2
FEATURE ARTICLE 14 I Thermal News MEETING THE HIGHER HEAT DENSITY CHALLENGE The outdated belief that there is a ceiling of around 6 kW of heat per cabinet that can effec- tively be cooled by air is based on an accurate assessment of the innate inefficiencies of stan- dard hot aisle/at cold aisle data centers and a poor understanding of the natural forces that can be harnessed to remove heat from a cabinet. This idea was based on an true understanding of the fixed relationship between airflow, heat dissipa- tion and temperature rise (CFM = 3.1W/ÄT) in the context of a standard hot aisle/cold aisle data center, where there is a dependency relationship between the volume of cold air delivered through a proximate perforated floor tile and a cabinet server heat load, plus the presence of heated server exhaust air in the room. The practical lim- its to how much air you can push through a per- forated floor tile and the looming presence of heated return air conspire to limit how much can be cooled in any particular cabinet. Removing these constraints allows for higher power/heat densities that can potentially be cooled by air. In a data center where the cabinets function as a complete isolation barrier between supply and return air, these constraints are removed. Complete isolation is accomplished using a combination of passive air cooling acces- sories such as blanking filler panels to block bypass airflow, equipment mounting area perimeter sealing air dams, floor-tile cut-out brush seal grommets along with a system to remove the return air from the room into a sus- pended ceiling return air space. Such a system would include a solid rear cabinet door with gas- ket seal and a vertical exhaust duct running between the cabinet and the suspended ceiling, thus creating a ducted exhaust system using pas- sive air cooling. COMPLETE AIRFLOW ISOLATION By implementing a ducted exhaust system, hot exhaust air no longer exists in the room and the dependency on how much air can be pushed through a single per- forated floor tile is eliminated, allowing cold air to be deliv- ered any- where in the room. As heat densities increase The Data Center Cooling Problem SOLVED By Ian Seaton, Technology Marketing Manager, Chatsworth Products, Inc. Passive air cooling solutions not only offer the most efficient way to cool today’s increasing density requirements, but present huge energy savings and a lower initial investment compared to close-coupled and liquid cooled solutions. Passive air cooling can successfully dissipate as much heat as can be generated by commercial servers that fit into a 42 to 45 U cabinet, and in fact more than most close-coupled and liquid-cooled solutions. Based on complete isolation between hot exhaust and cool supply air, passive air cooling solutions provide access to lower data center cooling, which translates into increased supply air tempera- tures and decreased energy consumption. Winter 08/09 I www.ThermalNews.com Figure 1. Typical Cabinet, air re-circu- lates inside the cabinet and into the room.

I FEATURE ARTICLE The Data Center Cooling Problem SOLVED

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

FEATURE ARTICLE14 I Thermal News

MEETING THE HIGHER HEAT DENSITY CHALLENGE

The outdated belief that there is a ceiling of

around 6 kW of heat per cabinet that can effec-

tively be cooled by air is based on an accurate

assessment of the innate inefficiencies of stan-

dard hot aisle/at cold aisle data centers and a

poor understanding of the natural forces that can

be harnessed to remove heat from a cabinet. This

idea was based on an true understanding of the

fixed relationship between airflow, heat dissipa-

tion and temperature rise (CFM = 3.1W/ÄT) in

the context of a standard hot aisle/cold aisle data

center, where there is a dependency relationship

between the volume of cold air delivered through

a proximate perforated floor tile and a cabinet

server heat load, plus the presence of heated

server exhaust air in the room. The practical lim-

its to how much air you can push through a per-

forated floor tile and the looming presence of

heated return air conspire to limit how much can

be cooled in any particular cabinet.

Removing these constraints allows for higher

power/heat densities that can potentially be

cooled by air. In a data center where the cabinets

function as a complete isolation barrier between

supply and return air, these constraints are

removed. Complete isolation is accomplished

using a combination of passive air cooling acces-

sories such as blanking filler panels to block

bypass airflow, equipment mounting area

perimeter sealing air dams, floor-tile cut-out

brush seal grommets along with a system to

remove the return air from the room into a sus-

pended ceiling return air space. Such a system

would include a solid rear cabinet door with gas-

ket seal and a vertical exhaust duct running

between the cabinet and the suspended ceiling,

thus creating a ducted exhaust system using pas-

sive air cooling.

COMPLETE AIRFLOW ISOLATION By implementing a ducted exhaust system, hot

exhaust air no longer exists in the room and the

dependency on how much air can be pushed

through a

single per-

forated

floor tile is

eliminated,

allowing

cold air to

be deliv-

ered any-

where in

the room.

As heat

densities

increase

The Data Center Cooling Problem SOLVEDB y I a n S e a t o n , T e c h n o l o g y M a r k e t i n g M a n a g e r , C h a t s w o r t h P r o d u c t s , I n c .P a s s i v e a i r c o o l i n g s o l u t i o n s n o t o n l y o f f e r t h e m o s t e f f i c i e n t w a y t o c o o l t o d a y ’ s i n c r e a s i n g d e n s i t y r e q u i r e m e n t s , b u t p r e s e n th u g e e n e r g y s a v i n g s a n d a l o w e r i n i t i a l i n v e s t m e n t c o m p a r e d t o c l o s e - c o u p l e d a n d l i q u i d c o o l e d s o l u t i o n s . P a s s i v e a i r c o o l i n g c a ns u c c e s s f u l l y d i s s i p a t e a s m u c h h e a t a s c a n b e g e n e r a t e d b y c o m m e r c i a l s e r v e r s t h a t f i t i n t o a 4 2 t o 4 5 U c a b i n e t , a n d i n f a c tm o r e t h a n m o s t c l o s e - c o u p l e d a n d l i q u i d - c o o l e d s o l u t i o n s . B a s e d o n c o m p l e t e i s o l a t i o n b e t w e e n h o t e x h a u s t a n d c o o l s u p p l y a i r ,p a s s i v e a i r c o o l i n g s o l u t i o n s p r o v i d e a c c e s s t o l o w e r d a t a c e n t e r c o o l i n g , w h i c h t r a n s l a t e s i n t o i n c r e a s e d s u p p l y a i r t e m p e r a -t u r e s a n d d e c r e a s e d e n e r g y c o n s u m p t i o n .

Winter 08/09 I www.ThermalNews.com

Figure 1. Typical Cabinet, air re-circu-lates inside the cabinet and into the room.

www.ThermalNews.com I Winter 08/09

FEATURE ARTICLEThermal News I 15

beyond the level

that could practi-

cally be achieved

by under-floor air

delivery without

creating extra

wide cold aisles,

the access floor

can be eliminated

and the room can

be flooded with

high volumes of

cold air through

wall grates or

from overhead.

With the availability of theoretically infinite cooling

capacity, the remaining constraint revolves around effec-

tively removing the heat from the cabinet. While it is not

particularly prudent to reveal all the intellectual property

in this solution until all the patents are issued, suffice to

say that CPI Passive Cooling Solutions used

to form ducted exhaust systems utilize spe-

cific geometries that exploit the forces

of the Bernoulli Principle (inverse

relationship between velocity and

pressure) and generate a vortex with-

in the space to push hot exhaust air

up the back of the cabinet and into

the ceiling plenum. From the ceiling

plenum the hot exhaust air is direct-

ducted back to the CRAC unit,

cooled and then re-used as supply air

for the data center.

These ducted exhaust systems have

been deployed in large numbers in

working data centers with actual,

measured heat loads in excess of 20

kW per cabinet. Testing has surpassed

30 kW per cabinet and there is cur-

rently a customer project where cabi-

nets are being shipped into a space

where they will be loaded with 30 kW of actual, measured

server heat load. Further testing is planned to extend

beyond these levels and those reports will be forthcoming.

DUCTED EXHAUST CABINETS - THE ENERGYEFFICIENT CHOICE

More important than power density, is the cus-

tomer’s costs for cooling these densities, and there is

no more efficient, lower cost way of cooling a data

center than with the above-described ducted exhaust

system. The two basic factors affecting this higher effi-

ciency are 100 percent utilization of HVAC output and

an access path to more hours of economization cool-

ing. With the ducted exhaust system, every bit of cold

air produced by the HVAC system has to go through a

server – the only path between supply air and return air

is one of heat transfer through a server, so there is no

waste – there is no bypass airflow and no need for the

over-provisioning, which is required in standard hot

aisle/cold aisle data centers.

The efficiency claims of close-coupled and liquid-

cooled solutions are based on comparisons to inherent-

ly inefficient data centers with a high amount of bypass

airflow, and over-provisioning of cooling required by

the extreme variations in pressure and airflow through-

out a room. Because of the traditional dependencies on

air delivered through proximate perforated access floor

tiles, cooling capacity provisioning formulas have had

to plan for supplying adequate air to the lowest airflow

spot in a room, resulting in typically 200 to 300 per-

cent over-provisioning and huge amounts of wasted

bypass airflow. When it no longer matters where the

cold air is delivered and when 100 percent of the air

must travel through a server, there is no longer a need

for that over-provisioning and therefore no more waste.

While the elimination of waste may sound like it

puts a ducted exhaust system on an even playing field

with the close-coupled and liquid-cooled solutions, it

actually puts the ducted approach at an advantage

because of the higher efficiencies of the larger fans

and motors moving air at the room level.

The coefficient of performance (COP) for the larger

motors and fans of bigger free-standing CRAC units is

always going to be higher than the smaller motors and

fans of close-coupled solutions, and the COP of the

extremely large water-cooled central air handlers is

always going to be superior to anything small enough to

fit on the data center floor. This has always been the

case, but because of the historical waste of standard hot

aisle/cold aisle data centers, this COP advantage never

translated into comparable efficiencies on the data center

floor. With a ducted exhaust cabinet system that results

in 100 percent utilization of the HVAC output, these

superior COP values can now be translated directly into

data center cooling efficiency.

Free Cooling

Additional benefits of ducted exhaust systems

arise from chiller plant efficiencies and access to

more hours of “free” cooling. In a ducted exhaust

data center, only one temperature exists within the

room, so supply air temperatures no longer need to

be delivered in the mid-to-low 50’s. If equipment

standards allow for a 77°F server inlet temperature,

then the room can be cooled to 77°F with a 77°F

supply air temperature. The higher supply tempera-

ture dramatically improves chiller plant efficiency as

well as opens the door for access to significantly

more hours of economization cooling. Table 1

describes the temperature thresholds for three differ-

ent economization strategies.

With the higher supply temperatures allowed by

ducted exhaust systems, the data center operator

benefits from improved chiller plant efficiency –

approximately a 1 to 1.5 percent reduction in

chiller plant energy use for every 1° increase in the

chilled water loop temperature, or 25 to 35 percent

energy use reduction. In addition, these tempera-

tures allow for many more hours of economization

cooling – all hours under 60°F for water-side econ-

omization; all hours under 72°F for KyotoCooling

heat recovery wheel economization and all hours

under 77°F wet bulb for evaporative air-side econ-

omization. In a data center with a 2.0 Power

Utilization Effectiveness (PUE), water side econo-

mization and evaporative air-side can reduce the

total data center energy use by 35 percent during

those economization hours, and by 43 percent dur-

ing KyotoCooling hours.

In conclusion, the airflow isolation achieved

with ducted exhaust systems raises the bar by a

factor of 4 or 5 for heat densities and provides

much more efficient cooling at a lower initial

investment than close-coupled or liquid cooled

solutions. While a completely contained close-cou-

pled system could provide access to similar water-

side economization hours and chiller plant efficien-

cies, those solutions will, by definition have poorer

coefficient of performance ratings and will not be

able to provide access to the most economical

economization of KyotoCooling nor to the higher

number of economization hours of evaporative air-

side economization.

For more information, visit www.chatsworth.com

Most Data

Centers are Here

CRAC w/

Economizer

TIA-942

Best Practices

CRAC w/

Economizer

100% Isolation

Heat Recovery Wheel

100% Isolation

Evaporative Air

Economizer 100%

Isolation

Delivered 60-85°F 68-77°F 77°F 77°F 77°F

Supply 52-55°F 52-55°F 77°F 77°F 77°F

Water 42°F 42°F 65°F N/A 65°F

Ambient 37°F 37°F 60°F 72°F 77°F

Figure 2. Ducted Exhaust Cabinet,removes hot air from the cabinetand room.

Figure 3.CPIPassive CoolingSolutions installedin the F-SeriesTeraFrame CabinetSystem form a duct-ed exhaust cabinet.

Table 1.