  • 7/30/2019 Hydrotest Preparation

    1/22

    HYDROTEST

  • 7/30/2019 Hydrotest Preparation

    2/22

    TESTS

    DESTRUCTIVE TESTS Tensile, Impact, Bend etc

    NON-DESTRUCTIVE TESTS

    Radiography

    Ultrasonic

    Dye Penetration

    Magnetic Particle

    Leak tests like Air test,Ammonia test etc. Hydrostatic test

  • 7/30/2019 Hydrotest Preparation

    3/22

    WHY HYDROSTATIC TEST

    To ensure the integrity of the equipment To ensure the strength of the weld joints &

    material

    To ensure the strength of the nozzleflange joints

    To relieve the stresses

    Ensures safe and reliable performance

    during the operational life

  • 7/30/2019 Hydrotest Preparation

    4/22

    HYDRO TEST

    Good planning is essential for completionof hydrotest in minimum possible time

    Gauges, transducer/ recorder , Sq. Bar,

    Hose pipes, PumpLocation, weight distribution, draining

    Saddles, slope, venting

    Water- quantity,quality & temperature

    Torque tightening / tensioning units

    Flanges, bolts / studs

  • 7/30/2019 Hydrotest Preparation

    5/22

    HYDRO TEST

    The hydro test saddles shall be located onshell in such a way that all circumferential

    seams are free from saddle location. Long

    seams if any covered by the saddle; the

    corresponding location of saddle material

    shall be grooved to facilitate the inspection

    of weld joint under test

  • 7/30/2019 Hydrotest Preparation

    6/22

    Sketch for Hydro test

  • 7/30/2019 Hydrotest Preparation

    7/22

    Valves

    Pressure Gauge

    Towards Venting pipe

    Arrangement for Outlet Pressure Gauge

    Square Bar

    Coupling

  • 7/30/2019 Hydrotest Preparation

    8/22

    From HydrotestPump

    Towards Drain

    Valves

    Pressure Gauge

    Square Bar

    Coupling

    Arrangement for Inlet Pressure Gauge

  • 7/30/2019 Hydrotest Preparation

    9/22

    HYDRO TEST

    Carry out tightening of Nozzle / Manway covers as per the required

    torque

    Use proper tightening unit to meet therequirement of PSI / Torque and

    follow the tightening sequence as per

    approved procedure for bolts / studs

    Start filling water after confirmation of

    all requirements ( like venting, PPM of

    water, Clearance of Job for fill up)

  • 7/30/2019 Hydrotest Preparation

    10/22

    1

    2

    34

    5

    6 7

    8

    TIGHTENING SEQUENCE(with torque tightening unit)

  • 7/30/2019 Hydrotest Preparation

    11/22

    1

    1

    22

    3

    3

    4

    4

    5

    5

    6

    6

    7

    7

    8

    8

    TIGHTENING SEQUENCE(with tensioning unit)

  • 7/30/2019 Hydrotest Preparation

    12/22

    HYDRO TEST

    Ensure that the nozzles (top) are

    open for air removal

    Let the water flow out of the topnozzles so that the air is removed

    Close the nozzle & allow the water to

    flow from top and confirm absence ofair bubbles

  • 7/30/2019 Hydrotest Preparation

    13/22

    AIR LOCK REMOVAL

    1 VESSEL IN HORIZONTAL, INCLINED AT 5 DEG.

    Packing

  • 7/30/2019 Hydrotest Preparation

    14/22

    AIR LOCK REMOVAL2 WHEN INTERNALS LIKE TSRs PROVIDED INSIDE THE VESSEL

  • 7/30/2019 Hydrotest Preparation

    15/22

    AIR LOCK REMOVAL

    3 NOZZLES ON DISHEND

  • 7/30/2019 Hydrotest Preparation

    16/22

    HYDRO TEST

    Start the pump for pressurizing thewater inside the equipment. (Selectionof pump depends on the pressure and

    discharge of water from pump. Set theoutput pressure of pump such that itshould not exceed hydro test pressurefor safer operation)

  • 7/30/2019 Hydrotest Preparation

    17/22

    HYDRO TEST

    Ensure that minimum two pressure

    gauges are attached The pressure gauges shall have an upper

    range of 2 times the test pressure but in

    no case less than 1.5 times or more than4 times the test pressure. The transducer

    shall have minimum upper range of 1.25

    times the test pressure. Only calibrated

    pressure gauge and transducer shall beused. Validity of calibration shall be

    verified on the calibration sticker pasted

    on the pressure indicators

  • 7/30/2019 Hydrotest Preparation

    18/22

    HYDRO TEST

    Increase the pressure as per therequirement given in drawing or the

    approved procedure

    During pressurizing from designpressure to test pressure, no one

    shall remain on the vessel or very

    near to bolted connections on the

    vessel

  • 7/30/2019 Hydrotest Preparation

    19/22

    HYDRO TEST

    Hold the test pressure for minimum30 minutes or as specified by the

    drawing / specification. The test

    pressure shall not get dropped

    during the holding time. The vessel

    connections shall not be inspected

    closely for any leakage at this stage

  • 7/30/2019 Hydrotest Preparation

    20/22

    HYDRO TEST

    Reduce the pressure to Designpressure

    Check for any leakage in weld joints

    and bolted joints If no leakage is observed,

    depressurizing can be started

  • 7/30/2019 Hydrotest Preparation

    21/22

    HYDRO TESTDepressurizing :

    If cycle is specified , follow the same If not specified, reduce pressure

    slowly by opening the square bars (at

    top) such that pressure drops to zero Neveropen bottom noz./ Sq. bar

    While draining the vessel, the top vent

    valve shall be kept open beforeopening any nozzle at the bottom. Thisis for eliminating the possible collapseof thin shells due to vacuum created

    within the test vessel

  • 7/30/2019 Hydrotest Preparation

    22/22

    HYDRO TEST

    Pressure gauges once used for apressure test shall be recalibrated. Forthis purpose, the pressure gaugesonce used shall be crossed on the

    calibration sticker and send to QA