been identified so for that was not considered in the IEE and in the EMP. (If any such impact arises in future, will be suitably addressed) All the areas that if disturbed by construction activities will be restored to pre-project condition by the contractors.

    Safeguards Monitoring and Reporting

    11.The States shall do the following:

    (a) Submit semi-annual Safeguards Monitoring Reports to ADB and disclose relevant information from such reports to

    affected persons promptly upon submission;

    (b) if any unanticipated environment and/or social risks and impacts arise during construction, implementation or operation of

    the Project that were not considered in the IEE, the EMP, any RP or any IPP, promptly inform ADB of the occurrence of

    such risks or impacts, with detailed description of the event and proposed corrective action plan; and Report any breach of

    compliance with the measures and requirements set forth in the EMP, any IPP promptly after becoming aware of the

    breach.

    The tenth semiannual report for Loan No. 3223 IND is submitted herewith. Subsequent reports will be submitted on time. In case of any unanticipated environmental risks and impacts arise, that shall be immediately informed to ADB with detailed description of the event and proposed corrective action plan. Breach will be reported to ADB immediately after becoming aware of it.

  • 35

    5. Compliance Status with Environment Management and Monitoring Plans as stipulated in the environmental documentation as agreed with ADB.

    13. The compliance Status with Environment Management and Monitoring Plan is shown in Table 6.

    Table 6: EMP Implementation Status

    S.

    No Sub Project Name

    EMP Part of Contract Documents

    (Yes/No)

    EMP being Implemented (Yes/ No)

    Status of EMP Implementation (Excellent/ Satisfactory/ Partially Satisfactory/ Below Satisfaction)

    Actions Proposed/ Additional Corrective Measures Required

    1 UK/IDIPT-III/ DDN/01 Yes Yes Satisfactory No additional Corrective Measures required.

    2 UK/IDIPT-III/ DDN/02 Yes Yes Satisfactory No additional Corrective Measures required.

    3 UK/IDIPT-III/ DDN/03 Yes Yes Satisfactory No additional Corrective Measures required.

    4 UK/IDIPT/III/BHT/01 Conservation of Cultural Heritage and Urban Place making in Nainital Lot 1

    Yes Contract Terminated due to contractual issues, Rebidding for the balance work was done. LOA issued to new contractor in March 2020. Due to COVID 19 pandemic works commenced in June 2020. Satisfactory

    No additional Corrective Measures required

    5 UK/IDIPT/III/BHT/03 Conservation and adaptive re-use of Almora Fort (Rani Mahal)

    Yes Contract Terminated due to contractual issues, rebidding was done. LOA issued to new contractor in January 2020. Due to COVID 19 pandemic works commenced in June 2020 Satisfactory

    No additional Corrective Measures required

    6 UK/IDIPT/III/BHT/06 Restoration and adaptive reuse of Almora Fort (Malla Mahal)

    Work not started NA

    7 UK/IDIPT/III/BHT/05 Conservation and adaptive re-use of Champawat Fort (Banasur)

    Yes Contract terminated due to technical and contractual issues. LOA issued to new contractor in January 2020. Due to COVID pandemic works commenced on June 2020 Satisfactory

    No additional Corrective Measures required

  • 36

    S.

    No Sub Project Name

    EMP Part of Contract Documents

    (Yes/No)

    EMP being Implemented (Yes/ No)

    Status of EMP Implementation (Excellent/ Satisfactory/ Partially Satisfactory/ Below Satisfaction)

    Actions Proposed/ Additional Corrective Measures Required

    8 UK/IDIPT/III/BHT/07 Restoration, Adaptive Reuse and Revitalization of Pithoragarh Fort Phase II

    Yes Yes Satisfactory No additional Corrective Measures required.

    9 UK/IDIPT-III/KOT/01 Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar

    Yes Yes Satisfactory No additional Corrective Measures required.

    10 UK/IDIPT-III/KOT/02 Development of Tourism Infrastructure in Sem Mukhem

    Yes Yes Work completed NA

    11 UK/IDIPT-III/KOT/03 Development of Rural Tourism Infrastructure in Pauri and Tehri District

    Yes Yes Site clearance and construction

    works were carried out till March,

    2019. After that work was held up

    due to PIL filed against the ongoing

    works on 08.03.2019 and stay orders

    by the Hon’ble High Court.

    NA

    12 UKIDIPT/III/GEN/03 Development of traditional medicine and Yoga Training centres

    Yes Yes Work completed NA

    13 UK/IDIPT/III/GEN/04 Development of “George Everest Heritage Park”

    Yes Yes

    Satisfactory

    No additional Corrective Measures required.

  • 37

    6. Status of Implementation of Environment Management Plan

    14. EMP Monitoring status of subprojects is presented in Table 7.

    Table 7 (i): EMP Monitoring Status Chart- Development of Tourism Infrastructure In Kartikeya Swami Circuit (Lot-1) (Tungeshwar & Durgadhar Temple) IEE/EMP

    Component Environmental issues Responsibility Compliance Status Corrective actions

    UK/IDIPT-III/ DDN/01

    Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters

    PMU & DSC Complied

    Pre-construction activities by the Contractor

    1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site

    Contractor &DSC

    Complied

    NA

    Construction 1. Improper stockpiling 2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles

    Complied. Works have been completed and handed over

    Construction waste generated was utilized for filling and leveling at site

    and remaining waste was adequately disposed off in consultation with

    village committee and local body.

    NA

  • 38

    IEE/EMP

    Component Environmental issues Responsibility Compliance Status Corrective actions

    9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site 13. Safety measures 14. Risks force majeure 15. Malaria risk

    16.Chance archaeological finds 17.Religious structures 18. Construction Staff causing disruption to migratory birds Conditions For Toilet and TICs work Cleaning of Septic Tanks at Toilet Blocks Safety during cleaning and Repair works of Septic Tanks

    Toilets and TICs Mechanical cleaning of septic tanks is being done. Waste properly disposed in existing STPs. Usage of PPEs by the workers was satisfactory.

    Operation 1. Environmental conditions 2. Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor

    maintenance of sanitation facilities and irregular solid waste collection

    6. Increased waste loads onto the existing

    PMU, UTDB The project not yet reached Operation phase

    NA

  • 39

    IEE/EMP

    Component Environmental issues Responsibility Compliance Status Corrective actions

    waste disposal facilities

    Conditions For Toilet and TICs work 1. Waste water from Toilet Facilities 2. Safety risks 3. Unhygienic conditions due to poor

    maintenance of sanitation facilities and irregular solid waste collection

    The project not yet reached Operation phase

    Table 7 (ii): EMP Monitoring Status Chart- Development of Tourism Infrastructure In Kartikeya Swami Circuit (Lot-2) (Kartikeya Swami Temple)

    IEE/EMP

    Component Environmental issues Responsibility Compliance Status Corrective actions

    UK/IDIPT-III/ DDN/02 Contract was terminated on 18.07.2018. New Contract for remaining work was awarded on 26.1.2019. Due to COVID 19 outbreak works halted. Works just started in the

    reporting period.

    Pre-construction activities by the Contractor

    Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters

    PMU & DSC Complied. Integrated in design None

    1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site

    Contractor & DSC Complied No construction camp. Labor staying in temple premises.

    None

    Construction 1. Improper stockpiling 2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion

    No water source in the impact area of subproject. Pre fab toilets at site for labour. Construction vehicles only enter till the main road. From there, material transported through mules. Barricading of construction zone done by the

    None

  • 40

    IEE/EMP

    Component Environmental issues Responsibility Compliance Status Corrective actions

    5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site 13. Safety measures 14. Risks force majeure 15. Malaria risk

    16.Chance archaeological finds 17.Religious structures 18. Construction Staff causing disruption to

    migratory birds

    contractor. Proper stockpiling of raw material was seen.

    Operation 1-Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing waste disposal facilities

    PMU, UTDB The project not yet reached Operation phase NA

  • 41

    Table 7 (iii): EMP Monitoring Status Chart- Rural Tourism in District Rudraprayag, Chamoli and Uttarkashi (8 Villages)

    IEE/EMP

    Component Environmental issues Responsibility Compliance Status Corrective actions

    UK/IDIPT-III/ DDN/03

    Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters

    PMU & DSC Complied None

    Pre-construction activities by the Contractor

    1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site

    Contractor & DSC Complied

    None

    Construction 1. Improper stockpiling 2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles 9. Noise from construction equipment 10. Material handling at site

    Complied Works completed in Phalasi (handed over) and Kanakchauri. Finishing works in Bora, Tungnath, Harshil , Mukhwa, and Niti. No construction camp in any site. Local labor is hired for the finishing works Potable drinking water is available in each site. The soil erosion issue is not there as finishing works are being carried out. Maximum waste generated has been utilized at site. Final waste disposal site has been identified. Usage of PPEs is satisfactory.

    None

  • 42

    IEE/EMP

    Component Environmental issues Responsibility Compliance Status Corrective actions

    11. Disposal of construction waste/debris 12. Sanitation facilities at project site 13. Safety measures 14. Risks force majeure 15. Malaria risk 16.Chance archaeological finds 17.Religious structures 18. Construction Staff causing disruption to migratory birds Toilet EMP conditions Cleaning of Septic Tanks at Toilet Blocks Safety during cleaning and Repair works of Septic Tanks

    Toilets and TICs Mechanical cleaning of septic tanks is being done. Waste properly disposed in existing STPs. Usage of PPEs by the workers was satisfactory.

    Operation 1-Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing waste disposal facilities

    PMU, UTDB The project not yet reached Operation phase. Not applicable

  • 43

    Table 7 (iv): EMP Monitoring Status Chart- Conservation of Cultural Heritage and urban place making in Nainital Lot-1

    IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions

    Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters

    PMU & DSC Integrated in the design

    Pre-construction activities by the Contractor

    1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas. 3. Circulation plan during construction. 4. Site clearance activities 5.Drinking water availability 6. Identification of disposal sites 7. Waste management on site

    Contractor & DSC Contract with the earlier contractor was terminated. LOA issued to new contractor in March 2020 for finishing some works left by the earlier contractor. Due to COVID pandemic outbreak, progress is very slow. Works just started in June 2020. Material is being procured from licensed quarries and separate stockpiling of raw materials is done.

    NA

    Construction 1. Improper stockpiling 2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site 13. Safety measures 14. Risks force majeure 15. Malaria risk 16.Chance archaeological finds 17.Religious structures 18. Construction Staff causing disruption to

  • 44

    IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions

    migratory birds

    Operation

    1-Environmental conditions PMU, UTDB Not yet reached Operation phase NA

    2.Uncontrolled tourism

    3. Management of the toilet blocks

    4. Adequate drainage

    5.Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection

    6. Increased waste loads onto the existing waste disposal facilities

  • 45

    Table 7 (v): EMP Monitoring Status Chart- Restoration and adaptive reuse of Almora Fort (Rani Mahal)

    IEE/EMP

    Component Environmental issues Responsibility Compliance Status Corrective actions

    UK/IDIPT/III/BHT/03

    Location

    Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters

    PMU & DSC Integrated in the design

    Pre-construction activities by the Contractor

    1.Construction Camps 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site

    Contractor & DSC Contract with the earlier contractor was terminated. LOA issued to new contractor in June 2020 for finishing the works left by the earlier contractor. Works started in June 2020. Contractor has started procuring materials. Proper stockpiling of raw material was seen. Barricading of site is done. Usage of PPEs is satisfactory.

    NA

    Construction 1. Improper stockpiling 2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site 13. Safety measures 14. Risks force majeure 15. Malaria risk 16.Chance archaeological finds 17.Religious structures 18.Construction Staff causing disruption to migratory birds

    Contractor & DSC

    Operation 1-Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage

    PMU, UTDB The project not yet reached Operation phase

    NA

  • 46

    IEE/EMP

    Component Environmental issues Responsibility Compliance Status Corrective actions

    UK/IDIPT/III/BHT/03

    5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing waste disposal facilities

  • 47

    Table 7 (vi): EMP Monitoring Status Chart- Restoration and adaptive reuse of Almora Fort (Malla Mahal)

    IEE/EMP

    Component Environmental issues Responsibility Compliance Status Corrective actions

    UK/IDIPT/III/BHT/06 Work not started

    Table 7 (vii): EMP Monitoring Status Chart- Restoration and adaptive reuse of Champawat Fort (Banasur)

    IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions

    UK/IDIPT/III/BHT/03

    Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters

    PMU & DSC Integrated in the design NA

    Pre-construction activities by the Contractor

    1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site

    Contractor & DSC Contract with the earlier contractor was terminated. LOA issued to new contractor in June 2020 for finishing some works left by the earlier contractor. Works started in June 2020. Proper stockpiling of raw materials was seen. Material being procured from licensed quarries. Usage of PPEs is satisfactory.

    NA

    Construction 1. Improper stockpiling

    2.Quarry/ Borrow pit operations

    3.Stripping, stocking & preservation of top soil

    4.Soil erosion

  • 48

    IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions

    5. Water pollution due to fuel/lubricants

    6. Siltation of water bodies

    7. Generation of dust

    8.Emission from construction vehicles

    9. Noise from construction equipment

    10. Material handling at site

    11. Disposal of construction waste/debris

    Operation 1-Environmental conditions PMU, UTDB Not yet reached Operation phase NA

    2.Uncontrolled tourism

    3. Management of the toilet blocks

    4. Adequate drainage

    5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection

    6. Increased waste loads onto the existing waste disposal facilities

  • 49

    Table 7(viii): EMP Monitoring Status Chart – Restoration and Adaptive Reuse of Pithoragarh Fort, Pithoragarh IEE/EMP

    Components

    Environmental Issues Responsibil

    ity

    Compliance Status Corrective Actions

    UK/IDIPT/III/BHT/07

    Location impacts Lack of sufficient planning to assure long term sustainability of the improvements and ensure protection of the assets created and the architectural character of the surroundings.

    PMU & Line Agency

    Complied None

    Design & pre construction impacts

    1. Increased storm water runoff from alterations of the site‘s natural drainage patterns due to additional structures in TRH complex and landscaping works in the area and on lake edge.

    DSC & PIU Complied None

    2. Selection of materials and construction technologies, if not carefully chosen, will adversely impact the aesthetic appeal of the destinations

    3. Integration of energy efficiency and energy conservation programs in design of subproject components

    Pre-construction activities by the contractor

    1. Circulation plan during construction in the tourist destinations Contractor & DSC

    Complied Construction/demolition waste is being disposed at designated site identified by PIU.

    None

    2. Site clearance activities, including delineation of construction areas

    3. Drinking water availability and water arrangement

    4. Identification of sites for disposal of construction and demolition work

  • 50

    IEE/EMP

    Components

    Environmental Issues Responsibil

    ity

    Compliance Status Corrective Actions

    Construction impacts 1. Improper stockpiling of construction materials cause impacts starting from obstruction of drainage, disturbance/safety hazard to tourists, etc. 2. Stripping, stocking and preservation of top soil 3. Soil Erosion 4. Soil and Water Pollution due to fuel and lubricants, construction waste 5. Generation of Dust 6.Emission from construction vehicles, equipment and machinery 7. Noise from construction equipment 8. Material Handling at Site 19. Disposal of Construction Waste/Debris/Cut Material 10. Safety Measures During Construction 11. Risk caused by Force Majeure 12. Malaria Risk

    Contractor Complied Works in finishing stage. Due to COVID slow work progress post March 2020.

    • Separate Stockpiling is done which is demarcated and covered with tarpaulin sheets

    • Water sprinkling is being done at construction site and construction material is being carried by covered trucks.

    • Waste management at site is satisfactory

    • Usage of PPEs is satisfactory

    None

    O & M impa