101
This research was sponsored by the Federal Highway Administration and the South Carolina Department of Transportation. The opinions, findings and conclusions expressed in this report are those of the authors and not necessarily those of the FHWA or SCDOT. This report does not comprise a standard, specification or regulation. In-Situ Monitoring of Precast Concrete Approach Slab Systems Final Report Paul Ziehl, P.E., PhD Mohamed ElBatanouny, PhD Matthew K. Jones Submitted to: South Carolina Department of Transportation and the Federal Highway Administration: Innovative Bridge Research and Development Program March, 2015 Department of Civil and Environmental Engineering 300 Main Street Columbia, SC 29208 (803) 777 3614 [email protected]

In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

This research was sponsored by the Federal Highway Administration and the South Carolina Department of Transportation. The opinions, findings and conclusions expressed in this report are those of the authors and not necessarily those of the FHWA or SCDOT. This report does not comprise a standard, specification or regulation.

In-Situ Monitoring of Precast Concrete Approach

Slab Systems

Final Report

Paul Ziehl, P.E., PhD Mohamed ElBatanouny, PhD

Matthew K. Jones

Submitted to:

South Carolina Department of

Transportation and the

Federal Highway Administration: Innovative Bridge Research and

Development Program

March, 2015

Department of Civil and Environmental Engineering

300 Main Street Columbia, SC 29208

(803) 777 3614 [email protected]

Page 2: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

IBRD Program: In-Situ Monitoring of Precast Approach Slabs University of South Carolina

i

Identification

Paul H. Ziehl, Professor Mohamed ElBatanouny, Postdoctoral Fellow

and Matthew K. Jones, Graduate Research Assistant

University of South Carolina Department of Civil and Environmental Engineering

300 Main Street Columbia, SC 29208

phone: 803 467 4030 fax: 803 777 0670

e-mail: [email protected]

Page 3: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

IBRD Program: In-Situ Monitoring of Precast Approach Slabs University of South Carolina

ii

Executive Summary

This report addresses the monitoring of precast concrete approach slabs on a replacement bridge located in Union County, South Carolina. The purpose of this project is to report on changes in the long-term behavior of the approach slab systems. Strain and displacement readings for the 18 month period following bridge construction were collected and are summarized. Significant adverse indications have not been observed and the approach slabs appear to be functioning as intended. However, during the last visit it was noticed that cracking of the asphalt had occurred between the approach slab and the approach roadway in four locations.

Page 4: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

IBRD Program: In-Situ Monitoring of Precast Approach Slabs University of South Carolina

iii

Table of Contents Section

Introduction .................................................................................................................................................. 1

Precast Approach Slab System ..................................................................................................................... 2

Instrumentation ............................................................................................................................................ 3

Sensor Layout ................................................................................................................................ 3.1

Gage Type, Placement, and Protection ........................................................................................ 3.2

Data Acquisition ............................................................................................................................ 3.3

Instrumentation Program ............................................................................................................................. 4

Tekna Precast Facility .................................................................................................................... 4.1

Union County Bridge Site .............................................................................................................. 4.2

Experimental Program .................................................................................................................................. 5

Concrete Testing ........................................................................................................................... 5.1

Long-Term Monitoring .................................................................................................................. 5.2

Load Testing .................................................................................................................................. 5.3

Results ........................................................................................................................................................... 6

Concrete Compressive Strength and Modulus ............................................................................. 6.1

Long-Term Measurements............................................................................................................ 6.2

Load Testing .................................................................................................................................. 6.3

Discussion of Results ..................................................................................................................................... 7

Long-Term Measurements............................................................................................................ 7.1

Load Testing .................................................................................................................................. 7.2

Visual Observations ...................................................................................................................... 7.3

Conclusions .................................................................................................................................................. 8

References ................................................................................................................................................... 9

Appendix

Page 5: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

1

1 Introduction

This report provides an overview of the on-site instrumentation, long-term monitoring, and load testing of precast concrete approach slab systems. The performance of the precast concrete approach slabs utilized on a replacement bridge over Big Brown Creek on River Road (S-86) in Union County, S.C. is summarized. The bridge has three continuous spans of Type IV girders, a length of 255 feet, a skew angle of 38 degrees, and integral end bents.

The approach slabs were fitted with a longitudinal shear key detail consisting of lopped interlocking reinforcement bars. The South Carolina Department of Transportation (SCDOT) is considering the use of this structural system in the future for bridge construction. This research program summarizes the performance of the precast concrete approach slab systems and addresses the practicality of further implementation as an alternative to current joint designs which historically have been subject to durability problems. Emphasis is placed on potential changes in long-term behavior of the approach slab systems.

Strain and displacement gages were installed inside the precast approach slabs and on the bridge approach. Concrete cylinders were sampled from each batch of concrete used during the casting of the approach slabs as well as the shear key closures adjoining each slab. The structural behavior of the precast approach slabs was monitored while in service for a period of 18 months after bridge construction was complete. Concrete cylinders were tested for compressive strength and modulus of elasticity. Details regarding the type and location of sensors used for monitoring as well as tasks performed by personnel from the University of South Carolina (U.SC) are summarized.

2 Precast Approach Slab System

The bridge consists of two approaches at either side of Big Brown Creek. The south side approach is referred to as the ‘Bent One’ approach and the north side approach is referred to as the ‘Bent Four’ approach. Detailed drawings from Tekna Corporation showing dimensions of the approach slabs and reinforcement schedules are included in the Appendix. Each approach is comprised of four separate precast concrete slabs which are joined with a female to female shear key closure joint. The general layout and labeling scheme of the precast slab system on the Bent One approach is shown in Figure 1. Each approach has two ‘exterior’ slabs labeled ‘A’ and ‘D’ and two ‘interior’ slabs labeled ‘B’ and ‘C’. The approach slabs are 12 inches thick and consist of both longitudinal and transverse reinforcing bars located at the top and bottom of the slabs. The shop drawings attached in the Appendix refer to slab A as ‘Panel 1-2’, slabs B and C as ‘Panel 1-3’ and slab D as ‘Panel 1-1’. Interior slabs are identical in size and reinforcing layout and are larger than the exterior slabs. They are situated directly beneath the two traffic lanes with the center shear key joint located directly in the middle of the roadway. The ‘exterior’ slabs are situated at the edges of the roadway. These slabs make up the shoulder of the roadway and also support the bridge parapet walls which were formed after the approach slabs were set in place. The layout of the Bent Four approach is similar to the Bent One approach but the individual slabs are not labeled as no sensors were placed within the precast concrete slabs on the Bent Four approach.

Page 6: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

2

Figure 1: Layout of precast approach slab system

The approach slabs rest on a macadam (crushed stone) sub-base material and provide a transition from the paved roadway to the deck of the bridge superstructure. The sub-base was roller compacted (relative compaction of 100%) to a depth of six inches (Figure 2). Beneath the sub-base a #789 stone (pea-size gravel) was used for back-filling around the wing walls up to the grade of the roadway. A corrugated pipe drain was provided at the base of the wing wall to allow for proper drainage. A 10 mil polyethylene moisture barrier was placed on top of the sub-base just prior to setting of the approach slabs.

The bridge side edge of each approach slab is seated on a ledger formed into the cast-in-place bridge deck. A photograph of the ledger is shown in Figure 3. Vertical dowel bars are embedded into the cast-in-place ledger and each approach slab has corresponding vertical sleeves embedded near the bridge side edge of the slab. These sleeves are located such that full alignment with the dowels is achieved. A section view of the bridge approach is shown in Figure 4. Alignment of reinforcing dowels is shown in Figure 5 for the placement of an interior slab on the bridge approach. Dowel sleeves were filled with grout after the approach slabs were set in place.

Page 7: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

3

Figure 2: Compacted crushed stone sub-base material on the Bent One approach

The precast concrete approach slabs utilized a connection joint detail consisting of interlocking looped (U-bar) reinforcement oriented transversely, relative to the joint, along with a female-to-female shear key as well as two longitudinal reinforcing bars. The purpose of the shear keys is to provide resistance to moving traffic loads by facilitating the transfer of shear forces between adjacent slabs. Shear keys allow the system of discrete panels to react monolithically (as a single piece of reinforced concrete) under applied loadings. The U-bars are spliced with the transverse reinforcement within the precast panel and are 0.625 inches in diameter (No. 5). The two longitudinal reinforcing bars are 0.75 inches in diameter (No. 6) , are located in the middle of the joint, are threaded through the inside of the loop bars, and are tied in at the top and bottom. The loop bars have an even spacing where each panel is out of phase with the adjacent panel by a half space. Plan and elevation details of the shear key are shown in Figure 6. A photograph showing the interlocking of reinforcement between adjacent slabs is shown in Figure 7. The finished shear key connection joint, including longitudinal reinforcement, is shown in Figure 8. The connection joint is intended to transfer and distribute shear and moments between adjacent panels and therefore enhance strength and durability of the approach slab system. After the precast concrete approach slabs were set in place, longitudinal bars were tied to the top and bottom loop bars and the shear keys were filled with concrete.

Page 8: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

4

Figure 3: Cast-in-place bridge deck ledger

Figure 4: Section view of approach slab and bridge deck

Page 9: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

5

Figure 5: Interior approach slab being set with vertical dowel alignment

After the bridge parapets were placed each approach was covered with asphalt pavement. The asphalt surfacing is 2.5 inches thick and extends up to the cast-in-place bridge deck (Figure 4). Figure 9 shows the bridge after construction was completed.

Page 10: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

6

Figure 6: Shear key connection detail

Figure 7: Interlocking of loop bars after slab placement

Page 11: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

7

Figure 8: Shear key connection joint with longitudinal reinforcing bars tied in

Figure 9: Completed replacement bridge over Big Brown Creek

Page 12: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

8

3 Instrumentation

Sensors were placed during fabrication of the precast approach slab segments, just after placement of the approach slabs and prior to casting of the shear keys, and after construction of the parapets. Vibrating Wire Strain Gages (VWSGs), Vibrating Wire Displacement Gages (VWDGs), and Electrical Resistance Strain Gages (ERSGs) were utilized to record strains and displacements due to service level loading conditions as well as long term behavior due to thermal and other effects.

Sensor Layout 3.1

The approach slabs are monitored with the following sensors:

(6) Model 4200 Geokon Vibrating Wire Strain Gages (VWSG)

(4) Model 4420 Geokon Vibrating Wire Displacement Gages (VWDG)

(12) Vishay Micro-Measurements Electrical Resistance Strain Gages (ERSG)

Information related to sensor placement is provided below.

3.1.1 Bent One Approach

The Bent One approach was instrumented with one VWDG mounted on each parapet and parallel to the direction of traffic, twelve ERSGs and six VWSGs. A plan view of the Bent One approach instrumentation is shown in Figure 10 and a cross-section view is shown in Figure 11. An expanded schematic of the details shown in Figure 10 is included in the Appendix.

The Electrical Resistance Strain Gages (ERSGs) were welded onto No. 4 sister bars and placed into the precast slabs during casting. These reinforcing bars, each instrumented with two gages, were constructed with sufficient length such that the bar was fully developed at either end. In the exterior slabs a single bar was located closest to the existing reinforcement nearest to the closure pour connecting the interior slabs. Each interior slab was instrumented with sister bars at either side of the slab. In each of the four slabs sister bars were placed parallel to the direction of traffic at a distance of approximately four feet from the bridge side edge of the approach slab. Sister bars were placed and tied in plane with the bottom mat reinforcing bars.

A single Vibrating Wire Strain Gage (VWSG) was placed in each closure pour perpendicular to the direction of traffic flow. These gages were used to measure concrete strain within the closure pours. Additional VWSGs were located within the precast slabs at the locations shown in Figure 10 and Figure 11. These gages were situated parallel to the direction of traffic flow at a distance of approximately four feet from the bridge side edge of the approach slab. VWSGs were placed and tied in plane with the bottom mat reinforcing bars.

Page 13: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

9

Figure 10: Bent One approach slab schematic - plan view

Figure 11: Bent One approach slab schematic - cross-section

3.1.2 Bent Four Approach

The Bent Four Approach was instrumented with two Vibrating Wire Displacement Gages (VWDGs) placed on the parapets. These gages are placed in the same manner and location as those placed on the Bent One approach and are shown in Figure 12 (plan view) and Figure 13 (cross-section view).

Page 14: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

10

Figure 12: Bent Four approach slab schematic – plan view

Figure 13: Bent Four approach slab schematic – cross section view

Gage Type, Placement, and Protection 3.2

All gages located within the precast slabs for the Bent One approach were placed during the casting of each slab. The four slabs were fitted with a 1.5 inch diameter PVC conduit which was used to pass cables through the slabs. This conduit can be seen tied into a reinforcing cage in Figure 14. This conduit was sealed at the locations within each slab where sensor cables enter.

Page 15: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

11

Figure 14: Conduit for sensor cables

Gages not cast in the precast concrete approach slabs, including the VWDGs placed on the parapets and the VWSGs placed in the shear key closure pours, were placed during the slab installation process.

Both vibrating wire gage types (VWSGs and VWDGs, manufactured by Geokon) are designed to withstand harsh conditions including embedment in concrete and exposure to the environment. Figure 15 shows a photograph of both sensor types. The associated cables are also capable of withstanding severe environments. Cable specifications for both VWSGs and VWDGs are shown in Table 1 and Table 2. The VWSGs have a range of 3,000 μ-strain, accuracy of +/- 0.5% of full scale, and one μ-strain sensitivity. The VWDGs have a range of 100 mm, accuracy of +/- 0.1% of full scale, and sensitivity of 0.025% of full scale.

Figure 15: a) Geokon model 4200 vibrating wire strain gage; and b) Geokon model 4420 vibrating wire displacement gage

a) b)

Page 16: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

12

Table 1: VWDG cable specifications

Vibrating Wire Strain Gages - Geokon Model 4200

Gage No. Orientation Wire Length (ft.) Enclosure Box T1 Transverse 2-250V6 14 1 T2 Transverse 2-250V6 16 1 T3 Transverse 2-250V6 14 2 P1 Parallel 2-250V6 25 2 P2 Parallel 2-250V6 15.5 2 P3 Parallel 2-250V6 13.5 2

Table 2: VWDG cable specifications

Vibrating Wire Displacement Gage - Geokon Model 4420

Gage No. Wire Length (ft) Enclosure Box

1 2-250V6 10 1 2 2-250V6 10 2 3 2-250V6 10 3 4 2-250V6 10 4

Each of the Vishay Micro-Measurements CEA-06-W250A-350 model ERSGs was connected to a specially made model 326-DSV copper vinyl shielded cable also provided by Vishay Micro-Measurements. A typical ERSG is shown in Figure 16 and ERSG cable specifications are shown in Table 3. The 120 Ω and 350 Ω ERSGs both have a sensitivity of +/- 0.4% of full scale and a range of +/- 5000 μ-strain.

Figure 16: Vishay Micro-Measurements model CEA-06-W250A-350 electrical resistance strain gage

Additional protection was provided for each ERSG with gagekote No. 5 protective coating (Vishay Micro-Measurements). This coating system is a two part polysulfide material with excellent chemical and mechanical resistance including waterproofing. A No. 4 sister bar with two ERSGs attached, fully waterproofed, and ready for installation is shown in Figure 17.

Page 17: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

13

Table 3: ERSG cable specifications

Electrical Resistance Strain Gages- Model CEA-06 W250A-120/350

Bar # Gage# Gage Ω Wire Length (ft) Enclosure Box

1 1 350 326- DSV 13.5 1 2 120 326- DSV 13.5 1

2 3 350 326- DSV 15.5 1 4 120 326- DSV 15.5 1

3 5 350 326- DSV 25 1 6 120 326- DSV 25 1

4 7 350 326- DSV 25 2 8 120 326- DSV 25 2

5 9 350 326- DSV 15.5 2

10 120 326- DSV 15.5 2

6 11 350 326- DSV 13.5 2 12 120 326- DSV 13.5 2

Figure 17: ERSG attached to No. 4 sister bar

Upon exiting each approach, sensor cables were routed directly to waterproof data acquisition enclosure boxes provided by SCDOT. These enclosure boxes are located on barrier parapets at either side of each instrumented bent. The location of the gage cables in each enclosure box is shown in the Appendix.

Data Acquisition 3.3

Data was acquired continuously during dynamic loading tests and discretely for long term measurements and static loading tests. In addition to data gathered through the instrumentation detailed in this report visual observations were recorded during each site visit. Visual observations include monitoring of cracking as well as other signs of distress. Visual observations are described in the results section of this report.

Page 18: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

14

Data acquisition systems included Vishay Micro-Measurements P3 strain indicators, a Vishay System 7000 data acquisition system, and a Geokon GK-404 vibrating wire readout system. The GK-404 and P3 systems were used for discrete measurements (Figure 18). The GK-404 was used to acquire data from VWSGs and VWDGs and the P3 was used to acquire data from the ERSGs. The P3 strain indicator has a one μ-strain resolution and a +/- 0.1% accuracy.

The System 7000 and Strain Smart software (Figure 19) were used to acquire data continuously from the ERSGs during dynamic loading. The 7000 System has accuracy of +/- 0.05% of full scale. Because the dynamic loads were applied over a brief period of time the higher data acquisition frequency of the System 7000 was needed for this loading scenario. A data acquisition frequency of 10 Hertz was used during the dynamic load testing.

Figure 18: a) Geokon GK-404 readout; and b) Vishay Micro-Measurements P3 strain indicator

a) b)

Page 19: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

15

Figure 19: Vishay Micro-Measurements System 7000 and Strain Smart data acquisition

3.3.1 Long-term Readings

Initial readings were taken before and just after casting of the concrete approach slabs and were recorded just after bridge completion and intermittently as shown in Table 4 thereafter. The data set includes initial readings and significant events during the slab setting process such as transportation of the approach slabs and filling of the shear key closures.

3.3.2 Dynamic and Static Loading Tests

Strain measurements were recorded periodically during dynamic and static loading of the Bent One approach slabs. Continuous readings were recorded for dynamic loading events using the Vishay Micro-Measurements System 7000 and Vishay Micro-Measurements Strain Smart software. Discrete measurements were recorded for the static loading events using the Geokon GK-404 portable readout system.

Page 20: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

16

Table 4: Approximate data acquisition schedule

Sensor Description

VWSG Prior to casting After casting After placement 3 months* 6 months* 13 months* 18 months*

VWDG N/A N/A After placement 3 months* 6 months* 13 months* 18 months*

ERSG Prior to casting After casting After placement 3 months* 6 months* 13 months* 18 months*

* after completion of bridge

4 Instrumentation Program

Instrumentation during the fabrication and casting of the approach slabs occurred over a three day period at the Tekna Corporation facility in Charleston, SC. Instrumentation at the bridge site located in Union County, SC occurred over a period of several months during the placement of the approach slabs and during general construction of the bridge and adjoining roadway. A description of the activities performed is presented in chronological order.

Tekna Precast Facility 4.1

Activities performed during the instrumentation of the precast concrete approach slabs during casting at the Tekna Precast facility are described below.

4.1.1 Date of Activity: December 6, 2012

ERSGs and VWSGs were tied into reinforcement cages for both Bent One interior precast approach slabs (Slabs ‘B’ and ‘C’). Figure 20 and Figure 21 show how the gages were tied into the bottom reinforcing mats. After gages were installed cables were routed through PVC conduit to the edge of the approach slabs. Initial readings were recorded prior to concrete placement.

Reinforcing cages for the precast approach slabs were incomplete and therefore concrete was not placed on this date as originally intended.

Page 21: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

17

Figure 20: ERSG and VWSG placement - top view

Figure 21: ERSG and VWSG placement – side view

4.1.2 Date of Activity: December 7, 2012

ERSGs and VWSGs were tied into reinforcement cages for the Bent One exterior approach slabs (Slabs ‘A’ and ‘D’). Figure 20 and Figure 21 show how the gages were tied into the bottom reinforcing mats. After gages were installed cables were routed through PVC conduits to the edge of the approach slabs.

Page 22: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

18

Initial readings were recorded prior to placement of the concrete. Readings were also taken just after placement of the concrete for both Bent One interior slabs.

Both Bent One interior approach slabs were cast on this date. Concrete placement was monitored closely to ensure that strain gages were not damaged or excessively disturbed during casting. Concrete test cylinders were collected and slump tests performed. For ‘Batch 1’ concrete used for casting interior slab ‘B’ a slump of 9.0 inches was measured. For ‘Batch 2’ concrete used for casting interior slab ‘C’ a slump of 8.5 inches was measured. Placement of concrete is shown in Figure 22. Vertical dowel sleeves can be seen in the lower left corner of the approach slab form.

Figure 22: Concrete placement - interior slab ‘B’

4.1.3 Date of Activity: December 10, 2012

Initial readings from strain gages in both Bent One exterior slabs were recorded prior to placement of concrete. Additional readings from the Bent One interior slabs were also recorded. Strain readings for both Bent One exterior slabs were recorded just after placement of the concrete. After measurements were recorded for all strain gages excess wire was bound and placed inside PVC tubes attached to the edge of each approach slab for protection from weather and damage during shipping.

Both Bent One exterior slabs were cast on this date (Slabs ‘A’ and ‘D’). Concrete placement was again monitored closely to ensure the strain gages were not damaged or disturbed during casting. Concrete test cylinders were collected and slump tests performed. A slump of 9.5 inches was measured for ‘Batch 3’.

Union County Bridge Site 4.2

Activities performed during the instrumentation of the approach slabs while on the site of the replacement bridge over Big Brown Creek are described below.

Page 23: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

19

4.2.1 Date of Activity: January 3, 2013

Measurements were recorded for all Bent One precast approach slabs prior to setting in place on the bridge approach. Figure 23 and Figure 24 show the slabs during placement. Figure 25 shows the approach after the precast concrete approach slabs have been placed.

Once the precast slabs were placed VWSGs were attached to reinforcing bars for each shear key closure joint (Figure 26 and Figure 27). Gage cables were then routed through conduit to the outside edges of the bridge. Measurements were recorded for all strain gages just after slab placement. Excess cable was bound and placed inside PVC tubes located near the wing walls to protect against weather and damage.

Figure 23: Placement of interior slab ‘C’

Page 24: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

20

Figure 24: Placement of exterior slab ‘D’

Figure 25: Approach slabs in place

Page 25: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

21

Figure 26: VWSG placement in shear key – top view

Figure 27: VWSG placement in shear key – side view

4.2.2 Date of Activity: January 11, 2013

Concrete was placed in all shear key closures adjoining the approach slabs on this date. A mechanical vibrator was used to ensure concrete was fully consolidated around reinforcement in the closures. Concrete placement and vibration was again monitored closely. Sufficient space was provided between vibrators and strain gages to prevent damage or disturbance of VWSGs. Concrete test cylinders were

Page 26: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

22

collected and slump tests performed. A slump of 5.25 inches was measured for ‘Batch 4’. Figure 28 and Figure 29 show concrete during placement in the shear key closures. Figure 30 shows the surface of the closure pour being finished with a trowel.

Figure 28: Placement of concrete in an instrumented shear key closure

Page 27: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

23

Figure 29: Concrete being vibrated during placement

Figure 30: Shear key closure being finished

4.2.3 Date of Activity: January 23, 2013

Measurements were recorded for the Bent One precast approach slabs before and after concrete placement for the bridge barrier parapets. Figure 31 shows the formed barrier parapet.

Page 28: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

24

Figure 31: Barrier parapet

4.2.4 Date of Activity: February 14, 2013

All four VWDGs were installed on the outside of the parapets on the Bent One and Bent Four approaches on this date and initial readings for the VWDGs were recorded. Cables for all gages were routed through conduits to enclosure boxes provided and installed by SCDOT. Cover plates provided by Geokon were also installed to protect the displacement gages from mechanical damage and disturbance. Cover plates are specially designed to be attached to the concrete substrate and to shield the gages without directly contacting the VWDGs or influencing the measurements. Images of the installed VWDGs and cover plates are shown in Figure 32 through Figure 34.

Figure 32: VWDG 3 prior to installation of cover plate

Page 29: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

25

Figure 33: VWDG 1 and Enclosure Box 1

Figure 34: VWDG with cover plate installed

Page 30: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

26

5 Experimental Program

Concrete Testing 5.1

Concrete cylinders were sampled from each batch of concrete used in casting the approach slabs and for the shear key closures. These cylinders were used to determine compressive strength and modulus of elasticity of the concrete. A total of 15 cylinders were collected for each batch of concrete to provide three specimens for testing compressive strength at 7, 14, 28, and 56 days and 3 specimens for modulus of elasticity testing at 56 days. The approach slab system required several separate batches of concrete: Batch 1 for the casting of approach slab ‘B’, Batch 2 for the casting of approach slab ‘C’, Batch 3 for casting of approach slabs ‘A’ and ‘D’, and Batch 4 for the shear key closures. Slump tests were also performed on each batch of concrete. Figure 35 shows concrete compression testing in progress and the modulus of elasticity test setup.

Figure 35: a) Concrete compressive strength test, b) Concrete modulus of elasticity test

Concrete compressive strength testing was performed in general conformance with ASTM C39 / C39M- 12a; modulus of elasticity testing was performed in general conformance with ASTM C469 / C469M; and sampling of concrete and slump testing were performed in general conformance with ASTM C31- 12 and ASTM C143- 12.

Long-term Monitoring 5.2

Discrete readings from VWSGs, VWDGs, and ERSGs were recorded on-site in accordance with the data acquisition schedule.

Strain and displacement measurements shown are relative to the initial readings. For VWSGs and ERSGs the initial reading is considered as the reading taken when instruments were tied securely into reinforcing cages just prior to concrete placement. For VWDGs the initial reading was recorded just after the installation of the gages on the outside of the bridge parapets. Vibrating wire based readings are

a) b)

Page 31: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

27

corrected for effects due to temperature variation and electrical resistance based sensors are corrected for the effect of cable gage length. Photos showing collection of data for VWSGs and ERSGs are shown in Figure 36 and Figure 37.

Figure 36: VWSG readings being collected with Geokon GK-404 readout

Figure 37: ERSG readings recorded with Vishay P3 strain indicator

Page 32: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

28

Load Testing 5.3

Load tests were conducted during on-site visits. Dynamic and static forces were applied to the precast approach slabs positioned on the Bent One approach using loading trucks of known weight and dimensions made available and operated by SCDOT. Two load trucks were supplied by SCDOT for each load test. A photograph of a typical loading truck is shown in Figure 38. Three load tests were conducted at discrete intervals (6, 13, and 18 months after bridge completion).

Figure 38: SCDOT loading truck

The axle weights and dimensions for each load truck are shown in Table 5 and Table 6. Each load truck had a total weight of approximately 45,000 pounds and each truck was dimensionally similar.

Page 33: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

29

Table 5: Weight of loading trucks

6 months after bridge completion

Truck Front Axle (pounds)

Rear Axle (pounds)

1 10,340 33,580

2 10,620 34,560

13 months after bridge completion

1 11,180 36,400

2 11,210 36,470

18 months after bridge completion

1 10,300 34,000

2 10,900 34,480

Table 6: Loading truck dimensions

Load Truck Wheel/Axle Dimensions (inches)

Wheel Base: front to 1st rear

Wheel Base: front to 2nd rear

Wheel Track

Tread Width: single front tire

Tread Width: double rear tire

125 178 95 9 23

5.3.1 Dynamic Load Testing

Strain measurements from ERSGs were recorded continuously while the Bent One approach slab system was subjected to dynamic loading. A series of low-velocity and high-velocity passes were made by the load trucks on each approach lane. For the low-velocity passes the driver was instructed to travel over each approach lane separately, in the direction of normal traffic flow, at a speed of approximately 5 mph. The drivers were instructed to keep the trucks in the center of the traffic lane during the pass. High velocity passes were made in a similar manner except the speed of travel was increased to 45 mph.

Readings from ERSGs within respective approach slabs were collected using Vishay Micro-Measurements 7000 system throughout the duration of loading. A photo showing the data acquisition setup is shown in Figure 39.

Page 34: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

30

Figure 39: On-site 7000 System data acquisition system setup

ERSGs within approach slabs ‘A’ and ‘B’ on the left side of Bent One were monitored while the load truck traveled in the southbound lane over the approach. These measurements are referred to as ‘Load Case 2’ in the schematic shown in Figure 40. ERSGs within approach slabs ‘C’ and ‘D’ on the right side of Bent One were monitored while the load truck traveled in the northbound lane over the approach. These measurements are referred to as ‘Load Case 1’ in the schematic shown in Figure 40. Each approach was loaded and monitored three times as described above for the low-velocity and high-velocity passes. Figure 41 shows a high speed pass on the southbound approach lane in progress during the first load test.

Figure 40: Dynamic load case schematic

Page 35: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

31

Figure 41: High speed pass on southbound approach lane

5.3.2 Static Load Testing

Strain measurements from VWSGs were recorded while the Bent One approach slabs were subjected to static loading. Loading trucks were parked with rear axles directly over the strain gage locations for approximately five minutes while measurements were recorded manually from the VWSGs. Each approach was loaded and monitored separately. A schematic showing the position of each truck and labeling of the approach slabs is shown in Figure 42. Measurements from the VWSGs within approach slabs ‘A’ and ‘B’ and the shear key closures were collected while the load truck was parked in the south bound lane with the rear axle located directly over the gage locations (a distance of four feet from the bridge side edge of the approach slabs). These measurements are referred to as ‘Load Case 4’ in the schematic. Measurements from VWSGs within the shear key closures were recorded while the load truck was parked in the north bound lane with the rear axles located directly over the strain gages (a distance of four feet from the bridge side edge of the approach slabs). These measurements are referred to as ‘Load Case 3’ in the schematic. Each approach was loaded three times with initial readings collected prior to each loading. Photographs of the static load testing procedure are shown in Figure 43 and Figure 44.

Page 36: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

32

Figure 42: Static load case schematic

Figure 43: Static load testing: Load Case 3

Page 37: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

33

Figure 44: Static load testing: Load Case 4

6 Results

Concrete Compressive Strength and Modulus 6.1

Compressive strength test results at 7, 14, 28, and 56 days along with modulus of elasticity (Ec) results the precast concrete approach slabs are shown in Table 7 through Table 9. Similar results are shown for the shear key closures in Table 10.

Table 7: Approach slab ‘B’ compression results (slump = 9 inches)

Specimen 7-day 14-day 28-day 56-day

σult (psi) σult (psi) σult (psi) σult (psi) Ec

(x106 psi) 1 7,470 8,500 9,950 11,410 5.95

2 7,340 9,260 9,300 10,080 6.00

3 7,500 7,150 9,730 10,430 5.05

Average 7,430 8,300 9,660 10,640 5.67

Page 38: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

34

Table 8: Approach slab ‘C’ compression results (slump = 8.5 inches)

Specimen 7-day 14-day 28-day 56-day

σult (psi) σult (psi) σult (psi) σult (psi)) Ec

(106 psi) 1 7,550 8,700 10,060 10,490 -

2 6,250 9,140 8,440 10,970 5.70

3 7,220 8,060 8,640 10,500 5.75

Average 7,004 8,630 9,050 10,650 5.73

Table 9: Approach slab ‘A’ and ‘D’ compression results (slump = 9.5 inches)

Specimen 7-day 14-day 28-day 56-day

σult (psi) σult (psi) σult (psi) σult (psi) Ec

(106 psi) 1 6,210 7,020 8,990 9,030 5.75

2 6,840 7,990 7,950 10,210 5.95

3 6,920 8,020 8,210 9,800 5.40

Average 6,660 7,680 8,390 9,680 5.70

Table 10: Shear key closure compression results (slump = 5.25 inches)

Specimen 7-day 14-day 28-day 56-day

σult (psi) σult (psi) σult (psi) σult (psi) Ec

(106 psi) 1 4,180 5,000 4,390 4,690 3.20

2 4,260 5,270 5,390 5,540 2.75

3 4,190 5,340 4,730 5,960 3.60

Average 4,210 5,200 4,840 5,400 3.18

Long-term Measurements 6.2

Long-term strain and displacement measurements are shown in Table 11 through Table 21 and Figure 45 through Figure 53. Initial readings and readings taken before and after major events are shown. Vibrating wire based readings shown in the tables and figures are corrected for effects due to temperature and electrical resistance based readings have been corrected for effects due to cable gage length.

Page 39: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

35

6.2.1 Vibrating Wire Strain Gages

Strain measurements collected from VWSGs in approach slabs ‘A’ and ‘B’ and within the shear key closures were recorded at different points in time occurring during instrumentation and construction of the bridge approach. These are described in Table 11 through Table 13. Plots corresponding to the data presented in each table are shown in Figure 45 through Figure 47.

Table 11: Vibrating wire strain gage measurements – approach slab ‘A’

Measurement Description Date μ-strain

VWSG P3

1 Initial reading - 3:00 pm 12/7/2012 0.0

2 After casting - 4:35 pm 12/7/2012 76.6

3 After casting - 12:30 pm 12/10/2012 24.1

4 Before placement/on truck- 2:05 pm 1/3/2013 -164

5 After placement - 4:50 pm 1/3/2013 -155

6 Before filling closure - 8:30 am 1/11/2013 -112

7 After filling closure - 1:00 pm 1/11/2011 -106

8 After barrier parapet placed - 12:15 pm 1/23/2013 -205

9 After barrier parapet placed - 1:45 pm 1/23/2013 -191

10 Before pavement 2/6/2013 -143

11 After pavement/bridge completed 3/27/2013 -136

12 3 months after bridge completed - 11:00 am 6/28/2013 107

13 6 months after bridge completed - 12:30 pm 9/16/2013 49.9

14 13 months after bridge completed - 12:00 noon 4/23/2014 -33.1

15 18 months after bridge completed - 11:00 am 9/18/2014 -2.0

Page 40: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

36

Table 12: Vibrating wire strain gage measurements – approach slab ‘B’

Measurement Description Date μ-strain

VWSG P1

1 Initial reading - 9:40 am 12/7/2012 0.0

2 After casting - 11:30 pm 12/7/2012 133

3 After casting - 2:50 pm 12/7/2012 137

4 After casting - 12:30 pm 12/10/2012 141

5 Before placement/on truck - 2:05 pm 1/3/2013 -40.6

6 After setting in place - 4:50 pm 1/3/2013 -19.4

7 Before filling closures - 8:30 am 1/11/2013 16.8

8 After filling closures - 1:00 pm 1/11/2013 22.4

9 After barrier parapet placed - 12:15 pm 1/23/2013 -87.0

10 After barrier parapet placed - 1:45 pm 1/23/2013 -72.3

11 Before pavement 2/6/2013 -36.7

12 After pavement/bridge completed 3/27/2013 -21.2

13 3 months after bridge completed - 11:00 am 6/28/2013 208

14 6 months after bridge completed - 12:30 pm 9/16/2013 142

15 13 months after bridge completed - 12:00 noon 4/23/2014 116

16 18 months after bridge completed - 11:00 am 9/18/2014 151

Page 41: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

37

Table 12 (continued): Vibrating wire strain gage measurements – approach slab ‘B’

Measurement Description Date μ-strain

VWSG P2

1 Initial reading - 9:40 am 12/7/2012 0.0

2 After casting - 11:30 pm 12/7/2012 135

3 After casting - 2:50 pm 12/7/2012 151

4 After casting - 12:30 pm 12/10/2012 149

5 Before placement/on truck - 2:05 pm 1/3/2013 -41.2

6 After setting in place - 4:50 pm 1/3/2013 -23.9

7 Before filling closures - 8:30 am 1/11/2013 25.6

8 After filling closures - 1:00 pm 1/11/2013 32.8

9 After barrier parapet placed - 12:15 pm 1/23/2013 -60.8

10 After barrier parapet placed - 1:45 pm 1/23/2013 -43.3

11 Before pavement 2/6/2013 -0.1

12 After pavement/bridge completed 3/27/2013 -7.7

13 3 months after bridge completed - 11:00 am 6/28/2013 218

14 6 months after bridge completed - 12:30 pm 9/16/2013 157

15 13 months after bridge completed - 12:00 noon 4/23/2014 5.1

16 18 months after bridge completed - 11:00 am 9/18/2014 37.1

Page 42: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

38

Figure 45: Vibrating wire strain gage measurements - approach slab ‘A’

Figure 46: Vibrating wire strain gage measurements – approach slab B

-400

-300

-200

-100

0

100

200

300

400

Oct

-12

Dec

-12

Jan-

13M

ar-1

3M

ay-1

3Ju

n-13

Aug

-13

Oct

-13

Nov

-13

Jan-

14M

ar-1

4A

pr-1

4Ju

n-14

Jul-1

4Se

p-14

Nov

-14

µStr

ain

Date

VWSG-P3

-400

-300

-200

-100

0

100

200

300

400

Oct

-12

Dec

-12

Jan-

13M

ar-1

3M

ay-1

3Ju

n-13

Aug

-13

Oct

-13

Nov

-13

Jan-

14M

ar-1

4A

pr-1

4Ju

n-14

Jul-1

4Se

p-14

Nov

-14

µStr

ain

Date

VWSG-P1

VWSG-P2

Page 43: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

39

Table 13: Vibrating wire strain gage measurements – shear key closures

Measurement Description Date μ-strain

VWSG T1

1 Before filling closures - 8:30 am 1/11/2013 0.0

2 After filling closures - 1:00 pm 1/11/2013 150

4 After barrier parapet placed - 12:15 pm 1/23/2013 -73.9

5 After barrier parapet placed - 1:45 pm 1/23/2013 -55.7

6 Before pavement 2/6/2013 -13.0

7 After pavement/bridge completed 3/27/2013 56.3

8 3 months after bridge completed - 11:00 am 6/28/2013 276

9 6 months after bridge completed - 12:30 pm 9/16/2013 196

10 13 months after bridge completed - 12:00 noon 4/23/2014 42.2

11 18 months after bridge completed - 11:00 am 9/18/2014 50.1

VWSG T2

1 Before filling closures - 8:30 am 1/11/2013 0.0

2 After filling closures - 1:00 pm 1/11/2013 144

4 After barrier parapet placed - 12:15 pm 1/23/2013 -91.5

5 After barrier parapet placed - 1:45 pm 1/23/2013 -69.7

6 Before pavement 2/6/2013 -53.8

7 After pavement/bridge completed 3/27/2013 -11.7

8 3 months after bridge completed - 11:00 am 6/28/2013 188

9 6 months after bridge completed - 12:30 pm 9/16/2013 92.1

10 13 months after bridge completed - 12:00 noon 4/23/2014 -405

11 18 months after bridge completed - 11:00 am 9/18/2014 -382

Page 44: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

40

Table 13 (continued): Vibrating wire strain gage measurements – shear key closures

Measurement Description Date μ-strain

VWSG T3

1 Before filling closures - 8:30 am 1/11/2013 0.0

2 After filling closures - 1:00 pm 1/11/2013 157

4 After barrier parapet placed - 12:15 pm 1/23/2013 -106

5 After barrier parapet placed - 1:45 pm 1/23/2013 -97.4

6 Before pavement 2/6/2013 -39.6

7 After pavement/bridge completed 3/27/2013 16.9

8 3 months after bridge completed - 11:00 am 6/28/2013 247

9 6 months after bridge completed - 12:30 pm 9/16/2013 174

10 13 months after bridge completed - 12:00 noon 4/23/2014 47.7

11 18 months after bridge completed - 11:00 am 9/18/2014 -80.8

Figure 47: Vibrating wire strain gage measurements – shear key closures

6.2.2 Electrical Resistance Strain Gages

Strain measurements were recorded from the ERSGs in approach slabs ‘A’, ‘B’, ‘C’, and ‘D’ as shown below. Measurements were recorded at different points in time occurring during instrumentation and construction of the bridge approach as described in Table 14 through Table 19. Plots showing discrete strain readings corresponding to the data presented in each table are shown in Figure 48 through Figure

-400

-300

-200

-100

0

100

200

300

400

Oct

-12

Dec

-12

Jan-

13M

ar-1

3M

ay-1

3Ju

n-13

Aug

-13

Oct

-13

Nov

-13

Jan-

14M

ar-1

4A

pr-1

4Ju

n-14

Jul-1

4Se

p-14

Nov

-14

µStr

ain

Date

VWSG-T1

VWSG-T2

VWSG-T3

Page 45: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

41

51. In some instances when taking strain readings, anomalies associated with ERSGs and data acquisition systems were encountered and as a result readings from some gages were unable to be collected. Readings marked ‘N/A’ in the tables presented below are associated with these occurrences.

Readings were not taken during the load testing at 13 months after completion as the sensor wires were vandalized. Re-attachment of the ERSG wires was conducted just prior to the third load test. The results up to 18 months after completion of the bridge are shown in the tables and figures below.

Table 14: Electrical resistance strain gage measurements – approach slab ‘A’

Measurement Description Date μ-strain

ERSG 11

1 Initial reading - 3:17 pm 12/7/2012 0

2 After casting - 4:35 pm 12/7/2012 1670

3 After casting - 12:30 pm 12/10/2012 1550

4 Before placement/on truck - 2:15 pm 1/3/2013 1430

5 After setting in place - 5:00 pm 1/3/2013 1530

6 Before filling closures - 9:00 am 1/11/2013 1460

7 After filling closures - 1:00 pm 1/11/2013 1440

8 After barrier parapet placed - 12:30 pm 1/24/2013 -100

9 After barrier parapet placed - 1:45 pm 1/24/2013 -4430

10 Before pavement 2/6/2013 1460

11 After pavement/bridge completed 3/27/2013 1550

12 3 months after bridge completed - 11:00 am 6/28/2013 1610

13 6 months after bridge completed - 12:30 pm 9/16/2013 1650

14 18 months after bridge completed - 11:30 am 9/18/2014 373

Page 46: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

42

Table 14 (continued): Electrical resistance strain gage measurements – approach slab ‘A’

Measurement Description Date μ-strain

ERSG 12

1 Initial reading - 3:17 pm 12/7/2012 0

2 After casting - 4:35 pm 12/7/2012 -257

3 After casting - 12:30 pm 12/10/2012 -3880

4 Before placement/on truck - 2:15 pm 1/3/2013 -184

5 After setting in place - 5:00 pm 1/3/2013 -481

6 Before filling closures - 9:00 am 1/11/2013 -837

7 After filling closures - 1:00 pm 1/11/2013 -378

8 After barrier parapet placed - 12:30 pm 1/24/2013 -4670

9 After barrier parapet placed - 1:45 pm 1/24/2013 -1650

10 Before pavement 2/6/2013 -312

11 After pavement/bridge completed 3/27/2013 -323

12 3 months after bridge completed - 11:00 am 6/28/2013 30

13 6 months after bridge completed - 12:30 pm 9/16/2013 358

14 18 months after bridge completed - 11:30 am 9/18/2014 1780

Page 47: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

43

Table 15: Electrical resistance strain gage measurements – approach slab ‘B’

Measurement Description Date μ-strain

ERSG 7

1 Initial reading - 3:17 pm 12/7/2012 0

2 After casting - 4:35 pm 12/7/2012 N/A

3 After casting - 12:30 pm 12/10/2012 1220

4 Before placement/on truck - 2:15 pm 1/3/2013 1420

5 After setting in place - 5:00 pm 1/3/2013 1380

6 Before filling closures - 9:00 am 1/11/2013 1360

7 After filling closures - 1:00 pm 1/11/2013 -61

8 After barrier parapet placed - 12:30 pm 1/24/2013 1430

9 After barrier parapet placed - 1:45 pm 1/24/2013 1460

10 Before pavement 2/6/2013 1460

11 After pavement/bridge completed 3/27/2013 1400

12 3 months after bridge completed - 11:00 am 6/28/2013 1410

13 6 months after bridge completed - 12:30 pm 9/16/2013 -117

14 18 months after bridge completed - 11:30 am 9/18/2014 -240

Page 48: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

44

Table 15 (continued): Electrical resistance strain gage measurements – approach slab ‘B’

Measurement Description Date μ-strain

ERSG 8

1 Initial reading - 3:17 pm 12/7/2012 N/A

2 After casting - 4:35 pm 12/7/2012 N/A

3 After casting - 12:30 pm 12/10/2012 N/A

4 Before placement/on truck - 2:15 pm 1/3/2013 N/A

5 After setting in place - 5:00 pm 1/3/2013 N/A

6 Before filling closures - 9:00 am 1/11/2013 N/A

7 After filling closures - 1:00 pm 1/11/2013 N/A

8 After barrier parapet placed- 12:30 pm 1/24/2013 N/A

9 After barrier parapet placed - 1:45 pm 1/24/2013 N/A

10 Before pavement 2/6/2013 N/A

11 After pavement/bridge completed 3/27/2013 N/A

12 3 months after bridge completed - 11:00 am 6/28/2013 N/A

13 6 months after bridge completed - 12:30 pm 9/16/2013 N/A

14 18 months after bridge completed - 11:30 am 9/18/2014 N/A

Page 49: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

45

Table 16: Electrical resistance strain gage measurements – approach slab ‘B’

Measurement Description Date μ-strain

ERSG 9

1 Initial reading - 3:17 pm 12/7/2012 0

2 After casting - 4:35 pm 12/7/2012 6040

3 After casting - 12:30 pm 12/10/2012 2340

4 Before placement/on truck - 2:15 pm 1/3/2013 2230

5 After setting in place - 5:00 pm 1/3/2013 2230

6 Before filling closures - 9:00 am 1/11/2013 2190

7 After filling closures - 1:00 pm 1/11/2013 3440

8 After barrier parapet placed - 12:30 pm 1/24/2013 -3260

9 After barrier parapet placed - 1:45 pm 1/24/2013 -3240

10 Before pavement 2/6/2013 3270

11 After pavement/bridge completed 3/27/2013 3500

12 3 months after bridge completed - 11:00 am 6/28/2013 2470

13 6 months after bridge completed - 12:30 pm 9/16/2013 N/A

14 18 months after bridge completed - 11:30 am 9/18/2014 -85

Page 50: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

46

Table 16 (continued): Electrical resistance strain gage measurements – approach slab ‘B’

Measurement Description Date μ-strain

ERSG 10

1 Initial reading - 3:17 pm 12/7/2012 0

2 After casting - 4:35 pm 12/7/2012 N/A

3 After casting - 12:30 pm 12/10/2012 1060

4 Before placement/on truck - 2:15 pm 1/3/2013 N/A

5 After setting in place - 5:00 pm 1/3/2013 N/A

6 Before filling closures - 9:00 am 1/11/2013 N/A

7 After filling closures - 1:00 pm 1/11/2013 N/A

8 After barrier parapet placed - 12:30 pm 1/24/2013 N/A

9 After barrier parapet placed - 1:45 pm 1/24/2013 N/A

10 Before pavement 2/6/2013 N/A

11 After pavement/bridge completed 3/27/2013 976

12 3 months after bridge completed - 11:00 am 6/28/2013 1010

13 6 months after bridge completed - 12:30 pm 9/16/2013 1030

14 18 months after bridge completed - 11:30 am 9/18/2014 1550

Page 51: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

47

Table 17: Electrical resistance strain gage measurements – approach slab ‘C’

Measurement Description Date μ-strain

ERSG 3

1 Initial reading - 3:17 pm 12/7/2012 0

2 After casting - 4:10 pm 12/7/2012 4420

3 After casting - 12:30 pm 12/10/2012 4240

4 Before placement/on truck - 1:35 pm 1/3/2013 4270

5 After setting in place - 5:00 pm 1/3/2013 4340

6 Before filling closures - 9:00 am 1/11/2013 4230

7 After filling closures - 1:00 pm 1/11/2013 3770

8 After barrier parapet placed - 12:30 pm 1/24/2013 -4200

9 After barrier parapet placed - 1:45 pm 1/24/2013 1950

10 Before pavement 2/6/2013 4330

11 After pavement/bridge completed 3/27/2013 4220

12 3 months after bridge completed - 11:00 am 6/28/2013 4180

13 6 months after bridge completed - 12:30 pm 9/16/2013 1690

14 18 months after bridge completed - 11:30 am 9/18/2014 786

Page 52: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

48

Table 17 (continued): Electrical resistance strain gage measurements – approach slab ‘C’

Measurement Description Date μ-strain

ERSG 4

1 Initial reading - 3:17 pm 12/7/2012 0

2 After casting - 4:10 pm 12/7/2012 -630

3 After casting - 12:30 pm 12/10/2012 350

4 Before placement/on truck - 1:35 pm 1/3/2013 131

5 After setting in place - 5:00 pm 1/3/2013 170

6 Before filling closures - 9:00 am 1/11/2013 -379

7 After filling closures - 1:00 pm 1/11/2013 -369

8 After barrier parapet placed - 12:30 pm 1/24/2013 459

9 After barrier parapet placed - 1:45 pm 1/24/2013 863

10 Before pavement 2/6/2013 190

11 After pavement/bridge completed 3/27/2013 217

12 3 months after bridge completed - 11:00 am 6/28/2013 -235

13 6 months after bridge completed - 12:30 pm 9/16/2013 1320

14 18 months after bridge completed - 11:30 am 9/18/2014 -311

Page 53: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

49

Table 18: Electrical resistance strain gage measurements – approach slab ‘C’

Measurement Description Date μ-strain

ERSG 5

1 Initial reading - 3:17 pm 12/7/2012 0

2 After casting - 4:10 pm 12/7/2012 3610

3 After casting - 12:30 pm 12/10/2012 3500

4 Before placement/on truck - 1:35 pm 1/3/2013 3580

5 After setting in place - 5:00 pm 1/3/2013 3560

6 Before filling closures - 9:00 am 1/11/2013 3570

7 After filling closures - 1:00 pm 1/11/2013 3530

8 After barrier parapet placed - 12:30 pm 1/24/2013 -3670

9 After barrier parapet placed - 1:45 pm 1/24/2013 3610

10 Before pavement 2/6/2013 3570

11 After pavement/bridge completed 3/27/2013 3590

12 3 months after bridge completed - 11:00 am 6/28/2013 3480

13 6 months after bridge completed - 12:30 pm 9/16/2013 1340

14 18 months after bridge completed - 11:30 am 9/18/2014 1230

Page 54: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

50

Table 18 (continued): Electrical resistance strain gage measurements – approach slab ‘C’

Measurement Description Date μ-strain

ERSG 6

1 Initial reading - 3:17 pm 12/7/2012 0

2 After casting - 4:10 pm 12/7/2012 -11310

3 After casting - 12:30 pm 12/10/2012 2740

4 Before placement/on truck - 1:35 pm 1/3/2013 1070

5 After setting in place - 5:00 pm 1/3/2013 1220

6 Before filling closures - 9:00 am 1/11/2013 1090

7 After filling closures - 1:00 pm 1/11/2013 627

8 After barrier parapet placed - 12:30 pm 1/24/2013 -1070

9 After barrier parapet placed - 1:45 pm 1/24/2013 -5370

10 Before pavement 2/6/2013 1110

11 After pavement/bridge completed 3/27/2013 1410

12 3 months after bridge completed - 11:00 am 6/28/2013 1480

13 6 months after bridge completed - 12:30 pm 9/16/2013 1580

14 18 months after bridge completed - 11:30 am 9/18/2014 1310

Page 55: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

51

Table 19: Electrical resistance strain gage measurements – approach slab ‘D’

Measurement Description Date μ-strain

ERSG 1

1 Initial reading - 3:17 pm 12/7/2012 0

2 After casting - N/A 12/7/2012 N/A

3 After casting - 12:30 pm 12/10/2012 9

4 Before placement/on truck - 1:35 pm 1/3/2013 23

5 After setting in place - 5:00 pm 1/3/2013 26

6 Before filling closures - 9:00 am 1/11/2013 -5940

7 After filling closures - 1:00 pm 1/11/2013 -11440

8 After barrier parapet placed - 12:30 pm 1/24/2013 -1870

9 After barrier parapet placed - 1:45 pm 1/24/2013 -3820

10 Before pavement 2/6/2013 10

11 After pavement/bridge completed 3/27/2013 6

12 3 months after bridge completed - 11:00 am 6/28/2013 -6810

13 6 months after bridge completed - 12:30 pm 9/16/2013 -2210

14 18 months after bridge completed - 11:30 am 9/18/2014 56

Page 56: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

52

Table 19 (continued): Electrical resistance strain gage measurements – approach slab ‘D’

Measurement Description Date μ-strain

ERSG 2

1 Initial reading - 3:17 pm 12/7/2012 0

2 After casting - 4:10 pm 12/7/2012 N/A

3 After casting - 12:30 pm 12/10/2012 36

4 Before placement/on truck - 1:35 pm 1/3/2013 15

5 After setting in place - 5:00 pm 1/3/2013 15

6 Before filling closures - 9:00 am 1/11/2013 137

7 After filling closures - 1:00 pm 1/11/2013 110

8 After barrier parapet placed - 12:30 pm 1/24/2013 -4570

9 After barrier parapet placed - 1:45 pm 1/24/2013 -1210

10 Before pavement 2/6/2013 103

11 After pavement/bridge completed 3/27/2013 51

12 3 months after bridge completed - 11:00 am 6/28/2013 144

13 6 months after bridge completed - 12:30 pm 9/16/2013 -1300

14 18 months after bridge completed - 11:30 am 9/18/2014 N/A

Page 57: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

53

Figure 48: Electrical resistance strain gage measurements – approach slab ‘A’

Figure 49: Electrical resistance strain gage measurements – approach slab ‘B’

-14000-12000-10000

-8000-6000-4000-2000

02000400060008000

Oct

-12

Jan-

13

May

-13

Aug

-13

Nov

-13

Mar

-14

Jun-

14

Sep-

14

Dec

-14

µStr

ain

Date

ERSG 11ERSG 12

-14000-12000-10000

-8000-6000-4000-2000

02000400060008000

Oct

-12

Jan-

13

May

-13

Aug

-13

Nov

-13

Mar

-14

Jun-

14

Sep-

14

Dec

-14

µStr

ain

Date

ERSG 7ERSG 9ERSG 10

Page 58: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

54

Figure 50: Electrical resistance strain gage measurements – approach slab ‘C’

Figure 51: Electrical resistance strain gage measurements – approach slab ‘D’

6.2.3 Vibrating Wire Displacement Gages

Displacement readings from VWDGs located on either side of the Bent One and Bent Four approaches are shown in Table 20 and Table 21 and Figure 52 and Figure 53.

-14000-12000-10000

-8000-6000-4000-2000

02000400060008000

Oct

-12

Jan-

13

May

-13

Aug

-13

Nov

-13

Mar

-14

Jun-

14

Sep-

14

Dec

-14

µStr

ain

Date

ERSG 3ERSG 4ERSG 5ERSG 6

-14000-12000-10000

-8000-6000-4000-2000

02000400060008000

Oct

-12

Jan-

13

May

-13

Aug

-13

Nov

-13

Mar

-14

Jun-

14

Sep-

14

Dec

-14

µStr

ain

Date

ERSG 1ERSG 2

Page 59: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

55

Table 20: Vibrating wire displacement gage measurements – Bent One

Measurement Description Date Displacement (mm)

VWDG 1

1 Initial reading - 4:00 pm 2/14/2013 0.00

2 Bridge completed - before cover plate 3/27/2013 1.19

3 Bridge completed - after cover plate 3/27/2013 0.72

4 3 months after bridge completed - 11:00 am 6/28/2013 -1.50

5 6 months after bridge completed - 12:30 pm 9/16/2013 -0.68

6 13 months after bridge completed - 12:00 noon 4/23/2014 -1.32

7 18 months after bridge completed - 12:00 noon 9/18/2014 0.59

VWDG 2

1 Initial reading - 4:00 pm 2/14/2013 0.00

2 Bridge completed - before cover plate 3/27/2013 1.57

3 Bridge completed - after cover plate 3/27/2013 1.08

4 3 months after bridge completed - 11:00 am 6/28/2013 -0.38

5 6 months after bridge completed - 12:30 pm 9/16/2013 1.02

6 13 months after bridge completed - 12:00 noon 4/23/2014 -0.04

7 18 months after bridge completed - 12:00 noon 9/18/2014 2.27

Figure 52: Vibrating wire displacement gage measurements – Bent One

-2.00

-1.00

0.00

1.00

2.00

3.00

4.00

5.00

Jan-

13

Mar

-13

May

-13

Jun-

13

Aug

-13

Oct

-13

Nov

-13

Jan-

14

Mar

-14

Apr

-14

Jun-

14

Jul-1

4

Sep-

14

Nov

-14

Disp

lace

men

t (m

m)

Date

VWDG 1

VWDG 2

Page 60: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

56

Table 21: Vibrating wire displacement gage measurements – Bent Four

Measurement Description Date Displacement (mm)

VWDG 3

1 Initial reading - 4:00 pm 2/14/2013 0.00

2 Bridge completed - before cover plate 3/27/2013 0.70

3 Bridge Completed - after cover plate 3/27/2013 0.53

4 3 months after bridge completed - 11:00 am 6/28/2013 -0.04

5 6 months after bridge completed - 12:30 pm 9/16/2013 -0.11

6 13 months after bridge completed - 12:00 noon 4/23/2014 2.15

7 18 mo. after bridge completed - 12:00 pm 9/18/2014 4.08

VWDG 4

1 Initial Reading - 4:00 pm 2/14/2013 0.00

2 Bridge completed - before cover plate 3/27/2013 1.41

3 Bridge completed - after cover plate 3/27/2013 1.36

4 3 months after bridge completed - 11:00 am 6/28/2013 -0.92

5 6 months after bridge completed - 12:30 noon 9/16/2013 0.17

6 13 months after bridge completed - 12:00 noon 4/23/2014 -1.52

7 18 months after bridge completed - 12:00 noon 9/18/2014 0.02

Figure 53: Vibrating wire displacement gage measurements – Bent Four

-2.00

-1.00

0.00

1.00

2.00

3.00

4.00

5.00

Jan-

13

Mar

-13

May

-13

Jun-

13

Aug

-13

Oct

-13

Nov

-13

Jan-

14

Mar

-14

Apr

-14

Jun-

14

Jul-1

4

Sep-

14

Nov

-14

Disp

lace

men

t (m

m)

Date

VWDG 3VWDG 4

Page 61: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

57

Load Testing 6.3

Results from the dynamic and static load tests are presented in the tables and figures below. ERSG readings are corrected for gage length and VWSG readings are corrected for temperature effects.

6.3.1 Dynamic Loading

Plots showing the change in strain with respect to time during dynamic loading of the Bent One approach slabs are presented below. Figure 54 shows results for the first load test Load Case 1 passes at 5 mph and Figure 55 shows the results for the same load case passes at 45 mph. Figure 56 shows test results for the first load test Load Case 2 passes at 5 mph and Figure 57 shows test results for the same load case passes at 45 mph.

Dynamic loading was not conducted during the load testing at 13 months after bridge completion as the sensor wires were vandalized. Repairs were conducted to re-attach the ERSG wires just prior to the third load test (18 months after bridge completion). Figure 58 shows results for the third load test Load Case 1 passes at 5 mph and Figure 59 shows the results for the same load case passes at 45 mph. Figure 60 shows test results for the third load test Load Case 2 passes at 5 mph and Figure 61 shows test results for the same load case passes at 45 mph.

Page 62: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

58

Figure 54: First load test: Load Case 1, 5 mph pass

a) Test 1

b) Test 2

c) Test 3

Page 63: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

59

Figure 55: First load test: Load Case 1, 45 mph pass

a) Test 1

b) Test 2

c) Test 3

Page 64: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

60

Figure 56: First load test: Load Case 2, 5 mph pass

a) Test 1

b) Test 2

c) Test 3

Page 65: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

61

Figure 57: First load test: Load Case 2, 45 mph pass

a) Test 1

b) Test 2

c) Test 3

Page 66: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

62

Figure 58: Third load test: Load Case 1, 5 mph pass

a) Test 1

b) Test 2

c) Test 3

-50

-40

-30

-20

-10

0

10

20

30

40

50

35 40 45 50 55µstr

ain

Time (s)

ERSG 10

ERSG 12

-50

-40

-30

-20

-10

0

10

20

30

40

50

40 45 50 55 60µstr

ain

Time (s)

ERSG 10

ERSG 12

-50

-40

-30

-20

-10

0

10

20

30

40

50

30 35 40 45 50µstr

ain

Time (s)

ERSG 10

ERSG 12

Page 67: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

63

Figure 59: Third load test: Load Case 1, 45 mph pass

a) Test 1

b) Test 2

c) Test 3

-200

-150

-100

-50

0

50

100

150

200

90 95 100 105 110µstr

ain

Time (s)

ERSG 10

ERSG 12

-200

-150

-100

-50

0

50

100

150

200

285 290 295 300 305µstr

ain

Time (s)

ERSG 10

ERSG 12

-200

-150

-100

-50

0

50

100

150

200

60 65 70 75 80µstr

ain

Time (s)

ERSG 10

ERSG 12

Page 68: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

64

Figure 60: Third load test: Load Case 2, 5 mph pass

a) Test 1

b) Test 2

c) Test 3

-50

-40

-30

-20

-10

0

10

20

30

40

50

30 35 40 45 50µstr

ain

Time (s)

ERSG 3

ERSG 5

ERSG 6

-50

-40

-30

-20

-10

0

10

20

30

40

50

55 60 65 70 75µstr

ain

Time (s)

ERSG 3

ERSG 5

ERSG 6

-50

-40

-30

-20

-10

0

10

20

30

40

50

30 35 40 45 50µstr

ain

Time (s)

ERSG 3

ERSG 5

ERSG 6

Page 69: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

65

Figure 61: Third load test: Load Case 2, 45 mph pass

a) Test 1

b) Test 2

c) Test 3

-50

-40

-30

-20

-10

0

10

20

30

40

50

5 10 15 20 25µstr

ain

Time (s)

ERSG 3

ERSG 5

ERSG 6

-50

-40

-30

-20

-10

0

10

20

30

40

50

130 135 140 145 150µstr

ain

Time (s)

ERSG 3

ERSG 5

ERSG 6

-50

-40

-30

-20

-10

0

10

20

30

40

50

140 145 150 155 160µstr

ain

Time (s)

ERSG 3

ERSG 5

ERSG 6

Page 70: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

66

6.3.2 Static loading

The results from static loading on the Bent One approach slabs are presented below. The tables and figures show the change in strain (Δμ-strain) occurring while the Bent One approach slab system was subjected to static loading. Initial readings were recorded during live load free conditions and then readings were taken while the load truck was parked on the approach. For the first load test (September 16, 2013), Load Case 3 test results are shown in Table 22 and Figure 62 while Load Case 4 test results are shown in Table 23 and Figure 63. For the second load test (April 23, 2014), Load Case 3 test results are shown in Table 24 and Figure 64 while Load Case 4 test results are shown in Table 25 and Figure 65. For the third load test (September 18, 2014), Load Case 3 test results are shown in Table 26 and Figure 66 while Load Case 4 test results are shown in Table 27 and Figure 67. Strain readings have been corrected for temperature effects.

Table 22: Static load test results – first load test, Load Case 3 Gage Measurement Load condition μ-strain ∆μ-strain

VWSG-T1

1 Before 221

-1.1 During 220

2 Before 220

1.1 During 221

3 Before 222

0.1 During 223

VWSG-T2

1 Before 114

0.6 During 115

2 Before 114

1.7 During 116

3 Before 114

2.7 During 117

Page 71: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

67

Figure 62: Static load test results – First load test, Load Case 3

-1.5

-1.0

-0.5

0.0

0.5

1.0

1.5

2.0

2.5

3.0

0 1 2 3

∆µStrain

Measurement

VWSG-T1

VWSG-T2

Page 72: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

68

Table 23: Static load test results – first load test, Load Case 4

Gage Measurement Load condition μ-strain ∆μ-strain

VWSG-P1

1 Before 178

5.9 During 184

2 Before 178

7.7 During 186

3 Before 179

6.6 During 186

VWSG-P2

1 Before 201

0.1 During 201

2 Before 205

-0.1 During 205

3 Before 203

-0.1 During 203

VWSG-P3

1 Before 87.2

-1.4 During 85.9

2 Before 88.1

-1.3 During 86.8

3 Before 89.0

0.0 During 89.0

VWSG-T3

1 Before 195

1.0 During 197

2 Before 195

3.2 During 199

3 Before 200

-1.1 During 199

Page 73: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

69

Figure 63: Static load test results – first load test, Load Case 4

-2.0

0.0

2.0

4.0

6.0

8.0

10.0

0 1 2 3

∆µSt

rain

Measurement

VWSG-P1

VWSG-P2

VWSG-P3

VWSG-T3

Page 74: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

70

Table 24: Static load test results – second load test, Load Case 3

Gage Measurement Load condition μ-strain ∆μ-strain

VWSG-T1

1 Before 62.8

-0.4 During 62.4

2 Before 62.4

-1.2 During 61.2

3 Before 61.5

1.0 During 62.5

VWSG-T2

1 Before -389.0

-3.0 During -392.0

2 Before -389.0

-2.7 During -391.7

3 Before -389.0

-1.2 During -390.2

Figure 64: Static load test results – second load test, Load Case 3

-4.0

-3.0

-2.0

-1.0

0.0

1.0

2.0

0 1 2 3

∆µStrain

Measurement

VWSG-T1

VWSG-T2

Page 75: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

71

Table 25: Static load test results – second load test, Load Case 4

Gage Measurement Load condition μ-strain ∆μ-strain

VWSG-P1

1 Before 129.5

6.5 During 136.0

2 Before 129.5

7.9 During 137.4

3 Before 129.5

6.5 During 136.0

VWSG-P2

1 Before 13.7

6.0 During 19.7

2 Before 13.3

5.1 During 18.4

3 Before 13.7

4.8 During 18.5

VWSG-P3

1 Before -28.2

4.5 During -23.7

2 Before -27.3

3.8 During -23.5

3 Before -27

3.6 During -23.4

VWSG-T3

1 Before 54.5

5.9 During 60.4

2 Before 56.2

5.4 During 61.6

3 Before 54.9

8 During 62.9

Page 76: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

72

Figure 65: Static load test results – second load test, Load Case 4

Table 26: Static load test results – third load test, Load Case 3 Gage Measurement Load condition μ-strain ∆μ-strain

VWSG-T1

1 Before 49.4 1.4 During 50.8

2 Before 50.5

1.8 During 52.3

3 Before 50.5

1.5 During 52.1

VWSG-T2

1 Before -400.1

29.8 During -370.3

2 Before -398.8

29.0 During -369.8

3 Before -347.9

-22.2 During -370.2

0.0

2.0

4.0

6.0

8.0

10.0

0 1 2 3

∆µSt

rain

Measurement

VWSG-P1

VWSG-P2

VWSG-P3

VWSG-T3

Page 77: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

73

Figure 66: Static load test results – third load test, Load Case 3

-30.0

-20.0

-10.0

0.0

10.0

20.0

30.0

40.0

0 1 2 3

∆µStrain

Measurement

VWSG-T1

VWSG-T2

Page 78: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

74

Table 27: Static load test results – third load test, Load Case 4

Gage Measurement Load condition μ-strain ∆μ-strain

VWSG-P1

1 Before 150.4

4.0 During 154.5

2 Before 151.7

4.1 During 155.9

3 Before 151.8

3.9 During 155.8

VWSG-P2

1 Before 36.7

10.2 During 46.9

2 Before 37.7

10.3 During 48.0

3 Before 36.8

10.1 During 46.9

VWSG-P3

1 Before -1.7

-0.3 During -2.0

2 Before -2.8

-0.8 During -2.0

3 Before -1.5

-0.4 During -1.9

VWSG-T3

1 Before -80.7

-0.3 During -80.9

2 Before -81.5

0.4 During -81.0

3 Before -80.2

0.3 During -79.8

Page 79: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

75

Figure 67: Static load test results – third load test, Load Case 4

7 Discussion of Results

The results of long-term monitoring of strains and displacements on the Bent One and Bent Four approaches are discussed below.

Long-term Measurements 7.1

Discrete measurements collected from VWSGs, ERSGs, and VWDGs during the casting of approach slabs, during general construction of bridge approaches and adjoining roadways, and up to 18 months of service are discussed below.

7.1.1 Vibrating Wire Strain Gages

Discrete measurements collected from VWSGs placed within the Bent One approach slabs and shear key closures show similar trends. Variation in strain is shown in Figure 45 to Figure 47. To assess overall performance of the approach slab system the strain readings collected during the first 18 months of service are considered relative to measurements recorded 3 days after casting. At this time (3 days after casting) the concrete was hardened and the approach slabs were fully supported by rigid steel decks in the precast yard. In similar fashion, strain readings collected during the first 18 months of service from VWSGs located in the shear key closures were compared with strain readings collected immediately after concrete was placed in the closures. From the ACI 318 building code the tensile rupture stress (fr) for concrete may be taken as:

fr = 7.5 λ �𝑓′𝑐 (ACI 318)

-2.0

0.0

2.0

4.0

6.0

8.0

10.0

12.0

0 1 2 3

∆µSt

rain

Measurement

VWSG-P1

VWSG-P2

VWSG-P3

VWSG-T3

Page 80: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

76

Where λ, a modification factor for light-weight concrete, is equal to 1.0 for normal weight concrete and 𝑓′𝑐 is the 28 day compressive strength of the concrete. This relationship can be used to estimate the tensile rupture stress of the concrete. Using the relationship between stress and strain, given by the modulus of elasticity (Ec), the tensile rupture strains can be estimated for each batch of concrete (Table 28). The tensile rupture strains (εr) for the concrete used in the approach slab systems are on the order of 150 µ-strain.

Based on commentary from the ACI 318, the compressive strain at ultimate stress (εc), where significant cracking begins to occur, is between 1,500 to 2,000 µ-strain. For the purposes of this report, a value of 2,000 µ-strain will be considered the cracking strain for areas of the approach slab system in compression. The values of compressive cracking strains are also shown in Table 28.

Table 28: Concrete cracking strains for approach slab system

Batch used for f'c (psi) Ec (106 psi) fr (psi) εr (10-6) εc (10-6)

1 Slab B 10,640 5.67 774 136 2,000

2 Slab C 10,650 5.73 774 135 2,000

3 Slabs A, D 9,680 5.70 738 129 2,000

4 Shear Key 5,400 3.18 551 173 2,000

Strain readings collected from VWSGs within the approach slabs are significantly less than the expected tensile rupture strains for the concrete approach slab system. For VWSGs placed within the approach slabs, the maximum measured tensile strain was 83 µ-strain relative to the strain conditions 3 days after the approach slabs were cast. All three VWSGs within the approach slabs showed tensile strains during the first six months of monitoring. At 18 months, VWSG P3 in slab ‘A’ and VWSG P2 in slab ‘B’ showed compressive strains relative to the strain conditions 3 days after the approach slabs were cast.

Strain readings collected from VWSGs placed within the shear key shows that the maximum measured tensile strain was 126 µ-strain relative to the strains occurring immediately after concrete placement. All VWSGs within shear key closures showed compressive strains after 18 months of testing. Overall strains within shear key closures are slightly larger than the strains occurring within the approach slabs but less than the expected rupture strains. Strain measurements collected from VWSGs within both the precast approach slabs and the shear key closures are within tolerable limits for cracking of the concrete.

7.1.2 Electrical Resistance Strain Gages

Discrete strain measurements collected from ERSGs placed within the Bent One approach slabs were inconsistent. Some ERSGs seem to provide data that is reasonable and concurrent with data collected from nearby VWSGs but many of the ERSGs show unrealistic strain readings. This is not unexpected as this type of gage is not as durable as the vibrating wire strain gages.

Readings were not taken during the load testing at 13 months after bridge completion as the sensor wires were cut (vandalized). Strain readings collected after six months of service range from as little as

Page 81: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

77

28 µ-strain up to more than 2,600 µ-strain relative to strain readings collected immediately after precast slabs were set on the Bent One approach. Based on compressive strength and modulus of elasticity tests, the compressive rupture strains, shown in Table 28, for the concrete used in the approach slab system is on the order of 2,000 µ-strain, and the tensile rupture strains are on the order of 150 µ-strain. Many of the ERSG readings, however, exceed these strains even though the VWSG readings are significantly less than the calculated rupture strains. Furthermore, the approaches show no visual signs of distress with the exception of visible cracking in the asphalt roadway as described below. Given that these measurements are recorded during live-load free conditions strain readings well beyond the rupture strains are not anticipated. It is likely that the long-term discrete readings collected from many of the ERSGs do not reflect the actual behavior of the approach slab system, and therefore much of the long-term data from the ERSGs should be discounted.

The exact cause of noise within the data set is difficult to determine, however, ERSGs are often unreliable. Some difficulty collecting data from ERSGs arose during the dynamic load testing that could be related to the data acquisition systems. It is possible that similar issues could be the reason for scatter in the long-term measurements as well. Well known and documented challenges with long-term measurements taken from ERSGs are the reason that vibrating wire gages were used in addition to the ERSGs. Due to the nature of the results no conclusions are drawn as to the performance of the approach slab system based on the long-term discrete ERSG measurements.

7.1.3 Vibrating Wire Displacement Gages

Displacement measurements collected from all four VWDGs on Bent One and Bent Four approaches show similar trends with respect to initial readings. The total displacement of the VWDGs from the initial reading up to 18 months of service ranges from approximately -1.52 to 4.08 mm. The largest displacement was observed for VWDG 3 (Table 21), which is located on the Bent Four approach. After 18 months of service VWDGs 2 and 3 exhibited extension relative to the initial reading whereas VWDGs 1 and 4 showed contraction relative to the initial reading.

Relatively small changes can be observed in the displacement readings before and after the cover plate installation. These changes are not thought to be a result of displacement of the bridge approaches and the movements described above take into account the differences between displacement before and after the cover plates were installed. It is difficult to identify with certainty the cause of these small variations. A reasonable conclusion is that during the drilling of holes, which house the anchor bolts by which the cover plates are attached, the displacement gages may have been disturbed by the vibration of the hammer drill. The anchor holes for the cover plates are fairly close to the anchors which attach the displacement gages to the parapet. However, these changes are small, ranging from 0.05 mm to 0.50 mm, and are accounted for because they are measured immediately before and immediately after the installation.

The displacements measured from VWDGs on Bent One and Bent Four approaches are relatively small and show trends that are concurrent with one another. Because readings from the VWDGs are small

Page 82: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

78

(maximum displacement of 4.08 mm) it is reasonable to conclude that movement or settlement of the approach slabs relative to the cast-in-place bridge deck are also small.

Load Testing 7.2

A discussion of load testing results on the Bent One approach slab is presented in the following commentary.

7.2.1 Dynamic Loading

Two dynamic load tests were conducted (instead of three dynamic load tests as originally planned) because the wires were vandalized prior to the second scheduled load test. Results from the dynamic load tests on the Bent One approach at six months and 18 months after bridge completion, respectively, were mixed between Load Cases 1 and 2. The Load Case 2 tests for both 5 mph and 45 mph were consistent for each case for both load tests. However, the Load Case 1 tests for both 5 mph and 45 mph were less coherent.

For the first load test, Load Case 2, the strain profiles of individual tests for the 5 mph passes are very similar. The largest strains occurred on sensor ERSG 7 which is located near the center shear key closure at the middle of the roadway. Very similar strain magnitudes were recorded for both ERSG 10 and 12 which are located next to the shear key closure adjoining approach slabs ‘A’ and ‘B’. A maximum strain for each test was consistently around 30 µ-strain and a minimum strain value of around 15 µ-strain was typical for each test. These strains are well below the calculated rupture strains for the precast concrete approach slab systems. The Load Case 2 strain profiles for each of the 45 mph tests are similar but show some variations in magnitude. Once again the largest strains occurred in sensor ERSG 7 which is located near the center shear key closure at the middle of the roadway. In general ERSG 10 and 12, located next to the shear key closure adjoining approach slabs ‘A’ and ‘B’, experienced lower strains that were similar to one another. The maximum strain for the series of tests was around 160 µ-strain while the minimum strain (based on the largest strain excursion for each gage) was around 50 µ-strain. During Test 2 the maximum strain recorded on ERSG 7 exceeded the expected rupture strains by approximately 50 µ-strain. It is therefore possible that some cracking of the approach slabs could have resulted from this load event. However, all the other strain readings for each of the Load Case 2 tests are below the expected rupture strains of the precast concrete approach slabs.

For the third load test, Load Case 2, similar results were achieved for the 5 mph passes with a maximum relative strain recorded at ERSG 7 of 9 µ-strain and a minimum strain of 2 µ-strain. Similar to the first load test, the Load Case 2 strain profiles for each of the 45 mph tests are similar. However, the maximum strain recorded during the third load test is lower than that recorded during the first load test. The largest strain was also recorded at ERSG 7 which is located near the center shear key closure at the middle of the roadway. In general, ERSG 10 and 12 (located next to the shear key closure adjoining approach slabs ‘A’ and ‘B’) experienced lower strains that were similar to one another. All the strains recorded during the third load test, Load Case 1, are well below the calculated rupture strains for the precast concrete approach slab systems.

Page 83: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

79

The Load Case 1 results from both load tests do not represent expected behavior of the approach slab system. Both 45 mph and 5 mph tests show highly variable results with maximum strains varying by magnitudes as much as 1,000 µ-strain or more for the same test conditions. Both compressive and tensile strains were recorded during the 5 mph and 45 mph passes but strain readings do not follow a harmonic profile as for the Load Case 2 results. Virtually every Load Case 1 test result shows high residual strains long after loading from the trucks. Maximum strains for the 5 mph tests are around 700 µ-strain and for the 45 mph tests are nearly 1,000 µ-strain. These strains are greater than the calculated rupture strains for the precast concrete approach slabs. The only results during Load Case 1 that were similar to those of Load Case 2 were recorded by ERSG 5 during the third load test. The maximum recorded strain by this gage is 8 µ-strain and 66 µ-strain for passes at 5 mph and 45 mph, respectively. These strains are well below the calculated rupture strain.

During the load testing for both Load Case 1 and 2 anomalies with data acquisition occurred. This resulted in a limited number of strain gages being available for collection of data. Three gages were able to be utilized for each load case, except for the third load test, Load Case 1, where only two sensors were utilized. As described previously, ERSGs are known to be unreliable due to issues associated with damage of the wiring embedded in the concrete, waterproofing of the gages, and other issues.

When considering the Load Case 2 test results for both 5 mph and 45 mph passes strains are generally below the calculated rupture strains. A single strain gage experienced strains larger than the rupture strains for the precast concrete slabs during one of the 45 mph passes for the first load test, Load Case 2. However, this strain was much higher than all other strains and still only exceeded the expected rupture strains by about 50 µ-strain. Data collected from strain gages during Load Case 1 does not allow for the drawing of firm conclusions.

7.2.2 Static Loading

Results from the first static load test on the Bent One approach at 6 months after bridge completion were very similar for Load Case 3 and 4. Additionally, the results from the second load test at 13 months and 18 months after bridge completion were similar to those of the first load test. Both approaches experienced very low strains during static loading. Strain readings for all load tests range from -22.2 µ-strain to around 29.8 µ-strain and are shown in Table 22 through Table 27. Some gages experienced both tensile and compressive strains during loading and some gages showed either tensile or compressive strains only. VWSG-T2 recorded the largest strains ranging from -22.2 to 29.8 µ-strain whereas the other gages experienced very low strains, most of which were around 10 µ-strain or less. Trends of increasing strains that may be indicative of damage were not observed. Overall discrete VWSG readings collected during static load tests at 6 months and 13 months after bridge completion were low with a maximum of 8.0 µ-strain while at 18 months after bridge completion higher strains were observed with a maximum of 29.8 µ-strain. All measured strains are less than the calculated rupture strain.

Page 84: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

80

Visual Observations 7.3

Visual inspections were conducted during each of the on-site visits. No visual signs of distress or damage due to service loads, such as cracking or distortions in the pavement surface or around parapets near the approach slab system, were observed up to 13 months after bridge completion. During the last load test, cracks at the interface of the approach slabs and the roadway were observed at both Bents (Figure 68). These cracks are most severe on the side of the bridge associated with vibrating wire displacement gages 1 and 4. In the case of VWDG 3 the largest extension was recorded (3.38 mm relative to the reading taken just after bridge construction) in combination with very small contraction at VWDG 4 (1.39 mm relative to the same point in time). This pattern is consistent with the observed cracking if rotation of the approach slab was a contributing factor. In the case of VWDG 1, a relatively small value of contraction was recorded (0.6 mm relative to the same point in time) in combination with 0.7 mm extension at VWDG 2 (relative to the same point in time). This pattern is again consistent with rotation that may lead to cracking, but the relative values are very small. It does not therefore appear that rotation of the approach slabs is the primary cause of the observed cracking. It is possible that differential settlement between the approach slab and the roadway has contributed to the cracking, perhaps in combination with temperature effects related to the roadway asphalt. No cracks were observed at the approach slab/bridge interface indicating that differential settlement between the approach slabs and the bridge is minimal.

Page 85: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

81

Figure 68: Photographs of observed cracks at approach slab/roadway interface

(Upper, approach to Bent Four looking south; lower, approach to Bent One looking north)

8 Conclusions

After 18 months of service, both the Bent One and Bent Four approach slab systems on the replacement bridge over Big Brown Creek in Union County, South Carolina appear to be functioning as intended based on long-term strain and displacement measurements as well as strain readings collected during load testing. No cracking or deformations have been observed around shear key joints connecting adjacent precast slabs or in other areas on the approach. The only cracks observed were at the approach slab/roadway interface as shown in Figure 68. Measured strains within precast panels and within shear key joints are generally below the calculated rupture strains for the approach slab system. Displacement readings collected from vibrating wire displacement gages were small and indicate negligible movement of the approach slabs relative to the cast-in-place bridge deck.

Long-term strain measurements collected throughout the first 18 months of service are generally well below the calculated rupture strains of the concrete approach slab system. Long-term Vibrating Wire Strain Gage (VWSG) readings show consistent trends among different gages placed in the various locations within the approach slab system and the maximum measured strains relative to initial conditions are below the rupture strains. Long-term Electrical Resistance Strain Gage (ERSG) readings

Page 86: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

82

collected during live load free conditions, throughout the first 18 months of service are scattered. The sensor wires were vandalized prior to the visit at 13 months of service. The reason for inconsistent long-term results for the ERSGs is not fully understood, however ERSGs embedded in concrete are often unreliable and this is not unexpected. Long-term displacement readings collected during the first 18 months of service from Vibrating Wire Displacement Gages (VWDGs) show similar trends for all gages and overall indicate negligible movement of the approach slabs relative to the cast-in-place bridge deck.

The first, second, and third load tests (static testing was completed during the second load test, however, dynamic load testing was not conducted due to the vandalism of the sensor wires) on the Bent One approach have been concluded and both dynamic and static load test results appear to indicate that the approach slab systems are functioning as intended. In general, strain readings collected from ERSGs during dynamic load testing are below or, in one case, close to the expected rupture strains of the concrete. Strain measurements collected from VWSGs during static load tests were negligible.

This project allowed for the assessment of the performance of precast approach slabs systems as a potential substitute for cast-in-place approach slab systems. The results showed satisfying performance of the precast approach slabs system in terms of cracking and settlement under service loading conditions. Future projects should assess the potential for differential settlement between the approach slabs and the roadway as cracks were observed in this region after 18 months of service.

9 References

ASTM C39 / C39M – 12a. 2012. Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens. American Society for Testing and Materials, 5 1-12.

ASTM C469 / C469M – 10. 2010. Standard Test Method for Static Modulus of Elasticity and Poisson's Ratio of Concrete in Compression. American Society for Testing and Materials, 1-12.

ASTM C31 / C31M – 12. 2012. Standard Practice for Making and Curing Concrete Test Specimens in the Field. American Society for Testing and Materials, 1-7.

ASTM C143 / C143M – 12. 2012. Standard Test Method for Slump of Hydraulic-Cement Concrete. American Society for Testing and Materials, 1-5.

Building Code Requirements for Structural Concrete (ACI 318-14) and Commentary. 2014. An ACI Standard. Farmington Hills, MI.: American Concrete Institute.

Page 87: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

IBRD Program: In-Situ Monitoring of Precast Approach Slabs University of South Carolina

APPENDIX

Description

Page

Approach Slab Framing Plan ......................................................................................................... A1

Approach Slab Panel 1-1 Detail .................................................................................................... A2

Approach Slab Panel 1-3 Detail ..................................................................................................... A3

Approach Slab Panel 1-2 Detail ..................................................................................................... A4

Approach Slab Panel 2-2 Detail ..................................................................................................... A5

Approach Slab Panel 2-3 Detail ..................................................................................................... A6

Approach Slab Panel 2-1 Detail ..................................................................................................... A7

Bent One Approach Slab Instrumentation Schematic ................................................................. A8

Bent Four Approach Slab Instrumentation Schematic ................................................................. A9

Detail A - Bent One Approach Slab Instrumentation Schematic ................................................ A10

Detail B - Bent One Approach Slab Instrumentation Schematic ................................................ A11

Detail C - Bent One Approach Slab Instrumentation Schematic ................................................ A12

Detail D and E- Bent One Approach Slab Instrumentation Schematic ....................................... A13

Detail F and G - Bent One Approach Slab Instrumentation Schematic ...................................... A14

Page 88: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

A1

Page 89: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

A2

Page 90: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

A3

Page 91: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

A4

Page 92: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

A5

Page 93: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

A6

Page 94: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

A7

Page 95: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

A8

Page 96: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

A9

Page 97: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

A10

Page 98: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

A11

Page 99: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

A12

Page 100: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

A13

Page 101: In-Situ Monitoring of Precast Concrete Approach Slab Systems · 2017. 9. 20. · of precast concrete approach slab systems. The performance of the precast concrete approach slabs

A14