Upload
ezekiel-farnsworth
View
215
Download
3
Embed Size (px)
Citation preview
IMPACT TO FREQUENCY CONTROL DURING STARTUP AND SHUT DOWN OF UNITS
Sandip Sharma ERCOT Operations Analysis
1
IntroductionThis presentation is intended to explain ERCOT’s expectation of the Resource Entities and QSEs during start-up and shut-down of the units based on the ERCOT Protocol, Operating Guides and Business Practice manual.
Due to improper start-up and shut-down at the individual Resource level, there have been performance issues and Base Point Deviation Charges.
At the system level, ERCOT has experienced frequency deviations and exhaustion of regulating reserves.
2
ObjectivesAt the completion of this course of instruction you will:
1. Identify the QSE’s responsibilities during Startup and Shutdown.
2. Identify the correct sequence of generation resource Startup.
3. Identify the correct sequence of generation resource Shutdown.
4. Identify the impact on ERCOT Grid Operations of improper start-up or shut-down of units.
5. Identify the impact on ERCOT Market Operations of improper start-up or shut-down of units.
3
AgendaDefinitionsResource StatusQSEs responsibility during Start-upStart-up SequenceStart-up issuesQSEs responsibility during Shut-DownShutdown issuesOther observed issuesQuestions
4
Definitions STARTUP – The Resource is On-Line and in a start-up sequence
and has no Ancillary Service Obligations. This Resource Status is only to be used for Real-Time telemetry purposes;
SHUTDOWN – The Resource is On-Line and in a shut-down sequence, and has no Ancillary Service Obligations. This Resource Status is only to be used for Real-Time telemetry purposes;
GREDP – Generation Resource Energy Deployment Performance SCED – Security Constrained Economic Dispatch RLC – Resource Limit Calculator LSL – Low Sustained Limit HSL – High Sustained Limit NURR – Normal Up-Ramp Rate NDRR – Normal Down-Ramp Rate BP – Base Point
5
Resource Status
Offline Status OUT – 11 (offline and unavailable) OFFNS – 12 (reserved for offline non-spinning) OFF – 13 (offline but available)
Online Status ONRUC – 1 (hour is RUC-committed interval) ONREG – 2 (with energy offer curve and providing regulation) ON – 3 (online with energy offer curve) ONDSR – 4 (dynamically scheduled resources) ONOS – 5 (with output schedule) ONOSREG – 6 (with output schedule providing regulation) ONDSRREG – 7 (dynamically scheduled resource providing regulation) ONOPTOUT – 18 (online and the hour is a RUC buy back hour)
Startup and Shutdown Status STARTUP – 16 SHUTDOWN - 15
6
QSE’s Responsibility During Start-upOnce the generator breaker is closed, QSE must change
telemetered Resource Status to STARTUP from OFF. This should be done about a minute prior to SCED run.
The QSE should telemeter a Normal Up Ramp Rate value to ERCOT that reflects the MW per minute rate at which the QSE anticipates bringing the Resource On-Line.
Low Sustained Limit (LSL) and High Sustained Limit (HSL) should reflect the true capabilities of the Resource (In other words, don’t mess with them)
ERCOT does not expect the telemetered Ramp Rate value will be exactly correct, but the QSE should update the ramp rate as often as needed during the start-up process to provide a reasonable estimation
7
Start-up SequenceThe QSE should align bringing the Resource On-
Line after a SCED execution, which takes into consideration the STARTUP status.
RLC will calculate Low Dispatch Limit (LDL) as the telemetered real power output plus the five-minute ramping capability of the Resources.
RLC will set the High Dispatch Limit (HDL) equal to the Low Dispatch Limit (LDL)
8
Start-up SequenceWhen SCED observes Resource Status of STARTUP,
SCED will issue a Base Point equal to LDL which is equal the current telemetered net real power plus five times normal ramp rate of the Resource
During periods in which the Resource has a telemetered Resource Status of STARTUP, the QSE is exempt from GREDP scoring and Base Point deviation charges.
Once the Resource has reached a stable operating condition and is ready to be dispatched normally by SCED, the QSE should change the Resource Status to an appropriate online status and begin responding directly to ERCOT dispatch instructions.
9
Observed Issues #1. Too high NURR during start-up
10
0
3
6
9
12
15
18
21
24
27
30
-150
-120
-90
-60
-30
0
30
60
90
120
150
09:55 10:00 10:05 10:10 10:15 10:20 10:25 10:30 10:35 10:40 10:45 10:50
NURR & Status
MW
GENERATION BASEPOINT DEVIATION RESOURCE STATUS NURR
Observed Issues #2. Too Low NURR during start-up
0
3
6
9
12
15
18
21
24
27
30
-210
-180
-150
-120
-90
-60
-30
0
30
60
90
120
150
180
210
240
270
300
330
360
390
420
450
480
510
09:40 09:45 09:50 09:55 10:00 10:05 10:10 10:15 10:20 10:25 10:30 10:35
NURR & StatusMW
GENERATION BASEPOINT DEVIATION RESOURCE STATUS NURR
11
CORRECT STARTUP SEQUENCE
12
0
3
6
9
12
15
18
21
24
27
30
33
36
39
42
45
48
51
54
57
60
-100
-65
-30
5
40
75
110
145
180
215
250
285
320
355
390
425
460
495
530
565
600
05:25 05:30 05:35 05:40 05:45 05:50 05:55 06:00 06:05 06:10 06:15 06:20
NURR & StatusMW
GENERATION BASEPOINT DEVIATION RESOURCE STATUS NURR
QSEs Responsibility During Shut-DownThe QSE will initiate the shut-down sequence by changing
the Resource status to SHUTDOWNThe QSE should telemeter a Normal Down Ramp Rate
value to ERCOT that reflects the MW per minute rate at which the QSE anticipates bringing the Resource Off-Line
The QSE should not begin taking the Resource Off-Line until a SCED execution has completed taking into consideration the SHUTDOWN status.
13
Shut-Down SequenceRLC will calculate HDL as the telemetered real
power output minus the five-minute ramping capability
RLC will set the Low Dispatch Limit (LDL) equal to the High Dispatch Limit (HDL)
SCED will issue Base Points equal to the HDL and ramp the resource smoothly down to a Base Point of zero
14
Shut-Down SequenceDuring the shut-down process when the Base Points
issued by SCED is above the Resource’s telemetered LSL, the QSE must follow the Base Point instructions issued by SCED
For periods in which the SCED Base Point is below the telemetered LSL, the QSE is exempt from Generation GREDP scoring and Base Point deviation charges
Once the Resource has reached a real power output level of zero and the generator breaker has been opened, the QSE will change the telemetered Resource Status to an appropriate offline status
15
Observed Issues #1. NDRR not updated accurately during shut-down
16
3
6
9
12
15
18
21
24
27
30
33
-200
-80
40
160
280
400
520
640
760
880
1000
16:40 16:45 16:50 16:55 17:00 17:05 17:10 17:15 17:20 17:25 17:30 17:35
NDRR &Status
MW
UDBP SCED BP GENERATIONBASEPOINT DEVIATION RESOURCE STATUS NDRR
Observed Issues#2 Improper sequence of shut-down
17
0
2
4
6
8
10
12
14
16
18
20
-200
-130
-60
10
80
150
220
290
360
430
500
22:10 22:15 22:20 22:25 22:30 22:35 22:40 22:45 22:50 22:55 23:00 23:05
NDRR &StatusMW
UDBP SCED BP GENERATIONBASEPOINT DEVIATION RESOURCE STATUS NDRR
CORRECT SHUTDOWN SEQUENCE
18
0
2.5
5
7.5
10
12.5
15
17.5
20
22.5
25
-100
-50
0
50
100
150
200
250
300
350
400
23:00 23:05 23:10 23:15 23:20 23:25 23:30 23:35 23:40 23:45 23:50 23:55
NDRR & Status
MW
GENERATION BASEPOINT DEVIATION RESOURCE STATUS NDRR
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
-100
-75
-50
-25
0
25
50
75
100
125
150
175
200
225
250
275
300
325
350
375
400
23:00 23:05 23:10 23:15 23:20 23:25 23:30 23:35 23:40 23:45 23:50 23:55
NDRR &Status
MW
UDBP SCED BP GENERATIONBASEPOINT DEVIATION RESOURCE STATUS NDRR
Other Observed IssuesNURR/NDRR telemetry is correct but it is outside the
RARF reasonability limitFor temporary limitations like configuration change,
activation of power augmentation, start second boiler feed-pump, etc.Resource HSLs are not updated to reflect temporary limitations SCED continuously dispatches these Resources economicallyWhile SCED dispatches these Resources with temporary limits
higher, SCED is also dispatching other more expensive generator lower. This has market impact as well as affects grid frequency and leads to exhaustion of regulation-up service.
The impact of these large deviations are similar to what were discussed with Startup and Shutdown
1For additional details on expected actions from a QSE, please see “ERCOT and QSE Operations Practices During the Operating Hour” Section 3.2 Generation Resource Power Operation. (http://www.ercot.com/content/mktrules/bpm/BP%20ERCOT%20And%20QSE%20Operations%20Practices_v5%205.doc )
19
Temporary Limitations without AS
-150
-140
-130
-120
-110
-100
-90
-80
-70
-60
-50
-40
-30
-20
-10
0
10
20
30
40
50
-100
-60
-20
20
60
100
140
180
220
260
300
340
380
420
460
500
540
580
620
660
700
12:15 12:20 12:25 12:30 12:35 12:40 12:45 12:50 12:55 13:00 13:05 13:10
NURR/BPDeviation
(MW)
MW
UDBP SCED BP GENERATION HSL HASL BASEPOINT DEVIATION NURR
Into duct firing mode
20
Temporary Limitations with AS
-150
-140
-130
-120
-110
-100
-90
-80
-70
-60
-50
-40
-30
-20
-10
0
10
20
30
40
50
-100
-60
-20
20
60
100
140
180
220
260
300
340
380
420
460
500
540
580
620
660
700
12:15 12:20 12:25 12:30 12:35 12:40 12:45 12:50 12:55 13:00 13:05 13:10
NURR/BPDeviation
(MW)
MW
UDBP SCED BP GENERATION HSL HASL BASEPOINT DEVIATION NURR
Into duct firing mode
21
SummaryImproper start-up and shut-down impacts
Grid Frequency, leads to exhaustion of regulation service and has market impacts
What RLC and SCED expects during Start-Up and Shut-Down of units were explained
Proper sequence of start-up and shut-down were explained
22
QuestionsQuestions
????23
1. The QSE’s responsibilities during Startup include:
a) about a minute before a SCED run, change Resource Status from OFF to STARTUP
b) calculate Low Dispatch Limit (LDL)
c) set the High Dispatch Limit (HDL) equal to the Low Dispatch Limit (LDL)
d) issue a Base Point equal to LDL which is equal the current telemetered net real power
24
2. When SCED observes a Resource Status of STARTUP on a unit:
a) It will issue a Base Point equal to LDL which is equal to current output plus 5 times NURR.
b) It will issue a Base Point equal to Normal Down Ramp Rate value.
c) It will change the Resource Status to ONLINE.
d) It will begin economically dispatching the unit.
25
3. The QSE correct sequence of generation resource Shut-Down is:
a) The QSE will initiate the shut-down sequence by changing the Resource status to SHUTDOWN
b) The QSE will telemeter a Normal Down Ramp Rate value to ERCOT
c) The QSE should not begin taking the resource off-line until a SCED execution
d) All of the above
26
4. One impact on ERCOT Grid Operations of improper shut-down of units is:
a) Improper shut-down impacts grid frequency
b) Off line non-spin is impacted
c) Start of HRUC delayed during those hours
d) Load resources are incorrectly calculated
27
5. One impact on ERCOT Market Operations of improper start-up of units is:
a) Prolonged regulation deployment and impacts system lambda calculation
b) DRUC is delayed for those hours
c) HRUC is delayed for those hours
d) Mid-term load forecast is incorrectly calculated
28