Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
IEA CCS Summer School
TransportationJames Watt, AMEC
2
Agenda
Current Experience
Compressors
Pipelines
Design issues for transport
Shipping
Infrastructure development
3
4
5
CO2 Source CompressionPipeline/
Boosting
Compression/
PumpingWellhead
Reservoir
CO2 Recovery
Oil Refining
Fuel Power Plant
Grid
Requirements
Emission
ControlCapture Dehydration Compression
Pipeline /
Boosting
Well
Boosting
(optional)
Sequestration
site
Storage Feedback
Emitter drivers
Grid Requirements
Lo
ad
Time
Dynamics are different
Power plants are not constant emitters,
they follow grid requirements producing
power between 40 and 90% of the time
Well heads and storage sites are
expected to prefer continuous operation
6
US Pipelines
CO2 Pipelines
CO2 Pipelines - planned
5000km, natural and anthropogenic sources
7
Transport Compression
6000 km, predominantly in the
US and Canada
50 million tonnes per annum
10 incidents
Typically dense phase or
supercritical fluid
Typical compressors used on
other CO2 processes
8
Compressor Train Options
Variable Speed Drive
Electric
Gas Turbine
Steam Turbine
Diesel/Fuel Oil
Natural Gas
Syngas/H2
Liquid fuels
Integrally Geared
Axial
Centrifugal – single
shaft
Centrifugal -
multiples
Reciprocating
PumpLiquefaction
Air
Water
Chilling
Closed loop
Open loop
Sea water
Chilled water
Refrigerant
Carbon Dioxide
(sidestream)
Mol Sieve
Glycol
Joule-Thomsom
Absorption
Compression –
Liquid drop out
Water content
Inhibitor injection
DRIVE TYPE PRIME MOVERCOOLING
INTER & AFTER STAGEDEHYDRATION HYDRATE CONTROL
9
Things to watch for,…
Basic configuration depends on
Flexibility
Reliability
Vendor data
Pipeline specification
Parasitic load requirements
In the future compression will
become more integrated
Dehydration technology and
requirements
Glycol, mol sieve, absorbers
Water content
10
Flexibility
Process flexibility How well can the system adjust to flow
changes
Operational flexibility How well can a system adjust to outages,
reliability, composition changes, failures
and start-up
Not just about load factors Flexibility can be caused by the store
Capture plant operating envelope
Pipeline capability (re-use)
Maintenance
Impact of reliability issues
Gaps in performance envelopes
Compressor operating ranges
Compressor inlet/outlet requirements
Multiple emitter impacts
Start-up/Shut-down -20
0
20
40
60
80
100
120
0 50 100 150 200 250
CCGT Uncoupled CCS
Compressor CurveOperating Points
11
Typical regulations and standards
US
“49 CFR 195, Transportation of
Hazardous Liquids by Pipeline”
“49 CFR 192, Transportation of
Natural and Other Gas by Pipelines:
Minimum Federal Safety Standard”
Canada
“Z662-07, Oil and Gas Pipeline
Systems”
Regulations specify design codes
US regulations require the use of
any named code or specification
49 CFR 192 is sometimes also
applied given a release is gaseous not
liquid
BS PD
8010:1
BS3293, 3518, 3974,
4515-1, 4515-2,
4882, 6651, 7361-
1, 4515-2, 4882,
6651, 7361-1,
7910
EN 287, 288,
10204, 10208,
10224, 13480,
60079-10, 60079-
14, ISO 3183-3,
PD 5500
API5L, 6A, RP 5L2
ASMEB16.5, B16.9,
B16.11, B16.20,
B16.21, B16.47,
B31.3, B31.8,
Section VIII
Division 1
MSSSP-44
ASTMA193/A193M
A194/A194M
A312/A312M
A320/A320M
A790/7990M
B423-03
B444-03 NFPANFPA 30
NACEMR-0175
IGETD/1
12
Critical Issues
Process Conditions
Properties
Operating conditions at entry and exit
Flow calculation method
Transient (surge) modelling
Flow characteristics
Typical carbon dioxide compositions
Two phase flow conditions
Piping design
Fracture propagation
Blow down assembly design
Blow down rate basis and calculation
Linebreak controls
Pig trap
Depth of cover
Routing topography
Safety & environmental
Ambient/ground temperature
Blow down rate basis and calculation
Dispersion pattern
Frequency and position of block valves
Leak detection systems
Line inventory
Measurement
Custody transfer methods
Moisture analysis
Material selection
Pipeline materials
Carbon equivalent
Hardness value
Fracture strength
Valve, fitting and trim types
Seal, packing materials of construction
Valve actuators
Cleaning and strength testing
Cleaning
Hydrostatic testing/drying/dewatering
Construction techniques
Corrosion monitoring
External corrosion
Fracture propagation
Special construction and welding
Stress relief
Pipeline Operation
Refrigeration effects during start-up/blow down
Start-up/Shutdown methodology
Line pressuring
Requirement for blow down noise control
Environmental considerations
Operational problems
Operational Safety
13
Key Issues
Caron Dioxide + water
Carbonic acid
Weak acid
Acidity increases with temperatrue and pressure
Clathrates (hydrates) can form at ambient temperatures and relatively low
pressures.
Depressurisation issues
Fracture characteristics of pipelines
Contamination influences
Material influences
14
Impurities
P-T Phase Envelope
Carbon Dioxide - Nitrogen
0
10
20
30
40
50
60
70
80
90
100
-140 -120 -100 -80 -60 -40 -20 0 20 40
Temperature,°C
Pre
ss
ure
, b
ar
CO2 0.1 N2 0.005 N2 0.03 N2 0.04 N2 0.05 N2 0.025 N2 0.06 N2
15
Entry Specification
EU’s Dynamis project has published a proposed entry specification
Based on contaminant issues around
Physical properties
Changes in critical point
HSE issues of contaminants on release
Geologic storage requirements
Corrosion
Provides reduced variability of fluids in a network
Sets part of the design basis for capture plants
EU Dynamis Proposed Entry Specifciation
15
16
Impact of material issues
17
Re-use of existing infrastructure
Existing Natural Gas network
30 – 94 bar
Not suitable for dense phase
Transport of gas is low
Offshore pipelines are higher
design pressures
Distance offshore is a factor
Onshore booster stations can be fitted
Offshore boosters would require a
platform
Existing pipelines are aging
Re-classify a pipeline
Re-do all calculations to appropriate
standard
Inspection and repair
18
19
Shipping vs. Pipelines
Over very long distance
pipelines become less
economical
Conditions are different
-50C, and 6.5 bar
Comparable to,
LNG, -160C, ~atm
LPG, -104C, 6 bar
20
Integration
Could integrate into
infrastructure
Would need storage
Valuable buffer for network
Typically 1.5x volume
Flow
Enables import or export
Enables remote emitters
Can be used to provide stable
flow to stores
The following example
considers Teesside
21
What do you need for shipping?
Ships!!! Plural, more than one
Investment cost
Direct to store
Not flexible, hook-up issues
Not suitable for long injection periods
Import to pipeline network
Flexible
Enables stranded/remote assets
Needs two terminals
Intermediate storage
Compression at source
Storage vessels
Recompression at pipeline/storages
Expensive!
Isle of Grain LNG Phase 1
Typical arrangement of CO2 terminal?
22
Shipping
• Consider Import / Export potential
• Import enables utilisation of a Tees based CO2 pipeline into a storage
site
• Removes flexibility/variance in flow rates through network
• Increases volume transported – reduces costs
• Export enables ship based export for EOR purposes
• Both require expensive terminals and ship fleet
• Terminal c. £150 million CAPEX at import/export points
• Shipping is scenario dependent £170 – 270 million CAPEX
• Significant buffer storage c. 60,000 tonnes
• £5.9 – 7.3/tonne CO2
23
Shipping Conclusions - Teesside
• Transport only costs
• For 10 million tonnes per year the 30 year relative cost is
• Import 4.47 £/te CO2
• For 5 million tonnes per year the 30 year relative cost is
• Import 7.32 £/te CO2
• Export 7.34 £/te CO2
• Influence on network
• Everyone pays
• 1 to 13% increase in network costs
• Importer pays
• 11 to 15% decrease (benefit for onshore emitters)
• Additional onshore CAPEX spend 5-7%
• Import beneficial to network as long as the importer pays the
shipping and terminal cost
• EOR will change this if CO2 has a commodity value
24
Common Infrastructure
Common infrastructure costs are the most difficult to cost or analyse
The assumptions aren’t often clear
Many are driven algorithms using GIS, which aren’t well discussed
Economics differ
Preference for comparison based on overnight cost per tonne
Followed by the complex economics
Modelled cost per tonne
Humber region £1.7/t
Scotland c. £8/t
Tees £2-4/t depending on storage target
Influences on cost per tonne
Period of operation
Scenario’s
Emitter size
Right sizing of pipelines
25
Cost of Infrastructure Schemes
26
James Watt
Process Engineering Manager
AMEC
Lingfield House
Lingfield Point
Darlington, County Durham
DL1 1RW, United Kingdom
Tel +44 (0)1325 744400 Fax +44 (0)1325 744404
DDI +44 (0)1325 744652
mailto:[email protected]
www.amec.com