Upload
eugene-mcdaniel
View
213
Download
0
Embed Size (px)
Citation preview
HUNTING CAMP FACILITYBY: Ryan Fremin
ET 494 Senior Design II
Construction Engineering Technology
Professor: Dr. Koutsougeras
Advisor : Mr. Rode
PURPOSE
Perform complete theoretical construction process of hunting camp facility Research Needed Location Selection Giving Structure Options Rough Drawing and Estimates Design Selection Complete drawings, schedule, and estimate
WHY HUNTING
In 2011 there was a total of 13.7 million hunters in the United States
23 % of all wild-life recreation is found in hunting
(US Census Bureau)
$564,385,000 Was spent in 2011 for trip–related hunting in Louisiana
$315,763,000 Was spent in 2011 for trip-related hunting in Mississippi
Louisiana-16 % Mississippi- 36 %
RESEARCH
The given statistics show that this can be a lucrative business.
Current pricing for pay hunts Lodging---------$1000-$2000 Hunting-----Min------$ 4,000 (8-Point)
Mississippi is in the top 15 places that hunters like to hunt Shows profitability and demand
DESIGN OPTIONS
LOG CABIN
Will give the owner and customers a more luxurious feel with all of the necessities.
Less cost effective
PRE-ENGINEERED METAL BUILDING
Will give the owner and customers all of the necessities with the option of adding luxuries after design and pricing is completed.
Cost Effective (Key for this build)
LOG CABIN
Example ( Gile’s Island)
Nice facility to conduct business
Most need separate buildings for lodging (Total- 6700 sq.ft.)
Lodging takes up possible land and reduces amount of huntable property
Popular but expensive to construct
PRE-ENGINEERED METAL BUILDING
Example ( Converted Metal Building)
Cost effective Fast Construction Combines facilities into
one location Gives added space for
possible upgrades 40’x80’( total – 7200
sq.ft.)
ROUGH DRAWING – LOG CABIN
ROUGH DRAWING – METAL BUILDING
DESIGN DECISION
Pre-Engineered Metal Building
$456,264 Log Cabin
$507,400 Difference
$ 51,136 or 10% cheaper
DETAILED DRAWINGS
The detailed drawings will be done from the last week of the semester into the break. They will be continued while doing a material takeoff at the same time.
This will allow sufficient time to complete drawings and estimate.
TIMELINE
Jan 21-Jan 24 First Week Back to Classes
Jan 27-Jan 31 Update Powerpoint for Semester
Feb 3 –Feb 7 Continue Drawings/Material Takedown
Feb 10 – Feb 14 Continue Drawings/ Material Takedown
Feb 17 –Feb 21
Continue Drawing/ Material Takedown
Feb 24– Feb 28 Finish drawings
Mar 3–Mar 7 Complete Survey of Location
Mar 10–Mar 14 Determine Foundation Plan
Mar 17– Mar 21 Begin Estimate
Mar 24- Mar28 Cont. Estimate
TIMELINE (CONT.)
Mar 31– April 4 Produce Final Estimate
April 7- April 11 Begin Planning and Scheduling
April 14 – April 18 Cont. Planning and Scheduling
April 21– April 25 Complete Planning and Scheduling
April 28– May 2 Begin Finalizing Project
May 5– May 9 Complete Final Project